TABLE
OF CONTENTS
6
Sewerage and Sewage
Treatment Implications
6.1 Introduction
6.2 Population and Employment Data
6.3 Methodology of Sewerage Impact Assessment
6.4 Existing and Planned Sewerage Infrastructure
6.5 Estimation of Sewage Discharge
6.6
Proposed Sewerage
Scheme
6.7
Proposed Emergency
Bypass
6.8
Implementation Phasing
6.9
Potential Impacts by
the Proposed Sewerage System
6.10 Recommended Mitigation Measures
6.11 Conclusion
List
of tables
Table 6.1........ Population
Summary of the Project in Recommended Outline Development Plan
Table 6.2........ Unit
Flow Factors for Residential and Commercial Population from GESF
Table 6.3........ Peaking
Factors for Various Population Ranges
Table 6.4........ Summary
of Estimated Sewage Discharge from the Project
Table 6.5........ Summary
of Estimated Sewage Discharge
Table 6.6........ Build
Up of the Sewage Flow within NTMA
Table 6.7........ Summary
of Sewage Peak Flow designed for the Proposed SPS
Table 6.8........ Wet
Well Arrangement
Table 6.9........ Preliminary
Hydraulic Assessment of Rising Main
Table 6.10 Preliminary List of Responsible Parties of the
Proposed Sewerage and Sewage Treatment Facilities
LIST OF EXHIBIT
6
Sewerage and Sewage Treatment Implications
6.1
Introduction
6.1.1
This section presents the assessment on the potential sewerage and
sewage treatment implications associated with the construction and operation of
the Project. The sewerage and sewage treatment implications have been assessed
in accordance with the criteria and guidelines on Annexes 6 and 14 of the Environmental Impact Assessment
Process, the requirements of WPCO and the requirements in Section 3.4.6
and Appendix E of the EIA
Study Brief (ESB-363/2023).
6.2
Population and Employment Data
Sewage Catchments in North-East New Territories
6.2.1
There is no existing sewerage system near the Development Area.
According to the approved EIA report for San Tin Technopole (STT) (Register
No.: AEIAR-261/2024), San Tin Effluent Polishing Plant (EPP) is planned under
the project. The expected commissioning year of the planned San Tin EPP is in
2031. Sewage generated by the Project would be pumped from the proposed on-site
sewage pumping station (SPS) to the San Tin EPP for treatment.
Population and Employment for Estimation of Sewage Flow
6.2.3 For technical assessments under the Study, a 0%
home space enhancement (i.e. 50 m2 for public housing and 75 m2
for private housing) was adopted as a more conservative approach. The
approximate population of the Project adopted in this assessment is summarised
in Table 6.1.
Table
6.1 Population Summary of the Project in
Recommended Outline Development Plan
|
|
Population
|
|
Base Case
|
Sensitivity Test
Scenario
|
|
Residential
|
38,500
|
42,200
|
|
Employment
|
26,000
|
35,700
|
6.3
Methodology of Sewerage Impact Assessment
6.3.1
The sewage flows are
estimated using unit flow factor (UFF) in Tables T-1 and T-2 of EPD*s
Guidelines for Estimating Sewage Flows for Sewerage Infrastructure Planning
Version 1.0 (GESF). With reference to the GESF, commercial flows comprise flows
due to commercial activities and employees. The total UFF is the sum of UFF for
employee plus various commercial activities, i.e. J2 to J12 as defined in Table
T-2 of GESF. The unit flows factors that were used to estimate the
sewage flows from the Project are listed in Table 6.2 below.
