9.            CULTURAL HERITAGE

             

9.1          Introduction

           

9.1.1       The EIA has recommended that the EM&A for cultural heritage resources is undertaken during construction phase of the project.  Implementation of the mitigation measures recommended by the EIA will be monitored through the site audit programme.

 

9.2          Mitigation Measures

 

9.2.1              Two main mitigation measures have been recommended by the EIA for the protection of the shrine in Lung Tseng Tau and the Fong Yuen Nunnery, as follows:

 

¨              a village shrine in Lung Tseng Tau, located 10 metres from the proposed works. Mitigation should be in the form of a protective barrier to be erected around the shrine if it falls within a works area during the construction phase.

 

¨              the abandoned nunnery at Fong Yuen lies at a minimum distance of 50 metres from the road alignment. The recommended mitigation is that a 50 metre wooded buffer zone between the road and the nunnery be retained to maintain the existing screening of the compound from the road during the construction and operational phases of the project.

 

¨              the abandoned nunnery at Fong Yuen lies approximately 10 metres from a proposed pipeline/cycle path, mitigation measures are as follows;

 

-      during construction, the main building should be fenced off and kept separate from the works area. Construction of the pipeline/cycle path will not require any specific monitoring of the buildings.

-       during the operational phase, planting of foliage along the cycle path in the vicinity of the monastery should be implemented in order to maintain the existing environment.

              

9.3          Baseline Monitoring

 

9.3.1       Baseline monitoring for the cultural heritage resources will comprise a pre-construction survey of the shrine in Lung Tseng Tau and the Fong Yuen Nunnery to establish the existing condition. 

 

9.4                    Construction Phase Audit

 

9.4.1       All measures undertaken by the Contractor during the construction phase in the vicinity of the shrine in Lung Tseng Tau and the Fong Yuen Nunnery shall be audited by a qualified archaeologist, as a member of the Environmental Team (ET), on a regular basis to ensure compliance with the intended aims of the recommended mitigation measures.  Site inspections should be undertaken at least once per week throughout the construction period adjacent to these properties.  The main aim of the survey is prevention of any possible damage through on-site liaison with the Contractor and Engineer’s Representative (ER) before and during the engineering works. The broad scope of the audit will involve supervision of the following:

 

¨              non-contact effects of the engineering works, such as vibration from pneumatic drills which could cause damage, such as  foundation or wall cracks and loosening of tiles or fixtures; and

 

¨              contact between the historic structures and equipment and materials associated with the engineering works.

 

9.4.2    Specifically the monitoring programme will entail the following tasks:

 

¨              the extent of the agreed works areas should be regularly checked during the construction phase.  Any trespass by the Contractor outside the limit of the works, including any works close to the historical buildings shall be noted;

 

¨              inspection of the surrounding area and ground around the structures to ensure that the foundations are not being undermined in any way; and

 

¨              ensure no stockpiling or equipment storage is affecting the structures.

 

9.4.3    In the event of non compliance the responsibilities of the relevant parties is detailed in the Event /Action plan provided on Table 9.1.

 


Table 9.1         Event / Action Plan for Construction Phase

 

Action Level

ES

IC (E)

ER

Contractor

Non-conformity   on one occasion

1.   Identify Source

2.    Inform the IC(E) and the ER

3.    Discuss remedial actions with the IC(E), the ER and the Contractor

4.    Monitor remedial actions until rectification has been completed

1.   Check report

2.   Check the  Contractor's working method

3.   Discuss with the ES and the  Contractor on possible remedial measures

4.   Advise the ER on effectiveness of proposed remedial measures.

5.   Check implementation of  remedial measures.

 

1.  Notify Contractor

2.     Ensure remedial measures are properly implemented

 

1.        Amend working methods

2.        Rectify damage and undertake any necessary replacement


 

Repeated Non-conformity

1.   Identify Source

2.    Inform the IC(E) and the ER

3.    Increase monitoring frequency

4.    Discuss remedial actions with the  IC(E), the ER and the Contractor

5.    Monitor remedial actions until rectification has been completed

6.    If exceedance stops, cease additional monitoring

1.   Check monitoring report

2.   Check the Contractor's working method

3.   Discuss with the ES and the Contractor on possible remedial measures

4.   Advise the ER on effectiveness of proposed remedial measures

5.   Supervise implementation of  remedial measures.

1.        Notify the  Contractor

2.        Ensure remedial measures are properly implemented

1.        Amend working methods

2.        Rectify damage and undertake any necessary replacement

Note:  ES – Environmental Specialist, IC(E) – Independent Checker (Environmental), ER – Engineer’s Representative