4.1
Consideration of
Different Options for an LNG Supply Facility Within
This
section of the EIA Report presents a
summary of the alternatives that have been considered by CAPCO for provision of
LNG within Hong Kong SAR, namely:
· Artificial Island in
· Gravity Base Structure (GBS);
· Floating Storage and Regasification Unit
(FSRU);
· Shipboard Regasification;
· Coastal Location; and
· The No Action Alternative.
4.2
Use of an
Artificial Island in
One
option that was examined by CAPCO was that of constructing an artificial island
for the purposes of siting the LNG Terminal.
The intention was that the island would be constructed using public
fill, referred to as Construction and Demolition (C&D) materials. A preliminary engineering and environmental
appraisal of this option has been conducted and is summarised below.
In
recent years, a number of investigations have been carried out to identify
suitable sites for the construction of artificial islands. Their uses have varied from disposal of
C&D materials to urban landfills, and developments have included waste
management and other industrial facilities for which sites elsewhere may be
more heavily constrained. A site search
exercise taking on board a wide range of constraints, identified an area in the
West Lamma Channel (south of Cheung Chau and south west of Lamma) for further
consideration. The site which was
termed, Lamma South West, was investigated further as a potential location for
an artificial island constructed for the purpose of locating a LNG
terminal.
4.2.2
Preliminary Engineering Appraisal
Artificial
/ the island was prepared on the basis that the use of C&D materials is
maximised and that the whole
·
The
supply of C&D materials; and
·
The
need to protect the island construction by building the east and southern
seawalls first. These seawalls require screened and sorted C&D materials at
a lower percentage of the original C&D supply rate. The rate for suitable screened and sorted
material has been assumed at 30% of the C&D material supply rate.
The
resulting programme indicates that construction of the infrastructure for the
LNG Terminal could not start until 5.5 years after commencement of construction
on the eastern side of the island and 6.3 years after commencement on the
western side based on the high forecast C&D material supply rates, and
almost twice as long assuming the low forecast C&D material supply
rates. Such a timeline would present
insurmountable programming constraints.
Pipeline
Issues
The
artificial island would require a submarine pipeline to transport the
re-gasified natural gas to the Black Point Power Station (BPPS). The alignment for the pipeline would run west
of the site prior to following the same alignment as the option for the
Another
major constraint would be the need to pass the active South Cheung Chau
Disposal Ground (SCCDG). The seabed in
and around the SCCDG varies considerably in bathymetry from – 6mPD to
-16mPD. The seabed sediments are also
dredged muds of low in situ density,
low load bearing capacity and hence geotechnically unstable. For the submarine pipeline to pass through
this area, remedial measures would have to be taken to ensure the long term
stability of the pipeline in order to prevent unacceptable span stresses. Such measures would involve the dredging of
deep trenches along possibly the entire length of the pipeline in this area,
the result of which would be significant quantities of mud for offsite
disposal.
From
an environmental perspective the construction of the artificial island for
locating the LNG terminal introduces the following issues.
Water Quality: The information summarised above has
indicated that the construction of the island would require extensive dredging
for the seawalls which has the ability to cause impacts to water quality. The pipeline from the site to BPPS would run
west of the site prior to following the same alignment as the option for
Marine Ecology: If the LNG terminal were located on an
artificial island southwest of Lamma, then it would introduce a permanent loss
of habitat to the Finless Porpoise. The
area to the southwest of Lamma is regarded as one of the key areas for
Landscape/Visual: The artificial island would introduce a
permanent change to the landscape and seascape of the southern waters. In terms of visual sensitive receivers the
island and terminal would be visible mainly from
Conclusions
and Recommendations
From
an environmental perspective, if the LNG terminal were located on an artificial
island southwest of Lamma, then it would introduce a permanent loss of habitat
to the Finless Porpoise. The area to the
southwest of Lamma is regarded as one of the key areas for
Although
construction of an artificial island at South West Lamma is technically
feasible, the proposal has two major constraints in comparison to other sites,
namely timing and cost. Additionally,
impacts to landscape and water quality would potentially be significant.
Even
using the high forecast for C&D materials supply, it is considered that the
minimum time of six years needed for the construction of the island will mean
that the first gas would not be available before the Yacheng would be
essentially depleted. If lower supply
rates of screened C&D material are used, longer delays to commissioning a
LNG terminal will result.
If
rockfill was also used for the seawall core and sandfill used for the
reclamation, as well as the use of C&D materials, the construction period
could be significantly reduced. However,
because of the thickness and low level of the base of the marine deposits and
depth of water, the seawall construction, reclamation filling and surcharge
periods are going to be longer than the options for
4.3
Consideration of
a Gravity Base Structure
An
option that has been examined worldwide is an offshore facility referred to as
a Gravity Base Structure (GBS). The
option of a GBS is typically considered for shallow water locations, with water
depths limited to the range of 15 to 30m.
LNG storage tanks are placed inside large concrete caissons that sit on
the seabed. Receiving and
re-gasification facilities are installed on top of these concrete
structures. Breakwater protection may be
required to increase the operating availability of offshore unloading of the
LNG carriers. Regasified LNG is sent out
as natural gas using a submarine pipeline to the end user.
An
offshore terminal in the form of a GBS was considered as a potential
alternative to a land-based terminal.
The use of a GBS LNG terminal in Hong Kong was examined and serious
geotechnical concerns were raised on the use of such a structure on the muds
that are prevalent in
4.4
Floating Storage
and Regasification Unit
A
Floating Storage and Regasification Unit (FSRU) is a floating LNG storage
vessel with regasification and offloading facilities on top. The FSRU would be moored to an anchored
turret and would weathervane to adapt to changing weather conditions. LNG carriers moor alongside the FSRU to
offload LNG to the FSRU to be vaporised.
Industry has several proposals for FSRU’s, but no actual
installations.
The
FSRU is not as dependent on soil conditions as the GBS, which results in
greater location flexibility. However,
the FSRU concept requires a sufficient water depth, 40 - 60 metres, to provide
for a long term, safe operating environment for the risers that connect the gas
pipeline to the FSRU. During severe
weather, the risers in water depths less than 40 - 60 m may get damaged, posing
safety, environmental, and economic risks.
CAPCO was not able to locate a site with a suitable water depth within
the HKSAR that also had suitable environmental and metocean conditions. The siting constraints coupled with the lack
of actual installations (ie not proven technology which is critical where
security of gas supply is so important) mean that the FSRU option was not
considered further.
The
shipboard regasification option is similar to an FSRU, however it is comprised
of a fleet of LNG vessels that have been constructed specifically with
regasification and offloading facilities on the deck. These ships serve as both the transport ships
and the regasification terminals that offload gas to a pipeline via an offshore
buoy (2 buoys for continuous operation).
This concept eliminates the requirement to offload LNG offshore between
two vessels (required for an FSRU). The
first shipboard regasification terminal has just been implemented by Excelerate
in the
Like
the FSRU concept, commercially proven Shipboard Regasification requires a
sufficient water depth, 40 - 60 metres, to provide for a long term, safe
operating environment for the risers that connect the gas pipeline to the
vessels. During severe weather, the
risers in water depths less than 40 - 60 m may get damaged, posing safety,
environmental, and economic risks. CAPCO
was not able to locate a site with a suitable water depth within the
HKSAR.
With
this technology, regasification equipment is installed on each LNG
carrier. It also requires an additional
LNG carrier in the fleet, since each remains on station to act as a LNG storage
tank. This technology can be cost effective
only if the source of LNG is very close to
In
addition, since the LNG ship is used as storage, it could take up to 11 days to
unload the LNG ship versus 14-18 hours when it is transferred to shore-based
storage tanks. If severe weather occurs,
the LNG ship would be required to disconnect from the mooring system and stop
gas transfer. Conversely, with onshore
LNG storage and regasification the gas transfer would continue. Therefore, this technology is used where the
market does not require a highly reliable supply of gas, ie a situation which
is in direct contrast with
4.6
Consideration of
a Coastal Location
The
above discussions and analyses of options for LNG provision have indicated that
siting a LNG receiving terminal along the coast in
The
alternative of not replacing the depleting gas source from Yacheng 13-1 would
signify that CAPCO would eventually, once the gas source was exhausted, have to
suspend power generation at Black Point Power Station. This would increase the burden of electricity
generation on CAPCO’s other power plants, particularly the Castle Peak Power
Station which utilises coal.
CAPCO
would therefore have to increase the percentage of coal in its fuel mix which
would lead to an increase above existing levels of emissions of NOx,
SOx and total particulates until a replacement source of natural gas
is identified. The no action alternative
has also been discussed in Section 2.8.5.
The
assessment presented above supports the conclusion that the development of a
LNG terminal at a coastal location in
4.9
Alternative Site
Locations Study
An alternative site location study was
conducted by CAPCO in order to aid in the identification of suitable sites in
4.9.1
Overview of Methodology
In considering alternatives for securing
timely implementation of a future reliable gas supply to the Black Point Power
Station, the preferred option was to develop the LNG terminal at a coastal
location in
The alternative site location study used a
qualitative approach consistent with other similar studies undertaken in
The study was subdivided in two
consecutive phases. The first phase
allowed, through a constraint mapping exercise, the identification of a
longlist of potential LNG sites within HK SAR compatible with environmental,
physical and social constraints.
In the second phase, the longlist of
potential sites was subjected to a three step screening assessment during which
the sites were evaluated in a qualitative narrative manner and eliminated from
the longlist on the basis of their environmental, social, planning and marine
transit drawbacks.
The methodology therefore comprises a
series of consecutive tasks which are listed and briefly discussed below:
Phase I – Longlisting of Viable Sites
Task 1 Definition
of Necessary Characteristics/ Features of the Required Site. In order to guide the alternative site
location process, the first step was to define general site requirements for
the LNG terminal’s construction and operation.
Task 2 Environmental
Constraint Mapping: A comprehensive set of environmental
screening criteria was identified and compiled onto digital base maps using a
Geographic Information System (GIS).
This exercise allowed the identification of existing environmental
constraints within HK SAR coastal areas, thus highlighting environmentally
suitable sites for the LNG.
Task 3 Physical & Social
Constraint Mapping. Similar to the previous task, a comprehensive
set of physical and social constraint screening
criteria was identified and compiled onto digital base maps using a GIS. This exercise permitted the identification of
sites compatible with HK SAR’s physical and social constraints.
Task 4 Identification of
Longlist of Viable Sites. The environmental and physical & social
constraint maps were combined to determine the areas that would not be
considered further for the siting of the LNG terminal. The remaining unconstrained areas became, in
essence, the potential coastal locations for the LNG terminal within
Phase II – Analysis and Identification of Preferred
Site(s)
Task 5 Preliminary Screening
of Longlisted Sites. The longlisted sites identified in Task 4 were subjected to a feasibility
review against three key site suitability criteria:
·
Proximity
to residential/commercial population,
·
Land
availability/constraints, and
·
Exposure
to meteocean conditions.
This approach led to the direct
elimination of 20 sites and the identification of 7 potentially suitable
shortlisted sites.
Task 6 Detailed Review of
Shortlist of Sites. The 7 shortlisted sites identified in Task 5 were subject to further
review. The approach adopted was a
qualitative narrative one which identified the potential environmental, social,
planning and marine transit advantages and disadvantages of each site based on
preliminary conceptual layouts. The
screening process led to the direct elimination of 4 of the 7 shortlisted
sites.
Task 7 Final Selection: The 3 sites remaining from Task 6
were subjected to further detailed qualitative narrative assessment based on a
suite of pre-defined environmental and technical criteria. This final detailed
assessment provided the necessary support for the elimination of one of the 3
sites and the election of the 2 preferred sites to carry forward to the
EIA.
The following sections present in detail
the rationale and outcome of each of the seven tasks which brought the election
of the two preferred sites for the LNG terminal location: Black Point and
4.10
Phase I -
Longlisting of Viable Locations
4.10.1
Task 1 - Definition of Necessary
Characteristics/ Features of the Required Site
In
order to guide the alternative site analysis process, the general site
requirements of the LNG terminal were defined.
Overall, the LNG terminal would require the following:
·
About
30 – 40 ha of land to locate the terminal infrastructure;
·
Approach
channel, turning basin and berth of depth around –15 mPD;
·
Submarine
gas pipeline to the Black Point Power Station.
4.10.2
Task 2 – Environmental Constraint Mapping
Constraint
mapping makes extensive use of GIS-presented information to take account of
potential territorial constraints. For
the purpose of this alternative site selection study, the first step was to identify a broad
range of environmental features and characteristics of
The key sets of environmental information
used were:
·
Designated
marine park or marine reserves;
·
Gazetted
fish culture zones;
·
Wild
animal protection areas;
·
Coastal
protection areas;
·
Conservation
areas;
·
Sites
of Special Scientific Interest (SSSIs);
·
Gazetted
and potential artificial reef deployment sites; and
·
Country
Parks.
The environmental constraints that have
been reviewed include formally identified areas under the Environmental Impact Assessment Ordinance (EIAO) and other constraints associated with areas recognised under
existing legislation/regulations as being of environmental importance that
could be expected to be of interest to key government departments.
There are a number of areas within
·
Marine
mammal habitat;
·
Mudflats;
·
Mangroves;
·
Seagrass
Beds;
·
Horseshoe
crab breeding grounds;
·
Sea turtle
nesting grounds;
·
Coral
communities of high abundance and diversity;
·
Important
areas for marine life; and
·
A detailed description and evaluation of
the environmental constraint mapping criteria utilised in this task is outlined
in Section 4.10.4. The composite outcome of the environmental
constraint mapping exercise is presented in Figure 4.8.
4.10.3
Task 3 – Physical and Social Constraint
Mapping
In a similar fashion to Task 2, a broad range of key physical
and social features and characteristics of
Physical Constraints
·
Designated
areas of marine dredging and mud disposal;
·
Existing
anchorages;
·
Marine
vessel fairways;
·
Areas
of current, future or proposed reclamation;
·
Restricted
areas;
·
Gazetted
bathing beaches;
·
Typhoon
shelters;
·
Utilities
(submarine cables, pipelines and outfalls); and,
·
Water
depth.
Social Constraints
·
Areas
of high population density; and
·
Areas
of marine recreational value.
A detailed description and evaluation of
the physical and social constraint mapping criteria utilised in this task is
outlined in Section 4.10.4. The composite outcome of the physical and
social constraint mapping exercise is reported in Figure 4.9.
4.10.4
Constraint Mapping Criteria
For the purpose of the constraint mapping
exercise, environmental, physical and social constraints were examined and
subdivided into either Exclusion
Constraints or Non-exclusion
Constraints to the siting of a LNG terminal and its associated facilities:
·
Exclusion constraints consist of locations/areas which possess
features where Government Departments/ Policies would not be compatible with a
LNG terminal and would thereby be recommended to be avoided; and,
·
Non-exclusion constraints exist at locations/areas that are
considered to be either important in terms of their ecological or environmental
value; or recognised by Government
Departments that, although not considered to be “no go areas”, their
sensitivity should be taken into account during the alternative site location
analysis so as to facilitate future permitting requirements and to allow an
objective assessment of the implementation risk.