Table
6.2 Unit Flow Factors for Residential and
Commercial Population from GESF
|
Description
|
Type
|
Unit
|
UFF per Employee
(m3/day)
|
UFF for Commercial Activities
(m3/day)
|
Total Unit Flow Factors (UFF) (m3/day)
|
|
Domestic Flows
|
|
Dedicated Rehousing Estate
|
Private Housing (R2)
|
Person
|
/
|
/
|
0.27
|
|
Private Housing/ Staff Quarter/ Residential Social Welfare Facilities
|
Private Housing (R2)
|
Person
|
/
|
/
|
0.27
|
|
Student, Hospital and Commercial Flows
|
|
Student
|
-
|
Person
|
/
|
/
|
0.04
|
|
Hospital Bed
|
-
|
Person
|
/
|
/
|
1.25(1)
|
|
Wet Lab Staff
|
J2
|
Employee
|
0.08
|
0.25
|
0.33
|
|
Wet Lab Admin Staff
|
J6
|
Employee
|
0.08
|
/
|
0.08
|
|
Dry Lab Staff
|
General
|
Employee
|
0.08
|
0.20
|
0.28
|
|
Dry Lab Admin Staff
|
J6
|
Employee
|
0.08
|
/
|
0.08
|
|
General Employee
|
General
|
Employee
|
0.08
|
0.20
|
0.28
|
Note:
(1) Referenced
from Appendix I of GESF issued by EPD.
Catchment Inflow Factors
6.3.2
The Catchment Inflow
Factors (Pcif) cater for the net overall ingress of water or wastewater to the
sewage system. They are catchment-dependent and applicable to major sewage
facilities of a catchment. They are not applicable to new catchments which are deemed
to be free from misconnections and pipe defects. Therefore, the Pcif are not
applicable in estimating the total flows from the new development area.
Peaking Factors
6.3.3
Peaking factors cater
for seasonal/diurnal fluctuation and normal amount of infiltration and inflow.
The peaking factors shall be in accordance with Table T-5 of EPD*s GESF.
6.3.4
Under normal condition,
peaking factors (excluding stormwater allowance) are applicable to planning
sewage facilities receiving flow from new upstream sewage systems which
essentially have no misconnections and defects for infiltration. If the service
conditions of the upstream sewage systems for the planning horizons under
considerations are unclear, peaking factors (including stormwater allowance)
shall be used.
6.3.5
Table 6.3 below shows the peaking factors for various population
range (including and excluding stormwater allowance) for design of sewer and
sewage treatment works.
Table
6.3 Peaking Factors for Various Population
Ranges
|
Population Range
|
Peaking Factor (including stormwater allowance) for facility with
existing upstream sewerage
|
Peaking Factor (excluding stormwater allowance) for facility with new
upstream sewerage
|
|
Sewers
|
|
<1000
|
8
|
6
|
|
1,100
每 5,000
|
6
|
5
|
|
5,000
每 10,000
|
5
|
4
|
|
10,000
每 50,000
|
4
|
3
|
|
>50,000
|
Max (7.3/N0.15, 2.4)
|
Max (6/N0.175, 1.6)
|
Sewage
Treatment Works, Preliminary Treatment Works and Pumping Stations
|
|
<10,000
|
4
|
3
|
|
10,000
每 25,000
|
3.5
|
2.5
|
|
25,000
每 50,000
|
3
|
2
|
|
>50,000
|
Max (3.9/N0.065, 2.4)
|
Max (2.6/N0.065, 1.6)
|
Note:
(1) N = Contributing population in
thousands
Contributing population = Calculated total average flow (m3/day) /
0.27 (m3/person/day)
6.3.6
The peaking factors (excluding stormwater allowance) should be adopted
for the gravity sewer, sewage pumping station and sewage rising mains because
the proposed sewerage facilities of the Project will only receive flow from new
upstream sewer systems which should have no misconnections and defects for
infiltration.
6.4
Existing and Planned Sewerage Infrastructure
Existing and Planned Sewerage Infrastructure
6.4.1
There is no existing sewerage system near the Development Area. Sewage generated
by the Project would be pumped from the proposed on-site SPS to the planned San
Tin EPP for treatment.
Interface with Planned Sewerage System
6.4.2
Planned sewerage network for the future Ngau Tam Mei (NTM) Station and
its associated railway facility (i.e. Ngau Tam Mei Depot (NTD)) under Northern
Link (NOL) Main Line (by MTRCL) is anticipated. In the sewerage network
design under the Project, it has been planned that the sewage discharged from
the operation of NTM Station and NTD will be collected by sewerage under the
Project.
6.5
Estimation of Sewage Discharge
Estimated Sewage Discharge from the Development Area
6.5.1
Based on the design parameters and assumptions discussed in Section
6.3, the estimated sewage discharge from the Project is summarised in Table
6.4.
