Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
Environmental Monitoring & Audit Manual
Contents
4............ EM&A
on DECOMMISSIONING OF THE REMAINING PARTS (EX-GFS BUILDING AND RADAR STATION) OF
THE FORMER KAI TAK AIRPORT. 4-2
4.1 Introduction. 4-2
4.2 Air Quality Impact 4-2
4.3 Noise Impact 4-2
4.4 Water Quality Impact 4-2
4.5 Waste Management Implications. 4-2
4.6 Land Contamination Impact 4-2
4.7 Impact on Cultural Heritage. 4-2
4.8 Landscape and Visual Impact 4-2
List of Tables
Table
4.1......... Summary
of Waste Handling Procedures and Disposal Routes
Table 4.2......... Event and Action Plan for Confirmation Sampling /
Testing for Soil Excavation
Table 4.3......... Concerned Action Levels for Soil Excavation
Table 4.4......... Event and Action Plan for Confirmation Sampling /
Testing for Biopiling
Table 4.5......... Concerned Action Levels for Biopiling
Table 4.6......... Event and Action Plan for Confirmation Sampling /
Testing for Solidification/ Stabilization
Table 4.7......... Concerned Action Levels for Solidification/
Stabilization
4
EM&A on DECOMMISSIONING OF THE REMAINING
PARTS (EX-GFS BUILDING
AND RADAR STATION) OF THE FORMER
KAI TAK
AIRPORT
4.1
Introduction
4.1.1
This section details
the specific EM&A requirements for Schedule 2 DP3a: Decommissioning of the
Remaining Parts (Ex-GFS Building and Radar Station) of the Former Kai Tak Airport.
The requirements, methodology, equipment, monitoring locations, criteria and
protocols for the monitoring and audit of this DP are presented. The project organisation, site environmental audit and
reporting requirements are stipulated in Chapters 1, 14 & 15 of this Manual
respectively.
4.2
Air Quality Impact
4.2.1
The findings of the EIA indicated that with the
implementation of dust suppression measures stipulated in the Air Pollution Control
(Construction Dust) Regulation during construction, no adverse residual air
quality impact would be expected. Dust monitoring is not required. However,
regular site audit (see Section 14 of this Manual) is required to ensure compliance of the Air
Pollution Control (Construction Dust) Regulation.
4.2.2
As described in the EIA
Report, no adverse air quality impacts at the ASRs are expected during the
construction phase of this DP.
4.2.3
Mitigation measures for
dust are recommended in the EIA Report. The Contractor shall be
responsible for the design and implementation of these measures.
4.2.4
In order to ensure
compliance with the acceptable criteria at the ASRs at all time, requirements
of the Air Pollution Control (Construction Dust) Regulation shall be
adhered to during the construction period. Misting for any stockpile of
materials and provision of windbreaks on three sides are proposed to prevent
wind erosion. In addition, the following good site practices are
recommended to minimise dust and other air pollutants impacts during
excavation, transportation, and loading and unloading of dusty
material:
The excavation area should be
limited to as small in size as possible and backfilled with clean and/or
treated soil shortly after excavation work.
The exposed excavated area should be
covered by the tarpaulin during night time.
The top layer soils should be
sprayed with fine misting of water immediately before the excavation.
Stockpiling site(s) should be lined
with impermeable sheeting and bunded. Stockpiles should be fully covered
by impermeable sheeting to reduce dust and other air pollutants emission.
Misting for the dusty material
should be carried out before being loaded into the vehicle.
Any vehicle with an open load
carrying area should have properly fitted side and tail boards.
Material having the potential to
create dust should not be loaded from a level higher than the side and tail
boards and should be dampened and covered by a clean tarpaulin.
The tarpaulin should be properly
secured and should extent at least 300 mm over the edges of the sides and
tailboards. The material should also be dampened if necessary before
transportation.
The vehicles should be restricted to
maximum speed of 10 km per hour and confined haulage and delivery vehicle to
designated roadways insider the site. On-site unpaved roads should be
compacted and kept free of lose materials.
Vehicle washing facilities should be
provided at every vehicle exit point.
