10.
FISHERIES
10.1
INTRODUCTION
10.1.1
This chapter assesses the impacts of the Project upon
commercial fisheries.
10.1.2
The Project consists of the construction of an extension of the
golf course on Kau Sai Chau, Sai Kung by 18 holes, from 36 to 54 holes. The golf course is basically constructed
on hill slopes, thus it is a terrestrial rather than a marine project. No component of the Project would cause a
permanent loss of marine habitat.
The Project does, however, include three components that could affect
the marine environment. These are a
desalination plant to provide irrigation water and a temporary barging point for
transport of building and excavated materials during construction. The potential impacts of these project
components and the potential for degradation of marine water quality by surface
runoff are the key concerns of this assessment.
10.1.3
The objective of this assessment is to identify existing fisheries
resources in the Fisheries Assessment Area so as to evaluate any impacts of the
Project at both construction and operational phases and, where required, to
propose mitigation measures to minimize adverse impacts. The assessment follows the criteria and
guidelines in Annexes 9 and 17 of the EIAO TM and the EIA Study Brief No. ESB-064-2000.
10.1.4
The assessment is mainly focused on the two marine structures
for the proposed golf course and the receiving water bodies. These are the temporary barging point
and the permanent desalination plant.
The impacts from site formation are covered in the chapter for terrestrial
ecological assessment in this report and in this chapter with respect to
fisheries.
10.1.5
The nature and scope of the Project is described in Section 2 of this Report. In accordance with the EIA Study Brief
No. ESB-064-2000, this section identifies and assesses the fisheries impact
associated with the Designated Project (DP) described in Section 2.
10.1.6
There are no scheduled concurrent designated projects in the
vicinity of the proposed golf course extension, temporary barging point or
desalination plant during the construction or operation phase.
10.2
Environmental Legislation,
Standards and Guidelines
10.2.1
The following Hong Kong SAR Government legislation, standards
and guidelines are relevant to the assessment of impacts to fisheries associated
with the construction and operation of the project:
l
Environmental
Impact Assessment Ordinance (Cap.499) and the Technical Memorandum on
Environmental Impact Assessment Process (EIAO TM);
l
Fisheries
Protection Ordinance (Cap. 171) and its subsidiary legislation, the Fisheries
Protection Regulations;
l
Marine
Fish Culture Ordinance (Cap. 353) and associated subsidiary legislation; and
l
Water
Pollution Control Ordinance (WPCO) and its supporting regulations and statements.
10.3
Environmental Baseline Methodology
10.3.1
The proposed new golf course is located on eastern Kau Sai
Chau, Sai Kung (Figure
10.3.2
Literature was reviewed to provide information on existing
conditions in the assessment area, and to identify fisheries resources that may
be affected by the Project.
Literature review included Government and private sector reports,
independent and Government published literature and academic studies. Literature review included the
following:
l
Port
Survey 96/97 (AFCD 1998);
l
Port
Survey 2001-2002 (AFCD 2003);
l
AFCD
annual reports
10.4
Assessment Methodology
10.4.1
Impacts to fisheries were assessed based on the guidelines in
Annexes 9 and 17 of the TM, the consultants’ local knowledge and international
standards.
10.4.2
The significance of fisheries impacts is evaluated based
primarily on the criteria set forth in Annex 9 of the TM:
l
Nature
of impact;
l
Size
of affected area;
l
Loss
of fisheries resources/production;
l
Destruction
and disturbance of nursery and spawning grounds;
l
Impact
on fishing activity; and
l
Impact
on aquaculture activity.
10.4.3
Impacts are generally ranked as "minor",
"moderate" or "severe", although in a few cases a ranking
of "minimal" (less than "minor") may be given. The ranking of a given impact would vary
based on the criteria listed above.
For example, an impact might be ranked as "minor" if it
affected only common species and habitats, or if it affected only small numbers
of individuals or small areas, whereas it might be ranked as "severe"
if it affected rare species or habitats, large numbers of individuals or large
areas. The major factors giving
rise to a ranking are explained in the text. As noted in Annex 16 of the TM, a degree
of professional judgment is involved in the evaluation of impacts.
10.5
BASELINE CONDITIONS
10.5.1
The proposed golf course lies within the Port Shelter WCZ. There are some sites of fisheries
importance within the Fisheries Assessment Area for the present Project and
within the Port Shelter WCZ (Fig.
Sites of Fisheries
Importance
10.5.2
The following sites of fisheries importance are located within
or on the boundary of the Fisheries Assessment Area and are shown in Figure
l
Tiu
Cham Wan Fish Culture Zone.
l
Tai
Tau Chau Fish Culture Zone.
l
Kai
Lung Wan Fish Culture Zone.
10.5.3
Three additional sites of fisheries importance are located in
the Port Shelter WCZ and are shown in Figure
l
Kau
Sai Fish Culture Zone.
l
Ma Lam
Wat Fish Culture Zone.
l
Leung
Shuen Wan Fish Culture Zone.
