2                                            The Need for a LNG receiving terminal in hong kong

2.1                                      Introduction

Since 1996 with the commissioning of the Black Point Power Station (BPPS), natural gas has been an important component of CAPCO's fuel supply.  Use of natural gas has delivered significant environmental benefits as well as added diversity to the fuel mix used for electricity generation, thereby enhancing the security of electricity generation.

It is estimated that the existing source of CAPCO’s gas supply, the Yacheng field off Hainan Island in the South China Sea, will be ([1]) depleted early in the next decade, depending upon the rate of offtake and actual reserve levels.  As analysed in Section 2.8 below, other South China gas reserves appear insufficient to supplement or replace the Yacheng field. 

Natural gas is generally delivered to markets in two ways.  One is to transport the gas through pipelines directly connecting a gas field to end users, as is now the case for CAPCO.  The other alternative is to liquefy the gas and transport it by ship in its liquid state, to receiving terminals where it is then converted back to gas form for use.

2.2                                      Fuel Diversity – Balancing Reliability, Cost and Environmental Benefits

Over the past decade, the fuel used for electricity generation in Hong Kong has evolved from being primarily coal to a diverse mix that is roughly 30% gas, 30% nuclear, and 40% coal ([2]).

Due partly to the introduction of nuclear power and natural gas into the fuel mix, CLP’s air emissions from power generation have significantly improved, with nitrogen oxides (NOx  down 77%, sulphur oxides (SOx ) down 44% and particulates down 70% over the period between 1990 and 2005 ([3]).  Fuel diversity has enabled these improvements to be achieved while maintaining competitive tariffs and world-class electricity supply reliability in the supply of electricity.  Often taken for granted, these factors are key contributors to Hong Kong’s quality of life, competitiveness in the global market, and ability to attract investment.  Businesses in Hong Kong, ranging from large multi-national companies to small local shops are all dependent on a cost-competitive and uninterrupted supply of electricity.

2.3                                      Benefits of Natural Gas as a Fuel

There are a number of benefits to utilising natural gas as a fuel in power generation, including:

Proven Use in Power Generation:  Natural gas has been employed around the world for electricity generation for over 30 years ([4]) and is used in the Combined Cycle Gas Turbines (CCGT) at BPPS BPPS uses advanced technology in terms of equipment and operating systems.  CCGTs have higher thermal efficiency than conventional fossil fuel fired power stations with the same generating capacity ([5]).

Adequate Reserves Available:  The increasingly wider use of LNG indicates that more of the world’s gas reserves are available to consumers in locations remote from existing sources.  In 2005 there were 13 countries producing LNG and 15 importing LNG, with total consumption of 141.5 MTA (million tonnes per annum).  According to the International Energy Agency (IEA), worldwide LNG production capability is expected to grow to approximately 500 MTA in 2030, representing a 5% annual growth rate ([6]).

Environmental Benefits:  Natural gas is one of the cleanest and most efficient forms of energy available.  Natural gas from LNG is clean burning, producing virtually no particulates, and less NOx and carbon dioxide (CO2 ) than other fossil fuels.  Since sulphur is almost entirely removed as part of the liquefaction process, combustion of regasified LNG emits negligible amounts of sulphur dioxide (SO2 ([7]) ).

The Government’s environmental policy includes the control of emissions from the existing power stations in Hong Kong.  Central to this effort is the use of natural gas.  The recognition of the role of natural gas in emissions control was affirmed by the Government in the 2005-06 Policy Address ([8]):

 

 61. To fully achieve the emissions reduction targets in 2010, we have asked the power companies to … use natural gas for power generation as much as possible.

As a consequence, natural gas is positioned to play an increasingly important role in the generation of electricity.  Maintaining a cost-effective, diverse, reliable and adequate supply of fuel will continue to be a priority. 

2.4                                      What is LNG?

LNG is the liquid form of natural gas, the main component of which is methane.  In the liquefied form, at atmospheric pressure, LNG occupies only 1/600th of its volume at gaseous state under normal temperature and atmospheric pressure and is therefore more economical to store and transport over long distances in contrast to the traditional pipeline delivery of natural gas. 

LNG is produced by cooling natural gas to -162 °C (-260 °F) through a liquefaction process.  Prior to cooling and condensing the natural gas into LNG, impurities such as carbon dioxide, water and sulphur are removed.  The end result of this process is an odourless, colourless fuel consisting mostly of methane (approximate range 85% to 99%) with small amounts of ethane, propane, butane and pentane. 

