Environmental
Protection Department
Agreement No.
CE20/2004 (EP)
North East New Territories (NENT) Landfill Extension
Environmental Monitoring
& Audit Manual
May 2007
1.2 Purpose and Scope of this
Manual
1.3 Description of the Project
2.1 Objectives of EM&A
Programme
2.2 Organisation for EM&A
Programme
2.3 Environmental Management Plan
2.7 Compliance with Action and
Limit Levels
2.11 Cessation of EM&A Programme
3.3 Precautionary Measures During
Operational, Restoration and Aftercare Phases
4.9 Environmental Mitigation
Measures
5.2 Precautionary / Mitigation
Measures during Construction and Operation Phases
6.2 Waste Control and Mitigation
Measures
8 Landscape
and Visual Monitoring
9 Cultural
Heritage Monitoring
9.3 Ngong Tong (North and West of
Shek Tsai Ha Road: Western & Central Section)
9.4 Tong To Shan (North of Shek
Tsai Ha Road: east section)
9.5 AMO requirements for Survey and
Preservation
10.2 Ecological Mitigation Measures
10.3 Monitoring and Audit for Ecology
11.2 Compliance with Environmental Requirements
12.2 Baseline Monitoring Report
12.5 Interim Notification of
Environmental Exceedances
APPENDICES
Appendix A Tentative Outline Programme
Appendix B Project Organisation
Appendix C Environmental Mitigation Implementation Schedule
Appendix D A Sample List of VOC Monitoring Parameters
DRAWINGS
24315/01/107 Landfill
Extension Layout Option 4
24315/13/151 Air
Monitoring Location
24315/13/251 Noise
Monitoring Location
24315/13/504 Existing
Landfill and Landfill Extension Monitoring Plan
24315/13/606 Archaeological
Findings
24315/13/702 Habitat Map Location of Species of
Conservation interest overlaid with Option 4
Currently, around 6 million tonnes of waste are disposed each year at the three strategic landfills in Hong Kong, including the West New Territories (WENT) Landfill, the South East New Territories (SENT) Landfill, and the North East New Territories (NENT) Landfill.
At time of commissioning, the three landfills with a total capacity
in the order of
To tackle the problem, further efforts have been taken to reduce and
recycle waste. Also, the HKSAR
Government has planned to develop Integrated Waste Management Facilities (IWMF)
to substantially reduce the volume of waste requiring landfill disposal. Yet these measures could not obviate totally
the need for new landfill capacity in
The Environmental Protection Department (EPD) of the HKSAR
Government therefore commissioned a study in Year 2000 on the Extension of
Existing Landfills and Identification of Potential New Waste Disposal
Sites. Amongst the potential sites
recommended in this territory-wide study is the extension of the existing NENT
Landfill, with a target capacity of about
In February 2005, EPD appointed Ove Arup & Partners Hong Kong Ltd. To undertake a detailed feasibility study for the NENT Landfill Extension (hereafter referred to “the Project”), with the following key tasks: formulation and evaluation of layout options for the landfill extension; EIA study; and conceptual design of landfill facilities.
Environmental Monitoring and Audit (EM&A) is an important aspect in the EIA process which specifies the timeframe and responsibilities for the implementation of environmental mitigation measures. The requirements on environmental monitoring (including baseline and impact monitoring) are given in the EM&A Manual (the Manual) which is a supplementary document to the EIA Study for the Project and prepared in accordance with the requirements in the EIA Study Brief and Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO).
The purpose of this EM&A Manual is to guide the establishment of an EM&A programme to ensure compliance with the EIA recommendations, to assess the effectiveness of recommended mitigation measures, and to identify further need for additional mitigation measures or remedial action.
This Manual outlines the monitoring and audit requirements for the construction, operation, restoration and aftercare stages of the NENT Landfill Extension. It aims to provide systematic procedures for monitoring, auditing and minimising environmental impacts associated with construction works and operational activities.
This Manual contains the following information:
·
Organisation,
hierarchy and responsibilities of the DBO Contractor, Environmental Team (ET),
Independent Environmental Checker (IEC), and Independent Consultant (IC), with
respect to the EM&A requirements during the construction, operation,
restoration and aftercare phases of landfill extension;
·
Information
on project organisation and programming of construction activities;
·
Requirements
with respect to the construction schedule and necessary EM&A programme to
track the varying environmental impacts;
·
Full
details of methodologies to be adopted, including all field, laboratory and
analytical procedures, and details on quality assurance;
·
Procedure
for undertaking on-site environmental audits;
·
Definition
of Action and Limit Levels;
·
Establishment
of Event and Action Plans;
·
Requirements
of reviewing pollution sources and working procedures required in the event of
non-compliance of environmental criteria and complaints;
·
Requirements
for reviewing the EIA predictions, implementation of mitigation measures, and
effectiveness of environmental protection and pollution control measures
adopted; and
·
Presentation
of requirements for EM&A data and appropriate reporting procedures.
1.3.1 General Description of the Project
The development of the NENT Landfill Extension will involve the following works:
·
Site
formation, drainage diversion and preparation;
·
Installation
of liner system;
·
Installation
of leachate collection, treatment and disposal facilities;
·
Installation
of gas collection, utilization and management facilities;
·
Operation
and environmental monitoring of landfill;
·
Restoration
and aftercare.
1.3.2 Key Project Requirements
The
key project requirements for the NENT Landfill Extension are:
·
Development
of sanitary landfill that covers an area of about
·
Provision
of liner system for the landfill to prevent contamination of land and water
resources;
·
Provision
of leachate collection, treatment and disposal facilities with sufficient
capacity for handling the leachate arising from the new landfill;
·
Provision
of landfill gas (LFG) collection, utilisation and management facilities;
·
Provision
of utilities, drainage and road network necessary for the proper operation of
the Project;
·
Provision
of facilities (both civil works and electrical and mechanical equipment) for
waste reception, inspection, charging, handling and compaction, and plant
maintenance;
·
Provision
of facilities for site administration;
·
Operation
of landfill in compliance with all relevant engineering, geotechnical and
environmental standards;
·
Restoration
of landfill in compliance with all relevant engineering, geotechnical and
environmental standards;
·
Provision
of aftercare for the landfill for a period of about 30 years
·
Carrying
out environmental monitoring and audits throughout construction, operation,
restoration and aftercare of the landfill; and
·
Implementation
of environmental measures necessary for the protection of the surrounding
environment.
1.3.3 Size, Scale, Shape and Design of the Project
The landfill extension site will be a
bowl-shape area with a large void space in the middle for waste filling. The
northwestern and southeastern boundaries of the landfill extension site follow
the ridgelines to maximise the landfill
capacity. Some set back of the northern
boundary is included to minimise the impact to
woodland and Lin Ma Hang Catchment. The total site
area is
·
Bottom
liner system – separate rubbish and leachate from groundwater;
·
Landfill
cells – store waste within the unit;
·
Storm
water drainage system – collect rain water run off on the landfill;
·
Leachate
collection system – collect liquid leaching from the waste mass and convey it
to a leachate treatment plant prior to discharging to Shek Wu Hui Sewage
Treatment Works;
·
Gas
collection system – collect gases formed during the decompositon of waste.
These gases will be treated and utilised for production of electricity on site;
and
·
Covering
and capping – seal off the top of the landfill with a gas venting layer, an
impermeable mineral layer, a drainage layer of at least
1.3.4 Construction Phase Activities
Simple excavation and slope formation works will be carried out during the construction stage. The permanent works comprise cut and fill earthworks, slope formation and earth wall construction. The temporary works will involve the formations of temporary ditches along the sides of excavations and associated drainage works, and material storage areas. During site formation, sediment will be contained in permanent detention ponds/silt traps that will be constructed according to landfill phasing. Final design and location of sediment traps are yet to be decided, but are likely to be down gradient of each landfill phase or in the downstream valleys near the existing waste reception area. Where possible they will be maintained during the operation of each phase to ensure the effective control of operational soil erosion problem.
1.3.5 Operation Phase Activities
During operation, waste will be disposed of at individual landfill
cells. Deposited waste will be compacted
to thin layers of up to two metres in thickness. The works will be maintained at a gradient of
not greater than
·
Heavy duty reusable and biodegradable sheets;
·
Biodegradable, non-reusable plastic
films;
·
Geotextiles;
and
·
Foams
and sprays.
Advantages of using alternative daily cover over traditional methods may include preservation of void space and soil material; biodegradable and less permeable to water and gas (reduce water infiltration, odour and dust emission).
1.3.6 Restoration Phase Activities
Restoration is a process to restore a landfill site to a condition suitable for afteruse. After completion of waste filling, final capping will be applied to minimise infiltration of rainwater into the waste body thus reducing the amount of leachate generated. The capping system normally includes a number of components including topsoil, subsoil, drainage layer and barrier layer.
1.3.7 Aftercare Phase Activities
Aftercare is the work done after the replacement of the soil and includes cultivations, fertilisation, planting, construction of pathways, access points, vegetation maintenance and an ongoing long term commitment to the restored landfill. Landscaped berms will be created and tree planting will be provided during the aftercare period for aesthetic purpose.
The Landfill Extension will start receiving waste only when the Existing NENT Landfill has ceased operation. The timing of this has yet to be determined as it depends on the rate of waste deliveries in the forthcoming period. Based on current predictions, the capacity of the Existing Landfill will probably run out by early-to-mid next decade, by which time the Landfill Extension shall start operation.
Taking into account of the time needed for mobilization and preparatory works prior to commencement of receipt of waste, it may be necessary to award the Landfill Extension contract towards the end of this decade, this should talling with Project Programme anywhere else in the EIA. In order to ensure that new landfill space will be available before the capacity of the existing landfill runs out.
It is anticipated that the DBO (Design-Build-Operate) contract form, which has hitherto worked well for the existing waste management contracts (notably the three strategic landfill contracts and the refuse transfer station contracts), will be adopted for NENT Landfill Extension. Detailed design and formulation of technical details for the construction, operation, restoration and aftercare of the NENT Landfill Extension will be carried out by the DBO Contractor, in accordance with requirements stipulated in the Specification and other documents of the DBO Contract.
A tentative outline programme for implementation of the NENT Landfill Extension is shown in Appendix A. As pointed out above, the exact timing of the various activities may vary, depending on actual volume of waste to be delivered in the forthcoming years.
The requirements of EM&A programme should include the
recommendations from the EIA study and with reference to EPD’s
“Environmental Monitoring and Audit Guidelines for Development Projects in
The EM&A requirements recommended in the EIA Report will ensure compliance with the specified mitigation measures. An EM&A programme should be designed based on these requirements to achieve the following key objectives:
·
Establishment
of existing environmental setting of the site to assist the development of
landfill design and to establish a baseline against which any adverse
environmental impacts can be evaluated;
·
Provision
of a database against which any short- or long-term environmental impacts of
the Project can be determined against the Project compliance with regulatory
requirements, standards and Government policies;
·
Verification
of environmental impacts predicted in the EIA study and provision of an early
indication of any failure of environmental control measures or practices to
achieve the acceptable standards;
·
Evaluation
of environmental impacts during site preparation works and operational phases
of the landfill extension project to assist the determination of effectiveness
of the mitigation measures to be implemented, ensure compliance with the
relevant environmental regulations, and design of any additional mitigation
measures requirements;
·
Provision
of information to enable environmental audit of Project activities during
construction, operation, restoration and aftercare phases, and taking remedial
action if unexpected problems or unacceptable impacts arise; and
·
Provision
of a basis for long-term monitoring programme folllowing the completion of
works during the aftercare phase.
