
TABLE OF CONTENTS
1.3
Purpose of this Executive Summary
2.1
Appreciation of Existing Environment
2.3
Development Opportunities and Constraints
2.4
Description of the Project
2.5
Designated Projects under EIAO
2.6
Project Benefits and Environmental Initiatives
2.7
Development Programme for Project
3 Key findings of THE Environmental IMPACT ASSESSMENT
3.5
Sewerage and Sewage Treatment Implications
3.6
Waste Management Implications
3.8
Ecological Implication (Terrestrial and Aquatic)
3.10
Landscape and Visual Impact
3.11
Impact on Cultural Heritage
3.14
Impact from Electric and Magnetic Field
4 Environmental Monitoring and Audit
5 Summary of ENVIRONMENTAL outcomes
List of tables
Table
2.1 Land Use
Budget of the RODP
Table
2.3 Schedule 2
Designated Projects Under the Project
Table 2.4
Schedule 2
Designated Projects Not Under the Project
Table 2.5
Summary of
Non-Designated Projects Under the Project
Table
2.6 Preliminary
Construction and Population Intake Schedule
Table
5.1 Summary
of Key Environmental Issues Avoided/Minimised and Sensitive Areas Protected
Table
6.1 Summary of
Environmental Impacts
LIST OF FIGURES
|
Project Location Plan |
|
|
Recommended Outline Development Plan |
|
|
Locations of Designated Projects |
(i) the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
(ii) the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
(iii) the acceptability of residual impacts after the proposed mitigation measures are implemented.
Development Opportunities
High Accessibility
Enhanced Railway Network
Favourable Geographical Location
Plentiful Natural and Landscape Features
Resolving Land Use Interface
Development Constraints
Environmental Constraints
(i) Two existing chicken farms, a LBF and NTM AWCP are located to the southeast and southwest of the Project Site. Besides, a sewage treatment plant within TMB directly borders the northern boundary of the NTM NDA. The proposed developments under the Project need to comply with the relevant requirements to minimise potential odour impacts from these facilities/uses.
(ii) The firing range of TMB is considered as a potential fixed noise source to the proposed noise sensitive uses in the northern part of the Project.
(iii) The NTMDC connects the pond habitat upstream, with the Deep Bay wetland habitats to the west of the assessment area of the Project. It serves as a bird flight path for various waterbird species. This channel also plays a role in flood management for the surrounding low-lying area. For minimising the environmental impacts, the Project should manage run-off and water quality, maintain habitat connectivity, and minimize potential disturbances to bird flight paths. Currently, the operation of NTMDC is governed by Environmental Permit No. FEP-01/003/1998/A held by Drainage Services Department (DSD) covering drainage channel from Ngau Tam Mei to Kam Tin River near Tai San Wai.
(i) The existing major distributor roads including San Tin Highway, Ngau Tam Mei Road, Chuk Yau Road, San Tam Road, Castle Peak Road – Tam Mi will likely pose air quality and road traffic noise impacts to the proposed developments in the western part of the Project Site.
(ii) The existing High Speed Rail (formerly known as Express Rail Link) runs underneath and through the Project Site in southeast-northwest orientation. The future NOL Main Line also traverses the Project Site, and the associated NTM Depot (NTD) is anticipated to pose development constraints and potential noise impacts to the developments of the Project.
(iii) The existing overhead electricity transmission lines with pylons are located to the south and east of the Project which require sufficient vertical and horizontal separation distances from adjacent proposed land uses in accordance with the requirements stated in Hong Kong Planning Standards and Guidelines (HKPSG).
(iv) The development of the NOL Main Line, including the planned NTM Station and the associated NTD within the Project Site, is being undertaken by the MTRCL separately. The railway scheme, including land area, and layout of the NTM Station, NTD, and ancillary facilities, was gazetted on 6 October 2023 and authorised on 8 April 2025. The potential interfacing challenges may arise concerning land use integration, infrastructure alignment, and construction sequencing between the railway facilities and the NTM NDA, and thus there should be close coordination to minimise the potential interface issues.
Positioning and Planning Framework
Size, Scale, Shape and Design of the Project
Table 2.1 Land Use Budget of the RODP
|
Land Use |
Approximate Area (ha) |
|
Government, Institution and Community (GIC) Facilities (including the UniTown, Integrated Hospital and other GIC Facilities and Reserve) |
66 |
|
Residential (including railway topside commercial / residential development) |
19 |
|
Open Space |
13 |
|
Roads and Other Uses (including Railway and Amenity) |
29 |
|
Green Belt (including permitted burial grounds) |
3 |
|
Total: |
130 |
Table 2.2 Key Comments Related to Environment Received During Statutory Public Inspection Period and PE Period
|
Key Issue |
Public Comments |
Consideration Taken in RODP |
|
Air Quality |
The cumulative air quality impacts should be assessed, and effective mitigation measures should be formulated to control the air pollution. Polluting industrial/commercial activities should be forbidden in order not to worsen the air quality. |
No polluting industrial/commercial activities are proposed within the Project Site.
|
|
Odour arising from the LBF and air quality impact arising from other pollution sources should be addressed to protect the interests of the community. |
• Odour and air quality impact from pollution sources have been assessed. • Details of air quality (including odour) impact assessment are provided in Section 3 of the EIA Report. |
|
|
Water Quality |
Any untreated surface run-off generated from the Project Site during both construction and operational phases should be prevented from discharging into NTMDC or its tributaries, other natural or man-made channels, stormwater drainage and wetlands directly. |
Proper drainage and sewerage systems with due consideration of avoidance and minimization of the potential water quality impacts will be adopted. Details of water quality impact assessment are provided in Section 5 of the EIA Report.
|
|
Watercourses with natural substrates and good water quality should not be destroyed and should be well protected. |
It is anticipated that removal of a few watercourses is unavoidable for site formation works under the Project. Nevertheless, NTMDC will be revitalised to bring positive impacts to the nature in NDA. |
|
|
Waste Management |
Storage, transportation and disposal of solid wastes should be under stricter monitoring and control to avoid any fly-tipping of solid wastes generated from the Project. |
• Global Positioning System (GPS) or equivalent system for tracking and monitoring of all dump trucks will be engaged to record their travel routings and parking locations for avoiding illegal dumping and landfilling. • A Trip Ticket System will be implemented to avoid illegal dumping. |
|
Ecology |
Given the high ecological sensitiveness around the Project Site, year-long ecological surveys for diverse taxa groups and habitats should be conducted in the EIA study. Additional bird survey efforts should be invested during the migratory seasons to assess the ecological impacts on migratory birds. |
A 12-month baseline ecological survey (including bird survey) was conducted. Details of baseline ecological data and impact assessment are provided in Section 9 of the EIA Report.
|
|
Eurasian Otter (Lutra lutra) could utilise the existing NTMDC and fishponds nearby. Intensive active search for field signs of Otters and the approach of employing Local Ecological Knowledge by conducting questionnaire interviews with local people should be taken.
|
There are no official published data or records of the Otter in the Project Site, and no Eurasian Otter was recorded during the baseline ecological survey. Further additional interview targeting the sightings of the Otter among the local people in NTM area was conducted upon receipt of the public comment. Based on the interview findings, no sightings of the Otter in NTM area were reported or heard by interviewees. |
|
|
Alternative alignment of the proposed road connection to/from STT should be explored to minimise woodland loss.
