1.2 Project
Scope & Implementation Program
2 SUMMARY OF KEY FINDINGS IN
EIA STUDY
2.4 Waste
Management Implications
2.8 Cultural
Heritage Impact (Terrestrial & Marine Archaeology)
2.9 Cultural
Heritage Impact (Built Heritage)
Figure 1.1 General Layout Plan of CKR
Tables
Table 1.1 Summary of Tentative Construction
Methods for Tunnel Alignment
The main objective of the proposed Central Kowloon
Route (CKR) is to relieve traffic congestion at peak hours on the existing
east-west corridors, including Lung Cheung Road, Boundary Street, Prince Edward
Road West, Argyle Street, Waterloo Road, Gascoigne Road Flyover and Chatham
Road North.
The proposed CKR will connect the West Kowloon Highway
at Yau Ma Tei Interchange
to the existing road network at Kowloon Bay as well as the future Trunk Road T2
at Kai Tak Development (KTD) and the Tseung Kwan O – Lam Tin Tunnel, thus forming a strategic
highway link to serve the existing and planned developments in West Kowloon,
East Kowloon and Tseung Kwan O. Figure 1.1 shows the CKR
alignment.
The proposed CKR will largely be in the form of a
tunnel to minimize its impact on the environment and existing buildings.
The length of CKR is approximately 4.7 km long and the tunnel section would be
approximately 3.9 km long, in particular, there will be an underwater tunnel of
about 370m long in Kowloon Bay to the north of the To Kwa
Wan Typhoon Shelter.
CKR comprises the following elements which are
classified as Designated Projects (DPs) as per Schedule 2, Part I of the Environmental
Impact Assessment Ordinance (EIAO):
·
A.1: A road which is an expressway, trunk road,
primary distributor road or district distributor road including new roads, and
major extensions or improvements to existing roads;
·
A.7: A road or railway tunnel more than 800 m in
length between portals;
·
A.8: A road or railway bridge more than 100 m in
length between abutments;
·
A.9: A road fully enclosed by decking above and by
structure on the sides for more than 100 m;
·
C.2: Reclamation works (including associated dredging
works) more than 1 ha in size and a boundary of which is less than 100 m from
an existing residential area.
·
G.5: A facility for the treatment of construction
waste
(a)
With a designed capacity of not less than 500 tonnes
per day; and
(b)
A boundary of which is less than 200m from an existing
or planned
(i)
Residential area;
(ii)
Place of worship;
(iii)
Educational institution; or
(iv)
Health care institution.
The Project also involves material changes to exempted
designated projects (existing roads), viz.
·
Re-provisioning of Gascoigne Road Flyover
·
Re-alignment of Kai Fuk Road and Hoi Wang Road
·
Widening of Lai Cheung Road
·
Re-arrange the
carriageway lines on Gascoigne Road Flyover (Ferry Street Section) and
Ferry Street
1.2
Project Scope & Implementation Program
The scope for CKR includes:
·
A dual 3-lane east-west trunk road about 4.7km long
with about 3.9km in tunnel connecting West Kowloon with the proposed Kai Tak Development (KTD);
·
Connection with Yau Ma Tei Interchange of the West Kowloon Highway and associated
road network in West Kowloon;
·
Connection to future Trunk Road T2 and associated road
network in Kowloon Bay and KTD;
·
A landscaped deck at the west portal and the structure
of landscaped decks above the depressed road at east end;
·
Demolition and/or re-provisioning of Government and
other facilities affected by CKR;
·
Re-provisioning of the section of Gascoigne Road
Flyover affected by CKR;
·
Conservation of the Yau Ma Tei Police Station;
·
Enhancement works at Yau Ma Tei and Ma Tau Kok;
·
Tunnel ventilation system and air purification system,
and associated ventilation buildings, adits and
shafts;
·
Administration building, tunnel management system and
operator facilities for the management and operation of the tunnel;
·
Traffic Control and Surveillance System;
·
Associated environmental, geotechnical, marine,
landscape, utility, drainage, traffic engineering, fire services, electrical
and mechanical works, and road works and modification works; and
·
All other works associated with the construction or
future operation of CKR.
The current implementation programme for CKR is to
commence construction in 2015 for commissioning in around end 2020.