The area where vehicle washing takes
place and the section of the road between the washing facilities and the exit
point should be paved with concrete, bituminous materials or hardcores.
Every main haul road should be
scaled with concrete and kept clear of dusty materials or sprayed with water so
as to maintain the entire road surface wet.
Every stock of more than 20 bags of
cement should be covered entirely by impervious sheeting placed in an area
sheltered on the top and the three sides.
Every vehicle should be washed to
remove any dusty materials from its body and wheels before leaving the
construction sites.
4.2.5
The mitigation measures
shall be implemented during the process of solidification and biopiling are
described as follows.
Solidification
The solidification pit/area should
be provided with dust suppression measures.
Handling and mixing of cement shall
follow Air Pollution Control (Construction Dust) Regulation to limit
cement emission.
The bin should be covered during
residence period after mixing process.
Biopiling
During the course of biopile
formation, the stockpiled soils at the biopiles should be covered by tarpaulin
or low permeable sheet to avoid fugitive emissions of dust or any air
pollutants from the biopiles affecting the surrounding environment and to
minimise runoff from the stockpiled soils. Biopile(s) should be covered by
impermeable sheeting (such that no longer than 5m of a biopile should be
exposed to open air) to avoid fugitive emissions of dust or any pollutants from
the biopile(s).
Upon formation of a biopile, the
biopile should be covered by low permeable geotextiles to prevent dust emission
and runoff.
During the operation of biopile, the
biopiles should be fully covered to control the extraction of VOCs.
The vented air from the biopile(s)
should be connected to blower and carbon adsorption system with 99% control
efficiency for treatment before release to the atmosphere. Exhaust air from the
blower and carbon adsorption system should be monitored for TVOC bi-weekly to
check the performance of the carbon filter. The frequency of monitoring might
be adjusted subject to review on site. The location of the exhaust of the
carbon filter should be sited as far away as possible from the nearby ASRs.
Spent activated carbon of the carbon
adsorption system should be replaced at appropriate intervals such that the
TVOC emission concentration from the system is acceptable (i.e. the measured
TVOC concentration is below 20ppm).
4.2.6
The implementation
schedule for the recommended air quality impact mitigation measures is
presented in Appendix
A3.
4.3
Noise Impact
4.3.1
The findings of the EIA study
indicated that no adverse construction noise impacts would be expected on the
noise sensitive receivers (NSRs) in the vicinity of the work areas of this DP
in view of the large separation distance between the potential construction
noise sources and the nearby NSRs. Construction noise monitoring is
therefore not considered necessary. However, regular site audit (see
Section 14 of this Manual) is required to ensure proper implementation of the
proposed good site practices.
Mitigation Measures
4.3.2
In
order to ameliorate the construction noise impacts, good site practices listed
below should be adopted by all the Contractors:
·
Only well-maintained
plant should be operated on-site and plant should be serviced regularly during
the construction program;
·
Mobile plant, if any, should be sited as
far away from NSRs as possible;
·
Machines and plant
(such as trucks) that may be in intermittent use should be shut down between
works periods or should be throttled down to a minimum;
·
Plant known to emit
noise strongly in one direction should, wherever possible, be orientated so
that the noise is directed away from the nearby NSRs;
·
Material stockpiles and
other structures should be effectively utilised, wherever practicable, in
screening noise from on-site construction activities.
4.3.3
The implementation
schedule for the recommended mitigation measures is presented in Appendix A3.
4.4
Water Quality Impact
Introduction
4.4.1
No off-site marine
water quality impact would be expected from this DP and given that there would
not be any marine-based works for the proposed works, water quality monitoring
is not considered necessary. However, it is recommended that regular site
audits (at least once per week) be undertaken to inspect the construction
activities and works areas in order to ensure the recommended mitigation
measures are properly implemented. Proposed mitigation measures for containing
and minimizing water quality impacts are listed in the implementation schedule
given in Appendix A3.
4.4.2
Implementation of
regular site audits (at least once per week) is to ensure that the recommended
mitigation measures are to be properly undertaken. It can also provide an
effective control of any malpractices and therefore achieve continual
improvement of environmental performance on site.
