2-1 Territory-wide Site
Search in 2004
2-3 Summary of
Environmental Factors in Site Selection
2-4 Operation Pattern
for “Worst Case” Throughput of 30,000 Chickens plus 3,000 Minor Poultry
2-5 Operation Pattern
for “Normal Case” Throughput of 20,000 Chickens plus 3,000 Minor Poultry
3-1 Hong Kong Air
Quality Objectives for NO2 and TSP
3-2 Background Air
Pollutant Concentrations
3-3 Air Sensitive
Receivers within the Study Area
3-4 Major Odour
Emission Sources and their Characteristics
3-5 ISCST3 Modelling
Assumptions for NO2 Assessment
3-6 Conversion Factor
for Odour Concentration
3-7 ISCST3 Modelling
Assumptions for Odour Assessment
3-10 Assumed Estimated
Odour Emission Rates for PSC
3-11 Predicted NO2
Concentrations at Representative ASRs
3-12 Predicted
Unmitigated 5-Second Average Odour Concentration at Representative ASRs
3-13 Predicted Mitigated
5-Second Average Odour Concentration at Representative ASRs
3-14 Key Assumptions and
Parameters for NO2 Assessment
3-15 Key Assumptions and
Parameters for Odour Assessment
4-1 EIAO-TM Noise
Standards for Construction Activities Undertaken During Non-Restricted Hours
4-2 Basic Noise Levels
(BNLs) in GW-TM
4-3 EIAO-TM Road
Traffic Noise Planning Criteria
4-6 NSRs for Operation
(Traffic) Phase
4-7 Scenarios for
Traffic Noise Assessment
4-8 Major Noise Source
from Mechanical Plant / Equipment Inside Plant Building
4-11 Predicted
Construction Noise Levels (Unmitigated Scenario)
4-12 Summary of Predicted
Traffic Noise Levels
4-13 Predicted Operation
Noise Levels (Unmitigated Scenario)
4-15 Predicted
Construction Noise Levels (Mitigated Scenario with Provision of Quiet PME)
4-17 Predicted Operation
Noise Levels (Mitigated Scenario)
5-2 Estimated Pollutant
Loading and Flow from Sewage
5-3 Estimated Pollution
Loading and Flow from Floor Washing
5-4 Estimated Pollution
Loading and Flow from Delivery Vehicle and Crate Washing
5-5 Estimated Pollution
Loading and Flow from Stunning and Killing
5-6 Estimated Pollution
Loading and Flow from Scalding & De-feathering
5-7 Estimated Pollution
Loading and Flow from Evisceration and Carcass Cleaning
5-8 Estimated Pollution
Loading from All Individually Identified Sources of Wastewater
5-10 Design Requirement
from WTFs
5-11 Wastewater Reduction
Measures and Impact on WTF
5-12 Wastewater Strength
and Loading Discharged to Foul Sewer Leading to SWHSTW
6-2 DAF Performance
with Chemical Precipitation
6-3 Effluent from DAF
Treatment Discharged to Sewer
6-4 Responsibilities
for Sewerage and Sewage Treatment Infrastructure
7-1 Estimated Solid Waste Arisings
from the Slaughter of 33,000 birds/day
7-2 Estimated Overall Waste Arisings
8-1 Conceptual Model
for the Site
9-1 Hierarchy of
Control and Control and Prevention Measures Adopted
10-1 The Significance
Threshold Matrix
10-3 LR1 – Sensitivity to
Potential Change
10-4 LR2 – Sensitivity to
Potential Change
10-5 LR3 – Sensitivity to
Potential Change
10-6 LR4 – Sensitivity to
Potential Change
10-7 LCA1 – Sensitivity
to Potential Change
10-8 LCA2 – Sensitivity
to Potential Change
10-9 LCA2 – Sensitivity
to Potential Change
10-10 LCA2 – Sensitivity to
Potential Change
10-11 LCA5 – Sensitivity to
Potential Change
10-12 Impacts on Landscape
Resources
10-13 Impacts on Landscape
Character Areas
10-14 VSR1 – Sensitivity to
Potential Change
10-15 VSR2 – Sensitivity to
Potential Change
10-16 VSR3 – Sensitivity to
Potential Change
10-17 VSR4 – Sensitivity to
Potential Change
10-18 VSR5 – Sensitivity to
Potential Change
10-19 VSR6 – Sensitivity to
Potential Change
10-20 Impacts on Visually
Sensitive Receivers Before Mitigation
10-21 Residual Impacts on
Landscape Resources
10-22 Residual Impacts on
Landscape Character Areas
10-23 Residual Impact on
Visual Sensitive Receivers
PHOTOGRAPHS |
2-1 View to the South –
Hung Kiu San Tsuen
2-2 View to the West –
Site Entrance and Man Kam To Road
2-3 View to the East –
Hills Surrounding the Site Creating a “Bowl” Effect
2-4 View to the North –
Concrete Batching Plant (Abandoned)
7-1 Existing Poor
Condition of the Hardstanding within the Site
8-1 Aerial Photograph –
February 2006
8-2 Aerial Photograph –
April 2005
8-3 Aerial Photograph –
August 2000
8-4 Aerial Photograph –
July 1995
8-5 Aerial Photograph –
September 1990
8-6 Aerial Photograph
(partial) – September 1985
8-7 Aerial Photograph –
September 1979
8-8 Aerial Photograph
(partial) – December 1973
8-9 Aerial Photograph–
October 1961
8-10 Aerial Photograph –
December 1956
8-11 Aerial Photograph –
November 1945
10-1 LR1 – Scrubland and
Grassland
10-3 LR3 – Urban /
Developed Area
10-5 LCA1 – Urban /
Developed Area
10-8 VSR1 – View from
Open Storage Area
10-9 VSR2 – View from
Graveyard 1
10-10 VSR3 – View from Man
Kam To Road 1
10-11 VSR4 – View from Man
Kam To Road 2
10-12 VSR5 – View from Hung
Kiu San Tsuen
10-13 VSR6 – View from Graveyard
2
ABBREVIATIONS |
A |
AADT |
Annual average daily
traffic |
AFCD |
Agriculture, Fisheries
and Conservation Department |
|
AGR |
Agriculture
(designation on OZP) |
|
ANL |
Acceptable Noise Levels |
|
APCO |
Air Pollution Control
Ordinance |
|
AQO |
Air Quality Objectives |
|
ArchSD |
Architectural Services
Department |
|
ASR |
Area Sensitivity Rating |
|
ASRs |
Air Sensitive Receivers |
|
