Agreement No. CE5/95
Central-Wan Chai Bypass and
Island Eastern Corridor Link
Project Review Study
ENVIRONMENTAL
IMPACT ASSESSMENT REPORT
TABLE
OF CONTENTS
1. INTRODUCTION
1.1 Project Background
1.2 Objectives of the EIA Study
1.3 Considerations of Environmental Impact Assessment Ordinance
1.4 Structure of EIA Report
2.1 Project Location
2.2 Development Requirements, Scope and Benefits
2.3 EIA Study Area
2.4 Project Design
2.5 Construction Methods and Engineering Requirements
2.6 Operation of the Project
2.7 Works Programme
2.8 "Without the Project" Scenario
2.9 Concurrent Projects
3. AIR QUALITY
3.1 Introduction
3.2 Environmental Legislation, Policies, Plans, Standards and Criteria
3.3 Description of the Environment
3.4 Sensitive Receivers
3.5 Assessment Methodology
3.6 Identification of Environmental Impacts
3.7 Prediction and Evaluation of Environmental Impacts
3.8 Mitigation of Adverse Environmental Impacts
3.9 Evaluation of Residual Impacts
3.10 Environmental Monitoring and Audit
3.11 Conclusion
4. NOISE
4.1 Introduction
4.2 Environmental Legislation, Policies, Plans, Standards and Criteria
4.3 Description of the Environment
4.4 Sensitive Receivers
4.5 Assessment Methodology
4.6 Prediction and Evaluation of Environmental Impacts
4.7 Mitigation of Adverse Environmental Impacts
4.8 Evaluation of Residual Impacts
4.9 Environmental Monitoring and Audit
4.10 Conclusion
5.1 Introduction
5.2 Environmental Legislation, Policies, Plans, Standards and Criteria
5.3 Description of the Environment
5.4 Water Sensitive Receivers
5.5 Assessment Methodology
5.6 Identification of Environmental Impacts
5.7 Prediction and Evaluation of Environmental Impacts
5.8 Mitigation of Adverse Environmental Impacts
5.9 Evaluation of Residual Impacts
5.10 Environmental Monitoring and Audit
5.11 Conclusion
6. CONSTRUCTION
WASTE MANAGEMENT AND DISPOSAL
6.1 Introduction
6.2 Environmental Legislation, Policies, Plans, Standards and Criteria
6.3 Assessment Methodology
6.4 Identification of Environmental Impacts
6.5 Prediction and Evaluation of Environmental Impacts
6.6 Recycling, Treatment, Storage and Disposal Options
6.7 Mitigation of Adverse Environmental Impacts
6.8 Evaluation of Residual Impacts
6.9 Environmental Monitoring and Audit
6.10 Conclusion
7. LANDSCAPE AND
VISUAL IMPACT ASSESSMENT
7.1 Introduction
7.2 Scope and Content of Study
7.3 Review of the Planning and Development Control Framework
7.4 Baseline Conditions
7.5 Potential Impacts
7.6 Mitigation Measures
7.7 Conclusion – Residual Impacts and Predicted Acceptability of the Project
8. ENVIRONMENTAL
MONITORING AND AUDIT
8.1 Introduction
8.2 Air Quality Impact
8.3 Noise Impact
8.4 Water Quality Impact
8.5 Waste Management
8.6 Landscape and Visual
9. CONCLUSION
9.1 Introduction
9.2 Air Quality Impact
9.3 Noise Impact
9.4 Water Quality Impact
9.5 Construction Waste Management and Disposal
9.6 Landscape and Visual Impact
9.7 Overall Conclusion
10. IMPLEMENTATION
SCHEDULE OF THE PROPOSED MITIGATION MEASURES
List of Tables
Table 2.1 Projects
that may be Undertaken Simultaneously with the CWB & IECL Project
Table 3.1 Hong Kong
Air Quality Objectives
Table 3.2 Tunnel Air
Quality Criteria
Table 3.3 Annual
Average Concentrations of Pollutants in 1999
Table 3.4 Locations
of Air Sensitive Receivers
Table 3.5 Emission
Factors for Construction Activities
Table 3.6 Different Major Dust Generating Activities in the
Worst-case Scenarios during Construction Phase
Table 3.7 Emission
Factors for Year 2011 for Different Vehicle Categories (EURO3)
Table 3.8 Portal and
Ventilation Building Emissions
Table 3.9 Design of
the Ventilation Buildings
Table 3.10 Predicted Cumulative 1-hour Average TSP
Concentration for Scenarios 1 to 10 (Unmitigated)
Table 3.11 Predicted Cumulative 24-hour Average TSP
Concentration for Scenarios 1 to 10 (Unmitigated)
Table 3.13 Predicted Cumulative 1-hour Average TSP
Concentration for Scenarios 1 to 10 (Mitigated)
Table 3.14 Predicted Cumulative 24-hour Average TSP