4.4.3
Site audits shall
include site inspections and monitoring audits.
Site Inspections
4.4.4
Site inspections shall
be carried out by the ET and shall be based on the mitigation measures for water
pollution control recommended in the implementation schedule as attached in Appendix A3.
In the event that the recommended mitigation measures are not fully or
properly implemented, deficiency shall be recorded and reported to the site
management. Suitable actions are to be carried out to:
·
Investigate the problems and the causes;
·
Issue action notes to the Contractor which is
responsible for the works;
·
Implement remedial and corrective actions immediately;
·
Re-inspect the site conditions upon completion of the
remedial and corrective actions; and
·
Record the event and discuss with the Contractor for
preventive actions.
Monitoring Audits
4.4.5
Monitoring audits are
to be undertaken to ensure that a valid discharge license has been issued by
EPD prior to the discharge of effluent from the construction site.
Parameters included in the WPCO licence, will also be included in the
monitoring programme. The chemical testing of water samples collected in
the monitoring programme should be undertaken by a Hong Kong Laboratory
Accreditation Scheme (HOKLAS) accredited laboratory. The audit results
reflect whether the effluent quality is in compliance with the discharge
license requirements and that the recommended water quality mitigation measures
are properly implemented. In case of non-compliance, suitable actions
should be undertaken to:
·
Notify the site management for the non-compliance;
·
Identify the sources of pollution;
·
Check the implementation status of the recommended
mitigation measures;
·
Investigate the operating conditions of the on-site
treatment systems;
·
Implement corrective and remedial actions to improve
the effluent quality;
·
Increase monitoring frequency until the effluent
quality is in compliance with the discharge licence requirements; and
·
Record the non-compliance and propose preventive
measures.
4.5
Waste Management Implications
4.5.1
Waste management will
be the Contractor’s responsibility to ensure that all wastes produced during the
decommissioning works of the Project are handled, stored and disposed of in
accordance with good waste management practices and EPD’s regulations and
requirements.
4.5.2
Waste materials
generated during the decommissioning works, such as construction and demolition
(C&D) material, general refuse and chemical wastes, are recommended to be
audited at regular intervals (at least once per week) to ensure that proper
storage, transportation and disposal practices are being implemented.
This monitoring of waste management practices will ensure that these solid and
liquid wastes are not disposed into the nearby harbour waters. The
Contractor will be responsible for the implementation of any mitigation
measures to minimise waste or redress problems arising from the waste
materials.
Waste
Control and Mitigation Measures
4.5.3
Mitigation measures for
waste management are summarised below. With the appropriate handling,
storage and removal of waste arisings during the decommissioning works as
defined below, the potential to cause adverse environmental impacts will be
minimised.
Good Site Practices
4.5.4
Adverse impacts related
to waste management are not expected to arise, provided that good site
practices are strictly followed. Recommendations for good site practices
during the decommissioning works include:
·
Nomination of an
approved person, such as a site manager, to be responsible for good site
practices, arrangements for collection and effective disposal to an appropriate
facility, of all wastes generated at the site;
·
Training of site
personnel in proper waste management and chemical waste handling procedures;
·
Provision of sufficient
waste disposal points and regular collection for disposal;
·
Appropriate measures to
minimise windblown litter and dust during transportation of waste by either
covering trucks or by transporting wastes in enclosed containers;
·
Regular cleaning and
maintenance programme for drainage systems, sumps and oil interceptors;
·
A recording system for
the amount of wastes generated, recycled and disposed of (including the
disposal sites).
Waste Reduction
Measures
4.5.5
Good management and
control can prevent the generation of a significant amount of waste.
Waste reduction is best achieved at the planning and design stage, as well as
by ensuring the implementation of good site practices. Recommendations to
achieve waste reduction include:
·
Sorting C&D waste
from demolition of the remaining structures to recover recyclable portions such
as metals;
·
Segregation and storage
of different types of waste in different containers, skips or stockpiles to
enhance reuse or recycling of materials and their proper disposal;
·
Encouraging collection
of aluminium cans, PET bottles and paper by providing separate labelled bins to
enable these wastes to be segregated from other general refuse generated by the
work force;
·
Recycling any unused
chemicals or those with remaining functional capacity;
·
Proper storage and site
practices to minimise the potential for damage or contamination of construction
materials;
·
Planning and stocking
construction materials carefully to minimise amount of waste generated and
avoid unnecessary generation of waste.