|
The alignment of the proposed road connection to/from STT has been reviewed and optimised with respect to engineering feasibility and other considerations to minimise the loss of woodland habitat.
|
|
|
Removal of trees and vegetation in the Project Site should be avoided as far as possible in order to reduce ecological impact, loss of habitats and urban heat island effect. Any vegetation loss in the Project should be compensated through the cultivation of native plant species. |
• It is anticipated that some trees and vegetation removal are unavoidable for site formation works. Nevertheless, the land use formulation has maximised the opportunity for open space with greening in order to reduce ecological impact including the loss of habitats as well as landscape impact. • Tree compensation is proposed to be provided at a 1:1 tree compensatory ratio at the roadside amenity areas and open space to compensate for tree loss due to the Project as far as practicable. Areas within the Project Site and off-site areas for compensatory tree planting would be explored and negotiated with relevant project proponent(s) to achieve 1:1 ratio in compensatory tree planting number as far as practicable. |
|
|
Avoidance / minimization of both direct and indirect impacts on wetland within/adjacent to Wetland Buffer Area (WBA) should be explored in both construction and operational phases. |
The Project has been carefully planned such that the works would only be situated at the existing developed area / wasteland habitat within WBA to avoid direct impact to wetland within/adjacent to WBA, and the modified watercourse within WBA would be retained. |
|
|
Off-site negative impact, such as construction noise during construction phase and human activities during operational phase, would adversely affect foraging behavior ardeids at NTMDC. |
• Construction Noise Management Plan will be prepared during pre-tender and pre-construction stages to formulate the requirement of mitigation measures, monitoring and audit programme. • Mitigation measures, such as provision of non-building area and “Open Space” along both sides of NTMDC and peripheral tree planting as screening, have been adopted to minimise the indirect impacts to ardeids during operational phase. |
|
|
Impact on Agricultural Land and Fishponds |
Agricultural land in NTM is generally in low degree of fragmentation which should be protected. Rural life and associated farmland and fishponds should be preserved in NDA developments under the concept of urban-rural integration to minimise impacts on local fisheries and agricultural industries. |
Currently, the agricultural land in NTM is scattered and mostly consists of abandoned farmland, which is assessed to have low to moderate ecological value. To maximise the utilisation of land resources, these scattered plots of agricultural land are consolidated for developing into a functional community providing land for a UniTown, Integrated Hospital and residential neighbourhood to complement with the I&T development in STT. That said, opportunities of introducing urban farming in the planned open space are allowed under the RODP. |
|
Cultural Heritage |
Direct and indirect impacts on cultural heritage items should be identified.
|
Direct and indirect impacts on the identified cultural heritage items have been assessed in Section 12 of the EIA Report. |
|
Alternatives should be further explored to avoid/minimize direct loss on the cultural heritage items identified in both construction and operational phases. |
Alternatives have been explored to avoid direct loss on Wai Cheung Ancestral Hall such that it would be preserved in situ.
|
|
|
Existing buildings with collective memories and heritage characters should be reserved to enrich the continuity of heritage. |
Flexibility for potential adaptive reuse of the building structures of the former Yau Tam Mei Primary School by future project proponents of UniTown is allowed in the RODP. |
|
|
Contingency measures should be prepared in case items of historical or archaeological importance can be spotted within the development area during construction phase. |
In accordance with the Antiquities and Monuments Ordinance (A&MO) (Cap. 53), Antiquities and Monuments Office (AMO) will be informed immediately in case of discovery of antiquities or supposed antiquities in the course of works. |
|
|
Landscape and Visual |
Yau Tam Mei Tsuen or nearby parks might contain "trees of particular interest (TPI)" which should be identified and protected in conservation plans.
|
• The findings of broad-brush tree and vegetation survey, including all TPI(s) that would be directly impacted by the Project, and the associated mitigation measures, are provided in Section 11 of the EIA Report. • Sensitivity analysis would be conducted in the detailed design and construction stages to further review and justify the need for any TPI(s) removal. |
|
Electric and Magnetic Field |
Due consideration should be given when planning developments at areas near the existing 400 kV overhead cables to the south of the Development Area to reduce potential impact of the electromagnetic field. |
It is expected that the electric and electromagnetic field generated by the existing 400 kV overhead cables should be well below the relevant exposure standards and limits, and therefore adverse impact on the proposed developments of the Project is not anticipated. |
|
Concern associated with the Proposed Revitalisation |
A buffer zone should be provided at each side of the revitalised NTMDC to provide sufficient riparian habitats and to accommodate a wide range of water flow. |
Open Space and non-building area (a combined width of 80 m) will be provided along the revitalised NTMDC (total length of about 2.2 km), serving as a buffer zone.
|
|
Additional water source might be required for the revitalised NTMDC during dry season. |
Provision for additional water source in dry season would be reviewed in detailed design stage. |
|
|
Cumulative Environment-al Impact |
Given other major developments, such as the STT, NOL Main Line and NM Highway – San Tin Section, interconnected with the Project, all the potential environmental impacts of the adjacent developments should be addressed so that the cumulative environmental impacts will not be underestimated. |
With the best available information, the cumulative impacts arising from the construction and operational phases of the identified interfacing projects have been assessed in the EIA Report. |
Table 2.3
Schedule 2 Designated Projects Under the Project
|
Ref. No. |
Schedule 2 Designated
Project |
Work Component / Reference in RODP |
|
|
DP1 |
Item A.1 |
A carriageway for motor vehicles that is an
expressway, trunk road, primary distributor road or district distributor road |
Construction and operation of district
distributor road (Road D1) and associated road works at San Tin Highway |
|
DP2 |
Item I.1(b) |
A drainage channel or river training and
diversion works located less than 300 m from the nearest boundary of an
existing or planned conservation area |
Part of Revitalisation of Ngau Tam Mei
Drainage Channel and river diversion works located less than 300 m from the
nearest boundary of an existing conservation area |
Table 2.4 Schedule 2 Designated Projects Not Under the Project
|
Schedule 2 Designated Projects in the Project Profile and Study Brief |
Relevant Work Component |
|
|
Item F.1 |
Sewage treatment works with an installed capacity of more than 15,000 m3 per day |
Only SPS and sewerage provided |
|
Item F.2 |
Sewage treatment works with an installed capacity of more than 5,000 m3 per day; and a boundary of which is less than 200 m from the nearest boundary of an existing or planned (i) residential area; (ii) place of worship; (iii) educational institution; (iv) health care institution; (v) site of special scientific interest; (vi) site of cultural heritage; (vii) bathing beach; (viii) marine park or marine reserve; (ix) fish culture zone; or (x) seawater intake point |
|
|
Item H.1 |
A 400 kV electricity substation and transmission line |
Only two 132 kV electricity substations proposed |
Table 2.5 Summary of Non-Designated Projects Under the Project
|
Non-Designated Project |
Sub-Element |
|
Education |
University Town (Post-secondary Education Use) |
|
Primary School |
|
|
Secondary School |
|
|
GIC Facilities |
Integrated Hospital |
|
Ambulance Depot |
|
|
Community Recycling Centre |
|
|
Electricity Substations (ESS) |
|
|
Fire Station and Departmental Staff Quarters |
|
|
Indoor Sports Centre |
|
|
Library |
|
|
Refuse Collection Points (RCPs) |
|
|
Sewage Pumping Station |
|
|
Staff Quarters |
|
|
Residential Development |
Private Housing |
|
Dedicated Rehousing Estate |
|
|
Open Space |
Recreational Facilities and Landscaping |
|
Amenity |
Roadside Amenity |
|
Green Belt |
- |
|
Other Specified Uses |
Other Specified Uses (Railway Depot with Commercial/Residential Development) |
|
Other Specified Uses (Railway Depot with Public Open Space) |
|
|
Road |
Local Roads |
Direct Benefits
(i) Northern Metropolis Synergy – With the vision to develop NM into a “New International I&T City”, NMAA outlines the strategic positioning and development themes of the four major zones in NM. Amongst them, the I&T Zone covers STT and NTM. STT will be the hub for clustered I&T development and the core of industry development of the entire NM. It is also proposed that land be reserved in NTM for use of post-secondary education institutions, with a focus on scientific research, to complement the I&T development in STT, promoting “research, academic and industry” collaboration. Through leveraging physical and functional connections with STT, the future planning of NTM NDA should aim to capture the synergistic and interactive relationship with STT and the other major development areas in NM, with a view towards fostering integration between the two NDAs within the I&T Zone and NM.
