CONTENTS
1.1 General
1.3 Purpose and Approach of the EIA Study
1.4 Structure of this EIA Study Report
2.2 Project History and Site Selection
2.3 Project Characteristics and Site Location
2.4 Nearby Projects
2.5 Likely Future Environmental Conditions Without the Project
3 Air Quality impact assessment
3.1 Introduction
3.2 Relevant Guidelines, Standards & Legislation
3.3 Baseline Conditions and Air Sensitive Receivers
3.4 Construction Dust Impact Assessment
3.6 Environmental Monitoring and Audit Requirements
3.7 Conclusions and Recommendations
4.1 Introduction
4.2 Relevant Guidelines, Standards & Legislation
4.4 Noise Environment at Peng Chau
4.5 Construction Noise Impact Assessment
4.6 Operational Noise Impact Assessment
4.7 Environmental Monitoring and Audit Requirements
4.8 Conclusions and Recommendations
4.9 References
5.1 Introduction
5.3 Baseline Conditions & Sensitive Receivers
5.5 Waste Types
5.6 Impact Assessment and Evaluation
5.7 Summary of Waste Materials Generated
5.8 Impact Mitigation & Residual Impact Assessment
5.9 Environmental Monitoring and Audit Requirements
5.10 Conclusions and Recommendations
5.11 References
6 water quality impact assessment
6.1 Introduction
6.3 Regulations, Standards and Guidelines
6.5 Assessment Approach & Methodology
6.6 Impact Assessment & Evaluation
6.7 Impact Mitigation & Residual Impact Assessment
6.8 Environmental Monitoring & Audit
6.9 Conclusions and Recommendations
6.10 References
7 Ecology
7.1 Introduction
7.3 Regulations, Standards and Guidelines
7.5 Impact Assessment & Evaluation
7.6 Impact Mitigation & Residual Impact Assessment
7.7 Environmental Monitoring & Audit Requirements
7.8 Conclusions & Recommendations
7.9 References
8.1 Introduction
8.3 Applicable Regulations, Standards and Guidelines
8.6 Impact Assessment & Evaluation
8.7 Impact Mitigation & Residual Impact Assessment
8.8 Environmental Monitoring & Audit Requirements
8.9 Conclusions & Recommendations
8.10 References
9 CULTURAL HERITAGE IMPACT ASSESSMENT
9.1 Introduction
9.3 Regulations, Standards and Guideline
9.6 Impact Assessment and Evaluation
9.7 Impact Mitigation & Residual Impact Assessment
9.8 Environmental Monitoring & Audit
9.9 Conclusions & Recommendations
9.10 References
10 Implementation Schedule of Recommended Mitigation Measures
10.1 Introduction
11 summary Conclusion & recommendations
11.1 Summary Conclusion of Technical Assessments
11.2 Key Recommendations
11.3 Summary of Environmental Outcomes
LIST OF FIGURES
Figure 2.1 Peng Chau Helipad Siting Options
Figure 2.2 Peng Chau Helipad – Site Location
Figure 3.1 Proposed Helipad Location and Environs
Figure 4.1 Representative Noise Sensitive Receiver Locations
Figure 4.2 Geographical Centres of Construction Activities
Figure 4.3 Approach and Departure Area and Surface Profile
Figure 4.4a Index Plan for Cross Sections between NSR and Helipad
Figure 4.4b Index Plan for Cross Sections between NSR and Flight Path
Figure 4.5a Cross Sectional View for NSR to the Helipad (NSR1, NSR2, NSR3)
Figure 4.5b Cross Sectional View for NSR to the Helipad (NSR4, NSR5, NSR6)
Figure 4.5c Cross Sectional View for NSR to Flight Path (NSR3, NSR4)
Figure 4.5d Cross Sectional View for NSR to Flight Path (NSR5, NSR6)
Figure 4.6 Illustration of Affected Area by Helicopter Noise
Figure 5.1 Cross Section of Helipad Footprint
Figure 5.2 EVA Footprint – Cross Section A
Figure 5.3 Helipad Footprint – Cross Section B and C
Figure 6.1 Frequency
and Direction of Current Velocity at Peng Chau
Figure 6.2 Cumulative
Spatial Extent of Construction Phase Mixing Zone
Figure 7.1 Ecology Assessment Area and Sensitive Receivers
Figure 7.2 Habitat Map of the Peng Chau Study Area
Figure 7.3 Habitat Photographs
Figure 8.1 Fisheries Areas of Peng Chau
Figure 9.1 Marine Geophysical / Marine Archaeology Survey Area and Sea Floor Features of Note
LIST OF TABLES
Table 2.1 Summary Matrix for Evaluation of Helipad Site Options & Alternatives
Table 2.2 Summary of Peng Chau Helipad Construction Programme
Table 3.1 Hong Kong Air Quality Objectives
Table 3.2 Annual Average Pollution Concentrations Recorded in Tap Mun (Year 2002)
Table 4.1 Recommended Construction Noise Levels (Non-restricted Hours)
Table 4.2 Area Sensitivity Rating Criteria
Table 4.3 Acceptable Noise Levels in Leq(5 min) dB(A)
Table 4.4 Helicopter Noise Standards for Planning Purposes
Table 4.5 Location of NSR Assessment Points in Peng Chau
Table 4.6 Noise Monitoring Results at Sea Crest Villa
