6.                   GROUND-BORNE NOISE impact

Introduction

6.1               Potential ground-borne noise impacts likely arising during construction and operation phases of the Project have been evaluated and mitigation measures, if required, are recommended.

Environmental Legislation, Standards and Guidelines

Construction Phase

6.2               Ground-borne construction noise is under the control of the Noise Control Ordinance (NCO), the Environmental Impact Assessment Ordinance (EIAO), and their subsidiary Technical Memorandum. With reference to the Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (IND-TM) under the NCO, the criteria for noise transmitted primarily through the structural elements of the building or buildings should be 10dB(A) less than the relevant acceptable noise level (ANL). 

6.3               Between 1900 and 0700 hours and all day on Sundays and public holidays, activities involving the use of powered mechanical equipment (PME) for the purpose of carrying out construction work is prohibited unless a Construction Noise Permit (CNP) has been obtained.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the NSRs.  ANLs are assigned depending upon the Area Sensitivity Ratings (ASRs).  The criteria applied for ground-borne noise assessment are summarised in Table 6.1 below.

 

Table 6.1          Ground-borne Construction Noise Criteria

 

Ground-borne Construction Noise Criteria, dB(A)


GBNSR Description

Daytime

(0700-1900 hrs)
(except General Holidays & Sunday)

Daytime during general holidays and Sundays and all days during Evening
(1900 to 2300 hrs)

Night-time
(2300 to 0700 hrs)

A

B

C

A

B

C

Education institutions

 

60/55 [a]

50

55

60

[b]

Domestic premises, hotels

 

65

50

55

60

35

40

45

Churches/temples, libraries, courts, performing arts, clinics

60

50

55

60

[b]

                Notes:

                [a] A 5dB(A) reduction to the ground-borne noise criteria is recommended for school during examination period.

                [b] No sensitive use during this period.

               

6.4               For construction activities involving the use of TBM and PME during the restricted hours (i.e. 1900-0700 hours), it is necessary to apply for a Construction Noise Permit (CNP) under NCO.  However, there is no guarantee that a CNP will be issued for the project construction.   The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant Technical Memoranda issued under the NCO. The Noise Control Authority will take into account contemporary conditions/ situations of adjoining land uses and any previous complaints against construction activities at the site before deciding whether to grant a CNP.  Nothing in the EIA Report should bind the Noise Control Authority in making its decision.  If a CNP is to be issued, the Noise Control Authority would include in the permit any condition it thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO.

Operation Phase

6.5               With reference to the IND-TM under the NCO, the criteria for noise transmitted primarily through the structural elements of the building or buildings should be 10dB(A) less than the relevant acceptable noise level (ANL).   The same criteria are applied to all residential buildings, schools, clinics, hospitals, temples and churches.

6.6               The operational ground-borne railway noise criteria for the representative ground-borne noise sensitive receivers (GBNSRs) along the Project alignment are presented in Table 6.2 below.

 

Table 6.2          Operational Ground-borne Railway Noise Criteria

 

Ground-borne Railway Noise Criteria, dB(A)


GBNSR Description

Day and Evening
Periods

(0900 to 2300 hrs)

Night-time Period
(2300 to 0700 hrs)

A

B

C

A

B

C

Churches/temples, schools,  medical clinics, libraries, courts and performing arts

 

50

55

60

[a]

Domestic premises, hotels and hospitals

 

50

55

60

40

45

50

                Note:

                [a] No sensitive use during this period.

                          

Identification of Ground-borne Noise Sensitive Receivers

6.7               In order to evaluate the construction and operational noise impacts likely to arise from the Project, representative GBNSRs (both existing and planned NSRs) within 300m of the Project boundary and at the most critical locations were selected, according to the criteria set out in the Annex 13 of EIAO-TM, observations from site visits and review of relevant land use plans including the Outline Zoning Plan (OZP) as presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M54/050 to 069, information available in the Statutory Planning Portal of the Town Planning Board (TPB) and land status plans published by Lands Department.

Construction Phase

6.8               Potential ground-borne noise impacts on GBNSRs during the construction phase would arise mainly from hydraulic breakers, drill rigs, pipe pile rigs and tunnel boring machine (TBM).

6.9               Under the assumption of worst-case scenario, two sets of representative GBNSRs were identified for the assessment of noise impact induced by (1) TBM operation for tunnelling; and (2) PME (i.e. hydraulic breakers, drill rigs and pile rigs) operation during the construction of adits.  Representative GBNSRs identified along the alignment were designated for the assessment of TBM-induced ground-borne noise impact.  As for the assessment of noise impact due to the use of PME for rock breaking / drilling, including hydraulic breakers, drill rigs and pipe pile rigs for the construction of adits, representative GBNSRs located in the closest proximity to the concerned areas were also identified.  The identified GBNSRs are presented in Tables 6.3 and 6.4 and shown in NOL/ERL/300C/XRL/ENS/M53/002 to 025.

Table 6.3          Identified GBNSRs for Assessment of Ground-borne Construction Noise Impacts due to TBM operation

GBNSR No.

Location

Uses

Existing / Planned NSR

No. of Storeys

GN3

Yaumati Catholic Primary School (Hoi Wang Road)

School

Existing

8

GN4

Block 9, Charming Garden

Residential

Existing

23

GN5

Tower 5 Phase 1 Park Avenue

Residential

Existing

48

GN6

Hing Wong Mansion

Residential

Existing

16

GN7

Tai Fung Building (Block F) Cosmopolitan Estates

Residential

Existing

14

GN8

Chung Yew Building

Residential

Existing

15

GN9

West Kowloon Disciplined Services Quarters Block 1

Institutional 

Existing

38

GN10

Fu Yun House, Fu Cheong Estate

Residential

Existing

8

GN12

SKH St. Mary's Church Mok Hing Yiu College

School

Existing

9

GN12a

Tack Ching Girls' Secondary School

School

Existing

8

GN13

Tower 6 Aqua Marine

Residential

Existing

46

GN14

HKIVE Haking Wong Waterfront Annex

School

Existing

2

GN14a

Lai Chi Kok Reception Centre

Institutional 

Existing

8

GN26

426A Tsang Uk Tsuen

Residential

Existing

3

GN27

431A Tsang Uk Tsuen

Residential

Existing

3

GN28

510B Nam Hing Lei

Residential

Existing

3

GN29

630 Sheung Tsuen

Residential

Existing

2

GN31

DD110 LOT 482, Wang Toi Shan

Residential

Existing

1

GN33

348 Tsat Sing Kong

Residential

Existing

1

GN34

349 Tsat Sing Kong

Residential

Existing

2

GN35

374 Chuk Yau Road

Residential

Existing

1

GN36

DD104 LOT 1786, Chuk Yau Road

Residential

Existing

2

GN37

DD104 LOT 1396, Yau Tam Mei Tsuen, Chuk Yau Road

Residential

Existing

1

GN37a

Chun Shin Road, Yau Tam Mei Tsuen

Residential

Existing

2

GN38

45 Wai Tsai Tsuen

Residential

Existing

2

GN38a

Petrus Avenue House 21 Phase 1 The Vineyard

Residential

Existing

3

GN38b

China Bible Seminary

School

Existing

3

GN39

62D Wai Tsai Tsuen

Residential

Existing

3

GN40

House 1, Green Crest

Residential

Existing

3

GN41

House A73 Maple Gardens

Residential

Existing

3

GN42

House A78 Maple Gardens

Residential

Existing

3

GN43

Planned Development

Residential

Planned

N/A

GN44

House 5 Phase A Royal Palms

Residential

Existing

3

GN45

Village house in Mai Po

Residential

Existing

1

 

Table 6.4          Identified GBNSRs for Assessment of Ground-borne Construction Noise Impacts due to the Construction of Adits

GBNSR No.

Location

Uses

Existing / Planned NSR

No. of Storeys

GN12a

Tack Ching Girls' Secondary School

School

Existing

8

GN14a

Lai Chi Kok Reception Centre

Institutional

Existing

8

GN14b

Ward A, Ex-Lai Chi Kok Hospital(1)

Hostel

Existing

2

GN14c

Po Leung Kuk Tong Nai Kan College

School

Existing

7

GN15

40A Cheung Hang Village

Residential

Existing

2

GN16

Tower 6 Regency Park

Residential

Existing

17

GN17

Block 21 Wonderland Villas

Residential

Existing

20

GN18

Block 2 Greenknoll Court

Residential

Existing

31

GN18a

Block 17 Wonder Land

Residential

Existing

21

GN19

Tower B Kwai Sing Centre

Residential

Existing

28

GN20

Block B Hutchison Estate

Residential

Existing

23

GN21

184 Yau Ma Hom Resite Village

Residential

Existing

3

GN21a

274 Yau Ma Hom Resite Village

Residential

Existing

3

GN22

18 Da Chuen Ping Village

Residential

Existing

3

GN22a

37 Chung Kwai Chung Tsuen

Residential

Existing

3

GN23

35 Sheung Kwai Chung Village

Residential

Existing

4

GN24

Sau Shan House, Cheung Shan Estate

Residential

Existing

25

GN25

Tsuen Wan Lutheran School

School

Existing

7

GN25a

DD 114 LOT 1405 Sheung Tsuen

Residential

Existing

2

GN30

51A Leung Uk Tsuen

Residential

Existing

3

GN35

374 Chuk Yau Road

Residential

Existing

1

Remark:

(1) The future usage of Ex-Lai Chi Kok Hospital was announced to be converted as holiday camp, hostel, arts and cultural village, educational institute under Revitalising Historic Buildings Through Partnership Scheme. 