The need for an alternative east-west traffic route across Kowloon,
particularly to cope with new developments on its western and eastern sides,
has been recognised for a number of years. Traffic congestion is now common on
many of the existing east-west surface routes, including Boundary Street,
Prince Edward Road, Argyle Street, Waterloo Road and
East Kowloon Corridor etc. A new trunk road is required
urgently to bypass traffic from these congested routes and connect directly
West Kowloon with Kowloon Bay and KTD, and thereby help relieving the traffic congestion on these
roads. If CKR does not proceed, traffic congestion would continue to worsen on
the existing east-west surface routes. Indeed, many of the existing major road
links in Kowloon are already operating close to or above capacity.
In fact, the benefits of the reduction in journey time in the above key
east-west traffic corridors could also be represented in terms of the increase
in average traffic speeds. For example, in 2021, the introduction of CKR
would allow the average traffic speed on some of these key east-west traffic
corridors to increase by up to 15kph during the peak hour. Since some of
these key east-west corridors are experiencing serious traffic congestion
during peak hour already and would probably be even more severe by 2021. The
introduction of CKR would allow the increase in average traffic speed of up to
70%, which represent a rather high percentage of increase. Since vehicular
emission would decrease as the average traffic speed increases, the
introduction of CKR would cause a decrease of emission from vehicles travelling
on these key east-west corridors. This decrease in vehicular emission would
definitely provide positive impacts on the large number of residential
buildings along these key east-west corridors, and also provide a contribution
in achieving a better air quality in the region. An estimation has been made on the
generation of nitrogen oxides, respirable suspended
particulates, carbon dioxide along these key east-west traffic corridors (see http://www.ckr-hyd.hk/pdf/044-02_English(Combined).pdf).
The proposed CKR, Trunk Road T2 and Tseung
Kwan O – Lam Tin Tunnel will form part of Route 6, which will connect West
Kowloon and Tseung Kwan O. If CKR does not proceed, it
would not be possible to complete this important strategic highway link.
The sections of the CKR that would interface with
other major projects and has the potential to lead to cumulative impacts. Expected concurrent/
interfacing projects include
·
Shatin to Central Link (Tai Wai to Hung Hom)
·
Kai Tak Development (KTD)
·
Trunk Road T2
·
Cross Bay Link
·
Tseung Kwan O – Lam Tin
Tunnel
·
Town gas submarine pipeline.
A number of alignment options have
been exhaustively considered during the design developments. The general
preferred criteria of the alignment options are that, firstly they should
connect to West Kowloon Highway at the already constructed connecting points at
the Yau Ma Tei Interchange,
secondly they should be mainly in the form of a tunnel and thirdly they should
avoid affecting private properties or public facilities, such as Yau Ma Tei Police Station, Yau Ma Tei Jockey Club
Polyclinic, to the maximum extent, if possible. A number of factors have
been considered in the alignment evaluation process, including environmental
impacts, engineering considerations and public views etc.
For the western portion of the alignment, the selection of the preferred
alignment is adopted since 1) The alignment will avoid the old wing of the Yau Ma Tei Police Station on the
north side of Kansu Street and also avoids the old residential buildings on the
south side of Kansu Street; 2) The alignment avoids any impact on private land
in this area. In addition the
vertical alignment is developed so as to pass under the MTRC Tsuen Wan Line and Kwun Tong Line
Extension tunnels; 3) The side-by-side cut-and-cover tunnel construction
is found to be the most engineering feasible of the options considered with a
relatively low depth and reasonable construction area. For the eastern
portion of the alignment, the preferred alignment would have the shortest marine tunnel section and
therefore generate the least amount of excavated sediment to be disposed of and
would have the least water quality impact to the surrounding waters.
Site-specific construction
methodologies have been developed comprising different tunnelling
methods, including cut-and-cover tunnel, drill-and-break tunnel,
drill-and-blast tunnel and underwater tunnels. With reference to the
longitudinal and geological profile of CKR, the cut-and-cover tunnels sections
at both portions of the tunnel will involve excavation of soil (fill) materials
using non-percussive method while the central portion of tunnel will be
accomplished by the traditional drill-and-blast (D&B) method within strata
of the bedrock at more than 30 m below ground. A summary of the
construction methods for the tunnel alignment is given in the table
below. Other than the tunnel sections, other approach roads, ventilation
buildings, landscaped decks etc would be constructed using conventional
approach.
