Contents

1                      INTRODUCTION                                                                          

1.1                   Background                                                                           

1.2                   Purpose of the Project                                                   

1.3                   Objectives the Environmental Impact Assessment Study      

2                      PROJECT DESCRIPTION                                                           

2.1                   The Project                                                                             

2.2                   Ecological Reserve                                                           

2.3                   Development Site                                                                 

2.4                   Sha Lo Tung Road Improvement                                    

2.5                   Works Programme                                                              

3                      ENVIRONMENTAL IMPACTS                                                    

3.1                   Air Quality                                                                                

3.2                   Noise                                                                                           

3.3                   Water Quality                                                                        

3.4                   Sewerage Impact Assessment                                       

3.5                   Waste Management                                                             

3.6                   Ecology                                                                                    

3.7                   Landscape and Visual Impact Assessment             

3.8                   Cultural Heritage                                                              

3.9                   Environmental Monitoring and Audit                       

3.10                 Overall Conclusion                                                           

 

LIST OF FIGURES

Figure 1

Three Components of the Project: Ecological Reserve, Development Site and Sha Lo Tung Road Improvement

Figure 2

Conservation Management Plan Zoning Map

Figure 3

Location of Proposed Footbridge and Safety Fencing within Sha Lo Tung Ecological Reserve

Figure 4

Master Plan

 

 

1                                            INTRODUCTION

1.1                                      Background

The Pilot Project for Public-Private Partnership Conservation Scheme, Sha Lo Tung Valley, Tai Po establishes the framework for a public-private partnership to conserve the Sha Lo Tung Valley in Tai Po.  The Project intends to ensure long-term active conservation management of the ecologically sensitive areas currently located on private land owned by the Sha Lo Tung Development Company (SLTDC).  More importantly, the Project will provide a source of funds to sustain such conservation action.  The Project is fully in line with Government’s announced policy intentions for conserving Priority Sites for Enhanced Conservation such as Sha Lo Tung, by packaging long term conservation management at the ecologically sensitive area with sustainable, commercial activities within the ecologically non-sensitive area within the site.  With appropriate development concessions granted in non-sensitive areas (as identified as the Development Site) adjoining the Conservation Area, the capital and ongoing costs of establishing and managing conservation operations and infrastructure in the Valley are assured.  The balance between development and conservation expectations is expected to enable the Valley to become a unique nature attraction and educational resource for both locals and tourists, which can be achieved quickly and without Government funding. 

1.2                                      Purpose of the Project

This Project responds directly to the former Environment, Transport and Works (ET&W) (now Environment) Bureau’s invitation to submit proposals for areas selected as potential “pilot projects” for “Public-Private Partnership” (PPP) schemes under the Government’s New Nature Conservation Policy announced in November 2004.  Under the PPP scheme, it is stated in the policy that “development of an agreed scale will be allowed at the ecologically less sensitive portion of the project site, provided that the project proponent undertakes to conserve and manage the rest of the site that is ecologically more sensitive on a long-term basis”.  The conservation objectives incorporated in the Project are directed at conservation, ecological enhancement, sustainable use and education.  Following the intention of the policy, the Proponent’s commitment to these objectives is achieved through an obligation to donate to the statutory fund an amount of fund upfront to cover the recurrent cost for long-term conservation management.  The Proponent partners with Green Power who will be the Conservation Agent.

With 96% of the private land within the Valley owned by the Sha Lo Tung Development Company Ltd (SLTDC), the commitment of Green Power and co-operation of Government, such a partnership can be established immediately to start early conservation action within the Valley and provide a basis for sustainable management over the long term. 

The Project identifies three critical reasons for endorsement of a pilot priority project within the Sha Lo Tung Valley under the New Nature Conservation Policy as detailed below.

(1) The Valley is Accorded High Priority for Nature Conservation and Management - In the announcement of the New Nature Conservation Policy on 12 November 2004, the Sha Lo Tung Valley was ranked no. 2 (scored 2.7 out of 3.0) among the 12 Priority Sites for Enhanced Conservation identified by an expert group convened by the Government based on an agreed scoring system.  The stream course and riparian habitats have been the subject of many local and international specialist studies and the ecological significance of the area is reflected in the Sha Lo Tung Outline Zoning Plan No. S/NE-SLT/4 which states “the primary planning intention is to conserve the areas of ecological significance, to preserve the natural landscape, to promote conservation and to maintain the rural character of the area”.  The Project will protect the habitats and preserve the natural landscape through active management and hence protect the habitats of wildlife, while preventing anthropogenic threats such as the use of four wheel drive vehicles, wargames and vegetation removal and undesirable natural succession which are unfavourable to the existing wildlife.  It will also relieve development pressure on buildings lots (up to some 29,000 sq m GFA as of right) and the development of small houses (NTEHs) (up to 160 as advised by District Office/Tai Po in 1996) in the Valley and hence minimise long term human disturbance to wildlife.  The development concession to fund conservation management in the Valley is sensitively designed so as to be compatible with the rural character of the Valley.

(2) Nature Conservation must be Beneficial to the Biodiversity, Successfully Planned and Sustainable alongside Limited Compatible Development - The Project proposes to set up an Ecological Reserve on ecological sensitive land in the Sha Lo Tung Valley (SLT Valley).  SLTDC will draw up a conservation management plan and inject an agreeable upfront capital into a Government statutory fund for the long term conservation and management of the Ecological Reserve.  The adequacy and practicability of the conservation management plan and funding will be advised by the Government.  Green Power is nominated to be the conservation agent to manage the Ecological Reserve and Nature Interpretation Centre with recurrent funding to be granted by the Government statutory fund.  The other institutional uses in the greenbelt zone comprising the Multi-Cultural Education Retreat and a Columbarium would be owned and operated by the SLTDC.  Sha Lo Tung Road, which requires improvement on public safety grounds, will remain a public road under the management of SLTDC.

(3) Institutional Arrangements and Funding Must Be Realistic and Achievable - The New Nature Conservation Policy encourages commitment from the landowner and proponent (the SLTDC) through encouraging compatible development concessions on less ecologically sensitive land within the project area under the pilot project that will fund conservation facilities and operations.  In this Project, the concession takes the form of institutional development in the form of a Multi-Cultural Education Retreat and Columbarium located in the greenbelt zone at the entrance to the Valley.  The details of all development within the green belt zone shall be subject to approval by the Town Planning Board and implemented according to the agreed terms of a later execution of lease modifications and land exchange.  This concession will enable the SLTDC to cover construction and equipping conservation, educational and public facilities supporting the Ecological Reserve and to improve SLT Road and to inject upfront capital into the Government statutory fund and to cover long term management of the conservation operation.  SLTDC will also set aside a lump sum for the long term maintenance of the improved SLT road.  The capital injected to the Government statutory fund will generate steady income to meet recurrent cost for carrying out measure to conserve the Ecological Reserve.  The conservation agent shall apply to the Government statutory fund for the funding to carry out the conservation management plan for Sha Lo Tung Valley.  The Government statutory fund will be responsible for assessing the performance of the conservation agent and the justification for the amount of funds applied for. 

