Liquefied Natural Gas Receiving Terminal

Safety Management System

 

Castle Peak Power Company Limited (CAPCO) plans to incorporate the proposed Liquefied Natural Gas (LNG) Receiving Terminal into its current Safety Management System.  An excerpt of the existing Safety Management System from the CAPCO Safety Case is included in Appendix 1.  In addition to the practices and procedures identified in the Safety Management System, the following measures will be taken to prevent or control accidents:

 

1.      Safety Feature Installations

 

A centralized spill, fire and combustible gas alarm and control system will provide input to an information management system.  The primary purpose is to provide plant operators with a central facility for monitoring the conditions of accidental spill, fire and the release of combustible gas.  It will also provide the operators with the information and the means of responding to emergencies involving these conditions.

 

The main distributed control system, DCS console, is the physical operator/alarm and control system interface and will be located in the central control room, which is manned 24 hours a day.  Various lighted push buttons, digital read outs and annunciates provide the operator with complete monitoring and control capabilities.  The information management in the main DCS console will display combustible gas concentrations, alarm locations, etc.

 

In the event of total power failure, the LNG terminal will be shut down, the unloading operation will be stopped and the boil-off gas will be routed to the LP and HP vent system.

 

Color TV monitors will be installed to allow a visual picture of the entire facility at the central control room and gatehouse area.

 

Automatic detection devices, manual alarms and audible and visual signaling devices will be strategically located throughout the terminal.  Hazard detection and alarm signaling devices will report to the central control room and tie-in to the DCS.

 

Automatic detection devices will include flame, fire and heat, smoke, low temperature and combustible gas detectors.  The hazard detection system will be designed to minimize the time a spill, leak or fire might go undetected by installing multiple and redundant different detectors within the terminal to detect gas, fire, low temperatures and low and/or high operating pressures outside normal operating levels.  The detectors are located to provide warning as quickly as possible.  The detector signals are continuously monitored by an online computer in the control room that identifies a hazardous condition within the terminal to alarm and locate the situation for operating personnel.

 

The operators will be trained so that they are familiar with the fire prevention, fire protection and fire fighting methods.

 

The following safety and fire fighting features will be installed:

 

i.        Deluge systems will be installed on the tank roof.

ii.       Spill-collection system designed and located to deflect and prevent a pressurized LNG spill.  The LNG leak detection system is typically designed to detect spills and to shutdown the plant less than two minutes after a spill, and the LNG spill is able to be contained in the drainage basin area.  LNG spill sump will be designed for removing water and keeping debris free.

iii.      Install fixed dry chemical fire suppression systems on the tank roof.

iv.      Portable dry chemical extinguishers will be installed on the tank roof platform.

v.      Fixed high expansion foam protect will be provided.  Foam generators will be blower type, with hydraulic turbine-driven fans, producing a nominal 500:1 foam at an application rate of 120 m³/hour of expanded foam per m² of contained LNG spill surface area.

vi.      Hydrants approximate 90 meters apart and firewater monitors approximate 60 meters apart to be installed on the firewater main.  Isolation valves in the fire water main will be provided.

vii.     Automatic actuation for the firefight system will be automatic actuated by combustible gas detectors and low temperature detectors installed near the entrance to the LNG spill sump, and by means of voting UV/IR optical flame detectors.

 

The LP and HP vent system is designed to consider the following:

 

-        LNG tank rollover and BOG from sudden drop in barometric pressure.

-        The inner tank-overfilling scenario is eliminated by safety instrumentation system by tripping the unloading system.

 

The LNG terminal is designed for safe handling of vapor discharges from the system, such as relief valves.  During normal operation, there is no vent and relief.  Venting will be a rare event during normal and unloading operations.

 

1.      Emergency Shutdown (ESD) and Depressurization (EDP) System

 

The isolation systems are located in different areas along with equipment with fire, explosion and toxicity potential risks. An Emergency Shut Down (ESD) and Emergency Depressurization (EDP) systems will be provided to protect plant personnel, plant equipment and the environment in case of an emergency such as fire, potential dangerous process upset or hydrocarbon leak.  The ESD system will isolate the unit/system where an incident is occurring from the adjacent units/system.  The EDP system will reduce the hydrocarbon inventory of the system and will decrease its pressure.  Equipment and piping are divided into sections called ESD zones, considering the plot plan and the process flow.

 

An emergency shutdown system (ESD) will be incorporated in the design of the Terminal and provide the operators with the capability of remotely shutting down the entire or selective portions of the Terminal.

 

There will be three major ESD modes for the Terminal:

 

i.                           LNG unloading Isolation – The LNG unloading dock to the LNG storage tanks.

 

The ESD system will be installed on the LNG unloading lines to block in the unloading lines in the case of an LNG leak, a sudden unplanned disconnect of the LNG carrier, an external fire or any other emergency during unloading.  It consists of quick shut-off valves at the unloading dock.  These valves are triggered automatically by ship separation or high pressure or manually by an operator.  The closure times of the valves are set to prevent a liquid surge in the lines.

 

ii.                                     Send-out Shutdown – The LNG tanks through the pipeline shutoff valves.  Shut down the Primary LNG pumps, send-out pumps and BOG compressors; Isolation of the Terminal from the pipeline by closure ESD valves; Isolation of the high pressure part of the Terminal by closure ESD valves at send-out pump suction, primary pump discharge, compressor discharge, and depressurization of the vaporizers.

