4                  NOISE

4.1          Introduction

4.1.1       This section presents the potential noise impacts arising from the proposed CWB & IECL during construction and operational phases. The construction noise levels associated with the proposed Project have been predicted based on the estimate of the construction plants used and the phasing of the construction programme, in addition to the construction noise levels arising from the concurrent projects including Central Reclamation Phase III (CRIII) and Wan Chai Development Phase II (WDII) and the Causeway Bay Flyover. During operational phase, noise impact from road traffic and the ventilation shafts of the proposed ventilation buildings are anticipated. The predicted noise levels during construction and operational phases have been assessed against the EIAO-TM noise criteria.  Appropriate mitigation measures have been recommended where adverse impacts are predicted.

4.2          Environmental Legislation, Policies, Plans, Standards and Criteria

4.2.1       Noise impacts have been assessed in accordance with the criteria and methodology given in the Technical Memoranda (TM) made under the Noise Control Ordinance (NCO) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

4.2.2       The Noise Control Ordinance (NCO) provides the statutory framework for noise control.  Assessment procedures and standards are set out in the following five Technical Memoranda:

·        EIAO-TM;

·        TM on Noise from Construction Work other than Percussive Piling (GW-TM);

·        TM on Noise from Percussive Piling (PP-TM);

·        TM on Noise from Construction Work in Designated Areas (DA-TM); 

·        TM on Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM).

Construction Noise

4.2.3       The NCO provides the statutory framework for noise control of construction work other than percussive piling using powered mechanical equipment (PME) between the hours of 1900 and 0700 or at any time on Sundays and a general holiday (that is, restricted hours).  Noise control on construction activities taking place at other times is subject to the Criteria for Evaluating Noise Impact stated in Table 1B of Annex 5 in the EIAO-TM.  The noise limit is 75 dB(A) Leq (30 minutes) at the facades of dwellings and 70 dB(A) Leq (30 minutes) at the facades of schools (65 dB(A) during examinations).

4.2.4       Between 1900 and 0700 hours and all day on Sundays and public holidays, activities involving the use of powered mechanical equipment (PME) for the purpose of carrying out construction work is prohibited unless a Construction Noise Permit (CNP) has been obtained.  A CNP may be granted provided that the Acceptable Noise Level (ANL) for the noise sensitive receivers (NSRs) can be complied with.  ANLs are assigned depending upon the Area Sensitivity Ratings (ASRs). The corresponding basic noise levels (BNLs) for evening and night time periods are given in Table 4.1.

Table 4.1        Construction Noise Criteria for Activity other than Percussive Piling

Time Period

Basic Noise Level (BNLs)

ASR A

ASR B

ASR C

Evening (1900 to 2300 hours) (1)

60

65

70

Night (2300 to 0700 hours)

45

50

55

Notes: (1)  Includes Sundays and Public Holidays during daytime and evening

4.2.5       Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a Construction Noise Permit (CNP) will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the Noise Control Ordinance. The Noise Control Authority will take into account contemporary conditions / situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.  Nothing in this EIA Report shall bind the Noise Control Authority in making its decision.  If a CNP is to be issued, the Noise Control Authority shall include in the permit any condition it thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution action under the NCO.

4.2.6       Percussive piling is prohibited between 1900 and 0700 hours on any weekday not being a general holiday and at any time on Sunday or general holiday.  A CNP is required for carrying out of percussive piling between 0700 and 1900 hours on any day not being a general holiday.  PP-TM sets out the requirements for working and determination of the permitted hours of operations.  ANLs for percussive piling for different type of NSRs are shown in Table 4.2.

Table 4.2        Acceptable Noise Levels for Percussive Piling

NSR Window Type or Means of Ventilation

ANL, dB(A)

(i)               NSR (or part of NSR) with no windows or other opening

       100

(ii)              NSR with central air conditioning system

        90

(iii)            NSR with windows or other openings but without central air conditioning system

        85

Note:     10 dB(A) shall be subtracted from the ANLs shown above for NSRs which are hospitals, medical clinics, educational institutes, courts of law or other NSRs which are considered by the Authority to be particularly sensitive to noise.

4.2.7       Effective from 1 October 1999, the use of diesel, pneumatic and / or steam hammers are not allowed to be used in Hong Kong.  The permitted hours of operation for carrying out of percussive piling work are listed in Table 4.3.


Table 4.3        Permitted Hours of Operation for Percussive Piling

Amount by which Corrected Noise Level (CNL) exceeds Acceptable Noise Level (ANL), CNL-ANL

Permitted hours of operation on any day not being a general holiday

10 dB(A) < CNL-ANL

0800 to 0900 AND 1230 to 1330 AND 1700 to 1800

0 dB(A) < CNL-ANL £ 10 dB(A)

0800 to 0930 AND 1200 to 1400 AND 1630 to 1800

CNL-ANL £ 0 dB(A)

0700 to 1900

4.2.8       Under the TM on Noise from Construction Work in Designated Areas, the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours would require to obtain a valid CNP.  The SPME includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker.  The PCW are:

·        erecting or dismantling of formwork or scaffolding;

·        loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and

·        hammering.

4.2.9       In general, the CNP would not be normally granted for carrying out PCW within a designated area during restricted hours involving the use of PME and / or SPME if the relevant Acceptable Noise Levels and criteria stipulated in the GW-TM and DA-TM could not be met.

Traffic Noise

4.2.10    Table 4.1 of Hong Kong Planning Standard Guidelines (HKPSG) and Annex 5 of EIAO-TM:  Criteria for Evaluating Noise Impact are adopted.  The criteria for road traffic noise at various NSRs are as follows:

·        70 dB(A) at the facades of dwellings, hotels, offices;

·        65 dB(A) at the facades of schools, places of public Worship, courts of law, the place where unaided voice communication is required; and

·        55 dB(A) at the facades of hospital.

4.2.11    Based on the above criteria and aiming at traffic noise impacts at the NSRs not worse than before, the predicted noise levels arising from ‘New’ roads (as defined in section 4.2.13) should be less than 70 dB(A) for dwellings and 65 dB(A) for educational institutions, and the contribution to the increase in the predicted overall noise level from the ‘new’ road should be not greater than 1.0 dB(A).  

4.2.12    If any facades of NSRs are still exposed to predicted noise levels exceeding the relevant noise criteria after the implementation of all direct mitigation measures, provision of indirect technical remedies in the form of acoustic insulation and air conditioning should be considered under the ExCo directive “Equitable Redress for Persons Exposed to Increased Noise Resulting from the use of New Roads”.  Eligibility for indirect technical remedies will be tested against the following three criteria:

·        The predicted overall noise level from the ‘new’ road, together with other traffic noise in the vicinity must be above 70 dB(A) for residential dwellings and 65 dB(A) for educational institutions.

·        The predicted overall noise level is at least 1.0 dB(A) more than the prevailing traffic noise level.

·        The contribution to the increase in the predicted overall noise level from the ‘new’ road must be at least 1.0 dB(A).

4.2.13    For the purpose of the traffic noise assessment in this Study, the roads within the 300 m of the Study Area are included in the assessment.  All roads are described as either one of the following:

·        ‘Existing’ Roads are the roads that are unchanged or subject to minor changes by the Project and the proposed roads from CRIII Project.