Table
6.4 Summary of Estimated Sewage Discharge
from the Project
|
Land Use
|
Total Unit Flow Factor(1) (m3/head/day)
|
Population/ Employment(4)
|
Total Average Dry Weather Flow (ADWF)
(m3/day)
|
|
Dedicated Rehousing Estate (R1)
|
0.27
|
2,352
|
635
|
|
Private Housing (R2)
|
0.27
|
38,491
|
10,393
|
|
Staff Quarters(5) (R2)
|
0.27
|
1,331
|
359
|
|
Post-Secondary Hostel Place(6) (R2)
|
0.27
|
28,196
|
7,613
|
|
Student(7)
|
0.04
|
49,892
|
1,996
|
|
Wet Lab Staff (J2)
|
0.33
|
1,760
|
581
|
|
Wet Lab Admin Staff (J6)
|
0.08
|
440
|
35
|
|
Dry Lab Staff (General)
|
0.28
|
3,520
|
986
|
|
Dry Lab Admin Staff (J6)
|
0.08
|
880
|
70
|
|
Hospital Bed
|
1.25
|
3,030
|
3,788
|
|
General Employee
|
0.28
|
29,088
|
8,145
|
|
Centralised Cooling Systems for UniTown and
Integrated Hospital
|
/
|
/
|
2,101(2)
|
|
NOL Development
|
/
|
/
|
459(3)
|
|
Sub-total
|
37,159(8)
|
|
Total ADWF (with 10% contingency) (m3/day)
|
40,875
|
Notes:
(1) Total UFF refers to Table
6.2.
(2) The predicted daily wastewater
discharge is based on its water consumption.
(3) According to the approved NOL
EIA report (Register No.: AEIAR-259/2024), the total ADWF of railway facilities
within the Development Area (i.e. NTM Station and NTD) under normal operation
is 459 m3/day.
(4) Population/employment figure
adopted in this table is based on the sensitive test scenario.
(5) ※Staff Quarter§ refers to staff
quarter to be provided at Site G.5.
(6) ※Post-Secondary Hostel Place§
refers to staff quarter and student hostel place to be provided by UniTown.
(7) ※Student§ refers to students
studying in UniTown, proposed kindergarten, and proposed primary and secondary
schools.
(8) Value may not be exactly sum up
due to the round-off of ADWF in each land use.
6.5.2
With addition of sewage discharge from existing adjacent villages as
mentioned in Section 6.2.2, the sewage generated within the Development
Area will reach approximately 44,875 m3/day (Table 6.5
refers). Taking into account the additional sewage flow from the
existing adjacent villages (i.e. 11,000 m3/day), the total sewage
generated from the entire Ngau Tam Mei Area (NTMA) will be 55,875 m3/day
in the long term. A buildup of the sewage flow with reference to the population
intake based on the Recommended Outline Development Plan (RODP) is shown in Table
6.6.
Table 6.5
Summary of Estimated Sewage Discharge
|
Description
|
Total ADWF (m3/day)
|
|
Total Sewage Flow from the Project (with 10% contingency)
|
40,875
|
|
Sewage Flow from Existing Adjacent Villages (Initial Stage)
|
4,000
|
|
Sub-total
|
44,875
|
|
Additional Sewage Flow from Existing Adjacent Villages (Long Term)
|
11,000
|
|
Total
|
55,875
|
Table 6.6 Build
Up of the Sewage Flow within NTMA (1)
|
Population Intake Year
|
Cumulative ADWF (m3/day) (2)
|
|
2034
|
11,013
|
|
2036
|
40,875
|
Note:
(1) With reference to Section 2,
the first population intake of the Project will be in Year 2033 for the
Dedicated Rehousing Estate (DRE) site within where temporary sewerage
arrangement (i.e. septic tank) will be provided. The DRE site will be
permanently connected to the proposed sewerage system of the Project in Year
2034.
(2) 10% contingency is added in
ADWF for sewerage design.
