4.                  WATER QUALITY

 

4.1              Introduction

 

4.1.1          In this section, the requirements, methodology, equipment, monitoring locations, criteria and protocols for the monitoring and audit of water quality impacts during the construction and operational phase of the Project are presented.  The key marine water monitoring components and objectives is provided in Table 4.1a.

Construction Phase

 

4.1.2          The implementation of good construction works practice as well as the mitigation measures identified in Appendix C are important to prevent pollution of marine water in the construction phase and therefore regular site audit of all the land and marine construction activities is recommended. Site audits shall include site inspections and compliance audits.

4.1.3          The water quality impact assessment conducted for this Study concluded that marine water quality impacts from the proposed Project were mainly associated with the WCR reclamation activities including the dredging and filling activities and the deep cement mixing (DCM) treatment. Marine water quality monitoring should be carried out at selected stations before and during the WCR reclamation activities as well as during the marine piling works for construction of the CBL.  During the field trial of DCM, a water quality monitoring programme should be implemented to confirm the water quality impact before the full-scale implementation of DCM for seawall construction.  

Operational Phase

 

4.1.4          For the operational phase, it is recommended to implement a 3-year post-project monitoring programme at Eastern Channel (EDC) to confirm the suitability of the proposed recreation uses at EDC. 

4.1.5          In any event of emergency sewage bypass at the seawall, the proposed recreation zone in EDC and Junk Bay will be closed.  Water quality monitoring should be carried out by DSD to determine when conditions are suitable for re-opening of the EDC and Junk Bay for recreational purposes.

Table 4.1a       Key Marine Water Monitoring Components

Description of Monitoring

Objectives

Monitoring Components

Tentative Timing

Action

Construction phase monitoring during WCR reclamation and during marine piling works for CBL

To monitor the marine water quality impacts from the WCR reclamation activities and marine piling works

Implement baseline monitoring

Before September 2010

ET, IE(C)

Establish baseline condition

Before October 2010

ET, IE(C)

Agree baseline condition

Before November 2010

EPD

Implement impact monitoring

November 2010 – September 2014 (During WCR reclamation);

February 2013 – Jan 2014 (During marine piling for CBL)

ET, IE(C)

Construction phase monitoring during DCM

To monitor the marine water quality impacts from the DCM

Implement water quality monitoring during DCM field trial

February - May 2011 (After the Phase 1 seawall is completed)

ET, IE(C)

Review / establish monitoring requirements for full scale DCM operation

Before December 2011

IE(C)

Agree monitoring proposal for full scale DCM operation

Before February 2012

EPD, AFCD

Implement water quality monitoring during full scale DCM operation

February - April 2012 and February - April 2014 (During full scale DCM operation)

ET, IE(C)

Operational phase monitoring at EDC

To confirm the suitability of the proposed water recreation uses at EDC

Implement water quality monitoring at EDC

After completion of the Project by 2016

Future operator of the water recreation area

Review the suitability of the proposed recreation uses at EDC

Continuous review during the monitoring period

Determine whether to discontinue the monitoring or not

After a 3-year post monitoring period

Operational phase monitoring during emergency discharge

To safeguard the users of the water creation zone against the water quality impact due to emergency sewage discharge from the TKO sewage treatment woks

Close the water recreation zone and implement water quality monitoring at EDC and inner Junk Bay

In any event of emergency discharge at seawall during operational phase of the Project

Future operator of the water recreation area

Review the suitability of re-opening the water recreation area

 

4.2              Construction Phase Monitoring

 

4.2.1          For construction phase monitoring, the proposed water quality monitoring schedule should be passed to EPD at least two weeks before the first day of the monitoring month.  EPD should also be notified immediately for any changes in schedule.  The monitoring stations proposed in this section are indicative subject to further review before construction phase.    The status and locations of water sensitive receivers and the marine activities may change after issuing this Manual. The proposed monitoring locations should be submitted four weeks before commencement of baseline monitoring for EPD approval. 

Impact Monitoring During WCR Reclamation and CBL piling works

 

4.2.2          For impact monitoring during WCR reclamation, it is recommended to set up 7 monitoring stations at Junk Bay Coral Site-South West (CM1), Junk bay Coral Site-Junk Island (CM2), Tseung Kwan O Salt Water Intake (CM3), two gradient stations (CM4 and CM5) and two control stations (C1 and C2).  Monitoring stations are shown in Figure 4.1 and Table 4.1.  The 3 stations (CM1, CM2 and CM3) represent sensitive receivers, which are potentially affected by the Project during the proposed reclamation works. The gradient stations, CM4 and CM5 (which are close to the boundary of the mixing zone as indicated in the EIA Report), are proposed to assist in the identification of the source of any impact at the monitoring stations, CM2 and CM3.  Stations C1 and C2 will therefore serve as control stations.

4.2.3          During CBL piling works, monitoring should be carried out at CM1, CM2, CM3, C1 and C2 only. The 3 stations (CM1, CM2 and CM3) represent sensitive receivers, which are potentially affected by the Project during the proposed piling works.  Stations C1 and C2 will serve as control stations.

Table 4.1   Proposed Marine Water Quality Stations for Baseline and Construction Phase Monitoring

Station

Description

Easting

Northing

CM1

Junk bay Coral Site-South West

843208.60

816416.20

CM2

Junk bay Coral Site-Junk Island

845285.60

815348.82

CM3

Tseung Kwan O Salt Water Intake

845512.05

817441.79

CM4

Gradient Station-Outer Junk Bay

843925.93

816132.22

CM5

Gradient Station-Inner Junk Bay

844761.83

817183.47

C1

Control Station-Southeast

845492.57

813618.36

C2

Control Station- Northwest

841702.41

816780.62

 

4.2.4          During the WCR reclamation and CBL piling, monitoring should be undertaken three days per week, at mid-flood and mid-ebb tides, with sampling/measurement at the designated monitoring stations including the control stations.  The interval between two sets of monitoring should not be less than 36 hours except where there are exceedances of Action and/or Limit levels, in which case the monitoring frequency will be increased.  It is proposed to conduct the DCM field trial for engineering design after completion of the Phase 1 seawall.  During the DCM field trial period, the monitoring frequency should be increased to daily at both mid-flood and mid-ebb tides to collect more water quality information at the designated monitoring stations (C1, C2, CM1 to CM5).  Table 4.2 shows the proposed monitoring frequency and water quality parameters.

