Environmental Permit No. EP-060/2000
環 境 許 可 證 編 號 EP-060/2000


ENVIRONMENTAL IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
Section 10

環 境 影 響 評 估 條 例
(第 499章 )
第 10條

ENVIRONMENTAL PERMIT TO CONSTRUCT AND OPERATE A DESIGNATED PROJECT

建 造 及 營 辦 指 定 工 程 項 目 的 環 境 許 可 證

PART A (MAIN PERMIT)
A部 (許 可 證 主 要 部 分 )

Pursuant to Section 10 of the Environmental Impact Assessment Ordinance (the EIAO), the Director of Environmental Protection (the Director) grants this environmental permit to the Civil Engineering Department (hereinafter referred to as the "Permit Holder") to construct and operate the designated project described in Part B subject to the conditions described in or attached to Part C. The issue of this environmental permit is based on the documents, approvals or permissions described below:

根 據 環 境 影 響 評 估 條 例 第 10條 的 規 定 ﹐ 環 境 保 護 署 署 長 (署 長 ) 將 本 環 境 許 可 證 批 予 土 木 工 程 署 (下 稱 "許 可 證 持 有 人 ") 以 建 造 及 營 辦 B部 所 說 明 的 指 定 工 程 項 目 ﹐ 但 須 遵 守 C部 所 說 明 的 條 件 。 本 環 境 許 可 證 的 發 出 ﹐ 乃 以 下 表 所 列 的 文 件 、 批 准 或 許 可 作 為 根 據 ﹕ -

Application No.
申 請 書 編 號
AEP-060/2000
Document in the Register:
登 記 冊 上 的 文 件 :
Environmental Impact Assessment - Construction of an International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructures
- Final EIA Report
- Annex (Volume 1)
- Annex (Volume 2)
- Annex (Volume 3)
- Executive Summary
(Register No.: AEIAR-032/2000) [Hereinafter referred to as the EIA Report]
The Director's letter of approval of the EIA Report dated 28 April 2000, ref: (53) in Annex (3) to EP2/N9/O/65 III.

北 大 嶼 山 竹 篙 灣 國 際 主 題 公 園 及 有 關 主 要 基 礎 設 施 建 造 工 程 - 環 境 影 響 評 估 :
- 環 境 影 響 評 估 報 告
- 附 件 (第 一 冊 )
- 附 件 (第 二 冊 )
- 附 件 (第 三 冊 )
- 摘 要
(登 記 冊 編 號 : AEIAR-032/2000) [下 稱 "環 評 報 告 "]

環 境 保 護 署 署 長 於 二 ○ ○ ○ 年 四 月 廿 八 日 發 出 批 准 環 評 報 告 的 信 件 (檔 案 編 號 : (53) in Annex (3) to EP2/N9/O/65 III)



___________________
Date
日 期


______________________________________
(Elvis W. K. AU)
Assistant Director
(Environmental Assessment and Noise)
for the Director of Environmental Protection
環 境 保 護 署 署 長
(助 理 署 長 (環 境 評 估 及 噪 音 )區 偉 光 代 行 )

PART B (DESCRIPTIONS OF DESIGNATED PROJECT)
B部 (指 定 工 程 項 目 的 說 明 )

Hereunder is the description of the designated project mentioned in Part A of this environmental permit (hereinafter referred to as the "Permit"):

下 列 為 本 環 境 許 可 證 (下 稱 "許 可 證 ")A部 所 提 述 的 指 定 工 程 項 目 的 說 明 :

Title of Designated Project
指 定 工 程 項 目 的 名 稱
Eastern Stormwater Drainage Channel at Penny's Bay
[This designated project is hereinafter referred to as "the Project"]
竹 篙 灣 東 部 排 水 渠 [本 指 定 工 程 項 目 下 稱 "工 程 項 目 "]
Nature of Designated Project
指 定 工 程 項 目 的 性 質
Construction and operation of a drainage channel which discharges into an area which is less than 300 metres from the nearest boundary of the existing Pai Tau Kwu Archaeological Site.

建 造 及 營 辦 一 條 排 水 道 , 而 該 工 程 排 水 入 一 個 地 區 距 離 現 有 的 扒 頭 鼓 文 化 遺 產 地 點 少 於 300米 。

Location of Designated Project
指 定 工 程 項 目 的 地 點
Penny's Bay, Lantau. The location of the Project is shown in Figure 1 attached to this Permit

