This section
presents an assessment of the potential air quality impacts arising from the construction,
operation, restoration and aftercare of the proposed Extension.
During the
construction phase, dust nuisance arising from blasting, excavation and
filling, slope stabilisation, site formation, stone crushing and vehicle
movements on the site is a potential concern. Potential sources of air quality and
odour impacts during the operation, restoration and aftercare phases of the
Extension will include waste filling activities, the landfill gas (LFG) treatment
facility, the new leachate treatment plant (LTP) and
the LFG generator.
Representative Air
Sensitive Receivers (ASRs) have been identified and an assessment of the
potential air quality impacts has been conducted. Adjacent emission sources such as
industrial emissions from Tseung Kwan O Industrial
Estate (TKOIE), restoration of existing SENT Landfill and the future operations
in TKO Area 137 during construction operation/restoration and aftercare phases
of the Extension have also been taken into consideration. Mitigation measures have been
recommended, where appropriate, to reduce the impacts.
The principal legislation for the
management of air quality in
Table 4.2a Hong
Kong Air Quality Objectives (mg m-3) (a)
Air Pollutant |
Averaging Time |
|||
|
1 Hour (b) |
8 Hour (c) |
24 Hour (c) |
1 Year (d) |
Total Suspended Particulates (TSP) |
- |
- |
260 |
80 |
Respirable Suspended Particulates (RSP) (e) |
- |
- |
180 |
55 |
|
800 |
- |
350 |
80 |
Nitrogen Dioxide (NO2) |
300 |
- |
150 |
80 |
Carbon Monoxide (CO) |
30,000 |
10,000 |
- |
- |
Notes: (a)
Measured
at 298K (25°C) and 101.325 kPa (one
atmosphere) (b)
Not
to be exceeded more than three times per year (c)
Not
to be exceeded more than once per year (d)
Arithmetic
means (e)
Suspended
airborne particulates with a nominal aerodynamic diameter of 10 micrometres
or smaller |
The Technical Memorandum on
Environmental Impact Assessment Process (EIAO-TM) also includes an hourly TSP criterion of 500 mg m-3 for construction dust
impacts and an odour criterion of 5 Odour Units (OUs)
for a 5-second averaging period for odour impact assessment.
The criteria outlined in Table 4.2a and in the EIAO-TM were used to assess the
potential air quality impacts associated with the Extension.
The measures set out in the Air Pollution Control (Construction Dust)
Regulations should be followed to reduce dust impacts from this Project.
If a stone crushing plant of a capacity
greater than 5,000 tonnes per year is needed, a licence must be obtained under
the Air Pollution Control (Specified
Process) Regulation and the control measures set out in the Guidance Note on the Best Practicable Means
for Mineral Works (Stone Crushing Plants) (BPM 11/1) should be followed.
Should the fuel consumption rate of a
premises/process with chimney emission exceed the specified fuel consumption
rates stated in the Air Pollution Control
(Furnaces, Ovens and chimneys) (Installation and Alternation) Regulations,
an approval of chimney installation/alternation should be obtained from the EPD
prior to the operation.
For those pollutants not covered by the HKAQOs, health risk criteria recommended in the
international guidelines, such as those promulgated by the World Health
Organisation (WHO), the United States Environmental Protection Agency
(US EPA) and the California Air Resources Board (CARB) have been
considered. The criteria/guideline
values were selected in the following order of preference:
·
WHO;
·
US
EPA; and
·
CARB.
Of the non-criteria substances emitted during
the operation/restoration and aftercare phases, benzene and vinyl chloride are
considered carcinogenic. Table
4.2b shows the Unit Risk Factors (URFs) for the
carcinogenic substances considered in this assessment.
Table 4.2b Guideline
Unit Risk Factors for Carcinogenic Substances
Substance |
Unit Risk Factor (mg m-3)-1 |
Benzene |
7.8x10-6 (a) |
Vinyl Chloride |
8.8x10-6 (b) |
Notes: (a)
Reference
to US EPA – Integrated Risk Information System – On-line data as in October
2007. The URF of benzene is in a
range of 2.2x10-6 – 7.8x10-6 per mg m-3. Upper range of URF is adopted for the
worst case assessment
(http://cfpub.epa.gov/iris/quickview.cfm?substance_nmbr=0276). (b)
Reference
to US EPA – Integrated Risk Information System – On-line data as in October
2007. The URFs
of vinyl chloride are 4.4x10-6 per mg m-3 for the exposure during
adulthood and 8.8x10-6 per mg m-3 for the exposure from birth. Higher URF is adopted for the worst
case assessment (http://cfpub.epa.gov/iris/quickview.cfm?substance_nmbr=1001). |
The risk assessment guidelines for
assessing the carcinogenic health risks from exposure to air toxics are
summarised in Table 4.2c.
Table 4.2c Risk
Assessment Guidelines for the Assessment of Carcinogenic Health Risks
Acceptability of Cancer
Risk |
Estimated Individual
Lifetime Cancer Risk Level |
Significant |
> 10-4 |
Risk should be reduced to As Low As Reasonably
Practicable (ALARP) |
> 10-6 – 10-4 |
Insignificant |
£ 10-6 |
Benzene and vinyl chloride have the
potential to cause chronic and/or acute impacts for long and/or short-term
exposures, respectively. The
reference chronic and acute concentrations of these pollutants are summarised
in Table 4.2d.
Table 4.2d Guideline
Values for Chronic and Acute Reference Concentrations
Substance |
Chronic Reference Concentration (Annual Average in mg m-3) |
Acute Reference Concentration (Hourly Average in mg m-3) |
Benzene |
30 (a) |
1,300 (b) |
Vinyl Chloride |
100 (a) |
1.8x105 (b) |
Notes: (a)
US
EPA – Integrated Risk Information System – On-line data as in October 2007 (b)
California
Environmental Protection Agency, Air Resources Board (ARB)/Office of
Environmental Health Hazard Assessment (OEHHA)
(http://www.oehha.ca.gov/air/acute_rels/allAcRELs.html). |
The risk assessment guidelines also recommend
criteria to assess the acceptability of chronic and acute non-cancer health
risks and these are summarised in Tables 4.2e and 4.2f,
respectively.
Table 4.2e Acceptability
of Chronic Non-Cancer Health Risks
Acceptability |
Assessment Results (a) |
Chronic non-cancer risks are considered
“Insignificant” |
ACA £ RCc |
Chronic non-cancer health risks are
considered “Significant”.
A more detailed assessment of the control requirements and further mitigation
measures are needed. |
ACA > RCc |
Note: (a)
ACA
and RCc represent annual average
concentration and chronic reference concentration, respectively. |
Table 4.2f Acceptability
of Acute Non-cancer Health Risks
Acceptability |
Assessment Results (a) |
Acute non-cancer risks are considered “Insignificant” |
ACHM £ RCA |
Acute non-cancer health risks are considered “Significant”. A more detailed assessment of the
control requirements and further mitigation measures are needed. |
ACHM > RCA |
Note: (a)
ACHM
and RCA represent hourly average and acute reference
concentrations, respectively. |
The proposed Extension is located to the south
of the existing SENT Landfill. The
TKOIE is located to the
No residential dwellings have been
identified within 500m of the Extension site boundary. The nearest residential use (LOHAS
Park), which is under construction, is located at about 1.8 km from the
Extension site boundary.
The existing air quality in the vicinity
of the Extension is affected by:
·
Emissions
from facilities in the TKOIE;
·
Dust,
odour and stack emissions from the SENT Landfill;
·
Dust
nuisance from TKO Area 137 Fill Bank;
·
Vehicular
emissions on Wan Po Road (both to and from the SENT Landfill and TKO Area 137
Fill Bank); and
·
Background
air quality in the Pearl River Delta.
During the operation of the Extension, the
existing SENT Landfill will be closed.
A capping system which will comprise (from bottom to top), as soil
layer, a non-woven geotextile, an HDPE liner
(impermeable liner), a sub-soil drainage layer and a final cover soil layer,
will be installed. The LFG and leachate generated from the existing SENT Landfill will be
collected by the leachate and LFG collection system
and conveyed to the new LTP and LFG treatment facility for treatment. Therefore, no odour will be anticipated
to be emitted from the restored area of the existing SENT Landfill.
EPD does not operate any Air Quality
Monitoring Stations (AQMSs) in the Tseung Kwan O area.
For TSP, RSP, NO2
and SO2, the past six years (2001 - 2006) of air pollutant data([1]) recorded at the Kwun Tong
AQMS (see Table 4.3a), which is the
nearest EPD AQMS to the Extension, have been used to characterise the
background air quality for the impact assessment. For CO, the past six years (2001 – 2006)
of air pollutant data recorded at the Mongkok AQMS
have been used as no CO monitored at Kwun Tong AQMS.
