Content


Chapter    Title                                                                                                                           Page

1.1              Background_________________________________________________________________ 1

1.2              Project Organisation___________________________________________________________ 2

1.3              Works Undertaken in the Reporting Month__________________________________________ 2

2.1              Summary of EM&A Requirements_________________________________________________ 5

2.2              Implementation of Environmental Mitigation Measures_________________________________ 5

3.1              Monitoring Parameters, Frequency and Duration_____________________________________ 6

3.2              Monitoring Location____________________________________________________________ 6

3.3              Monitoring Equipment__________________________________________________________ 6

3.4              Equipment Calibration_________________________________________________________ 7

3.5              Monitoring Methodology________________________________________________________ 7

3.5.1           Field Monitoring______________________________________________________________ 7

3.5.2           Maintenance and Calibration____________________________________________________ 7

3.6              Results of Impact Monitoring_____________________________________________________ 8

4.1              Site Inspections______________________________________________________________ 9

4.2              Environmental Meetings________________________________________________________ 9

4.3              Status of Environmental Submissions, Permits and Licences___________________________ 9

4.4              Advice on the Solid and Liquid Waste Management Status_____________________________ 10

4.5              Review of Environmental Monitoring Procedures____________________________________ 10

4.6              Implementation Status of Environmental Mitigation Measures__________________________ 10

5.1              Non-compliance of Action and Limit Levels_________________________________________ 11

5.2              Environmental Complaints_____________________________________________________ 11

5.3              Notifications of Summons and Successful Prosecutions______________________________ 11

6.1              Construction Programme for the Next Reporting Month________________________________ 12

6.2              Key Issues for the Next Reporting Month___________________________________________ 12

6.2.1           Air________________________________________________________________________ 12

6.2.2           Noise_____________________________________________________________________ 12

6.2.3           Water Quality________________________________________________________________ 13

6.2.4           Waste_____________________________________________________________________ 13

6.2.5           Ecology____________________________________________________________________ 13

6.2.6           Landscape and Visual________________________________________________________ 13

6.3              Monitoring Schedule for the Next Reporting Month___________________________________ 13

7.1              Conclusions________________________________________________________________ 14

7.2              Recommendations___________________________________________________________ 14

Appendices                                                                                                                               15

Appendix A.  Construction Works Programme_________________________________________________ 16

Appendix B.  Project Organisation Chart for Section 4___________________________________________ 17

Appendix C.  Environmental Quality Performance Limits_________________________________________ 18

Appendix D.  Event and Action Plans________________________________________________________ 19

Appendix E.  Schedule of Mitigation Measures from the EIA Report and EM&A Manual__________________ 21

Appendix F.  EM&A Schedule_____________________________________________________________ 33

Appendix G.  Calibration Certificates________________________________________________________ 34

Appendix H.  Noise Monitoring Results and Graphical Presentation________________________________ 35

Appendix I.   Monthly Waste Flow Table______________________________________________________ 37

Appendix J.   Complaint Log______________________________________________________________ 39

Appendix K.  Weather Information from Hong Kong Observatory___________________________________ 40

 

Figures

Figure 1.1:_ General Layout Plan_ 3

Figure 1.2:_ Location of Secondary Boundary Fence and Noise Monitoring Station at Section 4_ 4

 

Tables

Table 2.1:__ Summary of EM&A Impact Requirements_ 5

Table 3.1:__ Noise Monitoring Parameters, Frequency and Duration_ 6

Table 3.2:__ Noise Impact Monitoring Location_ 6

Table 3.3:__ Noise Monitoring Equipment 7

Table 3.4:__ Noise Monitoring Equipment Calibration Frequencies_ 7

Table 3.5:__ Results of Noise Impact Monitoring_ 8

Table 4.1:__ Summary of Environmental Site Inspections_ 9

Table 4.2:__ Status of Environmental Submissions, Permits and Licences_ 10

Table 4.3:__ Environmental Submissions Made under the Valid EP & FEP(s) during the Reporting Month_ 10

