This section presents the
Landscape and Visual Impact Assessment of the LNG terminal development at
The main components of the LVIA are as
follows:
·
Description
of the Project;
·
Review
of planning and development control framework;
·
Baseline
study of landscape resources;
·
Landscape
impact assessment during construction and operation;
·
Visual
impact assessment during construction and operation;
·
Recommendations
for landscape and visual mitigation
measures for both construction and operation stage;
·
Assessment
of night lighting and glare;
·
Baseline
study of landscape character;
·
Landscape
character impact assessment during construction and operation, and;
·
Assessment
of residual impact and conclusion on the acceptability of the Project.
11.3
Introduction & Project Description
The background to the project and the general description of the LNG
terminal at
The following description of the major
visual components of the LNG terminal and supporting infrastructure is based on
the preliminary design which will be subject to further refinement at the
detailed engineering design stage. The
preliminary layout plan, which shows the key visual features of the proposal,
is illustrated in Figure 11.1.
It must be noted that the layout presented
in Figure
11.1 has been selected from a number of alternative site layouts in
view of its minimisation of landscape and visual impacts to the Project
area. The design, dimensions and
location of the LNG terminal’s structures indicated in the preliminary layout
are thus the result of a preliminary assessment which has enabled the
optimisation of the LNG terminal’s design/layout in relation to the Project
area’s landscape character (i.e. morphology, exposure to sensitive receivers,
etc.).
11.3.1
Site
Area
The LNG terminal will be constructed
within a total site area of approximately 36.5 ha.
·
Approximately
5 ha of level land which was previously a Vietnamese Detention Centre and which
was demolished by Correctional Services Department in 1996.
·
Approximately
14 ha of land will be created by further cutting the slopes to the existing
north and south of the former Detention Centre.
·
Approximately
0.6 ha which will be created through extending reclamation on the western sides
of the site of the former Detention Centre and 1.1 ha of seawall modification.
The
remaining 15-16 ha will be within the boundary fence line of the LNG terminal
and will be physically undisturbed.
11.3.2
Construction
Impacts.
Figure 11.2 shows the extent of construction areas. Approximate areas are as follows:
·
Excavation
/ Site Levelling 15.3 ha
·
Reclamation
0.6 ha
·
Seawall
Upgrades 0.8 ha
·
New
Seawalls 0.3 ha
·
Cut /
Slope stabilisation – 3.2 ha
·
Temporarily
affected areas – 1.8 ha
·
Areas
Requiring Soil Nailing / Boulder Stabilisation 3.4
ha
The majority of this area requires minor excavation and site levelling.
11.3.3
Land
Excavation
Excavation of around 2 ha of land on the
northern part of
Site formation will involve
cutting into the western side slopes of the northern hillcrest. The major visual components of this work will be the resultant cut-slopes up to a
maximum height of 45m.
11.3.4
Land
Reclamation
Reclamation will be approximately 0.6 ha
of land within Sai Wan using marine sand fill and, if suitable and available,
public filling materials. There will also be an additional 1.1ha of seawall
modifications The works will involve
construction of about 1.1 km of a vertical and sloping seawall. The reclamation area will be used primarily
for the third expansion case LNG storage tank (in Sai Wan) and other associated
facilities such as the service berths.
11.3.5
LNG
Jetty
The LNG jetty will comprise one
approximately 240 m long trestle leading to the jetty structures and unloading arms for LNG carriers to unload LNG. The
trestle will be supported on piles and a concrete deck will be placed on top to
serve as an access road to the jetty. The steel structure will also support
pipe racks and associated facilities.
11.3.6
LNG
Terminal Facilities
The LNG terminal facilities and expansion
areas will include installation of the following:
(Note all dimensions are approximate based
on a preliminary design)
·
Two
cryogenic LNG Tanks with space for a third tank for future expansion, nominal
size of 90m diameter by 49m high to the top of the dome and capacity each of up
to 180,000 cubic metres. Alternative
tank sizes may be considered by CAPCO, however the capacity of the tanks will
be similar. The potential size of these
tanks could be 64 m high with a smaller diameter. In order to assess the worst
case scenario, a total tank height of 70m PD (64m tank + 6m) is shown in the
photomontages.
·
Process
Area
·
Low
Pressure and High Pressure pumping systems
·
Vaporization
(Re-gasification) Area including 6 sea water vaporizers
·
LNG
turbine generators (3) approximately 5m x 3.5m x 7m high plus stack
approximately 1.8 x 6m
·
Vents
- the low pressure vent is 50m in height and the high pressure vent is 60m in
height
·
Maintenance
Workshop (40m x 20m x 15m high)
·
·
Guard
House (10m x 5m x 4m high)
·
Utility
Area (40m x 20m x 4m high)
·
Control
Room (30m x 25m x 4m high)
·
Compressor
Shelter (20m x 20m x 8m high)
·
Jetty
control pulpit on jetty head (10m x 5m x 4m high)
·
Unloading
arms
·
Living
Quarter (20m x 20m x 18m high)
The major visual component
will be the LNG storage tanks.
Separate buildings will be
required for the Process Area, Maintenance Workshop,
11.3.7
Submarine
Gas Pipeline
A submarine natural gas
pipeline of approximately 38km in length connecting the LNG terminal at
The visual implications of
the submarine gas pipeline will only arise during construction by the marine
vessels and equipment used to lay and bury the pipeline. Therefore no operational visual impacts are
expected.
11.3.8
Land-based
Gas Pipeline
The land-based section of the pipeline
would be laid in an open trench followed by direct burial. The pipeline would, typically, be buried at
about 1.1 m below ground level within a trench approximately 1 m wide. An open cut method of construction would be
used and the trench would then be backfilled as per the relevant design
code. Since the pipeline will be buried,
and will be within the existing Black Point Power Station so there will be no
adverse landscape or visual impacts.
11.3.9
The existing Tin Hau temple is to be
re-located to the small headland at Pak So Wan.
The pipeline from
11.3.11
LNG
Carrier
LNG can be transported to the receiving
terminal in carriers of differing sizes.
An LNG carrier with a 125,000 m3 capacity is approximately
285m LOA, 43m beam with a draft of 11.3m.
A class of LNG carriers of up to 215,000 m3 may also be considered
by CAPCO and these vessels are typically 315m LOA, 50m beam and 12m draft.
The discharge of LNG from the carrier will
take approximately 18 hours. In addition, it will take
approximately 3 hours for mooring, cool down, connecting the unloading arms,
and cargo measurement. After discharging the LNG, it will also take
approximately 3 hours for cargo measurement, purging of the unloading arms,
disconnecting the arms, and unmooring. It is envisaged, based on the terminal throughput,
that one LNG carrier will berth at the terminal every five to eight days.
In view of this frequency, the Visual
Impact Assessment and associated photomontages in Section 11.12 includes the carrier moored, alongside the LNG jetty.
11.3.12
Construction
program
The construction program
is outlined in Part 2, Section 3 of this EIA.
The landscape and
visual mitigation works are to be carried alongside the construction of the
terminal where technically feasible.
11.4
Legislative
Requirements and Evaluation Criteria
The methodology of the LVIA is based on Annexes 10 and 18 in the Hong Kong SAR Government's Technical Memorandum on the Environmental Impact Assessment Process
(EIAO-TM) under the EIA Ordinance (Cap.499, S16), entitled
"Criteria for Evaluating Visual and Landscape Impact" and "Guidelines
for Landscape and Visual Impact Assessment", respectively and the EIAO Guidance Note No. 8/2002 “Preparation
of Landscape and Visual Impact Assessment Under the Environmental Impact
Assessment Ordinance.”
The landscape assessment considers the impact
of the proposed development on the existing landscape resources within 500m of
the development site and the landscape character areas within the viewshed.
In accordance with the requirements of Annex 10 of the EIAO-TM, the visual assessment analyses the impact of the proposed
development on the existing views and the visual amenity, particularly from the
Visually Sensitive Receivers (VSR) within the viewshed. In order to illustrate the visual impacts of
the proposed LNG terminal, photomontages prepared from selected viewpoints
compare the existing conditions with the anticipated view after
construction.
11.4.1
Planning
Issues
The Outline Zoning Plans (OZPs) and the Concept Plan for Lantau are
relevant to the landscape setting and the visual context of the study
area. The findings of a study entitled
‘The Landscape Value Mapping of Hong Kong” (Planning Department, The Government
of Hong Kong Special Administrative Region, July 2005) also provides a
benchmark for these island landscapes.
Figure
11.3 shows there are
currently no OZPs covering the proposed
The Concept Plan for Lantau (see Figure 11.4)
indicates a planning emphasis on nature conservation and environmentally
sustainable uses. These include
developments such as:
·
Possible
resort facilities at Tai Long Wan and
·
Additional
mountain bike trails for linking four existing mountain bike trails to form a
continuous 37km network;
·
11km
long cycle track network along the coast from Pui O to Shek Pik;
·
Beachside
boardwalk and water sports centres at Pui O Beach and
·
High
quality camp sites at Pui O;
·
Eco-trails
and heritage trails extending to Fan Lau and Shui Hau; and,
·
The Concept Plan for Lantau does not
address the
11.4.2
The South
West New Territories Development Plan
As a precursor the Concept Plan for
Lantau, the South West New Territories Plan set out recommendations for the
future of the area including the
The report stated that generally the areas
of high conservation value should be protected, and that development should
focus on recreational and tourism activities.
11.4.3
Landscape
Value Mapping of
The Landscape Value Mapping for Hong Kong
study rates
Such landscape character
mapping has been undertaken for
11.5
LANDSCAPE IMPACT ASSESSMENT
In accordance with Annex
18 of the EIAO-TM, the landscape impact assessment will cover the
following:
·
Describe the baseline landscape. This section
identifies and describes the landscape resources within 500m of the development
site. The existing landscape resources can be based on both topography and
vegetation. This section will also
describe edges as different Landscape Resources (LR’s).
·
Map the distribution of the LR’s on
·
A qualitative and quantitative assessment
methodology.
This is based on assessing thresholds that can determine the magnitude
of change and sensitivity to change of particular LR’s.
·
Analyse the landscape impact during
construction and operation. This section analyses the extent to which these LR’s are affected by the
proposal, using both quantitative and qualitative assessments.
· Discuss
mitigation measures. This
section examines landscape measures that will contribute to reducing landscape
impacts and that will enhance the landscape associated with the development.
This may include planting, new landscaped areas and re-vegetation. The residual
landscape impacts are also analysed.
Mitigation measures during construction and operation will be discussed,
at day 1 of mitigation and at year 10 of mitigation. An analysis of the
effectiveness of these mitigation measures is provided.