Table 4.3a Background
Air Quality
Air Pollutant |
Background Concentration (mg m-3) |
Total Suspended
Particulates (TSP) |
78 (a) |
Respirable Suspended Particulates (RSP) |
57 (a) |
Nitrogen Dioxide (NO2) |
66 (a) |
Sulphur Dioxide (SO2) |
18 (a) |
Carbon Monoxide (CO) |
1,294 (b) |
Benzene |
2.1 (c) |
Vinyl Chloride |
5.1 (c) |
Notes: (a)
From
six years (2001-2006) annual average data on air pollutant concentrations
measured at the EPD Kwun Tong AQMS (http://www.epd-asg.gov.hk/english/report/aqr.php). (b)
Since
no CO data is recorded at EPD Kwun Tong AQMS,
therefore, the CO data recorded at Mongkok AQMS is
used. (c)
Reference
to Table 4.5f. The maximum average benzene and vinyl
chloride concentrations measured at the ambient VOC monitoring stations at the
existing SENT Landfill for the past 5 years (2002 – 2006) were used. |
Ambient benzene and vinyl chloride
concentrations are measured at the ambient monitoring stations at the existing
SENT Landfill. The locations of the
ambient monitoring stations are shown in Figure 4.3a. In accordance with the Environmental
Management Plan (EMP) of the existing SENT Landfill, benzene and vinyl chloride
levels are measured at quarterly intervals. The measured data of benzene and vinyl
chloride at the existing SENT Landfill monitoring stations were used to
establish the background concentrations of these pollutants in the Study Area
(see Table 4.3a).
As the existing SENT Landfill will be closed
during the operation of the Extension, there will be no other similar odour
sources identified within 500m of the Extension site boundary. Hence, no background odour is
anticipated.
Table
4.4a and Figure
4.4a show the ASRs or those buildings that may be affected. Representative ASRs were identified in
line with the requirements set out in the EIA
Study Brief (ESB-199/2004) and
Annex 12 of the EIAO-TM. The list includes existing and planned buildings within
500m of the Extension and ASRs along the Wan Po Road and Chiu Shun Road, in
accordance with the requirements of Section
3.4.1.2 of the EIA Study Brief. Planned developments were identified
with reference to the latest Outline Zoning Plans (No. S/TKO/15 gazetted in
November 2004).
For the assessment of construction dust
and gaseous emission, the Study Area is defined as 500m from the Extension site
boundary.
Table 4.4a Identified
Representative Air Sensitive Receivers
ASR |
Location |
Approx. Distance from Extension
Site Boundary (m) |
Type of Uses (a) |
Approx. Max. Height above Ground
(m) |
Construction Dust (d) |
Gaseous Emission (d) |
Odour |
A1-1 |
Proposed
C&DM Handling Facility |
150 |
I |
30
(c) |
Ö |
Ö |
Ö |
A1-2 (1) |
Planned
Industrial Uses in TKO 137 (south of Extension) – 1 |
10 |
I |
30
(c) |
Ö |
Ö |
Ö |
A1-2 (2) (b) |
Planned
Industrial Uses in TKO 137 (south of Extension) – 2 |
200 |
I |
30
(c) |
Ö |
Ö |
Ö |
A1-3 (1) |
Planned
Industrial Uses in TKO 137 (south of TVB City) – 1 |
90 |
I |
30
(c) |
Ö |
Ö |
Ö |
A1-3 (2) (b) |
Planned
Industrial Uses in TKO 137 (south of TVB City) - 2 |
200 |
I |
30
(c) |
Ö |
Ö |
Ö |
A2 |
TVB City |
110 |
C |
30 |
Ö |
Ö |
Ö |
A3 |
HAESL |
410 |
I |
30 |
Ö |
Ö |
Ö |
A4 |
HAECO
Component Overhaul Building |
470 |
I |
30 |
Ö |
Ö |
Ö |
A5 |
Exhibition
Services & Logistics Centre |
690 |
I |
30 |
- |
- |
Ö |
A6 |
Gammon
Skanska |
950 |
I |
30 |
- |
- |
Ö |
A7 |
Yan
Hing Machinery Industrial Building |
400 |
I |
30 |
Ö |
Ö |
Ö |
A8 |
Apple
Daily |
505 |
C |
30 |
Ö |
Ö |
Ö |
A9 |
Mei Ah
Industrial Building |
530 |
I |
30 |
- |
- |
Ö |
A10 |
Asia
Netcom |
590 |
C |
30 |
- |
- |
Ö |
A11 |
Wellcome
Storage |
580 |
I |
30 |
- |
- |
Ö |
A12 |
Avery
Dennison Machinery |
600 |
I |
30 |
- |
- |
Ö |
A13 |
Hitachi |
700 |
I |
30 |
- |
- |
Ö |
A14 |
Next
Media Co. Ltd |
740 |
C |
30 |
- |
- |
Ö |
A15 |
Varitronix |
850 |
I |
30 |
- |
- |
Ö |
A16 |
Four Seas
Food Processing Co. Ltd |
1,060 |
I |
30 |
- |
- |
Ö |
A17 |
Committed
HSBC Office |
1,000 |
C |
30 |
- |
- |
Ö |
A18 |
Eastern
Pacific Electronics |
1,250 |
I |
30 |
- |
- |
Ö |
A19 |
Committed
Tung Wah Group of Hospital Aided Primary & Secondary
School |
1,470 |
E |
20 |
- |
- |
Ö |
A20 |
LOHAS
Park |
1,830 |
R |
200 |
- |
- |
Ö |
A21 |
Chiaphua-Shinko
Centre |
1,860 |
I |
30 |
- |
- |
Ö |
A22 |
Shaw Film
Studios |
2,290 |
C |
30 |
- |
- |
Ö |
A23 |
Oscar by
the Sea |
3,160 |
R |
170 |
- |
- |
Ö |
A24 |
Tseung
Kwan O Sport Ground |
3,810 |
Rec |
1.5 |
- |
- |
Ö |
A25 |
Tseung
Kwan O Town Park |
4,050 |
Rec |
1.5 |
- |
- |
Ö |
A26 |
Leung
Sing Tak Primary School |
4,010 |
E |
20 |
- |
- |
Ö |
A27 |
Nan Fung
Plaza |
4,070 |
R |
130 |
- |
- |
Ö |
A28 |
St
Andrew’s Church |
4,160 |
Church |
20 |
- |
- |
Ö |
A29 |
Fung Ching Memorial Primary School |
4,190 |
E |
20 |
- |
- |
Ö |
A30 |
On Ning Garden |
4,260 |
R |
120 |
- |
- |
Ö |
A31 |
Sheung
Ning Playground |
4,240 |
Rec |
1.5 |
- |
- |
Ö |
A32 |
Tseung
Kwan O Swimming Pool |
4,530 |
Rec |
1.5 |
- |
- |
Ö |
A33 |
La Cite
Noble |
3,930 |
R |
140 |
- |
- |
Ö |
A34 |
Yuk Ming
Court |
3,980 |
R |
110 |
- |
- |
Ö |
A35 |
Ming Tak Estate |
4,130 |
R |
110 |
- |
- |
Ö |
A36 |
Tin Ha Wan
Village |
3,950 |
R |
10 |
- |
- |
Ö |
A37 |
Tseung
Kwan O Hospital |
4,260 |
Hospital |
25 |
- |
- |
Ö |
A38 |
Ocean
Shore Phase I |
3,900 |
R |
160 |
- |
- |
Ö |
A39 |
Choi Ming
Estate, Choi Yiu Court |
3,820 |
R |
155 |
- |
- |
Ö |
A40 |
Park Central
Block 1 |
3,530 |
R |
185 |
- |
- |
Ö |
A41 |
Bauhinia
Garden Block 5 |
3,200 |
R |
165 |
- |
- |
Ö |
A42 |
Heng Fa Chuen |
3,300 |
R |
70 |
- |
- |
Ö |
A43 |
Island Resort |
2,400 |
R |
160 |
- |
- |
Ö |
Notes: (a) I
= Industrial premises, R = Residential developments, C = Commercial premises,
and Rec = Recreational facilities (b) As
the type of industrial uses in the TKO Area 137 is not available (except the
C&DM Handling Facility) at the time of the EIA Study, the HKPSG recommended
setback distance of 200m from the major odour source (ie
the SENT Landfill Extension) is included. The potential air quality impact
within and outside the 200m buffer area has been assessed. (c) Planning
Department has been consulted with respect to the building height restriction
of TKO Area 137. It was agreed
that the consultant should assume that the maximum height of the buildings at
TKO Area 137 will be 30m. (d) Representative
ASRs within 500m from the Extension site boundary will be included in the
assessment of the construction dust impact and impact due to gaseous
emission. |
Nuisance from dust generating activities
has the potential to arise during construction. The major construction works include
blasting, slope stabilization, excavation and filling, site formation, stone
crushing and vehicle movements on the site. Blasting, materials handling during
slope cutting and site formation, rock crushing and wind erosion of the filled
area will be the major dust generating activities during the construction of
the Extension. The construction works area is shown in Figure 4.5a.
Blasting will
take place for the slope cutting at the area currently occupied by the TKO Area
137 for about 107 days between the third quarter of 2011 and end of 2012. One blast will be made each day. A total of about 320,000 m3
of rock will be generated and approximately 3,000 m3 of rock will be
generated per day. It should be
noted that all construction works will be ceased during the blasting due to
site constraint and safety reason.
