Table
5.10a - Residual Discharges (m3s-1) through Major Flow
Channels and Percentage Change from Baseline
|
Wet Season
|
Dry Season
|
Channel
|
Baseline
|
NSLD
|
NSLD + CT
|
Baseline
|
NSLD
|
NSLD + CT
|
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Urmston
Road
|
799
|
819
|
2.5
|
867
|
8.5
|
1480
|
1499
|
1.3
|
1464
|
-1.1
|
Kap
Shui Mun
|
-164
|
-89
|
-45.7
|
-90
|
-45.1
|
651
|
647
|
-0.6
|
665
|
2.2
|
Ma
Wan Channel
|
1527
|
1508
|
-1.2
|
1510
|
-1.1
|
1111
|
1134
|
2.1
|
1095
|
-1.4
|
Rambler
Channel
|
-564
|
-601
|
6.6
|
-553
|
-2.0
|
-284
|
-284
|
0.0
|
-298
|
4.9
|
East
Lamma Channel
|
1823
|
1864
|
2.2
|
1557
|
-14.6
|
1226
|
1264
|
3.1
|
1691
|
37.9
|
West
Lamma Channel
|
-1563
|
-1653
|
5.8
|
-1114
|
-28.7
|
-512
|
-457
|
-10.7
|
-1150
|
124.6
|
Victoria
Harbour
|
-120
|
-44
|
-63.3
|
-152
|
26.7
|
1058
|
1031
|
-2.6
|
1068
|
0.9
|
Notes :
1.
Positive discharge is in the flood direction,
as defined in Figure 5.9a
2.
Positive change represents an increase in
discharge and a negative change a decrease in discharge.
|
Table
5.10b - Average Flood Discharges (m3s-1) through Major
Flow Channels and Percentage Change from Baseline
|
Wet Season
|
Dry Season
|
Channel
|
Baseline
|
NSLD
|
NSLD + CT
|
Baseline
|
NSLD
|
NSLD + CT
|
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Urmston
Road
|
24446
|
24035
|
-1.4
|
23577
|
-3.6
|
26346
|
25990
|
-1.4
|
25537
|
-3.1
|
Kap
Shui Mun
|
5718
|
5238
|
-5.4
|
5106
|
-10.7
|
7001
|
6621
|
-5.4
|
6542
|
-6.6
|
Ma
Wan Channel
|
15332
|
15475
|
0.6
|
15020
|
-2.0
|
16205
|
16296
|
0.6
|
15957
|
-1.5
|
Rambler
Channel
|
776
|
796
|
2.3
|
823
|
6.1
|
1065
|
1089
|
2.3
|
1083
|
1.7
|
East
Lamma Channel
|
13845
|
13763
|
-0.2
|
14454
|
4.4
|
14370
|
14338
|
-0.2
|
15500
|
7.9
|
West
Lamma Channel
|
10549
|
10077
|
-3.2
|
8261
|
-21.7
|
11343
|
10984
|
-3.2
|
8633
|
-23.9
|
Victoria
Harbour
|
3765
|
3836
|
1.9
|
3799
|
0.9
|
4504
|
4463
|
-0.9
|
4660
|
3.5
|
Notes :
1.
Positive change represents an increase in
discharge and a negative change a decrease in discharge.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table
5.10c - Average Ebb Discharges (m3s-1) through Major Flow
Channels and Percentage Change from Baseline
|
Wet Season
|
Dry Season
|
Channel
|
Baseline
|
NSLD
|
NSLD + CT
|
Baseline
|
NSLD
|
NSLD + CT
|
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Discharge
|
Discharge
|
Difference
|
Discharge
|
Difference
|
Urmston
Road
|
22718
|
22270
|
-2.0
|
21708
|
-4.4
|
23212
|
22828
|
-1.7
|
22447
|
-3.3
|
Kap
Shui Mun
|
6043
|
5413
|
-10.4
|
5283
|
-12.6
|
5761
|
5398
|
-6.3
|
5285
|
-8.3
|
Ma
Wan Channel
|
12596
|
12759
|
1.3
|
12326
|
-2.1
|
14142
|
14176
|
0.2
|
13912
|
-1.6
|
Rambler
Channel
|
2128
|
2259
|
6.2
|
2132
|
0.2
|
1688
|
1703
|
0.9
|
1733
|
2.7
|
East
Lamma Channel
|
10567
|
10407
|
-1.5
|
11643
|
10.2
|
12090
|
11977
|
-0.9
|
12377
|
2.4
|
West
Lamma Channel
|
13670
|
13392
|
-2.0
|
10489
|
-23.3
|
12358
|
11889
|
-3.8
|
10987
|
-11.1
|
Victoria
Harbour
|
4000
|
3920
|
-2.0
|
4094
|
2.4
|
2666
|
2674
|
0.3
|
2800
|
5.0
|
Notes :
1.
