2.                  Project Description

2.1              Introduction

2.1.1        The proposed NLDFS developments are largely to be built on reclaimed lands to be formed between 2000 to 2028.  Key elements of the Project as shown on the Draft RODP (Figure 1.1e), which can be broadly divided into five planning areas, are described in Section 2.4.

2.2              Site Location and History

2.2.1        The NLDFS Project Area comprises the north-eastern section of Lantau Island (Figure 1.1a).  The Study Brief gives the total Project Area of 2,600 ha, of which approximately 1,500 ha on land.  The Project Area is something less than 10% of the total area of Lantau Island, with a coastline of about 8.5 km to the north, 4 km to the east, and 2.5 km to the south.  The NLDFS Project Area covers the north-eastern part of Lantau Island which comprises generally three portions:

·                      Northshore Lantau which stretches along the northern shoreline of Lantau Island between Tai Ho and Kwai Shek;

 

·                      Tsing Chau Tsai which is an upland area at North Lantau; and

 

·                      Penny's Bay Reclamation which includes the broader Penny's Bay area stretching between Sze Pak Tsui and Pa Tau Kwu, Northeast Lantau between Pa Tau Kwu and Tso Wan, and the section of CKWLR stretching between Yam O Interchange and the R10 - NLYLH toll plaza at Fa Peng.

 

2.2.2        North-east Lantau is characterised by steep terrain and rugged relief comprising limited pockets of flat land dispersed along the coast with a saddle at Ngong Shuen Au cutting the area into two uplands.  The eastern upland is dominated by hilly relief with Fa Peng Teng (273 m) as the central peak surrounded by lower ranges on all directions, including Tai Yam Teng (186 m) to the west, Ng Kwu Leng (115 m) to the north and a hilltop at Pa Tau Kwu (120 m) to the south.  The western upland, with Tai Shan (291 m) as the highest point within the Project Area.

2.2.3        The Project Area is surrounded by deep water, especially to the north where the sea is 30 m deep at only 200 m from the shore.  At Penny's Bay and the area around Siu Ho Wan, the water is much shallower, with a depth of 10 m being 1 km from the shore.

2.2.4        The eastern part of the Project Area including the proposed reclamations at Yam O, Tsing Chau Tsai East, and Penny's Bay fall within the Draft North-East Lantau OZP (S/I-NEL/5) gazetted in August 1999 (Figure 1.1b ).  The north-western part of the Project Area falls within the Siu Ho Wan Layout Plan (L\I-SHW/D) (Figures 1.1c and 1.1d).

2.3              Existing Major Developments within the Project Area

2.3.1        Village sites identified within the Project Area include recognised villages at Tai Chuen, Fa Peng, Pa Tau Kwu, Tsing Chau Tsai, Luk Keng Tsuen and Ta Pang Po and non-recognised villages located around Ngong Shuen Au, Tso Wan and Sze Pak areas (Figure 2.3a).  Field surveys conducted confirmed that most of the villages were abandoned and the only villages with habitation were Luk Keng Tsuen and Tso Wan.

2.3.2        The Cheoy Lee Shipyard currently occupying an area of about 19 ha is situated at the head of Penny's Bay(Figure 2.3b).  The area accommodates facilities for the shipyard, glass reinforced plastic (GRP) mould storage, two wet boat launching basins, three building berths within launching facilities, a slipway, and an array of buildings housing workshops, offices, stores, canteen and toilets.  The shipyard commenced operations in the 1960’s and is primarily involved in the construction and repair of GRP yachts and boats, and steel ships up to about 80 m in length.  The decommissioning of this shipyard is a Schedule 2 Designated Project under the EIAO which is subject to a separate EIA study to be commissioned by CED.

2.3.3        The Yiu Lian Dockyards (Figure 2.3c), with a site area of about 0.8 ha and two floating docks of overall length of 334 m (Floating Dock No. 3 of 252 m and No.5 of 82 m), is located at To Kau Wan.  The main operation of the shipyard is ship repairing which covers container vessels, general cargo vessels, bulk carriers, tankers and passenger vessels.  The Government Lease under which the shipyard is held expires in 2008.

2.3.4        The log pond located at Yam O Bay is operated under short-term tenancy (STT) and the Government can give 3 months notice for the operators to vacate.  The facility makes use of shallow seawater in a sheltered bay to store large logs until required for use.  It consists of piles driven into the seabed in a series of bays.

2.3.5        Hong Kong Salvage and Towage (HKST) currently moors their crane barge "Proteus 1" north of Yam O.  The 350 tonne crane barge is used for servicing HKST's fleet of tugs as well as being available for lease to undertake heavy lifting works.

2.3.6        A CLP power station (Gas Turbine Plant, GTP) is located at the eastern side of Penny's Bay.  This GTP was commissioned in 1992 with a generating capacity of 300 MW and serves as a peak load and emergency back-up facility for the airport, Tung Chung and the future developments along NLH and the Project Area.  There are three chimneys with a stack height of 50 m at the GTP (Figure 2.3d).

2.3.7        The electricity substation, near Sham Shui Kok, is part of CLP's electricity distribution system and is directly connected to Penny's Bay GTP.  A series of power lines run from the substation to Discovery Bay and Tung Chung.

2.3.8        A MTR depot is located mainly on reclaimed land at Siu Ho Wan serving the Tung Chung and Lantau Airport railways (Figure 1.1c).  The main activities include stabling, repair, overhaul and cleaning the trains.  The site has been zoned Comprehensive Development Area (CDA) under the Siu Ho Wan Layout Plan which can be redeveloped for housing and commercial purposes by decking over the depot.  However, there is currently no firm commitment from either the Government or MTRC on the redevelopment programme.

2.3.9        The North Lantau Transfer Station (NLTS) at Sham Shui Kok is a refuse transfer station operated by EPD (Figure 2.3e).  The NLTS was commissioned in April 1998 and has a design throughput of 1,200 tonnes day-1.  The station currently accepts solid wastes from Tung Chung New Town, Hong Kong International Airport, and the MTR Siu Ho Wan Depot.  Wastes are compacted into 20 feet ISO containers for bulk transfer by marine vessels to the Western New Territories (WENT) landfill for disposal.  The NLTS is equipped with odour control facilities to control odour level to within 2 odour units at its site boundaries.


2.3.10     The Siu Ho Wan Sewage Treatment Works (STW) has been designed for a peak flow of 3,750 ls-1 (2011) and 5,000 ls-1 (ultimate) by providing preliminary treatment prior to discharge through the marine outfall (Figure 2.3f).  The Outlying Islands Sewerage - Stage I Phase I project has recommended to upgrade the STW to chemically enhanced primary treatment (CEPT) plus ultra violet (UV) light disinfection.

2.3.11     The Siu Ho Wan Water Treatment Works (WTW) is about 100 m south of the NLH and is bounded by the Siu Ho Wan STW in the southwest (Figure 2.3g ).  The WTW receives its water principally from Tai Lam Chung Reservoir via a submarine water pipeline and currently has capacity for treatment 150 million litres day-1.  There are plans to upgrade the WTW to meet the fresh water demand in North Lantau.  It is planned the WTW will eventually extend treated water supply to the developments proposed in the NLDFS.

2.3.12     In addition, there are also some minor isolated utility features in the remote headland and off shore islands, such as the aviation obstacle light and marine radar station on Fa Peng Teng, and the radar station at Kau Yi Chau.

2.4              Development Programme

Planning Area 1 : Southern Reclamation at Penny's Bay

Area 1A - Theme Park/ Resort Hotel

2.4.1        An area of about 180 ha to the south of Penny's Bay has been planned for the Theme Park, itself (Phases I and II), and a resort hotels area (Figure 2.3h).  The area assigned stays within the limit of reclamation previously gazetted for Container Terminals 10 and 11 in the previous North-East Lantau Port OZP.  A 3.5 km long Resort Road (District Distributor), namely D1 and D2, with a design speed of 70 kmhr-1 has been planned around the Phases I and II of the Theme Park, respectively.

2.4.2        The Theme Park will be developed into two phases.  Phase I of the theme park (western portion of the site) is expected to be opened in Q2 2005 according to the current schedule.  The annual attendance is assumed to be 7.5 million upon opening of the theme park (daily attendance of 39,000). Full completion (Build Out) of Phase I is planned for about 2014 and is expected to attract about 10 million visitors per year.  Full completion (Build Out) of Phase II is planned for about 2024 and is expected to attract about 20 million visitors per year.

