Construction of a Secondary
Boundary Fence and New Sections
of Primary Boundary Fence and
Boundary
Environmental
Impact Assessment
(Final)
January 2009
in association with
ADI Limited
Archaeological Assessments
Mott MacDonald Hong Kong Ltd
7th Floor,
Tsim Sha Tsui,
Hong Kong
Tel: 2828 5757
Fax: 2827 1823
This
document has been prepared for the titled project or named part thereof and
should not be relied upon or used for any other project without an independent
check being carried out as to its suitability and prior written authority of Mott
MacDonald being obtained. Mott MacDonald
accepts no responsibility or liability for the consequence of this document
being used for a purpose other than the purposes for which it was
commissioned. Any person using or
relying on the document for such other purpose agrees, and will by such use or
reliance be taken to confirm his agreement to indemnify Mott MacDonald for all
loss or damage resulting therefrom. Mott
MacDonald accepts no responsibility or liability for this document to any party
other than the person by whom it was commissioned.
To
the extent that this report is based on information supplied by other parties,
[Mott MacDonald] accepts no liability for any loss or damage suffered by the
client, whether contractual or tortious, stemming from any conclusions based on
data supplied by parties other than Mott MacDonald and used by Mott MacDonald in
preparing this report.
List
of Contents Page
Chapters
1.3 EIAO and Designated Projects
1.5 Need for the Project and
Consequences of not Proceeding with the Project
1.6 Consideration of Alternative
Alignment
1.7 Alternative / Preferred
Construction Methods and Sequence of Works
1.8 Interface with Concurrent Projects
1.9 Objectives of the EIA Study
1.12 Structure of the EIA Report
2.2 Legislation, Standards, Guidelines
and Criteria
2.3 Baseline Conditions and Air
Sensitive Receivers
2.4 Identification and Evaluation of
Air Quality Impact
2.6 Potential Concurrent Projects
2.7 Environmental Monitoring and Audit
3.2 Relevant Legislations, Standards
& Guidelines
3.3 Study Area and Construction
Programme
3.5 Assessment Approach &
Methodology
3.6 Analysis of Construction Activities
and Sources of Noise Impact
3.7 Unmitigated Construction Noise
Impacts
3.8 Possible Noise Mitigation Measures
and Mitigated Impacts
3.9 Operation Phase Noise Impact
Assessment
3.10 Environmental Monitoring and Audit
(EM&A) Requirements
4.2 Environmental Legislation,
Standards, Guidelines and Criteria
4.8 Environmental Monitoring and Audit
5 WASTE
MANAGEMENT IMplications
5.2 Environmental Legislation and
Standards
5.8 Environmental Monitoring and Audit
Requirements
6 Ecological
Impact assessment
6.3 Sites of Conservation Importance in
the Area
6.5 Ecological Value of Project Area /
habitats within the Assessment Area
6.6 Potential Ecological Impacts
6.9 Environmental Monitoring and Audit
Requirements
7.2 Environmental Legislation, Standards,
Guidelines and Criteria
7.5 Review
of Planning and Development Control Framework
7.6 Landscape and Visual Baseline Study
7.8 Landscape Impact Assessment
7.11 Recommended Mitigation Measures
7.12 Programme for Landscape Works
8.2 Environmental Legislation and
Standards
8.4 Results of the Desk-Based
Assessment
8.7 Mitigation Recommendations
9 SUMMARY OF ENVIRONMENTAL OUTCOMES
10 ENVIRONMENTAL
MONITORING AND AUDIT (EM&A) REQUIREMENTS
11 PROJECT IMPLEMENTATION SCHEDULE
List of Tables
Table 2‑1 Hong
Kong Air Quality Objectives (mg/m3)(i)
Table
2‑2 Annual Average Background Air Quality (2003 – 2007)
Table
2‑3 Representative Air Sensitive Receivers
Table
3‑1 Noise Standards for Daytime
Construction Activities
Table
3‑2 EIAO-TM Road Traffic Noise
Criteria
Table
3‑4 Locations of the Existing
Representative NSRs for Demolition of Exsiting Boundary Fence
Table
3‑5 Location of Existing
Representative NSRs for Demolition of Check Points
Table
3‑6 Location of Planned NSR for
Demolition of Existing Boundary Fence
Table
3‑7 Tentative Construction/ Demolition
Activities for All Sections
Table
3‑10 Maximum SWL of Each Activity for
Construction Noise Impact Assessment
Table
3‑13 Unmitigated Noise Impact due to the
Demolition of Existing Boundary Fence
Table
3‑14 Unmitigated Noise Impact due to the
Demolition of Check Points
Table
3‑15 Recommended Quiet PME and the SWL
Table
3‑16 Maximum SWLs of Plant Inventory with
Mitigation Measures Implemented
Table
3‑18 Mitigated Noise Impact due to the
Demolition of Existing Boundary Fence (Level 1)
Table
3‑19 Mitigated Noise Impact due to the
Demolition of Check Points (Level 1)
Table
3‑20 Sensitivity Test for Minimum
Separation Distance
Table
3‑21 Mitigated Noise Impact due to the
Demolition of Existing Boundary Fence (Level 2)
Table
3‑22 Construction Noise Impact Assessment
for WWF
Table
5‑1 Reviewed Historical Aerial
Photographs and Land Use in the Land Requirement Limit
Table
6‑1 Habitats present in Assessment
Area
Table
6‑2 Habitats present in Project Area
Table
6‑6 Relative abundance of herpetofauna
species recorded in Section 1
Table
6‑7 Odonata species recorded in
Section 1
Table
6‑8 Butterfly species recorded in
Section 1
Table
6‑11 Relative abundance of herpetofauna
species recorded in Section 2
Table
6‑12 Odonata species recorded in Section
2
Table
6‑13 Butterfly species recorded in
Section 2
Table
6‑14 Freshwater fish species recorded in
Section 2
Table
6‑17 Herpetofauna recorded in Section 3
Table
6‑18 Odonata species recorded in Section
3
Table
6‑19 Butterfly species recorded in
Section 3
Table
6‑20 Aquatic fauna species recorded in
Section 3
Table
6‑22 Herpetofauna recorded in Section 4
Table
6‑23 Odonata species recorded in Section
4
Table
6‑24 Butterfly species recorded in
Section 4
Table
6‑25 Ecological Evaluation of Project
Area in Section 1
Table
6‑26 Ecological Evaluation of Project
Area at Red Alignment in Section 2
Table
6‑27 Ecological Evaluation of Project
Area at Blue and Green Alignments in Section 2
Table
6‑28 Ecological Evaluation of Project
Area at Red Alignment in Section 3
Table
6‑29 Ecological Evaluation of Project
Area at Blue and Green Alignments in Section 3
Table
6‑30 Ecological Evaluation of Project
Area in Section 4
Table
6‑31 Potential Ecological Impacts of
Habitat Loss at Section 1 and 2
Table
6‑32 Potential Ecological Impacts of
Habitat Loss at Section 3 and 4
Table
6‑35 Potential Ecological Impacts of
Ecological Barrier on Blue Alignment of Section 3
Table
6‑37 Ecological Evaluation of Floral
Species within Proposed Project Area
Table
6‑38 Potential Ecological Impacts on
Floral Species of Conservation Concern
Table
6‑39 Potential Ecological Impacts on
Fauna Species of Conservation Concern
Table
6‑40 Potential Ecological Impacts on
Offsite Habitats
Table
6‑41 Potential Ecological Impacts on
Offsite Disturbance to Mammals of Conservation Concern
Table
6‑43 Potential Disturbance Impacts to
raptors of conservation concern in Assessment Area.