B |
BATBREF |
Reference Document on Best Available Techniques [in Slaughterhouse and
Animal By-products Industries, EU, May 2005 |
BNL |
Basic Noise Level |
|
BOD |
Biological Oxygen
Demand |
|
BPM |
Best Practicable Means |
|
C |
CAP |
Contamination
Assessment Plan |
CAR |
Contamination
Assessment Report |
|
CEDD |
Civil, Engineering and
Development Department |
|
C&D |
Construction & Demolition (Material) |
|
CIBSE |
Chartered Institution of Building Services Engineers ( |
|
CNP |
Construction Noise Permit |
|
COD |
Chemical Oxygen Demand |
|
CSWWM |
Cheung Sha Wan Wholesale Market |
|
CSWPWM |
Cheung Sha Wan Poultry Wholesale Market |
|
CRTN |
Calculation of Road Traffic
Noise, published by the Department of |
|
CWTC |
Chemical Waste Treatment Centre |
|
D |
DA-TM |
Technical Memorandum on
Noise from Construction Work other than Percussive Piling |
DAF |
Dissolved Air Flotation |
|
E |
EB |
Environment Bureau |
EIA |
Environmental Impact
Assessment |
|
EIAO |
Environmental Impact Assessment Ordinance |
|
EIAO-TM |
Environmental Impact
Assessment Ordinance Technical Memorandum |
|
EM&A |
Environmental
Monitoring and Audit |
|
EMP |
Environmental
Management Plan |
|
EN13725 |
European Standard Method for Dynamic Olfactometry |
|
EP |
Environmental Permit |
|
EPD |
Environmental
Protection Department |
|
ER |
Emission Rate (for
Odour) |
|
ESB |
EIA Study Brief |
|
ET |
Environmental Team |
|
ETWB |
Environment, Transport and Works Bureau (forerunner of EB) |
|
F |
FAO |
Food and Agriculture
Organisation (of the United Nations) |
FEHD |
Food and Environmental
Hygiene Department |
|
FHB |
Food and Health Bureau |
|
G |
GB |
Green Belt (designation
on OZP) |
GFA |
Gross Floor Area |
|
G/IC |
Government /
Institutional / Community (designation on OZP) |
|
GP-VS |
Good Practices on
Ventilation System Noise Control, EPD, 1999 |
|
GW-TM |
Technical Memorandum on Noise from Construction Work other than Percussive Piling |
|
H |
H5N1, H9N2 |
Types of avian
influenza virus, or bird ‘fllu’ |
HKPSG |
|
|
HKSAR |
|
|
HOKLAS |
|
|
HTML |
Hyper Text Markup
Language |
|
HVS |
High Volume Sampler |
|
I |
IEC |
Independent
Environmental Checker |
IFC |
International Finance
Corporation |
|
IND-TM |
Technical Memorandum for the Assessment of Noise from Places other
than Domestic Premises, Public Places or Construction Sites |
|
ISCST3 |
Industrial Source Complex Short-Term (air pollution model) developed by USEPA |
|
L |
LandsD |
Lands
Department |
LCA |
Landscape
Character Areas |
|
LIA |
Landscape
Impact Assessment |
|
LR |
Landscape Resources |
|
M |
mAG |
Metres Above Ground |
MBR |
Membrane Bio-Reactor |
|
MSW |
Municipal Solid Waste |
|
mPD |
Meters per Datum |
|
N |
NCO |
Noise Control Ordinance |
NENT |
Northeast New Territories
(Landfill) |
|
NO2 |
Nitrogen dioxide |
|
NOX |
Nitrogen oxides |
|
NSRs |
Noise Sensitive Receivers |
|
O |
OWTF |
Organic Waste Treatment
Facility |
OS |
Open Storage
(designation on OZP) |
|
OU |
Odour Unit or Other
Specified Use (designation on OZP) |
|
OZP |
Outline Zoning Plan |
|
P |
PHI |
Potentially
Hazardous Installation |
PlanD |
Planning Department |
|
PME |
Powered Mechanical
Equipment |
|
PNL |
Predicted Noise Level |
|
PolyU |
|
|
PPE |
Personal Protective
Equipment |
|
PP-TM |
Technical Memorandum on
Noise from Percussive Piling |
|
ProPECC |
Practice Note for
Professional Persons |
|
PSC |
Poultry Slaughtering Centre (this Project) |
|
R |
RAP |
Remediation Action Plan |
RCV |
Refuse Collection
Vehicle |
|
RR |
Remediation Report |
|
S |
SBR |
Sequencing Batch
Reactor |
SIA |
Sewerage Impact
Assessment |
|
SO2 |
|
|
SP |
Specified Process |
|
SPS |
Sewage Pumping Station |
|
SS |
Suspended Solids |
|
SSWTW |
Sheung Shui Water Treatment Works |
|
SWHSTW |
Shek Wu Hui Sewage Treatment Works |
|
STT |
Short-term Tenancy |
|
SWL |
Sound Power Level |
|
T |
T&C |
Testing and
commissioning |
TC |
Technical Circular |
|
TD |
Transport Department |
|
TM |
Technical Memorandum |
|
TPO |
Town Planning Ordinance |
|
TRA |
Tree Removal
Application |
|
TSP |
Total Suspended Particulates |
|
U |
USDA |
United States
Department of Agriculture |
USEPA |
United States Environmental Protection Agency |
|
V |
V |
Village-type
Development (designation on OZP) |
VIA |
Visual Impact
Assessment |
|
VOCs |
Volatile Organic Compounds |
|
VSRs |
Visual Sensitive Receivers |
|
W |
WBTC |
Works Bureau/Branch
Technical Circular |
WCZ |
Water Control Zone |
|
WHO |
World Health
Organisation |
|
WMP |
Waste Management Plan |
|
WPCO |
Water Pollution Control
Ordinance |
|
WPCO-TM |
Technical Memorandum on
the Water Pollution Control Ordinance |
|
WQO |
Water Quality
Objectives |
|
WSRs |
Water Sensitive Receivers |
|
WTF |
On-site Wastewater Treatment Facilities |
|
1.1.1 In order to pursue the goal of segregating live poultry and the population so as to minimise the risk of an outbreak of avian influenza, the Government of the HKSAR (the Government) has proposed to develop a Poultry Slaughtering Centre (PSC) for terrestrial poultry. A site in Sheung Shui has been identified for the development of the PSC, which will comprise two identical “stalls” that provide for reception of poultry, slaughter, packing and collection.
