Contents

 

1            INTRODUCTION   1

1.1           Background  1

1.2           Purposes of the Manual 2

2            Project Description  4

2.1           General Alignment 4

2.2           Summary of Design  5

2.3           Implementation Programme  5

2.4           Concurrent Projects  5

3            Project Organization  9

3.1           Project Organization  9

4            Environmental Submission  11

4.1           Introduction  11

4.2           Environmental Management Plan  11

4.3           Waste Management Plan  11

4.4           Construction Method Statement 12

5            Air Quality Impact 13

5.1           Introduction  13

5.2           Mitigation Measures  13

5.3           Air Quality Parameters  13

5.4           Monitoring Equipment 13

5.5           Laboratory Measurement / Analysis  15

5.6           Monitoring Locations  15

5.7           Baseline Monitoring  16

5.8           Impact Monitoring  17

5.9           Action / Limit Levels  17

5.10         Event and Action Plan  19

6            Noise Impact 22

6.1           Introduction  22

6.2           Mitigation Measures  22

6.3           Noise Monitoring Parameter and Monitoring Equipment 24

6.4           Construction Noise Impact 25

6.5           Operational Noise Impact 30

7            Water Quality Impact 32

7.1           Introduction  32

7.2           Mitigation Measures  32

7.3           Performance Review for Stone Column Installation  32

7.4           Monitoring Locations  32

7.5           Monitoring Parameters  33

7.6           Baseline Monitoring  33

7.7           Impact Monitoring  34

7.8           Monitoring Equipments  35

7.9           Laboratory Measurement / Analysis  37

7.10         Action and Limit Levels  38

7.11         Event and Action Plan  39

8            Waste Management Implications  42

8.1           Introduction  42

8.2           Waste EM&A Requirements  42

9            Land Contamination Impact 44

9.1           Introduction  44

9.2           Excavation of the Contaminated Soil 44

9.3           Closure Assessment 44

9.4           Protective and Safety Measures  45

9.5           Remediation Report 45

10          Hazard to Life  46

10.1         Introduction  46

10.2         Mitigation Measures  46

11          Landscape and Visual Impact 47

11.1         Introduction  47

11.2         Mitigation Measures  47

11.3         Audit Requirement 48

12          Impact on Cultural Heritage (Terrestrial and Marine Archaeology) 52

12.1         Introduction  52

12.2         Mitigation Measures  52

13          Impact on Cultural Heritage (Built Heritage) 53

13.1         Introduction  53

13.2         Mitigation Measures  53

13.3         Audit Requirements  55

14          Site Environmental Audit 57

14.1         Site Inspection  57

14.2         Environmental Compliance  58

14.3         Choice of Construction Method  58

14.4         Environment Complaints  59

15          Reporting  60

15.1         General 60

15.2         Baseline Monitoring Report 60

15.3         Monthly Monitoring Reports  61

15.4         Final EM&A Review Reports  65

15.5         Data Keeping  67

15.6         Interim Notifications of Environmental Quality Limit Exceedances  67

 

 

 

Figures

 

Figure 1.1         General Layout Plan of CKR

Figure 2.1         Location of Concurrent Projects

Figure 5.1         Location of Construction Dust Monitoring Stations (West Portion)

Figure 5.2         Location of Construction Dust Monitoring Stations (Central Portion)

Figure 5.3         Location of Construction Dust Monitoring Stations (East Portion)

Figure 6.1         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (West Portion) (Sheet 1 of 5)

Figure 6.2         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (West Portion) (Sheet 2 of 5)

Figure 6.3         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (West Portion) (Sheet 3 of 5)

Figure 6.4         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (West Portion) (Sheet 4 of 5)

Figure 6.5         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (West Portion) (Sheet 5 of 5)

Figure 6.6         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (East Portion) (Sheet 1 of 3)

Figure 6.7         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (East Portion) (Sheet 2 of 3)

Figure 6.8         Location of Proposed Noise Mitigation Measures for Road Traffic Noise (East Portion) (Sheet 3 of 3)

Figure 6.9         Location of Noise Monitoring Stations (West Portion) (Sheet 1 of 2)

Figure 6.10       Location of Noise Monitoring Stations (West Portion) (Sheet 2 of 2)

Figure 6.11       Location of Noise Monitoring Stations (Central Portion)

Figure 6.12       Location of Noise Monitoring Stations (East Portion)

Figure 7.1         Location of Water Monitoring Stations for Baseline and Construction Phase Monitoring

Figure 9.1         Estimated Contamination Zone at PBH4

Figure 13.1       Location of Built Heritage Resources in Yau Ma Tei Required Mitigation Recommendations

Figure 13.2       Location of Built Heritage Resources in Ma Tau Kok Required Mitigation Recommendations

 

Tables

 

Table 2.1          Summary of Design of CKR

Table 2.2          Summary of Potential Concurrent Projects

Table 5.1          Construction Dust Monitoring Locations

Table 5.2          Action / Limit Levels for Air Quality

Table 5.3          Event / Action Plan for Air Quality

Table 6.1          Noise Mitigation Measures for Operational Phase

Table 6.2          Proposed Airborne Construction Noise Monitoring Locations

Table 6.3          Action / Limit Levels for Construction Noise

Table 6.4          Event / Action Plan for Construction Noise

Table 6.5          Proposed Operational Noise Monitoring Locations

Table 7.1          Water Quality Monitoring Stations for Baseline and Construction Phase Monitoring

Table 7.2          Proposed Water Quality Monitoring Programme

Table 7.3          Proposed Water Quality Monitoring Programme

Table 7.4          Laboratory Analysis for Various Water Quality Parameters

Table 7.5          Action / Limit Levels for Water Quality

Table 7.6          Event / Action Plan for Water Quality

Table 9.1          Acceptance Criterion for the Closure Assessment

Table 11.1        Event / Action Plan for Design Plan

Table 11.2        Event / Action Plan for Landscape and Visual during Construction Phase

Table 13.1        Mitigation Recommendations for Yau Ma Tei Police Station (Construction Phase) of CKR

Table 13.2        Mitigation Recommendations for Other Impacted Heritage Features (Construction Phase) of CKR

Table 13.3        Audit Requirements and Frequency

 

 

Appendices

Appendix A

Construction Programme

Appendix B

Project Organization for Environmental Works

Appendix C

Environmental Mitigation Implementation Schedule

Appendix D

Sample Data Sheet for Monitoring

Appendix E

Performance Review Proposal for Stone Column Installation

Appendix F

Sample Template for Interim Notification

Appendix G

Proactive Environmental Protection Proforma

 

 

 

 


1                                INTRODUCTION

1.1                         Background

The need for additional traffic capacity on the east-west road links across central Kowloon, particularly for coping with the new developments on its western and eastern sides, has been recognized for a number of years. Since 1990, it was proposed in the West Kowloon Reclamation Transport Study that a route in tunnel, which is known as the Central Kowloon Route (CKR), should be developed to link the West Kowloon Highway with the future highway system.

Highways Department (HyD) commissioned the Design and Construction Assignment for the Central Kowloon Route in June 1998.  An alignment study, preliminary design and impact assessments were carried out without proceeding to the detailed design or construction phases due to substantial changes in scope of CKR.  The study was based on a dual two-lane configuration. Its findings indicated the need for resumption of some residential buildings in the vicinity of Bailey Street in To Kwa Wan and included an outline proposal for Re-provisioning of some government and community facilities in Yau Ma Tei.  These facilities included Yau Ma Tei Police Station, Kowloon Government Offices, Yau Ma Tei Multi-storey Carpark Building, Yau Ma Tei Jockey Club Polyclinic Building and Specialist Clinic Extension Building, Yau Ma Tei Jade Hawker Bazaar, public toilet and refuse collection point adjoining Temple Street, and other minor facilities.

In March 1999, Government confirmed that a toll plaza for CKR would no longer be necessary.  This removed a major constraint on the vertical alignment of CKR at the east portion.  The alternative alignment options for CKR were then re-examined taking into account the updated planning of the then South East Kowloon Development for reduced scale of reclamation.  In August 1999, HyD commissioned a further study to investigate alternative routes to the east of Ho Man Tin with a view to minimise resumption of residential properties while dovetailing with the overall planning of the road network in the then SEKD.  The study recommended a new alignment running through the bus terminus at Kowloon City Ferry Pier, which could avoid resumption of residential buildings.

Agreement No. CE 58/2006 (HY) – Central Kowloon Route and Widening of Gascoigne Road Flyover – Investigation was commissioned by HyD in August 2007 to conduct the investigation and preliminary design of the CKR (in dual 3-lane configuration) and Widening of GRF projects.

On 30 June 2011, HyD appointed the Arup – Mott MacDonald Joint Venture (AMMJV) under Agreement No. CE43/2010(HY) to provide consultancy services in respect of Central Kowloon Route – Design and Construction (the Assignment). This consultancy also includes the compilation of an Environmental Impact Assessment (EIA) Report to fulfil the relevant legislative requirements.

 

Through a number of studies and verifications of engineering feasibility, CKR is now a proposed dual 3-lane trunk road across central Kowloon linking the West Kowloon in the west and the proposed Kai Tak Development (KTD) in the east. The CKR will be about 4.7 km long with an underground tunnel section of about 3.9 km long, in particular, there will be an underwater tunnel of about 370 m long in Kowloon Bay to the north of the To Kwa Wan Typhoon Shelter. It will connect the West Kowloon Highway at Yau Ma Tei Interchange with the road network at Kowloon Bay and the future Trunk Road T2 at KTD which will connect to the future Tseung Kwan O – Lam Tin Tunnel (TKO-LTT) and Cross Bay Link (CBL). CKR, Trunk Road T2 and TKO-LTT will form a strategic highway link, namely Route 6, connecting West Kowloon and Tseung Kwan O. Consultancy studies for Trunk Road T2, TKO-LTT and CBL have been commissioned by CEDD. In addition, 3 ventilation buildings, which will be located in Ya Ma Tei, Ho Man Tin and ex-Kai Tak airport area, are proposed to ensure acceptable air quality within the tunnel.

