Environmental
Permit No. EP-654/2024
環境許可證編號 EP-654/2024

ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
SECTION 10
環境影響評估條例
(第499章)
第10條
ENVIRONMENTAL PERMIT TO DECOMMISSION
A DESIGNATED PROJECT
解除運作指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to Section 10 of the Environmental Impact Assessment
Ordinance (EIAO), the Director of Environmental Protection (the Director)
grants this environmental permit to the
Castle
Peak Power Company Limited (hereinafter referred to
as the “Permit Holder”) to decommission the designated project described in Part
B subject to the conditions specified in Part C. The issue of this
environmental permit is based on the documents, approvals or permissions
described below:
根據《環境影響評估條例》(環評條例) 第10條的規定,環境保護署署長(署長)將本環境許可證批予青山發電有限公司(下稱 “許可證持有人” )以解除運作B部所說明的指定工程項目,但須遵守C部所列明的條件。本環境許可證的發出,乃以下表所列的文件、批准或許可作為根據﹕
|
Application No. 申請書編號 |
AEP-654/2024 |
|
Document in the Register: 登記冊上的文件: |
(1)
Project Profile – Decommissioning and
Demolition of the Castle Peak A Power Station (Register No. PP-675/2024) 工程項目簡介 – 青山發電A廠發電機組停用及拆卸工程 (登記冊編號:PP-675/2024) (2) The
Director’s letter of Permission to Apply Directly for Environmental Permit
dated 8 November 2024 (Reference: (23) in EP2/N4/PT2/148) 署長於2024年11月 8 日發出准許直接申請環境許可證的信件 (檔案編號:(23) in EP2/N4/PT2/148) (3) Application
for Environmental Permit submitted on 26 November 2024 (Application No. AEP-654/2024) 於2024年11月26日 提交的環境許可證申請文件 (申請書編號: AEP-654/2024) |
23 December 2024
2024年12月 23 日
|
Date 日期 |
|
(Ms Clara U) Principal
Environmental Protection Officer for Director of Environmental Protection 環境保護署署長 (首席環境保護主任余錦華代行) |
PART B (DESCRIPTION OF
DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the
designated project mentioned in Part A of this environmental permit (hereinafter referred to as the “Permit”):
下列為本環境許可證(下稱“許可證” )A部所提述的指定工程項目的說明﹕
|
Title of Designated Project 指定工程項目的名稱 |
Decommissioning and Demolition of the Castle Peak A Power
Station [This
designated project is hereafter referred to as “the Project”] 青山發電A廠發電機組停用及拆卸工程 [本指定工程項目下稱 “工程項目”] |
|
Nature of Designated Project |
Decommissioning of an
electricity power plant running on fossil fuel with a production capacity of
more than 100 megawatts (Item 4 of Part II of Schedule 2 of the EIAO). 解除生產能力超過100兆瓦特的、以化石燃料發電的電力廠的運作(環評條例附表2第II部第4項)。 |
|
Location of Designated Project 指定工程項目的地點 |
The Project is
located at Castle Peak A Power Station in Tuen Mun. The location of the
Project is shown in Figure 1
of this Permit. 工程項目位於屯門青山發電A廠。工程項目的位置載於本許可證圖1。 |
|
Scale and Scope of
Designated Project 指定工程項目的規模和範圍 |
The
Project mainly includes the decommissioning and demolition of four coal-fired
electricity generating units (each with a power generation capacity of 350
megawatts), boiler house, turbine hall, chimney stack and the associated equipment
and structures at the Castle Peak A Power Station. 工程項目主要包括解除運作和清拆4台燃煤發電機組(每台機組的發電量均為350兆瓦特)、鍋爐機樓、渦輪機大堂、煙囪,以及青山發電A 廠內的相關設備和結構物。 |
C部 (許可證條件)
1. General Conditions
一般條件
1.1 The Permit Holder and any person decommissioning
the Project shall comply with all conditions set out in this Permit. Any
non-compliance by any person may constitute a contravention of the Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) and may become the subject of
appropriate action being taken under the EIAO.