Table 4.7 Powered Mechanical Equipment to be used for Construction of Helipad
Table 4.8 Construction Activities
Table 4.9 Predicted Construction Noise Levels Leq(30 min) dB(A) - Unmitigated
Table 4.10 Sound Power Levels for the Silenced Equipment
Table 4.11 Predicted Construction Noise Levels Leq(30 min) dB(A) – Mitigated
Table 4.12 Predicted Cumulative Construction Noise Levels Leq(30 min) dB(A) at NSR1
Table 4.13 Helicopter Noise Data – Airborne Helicopter with Lateral Movements
Table 4.14 Measured Lmax Noise Level of GFS Helicopters – Without Lateral Movements
Table 4.15 Helicopter Use for Peng Chau ‘Casevac’ Operations during years 2000 – 2004
Table 4.16 Worst-case Helicopter Noise Levels at NSRs during Helicopter Manoeuvring
Table 4.17 Worst-case Helicopter Approach / Departure Noise Levels at NSRs
Table 5.1 Material Import Requirements
Table 5.2 Summary of Construction Phase Waste Generation
Table 6.1 Relevant Water Quality Objectives for Southern WCZ
Table 6.2 Summary of Water Quality at ‘SM10’ between 1997 and 2001
Figure 6.1 Frequency and Direction of Current Velocity at Peng Chau
Table 6.3 Predicted SS Elevation
Table 7.1 Representative Species in the Peng Chau Marine Benthic Community (CityU, 2002)
Table 7.2 Univariate Statistics for S. Peng Chau & Similar HKSAR Survey Areas (CityU, 2002)
Table 7.3 Habitat Types in the Assessment Area
Table 7.4 Categorisation of Benthic Cover and Substrate
Table 7.5 Rank Abundance of Pak Wan Sub-tidal Benthic Community
Table 7.6 Inter-tidal Survey Data for Pak Wan (BMT, October 2002)
Table 7.7 Butterfly Survey Data for Pak Wan, Peng Chau (BMT, 2002 & 2003)
Table 7.8 Bird Survey Data for Northwest Peng Chau (BMT, 2002 & 2003)
Table 7.9 Ecological Evaluation of the Sub-tidal Habitat
Table 7.10 Ecological Evaluation of the Sandy Shore (Beach) habitat
Table 7.11 Ecological Evaluation of the Hard Shore habitat
Table 7.12 Ecological Evaluation of the Coastal Scrub habitat
Table 7.13 Ecological Evaluation of the Secondary Woodland habitat
Table 7.14 Ecological Evaluation of the Developed / Disturbed Area
Table 7.15 Summary of Ecological Impacts
Table 8.1 Top Ten Ranked Adult Fish / Crustacean Families (from AFCD, 2003)
Table 8.2 Top Adult Fish / Crustacean Species by Weight from Peng Chau (AFCD, 1998)
Table 8.3 Production of Peng Chau Fisheries Areas (AFCD, 1998)
Table 8.4 Production Range for Fishing Methods at Peng Chau (AFCD, 2003)
Table 8.5 Commercial Value of Top Adult Fish Species around Peng Chau (AFCD, 1998; BMT, 2003).
Table 8.6 Common Fish Catch species at Northwest Peng Chau (BMT, 2003)
Table 10.1 Air Quality – Implementation Schedule of Recommended Mitigation Measures
Table 10.2 Noise – Implementation Schedule of Recommended Mitigation Measures
Table 10.3 Waste Management – Implementation Schedule of Recommended Mitigation Measures
Table 10.4 Water Quality – Implementation Schedule of Recommended Mitigation Measures
Table 10.5 Ecology – Implementation Schedule of Recommended Mitigation Measures
Table 10.6 Fisheries – Implementation Schedule of Recommended Mitigation Measures
LIST OF
Appendices
Appendix 2.1 Visual Illustrations
Appendix 2.2 Construction Schedule
Appendix 2.3 Construction Schedule for DSD’s Sewage Treatment Works Upgrade
Appendix 4.1 Construction Equipment Inventory
Appendix 4.2 Construction Noise Calculation – Unmitigated
Appendix 4.3 Construction Noise Calculation – Mitigated
Appendix 4.4 Cumulative Construction Noise Calculation
Appendix 4.5 Helicopter Noise Measurement Points and
Noise Levels
Appendix 4.6 Helicopter Noise Survey Report
Appendix 4.7 Helicopter Noise Calculations
Appendix 5.1 Historical Sediment Quality Monitoring Locations & Results at Peng Chau
Appendix 5.2 Sediment Classification Flow Chart
Appendix 5.3 Actual Sediment Sampling Locations within Helipad Footprint
Appendix 7.1 Rapid Ecological Assessment (REA) Evaluation Framework
Appendix 7.2 Inter-tidal Survey Data for Pak Wan (BMT, April 2003)
Appendix 7.3 Marine Habitat Loss / Disturbance Calculations
(i)
The overall acceptability of
any adverse environmental consequences that are likely to arise as a result of
the proposed Project;
(ii)
The conditions and
requirements for the detailed design, construction and operation of the
proposed Project to mitigate against adverse environmental consequences
wherever practicable; and
(iii)
The acceptability of
residual impacts after implementation of proposed mitigation measures.