Positive change represents an increase in
discharge and a negative change a decrease in discharge.
|
|
|
|
|
|
|
|
|
|
|
|
|
5.10.21The contours of BOD (Figures D4i to D4l) show
that the modelling predicts that the operation of both the Northshore Lantau
Development and Container Terminal will result in little changes to the BOD
concentrations. The main effect will be
a slight reduction in concentrations in and to the south of Discovery Bay. Such an impact may be considered to be an
environmental improvement and may serve to offset the potential impact to
dissolved oxygen which may have been caused by the reduced flushing of this
area, as discussed above.
5.10.22The contours of total inorganic nitrogen
(Figures D4m to D4p) show that in the wet season the modelling predicts a reduction
in concentrations in the Western Harbour as a result of the operation of the
Northshore Lantau Development and Container Terminal. This improvement is likely to have been caused by the reduction
in flows past Ma Wan transporting less of the polluted Pearl River flows into
the Western Harbour. There are
predicted to be exceedances of the WQO in the Southern WCZ, to the south of the
Northshore Lantau Development and Container Terminal. These exceedances are present in all three scenarios and neither
the Northshore Lantau Development nor the Container Terminal are predicted to
cause an increase in the concentrations in this area. This means that the two developments are not responsible for the
exceedance nor are they predicted to make the existing conditions any
worse. To the north of Lantau Island
there are not predicted to be any exceedances of the WQO and the two developments
are predicted to only result in a slight increase in total inorganic nitrogen
concentrations to the south of the Brothers.
There are, therefore, predicted to be no adverse impacts to water
quality in terms of total inorganic nitrogen from the operation of the
Northshore Lantau Development and Container Terminal.
5.10.23The contours of unionised ammonia
concentrations (Figures D4q to D4t) show that the modelling results
predict that there will be no exceedances of the WQO. There are predicted to be increases in the unionised ammonia
concentrations in the wet season to the west of Hei Ling Chau and Peng Chau and
in the vicinity of the Northshore reclamation for the Northshore Lantau
Development. There are small increases
in the unionised ammonia concentrations at the location of the discharge point
for the Siu Ho Wan outfall. It is
concluded that there will be no adverse impacts to water quality in terms of
unionised ammonia concentrations as the predicted increases in concentrations
do not result in a breach of the WQO.
5.10.24The contours of chlorophyll-a
concentrations (Figures D4u to D4x) show that the modelling predicts
that the operation of the Northshore Lantau Development and Container Terminal
will have minimal effects on algal growth.
It is evident that there is an increase in algal growth in Sze Pak Wan,
which has likely caused the predicted increase in dissolved oxygen
concentrations. The predicted increase
in algal growth is not considered to be excessive and would not cause a
nuisance and is therefore not considered to be an adverse impact. The only other evident changes are that there
are predicted to be small decreases in algal growth to the south of the
Container Terminal.
5.10.25The contours of E. coli concentrations (Figures
D4y to D4ab) show that there are
predicted to be no exceedances of the WQOs for secondary contact recreation
sub-zones and bathing beaches due to the operation of the Northshore Lantau
Development and Container terminal as any exceedances are shown for the
Baseline scenario. In the dry season
there are predicted to be increases in E.
coli concentrations in the vicinity of Peng Chau due to the operation of
the Northshore Lantau Development and Container terminal, although the
concentration do not breach the WQO for secondary contact recreation
sub-zones. There are also predicted to
be increases in the vicinity of the discharge point for the Siu Ho Wan outfall,
which again do not breach the WQO. It
is therefore concluded that there will be no adverse impacts to water quality
with respect to E. coli from the
operation of the Northshore Lantau Development and Container Terminal.