Table 4.4:__ Implementation Schedule of Mitigation Measures_ 10

Table C.1:__ Action and Limit Levels for Construction Noise_ 18

Table D.1:__ Event and Action Plan for Construction Noise_ 19

Table E.1:__ Recommended Mitigation Measures – Air Quality 21

Table E.2:__ Recommended Mitigation Measures – Noise_ 23

Table E.3:__ Recommended Mitigation Measures – Water Quality 24

Table E.4:__ Recommended Mitigation Measures – Waste Management 26

Table E.5:__ Recommended Mitigation Measures – Ecology 28

Table E.6:__ Recommended Mitigation Measures – Landscape and Visual 29

Table I.1:__ Monthly Summary Waste Flow Table for 2010_ 37

Table I.2:__ Monthly Summary Waste Flow Table for 2011_ 38

Table J.1:__ Complaint Log for the Reporting Month (January 2011) 39

 


Executive Summary


Mott MacDonald Hong Kong Limited (MMHK) has been commissioned by the Architectural Services Department (ArchSD) as the Environmental Team (ET) to carry out Environmental Monitoring and Audit (EM&A) services for the construction of a secondary boundary fence (SBF) at Section 4 along the boundary in the Frontier Closed Area (FCA).

This is the 8th Monthly EM&A Report for the works carried out during the reporting month from 1 to 31 January 2011, and presents a summary of the environmental monitoring and audit works, list of activities, and mitigation measures implemented during the abovementioned reporting month.

Site Activities

The following major construction activities took place during the reporting month:

Works Order No. 1 (ASD 010962):

¡      No major works. (Substantial completion was certified on 12 October 2010.)

Works Order No. 2 (ASD 010969):

¡      Tree pruning work;

¡      Installation of transparent panel for the new boundary fence;

¡      Construction of footing for the new boundary fence;

¡      Construction of steel frame and mesh for the new boundary fence;

¡      Excavation works for footing of steel fence;

¡      Reinstatement of pavement and carriageway; and

¡      Construction of footing for the new pedestrian gate.

Works Order No. 3 (ASD 010974):

¡      Erection of hoarding for the new check point;

¡      Construction of stud wall and retaining wall at the new check point site; and

¡      Construction of footing and super-structural works at the new check point site.

Breach of Action and Level Limits

There was no breach of Action or Limit levels for noise level (measured as Leq) in the reporting month.

Complaints

There was no record of complaints received in the reporting month.

Notification of Summons and Successful Prosecutions

There was no record of Notification of summons and successful prosecution in the reporting month.

Reporting Changes

There are no reporting changes in the reporting month.

Future Key Issues

Future key issues to be considered in the forthcoming month include:

Air

¡      Regular maintenance of all plant and equipment;

¡      Handling of any excavated dusty materials or stockpile of dusty materials;

¡      Spraying of water prior to any loading, unloading or transfer of dusty materials; and

¡      Washing of vehicles before leaving the construction sites.

Noise

¡      Location of noisy equipment and noisy activities relative to the Noise Sensitive Receivers (NSRs);

¡      Avoiding the operation of unused equipment, and minimising the use of Powered Mechanical Equipment (PME) and parallel use of noisy equipment / machinery;

¡      Adoption of Level 1 site-specific direction mitigation measures (use of quiet plant and movable noise barrier) for construction/demolition work undertaken at a distance of 60m or less to the NSRs; and

¡      Regular maintenance of all plant and equipment.

Water Quality

¡      No discharge of silty water into the storm drain and drainage channel within and the vicinity of the site;

¡      Removal off-site of construction plant causing pollution to water system due to leakage of oil or fuel; and

¡      Temporary stockpiling of excavated soil in a specially designated area with provision of tarpaulin cover.

Waste

¡      Control measures at the stockpiling area to prevent the generation of dust and pollution of stormwater channels, fish ponds or river channels;

¡      Segregation, storage, transportation and disposal of different types of waste; and

¡      Keeping of records of quantities of wastes generated, recycled and disposal (with locations).

Ecology

¡      Good site practices for controlling the dust and water quality; and

¡      Clear definition of works limit to avoid impact on adjacent habitats.

