15              Implementation Schedules

15.1          Introduction

15.1.1    In order to provide a means of highlighting the mitigation measures and key EM&A requirements recommended in the EIA Report, the EIAO TM requires that the EIA Report contains a schedule of all the mitigation measures.  The schedule is required to list out what is required from each of the mitigation measures, describe who will implement it, and also define when, where and to what requirements it will be undertaken.

15.1.2    This Annex present the construction and operational phase Implementation Schedules for the CKWLR. As each of the other components of the NLDFS are at a less advanced stage of implementation, it is envisaged that Implementation Schedules will be produced for these schemes at a later date.

15.1.3    The Implementation Schedules for the construction and operational phases of the CKWLR are contained with Tables 15.1a and 15.1b respectively.

15.1.4    The Implementation Schedules have the following column headings:

EIA Ref

15.1.5    This denoted the section number or reference from the EIA Report Main text.

EM&A Log Ref

15.1.6    This denotes the sequential number of each of the recommended mitigation measures specified in the Implementation Schedule.

Environmental Protection Measures

15.1.7    This denotes the recommended mitigation measures, courses of action or subsequent deliverables that are to be adopted, undertaken or delivered to avoid, minimise or ameliorate predicted environmental impacts.

Location/Duration of Measures/Timing of Completion of Measures

15.1.8    This indicates the spatial area in which the  recommended mitigation measures are to be implemented together with details of the programming or timing of their implementation. 

Implementation Agent

15.1.9    This denotes where the responsibility lies for the implementation of the recommended mitigation measures.

Implementation Stage

15.1.10    This denotes the stage at which the recommended mitigation measures are to be implemented; either during the Design, Construction, Operation or Decommissioning.


Relevant Legislation & Guidelines

15.1.11    This section defines the controlling legislation or guidelines that are either required to be complied with, or should be complied with as good practice.

 


Table 15.1a - Implementation Schedule for the Chok Ko Wan Link Road - Construction Phase

EIA* Ref.

EM&A Log Ref

Environmental Protection Measures

Location/Duration of Measures/Timing of Completion of Measures

Implementation Agent

Implementation Stage*

Relevant Legislation & Guidelines

 

 

 

 

 

Des

C

O

Dec

 

3.4.3

 

AIR QUALITY - Construction Phase

 

 

 

 

 

 

 

 

 

In accordance with the Air Pollution Control (Construction Dust) Regulation the following mitigation measures shall be implemented to limit the dust emissions from the site:

 

 

 

 

 

 

 

3.4.3

A1

·       if a stockpile of dusty materials is more than 1.2 m high and lies within 50 m from any site boundary that adjoins a road, street, or other area accessible to the public, it shall be properly treated and sealed with latex, vinyl, bitumen or other suitable surface stabilizer;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A2

·       effective dust screens, sheeting or netting should be provided to enclose the scaffolding from the ground floor level of the building or if a canopy is provided at the first floor level, from the first floor level, up to the highest level of the scaffolding where a scaffolding is erected around the perimeter of a building under construction;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A3

·       skip hoist for material transport should be totally enclosed by impervious sheeting;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A4

·       any excavated dusty materials or stockpile of dusty materials shall be covered entirely by impervious sheeting or sprayed with water so as to maintain the entire surface wet, and recovered or backfilled or reinstated within 24 hours of the excavation or unloading;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A5

·       stockpile of dusty materials should not extend beyond the pedestrian barriers, fencing or traffic cones;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforces by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A6

·       dusty materials remaining after a stockpile is removed shall be wetted with water and cleared from the surface of roads;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A7

·       vehicle washing facilities shall be provided at every vehicle exit point

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A8

·       the area where vehicle washing takes place and the section of the road between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A9

·       where a site boundary adjoins a road, streets or other area accessible to the public, hoarding of not less than 2.4 m high from ground level shall be provided along the entire length except for a site entrance or exit;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A10

·       every main haul road shall be scaled with concrete and kept clear of dusty materials or sprayed with water so as to maintain the entire road surface wet;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A11

·       the portion of road leading only to a construction site that is within 30m of a designated vehicle entrance or exit should be kept clear of dusty materials;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A12

·       every stock more than 20 bags of cement should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A13

·       cement delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line such that, in the event of the silo approaching an overfilling condition, an audible alarm is triggered and the material filling stops within one minutes;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A14

·       silos used for the storage of cement should not overfilled;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A15