(ii) Nurture and Attract Talent – To complement the positioning of NTM NDA as an Academic and Research District, a worker- and student-friendly university town vibe will be developed to groom high-calibre talents to support I&T development in STT, tie in with the Government’s objective of building Hong Kong into an international post-secondary education hub. The planning and urban design of the NDA should target to facilitate knowledge exchanges and cultivation of innovative ideas. On the other hand, a comprehensive residential neighbourhood with commercial, leisure and GIC facilities should be planned to foster a quality living environment for residents and talents. This would in turn attract and nurture talent to provide manpower for supporting industrial development. Housing mix of the NDA should complement the positioning of NTM NDA as an Academic and Research District.
(iii) Versatile Community – To create a liveable area for the future population for NTM NDA as well as supporting the wider developments in NM, an integrated community with adequate and quality urban services and community facilities would be provided in NTM NDA to support the territorial housing demand with an emphasis on “live, learn, play and work”. To optimise the strategic location in NTM NDA, a large portion of land is reserved for the UniTown. Other key district facilities including healthcare and other supporting GIC facilities are also planned to serve NTM NDA and the wider communities. A residential neighbourhood with comprehensive amenities and supporting facilities is planned around the future NTM Station, to enable the residents to reach the GIC facilities for daily necessities, open space and major transport facilities by walking or cycling. A wide range of community facilities are also planned in NTM NDA to develop the area as a vibrant and liveable community to attract and retain global academics and researchers.
Environmental Benefits and Initiatives
(i) Revitalisation of the NTMDC – By integrating sustainability principles with engineering, Hong Kong’s completed river revitalisation projects[1] demonstrate how infrastructure can simultaneously achieve environmental and social objectives - bringing life back to the city’s waterways and setting a benchmark for urban ecological design. Upon completion of revitalisation works at previously concrete lined drainage channels, river ecosystems can be restored and biodiversity will be enhanced through the promotion of wildlife growth. The revitalised rivers serve to reconnect urban communities with nature. Post-revitalisation surveys1 have recorded a resurgence of native species (including bird, fish and dragonfly species) which indicate the improvement in the ecological health of these waterways. Similar to Hong Kong’s earlier successful river revitalisation initiatives, the treatments for the NTMDC including channel widening, flattening of the southern riverbank, as well as incorporating green and eco-conservation elements, such as planting a variety of vegetation and mimicking natural stream environments, are proposed for the revitalization of NTMDC. The slopes of NTMDC will be transformed into planting areas, and new plantings including riparian species would be introduced to enhance aquatic habitats and support the implementation of blue-green infrastructure. The planting of native vegetation and creation of wildlife environments will also maximise biodiversity and promote environmental sustainability. These treatments would bring positive impacts to the nature, as well as the future population of NTM, whereby the overall ecological value and biodiversity would increase. It is expected that the enhanced habitats could provide more ecological resources for the waterbirds species of conservation importance, such as Citrine Wagtail, Great Egret, Little Egret and White-throated Kingfisher. The details of the revitalisation features and ecological enhancement measures will be further developed following Drainage Services Department Practice Note No. 3/2021 Guidelines on Design for Revitalisation of River Channel, and design elements will be agreed with relevant parties and departments during detailed design stage.
Table 2.6 Preliminary Construction and Population Intake Schedule
|
Area |
Rationale of Phasing |
Earliest Date for Commencement of Infrastructure Works |
Earliest Date for Availability of Land for Building Works |
Anticipated First Occupation/ Population Intake Date |
|
|
Phase 1 |
• DRE site (RSc.1) • Integrated Hospital (G.8) & adjacent ESS site (G.9) • Part of UniTown (G.11) • Sewage pumping station (G.1) • Road network connecting to the Integrated Hospital |
• Early handover of the sites for building works (by others) |
Q1 2027 |
Q4 2028 |
2033 for DRE site |
|
Phase 2 |
• Remaining UniTown (G.6, G.10, G.11, G.12) • Residential Site (R.3, R.4) • Remaining G/ICs, School (E.1 & E2), Open Space (O.2, O.5-O.7), Amenity Areas • Majority of road network • NTMDC |
• To commence infrastructure works for targeted population intake • To allow early handover of UniTown |
Q3 2028 |
Q2 2031 |
Q2 2034 |
|
Phase 3 |
• Residential Site R.1, R.2 • Remaining open space • Remaining roadworks, landscape works, riverside & site formation works |
• To suit the programme of interfacing projects |
Q3 2030 |
Q3 2032 |
Q2 2036 |
· Air Quality Impact;
· Noise Impact;
· Water Quality Impact;
· Sewerage and Sewage Treatment Implications;
· Waste Management Implications;
· Land Contamination;
· Ecological Implication (Terrestrial and Aquatic);
· Fisheries Impact;
· Landscape and Visual Impact;
· Impact on Cultural Heritage;
· Hazard to Life;
· Landfill Gas Hazard; and
· Impact from Electric and Magnetic Field.
Construction Phase
Operational Phase
Construction Phase
Operational Phase
Construction Phase
Operational Phase
Construction Phase
Operational Phase
3.8.5 Direct impacts arising from the construction and operational phases of the Project include direct loss of habitats and vegetation, fragmentation of wooded area on Ngau Tam Shan, direct impact on species of conservation importance including flora and fauna species and bird collision. Avoidance, minimisation, mitigation and compensation measures, such as transplantation and translocation of species of conservation importance, incorporation of wildlife corridor and animal barriers design, pre-construction survey and nest control for White-throated Kingfisher, provision of screen hoardings and use of non-transparent or non-glaring materials as appropriate are recommended.