2.4.3        The Theme Park (Phase I) would be a “Magic Kingdom” type park and would include attractions (for example, rides, shows, and parades), food and beverage locations, shops and service facilities.  The maximum building height of the Theme Park (Phases I and II), as specified in the development schedule of the Draft RODP and OZP, is 100 m. Information provided by the future operator, Hongkong International Theme Parks Limited (HKITP) indicated that while the design of the Theme Park (Phases I and II) will be of predominantly low-rise, certain structures may exceed 50 m.  These structures will be located mainly at the south-eastern portion of the Phase I, which is outside 500 m from the Penny's Bay GTP.  At this stage the conceptual design of the Phase II is not available hence the maximum allowable building height of 100 m, as specified in the Draft OZP, has been assumed in this assessment.  Phase II of the Theme Park is located at approximately 750 m from the GTP.  The height of buildings/ structures within the Theme Park will be reviewed in the EIA on Construction of an International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures.

2.4.4        Two ferry piers (about 1 ha) has been planned to locate on the southern waterfront of the Theme Park (Phases I and II) to provide visitors with direct marine access (for both staff and guests) to the Theme Park and its associated developments from Central, Kowloon or nearby Discovery Bay.  Subject to demand, licensed ferry services will be tendered.  It is envisaged that vessels used will have a speed between 24 knots and 33 knots and a capacity of about 300 to 500 passengers.  Kiosks not greater than 20 m2 each and 10 in number as service trades have been considered ancillary to the "Pier" zone on the Draft OZP.  The use of fabric fender instead of tropical hardwood fender has been recommended in the pier construction.

2.4.5        An area of about 53 ha of reclaimed land at the water front of Penny's Bay has been designated for hotel uses.  A chain of hotels with low-rise structures is intended to provide overnight accommodation primarily to visitors of the Theme Park.  The hotel development associated with Phase I of the Theme Park development will have about 1,400 hotel rooms, which is also expected to be opened in 2005. Ultimately five individually-themed hotels would be built with an aggregate of approximately 7,000 rooms.  The maximum building height of the Theme Park hotels, as specified in the development schedule of the Draft RODP, is 40 m.

2.4.6        Construction of the Theme Park (Phase I) and hotels is currently assumed to be commenced in Q2 2002 for a period of about 36 months.  Construction of the Phase II of the Theme Park is currently assumed to commence in Q3 2008.

2.4.7        The Theme Park is a Schedule 2 Designated Project under the EIAO.  Environmental impacts arising from its construction and operation have been assessed in the EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures (see Section 2.6).

Area 1B - Government, Institution or Community (G/IC) Facilities

2.4.8        A strip of land of about 23 ha to the north of the Theme Park boundary has been assigned for supporting G/IC facilities related to security, rescue, parking and public transport.  It will include the Penny's Bay Rail Station and the following facilities will be provided :

·                      divisional police station,

·                      divisional fire station (including an ambulance station),

·                      bus terminus,

·                      car park,

·                      coach park,

·                      petrol filling/ service station,

·                      telephone exchange, and

·                      other utility services.

 

2.4.9        Two vehicle parking areas located to the north of the Theme Park will be provided by HKITP one for coach and one for car parking: East Public Carpark and West Public Carpark.  The parking areas will be located adjacent to the northern boundary of the Theme Park, to the south of Road P2 and on  either side of the PTI (see Figure 2.7a).  These parking areas will have a total combined area of about 11 ha and will provide parking for 300 to 600 tour coaches and 1,000 to 2,000 (Phase I - Opening Day - Phase II- Build Out, respectively) private cars.  Landscaping features will be primarily on the perimeter of the parking areas.

2.4.10     A Public Transport Interchanges will be provided by HKITP located to the north of the Theme Park between the Penny’s Bay Rail Station and Road P2.  This PTI will provide general drop off and pick up access for guests and employees of the Theme Park.

2.4.11     The maximum building height of the G/IC facilities, as specified in the development schedule of the Draft RODP, is 20 m.

Area 1C - Theme Park Extension Area or Other Tourism Uses

2.4.12     An area of about 70 ha located on reclaimed land to be formed adjacent to the Theme Park (Phase II) has been reserved for possible Theme Park Extension or other tourism uses.  An additional of about 10 ha of reclaimed land will be formed for the possible Road P2 and PBRL extensions.

2.4.13     Construction of the Theme Park Extension is currently assumed to be commenced in Q2 2026 for a period of 27 months.

2.4.14     The Theme Park Extension is a Schedule 2 Designated Project under the EIAO which will be subject to a separate EIA prior to its construction in the future (see Section 2.6).

Area 1D - Water Recreation Centre (WRC)

2.4.15     The Water Recreation Centre (about 32 ha) located to the north-west of the Theme Park (Phase I) includes an artificial lake (about 12 ha) and associated amenities (car park, access roads, footpaths, trail and boat store and landscaping).  The lake will serve the irrigation purpose for the Theme Park, as well as providing scope for public water recreation (secondary contact) uses and serve as a landscape feature.  Possible public water recreation activities on the lake include boating, sailing, canoeing, etc.  The WRC will be managed by the HKITP.

2.4.16     Planned uses for the WRC may include a boating facility, changing rooms, restaurant/dining, refreshment kiosk, canteen, and place of recreation.  Secondary uses may include storage, kitchens and food preparation areas, administrative offices, car and coach parking, and utility installation.  A small building to serve the public will be located on site in order to house water recreation uses.  The number of buildings and structures around the lake will be minimised and will be low-density and low-rise (6 m maximum height) in nature.

2.4.17     The artificial lake will be filled with fresh water comprising the runoff from the natural surrounding slopes.  Catchwaters are proposed at the toe of the natural slopes to collect runoff and convey it to two locations from which will be diverted to flow into the lake via box culverts.  It is understood that water required to maintain the lake water levels between periods of wet weather would be obtained from WSD's main supply of chlorinated water from Tai Lam Chung Reservoir, or alternatively from other planned/ proposed fresh water service reservoir at Yam O Tuk.

2.4.18     The area of the lake is approximately 12 ha with bottom level of +1.0 mPD and a top water level of +7.5 mPD.

2.4.19     To prevent loss of fresh water from the lake into the surrounding porous fill, it is proposed that the lake would be lined by a geosynthetic liner system that would include a high density polyethylene (HDPE) geomembrane sandwiched between protective geotextiles.

2.4.20     Construction of the WRC is currently assumed to commence in Q3 2003 for completion in Q4 2004.  The excavation of the lake will commence in Q2 2001.

2.4.21     The Water Recreation Centre is a Schedule 2 Designated Project under the EIAO.  Environmental impacts arising from its construction and operation have been assessed in the EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures (see Section 2.6).

Planning Area 2 : North Western Reclamation/Existing Luk Keng Headland

Area 2A : Eco Park

2.4.22     An Eco Park has been proposed on the Luk Keng Headland covering the Luk Keng Bay.  The aim of the park is to provide passive recreation in an unspoilt environment which includes woodland and natural coastline.  Eco-friendly activities such as viewing areas, boadwalk, and environmental education centre and an information centre or aviaries could be considered.  The Eco-Park would act as a buffer between the more commercial tourism uses on the Theme Park Gateway to the east and the planned residential areas at Siu Ho Wan to the west.

Planning Area 3 : North Eastern Reclamation at Yam O

Area 3A : Theme Park Gateway

2.4.23     A site covering some 20 ha has been proposed for the Theme Park Gateway which comprises of the Yam O Rail Station for the Penny's Bay Rail Link.  The aim of the development is to provide a high quality gateway function for visitors arriving at the Northshore Lantau for a total "tourism experience" which incorporates all the attractions planned in the Project Area.  The development will include retail facilities, hotel and serviced apartments.  There will also be office space in the development to build on synergy of land uses aimed for the business traveller.

2.4.24     An information centre, ticket sales, post office and police reporting centre, will also be accommodated in the site.  In addition, there will also be public car parking, public open space and a pedestrian link network.  Maximum building height of the Theme Park Gateway, as specified in the development schedule of the Draft RODP, is 30 m.

2.4.25     Construction of the theme park gateway is currently assumed to be commenced in Q1 2014 for a period of 39 months.

Area 3B : Cross Boundary Ferry Terminal

2.4.26     A Cross Boundary Ferry Terminal (CBFT) has been proposed which comprises a main pier (380 m long by 60 m wide) with 2 finger piers and a Public Transport Interchange.  The terminal building (located above the main pier) will include various government facilities, control centre, drop-off and pick-up, baggage handling, departure/ arrival, dining area, carpark and various utility services, subject to detailed design in the implementation stage.  This ferry terminal could serve mainland visitors for the Theme Park or other tourism/ recreation uses proposed. The use of fabric fender instead of tropical hardwood fender has been recommended in the pier construction.

2.4.27     Construction of the first CBFT is currently assumed to commence in Q1 2017 for completion in Q2 2018.  Construction of the second CBFT is currently assumed to commence in Q3 2029 for completion in Q2 2031.