Due to limited space
at the Extension site, most of the rocks will be exported off-site. A small rock crushing plant will be
employed on-site to crush the blasted rocks (about 155,800 m3) into
25mm – 100mm in size and used as leachate drainage
stones for the Project and the rest of the blasted rock will be broken down to
about 250 mm in size for disposal off-site. During this process, watering will be
carried out and no fugitive emission will be generated. Dust will be generated from the rock
crushing activities screening and at the conveyor transfer point. With the provision of enclosure for the
conveyor belt and watering at the conveyor transfer point, no fugitive dust
emission is anticipated. Other dust
control measures recommended in the Guidance
Note on the Best Practicable Means for Mineral Works (Stone Crushing Plants)
(BPM 11/1) will also be implemented at the rock crusher, and hence dust
will only be emitted from the crushing and screening processes.
Should the processing capacity of the rock
crusher exceeded 5,000 tonnes per day, it will be classified as a Specified
Process (SP) and a licence will be required for the operation under the Air Pollution Control (Specified Process)
Regulations.
About 770,000 m3
of excavated soil will also be generated during the slope cutting period
between the third quarter of 2011 and end of 2012 (around one and a half
years). Some of which will be
reused for site formation works (about 475,000 m3). Due to limited space at the Extension, a
small portion of the surplus soils (10,000 m3) will be stockpiled
on-site for subsequent use as daily or intermediate cover materials for the
Phase 1 operation of the Extension.
Throughout the construction period, good
site practices and dust control measures stipulated in the Air Pollution Control (Construction Dust) Regulations will be
implemented to reduce the dust emission as much as possible. The site-specific good site practices
and dust control measures are recommended in Section 4.8.1.
Section
3 details the activities
that will take place during operation and restoration of the Extension. As the restoration will take place
progressively, whilst operations are ongoing on other parts of the site, these
two phases have been considered together in the assessment.
The potential sources of air quality and
odour impacts arising from the Extension during the operational/restoration
phase include:
·
Gaseous
emissions from the new LFG treatment facility, the thermal oxidizer of the LTP
and generator at the new infrastructure area;
·
Vehicular
emissions from traffic associated with the Extension;
·
Fugitive
emissions from the active tipping face; and
·
Odour
emissions arising from Waste Filling Activities and Operation of LTP.
LFG is a by-product of the
waste decomposition process when this takes place under anaerobic
conditions. Typically, this
comprises methane (CH4), carbon dioxide (CO2) and trace
amounts of other gases (eg volatile organic compounds
(VOCs), hydrogen sulphide (H2S),
etc). The proportions of these
compounds vary over the life of the landfill and from landfill to
landfill. The quantity also varies
from little or none in the early years of operation, rising to a peak during
the operational period, before gradually declining over time following
restoration of the landfill.
During the operation/restoration phase,
the majority of the LFG generated will be collected by the extensive LFG
collection system and used on-site (as the first priority) or flared off. The LFG will be pre-treated (removal of
moisture) prior to utilization or flaring in order to minimize corrosion to the
equipment.
The LFG
treatment facility will comprise two flares (each with a maximum capacity of
10,000 m3 hr-1) located at the south-eastern
boundary of the site (see Figure 4.5b). During the operation/restoration phase,
the LFG collected will mainly be used in the LTP and LFG generator (IMW) to
supply power for the facilities in the Infrastructure Area and the remainder
will be diverted to the on-site utilization plant or flares at the LFG
treatment facility. Based on the
outline design of the LTP, the plant will consume a maximum of 3,125 m3
of LFG per hour and the LFG generator will consume about 1,500 m3 of
LFG per hour. If not utilized for
other beneficial uses, the remaining LFG (a maximum of 15,375 m3 hr-1)
will be flared. For the worst case
assessment, it is assumed that the LFG flares will be operated at their maximum
design capacity (ie 10,000 m3 hr-1 each). The combustion temperature of the flares
will be about 850°C. At
this temperature, methane, VOCs and the trace
pollutants (such as H2S) will be oxidised and destroyed. After flaring, trace amount of nitrogen
dioxide (NO2), carbon monoxide (CO), sulphur dioxide (SO2)
from the oxidation of H2S, benzene, vinyl chloride and non-methane
organic compound (NMOCs) will be emitted and the
potential impacts of these air pollutants have been assessed in the following
section.
Parameter |
Performance Standards |
Emission
limit for nitrogen oxides (NOx) |
11.28
mg m-3 (a) (b) |
Emission
limit for carbon monoxide (CO) |
28.19
mg m-3 (a) (b) |
Emission
limit for sulphur dioxide (SO2) |
1.55
mg m-3 (a) |
Emission
limit for benzene |
2.98x10-3
mg m-3 (a) (c) |
Emission
limit for vinyl chloride |
1.88x10-3
mg m-3 (a) (c) |
No.
of flares |
2 |
Stack
height |
25
m |
Stack
diameter |
3.8
m |
Exit
temperature (d) |
850°C |
Exhaust
gas flowrate |
499,582
m3 hr-1 (a) |
Exhaust
gas velocity |
12.24
m s-1 |
Notes: (a)
Emission limit of air pollutant in exhaust gas. For SO2, please refer to Annex A1 for detailed calculations. (b)
Emission limits were estimated based on the
specification of flares operating in the existing SENT Landfill. (c)
Emission limits for benzene and vinyl chloride were
estimated from the maximum concentrations of benzene and vinyl chloride in
raw LFG measured at the inlet of the flare at the existing SENT
Landfill. The maximum emissions
of vinyl chloride and benzene were 4.4 ppm and 5.6 ppm, respectively.
In accordance with the existing SENT Landfill Contract Specification,
at least 99% of VOC destruction efficiency should be maintained. The emission limits are estimated
based on the emission concentrations in the inlet, LFG flowrate,
exhaust flowrate and the VOC removal
efficiency. Please refer to Annex A1 for the detailed
calculations. |
The raw leachate
will be stripped in the ammonia stripping towers. The ammonia laden air and the exhaust
air of the enclosed tanks will be oxidised and destroyed in the thermal
oxidiser (which will operate at 850°C) prior to discharge to the
atmosphere. Under this combustion
temperature, the ammonia gas will be completely destroyed ([2]).
LFG will be used
as a fuel for the thermal oxidiser.
The estimated maximum LFG consumption will be 3,125 m3 hr-1
assuming that the LTP is operating at its maximum capacity of 1,500 m3d-1
([3]), and 50 m3 of LFG is required
for each cubic metre of leachate treated. A worst case assumption has been adopted
whereby the emissions of nitrogen oxides (NOx),
sulphur dioxide (SO2) (product of decomposition of any residual H2S
at high temperature), carbon monoxide (CO), benzene, vinyl chloride and NMOCs are assumed to be same as those for the flares (see Table 4.5a).
The physical parameters and emission data
of thermal oxidiser are summarized in Table
4.5b.
Table 4.5b Stack
Emissions and Physical Parameters of the Thermal Oxidiser
Parameter |
Thermal Oxidiser of the LTP |
Emission limit
for NOx |
28.4 mg m-3
(a) |
Emission limit
for CO |
70.91 mg m-3
(a) |
Emission limit
for SO2 |
3.9 mg
m-3 (a) |
Emission limit for
benzene |
7.51x10-3
mg m-3 (a) |
Emission limit
for vinyl chloride |
4.73x10-3 mg
m-3 (a) |
No. of Stack |
2 (one duty and
one standby) |
Stack height |
9.76 m (c) |
Stack diameter |
1.12 m (c) |
Exit
temperature |
171.6 °C (c) |
Exhaust gas velocity |
17.5 m s-1
(c) |
Exhaust gas flowrate |
62,068 m3
hr-1 |
Notes: (a)
All emission limits are under its exhaust gas
condition. (b)
Refer to the detailed calculations presented in Annex A1. (c)
With reference to the design of the Thermal Catalytic
Units of the existing Bioplant at SENT Landfill. |
A generator fuelled by LFG will be
installed to provide power for on-site plant and equipment. Taking account of the anticipated power requirements
of the infrastructure area of the Extension, the capacity of the generator will
be about 1MW which is similar to the generator used in the existing SENT
Landfill. The physical parameters
and emission data of generator, reference to the LFG generator operating in the
existing SENT Landfill, are summarized in Table
4.5c.
