5.                       WATER QUALITY

 

Introduction

 

5.1                   This section presents an assessment of the potential water quality impacts associated with the construction and operation phases of the proposed improvement works to San Tin Interchange.  The key environmental issue in respect of water quality impacts associated with the Project would be the proper control of construction site runoff and drainage during site formation and foundation works for the proposed slip roads.  Recommendations for mitigation measures have been made, where necessary, to reduce the identified water quality impacts to an acceptable level.  The project area would be located in-land and thus direct impacts on marine water quality would not arise.  Supports for the slip roads and Bridge A would not be located within the San Tin River nor the San Tin Eastern Main Drainage Channel.

 

Environmental Legislation and Standards

 

Water Pollution Control Ordinance (WPCO)

 

5.2                   The Water Pollution Control Ordinance (Cap. 358), in existence since 1980, is the major legislation relating to the protection and control of water quality in Hong Kong.  According to the Ordinance and its subsidiary legislation, Hong Kong waters are divided into ten water control zones (WCZ).  Corresponding statements of Water Quality Objectives (WQO) are stipulated for different water regimes (marine waters, inland waters, bathing beaches subzones, secondary contact recreation subzones and fish culture subzones) in the WCZ based on their beneficial uses.  The study area is located within the Deep Bay WCZ. 

 

5.3                   River water quality is ranked according to its compliance with the WQOs.  The annual compliance of the monthly water quality data with each of the water quality parameters is indicated by a percentage, with 100% compliance indicating that all 12 months’ data are within the WQO.  Details of the WQOs statement for the inland waters of the Deep Bay WCZ are listed in Table 5.1.

 

Table 5.1        Water Quality Objectives for Inland Waters

Parameters

Water Quality Objectives (WQOs)

Water Control Zones (WCZs) or sub-zones to which the WQOs apply

pH

6.5 – 8.5

Sub-zones of Deep Bay WCZ:

Yuen Long & Kam Tin sub-zones; Beas, Indus & Ganges sub-zones

6.0 – 9.0

Remaining parts of WCZs

Suspended solids (SS)

Annual median £ 20 mg/L

Sub-zones of Deep Bay WCZ:

Yuen Long & Kam Tin sub-zones; Beas, Indus & Ganges sub-zones

Annual median £ 25 mg/L

Remaining parts of WCZs

Dissolved oxygen (DO)

³ 4 mg/L

All WCZs

Chemical oxygen demand (COD)

£ 15 mg/L

Sub-zones of Deep Bay WCZ:

Yuen Long & Kam Tin (Upper) sub-zones; Beas, Indus & Ganges sub-zones

£ 30 mg/L

Remaining parts of WCZs

5-day biochemical oxygen demand (BOD)

£ 3 mg/L

Sub-zones of Deep Bay WCZ:

Yuen Long & Kam Tin (Upper) sub-zones; Beas, Indus & Ganges sub-zones

£ 5 mg/L

Remaining parts of WCZs

 

 

Technical Memorandum

 

5.4                   Besides setting the WQOs, the WPCO controls effluent discharging into the WCZs through a licensing system.  A Technical Memorandum (TM) on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters was issued under the WPCO which gives guidance on the permissible effluent discharges based on the type of receiving waters (foul sewers, storm water drains, inland and coastal waters). The limits control the physical, chemical and microbial quality of effluents.  Under the TM, effluents discharged into inland waters are subject to standards for particular volumes of discharge.  The discharge standard will vary with the use of downstream water.  The majority of the inland water bodies within the study area are used for pond fish culture, which are classified as Group C inland waters.  Any new effluent discharge during the construction phase would be required to comply with the terms and conditions of a discharge licence, issued by EPD, under the WPCO.

 

Practice Notes

 

5.5                   A practice note (PN) for professional persons was issued by the EPD to provide environmental guidelines for handling and disposal of construction site discharges.  The ProPECC PN 1/94 “Construction Site Drainage” provides good practice guidelines for dealing with various types of discharge from a construction site.  Practices outlined in the PN should be followed as far as possible during construction to minimize the water quality impact due to construction site drainage.

 

Baseline Conditions

 

5.6                   There is an existing streamcourse, the San Tin River, which runs north and to the immediate west of the line of the San Tin Eastern Main Drainage Channel (EMDC).  This river will be diverted under the EMDC project before the construction works commence for the slip roads. 

 

5.7                   River water quality data are not available for the San Tin River from the EPD routine river water quality monitoring programme.  The San Tin River drains agricultural, village and road areas.  Data available from the consultancy study for the Expansion of Kiosks and Other Facilities at Lok Ma Chau Boundary Crossing indicates that the quality of the river water is poor, with low dissolved oxygen, high BOD and high ammoniacal-nitrogen concentrations (Table 5.2).  Water quality was also measured in two inactive fishponds on the east side of the Lok Ma Chau Boundary Crossing (Figure 5.1). Water quality was generally good, with low nutrient levels.