The Project would involve temporary reclamation works, dredging, cut-and-cover tunnel, drill-and-blast tunnel, road bridges, landscaped decks and full enclosure over roads. These are designated projects under Schedule 2 of the EIA Ordinance (Cap. 499) and hence Environmental Permits (EPs) are required for their construction and operation. The general alignment layout of CKR is given in Figure 1.1.

1.2                         Purposes of the Manual

The purposes of this Environmental Monitoring and Audit (EM&A) Manual are to:

·         Guide the set up of an EM&A programme to ensure compliance with the EIA recommendations;

·         Specify the requirements for monitoring equipments;

·         Propose environmental monitoring points, monitoring frequency etc;

·         Propose Action / Limit Level; and

·         Propose Event / Action Plan.

This Manual outlines the monitoring and audit programme for the construction and operation of the proposed CKR and provides systematic procedures for monitoring, auditing and minimizing environmental impacts.

Hong Kong environmental regulations and the Hong Kong Planning Standards and Guidelines (HKPSG) have served as environmental standards and guidelines in the preparation of this Manual.  In addition, this EM&A Manual has been prepared in accordance with the requirements stipulated in Annex 21 of the Technical Memorandum on the EIA Process (TM-EIAO).

This Manual contains the following information:

·         Responsibilities of the Contractor, the Engineer or Engineer’s Representative (ER), Environmental Team (ET), and the Independent Environmental Checker (IEC) under the context of EM&A;

·         Project organization for the EM&A works;

·         The basis for, and description of the broad approach underlying the EM&A programme;

·         Details of the methodologies to be adopted, including all laboratories and analytical procedures, and details on quality assurance and quality control programme;

·         The rationale on which the environmental monitoring data will be evaluated and interpreted;

·         Definition of Action and Limit levels;

·         Establishment of Event and Action plans;

·         Requirements for reviewing pollution sources and working procedures required in the event of non-compliance with the environmental criteria and complaints; and

·         Requirements for presentation of environmental monitoring and audit data and appropriate reporting procedures.

For the purpose of this manual, the ER shall refer to the Engineer as defined in the Construction Contract, in cases where the Engineer’s powers have been delegated to the ER, in accordance with the Construction Contract.  The ET leader, who shall be responsible for and in charge of the ET, shall refer to the person delegated the role of executing the environmental monitoring and audit requirements.

 

2                                Project Description

2.1                         General Alignment

A number of alignment options have been considered for the west, east and central portions. These options have been evaluated by considering a number of factors including engineering, public comments, environmental factors etc. The preferred alignment for each portion has been recommended and Figure 1.1 shows the entire preferred alignment.

A brief summary of key elements of the Project is given below.

Key Elements

Description (Approximate dimension only)

Total Alignment

~ 4.7 km (dual 3-lane east-west trunk road)

Tunnel

~ 3.9 km (including a 370 m long underwater tunnel)

Ventilation Buildings (VB) and Administration Building

3 VBs and 1 Administration Building in total

-         Ventilation Building at Yau Ma Tei Interchange

(approx. footprint: 5,000 m2 with a building height of approximately 20m above ground)

-         Ventilation Building at Ho Man Tin

(approx. footprint: 3,300 m2 with a building height about 10m above ground)

-         Ventilation and Administration Building at Kai Tak

(approx. footprint: 6,200  m2 with building height less than 25m above ground)

Slip Roads / Connection Roads

In west and east ends of the tunnel for connecting to existing and future road networks

Landscaped Decks

3 nos. in total (one at the west portal in Yau Ma Tei, one at the Kowloon City Ferry Pier PTI at Ma Tau Kok and one above the depressed road at east portion in Kai Tak)

Demolition and / or Re-provisioning Works

-         Yau Ma Tei Multi-Storey Car Park Building

-         Special Clinic Extension Building

-         Jade Hawker Bazaar

-         Hong Kong Automobile Association

-         Reprovisioning of Gascoigne Road Flyover (GRF)

-         Landing Step for Temporary Relocation of Ma Tau Kok Public Pier

Enhancement Works

-         Ma Tau Kok waterfront area and Kowloon City Ferry Pier Public Transport Interchange with cover

Full Enclosures

3 nos. in total

-         West Portal End (approx. 100 m)

-         Re-provisioning of Gascoigne Road Flyover (approx. 200 m)

-         Gascoigne Road Flyover (Ferry Street Section) (approx. 100 m)

2.2                         Summary of Design

A board summary of the general design of CKR is given below:

Table 2.1       Summary of design of CKR

Type

Location

Design

Alignment

East Portion

At-grade Road + cut-and-cover tunnel

 

Central Portion

Drill-and-blast tunnel

 

West Portion

At-grade Road + Flyover + Drill-and-break tunnel + Drill-and-blast tunnel

Ventilation buildings

One for each of the East, Central and West Portions

At-grade structure

2.3                         Implementation Programme

According to the latest programme, the construction of CKR is to commence in 2015. The construction works would take about 5 years and the target commissioning date is around end 2020. The construction programme is presented in Appendix A.

2.4                         Concurrent Projects

The possible potential concurrent projects in the vicinity of the CKR are identified as follows. Figure 2.1 shows the location and alignment of these concurrent projects.

·        Kai Tak Development;

·        Kai Tak Development – Roads D3A &D4A;

·        Trunk Road T2;

·        Proposed Road Improvement Works in West Kowloon Reclamation Development;

·        Kwun Tong Line Extension & Associated Essential Public Infrastructure Works (EPIW);

·        Shatin to Central Link – Tai Wai to Hung Hom Section;

·        Express Rail Link – West Kowloon Terminus;

·        Road Works at West Kowloon;

·        Upgrading of Central and East Kowloon sewerage;

·        Replacement and Rehabilitation of Watermains;

·        Widening of Gascoigne Road;

·        Submarine Gas Pipelines and Associated Facilities from Ma Tau Kok to North Point;

·        Tseung Kwun O – Lam Tin Road;

·        Cross Bay Link; and

·        West Kowloon Cultural District.

2.4.1                  Summary of Concurrent Projects

The table below summarizes the major concurrent projects in the vicinity of the Project and the potential cumulative impacts during the construction and operation of the proposed CKR. Figure 2.1 illustrates the locations of each concurrent project.

 

Table 2.2       Summary of Potential Concurrent Projects

No.

Concurrent Project

Potential Cumulative Impacts

Construction Phase

Operational Phase

1

Agreement No.  CE 35/2006(CE) Kai Tak Development Engineering Study cum Design and Construction of Advance Works – Investigation, Design and Construction

 

Agreement No.  CE 30/2008(CE) Kai Tak Development – Infrastructure at Former Runway and Remaining Areas of North Apron and Improvement of adjacent Waterways – Design and Construction

 

 

 

·         A Site Formation for Kai Tak Cruise Terminal Development

·      Hydrodynamic and Water Quality

·      Nil

 

·         Kai Tak Development - Advance infrastructure works for developments at the southern part of the former runway (Including Roads D4, D3A, D4A and part of Roads D3)

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

·      Traffic noise and vehicular emission caused by induced traffic

 

·         Kai Tak Development - Remaining Infrastructure Works for Developments at the Former Runway (Including part of Roads D3)

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

·      Traffic noise and vehicular emission caused by induced traffic

 

·         Kai Tak Development Infrastructure at north apron area of Kai Tak Airport (Including part of Roads D3)

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

·      Traffic noise and vehicular emission caused by induced traffic

 

·         Kai Tak Nullah modification works

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

·      Nil

 

·         Road D2 and associated works

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

·      Traffic noise and vehicular emission caused by induced traffic

 

·         Kai Tak Development - Kai Tak Approach Channel and Kwun Tong Typhoon Shelter Improvement Works (Phase 1)

·      Hydrodynamic and Water Quality

·      Nil

 

·         600-metre opening at former airport runway

·      Hydrodynamic and Water Quality

·      Nil

2

Multi-Purpose Stadium Complex at Kai Tak

·      Fugitive dust

·      Airborne noise

·      Landscape & visual

3

Design-Build-Operate a District Cooling System (Phase II Works) at Kai Tak Development

·      Nil

·      Nil

4

Provision of Interception Facilities at Jordan Valley Box Culvert

·      Nil

·      Nil

5

Kai Tak Development – Trunk Road T2 and Infrastructure at South Apron – Investigation, Design and Construction

·      Fugitive dust

·      Airborne noise

·      Traffic noise and vehicular emission caused by induced traffic

6

Proposed Road Improvement in West Kowloon Reclamation Development - Feasibility

·      Fugitive dust

·      Airborne noise

·      Traffic noise and vehicular emission caused by induced traffic

7

Kwun Tong Line Extension (Construction of Ho Man Tin Station & EPIW)

·      Nil

·      Nil

8

Shatin to Central Link (Tai Wai to Hung Hom)

·      Fugitive dust

·      Landscape & visual

·      Nil

9

Hong Kong Section of Guangzhou-Shenzhen-Hong Kong Express Rail Link (Construction of West Kowloon Terminus)

·      Nil

·      Nil

10

Road Works at West Kowloon

·      Nil

·      Traffic noise and vehicular emission caused by induced traffic

11

Upgrading of Central and East Kowloon sewerage - phase 2

·      Nil

·      Nil

12

Upgrading of Central and East Kowloon sewerage

·      Nil

·      Nil

13

Replacement and Rehabilitation of Watermains, Stage 4 Phase 1

·      Nil

·      Nil

14

Replacement and Rehabilitation of Watermains Stage 4 - remaining works

·      Nil

·      Nil

15

Widening of Gascoigne Road Flyover

·      Nil

·      Traffic noise and vehicular emission caused by induced traffic

16

Installation of Submarine Gas Pipelines and Associated Facilities from To Kwa Wan to North Point for Former Kai Tak Airport Development

·      Nil

·      Nil

17

Tseung Kwan O – Lam Tin Tunnel[1]

·      Nil

·      Traffic noise and vehicular emission caused by induced traffic

18

Cross Bay Link[1]

·      Nil

·      Traffic noise and vehicular emission caused by induced traffic

19

West Kowloon Cultural District[1]

·      Nil

·      Traffic noise and vehicular emission caused by induced traffic

 


 

3                                Project Organization

3.1                         Project Organization

The proposed project organization and lines of communication with respect to environmental protection works are shown in Appendix B.