·        ‘New’ Roads are the roads that are completely new or existing road section undergoes major modification that will result in 25% increase in lanes or substantial changes in alignment or characters of the existing road due to the proposed Project.

·        ‘New (Others)’ Roads are all new roads or existing road section undergoes major modification which will result in 25% increase in lanes or substantial changes in alignment of the existing road due to the other projects such as CRIII and WDII.

4.2.14    The ‘new’ roads adopted for the CWB and IECL in the assessment are shown in Figures A4.1 to A4.3 in Appendix 4.3.

Ventilation Shaft Noise

4.2.15    Fixed noise source such as ventilation shaft noise is controlled by the NCO and IND-TM. The appropriate Acceptable Noise Levels (ANL) generated by fixed plant at neighbouring NSRs are provided in IND-TM.  The representative NSRs in the vicinity of ventilation buildings are located in urban area and are near busy roads such as Gloucester Road with an average daily traffic flow in excess of 30,000 and the low traffic flow rate would be more than 300 vehicles per hour.  Most of the representative NSRs would be directly or indirectly affected by traffic noise.  Therefore, the Area Sensitivity Rating (ASR) for these NSRs has been assumed as ‘C’.  However, some NSRs are facing north, and Gloucester Road is at the back of the receivers.  The ASR for these NSRs has been assumed as ‘B’.  The ANLs for an ASR of ‘B’ and ‘C’ under the IND-TM are shown in Table 4.4.  Since the EIAO-TM recommends that noise standard for fixed noise source is 5 dB(A) below the appropriate ANL, the noise criteria of 60 / 65 dB(A) (daytime and evening) and 50 / 55 dB(A) (night-time) will be adopted for assessment.

4.2.16    In any event, the ASR assumed in this EIA Report is for indicative assessment only given that fans and damper arrangement at each ventilation building may be refined in detailed design.  It should be noted that the fixed noise sources are controlled under section 13 of the NCO.  At the time of investigation, the Noise Control Authority shall determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force, and taking account of contemporary conditions / situations of adjoining land uses.  Nothing in this EIA Report shall bind the Noise Control Authority in the context of law enforcement against all the fixed noise sources being assessed.

Table 4.4        Acceptable Noise Level for Fixed Plant Noise

Time Period

NCO criteria

EIAO-TM

ASR ‘B’

ASR ‘C’

ASR ‘B’

ASR ‘C’

Daytime and Evening (0700 - 2300 hours)

65

70

60

65

Night-time (2300 - 0700 hours)

55

60

50

55

4.3          Description of the Environment

4.3.1       The major existing noise source in the Study Area is the traffic noise from busy Connaught Road Central, Harcourt Road and Gloucester Road.  The Study Area along the alignment is mainly composed of commercial buildings except the eastern side of the proposed alignment where residential uses and residential / commercial uses are the major land uses.

4.3.2       As the existing road traffic flow is high, it is expected that most of the facades along the above-mentioned roads would exceed the EIAO-TM noise criteria. 

4.3.3       During construction phase of the Project, it is expected that construction activities would pose adverse noise impacts on the nearby sensitive receivers, particularly near the IECL section. Taking into account the WDII and CRIII projects, cumulative construction noise impact is anticipated.

4.3.4       When the CWB & IECL is in operation, it is expected that the road traffic will constitute a higher background noise than that at present.

4.4          Sensitive Receivers

4.4.1       In accordance with Section 3 of Annex 13 of EIAO-TM, the existing noise sensitive receivers (NSRs) within 300 m of the Study Area have been identified and are summarised in Table 4.5. 

Table 4.5        Summary of Identified Existing Noise Sensitive Receivers

Area

Location

Use

Sheung Wan

Korea Centre

Residential

Central

City Hall

Performing Arts Centre

PLA Headquarters

Others (Military)

Wan Chai

The Hong Kong Academy for Performing Arts (HKAPA) (open arena)

Performing Arts Centre

 

Art Centre

Performing Arts Centre

 

Hong Kong Convention & Exhibition Centre (HKCEC) Extension

Convention and Exhibition

 

Causeway Centre

Residential

 

City Mansion

Residential

 

170 Gloucester Road

Residential

 

Kam Kwok Building, 210 Gloucester Road

Residential

 

Kei Wa Building

Residential

 

Hyde Centre

Residential

Wan Chai

Sang Woo Building

Residential

Causeway Bay

Elizabeth House

Residential

 

Hoi Kung Court

Residential

 

Hoi To Court

Residential

 

Hoi Deen Court

Residential

 

Riviera Mansion

Residential

 

Prospect Mansion

Residential

 

Miami Mansion

Residential

 

Highland Mansion

Residential

 

Marco Polo Mansion

Residential

 

Victoria Park Mansion

Residential

 

Chesterfield Mansion

Residential

 

Greenfield Mansion

Residential

Tin Hau

Viking Garden

Residential

 

Victoria Court

Residential

 

Mayson Garden

Residential

 

Gorden House

Residential

 

Belle House

Residential

 

Hoi Tao Building

Residential

 

Deport of Food and Environment Hygiene Department (FEHD)

Government quarters and office

 

Victoria Centre

Residential

 

Harbour Heights Tower

Residential

4.4.2       For the purpose of noise impact assessment, representative existing and planning NSRs within 300 m from the Study Area are identified.  Some representative NSRs along the Project alignment have been selected in accordance with the criteria in the EIAO-TM to evaluate the construction noise impacts.  While Table 4.6 summarises the selected NSRs for construction noise impact assessment, Table 4.7 summarises the representative NSRs for traffic noise impact assessment.  Their locations are shown in Figure 4.1.

Table 4.6        Summary of Representative Existing Noise Sensitive Receivers for Construction Noise Impact Assessment

NSR

Section

Location

Use

Ground Elevation (mPD)

No. of Floors

N1

Sheung Wan

Korea Centre

Residential

3.8

13

N2

Central

City Hall

Performing Arts Centre

4.0

11

N3

Central

PLA Headquarters

Military

4.9

4

N4

Wanchai

HKAPA (Open Arena)

Performing Arts Centre

5.0

G/F

N5

Wanchai

Art Centre

Performing Arts Centre

4.0

10

N6

Wanchai

HKCEC Extension

Convention and Exhibition

5.5

8

N7

Wanchai

Causeway Centre

Residential

4.0

42

N8

Wanchai

169-170 Gloucester Road

Residential

3.7

12

N11

Causeway Bay

Elizabeth House

Residential

3.7

21

N12

Causeway Bay

Riviera Mansion

Residential

4.3

15

N14

Causeway Bay

Marco Polo Mansion (eastern façade)

Residential

4.3

15

N17

Tin Hau

Mayson Garden Building

Residential

4.0

24

N19

Tin Hau

Belle House

Residential

3.6

24

N21

Tin Hau

Victoria Centre

Residential

4.0

30

Table 4.7        Summary of Representative Existing and Planned Noise Sensitive Receivers for Traffic Noise Impact Assessment

NSR

Section

Location

Use

Ground elevation (mPD)