(i)
Describe the proposed Project
and associated works together with the requirements for carrying out the
proposed Project;
(ii)
Consider alternative design and construction method(s) for the proposed
Project and to compare the environmental benefits and disadvantages of each of
the method(s) and design in selecting a preferred one;
(iii)
Identify and describe elements of community and environment likely to
be affected by the proposed Project and/or likely to cause adverse impacts to
the proposed Project, including natural and man-made environment;
(iv)
Identify and quantify emission sources and determine the significance
of impacts on sensitive receivers and potential affected uses;
(v)
Identify and quantify potential losses or damage to aquatic organism
and natural habitats and to propose measures to mitigate these impacts;
(vi)
Identify and quantify potential losses or damage to flora, fauna and
natural habitats and to propose measures to mitigate these impacts;
(vii)
Propose the provision of mitigation measures so as to minimize
pollution, environmental disturbance and nuisance during construction and
operation of the proposed Project;
(viii) Identify, predict
and evaluate the residual (i.e. after practicable mitigation) environmental
impacts and the cumulative effects expected to arise during the construction
and operation phases of the proposed Project in relation to the sensitive
receivers and potential affected uses;
(ix)
Identify, assess and specify methods, measures and standards, to be
included in the detailed design, construction and operation of the proposed
Project which are necessary to mitigate these environmental impacts and
reducing them to acceptable levels;
(x)
Investigate the extent of the secondary environmental impacts that may
arise from the proposed mitigation measures, and to identify the constraints
associated with the mitigation measures recommended in the EIA study as well as
the provision of any necessary modification;
(xi)
Design and specify environmental monitoring and audit requirements, if
required, to ensure the implementation and the effectiveness of the environmental
protection and pollution control measures adopted.
· Section 2 – Project Description
· Section 3 – Air Quality Assessment
· Section 4 – Noise Assessment
· Section 5 – Waste Management Assessment
· Section 6 – Water Quality Assessment
· Section 7 – Ecological Assessment
· Section 8 – Fisheries Assessment
· Section 9 – Cultural Heritage Assessment
· Section 10 – Implementation Schedule of Recommended Mitigation Measures
· Section 11 – Summary Conclusion & Recommendations.
a) The design and the location should be such that downwind operations are avoided and crosswind operations are kept to minimum to maximise helicopter manoeuvrability and operational safety. It should have two approach surfaces, separated by at least 150 degrees (i.e., a minimum flight path angle of 150 degrees).
b) The site should be conveniently situated as regards ground transport access mainly for emergency service (e.g. ambulance, fire engines) and adequate vehicle parking facilities.
c) The ambient noise level should be considered near noise sensitive receivers, and especially in relation to areas below the helicopter approach / departure path(s). This means that the helicopter flight path should be situated away from residential areas as far as is practicable, and for this reason the flight path for the proposed Peng Chau Helipad will approach and depart from the proposed helipad across the sea.
d) Ground conditions beneath the take-off climb and approach surfaces should permit safe landings in the event of engine failure or forced landings during which injury to persons on the ground and damage to property is minimized.
e) Consider, and assess with flight tests if necessary, the potential for and effects of eddies and turbulence that may be caused by any large structures close to the proposed helipad.
f) Consider the presence of high terrain or other obstacles, especially power lines, in the vicinity of the proposed site that may pose a potential hazard.
·
Helipad location and EVA link alignment;
·
Project Design and construction methods; and
·
Helicopter approach and departure paths.
·
The dredge and reclaim method would
require dredging of marine sediment to a suitable depth to allow construction
of a stable foundation, followed by deposition of filling materials up to the
required platform level.
·
Small
diameter pre-bored piling method involves sinking a
casing through the substrate and removing the material within. Concrete is then poured into the casing to
form the pile. A platform structure is then constructed on top of the piles.
·
Percussive piling method involves
driving steel piles into the bedrock. As the piles are driven through to the
bedrock, sediments are laterally displaced without the need for dredging or
excavation. A platform is constructed similarly as for the pre-bored piling
method.
· Time frame – site availability and the speed of construction was raised as important factors due to the fact the helipad is for emergency casualty evacuation.
· Direct ground access – given the inconvenience of the existing helipad, proximity to and availability of direct and uninterrupted access to the Peng Chau Clinic is another issue of key concern.
· Widening the footpath to 4.5m wide to cater for the need of the EVA would require slope cutting some 3 metres into the natural hillside along the 150m long EVA. Assuming that the slope faces along the EVA are very stable rock and can be formed vertically to ~3m height, there would be a loss of at least 500m2 of natural vegetation. There would also be a need to form a vertical strip of engineered slope some 3m high and 150m long across the middle of the hillside parallel to the coastline.
· The elevation of the footpath is at approximately 14mPD at its closest point to the proposed helipad. The helipad would be built to a final elevation of 5.15 mPD. In order to link up the EVA with the helipad to match the level difference while satisfying the maximum allowable gradient for use of the emergency vehicles, the length of the EVA has to be extended and the helipad would need to be located further offshore. Both requirements would increase the scale of the project and associated environmental impact potential.
· The elevation of the helipad and EVA have been lowered as far as practicable in order to minimize their footprint, and hence the disturbance to the affected coastal waters.
· The sea-facing sloping boulder wall has been designed to a steeper gradient, resulting in a reduction in the size of the foundation.
· The construction sequence shall be optimised to avoid cumulative construction noise effects with works for the proposed upgrading works of the Peng Chau Sewage Treatment Works.
