15.                   ENVIRONMENTAL MONITORING AND AUDIT

 

15.1               Introduction

 

15.1.1         The development of appropriate environmental monitoring and audit (EM&A) programmes and methodologies are a vital part of the environmental management and control of the Project.  This chapter provides an outline of the EM&A requirements for the Project, highlighting the environmental parameters to be monitored, timing of the monitoring work and the frequency of the monitoring and audit work.   A detailed scope of work will be provided in the EM&A Manual, prepared in accordance with Annex 21 of the TMEIA and EPD=s EM&A Guidelines for Development Projects in Hong Kong.

 

15.1.2         The broad objectives of the monitoring and audit process are:

 

(i)          to clarify and identify sources of pollution, impact and nuisance arising from the works;

 

(ii)         to establish a record of change associated with the implementation of a project;

 

(iii)         to verify all or selected parameters measured are in compliance with legal and contract specifications, internal policies and standards;

 

(iv)        to provide an early warning system for impact prevention;

 

(v)         to provide a database of environmental parameters against which to determine any short term or long term environmental impacts;

 

(vi)        to propose timely, cost-effective and viable solutions to actual or potential environmental issues;

 

(vii)        to setup event and action plans and determine the degree and scope of any necessary remedial measures in case of exceedance of compliance, for which environmental monitoring forms the basis, or the recommendation of environmental controls in the event that the environmental objectives are not achieved;

 

(viii)       to monitor performance of the mitigation measures and to assess their effectiveness and, whenever necessary, identify any further need for additional measures;

 

(ix)        to verify the EIA predicted impacts and compare the impact predictions with actual impacts for the purpose of assessing accuracy of impact predictions in EIA;

 

(x)         to collate information and evidence for use in public and Government consultation; and

 

(xi)        to audit the environmental performance.        


15.2               EM&A Requirements

 

15.2.1         In accordance with the EIA, EM&A procedures are required during the design, construction and operational phases of the project implementation only and a summary of the requirements for each of the environmental parameters is detailed in Table 15.1 below.

 

Table 15.1                Summary of EM&A Requirements

 

Parameter

EM&A Phase

Design Phase EM&A Phase

Construction Phase

Operational Phase

Air Quality

-

U

-

Noise

-

U

-

Water Quality

-

U

-

Ecology

U

U

U

Landscape and Visual

U

U

U

Cultural Heritage

-

(1)

-

Hazard to Life

U

-

-

Fuel Spillage Risk

U

-

-

Fisheries

-

-

-

Land Contamination

U

-

-

Waste

-

U

-

(1)     subject to the recommendations of the Marine Archaeological Investigation

 

15.2.2         The EM&A works during the design phase shall comprise an iterative audit process of specific design elements by a suitably qualified auditor(s).  This role could be filled by the Independent Checker (Environment).  The specifications for certain risk and spill control mitigation measures will be required to be designed during the detailed design phase of the project.  These items will include:

 

¨             land and marine spill response plan;

¨             pipeline leak detection and automatic shut-off system;

¨             pipeline rock armour protection;

¨             tank high level shut-off;

¨             tank bunding;

¨             tank leak drainage isolation and containment system;

¨             on-site fire fighting equipment;

¨             jetty protection; and

¨             fuel delivery shut off valves.

 

15.2.3         In addition, other measures which will require specifications during the detailed design will include and could require the input of specialists:

 

¨             dolphin acoustic monitoring;

¨             dolphin exclusion zone during percussive piling and dredging in the Marine Park;

¨             pre and post construction dolphin abundance monitoring;

¨             underwater noise monitoring during percussive piling;

¨             piling acoustic decoupling methods;

¨             bubble jacket design; and

¨             landscape design drawings.

 

15.2.4         The design audit shall be undertaken as and when the relevant design aspects are produced and the Design Auditor will be required to prepare a Design Audit Report at the end of the detailed design which will confirm that the requirements of the EIA have been fully taken into account in the project design.  The Design Audit report should be submitted to EPD, AFCD and the proponent at least.  Other relevant parties should be identified at the time of issue.

 


15.2.5         During the construction phase, the EM&A requirements are divided into environmental monitoring and/or project auditing in the form of site inspection and supervision.  The environmental monitoring will be conducted in three distinct stages, as follows:

 

(i)          baseline (pre-construction);

 

(ii)                   construction phase impact; and

 

(iii)                 operational phase impact.