No. of Floors

N1

Sheung Wan

Korea Centre

Residential

3.8

13

N2

Central

City Hall

Performing Art Centre

4.0

11

N4

Wanchai

HKAPA (Open arena)

Performing Art Centre

5.0

G/F

N5

Wanchai

Art Centre

Performing Arts Centre

4.0

10

N6

Wanchai

HKCEC Extension

Convention and Exhibition

5.5

8

N7

Wanchai

Causeway Centre

Residential

4.0

42

N8

Wanchai

169-170 Gloucester Road

Residential

3.7

12

N9

Wanchai

Kam Kwok Building

Residential

3.7

18

N10

Wanchai

Hyde Centre

Residential

3.7

22

N11

Causeway Bay

Elizabeth House

Residential

3.7

21

N12

Causeway Bay

Riviera Mansion

Residential

4.3

15

N13

Causeway Bay

Marco Polo Mansion (northern façade)

Residential

4.3

15

N14

Causeway Bay

Marco Polo Mansion (eastern façade)

Residential

4.3

15

N15

Tin Hau

Viking Garden

Residential

4.0

25

N16

Tin Hau

Victoria Court

Residential

4.0

18

N17

Tin Hau

Mayson Garden Building

Residential

4.0

24

N18

Tin Hau

Gordon House

Residential

4.0

15

N19

Tin Hau

Belle House

Residential

3.6

24

N20

Tin Hau

Hoi Tao Building

Residential

4.0

30

N21a

Tin Hau

Victoria Centre

(Tower 2)

Residential

4.0

30

N21b

Tin Hau

Victoria Centre

(Tower 1)

Residential

4.0

30

N22

Tin Hau

Harbour Heights

Residential

4.3

44

N23

Wanchai

Possible Tin Hau Temple Site

Temple

Future Development

4.4.3       In this project, three ventilation shaft buildings are proposed for the main tunnel along the CWB & IECL.  In order to evaluate the fixed noise impacts, existing representative sensitive receivers (Figure 4.1) have been identified near the proposed ventilation buildings. The shortest distance between the ventilation buildings and the representative NSRs are listed in Table 4.8.  Since no NSRs are located within 300 m of West Ventilation Building, no assessment for this ventilation shaft is undertaken.

4.4.4       Some NSRs such as PLA Headquarters, which are facing the tunnel section of the CWB & IECL and are far away from the Central section / Causeway Bay section of the CWB, would not be selected for traffic noise impact assessment as no adverse traffic noise impacts from the proposed ‘new’ roads will be expected on these NSRs.

4.4.5       According to the latest information from WDII project, all the land uses of future developments on the proposed reclamation land are commercial, hotels, museums, temple and recreational facilities.  Museums for exhibition purpose, and recreational facilities are not defined as NSRs according to Annex 13 of the EIAO-TM.  Hotels and museums would be provided with central air-conditioning system and they do not rely on openable window for ventilation.  No adverse noise impact on these NSRs would be expected.  Therefore, these NSRs are not selected for the assessment.  Only one future NSR, a temple that is located near Hing Fat Street, is identified.

Table 4.8        Summary of Selected Noise Sensitive Receivers for Fixed Noise Impact Assessment

NSR

Description

Use

Shortest Distance from the Louvres at WVB (m)

Shortest Distance from the Louvres at CVB (m)

Shortest Distance from the Louvres at EVB (m)

N4

HKAPA (Open Arena)

Performing Art Centre

N/A

172

N/A

N5

Art Centre

Performing Arts Centre

N/A

161

N/A

N7

Causeway Centre

Residential

N/A

N/A

393

N9

Kam Kwok Building

Residential

N/A

N/A

272

N10

Hyde Centre

Residential

N/A

N/A

269

Note:     WVB – West Ventilation Building; CVB – Central Ventilation Building; EVB – East Ventilation Building; N/A represents that the NSR is located out of 300 m from the ventilation building and is not included in the assessment.

4.5          Assessment Methodology

Construction Noise

4.5.1       The methodology outlined in the TM on Noise from Construction Works other than Percussive Piling has been used for the assessment of construction noise.  Notional noise sources for different construction areas were assumed in accordance with this TM.  All items of powered mechanical equipment (PME) were assumed to be located at these notional source positions.

4.5.2       Taking into account the different construction periods of the Project and other concurrent projects such as WDII and CRIII, the construction assessment has been carried out on quarterly basis since commencement of the Project.  The assessment period is from the first quarter of 2004 to first quarter of 2012.

4.5.3       Powered Mechanical Equipment (PMEs) for the different construction tasks are presented in Appendix 4.1.  The plant inventory list has been confirmed as being practical and practicable in completing the works within scheduled timeframe.  Sound power levels (SWLs) of PME were taken from Table 3 of the TM on Noise from Construction Work other than Percussive Piling.   

4.5.4       A positive correction of 3 dB(A) was made to the calculated result in order to allow for façade effect.  The boundary walls around HKAPA open arena are assumed as noise barriers and a 5 dB(A) reduction of the predicted noise levels at NSR N4 is expected due to the shielding effect.

4.5.5       The assessment is based on the cumulative SWL of PME likely to be used for each location, taking into account the construction period in the vicinity of the receiver location.  To predict the noise level, PME was divided into groups required for each discrete construction task.  The objective was to identify the worst case scenario representing those items of PME that would be in use concurrently at any given time.  The SWL of each construction task was calculated, depending on the number of plants, their frequency of operation, and their distance from receivers.  The noise levels at NSRs were then predicted by adding up the sound pressure level of all concurrently construction tasks.

4.5.6       Construction tasks, including construction works from other projects taking place within 500 m of a given NSR at the same period, are considered to contribute to the cumulative impact at that NSR.  Noise sources from the areas greater than this distance have been excluded from the assessment.  The minimum distances from the notional source point of each construction activity to the representative NSRs are given in Appendix 4.2.

4.5.7       The construction of the CWB & IECL is divided into several phases. The CWB & IECL tunnel works that pass through the CRIII and WDII area have been entrusted to Territory Development Department (TDD).  The foundation works for the Central Ventilation Building, East Ventilation and Administration Building are also entrusted to WDII project.  The construction works under work package of Highways Department (HyD) are in three main areas: Central Interchange Section, Exhibition Section and IECL Section.  Different phases of work associated with the required construction activities for each section are listed below:

Central Interchange Section (Figure 4.1.1)

·        construction of CWB Tunnel section;

·        bridge foundation works and deck construction;

·        bridge finishing works;

·        at-grade roads construction;

·        CWB West Ventilation Building - foundation works and superstructure construction;

·        tunnel modification at Road D5 junction; and

·        demolish Rumsey Street Flyover Downramp and re-provide a slip road connecting Rumsey Street Flyover.

           Trunk Road (Exhibition Section) (Figure 4.1.1)

·        CWB Central Ventilation Building – superstructure construction.

Trunk Road (IECL Section) (Figure 4.1.2)

·        bridge foundation and deck construction;

·        bridge finishing works; and

·        CWB East Ventilation and Administration Building – superstructure construction.