5.10.26The contours of suspended sediment
concentrations (Figures D4ac to D4af) show that the water quality
modelling predicts that the operation of the Northshore Lantau Development and
Container Terminal will not cause a breach of the WQO. The operation of the Northshore Lantau
Development is predicted to result in a reduction in suspended sediment
concentrations in the Ma Wan Channel, possibly by a reduction in the discharge
through this channel from the Pearl River Estuary. The operation of the Container Terminal is additionally predicted
to cause a reduction in suspended sediment concentration between the berths and
the breakwater, which is most likely due to the sheltering effect of these two
structures reducing the rate of exchange with the outside waters. There are therefore not predicted to be any
adverse impacts to water quality in terms of suspended sediment concentrations
due to the operation of the Northshore Lantau Development and the Container
Terminal.
5.10.27The water quality modelling has predicted
that there will be no exceedances of the WQOs at sensitive receivers caused by
the operation of the Northshore Lantau Development and the Container
Terminal. There are, however, a number
of exceedances of the WQO predicted at sensitive receivers for all three
modelling scenarios, but in these cases the operation of the Northshore Lantau
Development and Container Terminal is not contributing to the exceedance. The contour plots support the above
conclusions and show that in general the operation of the Northshore Lantau
Development and Container Terminal has little effect on water quality. The only exception is a predicted exceedance
of the WQO for dissolved oxygen within the Container terminal and it is recommended
that suitable mitigation measures be devised to reduce the predicted impact to
acceptable levels.
5.10.28The water quality modelling has been able
to predict water quality conditions in the majority of the areas surrounding
the Northshore Lantau Development and Container Terminal due to the refined
grid resolution used in the modelling for this study. However, the Yam O Bay following completion of the Northshore
Lantau Development is too narrow to be represented by the model used for this
study and as such it is not possible to quantitatively determine the water
quality conditions within the bay. The
modelling has been able to determine that the water quality conditions at the
mouth of the bay, through the positioning of a sensitive receiver output point
at this location, will be acceptable, which gives an indicator of conditions in
the bay. However, due to the expected
long retention times within the bay it is to be expected that the water quality
will be lower than that at the mouth, particularly with regard to dissolved
oxygen. The potential for poor water
quality within the bay has been partially mitigated by the prevention of
polluted discharges into the bay the diversion of any polluted stormwater to
the west of the Luk Keng headland.
Clean run-off from the surrounding hillsides will still be discharged
into the bay to maintain a salinity gradient, which may serve to provide
suitable conditions for continued mangrove growth on the mudflats at the head
of the bay. However, it cannot be
guaranteed that these measures will be successful in preventing adverse water
quality conditions from occurring within the bay and it is recommended that at
this stage further mitigation measures be adopted. The need for any further mitigation measures would be verified
and tested during further more detailed studies. The detailed studies should include the use of a detailed local
area water quality model with sufficient resolution to represent the bay at Yam
O.
5.10.29The potential impacts from contaminated
run-off fall into two broad categories, which are acute and chronic
contamination. Acute contamination
results from high concentrations of toxic substances in the runoff water. This is particularly associated with 'first
flushes' of stormwater, where 'plugs' of contaminated deposits are washed off
the road surfaces or are scoured from the deposits within the storm drainage
system. The magnitude of such impacts
increases in proportion to amount of sediment which can become mobilised, which
is partly determined by the length of time since the previous storm event.
Chronic contamination results from the continual discharge of run-off water to
the receiving waters. This run-off is
generally less contaminated than that occurring under storm conditions, as much
of the sediment which is contaminated with heavy metals and PAHs is removed by
settling out. It is likely that the
impacts described here will be minimal provided that suitable mitigation
measures are employed, which are described in Section 5.11.2.
5.11.1
The
identification and discussion of suitable measures to mitigate any adverse
impacts to water quality from the operation of the Theme Park is split into two
main aspects.
·
The
surrounding marine waters; and
·
The Chok Ko
Wan Link Road.
5.11.2
The
operation of the Northshore Lantau Development will have the potential to
affect the water quality of the surrounding marine waters in two ways, by
changing the hydrodynamics and through the discharges of pollutants from the
development. Any identified mitigation
measures for these two aspects are discussed separately.