10.5.4
A fisheries protection area has been proposed for establishment
in Port Shelter (Figure 10.2b). Within the fisheries protection area
fishing would be regulated and artificial reefs would be deployed. A “No-take Zone” within the fisheries
protection area is also proposed at outer Port Shelter. Although designated to provide specific
controls on fishing activities, the area can be regarded as a sensitive water
body and any impacts should be minimised as far as possible to achieve
compliance with the Water Quality Objectives.
10.5.5
No other designated or recognized sites of fisheries importance
lie within the assessment area or the Port Shelter WCZ
Capture
Fisheries
10.5.6
Detailed data on HKSAR capture fisheries in the fisheries study
area were taken from the results of Port Survey. Port survey is the most comprehensive
fisheries study conduced by AFCD every few years.
10.5.7
Within HKSAR waters, the highest yields for local fisheries
were mainly derived from the eastern and northeastern coasts as indicated in
the AFD Port Survey 96/97, while the western waters were comparatively less
productive.
10.5.8
The Port Shelter WCZ is within the “Port Shelter” (SE10)
sector (Figure 10.3). In the 96/97 Port Survey “Port Shelter”
sector ranked 11th of the 12 sectors in terms of average adult fish
production, and 10th in terms of average production value (Table 10.1). However, the fry production from this
sector ranked 2nd in
10.5.9
More recent data were extracted from the latest Port Survey
in 2001-2002. In this report a
uniform grid of
10.5.10
The results of the 2000/2001 Port Survey show that the fisheries
production in Port Shelter is generally distributed in a gradient of increasing
production from the inner bay to the outer bay. The waters at the innermost part of Port
Shelter (Grid cells Q9, R9 & S9) produced 50 to
10.5.11
Of the fishing areas in SE10 (Port Shelter), those around Kau
Sai Chau are the focus of this assessment (i.e. areas 193, 194 & 199). The proposed desalination plant would be
located in Fishing Area 193, while the temporary barging point would be located
in Fishing Area No. 194 (Figure 10.3).
Table 10.1 Fishing Areas within SE10 “Port
Shelter” sector
Fishing Area |
Area |
Total Production |
Total fish fry |
Total value |
Production /ha |
Fish fry/ha |
Value/ha |
Rank of Production /ha |
Rank of Fish fry/ha |
Rank of Value/ha |
|
121B |
|
17,495.75 |
7,363.44 |
\ |
179,000.00 |
0.42 |
\ |
10.23 |
117 |
\ |
178 |
147 |
Bate & Fung Head |
2,502.55 |
5,885.31 |
45,938.65 |
373,642.94 |
2.35 |
18.36 |
149.3 |
172 |
67 |
170 |
148 |
Tung & Sai Wan |
392.87 |
44,334.48 |
1,596.49 |
259,836.70 |
112.85 |
4.06 |
661.38 |
86 |
85 |
156 |
182 |
|
150.94 |
25,390.89 |
246,851.56 |
1,511,295.39 |
168.22 |
1,635.40 |
10,012.40 |
58 |
2 |
20 |
183 |
Lung Ha Wan |
1,160.51 |
29,767.67 |
5,000.00 |
771,847.22 |
25.65 |
4.31 |
665.09 |
144 |
83 |
155 |
184 |
Sheung Sze Wan |
123.06 |
20,041.39 |
21,897.51 |
464,836.06 |
162.85 |
177.95 |
3,777.18 |
61 |
27 |
66 |
185 |
|
400.99 |
114,592.35 |
68,301.51 |
3,332,517.36 |
285.78 |
170.33 |
8,310.79 |
27 |
28 |
24 |
186 |
Silver |
246.25 |
93,140.53 |
36,440.32 |
2,583,979.73 |
378.24 |
147.98 |
10,493.39 |
20 |
30 |
17 |
187 |
Pak Shui Woon |
268.34 |
30,490.23 |
10,432.45 |
1,405,936.64 |
113.63 |
38.88 |
5,239.43 |
84 |
51 |
51 |
188 |
Hebe Haven |
167.61 |
17,952.76 |
4,561.40 |
615,498.53 |
107.11 |
27.21 |
3,672.15 |
88 |
64 |
71 |
189 |
Ma |
449.84 |
44,771.57 |
115,355.45 |
1,647,162.48 |
99.53 |
256.44 |
3,661.67 |
94 |
21 |
73 |
190 |
Sai Kung |
127.03 |
38,697.06 |
137,901.31 |
1,389,551.79 |
304.62 |
1,085.56 |
10,938.58 |
25 |
7 |
14 |
191 |
Yeung Chau |
134.01 |