Concentration for Scenarios 1 to 10 (Mitigated)
Table 4.1 Construction Noise Criteria for Activity other than
Percussive Piling
Table 4.2 Acceptable Noise Levels for Percussive Piling
Table 4.3 Permitted Hours of Operation for Percussive Piling
Table 4.4 Acceptable Noise Level for Fixed Plant Noise
Table 4.5 Summary of Identified Existing Noise Sensitive
Receivers
Table 4.8 Summary of Selected Noise Sensitive Receivers for
Fixed Noise Impact Assessment
Table 4.9 The Number of Exhaust Fans required for Proposed
Ventilation Buildings during Normal Condition
Table 4.10 Summary of Unmitigated Construction Noise Levels
during Normal Daytime Working Hours
Table 4.11 Predicted Fixed Noise Levels at NSRs (Leq, 30
min dB(A))
Table 5.1 Summary of Water Quality Objectives for the Victoria
Harbour WCZ
Table 5.2 WSD Standards at Seawater Intakes
Table 5.3 Summary
Statistics of EPD Marine Water Quality data in Victoria Harbour WCZ for 1998
Table 6.1 Excavated Material from Works Managed by Highways
Department
Table 6.2 Excavated Material for Work Entrusted to Territory
Development Department
Table 6.3 Estimated Quantities of C&D Material from New
Building Construction
Table 6.4 Estimated Quantities of Demolition Material
Table
6.5 Summary
of the C&D Material requiring disposal off-site arising from the CWB &
IECL Project
Table 7.1 Matrix for
Assessment of Significance of Landscape Impact
Table 7.2 Matrix for
Assessment of Significance of Visual Impact
Table 7.3 Summary of
Landscape Impact Assessment
Table 7.4 Summary of Visual
Impact Assessment - Impacts on Visual Receivers
Table 7.5 Proposed
Landscape and Visual Mitigation Measures
Table 8.1 Tunnel Air
Quality Guidelines
Table 10.1 Implementation Schedule for Air Quality Control
Table 10.2 Implementation Schedule for Noise Control
Table 10.3 Implementation Schedule for Water Quality Control
Table 10.4 Implementation Schedule for Construction Waste
Management
Table 10.5 Implementation Schedule for Landscape and Visual
Impact Mitigation
Table 10.6 Implementation Schedule for Other EIA Requirements
List of Figures
Figure 2.1 Location and Alignment of CWB & IECL
Figure 2.2 Project Relationship Key Plan (Sheet 1 of
3)
Figure 2.3 Project Relationship Key Plan (Sheet 2 of
3)
Figure 2.4 Project Relationship Key Plan (Sheet 3 of
3)
Figure 2.5 Trunk Road Scheme Option A - Tunnel
and Flyover Scheme
Figure 2.6 Trunk Road Scheme Option B - Flyover
Scheme
Figure 2.7 Trunk
Road Scheme Option C - Flyover Scheme with Alignment close to the Shoreline
Figure 2.8 Trunk Road Scheme Option D - Flyover
Scheme with Alignment along the Breakwater
Figure 2.9 Trunk
Road Scheme Option E - Tunnel Scheme with Alignment close to the Shoreline
Figure 2.10 Trunk Road Scheme Option F - Cut and
Cover and Tunnel Scheme with Alignment close to the breakwater
Figure 2.11 Trunk Road Scheme Option F - Cut and
Cover and Tunnel Scheme with Alignment close to the breakwater
Figure 2.12 Trunk Road Scheme Option F1 -
Immersed Tunnel Scheme
Figure 2.13 Trunk Road Scheme Option G - At
Grade Road Scheme
Figure 3.1.1 Locations of Representative Air
Sensitive Receivers
Figure 3.1.2 Locations of Representative Air
Sensitive Receivers
Figure 3.2.1 Locations of Construction Sites
Figure 3.2.2 Locations of Construction Sites
Figure 3.3.1 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.3.2 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.3.3 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.3.4 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.3.5 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.3.6 2027 AM Peak Hour Forecast Traffic
Flow
Figure 3.4.1 Locations of Portals and
Ventilation Buildings Emissions
Figure 3.4.2 Locations of Portals and
Ventilation Buildings Emissions
Figure 3.5.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.5.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.5.3 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.5.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.6.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 10 m