Table 4.2   Proposed Marine Water Quality Monitoring Frequency and Parameters at Stations C1, C2, CM1 to CM5

Activities

Monitoring Frequency

Key Parameters

During marine construction for WCR Reclamation and CBL piling

Three days per week, at mid-flood and mid-ebb tides

Dissolved Oxygen (DO), turbidity, Suspended Solids (SS)

During DCM field trial

Daily, at mid-flood and mid-ebb tides

pH, DO, turbidity, SS

Note:       DO, pH and turbidity should be measured in situ whereas SS should be determined by laboratory. 

4.2.5          During the DCM field trial, in-situ measurement of DO, pH and turbidity should be undertaken at 2 additional stations (at 20 m upstream and 20 m downstream of the DCM treatment area respectively) at an hourly interval except where there are exceedances of Limit levels at the downstream station, in which case the monitoring frequency will be increased.  The locations of the upstream and downstream stations should be determined on-site as they are dependent on the location of the DCM treatment area and the current direction during the monitoring period. A review should be conducted after the DCM field trial to determine if the same monitoring programme should be applied during the full-scale DCM treatment.

4.2.6          All measurements should be taken at three water depths, namely, 1 m below water surface, mid-depth and 1 m above seabed, except where the water depth is less than 6 m, in which case the mid-depth station may be omitted.  Should the water depth be less than 3 m, only the mid-depth station will be monitored.  If the impact monitoring data collected at the sensitive receivers (i.e. Stations CM1, CM2 & CM3) indicate that the Action or Limit levels as shown in Table 4.5 are exceeded, assessment should be conducted to compare the impact monitoring data with those collected at the gradient stations and the control stations as appropriate and to identify whether the exceedance is caused by the marine construction activities . If the data analysis results indicate that the exceedance is caused by the reclamation activities, appropriate actions including lowering the working rate, or rescheduling of works should be taken and additional mitigation measures should be implemented as necessary.

Baseline Monitoring

 

4.2.7          Baseline conditions for marine water quality should be established and agreed with EPD prior to the commencement of works.  The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the marine construction works and to demonstrate the suitability of the proposed monitoring stations.  The baseline conditions should be established by measuring DO, pH, turbidity and SS levels at 7 selected monitoring stations as shown in Table 4.1. The baseline monitoring report should be submitted to EPD at least 4 weeks before the commencement of marine works for agreement.  The baseline monitoring report should be certified by the IE(C) before submission to EPD.

4.2.8          The measurements should be taken at all designated monitoring stations including control stations, 3 days per week, at mid-flood and mid-ebb tides, for at least 4 weeks prior to the commencement of marine works.  There should not be any marine construction activities in the vicinity of the stations during the baseline monitoring.  The interval between 2 sets of monitoring should not be less than 36 hours. 

Post-construction Monitoring

 

4.2.9          Upon completion of all marine works, a post-project monitoring should be carried out for 4 weeks in the same manner as the baseline monitoring. 

Construction Site Audits

 

4.2.10      Implementation of regular site audits is to ensure that the recommended mitigation measures are to be properly undertaken during construction phase of the Project. It can also provide an effective control of any malpractices and therefore achieve continual improvement of environmental performance on site.

4.2.11      Site audits should include site inspections and compliance audits.

Site Inspections

 

4.2.12      Site inspections should be carried out by the ET and should be based on the mitigation measures for water pollution control recommended in Section 4.10. In the event that the recommended mitigation measures are not fully or properly implemented, deficiency should be recorded and reported to the site management. Suitable actions are to be carried out to:

·         investigate the problems and the causes;

·         issue action notes to the Contractor which is responsible for the works;

·         implement remedial and corrective actions immediately;

·         re-inspect the site conditions upon completion of the remedial and corrective actions; and

·         record the event and discuss with the Contractor for preventive actions.

 
Compliance Audits

 

4.2.13      Monitoring of the treated effluent quality from the Works Areas is required during the construction phase of the Project. The monitoring should be carried out at the pre-determined discharge point. Compliance audits are to be undertaken to ensure that a valid discharge licence has been issued by EPD prior to the discharge of effluent from the Project site. The monitoring frequency and parameters specified in the discharge licence should be fully considered during the monitoring. All monitoring requirements should be approved by EPD. The audit results reflect whether the effluent quality is in compliance with the discharge licence requirements. In case of non-compliance, suitable actions should be undertaken to:

·         notify the site management for the non-compliance;

·         identify the sources of pollution;

·         check the implementation status of the recommended mitigation measures;

·         investigate the operating conditions of the on-site treatment systems;

·         implement corrective and remedial actions to improve the effluent quality;

·         increase monitoring frequency until the effluent quality is in compliance with the discharge licence requirements; and

·         record the non-compliance and propose preventive measures.

4.2.14      The implementation schedule for the recommended water quality mitigation measures is presented in Appendix C.

4.3              Operational Phase Monitoring

 

4.3.1          It is recommended to conduct water quality field survey at EDC after the proposed drainage diversion works (as mentioned in Section 5.7.6 of the EIA Report) is completed to confirm the suitability of the proposed recreation uses at EDC.   The field survey should be conducted at a frequency of twice per year in dry season and wet season respectively after operation of the drainage diversion works.  Monitoring should be conducted at mid-food and mid-ebb tides during each of the dry and wet season surveys.  The suitability of the proposed recreation uses at EDC should be continuously reviewed with reference to the field survey data.  After a 3-year operation period, a review should be conducted to determine whether the field survey programme should be discontinued.  The 3-year post-project monitoring should be conducted at upper EDC (OM1) and lower EDC (OM2) and parameters should include in-situ measurement of DO and laboratory analysis of 5-day biochemical oxygen demand (BOD5), ammonia nitrogen (NH3) and E.coli.  In-situ measurement of pH and salinity should also be measured for calculation of the unionized ammonia (UIA) levels.  Table 4.3 and Figure 4.1 shows the monitoring locations.  