Table 2.1 Summary Matrix for Evaluation of Helipad Site Options &
Alternatives
Option / Alternative |
Location
* |
Key
Environmental Benefit(s) |
Key
Environmental Dis-benefit(s) |
Other
Key Considerations (e.g., safety
& access) |
Conclusion |
A1 |
Pak
Wan – marine EVA |
· No helicopter manoeuvring noise impact during any
operations. · No helicopter flight path noise impacts under normal
operations.^ |
· Helicopter flight path noise impact from use of ‘Super Puma’ type
helicopter. |
· Easy access from Clinic. · No flight safety concerns. |
Residual flight path noise
impact from Super Puma, but no helicopter noise impact under normal
operations. |
A2 |
Pak
Wan – land EVA |
· No helicopter flight path noise impacts under normal
operations. |
· Potential ecological impact
from necessary slope works. · Manoeuvring noise impact from both helicopter types and flight path noise from ‘Super Puma’. |
· Easy access from Clinic,
although steep slopes to navigate to helipad. · No flight safety concerns. |
Potential ecology impact from
necessary EVA construction / slope works, and residual manoeuvring noise impacts for both helicopter
types. |
B1 |
Pei
Lei |
· Minimal construction works. |
· Potential impacts on hard
corals from construction works. · Helicopter flight path and manoeuvring
noise impact. |
· Easy access from Clinic. · No flight safety concerns. |
Potential adverse impacts on
hard corals, and likely residual helicopter noise impact under normal
operations. |
B2 |
Pei
Lei Southwest |
· Minimal construction works. |
· Potential impacts on hard
corals from construction works and shading effect of EVA & Helipad. · Helicopter flight path and manoeuvring
noise impact. |
· Easy access from Clinic. · No flight safety concerns. |
Potential adverse impacts on
hard corals, and likely residual helicopter noise impact under normal
operations. |
C |
Kam
Peng Estate |
· No significant construction
phase impacts (land already formed). |
· Significant helicopter flight path and manoeuvring noise impact on nearby residences. |
· Best access from Clinic. · Helicopter flight safety
concerns due to proximity to built-up area. |
No construction phase concerns,
but likely significant residual helicopter noise impacts under normal operations.
Unacceptable flight safety concerns. |
D |
Tai
Lei South |
· Minimal construction works. |
· Potential impacts on hard
corals from construction works. · Helicopter flight path and manoeuvring
noise impact. |
· Easy access from Clinic. · No flight safety concerns. |
Potential adverse impacts on
hard corals, and residual helicopter noise impact under normal operations. |
E |
Pak
Wan |
· No significant construction
phase impacts. |
· Significant helicopter flight path and manoeuvring noise impacts on nearby residences. |
· Easy access from Clinic. · Some flight safety concern due
to proximity of Sea Crest Villa. |
Likely significant residual
helicopter noise impacts under normal operations, and flight safety concerns. |
F |
Pak Wan Reclamation (Open Space) |
· No significant construction
phase impacts (land already formed). |
· Significant helicopter flight path and manoeuvring noise impact on nearby residences. |
· Best access from Clinic. · Helicopter flight safety
concerns due to proximity to built-up area. |
Likely
significant residual helicopter noise impacts under normal operations.
Unacceptable flight safety concerns. |
G |
Works Area of Highways Department on
Tai Lei |
· No significant construction
phase impacts (land already formed). |
· Helicopter flight path and manoeuvring
noise impact. |
· Easy access from Clinic. · Need to reprovision LPG storage
/ handling area, otherwise no flight safety concerns. |
Likely significant residual
helicopter noise impacts under normal operations. |
H |
Existing Small Pier on Tai Lei |
· No significant construction
phase impacts. |
· Helicopter flight path and manoeuvring
noise impact. |
· Easy access from Clinic. · Need to reprovision LPG storage
/ handling area, otherwise no flight safety concerns. |
Likely significant residual
helicopter noise impacts under normal operations. |
I |
Pak Wan (EVA East Extension) |
· No helicopter manoeuvring or flight path noise impact. |
· Extended EVA will encroach into
zoned “Coastal Protection Area” (CPA). |
· Easy access from Clinic. · No flight safety concerns. |
The extended EVA on to the
‘CPA’ zone would create a significant adverse landscape impact. |
Notes: * Figure 2.1 refers.
^ Normal operation refers to the use of EC155 B1 type helicopter.
· Approximately 14,000m3 of fine to coarse marine sand will need to be dredged.
· The EVA link will be about 150 metres long and 4.5 metres wide.
· The helipad will have a diameter of 25 metres.
· The EVA link and helipad surfaces will be formed to a height of approximately +5.0 mPD.
· Wave deflectors will be installed around the helipad to enhance operational safety.
· An off-site works area (including site office) to be located on existing vacant land immediately south of Sea Crest Villa that will be required for about 2 years, from December 2005. No off-site pre-casting works are anticipated.
Table 2.2 Summary of Peng Chau Helipad Construction Programme
Construction Activity |
Construction Period |
Site Clearance |
Dec 2005 – Jan 2006 |
Reclamation |
Feb 2006 – Sept 2006 |
Construction of Helipad |
Jan 2006 – Nov 2006 |
Construction of EVA |
Jul 2006 – Nov 2006 |
· Carpet Grass (Anoxopus compressus): 5 g/m2
· Bermuda Grass (Cynodon dactylon): 10 g/m2
· Bahia Grass (Paspalum notatum): 10 g/m2
· Mulch: 200 g/m2
· Fertilizer (NPK 15:15:15): 100 g/m2
Table 3.1 Hong Kong Air Quality Objectives
|
Concentration (mg/m3)(1) Averaging Time |
||||
Pollutant |
1 Hour(2) |
8 Hour(3) |
24 Hours(3) |
3 Months(4) |
1 Year(4) |
Sulphur Dioxide SO2 |
800 |
- |
350 |
- |
80 |
Total Suspended Particulates (TSP) |
- |
- |
260 |
- |
80 |
Respirable Suspended Particulates (RSP)(5) |
- |
- |
180 |
- |
55 |
Nitrogen Dioxide NO2 |
300 |
- |
150 |
- |
80 |
Carbon Monoxide CO |
30000 |
10000 |
- |
- |
- |
Photochemical Oxidants (as ozone(6)) |
240 |
- |
- |
- |
- |
Lead |
- |
- |
- |
1.5 |
- |
Notes:
(1) Measured at 298 K and 101.325 kPa (one
atmosphere).
(2) Not to be exceeded more than three times per
year.
(3) Not to be exceeded more than once per year.
(4) Arithmetic means.