There are a number of environmental and safety benefits ([9]) to using LNG, including the following:

·      Regasified LNG is clean burning, producing virtually no particulates and less NOx and CO2 than other fossil fuels. Since sulphur is almost entirely removed as part of the liquefaction process, combustion of regasified LNG emits negligible amounts of sulphur dioxide.

·      LNG is stored at near atmospheric pressure, reducing the storage hazard compared with pressurised fuels

·      LNG, when released to the atmosphere at normal temperatures, will evaporate and disperse quickly, leaving no residue behind and therefore requiring no environmental cleanup.

·      LNG vaporises when warmed and the resulting natural gas is lighter than air and therefore rises when released.

·      LNG is non-corrosive and non-toxic.

2.5                                      The LNG Value Chain Requires Long Term Planning

The LNG industry can be described by an LNG value chain consisting of 5 key elements :

1.         Exploration, development and production of gas,

2.         Liquefaction,

3.         Shipping,

4.         Storage and Regasification,

5.         End use (e.g. power generation).

Each of these elements has its own technological and investment requirements, but they share a common characteristic.  They all require long project lead time and significant resources and investment commitment.  Each element of the chain must be carefully planned and integrated with other elements; hence the supply chain requires long term sales and purchase relationships between each participant. 

2.6                                      Depletion of the Existing Gas Reserves at Yacheng 13-1

In the early 1990s, CAPCO examined potential sources of natural gas for Hong Kong ([10]).  The feasibility of developing a LNG terminal was studied by both private interests and the Government.  Although feasible sites were identified for a LNG terminal (one of which included locating the LNG terminal at the Soko Islands), the study also considered a submarine pipeline from the Yacheng 13-1 gas field in the South China Sea.  The Yacheng field was eventually developed to supply the Black Point Power Station and was expected to provide sufficient gas for 20 years.  With the identification and use of this option, the need for a LNG terminal in Hong Kong was deferred.  Upon completion of this analysis, CAPCO secured the option of obtaining gas from the Yacheng field through private investments.

A map illustrating the location of the Yacheng 13-1 field and the pipeline connecting to Black Point Power Station is presented in Figure 2.1.

Figure 2.1      Location of Yacheng 13-1 Gas Field and Existing Export Pipeline to BPPS

Under the contract for the supply of gas to CAPCO, the entire Yacheng 13-1 resource is dedicated to CAPCO, except for a small volume which is delivered to neighbouring Hainan.  Gas delivery began in 1996 and was expected to last until 2015 ([11]).

Given the geological and technical uncertainties of gas production, it is industry practice for reserves to be periodically re-determined.  CAPCO’s estimates ([12]) indicate that the Yacheng field will be depleted early in the next decade based on the projected gas offtake rate and actual reserve levels. 

2.7                                      Gas Supply Critical for Electricity Reliability

As explained above, electricity reliability plays a key role in Hong Kong’s quality of life.  The 2,500 MW Black Point Power Station (BPPS) provides about 25% of Hong Kong’s total electricity needs, and plays a large part in CLP’s 8,888 MW of maximum available electricity supply.  In the event that gas was not available to BPPS, CAPCO would need to meet electricity demand by a higher reliance on its available coal-fired generation which would result in increased air emissions beyond existing levels and Government targets.  Moreover, with 2005 peak local electricity demand at 6,475 MW and the electricity demand growth from 2006 to 2011, CLP’s supply capacity without BPPS would not be able to satisfy electricity demand (total capacity is not available at all times due to maintenance requirements) and Hong Kong consumers would be exposed to possible power cuts or rationing.  Although the BPPS is able to use diesel as a fuel, this capability is designed only for short term emergency back up ([13]).  Therefore, the absence of a replacement gas supply would not only entail an environmental impact in terms of increased coal burn and emissions of NOx, SOx and particulates, it would also compromise Hong Kong’s electricity supply reliability. 

Given Hong Kong’s total dependence on imported fuel and the importance of a quality and reliable replacement gas supply, CAPCO can only reasonably consider gas supplies that will not compromise Hong Kong’s electricity reliability.  In order to assess the replacement options, it is vital to have a clear understanding of the requirements for supply of this important fuel.  There are 5 fundamental requirements for the replacement gas supply:

1.   Certainty of timely availability:  Given the expected depletion of the Yacheng field early next decade, CAPCO must have absolute certainty that the replacement gas will be available on time.  As the gas infrastructure and supply chain typically take 7 - 8 years to put in place ([14]), only alternatives that have already achieved significant engineering and approval milestones together with proven gas reserves and operating track record can provide this certainty.