Above Ground
Figure 3.6.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 10 m
Above Ground
Figure 3.6.3 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 10 m
Above Ground
Figure 3.6.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 10 m
Above Ground
Figure 3.7.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 20 m
Above Ground
Figure 3.7.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 20 m Above
Ground
Figure 3.7.3 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 20 m
Above Ground
Figure 3.7.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 20 m
Above Ground
Figure 3.8.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 30 m
Above Ground
Figure 3.8.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 30 m
Above Ground
Figure 3.8.3 Contours of Cumulative Maximum 1-Hour
Average NO2 Concentration in mg m-3 at 30 m
Above Ground
Figure 3.8.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 30 m
Above Ground
Figure 3.9.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 70 m
Above Ground
Figure 3.9.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 70 m
Above Ground
Figure 3.9.3 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 70 m
Above Ground
Figure 3.9.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 70 m
Above Ground
Figure 3.10.1 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 110 m
Above Ground
Figure 3.10.2 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 110 m
Above Ground
Figure 3.10.3 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 110 m
Above Ground
Figure 3.10.4 Contours of Cumulative Maximum
1-Hour Average NO2 Concentration in mg m-3 at 110 m
Above Ground
Figure 3.11.1 Contours of Cumulative Maximum
24-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.11.2 Contours of Cumulative Maximum
24-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.11.3 Contours of Cumulative Maximum
24-Hour Average NO2 Concentration in mg m-3 at 1.5 m Above
Ground
Figure 3.11.4 Contours of Cumulative Maximum
24-Hour Average NO2 Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.12.1 Contours of Cumulative Maximum
24-Hour Average RSP Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.12.2 Contours of Cumulative Maximum
24-Hour Average RSP Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.12.3 Contours of Cumulative Maximum
24-Hour Average RSP Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.12.4 Contours of Cumulative Maximum
24-Hour Average RSP Concentration in mg m-3 at 1.5 m
Above Ground
Figure 3.13.1 Contours of Cumulative Maximum
1-Hour Average CO Concentration in mg m-3 at 1.5 m Above Ground
Figure 3.13.2 Contours of Cumulative Maximum
1-Hour Average CO Concentration in mg m-3 at 1.5 m Above Ground
Figure 3.13.3 Contours of Cumulative Maximum 1-Hour
Average CO Concentration in mg m-3 at 1.5 m Above Ground
Figure 3.13.4 Contours of Cumulative Maximum
1-Hour Average CO Concentration in mg m-3 at 1.5 m Above Ground
Figure 3.14.1 Contours of Cumulative Maximum
1-Hour Average TSP Concentration in mg m-3 at 1.5 m Above Ground (Mitigated)
Figure 3.14.2 Contours of Cumulative Maximum
1-Hour Average TSP Concentration in mg m-3 at 1.5 m Above Ground (Mitigated)
Figure 3.14.3 Contours of Cumulative Maximum
1-Hour Average TSP Concentration in mg m-3 at 1.5 m Above Ground (Mitigated)
Figure 3.14.4 Contours of Cumulative Maximum
1-Hour Average TSP Concentration in mg m-3 at 1.5 m Above Ground (Mitigated)
Figure 3.15.1 Contours of Cumulative Maximum
24-Hour Average TSP Concentration in mg m-3 at 1.5 m
Above Ground (Mitigated)
Figure 3.15.2 Contours of Cumulative Maximum
24-Hour Average TSP Concentration in mg m-3 at 1.5 m
Above Ground (Mitigated)
Figure 3.15.3 Contours of Cumulative Maximum
24-Hour Average TSP Concentration in mg m-3 at 1.5 m
Above Ground (Mitigated)
Figure 3.15.4 Contours of Cumulative Maximum
24-Hour Average TSP Concentration in mg m-3 at 1.5 m