4.5.8       The concurrently construction tasks undertaken by the CRIII and WDII are also considered in the assessment.  Locations of other construction sites (CRIII & WDII) are shown in Figure 3.2.  The major construction sites are listed as follows:

Central Reclamation Phase III (CRIII):

·        Initial Reclamation Area West (IRAW);

·        Initial Reclamation Area East (IRAE);

·        Final Reclamation Area West (FRAW); and

·        Final Reclamation Area East (FRAE).

Wan Chai Development Phase II (WDII):

·        Hong Kong Convention & Exhibition Centre (HKCEC) Reclamation Stage 1 – Water Channel (HKCEC1);

·        HKCEC Reclamation Stage 2 – West (HKCEC2W);

·        HKCEC Reclamation Stage 2 – East (HKCEC2E);

·        Wanchai Reclamation Stage 1 (WCR1);

·        Wanchai Reclamation Stage 2 – West (WCR2W);

·        Wanchai Reclamation Stage 2 – East (WCR2E);

·        Wanchai Reclamation Stage 3 – West (WCR3W);

·        Wanchai Reclamation Stage 3 – East (WCR3E);

·        Causeway Bay Reclamation Stage 1 – West (CBR1W);

·        Causeway Bay Reclamation Stage 1 – East (CBR1E);

·        Causeway Bay Reclamation Stage 2 – West (CBR2W); and

·        Causeway Bay Reclamation Stage 2 – East (CBR2E).

4.5.9       The construction noise assessment in this study is based on the CWB & IECL construction programme.

4.5.10    According to the latest programme provided by the HyD, the construction of Causeway Bay Flyover, which is a separate project from WDII and CWB & IECL projects, is scheduled to commence in May 2003 for completion in February 2006.  The construction period will be overlapped with the CWB project.  Therefore, the impact arising from the construction of Causeway Bay Flyover was also considered in the assessment.  For assessment purpose, the same PMEs for Hung Hing Road Flyover has been adopted for Causeway Bay Flyover.  This has been confirmed as being practical and practicable in completing the works within scheduled timeframe.

4.5.11    The plant inventory and SWL associated with tunnel construction works in CRIII and WDII areas are in accordance with the CRIII EIA Report([1]) and the WDII EIA Report([2]), respectively.  The plant inventory for tunnel work and other concurrent construction of WDII projects are listed in Appendix 4.1.  The construction activities considered in the assessment during each quarter for each NSR are listed in details presented in Appendix 4.2.

4.5.12    The assessment results and the proposed noise mitigation measures for construction tasks in the CRIII EIA Report are also adopted in this assessment.

4.5.13    Bridge construction for certain sections of IECL and some modified road works at Rumsey Street Flyover would be carried out at mid-night to minimise traffic impacts due to road diversion works.  According to GW-TM, for any construction works planned during the restricted hours, the Contractor will be required to submit CNP applications to the Noise Control Authority and has the responsibility to ensure compliance with the NCO and relevant TM.  Therefore, the potential noise impacts of construction works proposed within the restricted hours are not formally assessed within this EIA (see section 4.2.5).

Traffic Noise

4.5.14    Traffic noise was predicted using the methodology provided by the UK Department of Transport Calculation of Road Traffic Noise (CRTN) 1988.  The assessment was based on projected peak hour flows for the worst year within 15 years after opening of the road.  The road is scheduled to be operation in 2012.  Therefore, the traffic data for 2027, which is endorsed by Transport Department, is adopted for the assessment (see Appendix 4.9).  Since traffic flows at the major roads during the peak hour in the morning session are generally higher than that in the afternoon session, the morning peak hour traffic flows were used for modelling.  The projected 2027 morning traffic flow is presented in Figures 3.3.1 to 3.3.6.

4.5.15    Traffic speeds for the proposed Trunk Road system based on the Updated Design Memorandum Part A of the CWB & IECL Project Review Study in May 2001 are adopted and summarised as follows:

Road                                               Speed Limit                         

CWB Trunk Road                            80 km per hour

Slip Road and Operation Road 50 km per hour                    

4.5.16    The traffic speed limit for all existing roads has been assumed to be 50 km per hour except the Island Eastern Corridor and Rumsey Street Flyover, which has been assumed to be 80 km per hour.  The speed limit of Road P1/P2 will be 50 km per hour.  According to the “CWB & IECL Project Review Study, Updated Design Memorandum” in May 2001, a friction course (porous asphalt) would be used on the expressways or trunk roads with anticipated vehicular speed of 80 km per hour or above as the recommendation in TPDM Volume 2 Chapter 6 Clauses 6.3.1.4 – 6.3.1.7 and Road Note 5.  In this assessment, friction course (porous asphalt) is assumed on the Island Eastern Corridor, Rumsey Street Flyover, and the new roads (that is, the CWB & IECL) where the speed is 80 km per hour.  The location of porous asphalt road surfacing is shown in Figures 4.2.1 and 4.2.2.

4.5.17    The road network, proposed building layout and all other features that could have noise screening or reflective effects, were digitised in the road traffic noise model.  The roads were divided into segments, each of which was assigned a road layout number.  A road layout defined the road width, opposing traffic lane separation, road surface type and traffic mix, flow and road design speed.  Hard ground as defined in CRTN was assumed throughout the Study Area.  Noise levels were calculated at each receiver point at three different elevations (that is, 1st floor, mid-floor and top floor).  A sample of modelling listing file is included in Appendix 4.5.

Ventilation Shaft Noise

4.5.18    Three ventilation buildings for the main tunnel, as shown in Figure 4.3, are proposed along the CWB & IECL.

4.5.19    Potential noise impacts from the ventilation buildings with exhaust fans would be expected on the sensitive receivers.  The fixed plant noise impact arising from these ventilation buildings has been assessed in accordance with the IND-TM. 

4.5.20    According to Final Working Paper on Tunnel Electrical and Mechanical System (WP03) of CWB & IECL Design and Construction Assignment in November 2000 and the information provided by the Ventilation Engineer, 5 duty plus 2 standby exhaust fans are proposed for East Ventilation Building (EVB).  For Central Ventilation Building (CVB) and Western Ventilation Building (WVB), 3 duty plus 2 standby exhaust fans and 3 duty plus 1 standby fans are proposed, respectively.  Table 4.9 summarises the numbers of exhaust fans required for the proposed ventilation buildings during normal condition.

Table 4.9        The Number of Exhaust Fans required for Proposed Ventilation Buildings during Normal Condition

Ventilation Building

Fan Capacity (m3 s-1)

Number of Exhaust Fans Required

East Ventilation Building

190

100

3 (+1 standby)

2 (+1 standby)

Central Ventilation Building

100

90

1 (+1 standby)

2 (+1 standby)

Western Ventilation Building

140

3 (+1 standby)

4.5.21    It has assumed that all duty exhaust fans at each ventilation building are operated in the assessment.  Screening corrections from other buildings / structures and directivity have also been excluded in the assessment.  The information provided by the Ventilation Engineer that all the exhaust fans installed in each ventilation buildings will be provided with silencers.  Since the use of silencers will flatten the frequency band of the exhaust fan, no tonality correction is considered in the calculation.