 

Operation Phase

6.10            Sensitive receivers along the alignment generally include educational institutions, performing arts and domestic premises.  Domestic premises are taken into account during both the daytime and night time periods, while performing arts and educational institutions are considered to be noise sensitive during daytime and evening only.

6.11            Representative operational phase GBNSRs have been identified and are listed in Table 6.5. Their locations are shown in NOL/ERL/300C/XRL/ENS/M53/000 to 025.  As a conservative approach, it is assumed that the sensitive receivers are not affected by any IF.  For the interface between WKT and West Kowloon Cultural District (WKCD), MTR and WKCD Authority will further liaise with each other for dealing with the details of interfacing issues and mitigation measures.

6.12            Information necessary including the geometry of the closest point on a GBNSR relative to the alignment as well as the structure characterisation for noise prediction is shown in Table 6.5. 

Table 6.5          Operation Phase Ground-borne Railway Noise Sensitive Receivers

GBNSR No.

 

Location

Uses

Type of Area Containing NSR

Degree to which NSR is affected by IF(a)

ASR

No. of storeys

Building Type(b)

Basement(c)

TCF(h)

BCF Type(g)

Slant Distance to nearest Track, m

GN1

Future Development at West Kowloon Cultural District

Performing Art

Urban

Not Affected

B

N.A.

N.A.

N.A.

R

2

31

GN2

Future Development at West Kowloon Cultural District

Performing Art

Urban

Not Affected

B

N.A.

N.A.

N.A.

R

2

47

GN2a

WKT Topside Development

Comprehensive Development Area

Urban

Not Affected

B

N.A.

N.A.

N.A.

R

2

N.A.

GN2b

WKT Topside Development

Comprehensive Development Area

Urban

Not Affected

B

N.A.

N.A.

N.A.

R

2

N.A.

GN2c

WKT Topside Development

Comprehensive Development Area

Urban

Not Affected

B

N.A.

N.A.

N.A.

R

2

N.A.

GN2d

Block 6 Phase 1 Sorrento

Residential

Urban

Not Affected

B

52

0

0

R

2

47

GN2e

Man King Building

Residential

Urban

Not Affected

B

19

0

0

R

2

62

GN3

Yaumati Catholic Primary School (Hoi Wang Road)

School

Urban

Not Affected

B

8

0

0

S

1

30

GN4

Block 9, Charming Garden

Residential

Urban

Not Affected

B

23

0

0

S

3

32

GN5

Tower 5 Phase 1 Park Avenue

Residential

Urban

Not Affected

B

48

0

0

R

2

36

GN6

Hing Wong Mansion

Residential

Urban

Not Affected

B

16

0

0

R

1

34

GN7

Tai Fung Building (Block F) Cosmopolitan Estates

Residential

Urban

Not Affected

B

14

0

0

R

1

34

GN8

Chung Yew Building

Residential

Urban

Not Affected

B

15

0

0

R

1

34

GN9

West Kowloon Disciplined Services Quarters Block 1

Institutional 

Urban

Not Affected

B

38

0

0

S

3

40

GN10

Fu Yun House, Fu Cheong Estate

Residential

Urban

Not Affected

B

8

0

0

S

3

35

GN11

Planned Nam Cheong Station Properties Development

Residential

Urban

Not Affected

B

N.A.

N.A.

N.A.

S

3

32

GN11a

Planned Residential Development in Site 6

Residential

Urban

Not Affected

B

N.A.

N.A.

N.A.

S

3

N.A.

GN12

SKH St. Mary's Church Mok Hing Yiu College

School

Urban

Not Affected

B

9

0

0

S

3

42

GN12a

Tack Ching Girls' Secondary School

School

Urban

Not Affected

B

8

0

0

S

3

50

GN13

Tower 6 Aqua Marine

Residential

Urban

Not Affected

B

46

0

0

S

1

40

GN14

HKIVE Haking Wong Waterfront Annex

School

Urban

Not Affected

B

2

2

0

S

0

34

GN14a

Lai Chi Kok Reception Centre

Institutional 

Other

Not Affected

B

8

0

0

R

2

52

GN14b

Ward A, Lai Chi Kok Hospital

(e) 

Other

Not Affected

B

2

2

0

R

0

90

GN15

40A Cheung Hang Village

Residential

Low Density Residential Area

Not Affected

A

2

2

0

R

0

235

GN16

Tower 6 Regency Park

Residential

Other

Not Affected

B

17

0

0

R

2

248

GN17

Block 21 Wonderland Villas

Residential

Other

Not Affected

B

20

0

0

R

2

275

GN18

Block 2 Greenknoll Court

Residential

Urban

Not Affected

B

31

0

0

R

2

93

GN18b

Kwai Ying Building

Residential

Urban

Not Affected

B

19

0

0

R

2

76

GN19

Tower B Kwai Sing Centre

Residential

Urban

Not Affected

B

28

0

0

R

2

57

GN19a

Ming Tak Building

Residential

Urban

Not Affected

B

6

0

0

R

2

59

GN20

Block B Hutchison Estate

Residential

Urban

Not Affected

B

23

0

0

R

2

53

GN21

184 Yau Ma Hom Resite Village

Residential

Other

Not Affected

B

3

1

0

R

0

73

GN22

18 Da Chuen Ping Village

Residential

Rural Area

Not Affected

A

3

1

0

R

0

87

GN23

35 Sheung Kwai Chung Village

Residential

Rural Area

Not Affected

A

4

1

0

R

0

98

GN24

Sau Shan House, Cheung Shan Estate

Residential

Urban

Not Affected

B

25

0

0

R

2

124

GN25

Tsuen Wan Lutheran School

School

Urban

Not Affected

B

7

0

0

R

2

124

GN26

426A Tsang Uk Tsuen

Residential

Rural

Not Affected

A

3

1

0

S

0

23

GN27

431A Tsang Uk Tsuen

Residential

Rural

Not Affected

A

3

1

0

S

0

26

GN28

510B Nam Hing Lei

Residential

Rural

Not Affected

A

3

1

0

S

0

26

GN29

630 Sheung Tsuen

Residential

Rural

Not Affected

A

2

2

0

S

0

28

GN30

51A Leung Uk Tsuen

Residential

Other(f)

Not Affected

B

3

1

0

S

0

113

GN30a

Village Zone West Boundary, Leung Uk Tsuen

Residential

Other(f)

Not Affected

B

3

1

0

S

0

61

GN30b

Village house in Leung Uk Tsuen

Residential

Other(f)

Not Affected

B

3

1

0

S

0

46

GN31

DD110 LOT 482, Wang Toi Shan

Residential

Other(f)

Not Affected

B

1

2

0

R

0

19

GN33

348 Tsat Sing Kong

Residential

Rural Area

Not Affected

A

1

2

0

S

0

25

GN34

349 Tsat Sing Kong

Residential

Rural Area

Not Affected

A

2

2

0

S

0

25

GN35

374 Chuk Yau Road

Residential

Rural Area

Not Affected

A

1

2

0

S

0

46

GN36

DD104 LOT 1786, Chuk Yau Road

Residential

Rural Area

Not Affected

A

2

2

0

S

0

31

GN37

DD104 LOT 1396, Yau Tam Mei Tsuen, Chuk Yau Road

Residential

Rural Area

Not Affected

A

1

2

0

S

0

30

GN37a

Chun Shin Road, Yau Tam Mei Tsuen

Residential

Rural Area

Not Affected

A

2

2

0

S

0

53

GN38

45 Wai Tsai Tsuen

Residential

Rural Area

Not Affected

A

2

2

0

S

0

33

GN38a

Petrus Avenue House 21 Phase 1 The Vineyard

Residential

Low Density Residential Area

Not Affected

A

3

1

0

S

0

34

GN38b

China Bible Seminary

School

Rural Area

Not Affected

A

3

1

0

S

0

29

GN39

62D Wai Tsai Tsuen

Residential

Rural Area

Not Affected

A

3

1

0

S

0

34

GN40

House 1, Green Crest

Residential

Low Density Residential Area

Not Affected

A

3

1

0

R

0

42

GN41

House A73 Maple Gardens

Residential

Low Density Residential Area

Not Affected

A

3

1

0

S

0

39

GN42

House A78 Maple Gardens

Residential

Low Density Residential Area

Not Affected

A

3

1

0

S

0

38

GN43

Planned Development

Residential

Low Density Residential Area

Not Affected

A

N.A.

N.A.

N.A.

S

3

31

GN44

House 5 Phase A Royal Palms

Residential

Low Density Residential Area

Not Affected

A

3

1

0

S

0

51

GN45

Village house in Mai Po

Residential

Rural Area

Not Affected

A

1

2

0

S

0

32

Remark:

(a) As a conservative assessment, it is assumed that the sensitive receivers will not be affected by any IF.

(b) Building Type: 0 – Heavy Tall Structures; 1 – 2 to 4 storeys medium height; 2 – 1 to 2 storeys.

(c) Basement:  0 – no basement; 1 – basement.

(d) N.A.: Information for future property development is not available during the preparation of report.

(e) The future usage of Ex-Lai Chi Kok Hospital was announced to be converted as holiday camp, hostel, arts and cultural village, educational institute under Revitalising Historic Buildings Through Partnership Scheme.

(f) "Area other than those above" as the SSS by virtue of its size and characteristics plays a major role in determining the type of area within which the NSR is located in accordance with the Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites.