Table 4.3   Proposed Marine Water Quality Stations for Operational Phase Monitoring

Station

Description

Easting

Northing

OM1

Upper Eastern Channel

845384.83

818324.55

OM2

Lower Eastern Channel

845231.23

818075.81

OM3

Inner Junk Bay

844761.83

817183.47

OM4

Outer Junk Bay

843925.93

816132.22

 

 

4.3.2          In any event of emergency sewage bypass at seawall of Area 86, the proposed recreation zone in EDC and Junk Bay will be closed.  Water quality monitoring should be carried out by DSD and/or future operators of the proposed water recreation facilities after the bypass event to determine when conditions are suitable for re-opening of the EDC and Junk Bay for recreational purposes.  For each monitoring event, the monitoring should be conducted at both mid-flood and mid-ebb tides to confirm the water quality.  In case of exceedance of Limit levels, the monitoring should be carried out daily until the baseline water quality resumes. DO and E. coli should be measured at 4 selected stations including upper EDC (OM1), lower EDC (OM2), inner Junk Bay (OM3) and outer Junk Bay (OM4). Table 4.3 and Figure 4.1 shows the monitoring locations.  

4.3.3          All measurements should be taken at three water depths, namely, 1 m below water surface, mid-depth and 1 m above seabed, except where the water depth is less than 6 m, in which case the mid-depth station may be omitted.  Should the water depth be less than 3 m, only the mid-depth station should be monitored.   

4.4              Monitoring Equipment and Field Log

 

Dissolved Oxygen and Temperature Measuring Equipment

 

4.4.1          The instrument should be a portable and weatherproof DO measuring instrument complete with cable and sensor, and use a DC power source.  The equipment should be capable of measuring:

·         a DO level in the range of 0 ‑ 20 mg L-1 and 0 ‑ 200% saturation; and

·         a temperature of 0 ‑ 45 degree Celsius.

 

4.4.2          It should have a membrane electrode with automatic temperature compensation complete with a cable. Sufficient stocks of spare electrodes and cables should be available for replacement where necessary. (For example, YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with reel and cable or an approved similar instrument).

4.4.3          Should salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO equipment prior to each DO measurement.

Turbidity Measurement Instrument

                     

4.4.4          Turbidity should be measured in situ by the nephelometric method. The instrument should be portable and weatherproof using a DC power source complete with cable, sensor and comprehensive operation manuals.  It should have a photoelectric sensor capable of measuring turbidity between 0 - 1000 NTU (for example, Hach model 2100P or an approved similar instrument). The cable should not be less than 25m in length. The meter should be calibrated in order to establish the relationship between NTU units and the levels of suspended solids.  The turbidity measurement should be carried out on split water sample collected from the same depths of suspended solids samples.

Sampler

 

4.4.5          A water sampler is required.  It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

Water Depth Detector

 

4.4.6          A portable, battery-operated echo sounder should be used for the determination of water depth at each designated monitoring station.  This unit can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

Salinity

 

4.4.7          A portable salinometer capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) should be provided for measuring salinity of the water at each monitoring location.

Sample Containers and Storage

 

4.4.8          Water samples for SS, UIA and E. coli determinations should be stored in suitable containers with no preservative added, packed in ice (cooled to 4°C without being frozen) and delivered to the laboratory and analysed as soon as possible after collection.  Sufficient volume of samples should be collected to achieve the detection limit.

Monitoring Position Equipment

 

4.4.9          A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication or other equipment instrument of similar accuracy, should be provided and used during water quality monitoring to ensure the monitoring vessel is at the correct location before taking measurements. DGPS or the equivalent instrument, calibrated at appropriate checkpoint (e.g. Quarry Bay Survey Nail at Easting 840683.49, Northing 816709.55) should be provided and used to ensure the monitoring station is at the correct position before taking measurement and water samples.

Calibration of In-Situ Instruments

 

4.4.10      All in situ monitoring instruments should be checked, calibrated and certified by a laboratory accredited under HOKLAS or any other international accreditation scheme before use and subsequently re-calibrated at three monthly intervals throughout all stages of the water quality monitoring programme.  Responses of sensors and electrodes should be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter should be carried out before measurement at each monitoring location.

4.4.11      For the on site calibration of field equipment, the BS 127:1993, Guide to Field and On-Site Test Methods for the Analysis of Water should be observed.

4.4.12      Sufficient stocks of spare parts should be maintained for replacements when necessary.  Backup monitoring equipment should also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, etc.

Field Log

 

4.4.13      Other relevant data should also be recorded, including monitoring location / position, time, water depth, salinity, temperature, tidal stages, weather conditions and any special phenomena or work underway nearby. 

4.4.14      A sample data record sheet is shown in Appendix B for reference.

4.5              Laboratory Measurement / Analysis

 

4.5.1          Analysis of SS, UIA, BOD5 and E. coli levels should be carried out in a HOKLAS or other international accredited laboratory.  The UIA concentrations will be determined from the laboratory analysis of ammonia nitrogen (NH3) and the in-situ measurements of salinity, DO, temperature and pH for the marine water samples. Sufficient water samples of not less than 2 litres should be collected at the monitoring stations for carrying out the laboratory SS, NH3, BOD5 and E. coli determinations. The suggested testing method and lowest detection limit are provided in Table 4.4.

Table 4.4         Analytical Methods to be applied to Marine Water Quality Samples

Determinant

Suggested Method

Suggested Detection Limit

Suspended solids

APHA 2540D

1 mg L-1

Ammonia Nitrogen

APHA 4500-NH3

0.02 mg L-1

5-day biochemical oxygen demand

APHA 19ed 5210B

2 mg L-1

E.coli

EPD HKSAR, Wat. Sci. Tech. Vol. 35, No. 11-12 pp 409-413

1 cfu per100mL

APHA     American Public Health Association Standard Methods for the Examination of Water and Wastewater

 

4.5.2          Detailed testing methods, pre-treatment procedures, instrument use, Quality Assurance/Quality Control (QA/QC) details (such as blank, spike recovery, number of duplicate samples per batch, etc.), detection limits and accuracy should be submitted to EPD for approval prior to the commencement of monitoring programme. EPD may also request the laboratory to carry out analysis of known standards provided by EPD for quality assurance. The testing methods and related proposal should be checked and certified by IC(E) before submission to EPD for approval.