Area 3C : Tourist and Convention Village

2.4.28     The proposed Tourist and Convention Village situated adjacent to the CBFT will occupy an area of approximately 20 ha.  The development will accommodate a large convention centre accompanied by a low-density type resort hotel.  It is assumed in this EIA that the resort hotel will be equipped with central air-conditioning system and will not be relying on openable windows for ventilation. The maximum building height of the Tourist and Convention Village, as specified in the development schedule of the Draft RODP, is 40 m.

2.4.29     Construction of the Tourist and Convention Village is currently assumed to commence in Q1 2018 for completion in Q2 2020.

Area 3D : Technodrome

2.4.30     The proposed Technodrome will form a major landmark feature covering some 20 ha to the east of the Tourist and Convention Village.  It is aimed at providing hi tech entertainment and educational facilities which use state-of-the-art equipment set in a futuristic environment.  The development could include IMAX theatres and other visual presentations based on themes related to the natural world, space or aerospace or marine issues.  This is characterised by futuristic buildings and is mostly focused on indoor recreational and educational activities.

2.4.31     Construction of the Technodrome is currently assumed to commence in Q1 2020 for completion in Q2 2022.

Area 3E : Waterfront Promenade

2.4.32     A promenade of about 2 km long and 30 m wide has been proposed along the waterfront of the proposed reclamation at Yam O.  The promenade may be connected to the Luk Keng Conservation Area footpaths in the future depending on the detailed design.

Area 3F : Service Area

2.4.33     A site of about 1.8 ha is proposed as service area for all developments within the northern reclamation.  Initial concepts for the service area are to include a refuse collection point and a petrol/ LPG station.  Coach parking to serve the Technodrome and Tourist Convention Village could also be accommodated within the service area.  The maximum building height within the service area, as specified in the development schedule of the Draft RODP, is 25 m.

Area 3G : Bus Depot and Coach Parking

2.4.34     A site of about 5.4 ha has been allocated for coach parking and bus depot south of the Technodrome and Tourist and Convention Centre.  The development is intended to serve both these developments. The maximum building height of the bus depot and coach parking area, as specified in the development schedule of the Draft RODP, is 25 m.

Planning Area 4 : North-Western Reclamation at Siu  Ho Wan

Area 4A and 4B : Residential (R2)

2.4.35     Housing development at Siu Ho Wan is planned as an extension to Tai Ho New Town.  It will extend the R2 housing developments planned under the Remaining Development on Tung Chung and Tai Ho Comprehensive Feasibility Study.  The proposed housing development will provide about 5,500 residential units with a planning population of about 13,700.  The proposed housing development will be built after the completion of the CDA development on the existing MTRC Siu Ho Wan Depot.  The maximum building height assumed within the development in this EIA is 84 m.

2.4.36     The residential development will be constructed after the completion of the MTR Siu Ho Wan Depot redevelopment. Construction of the residential development is assumed in this EIA to commence in Q1 2017 for a period of 39 months.

Area 4C : Schools

2.4.37     One primary and one secondary school have been planned within the proposed housing development for the residents.

2.4.38     Construction of the two schools is assumed to be tied in with the proposed housing development for completion in 2021.

Area 4D: Open Space

2.4.39     An open space of 10 ha has been planned immediately to the east of the residential area.  The open space will link up with the waterfront promenade.

Area 4E : Marine Unit of Special Duties Unit

2.4.40     A site of about 1 ha at Sham Shui Kok to the east of the North Lantau Transfer Station has been planned for a new Special Duties Unit (SDU) Marine Base and the Small Boat Division (SBDIV) of the Marine Police.  The facility will have marine access (two concrete piers) and car parking facilities.

Planning Area 5 : Eastern Reclamation at Fa Peng (Tsing Chau Tsai East)

Area 5A : Tourism/ Recreation Use

2.4.41     The proposed reclamation at Fa Peng provides a land parcel of approximately 32 ha.  The site has been reserved mainly for tourism and recreation purposes to tie in with the development theme of the Study Area.  A promenade of approximately 1.5 km long and 30 m wide has been proposed along the waterfront of the proposed reclamation, allowing pedestrians views of Lantau Link and Tsing Ma Gateway area.  An indicative alignment of possible PBRL extension and a station has been shown on the Draft RODP.

2.4.42     Construction of the recreational development at Tsing Chau Tsai East is currently assumed to commence in Q1 2024 for a period of 63 months.

Tso Wan Village Expansion Area

2.4.43     A Village Area to accommodate 62 small houses has been planned at Tso Wan which is a small-medium sized inhabited unrecognised village.  Currently the village contains less than 30 buildings some of which are in good condition and show signs of intermittent habitation.

2.5              Major Roads and Railway

North Lantau Highway (NLH)

2.5.1        The main highways arterial route in Lantau is the NLH.  NLH is an existing dual 3-lane expressway which runs in a south west - north east alignment along the northern shores of Lantau Island.  The NLH serves as the main road link between the Hong Kong International Airport and the rest of the HK SAR.

2.5.2        The stretch of NLH within the Project Area consists of the Kap Shui Mun Bridge in the north, making landfall at +54 mPD at Tai Chuen, to a toll plaza at +46 mPD, across the Tsing Chau Wan and Ta Shui Wan viaducts onto the reclamation.

2.5.3        The Yam O Interchange of NLH has been constructed at Ngong Shuen Au with slip roads, which will ultimately link to Route 10 via the CKWLR.

Road P1

2.5.4        Road P1 is intended as a primary distributor road serving all the developments alongside the NLH.  The road runs essentially parallel to the NLH and north of it.  Road P1 has multiple access points to the developments proposed in the Draft RODP whilst providing only limited connections with the NLH.  According to the Final Preliminary Engineering Report, traffic figures indicate that the road should be of dual-3 standard south of the proposed Conservation Area at Luk Keng, and dual-2 east of this point.

2.5.5        Road P1 commences west of MTRC Siu Ho Wan Depot, passes around the Depot on its northern seaboard, runs parallel to the NLH for about 2.7 km before entering the western portal of the Yam Tsai tunnel, and then connects with the NLH.  The connections with the NLH is via the two existing end of the slip roads (namely Link Roads 5 & 6) of the Yam O Interchange.  Road P1 will be mostly run on at-grade road formed by reclamation, except for the section between the western tunnel portal and Sham Shui Kok which will be running on an elevated structure to avoid the encroachment to the existing sub-marine cables under this area.

2.5.6        An approximately 750 m long Yam Tsai Tunnels are provided under the proposed Conservation Area at Luk Keng.  After exiting the eastern portal of the Yam Tsai Tunnel, Road P1 crosses an embayment near Yam O Wan on at-grade road with a T-junction at the eastern end, which provides access from Road P1 to the Theme Park.   The Yam Tsai Tunnel avoids extension of the present Yam O cutting into the proposed Conservation Area or the construction of an elevated viaduct adjacent to the cutting which minimise the potential landscape and visual impact.

2.5.7        The design speeds of Road P1 are 100 km hr-1 and 85 km hr-1 for the mainline and link roads, respectively.

2.5.8        Road P1 is a Schedule 2 Designated Project under the EIAO which will be subject to a separate detailed EIA prior to its construction in the future (see Section 2.6).

2.5.9        Construction of Road P1 is envisaged to commence in Q1 2015 for completion in Q4 2016.

Road P2

2.5.10     The proposed Road P2 will be dual two lanes and of about 4 km long with two roundabouts.  Road P2 commences from the proposed development at Yam O and extends the existing Cheung Tung Road at Yam O interchange from P1 Junction and then connect to Penny's Bay Roundabout, provides a link from North Lantau to CKWLR and the Theme Park, and continuous along the southern coastal line.  The road will descend from a level of about +31 mPD at Yam O with an average gradient of +1.5% to the Penny's Bay roundabout.  It will primarily run on an elevated structure.  Road P2 will be in the form of dual-2 arrangement with a design speed of 70 km hr-1 and with 4 m verge on each sides.

2.5.11     Construction of Road P2 from Yam O to the Penny’s Bay roundabout is envisaged to commence in early 2003 with construction works completed within about 28 months.

2.5.12     Road P2 is a Schedule 2 Designated Project under the EIAO.  Environmental impacts arising from its construction and operation have been assessed in the EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures (see Section 2.6).

Chok Ko Wan Link Road (CKWLR)

2.5.13     The scope of the CKWLR, in accordance with Clause 4.4.2 of the Study Brief, are as follows :

i.                     About 3.5 km of dual 3-lane carriageway with hard shoulders from Yam O Interchange to the Pa Tau Kwu headland;

 

ii.                   A grade-separated Pa Tau Kwu Interchange (previously named as Lantau Port North Interchange) with R10-NLYLH, and with connection provisions for the proposed future R10-HKLL; and

 

iii.                  Associated civil, structural, geotechnical, drainage, landscape, street, lighting, traffic aids, traffic control and surveillance systems, electrical and mechanical systems and environmental mitigation measures.