Hydrodynamics
5.11.3
The
hydrodynamic modelling has predicted that the reclamations for the Northshore
Lantau Development will not cause major changes in tidal current patterns. The main effects are a reduction in current
speeds in the Sze Pak Wan and Discovery Bay area. This is likely to cause a reduction in the flushing of these
areas, which may in turn lead to effects on water quality. The potential impacts to water quality have
been assessed through water quality modelling, which whether such impacts would
be unacceptable. The need for
mitigation measures in these areas is discussed below. Along the northern shore of Lantau Island it
was determined that the current speeds in the vicinity of the remainder of the
Yam O bay would be significantly reduced due to the formation of an embayment,
which could again cause adverse impacts to water quality. This issue is also discussed below and
suitable mitigation measures identified.
5.11.4
The
Container Terminal was found to have large effects on tidal current patterns,
particularly in the vicinity of Peng Chau and in the Kap Shui Mun main flow
channel. The main effect was in
reducing current speeds in areas to the west of the Container Terminal and
hence reducing the flushing of these areas.
The potential impacts to water quality have been assessed through
detailed water quality modelling and the need for mitigation measures is
discussed below. In the Kap Shui Mun
the Container terminal was found to cause an increase in current speeds by
constraining the flows. This is
unlikely to cause any adverse environmental impacts and as such no mitigation
measures will be required.
5.11.5
Both the
Northshore Lantau Development and Container Terminal were predicted to cause
changes to tidal discharges through the major flow channels in the vicinity of
the developments, with the impacts due to the combined effect of the Northshore
Lantau Development and Container Terminal being generally greater than those
from the Northshore Lantau Development alone.
The Northshore Lantau Development was predicted to cause a small
reduction in the quantities of water flowing into and out of the Western
Harbour, with the main effect being a large reduction in the residual flows
through Victoria Harbour. These effects
could have the potential to cause adverse impacts to water quality and the need
for mitigation measures is discussed below.
The combined effect of the Northshore Lantau Development and Container
Terminal was predicted to cause large changes in the discharge patterns into
and out of the Western Harbour, which is a cause for concern with regard to
water quality. The need for mitigation
measures is discussed below.
Water
Quality
5.11.6
In terms of
global effects on water quality the operation of the Northshore Lantau
Development was not predicted to cause adverse impacts to water quality. However, on a precautionary principle it is
recommended that silt traps be installed on all storm drains serving developed
and landscaped/managed areas. This will
serve to ensure that the pollutants in the stormwater discharges are minimised
as far as is practicable.
5.11.7
The
assessment has assumed that the Siu Ho Wan Sewage Treatment Works will be able
to cater for the increased from the Northshore Lantau Development, whilst
maintaining the same level of treatment and that the sewerage system to convey
the sewage effluents from the Northshore Lantau Development to the Siu Ho Wan
STW will have sufficient capacity. The
capacities of both the Siu Ho Wan STW and of the sewerage system are being
assessed as part of the engineering feasibility study for the Northshore Lantau
Development under the Sewerage Impact Assessment (SIA). The SIA has determined that there will be no
insurmountable problems with providing sufficient capacity at both the Siu Ho
Wan STW and in the sewerage system.
5.11.8
It has been
determined that there is the potential for poor water quality conditions within
the embayed area of the Yam O bay. The
stormwater system has been designed to mitigate this potential by removing
polluted stormwater discharges from the bay.
However, it is not possible at this stage to quantitatively determine
whether additional measures will be required.
On a precautionary basis it is recommended that consideration be given
to reducing the size of the reclamation adjacent to the Yam O bay, which could
potentially increase the flushing of the bay by increasing the width of the
mouth of the bay. The need for a reduction
in the size of the reclamation in the vicinity if Yam O Bay would be determined
during further, more detailed water quality modelling, which would be capable
of representing the features of the Yam O Bay.
5.11.9
It was
predicted that adverse water quality conditions would occur between the Container
Terminal and the breakwater at Kau Yi Chau.
This is most likely to be due to the low flushing rates of this embayed
area. In order to improve the flushing
of this area and hence improve the water quality it is recommended that the
Container Terminal be connected to Kau Yi Chau by a bridge or causeway. This will mean that water will be allowed to
flow through the area between the Container terminal and Kau Yi Chau and hence
prevent the accumulation of pollutants.
This measure will also serve to improve the flows around Peng Chau,
where the currents were predicted to be decreased.
5.11.10The following mitigation measures should
be implemented to prevent adverse operational impacts to water quality from the
Chok Ko Wan Link Road.
