Table 6.15a
- Impacts Summary Table for NLDFS
Issue |
Construction Impact |
Operation Impact |
Assessment
Points |
NLDFS
Study Area |
NLDFS
Study Area |
Relevant
Criteria |
Waste Disposal Ordinance, Waste
Disposal (Chemical Waste) (General) Regulation, Land (Miscellaneous
Provisions) Ordinance, Public Health and Municipal Services Ordinance,
Dumping at Sea Ordinance, Waste Disposal Plan for Hong Kong, New Disposal
Arrangements for Construction Waste, Code of Practice on the Packaging,
Labelling and Storage oe Chemical Wastes, EPDTC 1-1-92, WBTC Nos. 6/92,
22/92, 32/92, 2/93, 16/96, 4/98, 5/98, 5/99 and 25/99,
and Waste Reduction Framework Plan. |
Waste Disposal Ordinance, Waste
Disposal (Chemical Waste) (General) Regulation, Public Health and Municipal
Services Ordinance, Waste Disposal Plan for Hong Kong, Environmental
Guidelines for Planning in Hong Kong and Waste Reduction Framework Plan. |
Potential
Impact |
Dredged/Excavated Sediment Due to the detection
limit of PAHs and PCBs being higher than LCEL, further testing of PAHs and
PCBS for all the sediment to be dredged will be required to confirm proper
classification. In addition, the
testing of TBT in interstitial water should be used instead, in accordance to
the new excavated/dredged sediment guidelines. At Penny’s Bay
reclamation and Yam O reclamation, approximately 0.11 M m3 is
seriously contaminated (Class C). The Class C sediment should be disposed of
at the East Sha Chau Contaminated Mud Pits. No adverse environmental impact
is anticipated if the Class C sediment is properly transported to and disposed. FMC has allocated 30 M m3 of
uncontaminated and disposal capacity to the Penny’s Bay Project (East Nine
Pin, East Tung Lung and North Lantau).
The Engineers should inform FMC the extra volume of sediment requiring
disposal so further disposal grounds can be allocated. For
Northshore reclamation, approximately 60,000 m3 of dredged
sediment would required confined marine disposal. However, this volume may increase as additional biological
screening is required to determine the disposal route for sediment exceeding
LCEL. At
Siu Ho Wan reclamation, the sediment to be dredged are likely to be
uncontaminated, although checking on exceedance on LCEL in terms of PAHs,
PCBs and TBT (in interstitial water) will be required. The
sediment at SDU reclamation and Road P1 reclamation are not likely to be
seriously contaminated. However
biological screening should be carried out to determine whether confined
marine disposal is required and further testing on PAHs, PCB and TBT (in
interstitial water) are needed. Biological
screening is required at TCT East reclamation to determine the disposal route
of dredged sediment although it is estimated that approximately 70,000 m3
will required confined marine disposal.
Further testing on PAHs, PCBs and TBT (in interstitial water) will
also required to check if there is any exceedance in LCEL. When the volume of
sediment requiring confined/open marine disposal is confirmed, during
detailed design stage, the FMC should be informed in order to allocate
suitable disposal sites(s). |
Municipal Solid Waste Based
on the current development options, the amount of waste to be generated will
be 335.13 tpd (without any waste reduction/recycling) when the Northshore
Lantau Development is in full operation. Significant amounts of waste will be
generated from the tourism related developments (314.05 tpd). This estimation
should be refined during detailed design stage. The
disposal of waste from NLDFS development to strategic landfill will via
NLTS. Since the information on NLTS
throughput forecast only up to 2016, although the NLDFS developments will be
fully operate later than 2016, comparison is made to see if the NLTS can
receive the waste arisings from NLDFS development. The anticipated quantity of waste arising from the NLDFS
developments would constitute an significant increase of the daily throughput
(at least 38 %, see Section 6.5) in
the waste arising from the catchment area of the NLTS which has a design
capacity of 1,200 tpd. According to
the current waste arisings prediction, the NLTS will not be able to handle
the waste generated within its catchment area (deficiency of approximately 15
tpd). With proper implementation of
the waste reduction and waste management plan, no insurmountable impacts
associated with the handling and disposal of waste will be expected. The floating refuse
from windblown refuse and litter may vary from small debris to large floating
objects such as plastic bags. The
floating refuse is likely to be chemically inert, however, if not collected
properly, these floating refuse may drift along the coastal area of the Theme
Park and associated developments and the artificial lake of the Water
Recreation Centre, which may create aesthetic or odour impact, or cause
damage to marine craft. Provided that
mitigation measures such as the use of surface boom to contain the floating
refuse, are properly implemented, no insurmountable environmental impacts
with regards to floating debris will be anticipated. |
|
Use of Public Fill for Reclamation Penny’s
Bay Reclamation (Stages I and II) requires about 85.4 M m3 of
filling material including surcharge, 10.5M m3 of public fills has
been planned will be included into the reclamation, the maximum uptake due to
various constraints. And the Yam O
Reclamation will use about 1.7 M m3 of filling material, of which
1.0 M m3 is public fill. The total amount of
fill requirements for other reclamations within the Project Area is 43.8 M m3. It is estimated approximately 34.4 M m3
(about 78%) of public fill will be utilised at those reclamations. Also, an extra 17.5 M m3 of
public fill will be used as surcharge.
The use of public fill will not only alleviate the demand for virgin
fill material but also reduce the pressure of disposing inert construction
and demolition material at the strategic landfills Excavated Material The
construction of the building foundation for the NLDFS infrastructures
(including at Penny’s Bay Reclamation Stages I and II, Theme Park and NLDFS
developments as well as other roads and drains) will generate some excavated
materials. The quality of the
excavated material will be the same as the fill materials used for the
reclamation ( ie either marine sand fill or clean public fill). The exact amount of surplus excavated
material to be generated from the foundation works cannot be determined until
detailed design information is available.
However, it is anticipated that the excavated material to be generated
will be of a small percentage (less than 5%) to the fill requirements (117.6
M m3) for all the reclamations and can all be reused, either
on-site or at adjacent reclamation, as fill materials About 7,800 m3
of excavated material will be generated from the excavation works for Road
P2. The excavated materials will be
reused on-site for filling at Cheoy Lee Shipyard area and no surplus
excavated material will be generated. Approximately
68,500 m3 of excavated materials from cut and cover, drill and
blast tunnel works for the PBRL will be generated between January 2003 and
June 2004 (approximately 18 months) and will comprise mainly clean rock and
soil. The Yam O station will be
constructed on pad foundation, and hence no piling will be required. The Penny's Bay Rail Station will be
seated on steel H-piles or pad foundation.
|
Recycling According to the
assessment carried out for the Theme Park Phases I and II ([29]),the
market driven recycling industry can recycle 23-26 % of waste to be generated
in the tourism related developments.
