
TABLE
OF CONTENTS
1
IntROduction
1.1 Project
Background
1.2 The Project
1.3 Designated
Project under Environmental Impact Assessment Ordinance (EIAO)
1.4 Purpose of the
Manual
1.5 Development
Programme of the Project
1.6 Project
Organisation
1.7 Structure of the
Manual
2
Air Quality Impact
2.1 Introduction
2.2 Construction Dust
Monitoring Parameters and Equipment
2.3 Construction Dust
Monitoring Stations
2.4 Construction Dust
Impact Monitoring
2.5 Construction Dust
Event and Action Plan
2.6 Construction Dust
Mitigation Measures
2.7 Construction Dust
Audit Requirements
3
NOISE Impact
3.1 Introduction
3.2 Construction
Phase
3.3 Operational Phase
¨C Road Traffic Noise
3.4 Operational Phase
¨C Fixed Noise Sources
3.5 Mitigation
Measures
3.6 Audit
Requirements
4
Water Quality impact
4.1 Introduction
4.2 Construction
Phase
4.3 Mitigation
Measures
4.4 Audit Requirement
5
Sewereage and sewage treatment implications
5.1 Introduction
5.2 EM&A
Requirements
6
WASTE MANAGEMENT implications
6.1 Introduction
6.2 Mitigation
Measures
6.3 Audit Requirement
7
Land Contamination
7.1 Introduction
7.2 Construction
Phase
7.3 Operational Phase
8
ecological Implication (Terrestrial and Aquatic)
8.1 Introduction
8.2 Mitigation
Measures
8.3 Monitoring
Requirements
8.4 Audit
Requirements
9
Fisheries impact
9.1 Introduction
9.2 Mitigation
Measures
9.3 Monitoring and
Audit Requirements
10
LandScape and Visual impact
10.1 Introduction
10.2 Mitigation Measures
10.3 EM&A Requirement
11
IMPACT ON cultural heritage
11.1 Introduction
11.2 Mitigation Measures
12
HAZARD TO LIFE
12.1 Introduction
13
lANDFILL GAS HAZARD
13.1 Introduction
14
IMPACT FROM ELECTRIC AND MAGNETIC FIELD
14.1 Introduction
15
Environmental auditing
15.1 Site Inspection
15.2 Compliance with Legal and
Contractual Requirements
15.3 Choice of Construction Method
15.4 Environmental Complaints
16
Reporting
16.1 General
16.2 Electronic Reporting of EM&A
Information
16.3 Baseline Monitoring Report
16.4 Monthly EM&A Reports
16.5 Quarterly EM&A Summary Reports
16.6 Final EM&A Review Reports for
Construction Phase
16.7 Final EM&A Report for
Operational Phase
16.8 Data Keeping
16.9 Interim Notifications of
Environmental Quality Limit Exceedances
List of
tables
Table 1.1 .... Schedule 2 Designated Projects under the Project
Table 1.2 Preliminary Construction and Population Intake
Schedule
Table 2.1 Proposed Construction Dust Monitoring Stations
Table 2.2 Summary of Construction Dust Monitoring Programme
Table 2.3 Current Action and Limit Levels for Impact Monitoring
Table 2.4 Event and Action Plan for Construction Dust Monitoring
Table 3.1 Action and Limit Levels for Airborne Construction
Noise Impact Monitoring
Table 3.2 Proposed Road Traffic Noise Monitoring Stations during
Operational Phase
Table 3.3 Extent and Locations of Proposed Direct Noise
Mitigation Measures
Table 4.1...... Proposed
River Water Quality Monitoring Stations for Baseline, Construction Phase and
Post-Construction Monitoring
Table 4.2 Action and Limit Levels for Water Quality Monitoring
Table 4.3 Event and Action Plan for Water Quality Monitoring
LIST OF FIGURES
|
Figure
1.1
|
Project Location Plan
|
|
Figure
1.2
|
Locations of Designated Projects
|
|
Figure
1.3
|
Recommended Outline Development Plan
|
|
Figure
2.1
|
Locations of Construction Dust Monitoring Stations
(Key Plan)
|
|
Figure
2.1.1
|
Locations of Construction Dust Monitoring Stations
(Sheet 1 of 4)
|
|
Figure
2.1.2
|
Locations of Construction Dust Monitoring Stations
(Sheet 2 of 4)
|
|
Figure
2.1.3
|
Locations of Construction Dust Monitoring Stations
(Sheet 3 of 4)
|
|
Figure
2.1.4
|
Locations of Construction Dust Monitoring Stations (Sheet
4 of 4)
|
|
Figure
3.1
|
Locations of Road Traffic Noise Monitoring Stations
(Key Plan)
|
|
Figure
3.1.1
|
Locations of Road Traffic Noise Monitoring Stations
(Sheet 1 of 2)
|
|
Figure
3.1.2
|
Locations of Road Traffic Noise Monitoring Stations
(Sheet 2 of 2)
|
|
Figure
4.1
|
Locations of Water Quality Monitoring Stations
|
|
Figure
13.1
|
Location Plan of Ngau Tam Mei Landfill and Project Site Boundary
|
LIST OF Appendices
1
IntROduction
1.1
Project Background
1.1.1
The Civil Engineering and
Development Department (CEDD) and the Planning Department (PlanD)
jointly commissioned the Ngau Tam Mei (NTM) Land Use Review Study (the Study)
in November 2021 to capitalise on the development
opportunities to be brought about by the NTM Station on the proposed Northern
Link (hereinafter refer to as NOL Main Line). The Study aims to examine the
comprehensive development of the brownfield clusters in NTM, which was
subsequently extended to cover a nearby site as identified under the ¡°Green
Belt¡± Review announced in the 2022 Policy Address for holistic planning
(hereinafter referred to as ¡°the Project¡±); to ascertain the feasibility and
acceptability of the Project with technical assessments including the statutory
Environmental Impact Assessment (EIA); to formulate a Recommended Outline
Development Plan (RODP); and to conduct public engagement (PE) for increasing
awareness and engagement among stakeholders.
1.1.2
The
Northern Metropolis Action Agenda (NMAA) promulgated in October 2023 outlines
the development positioning of four major zones in the Northern Metropolis
(NM). Amongst them, the Innovation and Technology (I&T) Zone covers San Tin
Technopole (STT) and NTM. STT will be a hub for clustered I&T development,
creating synergy with the Shenzhen I&T Zone. Upon completion of the
proposed NOL Main Line in 2034, NTM will only be one station away from STT. It
is stated in NMAA that land will be reserved in NTM for
use of post-secondary education institutions, with a focus on scientific
research to complement the I&T development in STT, promoting ¡°research,
academic and industry¡± collaboration.
1.1.3
The
2024 Policy Address announced to reserve land in the NM
for the ¡°Northern Metropolis University Town (NMUT)¡±, and encourage local post-seoncdary education institutions to introduce
more branded programmes, research collaboration and
exchange projects with renowned Mainland and overseas institutions in a
flexible and innovative manner. It is also stated in the 2024 Policy Address
that, land will be reserved in NTM for developing the third medical school and
an integrated medical teaching and research hospital (hereinafter referred to
as ¡°Integrated Hospital¡±). As
announced in the 2025 Policy Address, a Working Group on Planning and
Construction of the University Town (WG) will be set up under the Committee on
Development of the NM, to study the development mode for the NMUT and make
recommendations on the positioning and vision regarding the development of NMUT
sites to devise a clear, industry-led approach. The land in NTM can dovetail
with the overall I&T development of the STT and the Hong Kong-Shenzhen
Innovation and Technology Park (HSITP) at the Loop, among others, life and
health technology industries, and to be used for joint development with the
third medical school and an integrated medical teaching and research hospital.
The design and implementation of the UniTown will be
duly considered by the Education Bureau under the steer of the WG.
1.1.4
A
2-month PE was conducted between 14 November 2024 and 13 January 2025 to
solicit public views on a Broad Land Use Concept Plan developed under the
Study. Taking into account the public views collected in the PE, policy
directives, planning and engineering considerations, technical assessments as
well as departmental advice, a RODP for the NTM New Development Area (NDA) has
been formulated (Figure 1.3 refers).
1.1.5
Locations
of the Project Site (including the proposed works sites/areas) and the
Development Area are shown in Figure 1.1.
Located to the south of STT and to the northeast of Yuen Long New Town, the
total area of Development Area covers about 130 ha and is
currently occupied by Yau Tam Mei Tsuen, scattered brownfield operations,
farmland/fishponds, chicken farm, permitted burial grounds, etc. The Project
comprises mainly educational institutions, hospital, other government,
institution and community (GIC) facilities, housing, as well as the associated
infrastructure works (e.g. road networks, sewage pumping station (SPS), etc.).
1.1.6
The
NTM Station, the depot and the associated railway facilities under the NOL Main Line within the Project Site will be implemented
by another project proponent (i.e. MTR Corporation Limited (MTRCL)), thus the
construction and operation of these railway facilities are not part of this
Project. The associated environmental impacts arising from the construction and
operation of the NOL Main Line were assessed in its approved EIA report
(Register No.: AEIAR-259/2024).
1.2
The Project
1.2.1
The
proposed scope of the Project includes the following principal works elements to support the
development of NTM NDA as shown in Figure 1.1.
Site Formation and Engineering
Infrastructure Works
(a) Site formation works
including slope cutting and filling and retaining wall installation;
(b) Engineering
infrastructure works comprising roads including district distributor roads,
local roads, drainage works including revitalisation
works for Ngau Tam Mei Drainage Channel (NTMDC), sewerage provision including a
SPS and other utilities works to support the proposed development of the
Project;
(c) Landscaping,
streetscaping and ancillary works; and
(d) Provision of
environmental mitigation measures for the works mentioned above.
Other Works
(a)
Developments
including GIC facilities, residential development, schools, electrical
substations and other facilities to support the proposed development of the
Project.
1.3
Designated Project under Environmental Impact
Assessment Ordinance (EIAO)
1.3.1
The Development Area, covering an area of about 130
ha, constitutes a Designated Project (DP) by virtue of Item 1 under Schedule 3
of the EIAO:
¡¤ Item
1 ¨C An urban development or redevelopment project covering an area of more than
50 ha.
1.3.2
In addition, the Project also constitutes DPs under
Part I, Schedule 2 of the EIAO, which are listed in Table 1.1 and
illustrated in Figure 1.2.
Table 1.1 Schedule 2
Designated Projects Under the Project
|
Ref. No.
|
Schedule 2 Designated
Project
|
Work Component / Reference in RODP
|
|
DP1
|
Item A.1
|
A carriageway for motor vehicles that is an
expressway, trunk road, primary distributor road or district distributor road
|
Construction and operation of district
distributor road (Road D1) and associated road works at San Tin Highway
|
|
DP2
|
Item I.1(b)
|
A drainage channel or river training and
diversion works located less than 300 m from the nearest boundary of an
existing or planned conservation area
|
Part of Revitalisation
of Ngau Tam Mei Drainage Channel and river diversion works located less than
300 m from the nearest boundary of an existing conservation area
|
DP1 ¨C Construction and
Operation of District Distributor Road (Road D1) and associated road works at
San Tin Highway
1.3.3
The Project will be served by a network of District Distributor (DD) and
Local Distributors (LD). Road D1, which is a DD (i.e. Item A.1 of Schedule 2 of
the EIAO), is proposed to be a dual two-lane carriageway serving as the main
connection road between San Tin Highway and the NTM NDA. Most of the Road D1
will be constructed at-grade, except for an elevated section of
approximately 300 m long near Site E.1 and Site R.1, which connects to the
proposed elevated junction over the existing San Tin Highway. A
connection with the planned NM Highway ¨C San Tin Section is reserved at the
east end of Road D1.
DP2 ¨C Part of
Revitalisation of Ngau Tam Mei Drainage Channel and river diversion works
located less than 300 m from the nearest boundary of an existing conservation
area
1.3.4
The current NTMDC that sits within the Project Site is mainly a concrete
channelised waterway. As part of the blue-green spine
concept, the existing concrete channel will be revitalised
with a green and ecologically friendly approach for integration with the
overall land use planning. Provision of natural substrates that could encourage
colonisation of flora and freshwater fauna in the
bottom and banks of the revitalised watercourses
would be considered, subject to detailed design of the proposed revitalisation measures. The drainage channel would also be
widened to increase the hydraulic capacity of the river, creating a resilient
and dynamic design. These provisions, including planting of suitable trees,
would enable connectivity and usage for mammals and avifauna. Also, landscape
and recreation provisions as well as pedestrian walkway and cycling track will
be provided along the revitalised NTMDC.
1.3.5
Due to the proposed developments, a few watercourses (except NTMDC)
within the Project Site will be permanently diverted or removed.
Diversion works at these existing watercourses would involve diversion of water
flow from their existing routes to the new routes through the proposed covered
drainage system of the new development.
1.3.6
Part of the NTMDC and a few watercourses in the southeastern part of the
NTM NDA are located within 300 m from Conservation Area (CA). Revitalisation and river diversion works within 300 m from
CA fall into the category of Item I.1(b), Part I, Schedule 2 of the EIAO.
1.4
Purpose of the Manual
1.4.1
The purpose of this Environmental Monitoring and Audit (EM&A) Manual
is to guide the set-up of an EM&A programme to ensure
compliance with the EIA Study recommendations, to assess the effectiveness of
the recommended mitigation measures, to identify any further need for
additional mitigation measures or remedial actions, and to provide systematic
procedures for monitoring, auditing and minimising
environmental impacts associated with the construction and operational
activities of the Project.
1.4.2
Hong Kong environmental regulations have served as environmental
standards and guidelines in the preparation of this Manual. In addition,
this Manual has been prepared in accordance with the requirements stipulated in
Annex 21 of the Technical Memorandum on Environmental Impact Assessment Process
(EIAO-TM).
1.4.3
This Manual contains the following information:
¡¤
Responsibilities of the
Contractor, the Engineer or Engineer¡¯s Representative (ER), the Environmental
Team (ET), and the Independent Environmental Checker (IEC) with respect to the
EM&A requirements during the course of the Project;
¡¤
Project organization
for the EM&A work;
¡¤
The basis for, and
description of the broad approach underlying the EM&A programme;
¡¤
Details of the
methodologies to be adopted, including all field laboratories and analytical
procedures, and details on quality assurance and quality control programme;
¡¤
The rationale on which
the environmental monitoring data will be evaluated and interpreted;
¡¤
Definition of Action
and Limit (A/L) levels;
¡¤
Establishment of Event
and Action plans;
¡¤
Requirements for
reviewing pollution sources and working procedures required in the event of
non-compliance with the environmental criteria and complaints; and
¡¤
Requirements for
presentation of EM&A data and appropriate reporting procedures.
1.4.4
This Manual is a dynamic document that should be reviewed regularly and
updated as necessary during the construction and operational of the
Project. The Contractor should regularly review the mitigation measures
and project implementation schedule in Appendix C with respect to
the design developments and construction methodology.
1.5
Development Programme of the Project
Development Phasing
1.5.1
The Project would be commissioned in phases with the first population
intake in Year 2033. Construction of the Project is scheduled to commence in
early Year 2027, with completion targeted by 2036 to accommodate the intake of
residential population, the UniTown and Integrated
Hospital. The preliminary construction schedule under various phases is summarised in Table 1.2 with reference to Appendix B1. The construction
programme is presented in Appendix B2.
Table 1.2
Preliminary Construction and Population Intake Schedule
|
Develop-ment Stage
|
Area
|
Rationale of Phasing
|
Earliest Date for Commencement of Infrastructure Works
|
Earliest Date for Availability of Land for Building Works
|
Anticipated First Occupation/ Population Intake Date
|
|
Phase 1
|
• Dedicated Rehousing Estate (DRE) site (RSc.1)
• Integrated Hospital (G.8) & adjacent Electricity Substation
(ESS) site (G.9)
• Part of UniTown (G.11)
• Sewage pumping station (G.1)
• Road network connecting to the Integrated Hospital
|
• Early handover of the sites for building works (by
others)
|
Q1 2027
|
Q4 2028
|
2033 for
DRE site
|
|
Phase 2
|
• Remaining UniTown (G.6, G.10, G.11,
G.12)
• Residential Site (R.3, R.4)
• Remaining G/ICs, School (E.1 & E.2), Open Space (O.2, O.5-O.7),
Amenity Areas
• Majority of road network
• NTMDC
|
• To commence infrastructure works for targeted population
intake
• To allow early handover of UniTown
|
Q3 2028
|
Q2 2031
|
Q2 2034
|
|
Phase 3
|
• Residential Site R.1, R.2
• Remaining open space
• Remaining roadworks, landscape works, riverside & site
formation works
|
• To suit the programme of interfacing
projects
|
Q3 2030
|
Q3 2032
|
Q2 2036
|
Phase 1
1.5.2
Phase 1 comprises of site clearance and site formation of sites that
would require early completion for handover, including DRE site ¡°RSc.1¡±,
Integrated Hospital ¡°G.8¡±, ESS ¡°G.9¡±, part of UniTown
¡°G.11", sewage pumping station at ¡°G.1¡± and road
network connecting to the Integrated Hospital. The population intake of the
DRE site is expected to be in Year 2033.