(g) BCF Type: 0 – No piles, with BCF; 1 – Piles not to rock, with BCF; 2 – Piles to rock & tunnel in rock, no BCF; 3 –  Piles to rock & tunnel not in rock, with BCF

(h) TCF: R – Tunnel in rock, no TCF; S – Tunnel in soil, with TCF

 

Potential Sources of Impact

Construction Phase

6.13            Potential ground-borne noise impacts on GBNSRs during the construction phase will arise mainly from TBM operation, as well as PME for rock breaking/drilling including breakers, drill rigs and pipe pile rigs.  The standard working hours of PME will be from 0700 to 1900 hours and the TBM will be operated on a 24 hour basis.  The operation of TBM during restricted hours should be governed by the control of CNP under NCO.  Regardless of the results of construction noise impact assessment for restricted hours, the Noise Control Authority will process CNP application, if necessary, based on the NCO, the relevant technical memoranda issued under the NCO, and the contemporary conditions/situations of adjoining land uses and any previous complaints against construction activities at the site before making his decision in granting a CNP.

Operation Phase

6.14            When trains operate in tunnels that are located in close proximity to occupied structures, there is a possibility that vibrations associated with train passbys will be transmitted through the ground and structure, and be radiated as noise in the occupied spaces within the structure. The transmitted noise through the structure may have impact to the GBNSRs.

Ground-borne Noise Prediction Methodology

Construction Phase

6.15            The project methodology adopted for assessment is recommended in The Transit Noise and Vibration Impact Assessment[[1]] published by U.S. Department of Transportation Federal Transit Administration (FTA) (FTA Guidance Manual).  This methodology has been previously adopted for ground-borne noise assessment in approved Kowloon Southern Link (KSL) EIA Study (EIA Register No. AEIAR-083/2005) and West Island Line (WIL) EIA Study (EIA Register No. AEIAR-126/2008). The empirical based prediction model used to predict noise levels at the representative NSRs adopts the following equation:

L = FDL + LSR + BCF + BVR + CTN + SAF

            where

L

ground-borne noise level within the structure, re: 20 μ-Pascal

FDL

force density level for the TBM in rock, mixed face or soil, re: 1 N/m0.5 in SI unit

LSR

unit force incoherent line source response for the ground, re: 10-8 m/s/(1 N/m0.5) in SI unit

BCF

vibration coupling loss factor between the soil and the foundation, relative level

BVR

building vibration reduction or amplification within a structure from the foundation to the occupied areas, relative level

CTN

Conversion from floor and wall vibration to noise, 10-8 m/s to 20 μ Pascal

SAF

Safety margin to account for project uncertainties

TBM-induced Ground-borne Noise Impact Assessment

6.16            The TBM-induced ground-borne noise levels were calculated by incorporating the algorithms in a 3-D model, MoleRat, developed by Wilkinson Murray Limited. 

6.17            The prediction model adopted is based on the equation discussed in Section 6.15 and is referenced from the FTA Guidance Manual.  The prediction components particular for TBM-induced ground-borne noise are described in following sections.

Ground-Borne Noise Level within the Structure (L)

6.18            TBM-induced ground-borne noise would have an impact with frequency, conservatively, up to about 160 Hz and 400Hz for tunnels situated in soil and rock respectively.  Above these frequencies, the material attenuation of the ground would reduce the amplitude of the propagating waves below which there would be adverse impact.  Thus, structure-borne noise levels were presented in 1/3 octave bands over the frequency range of 12.5 Hz to 400 Hz.

Force Density Level (FDL)

6.19            FDL values to be adopted for assessment were reference from WIL EIA Study in which the assessment adopted the vibration measurement taken during the passby of a TBM operating in soil and rock along the MTR Lok Ma Chau (LMC) Extension.  Measurements were performed underground in an access shaft adjacent to the alignment at 7m setback from tunnel centreline.  The associated line source response (LSR) was obtained from surface and borehole impact tests performed on similar soil and rock geology.  On the assumption of a TBM source length of 10m, the FDL values in soil and rock are shown in Appendix 6.1.  FDL is dependent upon TBM diameter and ground condition, but these factors may be represented by the power to be used by the TBM.  The outside diameter (OD) of TBM to be adopted for the construction of the Project will be about 9.3m and a standard drive rate of 200m/month was assumed though the actual rate will be dependent on the ground condition.  Average rates were reference from the case in LMC with 11 m/day in soft ground and 8.0 m/day in rock.  While the outside diameter of TBM used for the construction of LMC is 8.8m, and therefore FDL values of the proposed TBM are therefore considered to be of comparable magnitude with the TBM used in LMC.

6.20            Measurement results indicated that the FDL for the TBM in rock is considerably higher than that in soil, especially at low frequencies.  As a conservative approach, the FDL values in mixed face geology rock have been assumed to be same as that in rock.

Line Source Response (LSR)

6.21            The LSR determines the vibration levels or attenuation in the ground as a function of distance caused by an incoherent line source of unit force point impacts, with line source (TBM) orientated along the alignment.  

6.22            LSR has already been measured in Hong Kong at a number of locations, and the most relevant measured results (taking into account the ground type) will be used for the calculations.  The LSR was referenced from the data adopted in KSL and WIL EIA Studies. The LSR for WIL EIA Study were determined based on the results of borehole impact tests performed in rock, soil and close to the rock head both on the soil side and the rock side, with receiver vibration data taken at many setback distances.  Appropriate LSR has been selected accordingly with consideration of geological characteristics along alignment.  Mostly the rock through which the tunnel will pass is granite with highly decomposed granite and alluvium on top, and the LSR values used from WIL are those obtained by testing in the same rock and ground material.  LSR for different geological characteristics have been presented in Appendix 6.2.   

6.23            The LSR values used for assessment are shown in Table 6.6.

Table 6.6          LSR Values used for Assessment

Alignment

Corresponding LSR selected from WIL EIA Study

Chainage (Northbound)

Chainage (Southbound)

Track Depth (m)

Rockhead Depth (m)

LSR Name

Borehole Depth (m)

Rockhead Depth (m)

From

To

From

To

116+015

116+815

116+000

116+800

No GBNSR

116+815

118+015

116+800

118+000

30

60

D012-18m

18

34.4

118+015

118+465

118+000

118+450

40

40

D012-41.4m

41.4

34.4

118+465

119+695

118+450

119+680

27

55

D012-18m

18

34.4

119+695

119+815

119+680

119+800

60

25

D049-60.4m

60.4

19.4

119+815

119+915

119+800

119+900

80

25

D049-87.8m

87.8

19.4

119+915

120+015

119+900

120+000

110

25

D049-87.8m

87.8

19.4

120+015

122+115

120+000

122+100

No GBNSR

122+115

122+315

122+100

122+300

65

15

D064-66.7m

66.7

14.7

122+315

122+415

122+300

122+400

45

10

D064-54.6m

54.6

14.7

122+415

122+515

122+400

122+500

38

20

D028-44.3m

44.3

22.3

122+515

122+675

122+500

122+660

38

25

D018-39.8m

39.8

27.6

122+675

122+975

122+660

122+960

27

30

D002-19.6m

19.6

24.1

122+975

123+175

122+960

123+160

20

32

D012-18m

18

34.4

123+175

123+515

123+160

123+500

17

13

D018-39.8m

39.8

27.6

123+515

125+365

123+500

125+350

20

25

D002-19.6m

19.6

24.1

125+365

125+465

125+350

125+450

25

15

D018-39.8m

39.8

27.6

125+465

125+565

125+450

125+550

50

10

D064-54.6m

54.6

14.7

125+565

125+665

125+550

125+650

75

10

D049-87.8m

87.8

19.4

125+665

125+765

125+650

125+750

95

10

D049-87.8m

87.8

19.4

125+765

131+815

125+750

131+800

No GBNSR

131+815

132+365

131+800

132+350

100

10

D049-87.8m

87.8

19.4

132+365

132+835

132+350

132+820

90

15

D049-87.8m

87.8

19.4

132+835

133+035

132+820

133+020

65

10

D064-66.7m

66.7

14.7

133+035

133+765

133+020

133+750

55

15

D064-54.6m

54.6

14.7

133+765

134+135

133+750

134+120

80

10

D049-87.8m

87.8

19.4

134+135

135+515

134+120

135+500

185

20

D049-87.8m

87.8

19.4

135+515

136+465

135+500

136+450

No GBNSR

136+465

136+695

136+450

136+680

95

25

D049-87.8m

87.8

19.4

136+695

136+915

136+680

136+900

35

20

D018-39.8m

39.8

27.6

136+915

137+235

136+900

137+220

35

35

D002-33.7m

33.7

24.1

137+235

137+595

137+220

137+580

35

40

D002-19.6m

19.6

24.1

137+595

137+835

137+580

137+820

33

55

D012-18m

18

34.4

137+835

137+935

137+820

137+920

33

33

D002-33.7m

33.7

24.1

137+935

138+115

137+920

138+100

33

50

D012-18m

18

34.4

138+115

138+465

138+100

138+450

33

80

D012-18m

18

34.4

138+465

139+115

138+450

139+100

35

50

D012-18m

18

34.4

139+115

139+315

139+100

139+300

35

30

D018-39.8m

39.8

27.6

139+315

139+815

139+300

139+800

40

20

D028-44.3m

44.3

22.3

139+815

139+905

139+800

139+890

38

38

D012-41.4m

41.4

34.4

139+905

140+215

139+890

140+200

40

60

D012-18m

18

34.4

140+215

141+115

140+200

141+100

30

50

D012-18m

18

34.4

141+115

141+315

141+100

141+300

30

30

D002-33.7m

33.7

24.1

141+315

141+671

141+300

141+656

27

40

D012-18m

18

34.4

Building Coupling Factor (BCF)

6.24            In general, larger and heavier structures have greater vibration attenuation than smaller and lighter structures. The recommended practice established within FTA Manual has been followed. Receivers in this study were divided into 4 types according to its structures and have different BCF attenuation as below:

Type 0 – Large masonry buildings

Type 1 – 2-4 storeys masonry buildings

Type 2 – 1-2 storeys buildings

Type 3 – Single family detached residences

6.25            The BCF for different types of structure is presented in Appendix 6.3.  It is indicated that larger and heavier structures have greater vibration attenuation than smaller and lighter structures. In fact, the extent of the attenuation is governed by the difference in mechanical impedance between the soil and the foundation, with impedance being determined by differences in mass and stiffness within the soil and foundation.  For structures founded on rock, there is no impedance contrast between the soil and the foundation, as a conservative approach, the BCF is considered to be zero.