Table 1.1: Summary of Tentative
Construction Methods for the Tunnel Alignment
Section |
Form |
Tentative Construction Method |
Selection Reason |
Yau
Ma Tei (from Hoi Wang Road to Shanghai Street) |
Tunnel |
Cut-and-Cover |
· To facilitate connection between drill-and-break
tunnel and depressed road. |
Yau
Ma Tei (Shanghai Street to The Regalia) |
Tunnel |
Drill-and-Break / Drill-and-Blast
Tunnel |
·
To facilitate the
geotechnical condition of the adjacent underground areas ·
To minimize impact to
adjacent public transport systems such as Tsuen Wan
Line and the proposed Kwun Tong Line Extension |
Ho Man Tin, To Kwa
Wan & Ma Tau Wai (The Regalia to San Ma Tau
Street) |
Tunnel |
Drill-and-Blast |
· To facilitate the geotechnical condition of the
adjacent underground areas. |
Kowloon
City Ferry
Pier Public Transport
Interchange |
Tunnel |
Cut-and-Cover |
·
To facilitate connection
between drill–and-blast tunnel and underwater tunnel. |
Kowloon Bay |
Tunnel |
Cut-and-Cover with temporary reclamation |
· The only viable construction method
for underwater tunnel. |
Ex-Kai Tak Runway |
Tunnel |
Cut-and-Cover |
·
To
facilitate connection between underwater tunnel and the east end tunnel
portal before comes to the depressed road section. |
2.1.1
Construction
Phase
Potential dust impact would be generated
from the soil excavation activities, backfilling, site erosion, storage of
spoil on site, transportation of soil, etc. during the construction of CKR.
Quantitative fugitive dust
assessments have been conducted, taking into account the cumulative impact
caused by nearby concurrent project. Effective dust control following the
requirements given in the Air Pollution Control (Construction Dust) Regulation
and in accordance with the EM&A programme during construction are
recommended. Assessment results
suggested that watering at site once per hour would be required to control the
fugitive dust impact to acceptable levels.
2.1.2
Operational
Phase
A
quantitative air quality assessment has been conducted to assess the cumulative
impacts from all neighbouring pollution sources. The assessment has been
determined according to the EIA Study Brief and concluded to be 2021 which is
the first operational year. The PATH model has been adopted to simulate the
regional air quality effects, which has included various pollution sources in Hong Kong and the
Pearl River Delta Economic Zone (PRDEZ). For the emission inventory in
Hong Kong, various sources have also been included in the PATH model, including
the including the power stations, Chek Lap Kok International Airport, marine emission, roads.
For
the road networks associated with the CKR, the
vehicular emission has been estimated by using a finer model EmFAC – HK (ver. 2.1),
whilst CALINE4 and ISCST3 models have been used to simulate the local
dispersion. The output of PATH, CALINE and ISCST have been combined and
compared against the Hong Kong Air Quality Objectives (HKAQO). The
combined results indicate that the cumulative air quality impacts at the
identified receivers would comply with the HKAQO and hence there would not be
any adverse residual impacts.
2.2.1
Construction
Phase
Potential construction airborne noise impacts
would be caused by various construction activities including excavation,
backfilling and construction of approach road and associated ventilation
buildings, etc.
Construction noise assessment has concluded that the unmitigated
construction noise impacts would be high at some NSRs. Suitable noise mitigation measures have
therefore been identified which could reduce the noise impacts at most of the
NSRs. In view of works that will be
carried out close to sensitive uses, especially in the West Portion, a number
of alternative construction methodologies have been considered to alleviate the
noise impact. These include the use of
top-down approach to enable earlier decking of the cut-and-cover tunnel
sites. The top slab thus constructed would contain noisy works activities to
continue underneath.
Careful selection of
construction equipment and working methods including the use of quiet plant is
adopted, where practicable has also been considered. Moreover, good site practice, the use of site hoarding, installation of movable
barriers and sequential operation of construction plant have also been
recommended. The predicted noise levels at most of the NSRs would comply with
the corresponding noise criteria, except for a few NSRs near the works areas
e.g. Kansu Street at West Portion, Chung Hau Street
at Central Portion and San Ma Tau Street at East Portion. According to the
current construction methodology, mucking-out points will be located in west,
central and east portion. Since the mucking out activities will be located in
the vicinity of residential premises, large full noise enclosures
would be adopted for these three mucking out points to minimize the potential
construction noise generated by the construction activities. All practicable mitigation measures are
exhausted and the impacts are minimised.
Potential construction groundborne
construction noise impacts may arise from tunnel boring activities. Groundborne noise assessment has therefore been conducted
for tunnel areas in West Portion, Central Portion and
East Portion. Predicted results
suggested that construction groundborne noise levels
will be within the statutory requirements and mitigation measures are not
required.