The leader of the ET shall be an independent party from the Contractor and has relevant professional qualifications, or have sufficient relevant EM&A experience subject to approval of the Engineer’s Representative (ER) and EPD.

The responsibilities of respective parties are:

The Contractor

·         Employ an Environmental Team (ET) to undertake monitoring, laboratory analysis and reporting of environmental monitoring and audit;

·         Provide assistance to ET in carrying out monitoring and auditing;

·         Submit proposals on mitigation measures in case of exceedances of Action and Limit levels in accordance with the Event and Action Plans;

·         Implement measures to reduce impact where Action and Limit levels are exceeded; and

·         Adhere to the agreed procedures for carrying out compliant investigation.

Environmental Team

·         Set up all the required environmental monitoring stations;

·         Monitor various environmental parameters as required in the EM&A Manual;

·         Analyse the environmental monitoring and audit data and review the success of EM&A programme to cost-effectively confirm the adequacy of mitigation measures implemented and the validity of the EIA predictions and to identify any adverse environmental impacts arising;

·         Carry out site inspection to investigate and audit the Contractors’ site practice, equipment and work methodologies with respect to pollution control and environmental mitigation, and take proactive actions to pre-empt problems;

·         Audit and prepare audit reports on the environmental monitoring data and site environmental conditions;

·         Report on the environmental monitoring and audit results to the IEC. Contractor, the ER and EPD or its delegated representative;

·         Recommend suitable mitigation measures to the Contractor in the case of exceedance of Action and Limit levels in accordance with the Event and Action Plans;

·         Undertake regular on-site audits / inspections and report to the Contractor and the ER of any potential non-compliance; and

·         Follow up and close out non-compliance actions.

Engineer or Engineer’s Representative

·         Supervise the Contractor’s activities and ensure that the requirements in the EM&A Manual are fully complied with;

·         Inform the Contractor when action is required to reduce impacts in accordance with the Even and Action Plans;

·         Employ an IEC to audit the results of the EM&A works carried out by the ET; and

·         Comply with the agreed Event Contingency Plan in the event of any exceedance.

Independent Environmental Checker

·         Review the EM&A works performed by the ET (at not less than monthly intervals);

·         Audit the monitoring activities and results (at not less than monthly intervals);

·         Report the audit results to the ER and EPD in parallel;

·         Review the EM&A reports (monthly and quarterly summary reports) submitted by the ET;

·         Review the proposal on mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;

·         Check the mitigation measures submitted by the Contractor in accordance with the Event and Action Plans;

·         Check the mitigation measures that have been recommended in the EIA and this Manual, and ensure they are properly implemented in a timely manner, when necessary; and

·         Report the findings of site inspections and other environmental performance reviews to ER and EPD.

Sufficient and suitably qualified professional and technical staff shall be employed by the respective parties to ensure full compliance with their duties and responsibilities, as required under the EM&A programme for the duration of the Project.

The ET Leader shall have at least 7 years of experience in conducting EM&A for infrastructure projects.  His / Her qualification shall be vetted by the ER and the IEC.


 

4                                Environmental Submission

4.1                         Introduction

The Contractor shall prepare the Environmental Management Plan (EMP) (including a Waste Management Plan), Construction Method Statement prior to the commencement of construction works and obtain approval from ER and IEC and other relevant authorities to encompass the recommended environmental protection / mitigation measures with respect to their latest construction methodology and programme.

4.2                         Environmental Management Plan

A systematic EMP shall be set up by the Contractor to ensure effective implementation of the mitigation measures, monitoring and remedial requirements presented in EIA, EM&A and Environmental Mitigation Implementation Schedule (EMIS) (See Appendix C).  The ER and the IEC will audit the implementation status against the EMP and advise the necessary remedial actions required.  These remedial actions shall be enforced by the ER through contractual means.

The EMP will require the Contractor (together with its sub-contractors) to define in details how to implement the recommended mitigation measures in order to achieve the environmental performance defined in the Hong Kong environmental legislation and the EIA documentation.

The review of on-site environmental performance shall be undertaken by ER and IEC through a systematic checklist and audit once the construction commences.  The environmental performance review programme comprises a regular assessment on the effectiveness of the EMP.  Reference should be made to ETWBTC 19 / 2005 “Environmental Management on Construction Sites” or its latest versions, and any other relevant Technical Circulars.

4.3                         Waste Management Plan

As part of EMP, the Contractor shall include WMP for the construction of the project and prior to the commencement of construction works submit to the ER and IEC for approval.  Where waste generation is unavoidable, the opportunities for recycling or reusing should be maximized.  If wastes cannot be recycled, recommendations for appropriate disposal routes should be provided in the WMP.  A method statement for stockpiling and transportation of the excavated materials and other construction wastes should also be included in the WMP and approved before the commencement of construction.  All mitigation measures arising from the approved WMP shall be fully implemented.

For the purpose of enhancing the management of Construction and Demolition (C&D) materials including rock, and minimizing its generation at source, construction would be undertaken in accordance with the Section 4.1.3 of Chapter 4 in the Project Administration Handbook for Civil Engineering Works (PAH). 

4.4                         Construction Method Statement

In case the Contractor would like to adopt alternative construction methods or implementation schedules, it is required to submit details of methodology and equipment to the ER for approval before the work commences.  Any changes in construction method shall be reflected in a revised EMP or the Contractor will be required to demonstrate the manner in which the existing EMP should accommodate the proposed changes.  The Contractor may need to apply for a Further Environmental Permit (FEP) from EPD before commencement of any construction activities.


 

5                                Air Quality Impact

5.1                         Introduction

The EIA has considered the potential air quality impacts during both the construction and operational phases of the Project.  Fugitive dust and vehicular emission would be the key impacts during the construction phase and operational phase respectively.

5.2                         Mitigation Measures

The EIA Report has recommended dust control measures including watering all works area once per hour during working hours.  Mitigation measures are not required for the operational phase.  All the proposed mitigation measures are summarized in the Environmental Mitigation Implementation Schedule (EMIS) in Appendix C.

5.3                         Air Quality Parameters

Monitoring and audit of the TSP levels shall be carried out by the ET to ensure that any deteriorating air quality could be readily detected and timely action taken to rectify the situation.

One-hour and 24-hour TSP levels should be measured to indicate the impacts of construction dust on air quality.  The 24-hour TSP levels shall be measured by following the standard high volume sampling method as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B. Upon approval of the IEC, 1-hour TSP levels can be measured by direct reading method which are capable of producing comparable results as that by the high volume sampling method, to indicate short event impacts.

All relevant data including temperature, pressure, weather conditions, elapsed-time meter reading for the start and stop of the sampler, identification and weight of the filter paper, and any other local atmospheric factors affecting or affected by site conditions, etc., shall be recorded down in detail.  A sample data sheet is shown in Appendix D.

5.4                         Monitoring Equipment

High volume samplers (HVSs) complying with the following specifications shall be used for carrying out the 1-hour and 24-hour TSP monitoring:

a)      0.6 – 1.7 m3 per minute adjustable flow range;

b)      Equipped with a timing / control device with +/1 5 minutes accuracy for 24 hours operations;

c)      Installed with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;

d)      Capable of providing a minimum exposed are of 406cm2;

e)      Flow control accuracy: +/-2.5% deviation over 24-hour sampling period;

f)        Equipped with a shelter to protect the filer and sampler;

g)      Incorporated with an electronic mass flow rate controller or other equivalent devices;

h)      Equipped with a flow recorder for continuous monitoring;

i)        Provided with a peaked roof inlet;

j)        Incorporated with a manometer;

k)      Able to hold and seal the filter paper to the sampler housing at horizontal position;

l)        Easily changeable filter; and

m)    Capable of operating continuously for a 24-hour period.

The ET is responsible for the provision, installation, operation, maintenance, dismantle of the monitoring equipment.  They shall ensure that sufficient number of HVSs with an appropriate calibration kit is available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring.  The HVSs shall be equipped with an electronic mass flow controller and be calibrated against a traceable standard at regular intervals.  All the equipment, calibration kit, filter papers, etc., shall be clearly labelled.

Initial calibration of dust monitoring equipment shall be conducted upon installation and thereafter at fortnightly intervals.  The transfer standard shall be traceable to the internationally recognized primary standard and be calibrated annually.  The concern parties such as IEC shall properly document the calibration data for future reference.  All the data should be converted into standard temperature and pressure condition.