A summary of this classification is
presented in Table 4.1 and 4.2 and a detailed description and
evaluation of the environmental constraint mapping criteria utilised in Tasks 2 and 3 is reported in Tables 4.3 and
4.4.
Table 4.1 Classification
of Environmental Constraints
Exclusion Constraints |
Non-exclusion Constraints |
Designated marine parks and marine reserve |
Important areas for marine life |
Gazetted fish culture zones |
Coral communities |
Wild animal protection areas |
Potential marine parks and marine reserves |
Coastal protection areas |
Biologically Productive Areas such as Spawning Grounds and/or Nursery
Areas for Commercial Fisheries Resources |
Conservation areas` |
Mudflats |
Sites of Special Scientific Interest |
|
Gazetted artificial reef deployment sites |
Mangroves |
Country parks and special areas |
Seagrass Beds |
|
Horseshoe crab breeding grounds |
|
Sea turtle nesting grounds |
|
Marine mammal habitat |
Table 4.2 Classification
of Physical & Social Constraints
Exclusion Constraints |
Non-exclusion Constraints |
Designated or gazetted areas of marine dredging and mud disposal
(active areas) |
Designated or gazetted areas of marine dredging and mud disposal
(gazetted inactive areas and constrained sand deposits) |
Existing anchorages |
Marine vessel fairways (minor fairways) |
Marine vessel fairways (major fairways) |
Future or proposed reclamations |
Areas of current reclamation |
Utilities (submarine cables, pipelines and outfalls) |
Restricted areas |
Water depth |
Gazetted bathing beaches |
Areas of recreational value |
Typhoon shelters |
|
Areas of high population density |
|
Table 4.3 Evaluation
of Identified Environmental Features
Feature |
Review |
Evaluation |
Designated
Marine Parks and Marine Reserve (Figure
4.2) |
There are four designated ·
Marine
Parks - Yan Chau Tong - Hoi Ha Wan - Tung Ping Chau - Sha Chau and Lung Kwu Chau ·
Marine
Reserve - The
Marine Parks Ordinance allows for the prohibition of a number of activities
within marine parks and reserves, including development. The Sha Chau and |
Designated
|
Gazetted
Fish Culture Zones (Figure 4.3) |
Marine fish culture in |
Each FCZ is considered to be an Exclusion Constraint to the siting of
a proposed LNG terminal in |
Wild Animals Protection Areas (Figure 4.2). |
The Wild Animals Protection Ordinance
(Cap. 170) restricts access to designated areas of wildlife habitat. Under the Ordinance three areas have been
designated as Wild Animal Protection Areas and are protected by the
Agriculture, Fisheries and Conservation Department. These areas are identified as the Mai Po
Marshes, Sham Wan Turtle Nesting Area and the Yim Tso Ha Egretry ([5]) . |
Wild Animal Protection Areas can be
considered to be Exclusion Constraints
to the siting of a proposed LNG terminal in |
Coastal
Protection Areas and Conservation Areas (Figure 4.2) |
To promote the environment, areas of
conservation value may be declared as Conservation Zones under the Town
Planning Ordinance. Such areas include
Coastal Protection Areas, which have been identified to retain natural
coastline, and Conservation Areas, which have been identified to retain
existing natural features and rural use ([6]) .
|
Coastal
Protection Areas and Conservation Areas can be considered to be Exclusion Constraints to the siting of a proposed LNG terminal in
|
Sites
of Special Scientific Interest (SSSIs) (Figure 4.2). |
Sites of Special Scientific Interest
(SSSIs) may be land based or marine sites that are of special interest
because of their flora, fauna, geographical, geological or physiographic
features as identified by the Agriculture, Fisheries and Conservation
Department. |
SSSIs
can be considered to be Exclusion
Constraints to the siting of a proposed LNG terminal in |
Important
Areas for Marine Mammals |
The Indo-Pacific Humpback or Chinese
White Dolphin (Sousa chinensis) and
the Finless Porpoise (Neophocaena
phocaenoides) are the only species of marine mammal regularly sighted in
Hong Kong waters ([8])
. The population of Sousa chinensis is reported to be centred around the Pearl River
Estuary and Hong Kong waters are thought to represent the eastern portion of
its range ([9]).
West and Northwest Lantau represent the major areas of distribution of
Sousa chinensis in |
Both of these species are mobile and
have large areas that they inhabit, often seasonally. Because of their mobile nature and the
large areas of their habitats, they are considered to be Non-exclusion Constraints to the siting of a proposed LNG terminal
in |
|
The finless porpoise, Neophocaena phocaenoides, is a small
cetacean endemic to southern and eastern |
|
Biologically Productive Areas such as
Spawning Grounds and/or Nursery Areas for Commercial Fisheries Resources (Figure 4.4) |
The location of spawning grounds and
nursery areas for commercial fisheries resources was identified in the |
As these areas cover large areas and are
seasonal they can be considered to be Non-exclusion
Constraints to the siting of a proposed LNG terminal in |
Mudflats (Figure 4.4) |
Mudflats often lie in sheltered heads of
harbours or in bays land-locked by the surrounding coasts ([12])
. They are classified as areas of
fine-grained sediment (ie silt or fines) which lie between the high and low
tide marks and which are not covered by seagrasses, mangroves or typical
wetland vegetation. The habitat is
generally fed with freshwater streams.
Wave action is weak but currents agitate fine sediments from the
substrate and create constantly turbid conditions. The habitat is susceptible to pollution
because of its poor flushing conditions.
Mudflats are known to support a variety of soft-bottom invertebrates
and thus provide valuable feeding habitat for migratory bird populations as
well as other organisms ([13]).
The largest of Hong Kong’s mudflats occurs in |
Mudflats are considered to be a Non-exclusion Constraint to the
siting of a proposed LNG terminal in |
|
Sandy shores are mobile and unstable
environments subjected to constant water movement and wave action and harbour
an array of marine species. |
|
Mangroves
(Figure
4.4) |
Mangroves
are characteristic of the tropics and mostly are found on intertidal to high shore
areas in the estuarine waters of sheltered bays, and seawards of salt
meadows. The mild climate and the
massive freshwater of the Pearl River (especially during the summer) promote
the development of mangrove communities in Hong Kong, particularly in the
western region (eg |
Acknowledged
mangrove habitats in Hong Kong are considered to be a Non-exclusion Constraint to the siting of a proposed LNG terminal
in |
Seagrass
Beds (Figure 4.4). |
Seagrass beds occur in shallow,
sheltered intertidal or subtidal areas and are recognised as areas of high
biological productivity. As such, they
provide high value habitat as feeding and nursery grounds for a range of
marine species ([16]).
However, seagrass beds have been recorded with a very low distribution
in |
Seagrass habitats in Hong Kong are
considered to be a Non-exclusion
Constraint to the siting of a proposed LNG terminal in |
Horseshoe Crab Breeding Grounds (Figure 4.4) |
Two species of Horseshoe Crabs (Tachypleus tridentatus and Carcinoscorpius rotundicauda) have
been recorded in |
These habitats are considered to be Non-exclusion Constraints to the
siting of a LNG terminal in |
Sea Turtle Nesting Grounds (Figure 4.4). |
Although four ([18]) species of sea turtle have been found in Hong Kong waters, only the
Green Turtle (Chelonia mydas) has
been recorded as breeding locally ([19]).
The Green Turtle is a highly endangered species listed under the
Convention on International Trade in Endangered Species of Wild Fauna and
Flora (CITES) Appendix I. Locally, the
Green Turtle is protected under the Wild Animals Protection Ordinance
Cap.170. Presently, the sandy beach at
Sham Wan on |
The beach has been designated as a
Restricted Area and can be considered to be a Non-exclusion Constraint to the siting of a LNG terminal in |
Gazetted Artificial Reef Deployment
Sites (Figure
4.3). |
At present, the Agriculture, Fisheries
and Conservation Department is undertaking an artificial reef deployment
programme to enhance fisheries and promote bio-diversity in |
Due to their ecological and fisheries
value, gazetted artificial reef deployment sites in Hong Kong are considered
to be an Exclusion Constraint to
the siting of a proposed LNG terminal in |
Coral Communities (Figure 4.4) ([21]) ([22]) ([23]) ([24]).
|
The Agriculture, Fisheries and
Conservation Department report that there are over 80 species of corals
recorded in Numerous studies have been undertaken in
Hong Kong that have provided information on the distribution of corals in |
Coral communities can be considered to
be Non-exclusion Constraints to
the siting of a proposed LNG terminal in |
|
A total of twenty-three
Country Parks and fifteen Special Areas (eleven of which lie inside Country
Parks) have been established in Hong Kong under the Country Parks Ordinance, which provides a legal framework for
their designation, development and management ([26])
. In total, the area of land protected under
this Ordinance covers approximately 42,000 hectares. Country Parks comprise scenic hills,
woodlands, reservoirs and coastline throughout Hong Kong Several islands,
such as Tung Ping Chau in |
Due to their conservation and recreation
value, Country Parks are considered to be an Exclusion Constraint to the siting of a proposed LNG terminal in |
|
In addition to Hong Kong’s
existing gazetted four ·
Proposed ·
Proposed ·
·
Outer ·
Tai Long Wan Due to the potential for
these areas to be gazetted under the Marine
Parks Ordinance and thereby being granted protection from development,
each of these areas are considered to be Non-exclusion Constraints to the
siting of a LNG terminal in Hong Kong.
It should be noted, that although it is understood that South Lamma,
Outer Port Shelter and Tai Long Wan in Sai Kung have also been identified as
potential marine parks ([27])
it is presently understood
that these areas are only at the feasibility stage and no firm plans have
been drawn up. It is noted that under
the Southwest New Territories Development Study the Southwest of Lantau as
well as the |
As those areas have yet to be designated
under the Marine Parks Ordinance
these areas are considered to be Non-exclusion
Constraints to the siting of a LNG terminal in |
Table 4.4 Evaluation
of Identified Physical Features
Feature |
Review |
Evaluation |
Designated or Gazetted Areas of Marine Dredging and
Mud Disposal (active and inactive) (Figure 4.5) |
The Civil Engineering and Development Department
(CEDD) of the Hong Kong SAR Government currently maintains a number of
gazetted areas in ·
Open sea disposal areas for
uncontaminated mud; ·
Exhausted sand borrow pits for disposal
of uncontaminated mud; ·
Sand deposit areas (extent prior to
dredging, sand remaining); and, ·
Contained disposal pits for contaminated
mud. |
Each of areas designated for specific marine
fill/disposal uses is considered to be an Exclusion Constraint to the siting of a LNG terminal in |
Existing Anchorages (Figure 4.6) |
There are a total of nineteen existing anchorages
in |
The Marine Department considers each anchorage to
be closed to future development and, as such, can therefore be considered as
an Exclusion Constraint to the
siting of a LNG terminal in |
Marine Vessel Fairways (Figure 4.6) |
The LNG carrier must be provided with safe access
to the LNG terminal. In doing so, the
density and routes of other traffic within the same navigable waterway must
be considered in order to mitigate against potential incidents. Control of transit speed, traffic control and
reporting are important elements while within designated channel fairways for
mitigating the incidence and consequences of either a collision or grounding. 'The LNG carrier is required to comply with
the applicable rules-of-the-road as are other ship types while within HK
waters A study of Hong Kong’s marine traffic,
based on a review of Marine Department casualty files between 1992 and 1994,
has subsequently designated four different marine categories to signify risk ([28]) as follows: ·
Highly restricted water area with high
traffic volumes; ·
Highly restricted water area with low
traffic volumes; ·
Unrestricted water area with high traffic
volumes; and, ·
Unrestricted water area with low traffic
volumes. In addition to these areas, frequently used access channels to · The Tathong Channel, which is the main
access channel on the eastern side of · The East Lamma Channel, which is the major
entry and exit route for · The West Lamma Channel, which is mainly
used by traffic to and from southerly destination and primarily by general
cargo vessels. · The
Adamasta (South West Lantau) Channel,
which is used mainly by smaller cargo vessels to and from the southwest and
the high speed ferries to and from |
Highly
restricted water areas and unrestricted water area with high traffic volumes are considered to be Non-exclusion Constraints to the
siting of a LNG terminal due to the associated risk. Unrestricted water area with low traffic
volume is considered not to be a constraint. Due to
restrictions on use imposed by Marine Department, frequently used access
channels are considered to be an Exclusion
Constraint to the siting of a LNG terminal. It should be noted that the LNG pipeline
would be able to pass through these channels as such use is allowed in There are also a number of other fairways in
Hong Kong waters, such as the Yantian Fairway and |
Areas of Current, Future or Proposed Reclamation (Figure 4.5) |
Civil Engineering and Development Department
records ([29]) indicate several areas of current, future or proposed reclamation
including at Tsing Yi, Pak Shek Kok, Victoria Harbour, North Lantau, Penny’s
Bay and Tseung Kwan O. |
All
reclamations currently in progress have been identified as Exclusion Constraints to the siting
of a LNG terminal in |
Restricted Areas (Figure 4.5). |
There are three types of restricted areas in |
Restricted Areas have been classified as an Exclusion Constraint to the siting of
a LNG terminal in |
Gazetted
Bathing Beaches (Figure 4.1) |
There are currently forty-one gazetted
beaches in |
All gazetted beaches in Hong Kong would
be considered to be Exclusion
Constraints to the siting of a proposed LNG terminal in |
Typhoon Shelters (Figure 4.6). |
There are fourteen public-use typhoon shelters
located within |
Hong Kong’s typhoon shelters are considered to be
an Exclusion Constraint to the
siting of a LNG terminal in |
Utilities (Submarine Cables, Pipelines and
Outfalls) (Figure 4.5) |
There are numerous
submarine cables, pipelines and outfalls in |
Each submarine cable, pipeline and outfall is
considered to be a Non-exclusion
Constraint to the siting of a coastal LNG terminal in |
Water Depth (Figure 4.7). |
One of the requirements for a safe transit and
approach to the proposed LNG terminal is to have a seabed depth of around
-15m PD and this would require some dredging.
|
Water depth of less than 10m is considered to be a Non-exclusion Constraint to the
siting of a LNG terminal in |
Table
4.5 Evaluation
of Identified Social Features
Feature |
Review |
Evaluation |
Areas of High
Population Density ([33]) (Figure 4.1) |
The
construction and operation of a LNG terminal could be considered to provide
an associated risk as well as having potentially adverse social
implications. |
Areas of
high population density, which, based on best professional judgement, are
taken as areas housing > 100,000 people per km2 are
considered to be an Exclusion
Constraint to the siting of a LNG terminal in |
Areas
of Recreational Value (Figure 4.1) |
Apart from the
recreational value provided by Hong Kong’s Country Parks, Marine Parks and
Marine Reserve, a number of Hong Kong’s coastlines and the surrounding waters
have been categorised by the Environmental Protection Department (EPD) of the
Government as Secondary Contact Recreation Zones ([34])
. |
Whilst
there are no regulations against development within these areas, they can be
considered to be a Non-exclusion
Constraint to the siting of a LNG terminal in |
|
|
|
4.10.5
Task 4 - Identification of Potentially Viable
Longlisted Sites for a LNG Terminal
The environmental and physical &
social exclusion maps (Figures 4.8 and 4.9 respectively) were combined
to produce a composite constraint map which details all those constrained areas
that would not be considered further for the siting of the LNG terminal. The comprehensive composite map is reported
in Figure
4.11.