·       loading, unloading, transfer, handling or storage of bulk cement or any cement during or after the de-bagging process should be carried out in a totally enclosed system or facility, and any vent or exhaust should be fitted with an effective fabric or equivalent air pollution control system or equipment;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A16

·       cement, or any dusty materials collected by fabric filters or other air pollution control system or equipment should be disposed of in totally enclosed containers;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A17

·       stockpiles of dusty materials shall be either covered entirely by impervious sheeting, placed in an area sheltered on the top and 3 sides; or sprayed with water so as to maintain the entire surface wet;

 

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A18

·       all dusty materials shall be sprayed with water prior to any loading, unloading or transfer operation so as to maintain the dusty material wet;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A19

·       vehicle speed within the worksite shall be limited to 10 kph;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A20

·       every vehicle shall be washed to remove any dusty materials from its body and wheels before leaving the construction sites;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A21

·       every vehicle should be washed to remove any dusty materials from its body and wheels before leaving the construction sites;

 

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A22

·       the load of dusty materials carried by vehicle leaving a construction site should be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A23

·       the working area of excavation shall be sprayed with water immediately before, during and immediately after the operation so as to maintain the entire surface wet;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A24

·       the area within 30 m from any blasting area shall be wetted with water prior to blasting; and

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A25

·       the area within 30 m from the blasting area should be wetted with water prior to blasting; and

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

A26

·       blasting shall not be carried out when the strong wind signal or tropical cyclone warning signal No.3 or higher is hoisted unless prior permission of the Commissioner of Mines is obtained.

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Air Pollution Control (Construction Dust) Regulation

3.4.3

 

In addition, according to the EPD’s Best Practicable Means Requirements for Cement Works (Concrete Batching Plant), the following mitigation measures shall be adopted to prevent fugitive dust emissions:

 

 

 

 

 

 

 

3.4.3

A27

·       loading, unloading, handling, transfer or storage of any dusty materials shall be carried out in totally enclosed system;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A28

·       all dust-laden air or waste gas generated by the process operations shall be properly extracted and vented to fabric filtering system to meet the emission limits for TSP;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A29

·       vents for all silos and cement/pulverized fuel ash (PFA) weighing scale shall be fitted with fabric filtering system;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A30

·       the materials which may generate airborne dusty emissions shall be wetted by water spray system;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A31

·       all receiving hoppers shall be enclosed on three sides up to 3m above unloading point;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A32

·       all conveyor transfer points shall be totally enclosed;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A33

·       all access and route roads within the premises shall be paved and wetted;

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

3.4.3

A34

·       vehicle cleaning facilities shall be provided and used by all concrete trucks before leaving the premises to wash off any dust on the wheels and/or body.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Best Practicable Means Requirements for Cement Works (Concrete Batching Plant)

4.8

 

NOISE - Construction Phase

 

 

 

 

 

 

 

 

 

In addition to the use of good site practice (as defined in the EIA Report) the following mitigation measures shall be implemented to minimise noise emissions:

 

 

 

 

 

 

 

 

 

Selecting Quiet Plant

 

 

 

 

 

 

 

4.8

B1

Where available, the Contractor shall use models of plant that are quieter than those specified in the EPD’s Technical Memorandum (GW-TM) for undertaking construction works

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

EIAO-TM

GW-TM

 

 

Cumulative noise impact

 

 

 

 

 

 

 

4.8

B2

Apart from the use of quiet plant, other mitigation measures for the construction of CKWLR shall be implemented to reduce the cumulative noise impact brought about from other concurrent construction works under the Theme Park Project and its associated developments and the NLDFS Project.  These include:

 

 

 

 

 

 

 

 

 

Use of Temporary and Movable Noise Barriers

 

 

 

 

 

 

 

4.8

B3

Temporary purpose-built noise barriers or screens, constructed of appropriate material with a suitable footing and a small cantilevered upper portion, shall be erected along active work sites boundaries at the following locations in order to minimise noise emissions:

 

 

 

 

 

 

 

4.8

B4

·          At the work sites for the construction of CKWLR (from Yam O Interchange to Penny’s Bay Interchange)

 

At the stated locations, and throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

EIAO-TM

GW-TM

4.8

B5

·          At the work sites for the slope protection work along the eastern boundary of Tsing Chau Tsai

At the stated locations, and throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

EIAO-TM

GW-TM

 

 

WATER QUALITY- Construction Phase

 

 

 

 

 

 

 

5.7

 

Land Based Construction Activities

 

 

 

 

 

 

 

 

 

Surface Run-off

 

 

 

 

 

 

 

5.7

C1

Surface run-off from the construction site shall be directed into storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins.  Channels, earth bunds or sand bag barriers shall be provided on site to properly direct stormwater to such silt removal facilities. 