大 嶼 山 竹 篙 灣 。 工 程 項 目 的 地 點 如 本 環 境 許 可 證 內 圖 1所 示 。

Scale and Scope of Designated Project(s)
指 定 工 程 項 目 的 規 模 和 範 圍

The proposed drainage structure comprises of a two to three cell box culvert (approximately 3.5 m wide and 3.5 m height each) arrangement with a length of about 1.7 km.
[Note: This Permit does not cover any reclamation works for the Project. The reclamation works for the Project are covered in another Environmental Permit No.EP-054/2000.]
建 造 及 營 辦 一 條 約 1.7千 米 長 由 二 至 三 個 箱 組 成 的 暗 渠 (每 個 箱 約 3米 闊 、 3.5米 高 )。
[註 : 本 環 境 許 可 証 並 不 包 括 與 工 程 項 目 相 關 的 填 海 工 程 。 有 關 的 填 海 工 程 己 包 括 在 另 一 份 環 境 許 可 証 編 號 EP-054/2000之 內 。 ]

PART C (PERMIT CONDITIONS)

1 General Conditions

1.1 The Permit Holder shall ensure full compliance with all conditions of this environmental permit. Any non-compliance may constitute a contravention of the EIAO and may become subject of appropriate action being taken under the Ordinance.

1.2 The Permit Holder shall ensure full compliance with all legislation from time to time in force including without limitation the Noise Control Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water Pollution Control Ordinance (Cap. 358), Dumping at Sea Ordinance (Cap. 466) and Waste Disposal Ordinance (Cap. 354). This Permit does not of itself constitute any ground of defense against any proceedings instituted under any legislation.

1.3 The Permit Holder shall make copies of this Permit together with all documents referred to in this Permit or the documents referred to in Part A of the Permit readily available at all times for inspection at all sites/offices covered by this Permit. Any reference to the Permit shall include all documents referred to in the Permit and also the relevant documents in the Register.

1.4 The Permit Holder shall give a copy of this Permit to the person(s) in charge of the site(s) and ensure that such person(s) fully understands all conditions and all requirements incorporated by the Permit.

1.5 The Permit Holder shall display a copy of this Permit on the construction site at all vehicular site entrances/exits or at a convenient location for public's information at all times. The Permit Holder shall ensure that the most updated information about the Permit, including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part or the whole of the Permit, the notice he sends to the Director shall also be displayed at the same locations as the original Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site.

1.6 The Permit Holder shall construct and operate the Project as described in Part B of this Permit.

1.7 The Permit Holder shall ensure that the Project is designed, constructed and operated in accordance with the information and recommendations described in the EIA Report (Register No. AEIAR-032/2000); other relevant documents in the Register; and the information or mitigation measures described in this Permit, or mitigation measures to be recommended in submissions that shall be deposited with or approved by the Director as a result of permit conditions contained in this Permit, or mitigation measures to be recommended under on going surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the documents of the Register are not expressly referred to in this Permit, such recommendations are nevertheless to be implemented unless expressly excluded or impliedly amended in this Permit.

1.8 All deposited submissions as required under this Permit, shall be rectified in accordance with the comments, if any, made by the Director, within one month of the receipt of the Director's comments or otherwise specified by the Director.

1.9 All submissions approved by the Director, all submissions deposited without comments by the Director, or all submissions rectified in accordance with comments by the Director under this Permit shall be construed as part of the permit conditions described in Part C of this Permit. Any variation of the submissions shall be approved by the Director in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions may constitute a contravention of the EIAO.

1.10 The Permit Holder shall release all finalized submissions, as required under this Permit, to the public by depositing copies in the Environmental Impact Assessment Ordinance Register Office, or in any other places, or any internet websites as specified by the Director, or by any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall provide sufficient copies of the submissions.

1.11 The Permit Holder shall notify the Director in writing the commencement date of construction of the Project no later than 6 weeks before the commencement of construction of the Project. The Permit Holder shall notify the Director in writing immediately if there is any change of the commencement date of the construction.

1.12 All submissions to the Director required under this Permit shall be delivered either in person or by registered mail to the Environmental Impact Assessment Ordinance Register Office (currently at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).

2. Submissions or Measures for the Construction of the Project

2.1 An Independent Environmental Checker (IEC) shall be employed no later than one month before the commencement of construction of the Project. The IEC shall have at least 7 years' experience in environmental monitoring and audit (EM&A) or environmental management. The IEC shall audit the overall EM&A programme including the implementation of all environmental mitigation measures, submissions relating to EM&A, and any other submissions required under this Permit. In addition, the IEC shall be responsible for verifying and certifying the environmental acceptability of permanent and temporary works, relevant design plans and submissions under this Permit.

2.2 An Environmental Team (ET) shall be established no later than one month before the commencement of construction of the Project. The ET shall be supervised by the ET Leader who has at least 7 years' experience in EM&A or environmental management. The ET Leader shall be responsible for the implementation of the EM&A programme in accordance with the EM&A requirements as contained in the approved EM&A Manual submitted and approved under Condition 2.3 of this Permit.