2.2.2
Operational
Phase
Noise impact during the operational phase of the
project include those from existing and planned road networks in the
vicinity, and the fixed plant such as ventilation system.
Without mitigation measures, the predicted road noise levels at most
representative NSRs would exceed the criteria.
With the implementation of the proposed direct noise mitigation
measures, including low noise road surfacing, combination
of vertical noise barrier, cantilevered section noise barrier, semi-enclosure
and full enclosure, compliance of EIAO criteria is achieved. However, given the noise environment, some of
the NSRs are dominated by the traffic on existing roads instead of the planned roads, exceedance is still
predicted at some NSRs. These NSRs
include those along Nathan Road, Ferry Street and West Kowloon Highway in West
Portion and Kai Fuk Road and other planned roads (D2,
D3 and T2) in East Portion. Indirect
noise mitigation measure in term of building orientation of planned schools in
West and East Portions to avoid direct facing the CKR is recommended. With all the practicable mitigation measures
within the context of this study, the noise contribution at these NSRs due to
this project would be controlled to within 1.0dB(A).
Fixed noise sources during the operational phase would be the
ventilation buildings. Operational noise impacts can be effectively mitigated
by implementing noise control treatment (e.g. acoustic silencers) at source during
the design stage to ensure compliance of the stipulated noise criterion.
The potential water quality impacts arising from the construction and
operation of the CKR have been assessed. The key focus is on the construction
of the proposed underwater tunnel in Kowloon Bay.
During construction phase, a pipepile seawall
method will be applied for the temporary reclamation. Excavation and filling
activities will be carried out within pipepile
seawall. Dredging activities will only be carried out during the re-location of
navigation channels. The assessment has also included the potential water
quality impacts due to other concurrent dredging activities.
Delft3D model was used in the quantitative assessment to study the
potential water quality impacts on different types of WSRs including cooling
water intakes and WSD flushing water intakes, as well as meeting the water
quality objectives (WQOs). Pollutants of concern include suspended solids (SS),
dissolved oxygen (DO) depletion, ammonia nitrogen, and SS elevation. It has
also included selected metals, total Polyaromatic
Hydrocarbons (PAH), unionized ammonia (UIA), and total inorganic nitrogen (TIN)
with potential release during dredging.
Mitigation measures such as use of silt curtains, reduction of dredging
rates, additional silt screen at seawater intakes, good site practices, etc,
were proposed. Modeling results indicate that most of
the parameters would be well within the respective criteria after
implementation of mitigation measures, except the Cu and total PAH levels at
WSR 3 (To Kwa Wan Typhoon Shelter) will exceed the
criteria proposed by the Australian Water Quality Guidelines for Fresh and
Marine Waters. However, these criteria are for protection of
irrigation/aquaculture and fresh water aquatic ecosystem respectively which is
under a conservative side. While WSR 3 is a typhoon shelter only and its
function are neither ecological importance nor for portable use, such exceedances will not deteriorate the existing functions of
WSR 3. In addition, the impact will be reversible since the dredging period
will be only last for 2 months. To ensure the effectiveness of the
mitigation measures, regular water quality monitoring in the Kowloon Bay and
its vicinity are recommended during the dredging periods.
During operational phase, adverse
water quality impact is not anticipated with the implementation of proper mitigation
measures for road runoff and wastewater from APS.
2.4
Waste Management Implications
The potential impacts of wastes arising from the construction and
operation of the Project have been assessed. The construction activities will
generate a variety of wastes including vegetation from site clearance,
excavated materials including soil and rocks, construction and demolition
(C&D) wastes, chemical and municipal wastes, etc.
There will be about 0.88 Mm3 of Grade I/II rocks generated from bored tunnelling. They are expected
to be of good quality and hence can be sent to quarry for re-use. The remaining
surplus C&D materials requiring disposal will amount to about 2.57 Mm3. This comprises 0.014Mm3 of non-inert C&D materials to be landfilled
and the remaining 2.56 Mm3 as public fill. The
quantity of inert C&D materials to be reused within the project is subject
to the availability of temporary stockpile area (TSA) and the project proponent
will continue to explore the feasibility to setting up TSA so as to maximize
the reuse of inert C&D materials.