· Provide
Conclusions on the impacts of the project. These are discussed along with the Visual
Impact and Landscape Character Impacts in Section
11.21.
11.6
Baseline Landscape Description
As specified by the Study
Brief, the area for the Landscape Impact Assessment covers the area within 500
metres of the proposed development. As
this project is on
The landscape resources of
the island have been categorized according to the presence of common
elements. These include factors such as:
·
Topography;
·
Vegetation type (both species and age);
·
Built forms;
·
Evidence of human modifications;
·
Land use (past and present); and
·
Edges.
11.6.1
Broad
Brush Tree Survey
As outlined in the EIAO Guidance Note No. 8/2002 “Preparation
of Landscape and Visual Impact Assessment Under the Environmental Impact
Assessment Ordinance.” a broad-brush tree survey has been carried out. A total of 61 tree groups were recorded
within the proposed project boundary.
The tree species were dominated by exotic fast growing trees Acacia
confusa, and accompanied by a few
native tree species such as Litsea glutinosa, Microcos
paniculata, Celtis chinensis and Sapium discolor.
None of the trees recorded in the proposed
project area are rare, protected by law or of significant amenity value. They are mostly exotic plantation species
with native shrubs and trees found at the understorey. Most of the tree species especially Acacia
confusa, Casuarina equisetifolia and the native tree species such as Litsea glutinosa and Microcos paniculata have reached
maturity. Most of these trees possessed
poor tree form due to overcrowding of the plantation.
Extensive patches of trees (around 50 to
85 individuals) were located at the north of the abandoned reservoir, which was
an Acacia plantation around 20 years old.
Scattered patches of trees (1 to 10 individuals) were found along the
rocky shore of Sai Wan and surrounding the former Detention Centre helipad
area. Climbing plants were found
smothering the trees, especially near to the platform area, which has resulted
in the death of some of the trees. All
of the trees were between 2 and 10 metres in height, whilst the crown spread
was on average 3 metres. The understorey
was densely occupied by some native shrub species including Litsea
rotundifolia and Psychotria rubra.
The identified tree groups and their
quantities are outlined below and illustrated on Figure 11.18.
1 Acacia
confusa 2
2 Ficus
microcarpus 1
3 Ficus
microcarpus, Ficus superba 2
4 Melia
azedarach, Ficus superba 3
5 Ficus
microcarpus 1
6 Ficus
superba 1
7 Acacia
confusa, Ficus microcarpus, Litsea glutinosa, Ficus hispida, Microcos paniculata 10
8 Araucaria
heterophylla 3
9 Schefflera
octophylla 1
10 Araucaria
heterophylla, Melia azedarach 3
11 Acacia
confusa 4
12 Casuarina
equisetifolia 1
13 Acacia
confusa, Schefflera octophylla, Litsea glutinosa 8
14 Acacia
confusa 1
15 Acacia
confusa, Rhus succedanea 4
16 Acacia
confusa, Schefflera octophylla, Mallotus
paniculatus 5
17 Microcos
paniculata 1
18 Acacia
confusa, Litsea glutinosa 7
19 Acacia
confusa 3
20 Acacia
confusa 3
21 Acacia
confusa 1
22 Casuarina
equisetifolia, Sapium discolor, Litsea glutinosa, Cratoxylum cochinchinense, 10
23 Casuarina
equisetifolia, Melia azedarach, Sapium discolor, Ficus microcarpus 10
24 Melia
azedarach, Ficus microcarpus 5
25 Acacia
confusa, Litsea glutinosa, Ficus microcarpus , Celtis chinensis 7
26 Litsea
glutinosa, Acacia confusa, Ficus hispida, Bridelia tomentosa, Sapium discolor 3
27 Celtis
chinensis 1
28 Acacia
confusa, Ficus hispida, Sapium discolor 8
29 Acacia
confusa 5
30 Acacia
confusa, Litsea glutinosa 7
31 Acacia
confusa, Microcos paniculata, Schefflera octophylla 8
32 Acacia
confusa, Celtis chinensis 2
33 Litsea
glutinosa, Acacia confusa, Ficus hispida, Celtis chinensis, Microcos paniculata 21
34 Acacia
confusa, Microcos paniculata, Litsea glutinosa, Sapium discolor 4
35 Acacia
confusa, Sapium discolor 17
36 Acacia
confusa, Sapium discolor, Litsea glutinosa,
Microcos paniculata, 13
37 Acacia
confusa 3
38 Acacia
confusa, Sapium discolor 42
39 Acacia
confusa, Aporusa dioica, Litsea glutinosa,
Microcos paniculata 58
40 Acacia
confusa, Litsea glutinosa, Microcos
paniculata 51
41 Acacia
confusa, Litsea glutinosa, Microcos
paniculata, Machilus chinensis 47
42 Acacia
confusa, Microcos paniculata, Machilus chinensis 41
43 Acacia
confusa 31
44 Acacia
confusa, Litsea glutinosa, Microcos
paniculata 85
45 Acacia
confusa, Litsea glutinosa, Machilus chinensis 65
46 Litsea
glutinosa, Schefflera octophylla 3
47 Acacia
confusa, Litsea glutinosa, Microcos
paniculata, Viburnum odoratissimum 34
48 Acacia
confusa, Sapium discolor, Viburmum odoratissimum, Microcos paniculata 27
49 Acacia
confusa, Litsea glutinosa, Microcos
paniculata, 50
50 Acacia
confusa, Litsea glutinosa, Rhus succedanea 50
51 Acacia
confusa, Litsea glutinosa, Rhus succedanea,
Melia azedarach 35
52 Acacia
confusa, Litsea glutinosa, Celtis
chinensis, Machilus chinensis 8
53 Acacia
confusa, Celtis chinensis, 22
54 Acacia
confusa, Litsea glutinosa, Sapium
discolor, Celtis chinensis ,Cratoxylum cochinchinense, Zanthoxylum avicennae 32
55 Acacia
confusa, Litsea glutinosa, Microcos
paniculata, Schefflera octophylla 10
56 Acacia
confusa, Microcos paniculata, 46
57 Acacia
confusa, Celtis chinensis 22
58 Ficus
superba, Viburnum odoratissium, Celtis
chinensis 40
59 Acacia
confusa, Microcos paniculata, 40
60 Acacia
confusa, Litsea glutinosa, Sterculia lanceolata, Schefflera octophylla 40
61 Acacia
confusa, Litsea glutinosa, Schefflera octophylla, Cerbera manghas, Sampium
sebiferum 44
Landscape Resources (LR’s)
have been identified as the following:
LR1 Secondary
LR2
LR3 Shrubland
LR4 Backshore
Shrubland
LR5 Grassland
LR6 Abandoned
Wet and Dry Agricultural Land
LR7 Abandoned
Reservoir
LR8 Disturbed
Area
LR9 Rock
Shoreline
LR10
LR11 Artificial
Shore
LR12
An
understanding of the sensitivity to change of the LR’s is important when
analysing the overall landscape impact of the project upon the LR’s.
Factors affecting the sensitivity of
change for evaluation of landscape are:
·
Quality
of landscape resources;
·
Importance
and rarity of special landscape elements;
·
Ability
of the landscape to accommodate change;
·
Significance
of the change in the local and regional context; and
·
Maturity
of the landscape.
The degree of sensitivity of the landscape
resources is classified as follows:
·
High – important components or landscape of particularly
distinctive character susceptible to small changes;
·
Medium – a landscape of moderately valued characteristics
reasonably tolerant to change;
·
Low – a relatively unimportant landscape which is able to
accommodate extensive change.
The following section
describes each of the landscape resources.
11.7.1
Secondary
Secondary Woodland (LR1) has an upper canopy height of between 5 and
10m. It is dominated by Celtis chinensis, Cinnamomum camphora, Machilus
chinensis, Ficus microcarpus and Dimocarpus
longan.
|
Figure 11.5 Secondary
Small patches of secondary woodland (approximately 1 ha) are located at
the west of the abandoned reservoir and at the fringe of shrubland. It covers approximately 0.9% of the island.
Although this LR has the tallest canopy of any LR on the island, it varies
somewhat in canopy size. Some areas
appear well established, with other areas appearing as an immature landscape
that is re-establishing opportunistically in the wetter areas.
The Secondary Woodland is considered to have a high sensitivity to
change.
11.7.2
The canopy species of the plantations were 10 to 12 meters in height.
The plantation was dominated by Acacia confusa established 10 to 20
years ago. Some of the native shrubs and
tree saplings in the understorey developed as canopy species after the
degeneration of individuals of Acacia confusa. The canopy species was
dominated by Acacia confusa and Casuarina equisetifolia. There were 54 plant species recorded within
the plantation and all of them are common or very common in
Figure 11.6
The
11.7.3
Shrubland
(LR 3)
The Shrubland LR has an upper canopy
height of approximately 1.5m and is dominated by native species of Downy Rose Myrtle (Rhodomyrtus tomentosa) and Cratoxylum cochinchinensis. Embelia
laeta is the most common vine species.
|
Figure 11.7 Shrubland (LR 3)
Shrubland
is common on the hill-side areas on the island and covers approximately 80% of
the island. It is an immature landscape
that has formed as a result of past tree canopy clearance and farming
practices. In many respects it
represents the initial re-establishment of vegetation. Shrubland is considered to have a medium sensitivity to
change.
11.7.4
Backshore
Shrubland (LR 4)
Backshore Shrubland also has an upper canopy height of approximately
1.5m however it differs from Shrubland by the presence of Pandanus (Pandanus tectorius).
|
Figure
11.8 Backshore Shrubland (LR 4)
Backshore Shrubland is a relatively small
component on the island and confined to two small areas and covers
approximately 1% of the island’s area. Backshore Shrubland is
considered to have a high sensitivity to change.
11.7.5
Grassland
(LR 5)
Grassland areas are less than 1m in height and are dominated by Batiki
Bluegrass (Ischaemum aristatum).
|
Figure 11.9 Grassland (LR 5)
The Grassland area is a disturbed area
that was partly created during the formation of a helipad in the 1990’s. It differs from the other disturbed areas in
that vegetation is re-establishing on the cleared ground, which was never
concreted.
The Grassland LR covers approximately 2.5%
of the island’s area.
Grassland is considered to have
a low sensitivity to change.
11.7.6
Abandoned
Wet and Dry Agricultural Land (LR 6)
There are two small areas on the island that are recently abandoned
agricultural land.
|
Figure 11.10 Agricultural Land (LR 6)
The figure above shows this abandoned agricultural
land which is relatively flat and contains mostly grasses and small
shrubs. Some shrubland is visible on the
sloping areas on either side of the abandoned agricultural land.
These areas contain two seasonal streams
of short length with small catchment areas.