 

iii.                                    Overall Shutdown – From the ship-unloading area through the pipeline shutoff valves, with activation of modes 1 and 2 above

 

The following Shutdown functions will be provided:

 

-     Block in of the LNG loading arms

-     Block in of the LNG vapor return arm

-     Block in at shore line all unloading lines

-     Block in of LNG lines to LNG storage tanks

-     Shut down return gas

-     Shut down LP LNG send-out pumps in the LNG tanks

-     Block in send-out valves to BOG condenser

-     Shut down BOG compressors

-     Shut down HP LNG booster pumps

-     Block in LNG to vaporizers

-     Block in the outlet of the vaporizers

-     Emergency depressurizing the vaporizer units

 

Detector types will include:

 

-     Fire/Flame detectors

-     Gas detectors

-     Low temperature detectors

-     High-level shutdowns on the LNG storage tanks’ High-pressure shutdowns

-     Low flow shutdowns

-     Smoke detectors (for Buildings)

-     Heat detectors

-     Camera surveillance of the facility

-     Manual ESD activation stations

 

2.      Instrumentation, Control and Tank Level Measurement

 

The control system of the plant is performed by a Distributed Control System (DCS).

 

The major process control loops described below are shown in the Process Flow Diagrams.

 

The control system for the Terminal will be designed for fail-safe operation.  The control valves will be designed to move to a “fail safe” position, fully opened or closed, depending on the service.

 

The LNG flow unloaded from the ship is measured by flow recorders in both unloading lines.

 

The LNG flow from the in-tank LNG send-out pumps is controlled by kickback into the LNG storage tank.  The LNG level in the BOG condenser is used to control the LNG feed flow rate to the BOG condenser.  The send-out flow to each LNG vaporizer uses a flow controller that is reset by the vaporizer outlet gas temperature.

 

Each LNG vaporizer has an independent control system.  The seawater flow is adjusted by a butterfly valve.  The gas outlet temperature of each vaporizer is also controlled.  The LNG flow is controlled by a flow control valve, which is overridden by low-low flow of seawater or low temperature at the vaporizer outlet.

 

The proper pressure control of the LNG storage tanks is of utmost importance both in terms of safeguarding the mechanical integrity of the LNG storage tanks and the overall safety of the terminal.  The tank pressure is primarily controlled by using the gage pressure in the boil-off vapor header to load or unload the reciprocating boil-off gas compressor.  If the LNG storage tank pressure falls to below the minimum allowable operating limit, natural gas would then be fed from the vacuum breaker header to increase the pressure.  The final level of protection against low or vacuum pressure levels is provided by vacuum breaker relief valves, which would allow ambient air into the LNG storage tanks to prevent collapse if the pressure were to drop below -5 mbarg vacuum (the typical negative design pressure).

 

A pressure controller that relieves excess vapor to the low-pressure vent at high tank vapor header pressures provides the primary tank overpressure protection.  A secondary level of tank overpressure protection is provided by the tank relief valves which discharge directly to the atmosphere.

 

For LNG tank level measurement, an automatic, multi-sensor probe assembly, a tank top entry electronic control module, continuous level and density measurement with temperature and pressure monitoring will be provided.  These measurements are achieved by means of a control unit and an electro-mechanical drive mechanism, which operates as a unit to position a multi-sensor probe assembly suspended within the LNG storage tank.  The probe is moved vertically by the drive mechanism in response to commands generated by the control unit.  Both automatic and manual control of the probe assembly is incorporated into the system design.  All system components, which are located inside the tank, can be completely removed from the tank for inspection and/or maintenance at any time. The system has a probe enclosure assembly with viewing glass, which allows for probe to be removed from tank for maintenance.  Solid-state level sensors detect liquid and vapor interface.  This system will also effectively detect any LNG layering so that preventative measures can be taken. Enraf and Scientific Instruments (SII), for example, manufacture such instrument packages for the LNG tanks.

 

An additional microprocess-based Servo Tank Gauge is provided to measure the level with accuracies to +/-0.04” and a solid-state based temperature gauging system is provided with accuracies up to 0.1 °C.

 

The volume of LNG delivered for any given shipment will be able to be checked by calculation based on measurement of level, temperature and pressure in the LNG tanks.

 

 

3.      LNG Spill / Storm Water Containment

 

The LNG Terminal shall be curbed for containment of LNG spills and storm water.  Catch basins shall be located strategically on the LNG Terminal to collect LNG spills and storm water and shall gravity flow to a Storm water / LNG Spill Sump via a collection header.  Open collection pan shall be provided under equipment where there is a possibility of a large LNG leak, and will be routed to the collection header.

 

LNG leak detection will be provided by:

 

a.      Gas detectors

b.      Low temperature detectors

 

The detection system will be designed to detect spills and to shut down the plant within two minutes after a spill occurs.

 

All the detection systems are connected to ESD and activate alarms on the operators’ console placed in the Main Control Room, Field Control Room, and Jetty Control Room.

 

High expansion foam system will be provided to control LNG fires and vapor dispersion of LNG spills.  Foam will be discharged to cover the impoundment area to a depth of 0.6 meter within 2 minutes.

 

The LNG spill sump will serve the following purposes:

 

a.      Vaporization reduction

b.      Thermal radiation reduction

c.      Efficient application area for high expansion foam

 

In the event of a large LNG spill, it will be collected in the sump.  Low temperature alarm will activate high expansion foam.