 

Table 5.2      Water quality in watercourses and unmanaged ponds alongside Lok Ma Chau Boundary Crossing

Parameter

Location

Fishpond 1
(inactive)

Fishpond 2
(inactive)

Stream
W1

Stream W2
(Upstream)

Stream W2
(Downstream)

pH

9.2

9.0

7.4

7.6

7.6

Turbidity (NTU)

76.0

28.0

43.0

3.6

1.2

DO

13.0

13.0

0.5

9.5

8.5

BOD5

28

14

24

<2

2

SS

-

-

59

7

18

Ammonia as N

<0.01

<0.01

44.0

0.35

5.50

NO2 + NO3 as N

0.02

0.02

0.78

2.00

1.40

Total Inorganic N

0.02

0.02

45.0

2.40

6.9

Total Phosphorous

0.2

0.1

12.0

<0.1

0.4

E.Coli (cfu/100 ml)

60

150

-

-

-

Notes: 1) Date of sampling: January 1999

                                2) All values in mg/l unless otherwise indicated.

 

5.8                   The water quality in active fishponds is expected to be higher in nutrient levels than fishponds that have been inactive for a long time.  This is due to the addition of fish feed and waste discharges from fish, as shown by data collected for the Phase 1 Monitoring of Off-site Compensation Works at Mai Po (Compensation for Regulation of Shenzhen River, Stage II, Phase I works).

 

Water Sensitive Receivers

 

5.9                   There are no fish ponds within the Project site boundary.  The nearest fishponds are located adjacent to the intersection of Lok Ma Chau Road and Castle Peak Road – Chau Tau to the east of the proposed slip roads E and F, at a distance of approximately 140m from the site boundary (also refer to Section 8.12).  The location and extent of fish ponds in the Assessment Area is included in the habitat map presented in Figure 7.2.  An existing nullah located to the south of the San Tin Interchange and running north-west adjacent to San Sham Road is the closest water body to the site.  An existing nullah runs parallel to Castle Peak Road – Chau Tau, to the north of Slip Road B, and is located approximately 35m to the north of the eastern site boundary.  The location of these two nullahs is also presented in Figure 7.2.  The water quality was observed to be very poor in these nullahs during the terrestrial ecology surveys, resulting from untreated domestic and agricultural wastes, as well as run-off from open storage and industrial areas.

 

5.10               The section of the proposed slip roads north of Castle Peak Road connecting with the existing VHA would lie immediately adjacent to the future San Tin EMDC.  This drainage channel will be located on the western side of San Sham Road, and be aligned adjacent to San Sham Road from Castle Peak road to Shenzhen River.  The construction of the San Tin EMDC is scheduled to be completed in the fourth quarter 2006.

 

Assessment Methodology

 

5.11               The assessment area for the water quality impact assessment is defined by a distance of 500m from the project boundary. 

 

5.12               The water sensitive receivers that may be affected by the construction works for the road improvement works were identified.  Potential sources of water quality impact that may arise during the construction and operation phases of the Project were described.  This task included identifying pollutants from point discharges and non-point sources to surface run-off.  All the identified sources of potential water quality impact were then evaluated and their impact significance determined.  The need for mitigation measures to reduce any identified adverse impacts on water quality to acceptable levels was determined. 

 

Identification and Evaluation of Environmental Impacts

 

Construction Phase

 

5.13               Potential sources of water quality impact associated with the construction of the proposed road improvement works have been identified and include:

 

·          construction site runoff and drainage;

·          general construction activities; and

·          sewage effluent produced by on-site workforce.

 

Construction Runoff and Drainage

 

5.14               Runoff from the construction works areas during site clearance and site formation activities may contain increased loads of sediments, other suspended solids and contaminants.  Potential sources of pollution from site drainage include:

 

·          runoff and erosion from exposed soil surfaces, earth working areas and stockpiles;

·          release of grouting and cement materials with rain wash;

·          wash water from dust suppression sprays; and

·          fuel and lubricants from maintenance of construction vehicles and mechanical equipment.

 

5.15               Sediment laden runoff may carry pollutants (adsorbed onto the particle surfaces) into the nearby nullahs.  Associated effects which may arise include increased suspended solids concentrations in receiving waters and blockage of storm water drains.  The construction of the San Tin EMDC would be in progress during the site clearance and formation activities for the slip roads, and therefore the San Tin EMDC would not be regarded as a water sensitive receiver.

 

5.16               Mitigation measures should be implemented to control construction site runoff and drainage from the works areas, and to prevent runoff and drainage water with high levels of suspended solids from entering the nearby nullahs or local storm water drainage system.  With the implementation of adequate construction site drainage and provision of sediment removal facilities as described in Section 5.25, it is anticipated that unacceptable water quality impacts would not arise.

 

General Construction Activities

 

5.17               On-site construction activities may cause water pollution from the following:

 

·          uncontrolled discharge of debris and rubbish such as packaging, construction materials and refuse; and

·          spillages of liquids stored on-site, such as oil, diesel and solvents etc, are likely to result in water quality impacts if they enter the nearby nullahs or local storm water drainage system.

 

5.18               Good construction and site management practices should be observed, as detailed in Sections 5.26 & 5.27, to ensure that litter, fuels and solvents do not enter the surrounding nullahs or storm water drains.   