The flow-rate of the sampler before and after the sampling exercise with the filter in position shall be verified to be constant and be recorded in the data sheet as mentioned in Appendix D.

If the ET proposes to use a direct reading dust meter to measure 1-hour TSP levels, they shall submit sufficient information to the IEC to prove that the instrument is capable of achieving a comparable results to the HVS.  The instrument should also be calibrated regularly, and the 1-hour sampling shall be determined periodically by the HVS to check the validity and accuracy of the results measured by direct reading method.

Wind data monitoring equipment shall also be provided and set up for logging wind speed and wind direction near the dust monitoring locations.  The equipment installation location shall be proposed by the ET and agreed with the IEC.  For installation and shall be proposed by the ET and agreed with the IEC.  For installation and operation of wind data monitoring equipment, the following points shall be observed:

a)      The wind sensors should be installed at 10m above ground so that they are clear of obstructions or turbulence caused by buildings;

b)      The wind data should be captured by a data logger, the data shall be downloaded for analysis at least once a month;

c)      The wind data monitoring equipment should be re-calibrated at least once every six months; and

d)      Wind direction should be divided into 16 sectors of 22.5 degrees each.

In exceptional situations, the ET may propose alternative methods to obtain representative wind data upon approval from the ER and agreement from the IEC.

5.5                         Laboratory Measurement / Analysis

A clean laboratory with constant temperature and humidity control, and equipped with necessary measuring and conditioning instruments to handle the dust samples collected, shall be available for sample analysis, and equipment calibration and maintenance.  The laboratory should be HOKLAS accredited.

If as site laboratory is et up or a non-HOKLAS accredited laboratory is hired for carrying out the laboratory analysis, the laboratory equipment shall be approved by the ER and the measurement procedures shall be demonstrated to the satisfaction of the ER and IEC.  IEC shall regularly audit to the measurement performed by the laboratory to ensure the accuracy of measurement results.  The ET Leader shall provide the ER with one copy of the Title 40 of Code of Federal Regulations, Chapter 1 (Part 50), Appendix B for his / her reference. 

Filter paper of size 8” X 10” shall be labelled before sampling.  It shall be a clean filter paper with no pinholes, and shall be conditioned in a humidity-controlled chamber for over 24-hours and be pre-weighed before use for the sampling.

After sampling, the filter paper loaded with dust shall be kept in a clean and tightly sealed plastic bag.  The filter paper shall then be returned to the laboratory for reconditioning in the humidity-controlled chamber followed by accurate weighing by an electronic balance with readout down to 0.1 mg.  The balance shall be regularly calibrated against a traceable standard.

5.6                         Monitoring Locations

Figure 5.1, Figure 5.2 & Figure 5.3 show the locations of the proposed construction dust monitoring station.  The status and locations of dust sensitive receivers may change after issuing this manual.  If such cases exist, the ET Leader shall proposed updated monitoring locations and seek approval from ER and agreement from the IEC.

Table 5.1     Construction dust monitoring locations

ID

Location

W-A5

The Coronation

W-A11

Hong Kong Community College (HKCC) of the HK

M-A6

Ko Fai House, Kwun Fai Court

E-A1

Hong Kong International Trade and Exhibition Centre

E-A14

Wyler Gardens

When alternative monitoring locations are proposed, the proposed site should, as far as practicable:

a)         be at the site boundary or such locations close to the major dust emission source;

b)         be close to the sensitive receptors; and

c)         take into account the prevailing meteorological conditions.

The ET shall agree with the ER in consultation with the IEC on the position of the HVS for the installation of the monitoring equipment.  When positioning the samplers, the following points shall be noted:

a)         a horizontal platform with appropriate support to secure the samplers against gusty wind should be provided;

b)         no two samplers should be placed less than 2 meters apart;

c)         the distance between the sampler and an obstacle, such as buildings, must be at least twice the height that the obstacle protrudes above the sampler;

d)         a minimum of 2 meters of separation from walls, parapets and penthouses is required for rooftop samplers;

e)         a minimum of 2 meters separation from any supporting structure, measured horizontally is required;

f)          no furnace or incinerator flue is nearby;

g)         airflow around the sampler is unrestricted;

h)         the sampler is more than 20 meters from the dripline;

i)          any wire fence and gate, to protect the sampler, should not cause any obstruction during monitoring;

j)          permission must be obtained to set up the samplers and to obtain access to the monitoring stations; and

k)         a secured supply of electricity is needed to operate the samplers.

The ET may, depending on site conditions and monitoring results, decide whether additional monitoring locations shall be included or any monitoring locations could be removed / relocated during any stage of the construction phase.

5.7                         Baseline Monitoring

Baseline monitoring shall be carried out at all of the designated monitoring locations (see Table 5.1) for at least 14 consecutive days prior to the commissioning of major construction works to obtain daily 24-hour TSP samples.  The selected baseline monitoring stations should reflect baseline conditions at the impact stations.  One-hour sampling should also be done at least 3 times per day while the highest dust impact is expected. 

During the baseline monitoring, there should not be any major construction or dust generation activities in the vicinity of the monitoring stations.  Before commencing baseline monitoring, the ET shall inform the IEC of the baseline monitoring programme such that, if required, the ER can conduct on-site audit to ensure accuracy of the baseline monitoring results.

In case the baseline monitoring cannot be carried out at the designated monitoring locations, the ET Leader shall carry out the monitoring at alternative locations that can effectively represent the baseline conditions at the impact monitoring locations.  The alternative baseline monitoring locations shall be approved by the ER and agreed with the IEC.

In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to ER for approval.

Ambient conditions may vary seasonally and shall be reviewed once every three months.  When the ambient conditions have changed and a repeat of the baseline monitoring is required to be carried out for obtaining the updated baseline levels, the monitoring should be at times when the Contractor's activities are not generating dust, at least in the proximity of the monitoring stations.  Should change in ambient conditions be determined, the baseline levels and, in turn, the air quality criteria, should be revised.  The revised baseline levels and air quality criteria should be agreed with the IEC and EPD.

5.8                         Impact Monitoring

The ET shall carry out impact monitoring during the entire construction period.  For regular impact monitoring, the sampling frequency of at least once in every 6 days, shall be strictly observed at all the monitoring stations for 24-hour TSP monitoring.  For 1-hour TSP monitoring, the sampling frequency of at least 3 times in every 6 days should be undertaken when the highest dust impact occurs.  Before commencing impact monitoring, the ET shall inform the IEC of the impact monitoring programme such that the IEC can conduct on-site audit to ensure accuracy of the monitoring results.

The specific time to start and stop the 24-hour TSP monitoring shall be clearly defined for each location and be strictly followed by the ET.

In case of non-compliance with the air quality criteria, more frequent monitoring, as specified in the Action Plan in the following section, shall be conducted within the specified timeframe after the result is obtained.  This additional monitoring shall be continued until the excessive dust emission or the deterioration in air quality is rectified, and agreed with the ER and the IEC.

5.9                         Action / Limit Levels

The baseline monitoring results form the basis for determining the air quality criteria for the impact monitoring.  The ET shall compare the impact monitoring results with air quality criteria set up for 24-hour TSP and 1-hour TSP.  Table 5.2 shows the air quality criteria, namely Action and Limit levels to be used.

Table 5.2       Action / Limit Levels for Air Quality

Parameters

Action

Limit

24-hour TSP Level in mg m-3

For baseline level £ 200 mg m-3, Action level = (baseline level * 1.3 + Limit level)/2;

For baseline level > 200 mg m-3 Action level = Limit level

260mg/m3

1-hour TSP Level in mg m-3

For baseline level £ 384 mg m-3, Action level = (baseline level * 1.3 + Limit level)/2;

For baseline level > 384 mg m-3, Action level = Limit level

500mg/m3


5.10                   Event and Action Plan

5.8.1    Should non-compliance of the air quality criteria occur, actions in accordance with the Action Plan in Table 5.3 shall be carried out.

Table 5.3       Event / Action Plan for Air Quality

EVENT

ACTION

ET

IEC

ER

CONTRACTOR

ACTION LEVEL

1. Exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform IEC and ER;

3. Repeat measurement to confirm finding;

4. Increase monitoring frequency to daily.

1. Check monitoring data submitted by ET;

2. Check Contractor’s working method.

1. Notify Contractor.

1. Rectify any unacceptable practice;

2. Amend working methods if appropriate.

 2. Exceedance for two or more consecutive samples

1. Identify source;

2. Inform IEC and ER;

3. Advise the ER on the effectiveness of the proposed remedial measures;

4. Repeat measurements to confirm findings;

5. Increase monitoring frequency to daily;

6. Discuss with IEC and Contractor on remedial actions required;

7. If exceedance continues, arrange meeting with IEC and ER;

8. If exceedance stops, cease additional monitoring.

 

1. Check monitoring data submitted by ET;

2. Check Contractor’s working method;

3. Discuss with ET and Contractor on possible remedial measures;

4. Advise the ET on the effectiveness of the proposed remedial measures;

5. Supervise Implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Ensure remedial measures properly implemented.

 

1. Submit proposals for remedial to ER within 3 working days of notification;

2. Implement the agreed proposals;

3. Amend proposal if appropriate.

LIMIT LEVEL

1. Exceedance for one sample

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Inform ER, Contractor and EPD;

3. Repeat measurement to confirm finding;

4. Increase monitoring frequency to daily;

5. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results.

