This section describes the requirements for
environmental monitoring and audit (EM&A) during the construction and operation of the Project. The objectives of carrying out EM&A include the
following:
·
to provide a database against which any short or long term environmental
impacts of the Project can be determined;
·
to provide an early indication should any of the environmental control
measures or practices fail to achieve the acceptable standards;
·
to monitor the performance of the Project and the effectiveness of
mitigation measures;
·
to verify the environmental impacts predicted in the EIA Study;
·
to determine Project compliance with regulatory requirements, standards
and government policies;
·
to take remedial action if unexpected problems or unacceptable impacts
arise; and
·
to provide data to enable an environmental audit.
The implementation schedule, containing the recommended
mitigation measures, monitoring and audit requirements, and implementation
agent of the mitigation measures for the Project, is presented in Annex I. Details
of the EM&A requirements are provided in a stand-alone EM&A Manual.
12.2
Organisation and
Personnel of the EM&A
The proposed organisation of all personnel
involved in the EM&A process is illustrated in Figure 12.1. The roles and responsibilities of the various
parties involved in the EM&A process are detailed in the EM&A Manual,
and summarised in Section 12.3.
Figure
12.1 Project Organisation Chart
12.3
Role
and Responsibilities
12.3.1
Project Proponent
The Project Proponent (PP), Sha Lo Tung Development Co.
(SLTDC), Ltd, should supervise the Contractor’s activities and ensure that the
requirements in the EM&A Manual and the Contract Document are fully
complied with. They should develop
appropriate contract clauses to ensure that the Contractor will have qualified
professionals to interface with the Environmental Representative (ER) to fulfil
the environmental requirements.
They should participate in join site inspections
undertaken by the Conservation Specialist (CS) and the Contractor, whenever requested.
They should inform the Contractor when action is
required to reduce impacts in accordance with the Event and Action Plans.
They should adhere to the procedures for carrying out
investigation of complaints.
12.3.2
Contractor
The Contractor (C) employed by the Project Proponent
should work within the scope of the construction contract and other tender
conditions that are related to the environmental requirements.
They should provide assistance to the Environmental
Team (ET) and CS in carrying out monitoring.
They should submit proposals on mitigation measures
in case of exceedances of Action and Limit levels in
accordance with the Event and Action Plans.
They should also implement measures to reduce impact where the Action
and Limit levels are exceeded and take the corrective actions instructed by the
PP, CS, ER or ET.
They should participate in joint site inspections
undertaken by the ET, CS and Independent Environmental Checker, whenever
requested.
12.3.3
Environmental Representative
During the construction phase of the project, Green
Power will act as Environmental Representative (ER). The ER should ensure the Contractor’s
compliance with the project’s environmental performance requirements during
construction of the Project. The ER
should be independent and should not be in any way connected to the
Contractor’s company.
They should compile an EM&A Manual and submit to
the PP, IEC, EPD and C one month before the commencement of construction works.
They should report to the PP, IEC, EPD and C on a regular
basis the progress of the monitoring work and the findings.
12.3.4
Environmental Team
The ET will be responsible for implementing all
environmental measures and EM&A requirements recommended in the EIA Report throughout the construction
and operation of the Project. The ET
will contain suitably qualified support staff to carry out the EM&A
programme and the ET leader should possess
at least 7 years experience in EM&A and/or environmental management. Members of the ET should be
independent and should not be in any way connected to the Contractor’s
company. Due to the specialist nature of
some of the EM&A works required for this Project, the ET should comprise
professionals qualified to undertake the tasks involved. Thus, the ET should include personnel experienced
in noise monitoring, water quality monitoring and ecology monitoring.
They should monitor various environmental parameters
as required in the EM&A Manual. They
should assess the EM&A data and prepare reports on the findings. They should also review the success of the
EM&A programme, determining the adequacy of the mitigation measures
implemented and the validity of the EIA predictions, as well as identify any
adverse environmental impacts before they arise. The monitoring reports should be provided to
the PP, IEC, EPD and C for review.
They should provide advice (if required) to the PP
for the development of environmental contract clauses for Contractor’s
contract.
They should review the Contractor’s working programme
and methodology and comment as necessary and also recommend suitable mitigation
measures to the C in the case of exceedance of Action
and Limit levels in accordance with the Event and Action Plans.
They should adhere to the procedures for carrying out
investigation of complaints.
They should also audit the trip tickets recorded by
the waste disposal stations for all dumping activities. This ensures that the waste is properly
disposed of at the designated locations.
12.3.5
Conservation Specialist
Green Power will provide a CS for the ET to stay
on-site to conduct environmental audits during the construction phase. The CS should be a person who has at least 5
years experience in environmental monitoring and auditing (EM&A) or
environmental management.
The CS should:
·
inspect the site daily to check the implementation and
effectiveness of proposed mitigation measures, in particular the temporary
drainage system and runoff control measures.
The person will have the authority to stop the construction works should
the implementation and effectiveness of the proposed mitigation measures not be
satisfied. The site audits should cover
seven key environmental aspects, where appropriate, including air quality,
noise, water quality, sewerage and sewage treatment, waste management, ecology,
landscape and visual, cultural heritage, environmental complaints and
housekeeping; and
·
report on a daily basis the environmental site audit
observations to the ER, IEC and EPD (copy to the PP and the C).
12.3.6
Independent Environmental
Checker
The IEC will be appointed by the PP as the
independent checker to verify the overall environmental performance of the
Project and to assess the effectiveness of the ET in their duties. The IEC should be responsible to certify all
environmental submissions to EPD. The IEC should advise PP and EPD on environmental
issues related to the project. The IEC
should possess at least 7 years experience in EM&A and/or environmental
management. The IEC should carry out
random sample check and audit the monitoring activities and results at least
monthly; review the proposed measures and results submitted by ET or C and
adhere to the procedures for carrying out complaints investigation.
