6.1
Potential ground-borne noise impacts likely arising during construction and
operation phases of the Project have been evaluated and mitigation measures, if
required, are recommended.
Environmental
Legislation, Standards and Guidelines
Construction Phase
6.2
Ground-borne construction noise is under the control of the Noise Control Ordinance (NCO), the Environmental Impact Assessment Ordinance
(EIAO), and their subsidiary Technical Memorandum. With reference to the Technical Memorandum for the Assessment of
Noise from Places Other Than Domestic Premises, Public Places or Construction
Sites (IND-TM) under the NCO, the criteria for noise transmitted primarily
through the structural elements of the building or buildings should be 10dB(A)
less than the relevant acceptable noise level (ANL).
6.3
Between 1900 and 0700 hours and all day on Sundays and
public holidays, activities involving the use of powered mechanical equipment
(PME) for the purpose of carrying out construction work is prohibited unless a
Construction Noise Permit (CNP) has been obtained. A CNP may be granted in cases where the noise
can be contained within the Acceptable Noise Level (ANL) at the NSRs. ANLs are assigned depending upon the Area Sensitivity
Ratings (ASRs). The criteria applied for
ground-borne noise assessment are summarised in Table 6.1 below.
Table 6.1 Ground-borne Construction Noise Criteria
|
Ground-borne
Construction Noise Criteria, dB(A) |
||||||
GBNSR Description |
Daytime (0700-1900 hrs) |
Daytime during general
holidays and Sundays and all days during Evening |
Night-time |
||||
A |
B |
C |
A |
B |
C |
||
Education institutions |
60/55 [a] |
50 |
55 |
60 |
[b] |
||
Domestic premises,
hotels |
65 |
50 |
55 |
60 |
35 |
40 |
45 |
Churches/temples, libraries, courts, performing arts,
clinics |
60 |
50 |
55 |
60 |
[b] |
Notes:
[a] A
5dB(A) reduction to the ground-borne noise criteria is recommended for school
during examination period.
[b] No sensitive use during this period.
6.4
For construction activities involving the use of TBM and PME
during the restricted hours (i.e. 1900-0700 hours), it is necessary to apply
for a Construction Noise Permit (CNP) under NCO. However, there is no guarantee that a CNP
will be issued for the project construction.
The Noise Control Authority will consider a well-justified CNP
application, once filed, for construction works within restricted hours as
guided by the relevant Technical Memoranda issued under the NCO. The Noise
Control Authority will take into account contemporary conditions/ situations of
adjoining land uses and any previous complaints against construction activities
at the site before deciding whether to grant a CNP. Nothing in the EIA Report should bind the
Noise Control Authority in making its decision.
If a CNP is to be issued, the Noise Control Authority would include in
the permit any condition it thinks fit.
Failure to comply with any such conditions will lead to cancellation of
the CNP and prosecution under the NCO.
6.5
With reference to the IND-TM under the NCO, the criteria for
noise transmitted primarily through the structural elements of the building or
buildings should be 10dB(A) less than the relevant acceptable noise level
(ANL). The same criteria are applied to
all residential buildings, schools, clinics, hospitals, temples and churches.
6.6
The operational ground-borne railway noise criteria for the
representative ground-borne noise sensitive receivers (GBNSRs) along the
Project alignment are presented in Table
6.2 below.
Table 6.2 Operational Ground-borne Railway Noise
Criteria
|
Ground-borne Railway Noise Criteria, dB(A) |
|||||
GBNSR Description |
Day and Evening (0900 to 2300 hrs) |
Night-time Period |
||||
A |
B |
C |
A |
B |
C |
|
Churches/temples, schools,
medical clinics, libraries, courts and performing arts |
50 |
55 |
60 |
[a] |
||
Domestic premises, hotels and hospitals |
50 |
55 |
60 |
40 |
45 |
50 |
Note:
[a] No
sensitive use during this period.
Identification of Ground-borne Noise Sensitive Receivers
6.7
In order to evaluate the
construction and operational noise impacts likely to arise from the Project,
representative GBNSRs (both existing and planned NSRs) within 300m of the
Project boundary and at the most critical locations were
selected, according to the criteria set out in the Annex 13 of
EIAO-TM, observations from site visits and review of relevant
land use plans including the Outline Zoning
Plan (OZP) as presented in Figure Nos. NOL/ERL/300/C/XRL/ENS/M54/050 to 069,
information available in the Statutory Planning Portal of the Town Planning
Board (TPB) and land status plans published by Lands Department.
Construction Phase
6.8
Potential ground-borne noise impacts on GBNSRs during the
construction phase would arise mainly from hydraulic
breakers, drill rigs, pipe pile rigs and tunnel boring machine (TBM).
6.9
Under the assumption of
worst-case scenario, two sets of representative GBNSRs were identified for the
assessment of noise impact induced by (1) TBM operation for tunnelling; and (2)
PME (i.e. hydraulic breakers, drill rigs and pile rigs) operation during the
construction of adits. Representative
GBNSRs identified along the alignment were designated for the assessment of
TBM-induced ground-borne noise impact.
As for the assessment of noise impact due to the use of PME for rock
breaking / drilling, including hydraulic breakers, drill rigs and pipe pile
rigs for the construction of adits, representative GBNSRs located in the
closest proximity to the concerned areas were also identified. The identified GBNSRs are presented in Tables 6.3 and 6.4 and shown in NOL/ERL/300C/XRL/ENS/M53/002
to 025.
Table 6.3 Identified GBNSRs
for
Assessment of Ground-borne Construction Noise Impacts due to TBM
operation
GBNSR
No. |
Location |
Uses |
Existing
/ Planned NSR |
No. of
Storeys |
GN3 |
|
School |
Existing |
8 |
GN4 |
Block 9, Charming Garden |
Residential |
Existing |
23 |
GN5 |
Tower 5 Phase |
Residential |
Existing |
48 |
GN6 |
|
Residential |
Existing |
16 |
GN7 |
|
Residential |
Existing |
14 |
GN8 |
|
Residential |
Existing |
15 |
GN9 |
|
Institutional |
Existing |
38 |
GN10 |
Fu Yun House, Fu Cheong
Estate |
Residential |
Existing |
8 |
GN12 |
|
School |
Existing |
9 |
GN12a |
Tack Ching Girls' Secondary
School |
School |
Existing |
8 |
GN13 |
Tower 6 Aqua Marine |
Residential |
Existing |
46 |
GN14 |
HKIVE Haking Wong
Waterfront Annex |
School |
Existing |
2 |
GN14a |
Lai
Chi Kok Reception Centre |
Institutional |
Existing |
8 |
GN26 |
426A Tsang |
Residential |
Existing |
3 |
GN27 |
431A Tsang |
Residential |
Existing |
3 |
GN28 |
510B |
Residential |
Existing |
3 |
GN29 |
630 Sheung Tsuen |
Residential |
Existing |
2 |
GN31 |
DD110 |
Residential |
Existing |
1 |
GN33 |
348 Tsat Sing Kong |
Residential |
Existing |
1 |
GN34 |
349 Tsat Sing Kong |
Residential |
Existing |
2 |
GN35 |
|
Residential |
Existing |
1 |
GN36 |
DD104 |
Residential |
Existing |
2 |
GN37 |
DD104 |
Residential |
Existing |
1 |
GN37a |
|
Residential |
Existing |
2 |
GN38 |
45 Wai Tsai Tsuen |
Residential |
Existing |
2 |
GN38a |
|
Residential |
Existing |
3 |
GN38b |
|
School |
Existing |
3 |
GN39 |
Residential |
Existing |
3 |
|
GN40 |
House 1, Green Crest |
Residential |
Existing |
3 |
GN41 |
House A73 |
Residential |
Existing |
3 |
GN42 |
House A78 |
Residential |
Existing |
3 |
GN43 |
Planned Development |
Residential |
Planned |
N/A |
GN44 |
House 5 Phase A Royal
Palms |
Residential |
Existing |
3 |
Village house in Mai Po |
Residential |
Existing |
1 |
Table 6.4 Identified GBNSRs
for Assessment of Ground-borne Construction Noise Impacts due to the
Construction of Adits
GBNSR No. |
Location |
Uses |
Existing / Planned NSR |
No. of Storeys |
GN12a |
Tack Ching Girls' Secondary School |
School |
Existing |
8 |
GN14a |
Lai Chi Kok Reception Centre |
Institutional |
Existing |
8 |
GN14b |
Ward A, Ex-Lai Chi Kok Hospital(1) |
Hostel |
Existing |
2 |
GN14c |
Po |
School |
Existing |
7 |
GN15 |
40A |
Residential |
Existing |
2 |
GN16 |
Tower 6 |
Residential |
Existing |
17 |
GN17 |
Block 21 Wonderland Villas |
Residential |
Existing |
20 |
GN18 |
Block |
Residential |
Existing |
31 |
GN18a |
Block 17 |
Residential |
Existing |
21 |
GN19 |
Tower B Kwai Sing Centre |
Residential |
Existing |
28 |
GN20 |
Block B Hutchison Estate |
Residential |
Existing |
23 |
GN21 |
184 Yau Ma Hom Resite Village |
Residential |
Existing |
3 |
GN21a |
274 Yau Ma Hom Resite Village |
Residential |
Existing |
3 |
GN22 |
18 Da Chuen |
Residential |
Existing |
3 |
GN22a |
37 Chung Kwai Chung Tsuen |
Residential |
Existing |
3 |
GN23 |
35 Sheung Kwai Chung Village |
Residential |
Existing |
4 |
GN24 |
Sau Shan House, Cheung Shan Estate |
Residential |
Existing |
25 |
GN25 |
Tsuen Wan |
School |
Existing |
7 |
GN25a |
DD 114 |
Residential |
Existing |
2 |
GN30 |
51A Leung |
Residential |
Existing |
3 |
GN35 |
|
Residential |
Existing |
1 |
Remark:
(1) The future usage of
Operation Phase
6.10
Sensitive receivers along the alignment generally include
educational institutions, performing arts and domestic premises. Domestic premises are taken into account
during both the daytime and night time periods, while performing arts and
educational institutions are considered to be noise sensitive during daytime
and evening only.