 

15.2.6         Environmental monitoring and audit for water quality during the construction phase is recommended in order to ensure all proposed mitigation measures are implemented and effective.  Obtaining a suitable and representative baseline data set will be critical to the whole monitoring and audit process because it forms the standard against which environmental impacts are assessed.  Thus, baseline monitoring for water quality will be required prior to the start of construction.  This parameter will also be subject to audit through site supervision.

 

15.2.7         Site supervision and procedures audit will be required during the construction phase to ensure the proper handling, storage, transportation and disposal of the various waste arisings from the project.

 

15.2.8         Monitoring in the form of regular site inspections shall also be required to ensure dust and noise levels are kept to a minimum and ecological measures in the form of tree transplantation and establishment are being implemented and are effective.  EM&A for landscape resources will extend through the construction phase into the operational phase to ensure that the planting/replanting has been effective.

 

15.2.9         The details of monitoring are discussed in the following sections and summarised in Table 15.2 below.

 

 


Table 15.2:                 Framework for Environmental Monitoring Plan

 

 

Monitoring

 

 

Period

 

Parameters

 

Monitoring

Frequency

 

Responsibility

 

Noise

Dust

Waste

 

 

 

Baseline

 

n/a

 

n/a

 

n/a

 

Construction Phase Impact

 

Routine supervision of construction works

 

As per site inspection schedule

 

Environmental Team

 

Water

 

Baseline

 

Measurements of suspended solids, turbidity, dissolved oxygen and pH.

 

Baseline data daily on both flood and ebb tides for at least one week before the start of the construction.

 

Environmental Team

 

Construction Phase Impact

 

 

Survey of drainage channels in area of construction site. Measurements of suspended solids, turbidity, dissolved oxygen and pH.

 

Daily when marine construction works are being undertaken within 1000m of the Lung Kwu Chau and Sha Chau Marine Park.

 

Environmental Team

 

Ecology

 

 

Design

 

Specifications for:

-   dolphin acoustic monitoring;

-   dolphin exclusion zones during piling at jetty and dredging in Marine Park;

-   underwater noise monitoring;

-   pre and post construction dolphin abundance monitoring;

-   piling acoustic decoupling methods;

-   bubble jacket design.

 

As and when designs are produced.

 

Auditor(s) designated by the Franchisee

 

 

 

 

 

 

Ecology

Baseline

Dolphin Abundance Monitoring

28 days worth prior to construction

Dolphin Specialist(s) / underwater acoustic specialist as members of the Environmental Team)

 

 

 

Construction Phase Impact

500m Dolphin Exclusion Zone

250m Dolphin Exclusion Zone

Dolphin Acoustic Monitoring

Post Marine Construction Dolphin Abundance Monitoring

Underwater Noise Monitoring

Audit of noise reduction measures

During piling operations

During dredging in Marine Park

First 7 days of piling activities

28 days worth after all marine works are completed

During Percussive Piling

Once per week during piling

 

Dolphin Specialist(s) / underwater acoustic specialist as members of the Environmental Team)

 

Landscape/

Visual

Resources

 

 

Design

 

Detailed landscape proposals and specifications

 

As and when designs are produced.

 

Auditor(s) designated by the Design Consultants

 

Baseline

 

 

Walkover tree survey and vegetation identification.

 

Once immediately prior to construction works.

 

Landscape Architect (member of the Environmental Team)

 

Construction Phase Impact

 

Survey of protection measures for trees and landscaping.

 

Twice a month during construction works

 

Landscape Architect (members of the Environmental Team)

Landscape/

Visual

Resources

 

Operational Phase Impact

 

Survey of coverage and growth of plantings.

 

Once every two months for one year after the completion of the construction works

 

Landscape Architect (members of the Environmental Team)

 

Hazard to Life

Fuel Spill Risk

Land Contamination

 

 

Design

 

Specifications for:

-   land and marine spill response plan;

-   pipeline leak detection and automatic shut-off system;

-   pipeline rock armour protection;

-   tank high level shut-off;

-   tank bunding;

-   tank leak drainage isolation and containment system;

-   on-site fire fighting equipment;

-   jetty fenders; and

-   fuel delivery shut off valves.

 

As and when designs are produced.

 

Auditor(s) designated by the Design Consultants


15.3               Baseline Monitoring

 

15.3.1         Water Quality

 

15.3.1.1   Baseline water quality monitoring of the marine environment in the study area will be carried out daily on both flood and ebb tides for a period of 1 week to measure suspended solids, turbidity, dissolved oxygen and pH at all monitoring stations.

