Client logo(s) —>

 

Upgrading of Ting Kok Road      

Pumping Station No. 5

 

Photograph(s) —>

 

 

Ninth Quarterly EM&A Report

(January – March 2008)

 

April 2008

Report no: 01284R0761

 

 

 

 

 

Hyder Consulting Ltd

COI Number 126012

47th Floor, Hopewell Centre, 183 Queens Road East, Wanchai, Hong Kong

Tel: +852 2911 2233 Fax: +852 2805 5028 www.hyderconsulting.com

Joint Venture or Associate logo(s) —>

 

 

 

 

Client logo(s) —>

 

Upgrading of Ting Kok Road

Pumping Station No. 5

 

 

 

Ninth Quarterly EM&A Report 

(January– March 2008)

 

 

Author:

Amy Bowker

 

 

Checker:

Alexi Bhanja

 

 

Approver:

Guiyi Li

 

 

 

 

Report no:

EA01284R0761

 

 

Date:

April 2008

 


This report has been prepared for
 in accordance with the terms and conditions of Maeda Corporation appointment for the Upgrading of Ting Kok Road Pumping Station No. 5 in October 2006. Hyder Consulting Ltd (Incorporated in Hong Kong with limited liability – COI Number 126012) cannot accept any responsibility for any use of or reliance on the contents of this report by any third party.

 

 

 

Certified by Landfill Gas Team Leader

Alexi Bhanja

 

 


Contents

1        Executive Summary............................................................................................................ 1

2        Introduction........................................................................................................................ 18

2.1      Basic Project Information................................................................................................ 19

2.2      Management Structure and Project Organisation........................................................... 26

2.3      Construction Programme............................................................................................... 35

2.4      Works Undertaken during the Quarter........................................................................... 37

3        Environmental Status...................................................................................................... 45

3.1      Works Undertaken during the Quarter with Illustrations.................................................. 46

3.2      Project Area and Monitoring Locations.......................................................................... 48

4        Brief Summary of EM&A Requirements.................................................................... 62

4.1      Monitoring Parameters.................................................................................................. 63

4.2      Monitoring Equipment.................................................................................................... 65

4.3      Event and Action Levels/Plans...................................................................................... 70

4.4      Mitigation Measures & Requirements in Contract Documents......................................... 78

5        Implementation Status of LFG Control Measures................................................ 81

6        Monitoring Results.......................................................................................................... 83

6.1      Fixed Location  MH3..................................................................................................... 85

6.2      Variable Locations......................................................................................................... 95

7        Report on Non-Compliance and Complaints......................................................... 98

8        Others................................................................................................................................. 102

8.1      Future Key Issues....................................................................................................... 103

8.2      Comments, Recommendations and Conclusions.......................................................... 113

 

List of Tables

Table 2-1            Contact Details for Key Project Personnel                                                      2

Table 3-2            Fixed Monitoring Locations for LFG EM&A                                                    3

Table 4-3            Equipment List for LFG Monitoring                                                                 4

Table 4-4            Action and Limit Levels and Action Plan for Landfill Gas                                 4

Table 6-5            Monitoring Results at MH3                                                                             5

 

List of Appendices

                         Appendix 1    Project Organisation

                         Appendix 2    Construction Programme

                         Appendix 3    Location of Works and Project Area

Appendix 4    Fixed Monitoring Locations

Appendix 5    Updated Implementation Schedule

Appendix 6    Calibration Records

Appendix 7    Field Measurement Recording Sheets

 

 


1                                Executive Summary

Drainage Services Department awarded the contract for the Upgrading of Ting Kok Road Pumping Station No. 5 to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas (LFG) Team during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.

This report recorded the results and findings of the January to March 2008. All relevant mitigation measures and requirements were implemented. There have been no exceedances in Action/Limit (A/L) Levels at of the locations monitored under the EM&A programme.

An 11m-deep borehole, designated “M1”, was installed by the Contractor to provide an “early warning” of potential LFG problems that could affect surface trenches, but does not form part of the EM&A programme. The Contractor has noted the monitoring results from M1 and will take them into consideration when planning surface trench works in the vicinity.

However, as works have progressed, Borehole M1 now clashes with boundary wall construction and so was dismantled on 30 August 2007. It is not proposed to replace Borehole M1 since its purpose was only to provide an early warning of potential LFG problems for surface trench works, which are now almost complete. Besides, as advised by the Contractor, future construction will not involve excavation of more than 3 m.  Therefore, monitoring at Manhole M3 will serve the purpose for dismantle of Borehole M1. As Borehole M1 did not form part of the EM&A programme, there is no impact to the effectiveness of the EM&A programme now that Borehole M1 has been dismantled.