Landscape and Visual

¡      Retain tree with high amenity or ecology value and contributing most to landscape and amenity of site;

¡      Precautionary area around trees to be retained equal to half of the tree canopy diameter;

¡      Prohibition of the storage of materials including fuel, the movement of construction vehicles, and the refuelling and washing of equipment including concrete mixers within the precautionary area;

¡      Pruning of the branches of existing trees identified for transplantation and retention;

¡      Rectification and repair of damaged vegetation following the construction phase to its original condition;

¡      Careful monitoring of all works affecting the trees identified for retention and transplantation; and

¡      Enforcement of construction site controls including storage of materials, location and appearance of site accommodation and the careful design of site lighting to prevent light spillage.

Environmental mitigation measures will be implemented on site as recommended and weekly site audits will be carried out to ensure that the environmental conditions are acceptable.



1.1               Background

The Frontier Closed Area (FCA) is an integral part of the package of measures aimed at maintaining the integrity of the boundary of the Hong Kong Special Administrative Region (HKSAR) with mainland China, and combating illegal immigration and other cross-boundary criminal activities.  Following a recent review, the HKSAR Government has concluded that with the erection of a secondary boundary fence (SBF) along the boundary patrol road (BPR) and construction of new sections of the BPR and primary boundary fence (PBF) at certain sections along the boundary, the FCA coverage can be substantially reduced without affecting the objective of maintaining the integrity of the boundary. 

The PBF and SBF (hereafter referred to as ‘The Project’) will be erected along the northern and southern curbs of the realigned BPR respectively to facilitate the Hong Kong Police Force (HKPF) in combating cross-boundary criminal activities.  The reduced FCA will comprise a narrow strip of land covering the realigned BPR and areas to its north, together with the points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau Kok town).  Areas south of the SBF will generally be excised from the FCA.

An Environmental Impact Assessment (EIA) for the proposed works was carried out under the Environmental Impact Assessment Ordinance (EIAO, Cap 499). An EIA Report and an Environmental Monitoring and Audit (EM&A) Manual were completed in January 2009 and approved by the Environmental Protection Department (EPD) in April 2009 (Register No. AEIAR-136/2009). The entire length of the proposed works is about 21.7 km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four sections. A general layout plan of the Project site is presented in Figure 1.1, while the location of the SBF at Section 4 in Sha Tau Kok is presented in Figure 1.2.

An Environmental Permit (EP) covering the overall proposed works was issued in June 2009 (Permit No. EP-347/2009). An application for Variation of the Environmental Permit (VEP) (Application No. VEP-314/2010) was subsequently submitted on 24 May 2010 and the amended Environmental Permit (Permit No. EP-347/2009/A) was issued by EPD on 9 June 2010.

With regard to Section 4, an application for a Further Environmental Permit (FEP) covering the works under Works Order No. ASD 010962 (also known as Works Order No. 1) was submitted to EPD on 2 March 2010 (Application No. FEP-104/2010) and this was granted on 29 March 2010 (Permit No. FEP-03/347/2009). Furthermore, another application for an FEP covering the works under Works Order Nos. ASD 010969 and ASD 010974 (also known as Works Order Nos. 2 and 3 respectively) – including a new section of SBF consisting of transparent panel, a new checkpoint and kiosk – was submitted to EPD on 13 August 2010 (Application No. FEP-112/2010) and was granted on 7 September 2010 (Permit No. FEP-04/347/2009/A).

The Architectural Services Department (ArchSD) has been entrusted with the management of the Project by the Project Proponent – the Secretary for Security of the HKSAR Government. Mott MacDonald Hong Kong Limited (MMHK) has in turn been commissioned by ArchSD as the consulting engineer for the entire Project under Consultancy Agreement No. 9SN005, and is the Engineer’s Representative (ER) for construction of the Project.

For Section 4 of the Project, MMHK and ENVIRON Hong Kong Limited (ENVIRON) have been commissioned as the Environmental Team (ET) and Independent Environmental Checker (IEC) respectively to undertake the Environmental Monitoring and Audit (EM&A) programme as described in the approved EM&A Manual of the Project. Also, the Contract to undertake and perform the construction works for Section 4 was awarded to Chun Wo Construction & Engineering Company Limited (‘The Contractor’) and is scheduled to last for approximately 18 months. It formally commenced on 28 May 2010, and the construction works and EM&A programme under the above-mentioned EP and FEP(s) also commenced on this date. The construction works programme is presented in Appendix A.