6.26            It has been assumed that buildings up to three stories in height do not have piles, and buildings over this height do, unless specific information is available for assessment.  For most of the high-rise buildings, details of the piles are available, including whether the piles are to rock or are friction piles.  In those cases where no details of the piles were available, a worst case scenario has been assumed; that the piles are to rock such that no coupling loss was taken into account.

Building Vibration Response (BVR)

6.27            The BVR is generally determined by three factors as described below:

I.             Resonance amplification due to floor, wall and ceiling spans: This resonance amplification is usually an issue for small and lightweight houses. In large, heavy framed structures, generally multi-floor concrete construction, structural resonances usually occur at sub-audible frequencies, with small resonance amplification due to massive structural elements having low mobility.   FTA Manual recommends a 6 dB correction at the likely natural frequency of structures to account for structural resonances. The corrections given in Appendix 6.4 were adopted, as was the case for the WIL EIA Study.

II.           Floor-to-floor attenuation: A floor-to-floor attenuation of 2 dB reduction per floor was assumed.  Where there is a multi-floor occupancy, only the structure-borne noise impact on the lowest occupied floor is considered.

III.          Attenuation across a structure, in the direction away from the alignment: When the noise sensitive area is situated in the back of the building away from the alignment, vibration attenuation across a structure would occur. Attenuation of 2 dB reduction was considered in this study, and this is conservative for large setbacks.

Conversion to Noise (CTN)

6.28            Based on FTA Manual, a -27 dB correction for conversion of vibration (re: 10-9 m/s) in room walls, floors and ceiling to noise (re: 20 micro Pa) was assumed in this study.

Safety Factor (SAF)

6.29            To tackle the problem of differences in overall predicted and measured A-weighted noise levels, a safety factor was applied in the model. As a conservative approach, a 10 dB safety factor was adopted to account for uncertainty and variation in geological characteristics.

PME-induced Ground-borne Noise Impact

6.30            For the assessment of PME-induced ground-borne noise, reference was made to the assessment approach, source terms and transmission factors adopted in the approved KSL and WIL EIA Studies.  The reference source levels adopted for assessment are given in Table 6.7.

Table 6.7          Reference Source Levels         

Plant

Vibration (rms) at reference distance of 5.5m from source[[2]]

Vibration (ppv) at distance 2m from source

Hydraulic Breaker

0.298 mm/s

-

Drill Rig

0.536 mm/s

-

Pile Rig

-

19.3 mm/s

Soil Damping

6.31            Internal losses of soil would cause the vibration amplitude to decay against the propagation distance and the decay relationship is based on the equation set out in the Transportation Noise Reference Book[[3]].

V(R) = V(Ro) ´ e-2pf h R/2c.

6.32            The velocity amplitude V is dependent on the frequency f in Hz, the soil loss factorh, the wave speed c in m/s, the distance R from the source to the GBNSR.  The properties of soil materials are shown in Table 6.8.

Table 6.8          Wave Propagation Properties of Soil   

Soil Type

Longitudinal Wave Speed c, m/s

Loss Factor, h

Density, g/cm3

Soil

1500

0.5

1.7

Rock

3500

0.01

2.65

6.33            It was assumed that no damping attenuation would apply for propagation in rocks. Therefore, soil damping for GBNSRs with piling foundation on rockhead was not required.

Coupling Loss into Building Structures

6.34            This was as assumed for TBM-induced ground-borne noise calculation above.

Loss Per Floor

6.35            This was as assumed for TBM-induced ground-borne noise calculation above.

Conversion from Floor Vibration to Noise Levels

6.36            This was as assumed for TBM-induced ground-borne noise calculation above.

Operation Phase

6.37            The railway ground-borne noise levels were calculated by incorporating the algorithms in a 3-D model, MoleRat, developed by Wilkinson Murray Limited. 

6.38            The methodology adopted for the ground-borne noise impact assessment is in accordance with the procedures outlined in FTA Guidance Manual and High-Speed Ground Transportation Noise and Vibration Impact[[4]](FRA High-Speed Guidance Manual).  This is a similar methodology as used for WIL EIA Study.  The ground-borne noise level in GBNSRs were calculated as follows:

                                L = FDL + TIL + TOC + TCF + LSR + BCF + BVR + CTN + SAF

where

L

ground-borne noise  level within building, in dB

FDL

force density level, in dB re 1N/m1/2

TIL

trackform attenuation or insertion loss, relative level

TOC

turnout and crossover factor

TCF

vibration coupling between the tunnel and the ground for soil based tunnels, relative level

LSR

line source transfer mobility, in dB re 1(nm/s)/(Nm^0.5)

BCF

BVR

CTN

SAF

adjustment to account for building coupling loss, in dB

building vibration amplification within the structure, in dB

conversion from vibration to noise within the building, in dB

safety factor to account for wheel/rail condition and uncertainties in ground conditions, in dB

Force Density Levels (FDL)

6.39            Since high speed trains in 200km/h are currently not running in Hong Kong and details of the CRH trains proposed for the Project are not available during the preparation of EIA study, the vibration source levels (force density levels, FDL) were referenced from the FRA High-Speed Guidance Manual, which is designed for assessment when details of train type is unknown.  The level adopted for train type of China Railway High-Speed (CRH) train has been based on the noisiest train reported (i.e. Acela) in FRA High-Speed Guidance Manual and is shown in metric units in Appendix 6.5.  The highest level among four trains as given in FRA High-Speed Guidance Manual was adopted for assessment.  This level is based on a standard high speed train trackform of a moderate to high stiffness, similar to the proposed 50kN/mm.

6.40            The adopted FDL is for a train on rails in moderate operational condition and a rail maintenance programme will be developed for the Project.  This FDL will be considered to identify the ground-borne noise mitigation measures for the Project.

6.41            In accordance with Table 8-2 of the FRA High-Speed Guidance Manual, the FDL was adjusted for speed as 20 log S/Sref.

Trackform Alternatives or Insertion Loss (TIL)

6.42            Trackform attenuation has two components: the magnitude of the attenuation and the frequency above which attenuation occurs (resonance frequency of the trackform).  Generally, more compliant trackform support and more massive elements in the trackform will result in a greater magnitude of attenuation occurring at lower frequencies.  In addition, more massive trackform elements would take up more space in tunnels and may cause spatial incompatibilities that are difficult to be overcome in the design.

6.43            The ground-borne noise levels at GBNSRs were calculated initially for a trackform of embedded concrete sleepers with slightly resilient fixings (approximately 50kN/mm) on top (e.g. Rheda system).  An example of proposed trackform is presented in Appendix 6.11. 

6.44            When the appropriate trackforms to meet the noise criteria had been identified, consideration was then given to the action to be taken if it is found that ground-borne noise levels exceed the criteria after construction.  Given there would be uncertainty on on-site/train specific data, a 600mm deep provision will be provided for the tunnel to allow for further enhancement of mitigation measures, such as installation of isolated slab track (IST), if required.  An example of low noise trackform is presented in Appendix 6.11.  As such, the currently proposed trackform (concrete sleepers with slightly resilient fixings) can be replaced with low noise trackfrom where practicable and necessary to accomplish  noise reduction of up to 15 dB(A), subject to the extent of low noise trackform provided and the dominant frequency of FDL and LSR, as a contingency measure.  Changing of the tunnel dimensions would therefore not be required if these contingency measures have to be in place.  Further measurements would be conducted to check the accuracy of the noise prediction during the tunnel construction where necessary.

Tunnel Coupling Factor (TCF)                                                                                            

6.45            Tunnel Coupling Factor (TCF) is the vibration coupling between the tunnel and the ground for soil based tunnels.  Vibration attenuation occurs at the interface between a transit tunnel and the surrounding soil on account of a mismatch in the soil and tunnel wall impedances. The TCF adopted in this study was referenced from the WIL EIA Study.  In general, tunnels borne in rock generally do not exhibit any significant vibration attenuation across the tunnel rock interface, thus no TCF attenuation is applied for rock-founded tunnels.  However, with reference to the FTA Manual, a 3dB(A) and 5dB(A) reduction in ground-borne noise level was assumed for cut-and-cover tunnels and station structures respectively in soil. 

6.46            For tunnels in soil, separate tests have been carried out in Hong Kong, and these are reported in the WIL EIA study.  The results showed a strong relationship to BCF, and the TCF adopted is the maximum envelope of the measured TCF and the type 2 BCF, as shown in Appendix 6.6.