The proposed project organisation and lines of responsibilities with respect to the EM&A programme are shown in Appendix B, which consists of the Project Proponent (EPD/WFG), DBO Contractor, Environmental Team (ET), Independent Environmental Checker (IEC), and Independent Consultant (IC), etc. It should be established to take the responsibilities for environmental protection for this landfill extension project. The IEC will be appointed by the Project Proponent as part of the IC to conduct independent auditing of the overall EM&A programme including environmental and operation monitoring, implementation of mitigation measures, EM&A submissions, and any other submissions required under the Environmental Permit (EP). The individual responsibilities are:
DBO Contractor
·
Employment
of an ET to carry out environmental monitoring, laboratory analysis and
reporting of environmental monitoring and audit;
·
Provision
of assistance to ET in carrying out monitoring and auditing;
·
Submission
of proposals of mitigation measures in case of exceedances of Action and Limit (A/L)
Levels in accordance with the Event and Action Plan (EAP);
·
Implementation
of mitigation measures to reduce the impacts where A/L Levels are exceeded; and
·
Adherence
to the agreed procedures for carrying out complaint investigation.
ET
·
Setting
up of all the required environmental monitoring stations;
·
Monitoring
of various environmental parameters as required;
·
Analysis
of monitoring and audit data and review the success of EM&A programme to
cost-effectively confirm the adequacy of mitigation measures implemented and
the validity of the EIA predictions and to identify any adverse environmental
impacts arising;
·
Carrying
out site inspections to investigate and audit the DBO Contractor’s site
practices, equipment and work methodologies with respect to pollution control
and environmental mitigation, and take proactive actions to pre-empt problems;
·
Auditing
and preparation of audit reports on environmental monitoring data and site
conditions;
·
Reporting
of environmental monitoring and audit results to the IEC, DBO Contractor, IC
and Project Proponent or its delegated representative;
·
Recommendation
of suitable mitigation measures to the DBO Contractor in case exceedance of A/L
Levels in accordance with the EAP; and
·
Undertaking
of regular on-site audits/ inspections and reporting to the DBO Contractor and
IC of any potential non-compliance; and
·
Following
up and closing out of non-compliance actions.
IEC
·
Review
of EM&A programme by the ET (at not less than monthly intervals);
·
Auditing
of monitoring activities and results (at not less than monthly intervals);
·
Reporting
of audit results to the IC and Project Proponent in parallel;
·
Reviewing
of EM&A reports (monthly, quarterly and annual summary reports) submitted
by the ET;
·
Reviewing
of proposal of mitigation measures submitted by the DBO Contractor in
accordance with the EAP;
·
Checking
of mitigation measures recommended in the EIA Report and EM&A Manual, and
ensuring they are properly implemented in timely manner when required; and
·
Reporting
of findings of site inspections and other environmental performance reviews to
IC and Project Proponent.
IC
·
Verification
and checking DBO Contractor’s activities and ensure that the requirements in
the EM&A Manual are fully complied with;
·
Informing
DBO Contractor when action is required to reduce impacts in accordance with the
EAP;
·
Ensure
compliance with the agreed Event Action Plan in case any exceedance.
Sufficient and suitably qualified professional and technical staff should be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project.
A systematic Environmental Management Plan (EMP) should be developed and implemented by the DBO Contractor in accordance with the ETWB TC(W) 19/2005 Environmental Management on Construction Sites to ensure effective implementation of the mitigation measures, monitoring and remedial requirements presented in the EIA, EM&A and environmental mitigation implementation schedule (EMIS) (Appendix C). The IEC should audit the implementation status of EMP and advise the necessary remedial action as required. Such remedial actions should be enforced through contractual requirements. The EMP should be certified by the ET and verified by the IEC.
The EMP should require the DBO Contractor (and sub-contractors) and
ET to define in details how to implement the recommended mitigation measures in
order to achieve the environmental performance stipulated in the
The EMP should summarise the requirements for the DBO Contractor to submit a Landfill Monitoring Plan (LMP) and an Emergency Response Plan (ERP) for approval. The LMP should describe the procedures and provide details of the environmental monitoring programme for the DBO Contractor to carry out throughout the construction, operation, restoration and aftercare phases of the Project. The ERP should address various scenarios within NENT Landfill Extension, in particular in the event of leakage of LFG/ leachate, failure of LFG/ leachate treatment operation, fire, chemical/ DG spillage, etc.
If the DBO Contractor would adopt alternative construction methods or implementation schedules, the detailed modifications of methodology and equipment should be submitted to the IEC for approval prior to the commencement of works. Any changes in construction methods should be indicated in the revised EMP. The DBO Contractor should review the EMIS with respect to the design developments and construction methodology. All necessary mitigation measures identified and recommended in the EIA study are summarised in the EMIS, which specifies the extent, locations, time frame and responsibilities for the implementation of the environmental mitigation measures identified.
The DBO Contractor should develop the waste management requirements as part of the EMP in Section 2.3 above for the construction phase of the Project. The DBO Contractor should also prepare a Waste Management Plan (WMP) for the Project during the operational, restoration and aftercare phases. Where waste generation is unavoidable, any opportunities for recycling or reuse of the wastes should be maximised. If the wastes cannot be recycled, recommendations for appropriate disposal routes should be provided in the WMP. A method statement for stockpiling and transportation of the excavated materials and other construction wastes should also be included in the WMP and approved before the commencement of construction. All mitigation measures arising from the approved WMP should be fully implemented. The WMP should be certified by the ET and verified by IEC.
It is not anticipated that any significant quantities of excavated C&D materials would require off-site disposal, as most will be reused on-site. Notwithstanding this, a trip-ticket system should be put in place in accordance with ETWB TC(W) No 31/2004. Copies/ counterfoils from trip-tickets (showing the quantities of C&D Materials taken off-site) should be kept for record purposes.
For the purpose of enhancing the management of Construction and Demolition (C&D) materials including rock, and minimising its generation at source, construction would be undertaken in accordance with the Environment, Transport and Works Bureau Technical Circular (Works) No 33/2002 – Management of Construction and Demolition Material Including Rock, or its latest versions. The management measures stipulated in the Technical Circular should be incorporated.
Prior to the commencement of construction works, the baseline
conditions of environmental parameters should be established at designated
monitoring locations to determine the nature and ranges of natural variation
and to demonstrate the suitability of the proposed impact, control and
reference monitoring locations in the EM&A programme. The baseline conditions of the following
environmental parameters should be established by the ET, including air quality
(dust, organic emissions, odour), noise, water quality (groundwater and surface water),
ecology (vegetation and biodiversity), landscape and visual, and cultural
heritage.
During the implementation of the Project, environmental monitoring should be conducted at designated monitoring locations to detect the changes of environmental parameters attributed to the Project. Impact monitoring should be conducted during all phases of the Project. The environmental monitoring parameters during construction phase should include air quality (dust, organic emissions, odour), noise, water quality (groundwater and surface water), ecology (vegetation and biodiversity), landscape and visual, and cultural heritage. The monitoring during operational, restoration and aftercare phases should include all parameters of construction phase, in addition to leachate and LFG.
The A/L Levels should be defined for environmental monitoring at designated monitoring locations exceeding which a prescribed response should be required. Individual A/L Levels should be quantitatively defined for the respective environmental monitoring parameters according to the following basic principles:
2.7.1 Action Level
Action Levels indicate deteriorating ambient environmental quality potentially due to the Project implementation. It acts as a sign to trigger appropriate remedial actions in order to rectify any mal-practices or non-conformance of Project activities thereby preventing the deterioration of environmental quality and to resume the ambient environmental quality back to normal levels.
2.7.2 Limit Level
Limit Levels are the statutory and/or contractual levels below which environmental conditions are considered unacceptable. If Limit Levels were exceeded, the relevant part of the works should not be continued without implementation of immediate remedial action, including a critical review of plant and working methods.
The EAP should lay down the systematic procedures for implementation in case exceedances of A/L Levels and environmental complaints in order to timely address, investigate and resolve such incidents and minimise their recurrence. The EAP should define the action under specific conditions, i.e. exceedances of A/L Levels, and trigger the relevant parties in the EM&A programme to take the action.
Environmental audit should include the following components:
·
Regular
inspection of site practices should be conducted to assess and ensure the
environmental protection and pollution control measures to be in accordance
with the EIA recommendations and complied with contract specifications.
·
Examination
of all available information related to the investigation of the nature and
cause of actual, potential and cumulative environmental impacts and complaints/
queries;
·
Proposal
for remedial measures for resolution of impacts, effective implementation of
proposed mitigation measures, documentation and summary of audit findings, and
liaison and consultation with the public and concerned parties on the effects
of such remedial works; and
·
Enquiries
and complaints related to the environmental performance of the Project should be
anticipated from individuals and organisations, which should be referred to the
ET Leader for investigation and action.
Systematic procedures for environmental complaints should be established
and followed. During the complaint
investigation, the DBO Contractor and IEC should facilitate the ET by providing
all necessary information.
2.10.1 Baseline Monitoring
Baseline Monitoring Report should be prepared by the ET and submitted within 4 weeks of completion of baseline monitoring to include all the baseline monitoring data and findings. The Report should be certified by the ET and verified by the IEC prior to submission to the EPD.
2.10.2 Impact Monitoring
Monthly EM&A Reports should be prepared by the ET and submitted within 21 days of each reporting month during construction, operational, restoration and aftercare phases to include all the impact monitoring data, findings and recommendations. Quarterly Summary, Annual Review and Final Review EM&A Reports should be prepared by the ET and submitted within 10 days of each reporting quarter, reporting year and cessation of project phase, respectively, during construction and operational, restoration, and aftercare phases to include all the summary of monitoring trends, findings and recommendations. These reports should be certified by the ET and verified by the IEC prior to formal submission to the EPD.
To implement the EM&A programme according to the Construction and Operational Phases, Restoration Phase and Aftercare Phase in which different EM&A requirements should be imposed, the ET and IEC should notify the EPD the completion of EM&A programme for the specific Project phases and request for agreement to cease the EM&A programme.
Monitoring of the Total Suspended Particulate (TSP) levels shall be
carried out by the ET to ensure that any deteriorating air quality could be
readily detected and timely action be taken to rectify the situation. 1-hour and 24-hour TSP levels should be
measured to indicate the impacts of construction dust on air quality. The TSP levels shall be measured by following
the standard high volume sampling method as set out in the Title 40 of the Code
of Federal Regulations,
All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and other special phenomena and work progress of the concerned site etc. shall be recorded down in details.
