Agreement No. CE 35/2006(CE)
Kai Tak Development Engineering Study
cum Design and Construction of Advance Works
– Investigation, Design and Construction
Kai Tak Development
environmental monitoring and audit manual
Contents
8............ Waste Management Implications
8.2 Waste Control and Mitigation Measures
List of Tables
Table 8.1.......... Summary of Waste Handling Procedures and Disposal Routes
· Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material. Excess material shall be cleaned from the decks and exposed fittings of barges and hopper dredgers before the vessel is moved.
· Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped with automatic self-monitoring devices as required under the Dumping at Sea Ordinance and as specified by the DEP.
· Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.
Table 8.1 Summary of Waste Handling Procedures and Disposal Routes
Waste Type |
Generated From Works Item |
Total Quantity Generated |
Quantity to be disposed or re-used |
Handling |
Disposal |
C&D Material
|
600m runway gap opening |
1,990,000 m3 |
Re-use 975,000 m3 |
Dust and water Dust quality mitigation measures |
Sort on-site into Inert C&D material to be disposed off-site to the designated public fill reception facility, C&D material should be reused as far as practicable |
Trunk Road T2 |
503,000 m3 |
Re-use 203,000 m3 |
|||
Kai Tak Nullah modification works |
600,000 m3 |
Re-use 300,000 m3 |
|||
Site formation cum Marine Works for cruise terminal |
958,000 m3 |
Re-use 237,000 m3 |
|||
|
304,000 m3 |
Re-use 66,000 m3 |
|||
Shatin to Central Link (SCL) (To Kwa Wan Station and the Kai Tak Station) construction works |
717,000 m3 |
Re-use 282,000 m3 |
|||
Public landing steps cum fireboat berth |
77,000 m3 |
Re-use 664,200 m3
|
|||
New sewage pumping stations serving the planned Kai Tak Development (including PS6) |
54000 m3 in total
|
||||
Decommissioning of the
remaining parts of the former |
- 9,500 m3
for demolition of
- 5,000 m3 for demolition of ASDE radar tower
- 28,750 m3 for decommissioning and decontamination of the south apron |
||||
New Distributor Roads Serving the Planned KTD |
2217 m3 |
||||
Other miscellaneous works[1] |
697,533 m3 |
||||
Dredged Marine Sediment |
Dredging of seabed in the proposed manoeuvring basin of cruise terminal (Category H and Category M sediment) |
430,000 m3 Stage 1: 210,000 m3 & Stage 2: 220,000m3 |
Dispose 430,000 m3 (Stage 1: 210,000m3 & Stage 2: 220,000m3) |
Dust, odour, noise , water quality mitigation measures |
Type 1 - |
Dredging of seabed in the proposed manoeuvring basin of cruise terminal (Category L sediment) |
950,000 m3 Stage 1: 490,000m3 (including 20,000m3 from removal of the Kai Tak Runway submarine outfall) & Stage 2: 460,000m3 |
Dispose 950,000 m3 (Stage 1: 490,000m3 & Stage 2: 460,000m3) |
Type 1 - Open Sea Disposal - gazetted marine disposal ground allocated by MFC |
||
Maintenance dredging of cruise terminal (sediment category to be determined by carrying out sampling and testing in accordance with ETWB TCW No. 34/2002) |
350,000 m3 |
Dispose 350,000 m3 |
Disposal requirement to be determined based on the sampling and testing results in accordance with ETWB TCW No. 34/2002 |
||
600m runway opening (Category H sediment) |
3,200 m3 |
Dispose 3,200 m3 |
|||
Localized maintenance dredging of KTAC (Category H sediment) |
120,000 m3 |
Dispose 120,000 m3 |
|||
Public landing step cum fireboat berth (Category L sediment) |
600 m3 |
Dispose 600 m3 |
|||
Immersed tunnel sections of road T2 (Category H sediment) |
2,260,000 m3 |
Dispose 2,260,000 m3 |
|||
CKR (Category H sediment) |
360,000 m3 |
Dispose 360,000 m3 |
|||
Relocation of the Hong Kong |
442,000 m3 |
Dispose 442,000 m3 |
|||
Chemical Wastes |
Lubrication oil, fuel etc. from operation, maintenance, and servicing of construction and decontamination treatment plant and equipment, and from decontamination works |
Few cubic metres per month (preliminary estimate) |
Few cubic metres per month (preliminary estimate) |
Recycle on-site or by licensed companies Stored on-site within suitably designed containers |
Chemical Waste Treatment Facility or other licensed facility |
General Refuse |
Waste paper, discarded containers etc. generated from workforce |
Few cubic metres per month (preliminary estimate) |
Few cubic metres per month (preliminary estimate) |
Provide on-site refuse collection points |
Refuse station for compaction and containerisation and then to landfill |
[1] Other miscellaneous works include public landing steps, sewage pumping stations, decommissioning works, underpass, underground shopping streets, subways, box culverts, roadworks, drains and sewers etc