Built Heritage
Construction Phase
Operational Phase
Archaeology
Table 5.1 Summary of Key Environmental Issues Avoided/Minimised and Sensitive Areas Protected
|
Design Approaches |
Environmental Issues Avoided/Minimised and Sensitive Areas Protected |
|
Avoidance of Impact on Sites of Conservation Importance
|
• Encroachment of LTCP, CA, WCA, Priority Site for Enhanced Conservation and OU(WCP) have been avoided. |
|
Avoidance/Minimisation of Ecological Impact on Pond Habitat |
• Impact to the ponds which are considered to have moderate ecological value, to the west of San Tin Highway have been avoided. |
|
Incorporation of Wildlife Corridor and Animal Barriers Design |
• Incorporation of wildlife corridor and animal barriers design will be adopted during the detailed design of the proposed road connection to/from STT to mitigate habitat fragmentation and maintain the movement access for non-flying mammals including species of conservation importance. |
|
Preservation of Natural Habitats |
• Sites GB.1 and GB.2 have been retained in the RODP such that the loss of natural habitats and the associated flora species of conservation importance could be avoided. |
|
Revitalisation of NTMDC |
• NTMDC will be revitalised to serve as green buffer, enhancing biodiversity as well as the overall ecological value. |
|
Avoidance of Impact from the Existing Odour Sources (i.e. chicken farms, LBF and TMB STP) |
• The planned ASRs have been proposed to be situated away from existing odour sources. • Height restriction of air sensitive uses including openable window, fresh air intake and recreational use in open space at concerned sites that fall within odour exceedance zone has been proposed. |
|
Clearing of Existing Odour Sources |
• A chicken farm within the Project Site will be removed to minimise the odour impact to the planned ASRs under the Project. |
|
Provision of Sustainable Transport Infrastructure to Promote Low-carbon Living |
• Pedestrian-friendly environment and robust cycling network has been proposed in the RODP to promote walkability and cycling for low-carbon living. |
|
Proper Design of TIH and PTT |
• Operational fixed noise impacts from the proposed TIH and PTT to NSRs are avoided. |
|
Provision of Direct Road Traffic Noise Mitigation Measures |
• NSRs will be protected to achieve the statutory road traffic noise requirement through adoption of direct noise mitigation measures such as provision of LNRS, absorptive type noise barriers, and acoustic windows/balconies or acoustic windows/balconies lined with sound absorptive material. |
|
Preservation of Points of Local Historical Interests |
• Local resources such as Wai Cheung Ancestral Hall and former Yau Tam Mei Primary School will be preserved in situ within the Project Site in the RODP. • Flexibility for potential adaptive reuse of building structures by future project proponents of UniTown is also allowed in the RODP for former Yau Tam Mei Primary School. |
|
Implementation of an EM&A Programme during Construction and Operational Phases |
• To ensure that all the recommended measures are in place. |
Table 6.1 Summary of Environmental Impacts
|
Sensitive Receivers / Assessment Points |
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance Predicted (Without Mitigation) |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of Mitigation Measures) |
|
Air Quality Impact |
|||||
|
Construction Phase |
|||||
|
· Representative existing and proposed residential, educational institution, commercial developments and government uses within 500 m from the boundary of the Project Site |
Potential dust impact from the construction works of the Project would mainly be related to the construction activities of excavation, material handling, spoil removal and wind erosion. Construction activities of the concurrent projects within 500 m assessment area would also pose cumulative construction dust impact. |
· Air Quality Objectives RSP o 24-hr average conc.: 75 μg/m3 (Number of exceedances allowed: 9) o Annual average conc.: 30 μg/m3 FSP o 24-hr average conc.: 37.5 μg/m3 (Number of exceedances allowed: 18) o Annual average conc.: 15 μg/m3 · Annexes 4 and 12 of the EIAO-TM
|
· N/A |
Air quality control measures stipulated in Air Pollution Control (Construction Dust) Regulation and good site practices listed below should be carried out to further minimise construction air quality impact: · Regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather; · Frequent watering for particularly dusty construction areas and areas close to ASRs; · Provide side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions. Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines; · For the works sites close to the ASRs with a separation distance less than 10 m, provide hoardings of not less than 3.5 m high from ground level along the site boundary; for the other works sites in general, provide hoarding of not less than 2.4 m high from ground level along site boundary except for site entrance or exit; · Avoid positioning material stockpiling areas, major haul roads and dusty works within the construction site close to concerned ASRs; · Avoid unnecessary exposed earth; · Locate all the dusty activities away from any nearby ASRs as far as practicable; · Open stockpiles shall be avoided or covered. Where possible, prevent placing dusty material storage piles near ASRs; · Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations; · Establishment and use of vehicle wheel and body washing facilities at the exit points of the site; · Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs; · Imposition of speed controls for vehicles on site haul roads; and · Instigation of an EM&A program with continuous construction dust monitoring to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.
Guidelines stipulated in EPD’s Recommended Pollution Control Clauses for Construction Contracts should be incorporated in the contract document to abate dust impacts.
Timely application of temporary electricity and water supply should be made and electric vehicles should be adopted as far as practicable.
To minimise the exhaust emissions from NRMMs during the construction phase, the following measures should be applied as far as practicable: · Connect construction plant and equipment to main electricity supply and avoid use of diesel generators and diesel-powered equipment; · Avoid exempted NRMMs; and · Deploy electrified NRMMs. |
· No residual impacts anticipated
|
|
Operational Phase |
|||||
|
· Representative existing and proposed residential, educational institution, commercial developments and government uses within 500 m from the boundary of the Project Site |
Year 2034 RSP · 10th highest 24-hr average conc: 51 – 55 μg/m3 · Annual average: 20 – 21 μg/m3 FSP · 19th highest 24-hr average conc: 30 – 33 μg/m3 · Annual average: 12 – 14 μg/m3 NO2 · 19th highest hourly average conc.: 55 – 114 μg/m3 · 10th highest 24-hr average conc.: 20 – 47 μg/m3 · Annual average conc.: 10 – 25 μg/m3 SO2 · 4th highest 10-minute average conc: 27 – 30 μg/m3 · 4th highest 24-hour average conc: 7 μg/m3 |
· Air Quality Objectives RSP o 24-hr average conc.: 75 μg/m3 (Number of exceedances allowed: 9) o Annual average conc.: 30 μg/m3 FSP o 24-hr average conc.: 37.5 μg/m3 (Number of exceedances allowed: 18) o Annual average conc.: 15 μg/m3 NO2 o 1-hr average conc.: 200 μg/m3 (Number of exceedances allowed: 18) o 24-hr average conc.: 120 μg/m3 (Number of exceedances allowed: 9) o Annual average conc.: 40 μg/m3 · Annexes 4 and 12 of the EIAO-TM |
· No exceedance was predicted |
· No mitigation measure is required |
· No residual impacts anticipated
|
|
|
Odour Impact <5 OU/m3 for the maximum 5-second average odour concentrations at most of the representative ASRs, except some planned ASRs at Sites OU(RDCRD).1, OU(RDPOS).1, G.5, G.6 and G.13. Odour exceedance zones were also found at Sites OU(RDCRD).1, OU(RDPOS).1, G.5, G.6 and G.13. |
· 5 odour units based on an averaging time of 5 seconds |
· Odour exceedances were predicted at some planned ASRs at Sites OU(RDCRD).1, OU(RDPOS).1, G.5, G.6 and G.13. · Odour exceedance zones were found at Sites OU(RDCRD).1, OU(RDPOS).1, G.5, G.6 and G.13. |