Table
6‑45 Potential Ecological Impacts to Tam
Kon Chau Egretry.
Table
7‑2 Residual Impact Significance
Threshold Matrix
Table
7‑3 Review of Existing Planning and
Development Control Framework
Table
7‑4 Landscape Resources and their Sensitivity to Change
Table
7‑5 Landscape Character Areas and their Sensitivity to Change
Table
7‑6 Visually Sensitive Receivers (VSRs) and their Sensitivity to Change
Table
7‑7 Magnitude of Change for Landscape Resources
Table
7‑8 Magnitude of Change for Landscape Character Areas
Table
7‑9 Significance of Impacts on Landscape Resources in the Construction and
Operational Phases
Table
7‑11 Magnitude of Change for Visually Sensitive Receivers
Table
7‑13 Proposed Construction Phase
Mitigation Measures
Table
7‑14 Proposed Operational Phase
Mitigation Measures
Appendices
Appendix A Tentative Construction Programme
Appendix B Typical Cross Sections of Proposed
PBF, SBF, BPR and Checkpoints
Appendix C Construction Noise Impact
Appendix D (Not Used)
Appendix G (Not Used)
List of Figures
Figure 1.1 General
Layout Plan
Figure 2.1 Study
Area for Air Quality Impact Assessment
Figure 2.2 Air
Sensitive Receivers for Section 1
Figure 2.2a Air
Sensitive Receivers for Section 1
Figure 2.2b Air
Sensitive Receivers for Section 1
Figure 2.3 Air
Sensitive Receivers for Section 2
Figure 2.3a Air
Sensitive Receivers for Section 2
Figure 2.3b Air
Sensitive Receivers for Section 2
Figure 2.3c Air
Sensitive Receivers for Section 2
Figure 2.3d Air
Sensitive Receivers for Section 2
Figure 2.4 Air
Sensitive Receivers for Section 3
Figure 2.4a Air
Sensitive Receivers for Section 3
Figure 2.4b Air
Sensitive Receivers for Section 3
Figure 2.4c Air
Sensitive Receivers for Section 3
Figure 2.4d Air
Sensitive Receivers for Section 3
Figure 2.4e Air
Sensitive Receivers for Section 3
Figure 2.4f Air
Sensitive Receivers for Section 3
Figure 2.4g Air
Sensitive Receivers for Section 3
Figure 2.5 Air
Sensitive Receivers for Section 4
Figure 2.5a Air
Sensitive Receivers for Section 4
Figure 3.1 Study
Area for Noise Impact Assessment
Figure 3.2 Location
of Noise Sensitive Receivers (Sheet 1 of 7)
Figure 3.3 Location
of Noise Sensitive Receivers (Sheet 2 of 7)
Figure 3.4 Location
of Noise Sensitive Receivers (Sheet 3 of 7)
Figure 3.5 Location
of Noise Sensitive Receivers (Sheet 4 of 7)
Figure 3.6 Location
of Noise Sensitive Receivers (Sheet 5 of 7)
Figure 3.7 Location
of Noise Sensitive Receivers (Sheet 6 of 7)
Figure 3.8 Location
of Noise Sensitive Receivers (Sheet 7 of 7)
Figure 3.9 Photos
of Existing Noise Sensitive Receivers (Sheet 1 of 2)
Figure 3.10 Photos
of Existing Noise Sensitive Receivers (Sheet 2 of 2)
Figure 3.11 Typical
Section of Movable Noise Barrier
Figure 6.1 Assessment
Area and Sites of Conservation Interest
Figure 6.3 Habitat
Map and Species of Conservation
Figure 6.4 Habitat
Map and Species of Conservation
Figure 6.5 Habitat
Map and Species of Conservation
Figure 6.6 Habitat
Map and Species of Conservation
Figure 6.7 Habitat
Map and Species of Conservation
Figure 6.8 Habitat
Map and Species of Conservation
Figure 6.9 Habitat
Map and Species of Conservation
Figure 7.1 Review
of Planning and Development Control Framework
Figure 7.2A Landscape
Resources
Figure 7.2B Landscape
Resources
Figure 7.2C Landscape
Resources
Figure 7.2D Landscape
Resources
Figure 7.2E Landscape
Resources
Figure 7.2F Landscape
Resources
Figure 7.2G Landscape
Resources
Figure 7.2H Landscape
Resources
Figure 7.3A Landscape
Character Areas and Impacts
Figure 7.3B Landscape
Character Areas and Impacts
Figure 7.3C Landscape
Character Areas and Impacts
Figure 7.3D Landscape
Character Areas and Impacts
Figure 7.4A Landscape
Character Areas Photographs
Figure 7.4B Landscape
Character Areas Photographs
Figure 7.4C Landscape
Character Areas Photographs
Figure 7.4D Landscape
Character Areas Photographs
Figure 7.4E Landscape
Character Areas Photographs
Figure 7.4F Landscape
Character Areas Photographs
Figure 7.5A Impacts
on Landscape Resources
Figure 7.5B Impacts
on Landscape Resources
Figure 7.5C Impacts
on Landscape Resources
Figure 7.6A Visual
Envelope and Zone of Visual Influence
Figure 7.6B Visual
Envelope and Zone of Visual Influence
Figure 7.6C Visual
Context of Visual Sensitive Receivers
Figure 7.6D Visual
Context of Visual Sensitive Receivers
Figure 7.6E Visual
Context of Visual Sensitive Receivers
Figure 7.6F Visual
Context of Visual Sensitive Receivers
Figure 7.6G Visual
Context of Visual Sensitive Receivers
Figure 7.8A Recommended
Landscape Mitigation Measures
Figure 7.8B Recommended