Turnout and Crossover Factor

6.47            At points and crossings, where the wheel transitions from one rail to another, the sudden loading/unloading of the leading and trailing rails results in increased broad band vibration levels over that of plain line continuous rail. While it is not possible to machine grind the rails through either the points or crossings, surface deterioration would often be evident.  For standard level turnouts and crossings receiving average maintenance, the FTA Manual recommends a correction of 10dB. For modern inclined turnouts in good condition, where impact loads are lessened, a correction of 5dB would be appropriate. As in the recent WIL EIA study, 5dB(A) adjustment was added for inclined turnout.

Line Source Response (LSR)

6.48            The LSR determines the vibration levels or attenuation in the ground as a function of distance caused by an incoherent line source of unit force point impacts, with line source (train) orientated along the alignment.  Thus, the basic quantity required for the determination of the LSR would be the vibration response caused by a unit point source impact, which is defined as the Point Source Response (PSR).  Given that the PSR would be along the alignment, the LSR would follow directly by incoherent integration of the PSR values. However, the determination of the PSR for force point impacts along the alignment over the length of the alignment is neither practical nor affordable.  For example, at underground sections, force impacting would have to be performed in numerous boreholes drilled to the depth of the alignment and closely spaced along the alignment.  Thus, certain assumptions have been invoked, which allow one PSR to be taken as representative along the alignment near a building receiver and to be used in the determination of the LSR.  These assumptions include:  

·          ground is layer-wise homogeneous;

·          ground is transversely isotropic along the alignment over the length of the train; and

·          ground is between the alignment segment and the vibration receivers at which the LSR is to be determined.

6.49            If the ground satisfies these assumptions rigorously, it would be acceptable to use one PSR in the determination of the LSR. In normal circumstances, deviation from the idealised assumptions of transverse isotropy and layer-wise homogeneity is not significant enough to warrant the time, expense and impracticality of impacting along the entire length of the alignment. 

6.50            LSR has already been measured in Hong Kong at a number of locations, and the most relevant measured results (taking into account the ground type) were used for the calculations.  The LSR has been referenced from the data adopted in the WIL EIA Study.  Appropriate LSR has been selected accordingly with consideration of geological characteristics along the alignment, which is characterised by similar ground material to WIL.  Table 6.6 above shows the LSR values adopted for assessment.

Other Factors

6.51            Other correction factors including BCF, BVR, CTN and SAF were adopted as that mentioned under the assessment methodology of TBM-induced ground-borne noise. 

Calculation of Leq

6.52            The Leq values have been calculated using MoleRat, by the following procedures:

·         Calculate the noise level from a full train at each of many locations at 10m intervals along the whole line

·         Sum the energy from these levels and calculate the SEL level

·         Calculate the Leq levels from

Leq = 10 log [10(SELlong + 10 log Vlong)/10 + 10(SELshort + 10 log Vshort)/10] – 35.6

where

Vlong

Number of long haul train movements in the relevant 30 minute or 24 hour period, expressed as the average number of movements per hour:

For Leq(30min): V = N(30min) x 2 (N = number of movements)

For Leq(24hour): V = N(24hour)  / 24 (N = number of movements)

 

Vshort

Number of short haul train movements in the relevant 30 minute or 24 hour period, expressed as the average number of movements per hour:

For Leq(30min): V = N(30min) x 2 (N = number of movements)

For Leq(24hour): V = N(24hour)  / 24 (N = number of movements)

Ground-borne Noise Impact Assessment

Construction Phase

TBM Induced Ground-borne Noise

6.53            The tunnel will be constructed by TBM mainly in soft ground, but also in some rock or rock/soft ground border.  The locations where TBM will be used are shown in Table 6.9.

Table 6.9          Chainages where TBM Operation will occur

From

To

115+930

117+385

117+485

119+850

122+490

123+540

124+910

125+330

136+780

137+760

137+968

140+380

6.54            The TBM-induced ground-borne noise levels were predicted, and the times of day when tunneling could be carried out whilst meeting the ANLs over specific sections of the Project were also determined, basing on the following assumptions:

·         For the case where the tunnel will be in rock and the NSR is piled down to rock, the vibration path has been assumed to be horizontally across the rock and up the piles into the building;

·         For the cases where the tunnel will be in soft ground or the NSR is not on piles, the vibration path has been assumed to be through the ground along a slant path to the nearest part of the NSR

6.55            The predicted TBM ground-borne noise levels at the GNSRs with the distances adopted in the calculation are shown in Table 6.10.  Sample calculations are given in Appendix 6.7. 

Table 6.10        Predicted Ground-borne Construction Noise levels due to TBM Operation

GBNSR No.

Location

Predicted Level(1), dB(A)

Criterion, dB(A)

Acceptable
Operating
Times(2)(5)

Calculated
Distance(4)
(m)

Leq
(30min)

Leq
(day)

Leq (evening)

Leq (night)

GN3

Yaumati Catholic Primary School (Hoi Wang Road)

62

60 (55 for exam)

55

-

D(3), N

5

GN4

Block 9, Charming Garden

60

65

55

40

D

5

GN5

Tower 5 Phase 1 Park Avenue

71

65

55

40

D(3)

6

GN6

Hing Wong Mansion

56

65

55

40

D

37

GN7

Tai Fung Building (Block F) Cosmopolitan Estates

65

65

55

40

D

36

GN8

Chung Yew Building

70

65

55

40

D(3)

19

GN9

West Kowloon Disciplined Services Quarters Block 1

53

65

55

40

D, E

19

GN10

Fu Yun House, Fu Cheong Estate

52

65

55

40

D, E

15

GN12

SKH St. Mary's Church Mok Hing Yiu College

51

60 (55 for exam)

55

-

D, E, N

21

GN12a

Tack Ching Girls' Secondary School

29

60 (55 for exam)

55

-

D, E, N

40

GN13

Tower 6 Aqua Marine

36

65

55

40

D, E, N

21

GN14

HKIVE Haking Wong Waterfront Annex

53

60 (55 for exam)

55

-

D, E, N

35

GN14a

Lai Chi Kok Reception Centre

63

65

55

40

D

43

GN26

426A Tsang Uk Tsuen

42

65

55

35

D, E

23

GN27

431A Tsang Uk Tsuen

40

65

55

35

D, E

26

GN28

510B Nam Hing Lei

40

65

55

35

D, E

26

GN29

630 Sheung Tsuen

44

65

55

35

D, E

28

GN31

DD110 LOT 482, Wang Toi Shan

80

65

55

40

D(3)

19

GN33

348 Tsat Sing Kong

59

65

50

35

D

27

GN34

349 Tsat Sing Kong

61

65

50

35

D

27

GN35

374 Chuk Yau Road

57

65

50

35

D

46

GN36

DD104 LOT 1786, Chuk Yau Road

43

65

50

35

D, E

31

GN37

DD104 LOT 1396, Yau Tam Mei Tsuen, Chuk Yau Road

40

65

50

35

D, E

29

GN37a

Chun Shin Road, Yau Tam Mei Tsuen

41

65

50

35

D, E

53

GN38

45 Wai Tsai Tsuen

46

65

50

35

D, E

33

GN38a

Petrus Avenue House 21 Phase 1 The Vineyard

42

65

50

35

D, E

33

GN38b

China Bible Seminary

41

60 (55 for exam)

50

35

D, E

29

GN39

62D Wai Tsai Tsuen

49

65

50

35

D, E

34

GN40

House 1, Green Crest

50

65

50

35

D, E

42

GN41

House A73 Maple Gardens

56

65

50

35

D

39

GN42

House A78 Maple Gardens

47

65

50

35

D, E

38

GN43

Area Zoned as R(A)

34

65

50

35

D, E, N

31

GN44

House 5 Phase A Royal Palms

32

65

50

35

D, E, N

51

GN45

Village house in Mai Po

39

65

50

35

D, E

32

 

Notes:

(1) Bold and underlined figure indicates the predicted level exceed the daytime noise criterion of EIAO-TM.

(2)  D = All days during daytime (0700 – 1900 hours) except general holidays (including Sundays), E = All days during evening period (1900 – 2300 hours), and general holidays (including Sundays) during the daytime and evening, N = All days during night-time period (2300 – 0700 hours).

(3) Ground-borne noise monitoring would be required to monitor the ground-borne noise impact induced by the TBM operation.

(4) The calculated distance is the minimum distance from the centre line of the nearest tunnel to the nearest part of the structure, including piles.  It is mostly a slant distance, the exception being when the nearest point of the piles is at the same level as the tunnel (in which case the distance is a horizontal distance).

(5) Evening and night-time operation of TBM presented in the table is for indication of acceptable operating time only.  TBM operation during restricted hours is subject to approval of CNP application. 

 

6.56            According to the predicted ground-borne noise levels, as shown in Table 6.10, four NSRs would be subject to ground-borne noise levels exceeding the daytime noise limit of 65dB(A), due to TBM operation.  The levels, however, are predicted based on a conservative assumption of good coupling between TBM operating in rock condition and building foundation (i.e. BCF is zero and the ground between has no discontinuities) and a safety factor. In practice, the safety factor may not be necessary and the good coupling may not occur at all locations.  Lower levels may result at many locations, and the predicted levels may be taken as the upper end of the likely range to be expected. 

6.57            Monitoring at the time of TBM operation will therefore be required to confirm and monitor the ground-borne noise levels.  Where it is possible that the 65dB(A) limit will be exceeded, reducing the rotational speed and scheduling of the works in consultation with affected parties will be the available way of alleviating the impact.  This action is required over the chainages shown in Table 6.11 at which exceedance of the daytime noise limit would be predicted.