Proposed SPS · Full enclosure of odour sources of the proposed SPS with negative pressure to prevent leakage of odourous air and provision of odour removal system with odour removal efficiency of at least 95% (>99.5% removal for H2S) at the ventilation exhaust to control the potential odour emission. · The exhaust of the deodouriser of the proposed SPS should be designed to be located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the vicinity ASRs. LBF · Prior to the population intake of the Proposed Development at OU (RDCRD).1, OU(RDPOS).1 and the proposed G/IC at G.5 and G.13, the following mitigation measures should be incorporated by Food and Environmental Hygiene Department as the licensing conditions after taking into account expert advice of EPD during the annual renewal of the offensive trade license for implementation: - Proper storage, transport and handling of raw materials; - Good housekeeping; - Full enclosure of all odour emission sources of LBF except the Cracklings Storage Area (CSA), including Unloading and Storage Area of Raw Materials, Processing Areas and Lard Boilers, and all these fully enclosed areas shall be maintained under negative pressure; and - Provision of deodouriser(s) (biofilters or other appropriate deodourizing equipment with the odour removal efficiency of at least 95%) to treat all odourous air from the fully enclosed sources before discharging into the atmospheric environment. NDA Planning · Proper planning on the location of air sensitive uses at Site G.6 should be adopted such that no air sensitive use, including openable window, fresh air intake and recreational use in open space, below 15 mAG within the odour exceedance zone. · Proper planning on the location of air sensitive uses at Sites (OU(RDCRD).1 and G.13 should be adopted such that no air sensitive use, including openable window, fresh air intake and recreational use in open space, should be located below 25 mAG and 20 mAG respectively within the odour exceedance zones. · No future air sensitive uses of the proposed development shall be situated within the exceedance zones. |
· No adverse residual odour impact anticipated. |
|
Noise Impact |
|||||
|
Construction Phase |
|||||
|
· Representative existing and planned domestic premises, educational institutions, places of public worship, barracks and noise sensitive temporary structures within 300 m from the boundary of the Project Site that rely on opened windows for ventilation. |
Potential adverse construction noise impact to existing or planned NSRs within 300 m from the boundary of the Project Site due to construction works from the Project |
· Annexes 5 and 13 of the EIAO-TM · Leq(30 min) 75 dB(A) at all domestic premises, temporary housing accommodation, hostels, convalescent homes and home for the aged · Leq(30 min) 70 dB(A) at places of public worship, courts of law, hospitals and medical clinics and educational institutions (including kindergartens and nurseries) (with criterion of 65 dB(A) during examinations) |
N/A |
· Good site practice - Only well-maintained PME to be operated on-site and should be serviced regularly. - Silencers or mufflers on construction equipment should be utilised and should be properly maintained. - Mobile plant, if any, should be sited as far away from NSRs as possible. - Machines and plant that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum. - Plant known to emit noise strongly in one direction should, where possible, be orientated to direct noise away from the nearby NSRs. - Material stockpiles and other structures should be effectively utilised in screening noise from on-site construction activities. · Use of Quality Powered Mechanical Equipment and quieter construction method · Use of temporary movable noise barriers / noise insulating fabric / noise enclosure |
· No adverse residual impacts anticipated |
|
Operational Phase |
|||||
|
· Representative existing and planned residential uses, educational institutions, places of public worship, barracks, noise sensitive temporary structures and planned residential developments within 300 m from the boundary of the Project Site that rely on opened windows for ventilation (for airborne noise impact assessments only). |
Road Traffic Noise Impact · Predicted overall noise levels: up to 84 dB(A) · Predicted road traffic noise levels of Project roads: up to 76 dB(A) Fixed Noise Sources Impact · Adverse fixed noise impact is not anticipated due to proposed fixed noise sources with good design and mitigation measures, and EM&A. Airborne Rail Noise Impact · No adverse airborne rail noise impact is anticipated Ground-borne Rail Noise Impact · No adverse ground-borne rail noise impact is anticipated |
Road Traffic Noise Impact · Annexes 5 and 13 of the EIAO-TM · Calculation of Road Traffic Noise (1988) by Department of Transport, UK · EIAO-GN 12/2023 · L10(1 hour) 70 dB(A) at 1 m from the façade of residential dwellings / noise sensitive temporary structures · L10(1 hour) 65 dB(A) at 1 m from the façade of educational institutions and places of public worship Fixed Noise Sources Impact · Annexes 5 and 13 of the EIAO-TM · Appropriate ANL-5 dB(A) as shown in Table 2 of IND-TM or the prevailing background noise level Airborne Rail Noise · Annexes 5 and 13 of the EIAO-TM · Table 2 of IND-TM Ground-borne Rail Noise · Annexes 5 and 13 of the EIAO-TM · Appropriate ANL-10 dB(A) as shown in Table 2 of IND-TM |
Road Traffic Noise Impact · Exceedance of the noise criteria by up to 14 dB(A) Fixed Noise Sources Impact · No exceedance predicted. Airborne Rail Noise Impact · No exceedance predicted. Ground-borne Rail Noise Impact · No exceedance predicted. |
Road Traffic Noise Impact · Provision of low noise road surfacing (LNRS) · Provision of absorptive type vertical barrier and cantilevered noise barriers on concerned Project road sections · Provision of at-receiver mitigation measures such as acoustic windows / balconies or acoustic windows / balconies lined with sound absorptive material Fixed Noise Sources Impact · All the pumps and noisy plants should be enclosed inside the building structure where practicable · Proper selection of quiet plant aiming to reduce the tonality at NSRs · Installation of silencer/acoustic enclosure/acoustic louvre for the exhaust of ventilation system · Openings of ventilation systems should be located away from NSRs as far as practicable · Implement noise reduction measures at the proposed fire station and ambulance depot, as recommended in the Hong Kong Fire Services Department Environmental Report 2017 and Preliminary Environmental Review Report for Proposed Fire Station cum Ambulance Depot with Department Quarters at On Yu Road, Anderson Road Quarry Development Area Airborne Rail Noise · N/A Ground-borne Rail Noise · N/A |
· No adverse residual impacts anticipated. |
|
Water Quality Impact |
|||||
|
Construction Phase |
|||||
|
· Representative water sensitive receivers in the vicinity of the Project and within 500 m from the boundary of the Project, covers the Deep Bay WCZ as designated under the WPCO |
The potential sources of water quality impacts arising from the inland construction works include: · General construction activities such as site clearance works, demolition works and site formation works; · Construction site run-off; · Sewage effluent from construction workforce; · Accidental spillage of chemicals; · Construction works in close proximity of inland waters; · Construction works in inland waters; · Removal / diversion of watercourses; · Removal / filling of ponds; and · Groundwater from contaminated areas, contaminated site run-off and wastewater from land decontamination |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for the Deep Bay WCZ · Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (DSS-TM) · Practical Note for Professional Persons Practice Note (ProPECC PN) 1/23 and 2/24 · Environmental, Transport and Works Bureau (ETWB) Technical Circular (Works) No. 5/2005 · Hong Kong Planning Standards and Guidelines (HKPSG) |
· N/A |
· Mitigation measures and good site practices in ProPECC PN 2/24 Construction Site Drainage · Provision of temporary sanitary facilities, such as portable chemical toilets, for construction workforce · Waste Disposal Ordinance · Waste Disposal (Chemical Waste) (General) Regulation · Precaution measures in ETWB Technical Circular (Works) No. 5/2005 · Provision of dry zone for all the construction works to be undertaken in watercourses and stormwater drainage · Proper treatment to wastewater and ingress water from the site in compliance with WPCO before discharge · Construction works at the existing ponds only after fully completion of dewatering · Proper treatment or recharge of contaminated groundwater in compliance with the DSS-TM · Emergency Response Plan |
