11.                SUMMARY

 

11.1               Introduction

 

11.1.1         Roads D1, D8, D10 and the extended Road P2 in Tseung Kwan O New Town are necessary to provide an efficient means of district transport network, to connect the east Tseung Kwan O area via the town centre south to Tseung Kwan O Area 72. These roads are proposed in order to meet the targeted population intake for the medium term and to enable road link to Area 86 to be in operation for population intake.

 

11.1.2         Each of these roads is a Designated Project (DP) under Schedule 2 Part 1, A.1 of the EIAO. Under the EIAO, an EIA is a statutory requirement for Schedule 2 DP and an Environmental Permit (EP) must be obtained before any construction works may commence.

 

11.1.3         The proposed construction period for Roads D1, D8 and D10 and the extended Road P2 is outlined as follows:

 

§           Road D1 (Phase 1: September 2003- December 2004, Phase 2: December 2003 –  December 2006)

§           Road D8 (December 2003 – November 2006)

§           Road D10 (Phase 1: October 2003 – November 2005, Phase 2: May 2004 – May 2007)

§           Minor road junction improvement works at road junction of Road D10/Wan Po Road, and road junctions along Roads D1 and D8 (2002 – 2009)

§           Extended Road P2 (December 2003 – December 2010)

 

11.1.4         The nearby concurrent construction activities in between the construction period of Roads D1, D8, D10 and the extended Road P2 include site development of Areas 65, 67 and 86, and possible future development to the south of Road D1.  Details of the concurrent construction activities have been taken into consideration in the construction phase impact assessment to assess the cumulative impacts.

 

11.1.5         In view of the speedy developments in Tseung Kwan O, this study has adopted a worst case scenario where possible future development to the south of Road D1 and at Area 78 is assumed. On such basis, a total population intake of 520,000 in the whole Tseung Kwan O area is assumed for the assessment purpose of this EIA and year 2030 is used as the planning horizon.

 

11.1.6         Considering that there is possible future development to the south of Road D1, two assessments have been done to evaluate the noise, air quality, and landscape and visual impacts. For Assessment 1, it is assumed that there will be further development to the south of Road D1, whereas Assessment 2 assumes that there will be no further development to the south of Road D1 based on the approved OZP.  Assessment 1 and thus the proposed measures are for worst case assessment purposed, the package of the proposed measures will need to be reviewed if further reclamation is put forward in the future.

 

11.1.7         Construction of Roads D1, D8, D10 and the extended Road P2 needs to take into account the engineering feasibility and the environmental acceptability. Based on the development works packages and programmes, the potential environmental impacts arising from the development proposals have been assessed and the major conclusions and recommended mitigation measures are summarized in the following sections.

 

11.2               Air Quality

 

Construction Dust

 

11.2.1         Cumulative construction dust impacts have been assessed taking into the concurrent construction activities in close proximity to the present project for the worst-case scenario.  Model calculations have shown that dust concentrations at the nearby existing receivers are expected to exceed the EIAO-TM Dust Criteria and the Air Quality Objectives with respect to TSP.  Watering the construction site twice a day together with strict implementation of other dust suppression measures as stipulated in the Air Pollution Control (Construction Dust) Regulation are recommended to reduce the dust nuisance.  Good site practices and a comprehensive dust monitoring and audit are also recommended.  It is anticipated that the Dust Guidelines and Air Quality Objectives can be achieved by the implementation of these dust suppression measures and no adverse residual impact is expected.

 

OPERATIONAL PHASE

 

11.2.2         During operation phase, since the proposed noise mitigation measures under the assumptions of the two assessments are different, the air quality impact for the two assessments was studied accordingly.

 

11.2.3         In both Assessments 1 and 2, model results indicated that exceedance of 1-hour average NO2, 24-hour average NO2 and 24-hour average RSP concentrations as specified in the Air Quality Objectives is not expected at any representative air sensitive receivers.  Thus, mitigation measures are not considered necessary.

 

11.2.4         For the air quality inside the proposed two sections of the deckover for Assessment 1, results of the air quality modelling show full compliance of relevant air quality standards hence adverse air quality impact is not expected.

 

11.3               Noise Impacts

 

Construction Phase

 

11.3.1         Noise assessment was carried out with respect to all construction works of Extended Road P2, Roads D1 and D8.  No assessment for construction of Road D10 was undertaken as there was no existing NSR identified near Road D10 during the construction phase.  In total, 7 representative NSRs located in close proximity to the proposed works were identified, taking into account the construction period of the work packages of the project and other concurrent construction activities nearby the NSRs.