This monthly EM&A report summarises the environmental monitoring and audit works, list of activities and mitigation measures implemented at Section 4 during the period of 1 to 31 January 2011 inclusive (‘reporting month’).

The scope of works for Section 4 consists of:

¡      Erection of an SBF from the entrance of the Sha Tau Kok town (i.e. the location of ‘Gate One’) to the Sha Tau Kok Control Point (approximately 0.5 km);

¡      Use of transparent panel for a section of an SBF;

¡      Provision of a two-storey high checkpoint at ‘Gate One’;

¡      Addition of a kiosk/guard house on an existing footpath of Sha Tau Kok Road; and

¡      Removal of the existing checkpoint at Shek Chung Au.

1.2               Project Organisation

The organisation chart and lines of communication with respect to the on-site environmental management structure together with the contact information of the key personnel are shown in Appendix B.

1.3               Works Undertaken in the Reporting Month

The following activities have taken place during the reporting month:

Works Order No. 1 (ASD 010962):

¡      No major works. (Substantial completion was certified on 12 October 2010.)

Works Order No. 2 (ASD 010969):

¡      Tree pruning work;

¡      Installation of transparent panel for the new boundary fence;

¡      Construction of footing for the new boundary fence;

¡      Construction of steel frame and mesh for the new boundary fence;

¡      Excavation works for footing of steel fence;

¡      Reinstatement of pavement and carriageway; and

¡      Construction of footing for the new pedestrian gate.

Works Order No. 3 (ASD 010974):

¡      Erection of hoarding for the new check point;

¡      Construction of stud wall and retaining wall at the new check point site; and

¡      Construction of footing and super-structural works at the new check point site.

 


 

Figure 1.1:     General Layout Plan

 


 

Figure 1.2:     Location of Secondary Boundary Fence and Noise Monitoring Station at Section 4

 

 

 

 


1.1               Summary of EM&A Requirements

The EM&A programme requires environmental monitoring of construction noise as well as environmental site inspections for air quality, noise, water quality, waste management, ecology, landscape and visual, as specified in the approved EM&A Manual.

Originally, the EM&A Manual designated two locations as noise monitoring stations during the construction phase. However, currently noise levels at only one of these monitoring stations (as shown in Figure 1.2) are monitored. The reasons for this arrangement are detailed in Section 3.2.

A summary of impact EM&A requirements is presented in Table 2.1. The Environmental Quality Performance Limits and the Event and Action Plans (for construction noise only) are shown in Appendix C and Appendix D respectively.

Table 2.1:      Summary of EM&A Impact Requirements

Parameters

Description

Location(s)

Frequency

Duration

Air

On-site Inspection

Active Works Sites

Weekly

During Construction

Noise

Leq, 30min

STK-DBD

Weekly

During Construction

Waste management

On-site Waste Audit

Active Works Sites

Weekly

During Construction

On-site Waste Inspection

Wastewater

On-site Wastewater Audit

Active Works Sites

Weekly

During Construction

Ecology

On-site Audit of Recommended Ecological Mitigation Measures

Active Works Sites

Periodically (by Contractor)

As specified in EM&A Manual (see Table E.5)

Landscape and Visual

On-site Audit of Recommended Landscape and Visual Mitigation Measures

Active Works Areas

Regular intervals (by Contractor/ Landscape Sub-Contractor)

As specified in EM&A Manual (see Table E.6)

General Site Conditions

Environmental Site Inspection

Works areas and areas affected by works

Weekly

During Construction

1.2               Implementation of Environmental Mitigation Measures

The Contractor is required to implement mitigation measures listed in the latest valid EP and FEP(s) (where applicable), EIA Report and EM&A Manual. During routine site inspections, the Contractor's implementation of mitigation measures, if any, are to be inspected and reviewed. A schedule of the implementation of mitigation measures identified at the EIA stage is given in Appendix E.