許可證持有人及任何解除工程項目運作的人士必須完全符合本許可證載列的全部條件。任何人士如有不符合本許可證的情況,可能違反《環境影響評估條例》(環評條例)(第499章)的規定,而當局可根據環評條例採取適當行動。
1.2 The Permit Holder and any person decommissioning the Project shall ensure full
compliance with all legislation from time to time in force including, without
limitation to, the Air Pollution Control Ordinance (Cap. 311), Noise Control Ordinance
(Cap. 400), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea
Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does
not of itself constitute any ground of defence against any proceedings
instituted under any legislation or imply any approval under any legislation.
許可證持有人及任何解除工程項目運作的人士須確保完全符合現行法例的規定,包括但不限於《空氣污染管制條例》(第311章)、《噪音管制條例》(第400章)、《水污染管制條例》(第358章)、《海上傾倒物料條例》(第466章)及《廢物處置條例》(第354章)。本許可證本身不會就根據任何法例提出的法律程序構成任何抗辯理由,或根據任何法例默示任何批准。
1.3 The Permit Holder shall make copies of
this Permit together with all documents referred to in this Permit and
the documents referred to in Part A of this Permit readily available at
all times for inspection by the Director or his authorised officers at all
sites covered by this Permit. Any reference to this Permit shall include all
documents referred to in this Permit and also the relevant documents in the
Register.
許可證持有人須印製本許可證的複本,連同本許可證所述的所有文件及本許可證A部所述文件,以供署長或獲授權人員任何時間內在本許可證所涵蓋的所有工地查閱。凡提述本許可證,須包括本許可證所述的所有文件及登記冊內的相關文件。
1.4 The Permit Holder shall give a copy of
this Permit to the person(s) in charge of the site(s) and ensure that such
person(s) fully understands all conditions and all requirements incorporated in this
Permit. The site(s) refers to site(s) of decommissioning of the Project and
shall mean the same hereafter.
許可證持有人須把本許可證的一份複本交予有關工地的負責人,並確保這些人士完全明白本許可證的所有條件與規定。工地是指解除運作工程項目的工地,下文所提及的工地亦屬同一意思。
1.5 The Permit Holder shall display
conspicuously a copy of this Permit on the Project site(s) at all vehicular
site entrances/exits or at a convenient location for public’s information at
all times. The Permit Holder shall ensure that the most updated information
about this Permit, including any amended Permit, is displayed at such
locations. If the Permit Holder surrenders a part or the whole of this
Permit, the notice he sends to the Director shall also be displayed at the same
locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the Project site(s).
許可證持有人須在工程項目的工地的所有車輛進出口或一處方便地點,顯眼地展示本許可證的複本,以供公眾在任何時間內閱覽。許可證持有人須確保在這些地點展示關於本許可證(包括任何經修訂的許可證)的最新資料。許可證持有人如交回本許可證的部分或全部,必須把其送交署長的通知書,在備有原有許可證的各處相同地點展示。遭暫時吊銷、更改或取消的許可證必須從工程項目的工地除下,不再展示。
1.6 The Permit Holder and any person decommissioning
the Project shall decommission the Project in accordance with the project
description in Part B of this Permit.
許可證持有人及任何解除工程項目運作的人士須依據本許可證B部的工程項目說明,解除工程項目的運作。
1.7 The Permit Holder and any person decommissioning
the Project shall ensure that the Project is decommissioned in
accordance with the information and recommendations described in the Project Profile (Register No.: PP-675/2024); the application document for environmental permit; other relevant documents in the Register;
the information and mitigation measures described in this Permit; mitigation
measures to be recommended in submissions that shall be deposited with or
approved by the Director as a result of permit conditions contained in this
Permit, and mitigation measures to be recommended under on-going surveillance
and monitoring activities during all stages of the Project. Where
recommendations referred to in the application documents of the Register are
not expressly referred to in this Permit, such recommendations are nevertheless
to be implemented unless expressly excluded in this Permit or otherwise agreed
by the Director.