6.11
Representative operational phase GBNSRs have been identified and are listed in Table 6.5. Their locations are shown in
NOL/ERL/300C/XRL/ENS/M53/000
to 025. As a conservative approach, it is assumed
that the sensitive receivers are not affected by any IF. For the interface between WKT and
West Kowloon Cultural District (WKCD), MTR and WKCD Authority will further
liaise with each other for dealing with the details of interfacing issues and
mitigation measures.
6.12 Information necessary including the geometry of the closest point on a GBNSR relative to the alignment as well as the structure characterisation for noise prediction is shown in Table 6.5.
Table
6.5 Operation Phase Ground-borne
Railway Noise Sensitive Receivers
GBNSR No. |
Location |
Uses |
Type of Area Containing NSR |
Degree to which NSR is affected by IF(a) |
ASR |
No. of storeys |
Building Type(b) |
Basement(c) |
TCF(h) |
BCF Type(g) |
Slant Distance to nearest Track, m |
GN1 |
Future Development at |
Performing Art |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
R |
2 |
31 |
GN2 |
Future Development at |
Performing Art |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
R |
2 |
47 |
GN2a |
Comprehensive Development Area |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
R |
2 |
N.A. |
|
GN2b |
WKT Topside Development |
Comprehensive Development Area |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
R |
2 |
N.A. |
GN2c |
WKT Topside Development |
Comprehensive Development Area |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
R |
2 |
N.A. |
GN2d |
Block 6 Phase 1 |
Residential |
Urban |
Not Affected |
B |
52 |
0 |
0 |
R |
2 |
47 |
GN2e |
|
Residential |
Urban |
Not Affected |
B |
19 |
0 |
0 |
R |
2 |
62 |
GN3 |
|
School |
Urban |
Not Affected |
B |
8 |
0 |
0 |
S |
1 |
30 |
GN4 |
Block 9, Charming Garden |
Residential |
Urban |
Not Affected |
B |
23 |
0 |
0 |
S |
3 |
32 |
GN5 |
Tower 5 Phase |
Residential |
Urban |
Not Affected |
B |
48 |
0 |
0 |
R |
2 |
36 |
GN6 |
|
Residential |
Urban |
Not Affected |
B |
16 |
0 |
0 |
R |
1 |
34 |
GN7 |
|
Residential |
Urban |
Not Affected |
B |
14 |
0 |
0 |
R |
1 |
34 |
GN8 |
|
Residential |
Urban |
Not Affected |
B |
15 |
0 |
0 |
R |
1 |
34 |
GN9 |
|
Institutional |
Urban |
Not Affected |
B |
38 |
0 |
0 |
S |
3 |
40 |
GN10 |
Fu Yun House, Fu Cheong Estate |
Residential |
Urban |
Not Affected |
B |
8 |
0 |
0 |
S |
3 |
35 |
GN11 |
Planned |
Residential |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
S |
3 |
32 |
GN11a |
Planned Residential Development in Site 6 |
Residential |
Urban |
Not Affected |
B |
N.A. |
N.A. |
N.A. |
S |
3 |
N.A. |
GN12 |
|
School |
Urban |
Not Affected |
B |
9 |
0 |
0 |
S |
3 |
42 |
GN12a |
Tack Ching Girls' Secondary School |
School |
Urban |
Not Affected |
B |
8 |
0 |
0 |
S |
3 |
50 |
GN13 |
Tower 6 Aqua Marine |
Residential |
Urban |
Not Affected |
B |
46 |
0 |
0 |
S |
1 |
40 |
GN14 |
HKIVE Haking Wong Waterfront Annex |
School |
Urban |
Not Affected |
B |
2 |
2 |
0 |
S |
0 |
34 |
GN14a |
Lai Chi Kok Reception Centre |
Institutional |
Other |
Not Affected |
B |
8 |
0 |
0 |
R |
2 |
52 |
GN14b |
Ward A, |
(e) |
Other |
Not Affected |
B |
2 |
2 |
0 |
R |
0 |
90 |
GN15 |
40A |
Residential |
Low Density Residential Area |
Not Affected |
A |
2 |
2 |
0 |
R |
0 |
235 |
GN16 |
Tower 6 |
Residential |
Other |
Not Affected |
B |
17 |
0 |
0 |
R |
2 |
248 |
GN17 |
Block 21 Wonderland Villas |
Residential |
Other |
Not Affected |
B |
20 |
0 |
0 |
R |
2 |
275 |
GN18 |
Block |
Residential |
Urban |
Not Affected |
B |
31 |
0 |
0 |
R |
2 |
93 |
GN18b |
|
Residential |
Urban |
Not Affected |
B |
19 |
0 |
0 |
R |
2 |
76 |
GN19 |
Tower B Kwai Sing Centre |
Residential |
Urban |
Not Affected |
B |
28 |
0 |
0 |
R |
2 |
57 |
GN19a |
|
Residential |
Urban |
Not Affected |
B |
6 |
0 |
0 |
R |
2 |
59 |
GN20 |
Block B Hutchison Estate |
Residential |
Urban |
Not Affected |
B |
23 |
0 |
0 |
R |
2 |
53 |
GN21 |
184 Yau Ma Hom Resite Village |
Residential |
Other |
Not Affected |
B |
3 |
1 |
0 |
R |
0 |
73 |
GN22 |
18 Da Chuen |
Residential |
Rural Area |
Not Affected |
A |
3 |
1 |
0 |
R |
0 |
87 |
GN23 |
35 Sheung Kwai Chung Village |
Residential |
Rural Area |
Not Affected |
A |
4 |
1 |
0 |
R |
0 |
98 |
GN24 |
Sau Shan House, Cheung Shan Estate |
Residential |
Urban |
Not Affected |
B |
25 |
0 |
0 |
R |
2 |
124 |
GN25 |
Tsuen Wan |
School |
Urban |
Not Affected |
B |
7 |
0 |
0 |
R |
2 |
124 |
GN26 |
426A Tsang |
Residential |
Rural |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
23 |
GN27 |
431A Tsang |
Residential |
Rural |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
26 |
GN28 |
510B |
Residential |
Rural |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
26 |
GN29 |
630 Sheung Tsuen |
Residential |
Rural |
Not Affected |
A |
2 |
2 |
0 |
S |
0 |
28 |
GN30 |
51A Leung |
Residential |
Other(f) |
Not Affected |
B |
3 |
1 |
0 |
S |
0 |
113 |
GN30a |
Village Zone West Boundary, Leung |
Residential |
Other(f) |
Not Affected |
B |
3 |
1 |
0 |
S |
0 |
61 |
GN30b |
Village house in Leung Uk Tsuen |
Residential |
Other(f) |
Not Affected |
B |
3 |
1 |
0 |
S |
0 |
46 |
GN31 |
DD110 |
Residential |
Other(f) |
Not Affected |
B |
1 |
2 |
0 |
R |
0 |
19 |
GN33 |
348 Tsat Sing Kong |
Residential |
Rural Area |
Not Affected |
A |
1 |
2 |
0 |
S |
0 |
25 |
GN34 |
349 Tsat Sing Kong |
Residential |
Rural Area |
Not Affected |
A |
2 |
2 |
0 |
S |
0 |
25 |
GN35 |
|
Residential |
Rural Area |
Not Affected |
A |
1 |
2 |
0 |
S |
0 |
46 |
GN36 |
DD104 |
Residential |
Rural Area |
Not Affected |
A |
2 |
2 |
0 |
S |
0 |
31 |
GN37 |
DD104 |
Residential |
Rural Area |
Not Affected |
A |
1 |
2 |
0 |
S |
0 |
30 |
GN37a |
|
Residential |
Rural Area |
Not Affected |
A |
2 |
2 |
0 |
S |
0 |
53 |
GN38 |
45 Wai Tsai Tsuen |
Residential |
Rural Area |
Not Affected |
A |
2 |
2 |
0 |
S |
0 |
33 |
GN38a |
|
Residential |
Low Density Residential Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
34 |
GN38b |
|
School |
Rural Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
29 |
GN39 |
62D Wai Tsai Tsuen |
Residential |
Rural Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
34 |
GN40 |
House 1, Green Crest |
Residential |
Low Density Residential Area |
Not Affected |
A |
3 |
1 |
0 |
R |
0 |
42 |
GN41 |
House A73 |
Residential |
Low Density Residential Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
39 |
GN42 |
House A78 |
Residential |
Low Density Residential Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
38 |
GN43 |
Planned Development |
Residential |
Low Density Residential Area |
Not Affected |
A |
N.A. |
N.A. |
N.A. |
S |
3 |
31 |
GN44 |
House 5 Phase A Royal Palms |
Residential |
Low Density Residential Area |
Not Affected |
A |
3 |
1 |
0 |
S |
0 |
51 |
GN45 |
Village house in Mai Po |
Residential |
Rural Area |
Not Affected |
A |
1 |
2 |
0 |
S |
0 |
32 |
Remark:
(a) As a conservative
assessment, it is assumed that the sensitive receivers will not be affected by any
IF.
(b) Building Type: 0 –
Heavy Tall Structures; 1 – 2 to 4 storeys medium height; 2 – 1 to 2 storeys.
(c) Basement: 0 – no basement; 1 – basement.
(d) N.A.: Information for
future property development is not available during the preparation of report.
(e) The future usage of
(f) "Area other than
those above" as the SSS by virtue of its size and characteristics plays a
major role in determining the type of area within which the NSR is located in
accordance with the Technical Memorandum for the Assessment of Noise from
Places other than Domestic Premises, Public Places or Construction Sites.
(g) BCF Type: 0 – No
piles, with BCF; 1 – Piles not to rock, with BCF; 2 – Piles to rock &
tunnel in rock, no BCF; 3 – Piles to
rock & tunnel not in rock, with BCF
(h) TCF: R – Tunnel in
rock, no TCF; S – Tunnel in soil, with TCF
Construction Phase
6.13
Potential ground-borne noise impacts on GBNSRs during the
construction phase will arise mainly from TBM operation,
as well as PME for rock breaking/drilling including breakers, drill
rigs and pipe pile rigs. The standard
working hours of PME will be from 0700 to 1900 hours and the TBM will be
operated on a 24 hour basis. The operation of TBM during
restricted hours should be governed by the control of CNP under NCO. Regardless of the results of
construction noise impact assessment for restricted hours, the Noise Control
Authority will process CNP application, if necessary, based on the NCO, the
relevant technical memoranda issued under the NCO, and the contemporary
conditions/situations of adjoining land uses and any previous complaints
against construction activities at the site before making his decision in
granting a CNP.
