7                     Ecology

7.1                 Introduction

7.1.1           The ecological impact assessment in the EIA Report identified that the key issues in terms of ecology would be potential direct impacts to moderate ecological value rivers as a result of drainage improvement works. Other identified impacts included potential increases in sedimentation during construction phase affecting aquatic communities downstream of works areas, and increased disturbance to wildlife during the construction phase resulting from noisy construction phase activities and increased human activity.

7.1.2           Measures to minimise and compensate for identified ecological impacts are recommended in the EIA Report. These measures include the design of Sai Kung and Ho Chung River drainage improvement works to incorporate ‘ecologically friendly’ features, and extensive compensatory planting along the banks of the new channels to compensate for the loss of riparian vegetation. Further measures to control potential increases in sedimentation, minimise construction phase disturbance and other identified impacts were also recommended. Ecological mitigation measures and monitoring requirements are detailed in the following sections.

 

7.2                 Ecological Mitigation Measures and Monitoring

Ecological Mitigation Measures

7.2.1           The most substantial identified impacts would be expected to occur at Sai Kung and Ho Chung Rivers, where extensive modification of the existing river channel would be undertaken to improve drainage capacity. The design of the improved drainage channels has been considered to minimise and compensate for these impacts, as described below:

- Sai Kung River

For the Sai Kung River, a short section of the river (approximately 150m) would be deepened and slightly widened. The base of the improved channel would be lined with natural substrates (e.g., gravel, cobbles and boulders). To re-create existing conditions as closely as possible, substrates found in the existing river section would be used to line the new channel. Substrates lining the improved channel would be arranged to re-create the existing riffle-pool sequence found in the river. The banks of the improved channel would be lined with rock-filled gabion to improve stability. Pits would be provided in the gabion to allow planting of herbaceous riparian vegetation.

- Ho Chung River

Approximately 650m of the Ho Chung River would be subject to drainage improvement works. Along most of the affected river section, the existing riverbed and substrates would be retained, and works would be limited to widening the river along the southern bank. Newly widened sections of riverbed would be lined with natural substrates (e.g., cobbles and boulders), with the size and arrangement of these substrates selected to complement adjacent areas of the existing riverbed. The substrates would be sourced as far as practicable from materials excavated during the river widening. The majority of the southern bank of the widened channel would be lined with rock-filled gabion. Pits would be provided in the gabion to allow planting of herbaceous riparian vegetation.

7.2.2           The excavation works for channels should be carried out in the dry condition where possible, with construction carried out by land-based plant. Excavation works should be restricted to an enclosed dry section of the river, with containment measures such as bunds and barriers used within the river to minimise the impacts upon the downstream water body. Site runoff should be directed towards regularly cleaned and maintained silt traps and oil/grease separators to minimise the risk of sedimentation and pollution of river water. The silt and oil/grease separators should be appropriately designed for the local drainage and ground conditions. To minimise leakage and loss of sediments during excavation in narrow channels, tightly sealed closed grab excavators should be deployed where material to be handled is wet.

7.2.3           Noise mitigation measures including the use of quiet construction plant and temporary noise barriers should be implemented to minimise disturbance to habitats adjacent to the works areas. In particular, measures such as noise barriers should be used to minimise disturbance to the bat roost identified close to the Pak Kong works area.

7.2.4           The proposed drainage improvement works would unavoidably impact several individuals of the rare tree species Ehretia acuminata recorded at Ho Chung. It is recommended that the trees and saplings be transplanted to another area within the Ho Chung site boundary before the commencement of construction phase activities (Figure 7.1 gives a suggested location for the receptor site. The exact location for transplantation would be determined by the Landscape Architect/Others who conduct the transplantation).. Fencing would be erected around the transplanted trees/seedlings to minimise potential construction phase disturbance.

7.2.5           It is also recommended that additional measures are undertaken to mitigate for impacts to E. acuminata: seeds from the existing trees should be collected and propagated. The seeds should be collected from mature fruits (the fruiting period of E. acuminata is from May to September) prior to transplantation, and germinated in containers under suitable conditions. Following germination and growth, the seedlings should be planted at suitable locations within the Ho Chung Works Area. The survival of newly planted seedlings should be monitored. Seed collection, propagation, planting and monitoring of E. acuminata should be undertaken by a suitably qualified botanist/horticulturalist appointed by the Project Proponent. A detailed methodology for these works should be formulated during the detailed design stage of the Project, in consultation with AFCD.