It is recommended that a additional further target of an additional
10% for recyclable recovery programme at these developments and potentially,
an extra 10% for food waste source separation (assuming that a composting
facility for food waste planned in the Waste
Reduction Framework Plan is available) programme be adopted in the Waste
Management Plan of the tourism related developments. Disposal According to Table 6.6a and based on the waste
arisings from the NLDFS developments and associated facilities and market
driven recycling rate of 23-26 % for tourism related developments, the daily
waste arisings after market driven recycling in full operation is at least
253.48 to 262.9 tpd. The tourism
related development recommended recyclable recovery programme can further
reduce waste by an additional 10 %, which is 31.41 tpd. In addition, if food waste composting facility is available in HK SAR, an extra
10 % of waste (i.e. 31.41 tpd) to be generated from the tourism related
developments can be reduced. The anticipated
waste throughout of NLTS are 370, 770, and 880 tpd for the years 2006, 2011
and 2016, respectively. It indicates
that there will be sufficient spare capacity at the NLTS to handle the waste
arising from the NLDFS developments at least to year 2016. |
|
A total of
approximately 3.0 M m3 of excavated is expected to be generated
from the construction of the CKWLR, primary as a result of excavation at
slopes of Pa Tau Kwu. Small amounts of excavated material will also expected
from the foundation works carried out at CKWLR Phases I and II. The daily generation rate is 3,000 m3
d-1. Excavated material
generated at Yam O to Penny’s Bay Interchange could be reused on-site for
filling at the Cheoy Lee Shipyard area.
Whereas excavated material generated at Pa Tau Kwu and CKWLR Phases I
and II could be re-used within other NLDFS reclamation such as Penny’s Bay
Reclamation Stage II or Theme Park (Phase III) Extension reclamation. No surplus excavated material will be generated. As all the
reclamations require a large quantity of fill material and the Project will
have an overall deficit of fill material.
It is anticipated that all the excavated soil and rock generated from
the Project will be re-used for the reclamation works. Since public filling areas only accept
public fill with certain size (< 200 mm diameter). Some of the excavated material may require
to be broken prior re-use on site. No
surplus of excavated material will be generated. C&D Waste Small amount of
demolition waste will be generated at Cheoy Lee Shipyard and Ngong Shuen Au
for the construction of CKWLR.
However, the small is likely to be small. However, there are potential environmental impacts associated
with the decommissioning and demolition of the shipyard is addressed in Section 12 and will be evaluated under
a separate Schedule 2 EIA to be commissioned by the CED. During the
infrastructure construction period, the highest cumulative daily C&D
waste arisings is during 2004 and will be generated from Theme Park Phase I
Opening Day, Theme Park Phase II Buildout, GIC at area 1B, Water Recreation Centre,
SDU Base and PBRL during Q2 2004 (the average and peak C&D waste
generation rate is 32 m3 d-1 and 49 m3 d-1,
respectively, whereas for public fill generation rate is 131 m3 d-1
and 198 m3 d-1). |
Chemical Waste The operation of the
Theme Park at Penny’s Bay will use a variety of chemicals. Some of the used chemicals have to be
disposed of. The operation of the
Theme Park at Penny’s Bay will be very similar to that of Disneyland. In addition, the remains of fireworks from
the fireworks shows in the Theme Park may contain heavy metal in low
concentrations (in a scale of ng kg-1). Chemical waste will
be stored, handled, transported and disposed of in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation and the Code of Practice
on Packaging, Labelling and Storage of Chemical Wastes. They should be collected and transported
to the CWTC or other licensed facility by a licensed waste haulier. Sewage Sludge Based on sludge
generation rate of 18,702 tds a-1 in 2016, approximately 40 tds
per day of sludge will be generated, which is equivalent to approximately 170
m3 of sludge. 10 m3
skips (as currently employed in Sha Tin STW) could be used for transportation
of sludge to the disposal facility. A
maximum of 17 truck loads will be required.
It is therefore considered that the traffic impacts associated with
off-site sludge disposal will be minimal. Should the proposed
centralised Sludge and Difficult Wastes Incineration Facility (SDIF) be
located near the WENT landfill, it will be more cost effective and
environmentally preferred to transport
the sludge in modified 20ft ISO containers (similar to the one
currently used at the Stonecutters’ Island STW) via the NLTS to the WENT
Landfill Reception Area and then to the SDIF.. |
|
Chemical Waste A small volume of
chemical waste, such as used lubricating oils from plant maintenance
materials, will be produced. Provided
chemical wastes are disposed of at a licensed facility, the contractor should
be in compliance with all relevant regulations and there will be little
environmental impact. General Refuse The maximum daily
number of workers on site is 6,000.
Based on a waste generation rate of about 0.65 kg per person, it is
estimated that the amount of general refuse to be generated will be in the
order of 3.9 tpd. |
Biogas
Assessment Given that, at this stage, it is not possible
to measure the rates of gas emission from the organic sediment within the
area of the proposed artificial lake of Water Recreation Centre in the Theme
Park, Penny’s Bay Reclamation Stage II, Yam O Reclamation, Northshore
Reclamation, Siu Ho Wan Reclamation, SDU Reclamation, Road P1 Reclamation,
Theme Park (Phase III) Extension Reclamation and TCT East Reclamation
(hereafter refer as undredged areas), an estimate of the future rate of gas
generation has been made from the results of analysis of the sediment for TOC
and SOD. Several assumptions and estimations have to be
made when making theoretical predictions about possible future rates of
methane generation at the undredged areas.
The estimated potential rates of methane gas generation based on both
TOC and SOD are within the maximum safe rate (3.6 l m-2 d-1)
of methane emission from landfill sites which is specified by the UK
Department of Environment in WMP26A
as indicating that such sites can be regarded as no longer posing a threat
due to gas and are safe to be developed. They are well within the suggested
maximum rate of methane emission per unit area of 10 l m2 d-1,
and the limit of 84.7 l m2 d-1 recommended by the
London Scientific Services. The
former criterion provides a reasonable general guide for determining whether
the rates of methane emission pose an unacceptable risk to unrestricted
development on a potentially gassing site.