· No adverse residual impacts anticipated |
|
Operational Phase |
|||||
|
· Representative water sensitive receivers in the vicinity of the Project and within 500 m from the boundary of the Project, covers the Deep Bay WCZ as designated under the WPCO |
The potential sources of water quality impacts arising from the operational phase include: · Non-point source surface run-off from new impervious areas; · Sewage disposal strategy for the new developments; · Revitalisation and greening of drainage channel banks; · Sewage overflow and emergency discharge from the proposed SPS; · Potential impact from refuse collection points; · Potential flood risk; and · Change in flow regime and hydrology. |
· Annexes 6 and 14 of the EIAO-TM · Water Quality Objectives for the Deep Bay WCZ · DSS-TM · HKPSG · ETWB TC (Works) No. 14/2004 · DSD Practice Note No. 4/2022 Guidelines on Water Harvesting · ProPECC PN 1/23 · Guidelines for the Design of Small Sewage Treatment Plant |
· N/A |
· Practices in ProPECC PN 1/23 · DSD Stormwater Drainage Manual (5th Edition) · ETWB TC (Works) No. 14/2004 Maintenance of Stormwater Drainage Systems and Natural Watercourses · DSD Practice Note No. 4/2022 Guidelines on Water Harvesting · Stormwater Pollution Control Plan · Provision of a sewerage network to allow diversion of sewage from the proposed on-site SPS to San Tin EPP and, when necessary, Yuen Long EPP via the proposed on-site SPS and Nam Sang Wai SPS respectively for the sewage treatment, subject to detailed design stage · Provision of backup power for dual power supply in case of power failure to sustain the function of pumping and treatment facilities at the SPS · Provision of standby unit for all major equipment in case of break down / emergency at the SPS · Regular maintenance and checking of plant equipment · Contingency Plan · Provision of sedimentation facilities, petrol interceptors or other appropriate wastewater treatment system to treat the wastewater or surface run-off · Screening facilities in drainage system to prevent substances present in stormwater run-off |
· No adverse residual impacts anticipated |
|
Sewerage and Sewage Treatment Implications |
|||||
|
· Existing and planned sewerage system, sewage treatment and disposal facilities |
· Increase in sewage discharge arising from the Project · Potential odour impact from the proposed SPS |
· EPD’s Guidelines for Estimating Sewage Flows for Sewerage Infrastructure Planning Version 1.0 · Annexes 6 and 14 of EIAO-TM |
· N/A |
· Non-dosing solutions should be considered in prior to dosing solutions · Sewage septicity control measures such as direct injection of oxygen into the rising mains and pre-aeration in the wet well of the proposed SPS should be adopted · Enclose the proposed SPS inside a building structure with odour control measures such as scrubber and activated charcoal filter at the exhaust of the ventilation system · Vent should be located away from both existing and planned air sensitive uses as far as practicable · Provide a sewerage network to allow diversion of sewage from the proposed on-site SPS to San Tin EPP and, when necessary, Yuen Long EPP via the proposed on-site SPS and Nam Sang Wai SPS for the sewage treatment, subject to detailed design stage |
· N/A |
|
Waste Management Implications |
|||||
|
Construction Phase |
|||||
|
· N/A
|
· Around 5,437 m3 of non-inert C&D materials and 1,422,222 m3 of inert C&D materials will be generated from site clearance and site formation works · Around 39,628 m3 of non-inert C&D materials and 356,649 m3 of inert C&D materials will be generated from construction of new buildings and infrastructures · Chemical wastes generated from building demolition, plant operation and maintenance of mechanical equipment would be a few cubic metres per month; the total amount of asbestos containing material to be generated will be verified prior to construction stage · Around 566 kg per day of general refuse will be generated from construction works and site-based staff and workers · Around 91,200 m3 of excavated sediment from pond excavation works · Up to 100 m3 of desilted materials from desilting works during revitalisation of NTMDC · Insignificant amount of floating refuse from construction activities along river channels or water bodies |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C) · Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N) · Land (Miscellaneous Provisions) Ordinance (Cap. 28) · Public Health and Municipal Services Ordinance (Cap. 132BK) – Public Cleansing and Prevention of Nuisances Regulation · Air Pollution Control Ordinance (APCO) · Project Administration Handbook (PAH) for Civil Engineering Works · ETWB TC(W) No. 19/2005 on Environmental Management on Construction Site · DEVB TC(W) No. 4/2020 “Tree Preservation” · Relevant guidelines on handling of yard waste on EPD’s website (https://www.epd.gov.hk/epd/ english/environmentinhk/waste/ manage_facility/ypark.html) and Y·Park’s website (https://www.ypark.hk/zh-hant/) · The Greening, Landscape and Tree Management Section of the Development Bureau Guidelines on Yard Waste Reduction and Treatment |
· N/A |
· Implementation of good site practices, waste reduction measures and proper storage, collection and transport of waste · Careful design, planning and good site management to reduce generation of C&D materials · Monitoring of disposal of C&D waste with trip-ticket system and installing CCTV on site · Sorting of yard waste for recycling and reuse on-site · Precautionary measures for handling and disposal of asbestos containing materials · Chemical waste should be stored in appropriate containers and collected by a licensed chemical waste contractor. · Education programme and clearly labelling recycling bins to encourage segregation and recycling of aluminium, plastic wastes and wastepaper and reduce general refuse production · All excavated sediment will be treated and reused on-site as backfilling materials for the Project · The desilted materials should be handled by the Contractor using standard good practices before transporting for disposal · Removing floating materials and eventually storing and disposing of together with the general refuse, after separating the recyclables for recycling |
· No adverse residual impact anticipated |
|
Operational Phase |
|||||
|
· N/A |
· Around 138.7 tonnes per day of municipal solid waste · A few cubic metres per month of chemical wastes will be generated from public facilities operation, maintenance of facilities and equipment, and laboratory testing in the Integrated Hospital · Around 1,000 kg per day of clinical waste · About 100 m3 of desilted materials per time of desilting works during maintenance of the revitalised NTMDC |
· Annexes 7 and 15 of the EIAO-TM · Waste Disposal Ordinance (Cap. 354) · Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C) · Public Health and Municipal Services Ordinance (Cap. 132BK) – Public Cleansing and Prevention of Nuisances Regulation · Code of Practice for the Management of Clinical Waste - Major Clinical Waste Producers and Waste Collectors (June 2010) |
· N/A |
· Implementation of waste prevention programme as well as materials recovery and recycling programme · Proper storage, collection and transport of waste · Chemical waste should be stored in appropriate containers and collected by a licensed chemical waste contractor · Clinical waste should be properly separated from other waste, packed, labelled, centrally collected and stored in designated clinical waste storage rooms. Clinical waste shall be collected by licensed clinical waste collectors for disposal at the licensed disposal facility · The desilted materials should be handled by the Contractor using standard good practices before transporting for disposal |
· No adverse residual impact anticipated |
|
Land Contamination |
|||||
|
· Future occupants |
· A total of 30 potentially contaminated sites and 16 sites suspected to be used for industrial purposes were identified within the Project Site (excluding the works sites / areas under the NOL Main Line project and the development area under the STLMC DN project) |