許可證持有人及任何解除工程項目運作的人士須確保工程項目按照下述資料解除運作:工程項目簡介(登記冊編號:PP-675/2024)所說明的資料及相關建議;環境許可證的申請文件;登記冊內的其他相關文件;本許可證所說明的資料及緩解措施;根據本許可證所載的條件須提交予署長存放或獲署長批准的文件所建議的緩解措施;以及在工程項目各階段進行的持續監察及監測工作所建議的緩解措施。登記冊內的申請文件所述建議如沒有在本許可證明確表示,則仍須實施這些建議,除非獲本許可證明確豁除或另獲署長同意。
1.8 All
submissions, as required under this Permit, shall be rectified and resubmitted
in accordance with the comments, if any, made by the Director within one month
of the receipt of the Director’s comments or otherwise as specified by the
Director.
所有按本許可證規定提交的文件,須在接獲署長的意見(如有者)後1個月內或署長另行指定的期限內,根據署長的意見加以修正及重新提交。
1.9 All submissionsapproved by the
Director, all submissions deposited without comments by the Director, or all
submissions rectified in accordance with comments by the Director under this
Permit shall be construed as part of the permit conditions described in Part
C of this Permit. Any variation of the submissions shall be approved by the
Director in writing or as prescribed in the relevant permit conditions. Any
non-compliance with the submissions may constitute a contravention of the EIAO
(Cap. 499). All submissions or any
variation of submissions shall be certified by the Environmental Team Leader
and verified by the Independent Environmental Checker referred to in Conditions
2.1 and 2.2 below before submitting to the Director under this Permit.
所有提交署長並獲批准的文件、所有提交署長存放而沒有收到署長意見的文件或根據本許可證提交並已依照署長的意見作出修訂的所有文件,將詮釋為本許可證C部所說明的許可證條件的一部分。對提交文件所作的任何修訂,均須獲得署長的書面批准,或符合有關許可證條件所述。凡與所提交的文件有不符合的情況,均可能構成違反環評條例(第499章)。所有提交文件或提交文件的任何修訂本,均須按下文條件第2.1及2.2項所述的環境小組組長核證及獨立環境查核人核實,然後才按本許可證規定向署長提交。
1.10 The
Permit Holder shall release all finalised submissions as required under this
Permit to the public by depositing copies in the Environmental Impact Assessment
Ordinance Register Office, or in any other places, or any internet websites as
specified by the Director, or by any means as specified by the Director, for
public inspection. For this purpose, the Permit Holder shall provide sufficient
copies of the submissions.
許可證持有人須把所有按本許可證規定提交的文件定稿公開給公眾人士知道,方法是把有關文件複本存放於環境影響評估條例登記冊辦事處,或署長指定的任何其他地方,或署長指定的任何互聯網網站,或署長指定的任何方法,以供公眾查閱。為此,許可證持有人須提供足夠數量的複本。
1.11 The
Permit Holder shall submit and / or deposit all submissions within the time as
specified in the Conditions of this Permit. All submissions to the Director required under this Permit
shall be delivered either in person or by registered mail to the Environmental Impact
Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130
Hennessy Road, Wanchai, Hong Kong). Electronic copies of all finalised
submissions required under this Permit shall be prepared in Hyper Text Markup
Language (HTML) (version 4.0 or later) and in Portable Document Format (PDF
version 1.3 or later), unless otherwise agreed by the Director and shall be
submitted at the same time as the hard copies.
許可證持有人須在本許可證條件所列明的時間內,提交及/或存放所有文件。本許可證規定向署長提交的所有文件,須親身送交或以掛號方式郵寄至環境影響評估條例登記冊辦事處(現址為香港灣仔軒尼詩道130號修頓中心27樓)。所有按本許可證規定提交的文件定稿的電子複本,均須以超文本標示語言(HTML)(第4.0或較後版本)和便攜式文件格式(PDF)(第1.3或較後版本)製作,除非另獲署長同意,電子複本須與硬複本同時提交。
1.12 The Permit Holder shall
notify the Director in writing the commencement date of decommissioning of the
Projectno later
than one month prior to the commencement of decommissioning
of the Project. The Permit Holder shall notify the Director in writing
immediately if there is any change of the commencement date of the decommissioning
works.