 

11.3.2         Predicted unmitigated noise levels at most NSRs would exceed the construction noise standard stipulated in EIAO-TM.  However, with the implementation of using quieter plants, installation of movable noise barriers and limiting the number of some PMEs, the mitigated noise levels at all NSRs would be in compliance with statutory criteria.  No residual impacts would be expected.

 

Operational Phase

 

11.3.3         Traffic noise from Roads D1, D8, D10 and Extended Road P2 would give rise to adverse traffic noise impacts to the nearby NSRs.  Deckovers (for Assessment 1) / semi-enclosures (for Assessment 2), cantilevered barriers and vertical barriers were proposed to alleviate noise impacts on the affected NSRs.  Low noise surfacing was assumed at the elevated section of Road P2 where the speed limit is 70 km/hr.  With the implementation of the proposed noise barriers, the noise levels at most of the NSRs would comply with the traffic noise criteria.  For those NSRs which overall exceedance of 70dB(A) is predicted, noise contributions from the proposed new roads are less than 1.0dB hence no further noise mitigation measures are recommended.  Indirect technical remedies in the form of acoustic insulation and air conditioning have been recommended to some NSRs at planned schools which full compliance of noise standard cannot be achieved even when all practicable at-source noise mitigation measures is exhausted.  Residual impacts in future development to the south of Road D1 should be reviewed based on the planned use of that area and the layout available then.

 

11.4               Water Quality

 

Construction Phase

 

11.4.1         The identified potential sources of water quality impact include construction runoff and drainage; debris, refuse and liquid spillages from general construction activities; and sewage effluent from the construction workforce.  Minimisation of water quality deterioration can be achieved through implementing adequate mitigation measures, such as control measures to minimise construction run-off and drainage from the site.  With the implementation of the recommended mitigation measures, the construction works are not expected to result in any unacceptable impacts on marine water quality. 

 

11.4.2         During construction of Road D10 adjacent to the TKO Stage 1 landfill at Area 77, groundwater pumped out during foundation works will not be permitted to be directly discharged into the nearby drainage channel or coastal waters.  It is recommended that the groundwater be stored temporarily on site as the volume is anticipated to be small. An identified option for the treatment and disposal of the collected groundwater is tankering of the groundwater to the TKO Preliminary Treatment Works (PTW) at Area 85.  Pre-treatment of the collected groundwater may be required to meet the Technical Memorandum on Effluent Discharge Standards prior to the groundwater being discharged to the TKO PTW.  On-site pre-treatment of the collected groundwater, if required, should be implemented to the satisfaction of the Director of Environmental Protection prior to its discharge to the TKO PTW.  The pile supports for the elevated section of Road D10 would not form a barrier to leachate seepage and thus it is expected that there would not be any significant change to the leachate migration profile at the landfill.

 

 

 

Operational Phase

 

11.4.3         The only source of potential water quality impact during the operation phase will be runoff from the road surfaces.  A surface water drainage system with adequate grit interceptors will be provided to collect the road runoff.

 

11.4.4         Assessments have shown that the placement of Road D10 bridge piers in the Eastern Drainage channel is likely to result in insignificant reduction in flushing capacity of the channel.

 

11.5               Solid Waste Management

 

11.5.1         Wastes generated by the construction works are likely to include construction and demolition material, workforce wastes and chemical waste.  Provided that the identified waste arisings are handled, transported and disposed of using approved methods and that the recommended mitigation measures are adhered to, adverse environmental impacts would not be expected during the construction phase.  The recommended reuse and disposal arrangements shall form the basis of the site Waste Management Plan to be developed by the Contractor at the commencement of the construction phase.

 

11.5.2         The operation of the proposed Roads D1, D8, D10 and the extended Road P2 will generate wastes associated with littering and road maintenance activities. The potential environmental impacts arising from the handling and disposal of these wastes is anticipated to be insignificant.

 

11.6               Landfill Gas Hazard

 

11.6.1         A qualitative landfill gas (LFG) hazard assessment has been undertaken to assess the potential hazard posed by Tseung Kwan O Stage I Landfill (TKO Stage I) to Road D10 and a section of Road D1 which will located within the Consultation Zone of TKO Stage I.