(5) Respirable suspended particulates means
suspended particles in air with a nominal aerodynamic diameter of 10
micrometers or less.
(6) Photochemical oxidants are determined by
measurement of ozone only.
(a) Site formation;
(b) Reclamation;
(c) Demolition of a building;
(d) Work carried out in any part of a tunnel that
is within 100 m of any exit to the open air;
(e) Construction of the foundation of a building;
(f) Construction of the superstructure of a
building; or
(g) Road construction work,
(a) Renovation carried out on the outer surface of
the external wall or the upper surface of the roof of a building;
(b) Road opening or resurfacing work;
(c) Slope stabilization work; or
(d) Any work involving any of the following
activities:
· Stockpiling of dusty materials;
· Loading, unloading or transfer of dusty materials;
· Transfer of dusty materials using a belt conveyor system;
· Use of vehicles;
· Pneumatic or power-driven drilling, cutting and polishing;
· Debris handling;
· Excavation or earth moving;
· Concrete production;
· Site clearance; or
· Blasting.
Table 3.2 Annual Average
Pollution Concentrations Recorded in Tap Mun (Year 2002)
Pollutants
Monitored |
Annual
Average in micrograms per cubic metre |
Respirable Suspended Particulates
(RSP) |
39 |
Sulphur Dioxide (SO2) |
11 |
Nitrogen Dioxide (NO2) |
13 |
Carbon Monoxide (CO) |
688 |
Ozone (O3) |
63 |
Notes:
1. All
concentrations are measured at 298K (25°C) and 101.325KPa (one atmosphere)
2.
Data of the Tap Mun Monitoring Station are extracted from “Air Quality in Hong Kong 2002”, published by EPD
· The working area for site clearance adjacent to Sea Crest Villa shall be sprayed with water or a dust suppression chemical immediately before, during and immediately after the operation so as to maintain the entire surface wet.
· Restricting heights from which materials are dropped, as far as practicable to minimise the fugitive dust arising from unloading/loading.
· For reclamation works, if a stockpile of dusty materials is more than 1.2 m high and within 50m of Peng Lei Road or the Pak Wan footpath, the stockpile shall be properly treated and sealed with latex, vinyl, bitumen or other suitable surface stabilizer.
· Immediately before leaving a construction site, every vehicle shall be washed to remove any dusty materials from its body and wheels.
· All spraying of materials and surfaces should avoid excessive water usage.
· Where a vehicle leaving a construction site is carrying a load of dusty materials, the load shall be covered entirely by clean impervious sheeting to ensure that the dusty materials do not leak from the vehicle.
· Travelling speeds should be controlled to reduce traffic induced dust dispersion and re-suspension within the site from the operating haul trucks.
· Erection of hoarding of not less than 2.4 m high from ground level along the site boundary.
· Any stockpile of dusty materials shall be either: (a) covered entirely by impervious sheeting; (b) placed in an area sheltered on the top and the 3 sides; or (c) sprayed with water or a dust suppression chemical so as to maintain the entire surface wet.
· All dusty materials shall be sprayed with water or a dust suppression chemical immediately prior to any loading, unloading or transfer operation so as to maintain the dusty materials wet.
·
Site
clearance for the erection of site office, hoarding and fencing;
·
Reclamation
for the helipad and the Emergency Vehicle Access (EVA); and
·
Construction
of helipad and EVA.
·
Helicopter
‘approaching’ the helipad while it is descending at an angle to the helipad
surface;
·
Helicopter
manoeuvring on and directly over the helipad; and
·
Helicopter
‘taking-off’ from the helipad while it is climbing up at an angle to the
helipad surface during departure.
Table 4.1 Recommended Construction Noise Levels (Non-restricted Hours)
Noise Sensitive Receiver Uses |
Noise Levels Leq(30 min) dB(A) |
All domestic premises including temporary housing accommodation, hotels and hostels |
75 |
Schools |
70 (normal school hours) 65 (during examination periods) |
Table 4.2 Area Sensitivity Rating Criteria
|
Degree to which NSR is affected by IF(4) |
||
Type of area containing the NSR |
Not Affected(1) |
Indirectly Affected(2) |
Directly Affected(3) |
(i) Rural area, including
country parks or village type developments |
A |
B |
B |
(ii) Low density residential
area consisting of low rise or isolated high-rise developments |
A |
B |
C |
(iii) Urban area |
B |
C |
C |
(iv) Area other than those
above |
B |
B |
C |
Notes:
(1) Not Affected means that the NSR is at such a location that the
noise generated by the influencing factors(4) (IFs) is not
noticeable at the NSR.
(2) Indirectly Affected means that the NSR is at such a location that
the noise generated by the IF, whilst noticeable at the NSR, is not a dominant
feature of the noise climate of the NSR.
(3) Directly Affected means that the NSR is in such a location that
the noise generated by the IF is readily noticeable at the NSR and is a
dominant feature of the noise climate of the NSR.
(4)
IFs are defined as
industrial areas, major roads or the area within the boundary of Hong Kong
International Airport.
Table 4.3 Acceptable Noise Levels in Leq(5 min) dB(A)
Time Period |
Area Sensitivity Rating |
||
|
A |
B |
C |
All days during the evening (1900-2300) and general holidays (including Sundays) during the day and evening (0700-2300) |
60 |
65 |
70 |
All days during the night-time (2300-0700) |
45 |
50 |
55 |
Table 4.4 Helicopter Noise Standards for Planning Purposes
Uses |
Helicopter Noise Lmax dB(A) |
- All domestic premises including
temporary housing accommodation; - Hotels and hostels - Educational institutions
including kindergartens, nurseries and all others where unaided voice
communication is required - Place of public worship and
courts of law - Hospitals, clinics,
convalescences and home for the aged, diagnostic rooms, wards |
85 |
Offices |
90 |
Notes:
(1) The
above standards apply to uses that rely on opened windows for ventilation.