許可證持有人須在解除運作工程展開前最少1個月,以書面方式把解除運作工程的展開日期通知署長。解除運作工程的展開日期如有任何更改,許可證持有人必須立即以書面方式通知署長。
1.13 For the purpose of this Permit,
“commencement of decommissioning” does not include works related to site
clearance and preparation, or other works as agreed by the Director.
為執行本許可證,「解除運作工程的展開」不包括有關工地清理和預備的工程或署長同意的其他工程。
2. Specific Conditions
特定條件
Establishment
of Environmental Team (ET)
成立環境小組
2.1
An ET shall be established by the Permit
Holder no later than one month before the commencement of decommissioning of
the Project. The ET shall not be in any way an associated body of
the Contractor or the Independent Environmental Checker (IEC) for the
Project. The ET shall be headed by an ET Leader. The ET
Leader shall be a person who has at least 7 years of experience in environmental
monitoring and audit (EM&A) or environmental management. The ET
and the ET Leader shall be responsible for duties defined in the Project Profile (Register
No.: PP-675/2024)
and this Permit, including the implementation of the EM&A programme described
in the Project
Profile (Register No.: PP-675/2024) and required under this Permit, and
the certification of the submissions required under this Permit.
許可證持有人須在工程項目的解除運作工程展開前最少1個月成立一個環境小組。環境小組不得與工程項目的承辦商或獨立環境查核人有任何關聯。環境小組須由一名環境小組組長帶領。該名環境小組組長須在環境監察及審核(“環監”)或環境管理方面至少有7年經驗。環境小組及環境小組組長須負責執行工程項目簡介(登記冊編號: PP-675/2024)及本許可證所列明的職責,包括實施工程項目簡介(登記冊編號: PP-675/2024)所說明及本許可證規定的環監計劃,以及核證本許可證所需提交的文件。
Employment of Independent Environmental
Checker (IEC)
聘用獨立環境查核人
2.2
An IEC shall be employed by
the Permit Holder no later than one month before the commencement of decommissioning of the
Project. The IEC shall not be in any way an associated body of
the Contractor or the ET for the
Project. The IEC shall be a person
who has at least 7 years of experience in EM&A or environmental
management. The IEC shall be responsible for duties defined
in the Project Profile (Register No. PP-675/2024) and this Permit, including
the audit of the implementation of mitigation measures recommended in the
Project Profile (Register No.: PP-675/2024) and required under this
Permit, and the verification of the submissions required under this
Permit.
許可證持有人須在工程項目的解除運作工程展開前最少1個月聘用一名獨立環境查核人。獨立環境查核人不得與工程項目的承辦商或環境小組有任何關聯。該名獨立環境查核人須在環監或環境管理方面至少有7年經驗。獨立環境查核人須負責執行工程項目簡介(登記冊編號: PP-675/2024)及本許可證所列明的職責,包括審核工程項目簡介(登記冊編號:PP-675/2024)所建議及本許可證規定的緩解措施的實施情況,以及核實本許可證所需提交的文件。
Submission of Dust Monitoring Plan
提交塵埃監測計劃
2.3
The Permit Holder shall, no
later than three months before the commencement of decommissioning works of the chimney (as shown in Figure 1), submit two hard copies and one
electronic copy of a Dust Monitoring Plan to the Director for approval. The
Dust Monitoring Plan shall include the details and reporting requirements of
the dust monitoring for the demolition works of the chimney. The Dust
Monitoring Plan shall be certified by the ET Leader and verified by the
IEC as conforming to the relevant
information and recommendations in the Project Profile (Register No. PP-675/2024)
before submitting to the Director under this Permit. The dust
monitoring and requirements recommended in the Dust Monitoring Plan shall be
fully and properly implemented.