2.   Supply security for Hong Kong:  Gas is expected to represent up to 50% of CAPCO/CLP’s fuel mix by early next decade, and security of gas supply is essential to maintain high levels of electricity reliability in Hong Kong.  The required supply security can be provided by:

a.    Priority for CAPCO’s gas requirements,

b.    Diversification of supply from at least two sources.  Disruptions to fuel supply can occur, as evident with recent gas supply disruptions in Ukraine ([15]) (which left the country short of gas for a period during winter), Singapore ([16])  (which resulted in blackouts in many parts of the island state in the summer of 2004), and closer to home with offshore oil production facilities ([17]) in the South China Sea which were damaged by Typhoon Pearl and inoperational for a prolonged period.  Given the increased share of gas in the fuel mix, it is not prudent to depend on only one gas supply source.

c.    Gas supply chain managed by companies with proven track records for operating in line with industry best practices.

3.   Adequate volume and flexibility:  CAPCO’s LNG requirement for its current gas-fired generation facilities is about 2.6 million tonnes per annum (MTA) of LNG, which represents roughly 75% of Hong Kong’s total gas demand.  The replacement supply must be able to meet this initial requirement as well as the following:

a.  Meet gas demand growth in future years as a result of Government’s environmental initiatives and Hong Kong’s electricity demand growth,

b.  Provide the flexibility for CAPCO to meet seasonal demand patterns and the power plants’ operational requirements, and

c.  Enable a smooth transition from Yacheng gas.

4.   Competitive supply:  CAPCO is competing with numerous other buyers for limited supplies of LNG.  Suppliers are focusing their efforts on buyers with strong markets for the gas, in addition to having existing terminal infrastructure or comprehensive and advanced plans for developing such terminals.  For CAPCO to attract suppliers and achieve the best possible terms on behalf of its electricity consumers, the procurement process must be structured efficiently so as to demonstrate the strengths of CAPCO as a buyer able to undertake long term commitments and demonstrate Hong Kong as a sustainable market.  Moreover, the process must be competitive and conducted through a fair and defensible process. 

5.  High environmental and safety standards:  CAPCO is committed to responsible environmental management and safe operations.  The replacement supply source and its suppliers must perform to internationally acceptable environmental and safety standards.

2.8                                      Replacement Gas Supply Alternatives

Given the importance of the availability of replacement gas to Hong Kong, CAPCO has carefully explored and evaluated the possible alternatives to fulfil this fuel requirement.  Five potential alternatives have been identified, and each has been systematically evaluated against Hong Kong’s requirements as discussed below.  The five potential alternatives are as follows:

1.         Import gas via pipeline from a nearby gas field;

2.         Import Natural Gas via the Guangdong Dapeng LNG terminal (GDLNG) located in Shenzhen;

3.         Import Natural Gas via a new terminal outside Hong Kong;

4.         Import LNG via a new terminal in Hong Kong; or

5.         No action or defer decision.

2.8.1                                Import Gas via Pipeline from a Nearby Gas Field

The South China Sea contains only limited discovered reserves of natural gas, with the majority of these gas reserves being exploited ([18]).  These gas discoveries are significantly smaller than Yacheng, are of varying qualities and therefore less suitable for use as fuel for power generation, and have been committed to identified customers (aside from the Yacheng Y-13 gas field, other reserves include the Dongfang and Ledong fields which are committed to Hainan ([19]) and the Panyu and Huizhou fields which have been targeted for users in Zhuhai ([20])).  Given the above, importing gas from any of the proven South China Sea fields is not feasible because there is insufficient supply available to meet CAPCO’s and Hong Kong’s long-term needs.  Plans for the development of multiple LNG terminals in southern China is clear recognition that gas reserves are insufficient to meet growing demand, and LNG imports are required. 

In 2006, there are reports ([21]) of what could be a significant deep water gas discovery in the South China Sea.  At present, information is very preliminary and insufficient to assess whether this deep water field is commercially viable and can play a role in CAPCO’s gas supply.  Considerable work is required to appraise the reserves and obtain better definition of the field.  The typical time to progress a deep water gas discovery from the discovery stage to gas delivery stage is between 8 and 14 years ([22]) (Table 2.1), which is an unacceptably long timeframe for CAPCO's replacement gas supply. 