 

11.6.2         Previous calculations indicated that the LFG generation rate at TKO Stage I peaked in 1988, producing a collectable volume of some 120 million m3yr-1.  The annual production rate by 1999 was predicted to be less than a third of the peak rate, at less than 40 million m3yr-1.

 

11.6.3         Comprehensive restoration works for TKO Stage I have been completed.  These include active extraction of LFG for flaring and electricity generation, passive venting of LFG across landfill site, leachate collection and treatment, and surface and subsurface drainage systems.  As part of the Restoration Contract for TKO Stage I, a comprehensive monitoring programme also commenced in late 1997 on a monthly basis.

 

11.6.4         Although the methane levels recorded from July 2000 to July 2001 at the monitoring wells located near the boundary of TKO Stage I Landfill are very low, significant levels (> 5%) of carbon dioxide were recorded in some wells.  As such, the source of LFG at TKO Stage I Landfill is considered ‘major’.

 

11.6.5         There are no known lateral fault lines between TKO Stage I and Road D10.  There are no existing utilities directly linking the landfill and Road D10.  Therefore, the LFG migration pathways to Road D10 are considered to be moderately short/direct.

 

11.6.6         Road D1 will be on reclaimed land, the upper underlying material is likely to be rock fill and sand fill.  The Eastern Drainage Channel situated between Road D1 and landfill will act as a barrier of LFG migration to this road.  There are no existing utilities directly linking the landfill and Road D1.  Therefore, the natural and manmade LFG migration pathways to Road D1 are considered to be moderately short/direct and long/indirect respectively.

 

11.6.7         The common targets of LFG migration at both Road D1 and Road D10 are the confined space (e.g. utility manholes, inspection chambers or ducts) and the temporary excavations created during the construction phase.  Since these areas are not accessible to public and restricted to trained personnel, the risk level of these targets are considered to be medium.

 

11.6.8         The overall LFG risk posed by TKO Stage I Landfill to both the concerned section of Road D1 and to the whole of Road D10 is assessed to be ‘high’.  As suggested in the EPD’s Landfill Gas Hazard Assessment Guidance Note, some engineering and detection measures  should be provided to safeguard the concerned section of Road D1 and the whole of Road D10.

 

11.6.9         The following mitigation measures are recommended:

 

§           Prior to and during development or construction, utility companies would be advised of the possible presence of LFG in the subsurface for them to take into account in the design, construction and maintenance of their works.

 

·          Void around any service ducts, pipes or cables etc. within conduits would be filled with gas resistant mastic.  All ducts, manholes, and chambers, either specific to the proposed developments or to utility services shall be sealed off from the ground to prevent gas entry and provided with vented covers to allow any gas that enters to dissipate harmlessly to atmosphere.

 

§           During site formation and construction works, portable gas detectors should be used to regularly check the gas levels in depressions, trenches, and other excavations.  The monitoring shall be undertaken at the beginning of each half working day (i.e. morning and afternoon) and for the entire period the excavation remains open.  If high LFG level is measured, ventilation of such excavations should take place and sources of ignition should be kept away from areas where build-up of gas is possible.

 

11.6.10     The following monitoring requirements are recommended: (i) Atmosphere within utility manholes or chambers should be checked for methane, carbon dioxide, and oxygen prior to entry.  It is recommended that the pre-entry monitoring shall be undertaken, where applicable, in accordance with the requirements of the Factories and Industrial Undertaking (Confined Spaces) Regulation; (ii) Routine monitoring should also be conducted at the manholes and chambers on a regular basis.  The frequency of the routine monitoring is recommended to be biweekly during the initial stage (the first 3 months of the operational phase).  The frequency shall be subsequently reviewed on a quarterly basis through discussion with EPD, based on all the available monitoring data for methane, carbon dioxide and oxygen (including that of pre-entry monitoring).

 

11.7               Landscape and Visual Impact

 

Proposed Landscape and Visual Mitigation measures

 

11.7.1         The following landscape and visual mitigation measures are proposed in the construction phase:

 

·          Regular checks shall be carried out to ensure that the work site boundaries are not transgressed, hoardings are properly maintained and that no damage is being caused to the surrounding areas (CM1). Any irregularities shall be brought to the attention of the appropriate adjacent management and maintenance agencies (e.g. private land owner, or HyD, LCSD, or HKHA etc.).  Remedial measures shall be designed and implemented as appropriate.