4.5.3          Additional duplicate samples may be required by EPD for inter laboratory calibration. Remaining samples after analysis should be kept by the laboratory for 3 months in case repeat analysis is required. If in-house or non-standard methods are proposed, details of the method verification may also be required to submit to EPD. In any circumstance, the sample testing should have comprehensive quality assurance and quality control programmes. The laboratory should prepare to demonstrate the programmes to EPD or his representatives when requested.

4.6              Event and Action Plan

 

4.6.1          The water quality assessment criteria, namely Action and Limit levels are shown in Table 4.5.  Should the monitoring results of the water quality parameters at any designated monitoring stations indicate that the water quality assessment criteria are exceeded, the actions in accordance with the Action Plan in Table 4.6, Table 4.7 and Table 4.8 be carried out. 

4.6.2          It is recommended that if monitoring results indicate that the reclamation activities have caused an adverse impact on water quality at the sensitive receivers, additional mitigation measures should be recommended to rectify the non-compliance or the construction programme should be carefully reviewed.  If the reclamation works have caused non-compliance with WSD’s seawater quality standards at the TKO saltwater intake, WSD should be informed.  The working schedule and the mitigation measures should be reviewed by the Contractor, the IC(E), the ET Leader and the ER, and if necessary, works should be slowed down or suspended until such impact is reduced to an acceptable level. 

4.6.3          The ET Leader should assess the effectiveness and efficiency of the proposed mitigation measures and/or remedial actions for the on-going construction activities.  The performance of the environmental management system (i.e. of the overall EM&A programme) should be reviewed by the ET Leader on a quarterly basis.  The findings of this review should be included in the quarterly EM&A summary reports, together with any recommendations to improve the performance of the EM&A programme.

Table 4.5   Action and Limit Levels for Marine Water Quality

Parameters

Action

Limit

Construction Phase – During WCR Reclamation and CBL piling (Action & Limit Levels are applicable to Stations CM1, CM2 and CM3

DO in mg L-1

(Surface, Middle & Bottom)

Surface and Middle

5 percentile of baseline

 

 

Bottom

5 percentile of baseline data

 

Surface and Middle

4 mg L-1 or

1 percentile of baseline data

  

Bottom

2 mg L-1 or

1 percentile of baseline data

SS in mg L-1 (depth-averaged)

95 percentile of baseline data or 120% of upstream control station's SS at the same tide of the same day

99 percentile of baseline or 130% of upstream control station's SS at the same tide of the same day

SS in mg L-1 (surface layer at monitoring stations close to WSD salt water intakes

10

10

Turbidity in NTU

(depth-averaged)

95 percentile of baseline data or 120% of upstream control station's Turbidity at the same tide of the same day

99 percentile of baseline or 130% of upstream control station's Turbidity at the same tide of the same day

Construction Phase - During DCM Treatment (Limit Levels are applicable to the downstream station only) See Remark

pH values measured at 20 m upstream and 20 m downstream of the DCM treatment area

(depth-averaged)

-

Limit level is exceeded if:

1.  the pH value measured at the downstream station is above 8.5; and

2.  the pH value measured at the downstream station is greater than the value at the upstream station by more than 0.2.

Turbidity in NTU measured at 20 m upstream and 20 m downstream of the DCM treatment area

(depth-averaged)

-

Limit level is exceeded if the turbidity measured at the downstream station is greater than 130% of the measured value at the upstream control station.

Operational Phase Monitoring - To safeguard the users of the water recreation zone in EDC and inner Junk Bay (Limit Levels are applicable to Stations OM1, OM2, OM3 and OM4)

DO in mg L-1

(Depth averaged & Bottom)

-

Depth-averaged

4 mg L-1

 

 Bottom

2 mg L-1

E.coli in cfu per 100 mL

(depth-averaged)

-

610 cfu per 100 mL

Notes:     1.     "depth-averaged" is calculated by taking the arithmetic means of reading of all three depths.

2.         For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

3.        For turbidity and SS, non-compliance of the water quality limits occurs when monitoring result is higher than the limits. 

4.        All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

Remark:   A review would be conducted after the DCM field trial before firming up the monitoring programme for the full scale DCM treatment.


Table 4.6   Event and Action Plan for Marine Water Quality During WCR Reclamation and CBL Piling

EVENT

ACTION

 

                     ET

          IC(E)

ER

CONTRACTOR

Action level being exceeded by one sampling day at water sensitive receiver(s)

Identify the source(s) of impact by comparing the results with those collected at the gradient stations and the control stations as appropriate;

If exceedance is found to be caused by the reclamation activities, repeat in-situ measurement to confirm findings;

Inform IC(E) and contractor;

Check monitoring data, all plant, equipment and Contractor's working methods;

If exceedance occurs at WSD salt water intake, inform WSD;

Discuss mitigation measures with IC(E) and Contractor;

Repeat measurement on next day of exceedance.

 

Discuss with ET and Contractor on the mitigation measures;

Review proposal on mitigation measures submitted by Contractor and advise the ER accordingly;

Assess the effectiveness of the implemented mitigation measures.

Discuss with IC(E) on the proposed mitigation measures;

Make agreement on the mitigation proposal.

Inform the ER and confirm notification of the non-compliance in writing;

Rectify unacceptable practice;

Check all plant and equipment;

Amend working methods if appropriate;

Discuss with ET and IC(E) and propose mitigation measures to IC(E) and ER;

Implement the agree mitigation measures.

 

Action level being exceeded by two or more  consecutive sampling days at water sensitive receiver(s)

Identify the source(s) of impact by comparing the results with those collected at the gradient stations and the control stations as appropriate;

If exceedance is found to be caused by the reclamation activities, repeat in-situ measurement to confirm findings;

Inform IC(E) and contractor;

Check monitoring data, all plant, equipment and Contractor's working methods;

Discuss mitigation measures with IC(E), and Contractor;

Ensure mitigation measures are implemented;

Prepare to increase the monitoring frequency to daily;

If exceedance occurs at WSD salt water intake, inform WSD;

Repeat measurement on next day of exceedance.

 

Discuss with ET and Contractor on the mitigation measures;

Review proposal on mitigation measures submitted by Contractor and advise the ER accordingly;

Assess the effectiveness of the implemented mitigation measures.