The latter criterion represents the absolute ‘cut-off’ level of
methane flux which developments should be allowed to build on the potentially
gassing site. Overall, based on the results of the sediment
analysis and comparison with published guidance on safe levels of gas
emissions, it is considered the predicted rates of gas generation from the
undredged areas are within the range which are considered as ‘likely be safe’
and will not constraint the developments on top of the reclamation areas. Given the inherent uncertainties involved in
estimating future rates of gas emissions from theoretical calculations of
rates of gas generation and given that mitigation measures for avoiding the
potential risks may be very expensive, it would be of benefit to select one
of the undredged areas to undertake monitoring of gas emission rates
following the construction works to confirm the findings of this
assessment. It is recommended that
the monitoring boreholes should be installed in areas where the predicted
methane flux is high and at areas to be reclaimed first so that the
monitoring results will be available as soon as possible. Should the
monitoring results show that biogas may be a problem, further monitoring
boreholes could then be installed at
other reclamation areas. Based on
these criteria (see Tables 6.5a, 6.14g
and 6.14h), it is recommended that
monitoring boreholes should be installed at the Water Recreation Centre of
the Theme Park. |
Mitigation
Measures |
The Contractor
should development a Waste Management Plan to Engineer approval prior to
construction. Such a management plan
should incorporate site specific factors, such as the designation of areas
for the segregation and temporary storage of reusable and recyclable
materials. Dredged/Excavated Sediment · minimising
exposure to any contaminated material by the wearing of protective gear such
as gloves, providing adequate hygiene and washing facilities, and preventing
eating during dredging/excavation; · any
contaminated sediment dredged should not be allowed to stockpile on the site
and should be immediately removed from site once dredged; · all
vessels for marine transportation of dredged sediment should be fitted with
tight fitting seals to their bottom openings to prevent leakage of materials;
and · loading
of barges and hoppers should be controlled to prevent splashing of dredged
material to the surrounding water, and barges or hoppers should under no
circumstances to be filled to a level which will cause other overflowing of
materials or polluted water during loading or transportation. Use of Public Fill for the reclamation The
Contractor should enforce strict application of the public fill license and
monitor the material placed in the reclamation and barges to control disposal
of unauthorised material. The
Contractor shall also provide floating booms and collect any floating
materials on a daily basis at the public filling areas. Excavated Material Wherever
practicable, excavated materials should be segregated from other wastes to
avoid contamination thereby ensuring acceptability at public filling areas or
reclamation sites and avoiding the need for disposal at landfill. The priority for off-site disposal of
surplus excavated material should be as follows: · transport
to other reclamation sites at North Lantau and Penny's Bay areas; and · transport
to public filling areas. |
The
tourism related development operators try to minimise the amount of waste to
be disposed of at landfill and to maximise the recovery of material from the
waste stream, these operators should will implement a waste prevention and
recycling programme. The waste
avoidance measures and material recovery and recycle programme will form part
of the Waste Management Plan for the operation and management of the tourism
related developments. To
minimise the potential adverse impacts to aesthetics and odour impacts,
floating refuse collection initiatives at both the coast of the reclamation
and within the artificial lake of the Water Recreation Centre of the Theme
Park should be carried out. Chemical Waste For
those processes which generate chemical waste, it may be possible to find
alternatives which generate reduced quantities or even no chemical waste, or
less dangerous types of chemical waste. Chemical
waste that is produced, as defined by Schedule
1 of the Waste Disposal (Chemical
Waste) (General) Regulation, should be handled in accordance with the Code of Practice on the Packaging,
Handling and Storage of Chemical Wastes as follows. Containers used for storage of chemical
wastes should: · be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed; · have
a capacity of less than 450 L unless the specifications have been approved by
the EPD; and · display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Regulations. |
|
Measures Taken in the Planning and
Design Stages to Reduce the Generation of C&DM
· avoidance
and minimisation, that is, not generating waste through changing or improving
practices and design; · reuse
of materials, thus avoiding disposal (generally with only limited
reprocessing); · recovery
and recycling, thus avoiding disposal (although reprocessing may be
required); and · treatment
and disposal, according to relevant law, guidelines and good practice. This
hierarchy should be used to evaluate the waste management options, thus
allowing maximum waste reduction and often reducing costs. For example, by reducing or eliminating
over-ordering of construction materials, waste is avoided and costs are
reduced both in terms of purchasing of raw materials and in disposing of
wastes. Records of quantities of
wastes generated, recycled and disposed (locations) should be properly kept. Standard
formwork should be used as far as practicable in order to minimise the
arisings of C&DM. The use of more
durable formwork or plastic facing for the construction works should be
considered during the detailed design. Any
uncontaminated soil should be reused on site as far as possible for landscape
works in order to minimise the amount public fill to be disposed off-site.
Should there be any surplus public fill generated from the project, the HKITP
should liaise with the Public Filling Sub-Committee to identify as far as
possible suitable reclamation or site formation projects near the project
site to reuse the material. The
design of the foundation works will minimise the amount of excavated material
to be generated. Should piling be
required, H-piling will be used as far as practical. The
purchasing of construction materials will be carefully planned in order to
avoid over ordering and wastage of construction materials, such as ready
mixed concrete. |
The
storage area for chemical wastes should: · by
clearly labelled and used solely for the storage of chemical waste; · be
enclosed on at least 3 sides; · have
an impermeable floor and bunding, of capacity to accommodate 110% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area, whichever is the greatest; · have
adequate ventilation; · be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed as chemical waste if necessary); and · be
arranged so that incompatible materials are adequately separated. Disposal
of chemical waste should: · be
via a licensed waste collector; and · be
to a facility licensed to receive chemical waste, such as the Chemical Waste
Treatment Facility which also offers a chemical waste collection service and
can supply the necessary storage containers; or · be
to a re-user of the waste, under approval from the EPD. The
Centre for Environmental Technology operates a Waste Exchange Scheme which
can assist in finding receivers or buyers Sewage Sludge The
containment, storage and delivery of the sewage sludge should be enclosed. Odour removal facilities should also be
installed to minimise the potential air quality impacts to any sensitive
receivers. |
|
Measures To be Taken in the
Construction Stage To Reduce the Generation of C&DM The
Contractor should recycle as much as possible of the C&D material
on-site. Public fill and C&D
waste should be segregated and stored in different containers or skips to
enhance reuse or recycling of materials and their proper disposal. Concrete and masonry, for example can be
crushed and used as fill and steel reinforcing bar can be used by scrap steel
mills. Different` areas of the work
sites should be designated for such segregation and storage. At
present, Government is developing a charging policy for the disposal of waste
to landfill. When it is implemented,
this will provide additional incentive to reduce the volume of waste
generated and to ensure proper segregation to allow disposal of inert
material to public filling areas. In
order to minimise the impacts of the demolition works these wastes must be
cleared as quickly as possible after demolition. The demolition and clearance works should therefore be
undertaken simultaneously. Chemical Waste For
those processes which generate chemical waste, it may be possible to find
alternatives which generate reduced quantities or even no chemical waste, or
less dangerous types of chemical waste. Chemical
waste that is produced, as defined by Schedule
1 of the Waste Disposal (Chemical
Waste) (General) Regulation, should be handled in accordance with the Code of Practice on the Packaging,
Handling and Storage of Chemical Wastes as follows. Containers used for storage of chemical
wastes should: · be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed; · have
a capacity of less than 450 L unless the specifications have been approved by
the EPD; and · display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Regulations. |
Biogas
Assessment Monitoring As discussed above,
a number of assumptions and estimations have to be made when theoretically
estimating the rate of gas generation.