 

2.5.14     CKWLR is a key component of the Northshore Lantau study area, providing free flowing interchange between the NLH, and the Route 10-NLYLH and the Route 10 - HKLL.  In addition to this function, the CKWLR provides arterial access to the future developments on the Penny's Bay and Tsing Chau Tsai East reclamations.  CKWLR joins the NLH via the Yam O Interchange, and Route 10-NLYLH via the Pa Tau Kwu Interchange.  The design speed of CKWLR is 100 km hr-1.


2.5.15     The CKWLR also connects to the district and local road network serving the new reclamation areas in Penny's Bay and potentially to Tsing Chau Tsai East.  These connections will be via roundabouts located at Penny's Bay (referred to as the Penny's Bay roundabout) and at Pa Tau Kwu (referred to as the Pa Tau Kwu Interchange).

2.5.16     A report, entitled CKWLR Alignment and Interchange, was issued in November 1999.  The report evaluated possible variations (eight schemes) to the alignment of CKWLR in the context that the Theme Park will be located at Penny's Bay.

Table 2.5a - Options of CKWLR Alignment Evaluated

Scheme

West Section

Central Section

East Section

A

Low level alignment with Penny's Bay roundabout above

Low level road through TCT headland

Pa Tau Kwu roundabout located to the south of Pa Tau Kwu interchange

B

High level alignment with Penny's Bay roundabout below

High level road through TCT headland

Pa Tau Kwu roundabout located to the south of Pa Tau Kwu interchange

C

Low level alignment with Penny's Bay roundabout above

Low level tunnel through TCT headland

Pa Tau Kwu roundabout located within Pa Tau Kwu interchange

D

High level alignment with Penny's Bay roundabout below

High level tunnel through TCT headland

Pa Tau Kwu roundabout located within Pa Tau Kwu interchange

E

High level alignment with Penny's Bay roundabout below

Road alignment south of TCT headland parallel to Road P2

Pa Tau Kwu interchange connects directly to second Penny's Bay roundabout

F

Low level alignment with Penny's Bay roundabout above

Road alignment south of TCT headland in cut and cover tunnel below Road P2

Pa Tau Kwu interchange connects directly to second Penny's Bay roundabout

G

High level alignment with Penny's Bay roundabout below

Road alignment cutting across south TCT headland

Pa Tau Kwu interchange connects directly to second Penny's Bay roundabout

H

Low level alignment with Penny's Bay roundabout above

Hybrid of road and tunnel through TCT headland

Pa Tau Kwu roundabout located within Pa Tau Kwu interchange

I

High level alignment with Penny's Bay roundabout below

High level road through TCT headland with a short tunnel section in the central section

Pa Tau Kwu roundabout located to the south of Pa Tau Kwu interchange

 

2.5.17     Of the eight alignment schemes (A-H) considered in the option evaluation, Alignment B has been recommended as the preferred alignment based on evaluations on key disciplines which include traffic, planning, engineering, environmental, land and implementation considerations.  The CKWLR horizontal alignment is determined by the location of Penny's Bay Roundabout and the space required for Road P2 to connect to the roundabout.  The proposed horizontal alignment minimises cut slopes on the north side at the entrance to the cutting, and to the west of the roundabout the alignment is located to maximise the space available for the Water Recreation Centre.

2.5.18     An additional CKWLR option (Option I) with a tunnel in the middle of the cutting has been considered.  The option would require major cuttings at both ends.  The cutting at the eastern end would be very visible on approach from Kowloon, Tsing Yi and Hong Kong.  Though the tunnel portal itself would be hardly visible, the cutting above and around the portal would be extensive and visible from most directions.  As a result, the mitigating effect of such an option would be negligible.  From a transport perspective, the tunnel would make the necessary weaving movements impossible between the two interchanges, as lane-changing within tunnels is not permitted.  Functionally, the tunnel option cannot work from a traffic engineering point of view and therefore not considered as a viable option.

2.5.19     Crash barriers of 0.8 m high have been assumed throughout the elevated sections of the CKWLR alignment in this EIA.

2.5.20     Environmental impacts on the western CKWLR sections from Yam O Interchange to Penny's Bay roundabout within the Project Area of the EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures has been broadly addressed in the Theme Park EIA report.  Detailed assessments of the construction and operation of the road have been included in this EIA report.

2.5.21     Construction of CKWLR (Yam O Interchange to Penny's Bay roundabout section) is scheduled to commence in Q3 2002 for completion in Q1 2005.  The section from Penny's Bay Interchange to R10-NLYLH toll plaza will be constructed from Q3 2003 for completion in Q3 2005.  While the section connected from R10-NLYLH toll plaza to the long term R10-HKLL (including the Pa Tau Kwu Interchange) will be constructed from Q2 2028 for completion in Q2 2030.

Route 10 - North Lantau to Yuen Long Highway (R10-NLYLH)

2.5.22     R10-NLYLH is proposed as a dual 3-lane carriageway between Northshore Lantau and Yuen Long.  It is scheduled for completion in 2007 and will provide a second road crossing to Lantau Island to relieve the Lantau Link and also Route 3 Country Park Section, Ting Kau Bridge and part of Tuen Mun Road.  The programme of CKWLR is to tie in with the programme of R10-NLYLH.

Discovery Bay Tunnel

2.5.23     Discovery Bay Tunnel comprises of a 2 km single 2-lane carriageway from Discovery Bay to Siu Ho Wan.  The tunnel is scheduled to be in operation in mid- 2000.

Route 10 - Hong Kong Lantau Link

2.5.24     The long term R10-HKLL is proposed as a dual 3-lane all-weather carriageway between the Pa Tau Kwu Interchange on Lantau Island and the road network in the proposed Green Island Reclamation.  The need and timing of the R10-HKLL are subject to review under separate studies.  For the purpose of this EIA, the road has been assumed to be available in 2017.

Tuen Mun - Chek Lap Kok Link

2.5.25     Tuen Mun - Chek Lap Kok (TM-CLK) Link is proposed as a dual 3-lane carriageway. The need and timing of the TM-CLK Link are subject to review under separate studies.  For the purpose of this EIA, the road has been assumed to be available in 2027.

 

MTR Airport Express and Tung Chung Line

2.5.26     The twin track electrified railway serving Tung Chung (the Tung Chung Line) and the Airport Express Rail Link traverse the entire northern shore of the Project Area.  The railway runs under the road level of Kap Shui Mun Bridge into a section of tunnel at Tai Chuen, diverting south of the alignment of NLH before crossing under the north end of toll plaza out onto embankments at Tai Tsing Chau (+15 mPD) and down to the reclamation at +5.5 mPD where it generally runs parallel to the highway.

Penny's Bay Rail Link

2.5.27     A new 3.6 km long rail line, the Penny’s Bay Rail Link (PBRL), partly in a tunnel from Yam O to Penny’s Bay with new stations at Yam O and at Penny's Bay([1]) has also been planned.  The PBRL is to be constructed at grade on the Penny's Bay Reclamation, with a tunnel of approximately 850 m through Tsing Chau Tsai headland.  Portions of the track will be depressed in the vicinity of Penny's Bay Rail Station and will be shielded from the Theme Park by comprehensive landscaping and visual berms alongside the PBRL alignment.  At Yam O, the alignment is at-grade, situated on the existing reclamation level as it passes under the roads of the NLH. The opening of Yam O, Penny's Bay Rail Stations and the Penny’s Bay Rail Link are expected to be tied in with the commissioning of the Theme Park and its associated developments in 2005.

2.5.28     The Penny's Bay Rail Link is a Schedule 2 Designated Project under the EIAO.  Environmental impacts arising from its construction and operation for the section from Yam O to Penny's Bay have been assessed in the EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures (see Section 2.6).  The proposed extension of the PBRL to the Tsing Chau Tsai East Reclamation and Hong Kong Island, as shown in the Draft RODP, will be subject to further EIA for its Environmental Permit application.

2.6              EIA Ordinance Requirements and Designated Projects

2.6.1        The Project comprises a number of individual elements which are classified as Designated Projects (DPs) under Schedule 2, Part I of the EIAO; DPs require an EIA and Environmental Permit (EP) before their construction and operation.  The DPs that have been identified are presented in Table 2.6a.