Discuss with IC(E) on the proposed mitigation measures;

Make agreement on the mitigation proposal;

Assess the effectiveness of the implemented mitigation measures.

Inform the Engineer and confirm notification of the non-compliance in writing;

Rectify unacceptable practice;

Check all plant and equipment and consider changes of working methods;

Discuss with ET, IC(E) and ER and propose mitigation measures to IC(E) and ER within 3 working days;

Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day at water sensitive receiver(s)

Identify the source(s) of impact by comparing the results with those collected at the gradient stations and the control stations as appropriate;

If exceedance is found to be caused by the reclamation activities, repeat in-situ measurement to confirm findings;

Inform IC(E), contractor and EPD

Check monitoring data, all plant, equipment and Contractor's working methods;

Discuss mitigation measures with IC(E), ER and Contractor;

Ensure mitigation measures are implemented;

Increase the monitoring frequency to daily until no exceedance of Limit level;

If exceedance occurs at WSD salt water intake, inform WSD.

Discuss with ET and Contractor on the mitigation measures;

Review proposal on mitigation measures submitted by Contractor and advise the ER accordingly;

Assess the effectiveness of the implemented mitigation measures.

Discuss with IC(E), ET and Contractor on the proposed mitigation measures;

Request Contractor to critically review the working methods;

Make agreement on the mitigation measures to be implemented;

Assess the effectiveness of the implemented mitigation measures.

Inform the ER and confirm notification of the non-compliance in writing;

Rectify unacceptable practice;

Check all plant and equipment and consider changes of working methods;

Discuss with ET, IC(E) and ER and submit proposal of mitigation measures to IC(E) and ER within 3 working days of notification;

Implement the agreed mitigation measures.

Limit level being exceeded by two or more consecutive sampling days at water sensitive receiver(s)

Identify the source(s) of impact by comparing the results with those collected at the gradient stations and the control stations as appropriate;

If exceedance is found to be caused by the reclamation activities, repeat in-situ measurement to confirm findings;

Inform IC(E), contractor and EPD;

Check monitoring data, all plant, equipment and Contractor's working methods;

Discuss mitigation measures with IC(E), ER and Contractor;

Ensure mitigation measures are implemented;

Increase the monitoring frequency to daily until no exceedance of Limit level for two consecutive days;

If exceedance occurs at WSD salt water intake, inform WSD.

Discuss with ET and Contractor on the mitigation measures;

Review proposal on mitigation measures submitted by Contractor and advise the ER accordingly;

Assess the effectiveness of the implemented mitigation measures.

Discuss with IC(E), ET and Contractor on the proposed mitigation measures;

Request Contractor to critically review the working methods;

Make agreement on the mitigation measures to be implemented;

Assess the effectiveness of the implemented mitigation measures;

Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the marine work until no exceedance of Limit level.

Inform the ER and confirm notification of the non-compliance in writing;

Rectify unacceptable practice;

Check all plant and equipment and consider changes of working methods;

Discuss with ET, IC(E) and ER and submit proposal of mitigation measures to IC(E) and ER within 3 working days of notification;

Implement the agreed mitigation measures;

As directed by the Engineer, to slow down or to stop all or part of the construction activities.

 

Table 4.7   Event and Action Plan for Marine Water Quality During DCM Field Trial

Event

Action

Limit level being exceeded at the station downstream of the DCM treatment area

1.       ET to inform the IC(E), the ER and the contractor.

2.       ET to repeat the in-situ measurements at a 15-minute intervals until no exceedance is recorded for 2 consecutive measurements.

3.       ER and the Contractor to check all plant, equipment, mitigation measures and Contractor's working methods.

4.       The contractor to stop the DCM field trial or slow down the DCM process until no exceedance is recorded for 2 consecutive measurements.

 

Table 4.8   Event and Action Plan for Marine Water Quality During Operational Phase

Event

Action

During Emergency Discharge Event

Limit level being exceeded

Conduct daily monitoring; Continue to close the recreational area until no exceedance is confirmed for 2 consecutive monitoring events.

 

4.7              Mitigation Measures

 

4.7.1          Mitigation measures for water quality control have been recommended in the EIA Report.  The Contractor should be responsible for the design and implementation of these measures.

4.7.2          Recommended mitigation measures to minimise the adverse impacts on water quality during construction and operation phases are detailed in Section 4.10 below.

Construction Phase

 

Dredging and Filling Activities

 

4.7.3          In view of the close vicinity of the coral community to the work site, silt curtain should be installed around the reclamation site.

4.7.4          Dredging and filling works should be carried out in a controlled manner such that release of sediments into the marine environment would be minimised.  The following list of measures should be followed:

4.7.5          The modelling results indicated that the maximum permissible production rates of dredging activities should not exceed 1,400 m3/day for Phase 1 reclamation.

4.7.6          For filling activities for Phase 1 reclamation, no more than 12 dump cycles should be performed each day.  The maximum volume of filling per dump cycle should not exceed 250 m3.

4.7.7          For backfilling using public fill, the maximum fine content of fills should not exceed 5%.

4.7.8          For each reclamation phase, core filing activities should be carried out after completion of the seawall of that particular phase.

4.7.9          Any gaps that may need to be provided for marine access should be shielded by silt curtains to control sediment plume dispersion away from the site.  Filling activities for seawall construction should be carried out behind a silt curtain.

4.7.10      Closed-grab dredger should be used for dredging.  Dredging activities should be carried out behind a silt curtain.

4.7.11      Properly maintained closed mechanical grabs should be used to minimise spillage and should be sealed tightly while being lifted.

4.7.12      All barges and hopper dredgers should be fitted with tight seals to their bottom opening to prevent leakage of materials.

4.7.13      The decks of all vessels should be kept tidy and free of oil or other substances that might be accidentally or otherwise washed overboard.

4.7.14      Loading of barges and hoppers should be controlled to prevent splashing of dredged materials to the surrounding environment and barges and hoppers should under no circumstances be filled to a level which would cause overflowing of material or sediment laden water during loading and transportation.

4.7.15      All barges and dredgers should maintain adequate clearance between vessels and the seabed at all states of the tide and should operate at a reduced speeds to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash.