2.3 No later than two weeks before commencement of the construction of the Project, the Permit Holder shall submit for the Director's approval an Environmental Monitoring and Audit (EM&A) Manual for the construction of the Project. Before the submission to the Director, the EM&A Manual shall be certified by the ET Leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report. All measures recommended in the EM&A Manual shall be fully and properly implemented in accordance with the requirements and time schedule(s) set out in the EM&A Manual. The EM&A Manual approved under this condition shall hereinafter be referred to as the "EM&A Manual".

2.4 Three sets of Waste Management Plan for the construction stage of the Project shall be submitted to the Director for approval within 4 weeks after the commencement of construction of the Project. The Plan shall be certified by the ET leader and verified by the IEC as conforming to the information and recommendations contained in the EIA Report. The Plan shall describe the arrangements for avoidance, reuse, recovery and recycling, storage, collection, treatment and disposal of different categories of waste to be generated from the construction activities and shall include the recommended mitigation measures on construction waste management in Section 6.7 and Section 16 of the EIA Report. Such a management plan shall include the designation of areas for segregation and temporary storage of reusable and recyclable materials. All measures in the approved Waste Management Plan shall be fully implemented throughout the construction period.

2.5 The Permit Holder shall, within 4 weeks after the commencement of construction of the Project, inform the Director in writing the management organization of the main construction companies and/or any form of joint ventures associated with the construction of the Project. The submitted information shall include at least an organization chart, names of responsible persons and their contact details.

Measures to Mitigate Water Quality and Marine Ecological Impacts during Construction

2.6 No underwater blasting shall be allowed.

2.7 No underwater percussive piling shall be allowed.

2.8 The speed of construction ferries and vessels shall not exceed 10 knots when passing through an area within 500 meters from the reclamation limit as shown in Figure 2 attached to this Permit.

2.9 To prevent pollution due to spillage of oil, fuel or other chemicals, all fuel tanks and chemical storage areas within the Project shall be sheltered from rain water and surrounded by bunds with a minimum capacity of 110% of the storage capacity of the largest tank. The storage area shall be provided with locks and be sited on sealed areas. Guidelines and procedures shall be prepared and implemented for immediate clean-up actions following any spillages of oil, fuel or chemicals, and shall be certified by the IEC and deposited with the Director within 2 months after the commencement of construction.

2.10 To mitigate environmental impacts due to site runoff and other potential water pollution caused by construction activities, mitigation measures described in Appendix A shall be implemented throughout the construction period.

Measures to Mitigate Terrestrial Ecological Impacts during Construction

2.11 To avoid disturbance to the White-bellied Sea Eagles at Pa Tau Kwu, quiet plant as described in Section 4.6.6 of the EIA report shall be adopted for any construction activities within areas as shown in Figure 3 attached to this Permit.

2.12 To avoid disturbance to the White-bellied Sea Eagles at Pa Tau Kwu, no construction activity, including transportation of equipment, shall be allowed at Pa Tau Kwu headland as shown in Figure 3 attached to this Permit.

2.13 To prevent access of workers to the nesting site of the White-bellied Sea Eagles, public land access from the Project works areas to Pa Tau Kwu shall be fenced off within 4 weeks after the commencement of construction.

Other Measures during Construction

2.14 To reduce the quantity of construction and demolition wastes, wood hoarding shall not be used.

2.15 No works except for investigation works necessary for the completion of the decommissioning EIA study for the shipyard, shall be carried out within the Cheoy Lee Shipyard at Penny's Bay.

2.16 All mitigation measures as described in the EM&A Manual and the submissions required under this Permit, shall be properly constructed and implemented.

3. Environmental Monitoring and Audit (EM&A) during the Construction

3.1 The EM&A programme shall be implemented in accordance with the procedures and requirements as approved under Condition 2.3. Any changes to the EM&A programme shall be justified by the IEC or ET Leader as conforming to the requirements set out in the EM&A Manual, and shall be approved by the Director.

3.2 Samples and measurements shall be taken in accordance with the requirements of the EM&A Manual by:

(a)conducting baseline monitoring as set out in the EM&A Manual.
(b)conducting impact monitoring as set out in the EM&A Manual.
(c)carrying out remedial actions in accordance with the Event/Action Plans, as set out in the EM&A Manual, in cases where specified criteria in the EM&A Manual are exceeded, and;
(d)logging and keeping records of the details of (a) to (c) above, within 3 working days of the collection of data or completion of remedial action, for the purposes of preparing and submitting the monthly EM&A reports and to make available the information for inspection on site.

3.3 All environmental monitoring and audit data submitted under this Permit shall be true, valid and correct.

3.4 One hard copy and one soft copy of the Baseline Monitoring Report shall be submitted to the Director within one week after the commencement of any major construction works that would affect the monitoring results. The submissions shall be certified by the ET Leader and verified by the IEC. Additional copies of the submission shall be provided to the Director upon request from the Director.