Table 6.11        Locations at which TBM Ground-borne Noise Levels would Exceed the Daytime Noise Limit

NSR

Chainages where Levels Predicted to Exceed Daytime Criteria

Track

From

To

GN3

Up

140+330

140+340

GN5

Up

140+840

140+860

GN8

Down

139+260

139+300

Up

139+310

139+320

GN31

Up

123+480

123+500

 

6.58            Based on the daily progress of the TBM at LMC of 8-11m per day, it is likely that any exceedance of the criteria would extend for about two or three days at the affected NSRs. 

PME Induced Ground-borne Noise

6.59            Table 6.12 shows a summary of the PME-induced ground-borne noise levels during the construction of adits.  Sample calculations are given in Appendix 6.7

Table 6.12      Predicted PME Ground-borne Noise Levels during Construction

NSR

Construction Site

Operation

Leq(30min), dB(A)

Daytime Criteria,  dB(A)

GN12a

Nam Cheong Shaft

Hydraulic breaker

44

60

GN14a

Drill & Blast Tunnel

Drill Rig

62

65

GN14b

Mei Lai Road Adit

Hydraulic breaker

<20

65

GN14c

Mai Lai Road Adit

Hydraulic breaker

59

60

GN15

Drill & Blast Tunnel

Drill Rig

<20

65

GN16

Drill & Blast Tunnel

Drill Rig

31

65

GN17

Drill & Blast Tunnel

Drill Rig

25

65

GN18

Drill & Blast Tunnel

Drill Rig

41

65

GN18a

Kwai Chung Adit

Hydraulic breaker

21

65

GN19

Drill & Blast Tunnel

Drill Rig

56

65

GN20

Drill & Blast Tunnel

Drill Rig

58

65

GN21

Drill & Blast Tunnel

Drill Rig

<20

65

GN21a

Shek Yam Adit

Hydraulic breaker

<20

65

GN22

Drill & Blast Tunnel

Drill Rig

<20

65

GN22a

Shek Yam Adit

Hydraulic breaker

<20

65

GN23

Drill & Blast Tunnel

Drill Rig

<20

65

GN24

Drill & Blast Tunnel

Drill Rig

56

65

GN25

Drill & Blast Tunnel

Drill Rig

46

60

GN25a

Pat Heung Adit

Drill Rig

<20

65

GN30

ERS Structure

Pile Rig

<20

65

GN35

Drill & Blast Tunnel

Drill Rig

<20

65

6.60            Predicted results indicate that all PME induced ground-borne noise levels comply with the daytime criteria.

Cumulative Construction Ground-borne Noise Impact

6.61            It is anticipated that there would be no cumulative construction ground-borne noise impact at GBNSR 14a due to TBM and PME operation, given that TBM and PME would not be operating simultaneously due to safety reason.  For GBNSR 12a, the cumulative ground-borne noise level is 44dB(A), which complies with EIAO-TM, and therefore no adverse cumulative ground-borne noise impact is anticipated.

Operation Phase

6.62            Operational ground-borne noise levels were calculated by incorporating the algorithms discussed in a 3-D model, MoleRat, which is developed by Wilkinson Murray Limited.  Leq(30min) for day and night, Leq(24hr) and Lmax levels were calculated at most affected floor levels and the noise impact has been quantified by indicating the total number of dwellings or other sensitive elements exposed to levels exceeding the criteria.

Operational Information

6.63            Two train types are expected to operate for the Project; a long haul train of length 427m and a short haul train of length 214m.

6.64            As a worst case, the number of through train movements has been assumed to be the operational capacity of the system at daytime and evening (0700 – 2300 hours) and an equivalent hourly number for the two operational hours at night-time (2300 – 2400 and 0600 – 0700 hours), as shown in Table 6.13.  In addition to this, there will be shunting movements between SSS and WKT during the operational hours, and these need to be added to allow calculation of total ground-borne noise levels.  However, since no speed profiles are available for shunting trains, a conservative approach has been adopted whereby the shunting trains are assumed to travel the full length of the project.

Table 6.13        Assumed Train Movements

Track

Train Type

Movements per Hour

Long Haul Train(1)

Short Haul Train(1)

Total

Daytime and evening

Night-time

Daytime and evening

Night-time

24 Hour(2)

Northbound

Short

13

6

0

3

6

Long

2

0

2

1

2

Total

15

6

2

4

8

Southbound

Short

12

5

1

0

6

Long

3

0

3

0

2

Total

15

5

4

0

8

Notes:

(1) Long haul and short haul trains will be operated during the period of 0600 – 2400 hours only.

(2) Train frequency for 24 hours was calculated based on the average hour of total 24-hour train movements.

 

6.65            The worst hours for through trains and shunting trains at night are not the same.  The worst hour for through trains is 0600 - 0700 hours and for shunting trains is 2300 – 2400 hours.  Nevertheless, the worst hours were added in a conservative approach.  Where 30 minute train movements were required, these were derived by dividing the hourly movements by two.

6.66            The speed profiles adopted in the present assessment are presented in Appendix 6.8. 

6.67            Turnouts of the inclined type have been assumed at the locations in Table 6.14.

Table 6.14            Locations of Turnouts

Up

Down

117+320

117+310

117+510

117+500

121+895

121+635

123+510

123+545

124+375

124+310

124+925

124+910

126+195

126+060

126+215

126+320

131+945

131+810

131+965

132+075

137+830

137+800

137+980

137+950

140+735

140+775

140+790

140+830

140+845

140+895

140+910

140+940

140+955

140+995

141+010

141+055

141+055

141+115

141+130

141+140

141+180

141+180

 

Predicted Ground-borne Noise Levels

6.68            The predicted ground-borne noise levels as a result of Project operation at the lowest occupied floor of GBNSRs, together with the distances used in the calculation are shown in Table 6.15.  The calculation of the noise levels assumes the following conditions:

·         For the case where the tunnel will be in rock and the NSR is piled down to rock, the vibration path has been assumed to be across the rock and up the piles into the building

·         For the cases where the tunnel will be in soft ground, the NSR is not on piles or the NSR is on piles not down to rock, the vibration path has been assumed to be through the ground along a slant path to the nearest part of the NSR or piles.

·         Where piling details are not known and the tunnel will be in rock, it has been assumed that the piles are down to rock (worst case assumption).

Table 6.15        Predicted Ground-borne Railway Noise Levels

GBNSR No.

Location

Predicted Ground-borne Noise Level, dB(A)

Criterion, dB(A)

Down Track Calculated
Distance (m)

Up
Track Calculated
Distance (m)

Leq, 30min (day)

Leq, 30min (night)

Leq (24hr)

Lmax

Leq, 30min (day)

Leq, 30min (night)

GN1

Future Development at West Kowloon Cultural District

25

20

22

36

N.A.

N.A.

20

20

GN2

Future Development at West Kowloon Cultural District

<15

<15

<15

21

N.A.

N.A.

40

40

GN2a

WKT Topside Development

38

34

36

48

55

45

27

27

GN2b

WKT Topside Development

39

34

37

48

55

45

27

27

GN2c

WKT Topside Development

41

36

39

50

55

45

27

27

GN2d

Block 6 Phase 1 Sorrento

<15

<15

<15

18

55

45

52

42

GN2e

Man King Building

<15

<15

<15

18

55

45

59

67

GN3

Yaumati Catholic Primary School (Hoi Wang Road)

28

23

26

40

55

45

15

5

GN4

Block 9, Charming Garden

26

21

24

38

55

45

5

15

GN5

Tower 5 Phase 1 Park Avenue

24

19

22

37

55

45

22

6

GN6

Hing Wong Mansion

<15

<15

<15

25

55

45

37

37

GN7

Tai Fung Building (Block F) Cosmopolitan Estates

19

<15

16

31

55

45

36

36

GN8

Chung Yew Building

22

17

20

35

55

45

19

19

GN9

West Kowloon Disciplined Services Quarters Block 1

17

<15

15

32

55

45

19

36

GN10

Fu Yun House, Fu Cheong Estate

23

18

21

39

55

45

15

30

GN11

Planned Nam Cheong Station Properties Development

29

24

27

43

55

45

7

9

GN11a(2)