1. Check monitoring data submitted by ET;

2. Check Contractor’s working method;

3. Discuss with ET and Contractor on possible remedial measures;

4. Advise the ER on the effectiveness of the proposed remedial measures;

5. Supervise implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Ensure remedial measures properly implemented.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within 3 working days of notification;

Implement the agreed proposals;

4. Amend proposal if appropriate.

2. Exceedance for two or more consecutive samples

1. Notify IEC, ER, Contractor and EPD;

2. Identify source;

3. Repeat measurement to confirm findings;

4. Increase monitoring frequency to daily;

5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented;

6. Arrange meeting with IEC and ER to discuss the remedial actions to be taken;

7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractor’s remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. In consultation with the IEC, agree with the Contractor on the remedial measures to be implemented;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC within 3 working days of notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.

Note:

ET – Environmental Team

IEC – Independent Environmental Checker

ER – Engineer’s Representative


6                                Noise Impact

6.1                         Introduction

The EIA has considered the potential airborne noise impacts during both the construction and operational phases of the Project. Construction noise from mechanical equipment would be the key impacts during the construction phases during which excavation, construction of approach roads and bridges etc. would need to be conducted. Vehicles running on new roads and bridges and fixed noise from ventilation buildings would also affect the neighbouring sensitive receivers during operational phase.

Prediction of construction groundborne noise indicates the criteria will be achieved and mitigation measures are not required. 

6.2                         Mitigation Measures

6.2.1                   Construction Phase

The EIA Report has recommended construction noise mitigation measures including the use of quiet plant and temporary noise barriers, etc. All the proposed mitigation measures are summarized in the EMIS in Appendix C.

6.2.2                   Operational Phase

Road Traffic Noise

A series of mitigation measures including noise barriers, semi/ full noise enclosure and application of low noise surfacing material would need to be implemented along the roads and flyovers of CKR. These mitigation measures include the following and are shown in Figure 6.1 to Figure 6.8:

Table 6.1     Noise mitigation measures for operational phase

Noise Mitigation Measures ID

Location

Type of Noise Mitigation Measures [1]

Height above road level (m)

Approximate Length (m)

F01

West portal of CKR

Full enclosure including landscape deck

9

250

 

F02

Gascoigne Road Flyover (Ferry Street section)

Full enclosure

10

110

 

F03

Gascoigne Road Flyover (Kansu Street section) (NB+SB)

Full enclosure

7

200

 

S01

Lin Cheung Road

Semi-enclosure with opening at west

10

120

 

S02

Re-aligned Hoi Wang Road

Semi-enclosure with opening at west

10

270

 

S03

Gascoigne Road Flyover (Ferry Street section) (SB)

Absorptive Semi-enclosure with opening at south

7

85

 

S04

Gascoigne Road Flyover (Kansu Street section) (NB+SB)

Semi-enclosure with opening at south

7

45

 

S05

Gascoigne Road Flyover (Kansu Street section) (SB)

Semi-enclosure with opening at north

7

60

 

C01

Connection E

5m high with 3m cantilever at 45o cantilevered barrier

7.1

155

 

C02

Lin Cheung Road

5m high with 3m cantilever at 45o cantilevered barrier

7.1

85

 

C03

Lin Cheung Road

5m high with 3m cantilever at 45o cantilevered barrier

7.1

85

 

C04

Connection D

5m high with 3m cantilever at 45o cantilevered barrier

7.1

190

 

C05

Connection C2

5m high with 3m cantilever at 45o cantilevered barrier

7.1

120

 

C06

Connection A

5m high with 3m cantilever at 45o cantilevered barrier

7.1

170

 

C07

Ferry Street Road (At-grade)

5m high with 1m cantilever at 45o cantilevered barrier

5.7

160

 

V01

Lin Cheung Road

4m vertical barrier

4

120

 

V02

Connection D

3.8m vertical barrier

3.8

190

 

V03

Connection E

5.8m vertical barrier

5.8

100

 

V04

Widening of Lai Cheung Road

4m vertical barrier

4

50

 

V05

Gascoigne Road Flyover (Ferry Street section) (SB)

3.3m vertical barrier

3.3

110

 

V06

Gascoigne Road Flyover (Ferry Street section) (central divider)

3.8m vertical barrier

3.8

100

 

V07

Gascoigne Road Flyover (Kansu Street section) (SB)

4.3m vertical barrier

4.3

60

 

V08

Gascoigne Road Flyover (Kansu Street section) (central divider)

2.8m vertical barrier

2.8

60

 

Notes:   

[1] The side(s) of noise mitigation measures facing to the road traffic will be installed with absorptive materials/ panels.

Fixed Plant Noise

The ventilation buildings shall be installed with sufficient sound attenuators to control its sound power level emitting to the environment. 

6.2.3                   Groundborne Noise

Since all the predicted groundborne noise impacts for construction phase ground-borne noise comply with the legislative requirements, no mitigation measures are required and hence no groundborne noise monitoring is recommended.

6.3                         Noise Monitoring Parameter and Monitoring Equipment

6.3.1                   Noise Monitoring Parameter for Construction Phase

Construction noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).  Leq (30min) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays.  For all other time periods, Leq (5min) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria.

As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

6.3.2                   Noise Monitoring Parameter for Operational Phase

The traffic noise level shall be measured twice within the first year of the road opening.  Measurement shall be made in terms of A-weighted L10 over three half-hour periods during the peak traffic hour.  Other metrics like Leq may be added as seen fit.  A sample data record sheet is shown in Appendix D for reference.

Fixed plant noise level shall be measured in terms of the A-weighted equivalent continuous sound pressure level (Leq).  Leq (30min) shall be used as the monitoring parameter for the time period between 0700 and 1900 hours on normal weekdays.  For all other time periods, Leq (5min) shall be employed for comparison with the Noise Control Ordinance (NCO) criteria.

As supplementary information for data auditing, statistical results such as L10 and L90 shall also be obtained for reference.

6.3.3                   Monitoring Equipment for Construction and Operational Phases

As referred to in the Technical Memorandum (TM) issued under the NCO, sound level meters in compliance with the International Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be used for carrying out the noise monitoring.  Immediately prior to and following each noise measurement, the accuracy of the sound level meter shall be checked using an acoustic calibrator generating a known sound pressure level at a known frequency.  Measurements may be accepted as valid only if the calibration level from before and after the noise measurement agrees to within 1.0 dB.

Noise measurements should be made in accordance with standard acoustical principles and practices in relation to weather conditions.

The ET is responsible for the provision, installation, operation, maintenance, dismantle of the monitoring equipment.  He shall ensure that sufficient noise measuring equipment and associated instrumentation are available for carrying out the baseline monitoring, regular impact monitoring and ad hoc monitoring.  All the equipment and associated instrumentation shall be clearly labelled.

6.4                         Construction Noise Impact

6.4.1                   Monitoring Locations

The locations of construction airborne noise monitoring stations are summarised in table below and shown in Figure 6.9 to Figure 6.12.

Table 6.2       Proposed airborne construction noise monitoring locations

ID

Description

Figure

W-N1A

Yau Ma Tei Catholic Primary School (Hoi Wang Road)

Figure 6.9

W-N8A

Tak Cheong Building

Figure 6.10

W-N25A

Prosperous Garden Block 1

Figure 6.10

W-P11

The Coronation Tower 1

Figure 6.10

M-N6

Ko Fai House, Kwun Fat Court

Figure 6.11

E-N12

Grand Waterfront Tower 3

Figure 6.12

E-N21

Hang Chien Court Block J

Figure 6.12

The ET shall select the monitoring locations from the above table based on the locations of the construction activities and seek approval from ER and agreement from the IEC and EPD to the proposal.  The monitoring locations should be chosen based on the following criteria:

·        At locations close to the major site activities which are likely to have noise impacts;

·        Close to the most affected existing noise sensitive receivers; and

·        For monitoring locations located in the vicinity of the sensitive receivers, care should be taken to cause minimal disturbance to the occupants during monitoring.

The monitoring station shall normally be at a point 1 m from the exterior of the sensitive receiver building facade and be at a position 1.2 m above the ground.  If there is problem with access to the normal monitoring position, an alternative position may be chosen, and a correction to the measurements shall be made.  For reference, a correction of +3 dB(A) shall be made to the free field measurements.  The ET shall agree with the IEC on the monitoring position and the corrections adopted.  Once the positions for the monitoring stations are chosen, the baseline monitoring and the impact monitoring shall be carried out at the same positions.

The ET may, depending on site conditions and monitoring results, decide whether additional monitoring locations shall be included or any monitoring locations could be removed/ relocated during any stage of the construction phase.

6.4.2                   Baseline Monitoring

The ET shall carry out baseline noise monitoring prior to the commencement of the construction works.  There shall not be any construction activities in the vicinity of the stations during the baseline monitoring.  Continuous baseline noise monitoring for the A-weighted levels Leq, L10 and L90 shall be carried out daily for a period of at least two weeks in a sample period of 5 minutes or 30 minutes between 0700 and 1900, and 5 minutes between 1900 and 0700.  A schedule on the baseline monitoring shall be submitted to the ER and IEC for approval before the monitoring starts.

In exceptional cases, when insufficient baseline monitoring data or questionable results are obtained, the ET shall liaise with the IEC and EPD to agree on an appropriate set of data to be used as a baseline reference and submit to the ER for approval.

6.4.3                   Impact Monitoring

During normal construction working hour (0700-1900 Monday to Saturday), monitoring of Leq, (30min) noise levels (as six consecutive Leq, (5min) readings) shall be carried out at the agreed monitoring locations once every week in accordance with the methodology in the TM. 

If a school exists near the construction activity, noise monitoring shall be carried out at the monitoring stations for the schools during the school examination periods.  The ET Leader shall liaise with the school’s personnel and the Examination Authority to ascertain the exact dates and times of all examination periods during the course of the contract.