1.1.2 The PSC is expected to provide freshly slaughtered chickens and a smaller number of freshly slaughtered “minor” poultry, such as pigeons, chukar, guinea fowl, pheasant, etc. The PSC products will cater for market demand for slaughtered poultry, such as from the restaurant trade, fresh provisions shops, wet markets and supermarkets.
1.1.3 The Food and Environmental Hygiene Department (FEHD) in consultation with the Food and Health Bureau (FHB) will oversee the development of the project, whilst Architectural Services Department (ArchSD) is the works department. Hyder Consulting Limited has been engaged by ArchSD to undertake the Environmental Impact Assessment (EIA) in accordance with EIA Study Brief (ESB) No. ESB-163/2007, which was issued by the Environmental Protection Department (EPD) on 15 February 2007 under Section 5(1)(a) of the Environmental Impact Assessment Ordinance (EIAO).
1.1.4 The Government intends to provide the infrastructure and buildings comprising the PSC and will tender out each stall to a private Operator who will be responsible for fitting out the buildings and operating their stall. Under this arrangement, an Environmental Permit (EP) will be applied for, prior to commencement of site formation and construction, and may reference this EIA Report. The two Operators will each be required to meet the operational requirements of the EP.
1.2.1 The purpose of this EIA Study is to provide information on the nature and extent of environmental impacts likely to arise from the construction and operation stages of the Project and related activities taking place concurrently. The information provided by this EIA Study will contribute to the decision on:
§ The overall acceptability of any adverse environmental consequences that are likely to arise as a result of the Project and the associated activities of the Project;
§ The conditions and requirements for the detailed design, demolition/ construction and operation stages of the Project to mitigate against adverse environmental consequences wherever practicable; and
§ The acceptability of residual impacts after the proposed mitigation measures.
1.3 Objectives of the EIA Study
1.3.1 The objectives of this EIA study are to:
§ Describe the Project and associated works together with the requirements for carrying out the Project;
§ Identify and describe elements of the community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including natural and man-made environment and the associated environmental constraints;
§ Give consideration to selecting alternative Project options, sites, layouts, designs and construction methods with a view to avoiding and minimizing the potential environmental impacts;
§ Provide reasons for selecting the preferred option(s) and describe the environmental considerations taken into account in the selection;
§ Identify and quantify key environmental issues/impacts and determine the significance of impacts on sensitive receivers and potential affected uses;
§ Propose mitigation measures so as to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project;
§ Investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
§ Identify, predict and evaluate the residual environmental impacts and the cumulative effects expected to arise during construction and operation stages of the Project in relation to the sensitive receivers and potential affected uses;
§ Identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation stages of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;
§ Investigate the extent of the secondary environmental impacts (if any) that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA Study, as well as the provision of any necessary modification; and
§ Design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.
1.4.1 The EIA Study will address the likely key issues described below, together with any other key issues identified during the course of the EIA Study:
§ Potential air quality impact to nearby air sensitive receivers during construction and operation of the Project;
§ Potential noise impact to nearby noise sensitive receivers during construction and operation of the Project, including night-time operation and off-site traffic noise along Man Kam To Road and Jockey Club Road from Man Kam To Road to Po Shek Wu Road;
§ Potential water quality impact on nearby water sensitive receivers, including Ng Tung River during construction and operation of the Project;
§ Sewerage and Sewage Treatment Implications;
§ Waste arising as a result of the construction and operation of the Project;
§ Potential land contamination from land to be resumed for the Project;
§
Potential landscape and visual
impacts from construction and operation of the Project; and
§ Potential cumulative environmental impacts of the Project, through interaction or in combination with other existing, committed and planned developments in the vicinity of the Project, and that those impacts may have a bearing on the environmental acceptability of the Project.
1.4.2 The EIA Study covers the combined impacts of the Project as well as the cumulative impacts of existing, committed and planned developments in the vicinity of the Project.
1.4.3 The EIA Report has been prepared in accordance with the requirements stipulated in the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM). This covers relevant project information, relevant legislation, existing environmental conditions, assessment criteria and methods, assessment findings and proposed mitigation measures.
1.5.1 The EIA Report is presented in two volumes. Volume I (this report) comprises:
§ Section 1: Introduction;
§ Section 2: Project Description;
§ Section 3: Air Quality Impact Assessment;
§ Section 4: Noise Impact Assessment;
§ Section 5: Water Quality Impact Assessment;
§ Section 6: Sewerage and Sewage Treatment Implications;
§ Section 7: Waste Management Implications;
§
Section 8: Assessment of
§ Section 9: Human Health Risk;
§
Section 10:
Landscape and Visual Impact Assessment;
§ Section 11: Environmental Outcomes;
§ Section 12: Environmental Monitoring and Audit Requirements; and
§ Section 13: Conclusion and Recommendations.