Table 2.1                Indicative Timing for Deepwater Development

Step

Activity

Duration (months)

1

Discovery

0

2

Project owner review

3 - 6

3

3-D seismic acquisition and interpretation

20 - 48

4

Appraisal well drilling, reserves certification

13 - 30

5

Final assessment and Overall Development Plan (ODP) formulation (Marketing)

6 - 12

6

ODP approval

3 – 6

7

Drilling, facility design and construction

48 – 63

8

First Gas

0

 

Total Time Required (years)

8 - 14

In view of Guangdong’s rapidly growing gas needs ([23]), it is also questionable whether any new proven gas discovery would be available for Hong Kong.  And if it were, gas supply from a South China Sea field would require a longer pipeline traversing the western waters of Hong Kong and introducing additional ecological and cost impacts.

2.8.2                                Import Natural Gas via the Guangdong Dapeng LNG Terminal (GDLNG)

The GDLNG terminal in Shenzhen, China’s first LNG terminal, was commissioned this year.  GDLNG’s initial capacity of 3.7 MTA ([24]) and supply are fully committed to its founding shareholders, including seven Mainland Chinese power and gas companies, Hongkong Electric and Hong Kong & China Gas ([25]).  With regard to expanding the terminal, CAPCO assessed this option and understands that the limited additional capacity will be dedicated to Guangdong gas users with unknown timing.

Even if a large portion of GDLNG’s expansion capacity were available to CAPCO, there would still be environmental considerations, as a new pipeline would need to be installed to Black Point Power Station.  An offshore route would be approximately 150 - 160 km in length, approximately four times the length of a pipeline from South Soko Island to BPPS, the latter part of which would traverse the same marine area in the western waters of Hong Kong as a Hong Kong terminal. 

An overland route would be approximately 85 km in length of which approximately 55 km would traverse the densely populated city of Shenzhen as well as several populated areas of The New Territories in Hong Kong, including Sheung Shui and Yuen Lung ([26]). Key issues related to this option include:

·       Acquisition and permitting of a technically viable route through several densely populated areas in Shenzhen and Hong Kong. 

·       Environmental and safety risk impact associated with routing the pipeline away from developed areas through rugged terrain.

·       Satisfying the approvals process in two jurisdictions with a risk that permits may be denied in one or both jurisdictions.

From a regional supply security perspective, it would be unwise to have all of Hong Kong and Guangdong’s gas needs supplied by one facility, as the entire region’s energy supply could be significantly impacted in the event of a lengthy interruption.  The need for diversity of supply infrastructure is demonstrated by overseas experience such as the U.S. ([27]), U.K, Japan, Singapore ([28]) and other energy-importing countries.  Tokyo’s LNG supply, for example, is received through 5 separate terminals.

Another consideration is that with Guangdong end-users having both equity in the terminal and most of the capacity rights, it is uncertain whether CAPCO could obtain the flexibility and priority of supplies to meet operational needs in the event of a supply disruption and to meet growing demand.

2.8.3                                Import Natural Gas via Proposed LNG Terminal in mainland China

Development of a LNG terminal requires considerable time for planning, permitting, construction, and to achieve satisfactory commercial arrangements among all parties involved.  As a reference, the Guangdong Dapeng LNG terminal took around 10 years from project planning to terminal commissioning in 2006 and the CAPCO project is estimated to take 8 years from start of planning in 2003 until commissioning in 2011 (Table 2.2).  Two LNG terminals are proposed in the Zhuhai area, one to serve Zhuhai as part of China’s long-term LNG importation plan and the other to serve Macau.

 

Table 2.2        Timing for Hong Kong LNG Terminal Development

Step

Activity

Timing

1

Project Planning

2003 – 2004

2

Environmental Impact Assessment, Permitting and Preliminary Engineering

2004 – 2007

3

Engineering, Procurement, Contracting and Construction

2007 – 2011

4

First Gas

2011

Import via a Proposed Mainland LNG Terminal

The Zhuhai terminal, with a planned capacity of 3 MTA, is intended to supply gas to the west Pearl River Delta.  It is one of nine terminals planned for coastal cities in China.  The Guangdong Dapeng terminal is the first to go into operation and a second terminal at Fujian is under construction.  Although China has a clear plan ([29]) to develop a number of LNG terminals to serve major cities in the coastal provinces, these plans have been held back so that they are timed to match developments in LNG supply projects ([30]).  The timing for a Zhuhai terminal, the second one for this region, is not clear ([31]). 