In case of non-compliance with the construction noise criteria, more frequent monitoring, as specified in the Action Plan, shall be carried out.  This additional monitoring shall be continued until the recorded noise levels are rectified or proved to be irrelevant to the construction activities.

A schedule on the compliance monitoring shall be submitted to the ER and IEC for approval before the monitoring starts.

6.4.4                   Event and Action Plan

Table 6.3       Action / Limit Levels for Construction Noise

Time Period

Action Level

Limit Level

0700 - 1900 hours on normal weekdays

When one documented complaint is received

75 dB(A) *

Note :     If works are to be carried out during restricted hours, the conditions stipulated in the construction noise permit issued by the Noise Control Authority have to be followed.          

* Reduce to 70 dB(A) for schools and 65 dB(A) during school examination periods.

 

 


Table 6.4       Event / Action Plan for Construction Noise

EVENT

ACTION

 

ET

IEC

ER

CONTRACTOR

Action Level

1. Identify source, investigate the causes of exceedance and propose remedial measures;

2. Notify IEC and Contractor;

3. Report the results of investigation to the IEC, ER and Contractor;

4. Discuss with the Contractor and formulate remedial measures;

5. Increase monitoring frequency to check mitigation effectiveness.

1.Review the analysed results submitted by the ET;

2. Review the proposed remedial measures by the Contractor and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1. Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures are properly implemented

1. Submit noise mitigation proposals to IEC;

2. Implement noise mitigation proposals.

Limit Level

1. Identify source;

2. Inform IEC, ER, EPD and Contractor;

3. Repeat measurements to confirm findings;

4. Increase monitoring frequency;

5. Carry out analysis of Contractor’s working procedures to determine possible mitigation to be implemented;

6. Inform IEC, ER and EPD the causes and actions taken for the exceedances;

7. Assess effectiveness of Contractor’s remedial actions and keep IEC, EPD and ER informed of the results;

8. If exceedance stops, cease additional monitoring.

1. Discuss amongst ER, ET, and Contractor on the potential remedial actions;

2. Review Contractors remedial actions whenever necessary to assure their effectiveness and advise the ER accordingly;

3. Supervise the implementation of remedial measures.

1.Confirm receipt of notification of failure in writing;

2. Notify Contractor;

3. Require Contractor to propose remedial measures for the analysed noise problem;

4. Ensure remedial measures properly implemented;

5. If exceedance continues, consider what portion of the work is responsible and instruct the Contractor to stop that portion of work until the exceedance is abated.

1. Take immediate action to avoid further exceedance;

2. Submit proposals for remedial actions to IEC  within 3 working days of notification;

3. Implement the agreed proposals;

4. Resubmit proposals if problem still not under control;

5. Stop the relevant portion of works as determined by the ER until the exceedance is abated.

Note:

ET – Environmental Team

IEC – Independent Environmental Checker

ER – Engineer’s Representative


6.5                         Operational Noise Impact

6.5.1                   Monitoring Locations

The locations of road traffic noise and fixed noise monitoring stations are summarised in table below and shown in Figure 6.9 to Figure 6.12.

Table 6.5       Proposed operational noise monitoring locations

ID

Description

Road Traffic Noise

Fixed Noise

Figure

W-N8A

Tak Cheong Building

X

Figure 6.10

W-N25A

Prosperous Garden Block 1

X

Figure 6.10

W-P11

The Coronation Tower 1

Figure 6.10

M-N6

Ko Fai House, Kwun Fai Court

X

Figure 6.11

6.5.2                   Impact Monitoring for Road Traffic Noise during Operational Phase

The ET should prepare and deposit to EPD, at least 6 months before the operation of the proposed roads under the Project, a monitoring plan for the purpose of assessing the accuracy of traffic noise predictions by comparing the noise impact predictions with the actual impacts.  The monitoring plan should contain monitoring locations, monitoring schedules, methodology of noise monitoring including noise measurement procedures, traffic counts and speed checks, and methodology of comparison with the predicted levels.  The ET should implement the monitoring plan in accordance with the deposited monitoring plan unless with prior justifications.  Monitoring details and results including the comparison between the measured noise levels and the predicted levels should be recorded in a report to be deposited with EPD within one month of the completion of the monitoring.  The report should be certified by the ET Leader before deposit with EPD.

Traffic noise monitoring shall be carried out at all the designated traffic noise monitoring stations.  The following is an initial guide on the traffic noise monitoring requirements during the operational phase:

·        one set of measurements at the morning traffic peak hour on normal weekdays;

·        one set of measurements at the evening traffic peak hour on normal weekdays;

·        a concurrent census of traffic flow and percentage heavy vehicles shall be conducted for the Project Road and the existing road network in the vicinity of each measurement points;

·        average vehicle speed estimated for Project Road and the existing road network in the vicinity of each measuring points; and

·        the two sets of monitoring data shall be obtained within the first year of operation.

Measured noise levels shall be compared with the predicted noise levels by applying appropriate conversion corrections to allow for the traffic conditions at the time of measurement.  A sample data record sheet for traffic noise monitoring is shown in Appendix D.

6.5.3                   Event and Action Plan

For the traffic noise, the measured/monitored noise levels shall be compared with the predicted results and the predicted traffic flow conditions (calculated noise levels based on concurrent traffic census obtained).  In case discrepancies are observed, explanation shall be given to justify the discrepancies.

6.5.4                   Impact Monitoring for Fixed Plant Noise during Operational Phase

The EIA report has provided the maximum allowable sound power levels for fixed noise sources.  The SWL criteria shall be implemented by the Contractor.  The Contractor should also carry out a noise commissioning test for all fixed noise sources before operation of the Project, in order to ensure compliance of the operational airborne noise levels with the TM’s stipulated noise standard.

 

Apart from commissioning test for the fixed noise sources, monitoring of fixed noise sources at sensitive receivers is also suggested.  The fixed noise will be operated with full power for 30 minutes during daytime and night-time and the monitoring of LAeq 30min noise levels during daytime and night-time will be carried out in accordance with the methodology stated in the TM at the proposed monitoring stations.  Any non-related operation activities in the vicinity of the monitoring stations during the monitoring shall be noted and the source and location shall be recorded.  The Lmax, L10 and L90 shall also be recorded at the specified interval.

 

The ET should prepare and deposit to EPD, at least 6 months before the operation of the proposed roads under the Project, a monitoring plan for the purpose of fixed noise.  The monitoring plan should contain monitoring locations, monitoring schedules, methodology of noise monitoring including noise measurement procedures and data analysis of measured noise level.  The ET should implement the monitoring plan in accordance with the deposited monitoring plan unless with prior justifications.  The monitoring plan should be certified by the ET Leader before deposit with EPD.


 

7                                Water Quality Impact

7.1                         Introduction

The EIA Report has assessed the water quality impacts associated with the Project.  According to the EIA Report, the water quality impact could be minimized with the implementation of mitigation measures. The water quality monitoring programme as discussed below could ensure the implementation of the recommended mitigation measures and provide continue improvements to the environmental conditions.

7.2                         Mitigation Measures

The EIA Report has recommended construction phase mitigation measures.  All the prepared mitigation measures are summarized in the EMIS in Appendix C.

7.3                         Performance Review for Stone Column Installation

Before the commencement of stone column installation, performance review is required. The review shall be conducted following the Performance Review Proposal as shown in Appendix E. The prepared Performance Review Proposal shall be reviewed and updated by ET, taking account of the Contractor’s proposed actual locations of his initial period of installation. The ET may counter propose alternative review methodology subject to approval of IEC and EPD.

7.4                         Monitoring Locations

Water quality monitoring at inshore waters during CKR construction is not required, marine water quality monitoring, however, shall be carried out while dredging activities are being conducted.

The water quality monitoring stations and control stations of CKR are shown in Figure 7.1.  The co-ordinates of the proposed monitoring stations (construction phase – dredging activities) are listed in below.  As shown in Figure 7.1, the proposed locations are classified as Impact Station and Control Station according to their functions. The ET shall seek approval from IEC and EPD for any alternative monitoring locations.

Table 7.1         Water Quality Monitoring Stations for Baseline and Construction Phase Monitoring

Station

Description

Easting

Northing

IS1

Planed Kai Tak Cooling Water Intake (subject to its implementation)

839050

819377

IS2

To Kwa Wan Typhoon Shelter

838450

819399

IS3

Tai Wan Salt Water Intake

837948

818202

CS1

Control Station 1

837787

817712

CS2

Control Station 2

838237

818804

CS3

Control Station 3

839105

819019

7.5                         Monitoring Parameters

The monitoring shall normally be established by measuring the Dissolved Oxygen (DO), temperature, turbidity, pH, salinity, Suspended Solids (SS) and copper level at all designated locations as specified in Section 7.3 above.

The measurements shall be taken at all designated monitoring stations including control stations, 3 days per week, at mid-flood and mid-ebb tides.  Tidal range of individual flood and ebb tides should be not less than 0.5m.

All the monitoring shall be taken at 3 water depths, namely 1m below water surface, mid-depth and 1m above sea bed, except where the water depth less than 6m, the mid-depth station may be omitted.  Should the water depth be less than 3m, only the mid-depth station will be monitored.

Replicate in-situ measurements and samples collected from each independent sampling event shall be collected to ensure a robust statistically interpretable database.  DO, pH value, salinity, temperature and turbidity should be measured in-situ whereas SS and copper should be determined by an accredited laboratory.

Other relevant data shall also be recorded, including monitoring location / position, time, water depth, tidal stages, weather conditions and any special phenomena or work underway at the construction site.