4.5.22    According to the East Kowloon Line / North Hong Kong Island Line (NHKIL) Feasibility Study Report issued in September 1999, the proposed ventilation buildings for NHKIL would be located near the junction of Fleming Road and Convention Ave (VB1) and Tonnochy Road near Harbour Road Indoor Games Hall (VB2), respectively.  It is noted that the proposed NHKIL has to undergo a statutory EIA and it is expected that the noise level generated from the ventilation shafts would comply with the EIAO-TM’s and NCO’s requirements.  The ventilation shaft noise from VB1 is not considered as a cumulative noise impact on the assessed NSRs in this study as the location of the VB1 is at least 300 m away from the proposed EVB, CVB and WVB.  The location of VB2 is near EVB but the separation distance between them is about 280 m.  Therefore, the additional fixed noise impact from VB2 on the representative NSRs is negligible.

4.6          Prediction and Evaluation of Environmental Impacts

Construction Noise

4.6.1       The construction period for whole Project is about 96 months from March 2004 to February 2012. In general, there are six sections of construction works during the construction period:

(a)   CWB Tunnel – March 2004 to March 2008;

(b)   Central Interchange – September 2005 to August 2008;

(c)   IEC Link – December 2007 to August 2011;

(d)   Demolition of temporary ramp structures – September 2011 to October 2011;

(e)   Tunnel Building and Installation – September 2008 to March 2011; and

(f)    Modification works at existing Rumsey Street (RS) Flyover and upramp and demolition of downramp of RS – September 2011 to February 2012.

4.6.2       In the absence of any mitigation measures, exceedance of the Leq (30 minutes) 75 dB(A) construction noise criterion for residential uses is predicted at most of the representative NSRs.   Details of construction noise calculations and results are presented in Appendix 4.2.  Results showed that the predicted noise levels at the representative NSRs were in the range between 55 and 93 dB(A) during the construction years of CWB & IECL.  A summary of the unmitigated construction noise levels of the representative NSRs during normal daytime working hours within the CWB & IECL construction period is listed in Table 4.10.

Table 4.10      Summary of Unmitigated Construction Noise Levels during Normal Daytime Working Hours

Representative NSRs

Predicted Unmitigated Construction Noise Levels during Normal Daytime Working Hour(1) (0700 to 1900 on weekday) (dB(A))

N1

66 – 80

N2

55 – 80

N3

64 – 93

N4

60 – 78

N5

68 – 85

N6

59 – 89

N7

62 – 83

N8

62 – 81

N11

60 – 81

N12

72 – 77

N14

74 – 85

N17

66 – 81

N19

67 – 83

N21

66 – 86

Note: (1)   For normal daytime working hours, the noise criterion for N2 and N5 is 70 dB(A).  The criterion for other NSRs is 75 dB(A).

4.6.3       According to the results, all NSRs in the Central Interchange area and its vicinity (namely NSRs N1, N2 and N3) would not comply with the construction noise standard.  The exceedance at PLA Headquarters (NSR N3) is dominantly due to CRIII project.  Since City Hall (NSR N2) is provided with central air conditioning and noise insulated facilities, no adverse noise impact is expected at the indoor of this NSR.  Therefore, noise mitigation measures such as using quiet plant are recommended for the construction tasks in Central Interchange Area to alleviate the construction noise impacts on NSR N1 only.  The representative NSRs in Wan Chai area and Causeway Bay area would be affected by WDII project and CWB & IECL project.  Practical mitigation measures such as quiet plants or movable noise barriers (Section 4.7) should be implemented in order to reduce noise levels to the stipulated standard.

Traffic Noise

4.6.4       Traffic noise levels have been calculated at a total of 23 representative NSRs including existing residential dwellings, performing art centres and one temple. The assessment results of the NSRs are listed in Appendices 4.4 and 4.7.

Central Interchange Section (Figure 4.1.1)

4.6.5       There is only one representative NSR near the Central Interchange section.  It is predicted that the noise level at NSR N1 would exceed the statutory limit by 10 to 13 dB(A).  However, the noise exceedances are attributed to the existing roads.  The noise level contributed from the proposed ‘new’ roads is not more than 70 dB(A) and the ‘new’ road noise contribution to the overall noise level is less than 1.0 dB(A).  Therefore, no direct noise mitigation measure is recommended on the proposed Central Interchange section.

Exhibition Section (CWB Tunnel Section) (Figure 4.1.1)

4.6.6       Generally, there are a main enclosed trunk road and some slip roads in this section.  The predicted noise levels at NSRs N2, N4 to N7 exceed the EIAO-TM criteria.  It is predicted that the NSR N2 is dominantly affected by the existing roads and the roads proposed in CRIII Project.  The other NSRs along this section are expected to be dominantly affected by the existing roads and the proposed roads in WDII project.  Only minimal noise levels contributed from the proposed slip roads of this Project would be expected.  Since the ‘new’ road noise contribution to the overall noise level is less than 1.0 dB(A) and ‘new’ road noise level is not more than 70 dB(A), no direct mitigation measure is proposed on the ‘new’ roads at this section.

IECL Section (Figure 4.1.2)

4.6.7       Noise exceedance is predicted at most of the respective NSRs along this section.  The existing road noise levels at all representative NSRs exceed the statutory limit of 70 dB(A) due to high traffic flow on the Gloucester Road and the existing Island Eastern Corridor.  Besides, the proposed ‘new’road near the Causeway Bay Typhoon Shelter and the Hing Fat Street upramp impose significant noise impacts on some NSRs near Victoria Park Road and along Hing Fat Street.  Direct noise mitigation measures (Section 4.7.11) are therefore required on the proposed ‘new’roads to alleviate the traffic noise impacts on these affected NSRs.

Ventilation Shaft Noise

4.6.8       Since the exhaust fans are expected to be operated 24 hours daily, referring to Table 4.4, the calculation will be based on the stringent fixed noise night-time criteria of 50 / 55 dB(A) in the assessment according to EIAO-TM requirement.  It is assumed all duty exhaust fans are operated for each ventilation building during assessment.  As the distances among the three proposed buildings are quite far away to each other, no cumulative fixed noise impact is determined in this case.

4.6.9       As directivity and screening corrections have not been included in the assessment, the predicted noise levels at NSRs represent the worst case scenario.  Correction for tonality has not been considered in the assessment as the use of silencers will flatten the frequency band of the exhaust fans.  Details of calculations of predicted noise levels at NSRs are shown in Appendix 4.6.

4.6.10    According to Table 4.11, there will be no exceedance of night-time criteria specified in the EIAO-TM at the identified NSRs if silencers are provided at all exhaust fans of each ventilation building.

4.6.11    According to the CRIII EIA Report, no adverse fixed noise impacts are expected on the closest NSR, and it is located far away from three proposed ventilation building.  Therefore, no cumulative fixed noise impacts are expected.

4.6.12    According to the East Kowloon Line / North Island Line Feasibility Study Report in September 1999, the proposed ventilation buildings for North Island Line would be located near the junction of Fleming Road and Convention Avenue (VB1) and Tonnochy Road near Harbour Road Indoor Games Hall (VB2), respectively.  It is noted that the proposed NHKIL has to undergo a statutory EIA and noise emission from the NHKIL ventilation shafts have to comply with the statutory standards under the EIAO-TM’s and NCO’s requirements.  The location of VB2 is near EVB but their separation distance is about 280 m.  According to the findings from WDII EIA Report([3]), the sound power level arising from VB2 should not be more than 96.4 dB(A) so that the nearest NSR (Causeway Centre) complies with the night-time fixed noise criterion of 50 dB(A).  It is expected that noise arising from ventilation shaft would fulfill the requirement with the installation of acoustic silencers.  Therefore, no adverse cumulative fixed noise impacts are anticipated at the NSRs close to both EVB and VB2.