Table 2.6a - Schedule 2 Designated Projects

Schedule 2

Description

Schedule 2 EIAO Reference

Part I - A - Roads, Railways and Depots

·       Approx.  3.5 km long Chok Ko Wan Link Road (Expressway Standard)

·       Approx. 4 km long Road P1

(Primary Distributor)

·       Approx. 4 km long Road P2 (Primary Distributor)

·       Approx. 3.5 km long Resort Road (District Distributor)

Part I - A.1

 

Part I - A.1

 

Part I - A1

 

Part I - A.1

 

 

·       3.6 km. Penny’s Bay Rail Link  and its associated stations (including 850 m of tunnel)

Part I - A.2, A.4 and A.7

Part I - C - Reclamation, Hydraulic and Marine Facilities, Dredging and Dumping

·       All reclamation works more than 5 ha in size including Penny's Bay Stages I and II (280 ha), Yam O (10 ha), Northshore Lantau (65 ha), Tsing Chau Tsai East (74 ha), Theme Park Extension (80 ha), and Siu Ho Wan (39 ha)

Part I - C.1, C.2, C.11 and C.12

Part I - I - Waterways and Drainage Works

·       12 ha artificial lake at the Water Recreation Centre (designed as a flood storage pond)

·       Stormwater drainage channel (discharges within 300 m of Pa Tau Kwu and Fa Peng Archaeological Site).

Part I - I.2 and O.8

 

Part I - I.1(b) (ii)

Part I - O - Tourist and Recreational Developments

·        Theme Park (Phases I and II) at Penny's Bay and associated developments with an area of about 180 ha

·       Theme Park Extension to the south of Pa Tau Kwu with an area of about 70 ha

Part I - O.8

 

 

Part I - O.8

Part II - Decommissioning Projects

·       Decommissioning of Cheoy Lee Shipyard with an area of about 19 ha

Part II - Item 17

 

2.6.2        Apart from the CKWLR section from Yam O Interchange to R10-NLYLH toll plaza which has been designed to preliminary design level which has been assessed in detail to the Schedule 2 EIA level for the Project Proponent's environmental permit (EP) application, all other Schedule 2 DPs are subject to separate EIAs for their EPs application.  A total of 9 DPs have been included in the concurrent Schedule 2 EIA on Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures (Study Brief Ref. ESB-043/1999).  These include :

1.                  Penny's Bay Reclamation (about 280 ha);

2.                  Yam O Reclamation for the temporary PTI (10 ha);

3.                  The Theme Park Phases I and II (about 180 ha including hotels);

4.                  Stormwater drainage channel discharge to the east of Penny's Bay within 300 m of the existing Pa Tau Kwu archaeological site;

5.                  The 3.6 km Penny's Bay Rail Link (including 850 m of tunnel) and its associated Yam O Rail Station and Penny's Bay Rail Station;

6.                  Road P2 (approximately 4 km long section of distributor road standard);

7.                  Resort Road D1 and D2 (approximately 3.5 km long of distributor standard);

8.                  The artificial lake (about 12 ha) at the Water Recreation Centre; and

9.                  Approximately 1.5 km section of Chok Ko Wan Link Road.

 


2.6.3        The findings of the EIA Study for the Construction of an International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructures has been broadly discussed in this report along with the evaluation of the cumulative environmental impacts.

2.6.4        For this EIA, it is assumed that the large-scale recreational development such as the Technodrome and the Tsing Chau Tsai East recreational area are not considered as Schedule 2 Designated Projects under the EIAO.  This may have to be reviewed when the detailed design of the proposed developments are available.

2.6.5        Schedule 2 DPs identified within the Draft RODP which may require further detailed assessments for their EPs application include the following :

1.                  Road P1 (Primary Distributor) of about 4 km;

2.                  Distributor Road for the Theme Park Extension (about 1 km);

3.                  Possible future Penny's Bay Rail Link Extension from Theme Park to Tsing Chau Tsai East Reclamation and Hong Kong, and its associated stations;

4.                  Reclamations proposed at Northshore Lantau (65 ha), Tsing Chau Tsai East (74 ha), Theme Park Extension (80 ha), and Siu Ho Wan (39 ha) including Special Duties Unit and Small Boat Division Marine Base and Road P2 (Siu Ho Wan to Ta Pang Po section);

5.                  Proposed drainage within 300 m from the Fa Peng archaeological site;

6.                  Theme Park Extension development (about 70 ha); and

7.                  Decommissioning of Cheoy Lee Shipyard.

 

2.7              EIA Study Assessment Areas

2.7.1        Various boundary conditions for assessing the environmental consequences of the developments included within the scope of the CKWLR EIA have been specified under Clause 4.2 of the Study Brief as below.

2.7.2        The boundary of the "Study Area" for the purpose of this EIA shall be of 300 m from either side and along the full stretch of the proposed road alignment, except that, for landscape impact and air pollution assessment, the study area shall generally be defined by a distance of 500 m from the proposed road alignment.  However, all sensitive receivers regarding the visual impact assessment shall be assessed regardless of the distance from the proposed road alignment.

2.7.3        With respect to noise impact assessment, the Study Area may be reduced accordingly if the first layer of noise sensitive receivers, closer than 300 m from the road, provide acoustic shielding to those receivers at further distance behind.  All the figures of distance mentioned above shall be measured at the edge of kerb or hard shoulder whichever is applicable.

2.7.4        Where sensitive receptors that may be potentially affected by Project activities have been identified beyond the above boundary conditions, the assessment areas have been extended to cover such areas. Such assessment areas are described in relevant technical sections.


2.8              Reclamation Construction Schedule

2.8.1        The currently proposed programme for reclamation works is summarised in Table 2.8a and Annex A; Figure 2.8a shows the reclamation elements.

Table 2.8a - Reclamation Construction Schedule (According to NLDFS Recommendation)

Activity

Start

Finish

Penny’s Bay Reclamation  (Stage I)

 

 

Dredging

Q2 2000

Q4 2001

Seawall Construction

Q3 2000

Q2 2002

Filling

Q4 2000

Q2 2002

Surcharge

Q1 2001

Q3 2002

Penny's Bay Reclamation (Stage II)

 

 

Dredging

Q3 2001

Q1 2005

Seawall Construction

Q4 2001

Q3 2005

Filling

Q2 2003

Q2 2007

Surcharge

Q3 2003

Q4 2008

Yam O (10 ha)

 

 

Dredging

Q4 2001

Q4 2002

Seawall construction

Q3 2002

Q1 2003

Filling

Q4 2002

Q2 2003

Surcharge

Q1 2003

Q3 2003

Northshore Lantau

Dredging

Q1 2012

Q2 2017

Seawall construction

Q2 2012

Q3 2017

Filling

Q3 2012

Q4 2017

Surcharge

Q4 2012

Q1 2018

Siu Ho Wan

Dredging

Q3 2014

Q2 2015

Seawall construction

Q4 2014

Q3 2015

Filling

Q1 2015

Q4 2015

Surcharge

Q2 2015

Q1 2016

Fa Peng (Tsing Chau Tsai East)

Dredging

Q2 2022

Q3 2025

Seawall construction

Q3 2022

Q4 2025

Filling

Q4 2022

Q1 2026

Surcharge

Q1 2023

Q2 2026

Theme Park Extension

Dredging

Q2 2026

Q3 2027

Seawall construction

Q3 2026

Q4 2027

Filling

Q4 2026

Q1 2028

Surcharge

Q1 2027

Q2 2028

Note: Q1 represent first quarter etc.

For the purpose of this EIA, the Penny's Bay (Stage II) reclamation works is based on a fast track programme to ascertain the worst possible adverse environmental impacts.

 

Penny's Bay Reclamation

2.8.2        The Penny's Bay Reclamation was gazetted under the Foreshore and Seabed (Reclamations) Ordinance on 15 and 22 October 1999.  Reclamation of about 280 ha of land within Penny’s Bay using marine sand fill and public filling materials will be undertaken. Average reclamation level is assumed to be varied from +6.5 to +8 mPD.

2.8.3        Land for the Theme Park Developments will be formed by land reclaimed from the sea. The reclamation will be undertaken in a two-stage reclamation programme (Penny’s Bay Reclamation Stages I and II). Penny’s Bay Reclamation Stage I will cover the Theme Park Phase I area, area north of the Theme Park Phase I (including area for the WRC) and part of the Theme Park Phase II area. Penny’s Bay Reclamation Stage II will cover the remaining Theme Park Phase II area and area for associated infrastructure.

2.8.4        Stage I of the Penny's Bay Reclamation, which will commence in Q2 2000 for completion in Q3 2002, comprises formation of 200 ha of land at Penny's Bay.  It comprises dredging and reclamation works of 126 ha for the Theme Park Phase I and 74 ha outside the theme park (Phase I) area including the Water Recreation Centre, road infrastructures and the Government, Institution and Community facilities.  Dredging in Penny’s Bay is expected to be carried out using a combination of Trailing Suction Hopper Dredger (TSHDs), commonly referred to as a trailer dredger, and grab dredgers.  The maximum cumulative dredging rate for this equipment spread will be about 634,000 m3 week-1.  Stage II reclamation works for the Theme Park (Phase II) are currently envisaged to be completed by Q1 2006.