Landscape Mitigation Measures
Figure 7.8C Recommended
Landscape Mitigation Measures
Figure 7.8D Recommended
Landscape Mitigation Measures
Figure 7.9A Photomontages
- Vantage Point A
Figure 7.9B Photomontages
- Vantage Point A
Figure 7.9C Photomontages
- Vantage Point B
Figure 7.9D Photomontages
- Vantage Point B
Figure 7.9E Photomontages
- Vantage Point C
Figure 7.9F Photomontages
- Vantage Point C
Figure 7.9G Photomontages
- Vantage Point D
Figure 7.9H Photomontages
- Vantage Point D
Figure 7.9I Photomontages
- Vantage Point E
Figure 7.9J Photomontages
- Vantage Point F
Figure 7.9K Photomontages
- Vantage Point G
Figure 7.9L Photomontages
- Vantage Point H
Figure 7.9M Photomontages
- Vantage Point H
Figure 8.1 Geological
map showing the western part of Section 3 (Pak Fu Shan to Lin Ma Hang)
Figure 8.2 Geological
map showing the eastern part of Section 3 (Lo Wu to Pak Fu Shan)
Figure 8.3 Geological
map showing Sections 1 and 2 (Mai Po to Lo Wu)
Figure 8.4 Geological
map showing Section 4 (Sha Tau Kok)
Figure 8.5 Map
showing the locations of known archaeological sites
Figure 8.6 Locations
of Shrine (BF-HB1) and Grave (BF-G1) near Liu Pok
Figure 8.7 Location
of Grave (BF-G2) on Lin Ma Hang Road
Figure 8.8 Locations
of HB-2 and HB-3 at the Abandoned Village near Chuk Yuen
Figure 8.9 Location
of BF-BH4 near Kong Ha (Sha Tau Kok)
1.1.1 The Frontier Closed Area (FCA) is an integral part of the package of measures for maintaining the integrity of the Hong Kong SAR’s boundary with the Mainland and for combating illegal immigration and other cross-boundary criminal activities. Following a recent review, the Government has concluded that with the erection of a secondary boundary fence (SBF) along the boundary patrol road (BPR) and construction of new sections of the BPR and primary boundary fence (PBF) at certain sections along the boundary, the FCA coverage can be substantially reduced without affecting the objective of maintaining the integrity of the boundary. The PBF and SBF will be erected along the northern and southern curbs of the realigned BPR respectively to facilitate the Police in combating cross-boundary criminal activities. The reduced FCA will comprise a narrow strip of land covering the realigned BPR and areas to its north, together with the points of crossing the boundary (i.e. the Boundary Control Points and Sha Tau Kok town). Areas south of the SBF will generally be excised from the FCA.
1.2.1 The Project mainly comprises the construction of an SBF along the southern edge of the existing BPR (approximately 21.7km) from west (Pak Hok Chau) to east (Sha Tau Kok). For sections where the existing PBF runs along the southern edge of the BPR, a new fence with sensor alarm system will be constructed on the northern edge of the BPR as part of the PBF whereas the existing PBF will become the SBF. The project also includes the conversion of the existing maintenance services road along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR with a PBF and an SBF; and construction of two new sections of the BPR with a PBF and an SBF along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village. In addition, the Project includes the construction of a checkpoint at the entrance to the Sha Tau Kok town (i.e. location of “Gate One”) and replacement of the existing checkpoint at Pak Hok Chau, removal of the existing checkpoints at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au, and removal of the existing PBF along those sections of the existing BPR which will be replaced by new sections of the BPR.
1.3 EIAO and Designated Projects
1.3.1
The Project is a designated project (DP) under
item Q.1, Part I, Schedule 2 of the Environmental Impact Assessment Ordinance
(EIAO) (Cap. 499) which reads "All
projects including new access roads, railways, sewers, sewage treatment
facilities, earthworks, dredging works and other building works partly or
wholly in an existing or gazetted proposed country park or special area, a
conservation area, an existing or gazetted proposed marine park or marine
reserve, a site of cultural heritage, and a site of special scientific
interest."
1.4.1 The entire length of the Project is about 21.7km from west of Pak Hok Chau to east of Sha Tau Kok and is divided into four sections as shown in Figure 1.1. The project scope of each section is described below.
Section 1 – Mai Po to Lok Ma Chau Control Point
(i) To erect an SBF along the existing BPR (approximately 4.1km); and
(ii) To replace the existing checkpoint at Pak Hok Chau.