Table 4.5c Stack
Emissions and Physical Parameters of the LFG Generator
Parameter |
LFG Generator |
Engine power |
1MW (a) |
LFG input to
generator |
1,500 m3 hr-1
(a) |
Emission limit
for NOx |
0.14 lb mmBTU-1
(b) |
Emission limit
for CO |
0.44 lb mmBTU-1
(b) |
Emission limit
for SO2 |
0.045 lb mmBTU-1
(b) |
Emission limit
for benzene |
2.1x10-5
lb mmBTU-1 (b) |
Emission limit
for vinyl chloride |
1.6x10-6
lb mmBTU-1 (b) |
No. of Stack |
2 (one duty and
one standby) |
Stack height |
28 m |
Stack diameter |
0.305 m (a) |
Exit
temperature |
454°C (a) |
Exhaust gas
velocity |
48.6 m s-1
(a) |
Notes: (a)
Reference to the generator being operated at the
existing SENT Landfill. (b)
Reference to the Compilation
of Air Pollutant Emission Factors, AP-42, 5th Edition, Table 3.1-1
and 3.1-2b. |
Table 4.5d Summary
of Gaseous Emission Inventory for the Flares and Thermal Oxidiser During Operation/Restoration Phase (a)
Parameter |
Flare |
Thermal Oxidiser |
LFG Generator |
No. of emission points |
2 |
1 (one duty and one standby) |
1 (one duty and one standby) |
Stack height (m) |
25 |
9.76 |
28 |
Stack diameter (m) |
3.8 |
1.12 |
0.305 |
Exhaust gas velocity (m s-1) |
12.24 |
17.5 |
48.6 |
Exhaust gas flowrate (m3
s-1) |
499,582 |
62,068 |
12,780 |
Exit temperature (°C) |
850 |
171.6 |
454 |
Emission limit for NOx
(b) |
11.28 mg m-3 |
28.4 mg m-3 |
0.14 lb mmBTU-1 |
Emission limit for CO (b) |
28.19 mg m-3 |
70.91 mg m-3 |
0.44 lb mmBTU-1 |
Emission limit for SO2 (b) |
1.55 mg m-3 |
3.90 mg m-3 |
0.045 lb mmBTU-1 |
Emission limit for benzene (b) |
2.98x10-3 mg m-3 |
7.51x10-3 mg m-3 |
2.1x10-5 lb mmBTU-1 |
Emission limit for vinyl chloride (b) |
1.88x10-3 mg m-3 |
4.73x10-3 mg m-3 |
1.6x10-6 lb mmBTU-1 |
Emission rate for NO2 (g s-1) |
0.31 (c) |
0.10 (c) |
0.11 (c) |
Emission rate for CO (g s-1) |
3.91 |
1.22 |
1.721 |
Emission rate for SO2 (g s-1) |
0.22 |
0.07 |
0.176 |
Emission rate for benzene (g s-1) |
4.14x10-4 |
1.29x10-4 |
8.22x10-5 |
Emission rate for vinyl chloride (g s-1) |
2.61x10-4 |
8.15x10-5 |
6.26x10-6 |
Notes: (a)
Detailed calculations are summarized in Annex A1. (b)
All emission limits are under its exhaust gas
condition. (c)
Assuming 20% of NOx
is NO2. |
The waste arising forecast indicates that
a maximum of 134 vehicles per hour([4]) will be generated from the operation of the
Extension which will be about 19% on the Wan Po Road south of Chung Wang Street
and about 2.4% on the Wan Po Road south of Pak Shing Kok Road as compared to forecasted background traffic in
2018 (refer to Annex B2-3). It is anticipated that this limited
increase in traffic flow will not result in adverse air quality impacts at the
identified ASRs.
The landfill activities during the
operation/restoration phase of the Extension will generate fugitive dust and
gaseous emissions from (1) the construction of drainage channels and sumps, LFG
and leachate extraction wells and collection systems;
(2) haul roads; and (3) operation of the construction equipment. Landfill surface emission from the
active tipping face is also a potential fugitive emission source.
Table 4.5e Total
Soil and Rock Fill Requirements
Phase |
Total Fill Requirement (m3) |
Fill Requirement Per Day (m3d-1)
(a) |
||
|
Soil |
Rock |
Soil |
Rock |
1 |
365,600 |
60,500 |
1,000 |
165.8 |
2 |
453,100 |
60,500 |
1,240 |
165.8 |
3 |
478,700 |
60,500 |
1,310 |
165.8 |
4 |
557,900 |
60,500 |
1,530 |
165.8 |
5 |
590,800 |
60,500 |
1,620 |
165.8 |
6 |
658,800 |
60,500 |
1,800 |
165.8 |
Total |
3,104,900 |
363,000 |
- |
- |
Note: (a)
For each phase, no. of day is 365. |
The management of fugitive dust at the Extension
will be similar to that being implemented at the existing SENT Landfill and
will include immediate compaction of the fill area; regular damping down of the
surface of the haul road; provision of vehicle washing facility for RCVs at the exit of the Extension (to ensure no significant
dust will be brought onto the public road); and regular cleaning of the main
access road and waste reception area by road sweeper.
Although the lining of side slopes will be
carried out concurrently with the waste tipping operation, no earthworks will
be required for the slope lining works.
Hence, there will be no cumulative dust impacts for these activities.
At the existing SENT Landfill, the average
ambient daily TSP concentration record at the ambient TSP monitoring stations
located at the site boundary ([5])
over the past five years
(2002-2006) was 89 µg m-3.
There were no exceedances of the daily dust
criterion of 260 µg m-3 due to the operation of the landfill.
As the majority of the Extension site will
be covered with impermeable liner, the potential areas from which dust can be
generated will be much lower when compared with the existing SENT Landfill
operation. Hence, it is anticipated
that the potential dust to be generated due to the operation of the Extension
will be much lower than that from the operation of the existing SENT
Landfill. With the implementation
of the dust control measures recommended in Section
4.8.2, it is expected that the TSP concentrations at the Extension site
boundary during the operation/restoration phase will be well below the daily
dust criterion and there will be no adverse dust impacts to the identified
ASRs.
Gaseous
Emissions from Construction Plant: Gaseous emissions such as nitrogen dioxide
(NO2) and sulphur dioxide (SO2) will be generated from
the operation of diesel-fuelled construction for the following activities.
·
Construction of drainage channels and
sumps – transportation of
materials, bar bending and cutting as well as concreting;
·
Road
construction – transportation
of materials, grading, road rolling;
·
Deposition
and compaction of waste –
transportation, deposition and compaction of waste;
·
Placement
and removal of daily covered materials – by excavator, bulldozer,
dump truck, vibratory roller and loader; and
·
Capping
and landscaping (progressive restoration) – by bulldozer, dump truck,
vibratory roller, loader and mobile crane.
These plants will be located across the
site, depending on need. The
nearest representative ASR, TVB City, is located at about 110 m away from the
nearest construction site boundary.
The total gaseous emissions generated by the plant over the construction
site area (ie, 20ha) are small and it will disperse
and diluted with the ambient air very rapidly. Therefore, the potential air quality
impact associated with operation of the construction plant on the identified
ASRs is envisaged to be limited and minor.
The composition
of LFG is anticipated to be similar to that from the existing SENT landfill,
given that the waste types accepted will be similar.
Samples obtained from the LFG abstraction
wells of the existing SENT Landfill contain about 40 to 60% methane, 30 to 45%
carbon dioxide and a trace amount of VOCs ([6]).
In 2005 and 2006, out of the 39 VOCs ([7])
analysed, only dichlorodifluoromethane, vinyl
chloride, dimethyle sulphide, methylene
chloride, benzene, heptanes, trichloroethylene, toluene, octanes,
tetrachloroethylene, ethylbenzene,
xylenes, propyl benzene and
dichlorobenzene were detected. For
most of these, the measured concentrations were in the range 0.01 and 39.7 µg m-3.
The ambient concentrations of the 39 VOCs were also monitored on a quarterly basis at the ambient
air quality monitoring stations at the site boundary. A summary of the measured concentrations
of these 39 VOCs from 2002 to 2006 is presented in Table 4.5f. Benzene, chloroform,
dichlorodifluoromethane, ethylbenzene, methylene chloride, propyl benzene,
toluene and xylene were measured in most of the
samples. However, the
concentrations were well below the respective trigger levels. Other VOCs
were not detected or measured. Exceedances of the trigger levels for chloroform and propyl benzene were detected in one occasion at the ambient
VOC monitoring stations.
Investigations were conducted and it was considered that the abnormal
readings were caused by off-site sources such as vehicle exhaust.