1.5.2 Volume II contains figures and appendices. The five appendices contain further information relating to air quality modelling; noise modelling; an excerpt from the Draft EIA for Proposed Cheung Sha Wan Wholesale Market Complex; the tree survey; and the project implementation schedule. A stand-alone EM&A Manual has also been prepared, and the entire EIA is summarised in a separate, bi-lingual Executive Summary.
|
Impact of Avian Influenza Outbreaks
2.1.1
Avian Influenza (such as H5N1,
H9N2, etc.) is a type of influenza A, known previously to infect poultry only.
In
2.1.2
In early 2004, there were
extensive outbreaks of Avian Influenza in over 10 countries or places in
2.1.3 Although Human-to-Human transmission is inefficient, all influenza viruses have the ability to change genetically, and scientists are concerned that the H5N1 virus could one day be able to spread easily from one person to another.
2.1.4 On 2 April 2004, the Administration briefed the Panel on Food Safety and Environmental Hygiene of the Legislative Council (the Panel) on the public consultation paper on "Prevention of Avian Influenza: consultation on long term direction to minimise the risk of human infection". Apart from enhanced surveillance and monitoring measures put in place to prevent Avian Influenza outbreaks in local farms and wholesale/retail markets, the Administration informed the Panel that, for the protection of public health, the present mode of operation of the live poultry trade would have to be modified. It was the policy to separate humans from live poultry and to minimise the contact between the public and live poultry. The Administration considered that the development of a PSC is the long-term measure to reduce the risk of human infection of H5N1.
Current Situation – the Need for the Project
2.1.5
To prevent Avian Influenza
outbreaks in
2.1.6 Notwithstanding, the presence of live poultry at wholesale/retail markets increases the risk of human infection. When the PSC comes into operation, the sale of live poultry at the Cheung Sha Wan Temporary Wholesale Poultry Market and at all retail outlets will no longer continue.
2.1.7
Avian influenza is now a global
issue – according to the WHO [Ref.[1]] as of 2 June 2009, a total of 433 human cases and 262 deaths have
been reported world-wide, many in
Absence of the Project
2.1.8 If the Project were not to go ahead then the current practice of poultry slaughtering in wet markets and other smaller facilities would continue. The public would continue to be exposed to live poultry and there is a credible public health risk to continuing this current practice.
2.1.9
With avian influenza in wet markets and a chicken farm confirmed in
Hong Kong in June 2008 and December 2008, respectively, and a number of human
cases and deaths reported in
2.1.10
The need for the PSC is
therefore urgent and forms part of Government’s efforts to prevent the
resurgence of avian influenza in
2.2 Consideration of Alternative Locations
2.2.1 Given the activities to be carried out within the PSC and in recognition of the human health issues related to poultry slaughtering, the site for the PSC should:
§ Be located in close proximity to local farms and the boundary with the Mainland;
§ Be distant from major residential areas;
§ Be well-ventilated;
§ Result in minimal environmental impact;
§ Be easily accessible via a well-developed transportation network;
§ Have access to basic infrastructure; and
§ Be available within the timeframe of the project.
Territory-wide Site Search in 2004
2.2.2 In consideration of the above, a number of possible areas were identified for the PSC during an initial site search in 2004. Table 2-1, below, describes the results of this site search exercise.
Area |
Discussion |
Compatibility
with Site Requirements |
Tuen
Mun West |
The
main border crossing at Man Kam To is a considerable distance from this area
and so would result in significant vehicular transport requirements within |
This
area failed to meet the requirements in terms of ease of transport access,
existence of basic infrastructure and availability within the project
timeframe. This
area has been rejected. |
Man
Kam To – in part of the closed border area that may be opened up for future
development |
The
possible opening up of this area is unlikely to be implemented until 2010 and
planning studies to identify appropriate land use have yet to be completed.
Thereafter, infrastructure (such as roads) and utilities (such as water,
electricity, sewage, communications) would need to be provided, which would
take another two and a half years. |
This
area failed to meet the requirements in terms of existence of basic
infrastructure and availability of a suitable site within the project
timeframe. This
area has been rejected. |
Lok Ma Chau |
The area is currently occupied by fishponds and other habitats of high
ecological value. There is little existing infrastructure (in particular for
sewage treatment) and a suitable piece of land available within the timeframe
was not identified |
This area failed to meet the requirements in terms of existence of
basic infrastructure, minimising environmental impact and availability of a
suitable site. This area has been rejected. |
Table 2-1 Territory-wide
Site Search in 2004
Second Site Search in Sheung Shui Area
2.2.3 Following the territory-wide consultation exercise in 2004, a more detailed site search study for the proposed Plant was carried out in Sheung Shui district. This considered the concerns raised by local residents during the consultation.
2.2.4 Two alternative sites were identified, namely Site A (adjacent to Hung Kiu San Tsuen) and Site B (adjacent to Sheung Shui Water Treatment Works – SSWTW, as indicated in Figure 2-1. Table 2-2, below, describes the results of this second site search exercise.
Area |
Discussion |
Compatibility
with Site Requirements |
Site
A – Adjacent to Hung Kiu San Tsuen |
This
open, well-ventilated site is bounded by Man Kam To Road to the southwest,
Hung Kiu San Tsuen to the south and vegetated areas to the east and north.
The total area is about 13,700m2. Man Kam To Road provides easy
access to the border. The Site is more than 900m from major residential areas
but is adjacent to the small |
The
site has met all of the requirements, although the proximity of Hung Kiu San
Tsuen is a concern. Notwithstanding,
this site is considered acceptable. |
Site
B – Adjacent to Sheung Shui Water Treatment Works |
This
site is about 13,000m2 in area and is bounded by the Sheung Shui
Water Treatment Works (SSWTW) to the southwest and small hills on all other
sides. The small hills form a natural shelter separating the site from nearby
dwellings. The site is rectangular and is about 1,600m from Tsung Pak Long
and 950m from Sheung Shui Heung. Access to the site is by way of a 300m long
x 11m wide side road leading from Man Kam To Road, but this would need upgrading.