·
all road
run-off should be collected and discharged via a stormwater drainage system;
·
oil and
grit interceptors should be incorporated into areas where spills are likely to
remove any oil or grease and sediment before being diverted to the public
stormwater system;
·
the
contents of oil and grit interceptors should be transferred to an appropriate
disposal facility on a regular basis, the frequency of which would depend upon
the amount of rainfall (ie more frequent removal during the wet season);
·
silt traps
or sedimentation tanks should be installed to remove suspended solids, which
may contain heavy metals and PAHs, from run-off water and, in the same way as
oil and grit interceptors, they should be regularly cleaned and maintained in
good working condition.
5.11.11The implementation of the above described
mitigation measures will be sufficient to prevent adverse impacts to water
quality from the operation of the Chok Ko Wan Link Road.
Construction
5.12.1
No residual
environmental impacts were predicted to occur during the construction phase,
provided that the mitigation measures, described in Section 5.7 are implemented.
The mitigation measures were specified in the form of constraints on the
construction programme and as a series of ‘best practice’ methods of working.
5.12.2
Water
quality modelling of the impacts of the operational phase of the Northshore
Lantau Development predicted that there would be no exceedances of the Water
Quality Objectives which could be attributed to the Northshore Lantau
Development. For total inorganic
nitrogen and E. coli there were
predicted to be exceedances of the WQOs in the baseline and operational
scenarios and it was therefore concluded that the breaches in the WQOs could
not be attributed to the operation of the Northshore Lantau Development. Furthermore, it was predicted that the
operation of the Northshore Lantau Development would not cause a deterioration
in water quality in those areas where the WQOs were already breached.
5.12.3
The
reclamation for the Northshore Lantau Development on the northern shore of
Lantau Island will lead to the formation of an embayed area in Yam O Bay. It was not possible to provide a
quantitative assessment of water quality within the bay using the water quality
model. It was determined that there was
the potential for poor water quality within the bay and a number of mitigation
measures. The need for and
effectiveness of these mitigation measures would be determined during further,
more detailed studies using a high resolution local area water quality
model. However, at this time it has
been assessed that the above described mitigation measures will be sufficient
to prevent adverse water quality conditions occurring in Yam O Bay.
5.12.4
The water
quality modelling predicted that there would be a breach of the WQOs within the
area between the Container Terminal and breakwater at Kau Yi Chau, which was
directly attributed to the operation of the Container Terminal. Mitigation measures were defined to reduce
the predicted impact to below acceptable levels.
5.12.5
No residual
impacts to marine water quality are therefore predicted from the operation of
the Northshore Lantau Development and the Container Terminal, provided that the
specified mitigation measures are implemented.
5.12.6
No residual
impacts to water quality are predicted to occur during the operation of the
Chok Ko Wan Link Road, provided that the mitigation measures described in Section 5.11.2 are implemented. The measures were specified in terms of the
design of the drainage system and management practices.
Construction
Reclamation Formation
5.13.1
An
Environmental Monitoring and Audit (EM&A) programme will be required during
construction of the reclamations for the Northshore Lantau Development to
ensure that no adverse water quality impacts occur at nearby sensitive
receivers. Should adverse impacts be
detected then the EM&A programme would act to trigger suitable mitigation
measures. Full details of the EM&A
programme are given in Section 15.4.
Construction
Activities
5.13.2
No
monitoring of water quality would be required during the construction
activities on the reclaimed land. It is
recommended, however, that audit be carried out to confirm that compliance with
the ‘best practice’ site procedures, as defined in Section 5.7.2, are being undertaken. Full details of the audit requirements are presented in Section 15.4.
5.13.3
No
monitoring of water quality during the operation of the Northshore Lantau
Development and Chok Ko Wan Link Road will be required, beyond that which is
required to satisfy WPCO discharge licence standards.
Construction
5.14.1
The
construction phase assessment has considered the following aspects.
·
the
potential impacts to marine water quality from the construction of the
reclamations associated with the Northshore Lantau Development, which are those
at Siu Ho Wan, Northshore, Fa Peng and Theme Park Extension; and
·
the
potential impacts to marine water quality from land based construction works
associated with the developments, including the Chok Ko Wan Link Road.