Phase 2
1.5.3
This phase of development aims to support the remaining UniTown and population intake projected for the Year 2034,
along with the essential supporting infrastructures. Majority of these areas
consist of main road network and road connection from existing road networks.
There will be interface with NOL Main Line in this phase.
1.5.4
The major site formation and infrastructure works (including site
clearance) in this development phase will include:
¡¤ Site formation and development
for key infrastructures including retention tank, RCPs and utilities laying,
etc.;
¡¤
Site formation and development for remaining areas of UniTown to facilitate completion for handover;
¡¤
Site formation for R.3 and R.4;
¡¤
Site formation and development for ¡°E¡± and
¡°G¡± sites such as primary school, etc.;
¡¤
Road improvement to Chuk Yau Road, Ngau Tam Mei Road and San Tam Road;
¡¤
Construction of District Distributor Road D1, proposed road connection
to/from STT, Road L1, Road L2, Road L3, associated junction works and slip
roads connecting San Tin Highway and local roads, pedestrian and cycling
connectivity including cycle bridge, associated pedestrian walkway and cycle
tracks;
¡¤
Site clearance and revitalisation of NTMDC; and
¡¤
Construction of associated open space and amenity areas.
Phase 3
1.5.5
The development in this phase is to support the remaining population
intake in Year 2036 and to develop the remaining sites that are currently
occupied by the transitional housing project in the western part of the NDA and
NOL Main Line works area. There will be interface with the transitional housing
and NOL Main Line in this phase.
1.5.6
The major site formation and infrastructure works in this development
phase will include:
¡¤
Site formation for R.1 and R.2 after partial demolition
of the transitional housing;
¡¤ Development of open space after partial
demolition of the transitional housing; and
¡¤ Remaining roadworks, landscape works,
riverside and site formation works.
1.6
Project Organisation
1.6.1
The roles and responsibilities of the various parties involved in the
EM&A process and the organisational structure of
the organisation responsible for implementing the
EM&A programme are outlined below. The proposed
project organisation and lines of communication with
respect to environmental protection works are shown in Appendix A.
The Contractor
1.6.2
The Contractor should report to the ER. The duties and responsibilities
of the Contractor are:
¡¤
Implement the EIA
recommendations and requirements;
¡¤
Strictly adhere to the
guidelines and requirements in this Manual;
¡¤
Provide assistance to
the ET in carrying out relevant environmental monitoring and auditing, and
investigation related to non-compliance;
¡¤
Participate in the
joint site inspections undertaken by ET, and undertake corrective action(s) as
necessary;
¡¤
Provide information /
advice to ET regarding works activities which may contribute, or be continuing
to the generation of adverse environmental condition(s);
¡¤
Submit proposals on
mitigation measures in case of exceedances of A/L levels, in accordance with
the Event and Action Plans;
¡¤
Implement measures to
reduce environmental impacts where A/L levels are exceeded until the events are
resolved; and
¡¤
Adhere to the
procedures for carrying out environmental complaint investigation.
Environmental Team
1.6.3
The ET should conduct the EM&A programme and
ensure the Contractor¡¯s compliance with the Project¡¯s environmental performance
requirements during construction. The ET should be an independent party
from the IEC and the Contractor.
1.6.4
An ET should be established before the commencement of construction of
the Project. The ET should be led and managed by the ET Leader (ETL). The
ETL should possess at least 7 years of experience in EM&A and/or
environmental management. The ET should monitor the mitigation measures
implemented by the Contractor on a regular basis to ensure the compliance with
the intended aims of the measures. The duties and responsibilities of the ET
are:
¡¤
Set up all the required
environmental monitoring stations;
¡¤
Monitor various
environmental parameters and implementation of environmental mitigation
measures as required in this Manual;
¡¤
Review construction
programme and methodology, and comment as necessary;
¡¤
Carry out regular and
ad hoc site inspections to investigate and audit Contractor¡¯s site practice,
equipment and work methodologies with respect to pollution control and
environmental mitigation measures, and anticipate environmental issues for
proactive and practicable action before problems arise;
¡¤
Analyse the EM&A
data, review the success of EM&A programme to confirm the adequacy of
mitigation measures implemented and the validity of the EIA predictions, and to
identify any adverse environmental impacts arising and report EM&A results to
the Contractor, IEC, and the ER;
¡¤
Liaise with IEC on all
environmental performance matters, and timely submission of all relevant
EM&A proforma for IEC's approval;
¡¤
Audit the relevant
document(s)/record(s) and prepare reports on the environmental monitoring data
and the site environmental conditions;
¡¤
Review the proposals of
remedial measure from the Contractor and recommend suitable mitigation measures
in the case of exceedances of A/L levels, in accordance with the Event and
Action Plans;
¡¤
Advise the Contractor
on environmental improvement, awareness, enhancement matters, etc., on site;
¡¤
Follow up and close out
non-compliance actions;
¡¤
Submit the EM&A report(s)
to the project proponent and the Environmental Protection Department (EPD)
timely; and
¡¤
Adhere to the
procedures for carrying out environmental complaint investigation.
Engineer or Engineer¡¯s Representative
1.6.5
The Engineer is responsible for overseeing the construction works and
ensuring that the works are undertaken by the Contractor in accordance with the
specification and contractual requirements. The duties and responsibilities of
the Engineer with respect to EM&A may include:
¡¤
Supervise the
Contractor¡¯s activities and ensure that the requirements in this Manual are
fully complied with;
¡¤
Inform the Contractor
when action is required to reduce environmental impacts in accordance with the
Event and Action Plans;
¡¤
Participate in joint
site inspections and audits undertaken by the ET;
¡¤
Comply with the agreed
Event and Action Plans in the event of any exceedance; and
¡¤
Adhere to the
procedures for carrying out exceedance and complaint investigations.
Independent Environmental Checker
1.6.6
The IEC should be employed by the ER / project proponent before
commencement of construction of the Project. The IEC should possess at least 10
years of experience in EM&A and/or environmental management and should be
an independent party from the ET and the Contractor. The duties and
responsibilities of the IEC are:
¡¤
Review and audit at not
less than monthly intervals in an independent, objective and professional
manner in all aspects of the EM&A programme;
¡¤
Validate and confirm
the accuracy of monitoring results, monitoring equipment, monitoring locations,
monitoring procedures and locations of sensitive receivers;
¡¤
Audit the EIA recommendations
and requirements against the status of implementation of environmental
protection measures on site;
¡¤
Review the
effectiveness of environmental mitigation measures and project environmental
performance;
¡¤
On as-needed basis,
verify and certify the environmental acceptability of the Environmental Permit
(EP) holder¡¯s construction methodology (both temporary and permanent works),
relevant design plans and submissions under the EP;
¡¤
Carry out random sample
check and audit on monitoring data and sampling procedures, etc;
¡¤
Conduct random site
inspections;
¡¤
Verify the
investigation results of environmental complaint cases and the effectiveness of
corrective measures;
¡¤
Verify EM&A report
that has been certified by the ETL; and
¡¤
Provide feedback on the
audit results to the ET, the ER or the project proponent according to Event and
Action Plans in this Manual.
1.7
Structure of the Manual
1.7.1
Following this introductory section, the remainder of this Manual is set
out as follows:
¡¤
Section 2 ¨C Sets out
EM&A requirement for air quality impact;
¡¤
Section 3 ¨C Sets out
EM&A requirement for noise impact;
¡¤
Section 4 ¨C Sets out
EM&A requirement for water quality impact;
¡¤
Section 5 ¨C Sets out
EM&A requirement for sewerage and sewage treatment implications;
¡¤
Section 6 ¨C Sets out
EM&A requirement for waste management implications;
¡¤
Section 7 ¨C Sets out
EM&A requirement for land contamination;
¡¤
Section 8 ¨C Sets out
EM&A requirement for ecological implication (terrestrial and aquatic);
¡¤
Section 9 ¨C Sets out
EM&A requirement for fisheries impact;
¡¤
Section 10 ¨C Sets out
EM&A requirement for landscape and visual impact;
¡¤
Section 11 ¨C Sets out
EM&A requirement for impact on cultural heritage;
¡¤
Section 12 ¨C Sets out
EM&A requirement for hazard to life;
¡¤
Section 13 ¨C Sets out
EM&A requirement for landfill gas hazard;
¡¤
Section 14 ¨C Sets out
EM&A requirement for impact from electric and magnetic field;
¡¤
Section 15 ¨C Describes
the scope and frequency of environmental site audits and sets out the general
requirements of the EM&A programme; and
¡¤
Section 16 ¨C Details
the EM&A reporting requirements.
2
Air
Quality Impact
2.1
Introduction
2.1.1
Potential air quality impacts arising from the construction phase of the
Project were assessed in the EIA Report. The major air quality impact
from the construction works of the Project would mainly be related to
construction dust from excavation, material handling, spoil removal and wind
erosion. No adverse air quality impact from construction of the Project would
be anticipated with the implementation of the proposed mitigation measures.
Nonetheless, construction dust monitoring and regular site audit are
recommended during the construction phase so as to check compliance with the
legislative requirements.
2.1.2
Cumulative air quality impact arising from the vehicular emission from
existing and planned open roads, proposed Transport Interchange Hub and Public
Transport Terminus, existing heavy goods vehicles/coach parking sites, as well
as existing and planned industrial emissions were assessed in the EIA Report.
No adverse air quality impact on the existing and planned sensitive receivers
is anticipated. Hence, no air quality monitoring and site inspections are
required during operational phase.
2.1.3
Cumulative odour impact from the planned (i.e.
the proposed SPS), and existing odour sources (i.e.
livestock farms, lard boiling factory, sewage treatment plant at Tam Mei
Barracks (TMB)) were assessed in the EIA Report. Adverse cumulative odour impact is not expected with the proposed mitigation
measures in place. Hence, no air quality monitoring and site inspections
are required during operational phase.
2.1.4
This section presents the requirements, methodology, equipment,
monitoring locations and criteria for the monitoring and audit of construction
dust impact during the construction phase of the Project.
2.2
Construction Dust Monitoring Parameters and
Equipment
2.2.1
For regulatory purpose, the respirable suspended particulate (RSP) and
fine suspended particulate (FSP) levels should be measured by the mean of air
sensor such that variation in dust impact on a real-time basis could be
observed and any dusty activities occurring in the concerned area can be
identified. Weather data including temperature, relative humidity, pressure,
wind speed and wind direction should also be monitored simultaneously with air
sensor. Other special phenomena and work progress of the concerned
site, etc., should also be recorded in detail during monitoring period.
2.2.2
An air sensor to be employed should meet the purpose of the monitoring
which are 1-hour RSP, and 24-hour RSP and 24-hour FSP concentrations in the
ambient air in minute-averaged monitoring data. The air sensor should have a resolution of at
least 1µg/m3, an accuracy of ¡À 10% to standard particles, equipped
with a shelter to protect the sensor and capable of operating continuously for
a 7-day period. It should be capable of detection of RSP and FSP, while
size specification would be optional subject to the environmental management
strategy of the site. The
measurement range and detection limit of the air sensor should be able to
measure the full range of particulates commonly found in the ambient, e.g. 0 ¨C
1000 µg/m3. The installation and operating
procedures of the instrument should be followed by the operation manual
supplied by the instrument manufacturer. The ET should propose the
instrument model and seek approval from IEC. The ET should follow the operation
manual to ensure the normal operation of the instrument.
2.2.3
Air sensor network which comprises one or more sensors should be
employed near works sites/works areas of the Project to capture the worst
cumulative impact from particulates concentration. Generally, air sensor should
be placed at least 1.5 metres above ground, and away
from any obstruction, vegetation or emission source which would interfere with
the measurement. Other factors of the monitoring location, such as security,
availability of power supply and reliable communication (cellular, Wi-Fi, etc.)
should also be considered.
2.2.4
To ensure the measurements are of acceptable air quality, the ET should
calibrate the monitoring equipment regularly. However, air sensor cannot
be calibrated in the same way as standard method. Instead, the performance of
the air sensor will be checked by a process called collocation which places the
sensors near a transfer standard (TS) and operating them simultaneously under
the same conditions. Instead of adjusting the physical setting of an air
sensor, which is often not possible, correction of raw data or response
produced by the air sensor will be carried out to better match the reference
monitor data by applying a scaling factor to the raw data.
2.2.5
Right before each on-site calibration, the TS itself needs to be
calibrated. Federal Reference Method (FRM) or Federal Equivalent Method (FEM)
particulate matter (PM) monitor maintained at the accredited laboratories or
research institutes are the PM reference monitors available in Hong Kong. The
collocation of TS with PM reference monitor should last at least seven days.
The TS is usually left collocated with PM refence monitor when not being moved
around the sensor network.
2.2.6
The TS with known performance characteristics will visit each air sensor
on the field for collocation. During collocation, the TS should be placed near
the subject sensor (<1m if practicable) so that both devices would be
monitoring under the same environment, i.e. the same pollution sources and
weather conditions. The TS should be first warmed up for 30 ¨C 60 minutes and
then left running with the subject sensor for the collocation period (at least
three hours). The measurements from the subject sensor and TS during the
collocation period will be statistically analysed.
2.2.7
The response of the air sensor should be adjusted if its performance
during on-site calibration does not meet the following evaluation criteria. For
each device, data below its detection limit will be excluded.
Tier
1: Correlation
1. The minute average measurements from the two devices when
subject to linear regression should have a coefficient of determination (R2)>0.7.
The regression line slope should be between 0.75 to 1.25. If these criteria are
not met due to narrow range of PM concentration (>30 ¦Ìg/m3
and >25µg/m3 as recommended span range for RSP and FSP,
respectively) during the collocation period, Tier 2 will apply.
Tier
2: Root Mean Squared Error
2. The root mean squared error of the
sensor minute average measurements should be <8 ¦Ìg/m3
for RSP and <5 µg/m3 for FSP.
2.2.8
On-site checking of the monitoring equipment should be conducted by ET
according to Appendix D.
The collocation of TS and each air sensor on the field should be carried out
every month. If an air sensor failed in 3 consecutive collocations, the air
sensor should be checked or maintained to improve its performance, or it should
be replaced.
2.2.9
Wind data monitoring equipment should also be provided and set up at
conspicuous locations for logging wind speed and wind direction close to/or at
the construction dust monitoring locations. The equipment installation location
should be proposed by the ET and agreed with the ER and the IEC. For
installation and operation of wind data monitoring equipment, the following
points should be observed.
a. The
wind sensors should be installed on masts at an elevated level 10m above ground
so that they are clear of obstructions or turbulence caused by the buildings;
b. The
wind data should be captured by a data logger. The data recorded in the data
logger should be downloaded for analysis simultaneously;
c. The
wind data monitoring equipment should be re-calibrated at least once every six
months; and
d. Wind
direction should be divided into 16 sectors of 22.5 degrees each.
2.2.10
Before commencing the construction dust monitoring, the ET should
formulate construction dust monitoring plan with air sensor and submit to IEC
to seek their feedback and consent. The plan should include but not limited to
the followings:
¡¤
Details on the
pollutants and environmental parameters to be monitored;
¡¤
Describe the equipment
and measurement method to be used;
¡¤
Address the criteria
for placing air sensors;
¡¤
Discuss the monitoring
locations selected and rationale;
¡¤
Describe the criteria
for selecting air sensors and test to determine if they are working properly;
¡¤
Determine the
collocation location and establish the calibration and/or collocation and data
correction methods;
¡¤
Identify types of data
that may be used in the data analysis, including nearby reference monitor data,
weather data, etc.;
¡¤
List the procedures to
maintain and operate air sensors, including site visits, routine maintenance,
emergency maintenance, daily data review, periodic collocations, etc.; and
¡¤
Describe the data processing
(including data checking against Quality Assurance and Quality Control (QA/QC)
procedures, data validation, data storage) and reporting requirements.