42,957.33 |
119,194.41 |
1,481,652.77 |
320.55 |
889.44 |
11,056.25 |
22 |
9 |
11 |
192 |
|
389.31 |
39,870.00 |
445,936.92 |
2,592,496.36 |
102.41 |
1,145.46 |
6,659.22 |
90 |
6 |
32 |
193 |
Kau Sai Chau W |
380.98 |
22,241.11 |
11,777.77 |
860,669.41 |
58.38 |
30.91 |
2,259.10 |
121 |
60 |
101 |
194 |
Kau Sai Chau E |
189.45 |
17,418.48 |
101,364.95 |
658,251.27 |
91.94 |
535.04 |
3,474.46 |
99 |
13 |
76 |
195 |
Tiu Chung Chau |
632.48 |
29,751.83 |
11,777.77 |
734,421.40 |
47.04 |
18.62 |
1,161.18 |
128 |
66 |
134 |
196 |
Wong Chuk Wan |
149.92 |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
197 |
Tai Mong Tsai |
64.69 |
2,508.31 |
104,179.69 |
328,083.33 |
38.78 |
1,610.48 |
5,071.72 |
136 |
3 |
54 |
198 |
Tsam Chuk Wan |
129.71 |
2,508.31 |
104,179.69 |
328,083.33 |
19.34 |
803.16 |
2,529.30 |
152 |
10 |
95 |
199 |
|
109.79 |
24,696.50 |
627,340.31 |
2,153,770.35 |
224.94 |
5,713.88 |
19,616.77 |
40 |
1 |
2 |
200 |
Sham Tuk Mun |
84.62 |
1,420.18 |
104,179.69 |
277,812.50 |
16.78 |
1,231.15 |
3,283.05 |
154 |
5 |
81 |
201 |
Tai She Wan |
264.3 |
45,864.27 |
22,677.15 |
458,176.97 |
173.53 |
85.8 |
1,733.55 |
56 |
35 |
115 |
202 |
Leung Shuen Wan |
128.58 |
63,203.72 |
62,245.59 |
1,331,404.47 |
491.56 |
484.11 |
10,354.80 |
15 |
15 |
19 |
203 |
|
117.37 |
60,502.97 |
50,989.86 |
1,220,092.28 |
515.51 |
434.45 |
10,395.68 |
14 |
18 |
18 |
204 |
Futaupun & Wang Chau |
1,097.46 |
40,229.07 |
40,033.19 |
1,091,257.24 |
36.66 |
36.48 |
994.35 |
138 |
55 |
138 |
205 |
|
2,122.77 |
52,841.48 |
112,661.31 |
1,720,289.50 |
24.89 |
53.07 |
810.4 |
145 |
44 |
149 |
206 |
Pak Lap |
104.78 |
3,390.59 |
7,441.41 |
130,764.72 |
32.36 |
71.02 |
1,247.96 |
141 |
41 |
132 |
207 |
|
858.63 |
3,100.48 |
7,441.41 |
116,369.37 |
3.61 |
8.67 |
135.53 |
171 |
80 |
171 |
208 |
Long Ke Wan |
139.64 |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
\ |
209 |
Fan Tsang Chau |
632.19 |
387.07 |
\ |
7,000.00 |
0.61 |
\ |
11.07 |
174 |
\ |
177 |
210 |
Tai Yue Ngam |
903.4 |
360.04 |
\ |
19,843.75 |
0.4 |
\ |
21.97 |
178 |
\ |
175 |
SE10 |
Port Shelter |
32,119.84 |
925,679.42 |
2,627,697.77 |
30,045,543.86 |
28.82 |
81.81 |
935.42 |
11 |
2 |
10 |
10.5.12
Five locations within Port Shelter were reported as home
ports in the 2001/2002 Port Survey, including Pak Sha Wan/Ma Nam Wat, Tai Tau
Chau/Kai Lung Wan, Leung Shuen Wan, Sai Kung, and Kau Sai. Only one of them (Tai Tau Chau/Kai Lung
Wan) lies on the boundary of the Fisheries Assessment Area, while others lie
outside.
10.5.13
Among these, Sai Kung is the biggest home port. 160 out of the 4,857 fishing vessels in
10.5.14
Tai Tau Chau/Kai Lung Wan is the closest homeport to the golf
course location. In the 96/97 Port
Survey 129 of the 4857 fishing vessels in
10.5.15
The focal areas for capture fisheries issues are the marine water
around Kau Sai Chau, covering the 500 m Fisheries Assessment Area, in which the
desalination plant and temporary barging point would be located. These areas are covered by Fishing Areas
193 (Kau Sai Chau W), 194 (Kau Sai Chau E) and 199 (
10.5.16
It is noteworthy that Fishing Area 199 Urn Island ranked
first in Hong Kong in terms of fish fry production per hectare (5,714
tails/ha). This contributed to its
high ranking (2nd in Hong Kong) for total value/ha among Fishing
Areas in all of
10.5.17
The 1996-97 data revealed that the dominant taxa reported
from the areas as landed catches are typically of low economic value. In rank order (by weight), the majority
of the top 10 fish types caught were mixed fish, Siganus oramin (rabbitfish), Sardinella jussieu (Sardine), Argyrosomus spp. (Croaker), Sebasticus marmoratus (Rockfish), and Platycephalus indicus (Flathead) (Table 10.2).