(2) The
above standards shall be viewed as the maximum permissible noise levels
assessed at 1 m from the external façade.
Table 4.5 Location of NSR Assessment Points in Peng Chau
NSR Assessment Point |
NSR Location |
Number of storeys |
Ground Level (mPD) |
Land Use |
NSR1 |
Sea Crest Villa - Block D, Flat A |
3 |
4.8 |
Residential |
NSR2 |
Sea Crest Villa - Block C, Flat A |
3 |
4.8 |
Residential |
NSR3 |
Kam Peng Estate – Kam Peng House |
7 |
4.7 |
Residential |
NSR4* |
Future Development in “Government, Institution or Community” Zone |
24 metres# |
20.0 |
School |
NSR5* |
Future Development in
“Residential (Group B)” Zone |
8 storey (maximum 24 metres)# |
6.0 |
Residential |
NSR6* |
Future Development in “Other Specified Uses” Zone |
2 storey (residential: 6 m; commercial: 8 m)# |
3.9 |
Commercial & Residential |
NSR7^ |
Sea Crest Villa - Block A,
Flat B |
3 |
4.8 |
Residential |
Notes:
* Location
of NSRs is based upon the most updated Peng Chau OZP No.S/I-PC/6 and ODP No.
D/I-PC/2.
# Maximum
building height based upon the most updated Peng Chau OZP No.S/I-PC/6 (gazetted
on 15.4.2005).
^ Existing
NSR used for construction noise impact assessment only.
Table 4.6 Noise Monitoring Results at Sea Crest Villa
Time Period |
June 2003 |
July 2003 |
August 2003 |
Day Time Leq(30 min) |
54 – 66 dB(A) |
51 – 64 dB(A) |
55 – 62 dB(A) |
Evening Time Leq(15 min) |
49 – 57 dB(A) |
52 – 57 dB(A) |
45 – 52 dB(A) |
Night Time Leq(15 min) |
45 – 54 dB(A) |
48 – 61 dB(A) |
50 – 56 dB(A) |
Source: Webpage http://www.pennysbaycontract1.com/noise1.html
Table 4.7 Powered Mechanical Equipment to be used for Construction of Helipad
Identification Code |
Description |
Sound Power Level, dB(A) |
CNP 003 |
Air compressor |
104 |
CNP 021 |
Bar bender (electric) |
90 |
CNP 045 |
Concrete mixer (electric) |
96 |
CNP 048 |
Crane, mobile (diesel) |
112 |
CNP 061 |
Derrick barge/ Split barge |
104 |
CNP 063 |
Dredger, grab |
112 |
CNP 067 |
Dump truck |
117 |
CNP 081 |
Excavator/ Backhoe |
112 |
CNP 101 |
Generator, Standard |
108 |
CNP 170 |
Poker, vibratory, hand-held |
113 |
CNP 186 |
Roller, vibratory |
108 |
CNP 221 |
Tug boat |
110 |
Source: GW-TM.
Table 4.8 Construction Activities
Construction Activities |
Details of Works |
Site Clearance |
·
Existing
ground breaking; ·
Removal
of demolition/ waste materials; and ·
Erection
of office, hoarding and fencing |
Reclamation |
·
Dredging; ·
Placing/
trimming of pell mell rubble; ·
Placing/
trimming of rock underlayer; and ·
Placing/
trimming of rock armour. |
Construction of Helipad |
·
Casting
pre-cast concrete wave deflector; ·
Installation
of pre-cast wave deflector; ·
Filling
the pad with granular material; ·
Compaction
of foundation material; ·
Construct
reinforced concrete slab; and ·
Install
helipad facilities. |
Construction of EVA |
·
Filling
EVA with granular material; ·
Compaction
of foundation material; ·
Construct
reinforced concrete slab; ·
Associated
drainage; ·
Install
railing and other E&M facilities; and ·
Landscape
work. |
Table 4.9 Predicted Construction Noise Levels Leq(30 min) dB(A) - Unmitigated
Assessment Period # |
NSR1 |
NSR2 |
NSR3 |
NSR4 |
NSR5 |
NSR6 |
NSR7 |
1 |
78* |
80* |
64 |
56 |
68 |
83* |
80* |
2 |
84* |
85* |
64 |
59 |
68 |
84* |
80* |
3 |
60 |
61 |
64 |
53 |
67 |
83* |
80* |
4 |
56 |
56 |
49 |
56 |
54 |
53 |
54 |
5 |
77* |
77* |
54 |
58 |
58 |
67 |
62 |
6 |
82* |
82* |
57 |
61 |
62 |
72 |
66 |
7 |
80* |
80* |
55 |
60 |
60 |
70 |
64 |
8 |
81* |
81* |
56 |
60 |
61 |
71 |
65 |
9 |
74 |
74 |
52 |
57 |
57 |
64 |
59 |
10 |
77* |
77* |
53 |
58 |
58 |
67 |
61 |
11 |
76* |
77* |
51 |
55 |
56 |
67 |
61 |
12 |
77* |
77* |
52 |
57 |
57 |
67 |
61 |
13 |
74 |
74 |
51 |
56 |
55 |
64 |
59 |
14 |
80* |
81* |
53 |
57 |
57 |
67 |
62 |
15 |
77* |
77* |
51 |
56 |
56 |
65 |
60 |
16 |
77* |
77* |
51 |
56 |
56 |
65 |
60 |
17 |
83* |
84* |
55 |
59 |
60 |
70 |
65 |
18 |
83* |
84* |
54 |
58 |
59 |
70 |
65 |
19 |
83* |
84* |
56 |
61 |
61 |
70 |
65 |
20 |
83* |
84* |
55 |
60 |
60 |
69 |
65 |
21 |
84* |
85* |
56 |
61 |
61 |
71 |
66 |
22 |
85* |
86* |
56 |
61 |
61 |
71 |
66 |
23 |
85* |
86* |
57 |
61 |
61 |
71 |
67 |
24 |
80* |
82* |
54 |
60 |
59 |
67 |
63 |
25 |
74 |
75 |
53 |
59 |
57 |
62 |
59 |
26 |
74 |
75 |
46 |
51 |
51 |
61 |
56 |
27 |
79* |
80* |
50 |
54 |
55 |
66 |
61 |
Notes:# * ‘Assessment Period’ refers to distinct construction tasks in the works programme [Appendix 4.2 refers].