6.6
Proposed Sewerage Scheme
6.6.1
Sewage collected within
the sewerage system under the Project will be conveyed to the proposed on-site
SPS with a capacity of 44,875 m3/day, equivalent to peak flow
of 0.97 m3/s, and
to be discharged to San Tin EPP for treatment. Space has been reserved for
potential upgrade to 55,875 m3/day to cater the additional
sewage flow from adjacent existing villages in the long term.
6.6.2
The land requirement
for the proposed on-site SPS with centrifugal pumps differs significantly from
wet well type and wet/dry well type installations. For land reservation
purposes, the required land should be estimated from the existing SPSs of
similar capacity. Table 6.7 and Table 6.8 below are derived from the land uptake of some existing SPSs. The land
required for the proposed SPS will be approximately 0.14 ha. The proposed
SPS will be located at Site G.1 which is of 0.37 ha. Location of the
proposed SPS is shown in Exhibit 6-1.
Table
6.7 Summary of Sewage Peak Flow designed
for the Proposed SPS
|
Pumping Capacity (m3/s)
|
Area (m2)
|
|
Not exceeding 0.15
|
400
|
|
0.15 每 0.35
|
400 每 900
|
|
0.35 每 1.00
|
900 每 1400
|
|
1.00 每 4.50
|
1400 每 2500
|
|
4.50 每 7.50
|
2500 每 4000
|
Table
6.8 Wet Well Arrangement
6.6.3 The sewage from the proposed SPS
will be pumped to San Tin EPP directly via a twin rising mains to be laid
across underneath existing roads (e.g. San Tin Highways, cycle track of Castle
Peak Road 每 Mai Po or San Tam Road) and end at San Tin EPP. The connection
level of the rising mains at San Tin EPP is subject to further coordination
with Drainage Services Department (DSD). A preliminary hydraulic assessment is
provided in Table 6.9.
Table 6.9
Preliminary Hydraulic Assessment of Rising Main
|
ADWF
(m3/day)
|
Peaking Factor
|
Peak Flow
(m3/s)
|
Pipe Size(1)
(DN) (mm)
|
Flow Velocity
(m3/s)
|
|
44,875
|
1.86
|
0.97
|
680
|
1.33
|
Note:
(1) Internal pipe diameter is
subjected to change of actual soil cover for the rising main, standard
dimension ratio of 13.6 is used for conservative design purpose
6.6.4 Based on the approved EIA report for
San Tin Technopole (STT) (Register No.: AEIAR-261/2024), the sewage generated
by STT would be approximately 98,700 m3/day. Taking into the
consideration of the sewage from the Project as well as sewage from
other nearby projects, there would be potential shortfall of design capacity of
San Tin EPP (i.e. larger than 125,000 m3/day), and thus the sewage
from the Project that could be delivered to San Tin EPP would be subject to the
residual capacity of the San Tin EPP. Subject to the detailed design stage of
the Project, in the event that the estimated sewage generation from the Project
exceeds San Tin EPP*s design capacity, other possible mitigation measures as
mentioned below should be considered.
6.6.5 Possible measures in mitigating the potential
shortfall in the long term could include the provision of another sewerage
network to allow sewage from the proposed on-site SPS to be diverted to the
existing Nam Sang Wai (NSW) SPS and ultimately to Yuen Long EPP, subject to
detailed design stage. Relevant technical studies for the associated
sewerage network will be reviewed in detailed design stage during which more
design/development information is available, and agreement will be sought on the
sewage quantity that needs to be diverted to NSW SPS.
6.6.6
As mentioned in Section
6.2.2, the sewage discharge from nearby existing villages would be
increased from 4,000 m3/day to ultimately 15,000 m3/day,
subject to further review in later stage. Therefore, the capacity of the
proposed on-site SPS will be potentially upgraded from 44,875 m3/day
to 55,875 m3/day, when the sewerage network is ready in future for
diverting the sewage generated from the nearby existing villages to the
proposed SPS. On top of 0.14 ha allowed for the proposed SPS mentioned in
Section 6.6.2, an additional land of 0.07 ha would be required for the
potential upgrade of capacity. The RODP has allowed 0.37 ha at Site G.1 to
serve sufficient flexibility for future upgrade to cater the sewage discharge
from the existing nearby villages.