Planned Residential Development in Site 6

41

36

39

56

55

45

26

10

GN12

SKH St. Mary's Church Mok Hing Yiu College

20

15

18

35

55

45

36

21

GN12a

Tack Ching Girls' Secondary School

<15

<15

<15

24

55

45

40

56

GN13

Tower 6 Aqua Marine

<15

<15

<15

21

55

45

21

37

GN14

HKIVE Haking Wong Waterfront Annex

<15

<15

<15

29

55

45

35

41

GN14a

Lai Chi Kok Reception Centre

26

21

24

39

55

45

44

43

GN14b

Ward A, Lai Chi Kok Hospital

<15

<15

<15

25

55

45

101

90

GN15

40A Cheung Hang Village

<15

<15

<15

<15

50

40

235

235

GN16

Tower 6 Regency Park

<15

<15

<15

<15

55

45

250

248

GN17

Block 21 Wonderland Villas

<15

<15

<15

<15

55

45

275

275

GN18

Block 2 Greenknoll Court

<15

<15

<15

27

55

45

89

89

GN18b

Kwai Ying Building

25

20

23

38

55

45

57

61

GN19

Tower B Kwai Sing Centre

29

24

27

43

55

45

41

42

GN19a

Ming Tak Building

28

23

26

42

55

45

45

48

GN20

Block B Hutchison Estate

30

25

27

43

55

45

34

36

GN21

184 Yau Ma Hom Resite Village

15

<15

<15

28

55

45

73

73

GN22

18 Da Chuen Ping Village

<15

<15

<15

28

50

40

87

87

GN23

35 Sheung Kwai Chung Village

<15

<15

<15

<15

50

40

98

98

GN24

Sau Shan House, Cheung Shan Estate

<15

<15

<15

<15

55

45

125

124

GN25

Tsuen Wan Lutheran School

<15

<15

<15

<15

55

45

124

124

GN26

426A Tsang Uk Tsuen

<15

<15

<15

29

50

40

26

23

GN27

431A Tsang Uk Tsuen

<15

<15

<15

26

50

40

27

26

GN28

510B Nam Hing Lei

<15

<15

<15

25

50

40

26

29

GN29

630 Sheung Tsuen

17

<15

15

33

50

40

28

42

GN30

51A Leung Uk Tsuen

<15

<15

<15

<15

55

45

113

132

GN30a

Village Zone West Boundary, Leung Uk Tsuen

<15

<15

<15

<15

55

45

61

79

GN30b

Village house in Leung Uk Tsuen

<15

<15

<15

21

55

45

46

64

GN31

DD110 LOT 482, Wang Toi Shan

30

25

28

45

55

45

35

19

GN33

348 Tsat Sing Kong

21

16

19

34

50

40

29

27

GN34

349 Tsat Sing Kong

21

15

18

33

50

40

27

34

GN35

374 Chuk Yau Road

<15

<15

<15

27

50

40

46

52

GN36

DD104 LOT 1786, Chuk Yau Road

20

15

18

34

50

40

31

33

GN37

DD104 LOT 1396, Yau Tam Mei Tsuen, Chuk Yau Road

21

16

19

35

50

40

30

29

GN37a

Chun Shin Road, Yau Tam Mei Tsuen

<15

<15

<15

18

50

40

67

53

GN38

45 Wai Tsai Tsuen

20

15

18

34

50

40

33

33

GN38a

Petrus Avenue House 21 Phase 1 The Vineyard

<15

<15

<15

30

50

40

33

41

GN38b

China Bible Seminary

17

<15

15

31

50

40

33

29

GN39

62D Wai Tsai Tsuen

15

<15

<15

29

50

40

34

34

GN40

House 1, Green Crest

<15

<15

<15

24

50

40

53

42

GN41

House A73 Maple Gardens

<15

<15

<15

28

50

40

42

39

GN42

House A78 Maple Gardens

<15

<15

<15

25

50

40

38

40

GN43

Area Zoned as R(A)

20

15

18

34

50

40

31

32

GN44

House 5 Phase A Royal Palms

<15

<15

<15

15

50

40

65

51

GN45

Village house in Mai Po

19

<15

17

34

50

40

36

32

Note:

(1)   Locations GN2a to GN2c are the locations of future WKT topside developments which are directly connected to the WKT by the station structure.  The distances shown are therefore distances through the structure and not through the ground.

 (2)  Layout and foundation design of the future development at Site 6 were not available at the time of reporting.  The potential ground-borne noise impact at the planned NSR was predicted by assuming that the worst affected noise sensitive use would be located at a minimum distance of 3m away from the outer surface of the tunnel box (10m from track), which is the boundary of the non-building/structural clearance zone.  On-going liaison with Housing Department will be carried out in detailed design stage such that the future residential development at Site 6 would not be adversely affected by railway ground-borne noise.  The Project Proponent will continue to liaise with the owner of Site 6, i.e. Hong Kong Housing Authority to resolve any interface issues between these two development projects.  Based on the outcome of the liaison process, the trackform design and mitigation measures proposal will be reviewed if needed.

 

6.69            All of the predicted levels at existing residential receivers and at possible CDA developments over WKT are well below the criteria, generally as a result of deep underground alignment.  Appendix 6.9 shows the sample calculation of selected GBNSRs.

6.70            Within the proposed West Kowloon Cultural District (WKCD) (locations GN1 and GN2), noise levels have been predicted at 20m and 40m from the nearest track to give an indication of the implications on any future development.  The feasibility of providing upgraded trackform at WKT to minimise the potential ground-borne noise impact at WKCD has been investigated.

6.71            It is unlikely that FDL values will be higher than assumed for this analysis due to deterioration of rails and rolling stock, with the implementation of good maintenance regimes such that the Project will operate properly.   

Recommended Mitigation Measures

Construction Phase

6.72            The predicted construction ground-borne noise levels will comply with the stipulated noise criteria at all NSRs, except four NSRs in proximity to TBM operation.  Based on the daily progress of the TBM at LMC of 8-11m per day, it is likely that any exceedance of the criteria will be for about only two or three days.  The operation of TBM during restricted hours will be subject to the control of CNP under NCO.

6.73            Monitoring at the time of TBM operation is recommended to confirm and monitor the ground-borne noise levels.  An EM&A programme, together with careful scheduling of the works and close liaison with affected parties which would have exceedance of the noise criterion, is recommended to minimise the impact from the operation of TBM. 

Operation Phase

6.74            With the predicted operation ground-borne noise levels complying with the stipulated noise criteria at existing NSRs, mitigation measures are not required during operation phase.  Concerning the potential ground-borne noise impact due to the uncertainty of the FDL and LSR values, installation of low noise trackform at the concerned areas has been proposed and would be implemented to further minimise the ground-borne noise levels.  Low noise trackform suitable for high speed railway includes isolated slab trackform (IST) and Vanguard.  The insertion loss values for this trackform are shown in Appendix 6.10.  The locations along the alignment where the predicted noise levels at the GBNSRs are comparatively high among other GBNSRs have been identified and the approximate chainages as presented in Table 6.16 will be provided with low noise trackform, where practicable.   

6.75            In addition, to minimise the noise impact to the future WKCD, low noise trackform will also be provided at WKT.  With the provision of low noise trackform at WKT, the Lmax levels at areas within the WKCD site and outside the WKT boundary were predicted to be in general lower than 25dB(A). 

6.76            The noise levels at the representative GBNSRs would be reduced to those shown in Table 6.17 with the provision of low noise trackform.  Appendix 6.11 shows the sample calculation of selected GBNSRs with the provision of IST.

Table 6.16        Approximate Chainages where Low Noise Trackform to be provided

Southbound

From

To

123+040

123+640

133+160

133+660

137+600

138+350

139+100

139+600

140+900

141+600

Northbound

From

To

123+050

123+650

133+170

133+670

137+620

138+370

139+120

139+620

140+900

141+600

 

Table 6.17   Predicted Ground-borne Noise Levels with the Provision of IST

GBNSR No.

Location

Predicted Ground-borne Noise Level, dB(A)

Criterion, dB(A)

Down Track Calculated
Distance (m)

Up
Track Calculated
Distance (m)

Leq, 30min (day)

Leq, 30min (night)

Leq (24hr)

Lmax

Leq, 30min (day)

Leq, 30min (night)

GN1

Future Development at West Kowloon Cultural District

<15

<15

<15

23

N.A.

N.A.

20

20

GN2

Future Development at West Kowloon Cultural District

<15

<15

<15

<15

N.A.

N.A.

40

40

GN2a

WKT Topside Development(1)

27

23

25

34

55

45

27

27

GN2b

WKT Topside Development(1)

27

23

25

32

55

45

27

27

GN2c

WKT Topside Development(1)

29

24

27

35

55

45

27

27

GN2d

Block 6 Phase 1 Sorrento

<15

<15

<15

<15

55

45

52

42

GN2e

Man King Building

<15

<15

<15

17

55

45

59

67

GN3

Yaumati Catholic Primary School (Hoi Wang Road)

28

23

26

40

55

45

15

5

GN4

Block 9, Charming Garden

26

21

24

38

55

45

5

15

GN5

Tower 5 Phase 1 Park Avenue

24

19

22

37

55

45

22

6

GN6

Hing Wong Mansion

<15

<15

<15

<15

55

45

37

37

GN7

Tai Fung Building (Block F) Cosmopolitan Estates

<15

<15

<15

17

55

45

36

36

GN8

Chung Yew Building

<15

<15

<15

24

55

45

19

19

GN9

West Kowloon Disciplined Services Quarters Block 1

17

<15

<15

32

55

45

19

36

GN10

Fu Yun House, Fu Cheong Estate

23

18

21

39

55

45

15

30

GN11

Planned Nam Cheong Station Properties Development

19

<15

17

34

55

45

7

9

GN11a(2)