4.5.6
In addition to the
above measures, specific mitigation measures are recommended below for the
identified waste arisings to minimise environmental impacts during handling,
transportation and disposal of these wastes.
Construction and Demolition Material
4.5.7
The C&D material
should be sorted on-site into inert C&D material (that is, public fill) and
C&D waste. The inert C&D material would require disposal to the
designated public fill reception facility. C&D waste, such as steel
and other metals should be re-used or recycled and, as a last resort, disposed
of to landfill. It is recommended that a suitable area be designated to
facilitate the sorting process and a temporary stockpiling area will be
required for the separated materials.
4.5.8
In order to monitor the
disposal of public fill and C&D waste at public filling facilities and
landfills, respectively, and to control fly tipping, a trip-ticket system
should be included as one of the contractual requirements and implemented by
the ET. The IEC should be responsible for auditing the results of the
system.
General Refuse
4.5.9
General refuse should
be stored in enclosed bins or compaction units separate from C&D
material. A licensed waste collector should be employed by the Contractor
to remove general refuse from the site, separately from C&D material.
Effective collection and storage methods (including enclosed and covered area)
of site wastes would be required to prevent waste materials from being blown
around by wind, wastewater discharge by flushing or leaching into the marine
environment, or creating odour nuisance or pest and vermin problem.
Chemical Wastes
4.5.10
After use, chemical
wastes (for example, cleaning fluids, solvents, lubrication oil and fuel)
should be handled according to the Code of Practice on the Packaging,
Labelling and Storage of Chemical Wastes. Spent chemicals should be
collected by a licensed collector for disposal at the CWTF or other licensed
facility, in accordance with the Waste Disposal (Chemical Waste) (General)
Regulation.
4.5.11
Table 4.1 provides a summary of the various
waste types likely to be generated during the decommissioning works, together
with the recommended handling and disposal methods.
Table 4.1Summary of Waste
Handling Procedures and Disposal Routes
Waste Type
|
Generated From Works Item
|
Total Quantity Generated
|
Quantity to be disposed
off-site / re-used
|
Handling
|
Disposal
|
C&D Material
|
Decommissioning of the
remaining parts of the former Kai
Tak Airport
and decontamination of the south apron area
|
- 9,500 m3 for demolition of ex-GFS Building
- 5,000 m3 for demolition of ASDE radar
tower
- 28,750 m3 for
decommissioning and decontamination of the south apron
|
Landfill / public fill
|
Dust and water Dust quality mitigation measures
|
Sort on-site into Inert
C&D material to be disposed off-site to the designated public fill
reception facility, C&D material should be reused as far as practicable
|
Chemical Wastes
|
Lubrication oil, fuel etc. from
operation, maintenance, and servicing of construction and decontamination
treatment plant and equipment, and from decontamination works
|
Few cubic metres per month
(preliminary estimate)
|
Few cubic metres per month
(preliminary estimate)
|
Recycle on-site or by
licensed companies
Stored on-site within
suitably designed containers
|
Chemical Waste Treatment
Facility or other licensed facility
|
General Refuse
|
Waste paper, discarded
containers etc. generated from workforce
|
Few cubic metres per month
(preliminary estimate)
|
Few cubic metres per month
(preliminary estimate)
|
Provide on-site refuse
collection points
|
Refuse station for compaction
and containerisation and then to landfill
|
4.5.12
The implementation
schedule of the recommended mitigation measures is presented in Appendix A3.
4.6
Land Contamination Impact
Introduction
4.6.1
The EIA study has evaluated
the potential land contamination issues for the remaining facilities,
structures and buildings within the former Kai Tak Airport that were not
covered under the previous EIAs on decommissioning of former Kai Tak Airport
registered under the EIAO (namely EIA on Decommissioning of the Former Kai Tak
Airport other than the North Apron and EIA on Kai Tak Airport North Apron
Decommissioning).