Import via a Proposed Macau LNG Terminal

The Macau Terminal proposal is also in the early stages of development with the recent introduction of its conceptual proposal, which was the stage that the Hong Kong terminal was in back in 2003.  Macau’s present gas demand is small, about 10% of CAPCO’s, and would not normally be sufficient to justify the cost of development and operation of a LNG terminal.  In addition, project development is especially complex, involving multiple separate jurisdictions – Macau ([32]), Zhuhai, Guangdong province and the central government, plus Hong Kong if supply to Hong Kong is added.

CAPCO commissioned the Construction Advisory Services group of Deloitte Financial Advisory Services LLP (“Deloitte FAS”) to analyse the proposed Macau LNG Terminal project and advise on whether it could rely on the proposed project to meet CAPCO’s gas requirements.  Deloitte used industry-standard procedures to take account of uncertainties in the project’s approval, development and construction processes and in its confidential report (1) provided the following recommendation to CAPCO:

Deloitte recommends that CAPCO should not rely on the proposed Macau LNG terminal for supply of LNG in 2011.

CAPCO’s customers are highly reliant on a secure supply of electricity. Given the importance of LNG availability in 2011 to ensure that there are no supply disruptions and to enable achievement of emissions targets, CAPCO needs to have a very high level of confidence (P90) that its source of gas for Black Point Power Station would be ready to supply gas in 2011.

Based on Deloitte FAS’s global experience (including China) of analysing similar major infrastructure projects, Deloitte FAS advises CAPCO that CAPCO should not rely on the proposed Macau LNG Terminal project as it does not provide the required confidence level (P90).

The basis of Deloitte FAS’s advice is set out in our report”.

Project Timing

Execution and timing for these projects are uncertain.  China has not been able to secure supply as planned, and this has led to delays in its terminal developments.  According to Xu Dingming, Vice Chairman of the Office of China’s national Energy Leading Group, China’s LNG import plans must slow down ([33]).  Other than these two proposed terminals, no other terminal has been proposed in Guangdong; any new terminal must commence the 8 - 10 year development process from the beginning.

Considering the early stages of development of the proposed projects, neither is likely to meet CAPCO’s timing requirement as the development process is subject to negotiations of complex commercial, offtake and regulatory framework arrangements among various stakeholders, as well as compliance with local permitting and regulations in multiple jurisdictions.  One such example is the submarine pipeline required to transport the gas from a new terminal to Black Point Power Station which would require rigorous approvals not only in Hong Kong but also in Macau and the mainland at the local and central level. 

The other option, of utilising the existing Yacheng pipeline presents both commercial and technical challenges ([34]), which could not be resolved within the timeframe for the replacement gas supply.  For example, the pipeline is not owned by CAPCO and its access would entail complex commercial negotiations. The technical challenges include:

·      A pipeline will be required running between the new LNG terminal and the tie-in point on the existing pipeline, this would entail similar environmental disturbance to the base case pipeline route and involve a permitting process in two jurisdictions;

·      An extended interruption to the gas supply to BPPS would be necessary to allow the insertion of a tie-in assembly in the existing pipeline ([35]);

·      The operation of connecting to the existing pipeline is extremely complex and would involve a significant risk of additional delay as a result of unforeseen events;

·      CAPCO’s Consultant studies confirm that blending of Yacheng gas and regasified LNG in the Yacheng pipeline would not be an appropriate solution due to the two types of gases being outside the interchangeability limit of the hardware design in BPPS.  While blending the gases is theoretically possible, operating flexibility would be severely restricted and there would be potential for hardware modifications to be required several times catering for the change in fuel ratios that would occur as Yacheng gas supply is depleted.  Accordingly, following conversion of the generator units to burn regasified LNG, the use of Yacheng gas would have to be curtailed ([36]).

LNG Supply

With a mainland terminal, CAPCO would be only one of several customers with competing gas demand.  Accordingly, CAPCO would not have a priority right to access gas supply, which is essential to meeting Hong Kong’s electricity generation demand, particularly during the peak summer demand period.

Given their early stages of project development, the potential Mainland terminal projects may struggle to attract sellers, particularly in the 2011 timeframe when LNG is in limited supply.  LNG sellers face no shortage of interested buyers during this period.  CAPCO's experience is that with limited resources and in a sellers’ market, sellers put their efforts into engaging with those LNG buyers able to demonstrate a clear commercial structure, a comprehensive implementation plan and a realistic and detailed schedule, both for the terminal and other new end-user facilities such as power plants.  The current CAPCO proposal meets all these expectations whereas the potential Mainland projects do not.  Also, as a general rule, the addition of a third party terminal operator as a middleman in supply arrangements leads to increased cost and commercial complexity. 