Table 10.2 Top ten
adult fish caught in the three Fishing Areas
Fishing |
Rank order of catch by Adult Fish Weight |
|||||||||
1 |
2 |
3 |
4 |
5 |
6 |
7 |
8 |
9 |
10 |
|
193 |
MIXSPP (Mixed fish) |
ARGSPP (Croaker) |
CARANX (Scad) |
SPARID (Sea breams) |
SARJUS (Sardine) |
MCRAB (Mud crab) |
NEMJAP (Melon coat) |
SIGORA (rabbit fish) |
LOLEDU (Squid) |
PLAIND (Flathead) |
194 |
MIXSPP (Mixed fish) |
SARJUS (Sardine) |
SIGORA (rabbit fish) |
SPARID (Sea breams) |
LOLEDU (Squid) |
SEBMAR (Rockfish) |
MCRAB (Mud crab) |
ARGSPP (Croaker) |
NEMJAP (Melon coat) |
CARANX (Scad) |
199 |
SIGORA (rabbit fish) |
MIXSPP (Mixed fish) |
SEBMAR (Rockfish) |
SPARID (Sea breams) |
PLOANG (Marine catfish) |
SEPPHA (Cuttle fish) |
MCRAB (Mud crab) |
LOLEDU (Squid) |
LOLIGO (Squid) |
MONCHI (File fish) |
10.5.18
As reported in the Port Survey 2001/2002, the catches from
the grid cells in which the desalination plant (Grid Cell R10) and temporary
barging point (Grid Cell S10) would be located (direct impact grid cells) (Figure 10.4) were not high, having
100-200 kg/ha adult fish production. Fishing vessels operated in these two
grid cells include single trawler, shrimp trawler, gill netter, long liner,
purse seiner, miscellaneous craft and Sampan. Sampan was the dominant fishing vessel in
both grid cells, as all other fishing vessels were less than 10 in number. About 50-100 fishing vessels operated in
S10, while 100-400 fished in R10.
Among these, however, only less than 10 were over 15 m in length in each
grid cell.
10.5.19
The top species (by weight of fish) in these two grid cells
in the 2000-2001 Port Survey was rabbitfish, with production of 40-60 kg/ha in
R10 and 20-40 kg/ha in S10.
10.5.20
Fishing Area 199 Urn Island ranked the highest in
10.5.21
For the economic value of the production, both cells ranked
medium in
10.5.22
These figures demonstrate that among the two direct impact grid
cells, S10 (in which the proposed temporary barging point is located) is of
medium to high importance to capture fishing operations in Hong Kong, while R10
(proposed desalination plant) is of medium importance.
Mariculture
10.5.23
The predominant type of mariculture in
10.5.24
Marine fish culture is protected and regulated by the Marine
Fish Culture Ordinance (Cap. 353) which requires all marine fish culture
activity to operate under licence in designated fish culture
zones. Currently, there are 26 fish
culture zones in which 1,125 licensed operators occupy a total sea area of 209
ha. In 2004, the production from
local marine fish culture was 1,540 tonnes (of value 79 million HK dollars),
constituting 9.1% of the local live marine fish consumption.
10.5.25
Water quality in Marine FCZs is regulated under the
WPCO and its supporting regulations and statements. Within Fish Culture Subzones, the
dissolved oxygen level should not be less than 5 mg l-1 for 90% of
the sampling occasions during the year; values should be calculated as water
column average (arithmetic mean of at least 3 measurements at 1
metre below
surface, mid-depth and 1 metre above seabed). In addition, the concentration of
dissolved oxygen should not be less than 2 mg l-1 within 2 metres of
the seabed for 90% of the sampling occasions during the year, and the annual
geometric mean of E. coli should not
exceed 610/100 ml.
10.5.26
Of the 26 Fish Culture Zones (FCZs) in
10.5.27
Tiu Cham Wan FCZ is the nearest to the Project area. It is located in a sheltered bay just
below the hill slopes adjacent to the proposed golf course. However, it has not been utilized for
mariculture for many years there are no fish culture rafts at the site. The other two FCZs, i.e. Tai Tau Chau
east of Kau Sai Chau and Kai Lung Wan west of Kau Sai Chau, were located
distant from the proposed golf course near the boundary of the fisheries
assessment area.
10.6
FISHERIES SENSITIVE
RECEIVERS
10.6.1
Fisheries sensitive receivers identified within the Study
Area include the followings:
l
Grid
cell R10 and S10; and
l
Six
fish culture zones, particularly Tai Tau Chau and Kai Lung Wan FCZs.
10.7
IMPACT ASSESSMENT
Identification of Environmental
Impacts
10.7.1
Construction of the golf course, the desalination plant and
the temporary barging point would include site preparation and clearance,
excavation, dredging, backfilling, and structure construction.
10.7.2
Potential sources of impact during the construction phase
include:
l
Temporary
loss of fishing grounds; and
l
Marine
water quality impact caused by coastal construction.
10.7.3
Potential sources of impact during the operation phase
include:
l
Marine
water quality impact caused by the discharge from the desalination plant; and
l
Marine
water quality impact caused by runoff from the future golf course.