·          Erection of decorative screen hoarding particularly in areas adjacent to existing developments (CM2). (Hoardings next to undeveloped areas / construction sites need not be decorative).

·          Storage of materials and plant shall be limited to areas less visible to receivers (CM3).

·          Control of night-time lighting to prevent upward glare to visually sensitive receivers.  Lighting should be directed to where it is required for security purposes only (or night working if permitted) (CM4).

·          Potential conflicts between landscape works and other works shall be avoided.  Utilities works in particular shall be checked to ensure that they do not compromise landscape and visual mitigation measures.  Where potential conflicts occur, engineering and utility layouts shall wherever possible be redesigned to avoid conflicts (CM5).

·          For construction works associated with the deckovers proposed in Assessment 1 - Worst Case Scenario, all impacts on all trees and shrubs shall be minimised (CM6).

 

11.7.2         The following landscape and visual mitigation measures are proposed in the operation phase:

 

·          Aesthetic design of elevated structures on Roads P2 and D10 with particular regard to form and finishes so as to create as slender and elegant an appearance as possible.  ACABAS approval shall be required (OM1).

·          Sensitive integration of road embankments with surrounding ground levels (OM2) The engineering and landscape designs should be prepared to create smooth changes in level at edges of embankments, with rounded profiles wherever possible;

·          Aesthetic design of all noise barriers, noise enclosures and deckovers with particular regard to chromatic treatments.  ACABAS approval shall be required (OM3);

·          Aesthetic design of road lighting with glare control measures (OM4). Light fittings and columns should be of an attractive design suitable to the streetscape setting and the overall style in TKO.  The light fittings should be of a type which efficiently projects light onto the intended areas, and does not cause any glare to adjacent residents;

·          Sensitive hard and soft landscape design to edge of Area 77 and landfill beneath viaduct (OM5) so as to provide an attractive waterfront edge and promenade walk;

·          Sensitive hard landscape design along roadsides, with particular regard to the creation of an attractive and user friendly pedestrian environment (OM6). The preferred width of soft landscape amenity areas should generally be 3m (but can be narrower e.g. at bus bay ingress / egress);

·          Tree, shrub and climber planting adjacent to the roads and structures with particular regard to the screening of noise barriers, provision of shade trees along footpaths, and climbing plants against abutment walls and viaduct columns (OM7);

·          Tree, planting along central dividers to provide structure planting for the townscape (OM8);

·          In the Worst Case Scenario, the two full deckovers over Road D1 adjacent to Areas 65 and 67 shall be designed as landscape decks.  Structural design of the deck shall allow for adequate soil depth to permit tree planting (1.5m min).  The appropriate maintenance agencies shall be involved in the approval of the design of the deckover (refer to table 8.9)

·          Attractive design of pedestrian subways including murals. ACABAS approval shall be required. (OM10)

 

11.7.3         All landscape mitigation measures indicated in this report will be included in the works boundaries and the landscape and visual mitigation measures implemented within these areas are therefore considered to be “on-site”.

 

Predicted Residual Impacts

 

Construction Phase – Assessment 1 – Worst Case Scenario (with further development)

 

11.7.4         Residual landscape impacts would be as described for Assessment 2 below, except that if the deckovers over Road D1 are constructed separately, after the completion of the other roadworks and amenity strips, then this would result in some additional adverse construction impacts, comprising adverse impacts of moderate significance on the future trees and shrubs in the planned amenity areas along Road D1 (LR1). However, these additional impacts would be avoided if the deckovers are constructed at the same time as the other roadworks.

 

11.7.5         Residual visual impacts would be as described for Assessment 2 below, except that if the deckovers over Road D1 are constructed separately, after the completion of the other roadworks and amenity strips, then this would result in adverse impacts of substantial significance being felt by the future pedestrians and cyclists on Road D1 (T6); users of open space in Area 66 (O5); and residents in the planned developments in Areas 65 (R6) and 67 (R7).  However, these additional impacts would be avoided if the deckovers are constructed at the same time as the other roadworks.

 

 

 

Construction Phase – Assessment 2 – Committed Development

 

11.7.6         No physical landscape resources would be impacted.  Residual Construction Phase landscape impacts would be minor and would be limited to adverse impacts of moderate significance to the quality of landscape character area LCA8 – Area 77 landfill and slight significance to the quality of landscape character area LCA12 – Eastern Drainage Channel.