High volume sampler (HVS) in compliance with the following specifications shall be used for carrying out the 1-hr and 24-hr TSP monitoring:
·
0.6
· equipped with a timing/control device with +/- 5 minutes accuracy for 24 hours operation;
· installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
·
capable of providing a minimum
exposed area of
· flow control accuracy: +/- 2.5% deviation over 24-hr sampling period;
· equipped with a shelter to protect the filter and sampler;
· incorporated with an electronic mass flow rate controller or other equivalent devices;
· equipped with a flow recorder for continuous monitoring;
· provided with a peaked roof inlet;
· incorporated with a manometer;
· able to hold and seal the filter paper to the sampler housing at horizontal position;
· easy to change the filter; and
· capable of operating continuously for 24-hr period.
The ET Leader is responsible for provision of the monitoring equipment. He shall ensure that sufficient number of HVSs with an appropriate calibration kit are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring. The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals. All the equipment, calibration kit, filter papers, etc. shall be clearly labeled.
Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at bi-monthly intervals. The transfer standard shall be traceable to the internationally recognised primary standard and be calibrated annually. The calibration data shall be properly documented for future reference. All the data should be converted into standard temperature and pressure condition. The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded down in the data sheet.
If the ET Leader proposes to use a direct reading dust meter to measure 1-hr TSP levels, he shall submit sufficient information to the IC and IEC to prove that the instrument is capable of achieving a comparable result as that of the HVS and may be used for the 1-hr sampling. The instrument should also be calibrated regularly, and the 1-hr sampling shall be determined periodically by HVS to check the validity and accuracy of the results measured by direct reading method.
Wind data monitoring equipment shall also be provided and set up at conspicuous locations for logging wind speed and wind direction near to the dust monitoring locations. The equipment installation location shall be proposed by the ET Leader and agreed with the ER. For installation and operation of wind data monitoring equipment, the following points shall be observed:
·
the wind sensors should be
installed on masts at an elevated level
· the wind data should be captured by a data logger and to be downloaded for processing at least once a month;
· the wind data monitoring equipment should be re-calibrated at least once every six months; and
· wind direction should be divided into 16 sectors of 22.5 degrees each.
In exceptional situations, the ET Leader may propose alternative methods to obtain representative wind data upon approval from the IC and IEC, and agreement from EPD.
3.1.3 Laboratory Measurement/Analysis
A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments, to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance. The laboratory should be HOKLAS accredited.
If a site laboratory is set up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the IC and IEC and the measurement procedures (first measurement) shall be witnessed by the IC and IEC. The ET Leader shall provide the IC and IEC with one copy of the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his reference.
Filter paper of size 8"x10" shall be labeled before sampling. It shall be a clean filter paper with no pin holes, and shall be conditioned in a humidity controlled chamber for over 24-hr and be pre-weighed before use for the sampling.
After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag. The filter paper is then returned to the laboratory for reconditioning in the humidity controlled chamber followed by accurate weighing by an electronic balance with a readout down to 0.1 mg. The balance shall be regularly calibrated against a traceable standard. All the collected samples shall be kept in a good condition for 6 months before disposal.
The dust monitoring locations are shown in Table 3.1. The status and locations of dust sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from IC and IEC and agreement from EPD on the proposal.
The ET shall also write to the relevant private owners or owner’s incorporation for their agreement to install the HVS at suitable location at least 3 months before construction works. The purpose of monitoring (to minimize potential impact and to safeguard the residential) should be clearly stipulated. The specification, wiring, fixing, maintenance, communication and payment of electricity cost shall be detailed in the letter. If there is objection from the owner, alternative monitoring location at premises in the vicinity shall be identified and agreed with EPD, IEC and IC. The monitoring location is illustrated in Drawing No. 24315/13/151.
Table 3.1 Description
of dust monitoring locations
AML ID |
EIA ASR Ref |
Location |
Land Uses |
Monitoring Parameters |
AM(D)1 |
ASR11 |
Tung Lo Hang |
Residential/ Pig Farm |
1-hr and 24-hour TSP |
AM(D)2 |
ASR7 |
Heung Yuen Wai |
Residential |
1-hr and 24-hour TSP |
AM(D)3 |
ASR1 |
Wo Keng Shan Tsuen |
Residential |
1-hr and 24-hour TSP |
When alternative monitoring locations are proposed, the following criteria, as far as practicable, should be followed:
· At the site boundary or such locations close to the major dust emission source;
· Close to the sensitive receptors; and
· Account for the prevailing meteorological conditions.
The ET Leader shall agree with the IC and IEC on the position of the HVS for installation of the monitoring equipment. When positioning the samplers, the following points shall be noted:
· a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;
· no two samplers should be placed less than 2 meter apart;
· the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;
· a minimum of 2 metres separation from walls, parapets and penthouses is required for rooftop samplers;
· a minimum of 2 metres separation from any supporting structure, measured horizontally is required;
· no furnace or incinerator flue is nearby;
· airflow around the sampler is unrestricted;
· the sampler is more than 20 metres from the drip-line;
· any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;
· permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and
· a secured supply of electricity is needed to operate the samplers.
The ET Leader shall carry out baseline monitoring at all of the designated monitoring locations for at least 14 consecutive days prior to the commencement of the construction works to obtain daily 24-hr TSP samples. 1-hour sampling shall also be done at least 3 times per day while the highest dust impact is expected. During the baseline monitoring, there should not be any construction or dust generation activities in the vicinity of the monitoring stations.
In case the baseline monitoring cannot be carried out at the designated monitoring locations during the baseline monitoring period, the ET Leader shall carry out the monitoring at alternative locations which can effectively represent the baseline conditions at the impact monitoring locations. The alternative baseline monitoring locations shall be approved by the IC and IEC and agreed with EPD.
In exceptional case, when insufficient baseline monitoring data or questionable results are obtained, the ET Leader shall liaise with EPD to agree on an appropriate set of data to be used as a baseline reference and submit to IC and IEC for approval.
If the baseline level for air quality exceeds the limit level, the ET shall carry out an investigation to determine the cause of the exceedance in consultation with EPD. Regardless of whether the exceedance was caused by poor weather condition (e.g. high API) or as a result of inadequate control measures on construction activities being carried out on other nearby construction sites, a second set of baseline monitoring shall be conducted by the ET to determine an appropriate baseline level for the EM&A programme in agreement with EPD.
Ambient conditions may vary seasonally and shall be reviewed at every three months. If the ET Leader considers that the ambient conditions have been changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring should be at times when the DBO Contractor's activities are not generating dust, at least in the proximity of the monitoring stations. Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, should be revised. The revised baseline levels and air quality criteria should be agreed with EPD.
The ET Leader shall carry out impact monitoring during the course of the Works. For regular impact monitoring, the sampling frequency of at least once in every six-days, shall be strictly observed at all the monitoring stations for 24-hr TSP monitoring. For 1-hr TSP monitoring, the sampling frequency of at least three times in every six-days should be undertaken when the highest dust impact occurs. The specific time to start and stop the 24-hr TSP monitoring shall be clearly defined for each location and be strictly followed by the DBO Contractor.
In case of non-compliance with the dust criteria, more frequent
monitoring exercise, as specified in the Action Plan in Section
The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring. The ET Leader shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP. Table 3.2 shows the dust criteria, namely Action and Limit levels to be used. Should non-compliance of the air quality criteria occur, the ET, the IC/IEC and the DBO Contractor shall undertake the relevant action in accordance with the Action Plan in Table 3.3.
Table 3.2 Action and limit levels for dust impact
Parameters |
Action |
Limit |
24-hour TSP Level in µg/m³ |
For baseline level 200 µg/m³,
Action level = (130% of baseline level + Limit level)/2 For baseline level > 200
µg/m³, Action level = Limit level |
260 |
1-hour TSP Level in µg/m³ |
For baseline level 384 µg/m³,
Action level = (130% of baseline level + Limit level)/2 For baseline level > 384
µg/m³, Action level = Limit level |
500 |
Table 3.3 Event/Action plan for dust impact
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action Level |
||||
1. Exceedance for one sample |
· Identify
source · Inform IEC and
DBO Contractor · Repeat
measurement to confirm findings · Increase monitoring
frequency to daily |
· Check
monitoring data and DBO Contractor's working methods |
· Notify DBO
Contractor for the identification of cause |
· Rectify any
unacceptable practice · Amend working
methods if appropriate |
2. Exceedance for two or more consecutive
samples |
· Identify
source · Notify IEC and
DBO Contractor · Repeat
measurements to confirm findings · Increase
monitoring frequency to daily · Discuss with
IEC/IC for remedial actions required · If exceedance continues, arrange meeting with IEC · If exceedance stops, cease additional monitoring |
· Review with
analysed results submitted by ET · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure
remedial measures are properly implemented |
· Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Amend proposal
if appropriate |
Exceedance of Limit Level |
||||
1.Exceedance for one sample |
· Identify
source · Inform IEC and
DBO Contractor · Repeat
measurement to confirm findings · Increase monitoring
frequency to daily · Assess
effectiveness of DBO Contractor's remedial actions and keep EPD and IEC/IC
informed of the results |
· Check
monitoring data and DBO Contractor's working methods · Discuss with
ET Leader and DBO Contractor potential remedial actions · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure remedial
measures are properly implemented |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Amend proposal
if appropriate |
2.Exceedance for two or more consecutive samples |
· Identify
source · Inform IEC,
IC, and EPD the causes and actions
taken for the exceedances · Increase
monitoring frequency to confirm findings · Carry out analysis
of DBO Contractor’s working procedures to determine possible mitigation to be
implemented · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If exceedance stops, cease additional monitoring |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed dust problem · Ensure
remedial measures are properly implemented · If exceedance continues, consider what activity of the work
is responsible and instruct DBO Contractor to stop that activity of work
until the exceedance is abated |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Resubmit
proposals if problem still not under control · Stop the
relevant activity of works as determined by the IC until the exceedance is abated |
3.1.8 Dust Mitigation Measures
The EIA report has recommended dust control and mitigation measures. The DBO Contractor shall be responsible for the design and implementation of these measures:
· Dust emission from construction vehicle movement are confined within the worksites area.
· Watering facilities will be provided at every designated vehicular exit point.
· Good site practice is recommended during construction phase. Covering with impermeable sheet should be provided for the inactive tipping area.
If the above measures are not sufficient to restore the air quality to acceptable levels upon the advice of ET Leader, the DBO Contractor shall liaise with the ET Leader on some other mitigation measures, propose to IC and IEC for approval, and implement the mitigation measures.
3.2.1 Odour Intensity Analysis
Odour Intensity Analysis is conducted by independent trained personnel / competent persons patrolling and sniffing around the Air Sensitive Receiver to detect any odour at the concerned hours.
The independent trained personnel / competent persons shall :
· have their individual odour threshold of n-butanol in nitrogen gas in the range of 20 to 80 ppb/v required by the European Standard Method (EN 13725).
· be at least 16 years of age and willing and able to follow instructions.
· be free from any respiratory diseases.
· be engaged for a sufficient period to build up and monitor/detect at several monitoring location;
· not be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30 min before and during odour intensity analysis;
· take great care not to cause any interference with their own perception or that of others by lack of personal hygiene or the use of perfumes, deodorants, body lotions or cosmetics;
· not communicate with each other about the results of their choices.