The abandoned wet and dry agricultural
land unit covers approximately 1.5% of the island’s area.
Abandoned
11.7.7
Disturbed
Area (LR 7)
The Disturbed Area LR is the site of the
former detention centre, and its associated facilities (concreted and abandoned
areas) and is located in the centre of the island.
The Disturbed Area LR area has some cut
engineered slopes and flat concrete areas; however, it does contain several
landscape plants including Norfolk Island Pine (Araucaria heterophylla) and Beefsteak Plant (Acalypha wilkesiana).
Figure 11.11 Disturbed Area (LR 7)
This area covers approximately 6% of the
island.
The Disturbed Area is considered to have a
low sensitivity to change.
11.7.8
Abandoned
Reservoir (LR 8)
The reservoir is man made, however it is
mostly natural in appearance as surrounding vegetation has re-colonised the
banks.
Figure 11.12 Abandoned Reservoir (LR 8)
The Abandoned Reservoir has a high
sensitivity to change.
11.7.9
Rocky
shoreline (LR 9)
|
The Rocky Shoreline LR is the most common
edge to the island and merges into the dominant Shrubland Landscape Resource.
Figure 11.13 Rocky Shoreline (LR 9)
Along the indented rocky shore there are steep rock-faces
which extend up from the shore with occasional inlets leading to small sea
caves.
The Rocky Shoreline LR
generally provides the border to the Shrubland LCU as it meets the sea. The Rocky Shoreline comprises approximately 85% of the perimeter of
The Rocky
Shoreline is considered to have a high sensitivity to change.
11.7.10
Figure 11.14
11.7.11
Artificial
Shore (LR 11)
|
Figure 11.15 Artificial Shore (LR 11)
There are no
trees in this landscape resource.
The artificial
shore is considered to have a low sensitivity to change.
11.7.12
A
Over the last 40 years for which aerial photographic
records exist, it is apparent that changes have occurred in the distribution,
and in some cases, the location of landscape resources.
11.8.1
The
1963 distribution of landscape resources
The distribution of LR’s at
Figure 11.16 shows that in 1963 much of
the central portion of the island was used for agricultural activity. The dominant LR, especially on the western
end of the island, is the Shrubland area.
This may have evolved due to clearance of woodland trees for
construction and firewood over many years.
Thus even this snapshot of the landscape units almost fifty years ago is
of a landscape that has been modified by human intervention for many years.
11.8.2
The
1986 distribution of landscape resources
Figure 11.17 shows that by 1986 the
distribution of the LR’s was altered further.
The areas of Shrubland were still dominant, however the
The Disturbed area was also
much smaller than at present and there was no
11.8.3
The
2005 distribution of landscape resources
By 2005 the distribution of the LR’s had altered
again. Figure
11.18 shows the present distribution of LR’s on
Table
11.1 Summary Table of Baseline
Conditions (2005)
This Table shows the
dominance of Shrubland and Rocky Shoreline as the most common LR’s. Shrubland may be the result of past clearance
that removed the taller canopy trees, which are starting to redevelop in other
areas, giving rise to the Plantation LR.
11.9
Landscape Resource Impacts
The two key factors that affect the
evaluation of Landscape Resource impacts are the magnitude of change and the
sensitivity of the Landscape Resources. The sensitivity to change for each of
the LR’s has been described above and the factors affecting the magnitude of
change are outlined below.
Factors affecting the magnitude of change for assessing landscape impacts are:
·
Compatibility
of the project with the surrounding landscape, i.e.; how well will the proposed
development fit in with its surroundings.
For example, a new housing development constructed in an area with other
housing developments or built forms will have a higher compatibility.
·
Scale
of the development, i.e.; how big is the development relative to its
surroundings. For example a 30 storey
building constructed on
·
Reversibility
of change. This refers to how easily the changes on the landscape can be
reversed. For the purposes of this assessment, we have assumed the terminal
changes are ‘irreversible’.
The magnitude of change is therefore classified as follows:
·
Large – ranging from notable change in the landscape
characteristics over an extensive area ranging to very intensive change over a
more limited area;
·
Intermediate – moderate changes to a local area;
·
Small – changes to specific components;
·
Negligible – no substantial changes to the baseline condition.
The landscape impact is a product of the
magnitude of change and the sensitivity of the Landscape Resources. Table
11.2 below shows the significance threshold of the Landscape Resource
impacts.
Table 11.2 Significance
Threshold of Potential Landscape Resource Impact
|
Sensitivity to Change |
|||
Magnitude of Change
caused by Proposals |
|
Low |
Medium |
High |
Large |
Moderate Impact |
Moderate/Significant Impact |
Significant Impact |
|
Intermediate |
Slight / Moderate Impact |
Moderate Impact |
Moderate / Significant Impact |
|
Small |
Slight Impact |
Slight / Moderate Impact |
Moderate Impact |
|
Negligible |
Negligible Impact |
Negligible Impact |
Negligible Impact |
Table
11.3 provides some
definitions of the significance thresholds for Landscape Impacts.
Table 11.3 Adverse
/ Beneficial Impact of Landscape Impact
Significant: |
Moderate: |
Slight: |
Negligible |
Adverse / beneficial impact where the proposal
would cause significant degradation or improvement in existing landscape
baseline conditions |
Adverse / beneficial impact where the proposal
would cause noticeable degradation or improvement in existing landscape
baseline conditions |
Adverse /beneficial impact where the proposal
would cause a barely noticeable degradation or improvement in existing
landscape conditions or where the changes brought about by the project would
not be apparent in visual terms |
The proposal does not affect the existing
landscape baseline conditions |
11.10
Unmitigated Landscape Impacts During Construction
Table 11.4 shows the potential impact of the proposed
development on each of the LR’s and the potential overall impact based on the
preceding Significance Threshold of Potential Landscape Impact matrix.
This overall impact does not take into
account the effects of remediation and mitigation works after construction,
this will be discussed in Section 11.11.
Table
11.4 Unmitigated Landscape Impact
Significance Threshold Matrix
LR |
Description |
Area /
Length (2005) |
Area
affected by proposed development (temporary and permanent) |
% of
LR Area / Length affected |
No of
trees affected (approx.) |
Sensitivity
to Change |
Magnitude
of Change |
Significance Threshold of Landscape Impact |
1 |
Secondary |
1 ha |
0.2 ha |
20% |
70 |
High |
Intermediate |
Moderate/Significant |
2 |
|
11.4 ha |
3.3 ha |
32% |
1330 |
Medium |
Intermediate |
Moderate |
3 |
Shrubland |
85.7 ha |
8.3 ha |
10% |
200 |
Medium |
Small |
Slight/Moderate |
4 |
Backshore
Shrubland |
0.5 ha |
Nil |
0% |
Nil |
High |
Negligible |
Negligible |
5 |
Grassland |
2.1 ha |
1.8 ha |
90% |
Nil |
Low |
Large |
Moderate |
6 |
Abandoned Wet and
Dry Agricultural land |
1.4 ha |
0.5 ha |
36% |
Nil |
Low |
Small |
Slight |
7 |
Disturbed Area |
6.5 ha |
5.6 ha |
83% |
10 |
Low |
Large |
Moderate |
8 |
Abandoned
Reservoir |
0.2 ha |
Nil |
0% |
Nil |
High |
Negligible |
Negligible |
12 |
|
25m2 |
25m2 |
100% |
Nil |
High |
Large |
Significant |
Total
Area |
|
108.8
ha |
19.7 ha |
|
|
|
|
|
9 |
Rocky Shoreline |
6 km |
0.27 km |
4% |
Nil |
High |
Small |
Moderate |
10 |
|
0.4 km |
0.035 km |
13% |
Nil |
High |
Large |
Significant |
11 |
Artificial Shore |
0.6 km |
0.56km |
100% |
Nil |
Low |
Large |
Moderate |
Total Length ([1])
|
|
7.0 km |
0.865
km |
|
|
|
|
|
The proposed development will
impact on approximately 19.7 ha of the land area and approximately an
additional 1.05 km of the perimeter of
11.10.1
Summary of Landscape Impacts
Significant
Landscape Impacts
Potential significant
landscape impacts have been identified on the Sandy Beach LR’s. The
During construction the Tin
Hau temple will be relocated. During this process, the impact will be
significant; however the relocation process will fully mitigate this impact.
Moderate/Significant
The removal of 20% of the
Secondary Woodland will have a moderate/significant impact as the LR is of a
high sensitivity. Mitigation of this impact will be accomplished through
re-planting of appropriate species.
Moderate Impacts
The removal of 4% of the
rocky shoreline of
There will be moderate
impacts on the
Slight/ Moderate
Impacts
There will be a
slight/moderate impact on the Shrubland LR’s.
A small percentage (10%) of the Shrubland is affected which, is of
medium sensitivity to change. The
Shrubland impacts will be mitigated with new plantings.
Slight Impacts
There
will be slight impacts on the Abandoned Wet and Dry Agricultural land. These
areas are of low sensitivity and will be replaced with similar landscape
elements.
Negligible
Impacts
There will be negligible
impacts on the Backshore Shrubland and the Abandoned Reservoir.
11.10.2
Offsite
Landscape Impacts
Gas Receiving Station (GRS)
A GRS will be constructed on an area of
reclaimed land adjacent to the existing power generating facilities at Black
Point. The new station will be of a
similar appearance to the existing LNG receiving station at Black Point. Given that the new station will be located
within the existing facilities, there will be negligible landscape impacts
associated with the new receiving station.
Water Main
A new water main is required to supply
The landscape impacts of this work will
only occur during the construction period.
Following excavation and installation of the new water main, the trench
will be backfilled and the landscape reinstated. The residual landscape impacts will be
negligible.
11.10.3
Landscape
Resource Impacts During Operation
No impacts on the Landscape Resources are
expected during operation.
The final detailed Landscape Mitigation
Measures will be the subject of a Landscape Master Plan that will be submitted
for approval to the relevant Authority prior to construction. This plan will
investigate further measures to mitigate the impacts of the development
including the feasibility of the use of techniques to green the tanks with
vegetation.
As mentioned in Section 11.2, the preliminary layout assessed in this EIA Report
has been selected from a number of alternative site layouts in virtue of its
minimisation of landscape and visual impacts.
The selection of the preferred preliminary layout was determined by a
preliminary landscape and visual impact assessment of the alternative layouts. Figures 11.20a and 11.20b clearly show the difference that
the reduction in the size of the terminal will potentially have on the
landscape.
The landscape mitigation measures proposed
will be installed progressively throughout the construction of the LNG terminal
where technically safe and practical.
This will assist in enhancing the effectiveness of the mitigation
measures from the first day of operation.