This means that the estimate of future rates of gas generation can
provide only an indication of the likely rate of gas emission. In order to determine more accurately the
risk related to biogas emissions from the organic sediment at the undredged
areas, therefore, it is recommended that monitoring of the artificial lake of
Water Recreation Centre in the Theme Park should be undertaken following
completion of the construction works.
This will enable actual rates of gas emission to be determined and
will ensure that account is taken of the effect of changing atmospheric
pressure on the behaviour of the gas reservoir which may accumulate within
the reclamation fill above the gas producing organic sediments. As it is not
practicable to install monitoring wells over the impermeable membrane of the
artificial lake due to potential leakage of water into monitoring wells, it
is recommended that monitoring wells should install in the edge of the
artificial lake of Water Recreation Centre where sediment will be left in
situ (see Figure 6.14b). It may take some
time for fully anaerobic conditions to be established within the organic
sediment and for a reservoir of gas to accumulate within the reclamation fill
so monitoring should be undertaken for as long as possible prior to the
commencement of construction works at the Water Recreation Centre. Ideally, monitoring should be undertaken
for a period of at least one year prior to the commencement of construction. If there is only
limited time between completion of the reclamation and commencement of
construction at Water Recreation Centre, monitoring should commence
immediately upon completion of the reclamation so that any trends may be
observed and results extrapolated to the period of construction and
occupation of the development. Monitoring should be
undertaken via purposely installed monitoring wells installed within
boreholes drilled into the fill material.
The boreholes should be drilled down to the level of the groundwater
(mean sea water level) and standard landfill gas-type monitoring wells should
be installed. These should be fitted
with a removable cap and gas monitoring valve so that gas concentrations may
be measured as well as flow rates from the open well. It is recommended
that two monitoring wells should be installed across the area of the Water
Recreation Centre (Figure 6.14b). These should be located such as to give an
approximately even distribution across the whole area. If they are located within areas
designated for open space, it may be possible to retain them for future
long-term monitoring. The wells
should be monitored as follows: ·
concentrations of the following gases should
be measured using portable monitoring equipment with gas chromatographic (GC)
analysis being undertaken on selected samples to confirm the results: ·
methane ·
carbon dioxide ·
oxygen ·
gas flow rates from the open wells - very
sensitive techniques (such as micro-anemometer) will need to be used to
measure the anticipated very low flow rates. The monitoring
schedule will depend on the relative timing of the reclamation and subsequent
construction works. Ideally, the
boreholes should be drilled and the monitoring wells installed as soon as
possible after the completion of the reclamation works. Monitoring should then take place over a
period of at least one year with the emphasis on the second part of the
year. It will be important to monitor
gas flows from the wells under different meteorological conditions and to
include some occasions when atmospheric pressure is falling quite quickly
(e.g. immediately proceeding a typhoon). |
|
The
storage area for chemical wastes should: · by
clearly labelled and used solely for the storage of chemical waste; · be
enclosed on at least 3 sides; · have
an impermeable floor and bunding, of capacity to accommodate 110% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area, whichever is the greatest; · have
adequate ventilation; · be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed as chemical waste if necessary); and · be
arranged so that incompatible materials are adequately separated. Disposal
of chemical waste should: · be
via a licensed waste collector; and · be
to a facility licensed to receive chemical waste, such as the Chemical Waste
Treatment Facility which also offers a chemical waste collection service and
can supply the necessary storage containers; or · be
to a re-user of the waste, under approval from the EPD. The
Centre for Environmental Technology operates a Waste Exchange Scheme which
can assist in finding receivers or buyers. Management of General Refuse General
refuse generated on-site should be stored in enclosed bins or compaction
units separate from construction and chemical wastes. A reputable waste collector should be
employed by the contractor to remove general refuse from the site, separately
from construction and chemical wastes, on a daily basis to minimise odour
pest and litter impacts. The burning
of refuse on construction sites is prohibited by law. General
refuse is generated largely by food service activities on site, so reusable
rather than disposable dishware should be used if feasible. Aluminium cans are often recovered from
the waste stream by individual collectors if they are segregated of easily
accessible, so separate, labelled bins for their deposit should be provided
if feasible. Office
wastes can be reduced through recycling of paper if volumes are large enough
to warrant collection. Participation
in a local collection scheme should be considered if one is available. In addition, waste separation facilities
for paper, aluminium cans, plastic bottles etc., should be provided. Management of Waste Disposal A
trip-ticket system should be established in accordance with Works Bureau Technical Circular No 5/99
to monitor the disposal of C&DM and solid wastes at public filling facilities
and landfills, and to control fly-tipping.
A trip- ticket system will be included as one of the contractual
requirements and implemented by the Engineer. The Engineer should audit the result of the system. A
recording system for the amount of waste generated, recycled and disposed of
(including the disposal sites) should be established during the construction
stage. Staff Training Training
should be provided to workers on the concepts of site cleanliness and on
appropriate waste management procedures, including waste reduction, reuse and
recycling at the beginning of the contract. |
Biogas
Assessment Monitoring A number of
assumptions and estimations have to be made when theoretically estimating the
rate of gas generation. This means
that the estimate of future rates of gas generation can provide only an
indication of the likely rate of gas emission. In order to determine more accurately the risk related to
biogas emissions from the organic sediment at the undredged areas, therefore,
it is recommended that monitoring of the artificial lake of Water Recreation
Centre in the Theme Park should be undertaken following completion of the
construction works. This will enable
actual rates of gas emission to be determined and will ensure that account is
taken of the effect of changing atmospheric pressure on the behaviour of the
gas reservoir which may accumulate within the reclamation fill above the gas
producing organic sediments. As it is not
practicable to install monitoring wells over the impermeable membrane of the
artificial lake due to potential leakage of water into monitoring wells, it
is recommended that monitoring wells should install in the edge of the
artificial lake of Water Recreation Centre where sediment will be left in situ (see Figure 6.14b). It may take some
time for fully anaerobic conditions to be established within the organic
sediment and for a reservoir of gas to accumulate within the reclamation fill
so monitoring should be undertaken for as long as possible prior to the
commencement of construction works at the Water Recreation Centre. Ideally, monitoring should be undertaken
for a period of at least one year prior to the commencement of construction. If there is only
limited time between completion of the reclamation and commencement of
construction at Water Recreation Centre, monitoring should commence
immediately upon completion of the reclamation so that any trends may be
observed and results extrapolated to the period of construction and
occupation of the development. Monitoring should be
undertaken via purposely installed monitoring wells installed within
boreholes drilled into the fill material.