許可證持有人須在煙囪(許可證圖1)的解除運作工程展開前最少3個月,向署長提交塵埃監測計劃的2份硬複本及1份電子複本,以供審批。塵埃監測計劃須包括就煙囪拆卸工程的塵埃監測細節及匯報要求。塵埃監測計劃須由環境小組組長核證及獨立環境查核人核實,證明符合工程項目簡介(登記冊編號:PP-675/2024)所載的相關資料及建議,然後才按本許可證規定向署長提交。塵埃監測計劃建議的塵埃監測及要求須徹底及妥善執行。
Submissions
for Land Contamination Assessment
提交土地污染評估的文件
2.4
To determine the
extent and level of land contamination and formulate necessary remedial measures at the Project site, the Permit Holder shall
comply with the following:-
為釐定工程項目工地的土地污染的程度及水平,並制訂所需的整治措施,許可證持有人須遵從以下事項:-
(i)
no later
than three months before the commencement of site investigation (SI) to
investigate the potentially contaminated areas at the Project site, submit two hard
copies and one electronic copy of a Supplementary Contamination Assessment Plan
(CAP) to the Director for approval. The
Supplementary CAP shall provide an updated sampling and testing schedule based
on the latest site condition;
許可證持有人須在工程項目潛在污染區域的場地勘察展開前最少3個月,向署長提交補充污染評估計劃書的2份硬複本及1份電子複本,以供審批。補充污染評估計劃書須就最新的工地情況,提供更新的採樣及測試時間表;
(ii)
no later
than two months after the completion of the SI in accordance with the
Supplementary CAP approved under Condition 2.4(i) of this Permit, submit two hard
copies and one electronic copy of a Contamination Assessment Report (CAR) to
the Director for approval. The CAR shall
document the findings of the SI works and assessment on the nature and extent
of land contamination;
許可證持有人須在根據本許可證條件第2.4(i) 項批准的補充污染評估計劃書進行的場地勘察完成後2個月內,把污染評估報告的2份硬複本及1份電子複本提交署長,以供審批。污染評估報告須載述土地污染調查工作的結果及就土地污染的性質及程度所作的評估;
(iii)
if land
contamination is confirmed, submit two hard copies and one electronic copy of a
Remedial Action Plan (RAP) to the Director for approval. The RAP shall formulate necessary remedial
measures. All remedial measures
described in the approved RAP shall be fully and properly implemented;
倘若土地證實受到污染,許可證持有人須把整治計劃書的2份硬複本及1份電子複本提交署長,以供審批。整治計劃書須制訂所需的整治措施。經批准的整治計劃書載述的所有整治措施必須徹底及妥善執行;
(iv)
if
remediation is required, deposit with the Director two hard copies and one
electronic copy of a Remediation Report (RR), no later than one month after the
completion of the remediation works. The RR shall provide details on
the remediation works carried out, types and volume of contaminated soil,
standards and levels of treatment, and locations of all on-site and off-site
disposal sites (including record of disposal);
如須進行整治工作,許可證持有人須在整治工作完成後1 個月內,向署長存放整治報告的2份硬複本及1份電子複本。整治報告須提供所進行的整治工作詳情、受污染泥土的類別及數量、處理標準及水平,以及所有工地內外棄置地點的位置(包括棄置紀錄);
(v)
no
excavation works at the potentially contaminated areas identified in the Supplementary
CAP shall be carried out prior to the approval of the CAR submitted under
Condition 2.4(ii) of this Permit, and, if remediation is required, deposition of
the RR under Condition 2.4(iv) of this Permit.
在根據本許可證條件第2.4(ii)項所提交的污染評估報告獲得批准之前,及在根據上述條件第2.4(iv)項存放整治報告(如果需要進行整治工作的話)之前,不得在補充污染評估計劃書中確定的潛在污染區域進行挖掘工程。
2.5
The Supplementary
CAP, CAR, RAP and RR (if any) shall be certified by the ET Leader and verified by
the IEC as conforming to the information and
recommendations contained in the Project Profile (Register No. PP-675/2024)
before submission to the Director.