4.6.2
For land contamination identified
within the ex-GFS building, the EIA study has recommended excavating the
contaminated soil from the proposed excavation zone within the ex-GFS building
area for carrying out soil treatment at the proposed decontamination works area
located at the northern part of the South Apron of the former Kai Tak Airport as shown in Figure 2.4.
4.6.3
The confirmation
sampling / testing shall be carried out by the Environmental Team (ET) for (i) soil
excavation (to ensure complete excavation of contaminated soil); (ii) biopiling
(to ensure attainment of cleanup targets); and (iii) solidification /
stabilization (to ensure attainment of cleanup targets). In addition,
independent environmental checker (IEC) shall carry out independent checking on
the above confirmation sampling / testing for not less than 10% of total
numbers of samples and the scope shall cover sampling works and laboratory
analysis by an independent Hong Kong Laboratory Accreditation Scheme (HOKLAS)
accredited laboratory.
4.6.4
All contamination
identified at the ex-GFS building shall be remediated before commencement of
any demolition / construction works at the concerned sites to avoid disturbance
on the ground. The duration of remediation shall be taken into account by
the Project Proponent and the Contractor as part of the decommissioning
programme.
4.6.5
In all cases,
contaminated soil remediation and treatment must be managed in an
environmentally sound manner, including compliance with all relevant
legislation and Government requirements.
Confirmation Sampling / Testing for Soil
Excavation
Sampling and Testing Requirements
4.6.6
After excavation,
confirmation samples shall be undertaken at limits of excavation to confirm
that all contaminated soils have been excavated. The confirmation samples
shall be analysed by a HOKLAS accredited laboratory and if the analytical
results are below the relevant Dutch B levels. If the analytical samples
exceed the relevant action levels, more soil shall be excavated (either with
0.5m increment in vertical or 1m in horizontal direction depending on whether
the exceeding confirmation sample is collected from a sidewall or excavation
base), and additional confirmation samples shall be collected and analysed
until all confirmation samples are below the relevant action levels.
4.6.7
One confirmation sample
shall be collected from the excavation pit bottom and one from each sidewall of
the excavation pit. The depth of sampling shall be based on the depth of
the original sample collected during the site investigation (SI) sample result
that triggered excavation in that area. If there are any visible
indications of impact, samples shall be collected from the apparent impact
zone(s).
Compliance Assessment and Event /
Action Plan
4.6.8
If the analytical
results of the confirmation samples are below the concerned action levels for
soil remediation, removal of the contaminated soil shall be considered
complete. If the analytical results exceed the relevant action levels,
more soil shall be excavated (either with 0.5m increment in vertical or 1m
horizontal direction depending on whether the exceeding confirmation sample is
collected from a sidewall or excavation base). Additional confirmation
samples shall be collected and analysed until all confirmation samples are
below the relevant Action Levels. The Event and Action Plan for
confirmation sampling / testing for soil excavation is provided in Table 4.2.
Table 4.2
Event and Action Plan for Confirmation Sampling / Testing for Soil
Excavation
Event
|
Action
|
Action Party
|
The concentration of the contaminant(s) for the SI sample that triggered
the excavation exceed the relevant Action Levels for soil remediation (as
tabulated in Table 4.3 below
|
(i)
Collect
one confirmation sample from the excavation pit bottom and one from each
sidewall of the excavation pit and analyse
|
Contractor
|
The concentration(s) of the contaminant(s) for the confirmation sample
exceed the relevant Action Levels for soil remediation (as tabulated in Table
4.3 below).
|
(i)
More
soil shall be excavated either laterally or vertically depending on whether the
exceeding confirmation sample is from a sidewall or excavation base;
(ii)Additional confirmation
samples shall be collected and analysed until all confirmation samples are
below the relevant Action Levels.
|
Contractor
|
Table 4.3
Concerned Action Levels for Soil Excavation
Contaminants
|
Action Level (mg/kg)*
|
TPH
|
1000
|
Phenanthrene
|
10
|
Benzo(a)pyrene
|
1
|
Fluoranthene
|
10
|
Pyrene
|
10
|
Copper
|
100
|
Lead
|
150
|
Zinc
|
500
|
Cadmium
|
5
|
Nickel
|
100
|
Cobalt
|
50
|
Remarks:
*The action level adopted is the Dutch B level
provided in the Practice Note ProPECC PN3/94 “Contaminated Land Assessment and
Remediation” issued by Environmental Protection Department.