2.8.5        A permanent 3.3 km seawall comprising sloping and vertical blockwork will be constructed around the seaward boundary of the reclamation to protect the reclamation site from wave and tidal action.  The seawall will be constructed to achieve a minimum height of +6.5 m mPD (after settlement).  A wave return structure (about 0.5 m high) will be provided on top of the seawall to protect against overtopping.

2.8.6        Sand is likely to be delivery to the site filling by THSDs; the maximum anticipated filling rate will be 994,800 m3 week-1.  It is understood that part of the Penny's Bay Reclamation sand sill material will be placed within a rehandling basin and will be transferred to the fill face by cutter suction dredger.  Marine sand and public fill will be will be used for the both the Stage I and II reclamations.  It is estimated that some 65 Mm3 of sand, 2 Mm3 of public fill will be required for Stage I reclamation.  Stage II reclamation is expected to require some 7.4 Mm3 of sand, 11 Mm3 of public fill, of which 2.5 Mm3 is used for surcharge material.

2.8.7        It is currently envisaged that the majority of Project fill material will be sourced from the Wailingding Marine Borrow Area which is in Mainland waters.  A small portion of the sand fill material is likely to be obtained from the East Lamma Channel Marine Borrow Area.  The East Lamma Channel Marine Borrow is allocated by the Fill Management Committee (FMC).

Yam O Reclamation (10ha)

2.8.8        A 10 ha reclamation has been proposed at Yam O for the construction of a temporary public transport interchange and for part of the Road P2.  Dredging of the seawall will be commenced in Q1 2002 and the entire reclamation works is expected to be completed in Q3 2003.  Dredging is expected to be carried out using a single grab dredger working at a rate of about 2,000 m3 day-1.  A seawall of about 0.7 km long will be constructed to retain the fill.  Average reclamation level is assumed to be +5.5 mPD.

2.8.9        The Yam O Reclamation requires approximately 1.7 Mm3 of fill material, public fill will be used as far as practicable for the reclamation.  It is estimated that about 0.9 Mm3 (about 64% of the fill requirement) of public fill will be used for the reclamation and the balance will be sand fill (about 500,000 m3 which will mainly used for the construction of the seawall and the sand blanket laid on top of the marine mud left in place). Filling will be carried out by bottom dumping from split barges at a working rate of 14,000 m3 day-1.

Northshore Lantau

2.8.10     An additional 65 ha reclamation has been proposed along the northshore of the Project Area from Yam O to To Kau Wan. Dredging of the seawall will be commenced in Q1 2012 and the entire reclamation works is expected to be completed in Q1 2018. Dredging in northshore reclamation is expected to be carried out using a maximum of 1 grab dredger.  The maximum dredging and filling rates for the Northshore Lantau reclamation are estimated to be 2,000 m3 day-1 and 8,000 m3 day-1, respectively. A seawall of about 3.2 km long will be constructed to retain the fill. Average reclamation level is assumed to be +5.5 mPD.

2.8.11     The total fill volume is estimated to be approximately 4.7 Mm3, of which about 3.3 Mm3 will be by public filling.  In addition, total surcharge volume is estimated to be 2.3 Mm3 by public filling.

Tsing Chau Tsai East

2.8.12     Reclamation at Tsing Chau Tsai East from Sam Chuen to Pa Tau Kwu comprises a total area of 74 ha.  The reclamation will be formed in three periods, namely CKWLR Phase I reclamation for CKWLR and R10-NLYLH sections including the R10 toll plaza, CKWLR Phase II reclamation for the CKWLR section connected to the R10-HKLL and the Pa Tau Kwu Interchange, and the Fa Peng reclamation for proposed recreational uses. Average reclamation level is assumed to be +5.5 mPD.

2.8.13     The CKWLR Phase I reclamation (17 ha) will be reclaimed from Q1 2002 for completion in Q1 2004 to provide land for the construction of CKWLR section (north of Pa Tau Kwu to the Route 10 toll plaza), the R10 toll plaza and the R10 section (Sam Chuen to Fa Peng).  The volume of fill required for CKWLR Phase I reclamation is estimated to be approximately 2.4 Mm3, of which about 1.8 Mm3 will be by public filling.  The surcharge volume is estimated to be 1 Mm3 by public filling.

2.8.14     The CKWLR Phase II reclamation (25 ha) for the CKWLR connection to R10-HKLL including the Pa Tau Kwu Interchange will be commenced in Q2 2006 for completion in 24 months.  The volume of fill required for CKWLR Phase II reclamation is estimated to be approximately 3.7 Mm3, of which about 3 Mm3 will be by public filling.  The surcharge volume is estimated to be 1.5 Mm3 by public filling.

2.8.15     The Fa Peng Reclamation comprises an area of 32 ha.  Dredging of the seawall of the Fa Peng reclamation will be commenced in Q2 2022 for completion in 48 months. The volume of fill required for Fa Peng reclamation is estimated to be approximately 4.7 Mm3, of which about 3.8 Mm3 will be by public filling.  The surcharge volume is estimated to be 1.9 Mm3 by public filling.

2.8.16     Dredging in TCT East is expected to be carried out using a maximum of 3 grab dredgers.  The maximum dredging and filling rates for the TCT East reclamation are both estimated to be 6,000 m3 day-1.  A seawall of about 2.5 km long will be constructed to retain the fill.

2.8.17     In summary, the total fill volumes for Tsing Chau East is therefore estimated to be approximately 10.8 Mm3, of which about 8.6 Mm3 will be by public filling.  Total surcharge volume is estimated to be 4.4 Mm3 by public filling.

Theme Park Extension

2.8.18     Reclamation of about 80 ha has been proposed between Pa Tau Kwu south and Phase II of the Theme Park for the possible Theme Park Extension or other recreational uses. Dredging of the seawall will be commenced in Q2 2026 and the entire reclamation works is expected to be completed in 24 months.  Dredging in the Theme Park Extension is expected to be carried out using a maximum of 3 grab dredgers.  The maximum dredging and filling rates for this reclamation are estimated to be 6,000 m3 day-1 and 28,000 m3 day-1, respectively.  A seawall of about 1.4 km long will be constructed to retain the fill. Average reclamation level is assumed to be varied from +6.5 to +8 mPD.

2.8.19     The total fill volume is estimated to be approximately 14.2 Mm3, of which about 11.8 Mm3 will be by public filling.  Total surcharge volume is estimated to be 4.8 Mm3 by public filling.

Siu Ho Wan

2.8.20     Reclamation of 39 ha has been proposed from Ta Pang Po to Siu Ho Wan for the Road P1 section (8 ha), the SDU and SBDIV Marine Base (1 ha) at Sham Shui Kok, and the proposed R2 residential development and schools (30 ha).  Except for the SDU and SBDIV Marine Base which the reclamation will commence in Q1 2002 for completion in Q4 2004, dredging of the seawall will commence in Q3 2014 and the entire reclamation works is expected to be completed in Q1 2016.  Dredging in Siu Ho Wan is expected to be carried out using a maximum of 2 grab dredgers.  The maximum dredging and filling rates for this reclamation are estimated to be about 4,000 m3 day-1 and 20,000 m3 day-1, respectively.  A seawall of about 3.7 km long will be constructed to retain the fill. Average reclamation level is assumed to be +5.5 mPD.

2.8.21     The total fill volume is estimated to be approximately 3.3 Mm3, of which about 2.1 Mm3 will be by public filling.  Total surcharge volume is estimated to be 1.6 Mm3 by public filling.

Table 2.8b - Reclamations Proposed within the Project Area

 

Reclamation

Area (ha)

Fill Volume - Sandfill (Mm3)

Fill Volume - Public Fill (Mm3)

Total Fill Volume (Mm3)

Surcharge Volume - Public Fill (Mm3)

Total Surcharge Volume (Mm3)

Penny's Bay Stage I

200

65

2

67*

---

---

Penny's Bay Stage II

80

7.4

8.5

15.9

2.5

2.5

Northshore

65

1.4

3.3

4.7

2.3

2.3

Yam O

10

0.5

0.9

1.4

0.3

0.3

Siu Ho Wan

39

1.2

2.1

3.3

1.6

1.6

TP PIII Extension

80

2.4

11.8

14.2

4.8

4.8

TCT East

74

2.2

8.6

10.8

4.4

4.4

* Includes surcharge material.

 

2.9              Project Roads Construction Works Schedule

2.9.1        A tentative schedule for all temporary and permanent road construction works for the Project is provided in Table 2.9a.