1.3                                      Objectives the Environmental Impact Assessment Study

The Project involves earthworks (building a footbridge crossing a stream within the Ecological Reserve) within Sha Lo Tung Site of Special Scientific Interest.  It is classified as a Designated Project under Schedule 2, Part I, Category Q, Item Q.1 of the Environmental Impact Assessment Ordinance (Cap. 499) and, therefore, the construction and operation of the Project will require an Environmental Permit.  The overall objectives of the EIA Study are to provide information on the nature and extent of environmental impacts arising from the Project; to recommend appropriate mitigation measures to control the potential environmental impacts so that it complies with the requirements of the Technical Memorandum on Environmental Impact Assessment Process of Environmental Impact Assessment Ordinance (EIAO-TM), and to confirm the environmental acceptability of the Project.

The specific objectives of the EIA Study described in the EIA Study Brief are listed below.

(i)            to describe the Project and associated works together with the requirements for carrying out the Project;

(ii)           to identify and describe elements of community and environment likely to be affected by the Project and/or likely to cause adverse impacts to the Project, including the natural and man-made environment and the associated environmental constraints;

(iii)         to provide information on the consideration of alternatives to avoid and minimise the potential environmental impacts to the environmentally sensitive areas and other sensitive uses; to compare the environmental benefits and dis-benefits of each of the different options (including the different development options for the three components of the Project); to provide reasons for selecting the preferred option(s) and to describe the part environmental factors played in the selection of preferred option(s);

(iv)         to identify and quantify emission sources and determine the significance of impacts on sensitive receivers and potentially affected uses;

(v)          to identify and quantify any potential loss or damage to flora, fauna and wildlife habitats;

(vi)         to identify and quantify any potential landscape and visual impacts and to propose measures to mitigate these impacts;

(vii)       to identify any negative impacts on site of cultural heritage, historic buildings and structures and to propose measures to mitigate these impacts;

(viii)      to propose provision of mitigation measures so as to minimize pollution, environmental disturbance and nuisance during construction and operation of Project;

(ix)         to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;

(x)          to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation phases of the Project in relation to the sensitive receivers and potential affected uses;

(xi)         to identify, assess and specify methods, measures and standards, to be included in the detailed design, construction and operation of the Project which are necessary to mitigate these environmental impacts and cumulative effects and reduce them to acceptable levels;

(xii)       to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification; and

(xiii)      to design and specify environmental monitoring and audit requirements to ensure the effective implementation of the recommended environmental protection and pollution control measures.

As specified above, the EIA Study addressed the following key environmental issues due to the construction and operation of the Project:

·            potential air and noise impacts on sensitive receivers located within and near the Project site arising from construction and during operation of the Project;

·            potential water quality and hydrological impacts on sensitive receivers located within and near the Project site including Sha Lo Tung Stream, Fung Yuen Stream, Sha Lo Tung Site of Special Scientific Interest (SSSI), Fung Yuen Valley SSSI, Water Gathering Ground, etc. during construction and operation of the Project;

·            potential ecological impact on habitats located within and near the Project site including the Sha Lo Tung Stream, Fung Yuen Stream, Sha Lo Tung SSSI, Fung Yuen Valley SSSI, Pat Sin Leng Country Park and conservation areas, etc. due to the construction and operation of the Project;

·            waste arising as a result of the construction and operation activities of the Project;

·            potential landscape & visual impacts from construction and operation of the Project;

·            potential impacts on sites of cultural heritage, historic buildings and structures likely to be affected by the construction and operation of the Project and its associated works;

·            cumulative impacts of the existing, committed and planned developments in the vicinity of the Project on the Sha Lo Tung SSSI and the adjacent conservation areas; and

·            the short-term and long-term conservation and management of the proposed Ecological Reserve within the project area including the financial arrangement.

 

2                                            PROJECT DESCRIPTION

2.1                                      The Project

The Project includes three inter-related components: Ecological Reserve, Development Site and Sha Lo Tung Road Improvement (Figure 1).  The Proponent, the Sha Lo Tung Development Company (SLTDC) and the Conservation Agent, Green Power (GP) propose to set up an Ecological Reserve (approximately 52.5 ha, accounting for more than 92% of the entire Valley) in Sha Lo Tung (SLT) Valley (of total area approximately 56.6 ha).  The SLTDC intends to dedicate their private housing lots (approximately 0.8 ha) and private agricultural lots (approximately 26 ha) in the Valley and agricultural lots in the adjacent Country Park (approximately 2 ha) for conservation purposes and establish an Ecological Reserve on both ecologically sensitive land (dedicated by SLTDC) and government land.  The Ecological Reserve will maintain, protect, restore and enhance the ecological resources of the SLT Valley.  This will be achieved by preventing unauthorised incompatible activities, managing and restoring habitats at the “optimal” succession state, and by enhancing grassland and woodland habitat.  Additionally, a Nature Interpretation Centre providing nature education activities to promote awareness, appreciation and understanding of the ecological value of the area, will be built adjacent to the Ecological Reserve in the Development Site.  The conservation management and funding of the SLT Ecological Reserve will be overseen by the Government statutory fund.

The Development Site of approximately 4.1 ha is outside of the Country Park and Conservation Area. Besides the Nature Interpretation Centre, the Development Site accommodates the necessary development concession in the form of a Multi-Cultural Education Retreat cum Columbarium (with a development footprint of approximately 1.625 ha or 39.6% of the total area of the Development Site (includes the Nature Interpretation Centre, public parking, footpaths landscaping areas and associated site formation) in a lower ecological value area at the entrance to the Valley.  These concession facilities provide revenue to payback the upfront capital injected by the SLTDC to sustain the initial set up and long term operation funding of the Ecological Reserve.

Sha Lo Tung Road Improvement also lies outside of the Country Park and Conservation Area.  The existing Sha Lo Tung Road (approximately 2.3 km) will be upgraded to a Single Track standard with the minimum required number of passing bays to meet the requirements of the Transport Department and Fire Services Department and provide safe public access to the Ecological Reserve, Development Site and Country Park.

2.2                                      Ecological Reserve

The Ecological Reserve, of approximately 52.5 ha, provides an opportunity to enhance Sha Lo Tung Valley’s environment for the benefit of the community and boost its ecological value.  Biodiversity conservation is the core focus of the Public Private Partnership (PPP) programme where value-added activities such as conservation education will be integrated into the management strategy of Sha Lo Tung Valley, when appropriate.  It can be achieved by adopting a Conservation Management Plan (CMP), which prescribes management to safeguard the ecological value of the area in perpetuity for the people of Hong Kong.  A summary of the CMP is presented in the following sections.