Table 4.5f VOC
Concentrations at Site Boundary and On-site of the Existing SENT Landfill (2002
- 2006)
Pollutant |
Trigger
Level |
Monitored
VOC Concentration (µgm-3) |
||||||||||||||
VOC/1 |
VOC/4 |
VOC/6 |
VOC/8 |
On-site |
||||||||||||
Min |
Max |
Average |
Min |
Max |
Average |
Min |
Max |
Average |
Min |
Max |
Average |
Min |
Max |
Average |
||
1,1,1-Trichloroethane |
19,000 |
ND |
2.3 |
1.2 |
ND |
2.9 |
1.5 |
ND |
5.8 |
1.7 |
ND |
4.1 |
1.2 |
ND |
4.1 |
1.4 |
1,2-Dibromoethane |
40 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
4.4 |
4.4 |
ND |
ND |
ND |
1,2-Dichloroethane |
400 |
ND |
0.6 |
0.4 |
ND |
2.1 |
0.9 |
ND |
1.3 |
0.7 |
ND |
2.5 |
1.2 |
ND |
4.4 |
1.7 |
Benzene |
160 |
ND |
4.4 |
1.0 |
<0.5 |
10.1 |
1.5 |
<0.5 |
25.1 |
2.1 |
<0.5 |
13.1 |
1.5 |
<0.5 |
4 |
1.2 |
Butan-2-ol |
3,000 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Buthanethiol |
4 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Butyl Benzene |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Carbon Disulphide |
255 |
ND |
0.9 |
0.9 |
ND |
41.2 |
26.0 |
ND |
5.5 |
5.1 |
ND |
6.7 |
6.7 |
ND |
6.8 |
6.3 |
Carbon Tetrachloride |
126 |
ND |
3.5 |
1.1 |
ND |
0.9 |
0.7 |
ND |
1.3 |
0.8 |
ND |
5 |
1.2 |
ND |
3.8 |
1.6 |
Chloroform |
98 |
ND |
67 |
9.5 |
ND |
409.2 |
36.1 |
ND |
19.1 |
3.4 |
ND |
30.2 |
11.0 |
ND |
67 |
17.2 |
Decane |
1,000 |
ND |
ND |
ND |
ND |
<1 |
<1 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Dichlorobenzene |
1500 |
ND |
29 |
4.1 |
ND |
95 |
19.3 |
ND |
65 |
5.6 |
ND |
137 |
13.8 |
ND |
4 |
1.5 |
Dichlorodifluoromethane |
49,500 |
1 |
37.1 |
3.7 |
ND |
450 |
27.1 |
ND |
159.4 |
11.0 |
ND |
490 |
25.9 |
ND |
8.1 |
1.9 |
Dimethyl Sulphide |
11 |
ND |
ND |
ND |
ND |
9.4 |
5.0 |
ND |
0.7 |
0.7 |
ND |
ND |
0.4 |
ND |
0.2 |
0.2 |
Di-n-Propyl
Ether |
2700 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Ethanethiol |
1 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Ethanol |
1,900 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Ethyl Butyrate |
- |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Ethyl Propionate |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Ethylbenzene |
1,000 |
ND |
160 |
14.1 |
ND |
268 |
28.3 |
ND |
562 |
32.3 |
ND |
182 |
17.8 |
ND |
160 |
16.7 |
Heptane |
16,000 |
ND |
21.9 |
7.2 |
ND |
<1 |
0.8 |
ND |
34 |
17.8 |
ND |
49 |
17.0 |
ND |
47.9 |
21.6 |
Limonene |
57 |
ND |
5.2 |
5.2 |
ND |
ND |
ND |
ND |
3.5 |
3.5 |
ND |
2 |
2.0 |
ND |
ND |
ND |
Methane |
- |
<1 |
480 |
31.2 |
<1 |
250 |
48.7 |
<1 |
97.9 |
21.1 |
<1 |
436.7 |
34.4 |
<1 |
130 |
10.2 |
Methanethiol |
- |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Methanol |
2,600 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Methyl Butyrate |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Methyl Propionate |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Methylene Chloride |
3,500 |
<0.4 |
557.3 |
49.5 |
<0.4 |
174 |
28.9 |
<0.4 |
104.2 |
17.1 |
ND |
680.6 |
97.9 |
<0.4 |
2885 |
197.5 |
n-Butyl Acetate |
1,500 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Nonane |
24,000 |
ND |
5 |
1.8 |
ND |
29 |
7.9 |
ND |
<0.9 |
<0.9 |
ND |
<0.9 |
<0.9 |
ND |
26 |
16.0 |
Octane |
14500 |
ND |
13 |
4.5 |
ND |
3 |
1.8 |
ND |
37 |
25.9 |
ND |
30 |
12.2 |
ND |
14.5 |
6.2 |
Propyl Benzene |
196 |
ND |
74.9 |
11.1 |
<0.8 |
605.1 |
42.3 |
ND |
340 |
31.0 |
ND |
280 |
24.0 |
ND |
282 |
21.9 |
Propyl Propionate |
56,000 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Terpenes |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Tetrachloroethylene |
3,350 |
ND |
94.5 |
10.1 |
ND |
19.5 |
6.3 |
ND |
24.5 |
3.8 |
ND |
11.5 |
6.1 |
ND |
7.5 |
2.7 |
Toluene |
1,880 |
4 |
124 |
24.2 |
<0.5 |
463 |
89.6 |
<0.5 |
1003 |
74.2 |
<0.5 |
423 |
55.0 |
<0.5 |
264 |
50.4 |
Trichloroethylene |
5,350 |
ND |
2.2 |
1.4 |
ND |
6 |
3.1 |
ND |
4.8 |
2.8 |
ND |
4.4 |
2.0 |
ND |
<1.2 |
<1.2 |
Undecane |
1,300 |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
ND |
Vinyl Chloride |
78 |
0.4 |
0.4 |
0.4 |
ND |
9.5 |
4.2 |
ND |
36.5 |
5.1 |
ND |
4.9 |
3.5 |
ND |
<0.3 |
0.3 |
Xylene |
4,350 |
ND |
200 |
16.7 |
<0.5 |
479 |
50.1 |
<0.5 |
941 |
54.4 |
<0.5 |
271 |
29.8 |
<0.5 |
200 |
22.8 |
Notes: (a)
“ND” means Not Detectable. (b)
Bold and underlined
figure indicates the exceedance of the trigger
level. |
As the majority of the Extension site will
be covered with an impermeable liner and LFG will be extracted via a comprehensive
LFG collection system during the operation phase, it is anticipated that the
fugitive LFG emission from the Extension due to waste tipping activities will
be significantly reduced relative to the existing SENT Landfill. Taking account of the ambient VOC
monitoring results at the existing SENT Landfill, it is expected that the
ambient VOC concentrations at the Extension Site boundary will be well below
the trigger levels for individual compounds. Further dilution of the VOC
concentration is expected due to dispersion off-site. The anticipated VOC concentrations at
the identified ASRs will be minimal and will not cause adverse impacts.
The restoration of the landfill will take place
progressively, whilst operations are ongoing on other parts of the site,
therefore, these two phases have been considered together in the assessment.
Potential sources of odour impact during
operation/restoration phase included:
·
Waste
filling area; and
·
Operation
of the LTP and the LFG treatment facility.
In order to minimize the potential odour
emissions during the operational phase of the Extension, a number of odour
management and control measures have been incorporated into the outline
design. These measures are
summarized in Table 4.8a.
The Extension is scheduled to commence
operation in 2013 and will be designed to receive MSW, special waste ([8])
and construction waste. By that time, the Sludge Treatment
Facilities (STF) are scheduled to be in operation ([9])
and sludge from sewage
treatment works (STWs) will be diverted to the STF
for treatment and disposal.
The operational life of the Extension is
expected to be about 6 years. The
Extension will be developed in 6 phases (Phases 1 to 6) and each phase will be
in operation for approximately 1 year.
The ground level of the first phase will be at about +6mPD and the
highest level will be at +150 mPD. The Extension will open to receive
wastes from 8 am to 11 pm every day.
Waste
Reception Area: All incoming and outgoing refuse
collection vehicles (RCVs) will be weighed at the
enclosed weighbridge office at the waste reception area. All RCVs
visiting the Extension are of enclosed-type and expected to comply with
relevant regulations and to be properly maintained, therefore, the potential
odour emission from RCVs and at the waste reception
area are assumed to be minimal.
Active
Tipping Face: After weighing, the RCVs
will be directed to the active tipping face for unloading. The operation at the active tipping face
will be similar to that of the existing SENT Landfill. Two platforms (ie
lower and upper platforms) will be used for separate unloading of MSW (at the
lower platform) and construction waste (at the upper platform). The construction waste will overlay the
MSW. The wastes will be promptly
spread by bulldozer and compacted by a landfill compactor to minimize the
exposure time of MSW thus minimise the opportunity of odour emission to the
atmosphere. The tipping face area
will be 30m x 40m ([10]).
After 11 pm, the Extension will be closed and the compacted waste will
be covered with 300mm of cover soil immediately. Therefore, odour emissions from the
active tipping face are expected during the operating hours; however, the
emissions will be much reduced thereafter.
Intermediate
Cover Area: Except for the active tipping face and
the final cover area (see below for details), all other areas of the Extension
will be covered with 600mm of soil ([11])
and an impermeable liner in
order to minimize rainwater infiltration into the waste and odour emission as
well as to enhance LFG extraction.
It is therefore anticipated that no odour will be emitted from this area
([12]).
Final
Cover Areas: After waste tipping reaches the final
levels, a capping system will be installed. The capping system will comprise (from
bottom to top) a soil layer, a non-woven geotextile,
an HDPE liner (impermeable layer), a sub-soil drainage layer and a final cover
soil layer. Permanent gas
extraction system will be installed to extract LFG from the waste mass. Planting will also be provided for the
final covered area. It is therefore
anticipated that no odour will be emitted from this area ([13]).
Operation of Leachate
Treatment Plant (LTP)
Leachate collected from the Extension and the
existing SENT Landfill will be pumped to the LTP in the new infrastructure
area. The LTP will consist of four
buffer storage tanks, two ammonia stripping towers, two thermal oxidisers
(i.e., one in operation and one standby), a stripped leachate
storage tank, two SBR tanks and a sludge holding tank. Except for the SBR tanks, all tanks will
be enclosed and the air exhaust from the tanks will be diverted to the thermal
oxidiser. The operation temperature
of the thermal oxidizer is about 850°C.