Section 2 – Lok Ma Chau
Control Point to Ng Tung River
(i) To convert the maintenance services road of Drainage Services Department along the Shenzhen River bank to the north of the Lok Ma Chau Loop and Hoo Hok Wai into a new section of the BPR (approximately 5.6km);
(ii) To erect a new PBF with the sensor alarm system and an SBF respectively along the northern and southern side of the converted road;
(iii) To remove the original PBF and the sensor alarm system thereon along the existing BPR south of the Lok Ma Chau Loop and Hoo Hok Wai; and
(iv) To remove the
existing checkpoint at
Section 3 – Ng Tung River
to Lin Ma
(i) To erect an SBF along the existing BPR except the sections to the north of Pak Fu Shan and northwest of Lin Ma Hang Village (approximately 7.5km);
(ii) To construct new sections of the BPR along the Shenzhen River side to the north of Pak Fu Shan and northwest of Lin Ma Hang Village without necessitating river training (approximately 4.0km);
(iii) To erect a new PBF with the sensor alarm system and an SBF along the northern and southern sides of the new sections of BPR respectively;
(iv) To remove the original PBF and the sensor alarm system thereon along the existing BPR near Pak Fu Shan and Lin Ma Hang Village; and
(v) To remove the existing checkpoints at Sha Ling and Ping Che.
Section 4 – Lin Ma
(i) To erect an SBF from the entrance of the Sha Tau Kok town (i.e. the location of “Gate One”) to the Sha Tau Kok Control Point (approximately 0.5km);
(ii) To provide a new checkpoint at “Gate One”; and
(iii) To remove the existing checkpoint at Shek Chung Au.
1.4.2 Typical cross sections of the proposed PBF, SBF, BPR and checkpoint are presented in Appendix B.
1.4.3 Apart from normal boundary patrol operation conducted by the Police, no significant operational or decommissioning activities would be involved in association with the proposed SBF, PBF and BPR.
1.4.4 Security Bureau is the project proponent, Police is the end-user of the boundary fences and the realigned BPR and Architectural Services Department is the works agent responsible for the management, planning, design and implementation of the Project.
1.5 Need for the Project and Consequences of not Proceeding with the Project
1.5.1 While the coverage of the Frontier Closed Area (FCA) will be substantially reduced, it would still be necessary to maintain the integrity and security of the boundary area. The construction of new sections of PBF and SBF is considered to be essential to ensure effective law enforcement to safeguard boundary integrity and security and to prevent and combat illegal immigration and other cross-boundary crimes.
1.5.2 Without the implementation, the above purpose cannot be achieved.
1.6 Consideration of Alternative Alignment
1.6.1 The alignment generally runs along the southern boundary of the reduced FCA, the coverage of which has taken account of the comments received during the consultation exercise conducted in September to November 2006.
1.6.2 For mitigating impacts on important habitats and wildlife in the order of priority of ‘Avoidance, Minimizing, Compensation’, the alignments are proposed along the existing boundary patrol road avoiding the environmentally sensitive areas as far as possible. Other alternatives are considered not feasible as they could only be established by creating new pathways in the adjacent natural habitats. The impacts would be minimized if the alignments stay along the existing boundary patrol road. In addition, mitigation measures have also been considered to minimize the environmental impacts. For example, special type of footing would be adopted to retain the existing trees if necessary.
1.6.3 For Section 2, it was originally proposed in the FCA review to retain all the land north of the existing BPR in the FCA. This covered about 100 hectares in the Lok Ma Chau Loop and about 300 hectares in the adjacent Hoo Hok Wai. During the consultation, the local community suggested that these areas should be excluded from the FCA. After consideration, Government decided to accept the suggestion and reduce the FCA coverage accordingly. To this end, the existing maintenance road of the Drainage Services Department to the north of the Lok Ma Chau Loop and Hoo Hok Wai will be used as the boundary patrol road, with a primary boundary fence to be constructed along the northern edge of the road and a secondary boundary fence along the southern edge of the road. To mitigate the environmental impacts, the proposed works would avoid the environmentally sensitive areas, e.g. fish ponds and marshes along Hoo Hok Wai, as far as possible.
1.6.4
The alignments to the north of Pak Fu Shan and
northwest of Lin Ma Hang Village are originally proposed along the existing
boundary patrol road in Section 3. The
relevant Rural Committee requested that two patches of land northwest of Lin Ma
Hang and north of Pak Fu Shan be excised from the FCA to release their
development potential. After
consideration, the alignment is amended to run along the
1.6.5 The latest alignment is shown in Figure 1.1. The alignment along the existing boundary patrol road and new sections of boundary patrol road is denoted in blue and red in Figure 1.1 respectively.
1.7 Alternative / Preferred Construction Methods and Sequence of Works
1.7.1 The major construction works of the Project is provision of the secondary and primary boundary fences. The fences mainly comprise the reinforced concrete footing and the steel fence. For the reinforced concrete footing, precast footing had been considered to minimize the concreting works on site. However, it was found that the precast option is not feasible due to the limited road width which hinders the transportation of the precast units. In addition, the longitudinal and horizontal alignment of the boundary patrol road varies significantly. Thus, standard precast concrete units cannot be applied and cast-in-situ option is necessary to match the site condition.
1.7.2 Apart from the boundary fences, the Project also involves provision of two checkpoints. Since the size of the proposed Pak Hok Chau Checkpoint is comparatively small, it is proposed to adopt prefabricated house instead of traditional reinforced concrete structure to minimize the environmental impact.