Manhole M2 was dismantled in July 2006 because of planned works and therefore monitoring at M2 has been terminated since July 2006.  However, LFG has never been detected at M2 and so it is not considered that termination of monitoring at this location will have any significant impact on the overall effectiveness of the environmental monitoring programme, as monitoring at manhole M3 will continue.

As works have progressed, connection of gravity sewer to the new pumping system is completed in Ting Kok Road.  As such, the existing pump pit, together with the fixed monitoring location M3 was demolished in December 2007.   A manhole MH3 (approximately 4m depth and 3m next to M3) of the new system has been constructed to be the alternative monitoring station to serve the same purpose of M3. 

EPD conducted site inspection on 10 March 2007, no inspections were carried out in January or February. General inspection on site condition was conducted for the inspection. No adverse comment was given.

Event and Action Levels

The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. For methane, A/L Levels are 0.5%/1.0%; for carbon dioxide, A/L Levels are 0.5%/1.5%; and for oxygen, A/L Levels are 19.0%/18.0%.

Complaint Log

There were no non-compliances during the reporting period and no complaints regarding LFG were received.

Reporting Changes

There have been no reporting changes during the reporting period.

Future Key Issues

Based on anticipated construction activities for the next quarter, on the construction programme and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.


2                                Introduction

2.1                         Basic Project Information

Upgrading of Ting Kok Road Pumping Station No. 5 (TKRPS) under North District and Tolo Harbour Sewerage, Sewage Treatment and Disposal – High Priority Works is implemented based on the findings of the Study Review of North District and Tolo Harbour Sewerage Master Plan.

The purpose of the Project is to upgrade the existing TKRPS to cope with the sewerage needs of both existing and future developments along Ting Kok Road up to Tai Mei Tuk. The design pumping capacity of TKRPS has to be increased from 2,888m3/day to 11,520m3/day in order to serve the increasing sewage flow along Ting Kok Road. The Project is of high priority and needs to commence as soon as possible because full commissioning of the upstream sewerage facilities along Ting Kok Road is dependent on the completion of this Project.

The proposed scope of works includes construction of a new pumping station, laying of about 350m long twin 450mm diameter rising mains and 250m long 600mm diameter gravity sewer, and demolition of the existing pump pit. The main pumping station, transformer room, gravity sewers, manholes and boundary wall (except the twin rising mains) will be located outside the existing passive vent trench of Shuen Wan Landfill and the three existing Landfill Gas (LFG) monitoring probes within the Project site will not be affected by the works.

There are six village houses located about 60m away from the boundary of the proposed pumping station. The proposed pumping station upgrading works therefore constitutes a Designated Project under type F.3(b)(i) in Schedule 2 of the Environmental Impact Assessment Ordinance. A Project Profile (PP) for direct application of the Environmental Permit (EP) (Application No.DIR-115/2005) was approved by the Environmental Protection Department (EPD) in March 2005 and an EP (EP-212/2005) was granted in April 2005, prior to the commencement of the upgrading works.

Drainage Services Department awarded the contract for the upgrading of TKRPS to Maeda Corporation in September 2005. Maeda appointed Hyder Consulting Limited as the Contractor’s Landfill Gas Team (LGT) during the construction period. The construction contract commenced in September 2005 and the total construction period is approximately 28 months.

Close proximity of the Project to Shuen Wan Landfill (within the 250m Consultation Zone of Shuen Wan Landfill) may also suggest the possibility of landfill gas being released during excavation works for substructure of pumping station, transformer room and associated rising mains and gravity sewers. As such, a Report on Landfill Gas Hazard Assessment has been prepared previously (as Appendix E to the PP) in accordance with EPD’s Landfill Gas Hazard Assessment Guidance Note and the Practice Note for Professional Persons – Landfill Gas Hazard Assessment for Development Adjacent to Landfills.

2.2                         Management Structure and Project Organisation

The Engineer (DSD) is responsible for overseeing the construction works and ensuring that they are undertaken by the Contractor (Maeda) in accordance with the specification and contractual requirements. The Contractor shall report to the Engineer. The LGT is employed by the Contractor and responsible for conducting the EM&A programme. The IC(LG) shall advise the Engineer on LFG issues related to the Project.

The key personnel contact names and telephone number are summarised in Table 2-1. The project organisation is shown in Appendix 1.

Party

Position

Name:

Tel. No.:

Project Proponent – DSD

Project Manager

Raymond LEE

2594 7457

Engineer’s Representative

Tim TSOI

2594 7460

Contractor – Maeda

Site Agent

George CHEUNG

9268 1918

LGT – Hyder Consulting

LGT Leader

Alexi BHANJA

2911 2916

IC(LG) –CH2M HILL

IC(LG)

Adlex LEE

2507 2203

Table 2-1        Contact Details for Key Project Personnel

2.3                         Construction Programme

Construction programme of the Project is attached in Appendix 2. As can be seen, all works carried out during the reporting period have been carried out with the required LFG control measures (e.g. LFG monitoring for “hot works”).