The travelling distance to |
This
site failed to meet the requirements in terms of access (the existing road
needs upgrading), environmental impact (the close proximity of the PHI) and
availability (rezoning will likely take a long time). This
site has been rejected. |
Table 2-2 Sheung
Shui Site Search
Conclusion
2.2.5 Areas in Tuen Mun West, Man Kam To and Lok Ma Chau were examined but were rejected on various grounds. The part played by environmental factors in the rejection of these areas included transportation distance (Tuen Mun West), availability of sewage treatment infrastructure (all areas) and ecological impact (Lok Ma Chau), and is summarised in Table 2-3.
2.2.6 Two sites, Site A and Site B, were subsequently identified in Sheung Shui. Upon closer examination, Site A was found to meet all requirements for siting the PSC, however, the close proximity of Hung Kiu San Tsuen is a concern that will need to be addressed by the design of the PSC and of mitigation measures, especially those relating to noise and odour.
2.2.7 Upon closer examination, Site B was rejected on various grounds. The part played by environmental factors in the rejection of Site B was primarily the hazard to life risk posed by the close proximity of SSWTW, which is a PHI by virtue of chlorine storage, and is summarised in Table 2-3. The preferred site, Site A, is described in more detail in the following sections.
|
Potential Site / Area |
||||
Environmental Factors |
Tuen Mun West |
Man Kam To CBA |
Lok Ma Chau |
Sheung Shui Site “A” |
Sheung Shui Site “B” |
Air |
û |
|
|
|
|
Noise |
û |
|
|
|
|
Water/Sewage |
û |
û |
û |
|
|
Waste |
|
|
|
|
|
Ecology |
|
|
û |
|
|
Landscape & Visual |
|
|
|
|
|
Hazard |
|
|
|
|
û |
Other* |
û |
û |
û |
|
û |
Overall |
û |
û |
û |
ü |
û |
Note: “ü” indicates acceptance and “û” indicates rejection on environmental grounds for
each site / area
* See explanation in Tables 2-1 and 2-2.
Table 2-3 Summary
of Environmental Factors in Site Selection
2.3 Consideration of Alternative Construction Methods and Sequences of Works
Alternative Construction Methods
2.3.1 The method by which the PSC will be constructed has not been examined in detail, since the detailed design and construction of the PSC will be carried out under separate arrangement at a later stage.
2.3.2 However, for the purpose of this EIA, it is reasonable to assume that conventional construction methods and plant will be used for the construction works. Construction involves standard site formation/earthworks; utilities laying and connections; building foundations; asphalt laying; and superstructure construction.
2.3.3
These standard construction
methods, including excavation by backhoe, piling and/or laying of foundation
slabs, reinforced concrete frame building using formwork, external cladding,
etc. are all well established in
2.3.4 With the implementation of appropriate mitigation measures and good site management practices, as described in Sections 3.7, 4.8 and 5.7, the proposed standard construction methods will not cause adverse environmental impacts. For this reason, it is unlikely that alternative construction methods will achieve any significant reduction in environmental impacts.
2.3.5 Notwithstanding, the following alternative construction methods have been considered:
§ Off-site Fabrication can reduce on-site environmental impacts (dust, noise, waste generation, etc.) by pre-fabricating repetitive elements of the building – it is often used in the construction of tower blocks. Considering the environmental benefits and dis-benefits of off-site fabrication, and the lack of significant repetition within the simple design of the PSC, it is unlikely that off-site fabrication will offer any environmental advantage and so is not recommended for further consideration.
§ Piling is unlikely, given the current design direction of the PSC. However, if piling is required, then percussive piles and socketted H-piles can be considered. Percussive piles would cause substantial noise and vibration impacts, particularly at the adjacent Hung Kiu San Tsuen, whereas the noise and vibration impacts from the use of socketted H-piles would be significantly lower. Considering the environmental benefits and dis-benefits of the alternative piling methods, in the unlikely event that piling is required then socketted H-piles are recommended.
§ Quality Powered Mechanical Equipment (QPME) are Powered Mechanical Equipment (e.g. backhoes, bulldozers, generators, etc.) that are relatively quiet and environmentally friendly, often meeting EU Directive 2000/14/EC or other equivalent standards. Although for reasons of worst case assessment the EIA has not assumed QPME will be used, it is recommended that the Works Contractor should support EPD’s QPME initiative and use QPME for this Project, particularly given the proximity of Hung Kiu San Tsuen.
Sequence of Works
2.3.6 The following alternative sequences of construction were considered.
§ Concurrent Construction involves various construction activities occurring at the same time. The environmental benefit of this construction sequence would be the reduction of the construction period and hence the duration of impact due to the construction. However, the magnitude of the overall environmental impact could be significant.
§ Phased Construction involves construction activities being carried out sequentially, one followed by another. This construction sequence would help reduce the magnitude of the overall impacts, but the construction period would be longer.
2.3.7 As the two approaches have their environmental benefits and disbenefits, a balanced approach involving both concurrent and phased construction in different stages of construction is recommended. This will enable the short timeframe for construction to be met (see Section 2.7), yet will also minimise the impact at sensitive receivers, such as Hung Kiu San Tsuen.
2.3.8 It will be the responsibility of the future Designer / Works Contractor to sequence the construction works appropriately to meet the target completion date, while also minimising the duration and magnitude of environmental impacts.
2.4 Preferred Scenario – Project Description
Location – Planning Context
2.4.1 The location of this site is shown in Figure 2-2. The site is bounded by Man Kam To Road to the southwest, Hung Kiu San Tsuen to the south and vegetated areas to the east and north. The total area is about 12,791m2.
2.4.2
The site comprises three small
areas i.e. two former Short-term Tenancies (STTs) and a site zoned for a Petrol
Fuel Station. STT 1118, a fee-paying public vehicle park, has expired, while
STT 1363 for car-repairing and open-storage, was terminated on 27 February
2009. Basic infrastructure, such as water and
electricity supply is readily available.