At all construction work site, throughout the whole duration of the construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C2

Catchpits and perimeter channels shall be constructed in advance of site formation works and earthworks.

At all construction work site prior to the commencement of site formation works and earthworks

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C3

Silt removal facilities, channels and manholes shall be suitably maintained with the deposited silt and grit being removed regularly, and at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C4

If excavation cannot be avoided during rainy seasons, temporarily exposed soil surfaces shall be covered e.g. by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds.  Intercepting channels should be provided (e.g. along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces.  Arrangements shall always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C5

Earthworks final surfaces shall be well compacted and the subsequent permanent work or surface protection shall be carried out as soon as practical after the final surfaces are formed to prevent erosion caused by rainstorms.  Appropriate intercepting channels shall be provided where necessary.  Rainwater pumped out from trenches or foundation excavations shall be discharged into storm drains via silt removal facilities.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C6

Open stockpiles of construction materials (e.g. aggregates and sand) on site shall be covered with tarpaulin or similar fabric during rainstorms.  Measures shall be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C7

Manholes (including any newly constructed ones) shall always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris from getting into the drainage system, and to prevent storm run-off from getting into foul sewers.  Discharges of surface run-off into foul sewers must always be prevented in order not to unduly overload the foul sewerage system.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

 

 

Groundwater

 

 

 

 

 

 

 

5.7

C8

Groundwater pumped out of wells, etc. for the lowering of ground water level in foundation construction shall be discharged into storm drains after being passed through appropriate silt removal facilities.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

 

 

Wheel Washing Water

 

 

 

 

 

 

 

5.7

C9

All vehicles and plant shall be cleaned before they leave the construction site to ensure that no earth, mud or debris is deposited by them on roads.  A wheel washing bay shall be provided at every site exit, if practicable, and wash-water shall have sand and silt settled out or removed before being discharged into the storm drains.  The section of construction road between the wheel washing bay and the public road shall be paved with backfall to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

At every site exit to all construction work sites, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

5.7

C10

Vehicle and plant servicing areas, vehicle wash bays and lubrication bays shall, as far as possible, be located within roofed areas.  The drainage in these covered areas shall  be connected to foul sewers via a petrol interceptor.  Oil leakage or spillage shall be contained and cleaned up immediately.  Waste oil shall be collected and stored for recycling or disposal,  in accordance with the Waste Disposal Ordinance.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance

Waste Disposal Ordinance

 

 

Storage and Handling of Oil, Other Petroleum Products and Chemicals

 

 

 

 

 

 

 

5.7

C11

All fuel tanks and chemical storage areas shall be provided with locks and be sited on sealed areas.  The storage areas shall be surrounded by bunds with a capacity equal to 110% of the storage capacity of the largest tank to prevent spilled oil, fuel and chemicals from reaching the receiving waters.  The Contractors shall prepare guidelines and procedures for immediate clean-up actions following any spillages of oil, fuel or chemicals.

At all construction work site, throughout the whole duration of the construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Water Pollution Control Ordinance


6.7.1

 

WASTE - Construction Phase

 

 

 

 

 

 

 

 

 

The following procedures and measures shall be implemented when handling waste material.

 

 

 

 

 

 

 

 

 

 

Dredged/Excavated Sediment

 

 

 

 

 

 

 

6.7.1

D1

Potential impacts associated with the exposure to and disposal of contaminated sediments could be mitigated by adopting the following measures:

 

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance, EPDTC 1-1-92

 

6.7.1

D2

·       minimising exposure to any contaminated material by the wearing of protective gear such as gloves, providing adequate hygiene and washing facilities, and preventing eating during dredging/excavation;

 

 

 

 

 

 

 

6.7.1

D3

·       any contaminated sediment dredged should not be allowed to stockpile on the site and should be immediately removed from site once dredged;

 

 

 

 

 

 

 

6.7.1

D4

·       all vessels for marine transportation of dredged sediment should be fitted with tight fitting seals to their bottom openings to prevent leakage of materials; and

 

 

 

 

 

 

 

6.7.1

D5

·       loading of barges and hoppers should be controlled to prevent splashing of dredged material to the surrounding water, and barges or hoppers should under no circumstances to be filled to a level which will cause other overflowing of materials or polluted water during loading or transportation.