2.4                         Works Undertaken during the Quarter

Works undertaken during the reporting period included:

§            Concrete carriageway;

§            Construction of boundary wall;

§            Grouting of existing disused pipes;

§            Demolition of existing pump pit; and

§            Modification of chequer plate.

 

3                                Environmental Status

3.1                         Works Undertaken during the Quarter with Illustrations

Works undertaken during the reporting period are identified in Section 2.4. Illustrations of these works, such as location of works, etc., are provided in Appendix 3.

3.2                         Project Area and Monitoring Locations

The site is located at Ting Kok Road in Tai Po, and the major items to be constructed are located outside the existing passive vent trench of the adjacent Shuen Wan Landfill, which has been restored and is currently being monitored.

The impact monitoring locations specified in the Report on Landfill Gas Hazard Assessment comprise “utilities’ manholes and chambers” (i.e. fixed locations for purposes of environmental protection) and at excavations of 1m depth or more (i.e. variable locations for purposes of worker safety).

An 11m-deep borehole, designated “M1”, was installed by the Contractor (in addition to contract requirements) to provide an “early warning” of potential LFG problems that could affect surface trenches. It is not intended that M1 forms part of the EM&A programme, since conditions deep below the surface do not fall within the scope of the EM&A programme (i.e. manholes and excavations >1m).

However, as works have progressed, Borehole M1 now clashes with boundary wall construction and so was dismantled on 30 August 2007. It is not proposed to replace Borehole M1 since its purpose was only to provide an early warning of potential LFG problems for surface trench works, which are now almost complete. Besides, as advised by the Contractor, future construction will not involve excavation of more than 3 m.  Therefore, monitoring at Manhole M3 will serve the purpose for dismantle of Borehole M1. As Borehole M1 did not form part of the EM&A programme, there is no impact to the effectiveness of the EM&A programme now that Borehole M1 has been dismantled.

In terms of fixed monitoring locations, the Baseline Report identified two existing manholes (M2 and M3). Manhole M2, however, was dismantled in July 2006 because of planned works and therefore monitoring at M2 has been terminated since July 2006.  LFG has never been detected at M2 and so it is not considered that termination of monitoring at this location will have any significant impact on the overall effectiveness of the environmental monitoring programme, as monitoring at manhole M3 will continue. There are no other suitable manholes within the site that can be monitored in lieu of M2.

As works have progressed, connection of gravity sewer to the new pumping system is completed in Ting Kok Road.  As such, the existing pump pit, together with the fixed monitoring location M3 was demolished in December 2007.   A manhole MH3 (approximately 4m depth and 3m next to M3) of the new system has been constructed to be the alternative monitoring station to serve the same purpose of M3. 

In terms of variable monitoring locations, these vary from month to month, depending on site activities. The fixed monitoring location is shown in Table 3-2:

Monitoring Station ID

Description

Purpose

M3

Existing Manhole (3m deep)

EM&A programme

MH3

Constructed Manhole (4m deep)

EM&A programme

Table 3-2        Fixed Monitoring Locations for LFG EM&A

 

Project area is shown in Appendix 3 and the fixed monitoring locations are shown in Appendix 4.

4                                Brief Summary of EM&A Requirements

4.1                         Monitoring Parameters

During the construction phase, impact monitoring of LFG is to be carried out in accordance with the Report on Landfill Gas Hazard Assessment at the selected locations. LFG parameters to be monitored comprise oxygen, methane and carbon dioxide. Temperature is also recorded but this is not a LFG parameter.

4.2                         Monitoring Equipment

Table 4-3 shows the equipment list for LFG monitoring.

Equipment

Manufacturer / Serial Nos.

GFM410

GAS DATA LTD / 10239

Table 4-3        Equipment List for LFG Monitoring

4.3                         Event and Action Levels/Plans

The baseline monitoring results documented in the baseline monitoring report for the Project (our report ref.: EA01284R0022) provided the Action and Limit (A/L) Levels for LFG impact monitoring and also the Action Plan. As per the Report on Landfill Gas Hazard Assessment, and in keeping with the standard presentation of LFG EM&A in other projects, both the A/L Levels and Action Plan are shown in the same table.

