Home  |    Print

 

10.                        ENVIRONMENTAL OUTCOMES

 

10.1                    Justification and Benefits of the Project

 

10.1.1              The need for the Project has evolved from the requirement to provide a secure water supply to Cheung Chau. Specifically, it has been determined that the existing water main serving as emergency backup is approaching its design life of 50 years. There will be increasing risk of having one water main under maintenance while another main has to be taken out of service without warning.

 

10.1.2              Being the only water supply to Cheung Chau, it is necessary to lay a new submarine water main from Lantau to Cheung Chau to maintain the reliability of water supply to Cheung Chau. The consequences of not proceeding with the Project will be serious interruption of water supply to Cheung Chau in the event the current water main is taken out of service unexpectedly.

 

10.1.3              The estimated population expected to be directly benefited by the Project will be the residents of Cheung Chau of about 23,000 as well as the tourists visiting Cheung Chau.

 

10.2                    Population and Environmental Sensitive Areas Protected

 

10.2.1              With the adoption of Horizontal Directional Drilling (HDD) and forward reaming, the main staging area of the Project will be located in Cheung Chau which has less ecological impact. Equipment and works area in Lantau is significantly minimized thereby avoiding impacts to Lantau South Country Park.

 

10.2.2              No marine works will be required with the use of HDD in laying the water main. The seabed of Adamasta Channel will not be disturbed. As such, impacts to Cheung Sha Wan Fish Culture Zone, fish spawning / nursery grounds, as well as fishing activities in the area will be avoided. Likewise, marine traffic along Adamasta Channel will not be affected during construction phase.

 

10.2.3              By adopting HDD, no marine sediment will need to be dredged and disposed thus reducing the burden on marine dumping sites. The associated water quality impacts from dredging and disposal of marine sediment can be avoided, thus avoiding adverse impacts to the marine environment.

 

10.2.4              The works site at Cheung Chau will utilize the existing works compound at Tai Kwai Wan, thereby minimising the need to secure additional land. The need for site formation can also be greatly reduced by using the already formed works compound. The works site will avoid the nearby sandy and rocky shores within the Coastal Protection Area zone.

 

10.2.5              A number of trees in the works area at Cheung Chau will be preserved in-situ by adjusting the works boundary. No trees will be affected in Lantau.

 

10.2.6              With the use of quiet plant and temporary noise barrier, residents near the works area at Cheung Chau will be protected from excessive construction noise.

 

10.2.7              Ultimately, all the residents of Cheung Chau will be directly benefited as a result of the Project in terms of a more secure and reliable water supply.

 

10.3                    Environmental Friendly Designs Recommended

 

10.3.1              The principle of using HDD instead of conventional dredging technique in laying the submarine water main is to avoid environmental impacts while at the same time to provide cost effective, maintenance free solution for a secure and reliable water supply to Cheung Chau. Views and comments from the Green Groups, District Council members and fishermen association obtained during public consultation have also been taken into consideration in the design.

 

10.3.2              When considering environmental impacts, minimization will be the key design principle only when avoidance is not possible. The following environmental friendly designs have been incorporated into the Project.

 

·                  A small temporary working platform using steel decking or wooden scaffolding will be erected in Lantau to provide a suitable working area for retrieving the water pipe and connection. Such platform can minimize the need for site formation, thereby avoiding adverse impact to the nearby natural coast.

 

·                  The length of the exposed main at Lantau will be redcued as much as possible. The exposed main at Lantau will be shielded with nearby rocks and boulders in order to blend in with the surrounding coastal environment. The use of concrete structure will be minimized as far as practicable.

 

·                  The launching site at Cheung Chau has been located on site currently being used by other project and on disturbed or developed land. The site can be set-up with minimal site formation.

 

·                  By using HDD, marine sediment dredging and removal works can be avoided thus minimizing impacts to water quality and ecological sensitive receivers.

 

·                  The site boundary at Cheung Chau has been modified to retain as much trees as possible.

 

·                  Water instead of bentonite will be used as drilling fluid in the final bore stage at Lantau landfall to minimize potential water quality impact.

 

·                  Several tiers of site drainage system will be adopted to totally confine the launching site works area. Adequate numbers of tank, pumps and treatment facilities will be stipulated in the contract document to ensure no site effluent is discharged untreated.

 

10.4                    Key Environmental Problems Avoided

 

10.4.1              The key environmental problems involve water quality, ecological and noise impacts during the construction phase. Minor impact from waste is expected. No operational phase impact is expected from the Project.

 

10.4.2              The EIA study has critically assessed the overall acceptability of environmental impacts which are likely to arise as a result of the construction of the Project. Where necessary and practicable, the EIA study has specified the conditions and requirements for the detailed design and construction of the Project in order to mitigate environmental impacts to an acceptable level.

 

10.4.3              In order to avoid or minimize the environmental impacts of the Project, a number of mitigation measures have been recommended in the EIA report. The key environmental measures and problems avoided are highlighted below.

 

·                  The adoption of HDD will avoid impacts to the marine environment and marine ecological sensitive receivers.

 

·                  Works within Lantau South Country Park have been minimized to an absolute minimum by adopting forward reaming and pipe pushing from Cheung Chau.

 

·                  Properly designed site drainage measures, wastewater treatment systems and good site working practices will be implemented to ensure no adverse water quality impact to the marine waters.

 

·                  During construction, surplus excavated materials will be reused on-site to minimize the amount of off-site disposal to public filling facilities.

 

·                  With the implementation of quiet plant, temporary noise barriers and good site practices, construction noise from construction activities will be reduced to acceptable level. No adverse construction noise impact on the nearby noise sensitive receivers is expected.

 

·                  A comprehensive EM&A programme will be setup to ensure effective implementation of mitigation measures recommended in the EIA report, to assess the effectiveness of the mitigation measures, and to identify any further need for additional measures or remedial actions.

 

10.4.4              The EIA study has demonstrated the acceptability of any residual impacts from the Project and the protection of the Lantau South Country Park, Coastal Protection Areas at Cheung Chau, fish spawning and nursery grounds, fisheries resources, marine habitats, Cheung Sha Wan Fish Culture Zone and other sensitive receivers. Environmental monitoring and audit programme have been recommended before and during construction to verify the expectations of the EIA study and the effectiveness of the recommended mitigation measures.

 

10.5                    Compensation Areas Included

 

10.5.1              No off-site compensation area will be required for this Project.

 

10.6                    Environmental Benefits of Environmental Protection Measures Recommended

 

10.6.1              The environmental benefits of implementing the recommended mitigation measures can be summarized as follows:

 

·                     The water quality and noise impacts at the sensitive receivers will all be minimized or mitigated to within the acceptable criteria and standards.

 

·                     The amount of construction and demolition materials requiring off-site disposal will be minimized through reduction, reuse and/or recycling.

 

·                     The landscape impact from the exposed main will be mitigated through careful selection of landfall location, minimize the use of concrete and use of nearby natural materials such as rocks and boulders to shield and blend in with the surrounding coastal environment.

 

·                     By avoiding dredging or other marine works, marine sediment will not be disturbed, impact on the marine habitat will be avoided.

 

10.6.1              With the implementation of the recommended mitigation measures, no unacceptable residual environmental impacts are expected. Details of the implementation schedule of the recommended mitigation measures are summarized in Appendix 10.

 

 

 Home  |    Print