The boreholes should be drilled down to the level of the groundwater
(mean sea water level) and standard landfill gas-type monitoring wells should
be installed. These should be fitted
with a removable cap and gas monitoring valve so that gas concentrations may
be measured as well as flow rates from the open well. It is recommended
that two monitoring wells should be installed across the area of the Water
Recreation Centre (Figure 6.14b). These should be located such as to give an
approximately even distribution across the whole area. If they are located within areas
designated for open space, it may be possible to retain them for future
long-term monitoring. The wells
should be monitored as follows: ·
concentrations of the following gases should
be measured using portable monitoring equipment with gas chromatographic (GC)
analysis being undertaken on selected samples to confirm the results: ·
methane ·
carbon dioxide ·
oxygen ·
gas flow rates from the open wells - very
sensitive techniques (such as micro-anemometer) will need to be used to
measure the anticipated very low flow rates. In addition, and if practical,
emissions from the surface of the reclaimed land could also be monitored
using flux boxes. The monitoring
schedule will depend on the relative timing of the reclamation and subsequent
construction works. Ideally, the
boreholes should be drilled and the monitoring wells installed as soon as
possible after the completion of the reclamation works. Monitoring should then take place over a
period of at least one year with the emphasis on the second part of the year. It will be important to monitor gas flows
from the wells under different meteorological conditions and to include some
occasions when atmospheric pressure is falling quite quickly (e.g.
immediately proceeding a typhoon). Biogas
Assessment Protection Measures-General Guidelines At this stage it is
difficult to provide precise guidelines on what measures would be required
for the specific rates of gas emission which may measured because this would
depend on the exact pattern of the results and the design/ purpose of the
specific buildings to be erected.
However, the following criteria provide the may be used as general
guidelines: Scenario 1 If rates of methane
emission are consistently much less than the trigger value (10 l m-2
d-1), including monitoring occasions when atmospheric pressure is
falling quite quickly, and they do not show any rising trend over time, then
the buildings will not require gas protection measures. The trigger value of
10 litres (methane) m-2 d-1 is an "area"
emission rate (ie rate at which gas is emitted per unit area of the
reclamation). In order to convert
this into an emission rate from a borehole, it is necessary to make an
assumption about the "area of influence" of a freely venting
borehole which depends on a number of factors - mainly how easy it is for gas
to escape from the surface of the site.
Thus, for a site covered in a hard surface (eg paved) it would be
expected that any borehole would have a much greater area of influence than
if the site had soft landscaping. Different people
have assumed different areas of influence - in WMP 26A, it assumed 100 m2 whereas in the South East Kowloon Development Study,
the consultant assumed approximately 20 m2 (radius of 2.5m). To be conservative, it is proposed to
adopt an area of influence of 20m2, which would give: ·
Trigger value of 10 l m-2 d-1 x 20 m2 =
200 l d-1 emitted from the borehole In practice, such
low rates of gas emission will be measured using 'flux box' methods as the
velocity of the gas (m s-1) will be too low to measure, unless very sensitive
flow meter is used. Thus, expressing
the flow rate as a volume per day or volume per hour will be acceptable. Hence, the criterion for safe flow rate
from the free venting boreholes becomes: ·
Flow rate of methane (in term of l d-1) <
200 l d-1 OR ·
(Gas flow rate in term of l d-1) x (concentration
of methane in gas (in % gas)) <
200 l d-1 Scenario 2 If the rates of
methane emission from any borehole frequently exceed the trigger value or
show a rising trend such that future emission rates are likely to exceed the
trigger value, then any buildings to be constructed on that part of the site
will require some form of gas protection measures. That is when: ·
(Gas flow rate in term of l d-1) x
(concentration of methane in gas (in % gas)) > 200 l d-1 The exact details of
the gas protection measures would need to be designed to take into account
the design and use of the particular buildings involved but would, most
probably, include the installation of a low gas permeability membrane in the
floor slab of the building. The exact
area of the reclamation over which buildings would need to have gas
protection measures would depend on the pattern of the results from the
different monitoring boreholes and further investigation may be required to
determine the area of land which is affected by gas emissions. The analysis and assessment of the results
and design of any gas protection measures, should be undertaken by suitably
qualified and experienced professionals who are familiar with the properties
of biogas and the way in which buildings may be protected against the impacts
of gases derived from the ground. Scenario 3 If there are
occasional exceedances of the methane emission rate trigger value or if there
is significant fluctuation of the results obtained with some readings coming
close to the trigger value, then the exact pattern and any trends in the
results will need to be assessed to determine their significance and whether
any building protection measures are required. It might be necessary to undertake additional monitoring by
extending the monitoring period, for example, if an apparently spurious high
reading is noted towards the end of the monitoring period or if it seems
likely that future rates of emission may exceed the trigger value. Whatever the results
obtained from the proposed monitoring of gas emission rates, the analysis and
assessment of the results and design of any gas protection measures, should
be undertaken by suitably qualified and experienced professionals who are
familiar with the properties of biogas and the way in which buildings may be
protected against the impacts of gases derived from the ground. Scenario 4 If the rates of
methane emission from any borehole frequently exceed the Limit value (84.7 l
m-2 d-1), or show a rising trend such that future emission rates are likely
to exceed the limit value, then no buildings should be constructed on that
part of the site. That is when: ·
Limit value of 84.7 l m-2 d-1 x 20 m2 =
1,694 l d-1 emitted from the
borehole OR ·
(Gas flow rate in term of l d-1) x
(concentration of methane in gas (in % gas)) > 1,694 l d-1 Typical /Generic Protection Measures Depending on the
results of the monitoring recommended above, it may be necessary (although at
this stage it is considered that it is unlikely to be required) to incorporate
a number of general protection measures into the design of the redevelopment
and to include specific measures in the design of individual buildings.
Specific details cannot be provided until the results of this
monitoring and exact details of individual building designs are
available. A combination of different
measures may be used for protecting the development against possible risks
due to biogas and discussions would need to be held with the developers and
architects to determine which are the most appropriate. Typical, generic,
protection measures which may be employed (depending on the results of the
monitoring and exact building designs) include the following: Ventilation
of Gas from the Reclaimed Land: Vertical
boreholes/wells could be installed across the area of the reclamation to
allow gas to vent to atmosphere thereby preventing the build-up of gas
pressures within the fill material.