At least three independent trained personnel / competent persons shall be selected to form a patrol team to conduct the odour intensity analysis, who should participated in a set of screening tests.
Subject to the prevailing weather forecast condition, odour intensity analysis shall be conducted by independent trained personnel / competent persons at the downwind locations. During the analysis, the sequence should start from less odorous locations to stronger odorous locations.
The independent trained personnel / competent persons shall use their nose (olfactory sensors) to sniff odours at different locations. The main odour emission sources and the areas to be affected by the odour nuisance shall be identified.
The perceived odour intensity is to be divided into 5 levels which are ranked in the descending order as follows:
· 0 - Not detected. No odour perceived or an odour so weak that it can not be easily characterised or described;
· 1 - Slight Identifiable odour, and slight chance to have odour nuisance;
· 2 - Moderate Identifiable odour, and moderate chance to have odour nuisance;
· 3 - Strong Identifiable, likely to have odour nuisance;
· 4 - Extreme Severe odour, and unacceptable odour level.
The independent trained personnel / competent persons shall record the findings including odour intensity, odour nature and possible odour sources, and also the local wind speed and direction at each location. In addition, some relevant meteorological data such as daily average temperature, and daily average humidity, on that surveyed day shall be obtained from the Hong Kong Observatory Station for reference.
3.2.2 Odour Patrol
Apart from odour intensity analysis, routine odour patrol by competent persons shall also be conducted to detect odour nuisance.
3.2.3 Odour Intensity Analysis / Odour Patrol Locations
The odour intensity analysis and odour patrol locations are shown in Table 3.4. The status and locations of air sensitive receivers may change after issuing this manual. If such cases exist, the ET Leader shall propose updated monitoring locations and seek approval from IC and IEC and agreement from EPD on the proposal. The monitoring location is illustrated in Drawing No. 24315/13/151.
Table 3.4 Description
of odour monitoring locations
AML ID |
EIA ASR Ref |
Location [1] |
Land Uses |
Monitoring Parameters |
AM(O)1 |
ASR1 |
Wo Keng Shan Tsuen |
Residential |
Odour Intensity |
AM(O)2 |
ASR2 |
Village houses at Junction
of Ng Chow Road and |
Residential |
Odour Intensity |
AM(O)3 |
ASR13 |
Nga Yiu Ha |
Residential |
Odour Intensity |
AM(O)4 |
ASR14 |
Ping Yeung |
Residential |
Odour Intensity |
AM(O)5 |
ASR10 |
Lin Ma Hang |
Residential |
Odour Intensity |
AM(O)6 |
ASR27 |
Tong To Shan Tsuen [2] |
Only if it is occupied by
residents |
Odour Intensity |
Remark:
[1] Odour odour intensity analysis and odour patrol shall only be conduced for the downwind monitoring locations.
[2] Tong To Shan Tsuen is currently a derelict isolated single house.
3.2.4 Event and Action
Table 3.5 shows the Action and Limit levels to be used, and the patrol frequency is listed in Table 3.6. Should non-compliance of the air quality criteria occur, the ET, the IC/IEC and the DBO Contractor shall undertake the relevant action in accordance with the Action Plan in Table 3.7.
Table 3.5 Action and limit levels for odour nuisance
Parameters |
Action |
Limit |
Odour Nuisance (from odour
intensity analysis or odour patrol) |
· When two documented complaint are received; or · Odour Intensity of 2 is measured from odour
intensity analysis. |
· Five or more consecutive geninue documented
complaints within a week; or · Odour Intensity of 3 or above is measured from odour
intensity analysis. |
Table 3.6 Odour Intensity Analysis and Odour Patrol Frequency
Routine Mode |
Action Level |
Limit Level |
Odour
Patrol : Once every six days during the following period: ·
early morning;
and ·
peak tipping
hour (e.g. 11:00am), Odour
Intensity Analysis : Quarterly during the following period: ·
early morning;
and ·
peak tipping
hour (e.g. 11:00am), |
Daily odour patrol. Weekly odour intensity analysis for 2 period during: · early morning; and · peak tipping hour (e.g. 11:00am) |
Daily odour patrol. Daily odour intensity analysis for 2 period during: · early morning; and · peak tipping hour (e.g. 11:00am) |
Table 3.7 Event/Action plan for odour nuisance
Event |
ET |
IEC |
IC |
DBO Contractor |
Action Level |
· Identify
source · Inform IEC and
DBO Contractor · If nuisance
stops or external source has been identified, resume monitoring to routine
mode · Recommend
precautionary measures |
· Review
submissions and reports from ET |
· Notify DBO
Contractor · Ensure
implementation of precautionary measures |
· Rectify any
unacceptable practice · Review the
operation of odour enhancement facilities at leachate
treatment plants · Amend working
methods if appropriate · Carry out
precautionary measures |
Limit Level |
· Identify
source · Inform IEC, and
IC, the causes and actions taken for the nuisance · Carry out
analysis of DBO Contractor’s working procedures to determine possible
mitigation to be implemented · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If nuisance
stops or external source has been identified, resume monitoring to routine
mode |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed odour nuisance · Ensure
remedial measures are properly implemented · If nuisance
continues, instruct DBO Contractor to stop that activity of work suspected to
be the origin of the nuisance source until the nuisance is abated |
· Take immediate
action to avoid further nuisance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Proposals
include tipping at the far end of the upwind location; thicker daily cover
can be arranged in case odour patrol identify potential odour nuisance; and
use of immediate soil cover for sewage sludge, animal waste · Implement the
agreed proposals · Resubmit
proposals if problem still not under control |
3.3.1 Stack Discharge from ASP, Flare and LFG Power Generator
· The maximum allowable discharge limit for ASP, flare and LFG power generator should be specified in the design specification.
· Owing to the requirement for the installation of stack, the design requirement shall be submitted to IEC and IC for vetting by the DBO Contractor under the Air Pollution Control (Furnaces, Ovens and Chimneys) (Installation and Alternation) Regulations.
· Subject to the subsequent EPD’s requirement on chimney installation, once every 3 months regular stack monitoring of vinyl chloride, benzene, TOC, NOx and SO2 shall be carried out to demonstrate compliance during the operations.
· A monthly monitoring report should be prepared by ET and submitted to IEC and IC for approval.
3.3.2 Odour from Leachate Treatment Facilities
For the
proposed leachate treatment plant in NENT Landfill
Extension, the overall leachate treatment facilities
include:
· Adopted updated treatment method such as Sequencing Batch Reactor for future leachate treatment. Provision of ventilated cover for the leachate storage lagoons / tanks and emissions extracted to suitable odour removal filters with odour removal efficiency of 99%.
· Ferric nitrate or sodium hypochlorite can be added to oxidise the odourous chemical in the leachate. The pH value of leachate can be controlled to a suitable value from future on-site experiment such that the generation of any odourous H2S and ammonia can be optimised.
· For the gaseous extraction system, the wind speed immediately above the leachate surface should be kept to minimal (in the order of 1E-3 m/s) such that the odour emission strength from lagoon can be minimised. Suitable treatment system should be provided for odour removal. The ventilated gaseous emission from lagoons should be provided with 5-10 air change per hour for further dilution before discharge.
· The notional centre of the future discharge point (e.g. stack) shall be located at a location with maximum setback distance from the ASRs and further away from the notional centre of the lagoons. The location of discharge point and discharge height should be determined at the detailed design stage to ensure that the odour criterion at the ASRs will not be exceeded.
· The overall arrangement should be investigated in details by the DBO Contractor and agreed with IEC and EPD. As such, the odour emission from the future leachate treatment facilities will be insignificant.
3.3.3 Odour from Waste Transfer Activities
The following are some odour precautionary measures that shall be considered by EPD and FEHD:
· As an improvement measure to enhance to environmental standard for waste transfer, EPD could take the initiative to recommend others to use enclosed type RCVs (dominantly government vehicles and sludge vehicles).
· Clearing / watering of the surface and clearing of the waste water receptor of government RCV is recommended before leaving refuse transfer station or government Refuse Collection Point (FEHD).
3.3.4 Precautionary Odour from Waste Tipping Activities
· The use of alternative daily cover (less permeable layer) instead of inert material should be considered under worst-case weather condition, subject to EM&A Programme.
· The use of immediate daily cover for odorous waste such as sewage sludge, animal waste etc. under critical condition should also be considered, subject to EM&A Programme.
· For the time being, there is no population in the derelict Tong To Shan Tsuen. If there is new residents moving in, thicker daily cover / alternative daily cover should be applied at phase 3 of the extension site such that the emission strength for the night time can be reduced (similar performance as that in the inactive tipping area). Odour patrol at Tong To Shan Tsuen should be arranged during night time / early morning in order to ensure the effectiveness of the measures.
·
In accordance with some
reference from
· During stable and calm weather condition and subject to EM&A programme, tipping could be arranged to further increase the setback distance.
3.3.5 VOC Surface Emission
· The VOC monitoring requirements are discussed in Section 7. Details will be further established in the Landfill Monitoring Plan (LMP) to be developed by the future DBO Contractor based on EM&A Manual for landfill gas monitoring.
· Subject to future engineering design, the arrangement of the landfill gas collection system and surface covering material for inactive tipping area shall be reviewed by DBO Contractor every 5 year to identify any modern technology/arrangement (covering material, LFG well spacing and locations) and the latest WHO/USEPA health-risk criteria. A working team shall be formulated to review all processes, control practice and extraction system in order to maximise the efficiency of the system. A review report should be prepared by the DBO Contractor for the submission to IC and IEC on the implementation/arrangement of LFG extraction system. The first review report should be submitted to IC and IEC for agreement before commencement. With a good system to collect LFG (high extraction efficiency), surface release of VOC to the nearby environment can be much reduced or utilised.
· Maintain a slightly negative pressure within the entire tipping area (by suction). Minimise any potential leakage of LFG to the surrounding by increase the number of gas-extraction wells. Improve the extraction efficiency by checking/reinstate gas wells with abnormally low extraction rate due to blockage/soil movement or sedimentation.
· Increase the coverage of inactive tipping area with HDPE/plastic sheet which can enhance the anaerobic decomposition (reduce air getting in and VOC leaking out).
· EM&A will be conducted at ASR to establish the future VOC ambient level one year before (as baseline) and one year after the commissioning of NENT extension. This monitoring work should be carried out in a frequency once every 3 month during the period when the ASP and flare are not in operation (only have the contribution from surface emission). Benzene and vinyl chloride are the key monitoring parameters. By comparing the monitoring data at the boundary and at ASR, the cause of VOC and the general downwind dispersion effect (dilution effect) from the boundary to the ASR can be identified. This monitoring should be repeated by the DBO Contractor once every 5 year and the findings should be incorporated into the landfill gas collection system review report as mentioned above.
· The monitoring location is listed in Table 3.4 and illustrated in Drawing No. 24315/13/151. This off-site VOC monitoring report shall be submitted to IC and IEC for vetting.