2.4.3 The Site is Government land, which currently falls partly in an area zoned “Open Storage” and partly in an area zoned “Other Specified Uses” annotated “Petrol Filling Station” on the Fu Tei Au and Sha Ling Outline Zoning Plan No. S/NE-FTA/10 (hereafter called the “OZP”).
2.4.4
The Site is situated adjacent
to Man Kam To Road, which is the main access road to/from the border area and
so provides direct vehicular access to/from the border crossing, which is
approximately 2km from the Site. The site is about 1,800m from Tsung Pak Long
and 950m from Sheung Shui Wan Shan. The travelling distance to/from
2.4.5
While the Site is more than
900m from major residential areas, to the immediate south of the site there are
dwellings – the small
2.4.6
Government
will initiate a re-zoning of the OZP to make it permissible for the site to be
used for developing the PSC.
Location – Physical Environment
2.4.7
The
surroundings of the site are mostly open carparks, open storage yards and
vehicle-repair workshops.
2.4.8
The
small
Photograph 2-1 View to the South – Hung Kiu San Tsuen
Photograph 2-2 View to the West – Site Entrance and Man Kam To Road
Photograph 2-3 View to the East – Hills Surrounding the
Site Creating a “Bowl” Effect
Photograph 2-4 View to the North – Concrete Batching
Plant (Note Sign Indicating that Operation
of the Plant Has Ceased)
Site History
2.4.9 Prior to its recent use as a fee-paying public vehicle park, the site was used for light industry and storage. Section 8 discusses the previous uses of the Site.
Scope of Project
2.4.10 The PSC will be a single-storey building with part of the supporting mechanical plant on the rooftop. As shown in Figure 2-3, two “stalls” (the main building) will each comprise loading/unloading areas; crate cleaning and storage areas; holding, killing, scalding, evisceration, packing and storage areas; isolation and inspection areas; changing rooms; and offices. At one end of the building will be a shared truck disinfection area. In addition to the main building, separate ancillary buildings will also be constructed, including an office, wastewater treatment facilities (WTFs), E&M plant rooms; fuel storage tanks and generators. As shown in Figure 2-4, the related supporting mechanical plant, such as boiler rooms, odour removal system and air handling units for each stall will be placed on the centre area of the rooftop.
2.4.11 As shown in Figure 2-5, which shows Section A-A from Figure 2-3, the PSC site will be formed into a series of flat platforms, rising from 13.7mPD at the boundary with Man Kam To Road to a maximum elevation of 22.1mPD. The maximum external elevation of the main building will be 10m, with an exhaust point 3m above this (i.e. at 13m). The maximum external elevation of the WTF building will be 6m, with an exhaust point 7m above this (i.e. at 13m). As shown in Figure 2-6, the main building will cover an area of approximately 5,545m2 and together with the ancillary buildings, the total site coverage will be some 7,095m2.
2.4.12 Under normal circumstances, the estimated daily throughput of the PSC will be about 20,000 chickens, however, to respond to market demands during festive periods (which occur only a few times annually, each lasting for not more than seven days), the daily maximum slaughtering capacity of the PSC will be increased to 30,000 chickens – this is considered to be the “worst case” scenario and will be used as the basis for assessment. Manual slaughtering of minor poultry will also take place, with a maximum slaughtering capacity of 3,000 minor poultry per day, in addition to the chickens. The PSC is anticipated to operate all year around.
Construction of the PSC Infrastructure by Government
2.4.13 The detailed design and construction of the PSC will be carried out under separate design and construction contracts. The poultry slaughtering machines will be provided by the Operators according to their needs. The anticipated construction activities will comprise:
§ Clearance of all vegetation within the Site;
§ Site formation and piling and drainage provisions;
§ Construction of the PSC main building and ancillary buildings, as detailed in Figures 2-3 and 2-4;
§ Provision of air-conditioning and ventilation system (with negative pressure maintained inside the PSC);
§ Provision of odour removal system;
§ Provision of the WTFs; and
§ Provision of fuel tanks and emergency generators.
Fit-out and Operation of the PSC by Operators
2.4.14 Upon completion of building construction, the two stalls will be ready for occupation by the Operators, who will be responsible for fit-out. While it is possible that the Operators will choose to fit a fully automated slaughtering line, it is also possible that the Operators will opt for manual slaughtering, or semi-automated slaughtering. Each will have different environmental impacts in terms of air, noise, water and waste.
2.4.15 For the purpose of assessment, therefore, this EIA has assumed the worst-case impacts in each case, whether this is from manual, semi-automated or fully automated processes. Details and justifications are provided in the relevant sections of this report.
2.5 Poultry Slaughtering
2.5.1 Daily operation of the stalls will be the responsibility of the Operators, and will be in accordance with the Operators’ own procedures. However, based on the best available information the following is anticipated (see Figure 2-7):
Reception / Holding
2.5.2 Vehicles with crates of live poultry coming from the Mainland, and with crates of live poultry from local farms will enter the PSC site through a dedicated “dirty” access route on the western side of the site. Crates will be unloaded at the unloading platform and moved into the holding area. After unloading, vehicles will pass through a disinfection area where they will be thoroughly cleaned before leaving the PSC through a dedicated “clean” route on the eastern side of the site.
2.5.3
Poultry shall not have access
to any type of food for about 6 to 10 hours prior to slaughter. This will
prevent the presence of food in the digestive
tract when this part is removed, thus risking to soil
the product. However, access to drinking water during transport and/or holding
in the PSC is advisable to ensure that the chickens do not suffer unnecessarily.
2.5.4
Cages of live poultry will be
stacked column by column. Each column will contain 10 layers of cages. The
height of each cage is about 25cm, so each column will be around 2.5m high. The
holding area will be air-conditioned and maintained at 23OC. Wall/ceiling mounted fans will
improve air circulation.
2.5.5
Swab tests and blood tests of
Mainland poultry will be carried out prior to slaughter. For each batch, blood
test result takes 1.5 hours and swab test results takes 4 hours, therefore
slaughtering cannot start for minimum of 4 hours after delivery. Any diseased
poultry that are identified will be placed in an isolation area and will be
destroyed and disposed of appropriately.