Confirmation Sampling / Testing for
Biopiling
Sampling and Testing Requirements
4.6.9
The objective of the
biopile closure assessment is to collect soil samples for testing in order to
ensure that the soil contaminant levels in the biopiles are below the cleanup
targets for TPH / SVOCs.
4.6.10 Confirmation samples shall be
collected at a sampling frequency of one sample per 100m3 of soil
treated. The samples shall be collected at representative locations
distributed evenly throughout the biopile and at various depths within the
biopile. Sample locations within the biopile shall be documented
accurately so that the analytical results can be correlated with the sampling
locations within the biopile.
4.6.11 Access to the sampling locations
shall be through opening of heat bonded cover panels. These openings shall be
closed after each access. Extracting of the soil samples shall be
accomplished by using a hand auger or other methods approved by the ER.
4.6.12 All soil samples shall be analysed
in an HOKLAS accredited laboratory for TPH and SVOCs.
Compliance Assessment and Event /
Action Plan
4.6.13 If the analytical results of the
confirmation samples are below the concerned cleanup targets for biopiling,
cleanup of the contaminated soil shall be considered complete. Individual
soil lot which has demonstrated meeting the cleanup target could be removed
from the biopile provided the lot would not affect the operation of biopile or
would not be affected by adjacent soil lots still under treatment. If the
analytical results exceed the relevant cleanup targets, the concerned biopile
treatment system shall have to be restarted to fully decontaminate the soil.
The Event and Action Plan for confirmation sampling / testing for biopile
closure assessment is given in Table 4.4.
Table 4.4
Event and Action Plan for Confirmation Sampling / Testing for Biopiling
Event
|
Action
|
Action Party
|
Exceedance of any cleanup targets for the contaminants ( as tabulated
in Table 4.5 below)
|
Concerned biopile treatment system shall be restarted to fully
decontaminate the soil
|
Contractor
|
Table 4.5
Concerned Action Levels for Biopiling
Contaminants
|
Action Level (mg/kg)*
|
TPH
|
1000
|
Phenanthrene
|
10
|
Benzo(a)pyrene
|
1
|
Fluoranthene
|
10
|
Pyrene
|
10
|
Remarks:
*The action level adopted is the Dutch B level provided
in the Practice Note ProPECC PN3/94 “Contaminated Land Assessment and
Remediation” issued by Environmental Protection Department
Confirmation Sampling / Testing for
Solidification / Stabilization
Sampling and Testing Requirements
4.6.14 Following solidification /
stabilization treatment for metal-contaminated soil and curing of the
solidified soil, confirmation sampling / testing shall be undertaken to ensure
that the cleanup targets have been attained.
4.6.15 Confirmation samples shall be
collected at a sampling frequency of one sample per 100m3 of treated
material. Each sample shall be a composite sample collected at 5
locations throughout the treated soil pile and the same volume of sample shall
be collected at each of the locations so that the composite sample is not
biased.
4.6.16 Confirmation samples shall be
analysed in an HOKLAS accredited laboratory for the concerned soluble metals
using Toxicity Characteristics Leaching Procedure (TCLP) in accordance with USEPA
Method 1311.
4.6.17 In order to ensure that the soil is
fully solidified in the solidification process, all the soil treated with
solidification / stabilization shall be tested for unconfined compressive
strength. All the treated soil shall have an unconfined compressive strength of
at least 150 pound-force per square inch (psi) (1MPa), with reference to USEPA
guideline (USEPA 1986) for hazardous waste solidification / stabilization
requirement.
Compliance Assessment and Event /
Action Plan
4.6.18 The “Universal Treatment Standards”
(UTS) shall be used for interpretation of the TCLP test results to assess if
the cleanup targets have been attained.