7.6                         Baseline Monitoring

Baseline conditions for marine water quality shall be established and agreed with EPD prior to be commencement of dredging works.  The purpose of the baseline monitoring is to establish ambient conditions prior to the commencement of the dredging works and to demonstrate the suitability of the proposed impact and control monitoring stations.

The baseline monitoring shall be conducted for at least 4 weeks prior to the commencement of dredging works. The proposed water quality monitoring schedule shall be submitted to EPD by the ET at least 2 weeks before the first day of the monitoring month.  The interval between two sets of monitoring shall not be less than 36 hours.  EPD shall also be notified immediately for any changes in schedule.

In general, where the difference in value between the first and second in-situ measurement of DO or turbidity parameters is more than 25% of the value of the first reading, the reading shall be discarded and further readings should be taken.

There should be no marine work in the vicinity of the stations during the baseline monitoring.  The monitoring programme may overlap with other non-project marine activities.  The monitoring exercise should be scheduled as far as possible to avoid concurrent dredging / backfilling activities around the monitoring stations such that representative ambient data could be sampled. 

As it is likely to have concurrent activities such as dredging works of T2, the ET shall seek approval from the IEC and EPD on an appropriate set of data, such as EPD’s routine monitoring data, baseline monitoring data for cruise terminal, etc., to be used with the baseline data collected by this study to establish the Action / Limit Levels.  The determination of Action / Limit Levels will be discussed in Section 7.9.

Table 7.2 below summarizes the proposed monitoring frequency and water quality parameters for baseline monitoring.

Table 7.2       Proposed water quality monitoring programme

 

Baseline Monitoring

Monitoring Period

At least 4 weeks prior to the commencement of dredging work

Monitoring Frequency

3 Days in a Week, at mid-flood and mid-ebb tides

Monitoring Locations

IS1, IS2, IS3,CS1, CS2 and CS3

Monitoring Parameters

DO, temperature, turbidity, pH, salinity, SS, copper, total PAH

Intervals between 2 Sets of Monitoring

Not less than 36 hours

Tide Range

Individual flood and ebb tides not less than 0.5m

7.7                         Impact Monitoring

The impact monitoring shall be conducted during dredging period. The purpose of impact monitoring is to ensure the implementation of the recommended mitigation measures, provide effective control of any malpractices, and provide continuous improvements to the environmental conditions. The proposed water quality monitoring schedule shall be submitted to EPD by the ET at least 2 weeks before the first day of the monitoring month.  The interval between two sets of monitoring shall not be less than 36 hours. EPD shall also be notified immediately for any changes in schedule.

In general, where the difference in value between the first and second in-situ measurement of DO or turbidity parameters is more than 25% of the value of the first reading, the reading shall be discarded and further readings should be taken.

In case of project-related exceedances of Action and/or Limit Levels, the impact monitoring frequency shall be increased according to the requirement of Event and Action Plan.  The details of Event Action Plan will be discussed in Section 7.10.

Table 7.3 below summarises the proposed monitoring frequency and water quality parameters for and impact monitoring.

Table 7.3       Proposed water quality monitoring programme

 

Impact Monitoring

Monitoring Period

During dredging period

Monitoring Frequency

3 Days in a Week, at mid-flood and mid-ebb tides

Monitoring Locations

IS1, IS2, IS3, CS1, CS2, and CS3

Monitoring Parameters

DO, temperature, turbidity, pH, salinity, SS, copper, total PAH

Intervals between 2 Sets of Monitoring

Not less than 36 hours

Tide Range

Individual flood and ebb tides not less than 0.5m

7.8                         Monitoring Equipments

7.8.1               Dissolved Oxygen and Temperature Measuring Equipment

The dissolved oxygen (DO) measuring instruments should be portable and weatherproof. The equipment should also complete with cable and sensor, and DC power source. It should be capable of measuring:

·         A DO level in the range of 0 – 20 mg/L and 0 – 200% saturation; and

·         A temperature of 0 – 45 degree Celsius

The equipment should have a membrane electrode with automatic temperature compensation complete with a cable.

Should salinity compensation not be built-in to the DO equipment, in-situ salinity should be measured to calibrate the DO measuring instruments prior to each measurement.

7.8.2               Turbidity Measuring Equipments

The turbidity measuring instruments should be a portable and weatherproof with DC power source.  It should have a photoelectric sensor capable of measuring turbidity level between 0 – 1000 NTU (for example, Hach model 2100P or an approved similar instrument).

7.8.3               Salinity Measuring Equipments

A portable salinometer capable of measuring salinity in the range of 0 – 40 parts per thousand (ppt) should be provided for measuring salinity of the water at each monitoring location.

7.8.4               pH Measuring Equipments

A portable pH meter capable of measuring a pH range between 0.0 and 14.0 shall be provided under the specified conditions (e.g., Orion Model 250A or an approved similar instrument).

7.8.5               Positioning Equipments

A hand-held or boat-fixed type digital Differential Global Positioning System (DGPS) with way point bearing indication and Radio Technical Commission for maritime (RTCM) Type 16 error message “screen pop-up” facilities (for real-time auto-display of error messages and DGPS corrections from the Hong Kong Hydrographic Office), or other equipment instrument of similar accuracy, should be provided and used during marine water monitoring to ensure the monitoring vessel is at the correct location before taking measurements.

7.8.6               Water Depth Detector

A portable, battery-operated echo sounder should be used for water depths determination at each designated monitoring station.  The detector can either be hand held or affixed to the bottom of the work boat, if the same vessel is to be used throughout the monitoring programme.

7.8.7               Water Sampling Equipment

A water sampler is required for SS, Ammonia (as N), Nitrite (as N) and Nitrate (as N) monitoring. It should comprise a transparent PVC cylinder, with a capacity of not less than 2 litres, which can be effectively sealed with latex cups at both ends.  The sampler should have a positive latching system to keep it open and prevent premature closure until released by a messenger when the sampler is at the selected water depth (for example, Kahlsico Water Sampler or an approved similar instrument).

7.8.8               Sample Containers and Storage

Water samples for SS, Ammonia (as N), Nitrite (as N) and Nitrate (as N) determinations should be stored in high density polythene bottles with no preservative added, packed in ice (cooled to 4°C without being frozen) and shipment to the testing laboratory.  The samples shall be delivered to the laboratory within 24 hours of collection and be analysed as soon as possible after collection. Water samples for Ammonia (as N), Nitrite (as N) and Nitrate (as N) shall be preserved with sulphuric acid (H2SO4)

7.8.9               Calibration of In-Situ Instruments

The pH meter, DO meter and turbidimeter shall be checked and calibrated before use. DO meter and turbidimeter shall be certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at quarterly basis throughout all stages of the water quality monitoring.  Responses of sensors and electrodes should be checked with certified standard solutions before each use.  Wet bulb calibration for a DO meter shall be carried out before measurement at each monitoring station.

7.8.10          Back-up Equipment and Vessels

Sufficient stocks of spare parts shall be maintained for replacements when necessary.  Backup monitoring equipment shall also be made available so that monitoring can proceed uninterrupted even when some equipment is under maintenance, calibration, malfunction, etc.

The water quality monitoring will involve three monitoring stations and measurements should be conducted within the prescribed tidal conditions in order to ensure the measurement/samples are representative.  A multi-probe monitoring equipment set integrated with water sampler(s) is highly recommended to improve the monitoring efficiency.  Depending on the actually operation, more than one field survey vessels might be required simultaneously to ensure the monitoring are conducted within the acceptable monitoring period.  The ET shall also consider the use of unattended automatic sampling/monitoring devices at fixed stations where monitoring are required throughout the construction period.  The use of such unattended automatic devices, however, shall be subject to the approval of the ER, IEC and EPD.

7.9                         Laboratory Measurement / Analysis

At least 3 replicate samples from each independent sampling event are required for the SS, copper measurement which shall be carried in a HOKLAS or international accredited laboratory.  Sufficient water samples shall be collected at the monitoring stations for carrying out the laboratory measurement and analysis.  The laboratory determination work shall start within 24 hours after collection of the water samples.  The analysis for SS, Ammonia (as N), Unionized Ammonia, Nitrite (as N) and Nitrate (as N) is presented in Table 7.4.

Table 7.4         Laboratory Analysis for Various Water Quality Parameters

Parameters

Analytical Method

Reporting Limit

Suspended Solid (SS)

APHA 2540-D

0.1 mg/L

Copper (Cu)

ICP-MS USEPA 6020A

1 μg/L

Total PAH[1]

GC-MSD USEPA 3510C, USEPA 3630C, USEPA 8270C

0.1 μg/L (individually)

Note [1] Low Molecular Weight PAHs shall include acenaphthene, acenaphthylene, anthracene, fluorene, naphthalene and phenanthrene. High Molecular Weight PAHs shall include benzo[a]anthracene, benzo[a]pyrene, chrysene, dibenzo[a,h]anthracene, fluoranthene, pyrene, benzo[b]fluoranthene, benzo[k]fluoranthene, indeno[1,2,3-c,d]pyrene and benzo[g,h,i]perylene.

7.10                   Action and Limit Levels

The Action and Limit Levels for water quality are defined in Table 7.5 below.

