13.                   LAND CONTAMINATION

 

13.1                Relevant Environmental Legislation

 

13.1.1         EPD ProPECC Note No. 3/94

 

13.1.1.1   The  Practice Note for Professional Persons issued by the Environmental Protection Department on Contaminated Land Assessment and Remediation advises that Environmental Impact Assessment reports for new industrial developments including oil depots should :

 

¨             identify possible sources of contamination; and

¨             formulate appropriate operational practices, waste management strategies and precautionary measures for the prevention of contamination problems.

 

13.1.1.2   It further advises that measures for the contamination of land contamination problems are relatively simple, mainly relying on good engineering practice, well developed waste management strategies and established industrial guidelines.

 

13.1.2         Hong Kong Code of Practice for Oil Storage Installations, 1992

 

13.1.2.1   The Hong Kong Code of Practice for Oil Storage Installations, 1992 issued by the Building Authority sets down the requirements for the design, construction and maintenance of oil storage installations in Hong Kong so as to reduce the risk of environmental pollution.  It deals with key design features such as foundations, containment bunds, tanks and drainage.  In addition it addresses inspection and repair requirements and provisions for contingency planning to deal with spillage and other environmental pollution incidents.

 

13.2               Description of Existing Conditions

 

13.2.1         The PAFF site at Tuen Mun Area 38 currently comprises undeveloped recently reclaimed land with was produced using public fill material. The site currently used for stockpiling of inert public fill material only. Thus, there is no reason to believe that the land is in any way contaminated at present. 

 

13.3                Key Issues

 

13.3.1         No contaminated ground should be exposed or excavated during construction of the project and thus, the key issue with regard to land contamination is to ensure that construction works or the operation of the facility at the site will not cause any land contamination in the future.

 

13.3.2         The PAFF site will ultimately provide for the storage of about 420,000m3 of aviation fuel.  Leakage or spillage of this material could result in serious contamination of the underlying ground and possibly seepage to sea, where it could pollute the coastal environment.  It is therefore essential to ensure that the fuel storage facilities are secure, provided with robust leakage detection systems and that effective spill control measures are implemented.

13.3.3         There will be no direct discharge of any wastewater anywhere on site.  However, uncontrolled polluted surface drainage from the site roads and workshops also has the potential to contaminate the ground.  These risks are relatively minor in comparison to the risk of bulk fuel spills and leaks and can easily be minimised by appropriate design of the storm water system.

 

13.3.4         No other chemicals will be held on site in any significant quantity except for oil dispersants and fire-fighting foam.

 

13.4               Assessment of Impacts

 

13.4.1         Pollution from surface drainage from the site roads and workshops can be controlled by the drainage from all areas of hardstanding, including fuel storage and handling facilities, areas of vehicular traffic, sites used for vehicle or plant maintenance or adjacent to covered workshops being diverted through an oil/water interceptor prior to discharge.   In order to reduce the amount of runoff to be treated, uncontaminated runoff such as from the building roof and landscaped areas should be collected separately and discharges to the storm water drain.

 

13.4.2         However, spills and leaks from storage tanks and pipework pose the principal potential contamination threat to the ground.  All storage areas will be bunded to 110% of the capacity of the largest tank in the bund and this provides the principal mitigation against sizeable spills.  Fuel oil losses to the surface of the facility outside the bunded area would be contained in the first instance by the stormwater drainage system providing the opportunity for clean up before any seepage into the underlying ground occurs.

 

13.4.3         Leakage from the bunded area could only occur following primary failure of tanks or pipework within the bund coupled with a secondary failure or overtopping of the bund wall or liner system.  Possible sources of contamination can be identified as follows :

 

¨             failure of tank walls;

¨             failure of pipelines;

¨             leaking pipejoints;

¨             failed seals within gaskets, pumps or valves;

¨             overfilling; and

¨             leakage from sampling points.

 

13.4.4         Prevention of losses from these sources will principally be addressed by design and adherence to international standards in the plant specification.  Once commissioned all storage facilities will require to be subjected to a regular inspection and maintenance programme.  The risk of spills and leaks from these sources has been examined in Section 10 and found to be very low (see Section 10.5).

 

13.4.1         To prevent seepage of lost fuel into the ground it is essential that any leaks are promptly identified and cleaned up. With such measures in place no significant contamination of the underlying ground would be expected even in the event of a spillage.   Recommended mitigatory measures to this effect are identified in the following section.

 

13.5               Mitigation Measures

 

13.5.1         The implementation of appropriate mitigation for the oil storage facilities and pipework is required to ensure that risk of ground contamination as a result of oil spills or leaks is kept to a practical minimum. Such measures should include the following. These measures are also summarised in the Environmental Mitigation Implementation Schedule in Appendix B:

 

¨             bunding of all fuel storage areas;

¨             adherence to relevant design standards for storage tanks, pipework, containment and drainage;

¨             regular plant inspections and maintenance;

¨             impermeable lining of tank pits;

¨             leak detection systems;

¨             controlled surface drainage and the provision of emergency shut off valves;

¨             emergency spill response plans; and

¨             provision of spill control materials and equipment on site.