Construction
phase
10.7.4
This section of the report considers the potential impacts of
project construction on capture fisheries and mariculture. The marine construction activities include
the desalination plant works which involve dredging and backfilling, and the
temporary barging point. Other
activities at the construction site include site preparation and clearance and
excavation.
Fishing
ground loss
10.7.5
In order to reduce the traffic burden on the only road on the
existing golf course, a temporary barging point will be constructed on the east
side of Kau Sai Chau. It will be
used for delivery of supporting materials or equipment for construction to the
construction site. The dimension of this temporary pier would be 20m in width x
40m in length. The temporary barging point will be a floating-pontoon (see Figure 9.8), to replace the pile-supported
design from the early stage of this study (see Figure 9.7). The entire pier is designed to float thereby avoiding
any and all direct impacts due to loss of seabed. No filling works would be required for
the barging point. Although there
would be no direct loss of seabed area, the entire shallow sea area occupied by
this barging point (800 m2) would be unavailable for fishing
operations. Construction of the
proposed golf course would require 1 year.
After the construction works are finished, the temporary barging point would
be removed. The area occupied by
the barging point would again be available for capture fisheries after the
1-year golf course construction period.
10.7.6
Besides the temporary barging point, a desalination plant would
be constructed on the west side of Kau Sai Chau, beside the existing ferry
pier. The desalination plant itself
would affect terrestrial habitats only but two pipelines would extend into the
sea. These would collect seawater
and discharge effluent form the desalination plant, respectively. The two pipelines would be installed
beneath the seabed surface by first dredging and then backfilling to cover the
two pipelines. There would be a short-term
and temporary seabed loss during the construction of these two pipelines.
10.7.7
The dimension of the intake pipelines would be 110 m in
length by 60 cm in diameter. The
discharge pipeline would be 40 m in length and 30 cm in diameter. A dredging area of about 1,500 m2
would be required for installation of the pipelines. Construction works on the pipelines would
be completed within 3 months (for dredging, installation and backfilling). The area disturbed by the dredging works
would not be available for fisheries during this period.
10.7.8
The fisheries production and catch value in grid cells R10
and S10 were ranked as medium and medium to high. However, the small area of fishing
ground affected (about 1,500 m2 (0.15 ha) & 800 m2 (0.08
ha) or 0.02% of R10 and 0.01 % of S10 grid cells), the temporary nature of the
loss, and the short period of impact duration (about 1 year at the barging
point and about 3 months for the pipelines) must all be considered when
evaluating fisheries impact. Based
on these considerations, the impact of fishing ground loss is ranked as minimal. This temporary loss would not be
significant to the proposed fisheries protection area which covers all of Port
Shelter.
Marine water quality
Desalination
plant
10.7.9
Installation of the two pipelines for the desalination plant will
involve dredging of approximately 1,500 m³ seabed materials and backfilling,
and might lead to re-suspension of sediments. Without controls or mitigation
measures, suspended solids would increase the turbidity of the waters thus
reducing the amount of light reaching the sea bed. As the suspended particles settle they
could bury sessile organisms, or settle on the surface of other benthos. Re-suspension of sediments would also
reduce oxygen levels and potentially release pollutants into the water
column. All these consequences
could affect the health and survival of marine organisms, including commercial
species, as well as mariculture species if the sediments are carried to Fish Culture
Zones by currents. These impacts
would be short-term (less than 3 months), small-scale and localised in nature,
and are therefore mitigable. As
discussed in Section 6 of this report (Section
6.9), 50mg/L is adopted as the criteria for suspended solid for fish
culture zone. This standard has
been applied in many other studies in which impacts on fish culture zone in
Golf course
site
10.7.10
Siltation is could affect marine water quality. Sediment would be generated by
construction works on the proposed golf course site, foremost among these being
earthworks for formation of the fairways, tees and greens. Cut and fill earth works, if not properly
controlled could cause sediment runoff.
10.7.11
Construction site runoff can contain sediments, organic
substances, oil, grease and solvents that can affect marine ecology and
therefore fisheries. These
substances can increase turbidity, decrease oxygen levels and introduce
contaminants, potentially injuring or killing benthic organisms (such as
shellfish) and driving motile organisms (such as fishes) away from the vicinity
and thereby causing a short-term degradation of fisheries resources. If the pollutants are carried by
currents to Fish Culture Zones, mariculture species might also be affected.
10.7.12
Impacts would be short-term and self-correcting after project
completion even in the absence of active restoration efforts. This was the case following construction
of the existing 36-hole golf course, which required a larger earthmoving
operation than would the proposed 18-hole extension. Construction site runoff could enter the
sea either through existing watercourses on Kau Sai Chau or through the temporary
drainage system of the construction site. It was stated clearly in both the water
quality assessment section and the terrestrial ecology section of this report
that only minimal disturbance would affect the water courses. There would also
be a temporary drainage system which would receive flows from all areas subject
to earth works. As stated in Section 6 Water Quality Assessment of
this report, the majority of the heavy construction works, in particular, the
cut and fill earth works, would be conducted within the 2005-2006 dry season. This means that the exposed cut and fill
slopes would be covered with new turfgrass prior to the onset of the wet season
in 2006. This would minimise runoff
because the slopes would be stabilised by vegetation. Any runoff would be retained for turf
grass irrigation. In addition,
there would be measures to control sedimentation such as silt fencing. Unacceptable marine water quality impacts
are not be predicted. The impacts
of such runoff would be ranked as minor but mitigation measures are required.