Deep Cement Mixing

 

4.7.16      To reduce any potential for water quality impact during the field trial of DCM, it is recommended to conduct the field trial after completion of the Phase 1 reclamation seawall so that the trial location can take place in a more sheltered location behind the Phase 1 reclamation.

4.7.17      It is also recommended that silt curtains should be employed during both the DCM field trial and during full-scale DCM for seawall construction to minimize the potential for water quality impacts due to any unforeseen sediment release.  A sand blanket should also be placed on top of the mud prior to DCM treatment to avoid seabed sediment disturbance.  The sand fill layer is to be around 1 m deep covering the area of DCM treatment.

4.7.18      Because the cement slurry injection uses highly pressured air and liquids, there is a possibility that slurry waste could leach out to the water body.  It is recommended that the cement slurry injection pressure should be carefully controlled to prevent leaching out of cement slurry and the slurry waste should be either properly disposed outside the site or used for back filling during reclamation after the slurry has solidified.

4.7.19      It is recommended to carry out water quality monitoring and audit during the DCM field trial. In-situ measurements of DO, turbidity and pH should be measured at both upstream and downstream of the DCM field trial. If the measurements indicate that the field trial have caused significant changes in water quality conditions at the downstream station in terms of turbidity and pH, appropriate actions should be taken to stop the field trial and mitigation measures such as slowing down the DCM process, or rescheduling of works would be implemented to reduce the impacts.  It is also recommended that water monitoring should be collected at selected water sensitive receivers during the field trial to confirm the water quality impact.  More detailed water quality assessment and water quality monitoring requirements for the DCM should be prepared based on the monitoring data of the field trial. All these should be summarized in a report to be submitted to EPD and AFCD for approval before starting the DCM operation. The monitoring requirements should be submitted to EPD at least 4 weeks before commencement of the DCM operation.

Marine Piling Activities for CBL Construction

 

4.7.20      All wastewater generated from the piling activities should be collected by a derrick lighter or other collection system and be treated before controlled discharge. Spoil should be collected by sealed hopper barges for proper disposal.

4.7.21      In view of the close vicinity of the coral community to the work site, silt curtain should be installed around the marine piling activities to reduce the any impact due accidental release of excavated sediment.

Construction Site Runoff and General Construction Activities

 

4.7.22      To minimise the potential water quality impacts from construction site runoff and various construction activities, the practices outlined in ProPECC PN 1/94 Construction Site Drainage should be adopted.

Surface Run-off

4.7.23      Surface run-off from construction sites should be discharged into storm drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sedimentation basins.  Channels or earth bunds or sand bag barriers should be provided on site to properly direct stormwater to such silt removal facilities.  Perimeter channels at site boundaries should be provided where necessary to intercept storm run-off from outside the site so that it will not wash across the site.  Catchpits and perimeter channels should be constructed in advance of site formation works and earthworks.

4.7.24      Silt removal facilities, channels and manholes should be maintained and the deposited silt and grit should be removed regularly, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.  Any practical options for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements in order to ensure adequate hydraulic capacity of all drains. Minimum distances of 100 m should be maintained between the discharge points of construction site runoff and the existing TKO saltwater intake.

4.7.25      There is a need to apply to EPD for a discharge licence for discharge of effluent from the construction site under the WPCO. The discharge quality must meet the requirements specified in the discharge licence. All the runoff and wastewater generated from the works areas should be treated so that it satisfies all the standards listed in the TM-DSS.  Reuse and recycling of the treated effluent can minimise water consumption and reduce the effluent discharge volume. The beneficial uses of the treated effluent may include dust suppression, wheel washing and general cleaning. It is anticipated that only a small quantity of wastewater would be generated from the works areas.

4.7.26      Construction works should be programmed to minimize soil excavation works in rainy seasons (April to September).  If excavation in soil could not be avoided in these months or at any time of year when rainstorms are likely, for the purpose of preventing soil erosion, temporary exposed slope surfaces should be covered e.g. by tarpaulin, and temporary access roads should be protected by crushed stone or gravel, as excavation proceeds.  Intercepting channels should be provided (e.g. along the crest / edge of excavation) to prevent storm runoff from washing across exposed soil surfaces.  Arrangements should always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.

4.7.27      Earthworks final surfaces should be well compacted and the subsequent permanent work or surface protection should be carried out immediately after the final surfaces are formed to prevent erosion caused by rainstorms.  Appropriate drainage like intercepting channels should be provided where necessary.

4.7.28      Measures should be taken to minimize the ingress of rainwater into trenches. If excavation of trenches in wet seasons is necessary, they should be dug and backfilled in short sections.  Rainwater pumped out from trenches or foundation excavations should be discharged into storm drains via silt removal facilities.

4.7.29      Open stockpiles of construction materials (e.g. aggregates, sand and fill material) on sites should be covered with tarpaulin or similar fabric during rainstorms.  Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

4.7.30      Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris from getting into the drainage system, and to prevent storm run-off from getting into foul sewers.  Discharge of surface run-off into foul sewers must always be prevented in order not to unduly overload the foul sewerage system.

4.7.31      Good site practices should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from the site area.  It is recommended to clean the construction sites on a regular basis.

Groundwater

4.7.32      Under normal circumstances, groundwater pumped out of wells, etc. for the lowering of ground water level in basement or foundation construction, and groundwater seepage pumped out of tunnels or caverns under construction should be discharged into storm drains after the removal of silt in silt removal facilities.

4.7.33      However, groundwater pumped out during construction of the northern cycle track footbridge and southern footbridge as well as the proposed sewage pumping station for TKO landfill development should not be discharged into the storm system as the groundwater may potentially be contaminated by leachate seepage from the TKO landfill.  The pumped out groundwater should be temporarily held in storage tanks on site as the volume is anticipated to be small.  It is recommended that the groundwater should be collected and tankered off site by a licensed wastewater collector for treatment and disposal at TKO PTW. The site investigation works at the detailed design stage of the Project should include groundwater sampling and analysis to determine the composition of groundwater.  The monitoring results of groundwater quality should be submitted to EPD and DSD for their approval.  Should the groundwater quality be found to exceed the TM standard for discharge into foul sewers, suitable treatment and disposal method of contaminated groundwater should be recommended.  It is proposed that a packaged treatment unit be installed at the site should pre-treatment be required.  All the required on-site pre-treatment of the collected groundwater should be implemented to the satisfaction of the EPD.  Sampling should be conducted for the groundwater to ensure that the groundwater quality meets the TM-DSS prior to the discharge of groundwater to the TKO PTW.  Estimate of the volume of groundwater should be made at the detailed design stage based on the site investigation data.   