Notwithstanding the concern of supply security, for future purchases to meet demand growth, being limited to one supply arrangement may place CAPCO at an economic disadvantage.  For example, with regard to a terminal outside Hong Kong, CAPCO may have no other option for gas supply, and without influence over the LNG supply process, CAPCO and the Hong Kong consumer could be in a disadvantaged commercial position.

Environmental and Safety

Importing LNG via a proposed mainland terminal would result in impacts both inside and outside of Hong Kong.  For example, pipelines connecting those terminals to BPPS would be considerably longer than a pipeline from Soko Island with increased ecological and cost impacts. 

The environmental impact assessment, risk assessments and safety regulations would fall outside Hong Kong’s jurisdiction, and it is unclear what standards would be applied to these facilities.

2.8.4                                Importing LNG via a New Terminal in Hong Kong

Project Timing

Constructing a LNG receiving terminal in Hong Kong will be able to meet CAPCO’s timing requirement in order to replace the depleting Yacheng field.  An LNG terminal located entirely within Hong Kong enables smoother and faster project development under one single jurisdiction with clear policy and regulations applicable to infrastructure built in Hong Kong.  Similar advantages are offered by CAPCO’s well established commercial structure under the Scheme of Control.  CAPCO has been progressing development activities for a LNG terminal in Hong Kong since 2003, the idea of such a terminal being first raised and supported by the Hong Kong Government as early as the early 1990’s ([37]).  Given the expected gas depletion by early in the next decade and a LNG terminal requirement date of 2011, CAPCO is progressing the development of a Hong Kong terminal as the best alternative ([38]).

LNG Supply

A Hong Kong terminal would enable both gas and electricity supply security and reliability for Hong Kong.  Hong Kong would have control of the terminal with a LNG delivery priority to maintain CAPCO’s electricity reliability.  In the unlikely case of a supply interruption where a reduced volume is available, the Hong Kong terminal can ensure that Hong Kong’s needs would be prioritised without the need to compete and share with other users. 

A Hong Kong terminal would meet CAPCO’s volume and flexibility requirements as the terminal can be planned, designed, built and operated specifically to meet anticipated growth in gas demand.  It would also allow CAPCO to closely coordinate Yacheng gas supply with LNG deliveries during the transition period, taking into account BPPS’s technical and operational requirements to ensure a reliable changeover to LNG.  While primarily to fuel CAPCO’s power plant at Black Point, other energy users in Hong Kong could be considered for terminal access.

With a Hong Kong terminal, CAPCO, as end user, would be responsible for negotiating directly with LNG suppliers to obtain a competitive gas supply.  CAPCO can demonstrate that the terminal development plan is comprehensive and realistic, the project is well along in the site selection and approval processes, and it has an experienced team in place to take the project forward, all of which are very attractive to sellers.  CAPCO would ensure that the procurement activities would be conducted in a fair and defensible manner, with contract details and results provided to the GOHK.  Such direct negotiations with LNG suppliers also eliminates non-value added middlemen, which enables CAPCO to negotiate in the Hong Kong consumer’s best interests directly with suppliers.

Environment and Safety

A Hong Kong terminal would be constructed to meet Hong Kong’s stringent environmental and safety standards utilising CLP Power’s experience in power plant operation and ExxonMobil’s expertise in developing LNG terminals around the world.  CAPCO, as both a terminal developer and a LNG buyer, will ensure the terminal and the fuel supply sources meet environmental and safety regulatory standards consistent with its existing power business operations. 

Moreover, the Hong Kong terminal would be operated and maintained to world-class standards in full compliance with Hong Kong Government regulations to the same standard as CAPCO’s existing operations, with seamless delivery of gas from terminal to the power plants.

2.8.5                                No Action or Defer decision

As noted previously, with BPPS providing about 25% of Hong Kong’s total electricity needs, having a reliable supply of natural gas that fuels this power station is critical for maintaining Hong Kong’s electricity supply.  In the event that gas was not available to BPPS, CAPCO will need to meet electricity demand by a higher reliance on coal-fired generation and more expensive diesel fuel generation (which is currently only used for emergency backup) both of which will increase emissions of NOx, SOx and particulates beyond existing levels and Governments targets.  Under such circumstances, in order to meet Government’s emission targets, Hong Kong consumers would be exposed to possible power cuts or rationing. 

In summary, the absence or delay of a replacement gas supply would not only entail an environmental impact, in the form of incremental emissions of NOx, SOx and particulates, but would also compromise Hong Kong’s electricity supply reliability.