Proposed mitigation measures to reduce the
potential impacts on the existing Landscape Resources and provide a potential
enhancement of the existing landscape quality are as follows:
LMM 1 – Cultivation of areas compacted
during construction. Areas compacted during the construction phase
that are not required during the operation phase, are to be cultivated to a
depth of up to 300mm in accordance with the future Landscape Specification.
LMM 2 – Soil stabilisation and planting. During the design phase, a soil
stabilisation and embankment planting strategy will be developed to ensure that
land affected by slope excavation can be replanted. Soil preparation and the selection and
provision of suitable growing medium is to be completed in accordance with the
relevant best practice guidelines.
LMM 3 – Tree and shrub planting. Planting of trees and shrubs is to be
carried out in accordance with the Landscape Details and the relevant best
practice guidelines. Plant species and
densities are to be provided in future detailed design documents and are to be
selected so as to achieve a finished landscape that matches the surrounding
equivalent landscape.
Note: LMM2 and LMM3 are to provide a
minimum compensatory planting area of 0.2ha of Secondary Woodland, 1.9ha of
Shrubland and 1.3ha of Grassland.
LMM4 – Utilising natural rock for
reclamation. The
reclamation areas shall utilise natural rocks for the engineered sea-walls.
LMM5 – Natural
accretion of sand. It is anticipated that sand will naturally form at the base of the new
sea walls creating a beach area similar to the existing beach. This process is
dependent on natural forces, but is likely to occur within ten years. It must
be noted that this is a natural process and is out of the control of the
project proponent.
LMM6
–
Cut Stabilisation. Areas
of cut to be stabilised for operational requirements. Materials and finishes of
stabilisation to be selected to complement the surrounding landscape where this
is technically feasible. This includes the addition of pigments and aggregates
in the finished slope that complement the existing geology of the area.
LMM7 – Bench Plantings. Cut Slopes to have benches created to
allow for plantings. Plantings will include Shrubs and climbers to minimise the
visual impact of the slope and mitigate impact on vegetation.
LMM8 - Relocation. Landscape Resources of value to be re-located where practically
feasible.
LMM9 – Landscape Berm/Planter 2 metre high landscape berm/planter is to
be constructed. Fast growing indigenous tree species to be installed to help
screen the tanks and reduce the scale of the terminal. A typical detail for
this measure is shown in detail 5 on Figure
11.21a.
LMM10 – New Access Construction of a new pier to allow public
access to the southern area of the site.
LMM11 – Early Planting Works. Where technically feasible, new
plantings are to be installed as early as possible during the construction
works. Due to the unknown nature of the construction timing, this mitigation is
not shown on Figure 11.20.
LMM12 – Site hoardings to be compatible
with the surrounding environment. Where possible site hoardings to be coloured to complement the
surrounding areas. Colours such as green and light brown are recommended. As
the proposed locations are not yet known this mitigation measure is not shown
on Figure 11.20.
Due to the land take and
operational requirements of the LNG terminal, some landscape impacts cannot be
mitigated. The trees that are to be removed for the terminal, will be
compensated by planting new trees in other parts of the island. This will help
restore some of the existing degraded areas to a more natural landscape.
Table
11.5 describes the
predicted un-mitigated impacts on the landscape resources of
Table
Table 11.5 Mitigated Landscape
Impacts
No mitigation measures are proposed for
LR’s 4 and 8 as there will be no impact on these resources. No mitigation
measures are proposed for LR’s 7 and 11 as these resources will be replaced
with similar resources as a result of the new Terminal.
11.11.1
Effectiveness
of Landscape Resource Mitigation Measures
Due to the land take and operational
requirements of the LNG terminal, some landscape impacts cannot be mitigated.
The trees that are to be removed will be
compensated by new plantings in other parts of the island. This will help
restore some of the more degraded areas to a historically more natural
landscape.
Where mitigation measures are proposed
they are effective measures, and will contribute to the mitigation of the
affected Landscape Resources.
11.12
Residual Landscape Impacts
The residual landscape impacts are those
landscape impacts that will remain after all mitigation measures have been
implemented. Figure 11.22 shows the residual landscape
impacts and they are quantified in Table
11.6.
Table
11.6 Residual Landscape Impacts
LR |
Description |
Area /
Length (2005) |
Area
affected by proposed development |
Mitigated
Area |
Residual
Impact |
1 |
Secondary |
1 ha |
0.2 ha |
0.2ha |
Nil |
2 |
|
11.4 ha |
3.3 ha |
Nil |
3.3ha |
3 |
Shrubland |
85.7 ha |
8.3 ha |
1.9ha |
6.4ha |
4 |
Backshore
shrubland |
0.5 ha |
Nil |
Nil |
Nil |
5 |
Grassland |
2.1 ha |
1.8 ha |
1.3ha |
0.5ha |
6 |
Abandoned wet and
dry agricultural land |
1.4 ha |
0.5 ha |
Nil |
0.5ha |
7 |
Disturbed area |
6.5 ha |
5.6 ha |
5.6ha |
Nil |
8 |
Abandoned
Reservoir |
0.2 ha |
Nil |
Nil |
Nil |
9 |
Rocky Shoreline |
6 km |
0.27 km |
Nil |
0.4km |
10 |
|
0.4 km |
0.035 km |
Nil |
0.05km |
11 |
Artificial Shore |
0.7 km |
0.56km |
0.7km |
Nil |
12 |
|
25m2 |
25m2 |
25m2 |
Nil |
11.12.1
Residual
Impact Summary
Due to the operational and safety
requirements of the Terminal, the cultivation of vegetation on the cut-slopes
behind the tanks is not appropriate. Bio-engineering of these slopes cannot
meet the technical requirements for the integrity of the slope, and for safety
reasons vegetation cannot be established on these slopes. Approximately 3.4 ha
of impacted areas will be mitigated. Since Secondary Woodland is of a higher
value and covers a smaller area than Shrubland, in general terms, the impact on
the Secondary Woodland will be fully mitigated.
As Shrubland is the next most valued landscape resource, the remaining
areas available for mitigation will reinstate Shrubland resources. This however will leave a residual impact of
approximately 6.4 hectares. The
disturbed areas and artificial shore areas are to be replaced with similar
resources (i.e., the new terminal) there will be no residual impacts on these
areas. The Tin Hau temple is to be
re-located to a suitable area on the island, therefore the residual impact will
be negligible.
11.12.2
Mitigation
Installation and Maintenance Responsibilities
The project proponent will be ultimately
responsible for the installation and maintenance of the mitigation measures.
A specialist Landscape Sub-Contractor
should be employed by the Contractor(s) for the implementation of landscape
construction works and subsequent maintenance operations during a 24 month
establishment period.
11.13
VISUAL IMPACT ASSESSMENT
In undertaking the visual assessment, the
following tasks were undertaken:
1.
Define the viewshed that would be
potentially impacted and map the areas of visual impact.
This section describes the viewshed of the LNG terminal which is based
on both the planning guidelines and the parameters of human vision. This section then utilises Geographical
Information System (GIS) software to determine areas that can potentially see
the LNG terminal. The GIS analysis is
based solely on topography and does not take into account the screening potential
of vegetation, which further reduces the actual viewshed. GIS analysis also maps the visibility of the
LNG terminal from roads and houses.
2.
Discuss atmospheric conditions. This section discusses the effects of
weather, particularly sea haze and rainfall.
3. Identify
and assess indicative viewpoints as a means of assessing the
visual impact on the broader landscape. This section describes a number of key Visually Sensitive Receiver (VSR) viewpoints around
the LNG terminal which were selected as representative of the range of views
from accessible locations within the viewshed. Several viewpoints will also
have photomontages or visual simulations prepared which show the existing
landscape and the landscape with the proposed LNG terminal site. The VSR’s will
be discussed to assess the visual compatibility and severity of any
obstructions or visual impacts.
4. Discuss
visual mitigation measures. This section examines measures incorporated into the design that will
reduce potential visual impacts such as, positioning of structures, planting of
vegetation and recommendations for material and finishes. These measures will
also help improve the overall amenity of the proposal. Residual impacts are
also discussed.
5. Assess
night lighting and glare impacts. This section examines the potential glare and night lighting impacts
associated with the proposal.
11.13.1
Viewshed
determination & areas of potential visual impact
The baseline for a visual assessment is an
understanding of the existing visual qualities within the region that can be
visually affected by a proposed development.
This area is referred to as the “viewshed” or sometimes the zone of visual influence (ZVI), or the
“visual envelope” All terms refer to the same thing, however this report will
use the term “viewshed”.
Defining an appropriate viewshed is the starting
point to understand the visual impacts of a development as the area of the
viewshed will vary depending on the nature and scale of the proposed
development. The larger a development
the greater the viewshed as it may be visually apparent from a greater
distance. Once the viewshed is
established, locations can be identified within the viewshed that are either
particularly sensitive or indicative of the visual impact for a number of
locations. In some circumstances,
viewpoints may be identified beyond the viewshed to recognise the visual impact
on locations of particularly high sensitivity.
As the viewer moves further away from the
LNG terminal, the visual impact decreases until the LNG terminal is no longer
visible. However, before the point of invisibility
is reached, the LNG terminal has reduced in scale such that it no longer has a
significant visual impact on the landscape.
In most landscapes, especially those which have some degree of human
intervention, the limit of the viewshed is defined as the point at which the
LNG terminal would have an insignificant effect on the view.
Recognising that the viewshed is not the
limit of visibility, but rather the extent to which an LNG terminal would have
an insignificant visual impact on the landscape, the extent of a viewshed
differs in the context of different landscapes.
A viewshed in a man-modified landscape is
different to a viewshed in a pristine landscape or landscapes where there are
no apparent signs of human influence. This is because in landscapes that appear
‘natural’ or pristine, a man made element such as an LNG terminal placed inside
the viewshed, can visually influence the landscape for as long as a viewer can
discern that newly introduced element. A
man made element in a pristine landscape irrevocably changes the landscape from
natural to man modified. Therefore,
viewsheds in pristine areas are extended to the limit of human visibility.
However in man modified landscapes, in
which there are many other existing built forms or modifications to the
landscape, the viewshed extends to that distance at which the LNG terminal
become a minor element or blends in with the existing landscape. The LNG terminal may still be visible beyond
this viewshed, however relative to the other surrounding structures it is
considered to have an insignificant visual impact.
Therefore the viewshed is the area that is
most likely to be visually impacted and once again, it is stressed that
particularly sensitive locations beyond the viewshed may still need to be
reviewed.
11.13.3
Viewshed
Determination
The visual impact of a development can be
quantified by reference to the degree of influence on a person’s field of
vision. The following diagrams
illustrate the typical parameters of human vision and are based on
anthropometric data (Human Dimension & Interior Space – A Source Book
of Design Reference Standards, Julius Panero and Martin Zelnik, The
Architectural Press Ltd. London, 1979).