 

11.7.7         Residual visual impacts during the construction phase would be relatively minor and would comprise mainly adverse impacts of moderate significance upon residents in the residential development in Area 51 (R1) and occupants and users of the commercial/residential development in Area 72 (C/R1).  Other impacts would be slight or insubstantial.

 

Operation Phase – Assessment 1 – Worst Case Scenario (with further development)

 

11.7.8         The operation phase residual landscape impacts would be as for Assessment 2 below, except that if the deckovers are built at a later stage than the other roadworks, then the deckovers on Road D1 would result in adverse impacts of slight significance on the future trees and shrubs in the planned amenity areas along Road D1 (LR1).  This is because the deckovers would preclude compensatory tree planting beneath them, but would allow compensatory planting on top of them, which would partially but not completely compensate for the loss of trees at ground level.  However, these additional impacts would be avoided if the deckovers are constructed at the same time as the other roadworks.

 

11.7.9         Operation phase residual visual impacts would include adverse impacts of substantial significance upon pedestrians and cyclists adjacent to Road D1 (east-west section) (T6).  The substantial significance of these impacts would be due principally to the nature of the full deckovers over Road D1 adjacent to Areas 65 and 67, which would be very visually overpowering and prevent tree planting and soft landscape treatment underneath the decks. On the other hand, the deckovers would tend to reduce long term visual impacts upon VSRs looking down from adjacent residential properties in Areas 65 and 67.

 

11.7.10     Residual adverse impacts of moderate significance, caused principally by noise barriers and/or elevated road structures, would be felt by those VSRs located immediately adjacent to the roads, including pedestrians and cyclists adjacent to extended Road P2 (T5); pedestrians and cyclists adjacent to Road D1 (north-south section) (T7); pedestrians and cyclists adjacent to Road D8 (T8); pedestrians and cyclists adjacent to Road D10 (T9); users of the open space adjacent to Road D8 (O4); users of the open space adjacent to Road D1 in Areas 66 (O5); and users of the open space adjacent to Road D1 adjacent to the Eastern Drainage Channel (O6).

 

11.7.11     The remaining visual impacts would be of either slight or insubstantial significance.

 

Operation Phase – Assessment  2 – Committed Development

 

11.7.12     Residual landscape impacts would be minor and would comprise adverse impacts of slight significance to the landscape character of landscape character areas LCA7 – TKO New Reclamation Area, LCA8 – Area 77 landfill, LCA10 – Area 86 Dream City and LCA12 – Eastern Drainage Channel.

 

11.7.13     Residual visual impacts would essentially be the same as for Assessment 1, with the exception that VSR C/R7 would not exist, and there would be slightly less, although still substantial, negative impacts on VSR T6 (pedestrians adjacent to Road D1 (east-west section) next to Areas 65 and 67).  The substantial significance of these impacts would be due principally to the nature of the semi-enclosures over Road D1 adjacent to Areas 65 and 67, which would be visually prominent. However, these impacts would be less than those caused by the deckovers in Assessment 1, as they would be partially mitigated by good aesthetic design of the structures and attractive tree and shrub planting (refer to figure 8.7.22).

 

Overall Assessment of the Acceptability of Impacts

 

11.7.14     In general terms, the landscape impacts are relatively minor and can be successfully mitigated.  The most significant visual impacts will be felt by those VSRs located immediately adjacent to the roads (i.e. pedestrians, cyclists and users of adjacent open spaces) and will result from the visual prominence of the noise barriers, semi-enclosures (in Assessment 2) and deckovers (in Assessment 1).  Most of these visual impacts can be largely mitigated by good aesthetic design of the structures themselves and by attractive and extensive tree and shrub planting in the roadside amenity areas. 

 

11.7.15     The only substantial adverse residual impacts that would remain after mitigation are the visual impacts identified on pedestrians and cyclists in Road D1 as a result of the noise barriers (in Assessment 2) and deckovers (in Assessment 1), and it is considered that because these impacts are limited to one group of receivers who are relatively transient (as they pass along the road), they do not justify a conclusion that the overall impacts are unacceptable.   

 

11.7.16     Therefore it is considered that, in the terms of Annex 10 of the EIAO TM, the landscape and visual impacts are acceptable with mitigation measures for both Assessment 1 and Assessment 2.