2.8.6                                Summary Comparison of Alternatives against Hong Kong’s Requirements

The following Table 2.3 summaries the requirements of the replacement gas supply and the assessment of the five potential alternatives in meeting those requirements.

 


Table 2.3        Summary Comparison of Alternatives against Hong Kong’s Requirements

Certainty of each of the five alternatives to meet Hong Kong's gas requirements is ranked as unknown, low, moderate, or high

 


There must be a degree of certainty to the arrival of a replacement gas supply for Black Point Power Station in 2011.  CAPCO has systematically explored and evaluated the potential options for a replacement gas supply.  The option that offers the highest degree of certainty for a replacement gas supply with respect to timing, security of supply, volume adequacy and flexibility and competitiveness is to import LNG via a new terminal in Hong Kong. 

Following the due process, once an Environmental Permit is obtained which is anticipated for early 2007, and with timely progress on regulatory regime resolution and other key approvals, CAPCO will be able to enter into a long term LNG supply commitment.  This will allow sufficient time for the construction of the LNG supply chain and ensure Yacheng replacement by 2011.  Any indecision or deferral of decision now would push out the first gas delivery beyond end 2011.

This urgency also applies to LNG supply contracts, as the LNG negotiations and agreement with suppliers are integrated into the progress of the LNG terminal approval process.  CAPCO must expeditiously finalise a Sales and  Purchase Agreement to allow sufficient time for the upstream supply chain to commence construction.  No buyer will commit to buy and no seller will commit to sell LNG if the availability of the Hong Kong terminal in 2011 is in doubt.  CAPCO is competing with numerous users in the region, including Japan which has 25 LNG terminals, for limited LNG supplies.  With the Yacheng field expected to deplete early in the next decade, obtaining Government support and site approval by early 2007 is a key milestone in the LNG procurement sequence.

In addition to meeting all of Hong Kong’s replacement gas requirements, a Hong Kong LNG receiving terminal provides a number of strategic, social and economic benefits to Hong Kong.  With energy issues high on government agendas internationally, the LNG terminal will be a strategic asset for Hong Kong as it will provide the means of access to global natural gas supplies when demand for energy is increasing.  The social and economic benefits include the generation of capital investment, construction and engineering employment ([39]) as well as revenue for the Hong Kong Government in terms of tax and land revenues.  In the environmental impact assessment appeal of KCRC on the Sheung Shui Station to Lok Ma Chau Spur Line, the ruling stated the following:

[In] assessing whether an alternative is practical and reasonable all the circumstances must be taken into account and a balanced judgement reached…many matters which must be weighed in assessing “practical and reasonable” included are adverse impacts, engineering constraints, extra-time involved, additional cost and even government policy (accepting it as a fact).  No alternative is likely to be practical if government policy will not enable it. …. 

The ruling further commented on the implementation of the EIA process:

[T]here are two main matters of public interest involved.  Both are important.  The first is the public interest in the protection of the environment upon which the quality of life in Hong Kong will increasingly depend.  The second is the public interest in ensuring that major designated projects are brought to fruition in a timely and efficient manner. 

This section has been written to satisfy the study brief requirements as well as to demonstrate the need for the LNG terminal in Hong Kong.

Now that the engineering and environmental feasibility studies have been completed, and with timely progress on regulatory regime resolution and other key approvals, a terminal in Hong Kong can be completed by 2011 and will meet all of CAPCO’s requirements.  CAPCO believes that the Hong Kong LNG receiving terminal is the only reasonable and practical option to ensure electricity supply reliability for Hong Kong and to comply with the 2010 Hong Kong Government environmental initiatives.

 



([1])      Relevant details were provided to Economic Development and Labour Bureau on 2 December 2004.  Those details are based on data provided by the Yacheng Gas Sellers and are therefore subject to confidential obligations owed to the Yacheng Gas Sellers under the Yacheng Gas Contract

([2])      Estimate for 2004 – 2006 as set forth in the Financial Plan..

([3])      CLP Group (2006) Social and Environmental Report 2005.