Table 3.8 Off-site
Surface gas monitoring locations at ASRs
AML ID |
EIA ASR Ref |
Location |
Land Uses |
Monitoring Indicator |
AM(V)1 |
ASR1 |
Wo Keng Shan Tsuen (West of NENT Extension) |
Residential |
Benzene and Vinyl Chloride |
AM(V)2 |
ASR3 |
Cheung Shan Monastery (South of NENT Extension) |
Religions |
Benzene and Vinyl Chloride |
AM(V)3 |
ASR10 |
Lin Ma Hang (North of NENT Extension) |
Residential |
Benzene and Vinyl Chloride |
AM(V)4 |
ASR27 |
Tong To Shan Tsuen (North-east of NENT Extension) |
Only if it is occupied by residents |
Benzene and Vinyl Chloride |
4.1 Monitoring Parameters
Construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq). Leq30min
shall be used as the monitoring parameter for the time period between 0700 and
1900 hours on normal weekdays. For all
other time periods, Leq5min shall be employed for comparison with
the Noise Control Ordinance (NCO) criteria.
As supplementary information for data auditing, statistical results such
as L10 and L90 shall also be obtained for reference.
4.1.2 Operational and Traffic Noise
The noise level shall be measured in terms of
the A-weighted equivalent continuous sound pressure level over a period of 30
minutes (LAeq, 30mins) and
A-weighted 10% of time over a period of one hour (LA10, 1hr) for operational noise and operational traffic
noise, respectively. As supplementary information for data auditing,
statistical results such as LA10, LAeq and LA90 shall
also be obtained for reference.
In accordance with the Technical Memorandum (TM)
issued under the Noise Control Ordinance (NCO), sound level meters in
compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1)
specifications shall be used for carrying out the noise monitoring. Immediately prior to and following each noise
measurement, the accuracy of the sound level meter shall be checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0dB.
The ET Leader shall be responsible for the
provision, installation and maintenance of the monitoring equipment. He shall ensure that sufficient noise
monitoring equipment and associated instrumentation are available for carrying
out the baseline monitoring, regular impact monitoring and ad hoc
monitoring. All the equipment and
associated instrumentation shall be clearly labelled. The location of equipment installation should
be proposed by the ET Leader and agreed with the IC and EPD in consultation
with the IEC.
Noise measurements should not be made in the
presence of fog, rain, wind with a steady speed exceeding 5m/s or wind with
gusts exceeding 10m/s. The wind speed shall
be checked with a portable wind speed meter capable of measuring the wind speed
in m/s.
The ET shall carry out noise monitoring during the construction and
operational phases at 3 monitoring stations as shown in Table 4.1 and Drawing No. 24315/13/251. The status and
locations of NSRs may change after issuing this
EM&A Manual. In such cases, the ET
Leader should propose updated monitoring locations and seek approval from EPD.
Table 4.1 Noise monitoring locations
Monitoring ID |
Location |
Type of Monitoring
|
Monitoring
Parameters |
Supplementary
Information |
NM1 |
Wo Keng Shan Tsuen |
Construction
& Operation |
LAeq, 30mins |
LA10 and LA90 |
NM2 |
Lin Ma Hang |
Construction
& Operation |
LAeq, 30mins |
LA10 and LA90 |
NM3 |
Cheung
Shan Monastery |
Traffic
Noise |
LA10, 1hr |
LAeq and LA90 |
When alternative monitoring locations are
proposed, the monitoring locations should be chosen based on the following criteria:
· At locations close to the major site activities which are likely to have noise impacts;
· Close to the noise sensitive receivers;
· For monitoring locations in the vicinity of the sensitive receivers, care should be taken to avoid disturbance to the occupants during monitoring.
The monitoring station shall normally be at a
point 1m from the exterior of the sensitive receivers building facade and be at
a position 1.2m above the ground. If
there is problem with access to the normal monitoring position, an alternative
position may be chosen, and a correction to the measurements shall be
made. For reference, a correction of
+3dB(A) shall be made to the free field measurements. The ET Leader shall agree with the IEC on the
monitoring positions and the corrections adopted. Once the positions for the monitoring
stations are chosen, the baseline monitoring and the impact monitoring shall be
carried out at the same positions.
4.4 Baseline Monitoring
The ET shall carry out baseline noise monitoring
prior to the commencement of the operation of landfill. The continuous
baseline monitoring shall be carried out daily for a period of at least two
weeks in a sample period of 5 minutes or 30 minutes. A schedule on the
baseline monitoring shall be submitted to the IC and IEC for approval before
the monitoring starts.
In exceptional case, when insufficient baseline
monitoring data or questionable results are obtained, the ET Leader shall
liaise with the IC, IEC and EPD to agree on an appropriate set of data to be
used as a baseline reference and submit to ER for approval.
During normal construction working hour
(0700-1900 Monday to Saturday), monitoring of Leq30min noise levels
(as 6 consecutive Leq5min readings) shall be carried out at the
agreed monitoring locations once every week.
If a school exists near the construction
activity, noise monitoring shall be carried out at the monitoring stations for
the schools during the school examination periods. The ET Leader shall liaise with the school’s
personnel and the Examination Authority to ascertain the exact dates and times
of all examination periods during the course of the contract.
In case of non-compliance with the construction
noise criteria, more frequent monitoring as specified in the Event and Action
Plan shall be carried out. This
additional monitoring shall be continued until the recorded noise levels are
rectified or proved to be irrelevant to the construction activities.
A schedule on the compliance monitoring shall be
submitted to the IEC and IC for approval before the monitoring starts. Sample data sheet for construction noise
measurements is given in Appendix
C2.
During normal operational working hours,
monitoring of LAeq, 30min noise
levels (as six consecutive LAeq, 5min
readings) shall be carried out at the agreed monitoring locations once
every week in accordance with the methodology in the TM.
Other noise sources such as road traffic and
construction activities may make a significant contribution to the overall
noise environment. Therefore, the
results of noise monitoring activities shall take into account such influencing
factors, which may not be present during the baseline monitoring period.
In case of non-compliance with the operational
noise criteria, more frequent monitoring as specified in the Event and Action
Plan shall be carried out. This
additional monitoring shall be continued until the recorded noise levels are
rectified or proved to be irrelevant to the operational activities.
During normal operational working hours,
monitoring of LA10, 1hr noise levels shall be carried out at the
agreed monitoring locations once every week in accordance with the methodology
in the Section III of the “Calculation of Road Traffic Noise, 1998”.
The operational traffic noise monitoring will be
measured in term of the A-weighted L10 within the peak traffic hour for each designated noise
monitoring location. Measurements were
paused if noise detected from other non-traffic activities became dominant.
In case of non-compliance with the traffic noise
criteria, more frequent monitoring as specified in the Event and Action Plan
shall be carried out. This additional
monitoring shall be continued until the recorded noise levels are rectified or
proved to be irrelevant to the operational activities.
The Action and Limit levels for construction,
operational and traffic noise are defined in Tables 4.2-4.4. Should
non-compliance of the criteria occur, actions in accordance with the Event and
Action Plan in Tables 4.5-4.6 shall
be carried out.
Table 4.2 Action and limit
levels for construction noise
Time Period |
Action
Level |
Limit
Level |
0700 - 1900 hours on normal weekdays |
When one documented complaint is received |
75 dB(A)* |
If
works are to be carried out during restricted hours, the conditions stipulated
in the construction noise permit issued by the Noise Control Authority have to
be followed.
* Reduce to 70dB(A) for schools and 65dB(A) during
school examination periods.
Table 4.3 Action and
limit levels for operational noise
Time Period |
Action
Level |
Limit
Level |
0700-1900 on all days |
When one documented complaint is received |
60 dB(A) * |
1900-2300 on all days |
60 dB(A) * |
|
2300-0700 on all days |
50 dB(A) * |
* Only apply to operational noise without road traffic and construction
activities noise.
Table 4.4 Action and
limit levels for traffic noise
Time Period |
Action
Level |
Limit
Level |
Hotel, hostels & All domestic premises including
temporary housing accommodation |
When one documented complaint is received |
70 dB(A) |
Schools & Place of public Worship |
65 dB(A) |
Table 4.5 Event and
action plan for construction noise
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action
Level |
· Identify
source, investigate the causes of exceedance and propose
remedial measures; · Notify IEC and
DBO Contractor; · Report the
results of investigation to IEC, IC and DBO Contractor; · Discuss with
DBO Contractor and formulate remedial measures; · Increase
monitoring frequency to check mitigation effectiveness. |
· Review the
analysed results submitted by ET; · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly; · Supervise the
implementation of remedial measures. |
· Confirm
receipt of notification of failure in writing; · Notify DBO
Contractor; · Require DBO
Contractor to propose remedial measures for the analysed noise problem; · Ensure
remedial measures are properly implemented. |
· Submit noise
mitigation proposals to IEC; · Implement
noise mitigation proposals. |
Exceedance of Limit
Level |
· Identify
source; · Inform IEC,
IC, EPD and DBO Contractor; · Repeat
measurements to confirm findings; · Increase
monitoring frequency; · Carry out
analysis of Contractor’s working procedures to determine possible mitigation
to be implemented; · Inform IEC, IC
and EPD the causes and actions taken for exceedances; · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results; · If exceedance stops, cease additional monitoring. |
· Discuss
amongst IC, ET, and DBO Contractor on the potential remedial actions; · Review DBO
Contractors remedial actions whenever necessary to assure their effectiveness
and advise IC accordingly; · Supervise
implementation of remedial measures. |
· Confirm
receipt of notification of failure in writing; · Notify DBO
Contractor; · Require DBO
Contractor to propose remedial measures for the analysed noise problem; · Ensure
remedial measures properly implemented; · If exceedance continues, consider what portion of the work
is responsible and instruct DBO Contractor to stop that portion of works
until the exceedance is abated. |
· Take immediate
action to avoid further exceedance; · Submit
proposals for remedial actions to IEC
within 3 working days of notification; · Implement the
agreed proposals; · Resubmit proposals
if problem still not under control; · Stop the
relevant portion of works as determined by IC until the exceedance
is abated. |
Table 4.6 Event and
action plan for operational and traffic noise
Event |
ET |
IEC |
IC |
DBO Contractor |
Exceedance of Action
Level |
· Notify IEC and
DBO Contractor · Carry out
investigation · Report the
results of investigation to IEC and the DBO Contractor · Discuss with
the DBO Contractor and formulate remedial measures · Increase monitoring
frequency to check mitigation measures |
· Review with
analysed results submitted by ET · Review the
proposed remedial measures by DBO Contractor and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed noise problem · Ensure
remedial measures are properly implemented |
· Submit noise
mitigation proposals to IEC · Implement
noise mitigation proposals |
Exceedance of Limit
Level |
· Identify
source · Notify IEC,
IC, EPD and DBO Contractor · Repeat
measurement to confirm findings · Increase
monitoring frequency · Carry out
analysis of DBO Contractor’s working procedures to determine possible mitigation
to be implemented · Inform IEC,
IC, and EPD the causes and actions taken for the exceedances · Assess
effectiveness of DBO Contractor’s remedial actions and keep IEC, EPD and IC
informed of the results · If exceedance stops, cease additional monitoring |
· Discuss
amongst IC, ET Leader and DBO Contractor on the potential remedial actions. · Review DBO
Contractor’s remedial actions whenever necessary to assure their
effectiveness and advise IC accordingly · Supervise the
implementation of remedial measures |
· Confirm
receipt of notification of exceedance in writing · Notify DBO
Contractor · Require DBO
Contractor to propose remedial measures for the analysed noise problem · Ensure
remedial measures are properly implemented · If exceedance continues, consider what activity of the work
is responsible and instruct DBO Contractor to stop that activity of work
until the exceedance is abated |
· Take immediate
action to avoid further exceedance · Submit
proposals for remedial actions to IEC within 3 working days of notification · Implement the
agreed proposals · Resubmit
proposals if problem still not under control · Stop the
relevant activity of works as determined by the IC until the exceedance is abated |
The DBO Contractor shall
be responsible for implementation of the noise control and mitigation measures
during operational phase, which shall include, but not limited to, the
following:
· Quiet equipment and construction method should be employed;
· Only well-maintained plant shall be operated on site and plant shall be serviced regularly during the construction work;
· Machines and plant that may be in intermittent use (such as breakers) shall be shut down between work periods or should be throttled down to a minimum;
· Mobile plant shall be sited as far away from NSRs as possible;
· Material stockpiles and other structures shall be effectively utilised, where practicable, to screen noise from on-site construction activities;
· Silencers or mufflers on construction equipment should be properly fitted and maintained during the construction works.