1.8 Interface with Concurrent Projects
1.8.1 There are three potential interface projects identified.
Liantang/Heung Yuen Wai
Boundary Control Point in Section 3
1.8.2
A new Boundary Control Point (
Advance Works for River Training
in Section 3
1.8.3
In association with the proposed
Proposed New Wave Wall /
Modification to Existing Wave Wall in Section 2
1.8.4
The works in Section 2 will have interface with
DSD’s proposed modification of the existing wave wall and construction of a new
wave wall alongside the
1.9 Objectives of the EIA Study
1.9.1 The objectives of the EIA study are as follows:
(i)
to
describe the Project and associated works together with the requirements for
carrying out the Project;
(ii)
to
identify and describe elements of community and environment likely to be
affected by the Project and/or likely to cause adverse impacts to the Project,
including natural and man-made environment, and the associated environmental
constraints;
(iii)
to
provide information on the consideration of alternatives to avoid and minimize
potential environmental impacts to environmentally sensitive areas and other
sensitive uses; to compare the environmental benefits and dis-benefits of each
of different options; to provide reasons for selecting the preferred option(s)
and to describe the part environmental factors played in the selection of
preferred option(s);
(iv)
to
identify and quantify all environmental sensitive receivers, emission sources
and determine the significance of impacts on sensitive receivers and potential
affected uses;
(v)
to
identify and quantify any potential losses or damage to flora, fauna and
natural habitats;
(vi)
to
identify and quantify any potential landscape and visual impacts and to propose
measures to mitigate these impacts;
(vii)
to
identify and quantify any potential archaeological and cultural heritage and
propose measures to mitigate these impacts;
(viii)
to
propose provision of mitigation measures so as to minimize pollution,
environmental disturbance and nuisance during construction and operation of
Project;
(ix)
to
investigate the feasibility, practicability, effectiveness and implications of
the proposed mitigation measures;
(x)
to
identify, within the study area, any individual project(s) that fall under
Schedule 2 and/or Schedule 3 of the EIAO; to ascertain whether the findings of
this EIA study have adequately addressed the environmental impacts of those
projects; and where necessary, to identify the outstanding issues that need to
be addressed in any further detailed EIA study;
(xi)
to
identify, predict and evaluate the residual environmental impacts (i.e. after
practicable mitigation) and the cumulative effects expected to arise during the
construction and operation phases of the Project in relation to sensitive
receivers and potential affected uses;
(xii)
to
identify, assess and specify methods, measures and standards, to be included in
the detailed design, construction and operation of the Project which are
necessary to mitigate these environmental impacts and cumulative effects and
reduce them to acceptable level;
(xiii)
to
investigate the extent of the secondary environmental impacts that may arise
from the proposed mitigation measures and to identify constraints associated
with the mitigation measures recommended in the EIA study, as well as the
provision of any necessary modification; and
(xiv)
to
design and specify environmental monitoring and audit requirements to ensure
the effective implementation of the recommended environmental protection and
pollution control measures.
1.10.1 The works are mainly located along the existing BPR from west of Pak Hok Chau to east of Sha Tau Kok, the Shenzhen River side at Lok Ma Chau Loop, Hoo Hok Wai, north of Pak Fu Shan and northwest of Lin Ma Hang Village within the FCA. Access to these areas is controlled by Closed Area Permits issued under Section 37(2) of the Public Order Ordinance. The location of the fence alignment, the new sections of BPR, the new checkpoint, the four existing checkpoints to be removed and the replacement checkpoint to be constructed are shown in Figure 1.1.
1.11.1 The Project is being planned and designed by the Consultant appointed by ArchSD. The works will be implemented by the Contractors appointed by ArchSD and the first Construction Contract is expected to be awarded in late 2009. The construction works are expected to commence in late 2009 for completion in late 2012 subject to the potential adjustment due to the project of Liantang/Heung Yuen Wai Boundary Control point and its advance river training works as described in Sections 1.8.2, 1.8.3 and 1.8.4. The tentative construction programme is shown in Appendix A.
1.12 Structure of the EIA Report
1.12.1 The EIA has been prepared to contain all the findings of the Study as follows:
· Section 2 presents the Air Quality Impact Assessment;
· Section 3 presents the Noise Impact Assessment;
· Section 4 presents the Water Quality Impact Assessment;
· Section 5 presents the Waste Management Implications;
· Section 6 presents the Ecological Impact Assessment;
· Section 7 presents the Landscape and Visual Impact Assessment;
· Section 8 presents the Impact on Cultural Heritage;
· Section 9 provides a summary of the Environmental Outcomes;
· Section 10 presents the Environmental Monitoring and Audit (EM&A) Requirements;
· Section 11 presents an Implementation Schedule; and
· Section 12 presents a summary of the Conclusions of the EIA.
2.1.1 This section describes the potential air quality impacts associated with the construction and operation of the proposed secondary boundary fences, new sections of primary and secondary boundary fences and boundary patrol roads as discussed in Section 1.4. The major air emission will be the dust generation from the construction of the boundary fences and patrol roads. During the operation phase, the patrol police cars on the new boundary patrol roads will be subject to the vehicular emission.
2.1.2 Representative Air Sensitive Receivers (ASRs) within 500m of the study area have been identified and extended to include off-site air quality impact along the boundary patrol roads. Suitable mitigation measures, where necessary, are recommended to protect the ASRs and to ensure that the legislative criteria are complied with. The study area for the air quality impact assessment is shown in Figure 2-1.
2.2 Legislation, Standards, Guidelines and Criteria
2.2.1 Legislation, Standards, Guidelines and Criteria relevant to the consideration of air quality impacts under this study include the following:
· Hong Kong Air Pollution Control Ordinance;
· Air Pollution Control (Construction Dust) Regulation; and
· Environmental Impact Assessment Ordinance and Technical Memorandum on Environmental Impact Assessment Process.