2.2.11
The ET is responsible for the provision of the monitoring equipment and
should provide sufficient number of air sensors for the field work and TS for
carrying out continuous impact monitoring and ad-hoc monitoring or
collocation.
2.2.12
If the ET proposes alternative dust monitoring equipment / wind data
monitoring equipment / methodology after the approval of this Manual, agreement
from the IEC should be sought. The instrument should also be calibrated monthly
following the requirements specified by the equipment
manufacturers.
2.3
Construction Dust Monitoring Stations
2.3.1
The tentative locations of the air sensors are listed in Table 2.1 and are
illustrated in Figure 2.1.
The actual locations would be subject to site constraints and the
ET should agree with IEC on the position of the air sensor for installation
taken into account the considerations detailed in Section 2.2.3.
Table 2.1
Proposed Construction Dust Monitoring Stations
|
Monitoring Station No.(1)(3)
|
Air Sensitive Receiver (ASR)
|
|
DM1
|
La Maison Vineyard
|
|
DM2
|
The Vineyard / Village House near Vineyard Boulevard
|
|
DM3
|
Greenacres Villa
|
|
DM4
|
Ha San Wai / EMINENT EIS International Preschool
|
|
DM5
|
Wah On Villa / San Wai Tsuen
|
|
DM6
|
Kadoorie Villas
|
|
DM7
|
Sheung Chuk Yuen
|
|
DM8
|
Hongtai Home for the Aged
|
|
DM9
|
Village House (2)
|
|
DM10
|
Village House (2)
|
|
DM11
|
Village House (2)
|
|
DM12
|
Village House (2)
|
Notes:
(1) RSP and FSP impact monitoring should
be conducted at the monitoring stations when there are Project-related major
construction activities including site formation, excavation and piling works
being undertaken within a radius of 500 m from the monitoring stations.
(2) Monitoring will not be
necessary if the proposed location is demolished/resumed under other project.
(3) Monitoring station at the ASR
should, where practicable, be positioned as close as possible to the works site
with major site activities, subject to future liaison and agreement with
respective ASR.
2.3.2
The status and locations of construction dust monitoring locations may
change after this Manual is issued. In such case, the ET should propose
alternative monitoring locations and seek approval from the ER and IEC as well
as agreement from the EPD.
2.3.3
When alternative monitoring locations are proposed, the monitoring
stations should be chosen based on the following criteria:
¡¤
Monitoring at ASRs
close to the major site activities which are likely to have air quality
impacts;
¡¤
Monitoring as close as
possible to the ASRs as defined in the EIAO-TM;
¡¤
Assurance of minimal
disturbance to the occupants and working under a safe condition during
monitoring; and
¡¤
Take into account the
prevailing meteorological conditions.
2.3.4
The ET should agree with the IEC on the position of the
instrument. When positioning the instrument, the following points should be noted:
¡¤
a horizontal platform
with appropriate support to secure the instrument against gusty wind should
be provided;
¡¤
general housekeeping,
cleaning works and other preventative maintenance activities such as checking
the operating status of individual monitoring equipment should be carried out
to ensure the proper operation of the system;
¡¤
the distance between
the instrument and an obstacle, such as buildings, must be at least twice the
height that the obstacle protrudes above the instrument;
¡¤
to ensure
representative sampling, the inlet of the instrument should not be obstructed
by nearby objects;
¡¤
any wire fence and
gate, to protect the instrument, should not cause any obstruction during
monitoring;
¡¤
no furnace or
incinerator flue is nearby;
¡¤
airflow around the
instrument is unrestricted;
¡¤
permission must be
obtained to set up the instrument and to obtain access to the monitoring
stations; and
¡¤
a secured supply of
electricity is needed to operate the instrument.
2.3.5
Subject to site conditions and monitoring results, the ET, with IEC and
EPD endorsement, may decide whether the monitoring locations should be removed
/ relocated during the construction phase.
2.4
Construction Dust Impact Monitoring
2.4.1
The ET should carry out hourly impact monitoring of RSP and FSP
continuously with air sensor networks during major construction activity of the
Project being undertaken within a radius of 500 m from the monitoring
stations. The daily averages of RSP and FSP are to be determined and
reported in monthly EM&A Report, together with the hourly RSP data.
The impact monitoring programme is summarised in Table 2.2.
2.4.2
The monthly collocation schedule should be drawn up by the ET one month
prior to the commencement of the scheduled construction period. Before
commencement of the collocation, the ET should inform the IEC such that the IEC
can conduct an on-site audit.
Table 2.2
Summary of Construction Dust Monitoring Programme
|
Monitoring Period
|
Duration
|
Sampling Equipment
|
Sampling Parameter
|
Frequency
|
|
Impact Monitoring
|
Throughout the construction phase(1)
|
Air Sensor Network
|
1-hour RSP, and 24-hour RSP and FSP
|
Continuous (Results to be reported in Monthly EM&A Report)
|
Note:
(1) Impact monitoring should be
conducted at the monitoring stations for 1-hour RSP, and 24-hour RSP and FSP
monitoring when there are Project-related major construction activities being
undertaken within a radius of 500 m from the monitoring stations.
2.5
Construction Dust Event and Action Plan
2.5.1
The air quality criteria for the impact monitoring should refer to the
relevant Air Quality Objectives (AQOs). The ET should compare the impact
monitoring results with air quality criteria set up for 1-hour RSP, 24-hour RSP
and FSP. Table 2.3 shows the current air quality criteria, namely A/L
levels. The A/L levels may be subject to changes based on the prevailing AQOs
implemented at the time of the impact monitoring.
Table 2.3
Current Action and Limit Levels for Impact Monitoring
|
A/L Level
|
Parameter
|
Criteria
|
|
Action Level
|
1-hour RSP level
|
128 ¦Ìg/m3
|
|
Limit Level
|
24-hour RSP level (Rolling average)
|
75 ¦Ìg/m3
|
|
24-hour FSP level (Rolling average)
|
37.5 ¦Ìg/m3
|
2.5.2
The Event and Action Plan prescribes procedures and actions associated
with the outcome of the comparison of air quality monitoring data recorded and
the agreed A/L levels. In the cases where exceedances of these A/L levels
occur, the ET, the IEC, the ER and the Contractor should strictly observe the
relevant actions of the respective Event and Action Plan listed in Table 2.4.
Table 2.4
Event and Action Plan for Construction Dust Monitoring
|
EVENT
|
ACTION
|
|
ET
|
IEC
|
ER
|
CONTRACTOR
|
|
ACTION
LEVEL
|
|
Exceedance
for one 1-hour RSP concentration
|
1. Notify
IEC and ER;
2. Check
the monitoring data and error messages to confirm if the performance of the
monitoring equipment is normal;
3. If exceedance is confirmed,
identify source(s), investigate the causes of exceedance and propose remedial
measures; and
4. Assess
effectiveness of Contractor¡¯s remedial measures and keep IEC, and ER informed
of the results until exceedance stops.
|
1. Check
monitoring data submitted by the ET;
2. Check
Contractor¡¯s working method;
3. Discuss with ET, ER
and Contractor on possible remedial measures;
4. Advise
the ET and ER on the effectiveness of the proposed remedial measures; and
5. Supervise
implementation of remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing.
2. Notify
Contractor;
3. In
consultation with ET and IEC, agree with the Contractor on the remedial
measures to be implemented; and
4. Ensure
the proposal for remedial measures are properly implemented.
|
1. Identify
source(s) of exceedance, and discuss with ER, ET and IEC on possible remedial
measures;
2. Implement
remedial measures; and
3. Amend
working methods if appropriate.
|
|
Exceedance
for two or more consecutive 1-hour RSP concentration
|
1. Notify
IEC and ER;
2. Check
the monitoring data and the performance of monitoring equipment (refer to Appendix D) to confirm if the performance of the monitoring equipment is normal;
3. If
exceedance is confirmed, identify source(s), investigate the causes of
exceedance and propose remedial measures;
4. Discuss
with IEC, ER and Contractor on possible remedial measures required; and
5. Assess
effectiveness of Contractor¡¯s remedial measures and keep IEC, and ER informed
of the results until exceedance stops; and
6. Notify EPD if the
exceedance is confirmed to be related to the Project.
|
1. Check monitoring data submitted by the ET;
2. Check Contractor¡¯s working method and verify the performance of the
monitoring equipment to be checked by ET (refer to Appendix D);
3. Discuss with ET, ER and Contractor on possible remedial measures;
4. Review and advise the ET and ER on the effectiveness of the proposed
remedial measures; and
5. Supervise Implementation of remedial measures.
|
1. Confirm
receipt of notification of exceedance in writing;
2. Notify
Contractor;
3. In
consultation with the ET and IEC, agree with the Contractor on the proposal
for remedial measures to be implemented; and
4. Ensure
the proposal for remedial measures are properly implemented.
|
1. Identify
source(s) of exceedance and discuss with ER, ET and IEC on possible remedial
measures;
2. Submit
a proposal for remedial measures to ER, IEC and ET within two working days of
notification of exceedance for agreement;
3. Implement
the agreed proposals; and
4. Amend
proposal as appropriate.
|
|
LIMIT
LEVEL
|
|
Exceedance
for one 24-hour rolling average RSP concentration record and/or one 24-hour
rolling FSP concentration record
|
1. Notify
IEC, ER and Contractor and EPD;
2. Check
the monitoring data and the performance of the monitoring equipment (refer to
Appendix D);
3. If
exceedance is confirmed, identify source(s), investigate the causes of
exceedance and propose remedial measures;
4. Discuss
with IEC, ER and Contractor on possible remedial measures required; and
5. Assess
effectiveness of Contractor¡¯s remedial measures and keep IEC, ER and EPD
informed of the results until exceedance stops.
6. Notify
EPD if the exceedance is confirmed to be related to the Project.
|
1. Check monitoring data submitted by the ET;
2. Check Contractor¡¯s working method; and verify the performance of the
monitoring equipment to be checked by ET (refer to Appendix D);
3. Discuss with the ET, ER and Contractor on possible remedial measures;
4.
Advise
the ET and ER on the effectiveness of the proposed remedial measures;
5.
Review
Contractors¡¯ remedial measures whenever necessary to assure their
effectiveness and advise ET and ER accordingly; and
6.
Supervise
implementation of remedial measures.
|
1. Confirm receipt of notification of exceedance in writing;
2. Notify Contractor;
3.
In
consultation with the ET and IEC, agree with the Contractor on the proposal
for remedial measures to be implemented;
4.
Ensure
the proposal for remedial measures properly implemented.
5.
If
exceedance continues, identify what portion of the work is responsible and instruct
the Contractor to stop that portion of work until exceedance is abated.
|
1. Identify
source(s) and discuss with ER, ET and IEC on possible remedial measures;
2. Take
immediate action to avoid further exceedance;
3. Submit
a proposal for remedial measures to ER, ET and IEC within two working days of
notification for agreement;
4. Implement
the agreed proposals;
5. Review
and resubmit proposals if the problem is still not under control.
6. Stop
the relevant portion of works as determined by ER until exceedance is abated.
|
2.6
Construction Dust Mitigation Measures
2.6.1
Site-specific dust mitigation measures recommended in the EIA Report include
watering on active works sites / works areas, exposed areas and haul roads,
good site practices and dust suppression measures stipulated in Air Pollution
Control (Construction Dust) Regulation. Details of the mitigation measures are
presented in Appendix C. The Contractor should be
responsible for the design and implementation of these measures.
2.7
Construction Dust Audit Requirements
2.7.1
Regular site inspection and audit at least once per week should be
conducted during the entire construction phase of the Project to ensure the
recommended mitigation measures are properly implemented.
3
NOISE Impact
3.1
Introduction
3.1.1
Construction noise, road traffic noise, fixed noise sources, airborne
rail noise and ground-borne rail noise impacts were assessed in the EIA Report.
3.1.2
With the mitigation measures in place, no adverse construction noise
impact would be anticipated. A Construction Noise Management Plan
(CNMP), which contains a quantitative construction noise impact assessment,
noise mitigation measures, monitoring and audit programme,
event and action plan and implementation schedule should be submitted before
tender invitation and before the commencement of construction works to evaluate
the potential construction noise impacts and assess the effectiveness and
practicality of all proposed noise mitigation measures for the Project. The
implementation of the mitigation measures recommended in CNMP should also be
audited as part of the EM&A programme. Regular
site environmental audit during construction phase is recommended to ensure
proper implementation of mitigation measures and good site practices.
3.1.3
Although no adverse
road traffic noise impact is anticipated from the Project with the proposed
mitigation measures in place, road traffic noise levels should be monitored at
selected representative noise sensitive receivers (NSRs) located in the vicinity of the
proposed at-source mitigation measures, during the first year of road opening
and population intake of protected NSRs to ascertain that the recommended
at-source mitigation measures are effective in reducing the noise levels.
3.1.4
There are no proposed
fixed noise sources under the DPs of the Project. For the non-DPs, a
quantitative fixed noise impact assessment (FNIA) with consideration of latest
available information and cumulative impacts, together with recommendation of
appropriate mitigation measures, should be conducted during detailed design
stage via various planning/funding/land lease mechanism in accordance with the
requirements of the Hong Kong Planning Standards and Guidelines (HKPSG). No
specific EM&A requirement would be required.
3.1.5
Based on the assessment results in the approved EIA reports for NOL Main
Line and High Speed Rail (HSR), no adverse airborne and ground-borne rail noise
impact would be anticipated with the mitigation measures in place. Noise
monitoring for rail noise is not required during the operational phase of the
Project.
3.1.6
This section presents the requirements, methodology, equipment,
monitoring locations, criteria and protocols for the monitoring and audit of
construction noise impacts during
the construction and road traffic noise impacts during operational phase of the Project.
3.2
Construction Phase
Noise Parameters
3.2.1
The construction noise level should be measured in terms of the
30-minute A-weighted equivalent continuous sound pressure level (Leq 30min), which should be used as
the monitoring parameter, for the time period between 0700 and 1900 hours on
normal weekdays.
3.2.2
Supplementary information for data auditing and statistical results such
as L10 and L90 should also be obtained for
reference. A sample data record sheet is shown in Appendix E for reference.
Monitoring Equipment and Set up
3.2.3
As
referred to the requirements of the Technical Memorandum (TM) issued under the Noise
Control Ordinance (NCO), sound level meters in compliance with the
International Electrotechnical Commission Publications 651:1979 (Type 1) and
804:1985 (Type 1) specifications should be used for carrying out the noise
monitoring. Immediately prior to and following each noise measurement,
the accuracy of the sound level meter should be checked using an acoustic
calibrator generating a known sound pressure level at a known frequency.
Measurements should be accepted as valid only if the difference between
calibration levels obtained before and after the noise measurement is less than
1.0 dB(A).
3.2.4
The construction noise monitoring station should normally be at a point
1 m from the exterior of the noise sensitive facade and be at a position 1.2 m
above ground. The ET should agree with the IEC on the monitoring position
and the corrections as required according to standard acoustic
principles.
3.2.5
Noise measurements should be made in accordance
with standard acoustic principles and practices in the relation to weather
conditions. Noise measurements should not be made in fog, rain, wind
with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The
wind speed should be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
3.2.6
The
ET is responsible for the provision of the monitoring equipment and should
ensure that sufficient noise measuring equipment and associated instrumentation
are available for carrying out the baseline monitoring and impact
monitoring. All the equipment and associated instrumentation should be
clearly labelled. The equipment installation location should be proposed by
the ET Leader and agreed with the ER and IEC.
Baseline
and Impact Monitoring
3.2.7
Baseline noise monitoring should be carried out at the monitoring
stations to be designated in the CNMP(s) as appropriate for at least 2
weeks prior to the commissioning of the construction works. During the baseline
monitoring, there should not be any construction activities as far as
practicable in the vicinity of the designated monitoring stations.
3.2.8
During impact monitoring, construction noise
monitoring should be carried out at the designated monitoring stations between
0700 and 1900 hours on normal weekdays when there are Project-related
construction activities being undertaken within a radius of 300m from the
respective monitoring stations.