Potential water pollution sources arising from construction activities include sources mainly from land-based activities, such as construction site runoff; sewage effluent due to workforce on site; accidental spillage of chemical; drainage diversion; and groundwater seepage.
Potential water pollution sources arising from operational include sources mainly from land-based activities, such as seepage of leachate, accidental Leakage of leachate and erosion.
The EIA Report has assessed the water quality impacts caused
by the construction and operation of NENT Landfill Extension. Mitigation measures have been recommended in
the EIA to ensure compliance with the relevant legislative requirements. These mitigation measures are summarised in
following sections. An implementation schedule of the recommended mitigation
measures is presented in Appendix
C3.
5.2.1 Construction Phase
5.2.1.1 Construction Site Runoff
In accordance with the Practice Note for Professional Persons on Construction Site Drainage, Environmental Protection Department, 1994 (ProPECC PN 1/94), and DSD Technical Circular TC14/2000, construction phase precautionary measures as presented in Appendix C3 shall be implemented where necessary. By adopting the above precautionary measures with Best Management Practices (BMPs) it is anticipated that the impacts of runoff from the construction site will be reduced to satisfactory levels before discharges.
The construction runoff discharged from the landfill site shall fully comply with the standards stated in Section 5.2 of the EIA report, otherwise the discharge shall be collected and conveyed to the on-site leachate treatment plant.
5.2.1.2 Sewage from Workforce
Portable chemical toilets and sewage holding tanks will be provided for handling the sewage generated by the workforce. A licensed contractor will be employed to provide appropriate and adequate portable toilets and be responsible for appropriate disposal and maintenance.
5.2.1.3 Accidental Spillage of Chemical
Any service workshops and maintenance facilities will be located within a bunding area, and sumps and oil interceptors will be provided. Maintenance of equipment involving activities with potential for leakage and spillage will only be undertaken within the areas appropriately equipped to control these discharges.
5.2.2 Operational Phase
5.2.2.1 Contingency Plan on Accidental Leakage of Leachate
Existing
Contingency Plan for Groundwater Contamination
The existing Contingency Plan is comprehensive and well-developed and will be used as basis for developing the Contingency Plan for the extension site. The parameters to be monitored include groundwater level and groundwater quality. The objective of the monitoring programme is to ensure that the trigger levels below are not exceeded.
Ammonia Nitrogen : 5 mg/L
COD : 30 mg/L
In the event that the above trigger levels are exceeded, the DBO Contractor will implement a Corrective Action Programme, which shall include:
· groundwater interception and diversion; and
· groundwater extraction (by active pumping of leachate from leachate and groundwater collection layers) and treatment prior to discharge.
Proposed Modifications to Contingency Plan for Groundwater
Contamination
Potential actions to be taken in case of identification of groundwater contamination should also include:
· Installation of additional ground-water monitoring well;
· Increased frequency of ground-water quality testing;
· Installation of ground-water extraction wells to remove contaminated groundwater for treatment;
· Installation of subsurface barriers, such as bentonite;
· Detailed investigation of the potential impact to be performed within six months of the first detection of the justified impact.
Contingency Plan for Surface Water Contamination
Surface water monitoring will be conducted to keep the ammonia-nitrogen and COD below the following trigger levels:
Ammonia Nitrogen : 0.5 mg/L
COD : 30 mg/L
Suspended Solid : 20 mg/L.
In the event that any one of the above parameters was exceeded, the landfill operation should implement a Corrective Action Programme. The key elements shall include:
· Surface water interception and temporary storage of the contaminated surface water;
· Installation of surface barriers, such as sand bund along the surface water channel / site boundary to avoid overflow off-site.
· Active pumping of the contaminated surface water to the leachate lagoons / leachate recirculation system / on-site leachate treatment plant;
· Additional monitoring locations will be selected to determine the pollution source;
· Installation of surface barriers, such as intercepting bund to separate the active and inactive tipping area.
· Change of working methods to prevent surface water contamination; and
· Implementation of diversionary works.
5.2.2.2 Erosion Control
The DBO Contractor shall devise a soil erosion control plan during the detailed design stage so as to define the site-specific measures and procedures (including the specific operation plan, implementation frequency, monitoring procedures, maintenance schedules, etc). Such requirement shall be specified in contract documents. Appendix C3 summarizes the most popular erosion control methods for reference.
5.2.2.3 Surface Water Drainage System
A temporary surface water drainage system to manage runoff will be adopted during construction and operation. It consists of perimeter channels around the site perimeter. It will collect surface water from higher elevations to lower elevations and ultimately to the discharge point. Details of surface water drainage system are included in Appendix C3.
The surface flow discharge from the landfill site shall fully comply with the standards stated in Section 5.2 of the EIA report, otherwise the contaminated surface flow shall be collected and disposed of to the on-site leachate treatment plant.
5.3 Leachate Monitoring
The DBO Contractor shall develop and operate a programme of monitoring which shall record the progressive generation of leachate at the NENT Landfill Extension in accordance with the following objectives:
· To determine the level of leachate within the landfill;
· To determine the quality of leachate arising from the landfill;
· To determine the quantity of leachate arising from the landfill and being treated;
· To monitor the quantity and quality of treated leachate from the leachate treatment works before discharging into leachate pipeline connecting to Shek Wu Hui Sewage Treatment Plant;
· To ascertain the landfill characteristics and effectiveness of the leachate treatment works.
The leachate monitoring programme shall commence at the start of landfill operations and continue until the issue of the Aftercare Certificate. The programme shall be developed with in-built flexibility to allow for modification during the development of the leachate treatment works and any modifications to the monitoring of the quality and quantity of leachate generated.
5.3.1 Equipment
Routine sampling and on-site measurements of leachate quality shall be carried out with appropriate equipment which include:
· Portable thermometer, pH and electrical conductivity (EC) meter
· Sample bottle of glass or PET of volume not less than 1 litre
· Flowmeters
At the leachate collection point, the submersible pump shall be used to discharge leachate flow from the leachate removal chamber. Level sensors shall be incorporated into the side slope riser pipe for pump control and measurement of leachate level. In addition, a dipstick and measuring tape shall be used to determine (in-situ) normal leachate levels if the level sensor is not operative.
5.3.2 Calibration and Maintenance
The DBO Contractor shall ensure that all equipment are calibrated and maintained according to manufacturer’s instructions. Routine maintenance shall be carried out in strict accordance with the manufacturer’s requirements. Where calibration intervals are not specified by the equipment manufacturer, the length of time between calibration periods shall not be greater than 6 months.
An inspection procedure shall be established to ensure that the frequency of maintenance is regularised for each equipment. Results from the monitoring programme shall be used to assist in the ongoing operation of the leachate treatment works to ensure that the facility is being operated under the optimum conditions, and that the leachate discharge complies with the trigger levels specified in Section 5.3.8.
5.3.3 Procedures
The DBO Contractor shall monitor leachate levels within the landfill using calibrated submersible level sensors incorporated into the side slope riser pipe.
Quantity of raw leachate shall be monitored using in-line flow meters installed in the pipe. The flow meters shall be designed and constructed to determine the volume and rate of leachate leaving the landfill site to an accuracy and precision of within +/- 1%.
At the same locations, the leachate shall also be monitored periodically to assess leachate quality produced within operational areas and after treatment. This shall be achieved using in-line sampling valves/taps. The design and construction of these valves/taps shall be such that samples of leachate of between 1 and 25 litres can be readily and easily obtained without sampling rates being too high resulting in unacceptably-high levels of splashing or too low making the duration of sampling unacceptably long.
The DBO Contractor shall use the groundwater drainage layer to detect any leachate escaping through the liner system. The detection system shall involve daily sampling at the groundwater discharge point (shown as Leachate Leakage Detector) and the groundwater monitoring boreholes.
All leachate samples shall be collected and transported to a HOKLAS accredited laboratory as soon after sampling as possible. Appropriate pre-treatment of samples shall be prepared in respect of the analytical parameters, with due regard to its holding times.
Leachate quality shall be monitored as a feedback to the operation for optimisation of the leachate treatment works and to establish its trend over the life of the landfill. The programmes shall generate data to support the establishment of a procedure for the necessary treatment and safe disposal of effluent from NENT Landfill Extension.
The following parameters shall be measured in accordance with the standards contained within the Specification:
Table 5.1
Programme A |
Programme B |
||||
Parameters |
Detection
Limit |
Frequency |
Parameters |
Detection
Limit |
Frequency |
Temperature * |
0.1°C |
Weekly basis initially and then
monthly when settled values are obtained for the first 3 years of NENT
Landfill Extension operation |
Mg |
50 mg/L |
Monthly basis initially and then 3
monthly Intervals when settled values are obtained for the first 3 years of
NENT Landfill Extension operation |
pH * |
0.1 |
Ca |
50 mg/L |
||
Electrical conductivity * |
1 mS/cm |
K |
50 mg/L |
||
COD |
10 mg/L |
Fe |
50 mg/L |
||
BOD5 |
3 mg/L |
Ni |
1 mg/L |
||
TOC |
1 mg/L |
Zn |
10 mg/L |
||
SS |
0.1 mg/L |
Mn |
1 mg/L |
||
Ammonia-nitrogen |
0.2 mg/L |
Cu |
1 mg/L |
||
Nitrate |
0.5 mg/L |
Pb |
1 mg/L |
||
Nitrite |
0.5 mg/L |
Cd |
0.2 mg/L |
||
Total Nitrogen |
0.4 mg/L |
|
|
||
Sulphate |
5 mg/L |
|
|
||
Phosphate |
0.01 mg/L |
|
|
||
Chloride |
0.5 mg/L |
|
|
||
Sodium |
50 mg/L |
|
|
||
Alkalinity |
1 mg/L |
|
|
||
Volatile fatty Acids |
2 mg/L |
|
|
*
On-site measurement
Table 52
Parameters |
Detection Limit |
Parameters |
Detection Limit |
Frequency |
Temperature |
0.1°C |
Phosphate |
0.01 mg/L |
Quarterly Basis after the first 3
years of NENT Landfill Extension operation |
pH |
0.1 |
Chloride |
0.5 mg/L |
|
COD |
10 mg/L |
Sodium |
50 mg/L |
|
BOD5 |
3 mg/L |
Alkalinity |
1 mg/L |
|
SS |
0.1 mg/L |
Fe |
50 mg/L |
|
Ammonia-nitrogen |
0.2 mg/L |
Zn |
10 mg/L |
|
Nitrate |
0.5 mg/L |
Cu |
1 mg/L |
|
Total Nitrogen |
0.4 mg/L |
Cd |
0.2 mg/L |
|
Sulphate |
5 mg/L |
|
|
|
Suite 1 (Programme A and Programme B) shall be used to
establish the quality of leachate from each
collection point (i.e., before and after treatment) for the first 3 years of
NENT Landfill Extension operation, and
For leachate leakage detection, the DBO Contractor shall analyse the samples taken at the groundwater discharge point for ammonia-nitrogen, pH and conductivity. If necessary, COD shall be tested when high ammonia-nitrogen is detected at the groundwater discharge point. Samples shall be stored and preserved according to the guidelines of the approved accredited laboratory.