· Annex 19 of the EIAO-TM · Practice Guide for Investigation and Remediation of Contaminated Land (EPD, revised in April 2023) · Guidance Note for Contaminated Land Assessment and Remediation (EPD, revised in April 2023) · Guidance Manual for Use of Risk-based Remediation Goals (RBRGs) for Contaminated Land Management (EPD, revised in April 2023) |
· N/A |
· Further site appraisal and submission of Contamination Assessment Plan(s) (CAP(s)) for the whole Project Site should be conducted at a later stage of the Project when site access is available. · Intrusive site investigation and any necessary remediation action should be carried out after operation of concerned site(s) has ceased but prior to the commencement of construction works. · The submission of Contamination Assessment Report(s), Remediation Action Plan(s) and Remediation Report(s) for EPD’s approval, if remediation is required, should follow the relevant Guidance Manual, Guidance Note and Practice Guide. |
· No adverse residual impact anticipated. |
|
Ecological Implication (Terrestrial and Aquatic) |
|||||
|
Construction Phase |
|||||
|
· Recognised sites of conservation importance · Wetland habitats (e.g. ponds, marsh / reed, watercourses) · Other terrestrial habitats (e.g. woodland) · Wildlife (including flora and fauna species of conservation importance) · Flight corridor
|
Direct Impacts · Direct impact on developed area/wasteland habitat within the WBA due to the construction works for a small section of cycle track and the associated connection · Permanent loss of habitat including marsh/reed, ponds, watercourses, wooded habitats, grassland, shrubland, and man-made habitats (i.e. agricultural land, village/orchard and developed area/wasteland) · Fragmentation of wooded areas · Direct impact on species of conservation importance · Potential direct injury/ mortality of wildlife species (e.g. bird collision)
Indirect Impacts · Disturbance impact (e.g. noise, glare, air/dust, traffic, anthropogenic activities and water quality deterioration etc.) to recognised sites of conservation importance, ecologically sensitive resources, flight corridor, potential bat roost, natural habitats and associated wildlife in the vicinity · Potential water quality, hydrodynamics impact · Night-time disturbance |
· Annexes 8 and 16 of the EIAO-TM · EIAO Guidance Notes Nos. 3/2010, 6/2010, 7/2023 and 10/2023 |
· N/A |
· Avoided loss of wetland habitat within the WBA · Preservation of NTMDC with enhancement measures and non-building area or “Open Space” on both sides · Preservation of mixed woodland habitat at the southern part of the Project Site · Pre-construction survey and transplantation / translocation, and nest control measures for species of conservation importance · Wetland compensation · Provision of temporary access for wildlife, screen hoardings/fencings · Phased construction works for revitalisation works in NTMDC · Use of non-transparent or non-glaring building materials · Provision of suitable lighting in construction sites, use of directional lighting and control of night-time lighting period · Provision of screening (e.g. hoarding) for demarcation of the construction site · Adoption of general good site practice · Exploration of the feasibility to adopt MiC technology in the detailed design stage · Adoption of noise, air and water quality mitigation measures |
· No unacceptable adverse residual impact anticipated |
|
Operational Phase |
|||||
|
· Recognised sites of conservation importance and ecologically sensitive resources · Wetland habitats (e.g. ponds, marsh / reed, watercourses) · Other terrestrial habitats (e.g. woodland) · Wildlife (including flora and fauna species of conservation importance · Flight paths |
· Potential direct injury or mortality for less mobile fauna species along the proposed road connection to/from STT · Potential bird collision to noise barriers, building façade and traffic flow of the proposed roads
Indirect Impacts · Disturbance impacts (e.g. human, noise, air quality, light pollution, traffic and visual) to the recognised sites of conservation importance, ecologically sensitive resources, species of conservation importance, wildlife and habitat · Obstruction and disturbance to flight corridor |
· Same as construction phase |
· N/A |
· Incorporation of wildlife corridor design and animal barriers along the proposed road connection to/from STT · Provision of embed/superimpose opaque strips or opaque dots/visual markers on proposed noise barriers · Provision of tree planting at the eastern margin as screening · Provision of non-building area or “Open Space” along both sides of NTMDC and peripheral tree planting as screening
|
· No unacceptable adverse residual impact anticipated |
|
Fisheries Impact |
|||||
|
· Pond Culture Fisheries (aquaculture activities and fisheries production) |
· Loss of active fishponds · Loss of inactive fishponds · Loss of abandoned fishponds · Loss of watercourses for aquaculture activities · Deterioration of water quality and hydrological condition · Bund stability · Blockage of access |
· EIAO-TM Annexes 9 and 17 · Water Pollution Control Ordinance (Cap. 358) |
· N/A |
· Maintaining bund stability · Minimisation of potential water quality impacts · Control of construction site run-off · Control of construction-related activities · Implementation of good site practices |
· No adverse residual impact anticipated |
|
Landscape and Visual Impact |
|||||
|
Construction Phase |
|||||
|
· Landscape Resources (LRs) |
· Beneficial impact on LR4 and LR14 · Slight impact on LR10 and LR13 · Moderate impact on LR1, LR2, LR3, LR5, LR6, LR7, LR8, LR9, LR11 and LR12 |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN No. 8/2023 Preparation of Landscape And Visual Impact Assessment under the EIAO |
· N/A |
· Preserve existing vegetation as far as practicable · Minimise disturbance on watercourses · Carefully manage construction activities and facilities · Reinstate temporarily disturbed landscape areas · Erect decorative screen hoarding |
· Beneficial residual impact on LR4 and LR14 · Slight residual impact on LR10 and LR13 · Moderate residual impact on LR1, LR2, LR3, LR5, LR6, LR7, LR8, LR9, LR11 and LR12 |
|
· Landscape Character Areas (LCAs) |
· Beneficial impact on LCA5 · Negligible impact on LCA3 and LCA6 · Slight impact on LCA4 · Moderate impact on LCA2 · Substantial impact on LCA1 |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN No. 8/2023 Preparation of LVIA under the EIAO |
· N/A |
· Beneficial residual impact on LCA5 · Negligible residual impact on LCA3 and LCA6 · Slight residual impact on LCA4 · Moderate residual impact on LCA2 · Substantial residual impact on LCA1 |
|
|
Operational Phase |
|||||
|
· Landscape Resources (LRs) |
· Same as Construction Phase |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN No. 8/2023 Preparation of LVIA under the EIAO |
· N/A |
· Compensate loss of existing trees by tree planting in a ratio of 1:1 in terms of number as far as practicable · Provide roadside and amenity planting · Incorporate sensitive and aesthetically pleasing design of aboveground structures · Provide buffer planting · Provide green roof · Revitalisation of NTMDC to create a Blue-Green Network · Maximise greening on building structures and surfaces
|
· Beneficial residual impact on LR4 and LR14 · Negligible residual impact on LR10, and LR13 · Slight residual impact on LR1, LR2, LR3, LR5, LR6, LR7, LR8, LR9, LR11 and LR12 |
|
· Landscape Character Areas (LCAs) |
· Same as Construction Phase |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN No. 8/2023 - Preparation of LVIA under the EIAO |
· N/A |
· Beneficial residual impact on LCA5 · Negligible residual impact on LCA3, LCA4 and LCA6 · Slight residual impact on LCA2 · Moderate residual impact on LCA1 |
|
|
· Vantage Points (VPs) |
· N/A |
· Annexes 10 and 18 of the EIAO-TM · EIAO-GN No. 8/2023 - Preparation of LVIA under the EIAO |
· N/A |
· Slight residual impact on VP7 · Moderate residual impact on VP1, VP2, VP3, VP4, VP5A, VP5B and VP6 |
|
|
Impact on Cultural Heritage |
|||||
|
Construction Phase |
|||||
|
· Built heritage, other identified items and archaeological resources |