 

13.5.2         Key mitigation recommendations for the bunded containment have been identified in Section 6.7.  The most important features are that all tanks shall be bunded to a capacity of at least 110% of the largest individual tank in each compound.  Tank pits shall be protected by an impermeable bed (e.g. geotextile sheeting, bitumen lining) to prevent seepage of oil to ground and a leak detection system shall be installed beneath the containment membrane.  A concept design for a tank incorporating these features is provided in Figure 13.1.

 

13.5.3         The facility operator shall be required to draw up detailed contingency plans based upon an approach of prevention and detection in the first instance and to ensure containment and safe disposal if any fuel is lost from tanks or pipework. The Emergency Response Plan for the PAFF will be developed for the approval of the Authorities.  The rationale for the plan is detailed in Table 13.1 below:

 

Table 13.1    Spill Management Plan Rationale

 

Operation

Approach

Method

Monitoring

Oil Leaks/ Spills

Prevention

 

Detection

Established practices & operator training

Regular ground water assessment through selected bore holes

Pipelines

Early detection and isolation

Automatic shut down

Pressure of line

Frequency and duration of pumping

Tankage

Early detection

Removal from service

Under tank hydrocarbon monitors

Prevention

Containment bunds

 

 

 

 

 

Transfer

operations

Prevention

High level liquid shutoffs

Visual inspections

Oil Spills Response

Containment and disposal

Response team training and pre-positioned equipment

Visual inspections

 

13.5.4         The key features which should be included in the plan are summarised  below:

 

¨             organisation of the oil spill response team and the responsibilities of each member. Suitable and regular oil spill response training should be provided to the operating personnel and regular oil spill response drills be conducted to test and exercise the responses;

 

¨             response strategies/procedures to be adopted in the case of an oil spill, including:

-         reporting to relevant Authorities;

-         identification of the source of spill;

-         containment of leaking fuel;

-         recovery and processing of free fuel;

-         clean up methodology; and

-         handling and disposal protocols.

 

¨             risk assessments to identify the maximum credible spill scenario for PAFF and other operational spill scenarios and the fate of a fuel spill;

 

¨             set up of emergency centre in PAFF;

 

¨             communication means during oil spill and 24-hours emergency contact list;

 

¨             training and competence level requirement of PAFF staff;

 

¨             oil spill equipment required;

 

¨             sub-contracting services;

 

¨             drills and exercise requirements; and

 

¨              follow-up procedures.

 

13.5.5         Other key mitigation measures for the protection against contaminated land include the following:

 

¨             run off from the roofs of site buildings and landscaped areas shall be conveyed in closed drains to the nearest storm water drain to prevent the generation of excessive quantities of surface water which may be polluted;

 

¨             suitable absorbent materials (e.g. sand or earth) shall be kept on site to deal with spills.  Chemical dispersants shall not be employed;

 

¨             the facility shall be designed, constructed, operated and maintained in full accordance with the Code of Practice for Oil Installations, 1992;

 

¨             tank pressure testing shall be carried out routinely to check for possible tank leaks.  Product inventory monitoring shall be integrated into site management procedures to check for any abnormal or unexpected product loss;

 

¨             tank overfill monitoring systems shall be installed and regularly tested.  Inlet valves should automatically shutdown on exceedance of “high-high level” to prevent over-filling;

 

¨             pipe leakages shall be routinely checked for by means of a pressure sensitive leak detection system and routine inventory control;

 

¨             drainage from areas of hardstanding shall be treated by means of oil / water separators prior to discharge to storm drain. All surface drainage shall be fitted with closure valves to provided additional containment and facilitate clean up of any leaks; and

 

¨             it is recommended that the delivery pipeline from the jetty and the supply line to the airport shall be fitted with pressure sensitive leak detectors.

 

13.6               Residual Impacts

 

13.6.1         With the recommended mitigatory measures in place to prevent, contain and clean-up spills and leaks of fuel oil stored or conveyed to and from the site, no ground contamination of environmental concern would be expected to arise and no adverse residual impacts are predicted.

 

13.7               Environmental Monitoring and Audit

 

13.7.1         Based upon the integrated mitigation measures and procedures which will be put in place to prevent, contain, clean-up and dispose of any spillage, significant environmental effects are highly unlikely to arise.  The regular programme of inspections of the system during the operational stage will be specified in the emergency response plan.  However, design phase audit of the spill response plan to ensure it includes the necessary elements and of the design of the pipelines, tanks and jetty to ensure key spill detection and control elements are included is recommended.  Further details are provided in Section 15 of this report and in the EM&A Manual