Hong
Kong Air Pollution Control Ordinance
2.2.2
Table 2‑1 Hong Kong Air Quality Objectives (mg/m3)(i)
Pollutant |
1 Hour (ii) |
8 Hours (iii) |
24 Hours (iii) |
3 Months (iv) |
1 Year (iv) |
|
800 |
N.A. |
350 |
N.A. |
80 |
Total Suspended Particulates |
500(vii) |
N.A. |
260 |
N.A. |
80 |
Respirable Suspended Particulates (v) |
N.A. |
N.A. |
180 |
N.A. |
55 |
Carbon Monoxide |
30,000 |
10,000 |
N.A. |
N.A. |
N.A. |
Nitrogen Dioxide |
300 |
N.A. |
150 |
N.A. |
80 |
Photochemical Oxidants (as ozone) (vi) |
240 |
N.A. |
N.A. |
N.A. |
N.A. |
Lead |
N.A. |
N.A. |
N.A. |
1.5 |
N.A. |
Notes:
(i) Measured at 298K(25 oC) and 101.325 kPa (one atmosphere).
(ii) Not to be exceeded more than three times per year.
(iii) Not to be exceeded more than once per year.
(iv) Yearly and three monthly figures calculated as arithmetic means.
(v) Respirable suspended particulates means suspended particles in air with nominal aerodynamic diameter of 10 micrometres and smaller.
(vi) Photochemical oxidants are determined by measurement of ozone only.
(vii) This is not an AQO but a criterion for construction dust impact assessment under Annex 4 of the Technical Memorandum on Environmental Impact Assessment Process.
Air
Pollution Control (Construction Dust) Regulation
2.2.3 Air Pollution Control (Construction Dust) Regulation stipulates the construction dust control requirements for both notifiable (e.g. site formation) and regulatory (e.g. road opening) works to be carried out by the Contractor. The requirements for various notifiable and regulatory works are given in Parts 1 and 2 of the Regulation respectively. Part 3 of the Regulation stipulates the general control requirements (e.g. site boundary and entrance) for construction dust. The control requirements for individual activities (e.g. stockpiling of dusty material) are given in Part 4 of the Regulation.
Environmental Impact Assessment Ordinance
and Technical Memorandum on Environmental Impact Assessment Process
2.2.4
The criteria for evaluating air quality impacts
are stated in Annexes 4 and 12 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM). The EIAO-TM states that the hourly Total
Suspended Particulates
(
2.3 Baseline Conditions and Air Sensitive Receivers
Baseline Conditions
2.3.1
The project mainly comprises the construction of
a secondary boundary fence along the southern edge of the existing boundary
patrol road from west (Pak Hok Chau) to east (Sha Tau Kok).
2.3.2
The nearest
Table 2‑2 Annual
Average Background Air Quality (2003 – 2007)
Air
Pollutants |
Annual Average Background Concentration
at Yuen Long Monitoring Station (ug/m3) |
Annual Average Background Concentration
at Tap Mun Monitoring Station (ug/m3) |
HKAQO (ug/m3) |
Total
Suspended Particulates ( |
103 |
- |
80 |
Respirable
Suspended Particulates (RSP) |
64 |
50 |
55 |
Nitrogen
Dioxide (NO2) |
60 |
14 |
80 |
|
26 |
15 |
80 |
Representative Air
Sensitive Receivers
2.3.3 The selected ASRs, represent the closest distance from the proposed project site boundary or patrol road alignment, have been identified within the study area of 500m of the proposed alignment of the secondary boundary fence in accordance with the criteria as set out in Annex 12 of the EIAO-TM by means of site inspections and reviews of land use plans.
2.3.4
Identified ASRs with horizontal distances from
the proposed alignment of the boundary fences are summarized in Table 2‑3. The
locations of the ASRs for each section (Sections 1 – 4) are shown in Figures
2-2 to 2-5.
Table
2‑3 Representative
Air Sensitive Receivers
|
Description |
Type of Use |
Separation Distance between the ASRs and the Project
Site Boundary |
Section 1 |
|||
|
|
Residential |
101.4 |
|
|
Residential |
63.6 |
|
Mai Po San Tsuen |
Residential |
346.7 |
|
Lin Barn Tsuen |
Residential |
441.1 |
Section 2 |
|||
|
Ha Wan Tsuen |
Residential |
13 |
|
Lok Ma Chau San Tsuen |
Residential |
21.7 |
|
Lok Ma Chau Village
House |
Residential |
77.9 |
|
|
Residential |
23.1 |
|
Ma |
Residential |
15.6 |
|
Liu Pok |
Residential |
117.9 |
|
|
Worship |
188.5 |
|
Tak Yuet Lau, House No. 4 |
Residential |
18.7 |
Section 3 |
|||
|
Lo Wu, House No. 3 |
Residential |
100.4 |
|
Lo Wu Public School, House No. 39 |
Educational |
58.5 |
|
|
Worship |
111.8 |
|
Muk Wu, House No. 125 |
Residential |
155 |
|
|
Educational |
341.8 |
|
Muk Wu Chuen Yiu, House No. 11 |
Residential |
75.8 |
|
Ta Kwu Ling, House No. 10 |
Residential |
56.3 |
|
|
Residential |
67.7 |
|
Chuk Yuen, House No. 19 |
Residential |
110 |
|
Tsz Tong |
Worship |
198.1 |
|
|
Residential |
55.8 |
|
|
Residential |
6.5 |
|
Lin Ma Hang, House No. 1A |
Residential |
199.5 |
Section 4 |
|||
|
Cannan English & Chinese Kindergarten |
Educational |
88 |
|
Ha Tam Shui Hang, House No. 221 |
Residential |
67 |
|
Sha Tau Kok Estate, Block 1 |
Residential |
88.2 |
|
Ha Tam Shui Hang, House No. 128 |
Residential |
121 |
|
Kong Ha Village |
Residential |
126.7 |
|
|
Residential |
88.2 |
2.4 Identification and Evaluation of Air Quality Impact
Construction Phase
2.4.1 The construction and demolition of the boundary fences and patrol road will be divided into four sections, from which the major construction activities include the excavation, footing construction, fence installation, road construction, the demolition of existing boundary fence and the check points at Pak Hok Chau and Sha Tau Kok. There is no consolidated demolition programme, but it is expected the demolition will be commenced after the completion of the construction of secondary boundary fence.