Killing / Bleeding
2.5.6 Poultry will be removed from the crates in the holding area and brought into the killing room, which will be maintained at 25OC. Empty crates will be taken to the crate cleaning area and disinfected using crate cleaning machine. Clean crates will be stored in the crate store and loaded back onto disinfected vehicles.
2.5.7 The head of the poultry is positioned downward so that the blood can flow down easily, preferably in such a way that the rest of the body is well secured. For example, the poultry can be placed head-first into an appropriately sized cone or funnel with a hole in the bottom to get access to the head to apply the bleeding cut. This would prevent the wings from flapping thus preventing blood from splashing on the wing tips afterwards. It is important to try to drain as much of the blood as possible, without causing damage to the body.
2.5.8 The best method and most humane way to kill poultry is to render the poultry unconscious prior to neck cutting. The carotid arteries and jugular veins will then be cut with a sharp knife so that blood is drained from the head quickly. Approximately two minutes of draining should be allowed to get the best possible bleeding out.
Scalding and De-feathering
2.5.9 Scalding involves passing the poultry through hot water after slaughter. This is done to prepare the epidermis (upper skin) such that the feathers come off more easily when plucked – specifically, scalding opens up the follicle in which the shaft of the feather is held.
2.5.10 The bled poultry is taken to the scalding room, which will be air-conditioned and maintained at 25OC. It is immersed in scalding tanks (maintained at about 60OC) for approximately one minute to loosen the feathers.
2.5.11 Plucking is started immediately after the scalding, otherwise the effect of scalding is lost as the poultry begins to stiffen. A de-feathering machine will be used to remove the feathers prior to evisceration. Typical de-feathering machines will operate at a rate of 100 birds/hour. Some manual plucking may be needed as de-feathering machines are rarely able to remove 100% of feathers. Each plucked poultry will be thoroughly washed by water jet or spray before evisceration.
Evisceration and Cleaning
2.5.12 Evisceration basically means removing everything inside the body cavity. During evisceration, the plucked poultry can be put on a table, however, this presents a risk of cross-contamination. It is therefore of the utmost importance that this table is cleaned thoroughly and preferably after each evisceration. Alternatively, suspended shackles could be used for evisceration.
2.5.13 The plucked poultry is taken to the evisceration room and laid on the table or shackled, as appropriate. The evisceration room will be air-conditioned and maintained at 23OC.
2.5.14 The neck skin is cut and split down the back and a second cut made at the base of the neck. The oesophagus, trachea and crop are separated from the neck skin. They can be cut off or left attached and be pulled from the body with the viscera.
2.5.15 The body cavity is opened by making a cut near the vent and extending the cut around the vent. Care must be taken not to cut the intestine to avoid the carcass being soiled with faecal material. All knives must be disinfected in 82OC hot water when used between carcasses.
2.5.16 When the abdomen is opened the viscera are removed through the opening. It is very important to remove all the viscera, including the lungs, which are attached to the back. For this, the incision in the skin around the vent should be big enough to allow the entrance of a worker’s gloved hand to remove the lungs properly – this may take some force to remove.
2.5.17 When all the contents of the cavity have been removed the carcass should be thoroughly washed using a water jet.
2.5.18 After the viscera have been inspected, the heart, liver and gizzard (stomach) are separated and saved, if required – they should be handled and washed at a separate area where the carcasses are rinsed. The ends of any parts of the vascular system that may still be attached to the heart are removed by trimming off the top to expose the chambers. The heart is washed and squeezed to force out any remaining blood. The green gall bladder is carefully trimmed away from the liver, avoiding any damage that could cause leakage of the green liquid within – this will not only spoil the way the product looks, but it also has a bitter taste.
2.5.19 Next the gizzard is split lengthwise and the contents washed away. The lining is then peeled away from the rest of the gizzard. Edible offal is further cleaned and the remains are discarded.
2.5.20 A post-mortem inspection area is located adjacent to the evisceration area to allow inspection of carcasses and viscera as needed.
Packing and Collection
2.5.21
The packing room will be
air-conditioned and maintained at 15OC. The carcass is packaged
(e.g. placed in an unsealed plastic bag) and labelled. The product is stored on
shelves in the cold store below 7OC, awaiting collection. Edible viscera after thorough washing, should be packed and labelled in separate area and stored immediately under
–18OC.
2.5.22
Collection vehicles will enter and leave the PSC site through the dedicated “clean” route on the eastern side of the site. Poultry
products will be loaded onto refrigerated vehicles, which will then distribute
the poultry products throughout
2.6.1 Two operation patterns have been prepared – one representing the normal throughput of 20,000 chickens plus 3,000 minor poultry (i.e. 23,000 poultry), and one representing the “worst case” throughput of 30,000 chickens plus 3,000 minor poultry (i.e. 33,000 poultry). Table 2-4, below, shows the operation pattern for the “worst case” throughput of 33,000 poultry – this has been prepared based on best available information, however, the actual operation pattern may vary, subject to requirements of future Operators. All assessments in this EIA are based on this “worst case” throughput, however, for comparison purposes only, Table 2-5, below, shows the operation pattern for the normal throughput of 23,000 poultry.
Worst
Case Throughput of 33,000 Poultry
2.6.2 Vehicles with crates of live poultry coming from the Mainland will arrive at the PSC between 10am and 6pm to unload 15,000 chickens plus 3,000 minor poultry. An average of 1,600 poultry per vehicle has been assumed, which represents about 80% capacity of each vehicle. A total of 12 no. vehicles has been calculated to arrive between 10am and 4pm but this could be up to 14 or more, depending on the packing capacity. Notwithstanding, a maximum of three vehicles per hour will arrive during the peak hours of midday to 2pm.