5.3.5 Frequency and Locations of Sampling
The DBO Contractor shall take raw leachate samples and treated leachate samples. The frequency and sampling locations summarized in Table 5.3.
Table 5.3 Frequency and
Locations of Sampling
Program |
Frequency |
Location |
|
Weekly
intervals initially and then monthly when settled values are obtained |
At new leachate
Collection Points (i.e prior to discharging points
at raw leachate lagoon for raw leachate
monitoring and final effluent holding lagoon for partially treated leachate monitoring) |
|
At monthly
intervals and then three monthly intervals when settled values are obtained
for the first three years of NENT Landfill Extension operation |
|
|
At
quarterly intervals after |
The DBO Contractor shall monitor levels of leachate continuously using calibrated submersible pressure transducers via data retrieving equipment. Daily records of leachate production shall be maintained via data logging flow meters for all abstraction of liquid from the site and leachate quantities leaving the site.
The DBO Contractor shall determine the locations of leachate monitoring points and submit the proposed plan to the Independent Consultant for approval.
5.3.6 Results
All sample containers shall be clearly marked, and identified with relevant sampling information. In addition, all monitoring results and observations made at time of sampling shall be recorded in a field data sheet specifically allocated to that sampling task. The following information shall be recorded on each sampling visit:
· Sampling point;
· Data and time of sample collection;
· Name of technician carrying out the sampling;
· Weather conditions and ambient temperature;
· General appearance, condition and temperature of the water body;
· Sampling device and method used;
· Sample preservation used;
· Storage requirements adopted;
· Space for listing analytical determinations.
5.3.7 Leachate Leakage Detection
Facilities to detect leakage within a 24-hr period shall be placed in the manner and positions specified and be monitored daily for the presence of leachate or contaminated water.
The DBO Contractor shall operate a programme of monitoring with the following objectives:
· Determine the level of leachate within the landfill;
· Determine the quality of leachate from the landfill;
· Determine the quantity of leachate from the landfill.
The DBO Contractor shall monitor the levels of leachate continuously at the leachate collection point through the use of calibrated submersible level sensors via data retrieving equipment. The level of leachate at any point within the landfill shall not exceed 1m height above the top of the primary barrier of the landfill liner system.
The standards for discharge of treated leachate from the leachate treatment works into the pipeline leading into Shek Wu Hui Sewage Treatment Works (SWHSTW) are given in Table 1 of the Water Pollution Control Ordinance (WPCO) Technical Memorandum – Standards for Effluent Discharged into Drainage and Sewerage System, Inland and Coastal Waters prepared by the EPD, with the exception for the following discharge limits.
Total Nitrogen : |
200 mg/L |
COD : |
2000 mg/L |
BOD : |
400 mg/L |
Ammonia-nitrogen : |
5 mg/L |
SS : |
400 mg/L |
|
|
Treated leachate shall be discharged to the leachate pipeline leading to the SWHSTW. The leachate generated by the NENT Landfill Extension has been estimated. Under normal meteorological condition (i.e. with an average annual rainfall of 1,875 mm, data taken from Ta Kwu Ling Station from 1999 to 2005), the peak leachate flow rate from restored NENT Landfill and NENT Landfill Extension (under fully operation in Year 10) is estimated to be (265+860 =) 1,105 m3 /day in wet season, which is within the design capacity of the existing leachate treatment plant (i.e. 1,200 m3 /day). Nevertheless, daily records shall also be made for the quantity of leachate production.
5.3.9 Corrective Action
If the trigger levels in Section 5.3.8 are exceeded, the DBO Contractor shall implement a Corrective Action Programme, which shall include:
· Leachate extraction;
· Phased development and closure to minimise the active area footprint;
· Temporary geosynthetic covers to minimize infiltration in active cells;
· Run-on and runoff control systems for active and closed areas;
· Low permeability final cover system to minimise infiltration during post-closure;
In event that the DBO Contractor detects leachate leakage (i.e. the trigger level is exceeded at the groundwater discharge point), the liquid shall be treated at the leachate treatment plant prior to discharge to the leachate pipeline leading to SWHSTW.
Groundwater Level
5.4.1 Introduction
Groundwater levels shall be monitored over the working life of the site to determine the following information:
· Natural seasonal variation in groundwater levels;
· Effects of any ground water abstraction;
· Identification of hydraulic gradients;
· Variation caused by the construction, operation or aftercare.
5.4.2 Equipment
A portable dip meter, not affected by condensation, shall be used to measure water depth and checked before use. The dip meter shall comprise a graduated tape and sonic indicator of water level.
5.4.3 Procedures
Water level measurements shall be carried out prior to any purging or sampling from monitoring holes.
The DBO Contractor shall take groundwater level measurements relative to a permanent fixed datum at a measured elevation at each location, situated and marked on the monitoring borehole casing or cover. Recorded levels shall be expressed as metres relative to Principal Datum, and the levels checked 3 times prior to recording the measurements.
5.4.4 Frequency and Locations of Sampling
All manual groundwater level measurements shall be carried out at least once a month.
In the event that automatic measuring equipment is installed, the associated data loggers shall be interrogated / downloaded at least on a monthly basis. The automatic monitoring equipment shall be calibrated monthly and periodic manual water level measurements shall be carried out to corroborate the measurements.
Monthly groundwater monitoring shall be carried out at specified points ED1-ED35 in accordance with Drawing No. 24315/13/504 unless otherwise approved by the IC.
5.4.5 Results
All manual water level measurements shall be recorded relative to both monitoring borehole datum and Principal Datum. All automatic monitoring equipment shall be in a form that can be input to computer and displayed in numerical or graphical form. Results shall include site name; unique monitoring borehole reference or location code; date and water level in metres below monitoring borehole datum and to Principal Datum.
Groundwater Quality
5.4.6 Equipment
The criteria for selection of appropriate equipment shall depend upon the purpose of the sampling exercise, the site characterisation and the parameters that are to be analysed. This shall be assessed using the following criteria:
· Required sampling accuracy and precision
· Sampling frequency;
· Sampler construction material;
· Required head;
· Required discharge rate;
· Reliability and ease of maintenance, including availability of spares.
Teflon and/or stainless steel samplers (e.g. bailers) shall be used to sample groundwater.
Where sampling relies on the sample being pumped to the surface via tubing, the tubing used shall be Teflon, Teflon lined, or polypropylene. Bladder pumps shall be used to purge and to sample. Groundwater may be pumped from depths in excess of 100m below ground level, due to the depth to groundwater and the topographic level of the site.
5.4.7 Calibration and maintenance
Before each purging process, field meters shall be calibrated according to manufacturer specifications and the calibration results recorded in a calibration log file. All sampling equipment shall be thoroughly decontaminated as per standard sampling protocol prior to use.
5.4.8 Procedures
The DBO Contractor shall purge a monitoring borehole before a sample is taken in order that representative groundwater is sampled. This process shall be combined with field monitoring of determinants such as electrical conductivity, pH and temperature, so that stable sampling conditions can be achieved. If the water is contaminated it shall be contained and treated as leachate, otherwise abstracted groundwater shall be discharged to the surface water drainage system.
Samples shall be stored and preserved according to the guideline of approved accredited laboratory. Representative groundwater sample shall be collected, in approved receptacles as follows:
· Sampling containers shall be pre-rinsed with the water being collected, except in the case where specific determinations require preservatives in pre-prepared bottles;
· Glass containers shall be used for receipt of samples for organic analysis;
· Polyethylene containers shall be used for other determinants, except trace metals determinants such as mercury;
· Water shall be poured into sampling bottles carefully until filled completely, unless a specific volume is required by the analytical laboratory;
· A minimum of one litre sample shall be taken, unless otherwise specified;
· On-site measurement of EC, pH and temperature shall be carried out;
· On completion of sampling, portable equipment shall be removed from the borehole, and cleaned prior to use at next installation.
All sample bottles shall be labelled, samples shall be kept at for degrees centigrade and sent to the laboratory within specified holding times for the analytical methods. Samples shall be sent to the laboratory with appropriate chain-of-custody documentation.
Analysis of samples shall be carried out in accordance with methods described in American Society for Testing and Material (ASTM) or American Public Health Association (APHA) – American Water Works Association (AWWA) – Water Pollution Control Federation (WPCF).
5.4.9 Results
All sample containers shall be clearly marked to show the site name, location and date of sample collection. All results shall be presented as following:
· Site name;
· Unique sampling location reference;
· Time and date of the sampling;
· Name of the sampling technician;
· Weather conditions and air temperature;
· Appearance, condition and temperature of the water body;
· Sampling device used;
· On-site measurements of EC, pH and temperature;
· Volume of water purged prior to sampling;
· Physical description of the sample.
5.4.10 Analysis Parameters
The DBO Contractor shall measure the parameters according to the Table 5.4 in monthly basis. In the event of contamination being detected in the monthly monitoring programme, additional groundwater monitoring shall be carried out in weekly basis.
Table 5.4 Groundwater Monitoring
Parameters |
Detection
Limit |
Normal
Frequency |
Additional
Frequency |
Temperature |
0.1°C |
Monthly basis |
|
pH |
0.1 |
Monthly basis |
Weekly Basis |
Electrical conductivity |
1 mS/cm |
Monthly basis |
Weekly Basis |
COD |
10 mg/L |
Monthly basis |
Weekly Basis |
BOD5 |
3 mg/L |
Monthly basis |
Weekly Basis |
SS |
0.1 mg/L |
Monthly basis |
Weekly Basis |
Ammonia-nitrogen |
0.2 mg/L |
Monthly basis |
Weekly Basis |
Nitrate |
0.5 mg/L |
Monthly basis |
- |
TKN |
0.4 mg/L |
Monthly basis |
- |
Sulphate |
5 mg/L |
Monthly basis |
- |
Sulphite |
2 mg/L |
Monthly basis |
- |
Phosphate |
0.01 mg/L |
Monthly basis |
- |
Chloride |
0.5 mg/L |
- |
Weekly Basis |
Iron |
50 mg/L |
- |
Weekly Basis |
Zinc |
10 mg/L |
- |
Weekly Basis |
Coliform Count |
1 cfu/
100mL |
Monthly basis |
Weekly Basis |
5.4.11 Trigger Levels
The DBO Contractor shall propose a permanent monitoring network at the site to include the following:
· Detailed information on the hydrogeological regime;
· Details on seasonal groundwater level fluctuations and short-term variations in certain areas;
· Detailed baseline groundwater quality information;
· Detailed pumping test data for areas down gradient of the site where contaminants are likely to migrate.