Based on the examination of the composite
constraint map and taking into consideration the residential and commercial
premises of HK SAR (Figure 4.10), a total of 27 unconstrained
sites for the potential siting of the LNG terminal were identified and compiled
into a longlist. In the Project Profile
for this EIA Study it is mentioned that there were 29 sites. Two of the 29 (Fan Lau East and Fan Lau West)
were revealed to be within the
Table 4.6 Longlist
of the 27 Potentially Viable Sites
N. |
Site |
N. |
Site |
1 |
Black
Point |
15 |
|
2 |
Lung
Kwu Sheung Tan |
16 |
Tsing
Yi |
3 |
Castle
Peak North |
17 |
|
4 |
West
Brothers |
18 |
Po |
5 |
Yam
Tsai |
19 |
Sung
Kong - Fury Rocks |
6 |
Brothers
Point |
20 |
|
7 |
Sham
Wat Wan |
21 |
|
8 |
North
Tai O |
22 |
|
9 |
Yi O |
23 |
Tung
Lung Chau |
10 |
Peaked
|
24 |
Area
137 |
11 |
|
25 |
Wang
Chau |
12 |
|
26 |
|
13 |
Shek
Kwu Chau |
27 |
Tap
Mun |
14 |
|
|
|
4.11
Phase II -
Analysis and Identification of Preferred Site(s)
4.11.1
Task 5 - Preliminary Screening of
Longlisted Sites
In order to proceed in the elimination of
sites deemed unsuitable for the LNG terminal, the 27 longlisted sites were
subjected to a social and technical feasibility review against three key site
exclusion criteria:
·
Criterion
1: Proximity
to existing residential/commercial population. The presence
of inhabited areas within a buffer zone of 500 m from the site’s perimeter was
selected as a safety-based exclusion criteria.
·
Criterion
2: Land
availability and physical constraints. The
availability of at least 30 - 40 ha of unconstrained land (natural or
reclaimed) is a necessary requirement for the siting of the LNG terminal. Failing to meet either of the parameters that
make up this criterion will lead to the direct elimination of the site from the
list of potentially viable sites.
·
Criterion
3: Exposure to
metocean conditions. The exposure of a site to significant
metocean (mainly wave and currents) conditions has direct repercussions on the
flexibility of site layout, and the extent of the marine works needed to
provide adequate safety for marine operations.
The extent of marine works introduces permitting risk as adverse
environmental impacts may be incurred.
Criterion 1: Proximity to Existing Residential/Commercial
Population
For the purpose of this site selection
study, a distance of 500 m from the LNG terminal’s boundary (including turning
circle, jetty and terminal) has been adopted as safety-based exclusion
criteria. The distance of 500 m has some
relevance in
The application of this criterion allows
to automatically exclude all sites which present residential or commercial
population within the 500 m buffer zone from the site’s perimeter. Based on this exclusion criterion, 10 sites
were eliminated from the longlist of 27 sites.
The eliminated sites are listed in Table
4.7.
Table 4.7 Criterion 1 –
Eliminated Sites
N. |
Site |
N. |
Site |
3 |
Castle Peak North |
13 |
Shek Kwu Chau |
6 |
Brothers Point |
14 |
|
7 |
Sham Wat Wan |
15 |
|
8 |
North Tai O |
21 |
|
9 |
Yi O |
22 |
|
Criterion 2: Land Availability and Physical Constraints
The site selection Criterion 2 is a
combination of two strongly correlated parameters deemed essential for the
location of the LNG terminal: Land
availability and land constraint
·
Land Availability:
The suitability of a potential site for the LNG terminal is strongly
dependent on the availability of least 30 - 40ha of land which may be natural
or artificially reclaimed. The need for
30 - 40 ha is an essential requirement based on technical and safety parameters
determined by the LNG industry for a terminal of the capacity proposed in
·
Physical Constraints:
From a construction feasibility point of view, certain areas/sites can
automatically be eliminated on the basis of their physical characteristics
(i.e. steep morphology/bathymetry).
On the basis of the above, the potential
viable candidate for the siting of the LNG terminal will necessarily have to
meet the physical characteristics/criteria listed in Table 4.8.
Table 4.8 Site’s Physical
Requirements
Requirement |
Technical
Description of Requirement |
30 ha of
land either on land or partially in the sea |
The need
for 30 ha is an essential requirement based on technical and safety
parameters determined by the LNG industry for a terminal of this capacity. |
Reclamation
needs to be completed in water depth less than 10 m |
This
requirement is based on the practical limitations of the marine works. |
Sufficient
access for hill cutting activities |
Where
cuttings are required in steep land areas, there must be sufficient means of
access from nearby areas without requiring the formation of additional
reclaimed platforms within the sea. |
50x50
area within 100m of the proposed site boundary |
This area
is essential for the initial stages of the construction of the LNG
terminal. A platform will be created
on this area to enable the initial mobilisation of the building material and
will serve as a logistic/storage base for construction works |
If
metocean conditions necessitate a breakwater (see Criterion 3), then the water depths within
100 m of the seaward of the side of the jetty should be less than – 15m |
This
requirement is based on the practical limitations of the marine works. |
Based on this exclusion criterion, 4 sites
were eliminated from the longlist of 27 sites.
The eliminated sites are listed in Table
4.9, together with a brief description of the rationale that led to their
exclusion.
Table 4.9 Criterion 2 –
Eliminated Sites
N. |
Site |
Description |
4 |
West Brothers |
Airport restrictions, shipping lanes, contaminated
mud pits, dredging areas |
16 |
Tsing Yi |
Insufficient space on land, requires reclamation in
an area where reclamation is heavily constrained |
17 |
|
Technical and environmental difficulties in
excavation and reclamation due to slope heights and surrounding water depths |
18 |
Po |
Technical and environmental difficulties in
excavation and reclamation due to slope heights and surrounding water depths |
Criterion 3: Exposure to Metocean Conditions
Exposure of a site to adverse metocean
conditions means that, in order to grant protection to the terminal structures
and to the LNG carrier during unloading operations, a breakwater would need to
be constructed. In such adverse/extreme
metocean conditions the extensive marine works that arise from the construction
of the breakwaters could in turn potentially have severe environmental and
technical implications which could introduce a major permitting risk.
Two metocean parameters were considered in
the evaluation of Criterion 3 as they are deemed directly correlated with
potential interference or damage to the LNG terminal/LNG carriers and,
therefore, with the siting of the LNG terminal:
·
Waves: Wave action
has the potential to affect the LNG carrier’s berthing and mooring manoeuvres
as well as causing potential damage to the LNG terminals structures (jetty,
etc.). The wave climate in
·
Currents: Currents
have the potential to affect the safety and efficiency of an LNG carrier’s
berthing and mooring manoeuvres. Current
velocities are influenced by the semi diurnal tidal regime of the
Based on these parameters, sites directly
exposed to long deepwater fetches extending towards the easterly and
south-easterly sectors were deemed not viable for the siting of the LNG
terminal as special measures would be required to mitigate the metocean
conditions. The measures themselves have
the potential to introduce insurmountable permitting risks as a result of
potentially severe environmental implications.
On the basis of this criterion 4 sites were eliminated from the longlist
due to their exposure to metocean conditions.
These sites and a brief description of the exclusion rationale are
listed in Table 4.10.
Table 4.10 Criterion
3 – Eliminated Sites
N. |
Site |
Description |
19 |
Sung Kong |
Sung |
20 |
|
|
23 |
Tung Lung Chau |
Tung Lung Chau Island is located approximately 500
m south of Fat Tong Mun and and Joss House Bay (Tai Miu Wan). With the exception of the north and
north-eastern shore (where a village and Fish Culture Zone are located), the
island is exposed to the prevailing easterly/south easterly metocean
conditions. In order to provide year
round access for berthing and unloading of LNG a large breakwater would be
required along the island’s exposed shores which in turn may lead to severe
environmental and technical implications.
Locating the LNG terminal on the more protected north and north
eastern shores has not been considered feasible due to the presence of the
village and gazetted fish culture zone.. |
25 |
Wang Chau |
Wang Chau is a small island located approximately 1
km east of |
Conclusions
The application of the three exclusion
criteria discussed in this section led to the direct elimination of 20 sites
and thus the identification of 7 sites on an interim shortlist (Table 4.11).
Table 4.11 Interim Shortlisted
Sites
N. |
Site |
1 |
Black
Point |
2 |
Lung Kwu
Sheung Tan |
5 |
Yam Tsai |
10 |
Peaked
Hill |
11 |
|
12 |
|
24 |
Area 137 |
4.11.2
Task 6 - Detailed Review of Interim
Shortlist of Sites
The 7 shortlisted sites identified in Task 5 were further assessed in a
qualitative integrated manner whereby the environmental aspects of each of the
sites, as well as their safety, social and marine transit considerations, were
subject to a detailed review.
A qualitative narrative approach was
adopted which identified the potential environmental advantages and
disadvantages of each site. The
screening process led to the direct elimination of the sites, based on objective
assessment of the environmental drawbacks or advantages of each option.
The initial approach was to conduct a
detailed review of the general site requirements that characterise the 7
selected sites with the aim to better identify and evaluate the potential
environmental aspects of the LNG terminal’s construction and operation. Once this first review was completed, a
number of environmental, safety and social parameters were examined to assess
the overall suitability of the sites.
In order to provide the qualitative
approach with the consistency needed for the site selection exercise, the same
list of both the general site requirements and the environmental, safety,
social and marine transit aspects was used to review each site’s suitability
criteria. This list is presented below:
General Site Requirements
1.
Land Availability and Constraints:
Approximately 30 ha of unconstrained land to locate the terminal
infrastructure. Further detailed
assessment with respect to Task 5 (Criterion 2) was completed with the aim of
determining the site’s potential issues related to land availability and
associated constraints.
2.
Operational Depth:
Approach channel, turning basin and berth require a water depth of approximately
–15 mPD to provide safe transit and manoeuvrability depths for the LNG
carriers. In order to reduce extensive
dredging and maintenance for the creation of a suitable turning basin and
approach channel, a water depth of > -10m within 50m and > -15m within
500m from the site’s coastline were adopted to determine the suitability of the
sites.
3.
Pipeline: Submarine
gas pipeline to the Black Point Power Station.
The primary aspects that were used to determine the suitability of a
site were length of the pipeline and the level of physical/planning constraints
along the proposed route. The level and
extent of constraints is strongly correlated with construction time and
potential environmental risks. Thus, in general terms, fewer constraints would
mean fewer potential environmental impacts.
4.
Distance from Sensitive Receivers:
Distance from populated areas.
Further detailed assessment with respect to Task 5 (Criterion 1) was
completed with the aim of determining the site’s potential safety drawbacks
concerning populations living in proximity to the LNG terminal’s site.
Environmental, Social and Planning
5.
Terrestrial Environment:
An overview of the site’s terrestrial environment, including its
proximity to terrestrial habitats of high ecological value, was completed in
order to determine the overall environmental sensitivity of the site. The primary objective of this review was to
identify major terrestrial habitats that may suffer, directly or indirectly, from
the construction and operation of the LNG terminal at the selected site. Loss of high ecological value habitat, loss
of rare/protected/endemic species and interferences with sensitive terrestrial
habitats found in close proximity of the site were considered as major
environmental drawbacks. The ecological
value of a habitat/species was determined in respect of its/their conservation
value, spatial distribution and abundance within HK SAR based on available
information.
6.
Marine Environment:
An overview of each location’s marine environmental characteristics,
including its proximity to marine habitats of high ecological value, was
completed to determine the overall sensitivity of the site. The primary objective of this review was to
identify major marine habitats that may be impacted directly or indirectly from
the construction and operation of the LNG terminal at the selected site. Loss of high ecological value habitat, loss
of rare/protected/endemic species and interference with sensitive marine habitats
found in close proximity of the site were considered as environmental
drawbacks. The ecological value of a
habitat/species was determined by virtue of its/their conservation value,
ecological importance, spatial distribution and abundance within HK SAR.
Although not strictly of an ecological
nature, data from AFCD’s Port Survey 2001/2002 data was examined for each site,
in order to determine the status of the fisheries resources/operations in and
around their coastal waters. Proximity
of the site to fish culture zones and gazetted artificial reefs were also
addressed in the assessment.
7.
Social: The
potential social interferences to local/neighbouring communities caused by the
LNG terminal’s construction and operation were assessed. The primary objective was to determine the
existing social conditions at and around the site and therefore identify
potential direct and indirect impacts that could arise from the development of
the LNG terminal.
8.
Planning: The site’s
existing/established planning framework was determined in order to identify the
potential for planning related conflicts as a consequence of the construction
and operation of the LNG terminal.
9.
Permitting Risk:
The permitting risks and complexity with regard to the likelihood of
objections that may result in significant schedule delays were determined.
Marine Transit
10.
Exposure: The
prevailing “metocean” conditions (waves and currents) at the site have the
potential to affect the ability of the LNG carrier to berth and manoeuvre. Further detailed assessment with respect to Task 5 (Criterion 3) was completed with the aim of determining the site’s
suitability with respect to its exposure to wave and currents.
11.
Interference with Shipping:
The terminal, jetty, turning circle and approach channel have the
potential to interfere with passing ships and vice versa. The chosen determining factors for this
marine transit aspect were the location and orientation of the site and its
approach channel/turning basin with respect to major or minor vessel fairways.
12.
Volume of Marine Traffic:
The transit of the LNG carrier to the terminal will require passage
through
4.11.3
Black Point
Introduction
Black Point is a headland located in the
western most part of the
The site is located to the north western
side of the headland, adjacent to BPPS.
Due to its steep morphology, the site will need to be created through a
combination of cutting into the hillside/headland and reclamation. The berth and jetty will be located towards
the west end of the reclamation in order to be in water as deep as possible and
yet to avoid the passage of vessels up and down the
The coastline at Black Point has partially
been modified in the past as a result of the works for the BPPS (Figure 4.13). The overall quality of the headland’s
surrounding marine waters is strongly affected by the discharges from the Pearl
River Delta and the Shenzhen River and, as a result, the marine ecology at
Black Point is under the influence of the seasonal changes in freshwater fluxes
between the summer and winter months which directly affects species diversity
and abundance.
With the exception of the reported
presence of the Indo-Pacific Humpback Dolphin (Sousa chinensis), recent information on marine ecological resources
of Black Point has not identified any assemblages of high ecological value and
the majority of marine habitats identified are considered to be of low
ecological importance.
Although Humpback dolphins have been
sighted in the area it must be noted that the waters around Blank Point’s
headland support a low number of sightings in comparison to other areas in
Black Point
Figure 4.13 Aerial
View of the Black Point Site
Terrestrial ecology at Black Point is
mainly dominated by shrubland habitat interspersed with grassland which is
typical of the granite hill slopes in
The site is located on the northern coast
of the headland and it is relatively sheltered from prevailing metocean conditions.