Odorous gas in the exhaust air (such as ammonia) will be oxidised and
destroyed at such high temperature ([14])
in the thermal oxidiser prior
to discharge to the atmosphere. The
SBR tanks will therefore be the only odour emission source in the LTP.
The dimension of each of the SBR tanks is
20m (width) x 35m (length). The
tank height is about 5m. The leachate temperature in the SBR will be maintained at about
40°C throughout
the year. The LTP will operate on a
24-hours per day basis.
Operation of LFG Treatment Facility
The LFG treatment facility will be
operated on a 24-hours per day basis.
The LFG collected from the LFG extraction system will be either diverted
to other utilization scheme for beneficial use or flared at the treatment
facility. The flaring temperature
is about 850°C and odorous compounds such as VOCs
or H2S in the LFG will be oxidised and destroyed at such
temperatures. Therefore, no odour
emission is expected from the LFG treatment facility.
Summary of Potential Odour Emission
Sources
As discussed above, the major potential
odour sources will include waste tipping activities at the active tipping face
and at the special waste trench as well as the operation of the LTP.
The odour emission sources during the
operation/ restoration phase are summarized in Table 4.5g.
Table 4.5g Summary
of Odour Emission Sources
Odour Emission Source |
Area |
Remarks |
During Operation Hour (8am – 12 midnight) |
||
Active tipping face for MSW +
construction waste |
30m x 20m |
·
From
8am to 11pm. Covering the active
tipping face after operation at 11pm to 12 midnight |
Active tipping face for construction
waste |
30m x 20m |
·
From
8am to 11pm. Covering the active
tipping face after operation at 11pm to 12 midnight |
Special waste trench |
6m x 2.5m (plan area exposed to air) (a) |
·
From
9am to 5pm. Covering the trench
at 5pm – 6pm |
After Operation Hour (12 midnight – 8am on the next day) |
||
Daily cover area |
30m x 40m |
12 midnight – 8am (on the next day) |
24-hour Operation |
||
SBR tanks of the LTP |
20m x 35m |
24 hours |
Note: (a)
Longer
side : 6m (l) x 2m (H); shorter side: 2.5m (l) x 2m (H); bottom: 6m x 2.5m |
Upon completion of final filling and
capping, the aftercare phase will commence and is estimated to last for up to
30 years. The LFG and leachate management systems as well as the LFG generator
will continue to operate during the aftercare phase.
It should be
noted that once the landfill is restored, the leachate
generation rate from the Extension will be significantly reduced and hence the
average daily volume of leachate to be treated will
be reduced from about 350 m3 d-1 to 23 m3 d-1,
ie approximately an 93% reduction). With respect to the small volume of leachate generated, it will be able to reduce the nitrogen
levels in the leachate using biological treatment (ie, nitrification and denitrification)
so that the effluent will comply with the discharge standards. The operation of the ammonia strippers
and thermal oxidisers will not be necessary.
The vent gas from the enclosed leachate storage and treatment tanks will be diverted to an
air scrubber or the flares prior to discharge to the atmosphere. The designed odour (including ammonia
gas) removal efficiency of the air scrubber will be at least 95%. Therefore, majority of the odorous gas
in the vent gas from enclosed tanks will be removed. The scrubbed vent gas will be used as
part of the air intake for the aeration system of the SBR tank. If the vent is diverted to the flare(s)
as part of the air intake, the odorous gas will be destroyed at high combustion
temperature (at 850oC).
The potential source of odour emission
during the aftercare phase will only be the open SBR tanks (please refer to Table 4.6e for the odour emission rate
of the SBR tanks).
Together with the final capping system,
the permanent LFG extraction system will prevent fugitive emission of LFG from
the restored landfill. The LFG
abstracted will be utilised or flared.
Under a high combustion temperature (850oC) at the flare, the
odorous VOCs in the LFG will be completely oxidised
and destroyed.
Conversely, the
total LFG generated from the restored SENT Landfill and the Extension will
increase (maximum yield of about 17,000 m3 hr-1). A worst case scenario has been assumed
where the two flares will be operated at full load (20,000 m3 hr-1). The emission inventory of flares is
summarized in Table 4.5h. The detailed calculation is summarized
in Annex A1.
LFG generator will continue to provide
power supply for the operation of LFG Treatment Facility, LTP and other
facilities at the infrastructure area.
The emission inventory of the LFG generator is summarized in Table 4.5h and detailed calculations are
presented in Annex A1.
Table 4.5h Summary
of Gaseous Emission Inventory for the Flares and Generator During
Aftercare Phase (a) (b)
Parameter |
Flare |
LFG Generator |
No. of emission points |
2 |
1 (one duty and
one standby) |
Stack height (m) |
25 |
28 |
Stack diameter (m) |
3.8 |
0.305 |
Exhaust gas velocity (m s-1) |
12.24 |
48.6 |
Exhaust gas flowrate (m3
s-1) |
499,582 |
12,780 |
Exit temperature (°C) |
850 |
454 |
Emission limit for NOx
(c) |
11.28 mg m-3 |
0.14 lb mmBTU-1 |
Emission limit for CO (c) |
28.19 mg m-3 |
0.44 lb mmBTU-1 |
Emission limit for SO2 (c) |
1.55 mg m-3 |
0.045 lb mmBTU-1 |
Emission limit for benzene (c) |
2.98x10-3 mg
m-3 |
2.1x10-5
lb mmBTU-1 |
Emission limit for vinyl chloride (c) |
1.88x10-3 mg
m-3 |
1.6x10-6
lb mmBTU-1 |
Emission rate for NO2 (g s-1) (d) |
0.31 |
0.11 |
Emission rate for CO (g s-1) |
3.91 |
1.721 |
Emission rate for SO2 (g s-1) |
0.22 |
0.176 |
Emission rate for vinyl chloride (g s-1) |
4.14x10-4 |
8.22x10-5 |
Emission rate for benzene (g s-1) |
2.61x10-4 |
6.26x10-6 |
Notes: (a)
Detailed calculations are summarized in Annex A1. (b)
Reference to Table
4.5d (c)
All emission limits are under exhaust gas condition.
(d)
Assuming 20% of NOx
is NO2 |
According to the EIA Study Brief requirement,
major emission sources in the vicinity should be included to assess the
cumulative air quality impact.
The operation of the existing SENT
Landfill (last year of operation) and the C&DM Handling Facility in TKO
Area 137 are identified as potential concurrent projects during the
construction phase of the Extension.
During the last year of the operation of
the existing SENT Landfill, most of the landfill area will be capped and
restored. Dust will be emitted from
the placement of cover materials, traffic movements on the unpaved haul roads
and traffic movements at the waste reception area (please refer to Figure
4.5a). As discussed in Section 4.5.3, due generation will be
minimised by implementation of dust control measures, including immediate
compaction of the fill area; regular damping down of the surface of the haul
road; provision of vehicle washing facility for RCVs
at the exit of the existing SENT Landfill (to ensure no significant dust will
be brought onto the public road); and regular cleaning of the main access road
and waste reception area by road sweeper.
The separation distance between the active
tipping area of the existing SENT Landfill and the dusty construction work area
of the Extension site is about 850m (refer to Figure 4.5a). As the worse wind angles which carry the
dust from dusty activity area of Extension and that for dust generated from the
active tipping area of the existing SENT Landfill are different, no cumulative
dust impacts are anticipated due to the operation of the existing SENT Landfill
and the construction of the Extension.
TKO Area 137 is currently planned for Deep
Water Front Industrial uses. A Construction
and Demolition Material (C&DM) Handling Facility is scheduled to be
commissioned in phases in TKO Area 137 (see Figure 3.9b) in 2009. The capacity of the C&DM Handling
Facility is about 20,000 tonnes per day.
However, the detailed design information is not available at this stage
but it is understood that the potential dust impacts associated with the
operation of the C&DM Handling Facility will be assessed as part of the
feasibility and engineering design of the facility. It is recommended that the cumulative
dust impact in the vicinity should be addressed in the environmental study
under that study. It is anticipated
that the facility will incorporate necessary dust control measures (as stipulated
in the Air Pollution Control
(Construction Dust) Regulations) in the design of the facility (which may
include enclosure of the dusty operations) and good site practices to control
dust emissions from the facility. It is expected that no adverse dust impact
will result from the operation of the facility.
As of the existing fill bank at TKO Area
137 will be decommissioned by the end of 2008, no cumulative dust impact will
be anticipated.
In summary, no cumulative dust impact is
anticipated during the construction of the Extension.
Odour Impact
When the Extension commences operation,
the existing SENT Landfill will be closed and will not generate odour. No other similar concurrent type of
odour source is identified within 500m of the Extension site boundary during
the operation/restoration and aftercare phases. Hence, no cumulative landfill odour
impact is expected.
Gaseous Emissions from the existing TKO
Industrial Estate
Within 500m from the Extension site
boundary, emissions from TVB City and HAESL may cause cumulative air quality
impact. On-site chimney survey
within the 500m area from the Extension site boundary was conducted in January
2008. Interviews were also conducted
to validate the stack operation and its emission inventory.