Care would be needed in the design of the venting stacks to ensure
that any gas was safely vented without causing nuisance or danger to users of
the land. This technique is probably
appropriate only if the monitoring indicates a relatively high rate of gas
emission. More specific areas
of the development could be targeted such as the footprints of specific
buildings or other sensitive areas.
In this case the ventilation measures would be designed specifically
to prevent the build up of gas pressure beneath a building, for example, and
could comprise a network of horizontal gas collection pipes installed underneath
the building connected to a number of risers to allow any accumulated gas to
be dispersed to atmosphere at a suitable level above ground. Barriers
to Prevent Ingress of Gas into Buildings:
There are a number of ways of ensuring that
any gas derived from the ground does not enter a building. Typically these involve the incorporation
of some kind of low gas permeability membrane in the design of the floor and
any below ground walls of any ‘at risk’ rooms. In addition, measures must be taken to avoid or seal any
openings in the floor (e.g. at service entry points). Such techniques are commonly used where
there is a risk of landfill gas entering a building and have been employed on
a number of developments in Hong Kong. There are various
proprietary products which may be used and the specific details of their
application will depend very much on the individual building design. In all cases,
extreme care is needed in the installation of the membrane and the other
protection measures to ensure that they meet the design requirements and to
avoid damage during installation and subsequent construction works. Adequate QA/QC procedures are therefore
essential to ensure that such measures are effective. Ventilation
within Buildings: As
an additional or alternative measure for the protection of specific rooms,
ventilation (passive or mechanical depending on the circumstances) may be
provided to ensure that if any gas enters the room it is dispersed and cannot
accumulate in dangerous volumes. For
particularly sensitive rooms, such as below ground confined spaces which
contain sources of ignition, forced ventilation may be used in addition to
the use of a low permeability membrane whereas for low sensitivity areas
ventilation may be used on its own. Protection
of Below Ground Services: As
they are installed below ground, conduits in which services (e.g. electricity
and other cables) are installed are particularly prone to the ingress and
accumulation of gas derived from the ground.
It is therefore important to prevent such conduits acting as easy
routes by which gas may enter buildings by avoiding, as far as possible, any
penetration of floor slabs by such services or, as a minimum, ensuring that
any unavoidable penetrations are carefully sealed using an appropriate low
permeability sealant. In addition,
accumulation of gas within any associated manholes or access chambers can
present a risk to the staff of the utility companies. All such companies and organisations which
may have cause to work on such below ground infrastructure should be warned
of the potential dangers and advised to take appropriate precautions. Clear warning notices together with
contact details for further information and advice should be provided on any
access points to below ground chambers. Precautions
During Construction Similarly,
precautions may be required to ensure that there is no risk due to the
accumulation of gas within any temporary structures, such as site offices,
during any construction works on the reclamation area. It may be necessary, for example, to raise
such structures slightly off the ground so that any gas emitted from the
ground beneath the structure may disperse to atmosphere rather than entering
the structure. The exact
requirements for precautionary measures during the construction phase would
need to be specified following assessment of the results obtained from the
monitoring recommended above and the details would depend on the depth of
excavation or nature of the voids/structures involved. Further information
and advice, including the precautions required for the drilling of the
monitoring boreholes, may be found in the Hong Government’s advisory document
Landfill Gas Hazard Assessment Guidance
Note prepared by the Environmental Protection Department. |
Residual Impact |
No
residual impact. |
No residual impact. |
Environmental Acceptability |
Acceptable |
Acceptable |
Table
6.15b - Impacts Summary Table for CKWLR
Issue |
Construction Impact |
Assessment
Points |
CKLWR
Boundary |
Relevant
Criteria |
Waste Disposal Ordinance, Waste
Disposal (Chemical Waste) (General) Regulation, Land (Miscellaneous
Provisions) Ordinance, Public Health and Municipal Services Ordinance,
Dumping at Sea Ordinance, Waste Disposal Plan for Hong Kong, New Disposal
Arrangements for Construction Waste, Code of Practice on the Packaging,
Labelling and Storage oe Chemical Wastes, EPDTC 1-1-92, WBTC Nos. 6/92,
22/92, 32/92, 2/93, 16/96, 4/98, 5/98, 5/99 and 25/99,
and Waste Reduction Framework Plan. |
Potential Impact |
Dredged/Excavated Sediment Dredging
of a large quantity of sediment within a short period of time will have the
potential to cause adverse water quality impact if not properly managed. Section
5 has discussed the mitigation measures necessary to avoid adverse water
quality impacts during the dredging works. Although the quality of cannot be
determined at this stage, based on the sediment quality at Fa Peng and
Penny’s Bay Reclamation Stage II, out of the 4.2 M m3 of sediment
to be dredged for CKWLR, high contamination in As and Cu is likely to be
found at seabed level, and, therefore, biological tests will be required to
determine the final disposal route. For
the sediment to be dredged for the Yam O to Penny’s Bay Interchange, which is
located at the vicinity of the Cheoy Lee Shipyard, although the volume is
minimal (1,300 m3), due to its seriously contaminated nature (Class C),
disposal at East Sha Chau Contaminated Mud Pit is required. Use of Public Fill for the Reclamation The
CKWLR Phases I and II reclamations will require 8.6 M m3 of
fill/surcharge material between Q2 2002 to Q1 2004 and Q4 2026 to Q2 2028 (45
months). Public fill will be used as
fill material and also surcharge material.
The volume of public fill to be used is 7.3 M m3, which is
approximately 85% of the total filling/surcharge material required. The
use of public fill as filling material may give rise as floating debris
during reclamation. Part of the all
the reclamations will be designated as a public filling area. Public fill comprising earth, building
debris and broken concrete may contain a small amount of floatable materials
such as timber, plastic and paper. If
not properly controlled, it may give rise to floating refuse |
|
Excavated Material A
total of approximately 3.0 M m3 of excavated is expected to be
generated from the construction of the CKWLR, primary as a result of
excavation at slopes of Pa Tau Kwu.
This figure include the 10,200 m3 of excavated material to
be generated from slope excavation for the Yam O to Penny’s Bay Interchange
as well as during the excavation at Yam O, Pa Tau Kwu. Small amounts of excavated material will
also expected from the foundation works carried out at CKWLR Phases I and
II. The daily generation rate is
3,000 m3 d-1. The
excavated materials generated at Yam O to Penny’s Bay Interchange and Pa Tau
Kwu will consist of clean rock and soil.