* Predicted
noise level exceeds the 75 dB(A) noise standard.
Table
4.10 Sound Power Levels for the
Silenced Equipment
Identification Code |
Description |
Sound Power Level, dB(A) |
Source of Information |
CNP 001 |
Air compressor |
100 |
NCO GW-TM, CNP 001 |
CNP 067 |
Dump truck |
109 |
BS5228, Table C.3 Item 52 |
CNP 081 |
Excavator/ Backhoe |
102 |
BS5228, Table C.8 Item 33 |
CNP 103 |
Generator, super silenced, 70 dB(A) at 7m |
95 |
NCO GW-TM, CNP 103 |
CNP 170 |
Poker, vibratory, hand-held |
100 |
BS5228, Table C.6 Item 32 |
Table 4.11 Predicted Construction Noise Levels Leq(30 min) dB(A) – Mitigated
Assessment Period |
NSR1 |
NSR2 |
NSR3 |
NSR4 |
NSR5 |
NSR6 |
NSR7 |
1 |
65 |
66 |
54 |
46 |
57 |
73 |
69 |
2 |
70 |
72 |
54 |
50 |
58 |
73 |
69 |
3 |
50 |
51 |
53 |
43 |
57 |
73 |
69 |
4 |
45 |
46 |
39 |
46 |
44 |
42 |
44 |
5 |
72 |
72 |
52 |
55 |
56 |
67 |
61 |
6 |
75 |
75 |
54 |
58 |
59 |
70 |
64 |
7 |
71 |
71 |
51 |
55 |
55 |
66 |
60 |
8 |
72 |
72 |
51 |
55 |
56 |
67 |
61 |
9 |
62 |
62 |
43 |
48 |
48 |
57 |
52 |
10 |
65 |
65 |
46 |
50 |
50 |
60 |
54 |
11 |
65 |
65 |
44 |
48 |
49 |
60 |
54 |
12 |
65 |
66 |
49 |
55 |
54 |
60 |
56 |
13 |
63 |
63 |
48 |
54 |
53 |
58 |
54 |
14 |
68 |
69 |
49 |
55 |
54 |
61 |
57 |
15 |
70 |
71 |
50 |
55 |
54 |
62 |
58 |
16 |
69 |
71 |
47 |
51 |
52 |
62 |
57 |
17 |
68 |
69 |
46 |
51 |
51 |
61 |
56 |
18 |
68 |
69 |
47 |
52 |
52 |
61 |
56 |
19 |
68 |
69 |
46 |
50 |
50 |
61 |
55 |
20 |
66 |
68 |
44 |
48 |
48 |
58 |
53 |
21 |
68 |
70 |
45 |
49 |
50 |
60 |
55 |
22 |
69 |
70 |
45 |
50 |
50 |
61 |
56 |
23 |
69 |
70 |
45 |
50 |
50 |
61 |
56 |
24 |
65 |
67 |
43 |
48 |
48 |
57 |
53 |
25 |
59 |
61 |
41 |
47 |
46 |
51 |
48 |
26 |
59 |
60 |
36 |
40 |
40 |
51 |
46 |
27 |
64 |
65 |
40 |
43 |
45 |
56 |
51 |
· Noisy equipment and noisy activities should be located as far away from the NSRs as is practical;
· Unused equipment should be turned off;
· Powered mechanical equipment should be kept to minimum and the parallel use of noisy equipment / machinery should be avoided;
· Regular maintenance of all plant and equipment; and
· The Contractor shall observe and comply with the statutory requirements and guidelines.
Table 4.12 Predicted Cumulative Construction Noise Levels Leq(30 min) dB(A) at NSR1
Assessment Period |
Predicted Noise Level (Leq(30 min)) dB(A) |
Assessment Period |
Predicted Noise Level (Leq(30 min)) dB(A) |
Assessment Period |
Predicted Noise Level (Leq(30 min)) dB(A) |
1 |
70 |
10 |
71 |
19 |
72 |
2 |
72 |
11 |
71 |
20 |
71 |
3 |
68 |
12 |
71 |
21 |
72 |
4 |
68 |
13 |
70 |
22 |
72 |
5 |
73 |
14 |
72 |
23 |
72 |
6 |
75 |
15 |
73 |
24 |
70 |
7 |
73 |
16 |
73 |
25 |
69 |
8 |
74 |
17 |
72 |
26 |
69 |
9 |
70 |
18 |
72 |
27 |
70 |
Helicopter manoeuvring above the
helipad within the Final Approach and Take-off Areas (FATO)[†††] includes several modes:
·
‘Hovering’
– helicopter turns on the spot over the helipad to achieve the desirable
orientation for touchdown / lift-off;
·
‘Touchdown’
– helicopter descends on to the helipad surface;
·
‘Idling’
– helicopter remains on the helipad surface with its rotary blades kept
running; and
·
‘Lift-off’
– helicopter ascends vertically from the helipad surface to achieve a hover
before departure.