Operation Phase
6.14
When trains operate in tunnels that are located in close
proximity to occupied structures, there is a possibility that vibrations
associated with train passbys will be transmitted through the ground and
structure, and be radiated as noise in the occupied spaces within the
structure. The transmitted noise through the structure may have impact to the
GBNSRs.
Ground-borne
Noise Prediction Methodology
Construction Phase
6.15
The project methodology adopted for assessment is
recommended in The Transit Noise and Vibration Impact Assessment[[1]] published by U.S. Department
of Transportation Federal Transit Administration (FTA) (FTA Guidance
Manual). This methodology has been
previously adopted for ground-borne noise assessment in approved Kowloon
Southern Link (KSL) EIA Study (EIA Register No. AEIAR-083/2005) and
L = FDL + LSR + BCF + BVR + CTN + SAF
where
L |
ground-borne noise level within the structure, re: 20 μ-Pascal |
FDL |
force density level for the TBM in rock, mixed face or soil, re: 1
N/m0.5 in SI unit |
LSR |
unit force incoherent line source response for the ground, re: 10-8
m/s/(1 N/m0.5) in SI unit |
BCF |
vibration coupling loss factor between the soil and the foundation,
relative level |
BVR |
building vibration reduction or amplification within a structure from
the foundation to the occupied areas, relative level |
CTN |
Conversion from floor and wall vibration to noise, 10-8 m/s
to 20 μ Pascal |
SAF |
Safety margin to account for project uncertainties |
TBM-induced Ground-borne Noise Impact Assessment
6.16
The TBM-induced ground-borne noise levels were calculated by
incorporating the algorithms in a 3-D model, MoleRat, developed by Wilkinson
Murray Limited.
6.17
The prediction model adopted is based on the equation
discussed in Section 6.15 and is referenced from the FTA Guidance
Manual. The prediction components particular
for TBM-induced ground-borne noise are described in following sections.
Ground-Borne Noise Level within the Structure (L)
6.18
TBM-induced ground-borne noise would have an impact with
frequency, conservatively, up to about 160 Hz and 400Hz for tunnels situated in
soil and rock respectively. Above these
frequencies, the material attenuation of the ground would reduce the amplitude
of the propagating waves below which there would be adverse impact. Thus, structure-borne noise levels were
presented in 1/3 octave bands over the frequency range of 12.5 Hz to 400 Hz.
Force Density Level (FDL)
6.19
FDL values to be adopted for assessment were reference from
WIL EIA Study in which the assessment adopted the vibration measurement taken
during the passby of a TBM operating in soil and rock along the MTR Lok Ma Chau
(LMC) Extension. Measurements were
performed underground in an access shaft adjacent to the alignment at 7m
setback from tunnel centreline. The
associated line source response (LSR) was obtained from surface and borehole
impact tests performed on similar soil and rock geology. On the assumption of a TBM source length of
10m, the FDL values in soil and rock are shown in Appendix 6.1. FDL is dependent upon TBM diameter and ground
condition, but these factors may be represented by the power to be used by the
TBM. The outside diameter (OD) of TBM to
be adopted for the construction of the Project will be about 9.3m and a
standard drive rate of 200m/month was assumed though the actual rate will be
dependent on the ground condition.
Average rates were reference from the case in LMC with 11 m/day in soft
ground and 8.0 m/day in rock. While the
outside diameter of TBM used for the construction of LMC is 8.8m, and therefore
FDL values of the proposed TBM are therefore considered to be of comparable
magnitude with the TBM used in LMC.
6.20
Measurement results indicated that the FDL for the TBM in
rock is considerably higher than that in soil, especially at low
frequencies. As a conservative approach,
the FDL values in mixed face geology rock have been assumed to be same as that
in rock.
Line Source Response (LSR)
6.21
The LSR determines the vibration levels or attenuation in
the ground as a function of distance caused by an incoherent line source of
unit force point impacts, with line source (TBM) orientated along the
alignment.
6.22
LSR has already been measured in
6.23
The LSR values used for assessment are shown in Table 6.6.
Table
6.6 LSR Values used for
Assessment
Alignment |
Corresponding LSR selected from
WIL EIA Study |
|||||||
Chainage (Northbound) |
Chainage (Southbound) |
Track Depth (m) |
Rockhead Depth (m) |
LSR Name |
Borehole Depth (m) |
Rockhead Depth (m) |
||
From |
To |
From |
To |
|||||
116+015 |
116+815 |
116+000 |
116+800 |
No GBNSR |
||||
116+815 |
118+015 |
116+800 |
118+000 |
30 |
60 |
D012-18m |
18 |
34.4 |
118+015 |
118+465 |
118+000 |
118+450 |
40 |
40 |
D012-41.4m |
41.4 |
34.4 |
118+465 |
119+695 |
118+450 |
119+680 |
27 |
55 |
D012-18m |
18 |
34.4 |
119+695 |
119+815 |
119+680 |
119+800 |
60 |
25 |
D049-60.4m |
60.4 |
19.4 |
119+815 |
119+915 |
119+800 |
119+900 |
80 |
25 |
D049-87.8m |
87.8 |
19.4 |
119+915 |
120+015 |
119+900 |
120+000 |
110 |
25 |
D049-87.8m |
87.8 |
19.4 |
120+015 |
122+115 |
120+000 |
122+100 |
No GBNSR |
||||
122+115 |
122+315 |
122+100 |
122+300 |
65 |
15 |
D064-66.7m |
66.7 |
14.7 |
122+315 |
122+415 |
122+300 |
122+400 |
45 |
10 |
D064-54.6m |
54.6 |
14.7 |
122+415 |
122+515 |
122+400 |
122+500 |
38 |
20 |
D028-44.3m |
44.3 |
22.3 |
122+515 |
122+675 |
122+500 |
122+660 |
38 |
25 |
D018-39.8m |
39.8 |
27.6 |
122+675 |
122+975 |
122+660 |
122+960 |
27 |
30 |
D002-19.6m |
19.6 |
24.1 |
122+975 |
123+175 |
122+960 |
123+160 |
20 |
32 |
D012-18m |
18 |
34.4 |
123+175 |
123+515 |
123+160 |
123+500 |
17 |
13 |
D018-39.8m |
39.8 |
27.6 |
123+515 |
125+365 |
123+500 |
125+350 |
20 |
25 |
D002-19.6m |
19.6 |
24.1 |
125+365 |
125+465 |
125+350 |
125+450 |
25 |
15 |
D018-39.8m |
39.8 |
27.6 |
125+465 |
125+565 |
125+450 |
125+550 |
50 |
10 |
D064-54.6m |
54.6 |
14.7 |
125+565 |
125+665 |
125+550 |
125+650 |
75 |
10 |
D049-87.8m |
87.8 |
19.4 |
125+665 |
125+765 |
125+650 |
125+750 |
95 |
10 |
D049-87.8m |
87.8 |
19.4 |
125+765 |
131+815 |
125+750 |
131+800 |
No GBNSR |
||||
131+815 |
132+365 |
131+800 |
132+350 |
100 |
10 |
D049-87.8m |
87.8 |
19.4 |
132+365 |
132+835 |
132+350 |
132+820 |
90 |
15 |
D049-87.8m |
87.8 |
19.4 |
132+835 |
133+035 |
132+820 |
133+020 |
65 |
10 |
D064-66.7m |
66.7 |
14.7 |
133+035 |
133+765 |
133+020 |
133+750 |
55 |
15 |
D064-54.6m |
54.6 |
14.7 |
133+765 |
134+135 |
133+750 |
134+120 |
80 |
10 |
D049-87.8m |
87.8 |
19.4 |
134+135 |
135+515 |
134+120 |
135+500 |
185 |
20 |
D049-87.8m |
87.8 |
19.4 |
135+515 |
136+465 |
135+500 |
136+450 |
No GBNSR |
||||
136+465 |
136+695 |
136+450 |
136+680 |
95 |
25 |
D049-87.8m |
87.8 |
19.4 |
136+695 |
136+915 |
136+680 |
136+900 |
35 |
20 |
D018-39.8m |
39.8 |
27.6 |
136+915 |
137+235 |
136+900 |
137+220 |
35 |
35 |
D002-33.7m |
33.7 |
24.1 |
137+235 |
137+595 |
137+220 |
137+580 |
35 |
40 |
D002-19.6m |
19.6 |
24.1 |
137+595 |
137+835 |
137+580 |
137+820 |
33 |
55 |
D012-18m |
18 |
34.4 |
137+835 |
137+935 |
137+820 |
137+920 |
33 |
33 |
D002-33.7m |
33.7 |
24.1 |
137+935 |
138+115 |
137+920 |
138+100 |
33 |
50 |
D012-18m |
18 |
34.4 |
138+115 |
138+465 |
138+100 |
138+450 |
33 |
80 |
D012-18m |
18 |
34.4 |
138+465 |
139+115 |
138+450 |
139+100 |
35 |
50 |
D012-18m |
18 |
34.4 |
139+115 |
139+315 |
139+100 |
139+300 |
35 |
30 |
D018-39.8m |
39.8 |
27.6 |
139+315 |
139+815 |
139+300 |
139+800 |
40 |
20 |
D028-44.3m |
44.3 |
22.3 |
139+815 |
139+905 |
139+800 |
139+890 |
38 |
38 |
D012-41.4m |
41.4 |
34.4 |
139+905 |
140+215 |
139+890 |
140+200 |
40 |
60 |
D012-18m |
18 |
34.4 |
140+215 |
141+115 |
140+200 |
141+100 |
30 |
50 |
D012-18m |
18 |
34.4 |
141+115 |
141+315 |
141+100 |
141+300 |
30 |
30 |
D002-33.7m |
33.7 |
24.1 |
141+315 |
141+671 |
141+300 |
141+656 |
27 |
40 |
D012-18m |
18 |
34.4 |
Building Coupling Factor (BCF)
6.24
In general, larger and heavier structures have greater vibration
attenuation than smaller and lighter structures. The recommended practice
established within FTA Manual has been followed. Receivers in this study were
divided into 4 types according to its structures and have different BCF
attenuation as below:
Type
0 – Large masonry buildings
Type
1 – 2-4 storeys masonry buildings
Type
2 – 1-2 storeys buildings
Type
3 – Single family detached residences
6.25
The BCF for different types of structure is presented in Appendix
6.3. It is indicated that larger and
heavier structures have greater vibration attenuation than smaller and lighter
structures. In fact, the extent of the attenuation is governed by the
difference in mechanical impedance between the soil and the foundation, with
impedance being determined by differences in mass and stiffness within the soil
and foundation. For structures founded
on rock, there is no impedance contrast between the soil and the foundation, as
a conservative approach, the BCF is considered to be zero.