Temporary
barging point
10.7.13
To avoid marine water quality impacts, a floating barging
point (see Figure 9.8 of this
report) is proposed as an alternative to the originally proposed barging point on
piles (see Figure 9.7 of this
report). The alternative floating
barging point would require no underwater construction works and no
piling. Construction works would
take place on land above the high-tide line. This would avoid any construction works
in the shallow waters of the coastal zone or on the seabed. It would also avoid production of
sediment-bearing waste water during piling works. Impacts on marine water and fisheries
resources would thus be avoided.
Operation
phase
10.7.14
This section of the report considers the potential impacts of
Project operation on capture fisheries and mariculture.
Water quality change by the
desalination plant
10.7.15
The water quality assessment showed that the operation phase
effluent from the desalination plant would have only limited and localized
impacts on marine water quality.
10.7.16
During the dry season (November to March each year, about 5-6
months) the desalination plant would operate and produce freshwater for turfgrass
irrigation. During the wet season,
for around 6-7 months, the plant would be shut down except for maintenance or
infrequent contingencies. Thus the
plant would be operated for less than half of each year. Seawater would be taken in (about 3,816 m3/d)
and the water within would be extracted through a Reverse Osmosis process
(maximum 1,450 m3/d). The
remaining seawater would have higher salinity and would be discharged as return
flow. The discharge flow rate would
be 0.0168 m3/s.
10.7.17
The main difference between the discharge and the normal
seawater would be elevated salinity in the discharge. It was reported in the water quality
assessment section of this report that about 40% of freshwater will be
extracted out of the seawater, and the salinity of the discharge would be 56.8
ppt. This represents an increase of
22.7 ppt when compared with the ambient salinity of 34.1 ppt. This increase would dilute very quickly,
dropping to 2.643 ppt above normal at the edge of the near field region (about 5.06
m from the discharge point), and to 1.103 ppt above normal about 200 m away and
south of the pier. This scenario
complies with the water quality criterion of no more than a 10% change. The increase itself is also negligible because
the ambient salinity also fluctuates greatly with varying amounts of rainfall. The nearest site of fisheries importance
would be Kai Lung Wan FCZ which is located about 500 m north of the pier. The change in salinity there would be undetectable.
Besides salinity, other related WQO parameters (which will be affected by the
desalination plant) including SS elevation (0.695 mg/L vs the tolerance criteria of 1.485
mg/L), sediment deposition rate (0.030 kg/m2/day vs the criteria of 0.1kg/m2/day),
and oxygen depletion (0.0027 mg/L, undetectable) at the nearest water quality
receivers (80m, the bedrock with corals) are also well within the WQO
requirements. The changes in these water quality parameters at Kai Lung Wan FCZ
would also be much lower or undetectable.
10.7.18
The active ingredient in the anti-scalant proposed for use in
the desalination plant would contain no heavy metals or hazardous substances. None of the substances in this product
are considered carcinogenic and the potential toxicity is low. The concentration of anti-scalant prior
to discharge was expected to be 3 mg/L. According to the dilution factor (Table 6.9 in Water Quality Assessment),
this concentration would drop to 0.168 mg/L at 50 m distance, and further
dilute to 0.146 mg/l at 200 m. The
anti-scalant it is not predicted to have adverse impacts on aquatic biota given
the low toxicity and low initial concentration (Appendix 6.3 in Water Quality Assessment Section). Minimal impact is predicted and
mitigation measures are not required.
Water quality impacts
10.7.19
Runoff from golf course turfgrass has been shown over 9 years
of water quality monitoring to be free of fertilizers and pesticides (see Section 6.4). Based on this performance history, it is
unlikely that detectable concentrations of such chemicals would to enter the
sea or affect marine ecological or fisheries resources.
10.7.20
Fertilizes are mostly inorganic nutrients (nitrogen,
phosphorous, potassium). Should
large volumes of such nutrients be introduced to the sea, there would be a risk
of exacerbating the problem of red tide by increasing concentrations of nutrients
in seawater. Due to proper handling
and applications of fertilizers at Kau Sai Chau this has not happened during 10
years of operation. Although all
pesticides used at Kau Sai Chau are selected from a list of pesticides approved
for use in
10.7.21
The use fertilizers and pesticides will be controlled and
minimized by following a Turfgrass Management Plan which has been proven at the
existing golf course over the last 10 years. During that time there was never an
incident where marine or freshwaters around/or Kau Sai Chau showed levels of
nutrients or pesticides that were not in compliance with the WQO. Although it is not possible to improve a
flawless record, the amount per unit area of fertilizers and pesticides applied
on the new golf course can be reduced by 20-30 % due to the higher pest
resistance of the proposed Paspalum turfgrass.