 

 

 


2.1               Monitoring Parameters, Frequency and Duration

Following the requirements in the EM&A Manual for noise, noise monitoring has to be carried out during the construction phase. Continuous noise monitoring for the A-weighted levels Leq, L10 and L90 is undertaken once per every week during daytime hours (between 07:00 and 19:00) on normal weekdays.

Table 3.1 summarizes the monitoring parameters, frequency and duration of air quality monitoring. The noise monitoring schedule during the reporting month is presented in Appendix F.

Table 3.1:      Noise Monitoring Parameters, Frequency and Duration

Monitoring Station

Parameter

Frequency

Duration

STK-DBD

Leq, L90 & L10

Once every week

30 min

2.2               Monitoring Location

Originally, two construction noise monitoring stations were proposed in the EM&A Manual, namely: STK03 (Block 1, Sha Tau Kok Estate) and STK05 (Village House at Sha Tau Kok). STK03 was mainly selected for the construction works related to the SBF and the new checkpoint in Sha Tau Kok, while STK05 was mainly selected for the removal of the existing checkpoint at Shek Chung Au.

However, access to STK03 to perform noise monitoring was not granted, therefore an alternative nearby location – STK-DBD (HKPF Operation Base, Sha Tau Kok Division, Border District) – was proposed by ET and agreed to by IEC and EPD. Baseline noise monitoring was subsequently conducted at STK-DBD from 16 to 29 March 2010.

Currently, there is no solid timetable or programme for the demolition works of the existing checkpoint at Shek Chung Au, although the end of 2011 has been proposed as a possible commencement date. This is subject to future confirmation of the demolition programme by the Security Bureau and HKPF. No noise monitoring at STK05 has been carried out at this stage.

As a result, only one noise impact monitoring station is included in the current EM&A programme for Section 4. The location of the agreed noise quality monitoring station is listed in Table 3.2 and shown in Figure 1.2.

Table 3.2:      Noise Impact Monitoring Location

Monitoring Station

Description of Location

Type of measurement

STK-DBD

HKPF Operational Base, 

Sha Tau Kok Division, Border District

Façade

2.3               Monitoring Equipment

Integrating Sound Level Meter will be used for noise monitoring. It is a Type 1 sound level meter capable of giving a continuous readout of the noise level readings including equivalent continuous sound pressure level (Leq) and percentile sound pressure level (Lx). They comply with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1). Table 3.3 summarizes the noise monitoring equipment model(s) being used.

Table 3.3:      Noise Monitoring Equipment

Equipment

Model(s)

Precision Integrating Sound Level Meter

Rion NL-18 & NL-31

Acoustic Calibrator

Castle GA607

2.4               Equipment Calibration

The calibration frequencies of the monitoring equipment are provided in Table 3.4.

Table 3.4:      Noise Monitoring Equipment Calibration Frequencies

Equipment, Model and Serial Number

Calibration Frequency

Calibration Due Date(s)

Precision Integrating Sound Level Meter (NL7-SLM-02)

Rion NL-18 (serial number 00570459)

Every year

12 Dec 2011

Precision Integrating Sound Level Meter

Rion NL-31 (serial number 01262786)

Every year

10 May 2011

Acoustic Calibrator

Castle GA607 (serial number 040162)

Every year

9 Dec 2011

The calibration certificates are presented in Appendix G.

2.5               Monitoring Methodology

2.5.1           Field Monitoring

¡      The Sound Level Meter was set on a tripod at a height of at least 1.2 m above the ground.

¡      Façade measurements were made at the monitoring locations.

¡      The battery condition was checked to ensure the correct functioning of the meter.

¡      Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

-      frequency weighting: A

-      time weighting: Fast

-      time measurement: 5-minute intervals (between 07:00 and 19:00); Leq (30 min) was determined by calculating the logarithmic average of six Leq (5-min) data.

¡      Prior to and after each noise measurement, the meter was calibrated using a Calibrator for 94 dB at 1 kHz.  If the difference in the calibration level before and after measurement was more than 1 dB, the measurement would be considered invalid and have to be repeated after re-calibration or repair of the equipment.