 

 

 

 

 

 

 

 

 

Use of Public Fill for Reclamation

 

 

 

 

 

 

 

6.7.1

D6

The Contractor should enforce strict application of the public fill license and monitor the material placed in the reclamation and barges to control disposal of unauthorised material.  The Contractor shall also provide floating booms and collect any floating materials on a daily basis at the public filling area.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

Excavated Material

 

 

 

 

 

 

 

6.7.1

D7

Wherever practicable, excavated materials should be segregated from other wastes to avoid contamination thereby ensuring acceptability at public filling areas or reclamation sites and avoiding the need for disposal at landfill.  The priority for off-site disposal of surplus excavated material should be as follows:

·       transport to other reclamation sites at North Lantau and Penny's Bay areas; and

·       transport to public filling areas.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

 

Measures Taken in the Planning and Design Stages to Reduce the Generation of C&DM

 

 

 

 

 

 

 

6.7.1

D8

The following waste management hierarchy shall be followed:

1.     avoidance and minimisation, that is, not generating waste through changing or improving practices and design;

2.     reuse of materials, thus avoiding disposal (generally with only limited reprocessing);

3.     recovery and recycling, thus avoiding disposal (although reprocessing may be required); and

4.     treatment and disposal, according to relevant law, guidelines and good practice.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D9

Records of quantities of wastes generated, recycled and disposed (locations) shall be properly kept.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D10

Any clean excavated soil shall be reused on site as far as possible for landscape works in order to minimise the amount public fill to be disposed off-site. Should there be any surplus public fill generated from the project, the Contractors shall liaise with the Fill Management Committee to identify as far as possible suitable reclamation or site formation projects near the project site to reuse the material.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

6.7.1

D11

The design of the foundation works will minimise the amount of excavated material to be generated.  Should piling be required, H-piling will be used as far as practical.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

6.7.1

D12

The purchasing of construction materials will be carefully planned in order to avoid over ordering and wastage of construction materials, such as ready mixed concrete.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

Measures To be Taken in the Construction Stage To Reduce the Generation of C&DM

 

 

 

 

 

 

 

6.7.1

D13

The Contractor shall recycle as much as possible of the C&D material on-site.  Public fill and C&D waste shall be segregated and stored in different containers or skips to enhance reuse or recycling of materials and their proper disposal.  Concrete and masonry, for example can be crushed and used as fill and steel reinforcing bar can be used by scrap steel mills.  Different areas of the work sites should be designated for such segregation and storage.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D14

The use of wooden hoardings shall not be allowed. An alternative material, for example, metal (aluminium, alloy etc) shall be used.

To be implemented at all worksites where a site boundary adjoins a road, street or other area accessible to the public. The hoarding shall be erected throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

 

 

Chemical Waste

 

 

 

 

 

 

 

6.7.1

D15

For those processes which generate chemical waste, it may be possible to find alternatives which generate reduced quantities or even no chemical waste, or less dangerous types of chemical waste.  Containers used for storage of chemical wastes should:

·       be suitable for the substance they are holding, resistant to corrosion, maintained in a good condition, and securely closed;

·       have a capacity of less than 450 L unless the specifications have been approved by the EPD; and

·       display a label in English and Chinese in accordance with instructions prescribed in Schedule 2 of the Regulations.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance, Waste Disposal (Chemical Waste) (General) Regulation, and Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

6.7.1

D16

The storage area for chemical wastes should:

·       by clearly labelled and used solely for the storage of chemical waste;

·       be enclosed on at least 3 sides;

·       have an impermeable floor and bunding, of capacity to accommodate 110% of the volume of the largest container or 20% by volume of the chemical waste stored in that area, whichever is the greatest;

·       have adequate ventilation;

·       be covered to prevent rainfall entering (water collected within the bund must be tested and disposed as chemical waste if necessary); and

·       be arranged so that incompatible materials are adequately separated.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance, Waste Disposal (Chemical Waste) (General) Regulation, and Code of Practice on the Packaging, Handling and Storage of Chemical Wastes

 

 

Management of General Refuse

 

 

 

 

 

 

 

6.7.1

D17

General refuse generated on-site shall be stored in enclosed bins or compaction units separate from construction and chemical wastes.  A reputable waste collector shall be employed by the contractor to remove general refuse from the site, separately from construction and chemical wastes, on a daily basis to minimise odour pest and litter impacts.  The burning of refuse shall not be permitted.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D18

Reusable rather than disposable dishware shall be used if feasible. Separate, labelled bins shall be  provided, if feasible, for the collection of aluminium cans.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D19

The Contractor shall participate in a local waste collection scheme, if one is available, to reduce office wastes.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

6.7.1

D20

A trip-ticket system should be established and used to monitor the disposal of C&DM and solid wastes at public filling facilities and landfills, and to control fly-tipping. 