The total volume of dredged/ excavated materials arising from the
Project is estimated at 218,894 m3, in which 500 m3 of land-based sediment is proposed to be reused for backfilling of pile caps of viaduct piers
with low headroom under the same project. The
amount of dredged sediment requiring disposal will be 218,394 m3. Out of the total 218,894 m3 of dredged/ excavated materials, 42,254 m3 of which will arise from construction of the
cut-and-cover tunnels at Yau Ma Tei,
and Ma Tau Kok where deep excavations can disturb
part of the sediment in the previously reclaimed areas as well as sediment that
could be disturbed by foundation works for piers of the connecting flyover/
elevated slip roads in the West Portion.
The amount of sediment expected from excavation in the temporary
reclamation has been estimated at 176,640 m3. In terms of sediment quality, the marine investigation results have
indicated that the footprint for the underwater tunnel and the fairway is
heavily contaminated with organic PAHs. The contamination by heavy metals is
also a key concern since exceedance of UCEL was
commonly found. All 4 types of disposal options have been recommended in line
with ETWB TCW No. 34/2002. Given the amount of C&D materials that will be
generated, it should be managed properly so that timely disposal arrangement
can be made. The C&D Materials Management Plan (“C&DMMP”) and the Waste
Management Plan (“WMP”) should be enforced by incorporating them as part of the
contract requirements.
Provided that the recommended waste management practices are
implemented, potential impacts on the environment associated with waste
generated during the construction phases of the Project should be surmountable.
A land contamination assessment has been conducted in order to
investigate the land contamination impact arising from works of the CKR
especially at sites coincide with the cut-and-cover tunnel alignments at both
portions. The middle section of the CKR tunnel is entirely created in rock by
drill-and-blast method and will not involve excavations through the ground
surface and hence is not going to be affected by any contaminated soil.
Based on the testing results
collected from the site investigation works conducted in 2009, exceedances of the relevant Risk-Based Remediation Goals
(RBRGs) limits have been detected at 3 boreholes including PBH4 and PBH5 in Yau Ma Tei and PBH7 in Ma Tau Kok. Based on the confirmatory investigation conducted in
2011 and 2012, the contamination extent at PBH4 has been determined and the
quantity of contaminated soil to be generated from PBH4 was estimated at 157m3.
Considering the small quantity of contaminated soil to be generated from
PBH4 and that the level of contamination detected did not exceed the RBRGs for
“Public Park” which is a more representative
land use for CKR, on-site reuse of the contaminated soil within the boundary of
CKR, such as using
to backfill in non-pedestrian use area under new flyover, would be recommended
as the remediation option for the contaminated soil.
Investigation of contamination
extents at PBH5 is not required as this borehole is located outside the CKR
alignment and does not fall within the excavation extent. For PBH7, since the
SI works could not be completed for 2 boreholes (EBH1 and EBH2) which are
intended to confirm the extent of the contamination detected at PBH7, the
contamination extent of PBH7 could not be determined at this stage.
The remaining SI works will be conducted at a later stage e.g. after
site possession and utility diversion by the construction contractor. Following
the completion of the remaining SI works, the Project Proponent would prepare
and submit a Second Supplementary CAR/RAP to EPD to present the
findings of the SI works and to recommend specific remediation measures, if
required. Upon completion of the remediation works, if any, a Remediation
Report (RR) would be prepared and submitted to EPD for agreement prior to
commencement of the construction works.
Nevertheless, the contamination issue is anticipated to be surmountable
with the supportive view that the contamination identified are relatively
localised, likely contaminants are generic and easily remediated as remediation
methods available in the market are well established and nature of the possible
contaminants can be dealt with by sufficient local remediation experience.
Considering that CKR will pass through very hard granite that could
cause extreme wear and tear to a Tunnel Boring Machine (TBM) and cause
excessive downtime, drill-and-blast method is considered most practicable and
effective method for constructing the bored tunnel section of CKR. A
Quantitative Risk Assessment (QRA) for transport and use of explosives during
construction of the CKR has been carried out as per the EIA Study Brief No.
ESB-156/2006 (EIA Study Brief) in terms of individual risk and societal risk
criteria stipulated in Annex 4 of the Environmental Impact Assessment Ordinance
Technical Memorandum (TM-EIAO).
Explosives have been identified as the major hazardous source in the
Project. The use of explosives and its delivery by approved trucks are the two
main issues addressed in the assessment.
For delivery of explosives, feasible routes have been identified. By
taking into account blasting schedule and consumption of explosives at different
period of time, frequency of accidental detonation of explosives and
consequence of detonation have been assessed using reasonably conservative
data. Impact of accidental detonation on indoor and outdoor population has been
considered.