Table 4.11      Predicted Fixed Noise Levels at NSRs (Leq, 30 min dB(A))

NSR

Description

Predicted Noise Levels, dB(A) (not including ventilation shaft noise from VB2 for NHKIL)

Night-time Criterion in NCO / EIAO-TM

N4

HKAPA

46.3

60 / 55

N5

Art Centre

46.9

55 / 50

N7

Causeway Centre

44.0

55 / 50

N9

Kam Kwok Building

47.2

60 / 55

N10

Hyde Centre

47.3

60 / 55

Note: * The location of VB1 is far away from the NSR, no cumulative noise impact is expected.

4.7          Mitigation of Adverse Environmental Impacts

Construction Noise

Adoption of Quiet PMEs

4.7.1       In order to reduce the excessive noise impacts at the affected NSRs during normal daytime working hours, mitigation measures such as adopting quiet plant, erection of noise barriers and reducing on-time operation of the plant, are appropriate to be used.  One of feasible solution is to adopt quieter construction plant for several construction tasks during all or part of construction years.  The Contractor may be able to obtain particular models of plant that are quieter than the PMEs given in GW-TM.  It is considered too restrictive to specify that a Contractor has to use specific items of plant for the construction operations.  It is, however, practical to specify the total SWL of all plant to be used on site so that the Contractor is allowed some flexibility to select plant to suit his needs.

4.7.2       In this assessment, the recommended silenced PMEs are taken from the BS 5228: Part 1: 1997, which are known to be in Hong Kong.  The quiet PMEs adopted for CWB construction activities are considered practical and practicable in completing the works within schedule. The quiet PMEs adopted for the CRIII and WDII construction tasks are in accordance with CRIII EIA Report([4]) and WDII EIA Report([5]).

4.7.3       The lists of silenced PME adopted in the assessment are shown in Appendix 4.1.  The following construction tasks of CWB & IECL are considered to adopt quiet PMEs:

·        CWB Tunnel in HKCEC1, HKCEC2E, HKCEC2W, WCR1, WCR2E, WCR2W and WCR3W;

·        piling, tunnel and deck construction in Mass Transit Railway tunnel crossing area;

·        demolition of existing IEC structure, bridge formation, deck formation, road formation and earthwork, road pavement at IECL section,

·        tunnel buildings, and

·        demolition of downramp of Rumsey Street.

4.7.4       According to the information provided by the HyD([6]), the construction noise levels arising from the construction of Causeway Bay Flyover at the closest NSRs will comply with the construction noise criteria with the implementation of appropriate mitigation measures.

4.7.5       The construction tasks adopting quiet PMEs in WDII project are listed as follows:

WDII Construction Tasks

·        Flyover Road P1/P2 to Fenwick Pier near the HKAPA and the Art Centre;

·        Road P1/P2 near the HKAPA, the Art Centre and the HKCEC Extension;

·        HKCEC Roads;

·        Local access roads near the HKAPA and the Art Centre;

·        Wan Chai North Public Transport Interchange;

·        Demolition of East Bridge (WCR2E) and West Bridge (HKCEC2);

·        Demolition of Ferry Structure and Reprovision of East Pier and West Pier;

·        Hung Hing Road Flyover;

·        Drainage culverts in CBR1E, CBR1W,CBR2E, WCR1,WCR2E and HKCEC2;

·        Cross Harbour Watermains – Land section; and

·        Cooling water intake pipeline in HKCEC1 near HKAPA, HKCEC2 West near HKAPA and Art Centre, and CBR1 near Riviera Mansion.

4.7.6       As shown in Appendix 4.2, with the use of the quiet equipment, the overall noise levels at NSRs could be reduced by 1 to 11 dB(A), depending on the type of construction activities.  The predicted noise levels at the performing art centres such as the Art Centre and the HKCEC Extension still do not comply with the construction noise standard.  However, it is known that central air-conditioning system and noise insulated facilities have been provided at the HKCEC Extension and the Art Centre.  In addition, they do not rely on openable windows for ventilation, no adverse noise impacts will therefore be expected at the indoor of these NSRs.  Nevertheless, the predicted construction noise levels relating to the CWB project at a residential representative NSR (Victoria Centre) would still be non-compliant with the EIAO-TM construction noise criteria.  Additional noise mitigation measures such as temporary noise barrier should be provided. 

Movable Noise Barrier

4.7.7       In order to alleviate the construction noise impacts on the affected NSRs, movable noise barriers are provided for particular plants.  According to GW-TM, it is anticipated that a movable noise barrier with a cantilevered upper portion located to the noise generating part of the PME can produce 5 dB(A) or up to 10 dB(A) noise screening, depending on the line of sight that could be blocked by the barriers when viewed from the NSR.  The noise screening benefit for each plant considered in this assessment is listed as follows:

·        Stationary plant – assuming 10 dB(A) reduction: concrete pump, compressor and poker vibrator;

·        Mobile plant – assuming 5 dB(A) reduction: excavator, mobile crane, grader and road roller.

4.7.8       The movable noise barriers are considered to be adopted for the following construction activities:

·        HKCEC2E – Diaphragm Wall;

·        HKCEC2W – Diaphragm Wall and Excavation;

·        Bridge M – Foundation and Deck Formation at Stage 2;

·        Bridge L – Deck Formation at Stage 2;

·        Deck of Bridges E6, E7 and E8 – Deck Formation at Stage 2;

·        Demolition of Existing IEC Structure, Substructure of Bridges W5, W6 and Bridge J and Deck of Bridges W5 and W6 at Stage 4A/4B.

4.7.9       With the installation of noise barriers, exceedance is still predicted at the Victoria Centre and the HKAPA (open arena).  Reduction in number of PME or / and PME percentage on-time are required to alleviate the construction noise impacts to comply with the established criteria.

Reduction in Number of PME and PME Percentage On-time

4.7.10    The following tasks are proposed to reduce the number of plant so as to reduce the noise impacts on the affected NSRs.

·        Bridge M – Deck formation at Stage 2;

·        Demolition of existing Island Eastern Corridor structure at Stage 4A;

·        CWB tunnel (HKCEC2W) – Diaphragm wall and excavation.

4.7.11    Since PMEs would not be fully operated in practice, appropriate on-time percentage of some plants during foundation work of Bridge M, deck formation for Bridges E6 and E7, deck formation for Bridge E8 and substructure of Bridges W5, W6 and Bridge J are recommended when these construction activities are close to the Victoria Centre.  The reduction of on-time operation is expected to be practical and practicable in completing the works within the schedule.  The locations of relevant construction activities are shown in Figures A4.4 to A4.11 of Appendix 4.8.