Boring and Drilling Water

4.7.34      Water used in ground boring and drilling for site investigation or rock / soil anchoring should as far as practicable be recirculated after sedimentation.  When there is a need for final disposal, the wastewater should be discharged into storm drains via silt removal facilities.

Wastewater from Concrete Batching and Precast Concrete Casting

4.7.35      Wastewater generated from the washing down of mixing trucks and drum mixers and similar equipment should whenever practicable be recycled.  The discharge of wastewater should be kept to a minimum.

4.7.36      To prevent pollution from wastewater overflow, the pump sump of any water recycling system should be provided with an on-line standby pump of adequate capacity and with automatic alternating devices.

4.7.37      Under normal circumstances, surplus wastewater may be discharged into foul sewers after treatment in silt removal and pH adjustment facilities (to within the pH range of 6 to 10).  Disposal of wastewater into storm drains will require more elaborate treatment. 

Wheel Washing Water

4.7.38      All vehicles and plant should be cleaned before they leave a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  A wheel washing bay should be provided at every site exit if practicable and wash-water should have sand and silt settled out or removed before discharging into storm drains.  The section of construction road between the wheel washing bay and the public road should be paved with backfall to reduce vehicle tracking of soil and to prevent site run-off from entering public road drains.

Bentonite Slurries

4.7.39      Bentonite slurries used in diaphragm wall and bore-pile construction should be reconditioned and reused wherever practicable.  If the disposal of a certain residual quantity cannot be avoided, the used slurry may be disposed of at the marine spoil grounds subject to obtaining a marine dumping licence from EPD on a case-by-case basis.

4.7.40      If the used bentonite slurry is intended to be disposed of through the public drainage system, it should be treated to the respective effluent standards applicable to foul sewer, storm drains or the receiving waters as set out in the WPCO Technical Memorandum on Effluent Standards.

Water for Testing & Sterilization of Water Retaining Structures and Water Pipes

4.7.41      Water used in water testing to check leakage of structures and pipes should be reused for other purposes as far as practicable. Surplus unpolluted water could be discharged into storm drains.

4.7.42      Sterilization is commonly accomplished by chlorination.  Specific advice from EPD should be sought during the design stage of the works with regard to the disposal of the sterilizing water.  The sterilizing water should be reused wherever practicable.

Wastewater from Building Construction

4.7.43      Before commencing any demolition works, all sewer and drainage connections should be sealed to prevent building debris, soil, sand etc. from entering public sewers/drains.

4.7.44      Wastewater generated from building construction activities including concreting, plastering, internal decoration, cleaning of works and similar activities should not be discharged into the stormwater drainage system.  If the wastewater is to be discharged into foul sewers, it should undergo the removal of settleable solids in a silt removal facility, and pH adjustment as necessary.

Acid Cleaning, Etching and Pickling Wastewater

4.7.45      Acidic wastewater generated from acid cleaning, etching, pickling and similar activities should be neutralized to within the pH range of 6 to 10 before discharging into foul sewers.  If there is no public foul sewer in the vicinity, the neutralized wastewater should be tinkered off site for disposal into foul sewers or treated to a standard acceptable to storm drains and the receiving waters.

Wastewater from Site Facilities

4.7.46      Wastewater collected from canteen kitchens, including that from basins, sinks and floor drains, should be discharged into foul sewer via grease traps capable of providing at least 20 minutes retention during peak flow.

4.7.47      Drainage serving an open oil filling point should be connected to storm drains via a petrol interceptors with peak storm bypass.

4.7.48      Vehicle and plant servicing areas, vehicle wash bays and lubrication bays should as far as possible be located within roofed areas.  The drainage in these covered areas should be connected to foul sewers via a petrol interceptor.  Oil leakage or spillage should be contained and cleaned up immediately.  Waste oil should be collected and stored for recycling or disposal in accordance with the Waste Disposal Ordinance.

Sewage from Workforce

4.7.49      The presence of construction workers generates sewage.  It is recommended to provide sufficient chemical toilets in the works areas.  The toilet facilities should be more than 30 m from any watercourse.  A licensed waste collector should be deployed to clean the chemical toilets on a regular basis.

4.7.50      Notices should be posted at conspicuous locations to remind the workers not to discharge any sewage or wastewater into the nearby environment.  Regular environmental audit on the construction site can provide an effective control of any malpractices and can encourage continual improvement of environmental performance on site.  It is anticipated that sewage generation during the construction phase of the project would not cause water pollution problem after undertaking all required measures.

Accidental Spillage of Chemicals

4.7.51      Contractor must register as a chemical waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354) and its subsidiary regulations in particular the Waste Disposal (Chemical Waste) (General) Regulation should be observed and complied with for control of chemical wastes.

4.7.52      Any service shop and maintenance facilities should be located on hard standings within a bunded area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving activities with potential for leakage and spillage should only be undertaken within the areas appropriately equipped to control these discharges.

4.7.53      Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:

·         Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling and transport.

·         Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents.

·         Storage area should be selected at a safe location on site and adequate space should be allocated to the storage area.

 

Construction Works at Storm Culvert or in Close Proximity of Inland Water or Seafront

 

4.7.54      To minimize the potential water quality impacts from the construction works located at or near any river channels, natural streams or seafront, the practices outlined in ETWB TC (Works) No. 5/2005 “Protection of natural streams/rivers from adverse impacts arising from construction works” should be adopted where applicable.  Relevant mitigation measures are listed below:

·         The proposed works should preferably be carried out within the dry season where the flow in the storm culvert/river channel/stream is low.

·         The use of less or smaller construction plants may be specified to reduce the disturbance to the riverbed.

·         Temporary sewerage system should be designed to prevent wastewater from entering the river, streams and sea.

·         Temporary storage of materials (e.g. equipment, filling materials, chemicals and fuel) and temporary stockpile of construction materials should be located well away from any water courses during carrying out of the construction works.