2.2.1                                Conservation Management Plan

The CMP will serve as a guideline for action covering the first 5-year period and will evolve as time passes and experience is gained.  The key objectives are:

·            Objective 1:  Conserve and Enhance Dragonfly Biodiversity

·            Objective 2:  Enhance Upland Habitats by Removal of Exotic Vegetation

·            Objective 3:  Enhance Quality and Area of Woodland Habitat

·            Objective 4:  Restore Abandoned Farmlands to Butterfly Garden and Marsh Habitats

·            Objective 5:  Sustainably Manage Visitors

·            Objective 6:  Conserve Target Species

·            Objective 7:  Enhance Conservation Education Opportunities

The plan will be implemented by the Conservation Agent (Green Power) with the funding to be granted by the Government statutory fund.

The Conservation Management Plan zoning map shown in Figure 2 outlines areas where various conservation measures will be implemented.  Biodiversity conservation is the core focus of the Public-Private-Partnership (PPP) programme under which Sha Lo Tung Valley is to be managed. 

2.2.2                                Other Works within Ecological Reserve

A detailed investigation of the existing structural condition of village houses in Lei Uk Village, most of the masonry walls have collapsed and the remaining walls, now in reasonable condition, may further deteriorate due to lack of maintenance and cause a potential public safety risk.  In view of this public safety concern, it is necessary to prevent unauthorized access to such houses.  To achieve this fencing will be provided along the western edge of Lei Uk adjacent to the footpath (Figure 3).  Getting materials to and from the village will not only involve utilising existing pathways (with minor improvement of the existing footpath to Lei Uk) but also the need to construct a small temporary footbridge across a narrow section of the Sha Lo Tung Stream SSSI (for location refers to Figure 3).  This temporary footbridge will be demolished after the safety measures have been completed.

The maintenance and operation of the Ecological Reserve will follow the guidelines of the Conservation Management Plan.  All functions of the components will be monitored and controlled by the Government statutory fund.  Only minor works will be required during emergencies or routine maintenance.  The ecological status of SLT Valley will be evaluated regularly, and additional action plans will be implemented if necessary.

2.2.3                                Ecological Benefit

The Development Site is located in area of less ecological concern (mainly shrubland grassland mosaic) and avoids all of the ecologically sensitive areas, including Country Park, SSSIs and Sha Lo Tung streams.  Further to the detailed assessment presented in the EIA Study, no unacceptable ecological impacts during the construction and operational phases of the proposed development at Development Site and Sha Lo Tung Road are predicted. 

With the implementation of the Conservation Management Plan, human disturbance will be largely reduced/ controlled.  Disturbance due to hillfire, visitors and vandalism would be controlled by pro-active management, including patrolling and conservation education.  Under the Sha Lo Tung pilot project, an aggressive fire-suppression programme will be implemented to prevent the occurrence of hill fires (regularly recorded within Sha Lo Tung Valley).  Rubbish and illegal traps would also be regularly removed by site managers.  As a consequence, the proposed development can be expected to generate ecological gain.

The PPP pilot scheme will not only avoid and minimise ecological impacts but will enhance the conservation value of Sha Lo Tung Valley through the following actions:

·            The project proponent has entered mutual agreement with village representatives to divert New Territories Exempted House (NTEH) demand amounting to 160 NTEH sites outside the Sha Lo Tung valley and dedicate all its land (including 236 building lots) for conservation.  This removes large scale village expansion as a threat to the ecological integrity and conservation value of the valley; and,

·            It protects the area by controlling site access and enhances the ecological values by active management.

2.3                                      Development Site

2.3.1                                Master Plan of the Development Site

Due to the sensitivity of the Sha Lo Tung Valley and the potential construction impacts to the Sha Lo Tung Stream, the design of the Master Plan of the Development Site has adopted the following considerations, in order to minimise potential construction impacts on the existing trees and Sha Lo Tung SSSI Stream.

·            Provision of a minimum additional 20 m wide Non-Building Buffer from the Sha Lo Tung SSSI

·            Retrofitting Development to the Natural Topography

·            Locating Development back from the Sha Lo Tung SSSI and Stream

·            Extensive Use of Green Roofing

·            Preservation of Existing Woodland and Trees

With the adoption of the above considerations, the Master Plan as presented in Figure 4 can avoid or minimise potential water quality and ecological impacts to the stream and SSSI, as well as impacts to woodland and trees. 

The preliminary Master Plan and the concept of the Nature Interpretation Centre, and a Multi-Cultural Education Retreat cum Columbarium is presented in Figure 4.  The proposed development comprises the following:

·            The Nature Interpretation Centre with barrier-free pedestrian access linkage to Ecological Reserve;

·            Public and private parking areas at the end of Sha Lo Tung Road;

·            Multi-Cultural Education Retreat including Confucius Halls & Multi-purpose Hall, ancillary Quarters and dining room / hall, and extensive open landscaping areas, and

·            Columbarium accommodating a maximum of 60,000 niches with extensive open gardens, pathways and landscaping.

2.4                                      Sha Lo Tung Road Improvement

2.4.1                                Alignment of the Sha Lo Tung Road Improvement

The existing Sha Lo Tung Road between Ting Kok Road and Sha Lo Tung Valley (approximately 2.3 km) is the only vehicular access to Sha Lo Tung Valley and the Development Site.  The reason for the proposed improvements is to upgrade the existing roadway to the minimum requirement of a safe Single Track Access Road that would also enable emergency access for fire engines.  In the absence of the road improvements, delivery of emergency services would not be practicable.  In order to meet the traffic demand during construction and facilitate the transportation of construction plants or raw materials to/from the Development Site, it is proposed to complete the road improvement works with drainage and sewerage systems prior to commencement of site formation works. 

The principles of the design for the road improvement works are: -

·            Minimize disturbance to the existing landscape and trees;

·            Preserve woodlands of ecological value;

·            Provide a safe access road; and

·            Enable emergency vehicle access to the Ecological Reserve, Nature Interpretation Centre, Multi-Cultural Education Retreat cum Columbarium.

Following the principles of the improvement works, the impacts arising from the upgrading of Sha Lo Tung Road will be kept to a minimum, and the improved road will be able to provide emergency service access, serve the conservation facilities, Pat Sin Leng Country Park and Water Supplies Department (WSD) Service Reservoirs etc.  In light of the low volume of traffic forecast, the access road shall remain a single track access road with basic improvements to satisfy the Transport and Planning Design Manual (TPDM) requirements.  These include:

·            Widening the existing access road to a minimum width of 4.5 m, which according to TPDM is suitable for use of emergency vehicles;

·            Providing additional inter-visible passing places at maximum spacing 60 m for 2-way traffic;

·            Appropriate local widening at bends of up to 6 m wide to cater for travel of emergency vehicles from Ting Kok Road to the proposed conservation facilities;

·            The access road shall follow the existing road alignment and profile to minimise earthworks and impacts to the existing environment.  Nevertheless, the road shall be re-profiled to ensure a maximum gradient less than 16% because a gradient more than 16% is not suitable for use of emergency vehicles;

·            The road will be widened towards the eastern side through cutting the uphill slopes to avoid disturbing the woodland dominating on the western side;

·            The soil nailing, if required to stabilise slopes particularly downhill, can be implemented carefully to avoid damage to trees and the slope surface can be planted to maintain a green landscape after the improvement works are finished;

·            Provision of a vehicle turn round facility at the entrance of Sha Lo Tung Valley suitable for the use of fire engines;

·            Provision of drainage system with additional verges and sewer along the route;

·            No encroachment to Conservation Area and Pat Sin Leng Country Park; and

·            Appropriate landscape design along the access road.