Above Ground (Mitigated)
Figure 4.1.1 Locations of Representative Noise Sensitive
Receivers (Sheet 1 of 2)
Figure 4.1.2 Locations of Representative Noise
Sensitive Receivers (Sheet 2 of 2)
Figure 4.2.1 The Extent of Porous Asphalt Road
Surfacing
Figure 4.2.2 The Extent of Porous Asphalt Road
Surfacing
Figure 4.3 Locations of Ventilation Buildings
Figure 4.4.1 Locations of Noise Mitigation Measures
(Sheet 1 of 2)
Figure 4.4.2 Locations of Noise Mitigation Measures
(Sheet 2 of 2)
Figure 7.1 Location Plan and Landscape Impact
Study Area
Figure 7.2.1 Works Layout Plan
Figure 7.2.2 Works Layout Plan
Figure 7.2.3 Works Layout Plan
Figure 7.3.1 Landscape Resources and Distinct
Landscape Areas Plan
Figure 7.3.2 Landscape Resources and Distinct
Landscape Areas Plan
Figure 7.3.3 Landscape Resources and Distinct
Landscape Areas Plan
Figure 7.3.4 Existing Significant Trees
Figure 7.4 Visual Envelope and Key Views
Location
Figure 7.5 Locations of Key Visual Sensitive
Receivers
Figure 7.6.1 Mitigation Measures
Figure 7.6.2 Mitigation Measures
Figure 7.6.3 Mitigation Measures
Figure 7.6.4 Mitigation Measures
Figure 7.6.5 Mitigation Measures
Figure 7.6.6 Mitigation Measures
Figure 7.6.7 Mitigation Measures
Figure 7.6.8 Mitigation Measures
Figure 7.6.9 Typical Section
Figure 7.6.10 Typical Section
Figure 7.7.1 Schematic Design of Noise Barriers
Figure 7.7.2 Schematic Design of Semi-Enclosure
Noise Barrier
Figure 7.8 Photomontage Location Plan
Figure 7.9.1 Photomontage View 1
Figure 7.9.2 Photomontage View 1
Figure 7.10.1 Photomontage View 2
Figure 7.10.2 Photomontage View 2
Figure 7.11.1 Photomontage View 3
Figure 7.11.2 Photomontage View 3
Figure 7.12.1 Photomontage View 8
Figure 7.12.2 Photomontage View 8
Figure 7.12.3 Photomontage View 8
Figure 7.13 Rumsey Street Flyover View 4
Figure 7.14 West Ventilation Building and Portal
View 5
Figure 7.15 Central Ventilation Building View 6
Figure 7.16 East Ventilation and Administration
Building View 7
List of Appendices
Appendix 2.1 Trunk Road Options
Appendix 3.1 Summary of Major Dust
Generating Activities
Appendix 3.2 Calculation of Dust
Emission Factors
Appendix 3.3 Sample Computer Output of
FDM Calculation
Appendix 3.4 Calculation of Emission
Factor in Year 2027 (Open Road)
Appendix 3.5 Sample Computer Output of
CALINE4 Calculation
Appendix 3.6 Calculation of Emission
Factor in Year 2027 (Portal)
Appendix 3.7 Sample Computer Output of
ISCST3 Calculation
Appendix 3.8 Dust Levels from
Different Construction Activities (Unmitigated)
Appendix 3.10 Dust Levels from
Different Construction Activities (Mitigated)
Appendix 4.1 Powered Mechanical
Equipment (PME) for Different Construction Tasks
Appendix 4.2 Construction Noise
Calculation
Appendix 4.3 Locations of ‘New’ Roads
Figure A4.1 Locations of New Roads for CWB Project (Sheet
1 of 3)
Figure A4.2 Locations of New Roads for CWB Project (Sheet
2 of 3)
Figure A4.3 Locations of New Roads for CWB Project (Sheet
3 of 3)
Appendix 4.4 Traffic Noise Assessment
Results
Appendix 4.5 Sample Output File
Appendix 4.6 Ventilation Shaft Noise
Assessment
Appendix 4.7 Eligibility Assessment
for Indirect Technical Remedies
Appendix 4.8 IEC Link Construction
Staging
Figure A4.4 IEC Link Construction Staging Stage 1
Figure A4.5 IEC Link Construction Staging Stage 2
Figure A4.6 IEC Link Construction Staging Stage 3A
Figure A4.7 IEC Link Construction Staging Stage 3B
Figure A4.8 IEC Link Construction Staging Stage 4A
Figure A4.9 IEC Link Construction Staging Stage 4B
Figure A4.10 IEC Link
Construction Staging Stage 5
Figure A4.11 IEC Link
Construction Staging Stage 6
Appendix 4.9 Endorsed Letter for
Traffic Flow Year 2027 from Transport Department
Appendix 7.1 Compensatory Planting Indicative Species List
List of Annex
Annex A Cultural
Heritage Review
Figure
AN1.1 Identified Historical Buildings
and Structures (Sheet 1 of 2)
Figure
AN1.2 Identified Historical Buildings
and Structures (Sheet 2 of 2)
Figure AN2
Location of Kellett Island Archaeological Site