The DBO Contractor shall monitor groundwater around the site to ensure that the following trigger levels are not exceeded Table 5.1.
5.4.12 Corrective Action
In the event that the above trigger levels are exceeded, the DBO Contractor shall implement a Corrective Action Programme, which shall include:
· Groundwater extraction and, if necessary, treatment prior to discharge;
· Groundwater interception and diversion.
5.5.1 Introduction
The DBO
Contractor shall carry out surface water monitoring from the commencement of
the works until the issue of the Aftercare Certificate in accordance with the
following objectives:
· To assess the performance of the
registered design, where: surface water leaves the site and/or the landfill
boundary; surface water leaves an operational area; and surface water leaves
areas of potential contamination e.g., waste reception area, vehicle and wheel
washing, haul route, vehicle servicing, etc.
· To ensure no long-term
deterioration in surface water quality adjacent to the site;
· To provide data for the design
and to monitor the effectiveness of any remedial measures which may be
necessary in the event of excessive leachate
migration or liner failure.
Surface
water monitoring stations shall be established in and around the site as part
of the monitoring programme.
5.5.2
Equipment
For monitoring surface water quality, the
DBO Contractor shall use the following sampling and measuring equipment:
· Varying water sample containers,
as appropriate to the type of analysis being determined, fabricated from
polyethylene, polypropylene, polycarbonate, aluminium, stainless steel or glass
o
Glass containers for organic constituents, but where major constituents
of glass are to be analysed (e.g. sodium, potassium, boron, silicon and trace
metallic impurities), glass containers shall not be used.
o
Polyethylene containers shall not be used for trace metallic impurities
such as mercury.
· Silicon sieve/disposable filters
for removal of suspended solids
· Thermometer with a range of 0-50°C
· Digital pH meter
· Electrical conductivity meter
A clamp, pole or string shall be attached to the bottle if the water poses
a threat to the sampling technician or if direct contact is likely to be made
with skin. However, in all situations, gloves shall be worn as a matter of
routine when sampling potentially-contaminated water.
The following equipment or the approved equivalents shall be provided
for monitoring flow:
· IS32 flow monitor complete with Druck transducer capable of measuring parameters of depth
and velocity at specified intervals, with trip mode built-in.
· Velocity calibrator – Montec 3013 portable Doppler measurement for in-situ
calibrations of velocity. A 1.25m logging wand shall be used for recording
in-situ measurements.
· Monitoring software –
specifically designed for use with IS32 and Montec
3013, to produce depth, velocity and discharge graphs, as well as tabulated
data.
5.5.3
Calibration and Maintenance
Clean,
pre-conditioned/washed sample containers shall be used during the sampling
programme. Sample containers shall be used only once with the exception of
glass containers appropriately decontaminated at the analytical laboratory
prior to use. All sampling equipment including open-mouthed collection vessels
(buckets and cans) and sieves shall be decontaminated prior to use between
sample points to prevent cross contamination. Decontamination procedures
involve the use of laboratory grade detergent and rinsing in de-ionized water.
Sample bottles that contain chemical preservatives shall not be rinsed or
cleansed in any way.
Thermometers
shall be rinsed with de-ionized water and then wiped with disposable towels immediately
after use before being replaced in the carrying case.
All flow measuring equipment shall be calibrated according to the
manufacturer’s specifications.
5.5.4
Procedures
The DBO
Contractor shall undertake sampling of surface water quality with reference to
the following documents:
· British Standard Institution
(BSI) BS6068: 1981 Water Quality Sampling Section 6.1. Guidance on the Design
of Sampling Programmes
· International Standard
Organisation (SO) ISO 5667-6 1990 Guidance on Sampling of Rivers and Streams
· BSI, BS 6068 1983 Water Quality
Section 6.2 Guidance on Sampling Techniques. Health and Safety Executive
· BSI, BS 6068: 1986 Water Quality
Section 6.3 Guidance on the Preservation and Handling of Samples (International
Standards Organisation ISO 5667/3 – 1985 Water quality – Sampling – Part 3:
Guidance on the Preservation and Handling of Samples).
Before sampling, the
flow rate of the stream/river shall be determined and the water and air
temperature, pH and electrical conductivity shall be measured and recorded.
All the precautions
outlined in the Specification for avoiding contamination during sampling shall
be taken, for example, pre-rinsing sampling containers (excluding those
containers which are preserved by certain type of chemicals) with the surface
water to be collected. In addition, appropriate health and safety precautions
including the wearing of protective waterproof gloves shall be followed.
In general, samples
shall be collected from within 500mm of the water surface. Samples shall be
collected within an open mouthed vessel with the lip pointing upstream. The
sample shall be filtered as appropriate. Alternatively the sample shall be
collected directly into the sample container. Sampling of the surface film
layer shall be avoided during the sampling programme.
During sample
collection, care shall be taken so that air is not introduced into the samples
thereby altering the relative compositions of the determinants. Once the sample
bottle is filled to the top with no remaining air space the lid shall be
securely screwed on. Where samples are to be preserved with acid or alkalis
prior to transport to the laboratory, the sample bottles shall be filled to the
level specified by the analytical laboratory.
Samples shall be
transported to the laboratory for analysis as soon as possible after the sample
is collected, since the longevity of some of the sample determinants is
limited. All samples shall be stored at 4°C and
transported to the laboratory within 48 hours from sampling.
Analyses shall be carried out in accordance with methods described in
ASTM or APHA – AWWA – WPCF Standard.
Flow measurements shall also be taken continuously using automatic
logging equipment.
The DBO Contractor shall measure the all parameters according to Table 5.5 in monthly basis. In the event of contamination being detected in the monthly monitoring programme, additional surface water monitoring shall be carried out in weekly basis.
Table 5.5 Surface Water Monitoring
Parameters |
Detection Limit |
Normal Frequency |
Additional Frequency |
pH |
0.1 |
Monthly
basis |
Weekly Basis |
Electrical conductivity |
1 mS/cm |
Monthly basis |
Weekly Basis |
Alkalinity |
1
mg/L |
Monthly basis |
- |
COD |
10
mg/L |
Monthly basis |
Weekly Basis |
BOD5 |
3
mg/L |
Monthly basis |
Weekly Basis |
TOC |
1
mg/L |
Monthly basis |
Weekly Basis |
SS |
0.1
mg/L |
Monthly basis |
Weekly Basis |
Ammonia-nitrogen |
0.2
mg/L |
Monthly basis |
Weekly Basis |
TKN |
0.4
mg/L |
Monthly basis |
- |
Nitrate |
0.5
mg/L |
Monthly basis |
- |
Sulphate |
5
mg/L |
Monthly basis |
- |
Sulphite |
2
mg/L |
Monthly basis |
- |
Phosphate |
0.01
mg/L |
Monthly basis |
- |
Chloride |
0.5
mg/L |
Monthly basis |
- |
Sodium |
50 mg/L |
Monthly basis |
- |
Mg |
50 mg/L |
Monthly basis |
- |
Ca |
50 mg/L |
Monthly basis |
- |
K |
50 mg/L |
Monthly basis |
- |
Fe |
50 mg/L |
Monthly basis |
Weekly Basis |
Ni |
1 mg/L |
Monthly basis |
- |
Zn |
10 mg/L |
Monthly basis |
Weekly Basis |
Mn |
1 mg/L |
Monthly basis |
- |
Cu |
1 mg/L |
Monthly basis |
- |
Pb |
1 mg/L |
Monthly basis |
- |
Cd |
0.2
mg/L |
Monthly basis |
- |
Coliform Count |
1 cfu/ 100mL |
Monthly basis |
Weekly Basis |
Oil and Gease |
5
mg/L |
Monthly basis |
- |
Surface water flow shall be monitored continuously using automatic data
logging equipment. Following periods of heavy rainfall, flow shall be monitored
weekly and more frequently to determine peak discharge rates.
5.5.6
Locations of Sampling
Monthly surface water
monitoring shall be carried out at specified points WM1 (Upstream of Lin Ma
Hang) and WM2 (
5.5.7
Results
Upon completion of each sampling exercise,
the sample containers shall be clearly labelled with site name; sampling
location reference; date and time of collection and sample number.
In addition, the
sampling technician shall record any abnormality which may affect water quality
in their record notebooks. The sampling
record shall include the following details:
· Sampling site and sampling point;
· Date and time of collection;
· Name of sampling technician;
· Weather conditions and air
temperature;
· Appearance, condition and
temperature of the water body;
· Sampling method and sampling
device used;
· Sample preservation;
· Storage requirements;
· List of parameters (with space
for the analytical results).
The DBO
Contractor shall conduct the surface water monitoring programme in order to
keep ammonia-nitrogen and COD below the following trigger levels:
Ammonia-nitrogen
: 0.5mg/L
COD : 30 mg/L
In addition, suspended solids
concentrations for surface waters leaving the site shall not exceed
20mg/L.
5.5.9
Corrective Action
In the event that these trigger
levels are exceeded, the DBO Contractor shall implement a Corrective Action
Programme, which shall include:
· Sampling upstream into landfill
to trace the source;
· Surface water interception and
treatment prior to discharge;
· Changes to working methods to
prevent surface water contamination;
· Diversionary works.
Where
analytical results indicate the presence of contamination, additional
monitoring locations shall be selected to determine the pollution source. The
DBO Contractor shall implement procedures in accordance with the corrective
action plan to mitigate any contamination sources identified, or discharge the
surface water to the leachate treatment plant.
The Action and Limit levels for surface and ground water quality are defined in Table 5.6 and Table 5.7. Should non-compliance of the criteria occur, action in accordance with the Action Plan in Table 5.8 shall be carried out.
Table 5.6 Action and Limit Levels for Surface Water
Quality
Parameters |
Action |
Limit |
|
Construction |
DO in mg L-1 (Surface, Middle & Bottom) |
Surface and Middle 5 percentile of baseline data for surface and middle layer Bottom 5 percentile of baseline data for bottom layer |
Surface and Middle 4 mg L-1 or 1%-ile of baseline data for surface and middle layer Bottom 2 mg L-1 or 1%-ile of baseline data for bottom
layer |
pH (depth averaged), Turbidity in
NTU (depth-averaged), SS in mg L-1 (depth-averaged) |
95 percentile of baseline data or 120% of
upstream control station's pH, Turbidity, SS at the same tide of the same day |
99 percentile of baseline or 130% of upstream
control station's pH, Turbidity, SS at the same tide of the same day |
|
Operation |
COD, Ammonia-nitrogen |
--- |