This data provides a basis for assessing and
interpreting the impact of a development by comparing the extent to
which the development would intrude into the central field of vision (both
horizontally and vertically).
Horizontal
cone of view
The central field of vision for most
people covers an angle of between 50O and 60O. Within this angle, both eyes observe an
object simultaneously. This creates a
central field of greater magnitude than that possible by each eye separately.
This central field of vision is termed the 'binocular field' and within this
field images are sharp, depth perception occurs and colour discrimination is
possible.
These physical parameters are illustrated in Figure
11.23 opposite.
The visual impact of a development will
vary according to the proportion to which the development consumes the central
field of vision. Developments, which
take up less that 5% of the central binocular field, are usually insignificant
in most landscapes (5% of 50O = 2.5O).
In assessing the visual impact of the
proposed LNG terminal it is assumed that the largest horizontal component is
the entire terminal, which is approximately 400m wide.
Table 11.7 Visual Impact based on the Horizontal
Field of View
Horizontal
Field of View |
Impact |
Distance
from an observer to a 400m wide facility |
<2.5O
of view |
The
development will take up less than 5% of the central field of view. The development, unless particularly
conspicuous against the background, will not intrude significantly into the
view. The extent of the vertical
angle will also affect the visual impact. |
|
2.5O
– 30O of view |
Potentially
noticeable The development may be noticeable and
its degree of visual intrusion will depend greatly on its ability to blend in
with its surroundings and how far someone is from the terminal. |
700 m
–9,000m |
>30O
of view |
Potentially
visually dominant |
< 700m |
Vertical Field
of View
A similar analysis can be undertaken based
upon the vertical line of sight for human vision. As can be seen in Figure
11.24 opposite the typical line of sight is considered horizontal or 0
O. A person’s natural or normal
line of sight is normally a 10 O cone of view below the horizontal
and, if sitting, approximately 15 O.
Objects which take up 5% of this cone of view
(5% of 10 O = 0.5 O) would only take up a small
proportion of the vertical field of view, and are only visible when one focuses
on them directly. Objects that take up
such a small proportion of the vertical view cone are not dominant, nor do they
create a significant change to the existing environment when such short objects
are placed within a disturbed or man-modified landscape. They may however be
more noticeable in a pristine environment.
Table 11.8 below shows the relationship between impact and the
proportion that the development occupies within the vertical line of sight.
Table 11.8 Extent of Impact
Based on Distance to Tanks
Vertical
Line |
Impact |
Distance
from an observer to a 70m high facility |
< 0.5O |
Insignificant A thin line in the landscape. |
|
0.5O – 2.5O |
Potentially noticeable The degree of visual intrusion will depend on the
development’s ability to blend in with the surroundings. |
|
> 2.5O |
Visually evident Usually visible, however the
degree of visual intrusion will depend of the width of the object and its
placement within the landscape. |
|
An apparent discrepancy in the distance of
the viewshed occurs when analysing horizontal and vertical parameters
separately. Generally, the more
conservative figures form the basis for the visual impacts assessment. For the LNG terminal it is proposed to
extend the viewshed to 9,000m, although it could be argued that a lesser extent
would also be valid.
For the proposed LNG terminal it is proposed that the
distances in Table 11.9 are used for the Viewshed analysis.
Table 11.9 Viewshed and
Degrees of Visual Influence
Impact |
Distance
from an observer to the LNG terminal |
Negligible |
|
Potentially noticeable |
|
Visually
evident Usually visible, however the
degree of visual intrusion will depend on the degree to which the
development will blend into the landscape. |
|
It must be noted that the areas that
define the viewshed are a guide only. Simply because a viewer moves from 1260m
from the Terminal to 1270m, this will not result in the impact moving from
‘Visually Evident’ to ‘Potentially Noticeable’. Similarly just because a
viewpoint is within either of these zones does not indicate that a view within
the viewshed will experience an impact. Other factors such as terrain,
vegetation and human-made elements in the landscape can reduce or even remove
visual impacts within the viewshed.
11.13.4
Areas of potential visual impact
A GIS analysis can determined those areas that can
potentially be visually impacted by the development. The GIS analysis is based on topography only,
and shows those areas that would be screened by intervening hills etc. It does not account for intervening vegetation
or buildings, nor does it take into account small variations in topography,
such as road cuttings. Therefore it is a
conservative assessment of those areas that may be potentially visually
impacted by the LNG terminal and the storage tanks.
Figure 11.25 shows an analysis of those areas within a 9000m
viewshed that may be able to see any part of the proposed terminal. As the
storage tanks are the largest element, they will be visible from the greatest
distance and therefore the assessment is based on the height of the tanks (70m
PD) as it is a worst case scenario.
The viewshed is divided into two
zones. The zones of greatest potential
visual impact include those areas within 1,260m of the LNG terminal. This zone mainly lies over the water between
South Soko and
The second zone is between 1,260m to
9,000m from the terminal and is still primarily ocean as
Table 11.10 Analysis of the
areas that lie within the viewshed where part of the LNG tanks would be visible
This analysis shows that the main views to
the entire LNG terminal will be from the water.
Land based viewing locations are only available within 5.6% of the 368km2 viewshed.
A similar analysis showing those areas
from which the entire LNG tankwould be visible was conducted to identify those
areas of greatest potential impact. This
analysis showed far less impacts than in the preceding analysis since it
precludes areas that may be able to see a proportion but not all of the LNG
terminal.
Figure
11.26 shows those
areas that will be able to view any entire LNG tank down to ground level and
these areas are mainly from the ocean, to the east or west and from a very
small area to the south west of Lantau.
Table 11.11 Analysis of the
areas that lie within the viewshed where an entire LNG tank would be visible
This analysis demonstrates that the
majority of the area that may be potentially impacted lies on the ocean. Land based vantage points are very limited
and only represent 0.8% of the total viewshed of 364km2.
The next section of the visual analysis
will focus on viewpoint locations on land that lie within those areas that can
potentially view the proposed LNG terminal.
Those areas are generally restricted to coastlines, where intervening
topography cannot screen views, and along ridges in the higher areas that also
have views towards
11.13.5
Atmospheric
Factors which will affect visual impact
Many climatic conditions such as sea haze,
rainfall and other atmospheric conditions will alter the visibility of the LNG
terminal. The diminution of visual
clarity bought about by atmospheric conditions increases with distance. As the
proposed site is located approximately 5km from Lantau, the impact of sea haze
and other atmospheric conditions will reduce visibility of the terminal.
Sea haze is a
climatic condition along coastlines that can reduce visibility even on days
when the weather is clear. Wind which blows across the ocean can cause a sea
haze, limiting views to the site and the proposed LNG terminal from surrounding
areas. Sea haze is unlikely
to have much impact on the visibility of the LNG terminal when viewed from
close proximity, (i.e., less than 1.2km).
However, when the same features are viewed from greater distances within
the viewshed the effect of sea haze will greatly reduce visibility and any
potential visual impact. This was
evident in 2005 when ERM was first asked to assess
The effect that
rainfall has on visibility can be measured in two ways. Firstly the event of
falling rain reduces visibility as the water droplets obscure vision. This
varies greatly depending on the heaviness of the precipitation, but even light
rain greatly obscures distant objects.
Secondly, the event of rain, particularly
sustained rain periods, reduces visitor numbers. Therefore, the overall visual
impact is reduced on those days as less viewers will be visiting the area and
looking at the site.
|
Figure
11.27
Figure 11.27 shows that during the wetter
months, particularly from May through to September,
11.13.6
Assessment
Scenarios
Whilst the above section 11.13.5 describe
some of the climatic conditions that reduce the visibility of the LNG Terminal,
the following assessment will be based on a worst case scenario that assumes
perfectly clear viewing conditions. Mitigation measures will then be proposed
reduce these impacts.
11.13.7
Baseline
Visual Character
The area within the viewshed (The Soko
Islands and
·
The
steeply sloping peaks of
·
The
Ocean areas;
·
The
offshore islands (including the Sokos);
·
The
beach areas and;
·
The
man modified areas, which generally comprises of roads and villages of a
typical height of 3 storeys that are visible on
These
elements combine to create a visually appealing landscape.
11.13.8
Visually
Sensitive Receivers
To determine the likely Visually Sensitive
Receivers (VSR’s), a desktop assessment and detailed site assessment were
carried out. The most sensitive VSR’s were then identified and to encompass the
likely range of potentially affected people. The identified VSR’s are in the
following areas:
·
Lantau
Residents; including Villages such as Cheung Sha, Pui O and Tong Fuk;
·
Lantau
visitors; including the Lantau Trail and the Big Buddha;
·
Road
transiting visitors; these include the main roads
·
Visitors
on marine vessels; these include visitors on passing ferries as well as
recreational boats in the area.
All
of the VSR’s selected are from located to the north of the proposed development
as there are no populated area to the south of the site. There are some passing
ships, however these are generally outside HKSAR waters. It is expected that
any visual impacts from experienced from passing marine vessels to the south of
the site would be similar to those to the north.
11.13.9
VSR
Assessment
There are a number of factors that must be
considered when carrying out the visual impact assessment on the VSR’s.
VSR Sensitivity
The first set of criteria relate to the sensitivity of the VSR’s. They include:
·
Value
and quality of existing views;
·
Availability
and amenity of alternative views;
·
Type
and estimated number of receiver population;
·
Duration
of frequency of view; and
·
Degree
of visibility.
The views available to the identified VSRs
are rated in accordance with their sensitivity to change using high, medium or
low as defined below:
·
High
–
i.
The
nature of the viewer groups expect a high degree of control over their
immediate environment, (e.g., people residing in their homes); and
ii.
The viewer
groups in close proximity to the Project which may include viewers aboard
recreational marine vessels.
·
Medium -
i.
The
nature of the viewer groups expect a medium degree of control over their
immediate environment, (e.g. hikers on a walking trail);
ii.
People
in transit (e.g., drivers and passengers in vehicles);
·
Low
–
i.
The
nature of the viewer groups does not expect a high degree of control over their
immediate environment, (e.g. people at their place of employment or temporarily
in attendance at the VSR location).
Magnitude
of Change
This set of criteria is related to the
specific details of the proposal; how it relates to the existing landscape and
the visible magnitude of change it will cause.
The criteria to be assessed are:
· Compatibility of the project with the surrounding landscape;
·
Scale
of the development;
·
Reversibility
of change;
·
Viewing
distance;
·
Potential
blockage of view; and
·
Duration
of impact under construction and operation phases.
The magnitude of change to a view is rated
as large, intermediate, small or negligible, as follows:
·
Large
- major change in view.