4.6.19 If either the cleanup targets or the
target unconfined compressive strength have not been achieved, the treated
material shall be crushed and returned to the solidification / stabilization
process. The Event and Action Plan for confirmation sampling / testing for
solidification / stabilization treatment is given in Table 4.6.
Table 4.6
Event and Action Plan for Confirmation Sampling / Testing for
Solidification/ Stabilization
Event
|
Action
|
Action Party
|
Respective cleanup targets (as tabulated in Table 4.7) of any confirmation
samples have not been attained
|
The treated material shall be crushed and returned to the
solidification / stabilization until the respective cleanup targets have been
achieved.
|
Contractor
|
Unconfined compressive strength of 150 pound force per square inch
(psi) (1MPa) has not been attained
|
Table 4.7
Concerned Action Levels for Solidification/ Stabilization
Contaminants
|
Action Level (mg/kg)*
|
Lead
|
0.75
mg/L as TCLP
|
Copper
|
7.8**
mg/L as TCLP
|
Zinc
|
4.3
mg/L as TCLP
|
Cadmium
|
0.11
mg/L as TCLP
|
Nickel
|
11
mg/L as TCLP
|
Cobalt
|
Not
Available**
|
Remarks:
* Reference to
Universal Treatment Standards (UTS) of U.S. Resource Conservation and Recovery
Act (RCRA) in Title 40 of the Code of Federal Regulations (CFR) Parts 268.
**It should be noted
that the UTS standard for copper and cobalt are unavailable. To determine the
UTS for copper, a comparison has been made between Drinking Water Standards for
the USEPA and the USEPA Federal Register. It was found that the 2 sets of
standards differ by a factor of ~6
(for Chromium) to ~2950 (for Cyanide).
Using a more conservative approach, the factor of 6 is taken. Therefore, the
UTS for copper is taken to be the Drinking Water Standard value of 1.3mg/L
times a factor of 6, giving a value of 7.8mg/L. For cobalt, it should be noted
that there is no UTS or USEPA Drinking Water Standard for Cobalt. Therefore, a
cleanup standard is not established for Cobalt. However, it is expected that
the solidification process will likely isolate the Cobalt in the same manner as
the other COC present.
Environmental Mitigation Measures and Safety
Measures
4.6.20 To minimise the potentially adverse
environmental impacts arising from the handling of potentially contaminated
materials in the ex-GFS building, the following environmental mitigation
measures are proposed during the course of the site remediation:
Excavation and Transportation
·
Excavation profiles must be properly designed and executed.
·
Stockpiling site(s) should be lined with impermeable sheeting and
bunded. Stockpiles should be fully covered by impermeable sheeting to
reduce dust emission. If this is not practicable due to frequent usage,
regular watering should be applied. However, watering should be avoided
on stockpiles of contaminated soil to minimise contaminated runoff.
·
Stockpiles of contaminated soil should be properly covered by
impermeable sheeting to minimize contaminated runoff from the stockpiles.
·
Excavation and stockpiling should be carried out during dry season as
far as possible to minimise contaminated runoff from contaminated soils.
·
Supply of suitable clean backfill material is needed after excavation.
·
Vehicles containing any excavated materials should be suitably covered
to limit potential dust emissions or contaminated wastewater run-off, and truck
bodies and tailgates should be sealed to prevent any discharge during transport
or during wet conditions.
·
Speed control for the trucks carrying contaminated materials should be
enforced.
·
Vehicle wheel and body washing facilities at the site’s exist points
should be established and used.
Biopiling
·
To avoid fugitive emissions of dust or any air pollutants from the
biopile(s) and to minimise runoff from the stockpiled soils, the stockpiled
soils at the biopiles should be covered by impermeable sheeting such that not
longer than 5m of the biopile is exposed to open air.
·
Upon formation of a biopile, the biopile should be fully covered by
impermeable sheeting to prevent dust emission and runoff.
·
Impermeable sheeting should be placed at the bottom of the biopiles and
leachate collection sump should be constructed along the perimeter of the
biopiles to prevent leachate from contaminating the underlying
soil/groundwater. The collected leachate should be discharged following the
requirements of Water Pollution Control Ordinance (WPCO).
