Table 12.8       Implementation Schedule of Landscape and Visual Impact Measures

 

EIA Ref

EM&A Ref

Environmental Protection Measures*

Location / Timing

Implementation Agent

Implementation Stages **

Relevant Legislation & Guidelines

D

C

O

Construction Phase

10.74

9.10

Retaining existing trees and minimizing damage to vegetation by close coordination and on site alignment adjusted of rising main and gravity sewer pipelines.

 

All sites

Contractor

 

Ö

 

WBTC No. 14/2002

 

 

Careful and efficient transplanting of affected trees to temporary or final transplant location (the proposed tree to be transplanted is a semi-mature Macaranga tanarius and is located at the proposed Pumping Station P2 location).

 

All sites

Contractor

 

Ö

 

WBTC No. 14/2002

 

 

Short excavation and immediate backfilling sections upon completion of works to reduce active site area.

 

All sites

Contractor

 

Ö

 

 

 

 

Screening of site construction works by use of hoarding that is appropriate to its site.

 

All sites

Contractor

 

Ö

 

WBTC No. 19/2001

 

 

Conservation of topsoil for reuse.

 

All sites

Contractor

 

Ö

 

 

 

 

Night-time light source from marine fleets should be directed away from the residential units.

 

Outfall area.

Contractor

 

Ö

 

 

Operation Phase

10.75

9.12

Architectural finishes to proposed structures, which area sympathetic to the surrounding landscape

 

Pumping stations and STW

DSD

 

Ö

 

 

 

 

Soft landscape to proposed structures

Pumping stations and STW

DSD

 

Ö

Ö

WBTC No. 14/2002

 

 

Planting to reformed slope in-keeping with the surrounding landscape character

Reformed Slope behind STW

DSD

 

Ö

Ö

WBTC No. 17/2000 & 25/93

 

 

Appropriate finishes to reinstated areas of footpath in-keeping with existing finishes

All sites

DSD

 

Ö

Ö

WBTC No. 14/2002

 

 

Appropriate paint finishes to sections of exposed pipeline

All sites

DSD

 

Ö

Ö

 

*            All recommendations and requirements resulted during the course of EIA Process, including ACE and/or accepted public comment to the proposed project.

**            D=Design, C=Construction, O=Operation

N/A          Not applicable