2.5                                      Works Programme

The works programme and the work sequence of the Project will be undertaken as follows:

·            Ecological Reserve – The enhancement work will be undertaken immediately once the commencement of the Project is confirmed in order to provide the greatest conservation and ecological benefit.  The Conservation Management Plan and the priority of the enhancement work shall be approved by the Government statutory fund prior to the commencement of the enhancement work.  The minor improvement of footpath, construction and installation of the temporary footbridge and fencing around broken village houses and structures at Lei Uk will be completed within 3 months (during dry season).

·            Sha Lo Tung Road Improvement – The road improvement works will be divided into three phases.  Each phase of the road works will be constructed generally in sequence with each will take approximately 8 to 9 months and overlap at certain periods of time.

·            Development Site – The site formation works will be carried out in three stages after Sha Lo Tung Road Improvement: Stage 1 (approximately 6 months), Stage 2 (approximately 5 months) and Stage 3 (approximately 6 months).  The duration of each of the three stages will overlap at certain periods of time so that the earthworks (soil and excavation and filling works) will only be undertaken during the dry season (November to March).

3                                            ENVIRONMENTAL IMPACTS

The environmental impacts associated with the construction and operation of the Project are summarised in the following sections.

3.1                                   Air Quality

The enhancement and associated works within the Ecological Reserve will be carried out with hand tools only.  No major excavation works will be required and no dust impact is anticipated.  Only minor works will be required during emergencies or routine maintenance.  No air pollution generating activity is required and no air quality impact is expected during the operational phase.

Dust nuisance from construction works and gaseous emissions from diesel-powered equipment are the potential air quality concerns during the construction of the Multi-Cultural Education Retreat cum Columbarium.  Dust may be generated from materials handling, excavation and filling, wind erosion and truck movements during site formation works.  The scale of the construction works is likely to be small and the rate of excavated soil generation will also be low (ie 94 m3/day on average).  With the implementation of recommended dust control measures and good site practices, dust impact is not expected.  The number of diesel-powered construction equipment to be operated at any one time will be limited owing to the small scale of the works and the division of the works into phases.  Gaseous emissions from the operation of diesel-powered equipment are expected to be minor, and no adverse air quality impact is anticipated. 

The number of visitors during public holidays and festival holidays will be increased.  However, burning of effigies and paper offerings will not be allowed at the future development; therefore no adverse air quality impact is anticipated during the operation of the development.  In-house management measures such as signage to remind visitors on the prohibition of burning effigy should be provided.  Vehicular emissions from Sha Lo Tung Road are the key air quality concern during the operation of the columbarium.  However, during normal days, two electric 24-seats shuttle buses will be provided for serving the visitors.  During festive periods, additional shuttle buses will be hired from coach suppliers and SLTDC will hire electric coaches as the first priority.  If hired electric coaches are not available in the market, SLTDC will hire LNG/ hybrid/ Europe V (or higher) coaches as the second priority before considering other environmental-friendly coaches.  In view of the large separation distances between ASRs and the future columbarium and compliance with HKPSG recommendations, no adverse air quality impact is anticipated. 

In addition, the Motor Vehicle Idling (Fixed Penalty) Ordinance has been in effect on 15 December 2011.  It is prohibited to allow the drivers leaving vehicle engines idling for more than three minutes in any 60-minute period.  As such, no air emission is anticipated from the shuttle buses during idling in the parking area.

Dust nuisance from construction works and gaseous emissions from diesel-powered equipment are the potential concerns during the road improvement works.  Materials handling, wind erosion and truck movements are expected to be the major sources of construction dust.  The road improvement works will be conducted over a period of 19 months and the works will be carried out in phases, each of which covers only a road section of approximately 800m in length, and therefore the works area will be small.  In view of the large separation distances between ASRs and the works area, no adverse dust impact is anticipated.  The number of diesel-powered equipment to be used for the works will be limited owing to the small size of the works area.  The air emissions from diesel equipment are expected to be minor and no adverse air quality impact is expected.  With the implementation of the recommended dust control measures and good site practices, the dust impact is expected to comply with the dust criteria.  Vehicular emissions are envisaged to be the only air quality concern during the operation of the widened Sha Lo Tung Road.  During normal days, two electric 24-seats shuttle buses will be provided for serving the visitors.  During festive periods, additional shuttle buses will be hired from coach suppliers and SLTDC will hire electric coaches as the first priority.  If hired electric coaches are not available in the market, SLTDC will hire LNG/ hybrid/ Europe V (or higher) coaches as the second priority before considering other environmental-friendly coaches.  In view of the sufficient buffer distances between ASRs and the widened road and compliance with HKPSG recommendation, no adverse vehicular emission impact is anticipated.

3.2                                      Noise

Owing to the proximity of the NSRs to the Sha Lo Tung Road Improvement, mitigation measures are required to be implemented to mitigate the construction noise impacts.  Practicable mitigation measures, including use of quiet construction plant, reduced utilisation rates of PME and movable noise barriers, have been recommended to be implemented during the three phases.  With the implementation of mitigation measures, the mitigated construction noise levels at the representative NSRs would comply with the construction noise criterion of 75 dB(A) throughout the construction period.  Noise monitoring during the construction stage is recommended to ensure compliance with the relevant noise criteria. 

During the operational phase of the Project, the induced traffic on Sha Lo Tung Road will not cause any adverse noise impact to the NSRs.  The predicted operational fixed plant noise levels at the representative NSRs would comply with the noise criterion based on the set of specified maximum SWLs for the Plant Rooms and VRV units at the Development Site.  Attenuation measures, if required, will be provided to the fixed plant items for achieving the guaranteed noise levels during the detailed design stage.  A detailed noise impact assessment should be undertaken during the detailed design of the fixed plant items for the development.  Noise monitoring is not required during the operational phase. 

3.3                                      Water Quality

Sha Lo Tung Valley comprises water quality sensitive receivers including Sha Lo Tung SSSI and stream, which are also considered of high ecological and conservation significance, as well as the wet abandoned agricultural land to the east of the Development Site.  It has been identified that the water quality sensitive receivers (WSRs) of the Development Site and Sha Lo Tung Road Improvement include Sha Lo Tung SSSI, Fung Yuen Valley SSSI and streams.