The proximity to the
The site is relatively remote from densely
populated areas and the closest villages are located at Lung Kwu Tan
(approximately 2 km from the potential site) where the population is
approximately 1,800. The closest
developments to the site, other than BPPS, are a mixture of small scale
industrial uses at Lung Kwu Sheung Tan.
No declared monuments or known sites of archaeology, graded buildings,
graves or significant archaeological deposits have been reported at Black Point
site.
Conceptual Layout
The main construction aspects of the site
are outlined below. These are based on
the preliminary conceptual layout reported in Figure 4.14:
·
Dredging: In order to
locate the LNG berth away from the marine traffic in Urmston Road significant
dredging will be required (approximately 2.5 Mm3) for the formation
of the approach channel and turning basin.
The dredging of the turning circle down to –15mPD, i.e. 9m deep in
places, will require maintenance dredging once every 4 years.
·
Reclamation: The area to
be reclaimed is approximately 16 ha and the mud underneath the seawall and
reclamation may reach 7 m in depth. The
majority of material excavated from Black Point shall be used within the
reclamation. However, due to the
relative timing of the excavation and reclamation works and the limited space
available on site it may be necessary to temporarily store the excavated
material at a designated stockpile site.
·
Site Formation and Construction:
In order to minimise blasting and yet provide material for the
reclamation only the LNG tanks have been located on the existing land at a
level of +5 mPD. Marine access and in
particular road access is already well established. There would be no requirement for gazettal of
access roads. The heavy load berth in
front of the power station could be used for marine access. For the most part tidal velocities at the
reclamation are relatively low and are not likely to affect construction
activities. Only at mid ebb tide on
Spring Tides are velocities likely to be strong enough to affect some
construction activities.
Figure 4.14 Conceptual
Layout for Black Point Site
Site Review
The general site requirements and the
environmental, safety, social, planning and marine transit aspects of the Black
Point site are summarised in Table 4.12.
Table 4.12 Site Review – Black
Point
General
site requirements |
|
1 |
Land Availability and Constraints: The site will be created through a combination of cutting into the
hillside/headland and reclamation. The
land impacted by the reclamation is unconstrained. The Planning Department stated that Black
Point has been identified as a potential second landing point for the
proposed |
2 |
Operational Depth: The waters bordering the headland are consistently shallow, often less
than -5mPD. Considerable dredging will
be required for turning circle and approach channel, dependant on the jetty
location and the approach channel orientation. |
3 |
Pipeline:
No pipeline is required due to close proximity to BPPS. |
4 |
Distance from Sensitive Receivers: The closest villages are located at Lung Kwu Sheung Tan (approximately
2 km from the potential site) where the population is approx. 1,800. The closest developments to the site, other
than BPPS, are small scale industrial complexes at Lung Kwu Sheung Tan. |
Environmental, Social and Planning |
|
5 |
Terrestrial
Environment: ·
The
headland is mainly composed of shrubland habitat interspersed with grassland.
The northern slopes present the densest and tallest shrubland vegetation,
whilst the southern side is mainly covered with grassland and scattered rocky
boulders and outcrops. |
6 |
Marine
Environment: ·
The
site is located to the south of mudflats at Ha Pak Nai and is relatively
distant from Mai Po Inner Deep Bay Ramsar Site. ·
Approximately
4km to the south west of Black Point is the designated Sha Chau and ·
Presence
of the Indo-Pacific Humpback Dolphin (Sousa
chinensis). ·
The
waters to the south of Black Point are reported as a spawning ground for
commercial fisheries. The adult fish production is however relatively low in
comparison to elsewhere in ·
Water quality at Black Point is
strongly influenced by the |
7 |
Social: The area is presently uninhabited and the
closest villages lie approximately 2 km from the site (Lung Kwu Sheung Tan). |
8 |
Planning: The northern
portion of the site is a Secondary Contact Recreation Zone. The coastline has
been proposed for potential reclamation for Tuen Mun Port Development, which
contains a recommendation for siting LPG facilities. Some government land landscaped by the BPPS
will be affected. Black Point has been identified as a second landing point for
the proposed |
9 |
Permitting Risk: The
northern portion of the site is a Secondary Contact Recreation Zone and some objections
may arise due to perceived safety concerns and Fung Shui from local
residents. |
Marine Transit |
|
10 |
Exposure: The LNG terminal will be sited on the north western
coast of the Black Point headland on the edge of |
11 |
Interference with Shipping: Although
the site is near the northern reaches of the busy |
12 |
Volume of Marine Traffic:
Transit to the site is assumed to be via the East
Lamma Channel, Western Fairway, Ma Wan Channel and the Urmston Rd
Channel. This is a long passage
through the “heart” of |
13 |
Need
to conduct a Quantitative Risk Assessment of the transit of LNG via a LNG
carrier to Black Point via the Ma Wan channel at the EIA stage to verify the
acceptability of the transit route. |
A summary of the environmental, social and
planning characteristics of the Black Point site are reported in Figure 4.15.
Conclusions
From a review of Black Point’s
environmental, social, planning and marine transit characteristics it emerges
that the site poses a series of advantages for the location of the LNG
terminal, namely:
·
The
main advantage from an environmental perspective is Black Point’s close
proximity to BPPS meaning that the construction of the subsea import pipeline
to the power station will not be needed.
This allows the elimination of environmental impacts associated with the
pipeline’s construction.
·
The
area is presently uninhabited and the closest village is located at
approximately 2 km from the site at Lung Kwu Tan. The nearest developments are small
scale industrial complexes.
·
The
site is relatively sheltered from prevailing metocean conditions.
·
Although
the necessary land for the construction of the LNG terminal will need to be
obtained from reclamation and excavation works, the coastal waters and the land
potentially affected by the works are largely unconstrained.
·
The
approach channel and turning basins will be located sufficiently far away from
the vessel fairway and will not interfere with existing shipping activities.
The location of the LNG terminal at Black
Point does have some disadvantages, summarised below:
·
Land
for the construction of the LNG terminal will be obtained partly from
reclamation and partly from the excavation of the hillside. This will lead to the loss of natural habitat
(marine and terrestrial) and to the overall change in morphology of the coast
and the hillside.
·
Recorded
presence of Indo-Pacific Humpback Dolphin (Sousa
chinensis) in the coastal waters of Black Point.
·
Considerable
dredging will be required for turning circle and approach channel. The final volumes will be dependent on the
jetty location and the approach channel orientation.
·
Marine
Transit of the LNG carrier will be via East Lamma Channel,
The site’s proximity to BPPS is considered to be the
site’s major environmental asset which, together with the site’s remoteness
form inhabited areas, its sheltered position with respect to prevailing
metocean conditions and the unconstrained nature of the area to be reclaimed
will strongly reduce the overall environmental impacts.
4.11.4
Lung Kwu Sheung Tan
Introduction
The site at Lung Kwu Sheung Tan lies on
the south side of Black Point headland in close proximity to the BPPS (Figure 4.16). Due to the headland’s relatively steep
morphology, the Lung Kwu Sheung Tan site will be created through reclamation.
The southern coastline of the headland
consists mostly of natural rocky shoreline with the exception of a relatively
short artificial section (approximately 200 m) found corresponding to a
government owned reclaimed land on the south eastern portion of the headland.
Lung Kwu Sheung Tan
Figure 4.16 Aerial View of the Lung Kwu Sheung Tan
Site
Due to the nature of the site’s
development, the construction of the LNG terminal will interfere with marine
and coastal habitats only and will comprise little to no terrestrial works as
it is assumed that the pipeline connecting this site with BPPS will run along
the shoreline.
Recent data on marine ecological resources
of Black Point has identified marine habitats of low ecological
importance. Indo-Pacific Humpback
Dolphin (Sousa chinensis) have been
recorded in the area, however the marine waters within Lung Kwu Sheung Tan bay
are regarded as of low importance to the humpback dolphins due to the
relatively low abundance of sightings with comparison to other areas of Hong
Kong Waters.
The site is in close proximity to the
The site is relatively remote from densely
populated areas and the closest villages are located at Lung Kwu Tan (<2 km
from the potential site) where the population is approximately 1,800. There appear to be no declared or deemed
monuments, graded buildings, graves or archaeological sites within the
site. However, in relatively close
proximity to the site is the Lung Kwu Sheung Tan site of archaeological
interest. Recent archaeological
investigations at this site have found artefacts from the late Neolithic (2500
- 1500BC).
Conceptual Layout
The main construction aspects of the site
are outlined below. These are based on
the preliminary conceptual layout reported in Figure 4.17:
·
Dredging: Dredge
quantities will be significantly larger than for Black Point as it is assumed
that that the site will be all reclamation with no cut into the hillside.
·
Reclamation: The marine
deposit thickness under the reclamations is up to 14 m thick and consequently
will require longer and higher surcharges than Black Point if not dredged. As there is no excavation reclamation fill
will have to be imported (marine sand or other suitable material). Additionally more seawall materials will be
required for the embankment which skirts the headland and carries the LNG
pipeline to BPPS and the access road.
·
Site Formation and Construction:
As all the land is formed by reclamation there is very little site
formation from existing land. Access to
the site from the main highway will have to be improved and a temporary jetty
constructed for the import of materials.
Access to BPPS is provided by extending the coastline embankment which
runs between the terminal site and the jetty access trestle.
Figure 4.17 Conceptual
Layout for Lung Kwu Sheung Tan Site
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the Lung Kwu Sheung
Tan site are summarised in Table 4.13.
Table 4.13 Site Review - Lung
Kwu Sheung Tan
General
site requirements |
|
1 |
Land Availability and Constraints: The site will need to be created through reclamation and the land impacted by the
reclamation is unconstrained. |
2 |
Operational Depth: The waters bordering the headland are consistently
shallow, often less than -5mPD.
Considerable dredging will be required for turning circle and approach
channel, dependent on the jetty location and the approach channel
orientation. |
3 |
Pipeline:
A short onshore pipeline will connect to BPPS |
4 |
Distance from Sensitive Receivers: The berthing/unloading facilities will be located on the north western
shore of the headland at < 2 km away from the closest village (Lung Kwu
Tan). The LNG terminal will be located
on the south shore of the headland at approximately 1 km from Lung Kwu Sheung
Tan. The site is in close proximity to
the BPPS. |
Environmental, Social and Planning |
|
5 |
Terrestrial
Environment: The construction area will involve marine
and coastal habitats only and does not comprise any terrestrial habitats. Impacts
to wildlife are likely to be minor as those animals that may be disturbed by
the construction activities will move away from the disturbed area to the
similar habitats nearby. |
6 |
Marine
Environment: · Presence of the Indo-Pacific Humpback
Dolphin (Sousa chinensis). · Approximately 4km to the south west of
Black Point headland is the designated Sha Chau and · The site is located to the south of
mudflats at Ha Pak Nai and is relatively distant from Mai Po Inner Deep Bay
Ramsar Site. · The waters to the south of Black Point
are reported as a spawning ground for commercial fisheries. The adult fish
production is however relatively low in comparison to elsewhere in · Water
quality at Lung Kwu Sheung
Tan is strongly influenced by the |
7 |
Social:
The site is presently uninhabited and the closest buildings lie
approximately 1 km from the LNG terminal (Lung Kwu Sheung Tan). The site also
abuts the boundary of the proposed Lung Kwu Tan archaeological site. |
8 |
Planning:
The site was identified in a 1992 Planning Study (TDD of HKSARG) for
Special Industry (Bulk Chemical Storage, LPG or liquid hydrocarbon
storage). There is Government Land Allocation
in the northeast of |
9 |
Permitting
Risk: |
Marine Transit |
|
10 |
Exposure: The LNG terminal will be sited on the
southwestern coast of the Black Point headland on the edge of |
11 |
Interference with Shipping:
The approach channel and turning basins are located in closer
proximity to the vessel fairway than those for the northern edge of the
headland and while final berthing will not interfere with existing shipping
activities the approach and slowing manoeuvres will occur close to the
channel. |
12 |
Volume of Marine Traffic:
Transit to the site is assumed to be via the East Lamma Channel,
Western Fairway, Ma Wan Channel and the Urmston Road Channel. This is a long passage through the “heart”
of |
A summary of the environmental, social and
planning characteristics of the Lung Kwu Sheung Tan site are reported in Figure 4.15.
Conclusions
From a review of Lung Kwu Sheung Tan’s
environmental, social, planning and marine transit characteristics it emerges
that the site poses some of advantages for the location of the LNG terminal,
namely:
·
The
main advantage from an environmental perspective is Lung Kwu Sheung Tan’s close
proximity to BPPS meaning that the construction of the subsea import pipeline
to the power station will be limited to a short onshore pipeline. This will allow to strongly reduce the potential
environmental impacts associated with the pipeline’s construction.
·
The
area is presently uninhabited and the closest village is located at
approximately 1 km from the LNG site and approximately 2 km from the jetty at
Lung Kwu Sheung Tan. The nearest
developments are small scale industrial complexes.
·
The
jetty is relatively sheltered from prevailing metocean conditions.
·
The
approach channel and turning basins will be located sufficiently far away from
the vessel fairway and will not interfere with existing shipping activities.
The location of the LNG terminal at Lung
Kwu Sheung Tan will however pose a number of potential environmental and marine
traffic issues summarised below:
·
Land
for the construction of the LNG terminal will need to be obtained form
extensive reclamation leading to the loss of natural habitat and coastline.
·
Recorded
presence of Indo-Pacific Humpback Dolphin (Sousa
chinensis) in the coastal waters of Lung Kwu Sheung Tan.
·
Considerable
dredging will be required for the turning circle and approach channel and
reclamation. The volume will be
dependent on the jetty location and the approach channel orientation.
·
Marine
Transit of the LNG carrier will be via East Lamma Channel,
Although several site selection advantages
discussed above are comparable to the ones discussed for Black Point, it is
deemed that the need for an onshore connecting pipeline to BPPS, the extensive
dredging for the reclamation, the proximity to Lung Kwu Tan and the expected
severe landscape and visual impacts makes the site less suitable from an environmental
perspective. Based on the above, it is
deemed that the disadvantages posed by siting the LNG terminal at Lung Kwu
Sheung Tan do not make the area a viable candidate site for further
consideration.
4.11.5
Introduction
South Soko Island (also called Tai A Chau)
is the largest (120 ha) of a small group of islands located over 6 km to the
south of southwest Lantau Island and about 2 km north of the boundary of HKSAR
territorial waters. The most dominating
feature of the island is the presence of a former Vietnamese detention centre
which has now been demolished (Figure
4.18).
Figure 4.18 Aerial
Photo of the
A large concrete platform now remains on
the centre of the island, surrounded by modified landforms such as cut slopes,
access road, reclaimed seawalls and a helicopter landing area. The topography of
The Indo-Pacific Humpback Dolphin (Sousa chinensis) and Finless Porpoise (Neophocaena phocaenoides) have been
recorded in the waters of Southern Lantau and South Soko, however sightings of
the Humpback Dolphins are more concentrated in Western Lantau whilst the Finless
Porpoises sightings are more concentrated in and around South Lamma.