Whereas the excavated material generated at CKWLR Phases I and II
reclamations will be the same as fill materials used for the reclamation ( ie
either marine sand fill or inert public fill). Excavated
material generated at Yam O to Penny’s Bay Interchange could be reused
on-site for filling at the Cheoy Lee Shipyard area ([30]). Whereas excavated material generated at Pa
Tau Kwu and CKWLR Phases I and II could be re-used within other NLDFS
reclamation such as Penny’s Bay Reclamation Stage II or Theme Park (Phase
III) Extension reclamation. No
surplus excavated material will be generated. As
the Penny’s Bay Stage II and Theme Park (Phase III) Extension reclamations
require a large quantity of fill material and the Project will have an
overall deficit of fill material. It
is anticipated that all the excavated soil and rock generated from the
Project will be re-used for the reclamation works. Since public filling areas only accept public fill with certain
size (< 200 mm diameter). Some of
the excavated material may require to be broken prior re-use on site. No surplus of excavated material will be
generated. |
|
C&D Waste Although
no details on the GFA is available, the structures to be demolished at Ngong
Shuen Au and Cheoy Lee Shipyard are considered is likely to be small and
simple and the volume of demolition material to be generated is likely to be
small. The potential environmental
impacts associated with the decommissioning and demolition of the shipyard is
addressed in Section 12 and will be
evaluated under a separate Schedule 2 EIA to be commissioned by the CED. With
respect to the demolition works at Ngong Shuen Au and Wan Tuk Village, the
volume demolition material to be generated is likely to be minimal and
consist of a mixture of inert (ie concrete, tiles, bricks, etc. which are
classified as public fill) and putrescible (paper, plastic, wood, etc. which
are classified as C&D waste) materials.
The public fill should be reused on site, as far as practicable. If on-site use is not practicable, the
public fill should be delivered to other reclamation sites or to public
filling areas available at that time.
The disposal of inert C&D material at public filling areas or other
reclamation sites is unlikely to raise any long term concerns because of its
inert nature. Due to small volume of
arisings, the disposal of C&D waste at strategic landfills will not cause
any unacceptable environmental impacts. It
is not anticipated that there will be any potential hazard associated with
handling and disposal of C&D material if general construction safety
procedures are properly implemented. Chemical Waste A
small volume of chemical waste, such as used lubricating oils from plant maintenance
materials, will be produced. Provided
chemical wastes are disposed of at a licensed facility, the contractor should
be in compliance with all relevant regulations and there will be little
environmental impact. |
|
General Refuse The
maximum daily number of workers on site is 350. Based on a waste generation rate of about 0.65 kg per person,
it is estimated that the amount of general refuse to be generated will be in
the order of 227.5 kg d-1. |
Mitigation Measures |
The
Contractor should development a Waste Management Plan to Engineer approval
prior to construction. Such a
management plan should incorporate site specific factors, such as the
designation of areas for the segregation and temporary storage of reusable
and recyclable materials. Dredged/Excavated Sediment · minimising
exposure to any contaminated material by the wearing of protective gear such
as gloves, providing adequate hygiene and washing facilities, and preventing
eating during dredging/excavation; · any
contaminated sediment dredged should not be allowed to stockpile on the site
and should be immediately removed from site once dredged; · all
vessels for marine transportation of dredged sediment should be fitted with
tight fitting seals to their bottom openings to prevent leakage of materials;
and · loading
of barges and hoppers should be controlled to prevent splashing of dredged
material to the surrounding water, and barges or hoppers should under no
circumstances to be filled to a level which will cause other overflowing of
materials or polluted water during loading or transportation. Use of Public Fill for the reclamation The
Contractor should enforce strict application of the public fill license and
monitor the material placed in the reclamation and barges to control disposal
of unauthorised material. The
Contractor shall also provide floating booms and collect any floating
materials on a daily basis at the public filling areas. Excavated Material Wherever
practicable, excavated materials should be segregated from other wastes to
avoid contamination thereby ensuring acceptability at public filling areas or
reclamation sites and avoiding the need for disposal at landfill. The priority for off-site disposal of
surplus excavated material should be as follows: · transport
to other reclamation sites at North Lantau and Penny's Bay areas; and transport
to public filling areas Measures Taken in the Planning and
Design Stages to Reduce the Generation of C&DM
· avoidance
and minimisation, that is, not generating waste through changing or improving
practices and design; · reuse
of materials, thus avoiding disposal (generally with only limited
reprocessing); · recovery
and recycling, thus avoiding disposal (although reprocessing may be
required); and · treatment
and disposal, according to relevant law, guidelines and good practice. |
|
This
hierarchy should be used to evaluate the waste management options, thus
allowing maximum waste reduction and often reducing costs. For example, by reducing or eliminating
over-ordering of construction materials, waste is avoided and costs are
reduced both in terms of purchasing of raw materials and in disposing of
wastes. Records of quantities of
wastes generated, recycled and disposed (locations) should be properly kept. Standard
formwork should be used as far as practicable in order to minimise the
arisings of C&DM. The use of more
durable formwork or plastic facing for the construction works should be
considered during the detailed design. Any
uncontaminated soil should be reused on site as far as possible for landscape
works in order to minimise the amount public fill to be disposed off-site.