Built Heritage and Other Identified Item · A total of 54 built heritage and other identified items are identified within the 300 m assessment area. · 9 other identified items are located within the Project Site. Wai Cheung Ancestral Hall will be retained in situ within a planned open space and the former Yau Tam Mei Primary School within the UniTown is proposed to be preserved in-situ, subject to the future project proponent’s consideration at detailed design in later stages. The remaining 7 would be inevitably removed due to the Project. · The remaining 45 built heritage and other identified items located outside the Project Site but within 300 m assessment area would be subject to indirect impacts. Archaeology · Potential direct impact on 3 high archaeological potential areas, namely Ngau Tam Mei SAI, Ngau Tam Mei ASA and Ngau Tam Mei (North) ASA, located within the Project Site is anticipated. · Potential direct impact to both the upper stream low-lying agricultural fields and hilly landscape within the Project Site having moderate-low archaeological potential is anticipated. · Acceptable impact on the low archaeological potential areas identified within the Project Site. · No impact is anticipated for the remaining areas that have been disturbed heavily due to modern development and have no archaeological potential and outside the Project Site. |
· EIAO-TM Annexes 10 and 19 · A&MO (Cap.53) |
· N/A |
Built Heritage and Other Identified Item · Cartographic and photographic record, and other documentation means (including 3D scanning) should be conducted for items that will be subject to direct impact (i.e. demolition) prior to the commencement of any construction works at the respective locations for record purposes and future use, such as research, exhibition and educational programmes. · Standard control measures on ground-borne vibration, tilting and settlement by drawing necessary references from relevant government guidelines should be implemented on other identified items when there are construction works nearby. · Standard measures of pre-construction condition survey should be carried out for Wai Cheung Ancestral Hall and the former Yau Tam Mei Primary School (if preserved in situ) to better understand its physical structural condition. A post-construction condition survey should also be carried out to confirm its structural stability · A buffer zone should be reserved for Wai Cheung Ancestral Hall and the former Yau Tam Mei Primary School (if preserved in situ) according to the results of the pre-construction condition survey in the design layout of the Project to mitigate potential adverse vibration impact arising from construction works. · Protective covering or sheltering should be provided for Wai Cheung Ancestral Hall and the former Yau Tam Mei Primary School (if preserved in situ) during construction activities in proximity to avoid potential damages through direct contact with construction machineries. · Dust suppression measures and good site practice should be adopted during the construction phase to avoid dust nuisance on Wai Cheung Ancestral Hall, San Yau Vegetable Marketing Co-operative Society, Ltd. and the former Yau Tam Mei Primary School (if preserved in situ). · A safe access route to Wai Cheung Ancestral Hall, San Yau Vegetable Marketing Co-operative Society, Ltd. and the former Yau Tam Mei Primary School (if preserved in situ) should be maintained for conducting mitigation measures. · Management measures should be deployed, such as briefing to site staff before commencement of construction works and posting notices at site office(s), to be aware of the other identified items in close proximity. Archaeology · Archaeological excavation is recommended for the Project Site within Ngau Tam Mei SAI prior to the commencement works involving soil disturbance. · Archaeological excavation and survey-cum-excavation are recommended for the Ngau Tam Mei ASA and Ngau Tam Mei (North) ASA prior to the commencement works involving soil disturbance at the concerned high archaeological potential areas. · Archaeological survey should be conducted at moderate-low archaeological potential areas. · As a precautionary measure and pursuant to the A&MO (Cap. 53), the project proponent is required to inform the AMO immediately in case of discovery of antiquities or supposed antiquities in the course of works, so that appropriate mitigation measures, if needed, can be timely formulated and implemented in agreement with and to the satisfaction of AMO. |
· No adverse residual impact anticipated. |
|
Operational Phase |
|||||
|
· Built heritage, other identified items and archaeological resources |
Built Heritage and Other Identified Item · No adverse impact on built heritage and other identified items is anticipated during operational phase, except Wai Cheung Ancestral Hall and former Yau Tam Mei Primary School at which direct impact is anticipated should they be utilised. Archaeology · No adverse impact would be anticipated on archaeological resources during the operational phase. |
· EIAO-TM Annexes 10 and 19
|
· N/A |
Built Heritage and Other Identified Item · No mitigation measure would be required for built heritage and other identified items except the preserved in situ Wai Cheung Ancestral Hall and the possible preserved in situ the former Yau Tam Mei Primary School. · Any revitalisation proposed for Wai Cheung Ancestral Hall and the former Yau Tam Mei Primary School in later stages should be further reviewed with mitigation measures as appropriate. Archaeology · No mitigation measure would be required for archaeological resources during the operational phase. |
· No adverse residual impact anticipated. |
|
Hazard to Life |
|||||
|
· Existing and planned population |
· Since there are no existing and planned hazardous facilities within and in the vicinity of the Development Area, no hazard to life impact is anticipated. |
· Annex 4 of the EIAO-TM · Hong Kong Risk Guidelines |
· N/A |
· N/A |
· N/A |
|
Landfill Gas Hazard |
|||||
|
Construction Phase |
|||||
|
· Workers that would work within the CZ of Ngau Tam Mei Landfill (NTML) |
· Qualitative LFGHA is assessed as “Very Low Risk” for construction phase and no mitigation measures are required. |
· Annexes 7 and 19 of the EIAO-TM · ProPECC PN 3/96 · Landfill Gas Hazard Assessment Guidance Note (2022) |
· N/A |
No mitigation measures are required. However, the following precautionary and protective measures should be considered to further minimize the landfill gas hazard: · A protective barrier at the point where a utility passes through the perimeter of the CZ of NTML such that trench excavations do not form a route for gas migration. · Service runs within the CZ of NTML should be designated as “special routes” and utility companies should be informed to that effect so that they may consider implementing precautionary measures. · The presence of LFG should be monitored before entry and periodically during the works, as a precautionary measure for excavations of 1 m depth within the CZ of NTML. |
· No adverse residual impact anticipated. |
|
Operational Phase |
|||||
|
· Future occupants / workers within the CZ of NTML |
· Qualitative LFGHA is assessed as “Very Low Risk” for operational phase and no mitigation measures are required. |
· Annexes 7 and 19 of the EIAO-TM · ProPECC PN 3/96 · Landfill Gas Hazard Assessment Guidance Note (2022) |
· N/A |
· No mitigation measures are required. However, the precautionary and protective measures same as construction phase should be considered to further minimize the landfill gas hazard.
|
· No adverse residual impact anticipated. |
|
Impact from Electric and Magnetic Field |
|||||
|
· Future occupants under/in the vicinity of the existing 400 kV overhead cables situated near/at the southern and eastern portions of the Development Area |
According to the SHR & HPR EIA report and STLMC DN EIA report: · The maximum electric field strength measured directly underneath the overhead cables was 288 V/m (rms) and 198 V/m (rms) respectively · The maximum magnetic flux measured directly underneath the overhead cables was 4.88 μT (rms) and 1.40 μT (rms) respectively |
· International Commission on Non-ionizing Radiation Protection (1998) guidelines (limits for continuous general public exposure: 5,000 V/m (rms) & 100 μT (rms); limits for continuous occupational exposure: 10,000 V/m (rms) & 500 μT (rms)) · HKPSG |
· N/A |
· No mitigating measures are required. |
· No adverse residual impact anticipated. |
[1] River Revitalisation
for the Good of Water (https://www.dsd.gov.hk/EN/Publicity_and_Publications/Publicity/
DSD_Sustainability_Reports/1/river_revitalisation.html)