6.26
It has been assumed that buildings up to three stories in
height do not have piles, and buildings over this height do, unless specific
information is available for assessment.
For most of the high-rise buildings, details of the piles are available,
including whether the piles are to rock or are friction piles. In those cases where no details of the piles
were available, a worst case scenario has been assumed; that the piles are to
rock such that no coupling loss was taken into account.
Building Vibration Response (BVR)
6.27
The BVR is generally determined by three factors as
described below:
I.
Resonance amplification due to floor, wall and ceiling
spans: This resonance amplification is usually an issue for small and
lightweight houses. In large, heavy framed structures, generally multi-floor
concrete construction, structural resonances usually occur at sub-audible
frequencies, with small resonance amplification due to massive structural
elements having low mobility. FTA
Manual recommends a 6 dB correction at the likely natural frequency of
structures to account for structural resonances. The corrections given in Appendix
6.4 were adopted, as was the case for the WIL EIA Study.
II.
Floor-to-floor attenuation: A floor-to-floor attenuation of
2 dB reduction per floor was assumed.
Where there is a multi-floor occupancy, only the structure-borne noise
impact on the lowest occupied floor is considered.
III.
Attenuation across a structure, in the direction away from
the alignment: When the noise sensitive area is situated in the back of the building
away from the alignment, vibration attenuation across a structure would occur.
Attenuation of 2 dB reduction was considered in this study, and this is
conservative for large setbacks.
Conversion to Noise (CTN)
6.28
Based on FTA Manual, a -27 dB correction for conversion of
vibration (re: 10-9 m/s) in room walls, floors and ceiling to noise
(re: 20 micro Pa) was assumed in this study.
Safety Factor (SAF)
6.29
To tackle the problem of differences in overall predicted
and measured A-weighted noise levels, a safety factor was applied in the model.
As a conservative approach, a 10 dB safety factor was adopted to account for
uncertainty and variation in geological characteristics.
PME-induced Ground-borne Noise Impact
6.30
For the assessment of PME-induced ground-borne noise,
reference was made to the assessment approach, source terms and transmission
factors adopted in the approved KSL and WIL EIA Studies. The reference source levels adopted for
assessment are given in Table 6.7.
Table 6.7 Reference Source
Levels
Plant |
Vibration (rms) at reference distance of 5.5m from source[[2]] |
Vibration (ppv) at distance 2m from source |
Hydraulic Breaker |
0.298 mm/s |
- |
Drill Rig |
0.536 mm/s |
- |
Pile Rig |
- |
19.3 mm/s |
Soil Damping
6.31
Internal losses of soil would cause the vibration amplitude
to decay against the propagation distance and the decay relationship is based
on the equation set out in the Transportation Noise Reference Book[[3]].
V(R) = V(Ro) ´ e-2pf h R/2c.
6.32
The velocity amplitude V is dependent on the frequency f in
Hz, the soil loss factorh, the wave speed c in
m/s, the distance R from the source to the GBNSR. The properties of soil materials are shown in
Table 6.8.
Table 6.8 Wave Propagation Properties of Soil
Soil Type |
Longitudinal Wave Speed c, m/s |
Loss Factor, h |
Density, g/cm3 |
Soil |
1500 |
0.5 |
1.7 |
Rock |
3500 |
0.01 |
2.65 |
6.33
It was assumed that no damping attenuation would apply for propagation
in rocks. Therefore, soil damping for GBNSRs with piling foundation on rockhead
was not required.
Coupling Loss into Building Structures
6.34
This was as assumed for TBM-induced ground-borne noise
calculation above.
Loss Per Floor
6.35
This was as assumed for TBM-induced ground-borne noise
calculation above.
Conversion from Floor Vibration to Noise Levels
6.36
This was as assumed for TBM-induced ground-borne noise
calculation above.
Operation Phase
6.37
The railway ground-borne noise levels were calculated by
incorporating the algorithms in a 3-D model, MoleRat, developed by Wilkinson
Murray Limited.
6.38
The methodology adopted for the ground-borne noise impact
assessment is in accordance with the procedures outlined in FTA Guidance Manual
and High-Speed Ground Transportation Noise and Vibration Impact[[4]](FRA High-Speed Guidance Manual). This is a similar methodology as used for WIL
EIA Study. The ground-borne noise level
in GBNSRs were calculated as follows:
L = FDL + TIL + TOC + TCF + LSR + BCF
+ BVR + CTN + SAF
where
L |
ground-borne noise level within building, in dB |
FDL |
force density level, in dB re
1N/m1/2 |
TIL |
trackform attenuation or
insertion loss, relative level |
TOC |
turnout and crossover factor |
TCF |
vibration coupling between the
tunnel and the ground for soil based tunnels, relative level |
LSR |
line source transfer mobility,
in dB re 1(nm/s)/(Nm^0.5) |
BCF BVR CTN SAF |
adjustment to account for
building coupling loss, in dB building vibration amplification
within the structure, in dB conversion from vibration to
noise within the building, in dB safety factor to account for
wheel/rail condition and uncertainties in ground conditions, in dB |
Force Density Levels
(FDL)
6.39
Since high speed trains in 200km/h are currently not running
in Hong Kong and details of the CRH trains proposed for the Project are not
available during the preparation of EIA study, the vibration source levels
(force density levels, FDL) were referenced from the FRA High-Speed Guidance
Manual, which is designed for assessment when details of train type is
unknown. The level adopted for train
type of China Railway High-Speed (CRH) train has been based on the noisiest
train reported (i.e. Acela) in FRA High-Speed Guidance Manual and is shown in
metric units in Appendix 6.5. The
highest level among four trains as given in FRA High-Speed Guidance Manual was
adopted for assessment. This level is
based on a standard high speed train trackform of a moderate to high stiffness,
similar to the proposed 50kN/mm.
6.40
The adopted FDL is for a train on rails in moderate
operational condition and a rail maintenance programme will be developed for
the Project. This FDL will be considered
to identify the ground-borne noise mitigation measures for the Project.
6.41
In accordance with Table 8-2 of the FRA High-Speed Guidance
Manual, the FDL was adjusted for speed as 20 log S/Sref.
Trackform
Alternatives or Insertion Loss (TIL)
6.42
Trackform attenuation has two components: the magnitude of
the attenuation and the frequency above which attenuation occurs (resonance
frequency of the trackform). Generally,
more compliant trackform support and more massive elements in the trackform
will result in a greater magnitude of attenuation occurring at lower
frequencies. In addition, more massive
trackform elements would take up more space in tunnels and may cause spatial
incompatibilities that are difficult to be overcome in the design.
6.43
The ground-borne noise levels at GBNSRs were calculated
initially for a trackform of embedded concrete sleepers with slightly resilient
fixings (approximately 50kN/mm) on top (e.g. Rheda system). An example of proposed trackform is presented
in Appendix 6.11.
6.44
When the appropriate trackforms to meet the noise criteria
had been identified, consideration was then given to the action to be taken if
it is found that ground-borne noise levels exceed the criteria after
construction. Given there would be
uncertainty on on-site/train specific data, a 600mm deep provision will be
provided for the tunnel to allow for further enhancement of mitigation
measures, such as installation of isolated slab track (IST), if required. An example of low noise trackform is
presented in Appendix 6.11. As
such, the currently proposed trackform (concrete sleepers with slightly
resilient fixings) can be replaced with low noise trackfrom where practicable
and necessary to accomplish noise
reduction of up to 15 dB(A), subject to the extent of low noise trackform
provided and the dominant frequency of FDL and LSR, as a contingency
measure. Changing of the tunnel
dimensions would therefore not be required if these contingency measures have
to be in place. Further measurements
would be conducted to check the accuracy of the noise prediction during the
tunnel construction where necessary.
Tunnel Coupling Factor (TCF)
6.45
Tunnel Coupling Factor (TCF) is the vibration coupling
between the tunnel and the ground for soil based tunnels. Vibration attenuation occurs at the interface
between a transit tunnel and the surrounding soil on account of a mismatch in
the soil and tunnel wall impedances. The TCF adopted in this study was
referenced from the WIL EIA Study. In
general, tunnels borne in rock generally do not exhibit any significant
vibration attenuation across the tunnel rock interface, thus no TCF attenuation
is applied for rock-founded tunnels.
However, with reference to the FTA Manual, a 3dB(A) and 5dB(A) reduction
in ground-borne noise level was assumed for cut-and-cover tunnels and station
structures respectively in soil.
6.46
For tunnels in soil, separate tests have been carried out in
Turnout and Crossover
Factor
6.47
At points and crossings, where the wheel transitions from
one rail to another, the sudden loading/unloading of the leading and trailing
rails results in increased broad band vibration levels over that of plain line
continuous rail. While it is not possible to machine grind the rails through
either the points or crossings, surface deterioration would often be evident. For standard level turnouts and crossings
receiving average maintenance, the FTA Manual recommends a correction of 10dB.
For modern inclined turnouts in good condition, where impact loads are
lessened, a correction of 5dB would be appropriate. As in the recent WIL EIA
study, 5dB(A) adjustment was added for inclined turnout.
