5.1 Introduction
5.1.1 The EIA has recommended that an EM&A for ecology is undertaken during both the design, construction and operational phases of the project. The objectives of the design audit are to ensure that the design process clearly implements the design ecology mitigation specified in the EIA and to ensure that such designs are ecologically feasible and effective. The construction and operational EM&A objectives are to ensure that the ecological contract works and construction mitigation procedures recommended in the EIA are carried out as specified and are effective. The construction and operational phase EM&A will be carried out as part of the site audit programme.
5.2.1 The design phase audit procedures are detailed in Section 1.5.3 and Figure 1.3. Ecological specifications for species relocation and habitat creation will be designed as part of the project detailed design phase. The specifications and designs will be reviewed as and when they are produced. The final ecological specifications and designs shall be signed off by the design auditor(s) using the appropriate proforma (see Appendix B).
5.2.2 The
construction phase ecological audit is concerned with checking the effectiveness
of the implementation of the ecology contract works, together with auditing the
effectiveness of site mitigation.
Operational phase EM&A will comprise the audit of the
reestablishment of habitat areas and the on-going effectiveness of mitigation
measures as appropriate. The
operational phase EM&A shall be undertaken during the Contractor’s one year
maintenance period. The overall
procedures for the ecological EM&A during construction and operation are
shown in Figures 1.4 and 5.1.
5.3.1 Ecological measures proposed by the EIA to mitigate the ecology impacts of the scheme will be incorporated into the detailed design of the project. In particular, ecology specifications and designs will be produced for the elements detailed in Table 5.1 below.
Table 5.1 Ecological Design Elements
Number |
Specification |
C1 |
Design of
wildlife tunnels for mammals and amphibians. |
C2 |
Design of
culverts and culvert inlets and outlets. |
C3 |
Design of
drainage channel escape ramps for amphibians. |
C4 |
Specification
for water filled pots as habitats for amphibians. |
C5 |
Translocations
specifications for the shrub Pavetta hongkongensis, orchids Acampe rigida and Liparis viridiflora and tree Artocarpus hypargyreus. |
C6 |
Translocation
specifications for Hong Kong Newt, Romer’s Tree Frog and Lesser Spiny Frog. |
C7 |
Translocation
specification for Bejiang Thick-lipped Barb. |
5.3.2 Design will be prepared during the detailed design stage. The designs will be checked by a design auditor(s) to ensure that the measures are fully incorporated and that potential conflicts with civil engineering, geo-technical, structural, lighting, signage, drainage, underground utilities and operational requirements are resolved prior to construction. In the event of a non conformity, the Event/Action plan detailed in Table 5.2 below shall be followed by the relevant parties.
Table 5.2 Event / Action Plan for Design Phase
Action Level |
Ecology
Auditor |
Project
Engineer (PE) |
Project
Ecologist (PEC) |
Non Conformity
(with Design Standards and Specification) |
C
Identify Source C
Inform PE and PEC C
Discuss remedial actions with PE,
and PEC C Verify remedial actions when complete |
C
Notify PEC C Discuss remedial actions with PEC C Ensure remedial designs are fully incorporated |
C
Amend designs C
Discuss remedial actions with PE |
5.4.1 Ecological baseline monitoring will
consist of a walk-over survey prior to construction works. It may be necessary to rope off and protect
specific habitats or species of special interest identified during the
ecological surveys. Works around
ecologically sensitive streams and rivers will require particular attention.
5.4.2
The purpose of the baseline works will be to confirm the existing
ecological conditions, with reference to the habitat maps included in the EIA
Report and the established baseline conditions, in relation to the extent and
condition of the habitats and species noted during the walkover survey. No detailed ecological surveys of flora and
fauna will be required at this stage.
5.5 Construction and Operational Phase EM&A
5.5.1 The Environmental Specialist (ES) (refer to Section 1 for a description of the ES and duties) shall be responsible for conducting the EM&A programme and ensuring the Contractor’s compliance with the project’s environmental performance requirements during both construction and operation. The ES will be required to audit the effectiveness of the implementation of the ecology contract works, detailed in Table 5.1 above, together with auditing the effectiveness of site mitigation measures. In respect of the translocation of the shrub Pavetta hongkongensis, orchids Acampe rigida and Liparis viridiflora and tree Artocarpus hypargyreus, Hong Kong Newt, Romer’s Tree Frog, Lesser Spiny Frog and Bejiang Thick-lipped Barb, these elements will be implemented during the Contractor’s mobilisation period but prior to any major construction works and thus, the EM&A for these will also be undertaken early in the Contract.
5.5.2 A qualified ecologist(s), as part of the ET, will carry out the audit. The ecological contract works, detailed in Table 5.1, shall be audited with reference to the audit schedule detailed in Table 5.3 below.