3.2.9
As discussed in Section 3.1.2, a CNMP should be submitted to EPD before
tender invitation and before the commencement of construction works. Subject
to the contractual arrangement, land resumption status and construction progamme as well as the assessment findings of quantitative
construction noise impact assessment, the details of the construction
noise monitoring requirements and audit programme,
event and action plan and implementation schedule should be derived and included in
the CNMP(s) for agreement with EPD.
Action and Limit Levels
3.2.10
The A/L levels for construction noise are defined in Table 3.1.
Table 3.1
Action and Limit Levels for Airborne Construction Noise Impact Monitoring
|
Time Period
|
Action Level
|
Limit Level
|
|
0700 - 1900 hours on normal weekdays (1)
|
When one documented complaint is received
|
75 dB(A) (2)
|
Notes:
(1) If works are to be carried out
during restricted hours, the conditions stipulated in the Construction Noise
Permit issued by the Noise Control Authority have to be followed.
(2) 70 dB(A) for educational
institutions and 65 dB(A) during school examination periods.
3.3
Operational Phase ¨C Road Traffic Noise
Noise Parameters
3.3.1
The ET should carry out monitoring of road traffic noise after the works
under Contract are completed and upon commencement of operation of the
Project¡¯s roads. The noise monitoring should be carried out during the first
year of road opening. The road
traffic noise during operation of the Project¡¯s roads should be measured
in terms of the A-weighted equivalent of L10 (1-hr). During the road
traffic noise measurement, traffic count including traffic volume, percentage
of heavy vehicles as defined in the Calculation of Road Traffic Noise and
traffic speed should also be undertaken concurrently. Supplementary information
for data auditing and statistical results such as Leq
and L90 should also be obtained for reference.
3.3.2
Noise measurements should not be made in fog, rain, wind with a steady
speed exceeding 5 m/s or wind with gusts exceeding 10 m/s. The wind speed
should be checked with a portable wind speed meter capable of measuring the
wind speed in m/s.
Monitoring Stations
3.3.3
Representative
NSRs that are mostly affected were identified in the EIA Report are selected as
the noise monitoring stations in this Manual, with their locations listed in Table 3.2 and illustrated
in Figure
3.1. The proposed location at the planned NSR should be defined during
detailed design on the basis of the status of the most up-to-date information
on the proposed development(s) of the Project.
Table 3.2
Proposed Road Traffic Noise Monitoring Stations during Operational Phase
|
Monitoring Station ID (1)
|
NSR ID in EIA Report
|
Noise Sensitive Receiver
|
|
For DPs
|
|
OM2
|
PN01
|
Proposed Dedicated Rehousing Estate at RSc.1
|
|
OM3
|
N39
|
Sheung Chuk Yuen
|
|
OM4
|
N42
|
Kadoorie Villas
|
|
OM5
|
N19
|
San Wai Tsuen
|
|
OM6
|
N44 / N19
|
Wah On Villa / San Wai Tsuen
|
|
OM7
|
N41
|
Hongtai Home for the Aged
|
|
For non-DPs
|
|
OM1
|
N09
|
Elegant Park
|
Note:
(1) Monitoring station at NSR should,
where practicable, be positioned as close as possible to the Project roads,
subject to future liaison and agreement with respective NSR.
3.4
Operational Phase ¨C Fixed Noise Sources
3.4.1
For non-DP fixed noise sources, quantitative fixed noise impact
assessment, with consideration
of latest available information and cumulative impacts, together with
recommendation of appropriate mitigation measures, should be conducted during
detailed design stage via various planning/funding/land lease mechanism for
agreement with Director of Environmental Protection (DEP) in accordance with the requirements
of the HKPSG.
3.5
Mitigation Measures
Construction Phase
3.5.1
Mitigation measures
including good site practices, use of quality powered mechanical equipment and
quieter construction methods, and use of temporary movable noise barriers,
noise insulating fabric or noise enclosure were recommended in the EIA Report.
The implementation schedule for the recommended mitigation measures is
presented in Appendix C.
3.5.2
Construction Noise Management
Plan(s) (CNMP(s)) should be prepared based on the best available information
before tender invitation and the commencement of construction works, subject to
the contract arrangement of the Project and agreement with EPD. The
CNMP(s) should include
the proposed/exact inventory of noise sources, quantitative construction noise
impact assessment, listing of the quieter construction method/equipment, review
the effectiveness and practicality of all proposed mitigation measures for
minimising the construction noise impact, implementation schedule of the
mitigation measures (including implementation party, location, timing of
implementation), and the details of the construction noise monitoring
requirements and audit program. The CNMPs should be prepared by a
Certified Noise Modelling Professional as recognised by the Hong Kong Institute
of Qualified Environmental Professionals (HKIQEP), or equivalent as agreed by
the DEP.
Operational Phase ¨C Road Traffic Noise
3.5.3
Direct road traffic
noise mitigation measures including low noise road surfacing (LNRS), noise
barriers and acoustic windows/balconies were proposed in the EIA Report to
alleviate adverse road traffic noise impact during the operational phase and
are presented in Table 3.3. The implementation schedule for the
recommended mitigation measures is presented in Appendix C.
Table 3.3
Extent and Locations of Proposed Direct Noise Mitigation Measures
|
ID
|
Type
|
Vertical Height, m
|
Approx. Length, m
|
Location
|
|
LNRS1
|
LNRS
|
N/A
|
260
|
San Tam Road
|
|
LNRS2
|
LNRS
|
N/A
|
511
|
San Tam Road
|
|
LNRS3
|
LNRS
|
N/A
|
80
|
Road L1
|
|
LNRS4
|
LNRS
|
N/A
|
68
|
Road L1
|
|
LNRS5
|
LNRS
|
N/A
|
151
|
Ngau Tam Mei Road
|
|
LNRS6
|
LNRS
|
N/A
|
101
|
Ngau Tam Mei Road
|
|
LNRS7
|
LNRS
|
N/A
|
110
|
Ngau Tam Mei Road
|
|
LNRS8
|
LNRS
|
N/A
|
197
|
Road D1
|
|
LNRS9
|
LNRS
|
N/A
|
42
|
Road D1
|
|
LNRS10
|
LNRS
|
N/A
|
55
|
Road D1
|
|
LNRS11
|
LNRS
|
N/A
|
294
|
Road D1
|
|
LNRS12
|
LNRS
|
N/A
|
103
|
Chuk Yau Road
|
|
LNRS13
|
LNRS
|
N/A
|
79
|
San Tam Road
|
|
AW1
|
Acoustic Windows / Balconies lined with Sound
Absorptive Material
|
N/A
|
N/A
|
Site RSc.1
(17th to 25th Floor of NAP RSc.1-2e)
|
|
AW2
|
Acoustic Windows / Balconies lined with Sound
Absorptive Material
|
N/A
|
N/A
|
Site RSc.1
(13th to 33rd Floor of NAP
RSc.1-1f)
|
|
AW3
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site RSc.1
(8th to 25th Floor of
NAPs RSc.1-2a;
5th
to 25th Floor of NAP RSc.1-2b;
4th
to 25th Floor of NAP RSc.1-2c;
3rd
to 25th Floor of NAP RSc.1-2d;
1st
to 16th Floor of NAP RSc.1-2e)
|
|
AW4
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site RSc.1
(1st to 42nd Floor of NAPs
RSc.1-1a to RSc.1-1b;
12th
to 42nd Floor of NAP RSc.1-1c;
1st
to 42nd Floor of RSc.1-1d;
9th
to 42nd Floor of RSc.1-1e;
1st
to 12th and 34th to 42nd Floor of RSc.1-1f)
|
|
AW5
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site R.1
(8th to 37th Floor of NAP
R.1-1a;
2nd to 37th Floor of NAP
R.1-1b;
5th to 37th Floor of NAP
R.1-1c;
24th to 37th Floor of NAP
R.1-1d)
|
|
AW6
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site R.1
(1st to 37th Floor of NAP
R.1-2d)
|
|
AW7
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site R.1
(26th to 37th Floor of NAP
R.1-3a;
23rd to 37th Floor of NAP
R.1-3b;
6th to 37th Floor of NAPs
R.1-3c to R.1-3d)
|
|
AW8
|
Acoustic Windows / Balconies
|
N/A
|
N/A
|
Site R.1
(11th to 37th Floor of NAP
R.1-4a;
10th to 37th Floor of NAP
R.1-4b)
|
|
NB1
|
Vertical Noise Barrier
|
7
|
53
|
San Tin Highway
|
|
NB2
|
Vertical Noise Barrier
|
4.5
|
31
|
San Tam Road
|
|
NB3
|
Vertical Noise Barrier
|
2.5
|
43
|
San Tam Road
|
|
NB4
|
Vertical Noise Barrier
|
2
|
18
|
San Tam Road
|
|
NB5
|
Vertical Noise Barrier
|
2.5
|
24
|
San Tam Road
|
|
NB6
|
Vertical Noise Barrier
|
4
|
10
|
San Tam Road
|
|
NB7
|
Vertical Noise Barrier
|
4
|
8
|
San Tam Road
|
|
NB8
|
Vertical Noise Barrier
|
2
|
48
|
Road D1
|
|
NB9
|
Vertical Noise Barrier
|
3
|
189
|
Road D1
|
|
NB10
|
Vertical Noise Barrier
|
5.5
|
80
|
Road D1
|
|
NB11
|
Vertical Noise Barrier
|
3
|
25
|
Road D1
|
|
NB12
|
Vertical Noise Barrier
|
4
|
71
|
Road D1
|
|
NB13
|
Vertical Noise Barrier
|
2.5
|
47
|
Site A.4
|
|
NB14
|
Vertical Noise Barrier
|
2
|
44
|
Road L1
|
|
CB1
|
7m (H) Vertical Noise Barrier with 3m Cantilever at
45 Degree
|
7
|
193
|
San Tin Highway
|
|
CB2
|
7m (H) Vertical Noise Barrier with 3m Cantilever at
45 Degree
|
7
|
118
|
San Tin Highway
|
Operational Phase ¨C Fixed Noise Sources
3.5.4
The tentative mitigation measures as recommended in the EIA Report for
the proposed fixed noise sources under the Project include enclosing pumps and
noisy plants inside building structures, proper selection of quiet plant,
installation of silencer/acoustic enclosure/acoustic louvre for the exhaust of
ventilation system and locating openings of ventilation systems away from NSRs
as far as practicable. Details of the suggested mitigation measures are
presented in Appendix C.
These measures should be reviewed and refined as appropriate by the proponent
of the proposed fixed noise sources if there are any major design changes
during the detailed design phase such that the recommended measures are
adequate for alleviating the potential operational fixed noise sources impact.
3.6
Audit Requirements
3.6.1
Regular site environmental audit during the construction phase of the
Project should be conducted at least once per week to ensure proper
implementation of mitigation measures and good site practices as listed in Appendix C and the noise
control requirements stated in EPD¡¯s "Recommended Pollution Control
Clauses for Construction Contracts¡± to further minimise
the potential noise nuisance during construction phase.
4
Water Quality impact
4.1
Introduction
4.1.1
Potential water quality impacts arising from the construction and
operational phases of the Project were identified and assessed in the EIA
Report. With the implementation of the recommended mitigation measures, no
adverse water quality impacts from the Project would be expected during the
construction and operational phases of the Project. Nevertheless, water
quality monitoring at NTMDC should
be conducted before, during and after the construction phase. Regular inspections of the construction
activities throughout the construction phase should also be conducted to ensure
that the recommended mitigation measures are properly implemented. With
proper implementation of mitigation measures during detailed design stage, no
monitoring or audit is required during the operational phase.
4.2
Construction Phase
Monitoring Parameters
4.2.1 Monitoring for
Dissolved Oxygen (DO), Dissolved Oxygen Saturation (DO%), temperature, pH,
turbidity, salinity, suspended solid (SS) and water depth should be undertaken
at all designated monitoring stations. All parameters should be measured
in-situ whereas SS should be determined by the laboratory. DO should be
presented in mg/L and in % saturation.
4.2.2
Other relevant data should also be recorded, including monitoring
station / position, time, tidal stages, weather conditions and any special
phenomena or work underway at the construction site. A sample data record sheet is shown in Appendix E
for reference.
Monitoring
Equipment
4.2.3
The following equipment
and facilities should be provided by the ET and used for the water quality
monitoring.
Monitoring
Position Equipment
4.2.4
A hand-held or
boat-fixed type digital Differential Global Positioning System (DGPS) with way
point bearing indication or other equipment instrument of similar accuracy,
should be provided and used during water quality monitoring to ensure the
correct position before taking measurement and water samples.
Sampler
4.2.5
A water sampler is
required. It should comprise a transparent PVC cylinder, with a capacity
of not less than 2 litres, which can be effectively sealed with latex cups at
both ends. The sampler should have a positive latching system to keep it
open and prevent premature closure until released by a messenger when the
sampler is at the selected water depth (e.g. Kahlsico
Water Sampler or an approved similar instrument).
Water Depth
Detector
4.2.6
A portable,
battery-operated echo sounder should be used for the determination of water
depth at each designated monitoring station. This unit can either be
hand-held or affixed to the bottom of the work boat, if the same vessel is to
be used throughout the monitoring programme.
Dissolved Oxygen
and Temperature Measuring Instrument
4.2.7
The instrument should
be a portable and weatherproof DO measuring instrument complete with cable and
sensor, and use a DC power source. The equipment should be capable of
measuring:
¡¤
a DO-level in the range
of 0 - 20 mg/L and 0 - 200% saturation; and
¡¤
a temperature of 0 - 45
degree Celsius with a capability of measuring to ¡À0.1 degree Celsius.
4.2.8
It should have a
membrane electrode with automatic temperature compensation complete with a
cable. Sufficient stocks of spare electrodes and cables should be
available for replacement where necessary, for example, YSI model 59 meter, YSI
5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved
similar instrument.
4.2.9
Should salinity
compensation not be built-in to the DO equipment, in-situ salinity should be
measured to calibrate the DO equipment prior to each DO measurement.
Turbidity
Measuring Instrument
4.2.10
Turbidity should be
measured in-situ by the nephelometric method. The instrument should be
portable and weatherproof using a direct current (DC) power source complete
with cable, sensor and comprehensive operation manuals. It should have a
photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (e.g.
Hach model 2100P or an approved similar instrument). The cable should not
be less than 25m in length. The meter should be calibrated in order to
establish the relationship between NTU units and the levels of suspended
solids.
Salinity
Measuring Equipment
4.2.11
A portable salinometer
capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt)
should be provided for measuring salinity of the water at each monitoring
station.
pH Measuring
Equipment
4.2.12
The instrument should consist of a potentiometer, a glass
electrode, a reference electrode and a temperature-compensating device.
It should be readable
to 0.1 pH in a range of 0 to 14. Standard buffer solutions of at least pH
7 and pH 10 should be
used for calibration of the instrument before and after use. Details of
the method should comply with American Public Health Association (APHA), 19th
Edition 4500-HTB.
Sample
Containers and Storage
4.2.13
Water samples for SS determination
should be stored in suitable containers with no preservative added, packed in
ice (cooled to 4¡æ without being frozen) and delivered to the laboratory and analysed as
soon as possible after collection. Sufficient volume of samples should be
collected to achieve the detection limit.
Calibration of
in-situ Instruments
4.2.14
All in-situ monitoring
instruments should be checked, calibrated and certified by a laboratory
accredited under Hong Kong Laboratory Accreditation Scheme (HOKLAS) or any
other international accreditation scheme before use and subsequently
re-calibrated at three monthly intervals throughout all stages of the water
quality monitoring programme. Responses of sensors and electrodes should
be checked with certified standard solutions before each use. Wet bulb
calibration for a DO meter should be carried out before measurement at each
monitoring station.
4.2.15
For the on-site
calibration of field equipment, the BS 127:1993, Guide to Field and On-Site
Test Methods for the Analysis of Water should be observed.
4.2.16
Sufficient stocks of
spare parts should be maintained for replacements when necessary. Backup
monitoring equipment should also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
Laboratory
Measurement / Analysis
4.2.17
Analysis of SS level
should be carried out in a HOKLAS or other international accredited laboratory
that is HOKLAS-equivalent. Sufficient volume of each water sample should
be collected at the monitoring stations for carrying out the laboratory SS determination.
All samples should be assigned a unique code and accompanied by Chain of
Custody sheets.
4.2.18
The SS determination
work should start within 24 hours after collection of the water samples.
