1                                  Introduction

1.1                            Background

In response to the Hong Kong SAR Government’s initiative to develop bulk waste reduction facilities to tackle Hong Kong’s waste disposal crisis, Green Island Cement Company Limited (hereafter referred to as “the Client” or GIC) established a pilot demonstration waste-to-energy facility (consisting of a Materials Recovery/Recycling Facility (MRRF) and a Co-Combustion Plant) within the Green Island Cement Plant (GICP) site at Tap Shek Kok, Tuen Mun.  The aims of the Co-Combustion Pilot Plant (CCPP) were to determine the technical and economic issues associated with the operation of a MRRF as part of an integrated waste management system; to demonstrate that the CCPP will meet the requirements of the Guidance Note on the Best Practical Means for Incinerators (Municipal Waste Incineration) (BPM 12/1 (08)) issued by the Environmental Protection Department (EPD); and to obtain engineering data to refine the design of the Co-Combustion Plant. 

The construction and installation of the CCPP was completed in February 2005 and commissioning tests were carried out in April and July/August 2005 in order to demonstrate its performance.  Continuous operation of the CCPP was started in early October 2005.  During the operation period, the cumulative operating time of the facility was 11 weeks and no more than 24 tonnes per day of Municipal Solid Waste (MSW) were treated.  After completion of the tests and achieving the research objectives, the operation of pilot plant was stopped on 17 December 2005. 

As the design throughput of the CCPP is less than 50 tonnes per day, it is not classified as a Designated Project (DP) under Category G.3 of Part I Schedule 2 of the Environmental Impact Assessment Ordinance (EIAO) and therefore the construction and operation of the plant did not require an Environmental Permit (EP).  However, the decommissioning of such municipal waste incinerator is classified as a DP under Item 3 of Part II Schedule 2 of the EIAO and hence it requires an EP prior to the decommissioning works. 

A Project Profile (PP-315/2007) for the decommissioning of the CCPP was submitted to EPD for application of an EIA Study Brief under the EIAO and Study Brief (ESB-164/2007) was issued on 7 June 2007 which sets out the scope of the work for this EIA Study.

1.2                            Objectives of the EIA Study

The decommissioning of the CCPP involves demolition of the existing structures and removal of used equipment and waste materials as well as to clean up the CCPP site (hereafter referred to as the Project).

This EIA Study is conducted in accordance with the requirements of the EIA Study Brief (No. ESB-164/2007) and the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).  The objectives of the EIA Study, as stated in the EIA Study Brief, are:

·        to describe the Project and associated works together with the requirements for carrying out the Project;

·        to identify and describe elements of community and environment likely to be affected by the Project, including natural and man-made environment and the associated environmental constraints;

·        to provide information on the consideration of alternative decommissioning methods; to provide reasons for selecting the preferred method(s) and to describe the part environmental factors played in the selection of preferred method(s);

·        to propose the provision of mitigation measures so as to minimize pollution, environmental disturbance and nuisance during the decommissioning activities;

·        to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

·        to identify, assess and specify methods, measures and standards, to be included in the proposed decommissioning works which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels; and

·        to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.

1.3                            Structure of the Report

The remainder of this EIA Report is organised as follows:

·        Section 2 describes the Project and the associated works together with the requirements for carrying out the Project; provides information on the consideration of alternative demolition methodologies and the reasons for selecting the preferred method(s) and describes the part environmental factors played in the selection of preferred method(s);

·        Section 3 presents the air quality assessment;

·        Section 4 presents the land contamination assessment;

·        Section 5 presents the an assessment of the waste management implications of the Project; 

·        Section 6 presents the water quality assessment; 

·        Section 7 describes the environmental monitoring and audit requirements during the decommissioning and demolition of the CCPP; and

·        Section 8 summarises the environmental outcomes associated with the decommissioning and demolition of the CCPP.