TABLE OF
CONTENTS
1.4 Recommended
Outline Development Plan
1.5 Designated
Project under EIAO
1.7 Objectives of this EIA Study
1.8 Structure
of the EIA Report
List of tables
Table 1.1 Schedule
2 Designated Projects Under the Project
Table 1.2 Schedule
2 Designated Projects Not Under the Project
Table 1.3 Summary
of Non-Designated Projects Under the Project
LISTS OF FIGURES
|
Project Location Plan |
|
|
Locations of Designated Projects |
(a) Site formation works including slope cutting and filling and retaining wall installation;
(b) Engineering infrastructure works comprising roads including district distributor roads, local roads, drainage works including revitalisation works for Ngau Tam Mei Drainage Channel (NTMDC), sewerage provision including a SPS and other utilities works to support the proposed development of the Project;
(c) Landscaping, streetscaping and ancillary works; and
(d) Provision of environmental mitigation measures for the works mentioned above.
Other Works
(a)
Developments
including GIC facilities, residential development, schools, electrical
substations and other facilities to support the proposed development of the
Project.
¡¤ Item 1 ¨C An urban development or redevelopment project covering an area of more than 50 ha.
Table 1.1 Schedule
2 Designated Projects Under the Project
|
Ref. No. |
Schedule 2
Designated Project |
Work Component / Reference in RODP |
|
|
DP1 |
Item
A.1 |
A
carriageway for motor vehicles that is an expressway, trunk road, primary
distributor road or district distributor road |
Construction
and operation of district distributor road (Road D1) and associated road
works at San Tin Highway |
|
DP2 |
Item
I.1(b) |
A
drainage channel or river training and diversion works located less than 300
m from the nearest boundary of an existing or planned conservation area |
Part
of Revitalisation of Ngau Tam Mei Drainage Channel and river diversion works
located less than 300 m from the nearest boundary of an existing conservation
area |
Table 1.2 Schedule 2 Designated Projects Not Under the
Project
|
Schedule 2
Designated Projects in the Project Profile and Study Brief |
Relevant
Work Component |
|
|
Item F.1 |
Sewage treatment works with an installed
capacity of more than 15,000 m3 per day |
Only SPS and sewerage provided |
|
Item F.2 |
Sewage treatment works with an installed capacity of more than 5,000 m3
per day; and a boundary of which is less than 200 m from the nearest boundary
of an existing or planned (i) residential area;
(ii) place of worship; (iii) educational institution; (iv) health care
institution; (v) site of special scientific interest; (vi) site of cultural
heritage; (vii) bathing beach; (viii) marine park or marine reserve; (ix)
fish culture zone; or (x) seawater intake point |
|
|
Item H.1 |
A 400 kV electricity substation and transmission line |
Only two 132 kV electricity substations
proposed |
Table 1.3 Summary of
Non-Designated Projects Under the Project
|
Non-Designated
Project |
Sub-Element |
|
Education |
University
Town (Post-secondary Education Use) |
|
Primary
School |
|
|
Secondary
School |
|
|
GIC
Facilities |
Integrated
Hospital |
|
Ambulance
Depot |
|
|
Community
Recycling Centre |
|
|
Electricity
Substations |
|
|
Fire
Station and Departmental Staff Quarters |
|
|
Indoor
Sports Centre |
|
|
Library |
|
|
Refuse
Collection Points |
|
|
Sewage
Pumping Station |
|
|
Staff
Quarters |
|
|
Residential
Development |
Private
Housing |
|
Dedicated
Rehousing Estate |
|
|
Open
Space |
Recreational
Facilities and Landscaping |
|
Amenity |
Roadside
Amenity |
|
Green
Belt |
- |
|
Other
Specified Uses |
Other
Specified Uses (Railway Depot with Commercial/Residential Development) |
|
Other
Specified Uses (Railway Depot with Public Open Space) |
|
|
Road |
Local
Roads |
(a) Should the change(s) involve a DP item under Schedule 2 of the EIAO, the requirements under the EIAO will be complied with; and
(b)
Should the change(s) not involve any DP items
under Schedule 2 of the EIAO, prevailing planning mechanisms and standards will
be followed and relevant EIA findings will be
conformed to.
(a) the overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project;
(b) the conditions and requirements for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences wherever practicable; and
(c) the acceptability of residual impacts after the proposed mitigation measures are implemented.
(a) to describe the Project and associated works together with the requirements and environmental benefits for carrying out the Project;
(b) to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including both the natural and man-made environment and the associated environmental constraints;
(c) to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potential affected uses, and to propose measures to mitigate these impacts;
(d) to identify and quantify any potential impacts from point and non-point pollution sources on the identified water systems and sensitive receivers and to propose measures to mitigate these impacts;
(e) to identify and quantify potential waste management requirements and to propose measures to mitigate these impacts;
(f) to identify and quantify contaminated land within the Project area, and to propose measures to avoid disposal in the first instance;
(g) to identify, evaluate and address any potential ecological impacts arising from the Project and to propose measures to mitigate these impacts;
(h) to identify and quantify the fisheries impacts and to propose measures to mitigate these impacts;
(i) to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;
(j) to identify any negative impacts on cultural heritage and to propose measures to mitigate these impacts;
(k) to identify potential hazard to life impacts and to propose mitigation measures to mitigate these impacts;
(l) to identify any impacts from electric and magnetic fields and to propose measures to mitigate these impacts;
(m) to propose the provision of infrastructure or mitigation measures so as to minimise pollution, environmental disturbance and nuisance during the construction and operation stages of the Project;
(n) to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
(o) to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;
(p) to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these residual environmental impacts and cumulative effects and reduce them to acceptable levels;
(q) to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification;
(r) to design and specify the environmental monitoring and audit requirements;
(s) to identify any additional studies necessary to implement the mitigation measures and proposals recommended in the EIA report; and
(t) to identify DP(s) listed under Schedule 2 of the EIAO as part of the Project for assessment under the EIA study.
¡¤ Section 3: Air Quality Impact
¡¤ Section 4: Noise Impact
¡¤ Section 5: Water Quality Impact
¡¤ Section 6: Sewerage and Sewage Treatment Implications
¡¤ Section 7: Waste Management Implications
¡¤ Section 8: Land Contamination
¡¤ Section 9: Ecological Implication (Terrestrial and Aquatic)
¡¤ Section 10: Fisheries Impact
¡¤ Section 11: Landscape and Visual Impact
¡¤ Section 12: Impact on Cultural Heritage
¡¤ Section 13: Hazard to Life
¡¤ Section 14: Landfill Gas Hazard
¡¤ Section 15: Impact from Electric and Magnetic Field