4.7.12    With the use of the above mitigation measures, the predicted construction noise levels at the Victoria Centre would comply with the construction noise standard.  Exceedance is still predicted at PLA Headquarters, dominantly due to CRIII construction works.  According to the noise mitigation measures for CRIII construction works presented in the EIA Report of the CRIII project([7]), movable noise barriers would be adopted for the Hong Kong Station Extended Overrun Tunnel (EOT), NHKIL protection works and road / drainage works immediately to the north of the PLA Headquarters.  These would reduce noise levels by at least 5 dB(A).  It should, however, be noted that the PLA Headquarters are already provided with air conditioning and therefore the noise levels predicted after the adoption of quiet PMEs and movable noise barriers would not result in adverse noise impacts to the buildings.  Table 4.12 summarises the mitigated noise levels during normal daytime working hours at representative NSRs.

Table 4.12      Summary of Mitigated Construction Noise Levels at Representative NSRs during Normal Daytime Working Hours

Representative NSRs

Predicted Mitigated Construction Noise Levels during Normal Daytime Working Hour(1) (0700 to 1900 on weekday) (dB(A))

N1

66 – 74

N2

55 – 80

N3

64 – 84

N4

58 – 71

N5

68 – 79

N6

59 – 82

N7

62 – 75

N8

62 – 73

N11

60 – 74

N12

57 – 74

N14

67 – 75 (2)

N17

66 – 75

N19

60 – 75

N21

59 – 75

Note: (1)   For normal daytime working hours, the noise criterion for N2 and N5 is 70 dB(A).  The criterion for other NSRs is 75 dB(A).

           (2)   According to information provided by the Highways Department, the construction noise impacts of the Causeway Bay Flyover project would be mitigated through proper implementation of appropriate noise control measures to ensure the noise levels comply with construction noise standards.

Traffic Noise

4.7.13    The following direct mitigation measures (DMMs) are proposed to reduce the traffic noise impact arising from the IECL section:

·         a 107 m long semi-enclosure for the eastbound carriageway of IECL (CH4883 – CH4990) (the roof covers the whole eastbound carriageway, solid vertical structure is provided at central divider from CH4930 – CH4990, support columns are provided at central divider from CH4883 – CH4930 and the west side of eastbound carriageway);

·         a 57 m long semi-enclosure for the westbound carriageway of IECL (CH4883 – CH4940) (the roof covers the whole westbound carriageway, solid vertical structure is provided at the south side of westbound carriageway and support columns are provided at central divider);

·         a 113 m long and 7 m high vertical barrier, located at the edge of the parapet of the westbound carriageway of IECL (CH4770 – CH 4883);

·         a 210 m long and 7 m high vertical barrier located at the edge of the parapet of the Slip Road J (CH350 - CH560);

·         a 139 m long and 5.5 m high vertical barrier, located at the edge of the parapet of the westbound carriageway of IECL (CH4116 – CH4255);

·         a 140 m long and 4 m high vertical barrier, located at the edge of the parapet of the westbound carriageway of IECL (CH4630 – CH4770);

·         a 81 m long cantilevered barrier (5.5 m high vertical barrier with 2 m cantilever length at 45 degrees to the horizontal) located at the central divider of IECL (CH4802 - CH4883); and

·         a 259 m long cantilevered barrier (5.5 m high vertical barrier with 2 m cantilever length at 45 degrees to the horizontal) located at the edge of the parapet of the westbound carriageway of IECL (CH4255 – CH4514).

4.7.14    The proposed DMMs mentioned in the paragraph above are shown in Figure 4.4 and the typical section drawings are shown in Figures 7.7.1 and 7.7.2.  The recommended barriers can be in the form of concrete or transparent panel, and this would be considered in the detailed design stage.  The predicted mitigated results are presented in Appendix 4.4.

4.7.15    With the implementation of the proposed DMMs on the IECL section, the noise levels at most of the representative NSRs in Causeway Bay (such as Elizabeth House and Marco Polo Mansion) and Tin Hau area (such as Viking Garden and Belle House) are still not compliant with the traffic noise criterion.  Exceedance is also predicted at City Garden, which is at the study area boundary. However, except the low to top floors of both NSRs N21a and N21b (Victoria Centre), the noise levels arising from ‘new’ roads in CWB & IECL project at all the representative NSRs and City Garden are below 70 dB(A) and the ‘new’ road noise contributions to the overall noise levels at these representative NSRs are less than 1.0 dB(A).  Therefore, no further direct mitigation measures on the ‘new’ roads are provided for these NSRs. On the other hand, further direct mitigation measures have to be investigated for the low to top floors of NSRs N21a and N21b.

4.7.16    The dominant noise sources at NSRs N21a and N21b are the section of IECL and existing IEC in front of Victoria Centre.  A section of semi-enclosure between chainage 4883 and 4990 has been proposed to cover the IECL westbound. Extension of this semi-enclosure eastward is not feasible since the structure would cause sightline problem near the diverging point of the Hing Fat Street downramp on IEC, and furthermore, space is insufficient to accommodate the semi-enclosure. However, installation of a noise barrier on Hing Fat Street downramp adjacent to Victoria Centre is neither feasible as the existing ramp structure was not designed to withstand the additional wind load from the noise barrier nor also the sightline of vehicle drivers on Hing Fat Street downramp would be much obstructed.  If the noise barrier is to be constructed on the existing ground, the structure for supporting the noise barrier would encroach upon the lot boundary of Victoria Centre, and also affect the existing emergency vehicular access to Victoria Centre.  On the other hand, if the supporting structure of the noise barrier is to be constructed on the seaward side, i.e., along the northern edge of the IECL, the huge span across both IECL eastbound and westbound would render the structure infeasible to build. 

4.7.17    According to the new policy guideline issued in November 2000 on the provision of measures to address noise impact of existing roads, engineering solutions by way of retrofitting of barriers and enclosures, and resurfacing with low noise material should be implemented where practicable on existing excessively noisy roads.  It is clear from the above noise assessment that a residential block, i.e. N22, is likely to be adversely affected by the section of the existing IEC near the eastern end of the project limit. Friction course has been provided at the existing IEC to reduce the traffic noise impacts on this noise sensitive receiver.  However, installation of barriers or enclosures on this section of the road would be severely restricted by site conditions and the need to resume private lots. It is considered not feasible to erect a noise barrier or an enclosure of, say, 7m high, on the existing bridge structure, as the bridge was again not designed to withstand the additional wind load from the noise barrier or enclosure. On the other hand, if the noise barrier or enclosure is to be constructed on the existing ground, the supporting structure, which would consist a number of above 10m high, closely spaced columns, and the noise barrier or enclosure itself, would seriously obstruct the sea view at the lower five storeys of Harbour Heights. Resumption of private lots for construction of this noise barrier would be difficult as there is at present no policy that would enable this to be proceeded.  Therefore, no further mitigation measures could be provided at these locations.

4.7.18    As all DMMs have been exhausted, the NSRs would be evaluated to determine whether they are eligible for the provision of indirect technical remedies (ITR) in the form of window insulation and air-conditioners.  Detailed assessment results are presented in Appendix 4.7.