Line Source Response
(LSR)
6.48
The LSR determines the vibration levels or attenuation in
the ground as a function of distance caused by an incoherent line source of unit
force point impacts, with line source (train) orientated along the
alignment. Thus, the basic quantity
required for the determination of the LSR would be the vibration response
caused by a unit point source impact, which is defined as the Point Source
Response (PSR). Given that the PSR would
be along the alignment, the LSR would follow directly by incoherent integration
of the PSR values. However, the determination of the PSR for force point
impacts along the alignment over the length of the alignment is neither
practical nor affordable. For example,
at underground sections, force impacting would have to be performed in numerous
boreholes drilled to the depth of the alignment and closely spaced along the
alignment. Thus, certain assumptions
have been invoked, which allow one PSR to be taken as representative along the
alignment near a building receiver and to be used in the determination of the
LSR. These assumptions include:
· ground is layer-wise homogeneous;
· ground is transversely isotropic along the alignment over the length of the train; and
· ground is between the alignment segment and the vibration receivers at which the LSR is to be determined.
6.49
If the ground satisfies these assumptions rigorously, it
would be acceptable to use one PSR in the determination of the LSR. In normal
circumstances, deviation from the idealised assumptions of transverse isotropy
and layer-wise homogeneity is not significant enough to warrant the time,
expense and impracticality of impacting along the entire length of the
alignment.
6.50
LSR has already been measured in
Other Factors
6.51
Other correction factors including BCF, BVR, CTN and SAF
were adopted as that mentioned under the assessment methodology of TBM-induced
ground-borne noise.
Calculation of Leq
6.52
The Leq values have been calculated using MoleRat, by the following procedures:
·
Calculate the noise level from a full train at each of many
locations at 10m intervals along the whole line
·
Sum the energy from these levels and calculate the SEL level
·
Calculate the Leq levels from
Leq = 10 log [10(SELlong + 10 log Vlong)/10 + 10(SELshort
+ 10 log Vshort)/10] – 35.6
where
Vlong |
Number of long haul train movements in the relevant 30 minute or 24
hour period, expressed as the average number of movements per hour: For Leq(30min): V = N(30min) x 2 (N = number of movements) For Leq(24hour): V = N(24hour) / 24 (N = number of movements) |
Vshort |
Number of short haul train movements in the relevant 30 minute or 24
hour period, expressed as the average number of movements per hour: For Leq(30min): V = N(30min) x 2 (N = number of movements) For Leq(24hour): V = N(24hour) / 24 (N = number of movements) |
Ground-borne Noise Impact Assessment
Construction Phase
TBM Induced Ground-borne Noise
6.53
The tunnel will be constructed by TBM mainly in soft ground,
but also in some rock or rock/soft ground border. The locations where TBM will be used are
shown in Table 6.9.
Table 6.9 Chainages where TBM Operation will occur
From |
To |
115+930 |
117+385 |
117+485 |
119+850 |
122+490 |
123+540 |
124+910 |
125+330 |
136+780 |
137+760 |
137+968 |
140+380 |
6.54
The TBM-induced ground-borne noise levels were predicted,
and the times of day when tunneling could be carried out whilst meeting the ANLs
over specific sections of the Project were also determined, basing on the
following assumptions:
·
For the case where the tunnel will be in rock and the NSR is
piled down to rock, the vibration path has been assumed to be horizontally
across the rock and up the piles into the building;
·
For the cases where the tunnel will be in soft ground or the
NSR is not on piles, the vibration path has been assumed to be through the
ground along a slant path to the nearest part of the NSR
6.55
The predicted TBM ground-borne noise levels at the GNSRs
with the distances adopted in the calculation are shown in Table 6.10. Sample calculations are given in Appendix
6.7.
Table 6.10 Predicted Ground-borne Construction Noise levels due to TBM
Operation
Location |
Predicted
Level(1), dB(A) |
Criterion,
dB(A) |
Acceptable |
Calculated |
|||
Leq |
Leq |
Leq
(evening) |
Leq
(night) |
||||
GN3 |
|
62 |
60 (55 for
exam) |
55 |
- |
D(3),
N |
5 |
GN4 |
Block
9, Charming Garden |
60 |
65 |
55 |
40 |
D |
5 |
GN5 |
Tower 5
Phase |
71 |
65 |
55 |
40 |
D(3) |
6 |
GN6 |
|
56 |
65 |
55 |
40 |
D |
37 |
GN7 |
|
65 |
65 |
55 |
40 |
D |
36 |
GN8 |
|
70 |
65 |
55 |
40 |
D(3)
|
19 |
GN9 |
|
53 |
65 |
55 |
40 |
D, E |
19 |
GN10 |
Fu Yun House,
Fu Cheong Estate |
52 |
65 |
55 |
40 |
D, E |
15 |
GN12 |
|
51 |
60 (55
for exam) |
55 |
- |
D, E, N |
21 |
GN12a |
Tack
Ching Girls' Secondary School |
29 |
60 (55
for exam) |
55 |
- |
D, E, N |
40 |
GN13 |
Tower 6
Aqua Marine |
36 |
65 |
55 |
40 |
D, E, N |
21 |
GN14 |
HKIVE
Haking Wong Waterfront Annex |
53 |
60 (55
for exam) |
55 |
- |
D, E, N |
35 |
GN14a |
Lai Chi
Kok Reception Centre |
63 |
65 |
55 |
40 |
D |
43 |
GN26 |
426A Tsang
|
42 |
65 |
55 |
35 |
D, E |
23 |
GN27 |
431A
Tsang |
40 |
65 |
55 |
35 |
D, E |
26 |
GN28 |
510B |
40 |
65 |
55 |
35 |
D, E |
26 |
GN29 |
630
Sheung Tsuen |
44 |
65 |
55 |
35 |
D, E |
28 |
GN31 |
DD110 |
80 |
65 |
55 |
40 |
D(3)
|
19 |
GN33 |
348
Tsat Sing Kong |
59 |
65 |
50 |
35 |
D |
27 |
GN34 |
349
Tsat Sing Kong |
61 |
65 |
50 |
35 |
D |
27 |
GN35 |
|
57 |
65 |
50 |
35 |
D |
46 |
GN36 |
DD104 |
43 |
65 |
50 |
35 |
D, E |
31 |
GN37 |
DD104 |
40 |
65 |
50 |
35 |
D, E |
29 |
GN37a |
|
41 |
65 |
50 |
35 |
D, E |
53 |
GN38 |
45 Wai Tsai
Tsuen |
46 |
65 |
50 |
35 |
D, E |
33 |
GN38a |
|
42 |
65 |
50 |
35 |
D, E |
33 |
GN38b |
|
41 |
60 (55
for exam) |
50 |
35 |
D, E |
29 |
GN39 |
62D Wai
Tsai Tsuen |
49 |
65 |
50 |
35 |
D, E |
34 |
GN40 |
House
1, Green Crest |
50 |
65 |
50 |
35 |
D, E |
42 |
GN41 |
House
A73 |
56 |
65 |
50 |
35 |
D |
39 |
GN42 |
House
A78 |
47 |
65 |
50 |
35 |
D, E |
38 |
GN43 |
Area
Zoned as R(A) |
34 |
65 |
50 |
35 |
D, E, N |
31 |
GN44 |
House 5
Phase A Royal Palms |
32 |
65 |
50 |
35 |
D, E, N |
51 |
GN45 |
Village
house in Mai Po |
39 |
65 |
50 |
35 |
D, E |
32 |
Notes:
(1) Bold and
underlined figure indicates the predicted level exceed the daytime noise
criterion of EIAO-TM.
(2) D
= All days during daytime (0700 – 1900 hours) except general holidays
(including Sundays), E = All days during evening period (1900 – 2300 hours),
and general holidays (including Sundays) during the daytime and evening, N =
All days during night-time period (2300 – 0700 hours).
(3)
Ground-borne noise monitoring would be required to monitor the ground-borne
noise impact induced by the TBM operation.
(4) The
calculated distance is the minimum distance from the centre line of the nearest
tunnel to the nearest part of the structure, including piles. It is mostly a slant distance, the exception being
when the nearest point of the piles is at the same level as the tunnel (in
which case the distance is a horizontal distance).
(5) Evening
and night-time operation of TBM presented in the table is for indication of
acceptable operating time only. TBM
operation during restricted hours is subject to approval of CNP
application.
6.57
Monitoring at the time of TBM operation will therefore be
required to confirm and monitor the ground-borne noise levels. Where it is possible that the 65dB(A) limit
will be exceeded, reducing the rotational speed and scheduling of the works in
consultation with affected parties will be the available way of alleviating the
impact. This action is required over the chainages
shown in Table 6.11 at which
exceedance of the daytime noise limit would be predicted.
Table 6.11 Locations at which TBM Ground-borne Noise Levels would Exceed
the Daytime Noise Limit
NSR |
Chainages where Levels Predicted
to Exceed Daytime Criteria |
||
Track |
From |
To |
|
GN3 |
Up |
140+330 |
140+340 |
GN5 |
Up |
140+840 |
140+860 |
GN8 |
Down |
139+260 |
139+300 |
Up |
139+310 |
139+320 |
|
GN31 |
Up |
123+480 |
123+500 |
6.58
Based on the daily progress of the TBM at LMC of 8-11m per
day, it is likely that any exceedance of the criteria would extend for about
two or three days at the affected NSRs.
PME Induced Ground-borne
Noise
6.59
Table 6.12 shows a summary of the PME-induced ground-borne noise
levels during the construction of adits.
Sample calculations are given in Appendix 6.7
Table 6.12 Predicted PME Ground-borne Noise Levels during
Construction
NSR |
Construction Site |
Operation |
Leq(30min), dB(A) |
Daytime Criteria,
dB(A) |
GN12a |
|
Hydraulic breaker |
44 |
60 |
GN14a |
Drill & Blast Tunnel |
Drill Rig |
62 |
65 |
GN14b |
|
Hydraulic breaker |
<20 |
65 |
GN14c |
|
Hydraulic breaker |
59 |
60 |
GN15 |
Drill & Blast Tunnel |
Drill Rig |
<20 |
65 |
GN16 |
Drill & Blast Tunnel |
Drill Rig |
31 |
65 |
GN17 |
Drill & Blast Tunnel |
Drill Rig |
25 |
65 |
GN18 |
Drill & Blast Tunnel |
Drill Rig |
41 |
65 |
GN18a |
Kwai Chung Adit |
Hydraulic breaker |
21 |
65 |
GN19 |
Drill & Blast Tunnel |
Drill Rig |
56 |
65 |
GN20 |
Drill & Blast Tunnel |
Drill Rig |
58 |
65 |
GN21 |
Drill & Blast Tunnel |
Drill Rig |
<20 |
65 |
GN21a |
Shek Yam Adit |
Hydraulic breaker |
<20 |
65 |
GN22 |
Drill & Blast Tunnel |
Drill Rig |
<20 |
65 |
GN22a |
Shek Yam Adit |
Hydraulic breaker |
<20 |
65 |
GN23 |
Drill & Blast Tunnel |
Drill Rig |
<20 |
65 |
GN24 |
Drill & Blast Tunnel |
Drill Rig |
56 |
65 |
GN25 |
Drill & Blast Tunnel |
Drill Rig |
46 |
60 |
GN25a |
Pat Heung Adit |
Drill Rig |
<20 |
65 |
GN30 |
ERS Structure |
Pile Rig |
<20 |
65 |
GN35 |
Drill & Blast Tunnel |
Drill Rig |
<20 |
65 |
6.60
Predicted results indicate that
all PME induced ground-borne
noise levels comply with the daytime criteria.