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

Works Bureau Technical Circular No 5/99

6.7.1

D21

A recording system for the amount of waste generated, recycled and disposed of (including the disposal sites) shall be established during the construction stage.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

 

Staff Training

 

 

 

 

 

 

 

6.7.1

D22

Training shall be provided to workers on the concepts of site cleanliness and on appropriate waste management procedures, including waste reduction, reuse and recycling at the beginning of the contract.

To be implemented at all worksites throughout the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

 

Waste Management Plan

 

 

 

 

 

 

 

6.7.1

D23

The construction Contractors shall incorporate the above recommendations into a Waste Management Plan for the construction works.  Such a management plan shall incorporate site specific factors, such as the designation of areas for the segregation and temporary storage of reusable and recyclable materials.

To be produced by all construction contractors prior to, and throughout, the full duration of the construction phase

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

Waste Disposal Ordinance

 

 

 

 

TERRESTRIAL ECOLOGY - Construction Phase

 

 

 

 

 

 

 

 

 

Habitat/Vegetation Loss

 

 

 

 

 

 

 

7.7.1

E1

Compensatory tree plantation (not less than 4.5 ha) on the adjacent hill side to the east of Ngong Shuen Au for the loss of approximately 1.4  ha of  the secondary woodland at Ngong Shuen Au.  Species used for planting should take reference from the species identified in the Tree Survey and be native to Hong Kong or South China region. 

Ngong Shuen Au secondary woodland/ During design and construction stage /At the end of construction period

CED/Contractors/ AFCD

ü

ü

ü

 

 

7.7.1

E2

Adjust development/construction area to avoid/minimize direct impact on locally restricted plant Thespesia populnea at Pa Tau Kwu Pak Wan.  Only certain individuals and part of the habitat of Thespesia populnea would be affected if avoidance of these plant species is not possible, transplanting the affected individuals to the vicinity areas, if situation permits, should be undertaken for the mitigation.

Pa Tau Kwu Pak Wan / During design and construction stage /At the end of construction period

CED/Contractors

ü

ü

ü

 

 

 

 

White Bellied Sea Eagle

 

 

 

 

 

 

 

7.7.2

 

 

E3

Protect the Pa Tau Kwu secondary woodland area where the pair of White-bellied Sea Eagles are present.  The Pa Tau Kwu area has been zoned Conservation Area in the RODP.  Additionally, a buffer area comprising a lagoon of approximately 10 ha will be formed surrounding the woodland area to reduce any potential indirect disturbance from NSLD, CKWLR and the Theme Park and associated developments.

Pa Tau Kwu secondary woodland/ Detailed design stage/At the end of detailed design stage

 

CED/Contractors

ü

 

 

 

 

7.7.2

E4

Schedule CKWLR blasting activities, within 500 m from the nesting site in the Pa Tau Kwu woodland, outside the White-bellied Sea Eagles breeding period (generally October to April)..

At all construction work sites within 500 m from the nesting site of the White-bellied Sea Eagles in Pa Tau Kwu secondary woodland/Throughout the whole construction period /At the end of construction period

CED/Contractors

 

ü

 

 

 

7.7.2

E5

Prohibit construction workers access to the nesting site of White-bellied Sea Eagles at Pa Tau Kwu secondary woodland through warning and regular audit by Site Engineer, and fence off the public land access from the development areas.

At all construction work sites close to Pa Tau Kwu secondary woodland/Throughout the whole construction period /At the end of construction period

CED/Contractors

 

ü

 

 

 

 

 

Stream Habitat

 

 

 

 

 

 

 

7.7.2

E6

Avoid any development, particularly the trails connecting Mong Tung Hang to lookout areas on Fa Peng Teng, to affect the natural Mong Tung Hang Stream, particularly the lower stream section where the locally rare Rice Fish was recorded.