The SS analyses should follow the standard method APHA 2540D with a detection
limit of 1 mg/L as described in APHA Standard Methods for the Examination of
Water and Wastewater, 21st Edition, unless otherwise specified.
4.2.19
Detailed testing
methods, pre-treatment procedures, instrument use, QA/QC details (such as
blank, spike recovery, number of duplicate samples per batch, etc.), detection
limits and accuracy should be submitted to EPD for approval prior to the
commencement of monitoring programme. EPD may also request the laboratory
to carry out analysis of known standards provided by EPD for quality
assurance. The testing methods and related proposal should be checked and
certified by IEC before submission to EPD for approval.
4.2.20
Additional duplicate
samples may be required by EPD for inter laboratory calibration. Remaining
samples after analysis should be kept by the laboratory for 3 months in case
repeat analysis is required. If in-house or non-standard methods are
proposed, details of the method verification may also be required to submit to
EPD. In any circumstance, the sample testing should have comprehensive
QA/QC control programmes. The laboratory should prepare to demonstrate
the programmes to EPD or his representatives when requested.
Monitoring
Schedule and Stations
4.2.21 The proposed water quality monitoring schedule should
be submitted to EPD at least two weeks before the first day of the monitoring
month. EPD should also be notified immediately for any changes in
schedule. The monitoring stations proposed in this section are indicative
and are subject to further review before the construction phase. The
locations of monitoring stations may change after issuing this Manual.
The proposed monitoring stations should be submitted four weeks before commencement
of baseline monitoring for EPD approval.
4.2.22 When alternative monitoring stations are proposed,
they should be chosen based on the following criteria:
¡¤
close to the sensitive
receptors which are directly or likely to be affected;
¡¤
for monitoring stations
located in the vicinity of the sensitive receptors, care should be taken to
cause minimal disturbance during monitoring; and
¡¤
control station should
be at representative location of the Project Site and in its undisturbed
condition, and should be located both upstream and downstream of the works
sites as far as practicable.
4.2.23 It is proposed to monitor the water quality at three
locations (i.e. M1 to M3) and one control station (i.e. C1) in NTMDC.
Impact stations (i.e. M1 to M3) are designated in the vicinity of
revitalisation works within the Project Site to measure any elevation of
pollutant levels (e.g. SS level) due to the Project. Control station (i.e. C1)
is assigned upstream of the NTMDC to compare the monitored water quality from
the proposed impact stations (i.e. M1 to M3) with the ambient water quality during
the ebb tide and flood tide. All the proposed river water quality monitoring
stations are listed in Table 4.1 and their locations are shown in Figure 4.1.
Table 4.1
Proposed River Water Quality Monitoring Stations for Baseline, Construction
Phase and Post-Construction Monitoring
|
Station
|
Description
|
Easting
|
Northing
|
|
C1
|
Control Station
|
826198
|
837341
|
|
M1
|
Impact Station
|
825129
|
837248
|
|
M2
|
Impact Station
|
824483
|
837636
|
|
M3
|
Impact Station
|
823590
|
837728
|
Monitoring
Requirements
4.2.24 Baseline,
impact and post-construction monitoring should be conducted and the following
requirements should be followed:
¡¤
Measurement should be
taken at three water depths, namely, 1m below water surface, mid-depth and 1m above
riverbed, except where the water depth is less that 6m, the mid-depth station
could be omitted. Should the water depth be less than 3m, only the
mid-depth station will be monitored. The ET should agree with EPD on all
the monitoring stations;
¡¤
Duplicate in-situ
measurements and water samples collected from each independent monitoring event
are required for all parameters to ensure a robust statistically interpretable
dataset;
¡¤
No sampling should be
carried out when typhoon signal No. 3 or above or black rainstorm signal is
hoisted; and
¡¤
At each measurement
depth, two consecutive measurements should be taken. The probes should be
retrieved out of the water after the first measurement and then redeployed for
the second measurement. When the difference in value between the first
and second measurement of on-site parameters is more than 25% of the value of
the first reading, the reading should be discarded and further readings should
be taken.
Baseline
Monitoring
4.2.25 Baseline conditions for river water quality should be
established and agreed with EPD prior to the commencement of works at
NTMDC. The purposes of the baseline monitoring are to establish ambient
conditions prior to the commencement of the works and to demonstrate the
suitability of the proposed monitoring stations. A baseline monitoring report
should be submitted to EPD at least four weeks before the commencement of works
at NTMDC for agreement. The baseline monitoring report should be certified
by the ET Leader and verified by IEC before submission to EPD.
4.2.26 The baseline conditions should be established by
measuring water quality parameters as specified in Section 4.2.1 and Section
4.2.2 at the designated monitoring stations as shown in Table 4.1. The measurement
depths should follow those specified in Section 4.2.24. The
measurements should be taken at all designated monitoring stations including
control station, three days per week, at mid-flood and mid-ebb tides, for at
least four weeks prior to the commencement of works at NTMDC. There should
not be any river construction activities in the vicinity of the stations during
the baseline monitoring. The interval between two sets of monitoring
should not be less than 36 hours.
Impact
Monitoring
4.2.27 During the construction period of the proposed
revitalisation works at NTMDC, impact monitoring should be undertaken three
days per week, at mid-flood and mid-ebb tides, with sampling/measurement at all
designated monitoring stations including control station as specified in Table 4.1. The interval
between two sets of monitoring should not be less than 36 hours except where
there are exceedances of action and/or limit levels, in which case the
monitoring frequency will be increased. The monitoring parameters and
measurement depths should follow those specified in Section 4.2.1, Section
4.2.2 and Section 4.2.24. Duplicate water samples should be
taken and analysed.
4.2.28 If the impact monitoring data collected at the
monitoring stations (i.e. M1 to M3) indicate that the action or limit levels as
shown in Table 4.2 are exceeded, analysis should be conducted to identify
whether the exceedance is caused by Project activities. If the data
analysis results indicate that the exceedance is caused by this Project,
appropriate actions including lowering the working rate, or rescheduling of
works should be taken and additional mitigation measures should be implemented as
necessary.
Post-Construction
Monitoring
4.2.29 Upon completion of all works at NTMDC, a post-project
monitoring should be carried out for four weeks in the same manner as the
impact monitoring.
Event and Action
Plan
4.2.30
The A/L levels for
water quality are defined in Table 4.2. The actions in accordance
with the Event and Action Plan in Table 4.3 should be carried out if the
defined Action and/or Limit levels for water quality are exceeded at any
designated monitoring points.
Table 4.2 Action
and Limit Levels for Water Quality Monitoring
|
Parameters
|
Action Level
|
Limit Level
|
|
DO (mg/L)
|
Surface and Middle
5 percentile of baseline data
|
Surface and Middle
4 mg/L, or
1 percentile of baseline data
|
|
Bottom
5 percentile of baseline data
|
Bottom
2 mg/L, or
1 percentile of baseline data
|
|
SS (mg/L)
|
Depth Average
95 percentile of baseline data or 120% of upstream
control station at the same tide of the same day
|
Depth Average
99 percentile of baseline data or 130% of upstream
control station at the same tide of the same day
|
|
Turbidity (NTU)
|
Depth Average
95 percentile of baseline data or 120% of upstream
control station at the same tide of the same day
|
Depth Average
99 percentile of baseline data or 130% of upstream
control station at the same tide of the same day
|
Remarks:
(1) "Depth
Average" is calculated by taking the arithmetic means of reading of all
sampling depths.
(2) For DO,
non-compliance of the water quality limits occurs when monitoring result is
lower than the limits.
(3) For turbidity and
SS, non-compliance of the water quality limits occurs when monitoring result is
higher than the limits.
(4) All the figures
given in the table are for reference only and EPD may amend the figures
whenever it is considered as necessary.
Table 4.3
Event and Action Plan for Water Quality Monitoring
|
EVENT
|
ACTION
|
|
ET
|
IEC
|
ER
|
CONTRACTOR
|
|
Action level being exceeded by
one sampling day
|
1. Repeat in-situ measurement on
next day of exceedance to confirm findings;
2. Identify reasons for
non-compliance and source(s) of impact;
3. Inform IEC, Contractor and
ER; and
4. Check monitoring data, all
plant, equipment and Contractor¡¯s working methods.
|
1. Check monitoring data
submitted by ET and Contractor¡¯s working methods.
|
1. Confirm receipt of
notification of exceedance in writing.
|
1. Inform the ER and confirm
notification of the non-compliance in writing; and
2. Check all plant and
equipment and rectify unacceptable practice.
|
|
Action level being exceeded by
two or more consecutive sampling days
|
1. Repeat in-situ measurement on
the next day of exceedance to confirm findings;
2. Identify reasons for
non-compliance and source(s) of impact;
3. Inform IEC, Contractor and
ER;
4. Check monitoring data, all
plant and equipment, and Contractor's working methods;
5. Discuss additional mitigation
measures with IEC and Contractor and ensure mitigation measures are
implemented; and
6. Prepare to increase the
monitoring frequency to daily.
|
1. Discuss with ET and
Contractor on the mitigation measures and advise the ER accordingly;
2. Assess the effectiveness of
the implemented mitigation measures; and
3. Check monitoring data
submitted by ET and Contractor(s)¡¯s working methods.
|
1. Confirm receipt of
notification of exceedance in writing;
2. Discuss with IEC on the
proposed mitigation measures and agree on the mitigation measures to be
implemented;
3. Ensure additional mitigation
measures are properly implemented; and
4. Assess the effectiveness of
the implemented mitigation measures.
|
1. Inform the ER and confirm
notification of the non-compliance in writing;
2. Check all plant and equipment
and rectify unacceptable practice;
3. Consider changes of working
methods;
4. Discuss with ET and IEC and
propose mitigation measures to ER within three working days; and
5. Implement the agreed
mitigation measures.
|
|
Limit
level being exceeded by one sampling day
|
1. Repeat in-situ measurement on
the next day of exceedance to confirm findings;
2. Identify reasons for
non-compliance and source(s) of impact;
3. Inform IEC, Contractor and
ER;
4. Check monitoring data, all
plant, equipment and Contractor's working methods;
5. Discuss additional mitigation
measures with IEC, ER and Contractor and ensure mitigation measures are
implemented; and
6. Increase the monitoring
frequency to daily until no exceedance of limit level.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on
mitigation measures submitted by Contractor and advise the ER accordingly;
and
3. Assess the effectiveness of
the implemented mitigation measures.
|
1. Confirm receipt of
notification of exceedance in writing;
2. Discuss with IEC, ET and
Contractor on the proposed mitigation measures and agree on the mitigation
measures to be implemented;
3. Ensure additional mitigation
measures are properly implemented;
4. Assess the effectiveness of
the implemented mitigation measures; and
5. Request Contractor to
critically review the working methods.
|
1. Inform the ER and confirm
notification of the non-compliance in writing;
2. Check all plant and equipment
and rectify unacceptable practice;
3. Consider changes of working
methods;
4. Discuss with ET and IEC and
propose mitigation measures to ER within three working days; and
5. Implement the agreed
mitigation measures.
|
|
Limit level being exceeded by two
or more consecutive sampling days
|
1. Repeat in-situ measurement on
next day of exceedance to confirm findings;
2. Identify reasons for
non-compliance and source(s) of impact;
3. Inform IEC, Contractor and
ER;
4. Check monitoring data, all
plant, equipment and Contractor's working methods;
5. Discuss additional mitigation
measures with IEC, ER and Contractor and ensure mitigation measures are
implemented; and
6. Increase the monitoring
frequency to daily until no exceedance of limit level.
|
1. Discuss with ET and
Contractor on the mitigation measures;
2. Review proposals on
mitigation measures submitted by Contractor and advise the ER accordingly;
and
3. Assess the effectiveness of
the implemented mitigation measures.
|
1. Confirm receipt of
notification of exceedance in writing;
2. Discuss with IEC, ET and
Contractor on the proposed mitigation measures and agree on the mitigation
measures to be implemented;
3. Ensure additional mitigation
measures are properly implemented;
4. Assess the effectiveness of
the implemented mitigation measures;
5. Request Contractor to
critically review the working methods; and
6. Consider and instruct, if
necessary, the Contractor to slow down or to stop all or part of the
construction activities until no exceedance of limit level.
|
1. Inform the ER and confirm
notification of non-compliance in writing;
2. Check all plant and equipment
and rectify unacceptable practice;
3. Consider changes of working
methods;
4. Discuss with ET and IEC and
propose mitigation measures to ER within three working days;
5. Implement the agreed
mitigation measures; and
6. As directed by the ER, to
slow down or to stop all or part of the construction activities.
|
4.3
Mitigation Measures
4.3.1
Mitigation measures recommended for mitigation
of construction phase water quality impacts are provided in the Appendix C of this Manual. The Contractor should be
responsible for the design and implementation of the mitigation measures.
4.4
Audit Requirement
4.4.1
Weekly site audits including site inspections
and compliance audits should be conducted to ensure that the recommended good
site practices and the recommended mitigation measures listed in Appendix C are properly implemented by the Contractor during the
construction phase of the Project. It can also provide an effective
control of any malpractices and therefore achieve continual improvement of
environmental performance on site.
4.4.2
In the event that the
recommended mitigation measures are not fully or properly implemented,
deficiency should be recorded and reported to the site management. Suitable
actions are to be carried out to:
¡¤
investigate the
problems and the causes;
¡¤
issue action notes to
the Contractor who is responsible for the works;
¡¤
implement remedial and
corrective actions immediately;
¡¤
re-inspect the site
conditions upon completion of the remedial and corrective actions; and
¡¤
record the event and discuss
with the Contractor for preventive actions.
4.4.3
Apart from site audit, relevant documents
including licences and permits should be reviewed and audited for compliance
with the legislation and contract requirements.
5
Sewereage
and sewage treatment implications
5.1
Introduction
5.1.1
Potential
sewerage and sewage treatment implications arising from the construction and
operational phases of the Project were identified and assessed in the EIA
Report. It is anticipated that the proposed developments under the Project
would be sustainable from sewerage collection, treatment and disposal
prospective, and thus there would be no identified insurmountable sewerage and
sewage treatment implications arising from the Project. Therefore, no specific
EM&A requirement would be required.
5.2
EM&A Requirements
5.2.1
No environmental monitoring and audit requirements would be required.
6
WASTE
MANAGEMENT implications
6.1
Introduction
6.1.1
Construction and demolition (C&D) materials, chemical waste, general
refuse, excavated sediment, desilted materials and floating refuse would be
generated during the construction phase. It is the Contractor¡¯s responsibility
to ensure all the waste arisen from the Project are properly handled, stored,
transported and disposed of in accordance with good waste management practices,
relevant legislation and waste management guidelines. Provided that these
wastes are handled, stored, transported and disposed of using approved methods
and that the recommended good site practices and relevant legislation are
strictly followed, adverse environmental impacts would not be expected.
6.1.2
Municipal solid waste, chemical waste, clinical
waste and desilted materials would be generated during the operational phase.
The proposed waste infrastructures including refuse collection points and a
community recycling centre will provide convenient collection of recyclables
from the local community, and to create synergy to achieve better operational
efficiency and environmental sustainability. Provided that the wastes
are handled, stored, transported and disposed of using approved
methods, no adverse environmental impacts would be anticipated with
the implementation of good waste management practices. Monitoring and
audit programme for the operational phase of the
Project would not be required.
6.2
Mitigation Measures
6.2.1
Mitigation measures are recommended in the EIA Report and Appendix C provides the
implementation schedule of the recommended mitigation measures during both
construction and operational phases.
6.2.2
Waste generated during the construction activities should be audited
weekly by the ET. The ET should check whether the Contractor has implemented
the recommended good site practices, waste reduction measures and other
mitigation measures. All aspects of on-site waste management practices
including waste generation, storage, recycling, transport and disposal should
be considered. Apart from site inspection, documents including licences, permits, disposal and recycling records should be
reviewed and audited for compliance with the legislations and contract
requirements.
6.2.3
With the appropriate handling, storage and removal of waste arisings
during the construction and operation of the Project as presented in Appendix C, the potential to
cause adverse environmental impacts would be minimised.