Planned Residential Development in Site 6

29

25

27

44

55

45

26

10

GN12

SKH St. Mary's Church Mok Hing Yiu College

19

<15

17

34

55

45

36

21

GN12a

Tack Ching Girls' Secondary School

<15

<15

<15

22

55

45

40

56

GN13

Tower 6 Aqua Marine

<15

<15

<15

21

55

45

21

37

GN14

HKIVE Haking Wong Waterfront Annex

<15

<15

<15

29

55

45

35

41

GN14a

Lai Chi Kok Reception Centre

26

21

24

39

55

45

44

43

GN14b

Ward A, Lai Chi Kok Hospital

<15

<15

<15

25

55

45

101

90

GN15

40A Cheung Hang Village

<15

<15

<15

<15

50

40

235

235

GN16

Tower 6 Regency Park

<15

<15

<15

<15

55

45

250

248

GN17

Block 21 Wonderland Villas

<15

<15

<15

<15

55

45

275

275

GN18

Block 2 Greenknoll Court

<15

<15

<15

27

55

45

89

89

GN18b

Kwai Ying Building

23

18

21

37

55

45

57

61

GN19

Tower B Kwai Sing Centre

21

16

19

33

55

45

41

42

GN19a

Ming Tak Building

21

16

19

30

55

45

45

48

GN20

Block B Hutchison Estate

23

18

20

35

55

45

34

36

GN21

184 Yau Ma Hom Resite Village

15

<15

<15

28

55

45

73

73

GN22

18 Da Chuen Ping Village

<15

<15

<15

28

50

40

87

87

GN23

35 Sheung Kwai Chung Village

<15

<15

<15

<15

50

40

98

98

GN24

Sau Shan House, Cheung Shan Estate

<15

<15

<15

<15

55

45

125

124

GN25

Tsuen Wan Lutheran School

<15

<15

<15

<15

55

45

124

124

GN26

426A Tsang Uk Tsuen

<15

<15

<15

29

50

40

26

23

GN27

431A Tsang Uk Tsuen

<15

<15

<15

26

50

40

27

26

GN28

510B Nam Hing Lei

<15

<15

<15

25

50

40

26

29

GN29

630 Sheung Tsuen

17

<15

15

33

50

40

28

42

GN30

51A Leung Uk Tsuen

<15

<15

<15

<15

55

45

113

132

GN30a

Village Zone West Boundary, Leung Uk Tsuen

<15

<15

<15

<15

55

45

61

79

GN30b

Village house in Leung Uk Tsuen

<15

<15

<15

21

55

45

46

64

GN31

DD110 LOT 482, Wang Toi Shan

18

<15

16

32

55

45

35

19

GN33

348 Tsat Sing Kong

20

15

18

34

50

40

29

27

GN34

349 Tsat Sing Kong

20

15

18

33

50

40

27

34

GN35

374 Chuk Yau Road

<15

<15

<15

27

50

40

46

52

GN36

DD104 LOT 1786, Chuk Yau Road

20

15

18

34

50

40

31

33

GN37

DD104 LOT 1396, Yau Tam Mei Tsuen, Chuk Yau Road

21

16

19

35

50

40

30

29

GN37a

Chun Shin Road, Yau Tam Mei Tsuen

<15

<15

<15

18

50

40

67

53

GN38

45 Wai Tsai Tsuen

20

15

18

34

50

40

33

33

GN38a

Petrus Avenue House 21 Phase 1 The Vineyard

<15

<15

<15

30

50

40

33

41

GN38b

China Bible Seminary

17

<15

15

31

50

40

33

29

GN39

62D Wai Tsai Tsuen

15

<15

<15

29

50

40

34

34

GN40

House 1, Green Crest

<15

<15

<15

24

50

40

53

42

GN41

House A73 Maple Gardens

<15

<15

<15

28

50

40

42

39

GN42

House A78 Maple Gardens

<15

<15

<15

25

50

40

38

40

GN43

Area Zoned as R(A)

20

15

18

34

50

40

31

32

GN44

House 5 Phase A Royal Palms

<15

<15

<15

15

50

40

65

51

GN45

Village house in Mai Po

19

<15

17

34

50

40

36

32

Note:

(1)   Locations GN2a to GN2c are the locations of future WKT topside developments which are directly connected to the WKT by the station structure.  The distances shown are therefore distances through the structure and not through the ground.

(2)   Layout and foundation design of the future development at Site 6 were not available at the time of reporting.  The potential ground-borne noise impact at the planned NSR was predicted by assuming that the worst affected noise sensitive use would be located at a minimum distance of 3m away from the outer surface of the tunnel box (10m from track), which is the boundary of the non-building/structural clearance zone.  The Project Proponent will continue to liaise with the owner of Site 6, i.e. Hong Kong Housing Authority to resolve any interface issues between these two development projects.  Based on the outcome of the liaison process, the trackform design and mitigation measures proposal will be reviewed if needed.

Cumulative Effect from Other Rail Lines

6.77            The Project will run close to other existing rail lines and the cumulative effect from other rail lines has been reviewed.  Locations where other rail lines are relatively close are as follows:

·         The WKT will be located in the vicinity of the KSL Austin Station

·         The XRL will be parallel to KSL and reasonably close just north of WKT, and also parallel to, but further away, Tung Chung Line (TCL) and Airport Express Line (AEL)

·         The XRL will pass close to the Tung Chung Line (TCL) Nam Cheong station

·         The XRL will pass under the Tsuen Wan Line (TWL) at Lai Chi Kok

6.78            Any cumulative effect from KSL would relate to West Kowloon Cultural District.  Whilst predicted noise levels Lmax at GN1 and GN2, which are located at approx. 31m and 47m from the tracks at WKT, are less than 23dB(A), KSL would be at least 150m from any potential cultural development.  At this distance low ground-borne noise levels are expected.  As such cumulative impact from the Project and KSL is not anticipated. 

6.79            Just north of WKT where the Project will be parallel to KSL, TCL and AEL, there are no GBNSRs located in proximity to these rail lines.  Any cumulative effect is therefore considered irrelevant.  At the point where XRL diverges from the other lines, GBNSR GN3 is 30m from the nearest XRL track and approximately 135m from KSL and further from the other lines.  Given that the level predicted for GN3 is 28dB(A) Leq,day, it is unlikely that other rail lines would increase the Leq levels at GBNSRs.

6.80            The nearest GBNSR near TCL Nam Cheong station and the project alignment is GN11a  With the predicted ground-borne noise level of up to 25dB(A) Leq,night at GN11a, the cumulative noise levels are therefore unlikely to be over the criteria, in particular TCL trains would slow down and stop at Nam Cheong station.

6.81            In Lai Chi Kok, the tracks will pass close to the TWL tracks.  At the intersection, the nearest GBNSR is GN14a at a distance from XRL of 39m.  However, this GBNSR is 100m from TWL and it is anticipated that the Leq levels from TWL would be low, especially considering the fact that the intersection is near Lai Chi Kok station and MTR trains would be at low speed.  Therefore, the operation of TWL would therefore not add significantly to the ground-borne noise level of less than 21dB(A) Leq,night at GN14a, as predicted from XRL to the extent of making the cumulative levels up towards the criteria.

Environmental Monitoring and Audit

Construction Phase

6.82            The predicted ground-borne noise levels comply with the stipulated daytime noise criteria, except at a few sensitive receivers, where TBM operation would induce noise levels exceeding the noise criteria of 65 dB(A).  Monitoring at the time of TBM operation is recommended to confirm and monitor the ground-borne noise levels. 

6.83            Prior to the final design of the trackform and the extent of each type of trackform, and after the proposed train in operation outside Hong Kong, tests of the FDL of the train will be carried out to update the ground-borne noise prediction and the recommendation on mitigation measures as necessary.

6.84            The vibration borehole testing will be carried out at two carefully selected locations along the proposed tunnel alignment prior to the commencement of construction works to determine the LSR values under certain geological conditions.  This will also allow updating of the ground-borne noise predictions and the recommendation on mitigation measures as necessary.

6.85            The construction stage of the Project could also be used to improve knowledge of the ground vibration conditions.  During use of the TBM, the vibration levels in surrounding buildings will be measured.  By also measuring the FDL of the TBM, the LSR values for some additional sections of the tunnel will be determined.  This may allow further update of the ground-borne noise level predictions and, if necessary, a refinement of the trackform design.

6.86            An Environmental Monitoring and Audit (EM&A) programme is recommended to be developed with details of the EM&A requirements are provided in a stand-alone EM&A Manual.

Operation Phase

6.87            Prior to the operation phase of the Project, a commissioning test should be conducted to ensure compliance of the operational ground-borne noise levels with the EIAO-TM noise criteria.  Details of the test requirements are provided in a stand-alone EM&A Manual.

Conclusion

Construction Phase

6.88            Construction ground-borne noise assessment has been conducted to assess the feasibility of TBM tunnelling construction.  Prediction results indicated the TBM and PME induced ground-borne levels at GBNSRs comply with the EIAO noise limit, except exceedance predicted at four sensitive receivers due to TBM operation.  It is however anticipated that the period of exceedance would be about only two or three days, basing on the TBM daily progress in LMC.  An EM&A programme and scheduling of works, is recommended to control and monitor the construction ground-borne level. It is considered that TBM tunnel construction method would be feasible for the tunnel construction but the operation of TBM during restricted hours should be governed by the control of CNP under NCO.   

Operation Phase

6.89            Ground-borne noise levels have been predicted based on the maximum operation capacity of railway system.  Assessment results indicated that the predicted ground-borne noise levels at the GBNSRs generally comply with the stipulated EIAO-TM noise criteria, and thus no special trackform will be required to meet the criteria.  Low noise trackform will however be installed at the selected alignment sections to account for the uncertainty of the FDL and LSR values.   

6.90            Low noise trackform will also be installed to minimise the impact on future development at WKCD.  The Lmax levels at areas within the WKCD site and outside the WKT boundary will be reduced to levels lower than 25dB(A) in general with the provision of low noise trackform.   

6.91            With the predicted low ground-borne noise levels at the GBNSRs, it is anticipated that there would be no cumulative effect from other rail lines, including KSL, TCL, AEL and TWL.

 



[1] Transit Noise and Vibration Impact Assessment. Report No. FTA-VA-90-1003-06

[2] Register No.: AEIAR-083/2005, KSL GSA 5100 Environmental Impact Assessment & Associated Services - Environmental Impact Assessment Report

[3] P. M. Nelson. Transportation Noise Reference Book. 1987.

[4] Final Report of High-Speed Ground Transportation Noise and Vibration Impact Assessment, HMMH Report No. 293630-4