 

 

11.8               Environmental Monitoring and Audit

 

11.8.1         Environmental monitoring and audit (EM&A) requirements have been specified in an EM&A Manual.  The requirements and principles in preparing the EM&A Manual have been briefly outlined in the EIA report.  The Manual has been prepared with reference to the EIAO-TM and EPD’s Generic EM&A Manual.  The EM&A Manual contains full details of proposed baseline and compliance monitoring programmes, as well as performance specifications, audit requirements and procedures for air quality, noise, landfill gas monitoring, waste management, water quality, landscape and visual.

 


 

11.9               Key Environmental Outcomes

 

11.9.1         The proposed Roads D1, D8, D10 and the extended Road P2 in Tseung Kwan O New Town will provide an efficient means of district transport network connecting the east TKO area via the town centre south to TKO Area 72 and also enabling road link to Area 86.  The proposed project is necessary to facilitate the rapid developments in TKO and the target population intake. 

 

11.9.2         Two scenarios have been assessed for the study, namely: Assessment 1 – with possible further development to the south of Road D1; and Assessment 2 – committed development without further development to the south of Road D1.  The key environmental outcomes and benefits arising from the study include:

 

·          Existing air sensitive receivers in the TKO New Town will be protected from cumulative construction dust impact by the recommended dust control measures during the construction phase.

·          No adverse air quality impacts were predicted during the operation phase at existing and planned air sensitive receivers in the TKO New Town.

·          Existing noise sensitive receivers in the TKO New Town will be protected from adverse noise impact during the construction phase by adopting quiet plant, installation of movable noise barriers and limiting the number of some PMEs.

·          Adverse traffic noise impact to existing and planned noise sensitive receivers will be ameliorated by the proposed mitigation measures including deckovers (for Assessment 1)/semi-enclosures (for Assessment 2), cantilevered barriers, vertical barriers and low noise road surface where applicable.  Indirect technical remedies have also been recommended to some NSRs at planned schools which full compliance of noise standard cannot be achieved even when all practicable at-source noise mitigation measures are exhausted.

·          Adverse water quality impact during the construction phase will be prevented by adopting the recommended mitigation measures such as minimising construction run-off and drainage from the site, and also on-site pre-treatment of groundwater prior to disposal.

·          Operation phase water quality impact would not be significant and it has been recommended that grit interceptors be provided to collect road runoff.

·          Environmental impacts due to waste generation during the construction phase would be avoided by the development of a Waste Management Plan.  The potential impacts arising from operational waste generation is anticipated to be insignificant.

·          The hazards of landfill gas at concerned road sections have been assessed and the common risk would be associated to confined spaces and temporary excavations.  For the construction phase, engineering and detection measures have been recommended.  For the operation phase, regular monitoring of LFG has been recommended.

·          The landscape and visual impacts for both Assessments 1 and 2 have been assessed and are acceptable with the recommended mitigation measures.

 

 

11.10           ENVIRONMENTAL BENEFITS OF THE PROPOSED NOISE MITIGATION MEASURES

 

11.10.1     The proposed at-source noise barrier will provide full protection to approximately 4,367 planned and existing residential dwelling and 125 classrooms of planned schools.  Without the at-source noise barriers, some 11,000 population will be subject to adverse noise impact from road traffic on the proposed roads, with predicted noise level up to 79 dB(A).  Alternatively, a large setback distance will have to be provided to achieve noise compliance which may sterilise large area of lands for planning of noise sensitive landuses.

 

11.10.2     The design of the at-source noise barriers has been optimised to take into consideration factors such as road safety, engineering practicality, and potential visual impacts.  Landscape and visual measures such as tree, shrub and climber planting, aesthetic design and chromatic treatment, etc. have been recommended to the design of the noise barrier.

 

11.11           Conclusions

 

11.11.1     The EIA of Roads D1, D8, D10 and the extended Road P2 has identified potential environmental impacts of various nature including water quality, air quality, noise, landfill gas hazard, and landscape and visual impacts.  The potential environmental impacts are expected to arise during both construction and operational stages.

 

11.11.2     The results of the EIA indicate that the environmental impacts identified are generally within acceptable environmental standards.  Where environmental exceedances are observed, appropriate mitigation measures have been recommended to meet the acceptable environmental standards and significant residual impacts after mitigation are not expected.  Monitoring requirements have also been specified in an EM&A manual to ensure proper implementation of the recommended mitigation measures.

 

11.11.3     Concerning landfill gas hazard, proper implementation of the proposed mitigation measures will protect the sensitive receptors (e.g. construction workers and maintenance personnel for utility) at the concerned section of Road D1 and the whole of Road D10.