The surrounding waters have been
identified as both a spawning ground and a nursery area for commercial
fisheries resources. The spawning ground
extends east through to the Po Toi and
Although the southern coast of the island
has higher exposure to the prevailing ocean swells, the metocean conditions are
reduced by the sheltering presence of the
Overall,
Seabed features surrounding
Conceptual Layout
The main construction aspects of the site
are outlined below. These are based on the preliminary conceptual layout
reported in Figure 4.19:
·
Dredging: In order
allow access to the site dredging will be required (approximately 1.1 Mm3)
for the formation of the approach channel and turning basin. Maintenance dredging requirement is expected
to be required once every ten years and will be restricted to specific small
areas.
·
Reclamation: An area of
approx. 0.6 ha will be reclaimed. A
relatively small proportion of the soil and rock material will be used within
the reclamation and therefore most of the material will need to be exported off
site. As there is no land access to the
island the material will need to be transported by barge.
·
Site Formation and Construction:
The site formation works will be carried out from several berms formed
at pre-determined levels to accommodate the necessary drainage works and landscaping
works. The berms are typically provided
at 10 m vertical intervals and will likely be used as a temporary working
platform for the drilling and blasting works.
Figure 4.19 Conceptual
Layout for
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the
Table 4.14 Site
Review -
General Site Requirements |
|
1 |
Land Availability and Constraints: Sufficient land is available for LNG site
and associated facilities at |
2 |
Operational Depth: Approximate depth at potential approach
channel/turning basin location: 12-14 mPD.
Some dredging would be required and quantity would depend on the
orientation of the approach channel/turning basin. |
3 |
Pipeline: Pipeline route to BPPS will be
approximately 40 km in length. The chosen route via Lantau’s western waters
is physically unconstrained, although the presence of Indo-Pacific Humpback
Dolphin (Sousa chinensis) would
require an ecological assessment to be undertaken. |
4 |
Distance from Sensitive Receivers: |
Environmental, Social and Planning |
|
5 |
Terrestrial Environment ·
Terrace cultivation, two small
abandoned settlements (Ha Tsuen and Sheung Tsuen) and a disused Vietnamese
detention centre have in the years modified most of the island’s terrestrial
habitats which result partially altered and of low ecological value. Shrubland is the dominant habitat type and
covers most of the hillsides. ·
The site of the ex-detention centre
occupies the flat land between Tung Wan and Sai Wan where no habitat of
ecological value can be found. The
hill slopes to the south of the ex-detention centre were modified into cut
slopes and all of the vegetation was removed.
The changes in the island terrain are expected to have disturbed the
soil strata containing the archaeological deposits of the Tai A Chau
archaeological site present on the island. |
6 |
Marine Environment: ·
Indo-Pacific Humpback Dolphin and
Finless Porpoise have been recorded in the waters of Southern Lantau, including
·
The surrounding waters have been
identified as both a spawning ground and a nursery area for commercial
fisheries resources. The spawning
ground extends east through to the Po Toi and ·
The scale of capture fisheries
operations in and around the ·
Surveys indicate that this coast
supports sparse cover of isolated and scattered hard corals. Most species found are common in ·
Wet and Dry season survey using
grab samples recorded Amphioxus in low abundance in Tung Wan. ·
The shorelines of Tung Wan and Sai
Wan bays have been partially reclaimed and are artificial. A rubble mound seawall was constructed in
Tung Wan and piers were constructed on the northern and southern edges of Sai
Wan bay. ·
Water quality of South Soko is
influenced the |
7 |
Social: The island was formerly a detention centre
for Vietnamese illegal immigrants which is now disused and demolished. Tai A Chau is a |
8 |
Planning: The island does not come under any
statutory plans, however it has been identified as a potential |
9 |
Permitting Risk: Potential objections to the development of
the site may come from NGOs. The
island’s coastal waters have also been identified as a potential marine
park. There is a potential need to
acquire land, however the permitting risks are considered to be relatively
low as the land is all is owned by one company. |
Marine Transit |
|
10 |
Exposure: The southern coast of the |
11 |
Interference with Shipping: The
terminal and approach would be located away from main shipping routes |
12 |
Volume of Marine Traffic: |
A summary of the environmental, social and
planning characteristics of the
Conclusions
From a review of
·
Sufficient
and unconstrained land is available for the construction and operation of the
LNG terminal and associated facilities.
Low severity environmental impacts are expected from the terrestrial
works due to the generally disturbed nature of the habitats. Little reclamation will be needed strongly
reducing potential environmental impacts to the marine environment.
·
The
site will provide unconstrained access to the LNG carriers avoiding major
shipping lanes and populated areas.
Little/no interference with existing shipping channels and marine
traffic would be expected.
·
·
The
unconstrained pipeline route to BPPS will reduce potential impacts on existing
seabed features.
·
The
absence of key sensitive terrestrial habitat due to the modified concrete
platform, predominance of shrubland and the presence of vegetation/faunal
assemblages of low ecological value.
Although
·
The
·
Recorded
presence of Indo-Pacific Humpback Dolphin (Sousa
chinensis) and Finless Porpoise (Neophocaena
phocaenoides).
·
Although
the pipeline route to BPPS is physically unconstrained, it will
pass through acknowledged Indo-Pacific Humpback Dolphin habitat.
·
The
presence of the Tai A Chau archaeological site located on the isthmus between
Tung Wan and Sai Wan, and the Tai A Chau Tin Hau Temple will require careful
examination.
·
Based
on the above, it is deemed that the environmental advantages posed by siting
the LNG terminal on the existing concrete platform on South Soko Island makes
the area a viable candidate site for further consideration. Planning and environmental disadvantages will
be further discussed in greater detail to determine their potential magnitude.
4.11.6
Introduction
North Soko (Siu A Chau) is a small island
located approximately 2 km south of
To provide sufficient land for the
construction a cut and fill reclamation will be required to expand the existing
area. Due to the shallow water depth
within Siu A Chau Wan, the preliminary layout positions the jetty in the
channel between North Soko and
Indo-Pacific Humpback Dolphin (Sousa chinensis) and Finless Porpoise (Neophocaena phocaenoides) have been recorded
in the waters of North Soko and throughout
The surrounding waters have been
identified as both a spawning ground and a nursery area for commercial
fisheries resources. Recent surveys have
however indicated that fish eggs and fry do not differ substantially between
the
The vegetation of
North Soko
Figure 4.21 Aerial
Photo of the
Of particular note for the
The southern coast of the
Conceptual Layout
The main construction aspects of the site
are outlined below. These are based on the preliminary conceptual layout
reported in Figure 4.22:
·
Dredging: Only nominal
dredging is required for the turning circle.
However, to achieve a navigation depth of –15 m PD, a 4 km navigation
channel is required to reach deeper water.
Existing depths of about –13 m are recorded. The channel initially lies in an Easterly
direction before turning South East, through the breakwaters to deep water.
·
Reclamation and Breakwaters: A
cut and fill reclamation will be required to expand the existing lowland area
at the centre of the island. The
materials for the reclamation will mostly be sourced from the excavation of the
land site formation.
·
Site Formation and Construction:
The excavation required should be balanced with the reclamation fill
quantities to provide the land needed.
Figure 4.22 Conceptual
Layout for
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the
Table 4.15 Site Review –
General
site requirements |
|
1 |
Land Availability and Constraints: A cut and fill reclamation will be required to expand the existing
lowland area at the centre of the island.
The land impacted by the reclamation is unconstrained. |
2 |
Operational Depth: Turning circle and approach channel will require significant dredging |
3 |
Pipeline:
The pipeline route to BPPS is approximately 38 km. The chosen route via Lantau’s western
waters is largely unconstrained, although the presence of Indo-Pacific
Humpback Dolphin (Sousa chinensis)
would require an ecological assessment to be undertaken.
In addition, there are a number of submarine cables that have been
laid between the island and Lantau island, as well as more to the east in
between the island and the South Cheung Chau Disposal Ground. |
4 |
Distance from Sensitive Receivers: The North Soko site lies in the southwestern waters of |
Environmental, Social and Planning |
|
5 |
Terrestrial
Environment: ·
The
area within the proposed construction site on ·
A
small abandoned village, Siu A Chau Tsuen is located behind the sandy beach
at Siu A Chau Wan. ·
With
the exception of the tropical climber Malaisia
scandens (not recorded in the Hong Kong SAR until 1996 when the species
was first recorded in Lantau Island), most of the vegetation species recorded
on North Soko Island are typical of outlying islands and well-represented
elsewhere within the Hong Kong SAR. Malaisia scandens was found to be
present in high abundance in the woodland and shrubland areas of the
island. |
6 |
Marine
Environment: ·
Indo-Pacific Humpback Dolphin (Sousa chinensis) and Finless Porpoise
(Neophocaena phocaenoides) have
been recorded in the waters of ·
The surrounding waters have been
identified as both a spawning ground and a nursery area for commercial
fisheries resources. ·
The scale of capture fisheries
operations in and around the ·
Water quality at North Soko is
influenced by the |
7 |
Social:
Siu A Chau is a |
8 |
Planning: The site is identified as a |
9 |
Permitting Risk: The waters are designated as secondary
contact recreation zones ([36]). The site is of archaeological/historical
interest. There is a potential need to
acquire land from approximately 70 private owners, which will require
assistance from the Government and South Lantau Rural Committee |
Marine Transit |
|
10 |
Exposure:
The island is relatively sheltered from prevailing metocean
conditions. The
southern coast of the |
11 |
Interference with Shipping:
The jetty’s extension into channel between North and |
12 |
Volume of Marine Traffic:
Local traffic between the two Soko islands is comparatively light and
the proposed location is well clear of fast ferry routes. The approach to the
site would be from the southeast with transits along the proposed PRD Traffic
Separation Schemes. |
A summary of the environmental, social and
planning characteristics of the
Conclusions
From a review of
·
The
site will provide easy access to the LNG carriers which will be approaching the
site from the southern unconstrained waters of HK SAR avoiding major shipping
lanes and populated areas. Little
interference with existing shipping channels and marine traffic is also
expected.
·
·
The
unconstrained pipeline route to BPPS will reduce potential impacts on existing seabed
features.
·
The
reclamation needed to provide sufficient land for the LNG terminal’s
construction and operation will affect unconstrained land.
Although
·
Land
for the construction of the LNG terminal will need to be obtained from
extensive cut and fill reclamation leading to the loss of natural terrestrial
and marine habitat.
·
The
·
Recorded
presence of Indo-Pacific Humpback Dolphin (Sousa
chinensis), Finless Porpoise (Neophocaena
phocaenoides) in the islands coastal waters.
·
Although
the pipeline route to BPPS is unconstrained, it will pass
through acknowledged Indo-Pacific Humpback Dolphin habitat.
·
The
presence the Siu A Chau Archaeological Site will require careful examination.
·
Significant
dredging will be required for the approach of the LNG carrier. The quantities are related to the fact that a
navigation channel approximately 4 km long will be required.
·
There
will be the need to acquire land from approximately 70 private owners and the
removal of the
Although several site selection advantages
discussed above are comparable to the ones discussed for
Based on the above, it is deemed that the
disadvantages posed by siting the LNG terminal at
4.11.7
Peaked Hill
Introduction
Peaked Hill is an isolated and uninhabited
offshore island located west of Tsin Yue Wan on
Due to the small size of the island and
its relatively steep morphology, the LNG terminal would be located on a cut and
fill reclamation which will create the necessary land for the construction and
operation of the LNG terminal. The jetty
would extend westward to the –10 mPD contour where the turning basin will be dredged. The waters to the west of the turning basin
are sufficiently deep to require minimal to no dredging for the navigation
channel.
The primary characteristic of Peaked
Hill’s marine ecology is the presence of Indo-Pacific Humpback Dolphin (Sousa chinensis). Abundance of humpback dolphins in
The island’s terrestrial ecology is
characterised by undisturbed habitats such as shrubland, grassland, plantation
woodland and bare rock/soil. The
community structure and vegetation species found on these islands are typical
to other similar habitats in parts of
Peaked Hill
Figure 4.23 Aerial
Photo of the Peaked
Offshore of Peaked Hill Island are the navigation
entrances to the existing deep water channel to Nansha and Guangdong, the
proposed Tonggu Waterway and any future Container Terminal 10, should the north
west Lantau option for their development be chosen. The site is well protected by its proximity
to Lantau Island from the prevailing easterly/south easterly metocean
conditions, however it is more exposed to locally generated waves from the
south west, albeit waves limited by the shallow waters of the PRD.
A review of the available literature
indicates that there are no declared or deemed monuments, graded buildings,
graves or archaeological sites within the site at Peaked Hill.
Conceptual Layout
The main construction aspects of the site
are outlined below. These are based on the preliminary conceptual layout
reported in Figure 4.24:
·
Dredging: The berth
and turning circle are located inshore of the 10 m contour so that dredging to
–15 mPD will be required.
·
Reclamation: The
reclamation can be formed by excavation of
·
Site Formation and Construction:
It is assumed the west side of the island is reduced to a level of about
10 mPD for location of the tanks. The
material removed from the island can be used for reclamation and any surcharge
loading required. There are no existing
berthing facilities at the site and no access roads to the adjacent Lantau
headland.
Figure 4.24 Conceptual Layout for Peaked Hill Site
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the Peaked Hill
site are summarised in Table 4.16.
Table 4.16 Site
Review – Peaked Hill
General site requirements |
|
1 |
Land Availability and Constraints: The site would partially be formed by reclamation with no constraints
on the extent of the reclamation. |
2 |
Operational Depth: Minimal dredging would be required for the construction for the
turning basin |
3 |
Pipeline:
The pipeline route to BPPS is ~ 25 km.
The chosen route via Lantau’s western waters is
unconstrained, although the presence of Indo-Pacific Humpback Dolphin (Sousa chinensis) would require an
ecological assessment to be undertaken. |
4 |
Distance from Sensitive Receivers:
The island is uninhabited and it is located in a remote and relatively undisturbed area
on the western coast of |
Environmental, Social and Planning |
|
5 |
Terrestrial Environment: ·
The
island’s terrestrial ecology is characterised by undisturbed habitats such as
shrubland, grassland and bare rock/soil. ·
The
surrounding terrestrial habitat on ·
In
proximity to the island are sensitive habitats such as: mudflat and mangrove habitat, an SSSI, and
a horseshoe crab breeding ground. |
6 |
Marine Environment: ·
Peaked
Hill’s coastal waters are considered to be ·
The
island coastal waters are within the perimeter of the proposed ·
Information
on the subtidal soft bottom assemblages indicates that the marine sediments
in vicinity of the site support high species abundance and biomass in
comparison to other areas in ·
Capture
fisheries operations in waters off Yam Tsai are reported to be of
moderate-high magnitude compared to other ·
Water
quality at Peaked Hill is influenced by the |
7 |
Social: The island is uninhabited and there are no
residential/commercial areas in close proximity of the site. However the island is in close proximity to
the |
8 |
Planning: The site is part of the |
9 |
Permitting Risk: The site is within a Secondary Contact Recreation
Zone. Although the development of the
Terminal is preferred on western side of Island this will have limited
ability to shield the development from |
Marine Transit |
|
10 |
Exposure:
The site is well protected by its proximity to |
11 |
Interference with Shipping: The LNG
terminal extension and the location of the jetty near the shipping channel
has the potential to create passing vessel effects on moored LNG
carriers. |
12 |
Volume of Marine Traffic: The
approach to the site would be from the southeast with transits along the
proposed PRD Traffic Separation Schemes.