2.4.2 Refer to the tentative construction programme in Appendix A, some construction activities will be carried out at the same period of time. However, in real situation, each construction activity will be carried out separately at different road sections.
2.4.3
The soil materials will be mainly generated from the
construction activities including site clearance, construction and demolition,
excavation and the waste generated from the construction works. The total amount of soil materials generated
each day from the project site will be in the range of 88m3/day to
248m3/day, which depends on the sections and the construction
activities which will be carried out. As
such, an average number of trucks hauling on the site will be in the range of
11-30 trucks/day so as to remove the soil materials generated from the
construction activities. Given the
2.4.4
The likely air quality impacts arising from the construction of the secondary
boundary fences include dust nuisances and gaseous emissions from
Powered Mechanical Equipment (PMEs) and construction vehicles. It is
anticipated that fugitive dust would also be generated from construction of concrete footing and fences, material handling
and wind erosion from the site.
2.4.5 As the PMEs used for each section will not be operating concurrently as the construction works for the four sections are anticipated to be carried out in phases, fugitive dust impacts and gaseous emissions will be minimal. In addition, fugitive dust impacts from the construction vehicles will be further minimised with the implementation of the appropriate dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation. As such, air quality impacts resulting from the proposed construction works are considered to be insignificant.
Operational Phase
2.4.6 Based on site observation during October 07 to August 08 and the confirmation from the Border District Police Headquarter, the traffic flow along the Border Patrol Road (BPR) observed is less than 50 veh/hr. The main function of BPR is for boundary patrol, the Border District Police (BDP) is the main user of the BPR, the BPR would not be opened to the public except permit holders and there is no plan to revise this policy. Based on such assumption, it is anticipated that the traffic flow of the BPR would not exceed 50 veh/hr in 15 years after its commissioning. Hence, there will be limited gaseous emissions from the cars on the patrol roads, the potential air quality impacts are considered to be insignificant during operation.
Construction
Phase
2.5.1
Construction dust impacts should be controlled
within the 1-hour
2.5.2
During construction phase, the Contractor shall
make reference, but not limited,
to the following measures:
·
any excavated dusty materials or stockpile of dusty materials should be
covered entirely by impervious sheeting or sprayed with water so as to maintain
the entire surface wet, and recovered or backfilled or reinstated within 24
hours of the excavation or unloading;
·
the working area
of excavation should be sprayed with water immediately before, during and
immediately after the operations so as to maintain the entire surface wet;
·
dusty materials
carried by vehicle leaving a construction site should be covered entirely by
clean impervious sheeting;
·
the area where
vehicle washing takes place and the section of the road between the washing facilities
and the exit point should paved with concrete, bituminous materials or
hardcores;
·
the portion of
road leading only to a construction site that is within 30m of designated
vehicle entrance or exit should be kept clear of dusty materials;
·
all dusty
materials should be sprayed with water prior to any loading, unloading or
transfer operation;
·
vehicle speed
should be limited to 10kph except on completed access roads; and
·
every vehicle
should be washed to remove any dusty materials from its body and wheels before
leaving the construction sites.
Operational Phase
2.5.3 As the gaseous emission from the operation of the secondary boundary fences and new boundary patrol roads are considered to be insignificant, air quality mitigation measures during the operational phase are not required.
2.6 Potential Concurrent Projects
2.6.1
As mentioned in Section 1.8, there are three
potential concurrent projects within the assessment area. The proposed works at Section 3 will be
completed at the end of 2012, prior to the construction of the new
Boundary Control Point (
2.6.2 The advance works from River Trainings in Section 3 and proposed new wave wall or modification to existing wave wall in Section 2 will be carried out concurrently with the project work. However, it is recommended that the proposed works from the two projects would be exercised from this project to avoid any duplications. At such, an entrustment approach for the concurrent projects would be adopted, and the cumulative impacts from the concurrent project are considered to be minimal.
2.7 Environmental Monitoring and Audit
2.7.1 Full compliance with the air quality criteria will be achieved at all ASRs with the implementation of dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation. Dust monitoring is considered not necessary during the construction phase but weekly site audits are required to ensure that the dust control measures are properly implemented. No operational monitoring is considered to be necessary for this project.
2.8.1 The construction works for the four sections will be carried out in phases, the potential air quality impacts will not be anticipated. Air quality impacts resulting from the construction works of the Project are considered to be insignificant to air sensitive receivers.
2.8.2 Gaseous emissions from the operation of the secondary boundary fence and the new boundary patrol roads are considered to be insignificant, no air quality impact will be anticipated during the operational phase.
3.2 Relevant Legislations, Standards & Guidelines
General
Construction Activities during Non-Restricted Hours
3.2.1 Noise impacts arising from general construction activities other than percussive piling during the daytime period (07:00-19:00 hours of any day not being a Sunday or general holiday) shall be assessed against the noise standards tabulated in Table 3-1 below.
Table 3‑1 Noise Standards for Daytime Construction Activities
Noise Sensitive Uses |
0700 to 1900 hours on any day not being a Sunday or
general holiday, Leq (30 min), dB(A) |
All
domestic premises including temporary housing accommodation |
75 |
Hotels and
Hostels |
|
Educational
institutions including kindergarten, nurseries and all others where unaided
voice communication is required |
70 65 during
examination |
Source: EIAO-TM, Annex
5, Table 1B - Noise Standards for Daytime Construction Activities.
Note:
·
The above
standards apply to uses, which rely on opened windows for ventilation.
·
The above
standards shall be viewed as the maximum permissible noise levels assessed at
General
Construction Activities during Restricted Hours
3.2.2 Noise impacts arising from general construction activities (excluding percussive piling) conducted during the restricted hours (19:00-07:00 hours on any day and anytime on Sunday or general holiday) and percussive piling during anytime are governed by the Noise Control Ordinance (NCO).