Ventilation Shaft Noise

4.7.19    No exceedance is expected on the representative NSRs, therefore no mitigation measure is recommended for the proposed EVB, WVB and CVB in this study.  It is recommended that, wherever possible, the louvres should face away from the NSRs to further reduce the noise levels at NSRs.  No adverse cumulative fixed noise impacts are anticipated at the NSRs close to both EVB and VB2.

4.8          Evaluation of Residual Impacts

Construction Noise

4.8.1       With the implementation of the above-mentioned mitigation measures, the construction noise levels at all representative NSRs are predicted to comply with the noise standard stipulated in EIAO-TM.  The above mitigation measures have been confirmed as being practical and practicable in completing the works within scheduled timeframe.  Residual impacts are therefore not anticipated.

4.8.2       In addition to the above-mentioned mitigation measures, the good site practices listed below should be adopted by all the Contractors to further ameliorate the noise impacts.  Although the noise mitigating effects are not easily quantifiable and the benefits are specific to the site and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.

·        Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme.

·        Silencers or mufflers on construction equipment should be utilised and should be properly maintained during the construction programme.

·        Mobile plant, if any, should be sited as far away from NSRs as possible.

·        Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum.

·        Plant known to emit noise strongly in one direction should, where possible, be orientated so that the noise is directed away from the nearby NSRs.

·        Material stockpiles and other structures should be effectively utilised, where practicable, in screening noise from on-site construction activities.

Traffic Noise

4.8.3       With the implementation of recommended noise barriers and semi-enclosures, the noise level arising from ‘new’ roads in the CWB & IECL project at two representative NSRs N21a and N21b would still exceed the traffic noise criterion (70 dB(A)).  It is estimated that the total number of dwellings at Victoria Centre that ‘new’ roads noise levels are higher than 70 dB(A) are 243 at N21a (from low to top floors) and N21b (from low to top floors).  At about 162 of these 243 dwellings, the contribution to the increase in the predicted overall noise from ‘new’ road is greater than 1.0 dB(A).  In order to redress the residual impact, indirect technical remedies in the form of window insulation and air-conditioning may need to be considered subject to the fulfilment of EPD’s eligibility criteria for consideration by the Exco.  Traffic flows in 2003 have been adopted for the prevailing traffic noise assessment.  Eligibility assessment results and Year 2003 traffic flow are presented in Appendix 4.7.

4.8.4       According to the results for NSR N21a, the predicted mitigated overall noise levels are less than the prevailing noise levels.  For NSR N21b, the contribution to the increase in the predicted overall noise from the ‘new’ road is less than 1.0 dB(A).  Therefore, they will not meet the ExCo directive criteria for noise insulation after the implementation of the recommended direct mitigation measures. 

Ventilation Noise

4.8.5       No residual fixed plant noise impacts arising from the proposed EVB, CVB and WVB are expected, provided that all exhaust fans at the proposed three ventilation buildings are equipped with silencers.

4.9          Environmental Monitoring and Audit

Construction Phase

4.9.1       An Environmental Monitoring and Audit (EM&A) programme has been established according to the predicted occurrence of noisy activities.  All the recommended mitigation measures should be incorporated into the EM&A programme for implementation during construction.  Details of programme are provided in the stand-alone EM&A Manual.

Operational Phase

4.9.2       Monitoring of operation noise is considered necessary to verify the effectiveness of the mitigation scheme.  It is recommended that the traffic noise monitoring should be carried out at representative NSRs within one year of the road opening.  Operational noise monitoring will also be required during the commissioning stage of the ventilation buildings to ensure that compliance with the noise limits specified in this report has been achieved.

4.9.3       The recommended mitigation measures, monitoring procedures and locations are presented in the stand-alone EM&A Manual.

4.10     Conclusion

Construction Phase

4.10.1    This assessment has predicted the construction noise impacts associated with the construction works of the proposed Project and other concurrent projects including the CRIII, the WDII and the Causeway Bay Flyover.  With the use of silenced equipment, the use of movable noise barriers for some plants, reduction in equipment number and on-time operation at some specific construction plants, all residential NSRs comply with the stipulated criteria.  Noise exceedances are still predicted at the City Hall, the Art Centre and the HKCEC Extension.  However, these NSRs are equipped with central air-conditioning system and good noise insulation facilities.  In addition, they do not rely on openable windows for ventilation, and adverse noise impacts are therefore not expected at the indoor of these NSRs and further mitigation measures for these NSRs will not be required.  Exceedance is also predicted at the PLA Headquarters dominantly due to construction noise from CRIII project.  According to the noise mitigation measures for CRIII construction works presented in the EIA report of the CRIII project, movable noise barriers would be adopted for the EOT, NHKIL Protection Works and road / drainage works immediately to the north of the PLA Headquarters.  These would reduce noise levels by at least 5 dB(A).  It should, however, be noted that the PLA Headquarters are already provided with air conditioning and, therefore, the noise levels predicted after the adoption of quiet PMEs and movable noise barriers would not result in adverse noise impacts to the indoor environment of the buildings.

Operational Phase

4.10.2    The potential road traffic noise impacts have been assessed for the worst case traffic flows in 2027.  Most of the noise sensitive receivers are predicted to exceed the EIAO-TM traffic noise criteria.  Direct mitigation measures such as vertical barriers, cantilevered barriers and semi-enclosure have been proposed on the ‘new’ roads to alleviate the traffic noise impacts.  With the implementation of all recommended practicable direct mitigation measures, exceedances are still predicted at most of the NSRs mainly due to noise contribution from existing roads.   As all direct mitigation measures are exhausted, eligibility assessment for the provision of indirect technical remedies has been undertaken for these NSRs. 

4.10.3    According to the eligibility assessment results, no NSRs are eligible for the consideration of indirect technical remedies in the form of window insulation and air-conditioning since none of them could fulfil all of the eligibility criteria.

4.10.4    The predicted ventilation shaft noise levels at the NSRs in the vicinity of the proposed ventilation buildings in this study would comply with the EIAO-TM criterion if silencers are provided at all exhaust fans of the proposed three ventilation buildings and included in the design specification.  No adverse cumulative fixed noise impacts are anticipated with the consideration of ventilation shaft noise impacts from NHKIL at the NSRs close to EVB and VB2.



(1) Atkins China Ltd. (June 2001).  Central Reclamation Phase III Comprehensive Feasibility Study for Minimum Option, Final EIA Report.

([2])   Maunsell Consultants Asia Ltd. (June 2001).  Wan Chai Development Phase II Comprehensive Feasibility Study, EIA Report.

([3])   Maunsell Asia Ltd. (June 2000).  Wan Chai Development Phase II, Comprehensive Feasibility Study, Environmental Assessment Study, EIA Report.

([4])   Atkins China Ltd. (June 2001).  Central Reclamation Phase III Comprehensive Feasibility Study for Minimum Option, Final EIA Report.

([5])   Maunsell Consultants Asia Ltd. (June 2001).  Wan Chai Development Phase II Comprehensive Feasibility Study, EIA Report.

([6])   Fax communication between the Highways Department and the consultant (Ref: (18) in HH 710/95 (8) XV (DWC), dated 29 May 2001).

([7])   Atkins China Ltd. (June 2001).  Central Reclamation Phase III Comprehensive Feasibility Study for Minimum Option, Final EIA Report.