10.7.22
With proper management practices, losses of nitrogenous
fertilizer would be minimal, as they have been for the past decade. The nitrogen source used in the existing
golf course is a slow-release formulation, and is rapidly absorbed by the soil.
Based on the marine water quality
monitoring results of the existing course during the last decade, the absorption
by turfgrass of nitrogen and phosphorus is as high as 97% and 99%, respectively.
Before reaching marine waters, any
remaining nutrients carried by runoff must pass over lands of varying widths
that are densely vegetated with natural grass, shrub and/or woody
vegetation. Because these areas
have been protected from fire since construction of the golf course, they
support increasingly dense stands of vegetation that produce increasing volumes
of leaf litter. This contributes to
development of soil and increases infiltration of surface water. These areas act as effective natural
buffers to absorb nutrients, thereby preventing their entry to the surrounding
marine waters. This buffering
effect probably explains the absence of any impact of golf operations on
nutrient levels in marine waters.
10.7.23
Under the current drainage plan, most runoff from the
fairways would not be discharged to the sea, but would be collected by a closed
drainage system and transferred to the existing reservoir at the north end of
Kau Sai Chau for recycling as irrigation water. This is to supplement the freshwater
supply from the desalination plant. The only exception is the runoff from
Hole 5 and part of Hole 6, which will be discharged to an existing marsh. The marsh is currently receiving runoff
from Holes N15, and S1 to S9 of the existing golf course, and the marsh
overflows to the sea. After the new
golf course is completed, the proposed closed drainage system of the new golf
course would also collect the runoff from some of the holes on the existing
golf course, including S1, S7 and S9. Even with the extra runoff from Hole 5
and Hole 6 of the new golf course, it is estimated that there would still be a
net reduction 7.3% of runoff flow volume to the marsh. There would also be a reduction of the
concentration of the chemicals in the runoff collected by the marsh because, as
mentioned in the above paragraphs, the amount of chemical applied per unit area
on the new golf course (including Hole 5 and Hole 6) would be reduced due to
greater disease resistance of the Paspalum turfgrass. In addition, the monitoring results at Marine Station B (immediately offshore
from the marsh, see Figure 6.2 of
this report) from the last decade show that all parameters complied with the
WQOs for Port Shelter WCZ. With the
reduction in both volume of runoff and applications of chemicals, no impact on
the water quality from the discharge of the marsh is predicted.
10.7.24
The future monitoring programme of the proposed golf course
will be tailored to the practices on the golf course, e.g. monitoring will focus
on those chemicals to be used. All
turfgrass chemicals to be used on the golf course will be selected from the
list of chemicals approved by AFCD for use in
10.7.25
Based upon the experience from the existing golf course,
during the 1995 to 2004 monitoring period, the concentrations of all pesticides
were below detection limits (0.5 ug/L). By reducing the amount of chemical
applied and recycling a high percentage of runoff, it is expected that the new
golf course would meet water quality standards as high as those of the existing
golf course.
10.7.26
In the case of heavy rainfall, the proposed closed drainage
system might overflow. The
frequency of overflowing would be low, based upon the estimation from past
10-year rainfall records. The
predicted water quality from the proposed drainage system would be better than that
in the existing reservoir, which also overflows when it reaches its capacity. No water quality impact is anticipated
from overflowing.
10.7.27
The existing golf course has been operated for a decade. The operation of the FCZs within Port
Shelter was not affected and the production of fish fry at
10.7.28
The magnitude of the changes in water quality and the extent
of the area affected by the operational discharge are very limited. Fisheries resources within Grid cells R10
and S10 are not going to be impacted significantly. None of the Fish Culture Zones would be
affected significantly either. Even
Kai Lung Wan west of Kau Sai Chau, the nearest FCZ to the discharge point of
the desalination plant, lies beyond the affected range. Tai Tau Chau, east of Kau Sai Chau, is
far away from the influence of the desalination plant and would be unlikely to
be impacted by the runoff from the golf course. All other FCZs within Port Shelter WCZ
are further away from the golf course and the affected area. No insurmountable impact on the FCZs is
expected. The impacts from the
operation of the golf course are thus ranked as minimal. Table 10.3 below summaries the construction and operation phase
impacts for easy reference.
Table 10.3 Summary
of fisheries impacts
Impacts
|
Due to
|
Duration
|
Receiver
|
Severity
|
Need for mitigation
|
Construction phase
|
|||||
Temporary
fishing ground loss (1,500+800 = 2,300m2)
|
Dredging at desalination plant
|
Temporary
|
Capture fisheries
|
Minimal
|
No
|
Marine water
quality
|
Construction of desalination pipelines Dumping, spilling, and leakage of chemicals from
vessels or equipment
|
Temporary
|
Capture fisheries and mariculture
|
Minor
|
Yes
|
Operational Phase
|
|||||
Marine water
quality by desalination plant
|
Increase in salinity during operation
|
Permanent
|
Capture fisheries and mariculture
|
Minimal
|
No
|
Marine water
quality by golf course
|
Pesticides and fertilizers
|
Permanent
|
Capture fisheries and mariculture
|
Minimal
|
No
(but precautionary
measures would be adopted) |
Cumulative
impacts
10.7.29
This section of the report considers the potential cumulative
impacts from other concurrent projects in the assessment area.