No pesticides or herbicides will be used for weed removal during the enhancement works.  Other work within the Ecological Reserve will include construction and removal of the temporary footbridge, and fencing at Lei Uk and minor improvement of the existing new footpath to Lei Uk.  These works will be carried out with hand tools only.  No major excavation works will be required and no water quality impact is anticipated.  Only minor works will be required during emergencies or routine maintenance.  No wastewater generating activity will occur and no water quality impact is expected during the operational phase.

During the construction phase of the Project water quality impacts have the potential to arise from construction runoff, general construction activities and domestic sewage discharge.  To avoid ecological risk to the downstream Sha Lo Tung Valley, any discharge of construction runoff from the Development Site is prohibited.  The following practices and measures to be proposed are targeted to ensure no discharge of construction runoff to the downstream ecological sensitive areas:

·            Complete the Sha Lo Tung Road improvement (with well designed drainage and sewerage systems) before any construction works are undertaken within the Development Site;

·            Restrict earthworks to the dry season;

·            Manage the construction sequences, in particular during the wet season;

·            Provide temporary drainage channels to divert site runoff to the sandtrap before discharging it from the site;

·            Provide silt removal facilities such sand traps;

·            Provide a separate temporary drainage system to divert the natural runoff away from the site and minimise the site runoff;

·            Erect a continuous site hoarding with seal along the northern boundary of the Development Site;

·            Carry out daily inspection; and

·            Carry out water quality monitoring programme during and after construction.

Effective controls, including but not limited to the construction of peripheral channels and erection of the site hoarding (with any gaps to be filled and cemented) in advance of site formation works and a restriction that earthworks are undertaken only during the dry season, will be implemented.  Consequently, the potential water quality impacts will be controlled and are expected to be minimal.

The principal impacts on the existing drainage that require mitigation are as follows:

·            Increase in the total volume of run-off;

·            Increase in peak intensity of run-off flow; and

·            Increase in risk of pollution.

The increase in water quantity has been addressed by minimising the creation of impermeable surfaces, encouraging natural ground water recharge through soakaways/filter drains and transferring all highway runoff into the adjacent urban catchment.  The increase in peak intensity has been addressed by controlled run-off attenuation using swales, naturally lined channels, catchpits, and vortex grit separator with outlet control and undeveloped buffer zones.  The risk of pollution has been addressed by transferring runoff from higher risk areas to the adjacent urban catchment, and the use of catchpits, filter drains and vortex grit separator in the traffic free, low risk Development Site.  The hazards and risk associated with accidental oil spillage and leakage are negligible because all storm water run-off from the access road and car park within the Development Site will be isolated, collected in the pumping station located beneath the proposed car park and then pumped back into the stormwater drainage system for the upgraded access road where it will re-enter the existing main storm water drainage system for the Ting Kong Road.

During the construction phase of the Sha Lo Tung Road Improvement, the water quality impacts have the potential to arise mainly from construction runoff and general construction activities.  It is anticipated that the effects on water quality from the construction activities are likely to be minimal, provided that major earthworks are undertaken during dry season, and that good construction practices and a well designed temporary drainage system are implemented.

Vehicles will enter the Ecological Reserve, Nature Interpretation Centre, and a Multi-Cultural Education Retreat cum Columbarium along the improved Sha Lo Tung Road to the car park which will be situated at the western side of the Development Site.  The road runoff may contain minimal amounts of oil, grease and grit that may cause water quality impacts to the watercourses, if uncontrolled.  With the collection of the run-off and then pumping back into the structured highway drainage system along the improved Sha Lo Tung Road that ultimately connects to the existing stormwater system in Ting Kok Road, no adverse impacts to the WSRs are anticipated.  Furthermore, it is anticipated that the number of vehicles entering the area will be relatively low when compared to the main roads and this will further minimise water quality impacts.

3.4                                      Sewerage Impact Assessment

Taking into consideration the constraints of the Development Site, and the existing and planned sewage network in the region, three sewage disposal options for the development of the Site have been investigated.   In broad terms, the three proposed sewage disposal options are discharging to Tai Po Sewage Treatment Works, treatment on Site and removal off site.

Among the three options, the option of discharging the sewage to Tai Po Sewage Treatment Works is recommended.  The option of provision of on-site sewage treatment plant and removal of the sewage off site by tanker are not recommended.  The recommended option is considered feasible and practical given that the impacts to the downstream sewer and the Tai Po Sewage Treatment Works are considered insignificant.  The details of the recommended sewage disposal scheme will be further confirmed at the detailed design stage and close liaison will be carried out with relevant departments to approve the scheme.

An assessment of the impacts of sewage generation during festival days has also been considered.  With the following measures to manage the increase in sewage generation, no adverse impacts to the sewerage system are expected:

·            Provision of adequate permanent water closets and urinals in the complex;

·            Emptying of the sewage storage tank before and immediately after the festivals;

·            Provision of portable toilets at the entrance of Sha Lo Tung road, next to Ting Kok Road for contingency purpose; and

·            Should the permanent sanitary facilities in the Development Site be closed due to malfunction or emergency maintenance, additional portable toilets can be arranged within a short period of time to cater the visitors (e.g. ten portable toilets to cater for a maximum of 7,600 visitors if cleaning exercise is performed).  

3.5                                      Waste Management

As part of the associated works within the Ecological Reserve, a temporary footbridge will be constructed across the stream within the Sha Lo Tung Stream SSSI.  Minor excavation for the construction of the bridge footing will be required.  It is estimated that about 1.1 m3 of C&D materials will be generated from the footing construction.  About 0.4 m3 of this material will be reused as backfilling onsite and the rest will be disposed offsite at the appropriately waste reception facility.  With the implementation of good waste management and on-site waste minimisation practices, no adverse impact associated with the management of green waste is expected during the maintenance and operation of the Ecological Reserve.

Approximately 16,100 m3 of inert soft materials will be excavated during site formation and approximately 7,600 m3 of public fill are required for filling to the required level.  The in-situ excavated materials will be reused for the backfilling, and the cutting and filling activities for the site formation and slope works will be planned and arranged in such a way that the requirement for stockpiling will be minimised.  The waste management assessment is based on the worst case scenario assuming there is no reuse of materials on-site.  The average rate of excavated soil generation and filling rate will be low (ie about 134 m3/day and 63 m3/day, respectively).  Assuming 10 working hours a day, about 4 to 5 trucks and 1 trucks will be required per hour on average (considered as worst case scenario as some materials will be reused on-site as much as possible) to dispose to public filling facilities and to import fill materials, respectively.  It should be noted that the trucks will only travel along the improved Sha Lo Tung Road (with pedestrian footpath after the improvement) during weekday’s normal working hours for five months but not in the weekends or public holidays.  The number of trucks can be reduced by reusing the materials on-site and the nuisance to hikers or visitors to Sha Lo Tung due to the trucks can therefore be minimised as well.  About 1,490 m3 of construction waste will be generated from new building construction.  Given the implementation of recommended mitigation measures (ie waste management programme) and good site practices, no adverse environmental impact is expected during the construction phase.