¡      During the monitoring period, the Leq, L10 and L90 noise levels were recorded.  In addition, any site observations and noise sources were recorded on a standard record sheet.

2.5.2           Maintenance and Calibration

¡      The microphone head of the sound level meter and calibrator is cleaned with soft cloth at quarterly intervals.

¡      The meter and calibrator are sent to the supplier or Hong Kong Laboratory Accreditation Scheme (HOKLAS) laboratory to check and calibrate at yearly intervals.

2.6               Results of Impact Monitoring

The measured construction noise levels, in terms of Leq (30-min), during the reporting month are summarised in Table 3.5.  Detailed results, including general weather conditions and graphical presentations are presented in Appendix H.

Table 3.5:      Results of Noise Impact Monitoring

Monitoring Station

Measured Leq (30-min) Range, dB(A)

Limit Level for Leq, dB(A)

STK-DBD

62 – 65

75

Note:        All figures are rounded off to the nearest whole number.

 

No exceedance of Action / Limit Levels for construction noise was recorded.

 

No direct comparison between the measured noise levels and the construction noise levels predicted in the EIA Report for this Project was possible due to the minor nature of site works conducted during the reporting month.

 

Wind data obtained from the nearest Hong Kong Observatory monitoring station, at Ta Kwu Ling, covering all noise monitoring days during the reporting month is included in Appendix K.

 

 

 

 

 


3.1               Site Inspections

Environmental site inspections were carried out on a weekly basis to monitor the proper implementation of environmental pollution control and mitigation measures for Section 4. In the reporting month, one monthly site inspections were carried out jointly by the ER, Contractor, ET and IEC on 31 January 2011, and additional weekly site inspections were carried out by the ER, Contractor and ET on 8, 14, 19 and 25 January 2011. The EM&A schedule is presented in Appendix F.

Major findings provided jointly by the ET and IEC during the joint monthly site inspections, and provided by ET during the additional weekly site inspections, are summarised in Table 4.1. In general, the works site areas were found to be in compliance with the environmental mitigation requirements listed in the EM&A Manual and no adverse impacts were found.

Table 4.1:      Summary of Environmental Site Inspections

Date of Inspection

Major Observations

Status

8 Jan 2011

The Contractor is again reminded to provide and maintain all necessary tree protection works in the areas covered by Works Order No. 2. This includes placement of construction materials away from trees and proper fencing of precautionary areas.

Tree protection measures, including fencing of precautionary areas and backfilling of excavated soil as early as possible as possible after completion of footing for the new boundary fence, were provided in the works areas covered by Works Order No. 2, as observed on 31 Jan 2011. (closed)

 

Extra hoarding was provided at the site entrance. However, some construction dust was still observed in the public area and should be cleared as soon as possible.

Construction dust was cleared from the public area, as observed on 14 Jan 2011. (closed)

 

The EP and FEP were not observed at the new checkpoint site. The Contractor is asked to reinstate these as soon as possible.

The EP and FEP were displayed at the new checkpoint site entrance, as observed on 25 Jan 2011. (closed)

14 Jan 2011

Some material from site concrete works had spilt to the adjacent car park. The Contractor is reminded to prevent dusty construction materials from leaving the site area. Wheel wash facilities should be implemented if required.

As observed during the follow-up site inspection on 19 Jan 2011, water hose was used to clean a cement truck during concrete works before its departure from the new checkpoint site. No silty run-off or dusty construction materials were discharged from the site. (closed)

19 Jan 2011

Nil.

N/A

25 Jan 2011

Some discarded plastic bottles were observed within a site boundary. The Contractor is reminded to dispose of these properly.

Discarded plastic bottles were removed from site and disposed of, as observed on 31 Jan 2011. (closed)

31 Jan 2011

Nil.

N/A

3.2               Environmental Meetings

During the reporting month, one environmental meeting was held on 31 January 2011.

3.3               Status of Environmental Submissions, Permits and Licences

A summary of status of all environmental submissions, valid permits/licences, and/or notifications to EPD for this Project during the reporting month is presented in Table 4.2. A summary of submissions made under the valid EP and FEP(s) for Section 4 during the same period is presented in