([4])      “Evolution of Electricity Generation by Fuel, International Energy Agency, 2006”

([5])      ‘Introduction to LNG’, University of Houston, Institute of Energy, Law & Enterprise

([6])      “Wood Mackenzie Research”

([7])      IEA (International Energy Agency) Natural Gas Prospects to 2010 (1986)

([8])      The 2005-06 Policy Address, Strong Governance For the People, Paragraph 61

([9])      a)  IEA (International Energy Agency) Natural Gas Prospects to 2010 (1986)

          b) ttp://www.lngfacts.org/faq/index.html#1 , FAQ, The Center for Liquefied Natural Gas

([10])    LNG Feasibility Study, Joint Study by CLP, Shell, Total with Guidance from EPD, September 1992

([11])    China Started to Supply Natural Gas to Hong Kong, 11 January 1996, Europe/Pacific Regional News (CND-EP, No. EP96-002), China News Digest

([12])    Relevant details were provided to Economic Development and Labour Bureau on 2 December 2004.  Those details are based on data provided by the Yacheng Gas Sellers and are therefore subject to confidential obligations owed to the Yacheng Gas Sellers under the Yacheng Gas Contract

([13])    Long term diesel use would require additional investment in infrastructure, higher fuel cost, and would increase emissions beyond existing levels and Government’s targets.

([14])       Ranges based on industry project experience for new areas

([15])       Rice Faults Russia on Natural Gas Disruption, The Epoch Times, 5 Jan 2006

([16])       Blackout plunges parts of Singapore into darkness – Reuters, Business Report, June 29 2004

([17])       Update 1 – China oilfield still out after typhoon, Reuters, June 13, 2006

([18])    Operations Overview – CNOOC Limited 2004 Annual Report,  b) Operations Review – CNOOC Limited 2005 Annual Report,  c) China Country Profile, EnergyFiles, www.energyfiles.com/asiapacific/asia/countries/china.htm, retrieved on 16 Aug 2006),  d) China’s CNOOC to develop two new gas fields in South China soon – report, 21 Feb 2005, Beijing (AFX),  e) Sinopec Hainan Refinery, CNOOC sign gas supply contracts, puworld.com

([19])    CNOOC says gas-based fertiliser project to start production on Thursday, Gas Matters Today Asia, 28 June 05,  b) Poten & Partners, CNOOC to Build Worlds Largest Methanol Production Base (SinoCast China Business Daily News), June 22 2006

([20])    CNOOC Ltd starts gas production at Hui Zhou 21-field in Eastern South China Sea, Gas Matters Today Asia, 19 Apr 2006

([21])    Update 1 – Offshore China gas find lifts Husky Stock, Reuters, Jun 15 2006

([22])    ExxonMobil Development Company, based on previous deepwater project experience

([23])    a)  CNOOC inks Australian gas deal for Guangdong (China Daily), 3 May 2004,  b) On time finish is no pipe dream for LNG project, China Daily, 24 May2005

([24])    CNOOC links Australian gas deal for Guangdong (China Daily), 3 May 2004

([25])    ASX Announcement – Guangdong LNG Agreement, Woodside, 13 Dec 2004,

([26])    CLP desktop study

([27])    Senate Natural Resources Committee, Testimony of Victor G. Carrillo, Commissioner, Railroad Commission of Texas,  June 2006

([28])    Consultation Paper Initial Findings and Views on LNG Importation into Singapore, Energy Market Authority

([29])    Gas Matters Analysis – China-LNG, Gas Matters, September 2005

([30])    Delays Best Bullish Plans for LNG Terminals In China, Horizon, December 14, 2005

([31])    Plan may not go ahead, China Daily, 13 Sep 2006

([32])    Program Analysis, Macau LNG Terminal and Pipeline Projects, Deloitte Financial Advisory Services LLP, October 2006 (Confidential Report to CAPCO)

([33])    Price Concerns Dampen China’s LNG Drive, International Gas Report, July 26, 2006

([34])    This EIA Report, Part II Section 2.3- Consideration of pipeline alignment

([35])    Y13 Pipeline Tie-in Study – Aker Kvaerner, CAPCO Consultancy Study

([36])    Alternative Natural Gas Supply Project: Feasible Options for Black Point Power Station, Advantica - CAPCO Consultancy Study

([37])    LNG Feasibility Study, Joint Study by CLP, Shell, Total with Guidance from EPD, September 1992

([38])    For example, extensive site investigation work, preliminary engineering as well as the pipeline route survey have been completed.  The 18-month Environmental Impact Assessment (EIA) process is also reaching a major milestone with the submission of the EIA study report.  Consultation with Government and the public has been ongoing since 2004.  Discussions with LNG suppliers and LNG shipping providers are also underway.  In short, CAPCO’s development of the Hong Kong LNG terminal is at an advanced stage to meet the 2011 timing.  These activities could not have been conducted with the earlier options as they have only recently been raised.

 

([39])    On the average, approximately 700 workers will be employed during the construction phase, and around 60 permanent jobs during operation