According to the information provided by
TVB City and the public information obtained from the EPD Regional Office
(East), the major gaseous emission sources identified at TVB City are the emergency
generators. As the emergency
generators will only operate when CLP’s grid is
suspended, the operating time of these generators is very limited and it will
not expected to cause cumulative air quality impact within the Study Area.
With reference to
the EIA Report of HAECO Aircraft Engine
Test Cell Facility at TKO, NO2, CO and SO2 are the
key air pollutants to be emitted during engine testing. These emission rates and stack
characteristics are summarized in Table
4.5i.
Table 4.5i Stack
and Emission Characteristics in Study Area (a)
Stack ID |
No. of Stacks |
Efflux Velocity (m s-1) |
Stack Diameter (m) |
Stack Height Above Ground
(m) |
Exit Temp. (°C) |
Emission Rate (g s-1) |
||
|
|
|
|
|
|
NO2 |
CO |
SO2 |
HAECO
/ HAESL (c) |
1 |
16.4
for NO2 and SO2; |
14.7 |
40 |
52 |
21.2 |
23.9 |
1.92 |
Notes: (a)
Reference to the EIA Report of HAECO Aircraft Engine Test Cell Facility at TKO. (b)
It is the equivalent diameter. The stack is in square shape with an
area of 13m x 13m. |
The above stack characteristic, emission
inventory and engine type being tested at HAESL have been confirmed by HAESL.
The emissions of NO2, CO and SO2
from HAESL are included to assess the cumulative air quality impact during both
the operation/restoration and aftercare phases.
Dust will be generated from blasting,
materials handling, wind erosion, rock crushing and truck movements on paved
haul roads within the site. It
should be noted that no construction works will be carried out during blasting
due to the site constraint and safety reason. The dust impact from blasting will be
assessed individually.
TSP levels at
the identified ASRs were predicted using the Fugitive Dust Model (FDM). The 2006 meteorological data obtained
from the existing SENT Landfill weather station and TKO weather station
operated by the Hong Kong Observatory (HKO) were used for the model runs. Dust emission rates and associated
particle size distributions for the assessment were determined in accordance
with the Compilation of Air Pollutant
Emission Factors, AP-42, 5th Edition. One blast will be made each day and the
construction works would be carried out for 12 hours (from 7am to 7pm) per day
and 24 days per month. During
night-time (7pm to 7am on next day), only wind erosion of open fill area was
considered. Mitigation measures
recommended in Section 4.8.1 have
been considered in the dust emission rate estimation.
The mitigated TSP emission rates during
blasting, rock crushing, materials handling, wind erosion and truck movement on
unpaved haul road within the construction site are estimated and summarized in Table 4.6a and detailed calculations are
presented in Annex A2.
Table 4.6a Mitigated
Dust Emission Rates (a) (b) (c)
Construction Works |
Dust Generating Activities |
Dust Emission Rate |
Remarks |
Slope Cutting |
Blasting |
1.93 gs-1 |
· Blasting area = 1,000 m2
(estimated by the engineer) · 1 blast per day during daytime · Total no. of day = 107 days · Emission height = 0,5m |
Excavation |
Materials
Handling |
0.0103 gs-1 |
· Excavation period = 1.5 year · Total volume of soil excavated = 770,000
m3 · Hourly soil generation rate = 148.5 m3/hr · 50% dust removal efficiency by watering · Working time: between 7am and 7pm · Emission height: 0.5m |
|
Rock crushing |
· Crushing = 0.0098 gs-1 · Screening = 0.018 gs-1 |
· Rock to be crushed per day = 400m3
per day (max.) · Working time: between 7am and 7pm · Emission height = 5m |
|
Truck movement on
unpaved haul road |
0.00435 gm-2s-1 |
· Total no. of vehicle trip per hour = 70
(including return trip) · Average truck weight = 21.5 tonnes · 90% dust removal efficiency by watering
of main haul road, limiting vehicle speed and paving with aggregate/gravel · Working time: between 7am and 7pm · Emission height: 0.5m |
Filling |
Materials
Handling |
0.0054 gs-1 |
· Filling period = 1.5 year · Total volume of fill materials = 407,200
m3 · Hourly filling rate = 78.5 m3/hr · 50% dust removal efficiency by watering · Working time: between 7am and 7pm · Emission height: 0.5m |
|
Truck movement
unpaved haul road |
0.00156 gm-1s-1 |
· Total no. of vehicle trip per hour = 26
(including return trip) · Average truck weight = 20 tonnes · 90% dust removal efficiency by watering of
main haul road, limiting vehicle speed and paving with aggregate/gravel · Only carried out during daytime between
7am and 7pm |
|
Wind erosion |
§ Daytime : 1.35x10-6 gm-2s-1 § Night-time : 2.7x10-6 gm-2s-1 |
· Total area = about 15 hectare · 50% dust removal efficiency by watering
during daytime and no dust reduction at night-time · 24-hour |
Notes: (a)
Detailed
calculations and location of the dust emission sources are presented in Annex A2. (b)
Dust
emission factors in Compilation of Air Pollutant
Emission factors, (AP-42), 5th Edition by USEPA is used. (c)
Dust
control measures recommended in Section
4.8.2 have been adopted. |
Hourly and daily TSP concentrations were
predicted at 1.5m and 10m above ground of the representative ASRs A1 to A4, A7
and A8 which are located within 500m of the Extension site boundary as the dust
impact is localized. Daily TSP
concentrations predicted from blasting, construction works and night-time wind
erosion activities will be directly added to obtain an overall daily TSP
concentration at the ASRs. The
background TSP concentration, as presented in Table 4.3a, was also used to assess the cumulative TSP
concentrations.
An EPD approved air dispersion model,
ISCST3, was employed for the assessment.
The 2006 meteorological data obtained from the existing SENT Landfill
weather station and TKO weather station operated by the Hong Kong Observatory
(HKO) were used for the model runs.
The “rural” mode was used. Terrain effects within 500m of the
Extension site boundary have been included.
The emission
rates of NO2, CO, SO2, benzene and vinyl chloride from the
operation of the LFG treatment facility, LTP and LFG generator during
operation/restoration and aftercare phases, presented in Tables 4.5d and 4.5h,
respectively, were used for the prediction. The thermal oxidiser, LFG flares and LFG
generator will be operated 24 hours per day. It is conservatively assumed that the
engine testing at HASEL will be carried on a 24-hour basis. The locations of the LFG treatment facility,
LTP, LFG generator and the emission points at HASEL are shown in Figure
4.5b.
The hourly, daily and annual average
concentrations of the key air pollutants were predicted at 1.5m to 30m above
ground at the representative ASRs A1 to A4, A7 and A8 as the maximum height of
these ASRs is 30 m above ground.
The worst affected height was identified and isopleths showing the
levels of these key air pollutants at 1.5m above ground and the worst affected
height were plotted.
Background concentrations presented in Table 4.3a were included in the assessment
of the cumulative air quality impact.
The operation/restoration of the Extension
will be divided into six phases starting from the south and filling
progressively to the north (see Figures 4.6a-1 and 4.6a-2) in general. Three worst-cases (Cases 1 – 3) in each
phase (except Phase 6) have been identified for the odour impact assessment,
which have taken into account the worst case odour impacts to existing ASRs in
TKOIE (eg TVB City), planned ASRs in the TKO Area
137, and ASRs at higher elevations (eg LOHAS Park
(ASR A20)). Odour emission
inventory including type of source, source area, source height, duration and
the temperature of each worst-case are summarized in Table 4.6b.
Table 4.6b Odour
Emission Inventory in Each Worst Case
Source Height |
Worst-case Scenario (b) |
Odour Source |
Area |
Air Temperature of Odour
Emission (a) |
Phase 1 · 10m above ground Phase 2 · 30m above ground Phase 3 · 50m above ground Phase 4 · 70m above ground Phase 5 · 100m above ground Phase 6 · 130m above ground |
In each phase, there will
be 3 worst cases (b): ·
Case
1 ·
Case
2 ·
Case
3 |
During Extension
Opening Hours (8am – 12 midnight) |
||
Active tipping face for MSW + construction waste |
· 30m x 20m |
30°C |
||
Active tipping face for construction waste |
· 30m x 20m |
30°C |
||
Special waste trench |
· 6m x 2.5m (plan area exposed to air) |
30°C |
||
After Extension Opening
Hours (12 midnight – 8am on the next day) |
||||
Daily cover area |
· 30m x 40m |
30°C |
||
24-hour Operation |
||||
SBR tanks |
· 35m x 20m |
30°C |
||
Notes: (a)
Reference
to the sensitivity analysis summarized in Annex
A3. (b)
For
Phase 6, since the waste tipping area is small, therefore, 2 worst cases are
assumed. |
Odour Sampling at SENT Landfill
Odour generated from landfill operation varies
from landfill site to landfill site; no general odour emission rates for landfilling activities are available. Odour samples were taken from the
existing SENT Landfill for olfactometry analysis by
the Odour Research Laboratory of the Hong Kong Polytechnic University to
establish a set of odour emission rates for this study.