·
Helicopter
‘approaching’ the helipad while it is descending at an angle to the helipad
surface; and
·
Helicopter
‘taking-off’ from the helipad while it is climbing up at an angle to the
helipad surface.
Noise Level Difference (dB) = 20 log10
Table 4.13 Helicopter Noise Data – Airborne Helicopter with Lateral Movements
Reference Measurement Configurations |
Super Puma AS332 L2 |
EC155 B1 |
||
ICAO Max. Noise Level EPNdB |
Demonstrated Noise Level EPNdB |
ICAO Max. Noise Level EPNdB |
Demonstrated Noise Level EPNdB |
|
Approach |
100.7 (87.7) |
96.1 (83.1) |
97.9 (84.9) |
95.7 (82.7) |
Take-off |
99.7 (86.7) |
94.6 (81.6) |
96.9 (83.9) |
92.2 (79.2) |
Flyover |
98.7 (85.7) |
93.5 (80.5) |
95.9 (82.9) |
88.9 (75.9) |
Notes:
Figures in brackets are the Lmax
dB(A) values.
Lmax = EPNdB – 13, with reference
to the ‘Transportation Noise Reference Book’ (Nelson, 1987).
Table 4.14 Measured Lmax Noise Level of GFS Helicopters – Without Lateral Movements
Measurement Configurations
(Reference distance: 150m) |
Super Puma AS332 L2 |
EC155 B1 |
Helicopter on ground, Idling |
82.0 |
80.0 |
Helicopter in the air * |
90.6 |
87.7 |
Notes:
Lmax noise levels in dB(A).
* For ‘Super
Puma AS332 L2’, the Lmax noise level is measured during the hovering
mode.
For ‘EC155
B1’, the Lmax noise level is measured during the lift-off mode.
Table 4.15 Helicopter Use for Peng Chau
‘Casevac’ Operations during years 2000 – 2004
Year |
Total No. of Casevac from 0700 to 2200 hours1 |
Total No. of Casevac from 2200 – 0700 hours2 |
No. of Casevac Training Flights3 |
2000 |
97 (1) |
51 |
2 |
2001 |
125 (9) |
57 |
3 |
2002 |
234 (29) |
56 |
5 |
2003 |
167 (4) |
42 |
5 |
2004 |
140 (5) |
37 |
3 |
Notes:
1.
The figures
in brackets ( ) are the number of casevac flights carried out by Super Puma (or
Sikorsky prior to 2004).
2.
Since 2003, all nighttime casevac has
been undertaken using the EC155 B1 type helicopter only, although for the
purpose of this noise impact assessment it cannot be discounted that the Super
Puma may be required for nighttime casevac in future years.
3.
Five casevac training flights were
conducted to the Peng Chau helipad in 2003 (i.e., an additional 2.3% of the
total casevac flights). As no such data
is available for other years, the number of casevac training flights for 2000-2002
and 2004 have been calculated using the same % contribution. It should be noted that GFS does not
anticipate any increase in training flights in the short to medium term as the
helicopter fleet was upgraded in 2001/02 and there are no plans to add additional
types of helicopters.’
Table 4.16 Worst-case Helicopter Noise Levels at NSRs during Helicopter Manoeuvring
NSR ID |
Horizontal separation to centre of the
Helipad (metres) |
Lmax @ NSR dB(A) 1 |
Façade Correction dB(A) |
Topographical Correction dB(A) 2 |
Corrected Lmax @ NSR dB(A) |
||
Super Puma AS332 L2 |
EC155 B1 |
Super Puma AS332 L2 |
EC155 B1 |
||||
NSR1 |
167 |
90 (81) |
87 (79) |
3 |
-10 |
83 (74) |
80 (72) |
NSR2 |
156 |
90 (82) |
87 (80) |
3 |
-10 |
83 (75) |
80 (73) |
NSR3 |
336 |
84 (75) |
81 (73) |
3 |
-10 |
77 (68) |
74 (66) |
NSR4* |
162 |
90 (81) |
87 (79) |
3 |
-10 |
83 (74) |
80 (72) |
NSR5* |
193 |
88 (80) |
86 (78) |
3 |
-10 |
81 (73) |
79 (71) |
NSR6* |
238 |
87 (78) |
84 (76) |
3 |
-10 |
80 (71) |
77 (69) |
Notes:
1 Calculated with reference to measured Lmax
noise level at reference distance of 150m.
2 By standard acoustic principles, if the
noise source is totally screened such that none will be visible when viewed
from any façade of the NSR, a negative topography correction of 10 dB(A) shall
be applied.
*
Future NSR.
Figures in brackets are the Lmax
during the idling mode.
Table 4.17 Worst-case Helicopter Approach / Departure Noise Levels at NSRs
NSR ID |
Slant distance between helicopter &
NSR (m) |
Lmax @ NSR dB(A) 1 |
Façade Correction dB(A) |
Topographical Correction dB(A) 2 |
Corrected Lmax @ NSR dB(A) |
||
Super Puma |
EC155 B1 |
Super Puma |
EC155 B1 |
||||
NSR1 |
163 |
85 |
82 |
3 |
0 |
88 |
85 |
NSR2 |
161 |
85 |
82 |
3 |
0 |
88 |
85 |
NSR3 |
336 |
79 |
76 |
3 |
-10 |
72 |
69 |
NSR4 |
165 |
85 |
82 |
3 |
-10 |
78 |
75 |
NSR5 |
193 |
84 |
81 |
3 |
-10 |
77 |
74 |
NSR6 |
238 |
82 |
79 |