Table 2.9a - Tentative Schedule for Major Road Construction Works

Activity

Start

Finish

Temporary Access Road

Q3 2000

Q4 2000

CKWLR (Yam O Interchange to Penny's Bay roundabout)

CKWLR (Penny's Bay roundabout to R10 toll plaza)

Q4 2002

Q4 2003

Q1 2005

Q3 2005

Road P2 (Yam O to Theme Park West)

Q1 2003

Q1 2005

Road P2 (Theme Park West roundabout to Theme Park East roundabout)

Q1 2006

Q1 2008

Resort Road D1 (Theme Park Phase I)

Q1 2003

Q1 2004

Road P1

Q1 2015

Q4 2016

 

Chok Ko Wan Link Road

2.9.2        CED will be the Project Proponent for the construction of the CKWLR.

2.9.3        Key identified constraints for the alignment of the western section of the CKWLR include the Yam O Interchange, the proposed Penny’s Bay Rail Link, the Penny's Bay GTP, the need to provide a drainage reserve and the need to connect to Road P2.

2.9.4        The required works for  the construction of the CKWLR will include the use of heavy plant for excavation, drilling, piling, concreting, surfacing and structures construction.  Key activities will include:

·                      Decommissioning of Cheoy Lee Shipyard;

·                      Excavation works;

·                      Blasting works;

·                      Slope protection works;

·                      Construction of road foundations and superstructures; and

·                      Road surfacing and construction of road sections.

 

2.9.5        The construction of the CKWLR will include construction of bored pile foundations, abutment embankments and retaining structures, support piers and elevated deck sections.  Construction will be by land-based equipment and adopting pre-cast and cast-in situ methods of construction.

2.9.6        The volume of excavation and dredged material to be generated from the construction of CKWLR are 3 Mm3 and 1.8 Mm3, respectively.  The excavation and dredged material generation rates are estimated to be 6,400 m3 day-1, and 6,000 m3 day-1, respectively.  Any excavated surplus material will be used within Penny' s Bay.  Dredged material to be disposed off site to marine mud disposal site is estimated to be 3,000 m3 day-1.  Details of the construction and demolition wastes management are provided in Section 6.

2.9.7        The design traffic conditions (design flow, percentage heavy goods vehicles and design speed) for the above road, which have been used in the air and noise impact assessments are summarised in Figure 2.9a.

2.10          Stormwater Drainage, Sewerage and other Utilities

Stormwater Drainage System

2.10.1     To minimise the potential for water pollution, stormwater collected from the Theme Park development and roads, the currently proposed urban trunk drainage system (with the exception of the GTP site) will flow towards the east and discharge to the Kap Shui Mun Channel.  This drainage structure is expected to comprise of a two to three cell box culvert (3.5 m wide and 3.5 m height each) arrangement with a length of about 1.7 km.

2.10.2     Stormwater runoff from natural hill slopes surrounding Penny’s Bay, landscaped areas of the new reclamation will be collected into a separate catchwater system for discharge to the sea via an open channel of about 2.2 km in length at the southwest corner of the reclamation. The eastern stormwater drainage channel comprises an EIAO Schedule 2 Designated Project, Table 2.6a, as it discharges within 300 m of the Pa Tau Kwu archaeological site.

2.10.3     It is proposed that drainage from the Theme Park (Phases I and II) and hotel areas will discharge to the sea via a number of 1-3 cell box culverts on the southern shoreline of the reclamation.

2.10.4     The construction of drainage culverts will include box cells, de-silting facilities and manholes.  The trenches for the construction of the culverts will be excavated using land-cased equipment prior to construction of the box cells.  The construction of the box cells will adopt a combination of pre-cast and cast-in situ methods.  After construction of the culvert structure, the culvert trenches will be backfilled with selected material.

2.10.5     Road surface runoff at the Luk Keng area will be diverted away from the proposed Yam O waterway and discharged to the west of the Luk Keng headland.

2.10.6     The provisional drainage layout for the Theme Park and associated facilities is shown on Figure 2.10a.  A conceptual drainage layout plan for the NLDFS developments is provided in Figure 2.10b .

Water Supply

2.10.7     The construction of two fresh water service reservoirs, two salt water service reservoir, and one salt water pumping station including laying of the associated water mains will be required to serve the proposed NLDFS developments.

2.10.8     Potential sites allocated for the fresh and salt water service reservoirs on the Draft RODP include Fa Peng and Yam O Tuk.

Sewerage and Sewage Disposal

2.10.9     The preliminary sewerage assessment indicated that sewerage flows generated by developments proposed under the NLDFS can be accommodated by the proposed upgrading of the Siu Ho Wan STW providing the treatment works is upgraded to its ultimate capacity by 2011.  A conceptual sewerage layout plan is provided in Figure 2.10c.

2.11          Developments construction

2.11.1     Site developments will include low rise structures (e.g. infrastructure associated buildings), medium rise structures (e.g. tourism and recreational developments) and high rise buildings (e.g. residential building blocks at Siu Ho Wan).  Building forms will range from reinforced concrete, structural steel and composite construction. 

2.11.2     Low-rise structures will include buildings for water pumping and sewerage pumping facilities and petrol filling station.  These building will be in one to two storey high.  A combination of open excavation and sheetpiling methods will be used for construction of pad / raft foundations (approximately 5 to 6 m deep).  This will be followed by formwork, reinforcement bar fixing and in-situ concrete works.

2.11.3     Medium-rise structures will adopt a combination of bored / driven pile and pad / raft foundations. Building forms will range from reinforced concrete, structural steel and composite construction.  Medium-rise structures will include large spanning roof frames for buildings requiring large column free area (e.g. for the convention centre, technodrome and other tourism-related facilities).  These large spanning roof frames will be constructed using a combination of reinforced concrete and structural steel adopting a combination of pre-cast and cast-in situ methods of construction.

2.11.4     The high-rise structures include construction of bored / driven pile foundations, pile caps, columns, beam and roof structure. Building forms will include reinforced concrete and structural steel works where gravity loads are transferred from floor slabs into beams which in turn are transmitted into the columns and core walls, and subsequently down into the foundations. Construction will be by land-based equipment and adopting pre-cast and cast-in situ methods of construction.  Fixed and mobile lifting equipment will be used for transporting material to the upper levels.

2.12          Concurrent Projects

2.12.1     Concurrent ongoing projects in the vicinity of this Project considered in impact assessments for cumulative purposes are described below.

2.12.2     The Route 10 - NLYLH southern section comprises the link between the toll plaza at Fa Peng and the interchange to the south of So Kwun Wat.  The construction work is scheduled to commence in 2002 for completion in 2007.  An EIA has been completed in 1999 for the Route 10-NLYLH southern section and has been approved under EIAO.

2.12.3     The Remaining Development in Tung Chung and Tai Ho Comprehensive Feasibility Study covers four major development areas in Tung Chung (Centre, West District, Valley and Coast) and four in Tai Ho (West, Central, East and Bay).  A Recommended Outline Development Plan has been produced for North Lantau with an ultimate target population of 320,000 for North Lantau at year 2011.

2.12.4     The proposed Dangerous Goods Anchorage (DGA) at Tang Lung Chau provides a total of 72 moorings and has a gross area of 67.5 ha, which is bounded by the centre lines of the surrounding breakwater.  According to the Tsuen Wan Bay Further Reclamation, Area 35 Engineering, Planning and Environmental Investigation (TDD, 1999), the latest estimate on the programme for was for commencement of the works in late 2000 for completion in mid 2003.

2.12.5     The proposed further reclamation at Sham Tseng covers an area of 16.3 ha located between Ting Kau and Sham Tseng Sewage Treatment Works and Tsing Lung Tau.  The dredging and reclamation work is proposed to commence in 2002 for completion in 2004 and the construction of the entire project will be completed by 2008.

2.12.6     In addition, a number of possible concurrent projects have been taken into consideration in this EIA.  These include dredging and filling at the Container Terminal No. 9 (CT9) reclamation which the construction work was commenced in 1999 for completion (first berth operational) in 2001.  Associated with construction of CT9 will be sand borrowing at the West of Sulphur Channel Marine Borrow Area (MBA) and dumping of dredged sediments at the South Tsing Yi MBA and/ or the South Cheung Chau marine disposal ground.  Contaminated mud dredged from the CT9 will be disposed at the East Sha Chau Contaminated Mud Pits.

2.12.7     Other reclamation projects considered including Tsuen Wan Bay Reclamation, sand winning at East Lamma Channel Marine Borrow Area, and Lamma Extension power station reclamation.  Details of the assumptions adopted are presented in the water quality impact assessment section.