3.5 One hard copy and one soft copy of monthly EM&A Report shall be submitted to the Director within 2 weeks from the end of the reporting month. The submission shall be certified by the ET Leader and verified by the IEC. Additional copies of the submission shall be provided to the Director upon request from the Director.

3.6 The actions described in the Event and Action Plans of the EM&A Manual shall be fully and properly carried out, in accordance with the time frame set out in the Event and Action Plans, or as agreed by the Director.

Notes:

1. This Permit consists of three parts, namely, PART A (Main Permit), PART B (Description of Designated Project) and PART C (Permit Conditions). Any person relying on this permit should obtain independent legal advice on the legal implications under the Ordinance, and that the following notes are for general information only.

2. The Permit Holder may apply under Section 13 of the Ordinance to the Director for a variation of the conditions of this Permit. The Permit Holder shall replace the original permit displayed on the construction site by the amended permit.

3. A person who assumes the responsibility for the whole or a part of the designated project may, before he assumes responsibility of the designated project, apply under Section 12 of the Ordinance to the Director for a further environmental permit.

4. Under Section 14 of the Ordinance, the Director may with the consent of the Secretary for the Environment and Food, suspend, vary or cancel this Permit. The suspended, varied or cancelled Permit shall be removed from display at the construction site.

5. If this Permit is cancelled or surrendered during construction or operation of the Project, another environmental permit must be obtained under the Ordinance before the Project could be continued. It is an offence under Section 26(1) of the Ordinance to construct or operate a designated project listed in Part I of Schedule 2 of the Ordinance without a valid environmental permit.

6. Any person who constructs or operates the Project contrary to the conditions in the Permit, and is convicted of an offence under the Ordinance, is liable: -

(i)on a first conviction on indictment to a fine of $ 2 million and to imprisonment for 6 months;
(ii)on a second or subsequent conviction on indictment to a fine of $ 5 million and to imprisonment for 2 years;
(iii)on a first summary conviction to a fine at level 6 and to imprisonment for 6 months;
(iv)on a second or subsequent summary conviction to a fine of $1 million and to imprisonment for 1 year; and
(v)in any case where the offence is of a continuing nature, the court or magistrate may impose a fine of $ 10,000 for each day on which he is satisfied the offence continued.

7. The Permit Holder may appeal against any condition of this Permit under Section 17 of the Ordinance within 30 days of receipt of this Permit.

Appendix A (as referred to in Condition 2.10)

Measures to Mitigate Environmental Impacts due to Site Run-off and Other Potential Water Pollution During Construction

 (a)Surface Runoff
 (i)Surface run-off from the construction site shall be directed into adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins before discharge into storm drains. Channels, earth bunds or sand bag barriers shall be provided on site to properly direct stormwater to such silt removal facilities.
 (ii)Catchpits and perimeter channels shall be constructed in advance of site formation works and earthworks.
 (iii)Silt removal facilities, channels and manholes shall be suitably maintained with the deposited silt and grit being removed at least once a week, and at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.
 (iv)Earthworks final surfaces shall be well compacted and the subsequent permanent work or surface protection shall be carried out immediately after the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate intercepting channels shall be provided along the site boundary or at the locations agreed with the IEC or EATL. Rainwater pumped out from trenches or foundation excavations shall be discharged into storm drains via silt removal facilities.
 (v)Open stockpiles of construction materials (e.g. aggregates and sand) on site shall be covered with tarpaulin or similar fabric during rainstorms. Measures such as providing sand bag barriers shall be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.
 (vi)Manholes (including any newly constructed ones) shall always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris from getting into the drainage system, and to prevent storm run-off from getting into foul sewers. Discharges of surface run-off into foul sewers shall always be prevented in order not to unduly overload the foul sewerage system.

(b) Groundwater

Groundwater pumped out of wells, etc. for the lowering of ground water level in foundation construction shall pass through appropriate silt removal facilities before discharge into storm drains.

(c) General Construction Activities

At all parts of all works areas and construction sites, and throughout the full duration of the construction contract(s), debris and rubbish on site shall be handled and disposed of to avoid entering the water column and causing water quality impacts. Temporary on-site storage of excavated materials from station and depot construction works shall be covered with tarpaulin or similar fabric during rainstorms. Any washout of construction or excavated materials should be diverted to the drainage system via sediment traps. Stockpiling of the excavated material shall be minimised by scheduling the construction programme in a way that one section of the alignment can be constructed and completed before the excavation works of the next section commence.


Figure 1 | Figure 2 | Figure 3


[ Back to First Page ] / [ Back to Main Index ]