2.6.3 Vehicles with crates of live poultry from local farms will arrive at the PSC between 7pm and midnight to unload 15,000 chickens. An average of 800 poultry per vehicle has been assumed, which represents about 80% capacity of each vehicle. A total of 19 no. vehicles will arrive between 7pm and midnight. A maximum of nine vehicles will arrive during the 9pm peak hour. Sufficient unloading bays will be provided for delivery vehicles and off-site queuing is not anticipated.
Time |
Mainland Poultry
Arrival |
Local Poultry
Arrival |
No. Delivery
Vehicles |
Poultry in
Holding Area |
Poultry
Slaughtered |
Poultry in Cold
Store |
Poultry
Collected |
No. Collection
Vehicles |
Remarks |
10:00 - 11:00 |
3,000 |
|
2 |
3,000 |
|
|
|
|
First batch from
Mainland arrives |
11:00 - 12:00 |
3,000 |
|
2 |
6,000 |
|
|
|
|
|
12:00 - 13:00 |
4,500 |
|
3 |
10,500 |
|
|
|
|
|
13:00 - 14:00 |
4,500 |
|
3 |
15,000 |
|
|
|
|
|
14:00 - 15:00 |
1,500 |
|
1 |
16,500 |
|
|
|
|
Swab results
available from first batch |
15:00 - 16:00 |
1,500 |
|
1 |
18,000 |
|
|
|
|
Last batch from
Mainland arrives |
16:00 - 17:00 |
|
|
|
18,000 |
|
|
|
|
|
17:00 - 18:00 |
|
|
|
18,000 |
|
|
|
|
|
18:00 - 19:00 |
|
|
|
18,000 |
|
|
|
|
|
19:00 - 20:00 |
|
750 |
1 |
18,750 |
|
|
|
|
First batch
of Local Chickens arrives |
20:00 - 21:00 |
|
7,200 |
9 |
23,450 |
2,500 |
|
|
|
Slaughtering
commences |
21:00 - 22:00 |
|
4,800 |
6 |
25,350 |
2,900 |
2,500 |
|
|
|
22:00 - 23:00 |
|
1,500 |
2 |
23,950 |
2,900 |
5,400 |
|
|
|
23:00 - 00:00 |
|
750 |
1 |
21,800 |
2,900 |
8,300 |
|
|
Last batch
of Local Chickens arrives |
00:00 - 01:00 |
|
|
|
18,900 |
2,900 |
11,200 |
|
|
|
01:00 - 02:00 |
|
|
|
16,000 |
2,900 |
14,100 |
|
|
|
02:00 - 03:00 |
|
|
|
13,100 |
2,900 |
17,000 |
|
|
|
03:00 - 04:00 |
|
|
|
10,200 |
2,900 |
19,900 |
|
|
|
04:00 - 05:00 |
|
|
|
7,300 |
2,900 |
18,800 |
4,000 |
2 |
First morning collection
truck arrives |
05:00 - 06:00 |
|
|
|
4,400 |
2,900 |
9,700 |
12,000 |
6 |
|
06:00 - 07:00 |
|
|
|
1,500 |
2,900 |
4,600 |
8,000 |
4 |
|
07:00 - 08:00 |
|
|
|
|
1,500 |
3,500 |
4,000 |
2 |
Slaughtering complete |
08:00 - 09:00 |
|
|
|
|
|
1,000 |
4,000 |
2 |
|
09:00
- 10:00 |
|
|
|
|
|
|
1,000 |
1 |
Last morning collection
truck leaves |
Total |
18,000 |
15,000 |
31 |
|
33,000 |
|
33,000 |
17 |
|
Maximum |
4,500 |
7,200 |
9 |
25,350 |
2,900 |
19,900 |
12,000 |
6 |
|
Note:
Indicates 3-hour Cleansing Period; indicates
Mainland delivery vehicle arrival window; indicates
local delivery vehicle arrival window
Time |
Mainland Poultry
Arrival |
Local Poultry
Arrival |
No. Delivery
Vehicles |
Poultry in
Holding Area |
Poultry
Slaughtered |
Poultry in Cold
Store |
Poultry
Collected |
No. Collection
Vehicles |
Remarks |
10:00 - 11:00 |
1,600 |
|
1 |
1,600 |
|
|
|
|
First batch from
Mainland arrives |
11:00 - 12:00 |
3,300 |
|
3 |
4,900 |
|
|
|
|
|
12:00 - 13:00 |
3,300 |
|
3 |
8,200 |
|
|
|
|
|
13:00 - 14:00 |
3,200 |
|
2 |
11,400 |
|
|
|
|
|
14:00 - 15:00 |
1,600 |
|
1 |
13,000 |
|
|
|
|
Last batch from
Mainland arrives |
15:00 - 16:00 |
|
|
|
13,000 |
|
|
|
|
|
16:00 - 17:00 |
|
|
|
13,000 |
|
|
|
|
|
17:00 - 18:00 |
|
|
|
13,000 |
|
|
|
|
|
18:00 - 19:00 |
|
|
|
13,000 |
|
|
|
|
|
19:00 - 20:00 |
|
750 |
1 |
13,750 |
|
|
|
|
First batch
of Local Chickens arrives |
20:00 - 21:00 |
|
6,250 |
8 |
20,000 |
|
|
|
|
|
21:00 - 22:00 |
|
1,500 |
2 |
21,500 |
|
|
|
|
|
22:00 - 23:00 |
|
750 |
1 |
19,350 |
2,900 |
|
|
|
Slaughtering
commences |
23:00 - 00:00 |
|
750 |
1 |
17,200 |
2,900 |
2,900 |
|
|
Last batch
of Local Chickens arrives |
00:00 - 01:00 |
|
|
|
14,300 |
2,900 |
5,800 |
|
|
|
01:00 - 02:00 |
|
|
|
11,400 |
2,900 |
8,700 |
|
|
|
02:00 - 03:00 |
|
|
|
8,500 |
2,900 |
11,600 |
|
|
|
03:00 - 04:00 |
|
|
|
5,600 |
2,900 |
14,500 |
|
|
|
04:00 - 05:00 |
|
|
|
2,700 |
2,900 |
|