Limited quantities of general refuse and chemical wastes are expected to be generated during the operation of the Nature Interpretation Centre, Multi-Cultural Education Retreat cum Columbarium.  With good site practices, the potential environmental impacts associated with the storage, handling, collection, transport and disposal of a small quantity of general refuse and chemical wastes arising from the operation of the Multi-Cultural Education Retreat will meet the relevant EIAO-TM criteria and no adverse impact associated with waste management is anticipated.

The road improvement works will be divided into three phases.  The three phases of the road improvement works will be undertaken in consecutive sequence with some overlap between phases.  A total of 11,000 m3 of soil will be excavated over the 19-month construction period.  About 20m3 of soil is estimated to be generated per day.  Even if a peak factor of 2 is applied to cater for the potential increase in spoil generation during the overlapping of two phases, the estimated peak volume of spoil to be generated per day (ie 40 m3) is still considered small.  Assuming a capacity of 7.5 m3 per truck and a bulk factor of 1.2, about 7 trucks per day will be required to dispose to public filling facilities.  A small volume of fill materials (ie, 1,000 m3) will be required.  Assuming 24 working days a month, a capacity of 7.5 m3 per truck and a bulk factor of 1.2, the filling rate, on average, will be 2 m3 per day and about 1 truck will be required to import the fill materials.  With such a small number of truck trips generated, the effect on the existing traffic on Sha Lo Tung Road would be minimal.

Chemical waste generated from maintenance of construction equipment will be generated during the construction phase.  Given the implementation of the recommended mitigation measures, no adverse environmental impact is expected during the construction phase.

3.6                                      Ecology

The ecological impact assessment has been prepared using the results of comprehensive literature reviews and ecological field update surveys conducted between 2004 and 2011.  The Ecological Reserve covers areas within Sha Lo Tung Valley and is considered of high ecological significance.  Habitats recorded include Fung Shui Woods, secondary woodlands, grassland shrubland mosaic, streams, wet and dry abandoned agricultural land, active agricultural land and developed area (abandoned village).  However, the habitat quality within Sha Lo Tung Valley is degrading due to threats such as the use of four wheel drive vehicles, hill fires, wargames and vegetation removal.  

The Development Site is mainly covered by grassland shrubland mosaic with a small part of the area occupied by secondary woodland and developed area.  The grassland shrubland mosaic is frequently disturbed by hill fire and is considered to have low to moderate ecological value.  The secondary woodland is dominated by climax native tree species such as Schima superba with densely vegetated understorey and is considered of moderate to high ecological value.  Faunal species of conservation interest recorded within the Development Site included Greater Coucal, Lesser Coucal, Hwamei, Savannah Nightjar with sightings of the Crested Serpent Eagle flying overhead.  Floral species of conservation interest included Bamboo Orchid and Willow-leaved Camellia.

Habitats within the Sha Lo Tung Road Improvement area include secondary woodland, plantation, grassland-shrubland mosaic and developed area.  The secondary woodland is of moderate to high ecological value, the grassland-shrubland mosaic of low to moderate ecological value, the plantation of low ecological value and the developed area of negligible ecological value.  Species of conservation interest recorded within the Construction Works Boundary along the Sha Lo Tung Road Improvement included Incense Tree, Lamb of Tartary, Hong Kong Pavetta, Rhodoleia, Common Tutcheria and Cycad fern and all the same bird species of conservation interest as found in the Development Site, with the addition of the Emerald Dove and a Common Buzzard flying overhead.  In addition, evidence of the Masked Palm Civet, a mammal of conservation interest, in the form of scats on the road, was also recorded.

The enhancement works for the establishment of the Ecological Reserve and the implementation of the Conservation Management Plan will enhance the conservation value of Sha Lo Tung Valley.  In addition, human disturbance such as hill fire will be largely reduced/ controlled.  As a consequence, the proposed Project is expected to bring about long term and sustainable benefits to the ecology of Sha Lo Tung Valley and the habitats and associated wildlife.

Direct habitat loss may result from the land taken for the construction of proposed buildings and facilities as well as the Sha Lo Tung Road improvement works.  The majority of the proposed development will be constructed on the grassland-shrubland mosaic and thereby reduce the impacts on the secondary woodland.  The proposed development also avoided impacts on the wet abandoned agricultural land and the associated aquatic species of conservation interest.

With the provision of a 20 m building buffer from Sha Lo Tung SSSI, the riparian woodlands which served as wildlife (particularly Family Gomphidae dragonflies) foraging/ roosting grounds are significantly preserved.  The small-sized habitat loss due to the proposed development is not predicted to cause adverse impacts to the wildlife using the SLT SSSI and associated habitats.  The ecological impacts on the larval stage of the dragonfly community in the SSSI due to the water quality impacts from the construction activities are likely to be avoided through water pollution control measures.  No unacceptable ecological impacts during the construction and operational phases are expected based on the current design given that appropriate mitigation measures are properly implemented, including the key measures listed below:

·            minimisation of the development footprint within the Development Site, occupying only 1.625 ha of development footprint out of the 4.1 ha Development Site (comprising about 39.6% of the total site area);

·            detailed engineering design avoiding habitat and vegetation loss;

·            completion of the Sha Lo Tung Road improvement (with well designed drainage systems) before any construction works for the Development Site;

·            managing the construction sequences and in the dry season, careful scheduling of the earthworks;

·            provision of an additional 20 m non-building buffer between the works area and Sha Lo Tung SSSI;

·            adoption of a phased schedule;

·            compensatory planting;

·            vegetation transplantation;

·            good construction practice;

·            a well designed temporary as well as a permanent drainage systems;

·            provision of silt removal facility;

·            erection of site hoarding in advance of the commencement of any works;

·            proper visitor control (particularly during special festivals); and,

·            restricting the workers within the Development Site during construction.

No adverse residual water quality or associated ecological impacts were predicted to occur due to construction and operation of the Project on the basis that the recommended mitigation measures are adopted in full.

3.7                                      Landscape and Visual Impact Assessment

Fourteen Landscape Resources and four Landscape Character Areas were identified within the 500 metre Study Area.  A number of mitigation measures have also been proposed for both the design and construction period to not only reduce potential landscape and visual impacts but also to improve the overall amenity of the Project.

The following residual landscape impacts have been identified during the construction phase:

·            There will be ‘Moderate’ impacts on LR1 Woodland, LR2 Open Shrubland, LR6 Plantation, LCA1 Upland and Hillside Landscape and LCA4 Sha Lo Tung Valley.

·            There will be ‘Slight’ impacts on LR3 Abandoned Agricultural Land, LR4 Developed Area, LR7 Roads and LCA2 Fung Yuen Valley.

·            There will be ‘Negligible’ residual impacts of all other LRs and LCAs during the construction phase.

The following residual landscape impacts have been identified during the operation phase:

·            During the operation phase, there will be ‘Moderate’ residual landscape impacts on LCA4 Sha Lo Tung Valley at Day 1 of operation, reducing to ‘Slight’ at Year 10 of operation.