Mong Tung Hang Stream / During design and construction stage /At the end of construction period

CED/Contractors

ü

ü

 

 

 

7.7.2

E7

Design the proposed Water Service Reservoirs and Waterworks reserve at Yam O Tuk to avoid the freshwater stream course.

Yam O Tuk Stream/ During design and construction stage /At the end of construction period

CED/Contractors

ü

ü

 

 

 

7.7.2

E8

Design and construct 220 m long drainage channels along the CKWLR to mimic natural streams to compensate for the unavoidable loss of stream courses due to the CKWLR construction.  The created stream courses should have natural substrate so as to provide suitable habitats for the colonization of stream invertebrates.  The stream habitats will be restored partly by natural silting due to flow from upper stream.  Selected substratum should resemble the existing stream conditions and large granite boulders may be placed at the upstream section so that these boulders will be weathered naturally to smaller pebbles and fine particles, forming natural stream substrate.

Stream behind the CLP Penny’s Bay Gas Turbine Plant / During design and construction stage /At the end of construction period

CED/Contractors

ü

ü

 

 

 

 

 

Construction Practice

 

 

 

 

 

 

 

7.7.3

E9

Erect wooden fences where practical along the boundary of construction sites before the commencement of works to prevent tipping, vehicle movements, and encroachment of personnel into adjacent areas, particularly where the rare/protected species, such as rare Rice FishOryzias latipes in Mong Tung Hang stream, White-bellied Sea Eagles Haliaeetus leucogaster at Pa Tau Kwu woodland, Pitcher Plant Nepenthes mirabilis,Fimbristylis acuminata and Fimbristylis complanata behind Cheoy Lee shipyard, are located;

At all construction work sites particularly the areas close to freshwater wetland behind Cheoy Lee shipyard, Pa Tau Kwu secondary woodland and Mong Tung Hang stream /Throughout the whole construction period /At the end of construction period

 

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

7.7.3

E10

Reinstate temporary work sites/disturbed areas to its original condition immediately after completion of the construction;

At all construction work sites /Throughout the whole construction period /At the end of construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

7.7.3

E11

Select haul routes, storage and works areas etc. to avoid or minimize disturbance to ecologically significant areas;

At all construction work sites /Throughout the whole construction period /At the end of construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

7.7.3

E12

Check the work site boundaries regularly to ensure that they are not exceeded and that no damage has been caused to surrounding natural habitats;

At all construction work sites /Throughout the whole construction period /At the end of construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

7.7.3

 

 

 

E13

Prohibit and prevent open fires within the work site boundary during construction and provide temporary fire fighting equipment in all work areas..

At all construction work sites /Throughout the whole construction period /At the end of construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

 

ü

 

 

 

-

7.7.3

E14

Ensure no access for site workers or delivery of machinery from Pa Tau Kwu Pak Wan and Pa Tau Kwu Nam Wan

 

At all construction work sites /Throughout the whole construction period /At the end of construction period

To be implemented by the Contractors and enforced by the Engineer/ENPO

 

ü

 

 

 

 

 

MARINE ECOLOGY AND FISHERIES - Construction Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

11.6

 

ARCHAEOLOGY AND CULTURAL HERITAGE - Construction Phase

 

 

 

 

 

 

 

11.6

F1

Detailed design on structural support for the CKWLR at the original coastal areas at Cheoy Lee Shipyard (CLS) site should be avoided and kept the potential impact to an absolute minimum. . An opportunity shall be provided for an archaeological field evaluation at the coastal area of existing CLS after its resumption, as part of the Schedule 2 EIA for the Shipyard decommissioning.  If preservation in situ is not possible for the archaeological deposit identified under the CLS decommissioning EIA, the impacted archaeological deposits should be mitigated by rescue excavation.   However, as the Penny’s Bay reclamation would result in limitation for future archaeological investigation at the area.  A total rescue excavation instead of a partial rescue excavation could be considered to preserve the site by record in totality.

The original coastline at the CLS site, prior to the construction of the CKWLR, PBRL and Road B2.

CED and AMO/LCSD

ü

 

 

 

Antiquities and Monuments Ordinance (Cap. 53)

11.6

F2

As the Chok Ko Wan archaeological may potentially filled up due to the Penny’s Bay reclamation and the site may potentially impacted by the structural support and construction work of the CKWLR, having considered that this site has been investigated a number of times and partially destroyed by the construction of the CLP power station, only partially preservation in situ is possible.  It is, therefore, recommended that a full rescue programme be implemented prior to the reclamation of this site to allow preservation by record in totality.