Should there be any surplus public fill generated from the project, the HKITP
should liaise with the Public Filling Sub-Committee to identify as far as
possible suitable reclamation or site formation projects near the project
site to reuse the material. The
design of the foundation works will minimise the amount of excavated material
to be generated. Should piling be
required, H-piling will be used as far as practical. The
purchasing of construction materials will be carefully planned in order to
avoid over ordering and wastage of construction materials, such as ready
mixed concrete. Measures To be Taken in the
Construction Stage To Reduce the Generation of C&DM The
Contractor should recycle as much as possible of the C&D material
on-site. Public fill and C&D
waste should be segregated and stored in different containers or skips to
enhance reuse or recycling of materials and their proper disposal. Concrete and masonry, for example can be
crushed and used as fill and steel reinforcing bar can be used by scrap steel
mills. Different` areas of the work
sites should be designated for such segregation and storage. |
|
At
present, Government is developing a charging policy for the disposal of waste
to landfill. When it is implemented,
this will provide additional incentive to reduce the volume of waste
generated and to ensure proper segregation to allow disposal of inert
material to public filling areas. In
order to minimise the impacts of the demolition works these wastes must be
cleared as quickly as possible after demolition. The demolition and clearance works should therefore be
undertaken simultaneously. Chemical Waste For
those processes which generate chemical waste, it may be possible to find
alternatives which generate reduced quantities or even no chemical waste, or
less dangerous types of chemical waste. Chemical
waste that is produced, as defined by Schedule
1 of the Waste Disposal (Chemical
Waste) (General) Regulation, should be handled in accordance with the Code of Practice on the Packaging,
Handling and Storage of Chemical Wastes as follows. Containers used for storage of chemical
wastes should: · be
suitable for the substance they are holding, resistant to corrosion,
maintained in a good condition, and securely closed; · have
a capacity of less than 450 L unless the specifications have been approved by
the EPD; and · display
a label in English and Chinese in accordance with instructions prescribed in
Schedule 2 of the Regulations. The
storage area for chemical wastes should: · by
clearly labelled and used solely for the storage of chemical waste; · be
enclosed on at least 3 sides; · have
an impermeable floor and bunding, of capacity to accommodate 110% of the
volume of the largest container or 20% by volume of the chemical waste stored
in that area, whichever is the greatest; · have
adequate ventilation; · be
covered to prevent rainfall entering (water collected within the bund must be
tested and disposed as chemical waste if necessary); and · be
arranged so that incompatible materials are adequately separated. |
|
Disposal
of chemical waste should: · be
via a licensed waste collector; and · be
to a facility licensed to receive chemical waste, such as the Chemical Waste
Treatment Facility which also offers a chemical waste collection service and
can supply the necessary storage containers; or · be
to a re-user of the waste, under approval from the EPD. The Centre for
Environmental Technology operates a Waste Exchange Scheme which can assist in
finding receivers or buyers. Management of General Refuse General
refuse generated on-site should be stored in enclosed bins or compaction
units separate from construction and chemical wastes. A reputable waste collector should be
employed by the contractor to remove general refuse from the site, separately
from construction and chemical wastes, on a daily basis to minimise odour
pest and litter impacts. The burning
of refuse on construction sites is prohibited by law. General
refuse is generated largely by food service activities on site, so reusable
rather than disposable dishware should be used if feasible. Aluminium cans are often recovered from
the waste stream by individual collectors if they are segregated of easily
accessible, so separate, labelled bins for their deposit should be provided
if feasible. Office wastes can be
reduced through recycling of paper if volumes are large enough to warrant
collection. Participation in a local
collection scheme should be considered if one is available. In addition, waste separation facilities
for paper, aluminium cans, plastic bottles etc., should be provided. Management of Waste Disposal A trip-ticket system
should be established in accordance with Works
Bureau Technical Circular No 5/99 to monitor the disposal of C&DM and
solid wastes at public filling facilities and landfills, and to control
fly-tipping. A trip-ticket system
will be included as one of the contractual requirements and implemented by
the Engineer. The Engineer should
audit the result of the system. A recording system
for the amount of waste generated, recycled and disposed of (including the
disposal sites) should be established during the construction stage. |
|
Staff Training Training should be
provided to workers on the concepts of site cleanliness and on appropriate
waste management procedures, including waste reduction, reuse and recycling
at the beginning of the contract. |
Residual
Impact |
No
residual impact. |
Environmental
Acceptability |
Acceptable |
([1]) "C&D material" refers to surplus materials arising from any land excavation or formation, civil/building construction, roadwork, building renovation or demolition activities. It includes various types of reusable materials, building debris, rubble, earth, concrete, timber and mixed site clearance materials. When sorted properly, materials suitable of building reclamation and site formation (known as public fill) should be reused at public filling areas whereas the remaining C&D waste are to be disposed at landfills.
([2]) EPD Communication red EP20/03/205 M.
([3]) Construction of An International Theme Park in Penny's Bay of North Lantau and Its Essential Associated Infrastructure EIA, for CED, prepared by ERM, February 2000.
([4])
Construction of An International Theme Park in Penny's Bay of North Lantau and
its Essential Associated Infrastructures, for CED, prepared by ERM, February
2000.
([5]) A Study of Tributylin Contamination of Marine Environment of Hong Kong, for EPD, Aspinwall (1998).
([6]) Construction of An International Theme Park in Penny’s Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, prepared by ERM, February 2000.
([7]) Construction and Demolition material (C&D material) contains a mixture of inert and non-inert material. The inert portion is 'public fill'. The non-inert portion is 'C&D waste'.
([8]) 4,300 from Penny’s Bay Reclamation, Yam O Reclamation and Theme Park, 1,700 from other NLDFS developments and CKWLR construction.
([9]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, prepared by ERM, February 2000.
([10]) Environmental Resources Management (1999). Sludge Treatment and Disposal Strategy Study Final Report, 9 July 1999.
([11]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([12]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([13]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([14]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([15]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([16]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([17]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([18]) Environmental Protection Department (1997), Landfill Gas Hazard Assessment Guidance Note.
([19]) Report 152: Risk Assessment for Methane and Other Gases from the Ground, 1995.
([20]) Calculation as follows:
·
0.05ms-1 from borehole = 4,320 m d-1
·
From cross-sectional area of borehole (1.96 x 10-3
m2) = 8.47m3 d-1
·
Assuming that the gas released from the borehole is
being collected from an area of ground of, say, 100m2 (radius of
influence = 5.6m), then maximum safe rate of emission is:
8.47/100 m3 CH4
m-2 d-1
= 0.0847 m3 CH4 m-2 d-1 or 84.7 litre CH4 m-2 d-1
([21]) Shelton David and Tiedje J (1984) General Method for Determining Anaerobic Biodegradation Potential. Applied and Environmental Microbiology, 47 (7), pp850-857
([22]) Biotal Ltd (1992) further development of Landfill Assessment Methods: The Potential Gas Yield and Gas Production Rate Test. DoE Report CWM 090/93, September 1992.
([23]) Croft BC and Campbell DJV Assessment of a Test for Biological Methane Potential, DoE Report CWM 103/94, May 1994.
([24]) Testing methods of SOD and TOC are agreed by EPD.
([25]) It is calculated based on the methane generation potential.
([26]) The hydraulic and water quality studies undertaken in 1989 indicated that the siltation rate in Victoria Harbour was only about 500 mm yr-1.
([27]) Remote Survey on Soft Bottom Environments in Coastal Waters of Hong Kong, 1983, Binnie Consultants Ltd.
([28]) Seabed Ecology Studies: Thathong Channel Final Report, 1997, ERM-HK.
(28)"Biogas Risk Assessment" report of Tsuen Wan Bay Further Reclamation and "Potential Methane Gas Risk" report of South East Kowloon, CES (Asia) Ltd.
([29]) Hock, J., (1992). Effect of leaking natural gas on soil and vegetation in urban areas, Wageningen.
([29]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.
([30]) Construction of An International Theme Park in Penny's Bay of North Lantau and its Essential Associated Infrastructure EIA, for CED, February 2000.