 

15.3.2         Landscape/Visual Resources

 

15.3.2.1   Baseline monitoring for the landscape will comprise a walkover vegetation survey of the vegetation and trees on the site.  Representative vegetation types will be identified along with typical species composition. 

 

15.3.3         Ecology

 

15.3.3.1   Baseline monitoring for ecology will comprise pre marine works dolphin abundance monitoring.  This should be undertaken in accordance with the specification prepared during the detailed design phase and should be undertaken for a minimum period of 28 days.

 

15.4               Construction Phase Impact Monitoring

 

15.4.1         Action and Limit Levels

 

15.4.1.1   Monitoring stations will be set up at representative sensitive receivers and the results will be used to ensure compliance with determined performance criteria, based upon specific action and limit levels. The definition of these are as follows:

 

C              the Action Level represents a level at which some appropriate action will be required to prevent conditions deteriorating to the extent that statutory or guide criteria are breached; and

 

C              the Limit Level represents the upper limit permitted and is generally equivalent to the statutory levels specified in legislation.

 

15.4.1.2   The construction phase monitoring and relevant audit criteria for water quality are highlighted below.  Action plans will be developed for use in the event of exceedances, or non conformities in the case of ecology, landscape and visual and waste, and these will be included in the EM&A Manual. 

 

15.4.1.3   Action plans and audit criteria are not relevant to the noise, air, waste and landscape and visual EM&A.  However, the supervision methodology is highlighted below.

 

15.4.2         Water Quality

 

15.4.2.1   Daily surveys are to be undertaken for marine water quality on both flood and ebb tides while dredging activities are being undertaken within 1000m of the Marine Park. The surveys should include measurements of suspended solids and dissolved oxygen. In addition to these water quality parameters, other relevant data shall also be measured, including monitoring location/position, time, water depth, water temperature, salinity, pH, DO saturation, weather conditions, sea conditions, tidal stage, and any special phenomena and work underway at the construction site etc.

 

15.4.2.2   Any noticeable change to water quality should be recorded, investigated and remedial actions shall be undertaken to reduce impacts. The key assessment parameters are dissolved oxygen and suspended sediment and thus Action and Limit Levels based on the assessment criteria are identified for these.  However, turbidity can also provide valuable instantaneous information on water quality and thus an Action Limit is also recommended for this parameter to facilitate quick responsive action in the event of any apparent unacceptable deterioration attributable to the works.  The proposed Action and Limit Levels are shown in Table 15.3.

 

Table 15.3:               Action and Limit Levels for Water Quality

 

 

Parameters

 

Action (mg/L)

 

Limit (mg/L)

 

DO in mg/L

(Depth Average & Bottom)

Depth Average

4.5 mg/L; and

upstream control stations’ mean D.O. (at the same tide of the same day)

 

Bottom

2.5 mg/L; and

upstream control stations’ mean D.O. (at the same tide of the same day)

Depth Average

4.0 mg/L; and

upstream control stations’ mean D.O. (at the same tide of the same day)

 

Bottom

2.0 mg/L; and

upstream control stations’ mean D.O. (at the same tide of the same day)

 

Suspended Solids

(depth averaged)

35  mg/L;  and

130% of upstream control stations’ mean SS (at the same tide of the same day)

40 mg/L;  and

130% of upstream control stations’ mean SS (at the same tide of the same day)

 

Turbidity in NTU

(depth averaged)

 

130% of upstream control stations’ mean Turbidity (at the same tide of the same day)

 

N/A

Notes:                

-      For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

-      For SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

-      All the figures given in the table are for reference only and these may be amended with the agreement of DEP.

-      “Depth Averaged” is calculated by taking the arithmetic mean of the in-situ parameters readings at all three depths.  For suspended solids “depth averaged” is calculated by combining all three samples into one mixed sample which is analysed to produce a physical arithmetic mean.

 

15.4.3         Noise, Air, Waste

 

15.4.3.1   Supervision of the construction works should be undertaken on a weekly basis during site inspections to ensure that waste material is being properly stockpiled and handled and that measures as recommended in the EIA are being undertaken to minimise noise and dust.  Any malpractice should be reported and remedial measures recommended. Review of the waste documents shall be undertaken on a weekly basis to ensure waste management is being undertaken in accordance with the Waste Management Plan.

 

15.4.4         Landscape and Visual

 

15.4.4.1   The landscape construction works will be closely monitored to ensure all measures specified to promote the healthy establishment of plants are undertaken fully and that any defects or omissions are rectified at the earliest opportunity and before the end of the construction period.