6.3
Audit Requirement
6.3.1
Regular audits and site inspections should be carried out by the ER, ET
and Contractor during construction phase to ensure that the recommended good
site practices and the recommended mitigation measures in Appendix C are properly
implemented by the Contractor. The audit should concern all aspects of on-site
waste management practices including waste generation, storage, recycling,
transport and disposal. Apart from site inspection, documents including licences, permits, disposal and recycling records should be
reviewed and audited for compliance with the legislation and contract
requirements. In addition, the routine site inspection should check the
implementation of the recommended good site practices and other waste
management mitigation measures.
6.3.2
The requirements of the environmental audit programme
are set out in Section 15 of this Manual. The audit programme will verify the implementation status and
evaluate the effectiveness of the mitigation measures.
7
Land Contamination
7.1
Introduction
7.1.1
Land contamination assessment was conducted for the Project. Site
appraisal, in the form of desktop review and site walkover, had been carried
out to identify the past and current potentially contaminating land uses within
the Project Site.
7.1.2
As the concerned sites are currently inaccessible and still in
operation, and the construction works would not commence until 2027, further
land contamination assessment, including further site appraisal and submission
of Contaminated Assessment Plan(s) (CAP(s)), should be conducted for the whole
Project Site at a later stage of the Project when site access is available to
confirm the existing land uses / activities, identify the presence of any
potential contamination sources, and address any new contamination issues. The
associated site investigation (SI) works and any necessary remediation action
will be recommended to be carried out after operation of concerned site(s) has
ceased but prior to the commencement of construction works. The recommended
further assessment and remediation works, including the submission of CAP(s),
Contamination Assessment Report(s) (CAR(s))/Remediation Action Plan(s) (RAP(s))
and Remediation Report(s) (RR(s)) would follow the relevant Guidance Manual,
Guidance Note and Practice Guide and be submitted to EPD for approval.
7.2
Construction Phase
7.2.1
Remediation works, if necessary, would be carried out after the
operation of concerned site(s) has ceased but prior to the commencement of
construction works. Mitigation measures for the remediation works, if
necessary, as recommended in the EIA Report, Appendix C of this
Manual and future RAP(s) should be implemented during the remediation
works. EM&A should be carried out in the form of weekly site
inspection to ensure the recommended mitigation measures are properly
implemented and findings of the audit should be reported in the EM&A
reports.
7.3
Operational Phase
7.3.1
As any soil / groundwater contamination would be identified and properly
treated prior to commencement of construction works at the concerned site(s),
no land contamination is anticipated during the operational phase.
Specific EM&A requirement is therefore not required.
8
ecological
Implication (Terrestrial and Aquatic)
8.1
Introduction
8.1.1
Potential ecological impacts arising from the construction and
operational phases of the Project were assessed in the EIA Report. There
would be no direct impact on LTCP, CAs, Wetland Conservation Area (WCA) and
Priority Site for Enhanced Conservation. A small section of cycle track and the
associated connection are located in the developed area/wasteland habitat in
Yau Mei San Tsuen area, within the Wetland Buffer Area (WBA). Mitigation
measures are recommended to minimise the potential direct
and indirect impacts to the nearby recognised sites
of conservation importance, ecologically sensitive areas, natural habitats, as
well as the associated wildlife. With the implementation of appropriate
mitigation measures, no unacceptable adverse residual impacts would be
anticipated. Nonetheless, EM&A is considered necessary during
pre-construction and construction of the Project, and the requirements are
described below.
8.2
Mitigation Measures
8.2.1
The mitigation measures recommended in the EIA Report to minimise potential ecological impacts are stated in Appendix C.
8.3
Monitoring Requirements
Transplantation of
Flora Species of Conservation Importance
8.3.1
All flora species of conservation importance should be protected and
preserved as far as practicable. Nonetheless, four flora species of
conservation importance (i.e. Aquilaria sinensis, Aralia chinensis,
Brainea insignis and Ceratopteris thalictroides)
are located within the Project footprint. In case of unavoidable loss of
flora species of conservation importance, transplantation of the affected
individuals to nearby suitable habitat(s) should be implemented prior to the
commencement of site clearance. Prior to the commencement of site clearance, a
detailed Pre-Construction Vegetation Survey should be conducted by a qualified
botanist / ecologist with at least 5 years of relevant experience to confirm
the locations and health conditions of these flora species of conservation
importance. All individuals suitable for transplantation would be
identified and rescued, and transplanted to suitable receptor site(s).
8.3.2
A Plant Protection and Transplantation Proposal (PPTP) should be
prepared by qualified botanist / ecologist with at least 5 years of relevant
experience and should be submitted for approval from relevant Government
departments (e.g. Agriculture Fisheries and Conservation Department (AFCD) and
Environmental Protection Department (EPD)) at least 2 months before works
commencement. The PPTP should describe the screening / selection of receptor
site(s), details of the transplantation methodologies and subsequent monitoring
programme, such as monitoring frequency, monitoring
parameter.
8.3.3
Upon the transplantation of the identified individuals, a
post-transplantation monitoring should be implemented to monitor the health
conditions and survival of the transplanted individuals. A 3-year establishment
period would be provided for the flora species of conservation importance to be
transplanted. Monitoring of the transplanted plants should be conducted
bi-weekly in the first three months and monthly throughout the remaining
establishment period. Details of post-transplantation monitoring programme such as monitoring frequency, parameters,
maintenance works and remedial actions should also be recommended in the PPTP
for approval.
Translocation of Fauna
Species of Conservation Importance
Amphibian Species of
Conservation Importance
8.3.4
One amphibian species of conservation importance (i.e. Chinese Bullfrog)
was recorded within the Project Site in current survey and literature review.
The species should be translocated to nearby suitable habitat(s), such as the
wetland habitats in the vicinity of the Project Site, including the WCA and
Other Specified Uses (Wetland Conservation Park) to the west of San Tin
Highway, prior to the commencement of site clearance. A detailed
pre-construction fauna survey, focusing on the locations where they were
previously recorded within the Project Site, should be conducted by a qualified
ecologist with at least 7 years of relevant experience to identify and record
the affected individuals prior to commencement of site clearance.
8.3.5
Capture and translocation approach should be adopted for amphibian
species of conservation importance (i.e. Chinese Bullfrog) within the Project
Site. Both adults and tadpoles should be included in the scope of
translocation. The pre-construction fauna survey, capture and
translocation should be conducted during night-time when amphibians are
relatively active in order to maximise the capture
rate. A Capture and Translocation Proposal with details of the capture
and translocation methodologies, screening / selection of receptor site(s), and
capture and translocation process should be prepared by qualified ecologist
with at least 7 years of relevant experience and be submitted for approval from
relevant Government departments (e.g. AFCD and EPD) at least two months before
works commencement.
8.3.6
A three-year post-translocation monitoring programme
for the targeted amphibian species of conservation importance is required for
determining the success of the mitigation. Direct observation and counting,
mark-recapture and active search would be potential methodology for the
monitoring programmes. Detailed methodology, schedule
and frequency of monitoring programme would be
provided in the corresponding Capture and Translocation Proposal.
Aquatic Fauna Species
of Conservation Importance
8.3.7
Three aquatic species of conservation importance (i.e. two freshwater
crab species, Cryptopotamon anacoluthon
and Nanhaipotamon hongkongense,
and one freshwater fish species, Small Snakehead) were recorded in semi-natural
watercourse in the vicinity of the Project Site from current survey and
literature review. The species should be translocated to nearby suitable
habitat(s) prior to the commencement of site clearance. A pre-construction
fauna survey, focusing on the locations where they were previously recorded
within the Project Site, should be conducted by a qualified ecologist with at
least 7 years of relevant experience to identify and record the affected
individuals prior to the commencement of site clearance.
8.3.8
The identified individuals of aquatic species of conservation importance
within the Project footprint should be captured and translocated to suitable
receptor site(s). The hillside unpolluted natural watercourses within the LTCP
to the south of the Project Site could be potential receptor sites for the crab
species, while the natural or semi-natural watercourse at further upstream
section of watercourse W8 or W8c outside the Project Site might be the
potential receptor site for the fish species. Preparation of Capture and
Translocation Proposal with details of capture and translocation methodologies,
screening / selection of receptor site(s), and capture and translocation
process should be conducted by qualified ecologist with at least 7 years of
relevant experience and submitted for approval from relevant Government
departments (e.g. AFCD) at least two months before works commencement.
8.3.9
A three-year post-translocation monitoring programme
for the abovementioned crab and fish species of conservation importance is
required for determining the success of mitigation. Direct observation and
counting, mark-recapture and active search are potential methodology for the
monitoring programme. Detailed methodology, schedule
and frequency of monitoring programme would be
provided in the corresponding Capture and Translocation Proposal.
Wetland Compensation
8.3.10
A proposed wetland compensation site of 2.55 ha situated between Tsing
Long Highway and San Tam Road at Sha Po area adjacent to Kam Tin River is
identified (Figure 9.7 in the EIA Report refers) to compensate for the loss of
marsh/reed and natural watercourse habitats. A Habitat Creation and
Management Plan (HCMP) should be prepared by a qualified ecologist with at
least 7 years of relevant experience to form the basis of the proposed wetland
compensation site and submit for approval from relevant Government departments
(e.g. AFCD and EPD) during detailed design stage, at least two months before
commencement of site clearance of marsh/reed habitat and natural watercourse
under the Project. The HCMP should cover habitat design and construction
methods, monitoring protocol with particular focus on detailed design and
implementation details of the proposed wetland compensation site.
8.3.11
Monitoring should be conducted by a qualified ecologist with at least 7
years of relevant experience after the establishment of the proposed wetland
compensation site. Parameters of monitoring should focus on the abundance of
target species and the habitat conditions (e.g. water depth, water quality and
condition of the wetland vegetation, etc.) and presence of fauna species.
Management programmes (e.g. water control, structural
maintenance, supplemental planting, pest control, repair of damage, etc.)
should be conducted as necessary according to the approved HCMP.
Pre-construction Survey
and Nest Control for Nest of White-throated Kingfisher
8.3.12
According to the recent survey, an active nest of White-throated
Kingfisher was found in the mud wall in hillside plantation behind TMB.
Despite the active nest was recorded outside the Project Site, as a mitigation
measure, pre-construction survey and nest control should be implemented to
avoid direct injury to breeding pairs, chicks or eggs of this species of
conservation importance.
8.3.13
Pre-construction survey should be conducted by qualified ecologist in
breeding season (April to July), with special attention given to the specific
breeding habitat of White-throated Kingfisher and to identify the locations and
condition of the nest of this species within Project Site. All
breeding/nesting behaviour of White-throated
Kingfisher identified and associated detailed nest control measures should be
presented in the Pre-construction Survey Report, which should be submitted for
approval from relevant Government departments (e.g. AFCD and EPD) no later than
two months before commencement of works at the mud wall along hillside
plantation behind TMB.
8.3.14
Nest control measures should be implemented in non-breeding season (i.e.
late August to early March) to discourage breeding behaviour
within the Project Site prior to construction works in Ngau Tam Shan. To
discourage the nesting of White-throated Kingfisher, the mud wall and mud wall
tunnels within the Project Site on Ngau Tam Shan should be sealed in
non-breeding season. Prior to the implementation of nest control
measures, the holes on the mud wall within the Project Site should be surveyed
carefully by qualified ecologists to ensure no avifauna and / or eggs are
present. The detailed schedule of specific nest control measures would be
subject to the findings of the pre-construction survey and Nest Control
Proposal.
8.3.15
Preparation of Nest Control Proposal, pre-construction survey, and the
nest control measures should be conducted by a qualified ecologist with at
least 7 years of relevant experience to ensure the control measures and the
subsequent works would not injure any breeding pairs, chicks or eggs.
Other Minimisation Measures
8.3.16
As described in Section 2 to Section 4, EM&A programmes were recommended to ensure compliance of the
potential air quality, noise impacts and water quality impact respectively
(e.g. potential dust emission during construction phase, potential noise
exceedance from construction noise, and potential water pollution). Monitoring
requirements are further stated in the corresponding sections. Regular site
environmental audit during construction phase is also recommended to ensure
proper implementation of mitigation measures and good site practices.
8.4
Audit Requirements
8.4.1
Regular site environmental audits should be undertaken on weekly basis
to ensure proper implementation and maintenance of the recommended mitigation
measures during the construction phase of the Project.
9
Fisheries impact
9.1
Introduction
9.1.1
Potential fisheries impacts arising from the
construction and operational phases of the Project were assessed in the EIA
Report. No adverse residual impact on fisheries resources would be expected
from the Project.
9.2
Mitigation Measures
9.2.1
The mitigation measures recommended in the EIA Report to minimise potential fisheries impacts are provided in Appendix C.
9.3
Monitoring and Audit Requirements
9.3.1
With the implementation of water quality mitigation and precautionary
measures proposed in Section 5 of the EIA Report, the potential water quality
impacts arising from the Project would be minimised. Given that the monitoring and
audit requirement for potential water quality impact are provided in the
EM&A programme recommended in Section 4, no specific EM&A
programme is required for the potential fisheries impact.
10
LandScape and Visual impact
10.1
Introduction
10.1.1
The EIA has recommended landscape and visual mitigation measures to be
undertaken during both the construction and operational phases of the Project. The design, implementation and
maintenance of landscape and visual mitigation measures should be checked to
ensure that they are fully realised such that any potential conflicts between
the proposed landscape and visual measures and any other works of the Project
could be resolved as early as practicable without affecting the implementation
of the mitigation measures.
10.2
Mitigation
Measures
10.2.1
The proposed mitigation measures of landscape and visual impacts are summarised in Appendix
C. The landscape
and visual mitigation measures proposed should be incorporated in the detailed
landscape and engineering design. The construction phase
mitigation measures should be adopted from the commencement of the construction
and should be in place throughout the entire construction period. Mitigation
measures for the operational phase should be adopted during the detailed design
and be built as part of the construction works so that they are in place on
commissioning of the Project.
10.2.2
Any potential conflicts among the proposed mitigation measures, the
Project works, and operational requirements should also be identified and
resolved as early as practicable. Any changes to the mitigation measures
should be incorporated in the detailed design.
10.3
EM&A Requirement
10.3.1
The construction phase
EM&A of the mitigation measures should be carried out as part of the site
audit programme. EM&A during operational phase of the Project should be
carried out within the 12-month establishment period of the landscape and
visual mitigation measures by the corresponding implementation agency to ensure
the proposed mitigation measures in the EIA and as depicted in the Landscape
and Visual Mitigation Plan are fully implemented.
10.3.2
All mitigation measures proposed in the EIA and implemented by the
Contractor should be audited by Registered Landscape Architect (RLA), as a
member of the Environmental Team, on a regular basis to ensure compliance with the intended aims of
the measures. The mitigation measures proposed should be included in the
detailed engineering design and landscape design drawings and contract
document. Site inspection should be undertaken monthly throughout
the construction period. In particular, the extent of the agreed
works areas should be regularly checked during the construction
phase. The landscape auditor should audit the proposed mitigation
measures in the EIA to ensure that they are fully implemented during
construction and the 12-month establishment period during operational
phase.
11
IMPACT
ON cultural heritage
11.1
Introduction
11.1.1
Baseline study, comprising of desktop research and field evaluation were
conducted and the findings indicated the presence of built heritage and
archaeological resources within the 300 m assessment area for the Project. Both
direct (i.e. demolition of other identified items) and indirect impacts (i.e.
ground-borne vibration, settlement and tilting) were anticipated during the
construction phase of the Project. Archaeological potential areas were also
identified within the Project Site.
11.2
Mitigation Measures
11.2.1
The recommended mitigation measures as presented in Appendix C and summarised below should be implemented to mitigate the
impacts on built heritage and archaeological heritage resources.
Built Heritage
Construction Phase
Cartographic and Photographic Record
11.2.2 A
total of seven other identified items (i.e. DD104 Lot 4186 S.E (Residence)
(YTMT01); DD104 Lot 4187 S.B (Watchtower) (YTMT02); Remnants of Nam Shan
Monastery (YTMT03); Subsidiary Station of San Yau Vegetable Marketing
Co-operative Society, Ltd. (YTMT04); Lee¡¯s Boundary Stone (YTMT07); Mailbox No.
299 (NB04) and Grave of Mr. Man Chiu Pak and His Wife (NB09)) located within
the Project Site will be subject to direct impact due to demolition.
Cartographic and photographic record, and other documentation means (including
3D scanning), should be carried out for these buildings/structures prior to the
commencement of the construction works by the
contractor(s) at the respective locations for record purposes and future
use. For NB09, implementation details would be subject to discussion between
project proponent(s) and stakeholders. If the former Yau Tam Mei Primary School
(YTMT06) is confirmed to be demolished in later stage, preservation by record
should also be conducted for the school.