For use of explosives, simultaneous accidental detonation of up to 6
maximum instant charge (MIC) due to human errors has
been considered. Frequencies for human errors leading to higher ground
vibrations have been derived using Human Error Assessment & Reduction Technique
(HEART) and Fault Tree Analysis. Sensitive receivers such as buildings and
structures potentially affected by excessive ground vibrations have been
identified. Impact of accidental detonation during transport in the underground
tunnel has also been assessed. It is found that none of the sensitive receivers
is anticipated to be subject to serious structural damage in case of accidents.
Failure of slopes is found to be highly unlikely.
During the design development of the Project, the originally proposed
fresh air supply ventilation building at the junction of To Kwa
Wan Road and San Ma Tau Street has been removed to eliminate the potential draw
in of accidental towngas release into the CKR tunnel
during operation of CKR.
The assessment results indicate the risk is acceptable in terms of
individual risk and societal risk. It is concluded that the risk associated
with the transport and use of explosives for the CKR project satisfies the Hong
Kong Government Risk Criteria set out in Annex 4 of the TM-EIAO. Hence, the
hazard to life impact due to the construction and operation of the CKR project
is considered acceptable.
As the majority of the
CKR is located underground, landscape and visual impacts would be restricted to
above ground construction works and operational facilities only. It is
considered there will be no substantial adverse landscape and visual impacts to
the surround sensitive receivers during the operation phase.
Based on the 2010
Tree
Survey, about 1304 trees will be
affected by the works and need to be removed by felling or transplanting, while
approximately 2812 will be retained. The
2010 Tree Survey estimated approximately 163 trees would be suitable for transplanting
and approximately 1141 trees will not be suitable for transplanting and would
therefore require felling. Due to the Project re-alignment and other projects
development (e.g. XRL), the number of trees affected by the CKR Project has
reduced since the 2010 Tree Survey. An updated Tree Survey will be carried out
(due to commence mid 2013) and tree treatments will only be finalised during
the Tree Removal Application.
For trees unavoidably
affected by the Project that have to be removed, where practical,
transplantation will be chosen as the top priority method of removal but if
this is not possible or practical (e.g. the tree is too large or has a low
survival rate), compensatory planting will be provided for trees unavoidably
felled. The felled trees will be compensated for mainly within the Project
Boundary including on the future landscape deck near the western tunnel portal
but it is likely that it will be necessary to agree additional receptor sites
for some compensatory trees (and possibly transplanted trees). Using worst case
scenario numbers, current estimates predict additional receptor sites will be
required for approximately 550 trees but given the reduced numbers of trees now
affected by the Project, particularly in the West Portion, this number is
likely to be reduced.
No Registered Old and
Valuable Trees are located within the Works Area and none of these affected
trees are LCSD champion Trees or Registered Old and Valuable Trees, neither are they rare or endangered species, but mainly common
exotic trees. All the trees with high amenity values that are unavoidably
affected by the works would be transplanted where possible. Detailed tree
preservation, transplanting and felling including compensatory planting
proposals will be submitted to the relevant Government Department for approval
in due course in accordance with ETWB TC no. 3/2006.
Part of the public
open spaces within the works area will be permanently taken by connection road,
tunnel portal, ventilation building or re-provisioned community facilities,
particularly in the West Portion. All areas of public open space affected by
the Project will be re-provisioned either at the same location following the
completion of temporary works, or at a separate site, as agreed with relevant
Government departments and under the proposed development. Overall more public open space will be
re-provisioned/ reinstated than is taken during construction providing a net
benefit to the regional environment.
A number of Landscape Resources (LRs) in the East Portion
are also considered to benefit from the Project once mitigation measures have
been implemented. These include Roadside Planting along
Impact on Landscape Character Areas (LCAs) during construction would be
primarily due to construction activities including associated temporary works
for the construction of cut-and-cover tunnel, ventilation and administration
buildings and connecting roads. After implementation of mitigation measures,
there would be moderate adverse residual impacts on the Transport Corridor
Landscape (LCA1.1) in the West Portion the Typhoon Shelter (LCA3.4) and and Transportation Corridor Landscape (LCA3.5) in the East
Portion during construction. The rest of the LCAs would experience slight or
insignificant adverse residual impacts at this stage. With the implementation
of mitigation measures, at the design year (operation year 10), impacts from
the Project on all the LCAs would be insignificant.