While the LNG terminal is set away from the PRD Traffic Separation
Scheme LNG carriers would be slowing to approach the terminal within the TSS,
and close to its crossing within the Adamasta Channel. |
A summary of the environmental, social and
planning characteristics of the Peaked Hill site are reported in Figure 4.25.
Conclusions
From a review of Peaked Hill’s
environmental, social, planning and marine transit characteristics it emerges
that the site poses advantages for the location of the LNG terminal, namely:
·
Peaked
·
The
site will provide easy access to the LNG carriers which will be approaching the
site from the Lema Channel, south of Lantau, causing no major impact on marine
traffic.
·
The
unconstrained pipeline route to BPPS will reduce potential impacts on existing
seabed features.
Although
·
Peaked
·
Peaked
·
Land
for the construction of the LNG terminal will need to be obtained form
extensive cut and fill reclamation leading to the loss of natural terrestrial
and marine habitat, including major Indo-Pacific Humpback Dolphin habitat.
·
Peaked
·
Although
the pipeline route to BPPS is unconstrained, it will pass
through major Indo-Pacific Humpback Dolphin habitat.
The potentially severe landscape and
visual impacts of the LNG terminal on the unspoilt natural landscape of SW
Lantau, the presence of major Indo-Pacific Humpback Dolphins habitat and the
need for an extensive cut and fill reclamation to provide sufficient land for
the construction and operation of the LNG terminal makes the site undesirable
from an environmental perspective and less suitable with respect to South Soko
which is located approximately 8 km to the south east.
Based on the above it is deemed that the
disadvantages posed by siting the LNG terminal at Peaked Hill do not make the
area a viable candidate site for further consideration.
4.11.8
Area 137
Introduction
Area 137 (Fat Tong O) occupies an area of
approximately 104 hectares and it is located on the southern side of the new
town development of Tseung Kwan O (Junk Bay) on the opposite shore to Chai Wan
(Figure 4.26).
Area 137
Figure 4.26 Aerial Photo of the Area 137 Site
The area has recently been reclaimed for special
industrial use and it is within close proximity to the Tathong Channel and a
restricted area of low marine traffic volume.
Due to its artificial nature, the area’s
terrestrial and marine habitats are generally of low ecological value and
complexity. Neither Indo-Pacific
Humpback Dolphins (Sousa chinensis),
nor Finless Porpoises (Neophocaena
phocaenoides) have been recorded in the vicinity of the Tseung Kwan O and
the nearest sighting of a Finless Porpoise was recorded 2km south of Tung Lung
Chau. Important terrestrial habitats can
be found in the neighbouring
Conceptual Layout
Area 137 is an existing industrial site
intended for Deep Waterfront Industry.
No dredging, reclamation or site formation will be needed. The preliminary conceptual layout reported in
Figure 4.27.
Figure 4.27 Conceptual
Layout for Area 137 Site
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the Area 137 site
are summarised in Table 4.17.
Table 4.17 Site
Review - Area 137
General Site Requirements |
|
1 |
Land Availability and Constraints: Sufficient land is available for LNG site
and associated facilities at Area 137.
No reclamation or site preparation works will be needed. |
2 |
Operational Depth: Little or no dredging would be required to access the site. |
3 |
Pipeline: The site is remote from BPPS and would require a pipeline of > 80
km. The route to the power station is
highly constrained as a number of submarine cables are buried in the southern
waters of |
4 |
Distance from Sensitive Receivers: Siu Sai Wan is located less than 2 km from Area 137 with a population
of 35,000 and Chai Wan at between 2 and 3 km from Area 137 has a population
of 111,4000. In addition planned residential
development in Area 85 (approx.10,000 people) and Area 86 (approx. 57,000
people) are located approximately 2 km to the North of Area 137. A number of seawater intake points are also
located relatively close to the site and there is a Fish Culture Zone approx
1 km from the site at Tung Lung Chau. |
Environmental, Social and Planning |
|
5 |
Terrestrial Environment: Area 137 is located on reclaimed land. The site is therefore characterised by vegetation/faunal
assemblages of low ecological value.
However it must be noted that the majority of the surrounding area is
country park ( |
6 |
Marine Environment: ·
The coastline around Area 137 is artificial
and it is unlikely to have corals of particular ecological value. A recent study on Tseung Kwan O indicated
low abundance and diversity of hard corals on the natural coast of the bay,
including ·
Capture fisheries operations in
waters off Area 137 are reported to be of moderate-high magnitude compared to
other ·
There is a Fish Culture Zone at
Tung Lung Chau, within approx. 1 km of the site. |
7 |
Visual: Visual
impacts at this site are a potential concern given the direct facing views of
residents in Chai Wan, Siu Sai Wan, Yau Tong, users of beaches in Shek O and
hikers in the |
8 |
Social: Planned
residential development in Area 85 (approx.10,000 people) and Area 86
(approx. 57,000 people) are located approximately 2 km to the North of Area
137. Siu Sai Wan is located less than
2 km from Area 137 with a population of 35,000 and Chai Wan at between 2 and
3 km from Area 137 has a population of 111,4000. |
9 |
Planning: ·
Area 137 has been zoned into two
areas, the north as a Deep Waterfront Industry and the south (33 ha) for Open
Use (OU). Area 137 is zoned “Other
Specified Uses” annotated for “Deep Waterfront Industry” on the Approved
Tseung Kwan O Outline Zoning Plan (OZP) No. S/TKO/15. According to the statutory planning
intention, this zone is intended primarily for special industries which
require marine access, access to deep water berths or water frontage. ·
According to the Definition of
Terms Used in Statutory Plans, there is no provision within the existing land
use zone for the LNG Terminal (either as of right or upon application to the
Town Planning Board - TPB). A rezoning
request to the TPB would be required. ·
At present, Area 137 is being used
as a Public Fill Storage Area (Fill Bank) and the contract expires in
2008. There are no plans at present to
extend it. ·
It is understood the ·
No breakwater/ reclamation is
allowed into the Tathong Channel gazetted limits. ·
The majority of the surrounding
terrestrial habitat is a |
10 |
Permitting Risk: Although
the area has been zoned for uses compatible for a LNG terminal, there is a
history of local residents objecting to the use of Area 137 for such
developments. |
|
Marine Transit |
11 |
Exposure: The site is somewhat exposed to southeast monsoon storm conditions. |
12 |
Interference with Shipping: The jetty
has been located on the western limit of the site due to the environmental
and marine transit issues (i.e. close proximity to Tung Lung Chau fish
culture zone, presence of the foul area, potential hazards to the LNG
manoeuvres within the turning circle) associated with the southern location within Joss House Bay (Tai Miu Wan). Any jetty extension required for clearance distances pushes the LNG
berthing area closer to the Traffic Separation Scheme and increases the
potential to create passing vessel effects on moored LNG carriers. |
13 |
Volume of Marine Traffic: The site lies adjacent to the Tathong Channel, the principal access to
HKSAR’s central and eastern harbour areas.
Traffic activity at this site is dominated by smaller craft, fishing
vessels and rivertrade, with strong growth in feeder services between Yantian
and Kwai Chung. Ocean-going vessel
activity is limited, with the largest vessels comprising cruise liners accessing
|
A summary of the environmental, social and
planning characteristics of Area 137 are reported in Figure 4.28.
Conclusions
From
a review of Area 137’s environmental, social, planning and marine transit
characteristics it emerges that the site presents environmental and planning
advantages, namely:
·
Area 137 has been zoned in the OZP for uses
compatible with Deep Waterfront Industry.
·
Little to no dredging would be required to
access the site;
·
The absence of key sensitive terrestrial,
coastal and marine habitat due to the recent artificial nature of the
site. The construction and operation of
the site would not lead to the direct loss of important habitats. Furthermore, based on existing data sets on
marine mammals distribution in HKSAR waters, neither Indo-Pacific Humpback
dolphins (Sousa chinensis), nor
Finless Porpoises (Neophocaena
phocaenoides) have been recorded in the immediate vicinity of the site.
The
site review has however highlighted several social, marine transit and planning
drawbacks associated with Area 137, namely:
·
Due to environmental and marine transit
issues identified within
·
The area is visually exposed to densely
populated residential areas, the closest being Siu Sai Wan which is located less
than 2 km away. The site’s visibility to major urban districts will lead to a
high level of public interests and impacts to perceived safety of the local
population.
·
The site is remote from BPPS and would
require a pipeline of > 80 km. The
route to BPPS is highly constrained as a number of submarine cables are buried
in the southern waters of
Based
on the above, it is considered that the environmental advantages posed by
siting the LNG terminal on the existing site at Area 137 with little to no
associated environmental impacts and its potential compatibility with the OZP -
Deep Waterfront Industry land use makes the area a viable candidate site for
further consideration.
However,
the potential marine traffic disadvantages highlighted will be further discussed
in greater detail at a later stage of this site selection study to determine if
the location of the jetty in close proximity to the Tathong Channel without a
safety zone makes the site unacceptable for reliable LNG unloading operations. Planning and social issues will also be
further examined.
4.11.9
Yam Tsai
Foreword
From a preliminary overview of the site’s
suitability criteria, it emerges that the site, although potentially viable
from an environmental, social and technical perspective, presents numerous
planning and permitting issues deemed sufficient for the site’s “early”
exclusion from the list of preferred sites.
The rationale behind this exclusion is summarised below.
Statutory planning context:
·
Yam
Tsai is not covered by any existing OZP, however, it is located immediately
adjacent to the Planning Scheme Boundary for the Approved North East Lantau
Port OZP No S/I-NEL/12 and north of the Approved Discovery Bay OZP No.
S/I-DB/4. The nearest land use zone is a
“Green Belt” at Cheung Sok and Penny’s Bay, the statutory planning intention of
which is for conservation of the existing natural landscape, ecological and
heritage areas, scenic areas and visual backdrops to the visitor
attractions. An LNG terminal which would
be highly visible from the Lantau Link, Airport Railway, the Tuen Mun Coastline
and Ma Wan would be contrary to this planning intention. There is also an approx. 79ha of land next to
Yam Tsai that is designated as the Sunny Bay Tourism and Entertainment Node a
strip of land along the northern coast is intended as a reserve the proposed
Road P1 extension.
Non-statutory planning context:
·
In
1995 the Visitors and Tourism Study identified the potential for a tourism
corridor along the northern coast of
·
The
Concept Plan for Lantau has recommended Yam Tsai as a Green Belt/Countryside
area. In addition, there is a large proposed Country Park Extension to the
south and large Leisure and Entertainment Node to the immediate east.
Introduction
Yam Tsai is located on the north eastern
coast of
The bathymetry of Yam Tsai headland’s
coastal waters are characterised by shallow waters to the east of the headland
in Yam O Wan and steeper shelving waters to the north and the west of the site
towards the Urmston Road vessel fairway.
With the exception of the presence of the
Indo-Pacific Humpback Dolphin (Sousa
chinensis), a review of existing information on the marine ecological
resources of Yam Tsai coastal waters has not identified any assemblages of high
ecological value. Although Humpback
dolphins have been sighted in the area, it must be noted that the waters of
north eastern Lantau do not support high number of sightings in comparison to
other areas in Hong Kong (such as West and Northwest Lantau) and that marine
waters around Yam Tsai are regarded as of low importance to the humpback
dolphins.
The terrestrial ecology of Yam Tsai is of
a little conservation importance and similar vegetation, flora and fauna are
well represented on
Yam Tsai
Figure 4.29 Aerial Photo of the Yam Tsai Site
Site Review
The general site requirements and the
environmental, safety, social and marine transit aspects of the Yam Tsai site
are summarised in Table 4.18.
Table 4.18 Site Review – Yam
Tsai
General
site requirements |
|
1 |
Land Availability and Constraints: The site would have to be formed largely by reclamation. The land impacted by the
expansion/reclamation is unconstrained. |
2 |
Operational Depth: Minimal dredging would be required |
3 |
Pipeline:
The submarine pipeline route to BPPS is < 20 km. The submarine
pipeline route to BPPS is severely constrained by the need for crossing
submarine cables, pipelines and outfalls.
There are a number of submarine cables traversing the channel to the
west of the site. |
4 |
Distance from Sensitive Receivers: Luk Keng Tsuen, a |
Environmental, Social and Planning |
|
5 |
Terrestrial
Environment: The terrestrial habitats at Yam Tsai are of
low conservation importance. |
6 |
Marine
Environment: ·
Indo-Pacific
Humpback Dolphin (Sousa chinensis)
have been sighted in the vicinity of the site, however it must be noted that
sightings in this area are less common than in the waters of western and
northern Lantau. ·
To
the east of the site, in Yam O Wan, lies a small area of mudflat and mangrove
habitat. .Seagrass has also been recorded in the bay. ·
Capture fisheries operations in
waters off Yam Tsai are reported to be of moderate-high magnitude compared to
other ·
Water quality at Yam Tsai is
influenced by the |
7 |
Social:
Luk Keng Tsuen, a |
8 |
Planning: ·
Yam
Tsai is not covered by any existing OZP; however it is located immediately
adjacent to the Planning Scheme Boundary for the Approved North East Lantau
Port OZP No S/I-NEL/12 and north of the Approved Discovery Bay OZP No.
S/I-DB/4. ·
The
nearest land use zone is a “Green Belt” at Cheung Sok and Penny’s Bay, the
statutory planning intention of which is for conservation of the existing
natural landscape, ecological and heritage areas, scenic areas and visual
backdrops to the visitor attractions. ·
The
Concept Plan for Lantau has recommended Yam Tsai as a Green Belt/Countryside
area. In addition, there is a large
proposed Country Park Extension to the south and large Leisure and
Entertainment Node to the immediate east. ·
The
2001 South West New Territories Development Strategy Review (SWNTDS)
identifies Yam Tsai as a Conservation Area (Landscape Protection Area/Coastal
Protection Area). ·
There
is an approx. 79ha “Undetermined” zone next to Yam Tsai which is intended as
a reserve the proposed Road P1 extension. ·
The
waters to the north of Yam Tsai are an exhausted sand borrow area which, until
late 2001, was used for the disposal of uncontaminated mud. The waters remain, however, gazetted for
such a purpose. |
9 |
Permitting
Risk: please refer to
the foreword of this section |
Marine Transit |
|
10 |
Exposure:
The site is located on the northern coast of |
11 |
Interference with Shipping:
Access to the site will be via the East Lamma Channel, |
12 |
Volume of Marine Traffic:
Transit to the site is assumed to be via the East Lamma Channel,
Western Fairway, Ma Wan Channel. This
is a long passage through the “heart” of |
A summary of the environmental, social and
planning characteristics of Yam Tsai are reported in Figure 4.30.