10.7.30
There are no scheduled concurrent designated projects (DPs)
in the vicinity of the proposed golf course during the construction or operation
phase.
10.7.31
As stated in the results of water quality assessment, no
cumulative impacts from other projects is expected on marine water quality . There is also no other concurrent marine
works project in the vicinity of the desalination plant or the barging point. Therefore, no cumulative construction and
operational fisheries impacts are likely to arise from this DP.
10.8
MITIGATION MEASURES
Construction
phase
10.8.1
Potential sources of marine water quality impact during
construction phase include:
l
Site
runoff;
l
Suspended
solid during the dredging and backfilling for the pipelines of the desalination
plant; and
10.8.2
In addition to the temporary drainage system which would collect
site runoff for re-use for irrigation, site runoff would also be controlled by
general site practices during the construction period.
10.8.3
Silt curtains will be deployed during dredging and
backfilling for the desalination plant. With the deployment of silt curtains
around the desalination plant construction area, adverse water quality impacts
associated with the dredging and back-filling would be controlled.
Operation
phase
10.8.4
Runoff from Hole 5 and part of Hole 6 would discharge into a
marsh and thence to the sea.
10.8.5
Although the water quality assessment has demonstrated that
the fisheries resources in the vicinity, including capture fisheries resources
and Tai Tau Chau FCZ, are unlikely to be affected by the runoff, some precautionary
measures would be adopted to further protect the nearby fisheries resources.
10.8.6
A filter system is proposed to further improve the quality of
the runoff from Hole 5 and part of the Hole 6. Nutrients and pesticides would be
absorbed by the filter system with the effectiveness ranging from 67-96%.
10.8.7
Biological methods will also be applied at Holes 5 and 6. The proposed biological insecticide and
fungicide products are all registered by AFCD. All are microbial or plant extracts,
which are non-toxic to non-target organisms according to USEPA information (see
Water Quality Assessment section). Chemical
methods will only be used when necessary. This could significantly reduce the
already low concentrations of chemicals in the runoff from Holes 5 and 6. Table
10.4 below summaries the construction and operation phase mitigation
measures for easy reference.
Impacts
|
Mitigation measures and effects
|
Construction phase
|
|
Site Runoff
|
Temporary drainage system for works areas
Buffer zones for
stream courses to prevent sedimentation Good Site
practices
|
Water quality impact from dredging at desalination
plant
|
Deployment of silt curtains
|
Operational phase
|
|
Runoff from the third golf course (precautionary
measure)
|
Filter system and biological methods to further
reduce the chemical concentrations in runoff from Holes 5 and 6
|
10.9
RESIDUAL IMPACT
10.9.1
No residual impacts on capture fisheries are predicted. This is due to the small scale and short
duration of the construction phase impacts, the small magnitude of water
quality change during operation, and the mitigation measures proposed.
10.9.2
No residual impacts on the FCZs within the fisheries
assessment area are predicted. This
is due to the small scale and short duration of the construction phase impacts,
the small magnitude of water quality change during operation, and the
mitigation measures proposed. For
the other FCZs within Port Shelter, there is no overlap between the area of
waters affected during the operational phase and these FCZs.
10.10
ENVIRONMENTAL AUDIT
10.10.1
During the construction phase, water quality monitoring will
be undertaken three days a week for
the dredging works at the desalination plant. Stream water would also be monitored to
ensure no sedimentation would go into the sea through the stream courses. During operation phase, the outfall of
the desalination plant would be monitored at lease once every two weeks during
the first three months of desalination plant commissioning.
10.10.2
Besides the EM&A for water quality, no specific EM&A
programme for fisheries would be required for the Project.
10.11
CONCLUSION
10.11.1
The construction of the desalination plant and temporary
barging point will result in minor temporary losses of fishing grounds. However, the size of the loss is small
(about
10.11.2
The above discussion should make it apparent that the
construction and operation of the Project would have no significant impacts on capture
fisheries or mariculture. A
well-planned program of site practices should be able to maintain the impacts
to acceptable levels. Fisheries monitoring
during the construction and/or operation phases will not be needed.
10.12
REFERENCES
AFCD 1998. Port
Survey 96/97. Agriculture, Fisheries and Conservation Department, Hong Kong
SAR.
AFCD 2003. Port
Survey 2000/2001. Agriculture, Fisheries and Conservation Department, Hong Kong
SAR.
AFCD 2004. 漁農自然護理署年報2001-2002.
Agriculture, Fisheries and Conservation Department, Hong Kong SAR.
Hyder Consulting Ltd. 2002. Lamma Power Station Navigation Channel
Improvement – Final report.