Chok Ko Wan archaeological site/prior to the site is filled due to the Penny’s Bay reclamation.

CED and AMO/LSCD

ü

 

 

 

Antiquities and Monuments Ordinance (Cap. 53)

11.6

F3

The detailed design of the CKWLR alignment should avoid the direct impact to the built structure as far as possible and the adverse visual impact to be mitigated through properly design of landscaping features.

A built structure to the northwest of Pa Tau Kwu during detail design stage of the CKWLR

Design Engineer

ü

 

 

 

 

11.6

F4

The detailed design of the structural support location of the CKWLR should avoid the direct impact and kept the impact to the Pa Tau Kwu Pak Wan archaeological site in an absolute minimum.  If the impact is proven unavoidable, the impacted area should be preserved by record, i.e. by partial rescue excavation.

Pa Tau Kwu Pak Wan archaeological site during the detail design stage of the CKWLR

Design Engineer

ü

 

 

 

 

11.6

F5

To ensure that construction activities avoided impacting upon the Pa Tau Kwu archaeological sites, Pa Tau Kwu Pak Wan archaeological site, a built structure near Pa Tau Kwu, a stone tablet at the cliff near Pa Tau Kwu Pak Wan and two grave sites near the CLP power station, these areas  should marked on all construction plans as “temporary protection areas”.  The sites boundary should be marked on physical sites, with the inclusion of at least 5 m buffer zone, so that construction worker’s attention and to ensure that they do not enter onto these sites.  And no direct impact and no soil disturbance at the archaeological sites are allowed.

Prior to and during any works with the potential to impact upon the Pa Tau Kwu and Pa Tau Kwu Pak Wan archaeological sites; a built structure to the northwest of Pa Tau Kwu and two grave sites to the east of CLP power station.

CED and the Contractors

ü

ü

 

 

 

11.6

F6

Access to the grave sites may be impacted during construction, therefore, the grave owners should be informed so that special arrangement to visit to sites is possible when necessary.  The Detailed Development Plan should retain any access possibility to the grave sites for future visitors after the completion of the developments.

Prior to and during any works with the potential to impact upon the access to the grave sites

CED and the Contractors

ü

ü

 

 

 

 

 

CONTAMINATED LAND - Construction Phase

 

 

 

 

 

 

 

12.7.2

G1

Although not included within the scope of the original Study Brief issued by the EPD for the Theme Park and associated developments, the Cheoy Lee Shipyard shall be appropriately remediated prior to the implementation of Road P2, the Chok Ko Wan Link Road and the Penny’s Bay Rail Link. The detailed requirements for the remediation of this site, to the satisfaction of the EPD, shall be assessed as part of the Schedule 2 EIA for the Decommissioning of the Cheoy Lee Shipyard, and an Environmental Permit shall be obtained before the decommissioning works are commenced.

Prior to any remediation works being conducted

CED

ü

ü

 

ü

EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repair/Dismantling Workshops

Professional Persons Environmental Consultative Committee Practice Note 3/94 -  Contaminated Land Assessment and Remediation (ProPECC PN 3/94)

 

 

LANDSCAPE AND VISUAL - Construction Phase

 

The following landscape and visual mitigation measures shall be implemented:

 

 

 

 

 

 

 

12.7.20

H1

Minimise slope cutting subject to geotechnical and planting mitigation constraints.To be added later when supplied by Shankland Cox

At proposed slope cutting in Ngong Shuen Au and at Pa Tau Kwu throughout the construction phase.

CED

ü

ü

 

 

WBTC 25/93 Control of Visual Impact of Slopes

12.7.21

H2

Minimise loss of tree/woodland vegetation by carrying out surveys to determine requirements for retention, transplanting and compensation.

At tree/woodland areas within alignment and works area throughout the duration of construction phase.

CED

ü

 

 

 

WBTC 24/94 Tree Preservation.

12.7.22

H3

Retain stockpile and reuse quality top soil.

At all areas of top soil removal along alignment throughout the construction phase

CED

 

ü

 

 

 

12.7.35

H4

Design viaducts to minimise visual intrusion

At viaduct sections of alignment throughout the construction phase

CED

ü

 

 

 

 

*  Des = Design, C = Construction, O = Operation, Dec = Decommissioning


Table 15.1b - Implementation Schedule for the Chok Ko Wan Link Road - Operational Phase

EIARef.