Table 4.6c Odour
Sampling Regime
Location |
Sampling ID |
Ambient Temperature (°C) |
MSW + Construction Waste
(S1) |
S1-1 |
30.83 |
|
S1-2 |
31.45 |
|
S1-3 |
26.01 |
|
S1-4 |
23.03 |
|
S1-5 |
20.85 |
|
S1-6 |
30.05 |
MSW + Construction Waste +
300mm Soil Cover (S2) |
S2-1 |
30.97 |
|
S2-2 |
31.58 |
|
S2-3 |
26.16 |
|
S2-4 |
29.55 |
Special Waste Trench (S3) |
S3-1 |
27.00 |
|
S3-2 |
26.47 |
SBR of LTP (S4) |
S4-1 |
26.90 |
As the existing SENT Landfill receives
MSW, construction waste, special wastes as well as dewatered sludge from sewage
treatment works (STWs), the sampling locations for S1
and S2 were therefore selected away the existing active tipping face and at the
upwind location to avoid potential odour contamination. A new tipping platform was formed at the
sampling location and MSW and construction waste were disposed of using the
normal practices. The ratio of MSW
to construction waste disposed was the same as that predicted for the Extension
(ie the ratio of MSW to construction waste is about 1
: 2). For S2, the compacted MSW and
construction waste was covered with 300mm of cover soil. The odour samples for S3 and S4 were
taken at the base of the special waste trench and at the water surface of the
SBR tank of the SENT Bioplant, respectively.
The odour emission from construction waste
is very low and on a conservative basis, it is assumed that the odour emission
rate from construction waste tipping is the same as that for S2.
It should be noted that the existing SENT
Landfill also receives sewage sludge; therefore, the odour emission rate
measured at the trench will be much higher than that expected for the
Extension. Adopting the measured
odour emission rates measured at the existing special waste trench in the
assessment is a conservative approach.
The odour
samples were analysed within 24 hours of the sampling using the olfactometry method by the Odour Research Laboratory of the
Hong Kong Polytechnic University.
The odour concentration of the samples, measured in Odour Units (OU) per
m3, was determined by a Forced-choice Dynamic Olfactometer
in accordance with the European Standard Method EN 13725.
Odour emission rate was then calculated
using the following equation:
Odour
Sampling Results: The measured odour concentrations and
calculated odour emission rates of each odour source are summarized in Table 4.6d.
Table 4.6d Odour
Sampling Results
Location |
Sampling ID |
Onsite Ambient
Temperature During Sampling (°C) |
Measured Odour
Concentration (OU/m3) |
Odour Emission Rate (OU/m2/s) |
MSW + Construction Waste (S1) |
S1-1 |
30.83 |
1,092 |
0.70 |
S1-2 |
31.45 |
1,738 |
1.11 |
|
S1-3 |
26.01 |
1,521 |
0.98 |
|
S1-4 |
23.03 |
1,296 |
0.83 |
|
S1-5 |
20.85 |
264 |
0.17 |
|
S1-6 |
30.05 |
1,579 |
1.01 |
|
MSW + Construction Waste + 300mm Soil Cover (S2) |
S2-1 |
30.97 |
80 |
0.051 |
S2-2 |
31.58 |
160 |
0.10 |
|
S2-3 |
26.16 |
169 |
0.11 |
|
S2-4 |
29.55 |
193 |
0.12 |
|
Special Waste Trench (S3) |
S3-1 |
27.00 |
10,768 |
6.90 |
S3-2 |
26.47 |
16,830 |
10.79 |
|
SBR of LTP (S4) |
S4-1 |
26.90 |
76 |
0.049 |
Definition of a Reasonable Worst-case
Odour Modelling Parameters
A sensitivity analysis was undertaken to determine
a reasonable worst-case scenario for the odour assessment. Details of the sensitivity analysis can
be found in Annex A3. The analysis shows that the reasonable
worst-case ambient temperature for estimating the odour emission rate is 30°C.
Therefore, the reasonable worst-case odour emission rates at this
temperature are summarized in Table 4.6e.
Table 4.6e Reasonable
Worst-case Odour Emission Rates Adopted in Odour Impact Assessment
Odour Source |
Source Area |
Odour Emission Rates at 30°C (OU/m2/s) (a) |
Total Odour Emission (OU/s) |
During Extension Opening Hours (8am – 12
midnight) |
|||
Active tipping face for MSW +
Construction Waste |
30m x 20m |
0.94 |
564 |
Active tipping face for construction
waste |
30m x 20m |
0.12 |
72 |
Special waste trench |
6m x 2.5m (plan area exposed to air) |
31.74 (c) |
476 |
After Extension Opening Hours (12
midnight – 8am on the next day) |
|||
Daily cover area (b) |
30m x 40m |
0.12 |
144 |
24-hour Operation |
|
|
|
SBR tanks |
2 number of |
0.049 |
69 |
Notes: (a)
Reference
to Annex A3. (b)
Total
area of active tipping face. (c)
Reference
to Annex A3 for the adjustment of
the odour emission rate at 30°C. |
Air Dispersion Model and Worst-case Odour Modelling
Parameters
The AUSPLUME model, developed by the
Australian Government (Environmental Protection Agency, Victoria), was employed
for the odour impact assessment.
The use of the AUSPLUME model has been approved by the EPD.
As discussed in Annex A3, the modelling parameters are summarized in Table 4.6f.
Table 4.6f Worst-case
Odour Modelling Parameters
Modelling Parameter |
Setting |
Surface roughness |
·
120
cm |
Meteorological data |
·
2006
hourly SENT landfill weather data : wind speed, wind direction and air
temperature ·
2006
HKO TKO weather data : stability class ·
2006
HKO King’s Park weather data : mixing height ·
90%
of data are valid |
Terrain effect |
·
Terrain
data within 500m from the Extension site boundary have been included in model ·
“Egan
half height” option is selected |
Type of odour source in
model |
·
Area
source : active tipping faces for MSW and construction waste, daily cover area
at night-time and special waste trench ·
Point
source : SBR tanks (with very low exit velocity of 0.001 m s-1) as
the leachate temperature is slightly higher than
ambient |
Also, odour management and control
measures summarized in Table 4.8a have
been considered in the worst-case assessment.
5-second odour concentrations were
modelled at 1.5m, 10m, 20m, 30m, 50m, 70m and 90m ([16])
above ground level at the identified
ASRs and the worst affected heights under different worst-case scenarios are
also identified in the assessment.
Contours of the predicted odour concentrations at the worst affected
height within the Study Area (500m from the Extension site boundary) under
different scenarios were plotted.
Under the EIAO-TM, the odour assessment criterion is defined as 5 OU under a
5-second averaging time. To convert
the AUSPLUME output (presented as the maximum 3-minute mean concentration) to a
maximum 5-second mean concentration, the approach suggested by the Warren
Spring Laboratory (WSL) ([17])
was adopted:
“Typical
maximum or peak 5-second average concentrations within any 3-minute period
appear to be of the order of 5 times the 3-minute average. During very unstable conditions larger
ratios, perhaps 10:1, are more appropriate…..”
It should be
noted that the ratios provided in the WSL report refer to peak to mean
concentrations for emissions from stacks.
Emissions from low-level area sources will fluctuate less and therefore
the peak to mean ratios will be lower.
The use of the peak to mean ratios provided in the WSL report therefore
provides a conservative estimate for the 5-second mean concentrations for area
sources.
For stable conditions (stability classes C
to F), a factor of 5 was applied whilst for unstable conditions (stability
classes A and B) a factor of 10 was applied to the emission rates input in the
model run. The modelled results
will be the 5-second odour concentrations.
The factored odour emission rates are
presented in Table 4.6g. These odour emission rates applied to
the three worst-cases described in Table
4.6b. An example showing hourly
emission rate file adopted in AUSPLUME model is presented in Annex A4.
Table 4.6g Odour
Emission Rates for AUSPLUME Model Run
Modelling
Period |
Odour
Emission Source |
Area Size in Model |
Air Temperature of Odour Emission |
Factored Odour Emission Rate to be used in Model Run to
obtain 5-second Results |
|
|
|
|
Stability Class A & B (c) |
Stability Class C to F (d) |
|
During Operation (8am – 12 midnight) |
Active tipping face for MSW + Construction Waste |
30m x 20m |
30°C |
9.4 |
4.7 |
Active tipping face for construction Waste (a) |
30m x 20m |
30°C |
1.2 |
0.6 |
|
Special Waste Trench |
6m x 2.5m (plan area exposed to
air) |
30°C |
317.41 |
158.7 |
|
Night-time (Midnight to 8am on the next day) |
Daily Cover Area (a) |
30m x 40m |
30°C |
1.2 |
0.6 |
24-hour Operation |
2 numbers of SBR tanks |
20m x 35m (each) |
30°C |
343 (OU s-1) |
171.5 (OU s-1) |
Notes: (a) The
odour emission rates of daily cover area at night and the active tipping face
for construction waste during operation are similar due to the odour nature
of the ground is the same. (b) Reference
to Tables 4.6b and 4.6e for original odour emission at 30°C. (c) |