Reclamation
Construction
5.14.2
The
potential impacts to marine water quality from the construction of the
reclamations for the Northshore Lantau Development was assessed through
sediment plume modelling using a particle tracking model. The sediment plume modelling predicted that
there would be no adverse impacts at sensitive receivers due to elevations in
suspended sediment concentrations and that there would be no adverse impacts in
terms of sediment deposition. Sediment
quality data was obtained as part of this project for the areas to be dredged
and this data, in combination with the modelling predictions on suspended
sediment concentrations, to calculate the impacts of the construction works on
water quality in terms of dissolved oxygen, nutrients and the release of
micro-pollutants. It was determined
that there would be no adverse impacts to water quality, with the exception of
the release of TBT. However, the
assessment methodology for TBT impacts was very conservative and despite this
the predicted release of TBT was not predicted to significantly increase the
background levels. It was recommended that
elutriate testing be carried out to obtain better estimates of the potential
release of TBT to the surrounding marine waters, which would then enable a
determination to be made of the necessity for mitigation measures.
5.14.3
Mitigation
measures for the construction of the reclamations were specified in terms of
operational constraints, ie limiting the rates of working to those simulated in
the sediment plume modelling and the sequence of construction, to ensure that
the impacts would remain below those predicted. A series of ‘best practice’ methods of working were also
specified. The implementation of these
measures would prevent adverse impacts to water quality during the construction
of the reclamations.
5.14.4
It was
recommended that Environmental Monitoring and Audit be carried out to ensure
that there would be no adverse impacts to sensitive receivers during the
construction of the reclamations for the Northshore Lantau Development.
Land
Based Construction Activities
5.14.5
It was
determined that the potential for adverse impacts to water quality from land
based construction activities for the Northshore Lantau Development and the
Chok Ko Wan Link Road would primarily be from contaminated surface run-off and
from sewage effluent generated by the construction workforce. A number of mitigation measures were
specified to reduce the potential adverse impacts to acceptable levels.
5.14.6
The
operation phase assessment has considered the following aspects.
·
the
potential impacts to hydrodynamics from the Northshore Lantau Development
reclamations alone and in combination with a Container Terminal;
·
the
potential impacts to water quality from changes in hydrodynamics and treated
sewage effluent and stormwater discharges from the Northshore Lantau
Development and the Container Terminal; and
·
the
potential impacts to marine water quality from the operation of the Chok Ko Wan
Link Road.
Hydrodynamics
and Water Quality
5.14.7
The
potential impacts to hydrodynamics from the operation of the Northshore Lantau
Development and Container terminal were assessed using computational
modelling. The computational modelling
predicted that the reclamations would cause the tidal current patterns and
tidal discharges in the vicinity of the developments to be altered. The predicted changes in the hydrodynamic
patterns could have effects on water quality, which is discussed below.
5.14.8
The
potential impacts to water quality from the changes in hydrodynamics and
discharges of treated sewage effluent and stormwater from the Northshore Lantau
Development and Container Terminal were assessed using computational water
quality modelling. The sewage effluent
from the Northshore Lantau Development and Container Terminal will be conveyed
to the Siu Ho Wan Sewage Treatment Works, while the stormwater will be
discharged via culverts along the face of the reclamations. The increased treated effluent flows from
the Siu Ho Wan STW due to the load from the Northshore Lantau Development and
Container Terminal and the stormwater discharges were included in the water
quality modelling. The water quality
modelling predicted that there would be no adverse impacts to water quality
from the operation of the Northshore Lantau Development. It was predicted that there would be an
exceedance of the WQOs within the Container Terminal development and suitable
mitigation measures were devised, which specified a change in the design of the
Container Terminal.
5.14.9
It was
determined that there would be the potential for poor water quality to occur
within the embayed area in Yam O bay, formed as a result of the Northshore
Lantau Development reclamations. The
modelling carried out for this study was not sufficiently detailed to
quantitatively assess the water quality within the bay. A number of mitigation measures were devised
to reduce the risk of poor water quality in terms of re-locating polluted
stormwater discharges away from the bay and reducing the size of the Northshore
reclamation to provide a wider mouth to the bay and encourage flushing. The need for and extent of these mitigation
measures would be determined through further, refined modelling during the
detailed EIA stage for this portion of the Northshore Lantau Development.
5.14.10It was not recommended that Environmental
Monitoring and Audit be carried out during the operation phase of the
Northshore Lantau Development, beyond that which would be required to apply for
discharge licences under the WPCO.