·         Stockpiling of construction materials and dusty materials should be covered and located away from any water courses.

·         Construction debris and spoil should be covered up and/or disposed of as soon as possible to avoid being washed into the nearby water receivers.

·         Construction activities, which generate large amount of wastewater, should be carried out in a distance away from the waterfront, where practicable.

·         Mitigation measures to control site runoff from entering the nearby water environment should be implemented to minimize water quality impacts.  Surface channels should be provided along the edge of the waterfront within the work sites to intercept the runoff.

·         Construction effluent, site run-off and sewage should be properly collected and/or treated.

·         Any works site inside the storm water courses should be temporarily isolated, such as by placing of sandbags or silt curtains with lead edge at bottom and properly supported props to prevent adverse impact on the storm water quality.

·         Silt curtain should be installed around the construction activities for the proposed landing steps at the seafront of TCS to minimize the potential impacts due to accidental spillage of excavated materials.

·         Proper shoring may need to be erected in order to prevent soil/mud from slipping into the storm culvert/river/stream/sea.

·         Supervisory staff should be assigned to station on site to closely supervise and monitor the works.

 

Operational Phase

 

Eastern Channel

 

4.7.55      The EDC and inner Junk Bay are proposed to be used for secondary contact recreation.  To reduce the water quality impact on the EDC and inner Junk Bay under the ultimate development scenario, it is recommended to divert all storm discharges from Catchment M and 60% of the total discharges from Catchment L to the southern boundary of TCS (refer to Section 5.7.7 of the EIA Report). 

Impact from Emergency Sewage Bypass

 

4.7.56      It is recommended to conduct water quality field survey at EDC after the proposed drainage diversion works (as mentioned in Section 5.7.6 of the EIA Report) is completed to confirm the suitability of the proposed recreation uses at EDC.   The field survey should be conducted at a frequency of twice per year in dry season and wet season respectively after operation of the drainage diversion works.  The suitability of the proposed recreation uses at EDC should be continuously reviewed with reference to the field survey data.  After a 3-year operation period, a review should be conducted to determine whether the field survey programme should be discontinued. 

4.7.57      In the very unlikely event of any sewage bypass occurring at the seawall, the proposed secondary contact recreation zone in EDC and Junk Bay should be closed. It is recommended that relevant government departments including EPD and LCSD shall be informed by DSD as soon as possible of any emergency bypass so that appropriate actions can be taken to prevent any water sports activities to be carried out in EDC and Junk Bay.  The Plant operators should maintain good communications with various concerned parties.  A list of address, email address, phone and fax number of key persons in relevant departments responsible for action should be made available to the plant operators.  Water quality monitoring should be carried out by DSD to determine when conditions are suitable for re-opening of the EDC and Junk Bay for recreational purposes.

Reservoir Cleansing

 

4.7.58      All cleansing effluent generated from the proposed Pak Shing Kok high level fresh water service reservoir should be collected by a licensed waste collector for proper disposal and should not be discharged into the nearby water environment.

Sewage Pumping Station and Rising Mains

 

4.7.59      The emergency bypass location of the sewage pumping station for the recreational development at TKO landfill will be designed to be located 500 m away from the TKO saltwater intake.  A standby pump will be provided to minimize the potential water quality impact from sewage overflow.

Handling of Site Drainage and Effluent

 

4.7.60      Connection of sewage generated from the administration building at the WCR toll plaza to the existing gravity sewer in TCS is considered not feasible (about 1km away).  As the sewage quantity generated from the site (about 80 employed population) is small (about 5m3/d), sewage would be collected in holding tank and transferred by lorry to TKO Preliminary Treatment Works (PTW) for treatment.  Transfer of sewage should be arranged within office hours of the TKO PTW to facilitate normal plant operators. The proposed sewage tankering away services should be provided on a regular basis to prevent any discharge of sewage to the nearby storm system. If the future operator of the administration building changes the sewage disposal scheme, using either a pumping scheme or a small treatment plant due to change of development parameter, the proposed holding tank could still be used to withhold the raw sewage in case of emergency. It is therefore not expected that there would be raw sewage discharges into the Junk Bay provided that the measures recommended above are properly implemented.

4.7.61      For handling, treatment and disposal of other operational stage effluent, the practices outlined in ProPECC PN 5/93 should be adopted where applicable.  The following relevant recommendations should be followed:

·         Drainage outlets provided in open areas and areas subjected to a substantial amount of wind-blown rain, including open carparks, balconies, podiums, yards, etc., should be connected to storm drains.

·         Drainage outlets provided in covered areas, including covered podiums and other roofed areas, should be discharged to foul sewers.

·         Subsoil drains of slopes, road embankments and earth retaining structures, and groundwater collection drains for basements, subways and tunnels, and similar drains, should under normal circumstances, be connected to storm water drains.  Silt removal facilities should be provided where necessary.  A separate drainage system that connects to foul sewers should be provided to collect wastewater from basements, subways and tunnels and similar areas.

·         Drainage serving the proposed open lorry park should be connected to storm water drains via a petrol interceptor that would allow storm water bypass during peak flow periods.

·         Drainage serving any covered carparks should be connected to foul sewers via petrol interceptors.

·         To prevent hazards from sewage overflowing from the proposed pumping station for handling sewage arising from TKO landfill site, sewage pump sumps should be provided with a standby pump whose capacity should not be less than any of the duty pumps, and duty pumps should not be required to operate more than 10 on-off cycles per hour.

·         Surface water drainage should be provided for discharging storm water off slopes and from open surfaces.  Such drainage as normally collected in open surface channels should be led to storm water drains via silt removal facilities.  Runoff in kerb gutters of roads or channels of building platforms should pass through a gully pit with necessary gratings to prevent objects from entering the storm water drains.

 

4.7.62      For maintenance of stormwater drainage system, reference should be made to Environment, Transport and Works Bureau (ETWB) Technical Circular (Works) No. 14/2004 “Maintenance of Stormwater Drainage Systems and Natural Watercourses” where applicable.  The circular sets out the departmental responsibilities for the maintenance of stormwater drainage systems and natural watercourses in government and private lands. 

4.7.63      The implementation schedule for the recommended water quality mitigation measures is presented in Appendix C.