·
The vented air from the biopile(s) should be connected to blower and
carbon adsorption system with 99% control efficiency for treatment before
release to the atmosphere. Exhaust air from the blower and carbon adsorption system
should be monitored for TVOC bi-weekly to check the performance of the carbon
filter. The frequency of monitoring might be adjusted subject to review on
site.
·
The biopiles should be fully covered by impermeable sheeting to control
the extraction of TVOC.
·
Spent activated carbon of the carbon adsorption system should be
replaced at appropriate intervals such that the TVOC emission concentration
from the system is acceptable (i.e. the measured TVOC concentration is below
20ppm).
·
Silencers should be installed at the biopile blowers to minimise noise
impact.
·
Contaminated runoff from biopile(s) should be prevented by constructing
concrete bunds along the perimeter of the biopiles.
Solidification / Stabilization
·
The loading, unloading, handling, transferring and storage of cement
should be carried out in an enclosed system.
·
Mixing process and other associated material handling activities should
be properly scheduled to minimise potential noise impact.
·
Mixing of contaminated soils with cement / water / other additive(s)
should be undertaken at a solidification plant to minimise the potential for
leaching.
·
Runoff from the solidification / stabilization area should be prevented
by constructing concrete bunds along the perimeter.
4.6.21 In addition, the following basic
health and safety measures shall be implemented as far as possible to minimise
the potentially adverse effects on health and safety of construction workers
during the course of site remediation:
·
Set up a list of safety measures for site workers;
·
Provide written information and training on safety for site workers;
·
Keep a log-book and plan showing the contaminated zones and clean zones;
·
Maintain a hygienic working environment;
·
Avoid dust generation;
·
Provide face and respiratory protection gear to site workers;
·
Provide personal protective clothing (e.g. chemical resistant jackboot,
liquid tight gloves) to site workers; and
·
Provide first aid training and materials to site workers.
4.6.22 Since some small parts of the ex-GFS building and Radar Station
including the transformer room and the generator room etc. were still under
operation during the previous land contamination site investigation (SI), SI at
those areas was not possible due to site accessibility and safety issues.
For these remaining areas with potential land contamination concerns, a
supplementary land contamination SI was recommended to be carried out upon the
cessation of the operations and prior to the redevelopment. A
supplementary sampling plan providing the sampling and laboratory analysis
information for supplementary SI in these areas has been included in the respective
CAR and/ or RAP for ex-GFS building and Radar Station. The supplementary
SI shall be carried out once the area is accessible, and a supplementary CAR
and if necessary RAP shall be prepared. If contamination is identified in
the supplementary SI, remediation shall be performed according to the
supplementary CAR/RAP upon EPD’s approval.
4.6.23 For any excavation works at Radar
Station and ex-GFS building, as the risk due to dermal contact with groundwater
by site workers is uncertain, it is recommended that personnel protective
equipment (PPE) be used by site workers as a mitigation measure.
4.6.24 The implementation for the
recommended land contamination mitigation measures is presented in Appendix A3.
In the event of exceedances or complaints, the ET and / or the Contractor shall
be responsible for reviewing the effectiveness of these measures and for
proposing, designing and implementing alternative measures as appropriate.
4.7
Impact on Cultural Heritage
4.7.1
The EIA Study concluded
that the sites of the proposed decommissioning sites of the ex-GFS Building
and the Radar Station are not in close proximity to any of the existing built
heritage resources and are not on any area of archaeological potential.
No mitigation and monitoring and audit programme specific for cultural heritage
would be required for the proposed decommissioning works.
4.8
Landscape and Visual Impact
4.8.1
The sensitive receivers
are shown in Figure 4.1, 4.2, 4.3.
4.8.2
The EIA Study concluded
that due to the small scale and temporary nature of
DP3a, it will result in insubstantial landscape and visual impacts during the
construction phase and there will be no impact during the operation phase. Therefore, no mitigation measure and monitoring and audit programme
specific for landscape and visual impact would be
required for the proposed decommissioning works.