Conclusions
From a review of Yam Tsai’s environmental,
social, planning and marine transit characteristics it emerges that the site
poses limited advantages for the location of the LNG terminal, namely:
·
The
site is relatively sheltered from prevailing metocean conditions; hence
breakwaters will not be needed reducing potential environmental impacts form
the marine works.
·
Although
the necessary land for the construction of the LNG terminal will need to be obtained
form reclamation and excavation works, the coastal waters and the land
potentially affected by the works are unconstrained.
In addition to the planning and permitting
drawbacks identified in the Foreword of this section, the location of the LNG
terminal at Yam Tsai will pose a number of potential environmental and marine
transit issues, namely:
·
The
submarine pipeline route to BPPS will be severely constrained by the need for
crossing submarine cables, pipelines and outfalls.
·
Recorded
presence of Indo-Pacific Humpback Dolphin (Sousa
chinensis) in the coastal waters of Yam Tsai. It must be noted that marine waters around
Yam Tsai are regarded as of low importance to the humpback dolphins.
·
Land
for the construction of the LNG terminal will be obtained partly from
reclamation and partly from the excavation of the hillside. This will lead to the loss of natural habitat
(marine and terrestrial) and to the overall change in morphology of the coast
and the hillside.
·
Marine
Transit of the LNG carrier will be via East Lamma Channel,
·
The
LNG terminal will be in close proximity to the Sunny Bay Disney MTR station.
Based on the above, it is deemed that the
disadvantages posed by the numerous planning issues of the Yam Tsai site and
its few environmental advantages do not make suitable area for the siting of
the LNG terminal and will therefore not be considered as a viable candidate for
further examination.
4.11.10
Conclusion
A summary of the site characteristics of
the 7 sites is provided in Table 4.19.
Table 4.19 Summary
of Site Characteristics
Location |
Marine Works |
Onshore works |
Pipeline to Black Point |
Marine Transit |
Permitting Risks |
Remarks |
Black
Point |
·
Extensive reclamation would be required
(approx. 16 ha). ·
Dredging
of approach channel and turning basin would require extensive dredging
(approximately 2.5 x 106 m3). |
·
Extensive onshore works would be
required. The headland would be excavated and graded. |
·
No pipeline would be required |
·
Although the site is near the
northern reaches of the busy |
·
The site presents no significant
planning or, social issues. There are
no visually sensitive receivers and thus no major objections are expected
during the public notification period. |
·
The site is SUITABLE and will be further assessed |
Lung Kwu
Shung Tan |
·
Extensive reclamation would be
required. ·
Rock armour would be required for
the onshore coastal pipeline route to BPPS. ·
Dredging of approach channel and
turning basin would require extensive dredging. |
·
Minor onshore works would be
required. The site would be located on
reclaimed land |
·
Very short onshore coastal pipeline
would connect the LNG terminal to BPPS. |
·
As above |
·
The site presents no significant
planning or, social issues; however the area is exposed to visually sensitive
receivers: Lung Kwu Sheung Tan village and the Lung Kwu Sheung
Tan beach. It is expected that local
objections may be submitted during the public notification period of
gazetting due to landscape and visual objections. |
·
The site is NOT A PREFERRED SITE
and will thus not be assessed further. |
|
·
Little reclamation is required
(approx. 0.6 ha) ·
Dredging of approach channel and
turning basin would require extensive dredging (approximately 1.1 x 105 m3). |
·
Onshore works would be limited as the
LNG site would be constructed on an existing concrete platform of a disused
detention centre. Onshore excavation
works would be needed to accommodate the tanks. |
·
Pipeline of approx. 40 km in
length. The route presents no
significant physical constraints however it would potentially interfere with Sousa chinensis habitat and would thus
need further assessment. |
·
The terminal and approach channel
would be located away from main shipping routes. ·
The approach to the site would be from
the southeast away from the busy Adamasta Channel or other busy vessel
fairways. |
·
The site presents no insurmountable
planning or, social issues. There are
no visually sensitive receivers. |
·
The site is SUITABLE and will be
further assessed in Task 7 |
|
·
A
cut and fill reclamation would be required to expand the existing lowland
area at the centre of the island ·
Dredging of approach channel and
turning basin would require extensive dredging. A 4 km navigation
channel is required to reach deeper water. |
·
Extensive onshore works would be
required. |
·
Pipeline of approx. 40 km in length
and presents no significant physical constraints. However it would potentially interfere with
Sousa chinensis habitat and would
thus need further assessment. |
·
No
significant marine transit impacts.
The jetty’s extension into channel between North and |
·
The site presents no significant
planning or, social issues. There are
no visually sensitive receivers.
However there is a potential need to acquire land from approximately
70 private owners, which will require assistance from the Government and
South Lantau Rural Committee which will cause potential permitting delays. |
·
The site is NOT A PREFERRED SITE
and will thus not be assessed further. |
Peaked
Hill |
·
Due to the small size of the
island, extensive marine works and reclamation would be required to provide
the 30 ha required for the site construction. ·
Minimal
dredging would be required for the construction for the turning basin |
·
Extensive onshore works would be
required. |
·
The
pipeline route to BPPS is ~ 25 km and presents no significant
physical. However it would potentially interfere with Sousa chinensis habitat and would thus need further assessment. |
·
Access
to the site would be via Lema Channel..
The site is sufficiently far from the main channel area and the
recently designated anchorages at Shan Shui Kok. |
·
The site presents no significant
planning or, social issues. However,
it would be exposed to |
·
The site is NOT A PREFERRED SITE
and will thus not be assessed further. |
Area 137 |
·
No marine works are required. The site is an existing industrial site |
·
No onshore works are required. The site is an existing industrial site |
·
The
pipeline route to BPPS is ~ 80 km. The
route to the power station is highly constrained as a number of submarine
cables are buried in the southern waters of |
·
The jetty would be in close
proximity to the Tathong Shipping Channel. ·
LNG terminal’s operations and ship
transits would potentially be impacted. ·
A safety zone to facilitate the LNG
carrier’s manoeuvres and off-loading operations would encroach on the vessel
fairway and would thus not be permitted in ·
The location of the jetty exposes
the moored LNG carriers and the jetty itself to potential collisions with
passing ships. ·
A Marine Quantitative Risk
Assessment (MQRA) would be required. |
·
Although the area has been zoned in
the OZP for uses compatible with Deep Waterfront Industry, the area is
visually exposed to densely populated residential areas, the closest being
Siu Sai Wan which is located less than 2 km away. The site’s visibility to major urban
districts will lead to a high level of public interests and impacts to
perceived safety of the local population.
This may ultimately cause permitting delays. |
·
The site is SUITABLE and will be
further assessed in Task 7 |
Yam Tsai |
·
The
site would have to be formed largely by reclamation. Extensive
reclamation would be required. ·
Minimal
dredging would be required |
·
Extensive onshore works would be
required. |
·
The
submarine pipeline route to BPPS is < 20 km. The submarine pipeline route to
BPPS is severely constrained by the need for crossing submarine cables,
pipelines and outfalls. There are a
number of submarine cables traversing the channel to the west of the site. |
·
Access
to the site would be via the East Lamma Channel, |
·
Numerous
planning issues have been identified (see Section
4.9.9) |
·
The site is NOT A PREFERRED SITE
and will thus not be assessed further. |
This initial shortlisting assessment provided the
necessary support for the elimination of 4 sites. The preferred suitable sites identified for
further examination were:
·
·
Black
Point, and
·
Area
137.
4.11.11
Task 7 - Final Selection
The 3 sites identified in the previous
task were subjected to further detailed qualitative narrative assessment based
on a suite of pre-defined environmental and technical criteria:
1.
Planning
and Land Use Features
2.
Potential
Hazard to Life Impacts (including transit route and terminal)
3.
Potential
Water Quality Impacts
4.
Potential
Terrestrial Ecological Impacts
5.
Potential
Marine Ecological Impacts
6.
Potential
Impacts to Fisheries Resources and Operations
7.
Potential
Impacts to Cultural Heritage Resources
8.
Potential
Impacts to Landscape and Visual Environment
9.
Potential
Impacts from Waste Disposal
10.
Other
potential impacts (e.g. air, noise that may be site specific)
The assessment against the above criteria
was based upon the engineering items listed in the EIAO Study Brief (Clauses
3.3.3 and 3.6.6) around which the
CAPCO team has sufficient conceptual detail available:
·
Size
and location of the facility;
·
The
size of reclamation;
·
The
extent of dredging for the navigation channel;
·
The
extent of natural slope cutting;
·
Submarine
pipeline alignment;
·
Submarine
power cable;
·
Submarine
water main;
·
Construction
method;
·
Number
and size of the fuel tanks and piers.
The potential conceptual layouts for
This final assessment will provide the
necessary support for the election of the final 2 preferred sites, Black Point
and
4.11.12
General Layout
South Soko Island (also called Tai A Chau)
is the largest (120 ha) of a small group of islands located over 4 km to the
south of southwest Lantau Island and about 2 km north of the boundary of HKSAR
territorial waters.
The coastline is mainly steeply sloped and
rocky in nature. Notable coastal
features include two bays located on the east and west side of the island
(called Tung Wan and Sai Wan, respectively). The southern coast of the island
has higher exposure to the prevailing ocean swells, while the northern shores
(facing the neighbouring
Overall,
The potential conceptual site layout ([37])
for
Planning and Land Use Features
Historically,
The construction of the Detention Centre
started in 1989 (aerial photograph 1989 Figure 4.33) and was completed in
1991. The Detention Centre occupied the
flat land between Tung Wan and Sai Wan and reclaimed some of the shoreline in
both of these bays. The hill slopes to
the south of the Detention Centre were modified into cut slopes and all the
vegetation removed. The natural
shoreline of Sai Wan was modified into artificial shore with piers constructed
on the northern and southern edges of this bay.
The natural
Water Quality Conditions
The location of
The marine works foreseen for the
construction of the LNG terminal have the potential to impact the water quality
parameters of
Sediment Quality Conditions
Sediment quality monitoring data ([39])
collected at Station SS6
approximately 10km to the northeast of the Soko Islands would suggest that the
site would be considered uncontaminated (Category L) as there were no
exceedances of the Lower Chemical Exceedance Level (LCEL).
Terrestrial Ecological Resources
Ecology surveys previously conducted in
2004 on
All faunal species recorded on the island
were considered common and widespread with the exception of small number (11)
of bird species of conservation interest, 8 uncommon butterflies, and one
protected snake. The majority of the
species were recorded in habitats that would not be directly impacted by the
proposed terminal footprint. Terrestrial ecology issues associated with
proposed LNG terminal and associated facilities at the
The LNG terminal will be constructed on an
existing concrete platform, thus significant direct and indirect impacts on
terrestrial habitats present on
Marine Ecological Resources
The waters and
coastal areas of Southwest Lantau including the Soko Island group, which are
located away from the major population centres of Hong Kong, have been
considered by some academics, government and green groups to be a general area
of high ecological value including from a marine perspective. Both dolphins and porpoises are sighted in
the waters of
There have been a variety of studies,
which have investigated the marine ecology of Southwest Lantau waters and as a
result of these, in particular the AFCD-commissioned Marine Park feasibility
study ([40]), both the coastal waters off Southwest
Lantau Island and the waters around the Soko Island Group have been proposed
for designation as Marine Parks. Recently gathered
information on the
Of the two marine cetacean species
(Indo-Pacific Humpback Dolphin, Sousa
chinensis; and Finless Porpoise, Neophocaena
phocaenoides) that are resident in Hong Kong waters, both are recorded in
Based on Agriculture, Fisheries and
Conservation Department (AFCD) monitoring data (1995-2006), dolphin numbers in
Finless Porpoise are also recorded in
South Lantau waters, including in waters close to
In addition to the AFCD data set (1995 –
2006), a recent extensive programme of vessel-based surveys has been
conducted. These surveys have provided a
detailed overview of dolphin utilisation of Hong Kong western waters spanning
South West Lantau, West Lantau, North West Lantau and
Finless Porpoises were only seen in
Surveys ([41])
conducted at the Soko
The marine works foreseen for the
construction of the LNG terminal have the potential to impact the marine
ecology of
Fisheries Resources and Operations
The
It must be noted that a recent fisheries
survey (Part 2 of the EIA - Annex 10)
shows an overall low density of fish larvae for the waters of South Soko and a
family composition dominated by non-commercially important fish (i.e.,
Clupeiform, Engraulidae, and Ambassidae).
Furthermore the survey concludes that there is no statistically
significant difference in fish density and eggs density between the
non-spawning/non-nursing grounds of western Lantau and the spawning/nursing
grounds of southern Lantau and
The scale of capture fisheries operations
in around the
In view of the overall moderate level of
importance of the commercial fisheries activities at
Cultural Heritage Resources
At this early stage of the assessment it
is expected that the construction of the LNG terminal at
Landscape and Visual Conditions
In terms of landscape,
The siting of the LNG
terminal on the island will potentially have a significant negative impact on
the existing Landscape Character of South Soko island, and to a lesser extent,
the
As the Visually Sensitive Receivers (VSRs)
within this distance are located in ocean areas, or from other islands in the
Soko chain, the impact is greatly reduced as all visitors will experience this
impact from marine vessels, or when visiting the
4.11.13
Black Point
General Layout
The Black Point site is adjacent to BPPS
and borders the northern reaches of the
The major development that has occurred at
Black Point is the construction of the Black Point Power Station (the first
natural gas-fired plant in
The potential conceptual site layout ([44])
for Black Point, together
with its main engineering parameters (as listed in the EIAO Study Brief), are
reported in Figure 4.36. The layout positions the approach channel,
turning basin and jetty near the northern reaches of the
It must however be noted that the transit
route of the LNG carriers to the site is assumed to be via the East Lamma
Channel, Western Fairway, Ma Wan Channel and the Urmston Rd Channel which will
expose the LNG carrier to significant marine traffic activity and thus
potential collision risks.
Planning and Landuse
Black Point does not fall under any statutory
plans. The site has been studied in the
past for the development of the Tuen Mun Port.
As part of this study, a recommended plan was prepared including
locations for PHIs. The plan included
provisions for LPG and other hydrocarbon storage. There are no private lots within the area
proposed for locating the LNG terminal.
The closest developments to the site, other than the BPPS, are a mixture
of small scale industrial uses at Lung Kwu Sheung Tan (0.8 km from site) and
the closest villages are located at Lung Kwu Tan (> 2 km from site) where
the population is around 1,800.
As mentioned above, studies have been
conducted to assess the future development of the area for a port. Additional studies on other uses include the
potential siting of a Waste-to-Energy Facility, Sludge Treatment Facility and
Animal Carcass Treatment Facility.
