Construction of Approach
Channel & Turning Basins for the South Soko Location
C1
Construction of
In order to reduce dredging, it is necessary to construct the jetty for berthing of LNG carriers in water as deep as –15mPD and as close as possible to marine fairways where the deep water exists. The jetty will be located in an area free from marine services and traffic. In all site layouts considered, the dredging of the turning circle and approach channels are undertaken to approximately –15mPD which will require significant maintenance dredging as well as affecting tidal flows in the vicinity.
The available investigation information indicates that the dredging is likely to be wholly within the soft Marine Deposit layer, which will require side slopes of about 1:4 for long-term stability. It has been assumed that the dredged sediment is not significantly contaminated and can be dumped at an uncontaminated mud disposal ground. Rock excavation for the construction of approach channel and turning basin should be avoided in order to reduce impacts on the seabed and surrounding water environment.
In order to assess the engineering implications of the marine dredging at each of the sites the following assessment parameters have been used: -
· Total length of approach channel & turning basin.
· Volume of dredging.
· Rock excavation in dredged zone.
· Impact on existing utilities.
· Siltation & maintenance.
C2
Total Length of Approach
Channel and
C2.1 Option 1 – Base Case
The position of the jetty head results in a significant amount of dredging to give access to the jetty from the navigation channel. The total length of the approach channel and turning basin is estimated to be 6.3km from the deep water with a seabed level of approximately -15mPD.
c2.2 Option 2 – Full Reclamation
The route of the approach channel and turning basin and the location of the jetty of Option 2 are the same as that of Option 1.
C2.3 Option 3 – SE Jetty
The location of the jetty at
the southeast corner of
C3 Volume of Dredging
C3.1 Option 1 – Base Case
Dredging is required for both the approach channel and the turning basin. The total volume of dredging and subsequent rock excavation is estimated to be 3.36 x 106m³.
C3.2 Option 2 – Full Reclamation
The approach channels and turning basins are the same as Option 1.
C3.3 Option 3 – SE Jetty
The total volume of dredging and subsequent rock excavation of the shorter approach channel and turning basin is estimated to be 1.07 x 106m³.
C4 Rock Excavation in Dredged Zone
The quantity of the rock required to be excavated is estimated at about 0.03 x 106 m3 for all options.
C5 Impact on Existing Utilities
Dredging of the approach channel and turning basin is not likely to encounter any existing submarine cables.
C6 Siltation & Maintenance
Siltation study recently carried out suggests that siltation
rate in the vicinity of
C7
Summary for the
A summary of the parameter values and relative scores derived from the engineering assessment for the construction of the approach channel and turning basin is given in Table C1 below.
Table C1 - Summary for Approach Channel
and
Parameter |
Option 1 |
Option 2 |
Option 3 |
Total length of approach channel + turning basin (km) |
RS = 3 (6.3) |
RS = 3 (6.3) |
RS = 5 (2.2) |
Volume of dredging |
RS = 3 (3.36) |
RS = 3 (3.36) |
RS = 5 (1.07) |
Rock excavation in dredged zone (106m3) |
RS = 3 (0.03) |
RS = 3 (0.03) |
RS = 3 (0.03) |
Impact on existing utilities |
RS = 3 |
RS = 3 |
RS = 3 |
Siltation and
maintenance dredging (cm/yr) |
RS = 3 (0.5) |
RS = 3 (0.5) |
RS = 3 (0.5) |
RS = Relative Score
C8
Scoring for the
Each of the parameters summarised above in Table C1 have been scored in accordance with the procedure described in Section 2.1.3. The results are shown below in Table C2. The table also shows the total score for each site derived using the relative weightings given in Table 2.5.
Table C2 – Scoring for Each Layout
Option for the Approach Channel and
Parameter |
Weight |
Option 1 |
Option 2 |
Option 3 |
|||
Score |
WS |
Score |
WS |
Score |
WS |
||
Total length of Approach
Channel + turning basin |
0.2 |
3 |
0.60 |
3 |
0.60 |
5 |
1.00 |
Volume of dredging |
0.35 |
3 |
1.05 |
3 |
1.05 |
5 |
1.75 |
Rock excavation in dredged
zone |
0.2 |
3 |
0.60 |
3 |
0.60 |
3 |
0.60 |
Impact on existing utilities |
0.15 |
3 |
0.45 |
3 |
0.45 |
3 |
0.45 |
Siltation &
maintenance |
0.1 |
3 |
0.30 |
3 |
0.30 |
3 |
0.30 |
Total Weighted Score |
|
3.00 |
|
3.00 |
|
4.10 |
|
Normalised Score |
3.66 |
3.66 |
5.00 |
From the result of the assessment of all parameters for the approach channel and turning basin, it is found that layout option 3 is preferred.