Table 5.3 Audit Schedule for Ecological Contract
Works
Number |
Construction Phase |
Operation Phase |
C1, C2, C3, C4 |
Audit
compliance once at the end of the contract. |
Audit success
of wildlife tunnels, culverts and drainage channel escape ramps once every
two months. Continue for a period of
one year. |
C5 |
Audit
compliance at least three times per week during implementation which will be
prior to the start of the main construction activities. After
translocation is complete, carry out audit survey to determine if all Pavetta hongkongensis, Acampe rigida, Liparis viridiflora and Artocarpus
hypargyreus have been translocated. |
Audit success
of transplantation twice every month for the first 4 months after
transplantation and once every two months after this period by assessing
survival of transplanted plants.
Continue for a period of one year. If audit
records any sign that the plants have not established properly, measures to
rescue the plants should be undertaken.
specific measures should be determined by the landscape architect at
the time. |
C6, C7 |
Audit
compliance at least three times per week during implementation which will be
prior to the start of the main construction activities. After
translocation is complete, carry out audit survey to determine if all Hong
Kong Newt, Romer’s Tree Frog, Lesser Spiny Frog and Beijiang Thick-lipped
Barb have been moved. |
Audit success
of translocation once every two months after completion by assessing survival
of transplanted species. Continue for
a period of one year. |
5.5.3 Mitigation measures to preserve ecological resources within and at the border of the site works area have been recommended by the EIA. The ecological mitigation measures to be implemented during the construction phase are as follows:
¨
control
of site run-off to protect ecology of water courses, particularly important for
the Tung Chung Stream and the Cheung Sha Stream;
¨
survey
and transplantation of location of floral species shrub
Pavetta hongkongensis, orchids Acampe rigida and Liparis viridiflora and tree
Artocarpus hypargyreus;
¨
translocation
of the Beijiang Thick-lipped Barb from Stream 15 to the Tung Chung Stream;
¨
translocation
of Hong Kong Newt, Lesser Spiny Frog and Romer’s Tree
Frog from streams 15, 18, 19 and 21;
¨
scheduling of works in streams 15, 18, 19 and 21 to avoid
the period April to June which is the key breeding period for fish,
amphibians and odonates;
¨
translocation of Romer’s Tree Frog between Lung Tseng Tau and Shek
Mun Kap;
¨
provision of water filled pots as habitats for
the Romer's Tree Frog between Lung Tseng Tau and Shek Mun Kap;
¨
compensatory
planting of approximately 25ha to mitigate and provide enhancement for
vegetation loss and fragmentation (see landscape proposal in Appendix C);
¨
reinstatement
of land temporarily required during construction within 3 weeks of the works
completion in that area in accordance with the landscape proposals;
¨
install drainage system in advance of main roadworks;
¨
all site drainage shall be isolated
from the existing natural hillside drainage system;
¨
areas of exposed soil should be
minimised to reduce the extent of soil erosion. Spoil heaps should be covered
at all times to minimise erosion.
Stockpiled materials shall be stored down gradient from any stream
course or up gradient with a suitably constructed barrier to reduce loss of
materials to the stream.
¨
cmpleted works areas should be
restored within 3 weeks of the area being completed in accordance with the
Landscape Proposal; and
¨
for all haulage roads, temporary
brides shall be used to cross all streams with a span at least twice the width
of the stream and no contact shall be made with the stream or its riparian
vegetation unless authorised by the Engineer.
5.5.4 The mitigation measures shall be audited at least once every week as part of the site audit programme.
5.5.5 In the event of a non-compliance, the
Event /Action plan provided on Table 5.4 shall be followed by the relevant
parties.
Table 5.4 Event / Action Plan
for Construction Phase/Operation Phase
Action Level |
ES |
IC (E) |
ER |
Contractor |
Non-conformity
on one occasion |
1. Identify Source 2. Inform the IC(E) and the ER 3. Discuss remedial actions with the IC(E), the ER and the Contractor 4. Monitor remedial actions until rectification has been
completed |
1. Check report 2. Check the
Contractor's working method 3. Discuss with the ES and the Contractor on possible remedial measures 4. Advise the ER on effectiveness of proposed remedial
measures. 5. Check implementation of
remedial measures. |
1.
Notify Contractor 2.
Ensure remedial measures
are properly implemented 3.
Consider and instruct, if
necessary, the Contractor to slow down or to stop all or part of the works in
the case of a serious non-conformity until situation rectified. |
1. Amend working methods 2. Rectify damage and undertake any necessary replacement |
Repeated Non conformity |
1. Identify Source 2. Inform the IC(E) and the ER 3. Increase monitoring frequency 4. Discuss remedial actions with the IC(E), the ER and the Contractor 5. Monitor remedial actions until rectification has been
completed 6. If exceedance stops, cease additional monitoring |
1. Check monitoring report 2. Check the Contractor's working method 3. Discuss with the ES and the Contractor on possible
remedial measures 4. Advise the ER on effectiveness of proposed remedial
measures 5. Supervise implementation of remedial measures |
1. Notify the Contractor 2. Ensure remedial measures are properly implemented 3. Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the works in the case of a serious non-conformity until situation rectified. |
1. Amend working methods 2. Rectify damage and undertake any necessary replacement |
Note: ES – Environmental Specialist, IC(E) – Independent Checker (Environmental), ER – Engineer’s Representative