Water Quality Conditions
The quality of the surrounding marine
waters is dominated by the influence of discharges from the
Black Point waters are located in the Deep
Bay Water Quality Control Zone. Waters in the northern portion of the site are
also part of a Secondary Contact Recreation Zone that extends into the western
reaches of
From a review of the engineering
parameters listed in Figure 4.36, it emerges that the marine
works necessary for the construction of the LNG terminal at Black Point would
entail a large reclamation area of approximately 16 ha and the dredging of both
approach channel and turning basin. As a
result, it is expected that the overall impacts to the water quality of Black
Point, though primarily localised to the marine works areas (reclamation and
dredging), will impact water quality parameters both in nearshore and offshore
areas.
Sediment Quality Conditions
Some marine sediments in the vicinity of
the site are known to have levels of Arsenic that exceed the Lower Chemical
Exceedance Level, which could indicate contamination, and the requirement for
confined marine disposal.
Terrestrial Ecological Resources
Black Point is mainly composed of
shrubland habitat interspersed with grassland. The densest and tallest
shrubland vegetation occurs on the northern slopes of the headland. The southern side of the headland is covered
with grassland and scattered rocky boulders and outcrops. The vegetation is typical of granite hill
slopes in
Land for the construction of the LNG
terminal at Black Point will be obtained partly from the excavation of the
hillside (Figure
4.36). This will lead to the
direct loss of natural habitat (marine and terrestrial) and will potentially
lead to an increase of several detrimental effects on the headland’s fauna and
flora by increasing the level of fragmentation of the natural habitats. It must however be noted that the absence of
a subsea interconnecting pipeline partially compensates the greater magnitude
of water quality impacts associated with the reclamation works.
Marine Ecological Resources
The site at Black Point is located at the
outer limit of
The composition of benthic fauna
inhabiting subtidal soft bottom sediments off Black Point comprise estuarine
species reflecting the pronounced influence of freshwater discharges from the
Pearl River. Species richness of fauna is medium and diversity is low compared
to other areas in
Despite the ever-present marine traffic in
the Urmston Road Channel, the waters off the west
In addition to the AFCD data set (1995 –
2004), a recent extensive programme of vessel-based surveys has been
conducted. The survey has provided a
detailed updated overview of dolphin utilisation of Hong Kong western waters
spanning South West Lantau, West Lantau, North West Lantau and
The results of the survey showed that
The extensive reclamation foreseen for the
construction of the LNG terminal at Black Point (Figure 4.36) will lead to the
loss of natural habitat and the alteration of water quality parameters (e.g.
suspended sediments) that have potential detrimental effects on the marine
organisms of Black Point’s coastal waters.
Due to the overall low ecological importance of the marine habitats identified
at and around Black Point, it is however expected at this early stage of the
assessment that the overall impacts as a result of the construction and
operation of the LNG terminal will not be significant. Furthermore, with respect to
Fisheries Resources and Operations
The waters beyond 3km to the south of
Black Point are reported to be a spawning ground for commercial fisheries and
hang trawl fishermen are particularly dependent on these waters for their
catches. Overall, in comparison to other
In view of the overall low level of
importance of the commercial fisheries activities at Black Point, it is
expected that the potential construction and operation impacts of the LNG
terminal on the local fisheries will not be significant.
Cultural Heritage Resources
The site of the Black Point Power Station
was formerly the Yung Long Archaeological Site.
This archaeological site was rescue excavated during the construction of
the Black Point Power Station. Although
the hillsides of the site for the LNG terminal are part of the area of the
former archaeological site it is not expected that significant archaeological
deposits remain.
There are some graves in the vicinity of
the site but a review of information on declared monuments and recognised sites
of archaeological significance indicated there were no declared or deemed
monuments, graded buildings, graves or significant archaeological deposits
within the Black Point site. Owing to historic use of waters around the
At this early stage of the assessment it is expected
that the potential impacts associated with the construction of the LNG terminal
at Black Point will have no significant impact on sites of cultural,
historical/heritage or archaeological importance.
Landscape and Visual Conditions
Owing to the presence of the Black Point
Power Station and current industrial usage of areas adjacent to Black Point,
this site is generally considered to be of low landscape quality, which could
accommodate additional industrial facilities such as the LNG terminal. The proposed terminal will only be visible
from a limited number of locations, and these impacts will only be significant
at close proximity to the Black Point Terminal as at distances of greater than
1260m, the LNG terminal will not have a substantial visual impact.
The installation of the LNG terminal will
potentially have a moderate to significant negative impact on the existing
Landscape Character of Black Point, particularly the hill slope area. However, this impact will only be apparent
when the site is viewed from relatively close proximity. As most of the Visually Sensitive Receivers
(VSRs) are located in ocean areas, the impact is greatly reduced as all
visitors will experience this impact from marine vessels. No VSRs located in residential areas, on
public roads, or in publicly accessible lookouts or Country Parks will
experience this impact on the Landscape Character.
Therefore whilst the impact on the
Landscape Character of Black Point is moderate - significant, it is considered
acceptable, as there is a low number of VSRs affected (Figure 4.37).
4.11.14
Area 137 - Tseung Kwan O
General Layout
Located on a site that has recently been
reclaimed for special industrial use, this site lies on the opposite shore to
Area 137 occupies an area of approximately
104 hectares. This reclamation site has
served as a public filling area since January 1997 to receive public fill
generated from the construction industry.
Reclamation works in the northern part of Area 137 were completed in
2004 (Figure
4.38).
The potential conceptual site layout ([47])
for Area 137, together with
its main engineering parameters (as listed in the EIAO Study Brief), are
reported in Figure 4.39. The jetty has been located on the western
limit of the site facing the Tathong Shipping Channel.
This
layout has been preferred to the location of the jetty on the southern limit of
the site within
Furthermore,
the northern portion of Joss House Bay (just south of the site) has been
identified on the admiralty charts as a Foul
Area in which anchoring or trawling should be avoided. Marine works within Joss House Bay may be
feasible; however they may potentially be constrained due to the presence of
sunken/abandoned facilities or objects.
It must however be noted that, although
the selected layout avoids the potential issues highlighted above for Joss
House Bay, it will potentially pose marine operation/collision risk issues due
its proximity to the Traffic Separation Scheme of the Tathong vessel fairway,
increasing the potential impacts of passing vessels on the LNG carriers manoeuvres,
as well as exposing the jetty and the LNG carrier to potential collision risks
with existing shipping activities.
In order to reduce the frequency of
existing shipping activities interfering with the LNG carriers operations
(approach, manoeuvre, berthing and unloading), international maritime
practices, as well as standard operators procedures, set a safety zone around
the terminal/approach channel/turning basin to allow the LNG carriers to
manoeuvre safely. This however is deemed
not feasible for the Area 137 site as, due to the proximity of the site to the
Tathong channel, the safety zone would encroach on one of
Planning and Landuse
Area 137 is zoned “Other Specified Uses”
annotated for “Deep Waterfront Industry” on the Approved Tseung Kwan O Outline
Zoning Plan (OZP) No. S/TKO/15.
According to the statutory planning intention, this zone is intended
primarily for special industries which require marine access, access to deep
water berths or water frontage.
Industries to be accommodated within this zone are usually capital
intensive, land intensive and cannot be accommodated in conventional industrial
buildings.
According to the Definition of Terms Used
in Statutory Plans, there is no provision within the existing land use zone for
the LNG Terminal (either as of right or upon application to the Town Planning
Board). Thus a rezoning request would be
required which entails a statutory procedure under Section 12A of the Town
Planning Ordinance with potential statutory opportunities for public comment
and associated planning delays/risks. As
the site is relatively close to major urban areas and clearly visible from Hong
Kong Island East and parts of Tseung Kwan O, there is potential for significant
public objections to slow down the process.
Presently there are several planning
intentions for Area 137 which can be referred back to a number of strategic
planning documents including:
·
Port
and Airport Development Strategy – Strategy Statement No. 5 – Tseung Kwan O
Port Development which sets out the requirements to be met by the proposed port
facilities in TKO
·
Territorial
Development Strategy Review (TDSR) which identified Area 137 as a Special
Industrial Zone for various port-related uses that require deep water for the
delivery of bulk products
Existing land uses in the Tseung Kwan O
area located within 2 km of the site are mainly industrial in nature. Tseung Kwan O Industrial Estate, Fat Tong
Chau (
Existing residential developments and
schools on the New Territories side are located in excess of 3 km of the site,
with the nearest existing residential development, Oscar By The Sea (OBS),
located 3.2 km from the boundary of the site (to the North). Planned residential developments in Area 85
(approx. 10,000 people) and Area 86 (approx 57,000 people) are located
approximately 2.0 km to the North of the site.
The first phases of these planned developments are anticipated to have
population intake in 2007/8, according to information provided by Planning
Department. On the Hong Kong Island
side, across the Tathong Channel, Siu Sai Wan is located less than 2 km from
the site with a population of 35,000 and Chai Wan at between 2 and 3 km from
the site with a population of 111,400 (Figure 4.40).
Area 137 is not located within close
proximity to residential developments. However, it is much more visible than
the other two potentially eligible sites and closer to major urban districts
thus having more public interests that are directly affected by the proposal
and raising the site’s level of sensitivity from a planning perspective. Major viewpoints would be from Siu Sai Wan,
Water Quality Conditions
Waters off Tseung Kwan O are located in
the Eastern Buffer Control Zone. These
waters are not markedly affected by
No significant marine works are foreseen
for the construction of the LNG terminal, thus the potential impacts on the
water quality parameters of Area 137’s coastal waters are expected to be
acceptable. However, due to the
remoteness of Area 137 from BPPS, the extent of the impacts on water quality as
a result of the interconnecting pipeline’s construction activities will
potentially be significant.
Sediment Quality Conditions
Routine monitoring of sediment quality in
the vicinity of the Area 137 site at Station ES4, located approximately 2km to
the west of Area 137, has indicated that coppers levels exceed the Lower
Chemical Exceedance Level (LCEL), while silver levels exceed the Upper Chemical
Exceedance Level (UCEL), which could indicate contamination, and the
requirement for confined marine disposal.
Terrestrial Ecological Resources
The Tseung Kwan O site is formed by
recently reclaimed land and is therefore considered to be of no particular
ecological value. Nevertheless the eastern side of Area 137 is bounded by the
The LNG terminal will be constructed on an
existing industrial site, thus significant direct and indirect impacts on
terrestrial habitats present in and around Area 137 are not expected to be
significant.
Marine Ecological Resources
Neither Indo-Pacific Humpback dolphins (Sousa chinensis) nor Finless Porpoises (Neophocaena phocaenoides) have been
recorded in the vicinity of the Tseung Kwan O site. The nearest sighting of a Finless Porpoise
was 2km south of Tung Lung Chau.
As the Tseung Kwan O site consists of
newly reclaimed land it is considered that this coast is unlikely to have
corals of particular ecological value. A recent study ([48])
on Tseung Kwan O indicated
low abundance and diversity of corals on natural coasts in the bay including
Junk Island, while moderate coral cover and low diversity of hard corals was
recorded in East Joss House Bay and Tung Lung Chau. The west coast of
No significant marine works are foreseen
for the construction of the LNG terminal, thus the potential impacts on the
marine ecological resources of Area 137 are expected to be acceptable. However, the overall magnitude of marine
ecology impacts along the proposed pipeline route from Area 137 to BPPS will
potentially be significant due to the length of the pipeline (>80 km) and
the level/number of physical constraints present. The first ~40 km of the pipeline route from
Area 137 to the
Fisheries Resources and Operations
Capture fisheries operations in waters off
Area 137 are reported to be of moderate to high magnitude compared to other
In view of the overall moderate level of
importance of the commercial fisheries activities at Area 137, it is expected
that the potential construction and operation impacts of the LNG terminal on
the local fisheries will not be significant.
Cultural Heritage Resources
Owing to the fact that Area 137 is formed
by reclaimed land, the site is considered to have no archaeological
potential. Monuments and buildings of
recognised cultural or historical interest in the vicinity of Area 137 include
a Tin Hau Temple located about 1.2km to the east of the site in Joss House Bay
and the Old Customs House located 1.5km to the north on Junk Island.
Due to the artificial nature of the site,
the construction of the LNG terminal at Area 137 will have no significant
impact on sites of cultural, historical/heritage or archaeological importance.
Visual and Landscape Conditions
The landscape character of Area 137 is
considered to be urban industrial and it is expected that the Area 137 site
could accommodate an LNG terminal and associated facilities with no substantial
change to landscape quality.
The proposed LNG Terminal location at Area
137 would be visible from several Visually Sensitive Receivers (VSRs) which
would include residents at densely populated urban areas of Siu Sai Wan and
Chai Wan as well as residents at some of the existing or future residential
developments at Tseung Kwan O including the cemetery. Other sensitive receivers may include hikers
in the
Four VSRs (Siu Sai Wan,
Although Area 137 has been built to
accommodate Deep Waterfront Industry, the site’s high visibility to major urban districts such as Siu Sai
Wan and Chai Wan (total population of approximately 146 000) will expose a
large population to increased levels of perceived risks/perceived safety due to
the apparent vicinity of the LNG terminal to these populated areas. This will potentially lead to an increase in
the level of public interests with regards to the proposed development and may
cause planning issues.
4.11.15
Conclusions
From a review of the detailed
environmental, social and planning information of the three elected sites, it
is deemed that
From a terminal perspective, due to the
environmental and marine transit issues identified within
From a perceived safety perspective,
although Area 137 is not located within close proximity to residential
developments, it is much more visible than the other two elected sites and
closer to major urban districts, leading to greater public interests in an area
which bears a history of local residents objecting to the use of Area 137 as an
industrial site on site for Potentially Hazardous Installations (PHIs). In this respect, this site is considered to
present greater permitting risks than the development of the
From a landscape and visual impact
perspective, the development of the LNG terminal at Area 137 is estimated to
have a significant adverse visual impact due to its exposure and proximity to
densely populated areas. On the other
hand, due to the remoteness and orientation of the sites at
To highlight the greater perceived safety
issue and the landscape intrusion of Area 137 with respect to
The greater length and level of
constraints of the connecting pipeline from Area 137 to BPPS is considered to
be a further drawback to the selection of Area 137 as a viable site for the LNG
terminal due to the greater potential impacts of the marine works to marine
ecology and water quality. In comparison
to the South Soko - BPPS pipeline, the > 80 km pipeline from Area 137 to
BPPS presents approximately 40 km (from Area 137 to the
From a planning perspective, although Area
137 has been zoned in the OZP for uses compatible with Deep Waterfront
Industry, there is no provision within the existing land use zone for the LNG
Terminal (either as of right or upon application to the Town Planning
Board). A rezoning request would
therefore be required which would entail a statutory procedure creating
potential statutory opportunities for public comment and associated planning
delays/risks.
Following the conduct of an alternatives
assessment, the results indicate that the development of a LNG terminal at a
coastal location in
The results of this Hong Kong wide site search
exercise indicated that two sites were worthy of further analysis based on
their relative performance against a series of other shortlisted sites in
relation to environmental, risk, planning, social, marine traffic and
engineering criteria. The two preferred
sites were
http://
www.epd.gov.hk/epd/english/environmentinhk/water/marine_quality/mwq_report.html