Table 4-4 shows the combined A/L Level and Action Plan for the Project, to be triggered if the LFG criteria are exceeded at fixed locations M2 or MH3, or at any of the variable locations:


Parameter

A/L Level

Action Plan

Oxygen

<19%

         Ventilate to restore oxygen to > 19%

<18%

         Stop works

         Evacuate personnel/prohibit entry

         Increase ventilation to restore oxygen to >19%

Methane

>10% LEL

(i.e. > 0.5 % by volume)

         Prohibit hot works

         Ventilate to restore methane to < 10% LEL

> 20% LEL

(i.e. > 1% by volume)

         Stop works

         Evacuate personnel/prohibit entry

         Increase ventilation to restore methane to < 10% LEL

Carbon Dioxide

>0.5%

         Ventilate to restore carbon dioxide to <0.5%

>1.5%

         Stop works

         Evacuate personnel/prohibit entry

         Increase ventilation to restore carbon dioxide to >0.5%

Table 4-4        Action and Limit Levels and Action Plan for Landfill Gas

4.4                         Mitigation Measures & Requirements in Contract Documents

Measures for mitigating LFG hazards during the construction works have been stated clearly in the Report on Landfill Gas Hazard Assessment, which forms part of the contract documents Specification. Relevant excerpts could be referred to the Project Profile for Upgrading of Ting Kok Road Pumping Station No. 5.

Section 5 and Appendix 5 summarise the mitigation measures and requirements as well as the implementation status.

5                                Implementation Status of LFG Control Measures

The status of the mitigation measures implemented by the Contractor is listed in Appendix 5. All LFG hazard control measures have been implemented as stipulated in the contract documents and in the Report on Landfill Gas Hazard Assessment.

6                                Monitoring Results

Calibration records for the equipment used for LFG monitoring are provided in Appendix 6. Original Field Measurement Recording Sheets for both fixed locations and variable locations are provided in Appendix 7.

6.1                         Fixed Location  MH3

During the reporting period, LFG was monitored at the fixed location MH3 for purposes of environmental protection. This is shown in Table 6-5, below:

Monitoring Station ID

Date

Gas Concentration (%)

Temperature (OC)

Methane

Carbon Dioxide

Oxygen

MH3

29 January 2008

0.0

0.0

20.9

10.0

0.0

0.0

20.9

10.0

MH3

28 February 2008

0.0

0.0

20.6

11.0

0.0

0.0

20.6

11.5

MH3

27 March 2008

0.0

0.0

23.0

23.0

0.0

0.0

23.5

23.5

Note : bold indicates an exceedance of Action Level and bold indicates  exceedance of Limit Level

Table 6-5        Monitoring Results at MH3

 

Appendix 4 shows the position of each fixed monitoring station. There were no exceedances of A/L Levels at the two fixed locations during the reporting period.

6.2                         Variable Locations

During the reporting period, LFG was monitored at variable locations (for purposes of worker safety) within Portions 4 to 7, as shown in Appendix 3. Readings were taken for safety-related reasons, including piling works, trench excavation, hot works, post-drilling work and the construction of the temporary drainage system.

A total of 120 nos. of readings were taken in January 2008, 78 nos. of readings in February 2008 and 102 nos. of readings in March 2008, giving a total of 300 for the reporting period. There were no exceedances of A/L Levels at any variable locations during the reporting period. The LFG monitoring results are provided on the Field Measurement Recording Sheets in Appendix 7.

7                                Report on Non-Compliance and Complaints

EPD conducted a on 10 March 2008, there were no site inspections carried out in January and February in the reporting period. General inspection on site condition was conducted for the site inspection. No adverse comment was given. 

There were no non-compliances during the reporting period and no complaints regarding LFG were received.

 

8                                Others

8.1                         Future Key Issues

Construction activities for next quarter are anticipated to include:

§            Landscaping;

§            Extension of Cat ladder; and

§            Concrete carriageway.

Based on the above, on the construction programme (shown in Appendix 2) and on the review of relevant Contractor’s method statements by the LGT, no significant future key issues in terms of LFG have been identified at this time.

LFG monitoring will be continued and the monitoring schedule for the next three months is shown below:

§            1 April 2008

§            1 May 2008

§            1 June 2008

8.2                         Comments, Recommendations and Conclusions

The LFG mitigation measures adopted by the Contractor during the reporting period are considered to have been implemented in a satisfactory manner and there have been no exceedance of A/L Levels.

The EM&A programme is considered to have performed acceptably and there are no recommendations for improvements or modifications at this time.

In conclusion, there have been no significant issues relating to LFG hazard during the reporting period.

 



Appendix 1

Project Organisation

 


 

Project Proponent

Drainage Services Department

Contractor

Maeda Corporation

Landfill Gas Team

Hyder Consulting Limited

Landfill Gas (Independent Checker)

CH2M-HILL

Environmental Protection Department

Line of communication

Line of Authority

 



Appendix 2

Construction Programme

Appendix 3

Location of Works and Project Area

 

 

 

 

 

 

 

 

 

 

 

Appendix 4

Fixed Monitoring Locations

 

 

 

 

 

 

 

 

 

 

 

Appendix 5

Updated Implementation Schedule

 

 

 

 

 

 

 

 

 

 

 

Appendix 6

Calibration Records

 

 

 

 

 

 

 

 

 

 

 

Appendix 7

Field Measurement Recording Sheets