 

15.4.4.2   The protection provided to all trees identified will be monitored throughout the construction period to ensure that it is kept in a good condition.  Any damage by the Contractor or by other parties to the protection of the trees will be noted for remedial action.

 

15.4.4.3   Operations relating to the supply of specialist plant material (including the collecting, germination and growth of plants from seed) will be monitored to ensure that plants will be available in time to be used within the construction works.

 

15.4.4.4   The progress of the engineering works will be regularly reviewed on site to identify the earliest opportunities for the landscape works to be undertaken.

 

15.4.5         Ecology

 

15.4.5.1   Audit of the ecological mitigation measures recommended by the EIA to reduce noise during the piling activities for the jetty shall be undertaken once per week during active piling activity.   Reference should be made to the detailed specifications prepared during the detailed design stage which will define the measures to be employed and the method of application.

 

15.4.5.2   In addition, The ES will be required to undertake the acoustic dolphin monitoring, establish the dolphin exclusion zone during piling and dredging in the marine park and undertake underwater noise monitoring during piling activities.

 

15.5               Operational Impact Monitoring

 

15.5.1         Post construction monitoring is limited to monitoring landscaping to ensure the viability of the planting/replanting.  Site inspections shall be undertaken once every 2 months for the first year of operation.

 

 

15.6               EM&A Responsibilities

 

15.6.1         In respect of the design phase EM&A, the Consultant commissioned to undertake the Design and Construct contract will be required to designate an auditor(s) to undertake an environmental audit of the design of these measures in order to ensure that the recommendations of the EIA have been fully and properly specified.  The design audit shall be undertaken as and when the relevant design aspects are produced.  The Consultant shall use suitably qualified staff to undertake the audit requirements to the approval of the DEP and the PlanD/LPU as appropriate.

 

15.6.2         During the construction and operational phase of the project, an Environmental Specialist (ES) is to be employed by the Contractor.  He shall ensure the Contractor=s compliance with the project=s environmental performance requirements during construction and undertake the post construction EM&A works and his responsibilities will include field measurements, sampling, analysis of monitoring results, reporting and auditing.  The ES shall be approved by the ER and the Director of Environmental Protection (DEP) and shall be competent and shall have at least 7 years relevant environmental monitoring and audit experience on projects of a similar scale and nature.

 

15.6.3         The ES will require suitably qualified support staff (the Environmental Team, (ET)) to carrying out the EM&A programme.  Both the ES and members of the ET shall be independent and shall not be in any way connected to the Contractor=s company.  Due to the specialist nature of some of the EM&A works required for this project, the ET should comprise professionals proficient to undertake the tasks involved.  Thus, the ET should include personnel experienced in noise and dust mitigation, water quality monitoring, supervision of waste management, compensatory tree planting, underwater acoustic monitoring and dolphin spotting and supervision.

 

15.6.4         Accordingly, a Registered Landscape Architect, as defined by the Landscape Architect=s Registration Board, will be required on the ET to monitor and audit the landscaping installation works. Any archaeological EM&A as defined by the Marine Archaeological Investigation shall be undertaken by a suitably qualified person to the acceptability of the AMO.  

 


15.6.5         In addition to the ES, an Independent Checker (Environment) (IC(E)) shall advise the ER on environmental issues related to the project.  The role of the Checker shall be independent from the management of construction works, but the Checker shall be empowered to audit the environmental performance of the construction activities and operational mitigation.  The IC(E) shall have project management experience in addition to the requirements of the ES specified in Section 15.5.2 and the appointment of the IC(E) will be subject to the approval of the ER and the DEP.  The IC(E) may require specialist support staff in order to properly carry out his duties.

 

15.7               Reporting

 

15.7.1         Deliverables during the design phase will comprise a Design Audit Report at the end of the detailed design which will confirm that the requirements of the EIA have been fully taken into account in the project design.  Construction and operational reporting will be in the form of the baseline survey report and regular and summary EM&A Reports which should be prepared in accordance with the requirements of Annex 21 of the TMEIA.  It is recommended that EM&A Reports are issued monthly and bi-monthly for the construction and operational stages respectively.   Further details on the contents of these reports is provided in the EM&A Manual.

 

15.8               Implementation Schedules

 

15.8.1         The recommended mitigation measures specified in this EIA report have been summarised in the Environmental Mitigation Implementation Schedules provided in Appendix B for noise, water quality, waste, ecology, landscape and visual, cultural heritage, contaminated land and fuel spill risk.