2.13          Benefits and Disbenefits of the Project

2.13.1     The perceived benefits associated with the proposed tourism and recreational developments are expected to be primarily of an economic nature.  The Theme Park development and associated hotels and RD&E facilities would be expected to strengthen Hong Kong SAR’s role as a major tourist destination in Asia and the world and generate substantial employment opportunities during both construction and operation. The NLDFS developments would also be expected to act as a catalyst in attracting further tourism, recreational and leisure investment (eg. hotels, retail, tourism services, air line and transport activities).

2.13.2     In addition, environmental enhancement arising from the Project comprise the following, which are detailed further in the relevant technical sections:

·                      The Theme Park and associated developments will reclamation’s require a large amount of fill material and therefore offers a very good opportunity to utilise the public fill generated in the SAR.  The use of public fill will not only alleviate the demand for virgin fill material but also reduce the pressure of disposing inert Construction and Demolition Material (C&DM) at the strategic landfills.  The entire NLDFS has assumed in an overall 40% of the total filling material to be public fill.  Section 6 details the intention to maximise the use of good quality public filling material for the proposed reclamations.  Except for the Penny’s Bay (Phase I) Reclamation which the use of public fill is constraint by the construction programme, over 77% of public fill will be used as fill materials at other proposed NLDFS reclamations.

 

·                      The Luk Keng headland and the nearby Cheung Sok Island have been zoned Conservation Area in the OZP. Subject to detailed study, a preliminary planning of concept Eco Park has been proposed at Luk Keng under the Draft RODP and it is expected that re-creation of habitats or introduction of new habitats/ species would be required to upgrade the interest of the site and enhance visitor appeal.

 

·                      The deletion of two reclamation areas (about 16 ha) to the south-west and east of Cheung Sok from the North-East Lantau Port OZP has preserved approximately 1 km of natural coastline.

 

·                      As an additional habitat enhancement measure, the Project proponent, CED, has undertaken to deploy 4,350 m3 Artificial Reefs (ARs) in Hong Kong waters at a site (or sites) to be decided upon in consultation with the DAFC. ARs act as habitat enhancement devices and provide hard bottom, high profile habitat in areas without natural cover. The ARs subsequently will provide food, shelter and a nursery ground for commercial fish and, over the long term, enhance fishery stocks.  Enhanced fish stocks in the area will not only benefit local fisheries resources but will also increase the availability of prey items for the seasonal population of marine mammals that uses the area.  The deployment of AR within the Project Area is subject to detailed study.

 

·                      The rubble mound and concrete sloping seawalls proposed for the reclamation have been demonstrated (Section 8) to become colonised by subtidal hard surface assemblages after construction.

 

·                      Provide secondary woodland planting to compensate for the approximate loss of 1.8 ha of  the woodland at Ngong Shuen Au which cannot be avoided by the PBRL, Road P2 and CKWLR alignment.  As considerable areas, not less than 6 ha, of woodland planting are proposed as landscape and visual impact mitigation on the adjacent hill side to the east of Ngong Shuen Au, sufficient compensatory woodland will be provided.  Species used for planting should take reference from the species identified in the Tree Survey and be native to Hong Kong or South China region.

 

·                      A 10 ha Conservation Area has been designated around Pa Tau Kwu may, as described in Section 7, indirectly benefit the environment of an identified breeding pair of White-bellied Sea Eagles which have one nesting site at Pa Tau Kwu. The indirect benefit during construction through addition of buffer distance from construction works and through isolation of the secondary woodland area from the Theme Park and associated developments.

 

·                      An open channel will be built at western Penny's Bay to conserve the natural coastline.

 

·                      Protection of pitcher plants by restricting access during construction works has been recommended even though the works area may not encroach their habitat.

 

·                      The use of fabric (plastic) fenders instead of tropical hardwood fenders has been recommended in the proposed Theme Park Ferry Pier and service quay, as well as the Cross Boundary Ferry Terminal construction.

 

·                      The use of wooden hoardings in the Project construction will not be allowed and metal (aluminium, alloy, etc.) has been recommended to help reducing the construction and demolition (C&D) wastes.

 

·                      The Theme Park operator, HKITP, will additionally benefit the environment by implementation of waste reduction initiatives. The quantity of recyclable materials potentially recovered by local recyclers under market driven conditions is estimated to be about 23 to 26% of the total waste generated. These estimates are based on the market conditions in Hong Kong.  The analysis on the markets show that the market for the major recyclables exists, especially when source separation programmes are in place to enhance the market value of the materials.  It has been recommended in the Theme Park EIA that the operator should institute a source separation programme to recover recyclables from the remaining waste stream with a preliminary recycling target of 10% for remaining recyclable materials and 10% for compostable materials if composting facility is available, be adopted in the Waste Management Plan of the Theme Park.  A waste avoidance and recycling programme, which forms a major part of the HKITP’s Waste Management Plan for the operation of the Theme Park, should be implemented and annually monitored (Section 6).  It is recommended similar waste reduction and recycling arrangement could be considered by other NLDFS tourism and recreation developments.

 

·                      The current dredged and drained design of Penny's Bay Reclamation will have a 30% decrease in total dredging volume, a 34% in fill volume, and a 97% reduction in the volume of contaminated sediments requiring disposal compared to the combined Container Terminals No. 10 & 11 Ancillary Works (Design) and the Design of Reclamation and Edge Structures for Container Terminals 10 and 11 and Back-up Areas (fully dredged option) of the Lantau Port Development - Stage 1 Study.

 

·                      Environmental benefits arising from the conversion of land uses from port developments to tourism recreation purposes, in particular for visual and landscape aspects.

 

·                      The public modes of transport to the proposed NLDFS developments are expected to be dominated.  Of the public modes, the rail mode will be dominant through the proposed Penny's Bay Rail Link, which is connected with the Tung Chung Line,  and its possible future extensions and will be complemented by other transport mode and the provision of integrated transport facilities (PTIs at Yam O and the Theme Park) to improve accessibility by rail.

 

·                      The proposed NLDFS developments will transform the area from a predominantly rural to suburban area and tourism and recreation oriented landscape.  It will provide an opportunity to create positive visual features and high quality landscape setting.

 

2.13.3     Potential disbenefits associated with the proposed Project may include:

·                      Loss of natural shoreline and associated inter-tidal habitats;

·                      Loss of natural shallow coastal marine habitats;

·                      Potential impact to natural terrestrial habitats and fauna;

·                      Increased solid waste generation;

·                      Potential floating debris due to the use of public fill during reclamation;

·                      Potential noise impacts;

·                      Potential air quality impact;

·                      Potential water quality impacts; and

·                      Potential landscape, visual and cultural heritage impacts.

 

2.13.4     These potential disbenefits will be examined in this EIA relative to the assessment criteria laid down in the EIAO TM.  The main purpose of the Schedule 3 NLDFS EIA Study is to provide a comprehensive impact assessment for the overall development scenario and to avoid/minimise the potential environmental impacts through proper landuse planning and design.  Also, opportunities of conserving and enhancing the existing environment have been explored and examined.

2.13.5     For the CKWLR for which a more detailed Schedule 2 EIA has been performed for the Project Proponent's Environmental Permit application, conditions and requirements have been identified, where appropriate, for the detailed design, construction and operation of the Project to mitigate against adverse environmental consequences.  The EIA will also identify the overall environmental acceptability of residual impacts, where appropriate, after proposed mitigation measures are implemented.

2.14          “Without the Project” Scenario

2.14.1     A key development objective of the Project is to provide a series of world-class tourism and recreational facilities including the Theme Park together with its related developments.  The proposed developments are also expected to become a core tourist attraction in the HK SAR.  Without the Project, the perceived benefits identified in Section 2.12 will not be realised and environmental impacts described later in this EIA Report will not arise. 

2.14.2     Prior to the amendment of the previous North-East Lantau Port OZP and rezoning of part of the Penny’s Bay area for theme park and related recreational usage, the area was designated for the development of Container Terminals 10 and 11.  Without the Theme Park and associated developments, rezoning of the Project area for container terminals and port related uses, including container back-up areas, business park and industrial uses could not be precluded.  Such container port and associated development would likely involve 24 hour working leading to associated noise impacts, a higher percentage of heavy good vehicles in the Project Area with air and noise impacts, visual and glare impacts from 24 hour night-time port operation lighting requirements.

2.14.3     On balance, it is considered that the consequences to the environment and adjacent environmental sensitive receivers arising from both the construction and operation of the previously proposed container ports (CT10 and CT11) would be greater than those predicted to arise for the construction and operation of the Theme Park and associated developments.



([1]) Penny's Bay Rail Station is referred to as Disneyland Station in the EIA Report for the PBRL in the Theme Park EIA Report (Annex M).  This is only a working name.  The formal name of the Penny's Bay Rail Station will be determined in due course.