7                                  Environmental Monitoring and Audit Requirements

7.1                            Introduction

This Section describes the requirements for environmental monitoring and audit requirements during the demolition of the CCPP.  With respect to the identified potential impacts and the nature (including general site audits during demolition works) and frequency (monthly) of the site audit to be undertaken, it is considered that real-time reporting of the monitoring data is not applicable.  With respect to the nature of the environmental monitoring and audit (EM&A) required for the Project, it is considered that a separate EM&A Manual will not be required. 

The Implementation Schedule, containing the recommended mitigation measures, monitoring and audit requirements, and implementation agent of the mitigation measures for the Project, is presented in Annex C.

7.2                            Site Audits

Monthly site audits will be undertaken jointly by the site representative of GIC and the contractor during the demolition works to ensure that dust control, construction waste and site runoff and are managed in accordance with the good site practices described in Sections 3, 5 and 6 respectively.

7.3                            Air quality

With the implementation of the recommended control measures described in the EIA and those stipulated in the Air Pollution Control (Construction Dust) Regulation, no adverse air quality impact is anticipated.  The potential dust impact will be minimal.   No dust monitoring will be considered necessary.

The Co-Combustion residues (including bottom ash, fly ash and the residual dust collected during the cleaning process) will be used as part of the raw materials for the cement production.  As the properties of the residues are similar to the raw materials used for the cement production and they contain negligible concentration of dioxins (in terms of part per trillion) and very low concentrations of heavy metals, the reuse of the residues for the cement production at the proposed rates will not affect the air emissions of the cement plant.   No air quality monitoring will be required.  

7.4                            Land Contamination

The site investigation indicates that the contaminants analysed for all soil samples were either not detected or with concentrations well below the RBRG guideline values, the potential risk to the workers due to demolition activities will be minimal. 

After the demolition works, the Project Site will be levelled using clean imported soil.  The Project Site will remain as an open area for the operation and future development of the GICP.  It is currently proposed that the Project Site will be rehabilitated into and restored to a grass lawn.  The potential for human contact with any underlying contamination (if any) in the future is considered low.  It is therefore concluded that the risk of future exposure to any contamination is deemed negligible.  There will be no residual impacts due to the Project after the decommissioning and demolition works have been completed.

It is therefore considered that no environmental and audit requirement with respect to land contamination is required. 

7.5                            Waste Management

It is recommended that monthly site audits of the waste management practices be carried out during the Project to determine if wastes are being managed in accordance with the good site practices described in this EIA Report.  The audits should examine all aspects of waste management including waste storage, recycling, transport and disposal.

7.6                            Water Quality

The anticipated quantities of wastewater to be generated during the Project will be small and all wastewater will be treated in the on-site wastewater treatment plant.  With the implementation of general good site practices, the demolition of CCPP will not cause adverse water quality impact.  The effluent discharge from the existing wastewater treatment plant will be monitoring in accordance with the existing monitoring programme as required under the WPCO Licence.  No additional water quality monitoring is considered necessary.

7.7                            Implementation Schedule

Mitigation measures discussed in the preceding sections are summarised in the Implementation Schedule in Annex C.