 

Sewage Effluents

 

5.19               Domestic sewage would be generated from the workforce during the construction phase. However, this temporary sewage can be adequately treated by interim sewage treatment facilities, such as portable chemical toilets, which can be installed within the construction site. It is unlikely that sewage generated from the site would have a significant water quality impact, provided that sewage is not discharged directly to the adjacent watercourse, and chemical toilets are used and properly maintained.

 

Cumulative Impacts

 

5.20               The identified concurrent projects which involve construction activities during the construction period of the road improvement works are:

 

·                East Rail Extension – Sheung Shui to Lok Ma Cha Spur Line

·                San Tin Eastern Main Drainage Channel

 

5.21               The construction works of the above two projects are scheduled to commence in the third quarter 2002 and fourth quarter 2002, respectively.  The excavation works for the San Tin EMDC would be completed before the commencement of construction activities for the Project, and therefore there is limited potential for cumulative water quality impacts to result from the construction activities of the EMDC project.  With the implementation of mitigation measures to control construction site runoff and drainage, potential impacts on water quality would be controlled to within the site boundary. 

 

5.22               The site formation and foundation works for the Spur Line would be completed before the commencement of construction activities for the Project.  There is very limited potential for cumulative impacts on water quality to result from the construction activities of the Spur Line as the works areas would not be located in close proximity to the project site boundary. 

 

Operation Phase

 

5.23               The only identified potential source of impact on water quality during the operation phase would be runoff from the road surfaces.  A surface water drainage system would be provided to collect the road runoff.  It is recommended that the HyD standard road gullies be installed along the drainage system to trap silt and grit in the first flush of runoff.  The road drainage system will facilitate drainage of runoff during rainstorms directly into the nullahs and thus prevent run-off entering any fishponds in the San Tin area.

 

Mitigation Measures

 

5.24               Proposed mitigation measures for containing and minimizing water quality impacts are summarised below.

 

Construction Phase

 

Construction run-off and Drainage

 

5.25               The site practices outlined in ProPECC PN 1/94 “Construction Site Drainage” should be followed as far as practicable in order to minimise surface runoff and the chance of erosion, and also to retain and reduce any suspended solids prior to discharge.  These practices include the following items :

 

·          Silt removal facilities such as silt traps or sedimentation facilities should be provided to remove silt particles from runoff to meet the requirements of the Technical Memorandum standard under the Water Pollution Control Ordinance.  The design of silt removal facilities should be based on the guidelines provided in ProPECC PN 1/94.  All drainage facilities and erosion and sediment control structures should be inspected monthly and maintained to ensure proper and efficient operation at all times and particularly during rainstorms. 

·          Careful programming of the works to minimise surface excavations for the road improvement works during the wet season.  If excavation of soil cannot be avoided during the wet season, exposed slope surfaces should be covered by a tarpaulin or other means.  Other measures that need to be implemented before, during, and after rainstorms are summarized in ProPECC PN 1/94.

·          Exposed soil surfaces should be protected by paving or fill material as soon as possible to reduce the potential of soil erosion.

·          Open stockpiles of construction materials or construction wastes on-site of more than 50m3 should be covered with tarpaulin or similar fabric during rainstorms.  These materials should not be placed near water courses.

·          A Drainage Management Plan (DMP) should be prepared by the Contractor and submitted to EPD before the commencement of any construction works to detail the procedures for control of construction site runoff.  The DMP should at least cover the construction works areas for slip roads E and F and for Bridge A, and the local widening of the existing Castle Peak Road.  No site run-off nor drainage should enter fishponds.

 

General Construction Activities

 

5.26               Debris and refuse generated on-site should be collected, handled and disposed of properly to avoid entering the nearby nullahs or local stormwater drainage system.  Stockpiles of cement and other construction materials should be kept covered when not being used. 

 

5.27               Oils and fuels should only be used and stored in designated areas which have pollution prevention facilities.  All fuel tanks and storage areas should be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank.  The bund should be drained of rainwater after a rain event.

 

Sewage from Construction Workforce

 

5.28               Temporary sanitary facilities, such as portable chemical toilets, should be employed on-site.  A licensed contractor would be responsible for appropriate disposal and maintenance of these facilities.

 

Operation Phase

 

5.29               It is recommended that the HyD standard road gullies be installed along the surface water drainage system for the slip roads to trap any silt and grit in the first flush of runoff. 

 

Residual Environmental Impact

 

5.30               With the full implementation of the recommended mitigation measures for the construction and operation phases of the proposed Project, no unacceptable residual impacts on water quality are anticipated.  It is recommended that regular audit of the implementation of the recommended mitigation measures be carried out during the construction phase.

 

 

 

 

 

 

 

 

Environmental Monitoring and Audit

 

5.31               There are no fish ponds located within close proximity of the site limit.  In addition to auditing the implementation of the recommended mitigation measures, a specific water quality EM&A programme is recommended during the site clearance and formation of the at-grade road sections for slip roads E and F and for Bridge A and the local widening of the existing Castle Peak Road, in view of these construction works being located in the vicinity of the San Tin River.  Details of the EM&A are provided in a stand-alone EM&A Manual.