Cumulative
Construction Ground-borne Noise Impact
6.61
It is anticipated that there would
be no cumulative construction ground-borne noise impact at GBNSR 14a due to TBM
and PME operation, given that TBM and PME would not be operating simultaneously
due to safety reason. For GBNSR 12a, the
cumulative ground-borne noise level is 44dB(A), which complies with EIAO-TM,
and therefore no adverse cumulative ground-borne noise impact is anticipated.
Operation Phase
6.62
Operational ground-borne noise levels were calculated by
incorporating the algorithms discussed in a 3-D model, MoleRat, which is
developed by Wilkinson Murray Limited.
Leq(30min) for day and night, Leq(24hr) and Lmax levels were
calculated at most affected floor levels and the noise impact has been
quantified by indicating the total number of dwellings or other sensitive
elements exposed to levels exceeding the criteria.
Operational Information
6.63
Two train types are expected to operate for the Project; a
long haul train of length 427m and a short haul train of length 214m.
6.64
As a worst case, the number of through train movements has
been assumed to be the operational capacity of the system at daytime and
evening (0700 – 2300 hours) and an equivalent hourly number for the two
operational hours at night-time (2300 – 2400 and 0600 – 0700 hours), as shown
in Table 6.13. In addition to this, there will be shunting
movements between SSS and WKT during the operational hours, and these need to
be added to allow calculation of total ground-borne noise levels. However, since no speed profiles are
available for shunting trains, a conservative approach has been adopted whereby
the shunting trains are assumed to travel the full length of the project.
Table 6.13 Assumed Train Movements
Track |
Train Type |
Movements per Hour |
||||
Long Haul Train(1) |
Short Haul Train(1) |
Total |
||||
Daytime and evening |
Night-time |
Daytime and evening |
Night-time |
24 Hour(2) |
||
Northbound |
Short |
13 |
6 |
0 |
3 |
6 |
Long |
2 |
0 |
2 |
1 |
2 |
|
Total |
15 |
6 |
2 |
4 |
8 |
|
Southbound |
Short |
12 |
5 |
1 |
0 |
6 |
Long |
3 |
0 |
3 |
0 |
2 |
|
Total |
15 |
5 |
4 |
0 |
8 |
Notes:
(1) Long haul and short haul trains will be operated
during the period of 0600 – 2400 hours only.
(2) Train
frequency for 24 hours was calculated based on the average hour of total
24-hour train movements.
6.65
The worst hours for through trains and shunting trains at
night are not the same. The worst hour
for through trains is 0600 - 0700 hours and for shunting trains is 2300 – 2400
hours. Nevertheless, the worst hours
were added in a conservative approach.
Where 30 minute train movements were required, these were derived by
dividing the hourly movements by two.
6.66
The speed profiles adopted in the present assessment are
presented in Appendix 6.8.
6.67
Turnouts of the inclined type have been assumed at the
locations in Table 6.14.
Table 6.14 Locations of Turnouts
Up |
Down |
117+310 |
|
117+510 |
117+500 |
121+895 |
121+635 |
123+510 |
123+545 |
124+375 |
124+310 |
124+925 |
124+910 |
126+195 |
126+060 |
126+215 |
126+320 |
131+945 |
131+810 |
131+965 |
132+075 |
137+830 |
137+800 |
137+980 |
137+950 |
140+735 |
140+775 |
140+790 |
140+830 |
140+845 |
140+895 |
140+910 |
140+940 |
140+955 |
140+995 |
141+010 |
141+055 |
141+055 |
141+115 |
141+130 |
141+140 |
141+180 |
141+180 |
Predicted Ground-borne Noise Levels
6.68
The predicted ground-borne noise levels as a result of
Project operation at the lowest occupied floor of GBNSRs, together with the
distances used in the calculation are shown in Table 6.15. The calculation of the noise levels assumes
the following conditions:
·
For the case where the tunnel will be in rock and the NSR is
piled down to rock, the vibration path has been assumed to be across the rock
and up the piles into the building
·
For the cases where the tunnel will be in soft ground, the
NSR is not on piles or the NSR is on piles not down to rock, the vibration path
has been assumed to be through the ground along a slant path to the nearest
part of the NSR or piles.
·
Where piling details are not known and the tunnel will be in
rock, it has been assumed that the piles are down to rock (worst case
assumption).
Table 6.15 Predicted
Ground-borne Railway Noise Levels
Location |
Predicted
Ground-borne Noise Level, dB(A) |
Criterion,
dB(A) |
Down
Track Calculated |
Up |
|||||
Leq,
30min (day) |
Leq,
30min (night) |
Leq
(24hr) |
Lmax |
Leq,
30min (day) |
Leq,
30min (night) |
||||
GN1 |
Future
Development at |
25 |
20 |
22 |
36 |
N.A. |
N.A. |
20 |
20 |
GN2 |
Future Development
at |
<15 |
<15 |
<15 |
21 |
N.A. |
N.A. |
40 |
40 |
GN2a |
WKT Topside Development |
38 |
34 |
36 |
48 |
55 |
45 |
27 |
27 |
GN2b |
WKT Topside Development |
39 |
34 |
37 |
48 |
55 |
45 |
27 |
27 |
GN2c |
WKT Topside Development |
41 |
36 |
39 |
50 |
55 |
45 |
27 |
27 |
GN2d |
Block 6
Phase 1 |
<15 |
<15 |
<15 |
18 |
55 |
45 |
52 |
42 |
GN2e |
|
<15 |
<15 |
<15 |
18 |
55 |
45 |
59 |
67 |
GN3 |
|
28 |
23 |
26 |
40 |
55 |
45 |
15 |
5 |
GN4 |
Block
9, Charming Garden |
26 |
21 |
24 |
38 |
55 |
45 |
5 |
15 |
GN5 |
Tower 5
Phase |
24 |
19 |
22 |
37 |
55 |
45 |
22 |
6 |
GN6 |
|
<15 |
<15 |
<15 |
25 |
55 |
45 |
37 |
37 |
GN7 |
|
19 |
<15 |
16 |
31 |
55 |
45 |
36 |
36 |
GN8 |
|
22 |
17 |
20 |
35 |
55 |
45 |
19 |
19 |
GN9 |
|
17 |
<15 |
15 |
32 |
55 |
45 |
19 |
36 |
GN10 |
Fu Yun
House, Fu Cheong Estate |
23 |
18 |
21 |
39 |
55 |
45 |
15 |
30 |
GN11 |
Planned
|
29 |
24 |
27 |
43 |
55 |
45 |
7 |
9 |
GN11a(2) |
Planned
Residential Development in Site 6 |
41 |
36 |
39 |
56 |
55 |
45 |
26 |
10 |
GN12 |
|
20 |
15 |
18 |
35 |
55 |
45 |
36 |
21 |
GN12a |
Tack
Ching Girls' Secondary School |
<15 |
<15 |
<15 |
24 |
55 |
45 |
40 |
56 |
GN13 |
Tower 6
Aqua Marine |
<15 |
<15 |
<15 |
21 |
55 |
45 |
21 |
37 |
GN14 |
HKIVE
Haking Wong Waterfront Annex |
<15 |
<15 |
<15 |
29 |
55 |
45 |
35 |
41 |
GN14a |
Lai Chi
Kok Reception Centre |
26 |
21 |
24 |
39 |
55 |
45 |
44 |
43 |
GN14b |
Ward A,
|
<15 |
<15 |
<15 |
25 |
55 |
45 |
101 |
90 |
GN15 |
40A |
<15 |
<15 |
<15 |
<15 |
50 |
40 |
235 |
235 |
GN16 |
Tower 6
|
<15 |
<15 |
<15 |
<15 |
55 |
45 |
250 |
248 |
GN17 |
Block
21 Wonderland Villas |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
275 |
275 |
GN18 |
Block |
<15 |
<15 |
<15 |
27 |
55 |
45 |
89 |
89 |
GN18b |
|
25 |
20 |
23 |
38 |
55 |
45 |
57 |
61 |
GN19 |
Tower B
Kwai Sing Centre |
29 |
24 |
27 |
43 |
55 |
45 |
41 |
42 |
GN19a |
|
28 |
23 |
26 |
42 |
55 |
45 |
45 |
48 |
GN20 |
Block B
Hutchison Estate |
30 |
25 |
27 |
43 |
55 |
45 |
34 |
36 |
GN21 |
184 Yau Ma
Hom Resite Village |
15 |
<15 |
<15 |
28 |
55 |
45 |
73 |
73 |
GN22 |
18 Da
Chuen |
<15 |
<15 |
<15 |
28 |
50 |
40 |
87 |
87 |
GN23 |
35
Sheung Kwai Chung Village |
<15 |
<15 |
<15 |
<15 |
50 |
40 |
98 |
98 |
GN24 |
Sau
Shan House, Cheung Shan Estate |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
125 |
124 |
GN25 |
Tsuen
Wan |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
124 |
124 |
GN26 |
426A
Tsang |
<15 |
<15 |
<15 |
29 |
50 |
40 |
26 |
23 |
GN27 |
431A
Tsang |
<15 |
<15 |
<15 |
26 |
50 |
40 |
27 |
26 |
GN28 |
510B |
<15 |
<15 |
<15 |
25 |
50 |
40 |
26 |
29 |
GN29 |
630
Sheung Tsuen |
17 |
<15 |
15 |
33 |
50 |
40 |
28 |
42 |
GN30 |
51A
Leung |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
113 |
132 |
GN30a |
Village
Zone West Boundary, Leung |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
61 |
79 |
GN30b |
Village
house in Leung Uk Tsuen |
<15 |
<15 |
<15 |
21 |
55 |
45 |
46 |
64 |
GN31 |
DD110 |
30 |
25 |
28 |
45 |
55 |
45 |
35 |
19 |
GN33 |
348
Tsat Sing Kong |
21 |
16 |
19 |
34 |
50 |
40 |
29 |
27 |
GN34 |
349 Tsat
Sing Kong |
21 |
15 |
18 |
33 |
50 |
40 |
27 |
34 |
GN35 |
|
<15 |
<15 |
<15 |
27 |
50 |
40 |
46 |
52 |
GN36 |
DD104 |
20 |
15 |
18 |
34 |
50 |
40 |
31 |
33 |
GN37 |
DD104 |
21 |
16 |
19 |
35 |
50 |
40 |
30 |
29 |
GN37a |
|
<15 |
<15 |
<15 |
18 |
50 |
40 |
67 |
53 |
GN38 |
45 Wai
Tsai Tsuen |
20 |
15 |
18 |
34 |
50 |
40 |
33 |
33 |
GN38a |
|
<15 |
<15 |
<15 |
30 |
50 |
40 |
33 |
41 |
GN38b |
|
17 |
<15 |
15 |
31 |
50 |
40 |
33 |
29 |
GN39 |
62D Wai
Tsai Tsuen |
15 |
<15 |
<15 |
29 |
50 |
40 |
34 |
34 |
GN40 |
House
1, Green Crest |
<15 |
<15 |
<15 |
24 |
50 |
40 |
53 |
42 |
GN41 |
House
A73 |
<15 |
<15 |
<15 |
28 |
50 |
40 |
42 |
39 |
GN42 |
House
A78 |
<15 |
<15 |
<15 |
25 |
50 |
40 |
38 |
40 |
GN43 |
Area Zoned
as R(A) |
20 |
15 |
18 |
34 |
50 |
40 |
31 |
32 |
GN44 |
House 5
Phase A Royal Palms |
<15 |
<15 |
<15 |
15 |
50 |
40 |
65 |
51 |
GN45 |
Village
house in Mai Po |
19 |
<15 |
17 |
34 |
50 |
40 |
36 |
32 |
Note:
(1) Locations GN2a to
GN2c are the locations of future WKT topside developments which are directly
connected to the WKT by the station structure.