6.6.7
The preliminary list of
responsible parties of the proposed sewerage and sewage treatment facilities is
shown in Table 6.10.
Table 6.10 Preliminary
List of Responsible Parties of the Proposed Sewerage and Sewage Treatment
Facilities
|
Sewerage/Sewage Treatment Facilities
|
Parties Responsible for Construction
|
Parties Responsible for Maintenance
|
|
SPS and twin rising mains
|
CEDD
(subject to review during detailed design stage)
|
DSD
(subject to review during detailed design stage)
|
6.7
Proposed Emergency Bypass
6.7.1
There will also be an emergency bypass discharged to NTM Drainage
Channel, and ultimately discharged to Deep Bay control zone. Location of the
proposed on-site SPS and the routing of emergency bypass are shown in Exhibit
6-1.

Exhibit 6-1
Proposed Location of SPS and Emergency Bypass Alignment
6.8
Implementation Phasing
6.8.1 The DRE site with population intake
in Year 2033 will have its own temporary sewerage arrangement and will
permanently connect to the proposed sewerage system of the Project in Year
2034. The full sewage discharge buildup is expected to be in Year 2036
for full population intake.
6.9
Potential Impacts by the Proposed Sewerage System
6.9.1
For the proposed SPS and rising mains serving Development Area, those
facilities have to be completed and commissioned early on the Development Area,
but it can be years before they receive the design flows from full occupancy of
the Development Area. This results in low flows entering the wet well and long
retention times in the rising mains give the opportunity for bacteria to
multiply in the anaerobic conditions in which formation of Hydrogen Sulphide
would occur.
6.9.2
Odour impact is one of the possible impacts generated from the operation
of the sewage system. The main odour nuisances can be attributed to the wet
wells/ retention tanks of the proposed SPS. Use of chemical dosing to oxygen
injection for septicity control should be considered in the detailed design.
6.10
Recommended Mitigation Measures
6.10.1
Sewage septicity control measures should be
considered for the proposed SPS and rising mains. Non-dosing solutions should
be considered prior to dosing solutions.
6.10.2
At this preliminary
stage, direct injection of oxygen into the rising mains and pre-aeration in the
wet well of the proposed SPS should be adopted as the sewage septicity control
measures with details to be addressed in the detailed design stage.
6.10.3 Enclosing the proposed SPS inside a building
structure is considered as an odour mitigation measure. The structure should be
equipped with adequate odour control measures such as scrubber and activated
charcoal filter at the exhaust of the ventilation system. The vent should be
located away from both existing and planned air sensitive uses as far as
practicable.
6.11
Conclusion
6.11.1
There is no existing
sewerage system near the Development Area. An on-site SPS with a
capacity of 44,875 m3/day, requiring 0.14 ha land, is proposed to
cater for the sewage generated from the Project including the operation of
future NOL Main Line (i.e. 504 m3/day, with 10% contingency) and the
existing villages (i.e. 4,000 m3/day) in initial stage.
Subject to residual capacity of San Tin EPP, the collected sewage could be
pumped from the proposed SPS to San
Tin EPP for treatment.
6.11.2
Since there will be a potential shortfall in the long term for the
sewage treatment capacity in San
Tin EPP, potential mitigation measure such as providing another sewerage
network to allow diversion of sewage from the proposed on-site SPS to NSW SPS
could be considered, subject to detailed design in the next stage of the
Project.
6.11.3
The sewage discharge from nearby existing villages would be increased
from 4,000 m3/day to ultimately 15,000 m3/day at the
proposed on-site SPS in the long term, subject to further review in later
stage. As such, the proposed on-site SPS would be further upgraded from
44,875 m3/day to 55,875 m3/day when need arises.
Space has been reserved at Site G.1 for the potential upgrade.
6.11.4 Sewage septicity control measures should be considered for the
proposed SPS and the associated sewerage system. Non-dosing solutions should be
considered prior to dosing solutions.
6.11.5
Based on the findings
of preliminary sewerage
impact assessment as described in this section, it is anticipated that the
proposed developments under the Project would be sustainable from sewerage
collection, treatment and disposal perspective, and thus there would be no
identified insurmountable sewerage and sewage treatment implications arising
from the Project.