·
Intermediate
- moderate change in
view.
·
Small
- minor change in view.
·
Negligible
- no discernible change
in view.
The degree of visual impact or
significance threshold is rated in a similar fashion to the landscape impact
(significant, moderate, slight and negligible). The impacts may be beneficial
or adverse, however with this project, it is assumed that all visual impacts
will be adverse. Therefore, the visual impact is a product of the magnitude and
degree of change to the existing baseline conditions, the landscape context and
the sensitivities of VSR’s. The
significance threshold of visual impact is rated for the construction phase and
for Day 1 and Year 10 of the operation phase as described in Table 11.27
11.13.10
Photomontage
Preparation
The visual assessments are also partly
based on photomontages, which show the view with and without the terminal.
Photographs that form the base of the photomontages are taken with a
70mm Nikon lens on a 35mm film single lens reflex camera. A 70mm lens has a picture angle of 34.34O
and a horizontal angle of view of 28.84O. (http://www.europepress.com/lenses/nikon_standard_zoom.htm). When two photographs taken with a 70mm lens
are overlapped approximately 1/3, the resultant image has a picture angle of
approximately 50O, which is very similar to the central cone of view
of human vision.
Figure 11.28 Two
photographs overlapped 1/3 to create an image approximately the same as the
central cone of view of human vision
As discussed above, the central field of
human vision is approximately 50O - 60O. Two photographs taken with a 70mm lens with approximately
1/3 overlap best show this static view.
A 50mm lens (picture angle 48.45O, horizontal field of view
39.59O) is often used for visual assessments as it is called a
‘normal lens’ because it produces roughly the same picture angle as the human
eye (about 50°). However, the 70mm lens
slightly increases the apparent size of objects in the middle and far distance
and hence increases the apparent size of the terminal in the photomontages. For
this reason this 1/3 overlap technique has been adopted for the photomontages
preparation within this report.
11.13.11
Visual
Impact Assessment from Visually Sensitive Receivers (VSR)
Figure 11.29 shows the indicative viewpoints from publicly accessible
locations, which have been selected for analysis.
As mentioned previously the land based
VSR’s are generally along the coastline, where intervening topography cannot
screen views, and along ridges in the higher areas that also have views towards
As well as these land based viewpoints,
other locations have been selected as sea based VSR’s that can be used to
represent the view from shipping / ferry lanes and therefore ocean based views.
These viewpoints have been selected to represent the range of views from
publicly accessible locations. The
selected viewpoints are representative of four different viewing types, which
are described below.
Views from
Six viewpoints have been selected to represent the views from
VSR3
VSR4
VSR6
Pui O Beach
VSR7
Big Buddha Statue
VSR12
VSR15
Fan Lau
Photomontages have been prepared for all viewpoints with
the exception of VSR12 and VSR15, which have had computer simulations prepared
of the potential view. The computer simulations were created as clear photos of
the site from these viewpoints could not be obtained during the site visits.
These simulations give a ‘worst case scenario’ as they do not account for local
atmospheric conditions.
Views from Villages
Four viewpoints have been selected to represent the views from
Villages. These are:
VSR1 Tai Long Wan Tsuen
VSR5
Cheung Sha Ha Tsuen
VSR13
Chi Ma Wan
VSR 14 Shek Kwu
Chau (Visual Simulation)
Views from Road Network
The local road network provides limited
opportunities to view the LNG terminal from publicly accessible locations. Indicative viewpoints have been selected from
the surrounding road network and have been chosen at locations where views are
uninterrupted by roadside vegetation / road cuttings etc. The two viewpoints were chosen at the
southern end of Lantau and on an elevated location towards the centre of
VSR2
– View from Shek Mun Sha
VSR8 – View from
Views from the Ocean
The ocean provides opportunities to easily
view
11.13.12
VSR1
– View from Tai Long Wan Tsuen
Tai Long Wan Tsuen is a small village on
the coastline approximately 6.3km north west of the proposed Terminal. This
location is also popular with weekend visitors, for the purposes of the
assessment, both types of VSR’s are given the same sensitivity.
|
Figure 11.29 VSR1
Tai Long Wan Tsuen
Table
11.12 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Medium |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low-medium |
Sensitivity/Quality of VSR |
High |
The duration
and frequency of views is short and variable as at this distance there is a
high availability of other views and the terminal will occupy a very small part
of the field of view.
Table 11.12a Magnitude
of Change
Table 11.12b Significance Threshold during
Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.12c Significance Threshold during
Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 1 shows that the LNG
terminal may be visible on clear days. This
VSR has a high degree of sensitivity however, given the long distance from this
viewpoint and the high availability of other views, and the partial screening
provided by other
11.13.13
VSR2
– View from Shek Mun Sha
Shek Mun Sha lies at the southern end of Lantau and approximately 5km to
the north of the proposed LNG terminal. It is considered the closest land based
potential viewing point. This VSR is classified as road users.
|
Figure 11.32 VSR2
Shek Mun Sha
Table
11.13 Sensitivity / Quality of VSR
Table
11.13a Magnitude of Change
Table 11.13b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.13c Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage
2 shows that the LNG terminal will only be discernable on the clearest of
days. The majority of the proposed LNG
terminal is also partly hidden by North Soko and the northern ridgeline of
11.13.14
VSR3
– View from
The
|
Figure 11.34 VSR3
Table
11.14 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Low - Medium |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
Table 11.14a Magnitude
of Change
Table 11.14b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.14c Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 3 shows that views
from this location are screened by both the Lantau headland and
VSR4 – View from
This viewpoint also lies to the NNE of
|
Figure 11.36 VSR4
– View from
Table 11.15 Sensitivity / Quality of VSR
Table
11.15a Magnitude of Change
Table
11.15b Significance Threshold during
Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table
11.15c Significance Threshold during
Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 4
on the following page shows that views from this location are partly screened
by the Lantau headland and North Soko, however a tiny
section of a tank may be visible above
The above tables are a guide only and show
the significance threshold as Moderate. However since a tiny fragment of the
LNG terminal is only partly visible and the distance is large, the visual
impact will be Slight.
11.13.15
VSR5
– View from Cheung Sha Ha Tsuen
Cheung Sha Ha Tsuen is a residential VSR and lies to the NNE of
|
|
Figure 11.38 VSR5 - Cheung Sha Ha Tsuen
Table 11.16 Sensitivity
/ Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Small |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
The duration
and frequency of views is short and variable as at this distance there is a
high availability of other views and the terminal will occupy a very small part
of the field of view.
Table 11.16a Magnitude of Change
Table 11.16b Significance Threshold
during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.16c Significance Threshold
during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 5
shows views from this location are screened by the Lantau headland and
11.13.16
VSR6
– View from Pui O Beach
Pui O Beach is on the coast approximately
10.5km to the north east of the proposed LNG terminal. At this distance the beach is outside of the
viewshed, however since it is an important weekend tourist destination it was
included to illustrate the impact of the LNG terminal may have at this
distance. This VSR is
classified as a scenic lookout due to its popularity with tourists. The site is
also a residential area so for the purposes of the assessment, both types of
VSR’s are given the same sensitivity.
|
Figure 11.40 VSR6 Pui O Beach
Table 11.17 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Medium |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
Table 11.17a Magnitude of Change
Table 11.17b Significance Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.17c Significance Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage
6 on the following page shows that the LNG terminal will not be discernable
on any but the clearest of days. The
proposed Terminal is also partly hidden by North Soko and the northern
ridgeline of
11.13.17
VSR7
– View from Big Buddha Statue
The Big Buddha Statue is located on a ridgeline in Lantau approximately
9.5km north of the LNG terminal.
Although it is theoretically beyond the viewshed, its importance as a
tourism and cultural destination warranted its consideration within the visual
assessment. It is also one of the few
high points from which views to the LNG terminal are possible. This VSR is
classified as a scenic lookout due to its popularity with tourists.
|
Figure 11.42 VSR7
Big Buddha Statue
Table 11.18 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
High |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
Table 11.18a Magnitude of Change
Table 11.18b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.18c Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
This VSR is
possibly the most sensitive given its cultural value and the high number of
tourists that visit the site.
Photomontage 7 on the
following page shows that views from this location are partly screened by the
Lantau headland and
11.13.18
VSR8
– View from
This VSR is assessed as part of the road
network.
|
Figure
Table
11.19 Sensitivity / Quality of VSR
Table 11.19a Magnitude
of Change
Table 11.19b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.19c Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 8 on the following page
shows that the above factors along with the large distance to the site indicate
that from this VSR the visual impact will be negligible.
11.13.19
VSR9
– View from
The Macau Ferry route runs along the
northern edge of
|
Figure
Table
11.20 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
High |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short |
Degree of visibility |
Medium - High |
Sensitivity/Quality of VSR |
Medium |
Table 11.20a Magnitude of Change
Table 11.20b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.20c Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage
9 on the following page shows that the Terminal will be visible. Views will
be very short however, and will depend on the seating arrangement of the
viewer. The visual impact from this location will therefore be more likely to
be Slight-Moderate.
11.13.20
VSR10
– View from
|
Figure 11.48 VSR10
Table
11.21 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Low |
Availability and amenity of alternative
views |
Medium |
Duration and frequency of views to
facility |
Medium |
Degree of visibility |
Medium |
Sensitivity/Quality of VSR |
High |
Table 11.21a Magnitude
of Change
Table 11.21b Significance
Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.21b Significance
Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 10 on the following page
shows that some components of the LNG terminal will be visible. The sites position is such that the eastern
11.13.21
VSR11
– View from Off
This view is taken 417m west of the proposed facility which is the closest
ocean viewing point to the proposed LNG terminal. This site was selected as it
is a view typically experienced by visitors aboard vessels travelling to the
|
Figure 11.50 VSR11 Off
Table 11.22 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Low |
Availability and amenity of alternative
views |
Low |
Duration and frequency of views to
facility |
Long and frequent |
Degree of visibility |
High |
Sensitivity/Quality of VSR |
High |
Table 11.22a Magnitude of Change
Table 11.22b Significance Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.22c Significance Threshold during Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 11 on the following page
shows that the LNG terminal will be clearly visible, and the impact will be Significant.
However as discussed above there are low visitor numbers to this
location who will experience this impact.
11.13.22
VSR12
– Visual Simulation from
|
Figure 11.52 VSR12
Table
11.23 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Med |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
Table 11.23a Magnitude
of Change
Table
11.23b Significance Threshold
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table
11.23c Significance Threshold
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
This VSR has a high degree of
sensitivity based on the medium level of user numbers. Whilst the table shows a
Moderate impact, given that tiny
parts of the terminal may be visible, the impact is assessed as Slight.