補充污染評估計劃書、污染評估報告、整治計劃書及整治報告(如有者)在提交署長前,須由環境小組組長核證及獨立環境查核人核實,確定符合工程項目簡介(登記冊編號:PP-675/2024)內的相關資料及建議。
Measure to Minimise Fugitive Dust Impact
減少建築塵埃影響的措施
2.6
During the demolition works of the chimney, a top-down
demolition method shall be adopted. A
ring working platform around the top of the chimney with surrounding dust
screen erected shall be employed to minimise dust generation.
在進行煙囪的拆卸工程期間,應從上至下地進行拆卸工程。煙囪頂部須設置一個環形作業平台並圍繞搭建塵埃防護網以減少塵埃的產生。
Measure for Waste Management
廢物管理措施
2.7 All
dump trucks for waste transportation and disposal under the Project shall be
equipped with Global Positioning System or equivalent automatic identification
system for real time tracking and monitoring of their travel routings and
parking locations in order to avoid illegal dumping or landfilling of
construction and demolition materials.
工程項目所有用於運送和處置廢物的泥頭車,均須配備全球衞星定位系統或同等的自動識別系統,以實時追蹤及監察泥頭車的行車路線及泊車地點,防止非法棄置或堆填建築和拆卸物料。
3 Environmental Monitoring and Audit (EM&A) Requirements
環境監察及審核規定
3.1
The EM&A programme shall be implemented in
accordance with the procedures and requirements as set out in the EM&A
requirements described in the Project Profile (Register No.: PP-675/2024). Any
changes to the EM&A requirements or programme shall be justified by
the ET Leader and verified by the IEC as conforming to the relevant information
and requirements set out in the EM&A requirements described in the
Project Profile (Register No.: PP-675/2024) before submission to the
Director for approval.
環監計劃須按工程項目簡介(登記冊編號: PP-675/2024)的環監規定內所載的程序和規定執行。環監規定或計劃如有更改,須由環境小組組長提出充分理據,並由獨立環境查核人核實,證明其符合工程項目簡介(登記冊編號: PP-675/2024)的環監規定內所載的資料及規定,並須事先獲署長批准,方可執行。
3.2
The Permit Holder
shall submit two hard copies and one electronic copy of the Monthly EM&A
Reports for the Project to the Director, within 10 working days after the end
of the reporting month. The monthly EM&A Reports shall include an
executive summary of all environmental audit results, together with
actions taken in the event of non-compliance (exceedances) of the
environmental quality performance limits (Action and Limit Levels), complaints
received and emergency events relating to violation of environmental
legislation. The submissions shall be certified by the ET Leader and verified
by the IEC as having complied with the EM&A requirements as set out in Project
Profile (Register No.: PP-675/2024) before submission to the Director.
Additional copies of the Monthly EM&A Reports shall be provided upon
request by the Director.
在每個提交報告的月份結束後10個工作天內,許可證持有人須向署長提交工程項目每月環監報告的2份硬複本及1份電子複本。每月環監報告須包括各項環境審核結果,以及在發生不符合(超出)環境質素表現規限(行動及極限水平)情況時所採取的行動、接獲有關違反環境法例的投訴及發生相關緊急事件的行政摘要。提交的報告須由環境小組組長核證及獨立環境查核人核實,證明其符合工程項目簡介(登記冊編號: PP-675/2024)的環監規定內所載的相關規定,然後才提交署長。如署長要求,則須向署長提交每月環監報告的額外複本。
Notes:
註:
1. This Permit consists of three parts,
namely, Part A (Main Permit), Part B (Description of Designated
Project) and Part C (Permit Conditions).
Any person relying on this Permit should obtain independent legal advice
on the legal implications under the EIAO, and the following notes are for
general information only.
本許可證共有3部,即 A部 (許可證主要部分);B部(指定工程項目的說明) 及C部(許可證條件)。任何援引本許可證的人士須就環評條例的法律含意徵詢獨立法律意見,下述註解只供一般參考用。
2. If there is a breach of any condition
of this Permit, the Director or his authorised officer may, with the consent of
the Secretary for Environment and Ecology,
order the cessation of associated work until the remedial action is taken in
respect of the resultant environmental damage, and in that case the Permit
Holder shall not carry out any associated works without the permission of the
Director or his authorised officer.