The distances shown are therefore distances through the structure and not
through the ground.
(2) Layout and foundation design of the future
development at Site 6 were not available at the time of reporting. The potential ground-borne noise impact at
the planned NSR was predicted by assuming that the worst affected noise sensitive
use would be located at a minimum distance of 3m away from the outer surface of
the tunnel box (10m from track), which is the boundary of the
non-building/structural clearance zone.
On-going liaison with Housing Department will be carried out in detailed
design stage such that the future residential development at Site 6 would not
be adversely affected by railway ground-borne noise. The Project Proponent will continue to liaise
with the owner of Site 6, i.e. Hong Kong Housing Authority to resolve any
interface issues between these two development projects. Based on the outcome of the liaison process,
the trackform design and mitigation measures proposal will be reviewed if
needed.
6.69
All of the predicted levels at existing residential
receivers and at possible CDA developments over WKT are well below the
criteria, generally as a result of deep underground alignment. Appendix 6.9 shows the sample
calculation of selected GBNSRs.
6.70
Within the proposed West Kowloon Cultural District (WKCD)
(locations GN1 and GN2), noise levels have been predicted at 20m and 40m from
the nearest track to give an indication of the implications on any future
development. The feasibility of
providing upgraded trackform at WKT to minimise the potential ground-borne
noise impact at WKCD has been investigated.
6.71
It is unlikely that FDL values will be higher than assumed
for this analysis due to deterioration of rails and rolling stock, with the
implementation of good maintenance regimes such that the Project will operate
properly.
Recommended Mitigation Measures
Construction Phase
6.72
The predicted construction ground-borne noise levels will
comply with the stipulated noise criteria at all NSRs, except four NSRs in
proximity to TBM operation. Based on the
daily progress of the TBM at LMC of 8-11m per day, it is likely that any
exceedance of the criteria will be for about only two or three days. The operation of TBM during restricted hours will be
subject to the control of CNP under NCO.
6.73
Monitoring at the time of TBM operation is recommended to
confirm and monitor the ground-borne noise levels. An EM&A programme, together with careful
scheduling of the works and close liaison with affected parties which would
have exceedance of the noise criterion, is recommended to minimise the impact
from the operation of TBM.
Operation Phase
6.74
With the predicted operation ground-borne noise levels
complying with the stipulated noise criteria at existing NSRs, mitigation
measures are not required during operation phase. Concerning the potential ground-borne noise
impact due to the uncertainty of the FDL and LSR values, installation of low
noise trackform at the concerned areas has been proposed and would be
implemented to further minimise the ground-borne noise levels. Low noise trackform suitable for high speed
railway includes isolated slab trackform (IST) and Vanguard. The insertion loss values for this trackform
are shown in Appendix 6.10. The locations along the alignment where the
predicted noise levels at the GBNSRs are comparatively high among other GBNSRs
have been identified and the approximate chainages as presented in Table 6.16 will be provided with low
noise trackform, where practicable.
6.75
In addition, to minimise the noise impact to the future
WKCD, low noise trackform will also be provided at WKT. With the provision of low noise trackform at
WKT, the Lmax levels at areas within the WKCD site and outside the
WKT boundary were predicted to be in general lower than 25dB(A).
6.76
The noise levels at the representative GBNSRs would be
reduced to those shown in Table 6.17
with the provision of low noise trackform.
Appendix 6.11 shows the sample calculation of selected GBNSRs
with the provision of IST.
Table 6.16 Approximate Chainages where Low Noise Trackform to be provided
Southbound |
|
From |
To |
123+040
|
123+640
|
133+160
|
133+660
|
137+600
|
138+350
|
139+100
|
139+600
|
140+900 |
141+600
|
Northbound |
|
From |
To |
123+050
|
123+650
|
133+170
|
133+670
|
137+620
|
138+370
|
139+120
|
139+620
|
140+900 |
141+600
|
Table 6.17 Predicted Ground-borne Noise Levels with the Provision of IST
GBNSR
No. |
Location |
Predicted
Ground-borne Noise Level, dB(A) |
Criterion,
dB(A) |
Down
Track Calculated |
Up |
||||
Leq,
30min (day) |
Leq,
30min (night) |
Leq
(24hr) |
Lmax |
Leq,
30min (day) |
Leq,
30min (night) |
||||
GN1 |
Future
Development at |
<15 |
<15 |
<15 |
23 |
N.A. |
N.A. |
20 |
20 |
GN2 |
Future
Development at |
<15 |
<15 |
<15 |
<15 |
N.A. |
N.A. |
40 |
40 |
GN2a |
WKT Topside Development(1) |
27 |
23 |
25 |
34 |
55 |
45 |
27 |
27 |
GN2b |
WKT Topside Development(1) |
27 |
23 |
25 |
32 |
55 |
45 |
27 |
27 |
GN2c |
WKT Topside Development(1) |
29 |
24 |
27 |
35 |
55 |
45 |
27 |
27 |
GN2d |
Block 6
Phase 1 |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
52 |
42 |
GN2e |
|
<15 |
<15 |
<15 |
17 |
55 |
45 |
59 |
67 |
GN3 |
|
28 |
23 |
26 |
40 |
55 |
45 |
15 |
5 |
GN4 |
Block
9, Charming Garden |
26 |
21 |
24 |
38 |
55 |
45 |
5 |
15 |
GN5 |
Tower 5
Phase |
24 |
19 |
22 |
37 |
55 |
45 |
22 |
6 |
GN6 |
|
<15 |
<15 |
<15 |
<15 |
55 |
45 |
37 |
37 |
GN7 |
|
<15 |
<15 |
<15 |
17 |
55 |
45 |
36 |
36 |
GN8 |
|
<15 |
<15 |
<15 |
24 |
55 |
45 |
19 |
19 |
GN9 |
|
17 |
<15 |
<15 |
32 |
55 |
45 |
19 |
36 |
GN10 |
Fu Yun
House, Fu Cheong Estate |
23 |
18 |
21 |
39 |
55 |
45 |
15 |
30 |
GN11 |
Planned
|
19 |
<15 |
17 |
34 |
55 |
45 |
7 |
9 |
GN11a(2) |
Planned
Residential Development in Site 6 |
29 |
25 |
27 |
44 |
55 |
45 |
26 |
10 |
GN12 |
|
19 |
<15 |
17 |
34 |
55 |
45 |
36 |
21 |
GN12a |
Tack
Ching Girls' Secondary School |
<15 |
<15 |
<15 |
22 |
55 |
45 |
40 |
56 |
GN13 |
Tower 6
Aqua Marine |
<15 |
<15 |
<15 |
21 |
55 |
45 |
21 |
37 |
GN14 |
HKIVE
Haking Wong Waterfront Annex |
<15 |
<15 |
<15 |
29 |
55 |
45 |
35 |
41 |
GN14a |
Lai Chi
Kok Reception Centre |
26 |
21 |
24 |
39 |
55 |
45 |
44 |
43 |
GN14b |
Ward A,
|
<15 |
<15 |
<15 |
25 |
55 |
45 |
101 |
90 |
GN15 |
40A |
<15 |
<15 |
<15 |
<15 |
50 |
40 |
235 |
235 |
GN16 |
Tower 6
|
<15 |
<15 |
<15 |
<15 |
55 |
45 |
250 |
248 |
GN17 |
Block
21 Wonderland Villas |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
275 |
275 |
GN18 |
Block |
<15 |
<15 |
<15 |
27 |
55 |
45 |
89 |
89 |
GN18b |
|
23 |
18 |
21 |
37 |
55 |
45 |
57 |
61 |
GN19 |
Tower B
Kwai Sing Centre |
21 |
16 |
19 |
33 |
55 |
45 |
41 |
42 |
GN19a |
|
21 |
16 |
19 |
30 |
55 |
45 |
45 |
48 |
GN20 |
Block B
Hutchison Estate |
23 |
18 |
20 |
35 |
55 |
45 |
34 |
36 |
GN21 |
184 Yau Ma
Hom Resite Village |
15 |
<15 |
<15 |
28 |
55 |
45 |
73 |
73 |
GN22 |
18 Da
Chuen |
<15 |
<15 |
<15 |
28 |
50 |
40 |
87 |
87 |
GN23 |
35
Sheung Kwai Chung Village |
<15 |
<15 |
<15 |
<15 |
50 |
40 |
98 |
98 |
GN24 |
Sau
Shan House, Cheung Shan Estate |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
125 |
124 |
GN25 |
Tsuen
Wan |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
124 |
124 |
GN26 |
426A
Tsang |
<15 |
<15 |
<15 |
29 |
50 |
40 |
26 |
23 |
GN27 |
431A
Tsang |
<15 |
<15 |
<15 |
26 |
50 |
40 |
27 |
26 |
GN28 |
510B |
<15 |
<15 |
<15 |
25 |
50 |
40 |
26 |
29 |
GN29 |
630
Sheung Tsuen |
17 |
<15 |
15 |
33 |
50 |
40 |
28 |
42 |
GN30 |
51A
Leung |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
113 |
132 |
GN30a |
Village
Zone West Boundary, Leung |
<15 |
<15 |
<15 |
<15 |
55 |
45 |
61 |
79 |
GN30b |
Village
house in Leung Uk Tsuen |
<15 |
<15 |
<15 |
21 |
55 |
45 |
46 |
64 |
GN31 |
DD110 |
18 |
<15 |
16 |
32 |
55 |
45 |
35 |
19 |
GN33 |
348
Tsat Sing Kong |
20 |
15 |
18 |
34 |
50 |
40 |
29 |
27 |
GN34 |
349 Tsat
Sing Kong |
20 |
15 |
18 |
33 |
50 |
40 |
27 |
34 |
GN35 |
|
<15 |
<15 |
<15 |
27 |
50 |
40 |
46 |
52 |
GN36 |
DD104 |
20 |
15 |
18 |
34 |
50 |
40 |
31 |
33 |
GN37 |
DD104 |
21 |
16 |
19 |
35 |
50 |
40 |
30 |
29 |
GN37a |
|
<15 |
<15 |
<15 |
18 |
50 |
40 |
67 |
53 |
GN38 |
45 Wai