3.2.3
For carrying out general construction activities
involving the use of Powered Mechanical Equipment (
3.2.4
The use of Specified
3.2.5
Designated areas, in which the control of SPME
and
3.2.6 All sections of the construction works except the Sha Tau Kok section have been checked to fall outside the Designated Areas defined under the NCO (with effective from 1 January 2009). Moreover, no percussive pilling will be involved in this Project.
3.2.7
As such, the application for
3.2.8
Regardless of the description or assessment made
in this chapter, the assessment of a filed application for a
3.2.9 Relevant criteria for road traffic noise levels at the affected sensitive façade are given in Table 3-2 below.
Table
3‑2 EIAO-TM Road Traffic
Noise Criteria
Noise
Sensitive Uses |
Road Traffic
Noise, Peak Hour Traffic, L10 (1-hr) dB(A) |
All domestic premises
including temporary housing accommodation |
70 |
Hotel and Hostels |
|
Educational institutions including kindergarten,
nurseries and all others where unaided voice communication is required |
65 |
Source: EIAO-TM, Annex
5, Table 1 - Noise Standards for Planning Purposes
Note:
·
The above
standards apply to uses, which rely on opened windows for ventilation.
·
The above
standards shall be viewed as the maximum permissible noise levels assessed at
3.3 Study Area and Construction Programme
3.3.1
As stated in Clause 3.4.2.2(i) of the EIA Study
Brief, the Study Area shall include all areas within
3.3.2 A tentative construction programme is shown in Appendix A. The construction programme shows that the construction activities including the excavation, footing construction, fence installation, road construction and the check point superstructure at Sha Tau Kok of all sections are in phases. However, in real situation, each construction activities will be carried out in segment by segment, the length of each segment is estimated to be 50m, which is a normal practice of construction.
3.3.3 Given that the narrow and long construction works area of Section 1 to Section 3 (~4m to 8m in width), the construction activities would be constructed sequentially along each Section. The construction works would start from the west end of each Section and cumulative impact from the concurrent works could be avoided as the length of each Section is more than 2km. Hence, the construction noise impact would be dominated by the construction activity of any one Section for each NSR.
3.3.4 Moreover, there is currently no firmed demolition programme of existing boundary fence and the check points at Lok Ma Chau, Sha Ling, Ping Che and Shek Chung Au. It is expected the demolition activities will be commenced after the secondary boundary fence is constructed. Hence, the noise impact of construction and demolition activities could be assessed separately.
3.4.1 Representative Noise Sensitive Receivers (NSRs) have been identified in accordance with Annex 13 of the EIAO-TM. The NSRs include existing, planned/ committed noise sensitive developments and relevant uses earmarked on the relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by Lands Department, where applicable.
3.4.2 There are numerous villages situated along the proposed alignment which are identified as NSRs. For the purpose of this construction noise assessment, representative NSRs of each village close to the site have been selected within the Study Area for prediction of the levels of construction noise impact. Descriptions of selected representative existing NSRs are tabulated in Table 3-3 to Table 3-6 below and the respective locations are shown in Figure 3-2 to Figure 3-8. The shortest distance between the noise source, construction of boundary fence/ road construction, demolition of existing boundary wall and check points, which are the footing foundation of the fence and the receivers are measured and listed in Table 3-3 to Table 3-6 below. Photos of existing noise sensitive receivers are shown in Figure 3-9 and Figure 3-10.
Table 3‑3 Locations of the Existing Representative NSRs for Construction of Boundary Fence/ Road Construction/ Check Point Superstructure
NSR ID |
Description |
Usage |
Shortest Distance
(m) |
Section 1 |
|||
Mai Po |
|||
VH01 |
Village House |
Residential |
44 |
VH02 |
Village House |
Residential |
59 |
VH03 |
Village House |
Residential |
147 |
Section 2 |
|||
Ha Wan Tsuen |
|||
HAT01 |
Village House |
Residential |
206 |
Lok Ma Chau San Tsuen |
|||
LMC01 |
Village House |
Residential |
>300 |
LMC02 |
Village House |
Residential |
>300 |
LMC03 |
Village House |
Residential |
>300 |
Ping Hang |
|||
PH01 |
Village House |
Residential |
>300 |
Ma Tso Lung |
|||
MTL01 |
Village House |
Residential |
>300 |
Liu Pok |
|||
LP01 |
House No. 1B, Liu Pok |
Residential |
>300 |
Tak Yuet Lau |
|||
|
House No. 4, Tak Yuet Lau |
Residential |
204 |
Section 3 |
|||
Lo Wu |
|||
LW01 |
House No. 3, Lo Wu |
Residential |
103 |
LW02 |
House No. 39, Lo Wu |
Residential |
60 |
Muk Wu |
|||
MW01 |
House No. 125, Muk Wu |
Residential |
130 |
MW02 |
House No. 11, Muk Wu Chuen Yiu |
Residential |
78 |
Ta Kwu Ling |
|||
TKL01 |
House No. 10, Tak Kwu Ling |
Residential |
43 |
|
|||
KL01 |
Village House |
Residential |
18 |
Chuk Yuen |
|||
CY01 |
House No. 19, Chuk Yuen |
Residential |
106 |
Wang Lek |
|||
WL01 |
Village House |
Residential |
101 |
WL02 |
Village House |
Residential |
85 |
WL03 |
House No. 1A, Lin Ma
Hang |
Residential |
155 |
Section 4 |
|||
Sha Tau Kok |
|||
|
House No. 221, Ha Tam
Shui Hang |
Residential |
42 (Boundary Fence) 132 (Checkpoint superstructure) |
|
House No. 128, Ha Tam
Shui Hang |
Residential |
100 (Boundary Fence) 235 (Checkpoint superstructure) |
|
Block 1, Sha Tau Kok Estate |
Residential |
16 (Boundary Fence) 73 (Checkpoint superstructure) |