7.2.6           Potential operational phase activities would be limited to regular channel maintenance such as de-silting. Impacts to aquatic communities resulting from these activities are expected to be minor. Nevertheless, the following measures are recommended to minimise potential impacts resulting from operational phase activities:

·         To minimise sedimentation, de-silting should be limited to the dry season (November-March).

·         The implementation of de-silting and other activities that could disturb aquatic fauna should be phased to ensure some areas of relatively undisturbed habitat remain available for resident aquatic fauna at all times.

·         Waste material produced during de-silting should be disposed of in a timely and appropriate manner.

7.2.7           Standard good site practice measures should be implemented throughout the construction phase. The measures should include:

·         Placement of equipment or stockpile in designated works areas and access routes selected on existing disturbed land to minimise disturbance to natural or moderate-high ecological value habitats.

·         Construction activities should be restricted to work areas that should be clearly demarcated. The work areas should be reinstated after completion of the works.

·         Waste skips should be provided to collect general refuse and construction wastes. The wastes should be disposed of timely and properly off-site.

·         General drainage arrangements should include sediment and oil traps to collect and control construction site run-off.

·         Open burning on works sites is illegal, and should be strictly prohibited.

7.2.8           The improved Ho Chung River is expected to provide a suitable habitat for fish communities previously recorded from the river. To further increase the value of the River for fish communities, it is recommended that small fish ladders are constructed over the weirs along the river channel. Existing weirs within the river currently impede the movement of fish between upstream and downstream sections of the river. The fish ladders would facilitate movement past these obstacles, extending the range of fish communities in both upstream and downstream areas. The detailed design of the ladders would be submitted to AFCD for comment and approval before finalisation.

7.2.9           The banks of the newly created channels would be extensively planted with trees and other vegetation to provide compensation for unavoidable tree-felling and loss of riparian vegetation resulting from the proposed works. Where possible, compensatory planting should make use of native plant species with flowers/fruits attractive to wildlife.

Environmental Monitoring and Audit Requirements

7.2.10       The proper implementation of mitigation measures recommended in Sections 7.2.1-7.2.9 should be audited.

7.2.11       A specific monitoring programme of channels constructed to replace Sai Kung and Ho Chung Rivers shall be carried out by a suitably qualified ecologist(s) (with at least 7 years’ experience in ecological monitoring) appointed by the Project Proponent or ER. The programme should provide data on the re-establishment of aquatic/riparian communities in the channels, and allow an assessment of the relative success of mitigation measures to be made. Baseline data should be collected several months before the commencement of the construction phase, with monitoring conducted 3 times a year during the construction phase, and 3 times a year for 3 years after the completion of works. Data collected should include abiotic (e.g., water quality, sediment characteristics) and biotic (e.g., avifauna, macroinvertebrate and fish populations, aquatic, emergent and riparian vegetation) parameters. Reports on the findings of each monitoring trip should be submitted to AFCD for review/discussion. A final report summarising the results of monitoring over 3 years should be prepared to serve as a reference for future projects of this kind.

7.2.1           The newly constructed Sai Kung and Ho Chung River Channels are expected to provide a similar habitat to the rivers they would replace. It is therefore anticipated that wildlife found in the existing rivers would successfully re-colonise the new channels. However, if the post-construction phase monitoring demonstrates that re-colonisation is unsuccessful the following contingency plan should be implemented:

·         Baseline data collected prior to the construction phase should be compared with post-construction phase data. Any substantial differences in habitat characteristics (e.g., water quality, aquatic/emergent vegetation) should be noted.

·         The potential cause of differences between pre- and post-construction phase habitat characteristics (e.g., changes in water depth, sediment characteristics) should be identified.

·         Measures to further rehabilitate the habitat characteristics of river channels should be implemented (e.g., minor re-profiling of riverbed, planting of emergent/aquatic vegetation, increasing heterogeneity of substratum).

·         Further monitoring of abiotic and biotic parameters should be conducted to determine the relative success of the contingency habitat rehabilitation measures.

7.2.2           Following transplantation of the two Ehretia acuminata trees and six seedlings, and the planting of seedlings germinated from seeds collected from the two trees, regular monitoring of the trees and seedlings should be conducted to check on the health and condition of the plants. Monitoring should cover the 12-month period following transplantation and planting, and be conducted at least twice a month for the first four months after transplantation/planting, and once a month for the remaining eight months. Monitoring should be conducted by a suitably qualified botanist/horticulturalist appointed by the Project Proponent.