12.3.7
EPD
As the Authority
under the EIAO,
the EPD will be the authority to approve all submissions under the EIAO.
Monitoring of noise levels,
stream water quality, stream hydrology, ecology (species composition and relative
abundance of riparian vegetation, adult odonate and
fish communities) and cultural heritage are required during the construction
phase. Baseline monitoring will also be
required prior to construction commencement to establish the baseline conditions
for ecology, stream water quality and hydrology. Post project (or construction) or operation
monitoring for stream water quality and ecology will also be required. The details of the monitoring requirements
are summarized in Table 12.1 and the
monitoring locations are shown in Figure 12.2.
Table
12.1 Summary of Monitoring
Requirements
Environmental Aspect |
Location |
Frequency |
Parameters |
Pre- Construction Phase |
Construction Phase |
Post Construction |
Operation Phase |
Noise |
Two representative
NSRs (N1 and N5) as shown in Figure
5.3
in Section 5. |
Weekly |
LAeq 30 min |
|
ü |
|
|
Water Quality |
Sha Lo Tung
SSSI Stream (R1-U, R1-UM, R1-M, R1-D) |
Baseline monitoring: once every two days
for at least 4 weeks Impact monitoring: For
the in-situ parameters and SS: 3 days per week; For oil and grease, ammonia nitrogen,
total reactive phosphorus, BOD5 and E. coli: once a month Post-project monitoring:
3 days per week after construction completion Operation
monitoring: Once a month for 12 months. Two of the monitoring events should
be scheduled on the day just after the Ching Ming Festival Day and Chung
Yeung Festival Day. |
In situ
measure: pH, water
temperature, turbidity, dissolved oxygen (DO), dissolved oxygen (DO,
saturation), salinity and water flow rate. Laboratory measure: suspended
solids (SS), oil and grease, ammonia nitrogen, total reactive phosphorus,
5-day biochemical oxygen demand (BOD5), Chemical Oxygen Demand
(COD), Escherichia coli (E.coli) |
ü |
ü |
ü |
ü |
Ecology –
Stream Monitoring |
Along Sha Lo
Tung Stream next to the Development Site as shown in Figure
12.2 |
Baseline monitoring: 3 days per week and commence no more than 3 weeks
prior to the commencement of the construction phase and the impact
monitoring. Impact
monitoring: Daily Post-project monitoring: 3 days per week
within a week after completion of the construction works |
Stream monitoring to identify the signs
of the abiotic impact as
presented in Table 9.20 in Section 9. |
ü |
ü |
ü |
|
Ecology –
Stream Hydrology Monitoring |
Stations R1-U, R1-M and R1-D as shown in Figure
12.2 |
Baseline
monitoring: 5 days in wet season and 5 days in dry season prior to the
commencement of the construction phase and the impact monitoring. Impact stream
hydrology monitoring should be conducted quarterly (3 monitoring days per
quarter) during construction phase Operational
monitoring should be conducted quarterly within the first three years after
the completion of construction works (a total twelve occasions). |
Stream water level, stream wet width and
flow rate. |
ü |
ü |
|
ü |
Ecology –
Biological Monitoring |
Along Sha Lo
Tung Stream next to the Development Site as shown in Figure
12.2 The wet abandoned agricultural land to
the east of the Development Site |
Baseline monitoring: Once during the wet
season (at least 5 days) and once during the dry season (at least 5 days)
prior to the commencement of any construction works. Impact
monitoring: Biweekly Operational monitoring should be conducted quarterly within
the first three years after the completion of construction works (a total
twelve occasions). |
Biological
monitoring to record the species diversity, relative abundance and community
structure of the riparian vegetation, adult odonate
and fishes in the aquatic habitat |
ü |
ü |
|
ü |
Cultural
Heritage |
Southern section of the Sha Lo Tung Road
Improvement |
During
construction of the southern section of the proposed Sha Lo Tung Road
Improvement alignment as shown in Figure 11.13 in Section 11.
The need and scope of archaeological monitoring is subject to the
detailed design of construction works. |
Archaeological
monitoring |
ü |
ü |
|
|
|
LF01 at the southern section of the Sha Lo Tung Road
|
During construction of the southern section of the
proposed Sha Lo Tung Road Improvement as shown in Plan 6 in Annex H2 and Figure 11.5 under Section
11. Frequency to be agreed with AMO.
|
To be defined after the pre-condition survey
is completed which recommendation of vibration monitoring will be provided. |
ü |
ü |
|
|
12.5.1
Construction Phase
The CS will conduct daily site audit and weekly site
audits will be undertaken jointly by the Contractor, the IEC, CS and the ET
during the during the construction phase of the Project to ensure that the
proposed mitigation measures and good site practices are implemented.
The audit will cover the aspects on management of air
quality, noise, water quality, sewerage and sewage treatment, waste, ecology,
landscape and visual and cultural heritage for the Project.
During the preparation of the detailed landscape
design plan, the design submission will be audited against the recommendation
proposed in this EIA Report by the
landscape architect from the IEC.
12.5.2
Operation Phase
Regular site audits will be undertaken to ensure the
proposed environmental mitigation measures are implemented. The audit will cover the aspects on the
management of air quality,
noise, water quality, sewerage and sewage treatment, waste, ecology, landscape
and visual and cultural heritage. The audits
will be undertaken jointly by the Contractor, the IEC, CS and ET.