11.13.23
VSR13
– Visual Simulation from Chi Ma Wan
This VSR is residential and is taken on
the edge of the Chi Ma Wan Peninsular.
It is approximately 9.2km to the north east of the proposed LNG
terminal, and it is just on the edge of the 9km viewshed. Atmospheric conditions, when visiting this
location, did not permit views to
|
Figure 11.54 VSR13
Chi Ma Wan
Table
11.24 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Low |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Low |
Sensitivity/Quality of VSR |
High |
The duration and
frequency of views is short and variable as at this distance there is a high
availability of other views and the terminal will occupy a very small part of
the field of view.
Table 11.24a Magnitude
of Change
Table 11.24b Significance Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table 11.24c Significance Threshold during Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 13 on the following page
shows that the LNG terminal will only be discernable on the clearest of days.
The proposed Terminal is also partly hidden by North Soko and the northern
ridgeline of
11.13.24
VSR14
Visual Simulation from Shek Kwu Chau
This is a residential VSR and is 8.2km
from the site. As this location is on the outer limits of the viewshed for the
project, a visual simulation has been prepared.
|
Figure 11.56 VSR14 Shek Kwu Chau
Table 11.25 Sensitivity
/ Quality of VSR
Value
and quality of view |
High |
Visitor
numbers |
Low |
Availability
and amenity of alternative views |
High |
Duration
and frequency of views to facility |
Short and Variable |
Degree
of visibility |
Low |
Sensitivity/Quality
of VSR |
High |
The duration and frequency of views is short and
variable as at this distance there is a high availability of other views and the
terminal will occupy a very small part of the field of view.
Table 11.25a Magnitude of Change
Table 11.25b Significance Threshold during
Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude
of Change |
Large |
Moderate Impact |
Moderate
-Significant impact |
Significant
impact |
|
Intermediate |
Slight–
Moderate impact |
Moderate Impact |
Moderate –
Significant impact |
Adverse |
|
Small |
Slight impact |
Slight –
Moderate impact |
Moderate impact |
||
Negligible |
Negligible
impact |
Negligible
impact |
Negligible
impact |
Table 11.25c Significance Threshold during
Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude
of Change |
Large |
Moderate Impact |
Moderate
-Significant impact |
Significant
impact |
|
Intermediate |
Slight–
Moderate impact |
Moderate Impact |
Moderate –
Significant impact |
Adverse |
|
Small |
Slight impact |
Slight –
Moderate impact |
Moderate impact |
||
Negligible |
Negligible
impact |
Negligible
impact |
Negligible
impact |
From
this viewpoint, the terminal may be visible on very clear days. Therefore due
to the long distance, the visual impact will be Negligible.
11.13.25
VSR15
– Visual Simulation from Fan Lau
Fan Lau is classified as a Country Park/Scenic Lookout and is located on
Lantau approximately 7.1km NW of the LNG terminal. This photomontages has been created using a
computer simulation.
|
Figure 11.58 VSR15 Fan Lau
Table 11.26 Sensitivity / Quality of VSR
Value and quality of view |
High |
Visitor numbers |
Low |
Availability and amenity of alternative
views |
High |
Duration and frequency of views to
facility |
Short and Variable |
Degree of visibility |
Medium |
Sensitivity/Quality of VSR |
High |
Table 11.26a Magnitude of Change
Table
11.26b Significance Threshold during
Construction
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Table
11.26b Significance Threshold during
Operation
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
Photomontage 15 on the following page
shows that given the sites location, this VSR has a high degree of
sensitivity. Whilst the above
significance threshold shows a Moderate impact,
the photomontage shows that the impact will be small, therefore the visual
impact will be as Slight-Moderate.
11.14
Visual Mitigation Measures
The final detailed Visual Mitigation
Measures will be the subject of a Landscape Master Plan that will be submitted
for approval to the relevant Authority prior to construction.
The above analysis has shown that 6 of the
15 VSR’s selected will experience a Negligible
visual impact. However for those VSR’s
that are expected to experience an impact, the following Visual Mitigation
Measures (VMM’s) are proposed to reduce these impacts and provide a potential
enhancement of visual quality.
VMM 1 Design of Structures
Where possible, built structures will be
utilise appropriate designs to complement the surrounding landscape. Materials and finishes will also be
considered during detailed design.
VMM 2 Colours
Colours for the terminal can be used to
complement the surrounding area. Lighter
colours such as shades of light grey and light brown may be utilised where
technically feasible to reduce the visibility of the terminal.
VMM 3 Plantings
In addition to the landscape mitigation
plantings proposed in Section 11.10
of this report, appropriate new plantings will be installed as appropriate to
help integrate the new structures into the surrounding landscape.
11.14.1
Alternative
Site Layouts
Section
2 of this EIA discusses
the layout changes to the South Soko Terminal that have been undertaken in
order to provide a comparison and therefore reduce the visibility of the major
visible elements.
11.14.2
Mitigated
Visual Impacts
Table
11.27 predicts the
potential mitigated visual impacts during construction and operation. It also predicts the mitigated visual impacts
during construction, day 1 and year 10 of operation.
Table 11.27 Mitigated
Visual Impacts
11.15
Summary of Visual Impacts
Of the 15 VSR’s analysed in this study, 1
VSR group will experience a significant impact, 1 VSR group will experience a
moderate-significant impact, 1 VSR group will experience a moderate impact, 2
VSR’s will have a slight-moderate impact 4 VSR’s will experience a slight
impact and 6 VSR’s will experience a negligible impact.
11.16
Night Lighting and Glare
The above analysis examined the visual
impacts of the proposal during daylight hours.
Although distance between land based VSR’s and the project is greater
than 5km, lighting associated with the terminal may create a night time visual
impact. While detailed lighting plans
and specifications are not available at this preliminary design stage, the
following lighting practices will be considered during the detailed design
stage.
·
Security lighting of the site boundary. These are generally spot lights mounted on the external fencing
and will have the beams directed towards the ground.
·
General access lighting. This will provide safe access and
operational lighting conditions around the site. Baffles will be fitted where possible to
reducing upward light spill.
·
Emergency lighting. These lights will provide safe levels of
illumination to facilitate evacuations or repairs in emergency situations. The use of these lights will be infrequent.
·
Aviation lighting. It is anticipated that some lighting will
be required at the tops of the storage tanks and vent stacks to provide
aviation safety. These lights are typically flashing coloured lights that are
visible from large distances, however they will not have a large contribution
to the overall ambient light levels of the site.
11.16.1
Distances
between Source lighting and VSR’s.
The distances between the land based VSR’s
and the project are greater than 5 kms. While the visibility of individual
light fittings from these distances is low, the general night time glow and
aviation lighting on the tops of the tanks will be visible. It should also be noted that some previously
discussed climatic conditions such as rain events and sea haze, also apply to
light visibility and are expected to reduce night time visibility. However, occasionally, cloud cover can
increase the visibility of night lighting in the form of reflected light. This will occur when a heavy cover of low
cloud sits above the site and consequently reflects the light from beneath.
11.16.2
The
Surrounding Ambient Light of the VSR
Night lighting from a source is more
visible when one is observing in darkness.
As the surrounding ambient light increases, the visibility of distant
objects reduces. This includes viewers
in cars, near street lights, or inside illuminated homes. Due to its remote location, viewers looking
towards the terminal site in darkness are expected to be very low in number.
11.16.3
The
Surrounding Lighting Conditions of the Source.
The main form of lighting in the area
surrounding the site is from passing vessels, the existing lighting of the Low
Level Nuclear Waste Storage facilities located on
11.16.4
Visual
impact of night time lighting
The above analysis indicates that
potential night time lighting impacts will be low. This is due to the
following:
·
The
lighting for the proposal will generally be provided by spot lights angled
downwards and while this will result in an illuminated glow from the site, and
the overall impact is expected to be low.
·
The
large distances between the site and the majority of VSR’s and associated
atmospheric conditions will reduce any lighting impacts;
·
Most
views towards the site will occur in areas with existing ambient lighting
levels, therefore reducing the visibility of distant lights;
·
A
variety of marine vessels with night lighting are commonly in the vicinity and
·
All
of the major light sources will be pointed inward and downwards to reduce light
spill.
11.17
Existing Landscape Character
To analyze the effects on the
overall pattern of landscape elements that give rise to landscape character,
one must first describe the existing landscape character of the site and of the
surrounding areas that fall within the viewshed.
11.17.1
Landscape
Value Mapping
The study ‘Landscape Value
Mapping of Hong Kong’[2] recognized the value in
these island landscapes:
“The remoteness and outlying locations mean that in some cases (notably
at Tung Ping Chau) they form unique landscapes, rich in nature conservation
interests.”
“The landscape is in poor condition when the pattern of natural
resources which make up the landscape is highly degraded. This means that there
will be almost total disturbance to natural terrain, natural features and water
courses with little or no vegetation.”
The ‘Landscape Value Mapping
of Hong Kong’ also found that South Soko generally has a high terrestrial
Landscape Character Area value in good condition with a
‘..reasonably intact pattern of topography, built and
natural features.’
The study also noted that
major development would
‘..likely have a significant effect on the character
of the landscape’
However, while many of the
islands around Hong Kong are undoubtedly in good condition and more sensitive
to development, as noted previously South Soko and
The mapping within the
‘Landscape Value Mapping of Hong Kong’ does not differentiate between the
lesser sensitivity inherent within man modified island landscapes such as those
of
11.17.2
Topography
The topography of
The island has four main
rises in the landform, with two at the northern headland and two to the
south. A ridge line runs from northeast
to southwest; with the highest peak approximately 150m in height to the south,
followed by an 85m high hill at the headland.
|
Figure 11.60 Existing topography
The figure above illustrates
the view looking to the ridge line on the south from the northern ridgeline
across the former detention centre site.
11.17.3
Landscape
Character Areas
The Landscape Value Mapping
of Hong Kong describes the general Landscape Character Type of South Soko as
‘Coastal Waters Landscape’ and it is given a high Landscape value. There are
four Landscape Character Areas within the area and they are:
LCA 1 –
LCA 2 – Abandoned
Institutional Landscape
LCA 3 – Offshore Water
Landscape
LCA 4 – Inshore Water
Landscape
LCA 1
This LCA is typical of the
outlying Islands found in
Figure 11.61
LCA
2 Abandoned Institutional Landscape
This area comprises the
former Vietnamese Detention Centre. The area is characterized by large expanses
of concrete in a state of disrepair and large cut-slopes to the north and south
of the main concrete platform.
Figure 11.62 Abandoned Institutional Landscape
LCA 3 Offshore
Water Landscape
The Offshore Waters are
characterized by large open expanses of ocean with scattered off shore islands.