·            There will be ‘Slight’ impacts on LR1 Woodland, LR2 Open Shrubland, LR2 Open Shrubland, LR6 Plantation and LCA1 Upland and Hillside Landscape at Day 1 of operation. At year 10 of operation, ‘Slight’ impacts will remain for LR1 Woodland, LR 3 Abandoned Agricultural Land and LCA1 Upland and Hillside Landscape.  The impacts will reduce to ‘Negligible’ for LR3 Abandoned Agricultural Land and LR6 Plantation.

·            There will be ‘Negligible’ residual impacts of all other LRs and LCAs during the operation phase at both Day 1 and Year 10.

In addition to a review of the physical barriers forming the natural visual envelope of the project, a GIS analysis and an analysis of the parameters of human vision was undertaken.  The visual envelope was found to extend to 2.3 km from the boundary of the Development Site and 900m from the road improvement works.

Ten recreational, seven residential, two occupational and three travelling VSRs were identified within the visual envelope.

The following residual visual impacts have been identified during the construction phase:

·            Temporary residual visual impacts of ‘Moderate’ significance will include R1 Hikers on the Wilson Trail west of the site, R2 Cyclists along Ting Kok Road, R3 Hikers within the Pat Sin Leng Country Park west of the site, R4 and R5 visitors to Cheung Uk and Lei Villages, R6 Hikers on the path from Fung Yuen to Sha Lo Tung Road, R7 Hikers in Fung Yuen valley, R8 Hikers on the Wilson Trail north of the site, R9 Hikers in Pat Sin Leng Country Park North of project areas and T3 Travelers along Sha Lo Tung Road.

·            Residual visual impacts of ‘Slight’ significance will include R10 Hikers in Pat Sin Leng Country Park east of project areas.  Residential VSRs including H1 residents and Fu Heng Estate, H2 Residents in Pinehill, Yue Kok Tsuen and Tit Mei Tsai, H3 and H4 Residents in Fung Yuen village and the proposed new Fung Yuen development and H5 Residents at Ha Hang will experience ‘Slight’ visual impacts.  T1 and T2 Travelers along Ting Kok and Fung Yuen roads will also experience ‘Slight’ residual impacts.

·            All other VSRs will experience ‘Negligible’ impacts during construction.

The following residual visual impacts have been identified during at Day 1 of the operation phase:

·            At Day 1 of the operation phase, ‘Moderate’ residual visual impacts have been identified for R1 Hikers on the Wilson Trail west of the site ,R2 Cyclists along Ting Kok Road, R3 Hikers within the Pat Sin Leng Country Park west of the site ,R4 and R5 visitors to Cheung Uk and Lei Villages, R6 Hikers on the path from Fung Yuen to Sha Lo Tung Road, R7 Hikers in Fung Yuen valley and T3 Travelers along Sha Lo Tung Road.

·            Residual visual impacts of ‘Slight’ significance at Day 1 of operation will include R8 Hikers on the Wilson Trail north of the site and R9 and R10 Hikers in Pat Sin Leng Country Park north and east of project areas. 

·            All other VSRs will experience ‘Negligible’ residual visual impacts at Day 1 of operation.

·            At Year 10 of operation, ‘Slight’ impacts will remain for R1 Hikers on the Wilson Trail west of the site, R2 Cyclists along Ting Kok Road, R3 Hikers within the Pat Sin Leng Country Park west of the site, R4 and R5 visitors to Cheung Uk and Lei Villages, R6 Hikers on the path from Fung Yuen to Sha Lo Tung Road, R7 Hikers in Fung Yuen valley and T3 travelers along Sha Lo Tung road.

In accordance with Annex 10 of the EIAO-TM, the landscape and visual impacts are considered acceptable with mitigation measures.

3.8                                      Cultural Heritage

Desktop review supplemented by field survey identified that there is no declared monument within the Built Heritage Impact Assessment (BHIA) and the Archaeological Impact Assessment (AIA) assessment areas.  Hok Tau Reservoir – Cheung Uk Boulder Trackway, a site of archaeological interest recorded by the Antiquities and Monuments Office (AMO), is partly located within the Ecological Reserve.  The trackway will be retained in the Ecological Reserve and no adverse impact is anticipated.

Two graded historic buildings (Cheung Uk being confirmed as grade 2 historic building whereas Lei Uk being confirmed as grade 3 historic building), one landscape feature and five clan graves are identified within the Ecological Reserve.  They will be retained in the Ecological Reserve.  No adverse impact is anticipated.   

Five graves are identified within the Development Site, the project proponent and the grave owners have come up to an agreement that all the graves in the Development Site will be relocated.  No other cultural heritage resources are identified within the Development Site.

The archaeological impact assessment identified two pieces of artefacts dated back to Neolithic Age and Tang to Song Dynasties respectively at the southern portion of the proposed Sha Lo Tung Road Improvement.  Archaeological monitoring has been recommended during construction stage of the Sha Lo Tung Road Improvement to preserve potentially impacted archaeological resources by record.  The need and scope of the archaeological monitoring is subject to the detailed design of the construction works.

A landscape feature, an earth shrine (LF01), is identified at the southern section of the Sha Lo Tung Road Improvement.  The construction work adjacent to the shrine may affect the access to the shrine.  It is recommended that safe access of visitors to the shrine should be ensured.  A temporary fence with access entrance should be erected to prevent any direct impact to LF01 during the construction work.  Potential vibration impact will also be a concern if sheet piling works are required for laying of drainage pipes adjacent to the earth shrine.  Recommendations have been made to avoid and minimise the potential vibration impact through construction method review.  If it is considered not feasible, a vibration monitoring has been recommended.  No other built heritage resources are identified within the Sha Lo Tung Road Improvement.

3.9                                      Environmental Monitoring and Audit

Monitoring of noise, stream water quality, stream hydrology, ecology (species composition and relative abundance of riparian vegetation, adult odonate and fish communities) and cultural heritage are required during the construction phase.  Baseline monitoring will also be required prior to construction commencement to establish the baseline conditions for ecology, stream water quality and hydrology.  Post project (or construction) or operation monitoring for stream water quality and ecology will also be required. 

3.10                                  Overall Conclusion 

3.10.1                            Environmental Outcomes

The environmental impact assessment (covering air quality, noise, water quality, sewerage and sewage, waste management, ecology, landscape and visual, and cultural heritage) has concluded that no unacceptable residual environmental impacts are envisaged due to the construction and operation of the Project. 

3.10.2                            Environmental Benefit

With Project Scenario

Sha Lo Tung Development Company (SLTDC) will dedicate private housing lots (approximately 0.8 ha) and private agricultural lots (approximately 26 ha) in the Sha Lo Tung Valley and agricultural lots in the adjacent Country Park (approximately 2 ha) for conservation purposes.  An Ecological Reserve (approximately 52.5 ha) will be established on ecologically sensitive land within the Valley comprising land dedicated by SLTDC and government land.  The Ecological Reserve is anticipated to enhance to the ecology of the Sha Lo Tung Valley, achieved by preventing unauthorized incompatible activities, managing and restoring habitats at the “optimal” succession state, and by enhancing grassland and woodland habitat.  Additionally, a Nature Interpretation Centre providing nature education activities to promote awareness, appreciation and understanding of the ecological value of the area, will be built adjacent to the Ecological Reserve in the Development Site.