Visual impact during the construction phase would be primarily due to
construction activities such as excavation for cut and fill, piling and
demolition of existing buildings as well as actual construction of new
structures such as the ventilation and administration buildings, depressed and
connecting roads and tunnel portals including landscape deck. With
implementation of mitigation measures during construction, there would still be
some substantial impacts on VSRs adjacent or close to the CKR especially
residential and GIC Visual Sensitive Receivers (VSRs) while adverse residual impacts on VSRs further away from the works would be moderate to
slight except for those who will be shielded from the view by future
development in the former Kai Tak Airport area and
not be affected by the Project. After the implementation of mitigation measures in operation year 10, visual impacts on all VSRs will be
insignificant with the exception of some slight adverse visual impacts on
residential and GIC VSRs that are close to the tunnel portal in the West Portion.
Considerable effort has been made to integrate the CKR with KTD and
overall the former
Overall, it is considered that the adverse residual landscape and visual
impacts of the proposed Project are considered as acceptable with mitigation
measures during construction and operation phase.
2.8
Cultural Heritage Impact (Terrestrial & Marine
Archaeology)
Terrestrial
Archaeology
A baseline study on terrestrial archaeology has been conducted
comprising desk-top research and site visits. The findings of the study have
indicated that the impacted areas are of no or very low archaeological
potential. As no adverse impacts are expected to arise from the Project,
mitigation measures are not considered necessary. As a precautionary measure, the Antiquities and
Monuments Office should be informed immediately in case of discovery of
antiquities or supposed antiquities during the construction.
Marine Archaeology
A Marine Archaeological Investigation (MAI) of the seabed has been
carried out to identify any potential impacts that may be caused by the
construction of the underwater tunnel between Kowloon City Ferry Pier and the
Kai Tak runway.
The purpose of the MAI was to locate and assess underwater
archaeological resources, which may be damaged by the Project. In accordance
with AMO Guidelines, the MAI has included a Marine Archaeological Review,
Baseline Review, Geophysical Survey and
Underwater Diver Survey. The Baseline Review also included examination of
earlier MAI reports covering the study area.
The first phase of the MAI was completed in 2008. The MAI Baseline Review established high marine archaeological potential
for Kowloon Bay. The 2008 geophysical survey located 8 unknown seabed objects. Diver
inspection of them identified them as modern dumped debris.
As the design has developed in 2012, additional dredging is required and
hence additional geophysical survey was conducted. The two MAI surveys together combine to
provide 100% coverage of the study area.
The
2012 geophysical survey located 36 unknown seabed objects. Diver inspection of 28 of them identified
them as modern debris with no archaeological value. The eight objects that were not practicable to
inspect were deemed to have low archaeological potential due to their location
underneath the disused fuel dolphin which is a current
work site creating debris.
A watching brief is therefore not required during dredging. However, contractor should be alerted during the
construction on the possibility of locating archaeological remains, such as
cannon and AMO shall be informed immediately in case of discovery of antiquities
or supposed antiquities in the subject sites.
2.9
Cultural Heritage Impact (Built Heritage)
A baseline study comprising a desk-top study and a built heritage field
survey has been conducted to identify if there is any built heritage resources
within the Study Area that could be affected by the Project. The study has
identified 9 graded or proposed
graded historical buildings and 9 structures with
heritage value. There are no government historic (GH) sites or declared
monuments identified within the Study Area. The construction and operation of
the CKR tunnel and road network will not cause any insurmountable adverse
impacts if proper protection measures and ground-borne vibration monitoring are
implemented. These measures include:
Yau Ma Tei Police Station
New Wing
The proposed works will directly impact on the Yau
Ma Tei Police Station Compound. The 1-storey
kitchen
and laundry block and the car port are recommended to be demolished and an underpinning scheme
will be implemented for the new wing. There are no direct impacts to the old
wing, however, as the old wing and new wing are extremely close to the
works, an engineering study has been conducted and considered that the most
effective means of ensuring no damages to the structures during the
construction period of the CKR is by underpinning the new wing prior to
commencement of construction works. Once implemented, the underpinning will
become a permanent part of the structure. The old wing however does not required
to be underpinned.
As the construction works will be expected to be close to the new wing,
the following mitigation measures are recommended to be undertaken:
·
A protective covering should be provided for the
buildings in the form of plastic sheeting;
·
Buffer zones should be provided between the
construction works and the external walls of the buildings. The buffer zones
should be as large as site restrictions allow and shall be marked out by
temporary fencing or hoarding.
