6                                  Water Quality

6.1                            Introduction

This section presents the EM&A recommendations for auditing the water quality mitigation measure during the construction phase of the Project.

6.2                            Environmental Monitoring and Audit

As stated in the EIA Report, no water quality monitoring will be required for the construction phase.  However, as the part of the monthly site audit procedures, it is recommended that the ET Leader confirms that the Contractor has implemented the drainage management plan and the good construction site practices, as described in Sections 7.5 and 7.6 of the EIA Report.

6.3                            Mitigation Measures

The Contractor will implement the following good construction site practices to avoid or minimise potential water quality impacts associated with land based construction. 

6.3.1                      Construction Runoff and Drainage

Construction site runoff and drainage will be prevented or reduced in accordance with the guidelines stipulated in the EPD Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94).  The good practices include:

·           Provision of perimeter channels to intercept stormwater run-off from outside the site.  These will be constructed prior to the site formation works and other earthworks at the Project Site.

·           Exposed soil surfaces will be covered by a tarpaulin as soon as possible to reduce the potential for soil erosion.

·           Open stockpiles of construction materials on site will be covered with tarpaulin or similar fabric during rainstorms.

·           Surface run-off from the construction site will be directed into an existing stream channel via adequately designed sand/silt removal facilities such as sand traps, silt traps and sediment basins.  Channels, earth bunds or sand bag barriers will be provided on site to properly direct stormwater to such silt removal facilities. 

·           Silt removal facilities, channels and manholes will be maintained and the deposited silt and grit will be removed regularly, at the onset of and after each rainstorm to ensure that these facilities are functioning properly at all times.

·           During excavation in the wet season, temporarily exposed soil surfaces will be covered, eg by tarpaulin, and temporary access roads will be protected by crushed stone or gravel, as excavation proceeds.  Intercepting channels will be provided (eg along the crest/edge of the excavation) to prevent storm runoff from washing across exposed soil surfaces.  Arrangements will always be in place to ensure that adequate surface protection measures can be safely carried out well before the arrival of a rainstorm.

·           Earthworks final surfaces will be well compacted and the subsequent permanent work or surface protection will be carried out as soon as practical after the final surface are formed to prevent erosion caused by rainstorms.  Appropriate intercepting channels will be provided, where necessary.  Rainwater pumped out from trenches or foundation excavations will be discharged into storm drains via silt removal facilities.

·           The contractor(s) concerned should apply for and obtain all the necessary discharge licences.

6.3.2                      General Construction Activities

Debris and rubbish generated on-site will be collected, handled and disposed of properly to avoid entering the nearby stormwater drains and open drainage channels.  All fuel tanks and storage areas will be provided with locks and be sited on sealed areas, within bunds of a capacity equal to 110% of the storage capacity of the largest tank.  Open stormwater drains and culverts near the works area will be covered to block the entrance of large items of debris and refuse.  

6.3.3                      Sewage from Workforce

Temporary sanitary facilities, such as portable chemical toilets, will be employed.  A licensed contractor would be responsible for appropriate disposal and maintenance of these facilities.