The conservation management and funding of the SLT Ecological Reserve will be overseen by the Government statutory fund.  The Development Site (of approximately 4.1 ha) is outside of the Country Park and Conservation Area.  Besides the Nature Conservation Centre, the Development Site accommodates the necessary development concession in the form of a Multi-Cultural Education Retreat cum Columbarium (with a development footprint of approximately 1.625 ha (includes the Nature Interpretation Centre, public parking, footpaths, landscaping areas and associated site formation) in a lower ecological value area at the entrance to the Valley.  These concession facilities provide revenue to payback the initial set up and upfront capital injected by the SLTDC to sustain long term operation of the Ecological Reserve.  Sha Lo Tung Road Improvement also lies outside of the Country Park and Conservation Area.  The existing Sha Lo Tung Road (approximately 2.3 km) will be upgraded to Single Track standard with minimum required number of passing bays to meet the requirements of the Transport Department and Fire Services Department and provide safe public access to the Ecological Reserve, Development Site and Country Park.

The Pilot Project for Public-Private Conservation Scheme, Sha Lo Tung Valley, Tai Po is proposed to be the pilot projects under the scheme of Public-Private Partnership (PPP).  This proposal establishes the framework for a public-private partnership to conserve the Sha Lo Tung Valley.  Under the current proposal, Sha Lo Tung Valley will be ensured of long-term active conservation management in which the ecologically sensitive areas currently located on private land owned by the SLTDC will be protected. 

The Development Site is located in areas of less ecological concern (mainly shrubland grassland mosaic) and avoids all of the ecological sensitive areas, including Country Park, SSSIs and Sha Lo Tung streams as well as the wet abandoned agricultural land.  Further to the detailed assessment presented in the above sections, ecological impacts due to the development (including minor works in the Ecological Reserve and widening works of Sha Lo Tung Road), no unacceptable ecological impacts are expected during the construction and operational phases. 

With the implementation of the Conservation Management Plan, human disturbance of the Ecological Reserve will be largely reduced/ controlled.  Disturbance due to hill fire, visitors and vandalism would be controlled by pro-active management, including patrolling and conservation education.  Under the Sha Lo Tung pilot project, an aggressive fire-suppression programme will be implemented to prevent the occurrence of hill fires (recently recorded within Sha Lo Tung Valley).  Rubbish and illegal traps would also be constantly removed by site managers.  As a consequence, the proposed development is expected to bring about long term ecological benefits to Sha Lo Tung Valley.

The PPP pilot scheme will not only avoid and minimise ecological impacts but will enhance the conservation value of Sha Lo Tung Valley through the following actions:

·            The project proponent has entered into mutual agreements with village representatives to divert New Territories Exempted House (NTEH) demand amounting to 160 NTEH sites outside the Sha Lo Tung valley and dedicate all its land (including 236 building lots) for conservation.  This removes large scale village expansion as a threat to the ecological integrity and conservation value of the valley; and,

·            It protects the area by controlling site access and enhances the ecological values by active management.

Without Project Scenario

The remnants of three village settlements, Cheung Uk, Lei Uk and Lo Wai, which were settled over 300 years ago, now lie abandoned surrounded by mature woodland and abandoned agricultural fields.  A recognised village burial ground exists on the eastern knoll at the entrance of the Valley.  While the villagers have left, their traditional rights to New Territories Exempt Housing (NTEH) in the Sha Lo Tung Valley, are still valid.  In 1996, the District Officer/Tai Po advised that these rights would require some 160 NTEH sites.  Under the prevailing Outline Zoning Plan No. S/NE-SLT/4, building of new NTEH house is always permitted within “Village” zone.  The building of new NTEH houses within the Sha Lo Tung Valley will increase human disturbance to the wildlife and there would also be long term associated sewerage and waste disposal impacts to the Valley.  On top of these, the villages include 240 building lots totaling some 9849.4 sq m of land, which allows development of housing as of right up to some 29,000 sq m Gross Floor Area (GFA).  Should building of new NTEH houses be permitted within SLT Valley, the potential impacts that may deteriorate the quality of the Sha Lo Tung Valley include, but are not limited to:

·            Uncontrolled surface runoff or waste water or sewage discharge may lead to deterioration of the water quality of the Sha Lo Tung perennial streams and the Sha Lo Tung SSSI (which are important odonate and fish habitats and of ecological significance) and threaten the survival of the stream fauna in particular the larval stage of the odonate community, other stream macroinvertebrates and freshwater fish;

·            Potential impacts to the surrounding habitats and ecologically sensitive areas including Country Park, SSSIs, Conservation Area and natural streams, and associated wildlife due to uncontrolled increased human activity, noise disturbance, uncontrolled lighting or hill fire within Sha Lo Tung Valley;

·            Uncontrolled or illegal dumping/ waste disposal may deteriorate the surrounding habitats and ecologically sensitive areas including Country Park, SSSIs, Conservation Area and natural streams, and impact on the associated wildlife;

·            Stream water extraction for domestic uses may affect the downstream aquatic community;

·            Potential impacts due to infrastructure and utility installation and maintenance within the Sha Lo Tung Valley; and

·            Uncontrolled fishing, vegetation collection and removal may affect the aquatic and floral communities within the Sha Lo Tung Valley.

Being served by an access road and as one of the major entrances to the Pat Sin Leng Country Park, Sha Lo Tung Area is a nodal point of a number of popular walking trails.  However, being excluded from the Country Park itself, four wheel drive enthusiasts and war-gamers have also made the abandoned villages and farmland their haven.  Illegal immigrants have also been found removing vegetation or even robbing hikers and the then remaining inhabitants (who were then operating small shops serving weekend visitors).

Despite widespread appreciation amongst the public, conservationists and the scientific community that the specialised and diverse dragonfly fauna associated with the stream course and riparian habitats here are in urgent need of active conservation, and despite of the statutory protection afforded by the Outline Zoning Plan (OZP), these and other habitats in the Valley are and continue to be abused by incompatible recreation activities.  Neglect of the site in terms of a total lack of conservation management is also taking a steady toll, with natural succession slowly but relentlessly altering the open habitats so prized by the dragonfly fauna.  Eventually these habitats will become so densely vegetated that Hong Kong will lose one of its most unique ecological settings.

Reconciling the needs of nature conservation on the one hand with human use expectations on the other can not realistically be achieved without this Project, leaving the Valley currently unmanaged and effectively unprotected.  It should also be noted that the habitat quality within Sha Lo Tung Valley is degrading due to threats such as use of four wheel drive vehicles, hill fires, wargames and vegetation removal.