·
The Alert, Alarm and Action (AAA) settlement and
tilting limit should be 6/8/10 mm and 1/2000, 1/1500 and 1/1000.
·
Monitoring of vibration levels will be undertaken
during the construction phase and the AAA vibration limit will
be set at 5/6/7.5 mm/s.
·
A monitoring proposal will be prepared and submitted
to AMO.
Regular site inspections and monitoring
works will be carried out by the contractor and the monitoring results will be
submitted to the resident site staff of HyD to ensure
compliance.
Old Wing
The
mitigation measures will include the use of a diaphragm wall construction
method and providing a grout curtain in front of the building.
·
The Alert, Alarm and Action (AAA) settlement and
tilting limit should be 6/8/10 mm and 1/2000, 1/1500 and 1/1000.
·
Monitoring of vibration levels will be undertaken
during the construction phase and the AAA vibration limit will
be set at 5/6/7.5 mm/s.
·
A monitoring proposal will be prepared and submitted
to AMO.
With the
above measures, it is anticipated that effect on the building will be
controlled to an acceptable level.
Regular site inspections and monitoring
works will be carried out by the contractor and the monitoring results will be
submitted to the resident site staff of HyD to ensure
compliance.
1-storey kitchen and laundry block and the car port
The 1-storey kitchen and laundry block
and the car port are of low heritage and architectural
value, demolition is an acceptable impact and no mitigation is required.
Boundary Wall and Vehicular Entrance of the New Wing
The existing boundary wall and vehicular
entrance gate of the New Wing are of low heritage and architectural value,
demolition is an acceptable impact and no mitigation is required.
The Tin Hau Temple at Yau Ma Tei
Monitoring of vibration levels will be undertaken during the
construction phase and the AAA vibration limit will be set at
3/4/5 mm/s.
A condition survey shall be carried out by the Project
Proponent
prior to the construction phase.
With the above measures, it is anticipated that effect on the buildings will
be controlled to an acceptable level.
Kowloon Methodist
Church & Ma Tau Kok Animal Quarantine Depot
Monitoring of vibration levels will be undertaken
during the construction phase and the AAA vibration
limit will be set at 5/6/7.5 mm/s.
The vibration
monitoring proposal will be submitted to AMO for comment.
With the above measures, it is anticipated that
effect on the buildings will be controlled to an acceptable level.
Kowloon City Ferry Pier and Kowloon City
Vehicular Ferry Pier
A monitoring system for settlement, vibration and tilting will be
determined and implemented pending determination of the future grading.
Ma Tau Kok
Public Pier
No mitigation
is required at present. If the public pier is granted Grade 1, Grade 2 or Grade
3 status, the mitigation will be revised to adhere to the requirements for
protective measures for Graded Historic Buildings.
Kowloon Permanent Pier No. 70
The pier
contains active gas pipelines and will be strictly monitored for safety
precautions during the works based on guidelines from the HK China Gas Company.
It is concluded that these guidelines will provide sufficient protection for
the pier structure and no additional precautions from a heritage perspective
would be required. However, if the pier is granted Grade 1, Grade 2 or Grade 3
status, the mitigation will be revised if necessary, to adhere to the requirements for protective
measures for Graded Historic Buildings.
Air Raid Precaution
Tunnels of the K1 Network
A condition survey for the tunnel network should be undertaken by the Project Proponent to determine the present condition of the air raid
tunnels and to recommend protective measures to ensure that the tunnels are not
damaged by the construction works and as such appropriate vibration monitoring
on the tunnel should be complied with as appropriate.
An EIA Report has been prepared
to fulfil the requirements as specified in the EIA Study Brief No ESB-156/2006 and the TM-EIAO. All the latest design information has been incorporated
into the EIA process. The aspects that have been considered in this EIA Report
include:
·
Alignment
evaluation;
·
Description
of construction and operational activities;
·
Air
Quality impact;
·
Airborne
noise impact;
·
Groundborne noise impact;
·
Water
quality impact;
·
Waste
management implications;
·
Land
contamination impact;
·
Impact
on hazard to life;
·
Landscape
and visual impact;
·
Impact
on cultural heritage; and
·
EM&A
requirements
Overall, the EIA Report has predicted
that the Project would be environmentally acceptable and individual impacts are
minimized with the implementation of the proposed mitigation measures for
construction and operational phases. An environmental monitoring and audit
programme has been recommended to check the effectiveness of recommended
mitigation measures.