There are also passing marine vessels, mostly container ships. These areas
experience high degree of remoteness.
Figure 11.63 Offshore Waters Landscape
LCA 4 Inshore
Water Landscape
The Inshore Waters experience
a greater interaction with LCA 1 as the
Figure 11.64 Inshore Waters Landscape
11.17.4
Factors
Affecting the Sensitivity of the LCA’s
To assess the impact the LNG
terminal will have on the Landscape Character of South Soko, it is important to
establish how sensitive the landscape is to change. Generally, the more natural
the landscape character, the higher the sensitivity. The following factors will have an affect on
the sensitivity of the Landscape Character Areas
·
The general landscape quality and landscape elements of the area;
·
The importance and rarity of the area or special features;
·
The ability of the LCA to accommodate change;
·
Significance of the change in a local and regional context; and
·
The maturity of the landscape.
Table 11.28 Landscape Character Sensitivity Matrix
11.17.5
Factors
Affecting The Magnitude of Change to the LCA’s
To establish the degree of impact on the
LCA’s, the same criteria for assessing the magnitude of change as described
previously was used;
·
The projects compatibility with the surrounding landscape;
·
Duration of the impacts under construction and operation
·
The scale of the development (relative to the baseline conditions of the
LCA); and
·
The reversibility of change.
Table 11.29 Landscape Character Magnitude of Change
Matrix
11.18
Landscape Character Impacts
LCA 1 –
Table
11.30 Impacts on
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
The table above shows that
for LCA1, the proposal will have a Significant
adverse impact on the landscape character of this LCA.
LCA 2 – Abandoned Institutional Landscape
Table 11.31 Impacts on Abandoned
Institutional Landscape Matrix
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
The table above shows that
for LCA 2, there will be a Slight-Moderate adverse impact on the
landscape character of the Abandoned Institutional Landscape.
LCA 3 – Offshore Waters Landscape
Table 11.32 Impacts on Offshore Waters Landscape Matrix
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
The table above shows that
for LCA 3, there will be a Moderate impact
on the existing landscape character of the Offshore Waters Landscape.
LCA 4 Inshore Water Landscape
Table 11.33 Impacts on Inshore Water Landscape Matrix
|
Sensitivity / Quality |
Beneficial |
|||
Low |
Medium |
High |
|||
Magnitude of Change |
Large |
Moderate Impact |
Moderate -Significant impact |
Significant impact |
|
Intermediate |
Slight– Moderate impact |
Moderate Impact |
Moderate – Significant impact |
Adverse |
|
Small |
Slight impact |
Slight – Moderate impact |
Moderate impact |
||
Negligible |
Negligible impact |
Negligible impact |
Negligible impact |
The above table shows that
there will be a Moderate-Significant
impact on the Inshore Waters Landscape
11.18.1
Impacts
on ‘Remoteness’
A factor that requires some
consideration is the change to the feeling of ‘remoteness’ of the
11.19
Landscape Character Mitigation Measures
All of the Landscape
Mitigation Measures proposed in section 11.11 along with the Visual
Mitigation Measures proposed in section 11.14 will also mitigate the
impacts on the LCA’s. The
final detailed Landscape and Visual Mitigation Measures will be the subject of
a Landscape Master Plan that will be submitted for approval to the relevant
Authority prior to construction.
A summary of the
effectiveness of these measures in reducing the LCA impacts is provided below:
LMM 1 – Cultivation of areas compacted
during construction. This
will assist in the re-vegetation of these areas. This will contribute to
establishing more native plants that are found in the Island Landscape LCA
LMM 2 – Soil stabilisation and planting. The addition of vegetation on the cut
slopes will reduce the visibility of the slopes and therefore assist in the
ability of the LCA’s to accommodate the project
LMM 3 – Tree and shrub planting. This will contribute to the vegetation
common to the Island Landscape LCA.
LMM4 – Utilising natural rock for
reclamation. This will
help integrate the edge of the reclamation into the natural rocky edge of the
island which will reduce impacts to LCA’s 1,3 and 4.
LMM5 – Natural
accretion of sand. This will help integrate a portion of the
edge of the reclamation into the sandy beaches of the island which will reduce
impacts to LCA’s 1,3 and 4.
LMM6
–
Cut Stabilisation. Where the use of shot-crete is un-avoidable, the
addition of pigments will help to reduce the visibility of the cut-slopes.
LMM7 – Bench Plantings. The addition of vegetation on the cut
slopes will reduce the visibility of the slopes and therefore assist in the
ability of the LCA’s to accommodate the project
LMM8 - Relocation. The relocation of the Tin Hau
temple will ensure that this structure of value will remain useable.
LMM9 – Landscape Berm/Planter The berm/planter and associated plantings
will reduce the visibility of the tanks and the scale of the terminal.
LMM10 – New Access The new pier will allow visitors to
explore the southern end of the island without the need to move through the
terminal.
LMM11 – Early Planting Works. This will help to reduce impacts as
early as possible.
LMM12 – Site hoardings to be compatible
with the surrounding environment. This will help to reduce the impacts of the terminal during
construction.
VMM 1 Design of Structures – The sensitive design of structures will
help to complement LCA1 Island Landscape.
VMM 2 Colours – The selection of suitable complementary
colour will help the LCA’s accommodate the terminal.
VMM 3 Plantings - Plantings will reduce the visibility of
the tanks and the scale of the terminal.
Design Measures – Reducing the tank height from 70mPD to 61m
PD will reduce the scale of the terminal.
Figure
11.51a shows the
conceptual view of the terminal with the addition of the Landscape Berm/Planter
and the reduced tank height of 70mPD to 61mPD.
11.19.1
Avoidance
The refinements discussed in section
11.2 of this report show how the potential impacts on the Landscape
Character of South Soko have been mitigated. Figures 11.20a and 11.20b show the reduction in scale of
the terminal from its pre-EIA layout to the EIA layout. The impacts on the
Landscape Character have been reduced by:
·
The reduction of the extent of the reclamation;
·
The clustering of the tanks closer together;
·
The positioning of the tanks behind the hill at the northern end of
·
The overall reduction in the scale of the terminal.
Table Table 11.34 LCA Mitigated Landscape Character
Impacts
Table 11.34 above shows that when all Landscape
and Visual Mitigation Measures are in place, along with the mitigating
conditions of the improved design of the terminal, the impacts on the LCA’s
will reduce one order if significance threshold.
At present there are no committed projects that could
have cumulative impacts with the construction of the terminal at
11.21
Evaluation of Residual Environmental Impacts
Taking into consideration the baseline
landscape, landscape character and visual conditions and along with the
mitigation measures, residual impacts have been identified occurring as a
result of the proposed terminal
Section
4.4.3 of the Technical
Memorandum identifies a number of factors that are to be considered when
considering residual impacts. These are
outlined in Table 11.34. For the
purposes of the evaluation, an overall assessment of the impacts on the LR’s,
LCA’s and VSR’s has been carried out. It
must also be noted that this assessment is based on the overall impacts.
Table 11.35 Residual Impact Analysis
Evaluation Criteria |
Residual Impact
Type |
||
Landscape
Resources (LR’s) |
Landscape
Character Areas (LCA’s) |
Visual
Impacts (VSR’s) |
|
Effects on
Public health and health of biota or risk to life |
No effects applicable to LR’s |
No effects applicable to LCA’s |
No effects applicable to VSR’s |
The magnitude of the adverse
environmental impacts |
Overall the impacts on the LR’s
will be small. |
Overall there will be slight to moderate-significant
impacts on the LCA’s. |
Overall the impacts on the VSR’s
will be moderate with some significant impacts in close proximity to the
terminal. |
The geographic extent of the
adverse environmental impacts |
The impacts on the LR’s will be
confined to the works area of |
The impacts on Landscape Character
will be confined to the |
The larger impacts in the VSR’s
will be largely confined to areas in close proximity to |
The duration and
frequency of the adverse environmental impacts |
The impacts on the LR’s will be for
approximately 4 years during terminal construction. |
The impacts on LCA’s will be
continuous for as long as the project exists. |
The visual impacts will be
continuous for as long as the project exists. |
The likely
size of the community or the environment that may be affected by the adverse
impacts |
The area of the affected
environment will be the works area of |
The impacts on Landscape Character will
be confined to the |
Visitors to or near The Soko
Islands |
The degree to
which the adverse environmental impacts are reversible or irreversible |
During operation the impacts on the
LR’s are irreversible. Construction phase impacts can be mitigated through
landscaping measures. |
During operation the impacts on the
LCA’s are irreversible. Construction phase impacts can be mitigated to the
full extent practicable. |
During operation the impacts on the
VSR’s are irreversible. |
International
and regional importance |
The adverse impacts on the LR’s do
not affect an issue of international or regional concern. |
The landscape character of the |
The visual quality of the |
Both the
likelihood and degree of uncertainty of adverse environmental impacts |
The detailed assessment shows there
are no uncertainties regarding the impacts on the LR’s |
The detailed assessment shows there
are no uncertainties regarding the impacts on the LCA’s |
The detailed assessment shows there
are no uncertainties regarding the impacts on the VSR’s |
Table 11.35 above shows that the impacts on the Landscape
Resources will have no effect on public health and are confined to the works
area at
The impacts on the LCA’s will have no
effect on public health and they are considered overall to be moderate in
magnitude. However the impacts will be confined to areas in close proximity to
The impacts on the VSR’s will have no
effect on public health, they will be generally moderate in magnitude and will
mostly be confined to areas in close proximity to
·
Compensatory
planting of indigenous species will mitigate the effects of the development on many
of the Landscape Resources. The effects on the rocky shoreline can be partially
mitigated by the use of natural rock in the reclamation areas and the sandy
beach will be partially mitigated by the natural accretion of sand. The overall
residual impacts on the Landscape Resources are assessed as slight.
·
Visually
the main land based viewing locations are located on the periphery of the
viewshed from which the proposed development will not cause a significant
change to the view. Most land based
viewing locations particularly those to the north and east of the
·
Potential
night time glow and visibility of maritime and aviation lighting may be visible
on clear nights from land based and ocean based viewing locations, however
given that lighting already exists on North Soko, the other night lighting
sources as well as lighting associated with shipping and maritime uses, the
additional night lighting from the proposed LNG terminal is considered
acceptable.
·
The
residual impacts on the existing Landscape Character of South Soko will vary
from slight to moderate-significant. The overall impact on the
LCA’s is assessed as moderate.
According to the Technical
Memorandum on the Environmental Impact Assessment Process (EIAO-TM) the Landscape and Visual
Impacts are considered acceptable with
mitigation.
[2] Landscape Value Mapping of Hong Kong, Executive
Summary, Planning Department, Government of Hong Kong SAR, July 2005.