如違反本許可證的任何條件,署長或獲授權人員徵得環境及生態局局長的同意後可勒令停止相關工程,直至許可證持有人為所造成的環境損害採取補救行動為止。在此情況下,許可證持有人未經署長或獲授權人員同意,不得進行任何相關工程。
3. The Permit Holder may apply under
Section 13 of the EIAO to the Director for a variation of the conditions of
this Permit. The Permit Holder shall replace the original permit displayed on
the Project site by the amended permit.
許可證持有人可根據環評條例第13條的規定向署長申請更改本環境許可證的條件。許可證持有人須以經修改的許可證替換在工程項目工地內展示的原有許可證。
4. A person who assumes the responsibility
for the whole or a part of the Project may, before he assumes responsibility of
the Project, apply under Section 12 of the EIAO to the Director for a further
environmental permit.
承擔工程項目整項或部分工程的責任的人,在承擔責任之前,可根據環評條例第12條的規定向署長申請新的環境許可證。
5. Under Section 14 of the EIAO, the
Director may with the consent of the Secretary
for Environment and Ecology, suspend, vary or cancel this Permit. The
suspended, varied or cancelled Permit shall be removed from display at the
Project site.
根據環評條例第14條的規定,署長可在取得環境及生態局局長的同意下暫時吊銷、更改或取消本許可證。遭暫時吊銷、更改或取消的許可證必須從工程項目工地除下,不再展示。
6. If this Permit is cancelled or
surrendered during decommissioning of the Project, another environmental permit
must be obtained under the EIAO before the Project could be continued. It is an offence under Section 26(1) of the
EIAO to decommission a designated project listed in Part II of Schedule 2 of
the EIAO without a valid environmental permit.
如果本許可證在工程項目解除運作期間取消或交回,則在繼續進行工程項目之前,必須先根據環評條例規定取得另一份環境許可證。根據環評條例第26(1)條的規定,任何人在沒有有效環境許可證的情況下解除運作環評條例附表2第2部所列明的指定工程項目,即屬犯罪。
7. Any person who decommissions the
Project contrary to the conditions in this Permit, and is convicted of an
offence under the EIAO, is liable:
(i)
on a first conviction on indictment to a fine of $2 million
and to imprisonment for 6 months;
(ii)
on a second or subsequent conviction on indictment to a fine
of $5 million and to imprisonment for 2 years;
(iii)
on a first summary conviction to a fine at level 6 and to
imprisonment for 6 months;
(iv)
on a second or subsequent summary conviction to a fine of
$1 million and to imprisonment for 1 year; and
(v)
in any case where the offence is of a continuing nature,
the court or magistrate may impose a fine of $10,000 for each day on which he
is satisfied the offence continued.
如任何人在違反本許可證的條件下解除運作工程項目,且被裁定觸犯環評條例所訂明的罪行,即屬犯罪:
(i)
一經循公訴程序首次定罪,可處罰款200萬元及監禁6個月;
(ii)
一經循公訴程序第二次或其後每次定罪,可處罰款500萬元及監禁2年;
(iii)
一經循簡易程序首次定罪,可處第6級罰款及監禁6個月;
(iv)
一經循簡易程序第二次或其後每次定罪,可處罰款100萬元及監禁1年;以及
(v)
在任何情況下如該罪行屬持續性質,法院或裁判官可就其信納該罪行持續的每天另處罰款10,000元。
8. The Permit Holder may appeal against
any condition of this Permit under Section 17 of the EIAO within 30 days of
receipt of this Permit.
許可證持有人可在接獲本許可證後30天內,根據環評條例第17條就本許可證的任何條件提出上訴。
9. The Notes are for
general reference only and that the Permit Holder should refer to the EIAO for
details and seek independent legal advice.
上述註解只供一般參考用,欲知有關詳情,許可證持有人須參閱環評條例及徵詢獨立法律意見。
Environmental Permit No. EP-654/2024
境許可證編號 EP-654/2024
| Figure 1 |