Chok
Ko Wan Link Road
5.14.11The operation of the Chok Ko Wan Link
Road would have the potential to cause adverse impacts to water quality through
the discharge of contaminated surface run-off to the stormwater system. Suitable mitigation measures were specified
to minimise the potential impacts. It
was therefore assessed that there would be no adverse impacts to water quality
from the operation of the Chok Ko Wan Link Road.
5.15.1
Water
quality impacts due to construction and operation of the proposed NLDFS
developments and the preferred CKWLR alignment have been summarised in Table
5.15a as follows.
Table 5.15a - Impact Summary Table
Issue
|
Construction Impact
|
Operational Impact
|
Assessment Points
|
·
Impacts to water quality from dredging and
filling for the Northshore Lantau Development; and
·
Impacts to water quality from land based
construction works from the land based construction works associated with the
developments, including the Chok Ko Wan Link Road.
|
·
Impacts to hydrodynamics from the Northshore
Lantau Development reclamations alone and in combination with those for a
container terminal development to the south east;
·
Impacts to marine water quality due to changes in hydrodynamics
and treated sewage effluent and stormwater discharges from the Northshore
Lantau Development and container terminal development;
·
The impacts to marine water quality from the
operation of the Chok Ko Wan Link Road.
|
Relevant Criteria
|
·
Water Pollution Control Ordinance;
·
Technical Memorandum for Effluents Discharged
into Drainage and Sewerage Systems, Inland and Coastal Waters;
·
Environmental Impact Assessment Ordinance
(Cap. 499 S16), Technical Memorandum on Environmental Impact Assessment
Process, Annexes 6 and 14; and
·
Practice Note for Professional Persons,
Construction Site Drainage (ProPECC PN 1 /94).
|
·
Water Pollution Control Ordinance;
·
Technical Memorandum for Effluents Discharged
into Drainage and Sewerage Systems, Inland and Coastal Waters;
·
Environmental Impact Assessment Ordinance
(Cap. 499 S16), Technical Memorandum on Environmental Impact Assessment
Process, Annexes 6 and 14; and
·
Drainage Services Department Sewerage Manual.
|
Potential Impacts
|
·
No adverse impacts to water quality in terms
of increased suspended sediment concentrations and increased sediment
deposition were predicted from the construction of the Northshore Lantau Development
reclamations;
·
Potential adverse impacts were predicted due
to the release of TBT from sediments suspended during dredging but it was
determined that, despite a very conservative assessment methodology, that the
release of TBT would not significantly increase background concentrations ;
and
·
No adverse impacts to water quality during
land based construction activities, provided that ‘best practice’ measures
implemented.
|
·
No adverse impacts water quality due to
changes in hydrodynamics and due to the discharge of sewage effluents and
stormwater were predicted for the Northshore Lantau Development alone;
·
The present modelling work was not detailed
enough to determine the potential impacts to the embayed area at Yam;
·
No adverse impacts to water quality were
predicted due to the cumulative impacts of the Northshore Lantau Development
and Container Terminal Development, except in the immediate vicinity of the
container terminal; and
·
No adverse impacts to water quality from the
operation of the Chok Ko Wan Road Link were predicted, provided certain
design features were incorporated.
|
Mitigation Measures
|
·
Operational constraints were specified for the
construction of the reclamations, in terms of rates of working, methods of
construction and sequence of construction;
·
In addition, ‘best practice’ working methods
were specified for reclamation construction; and
·
For the land based construction activities
measures were specified to minimise the potential for contaminated surface
run-off entering marine waters and to prevent the discharge of untreated
sewage effluent.
|
·
It was recommended that consideration be given
to decreasing the size of the Northshore reclamation to prevent reductions in
the flushing of Yam O and that the necessity for such reductions be
determined through detailed modelling during further studies for the
Northshore reclamation;
·
It was recommended that the container terminal
be connected via a bridge to Kau Yi Chau to encourage greater mixing in the
immediate area to mitigate the predicted adverse impact; and
·
Measures were devised to mitigate the
potential impacts due to surface run-off from the road and rail links.
|
Residual Impacts
|
No residual impacts
were predicted to occur provided suitable mitigation measures were
implemented.
|
No residual impacts
to occur were predicted to occur provided that the recommended mitigation
measures were implemented.
|
Environmental
Acceptability
|
Acceptable.
|
Acceptable.
|