Tsai Tsuen |
20 |
15 |
18 |
34 |
50 |
40 |
33 |
33 |
GN38a |
|
<15 |
<15 |
<15 |
30 |
50 |
40 |
33 |
41 |
GN38b |
|
17 |
<15 |
15 |
31 |
50 |
40 |
33 |
29 |
GN39 |
62D Wai
Tsai Tsuen |
15 |
<15 |
<15 |
29 |
50 |
40 |
34 |
34 |
GN40 |
House
1, Green Crest |
<15 |
<15 |
<15 |
24 |
50 |
40 |
53 |
42 |
GN41 |
House
A73 |
<15 |
<15 |
<15 |
28 |
50 |
40 |
42 |
39 |
GN42 |
House
A78 |
<15 |
<15 |
<15 |
25 |
50 |
40 |
38 |
40 |
GN43 |
Area Zoned
as R(A) |
20 |
15 |
18 |
34 |
50 |
40 |
31 |
32 |
GN44 |
House 5
Phase A Royal Palms |
<15 |
<15 |
<15 |
15 |
50 |
40 |
65 |
51 |
GN45 |
Village
house in Mai Po |
19 |
<15 |
17 |
34 |
50 |
40 |
36 |
32 |
Note:
(1) Locations GN2a to
GN2c are the locations of future WKT topside developments which are directly
connected to the WKT by the station structure.
The distances shown are therefore distances through the structure and not
through the ground.
(2) Layout and
foundation design of the future development at Site 6 were not available at the
time of reporting. The potential
ground-borne noise impact at the planned NSR was predicted by assuming that the
worst affected noise sensitive use would be located at a minimum distance of 3m
away from the outer surface of the tunnel box (10m from track), which is the
boundary of the non-building/structural clearance zone. The Project Proponent will continue to liaise
with the owner of Site 6, i.e. Hong Kong Housing Authority to resolve any
interface issues between these two development projects. Based on the outcome of the liaison process,
the trackform design and mitigation measures proposal will be reviewed if
needed.
Cumulative Effect
from Other Rail Lines
6.77
The Project will run close to other existing rail lines and
the cumulative effect from other rail lines has been reviewed. Locations where other rail lines are
relatively close are as follows:
·
The WKT will be located in the vicinity of the KSL Austin
Station
·
The XRL will be parallel to KSL and reasonably close just
north of WKT, and also parallel to, but further away, Tung Chung Line (TCL) and
Airport Express Line (AEL)
·
The XRL will pass close to the Tung Chung Line (TCL) Nam
Cheong station
·
The XRL will pass under the Tsuen Wan Line (TWL) at Lai Chi
Kok
6.78
Any cumulative effect from KSL would relate to West Kowloon
Cultural District. Whilst predicted
noise levels Lmax at GN1 and GN2, which are located at approx. 31m and
47m from the tracks at WKT, are less than 23dB(A), KSL would be at least 150m
from any potential cultural development.
At this distance low ground-borne noise levels are expected. As such cumulative impact from the Project
and KSL is not anticipated.
6.79
Just north of WKT where the Project will be parallel to KSL,
TCL and AEL, there are no GBNSRs located in proximity to these rail lines. Any cumulative effect is therefore considered
irrelevant. At the point where XRL
diverges from the other lines, GBNSR GN3 is 30m from the nearest XRL track and
approximately 135m from KSL and further from the other lines. Given that the level predicted for GN3 is
28dB(A) Leq,day, it is unlikely that other rail lines would increase
the Leq levels at GBNSRs.
6.80
The nearest GBNSR near TCL Nam Cheong station and the
project alignment is GN11a With the
predicted ground-borne noise level of up to 25dB(A) Leq,night at
GN11a, the cumulative noise levels are therefore unlikely to be over the
criteria, in particular TCL trains would slow down and stop at Nam Cheong
station.
6.81
In Lai Chi Kok, the tracks will pass close to the TWL
tracks. At the intersection, the nearest
GBNSR is GN14a at a distance from XRL of 39m.
However, this GBNSR is 100m from TWL and it is anticipated that the Leq
levels from TWL would be low, especially considering the fact that the
intersection is near Lai Chi Kok station and MTR trains would be at low
speed. Therefore, the operation of TWL
would therefore not add significantly to the ground-borne noise level of less
than 21dB(A) Leq,night at GN14a, as predicted from XRL to the extent of making
the cumulative levels up towards the criteria.
Environmental Monitoring and Audit
Construction Phase
6.82
The predicted ground-borne noise levels comply with the
stipulated daytime noise criteria, except at a few sensitive receivers, where
TBM operation would induce noise levels exceeding the noise criteria of 65
dB(A). Monitoring at the time of TBM
operation is recommended to confirm and monitor the ground-borne noise levels.
6.83
Prior to the final design of the trackform and the extent of
each type of trackform, and after the proposed train in operation outside Hong
Kong, tests of the FDL of the train will be carried out to update the
ground-borne noise prediction and the recommendation on mitigation measures as
necessary.
6.84
The vibration borehole testing will be carried out at two
carefully selected locations along the proposed tunnel alignment prior to the
commencement of construction works to determine the LSR values under certain
geological conditions. This will also
allow updating of the ground-borne noise predictions and the recommendation on
mitigation measures as necessary.
6.85
The construction stage of the Project could also be used to
improve knowledge of the ground vibration conditions. During use of the TBM, the vibration levels
in surrounding buildings will be measured.
By also measuring the FDL of the TBM, the LSR values for some additional
sections of the tunnel will be determined.
This may allow further update of the ground-borne noise level
predictions and, if necessary, a refinement of the trackform design.
6.86
An Environmental Monitoring and Audit (EM&A) programme
is recommended to be developed with details of the EM&A requirements are
provided in a stand-alone EM&A Manual.
Operation Phase
6.87
Prior to the operation phase of the Project, a commissioning
test should be conducted to ensure compliance of the operational ground-borne
noise levels with the EIAO-TM noise criteria.
Details of the test requirements are provided in a stand-alone EM&A
Manual.
Construction Phase
6.88
Construction ground-borne noise assessment has been
conducted to assess the feasibility of TBM tunnelling construction. Prediction results indicated the TBM and PME
induced ground-borne levels at GBNSRs comply with the EIAO noise limit, except
exceedance predicted at four sensitive receivers due to TBM operation. It is however anticipated that the period of
exceedance would be about only two or three days, basing on the TBM daily
progress in LMC. An EM&A programme
and scheduling of works, is recommended to control and monitor the construction
ground-borne level. It is considered that TBM tunnel construction method would
be feasible for the tunnel construction but the operation of TBM during restricted hours should be
governed by the control of CNP under NCO.
Operation Phase
6.89
Ground-borne noise levels have been predicted based on the
maximum operation capacity of railway system.
Assessment results indicated that the predicted ground-borne noise
levels at the GBNSRs generally comply with the stipulated EIAO-TM noise
criteria, and thus no special trackform will be required to meet the
criteria. Low noise trackform will
however be installed at the selected alignment sections to account for the uncertainty
of the FDL and LSR values.
6.90
Low noise trackform will also be installed to minimise the
impact on future development at WKCD.
The Lmax levels at areas within the WKCD site and outside the WKT
boundary will be reduced to levels lower than 25dB(A) in general with the
provision of low noise trackform.
6.91 With the predicted low ground-borne noise levels at the GBNSRs, it is anticipated that there would be no cumulative effect from other rail lines, including KSL, TCL, AEL and TWL.
[1] Transit Noise and Vibration Impact
Assessment. Report No. FTA-VA-90-1003-06
[2] Register No.:
AEIAR-083/2005, KSL GSA 5100 Environmental Impact Assessment & Associated
Services - Environmental Impact Assessment Report
[3] P. M. Nelson. Transportation Noise Reference Book. 1987.
[4] Final Report of High-Speed Ground
Transportation Noise and Vibration Impact Assessment, HMMH Report No. 293630-4