Monitoring of Ground-borne Vibration, Tilting and Ground
Settlement
11.2.3
Located within or adjacent to the Project Site,
eight other identified items, including Wai Cheung Ancestral Hall (HB1219), San
Yau Vegetable Marketing Co-operative Society, Ltd (YTMT05), DD104 Lot 2729
(Residence) (WTT01), Nos. 16-17, San Wai Tsuen (SW03), No. 25A, San Wai Tsuen
(SW04), Mailbox No. 35 (NB02), Mailbox No. 169 (NB03) and Chun Chi Education
Park (NB08), may experience indirect impacts of ground-borne vibration, tilting
and settlement. The future contractor(s) should implement standard control measures on
ground-borne vibration, tilting and settlement by drawing necessary references
from relevant government guidelines, including but not limited to the Code of
Practice for Foundations[1] and Practice Note for Authorised
Person, Registered Structural Engineers and Registered Geotechnical Engineers
APP-137 (PNAP APP-137)[2].
11.2.4
During the construction phase, monitoring of ground-borne
vibration, tilting and ground settlement should be implemented by the
contractor(s) on these other identified items when there are construction works
nearby. The monitoring should be incorporated with a set of Alert, Alarm
and Action (3As)
system. The proposed 3As criteria should be further confirmed via
pre-construction condition survey and an assessment on the effects of
ground-borne vibrations, settlements and tilting on the concerned buildings.
11.2.5
Considering that HB1219 is proposed to be
preserved in situ within the Project Site, standard measures of
pre-construction condition survey, as suggested in PNAP APP-137, should be
conducted on HB1219 for better understanding on its structural condition.
The survey should be undertaken by registered structural engineers or heritage
specialists. The methodology for the condition survey should be proposed
by the registered structural engineer(s) or heritage specialist(s). The
results of the pre-construction condition survey should form a baseline and
taken into consideration when formulating the abovementioned monitoring
proposal (Sections 11.2.3 to 11.2.4 refer) and buffer zone (Section 11.2.6
refers). A post-construction condition survey should also be carried out
to confirm its structural stability. If preservation of YTMT06 in situ is
confirmed in subsequent stages, the abovementioned standard control measures
(i.e. condition survey, ground-borne vibration, tilting and ground settlement)
should also be conducted for the school.
Buffer Zone
11.2.6
A buffer zone should be reserved for HB1219 by the project proponent or its contractor(s) according to the results of the
pre-construction condition survey in the design layout of the Project for
mitigating potential adverse vibration impact arising from construction
works. No piling works should be allowed within the buffer zone during
the construction phase. The said
buffer zone could be contained within the proposed Open Space O.3. If
preservation of YTMT06 in situ is confirmed in subsequent stages, same measures
should also be conducted for the school.
Physical Barriers
11.2.7
The contractor(s) should enforce protocol to forbid any light machinery,
such as handheld jackhammer, or heavy machinery to come into direct contact
with HB1219. Protective covering or sheltering should be provided for
HB1219 during construction activities in proximity to avoid potential damages
through direct contact with construction machineries. Physical protective
barriers/covers, intervention/cushioning materials, or structural strengthening
with minimal impact to the building fabric might need to be set up to protect
the building if necessary. If preservation of YTMT06 in situ is
confirmed in subsequent stages, physical barriers should be also deployed for
the school during construction phase.
Dust Suppression
11.2.8 As
HB1219, YTMT05 and YTMT06 (if preserved in situ) are located within or in close
proximity of the Project Site, dust nuisance from
the construction works nearby might have potential impact to the buildings and
their users. Therefore, Air Pollution Control (Construction Dust)
Regulation shall be followed. Dust suppression measures and good site
practice should be adopted by the contractor(s) during the construction phase
in order to avoid dust accumulation on these buildings.
Temporary Change of Access
11.2.9 There
would be a temporary change of access to HB1219, YTMT05 and YTMT06 (if preserved in situ) during the
construction phase. A safe access route to the concerned buildings should
be maintained by
the contractor(s) for conducting any mitigation measures.
Awareness to Other Identified Items in Close Proximity
11.2.10 A total of eight other
identified items are located in proximity to the Project Site, namely YTMT05,
WTT01, SW03, SW04, NB02, NB03, NB05 and NB08. To ensure no direct
disturbance would be caused to the physical fabrics of these items, project
proponent(s), subsequent developer(s) and contractor(s) should be aware of
these items when construction works are carrying out nearby. Management
measures should be deployed by the
contractor(s), such as briefing to site staff before commencement of
construction works and posting notices at site office(s).
Operational Phase
Revitalisation
11.2.11 HB1219 is proposed to be preserved in situ within the
land use of Open Space (O.3). Any revitalisation proposed for the
building in later stages should be further reviewed by the future project
proponent(s) or subsequent developer(s).
11.2.12
YTMT06 is located within the land use of Government, Institution or
Community (G.11). If the preservation of YTMT06 in situ is confirmed in
subsequent stages, opportunity for potential revitalisation
of the school should be explored by future project proponent(s) or subsequent
developer(s).
Archaeology
11.2.13 Based on the desktop
review and the findings of previous archaeological surveys, there are high
archaeological potential areas located within the Project Site, namely Ngau Tam
Mei Site of Archaeological Interest (SAI), Ngau Tam Mei Archaeologically
Sensitive Area (ASA) and Ngau Tam Mei (North) ASA. Direct impact on
archaeological heritage is anticipated during the construction phase.
11.2.14
Archaeological excavation is necessary to be conducted at the Ngau Tam
Mei SAI within the Project Site in order to obtain adequate archaeological
information of the area, and retrieve the archaeological data, if any, before
commencement of works involving soil disturbance at the respective area,
subject to future land resumption status and discussion with Antiquities and
Monuments Office (AMO) in later stages.
11.2.15
A comprehensive review has been conducted in the EIA Report based on all
available information at this stage, in order to safeguard any archaeological
resources that might have existed within the Project Site. Considering the potential direct impact to both Ngau Tam Mei ASA and Ngau Tam Mei (North) ASA
where have high archaeological potential, archaeological survey-cum-excavation
is recommended to be conducted at these areas. The aim is to obtain
adequate archaeological information of these areas for verifying their
archaeological potential, and retrieve the archaeological data, if any, before
commencement of works involving soil disturbance at the respective areas.
It should be subject to future land resumption status and discussion with AMO
in later stages.
11.2.16
Considering the potential direct impact to both the low-lying
agricultural fields and hilly landscape within the Project Site where possess
moderate-low archaeological potential, archaeological survey should be
conducted to obtain adequate archaeological information of these areas for
verifying their archaeological potential, and retrieve the archaeological data,
if any, before commencement of works involving soil disturbance at the
respective areas. It should be subject to future land resumption status
and discussion with AMO in later stages.
11.2.17
The low archaeological potential areas identified in the archaeological
assessments of the EIA studies for NOL Main Line and San Tin / Lok Ma Chau
Development Node (STLMC DN) within the Project Site is considered as having
acceptable impact, while there would be no impact on archaeological heritage by
the Project for the areas that have been disturbed heavily due to modern
development and have no archaeological potential. As a precautionary
measure and pursuant to the Antiquities and Monuments Ordinance (Cap. 53), the
project proponent is required to inform the AMO immediately in case of
discovery of antiquities or supposed antiquities in the course of works, so
that appropriate mitigation measures, if needed, can be timely formulated and
implemented in agreement with and to the satisfaction of AMO.
12
HAZARD TO LIFE
12.1
Introduction
12.1.1
Since there are no existing and planned hazardous facilities within and
in the vicinity of the Development Area, no hazard to life impact is
anticipated. Mitigation
measures and EM&A are considered not necessary.
13
lANDFILL GAS HAZARD
13.1
Introduction
13.1.1
A small portion of the Project Site lies within the consultation zone of
the closed and restored Ngau Tam Mei Landfill as shown in Figure 13.1.
13.1.2
Qualitative landfill gas (LFG) hazard assessment in Section 14 of the
EIA Report indicates that potential hazard associated with LFG presents ¡°Very
Low¡± risk during both construction and operational phases of the Project, and
thus no mitigation measures are therefore required. However, appropriate
precautionary and protective measures as suggested in Section 14 of the EIA
Report should be considered. EM&A is considered not necessary.
14
IMPACT
FROM ELECTRIC AND MAGNETIC FIELD
14.1
Introduction
14.1.1
Section 15 of the EIA Report indicates that, based on previous EIA
studies, the electric and magnetic field generated by the existing 400 kV
overhead cables located within/in the vicinity of the Development Area are well
below the stipulated guidelines issued by International Commission on
Non-ionizing Radiation Protection (ICNIRP) in Year 1998. Therefore, no
adverse impacts would be anticipated, and no specific electric and magnetic
field monitoring programme is required.
15
Environmental
auditing
15.1
Site Inspection
15.1.1
Site inspection is one of the most effective and direct tools to trigger
and enforce specified environmental protection and pollution control
measures. Site inspection should be undertaken regularly during the
construction phase to ensure that appropriate environmental protection and
pollution control mitigation measures are properly implemented for the
activities associated with the Project.
15.1.2
The ET should be responsible for formulating the environmental site
inspection programme as well as the deficiency and
remedial action reporting system, and for carrying out the site
inspections. He should submit a proposal for site inspection and
deficiency and remedial action reporting procedures to the Contractor for
agreement, and to the Engineer¡¯s Representative (ER) for approval. The proposal
for rectification, if any, should be prepared and submitted to the ETL and IEC
by the Contractor.
15.1.3
Regular site inspections should be carried out and led by the ER and
attended by the Contractor and ET at least once per week during the
construction phase, while the IEC should undertake regular site audit at least
once per month to audit and verify the overall environmental performance of the
works and to assess the effectiveness of the ET and Contractor in their
duties. The areas of inspection should not be limited to the
environmental conditions and the pollution control and mitigation measures
within the Project Site, it should also review the environmental conditions of
locations that are beyond the boundary of the Project Site that are likely to
be affected directly or indirectly by the construction activities of the
Project. The following information should be referred during the
inspection:
¡¤
The EIA Report and
EM&A recommendations on environmental protection and pollution control
mitigation measures;
¡¤
Ongoing results of the
EM&A programme;
¡¤
Works progress and
programme;
¡¤
Individual works
methodology proposals (which should include the proposal on associated
pollution control measures);
¡¤
Contract specifications
on environmental protection and pollution prevention control;
¡¤
Relevant environmental
protection and pollution control legislations; and
¡¤
Previous site
inspection results undertaken by the ET and others.
15.1.4
The Contractor should keep the ER and ET updated with all relevant
environmental related information on the construction contract necessary for
him/her to carry out the site inspections. Site inspection results and
associated recommendations for improvements to the environmental protection and
pollution control efforts should be submitted to the IEC and the Contractor
within 24 hours for reference and for taking immediate remedial action.
The Contractor should follow the procedures and time-frame stipulated in the
environmental site inspection, and the deficiency and remedial action reporting
system formulated by the ET, to report on any remedial measures subsequent to
the site inspections.
15.1.5
The ER, IEC, ET and the Contractor should also carry out ad hoc site
inspections if significant environmental problems are identified. Inspections
may also be required subsequent to receipt of an environmental complaint, or as
part of the investigation work, as specified in the Event and Action Plan for
the EM&A programme.
15.2
Compliance with Legal and Contractual Requirements
15.2.1
To ensure that the works are in compliance with the statutory
requirement, all method statements of works should be submitted by the
Contractor to the ER for approval and to the ET for vetting to ensure
sufficient environmental protection and pollution control measures have been
included. The implementation schedule of the proposed mitigation measures is summarised in Appendix
C. Any proposed changes to the mitigation measures shown in Appendix C should be
certified by the ET and verified by the IEC as conforming to the relevant
information and recommendations contained in the EIA Report.
15.2.2
The ER and ET should also review the progress and programme
of the works to check that relevant environmental legislations have not been
violated, and that any foreseeable potential for violating laws can be
prevented.
15.2.3
The Contractor should provide the update of the relevant documents to
the ET so that works checking could be carried out effectively. The document
should at least include the updated Works Progress Reports, updated Works Programme, method statements, any application letters for licences / permits under the environmental protection
legislations, and copies of all valid licences /
permits. The site diary should also be available for the inspection by
the relevant parties.
15.2.4
After reviewing the documentation, the ET should advise the Contractor
of any non-compliance with contractual and legislative requirements on
environmental protection and pollution control so that they can timely take
follow-up actions as appropriate. If the follow-up actions may still
result in violation of environmental protection and pollution control
requirements, the ER and ET should provide further advice to the Contractor to
take remedial action to resolve the problem.
15.2.5
Upon receipt of the advice, the Contractor should undertake immediate action
to remedy the situation. The ER and ET should follow up to ensure that
appropriate action has been taken in order to satisfy contractual and legal
requirements.
15.3
Choice of Construction Method
15.3.1
At times during the construction phase, the Contractor may propose
alternative construction method(s) that had not been assessed in the EIA
Report. The Contractor should submit a proposal which provides the
details of the proposed alternative construction method and the associate
construction equipment to the ER, ETL and IEC for approval before commencement
of the proposed works. The Contractor¡¯s options for alternative construction
method(s) may introduce adverse environmental impacts into the Project, and
therefore the Contractor and ET should review and determine, in accordance with
established environmental standards and guidelines, as well as the
recommendations and requirements in the EIA Report, the adequacy of the
environmental protection and pollution control measures in the Contractor¡¯s
proposal in order to ensure no unacceptable impacts would result. To achieve this
end, the ET should provide a copy of the Proactive Environmental Protection
Proforma as shown in Appendix
E to
the IEC for verification before commencement of the proposed works. The IEC
should verify the review of the alternative construction method(s) and endorse
the proposal(s) on the basis of no adverse environmental impacts.
15.3.2
In case the Contractor needs to update
the mitigation measures and/or the project implementation schedule as a result of
alternative construction method(s) or other condition (e.g. site
constraint(s)), the ET should also review the latest recommendation of
mitigation measures and/or project implementation schedule by submission of a
Proactive Environmental Protection Proforma as shown in Appendix E. The IEC should verify the Proforma and
conduct audit to confirm proper implementation of the alternative
measures.
15.4
Environmental Complaints
15.4.1
The following procedures should be undertaken upon receipt of any
environmental complaint (Appendix
F refers):
¡¤
The Contractor to log
complaint and date of receipt onto the complaint database and inform the ER, ET
and IEC immediately;
¡¤
The Contractor to
investigate, with the ER and ET, the complaint to determine its validity, and
assess whether the source of the problem is due to construction works of the
Project with the support of additional monitoring frequency and stations, if
necessary;
¡¤
The Contractor to
identify remedial measures in consultation with the IEC, ET and ER if a
complaint is valid and due to the construction works of the Project;
¡¤
The Contractor to
implement the remedial measures as required by the ER and to agree with the ET
and IEC any additional monitoring frequency and stations, where necessary, for
checking the effectiveness of the remedial measures;
¡¤
The ER, ET and IEC to
review the effectiveness of the Contractor's remedial measures and the updated
situation;
¡¤
The ET/Contractor to
undertake additional monitoring if necessary and audit to verify the situation,
and oversee that circumstances leading to the complaint do not recur;
¡¤
If the complaint is
referred by the EPD, the Contractor to prepare interim report on the status of
the complaint investigation and follow-up action stipulated above, including
the details of the remedial measures and additional monitoring identified or already
taken, for submission to EPD within the time frame assigned by the EPD; and
¡¤
The ET to record the
details of the complaint, results of the investigation, subsequent
actions taken to address the complaint and updated situation including the
effectiveness of the remedial measures, supported by regular and additional
monitoring results in the monthly EM&A reports.
16
Reporting
16.1
General
16.1.1
Reports can be provided in an electronic medium upon agreeing the format
with the ER and EPD. This would enable a transition from a paper /
historic and reactive approach to an electronic / real time proactive
approach. All the monitoring data (baseline and impact) should also be
submitted in electronic format. The formats for noise and water quality
monitoring data to be submitted are shown in Appendix E.
16.1.2
Types of reports that the ET Leader should submit include baseline
monitoring report, monthly EM&A report, quarterly EM&A summary report
and final EM&A report. In accordance with Annex 21 of the EIAO-TM, a
copy of the monthly, quarterly summary and final EM&A reports should be
made available to the DEP.