EM&A Log Ref

Environmental Protection Measures

Location/Duration of Measures/Timing of Completion of Measures

Implementation Agent

Implementation Stage*

Relevant Legislation & Guidelines

 

 

 

 

 

Des

C

O

Dec

 

 

 

AIR QUALITY - Operational Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

NOISE - Operational Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

WATER QUALITY- Operational Phase

 

 

 

 

 

 

 

 

 

The following mitigation measures shall be implemented to prevent adverse operational impacts to water quality from the road links.

 

 

 

 

 

 

 

 

A1

·       all road run-off shall be collected and discharged via a stormwater drainage system;

To be incorporated into the detailed design and fully implemented prior to the use of the road links

Detailed Design Consultants

ü

ü

 

 

Water Pollution Control Ordinance

 

A2

·       oil and grit interceptors shall be incorporated into areas where spills are likely to remove any oil or grease and sediment before being diverted to the public stormwater system;

To be incorporated into the detailed design and fully implemented prior to the use of the road links

Detailed Design Consultants

ü

ü

 

 

Water Pollution Control Ordinance

 

A3

·       the contents of oil and grit interceptors shall be transferred to an appropriate disposal facility on a regular basis, the frequency of which will depend upon the amount of rainfall (ie more frequent removal during the wet season);

To be undertaken throughout the operational lifetime of the roads

Theme Park Operator

 

 

ü

 

Water Pollution Control Ordinance

 

A4

·       silt traps or sedimentation tanks shall be installed to remove suspended solids, which may contain heavy metals and PAHs, from run-off water and, in the same way as oil and grit interceptors, they should be regularly cleaned and maintained in good working condition.

To be incorporated into the detailed design and undertaken throughout the operational lifetime of the roads

Detailed Design Consultants / Theme Park Operator

ü

ü

ü

 

Water Pollution Control Ordinance

 

 

WASTE - Operational Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

TERRESTRIAL ECOLOGY - Operational Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

MARINE ECOLOGY AND FISHERIES - Operational Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

ARCHAEOLOGY AND CULTURAL HERITAGE - Operational Phase

 

 

 

 

 

 

 

 

B1

The Detailed Development Plan should retain any access possibility to the grave sites to the east of CLP power station for future visitors after the completion of the developments.

The grave sites to the east of CLP power station

CED

 

 

 

 

 

 

 

CONTAMINATED LAND - Construction Phase

 

 

 

 

 

 

 

 

 

Not applicable

 

 

 

 

 

 

 

 

 

LANDSCAPE AND VISUAL - Operational Phase

 

 

 

 

 

 

 

 

 

The following landscape and visual mitigation measures shall be implemented:

 

 

 

 

 

 

 

12.7.34

C1

Roadside planting to be designed and implemented to screen, create biodiversity and visual interest.

Along road alignment and for duration of operational phase.

CED / CCSD

ü

ü

ü

 

 

12.7.23

C2

Road slope design considerations shallinclude:
a)  use of wire mesh rather than shotcrete to allow exposed rockface
b)  bench and lift design with associated planting
c) coloured shotcrete where there is no alternative to its use

At slope cutting location along alignment for duration of operation phase.

CED

ü

ü

 

 

 

12.7.26

C3

Control highway lighting to avoid light overspill.

Along all road alignment for duration of operational phase.

CED/HyD

ü

ü

ü

 

 

 

 

EM&A REQUIREMENTS - Operational Phase

 

 

 

 

 

 

 

 

 

Terrestrial Ecology

 

 

 

 

 

 

 

 

 

Rare/Restricted/Protected Plant

 

 

 

 

 

 

 

9.1.2

C4

The affected restricted plant species, Thespesia populnea, will be transplanted to a suitably selected site (see Section 7.7.1 of the EIA Report). After transplantation of the restricted plants is complete, monitoring shall be undertaken to check the performance, health and condition of the plants and to ensure that they are experiencing no adverse effects.

The restricted plant species shall be transplanted before the works commence.  The monitoring shall be undertaken at monthly intervals for a period of three years.  The field monitoring should be evenly spread over the duration of the monitoring programme.

CED/AFCD - Monitoring shall  be undertaken , and the results reviewed by, an experienced botanist specialist

 

 

ü

 

 

*  Des = Design, C = Construction, O = Operation, Dec = Decommissioning