16.2
Electronic Reporting of EM&A Information
16.2.1
To facilitate public inspection of the baseline monitoring report and
various EM&A reports via the EIAO Internet website and at the EIAO register
office, electronic copies of these reports should be prepared in Hyper Text
Markup Language (HTML) (version 4.0 or later) and in Portable Document Format
(PDF Adobe 11 Pro version or later), unless otherwise agreed by EPD and should
be submitted at the same time as the hardcopies. For the HTML version, a
content page capable of providing hyperlink to each section and sub-section of
these reports should be included at the beginning of the document.
Hyperlinks to all figures, drawings and tables in these reports should be
provided in the main text from where the respective references are made.
All graphics in these reports should be in interlaced GIF format unless
otherwise agreed by EPD. The content of the electronic copies of these
reports must be the same as the hard copies. The summary of the
monitoring data taken should be included in the various EM&A Reports to
allow for public inspection via the EIAO Internet website.
16.3
Baseline Monitoring Report
16.3.1
Baseline Environmental Monitoring Report(s) should be prepared within 10
working days of completion of the baseline monitoring and then certified by the
ET Leader. Copies of the Baseline Environmental Monitoring Report should
be submitted to the Contractor, the IEC, the ER and EPD. The ET Leader
should liaise with the relevant parties on the exact number of copies they
require. The report format and baseline monitoring data format should be
agreed with EPD prior to submission.
16.3.2
The baseline monitoring report should include, but not be limited to the
following:
i.
up to half a page
executive summary;
ii.
brief project
background information;
iii.
drawings showing
locations of the baseline monitoring stations;
iv.
an updated construction
programme with milestones of environmental protection / mitigation activities
annotated;
v.
monitoring results (in
both hard and soft copies) together with the following information:
-
monitoring methodology;
-
name of laboratory and
types of equipment used and calibration details;
-
parameters monitored;
-
monitoring locations
(and depth);
-
monitoring date, time,
frequency and duration; and
-
QA/QC results and detection
limits.
vi.
details on influencing
factors, including:
-
major activities, if
any, being carried out on the site during the period;
-
weather conditions
during the period; and
-
other factors which
might affect results.
vii.
determination of the
A/L Levels for each monitoring parameter and statistical analysis of the
baseline data, the analysis should conclude if there is any significant
difference between control and impact stations for the parameters monitored;
viii. revisions for inclusion in the
EM&A Manual; and
ix.
comments,
recommendations and conclusions.
16.4
Monthly EM&A Reports
16.4.1
The results and findings of all EM&A
work required in the Manual should be
recorded in the monthly EM&A reports certified by the ET Leader. The
EM&A report should be prepared and
submitted within 10 working days at the end of each reporting month, with the
first report due the month after construction commences. Each monthly
EM&A report should be submitted to
the following parties: the Contractor, the IEC, the ER and EPD. Before
submission of the first EM&A report, the ET Leader should liaise with the parties on the required number of
copies and format of the monthly reports in both hard copy and electronic
medium.
16.4.2
The ET leader should review the number and location of monitoring stations
and parameters every six months, or on as needed basis, in order to cater for
any changes in the surrounding environment and the nature of works in progress.
First Monthly EM&A Report
16.4.3
The first monthly EM&A report should include at least but not be limited to the following:
i.
executive summary (1-2
pages):
-
breaches of A/L levels;
-
complaint log;
-
notifications of any
summons and successful prosecutions;
-
reporting changes; and
-
future key issues.
ii.
basic project
information:
-
project organisation including
key personnel contact names and telephone numbers;
-
construction programme
with fine tuning of construction activities showing the inter-relationship with
environmental protection/mitigation measures for the month;
-
management structure,
and
-
works undertaken during
the month.
iii.
environmental status:
-
works undertaken during
the month with illustrations (such as location of works, percentage of fines in
the fill materials used, etc); and
-
drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations (with co-ordinates of the monitoring
locations).
iv.
a brief summary of
EM&A requirements including:
-
all monitoring
parameters;
-
environmental quality
performance limits (A/L levels);
-
Event-Action Plans;
-
environmental
mitigation measures, as recommended in the EIA Report; and
-
environmental
requirements in contract documents.
v.
implementation status:
-
advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the EIA Report, summarised in the
updated implementation schedule.
vi.
monitoring results (in
both hard and diskette copies) together with the following information:
-
monitoring methodology;
-
name of laboratory and
types of equipment used and calibration details;
-
parameters monitored;
-
monitoring locations
(and depth);
-
monitoring date, time,
frequency, and duration;
-
weather conditions
during the period;
-
graphical plots of the
monitored parameters in the month annotated against:
o the major activities being carried out on site during the period;
o weather conditions that may affect the results; and
o any other factors which might affect the monitoring results;
-
any other factors which
might affect the monitoring results; and
-
QA/QC results and
detection limits.
vii.
report on
non-compliance, complaints, notifications of summons and successful
prosecutions:
-
record of all
non-compliance (exceedances) of the environmental quality performance limits
(A/L levels);
-
record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary;
-
record of all
notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislations, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
-
review of the reasons
for and the implications of non-compliance, complaints, summons and
prosecutions including review of pollution sources and working procedures; and
-
description of the
actions taken in the event of non-compliance and deficiency reporting and any
follow-up procedures related to earlier non-compliance.
viii. others:
-
an account of the
future key issues as reviewed from the works programme and work method
statements;
-
advice on the solid and
liquid waste management status;
-
a forecast of the works
programme, impact predictions and monitoring schedule for the next three
months;
-
compare and contrast
the EM&A data with the EIA predictions and annotate with explanation for
any discrepancies; and
-
comments (for examples,
effectiveness and efficiency of the mitigation measures), recommendations (for
example, any improvement in the EM&A programme) and conclusions.
Subsequent monthly EM&A
Reports
16.4.4
Subsequent monthly EM&A reports should include the following:
i.
executive summary (1 -
2 pages):
-
breaches of A/L levels;
-
complaints log;
-
notifications of any
summons and successful prosecutions;
-
reporting changes; and
-
future key issues.
ii.
environmental status:
-
construction programme
with fine tuning of construction activities showing the inter-relationship with
environmental protection / mitigation measures for the month;
-
works undertaken during
the month with illustrations including key personnel contact names and
telephone numbers; and
-
drawing showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations.
iii.
implementation status:
-
advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the EIA Report, summarised in the
updated implementation schedule.
iv.
monitoring results (in
both hard and diskette copies) together with the following information:
-
monitoring methodology;
-
name of laboratory and
types of equipment used and calibration details;
-
parameters monitored;
-
monitoring locations
(and depth);
-
monitoring date, time,
frequency, and duration;
-
weather conditions
during the period;
-
graphical plots of the
monitored parameters in the month annotated against;
o the major activities being carried out on site during the period;
o weather conditions that may affect the results; and
o any other factors which might affect the monitoring results.
-
any other factors which
might affect the monitoring results; and
-
QA/QC results and
detection limits.
v.
report on
non-compliance, complaints, and notifications of summons and successful
prosecutions:
-
record of all
non-compliance (exceedances) of the environmental quality performance limits
(A/L levels);
-
record of all
complaints received (written or verbal) for each media, including locations and
nature of complaints investigation, liaison and consultation undertaken,
actions and follow-up procedures taken, results and summary;
-
record of all
notification of summons and successful prosecutions for breaches of current
environmental protection / pollution control legislations, including locations
and nature of the breaches, investigation, follow-up actions taken, results and
summary;
-
review of the reasons
for and the implications of non-compliance, complaints, summons and
prosecutions including review of pollution sources and working procedures; and
-
description of the
actions taken in the event of non-compliance and deficiency reporting and any
follow-up procedures related to earlier non-compliance.
vi.
others:
-
an account of the
future key issues as reviewed from the works programme and work method
statements;
-
advice on the solid and
liquid waste management status;
-
a forecast of the works
programme, impact predictions and monitoring schedule for the next three
months;
-
compare and contrast
the EM&A data with the EIA predictions and annotate with explanation for
any discrepancies; and
-
comments (for examples,
effectiveness and efficiency of the mitigation measures), recommendations (for
example, any improvement in the EM&A programme) and conclusions.
vii.
appendix
-
A/L levels;
-
graphical plots of
trends of monitored parameters at key stations over the past four reporting
periods for representative monitoring stations annotated against the following:
o major activities being carried out on site during the period;
o weather conditions during the period; and
o any other factors that might affect the monitoring results.
-
monitoring schedule for
the present and next reporting period;
-
cumulative statistics
on complaints, notifications of summons and successful prosecutions;
-
outstanding issues and
deficiencies
16.5
Quarterly EM&A Summary Reports
16.5.1
A quarterly EM&A summary report of around five pages should be
produced by the ET Leader and should contain at least the following
information. Apart from these, the first quarterly summary report should
also confirm that the monitoring work is proving effective and that it is
generating data with the necessary statistical power to categorically identify
or confirm the absence of impact attributable to the works. Each
quarterly EM&A report should be submitted to the following parties: the IEC,
the ER and EPD.
i.
executive summary (1 -
2 pages);
ii.
basic project
information including a synopsis of the project organisation, programme,
contacts of key management, and a synopsis of works undertaken during the
quarter;
iii.
a brief summary of
EM&A requirements including:
-
monitoring parameters;
-
environmental quality
performance limits (A/L levels); and
-
environmental
mitigation measures, as recommended in the EIA Report.
iv.
advice on the
implementation status of environmental protection and pollution control /
mitigation measures, as recommended in the EIA Report, summarised in the
updated implementation schedule;
v.
drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations;
vi.
graphical plots of the
trends of monitored parameters over the past four months (the last month of the
previous quarter and the present quarter) for representative monitoring
stations annotated against:
-
the major activities being
carried out on site during the period;
-
weather conditions
during the period; and
-
any other factors which
might affect the monitoring results.
vii.
advice on the solid and
liquid waste management status;
viii. a summary of non-compliance
(exceedances) of the environmental quality performance limits (A/L levels);
ix.
a brief review of the
reasons for and the implications of non-compliance, including a review of
pollution sources and working procedures;
x.
a summary description
of the actions taken in the event of non-compliance and any follow-up
procedures related to earlier non-compliance;
xi.
a summarised record of
all complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
xii.
a summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection / pollution control legislations, locations
and nature of the breaches, investigation, follow-up actions taken and results;
xiii. comments (for examples, a review of
the effectiveness and efficiency of the mitigation measures and the performance
of the environmental management system, that is, of the overall EM&A
programme); recommendations (for example, any improvement in the EM&A
programme) and conclusions for the quarter; and
xiv. proponents' contacts and any hotline
telephone number for the public to make enquiries.
16.6
Final EM&A Review Reports for Construction Phase
16.6.1
The EM&A program for construction
phase should be terminated upon
completion of those construction activities that have the potential to result
in a significant environmental impact.
16.6.2
The proposed termination should only be
implemented after the proposal has been endorsed by the IEC, the Engineer and
the Project Proponent followed by final approval from the DEP.
16.6.3
The final EM&A report should be
prepared by the ET Leader and contain at least the following information.
The Final EM&A Review report should
be submitted to the following parties: the IEC, the ER and EPD.
i.
executive summary (1 -
2 pages);
ii.
basic project
information including a synopsis of the project organisation, contacts of key
management, and a synopsis of work undertaken during the course of the project
or past twelve months;
iii.
a brief summary of
EM&A requirements including:
-
monitoring parameters;
-
environmental quality
performance limits (A/L levels); and
-
environmental
mitigation measures, as recommended in the EIA Report.
iv.
advice on the implementation
status of environmental protection and pollution control / mitigation measures,
as recommended in the EIA Report, summarised in the updated implementation
status proformas;
v.
drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and control stations;
vi.
graphical plots of the
trends of monitored parameters over the course of the project, including the
post-project monitoring for all monitoring stations annotated against:
-
the major activities
being carried out on site during the period;
-
weather conditions
during the period;
-
any other factors which
might affect the monitoring results; and
-
the return of ambient environmental
conditions in comparison with baseline data.
vii.
compare and contrast
the EM&A data with the EIA predictions and annotate with explanation for
any discrepancies;
viii.
provide clear-cut
decisions on the environmental acceptability of the project with reference to
the specific impact hypothesis;
ix.
advice on the solid and
liquid waste management status;
x.
a summary of
non-compliance (exceedances) of the environmental quality performance limits
(A/L levels);
xi.
a brief review of the
reasons for and the implications of non-compliance including review of
pollution sources and working procedures;
xii.
a summary description
of the actions taken in the event of non-compliance and any follow-up
procedures related to earlier non-compliance;
xiii.
a summary record of all
complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up procedures taken;
xiv.
review monitoring
methodology adopted and with the benefit of hindsight, comment on its
effectiveness (including cost effectiveness);
xv.
a summary record of
notifications of summons and successful prosecutions for breaches of the
current environmental protection/pollution control legislations, locations and
nature of breaches, investigation, follow-up actions taken and results;
xvi.
review the practicality
and effectiveness of the EIA process and EM&A programme (for examples, a
review of the effectiveness and efficiency of the mitigation measures and the
performance of the environmental management system, that is, of the overall
EM&A programme), recommendations (for example, any improvement in the
EM&A programme); and
xvii.
a conclusion to state
the return of ambient and / or the predicted scenario as per EIA findings.
16.7
Final EM&A Report for Operational Phase
16.7.1
A final EM&A review report for operational phase should be submitted
after completion of operation monitoring. The final EM&A review report for
operation phase should contain at least the following information:
i.
executive summary (1 -
2 pages);
ii.
drawings showing the
project area, any environmental sensitive receivers and the locations of the
monitoring and/or control stations;
iii.
basic project
information including a synopsis of the project organisation, contacts of key
management, and a synopsis of work undertaken during the course of the project
or past twelve months;
iv.
a brief summary of
EM&A requirements including:
-
Environmental
mitigation measures for operation stage, as recommended in the project EIA
Report;
-
environmental impact
hypotheses tested;
-
environmental quality
performance limits (Action and Limit levels);
-
all monitoring
parameters;
-
Event and Action Plans;
v.
a summary of the
implementation status of environmental protection and pollution control / mitigation
measures for operation stage, as recommended in the project EIA Report and
summarised in the updated implementation schedule;
vi.
graphical plots and the
statistical analysis of the trends of monitoring parameters over the course of
the project, including:
-
the major activities
being carried out on site during the period;
-
weather conditions
during the period; and
-
any other factors which
might affect the monitoring results;
vii.
a summary of
non-compliance (exceedances) of the environmental quality performance limits
(Action and Limit levels);
viii.
a review of the reasons
for and the implications of non-compliance including review of pollution
sources and working procedures as appropriate;
ix.
a description of the
actions taken in the event of non-compliance;
x.
a summary record of all
complaints received (written or verbal) for each media, liaison and
consultation undertaken, actions and follow-up actions taken and results;
xi.
a review of the
validity of EIA predictions for operation stage and identification of
shortcomings in EIA recommendations;
xii.
comments (for example,
a review of the effectiveness and efficiency of the mitigation measures, the
performance of the environmental management system, and the overall EM&A
programme for operation stage); and
xiii.
recommendations and
conclusions (for example, a review of success of the overall EM&A programme
for operational stage to cost-effectively identify deterioration and to
initiate prompt effective mitigatory action when necessary).
16.8
Data Keeping
16.8.1
No site-based documents (such as monitoring field records, laboratory
analysis records, site inspection forms, etc.) are required to be included in
the monthly EM&A reports. However, any such document should be well
kept by the ET Leader and be ready for inspection upon request. All
relevant information should be clearly and systematically recorded in the
document. Monitoring data should also be recorded in electronic format,
and the software copy must be available upon request. Data format should
be agreed with the EPD. All documents and data should be kept for at
least one year following completion of the construction contract.
16.9
Interim Notifications of Environmental Quality
Limit Exceedances
16.9.1
With reference to the Event and Action Plan, when the environmental
quality performance limits are exceeded, the ET Leader should immediately
notify the IEC and EPD, as appropriate. The notification should be
followed up with advice to IEC and EPD on the results of the investigation,
proposed actions and success of the actions taken, with any necessary follow-up
proposals. A sample template for the interim notifications is presented
in Appendix G.