Table 7.5       Action and Limit levels for Water Quality

Parameters

Action Level

Limit Level

DO in mg/L (Surface, Middle & Bottom)

Surface and Middle

5 percentile of baseline data for surface and middle layer

Bottom

5 percentile of baseline data for bottom layer

Surface and Middle

4mg/L or 1 percentile of baseline data for surface and middle layer

Bottom

2mg/L or 1 percentile of baseline data for bottom layer

SS in mg/L (Surface, Middle & Bottom)

95 percentile of baseline data or 120% of upstream control station’s SS at the same tide of the same day

99 percentile of baseline data or 130% of upstream control station’s SS at the same tide of the same day or 10mg/L for WSD Seawater intakes

Turbidity in NTU (Surface, Middle & Bottom)

95 percentile of baseline data or 120% of upstream control station’s Turbidity at the same tide of the same day

99 percentile of baseline data or 130% of upstream control station’s Turbidity at the same tide of the same day or 10 NTU. WSD Seawater intakes

Copper in μg/L (depth averaged)

95 percentile of baseline data or 120% of upstream control station's nutrient level at the same tide of the same day

99 percentile of baseline or 130% of upstream control station's nutrient level at the same tide of the same day or 5 μg/L

Total PAH in μg/L (depth averaged)

95 percentile of baseline data or 120% of upstream control station's nutrient level at the same tide of the same day

99 percentile of baseline or 130% of upstream control station's nutrient level at the same tide of the same day or 3 μg/L

Notes:    1. For DO, non-compliance of the water quality limits occurs when monitoring result is lower than the limits.

2. For turbidity, SS, Copper and Total PAH,  non-compliance of the water quality limits occurs when monitoring result is higher than the limits.

3. All the figures given in the table are used for reference only and the EPD may amend the figures whenever it is considered as necessary.

4. For baseline monitoring, seasonal and spatial variation should be taken into account when setting up the baseline data.

7.11                   Event and Action Plan

Should non-compliance of the criteria occur, action in accordance with the Action Plan in the Table 7.6 below shall be carried out.

Table 7.6       Event / Action Plan for Water Quality

EVENT

ACTION

 

ET

IEC

ER

CONTRACTOR

Action level being exceeded by one sampling day

1. Inform IEC, contractor and ER;

2. Check monitoring data, all plant, equipment and Contractor’s working methods; and

3. Discuss remedial measures with IEC and Contractor and ER.

1. Discuss with ET, ER and Contractor on the implemented mitigation measures;

2. Review proposals on remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with IEC, ET and Contractor on the implemented mitigation measures;

2. Make agreement on the remedial measures to be implemented;

3. Supervise the implementation of agreed remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment;

5. Consider changes of working methods;

6. Discuss with ER, ET and IEC and purpose remedial measures to IEC and ER; and

7. Implement the agreed mitigation measures.

Action level being exceeded by more than one consecutive sampling days

1. Repeat in-situ measurement on next day of exceedance to confirm findings;

2. Inform IEC, contractor and ER;

3. Check monitoring data, all plant, equipment and Contractor’s working methods;

4. Discuss remedial measures with IEC, contractor and ER

5. Ensure remedial measures are implemented

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the proposed mitigation measures;

2. Make agreement on the remedial measures to be implemented ; and

3. Discuss with ET, IEC and Contractor on the effectiveness of the implemented remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of remedial measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed mitigation measures.

Limit level being exceeded by one sampling day

1. Repeat measurement on next day of exceedance to confirm findings;

2. Inform IEC, contractor and ER;

3. Rectify unacceptable practice;

4. Check monitoring data, all plant, equipment and Contractor’s working methods;

5. Consider changes of working methods;

6. Discuss mitigation measures with IEC, ER and Contractor; and

7. Ensure the agreed remedial measures are implemented

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the implemented remedial measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the remedial measures to be implemented; and

4. Discuss with ET, IEC and Contractor on the effectiveness of the implemented remedial measures.

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of additional mitigation measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed remedial measures.

Limit level being exceeded by more than one consecutive sampling days

1. Inform IEC, contractor and ER;

2. Check monitoring data, all plant, equipment and Contractor’s working methods;

3. Discuss mitigation measures with IEC, ER and Contractor; and

4. Ensure mitigation measures are implemented; and

5. Increase the monitoring frequency to daily until no exceedance of Limit Level for two consecutive days

1. Discuss with ET, Contractor and ER on the implemented mitigation measures;

2. Review the proposed remedial measures submitted by Contractor and advise the ER accordingly; and

3. Review and advise the ET and ER on the effectiveness of the implemented mitigation measures.

1. Discuss with ET, IEC and Contractor on the implemented remedial measures;

2. Request Contractor to critically review the working methods;

3. Make agreement on the remedial measures to be implemented;

4. Discuss with ET and IEC on the effectiveness of the implemented mitigation measures; and

5. Consider and instruct, if necessary, the Contractor to slow down or to stop all or part of the dredging activities until no exceedance of Limit level. 

1. Identify source(s) of impact;

2. Inform the ER and confirm notification of the non-compliance in writing;

3. Rectify unacceptable practice;

4. Check all plant and equipment and consider changes of working methods;

5. Discuss with ET, IEC and ER and submit proposal of additional mitigation measures to ER and IEC within 3 working days of notification; and

6. Implement the agreed remedial measures.

7. As directed by the ER, to slow down or stop all or part of the dredging activities until no exceedance of Limit level.

Note:

ET – Environmental Team

IEC – Independent Environmental Checker

ER – Engineer’s Representative


8                                Waste Management Implications

8.1                         Introduction

The quantity and timing for the generation of waste during the construction phase have been estimated. Measures including the opportunity for on-site sorting, reusing excavated materials etc, are devised in the construction methodology to minimise the surplus materials to be disposed off-site.  Proper disposal of chemical waste should be via a licensed waste collector.  All the proposed mitigation measures are stipulated in the EIA Report and summarised in the EMIS in Appendix C.

The types and quantities of waste that would be generated during the operational phase have been assessed.  It is anticipated there would not be any insurmountable impacts during the operational phase.  A trip-ticket system should be operated to monitor all movements of chemical wastes which will be collected by a licensed collector to a licensed facility for final treatment and disposal.  Recommendations have been made to ensure proper treatment and proper disposal of these wastes in the EIA Report and summarised in the EMIS in Appendix C.  The mitigation measures should form the basis of the Environmental Management Plan (EMP).

EM&A requirements are required for waste management during the construction phase only and the effective management of waste arising during the construction phase will be monitored through the site audit programme.  The aims of the waste audit are:

·         To ensure the waste arising from the works are handled, stored, collected, transferred and disposed of in an environmentally acceptable manner; and

·         To encourage the reuse and recycling of material.

8.2                         Waste EM&A Requirements

The Contractor shall be required to pay attention to the environmental standard and guidelines and carry out appropriate waste management and obtain the relevant licence/permits for waste disposal.  The ET shall ensure that the Contractor has obtained from the appropriate authorities the necessary waste disposal permits or licences including:

·         Chemical Waste Permits/licenses under the Waste Disposal Ordinance (Cap 354);

·         Public Dumping Licence under the Land (Miscellaneous Provisions) Ordinance (Cap 28);

·         Marine Dumping Permit under the Dumping at Sea Ordinance (Cap 466); and

·         Effluent Discharge Licence under the Water Pollution Control Ordinance.

The Contractor shall refer to the relevant booklets issued by the DEP when applying for the licence/permit and the ET shall refer to these booklets for auditing purposes.

Regular audits and site inspections should be carried out during construction phase by the ET to ensure that the recommended good site practices and other recommended mitigation measures are properly implemented by the Contractor.  The audits should concern all aspects of on-site waste management practices including waste generation, storage, recycling, transport and disposal.  Apart from site inspection, documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation and contract requirements.

The requirements of the environmental audit programme are set out in Section 14 of this Manual.  The audit programme will verify the implementation status and evaluate the effectiveness of the mitigation measures.


 

9                                Land Contamination Impact

9.1                         Introduction

Based on the site investigation (SI) works conducted in accordance with the endorsed Contamination Assessment Plan and the endorsed Supplementary Contaminated Assessment Plan, it was estimated that approximate 157m3 of contaminated soil would be generated from the cut-and-cover section on the Western Portion.

Considering the small quantity of contaminated soil to be generated and that the level of contamination detected only exceeded the RBRGs for “Rural Residential” and “Urban Residential”, but not the RBRGs for “Public Park” which is a more representative land use for CKR, on-site reuse of the contaminated soil within the boundary of CKR, such as using to backfill in non-pedestrian use area under new flyover, was recommended as the remediation option. The estimated contamination zone is shown in Figure 9.1.

9.2                         Excavation of the Contaminated Soil

Prior to commencement of the excavation works at the contamination zone, the zone should be clearly marked out on site and the surface levels recorded.  Excavation of contaminated material should be undertaken using dedicated earth-moving plant that should be thoroughly cleaned (e.g. jet-washed) following completion of the excavation works. The excavated contaminated soils would be stockpiled at designed area on site and covered by sheet to prevent dispersion of contamination during stockpiling.

The Contractor should pay attention to the selection of suitable groundwater lowering schemes and discharge points if the groundwater table is higher than the contaminated soils during excavation. The Contractor should also obtain a valid Water Pollution Control Ordinance (WPCO) discharge licence from EPD where applicable.

9.3                         Closure Assessment

Following completion of the excavation to the specified depth, at least one sample from the base of the excavation and four samples evenly distributed along the boundary of the excavation shall be taken for a closure assessment testing. The purpose of the closure assessment is to determine if all contaminated soil has been excavated. The acceptance criterion for the closure assessment is shown in Table 9.1.

Table 9.1   Acceptance criterion for the closure assessment

Locations

Testing Parameter

Acceptance Criterion

PBH4

PCBs

RBRGs (Public Park)

If the analysis indicates presence of contamination (i.e. non-compliance of the acceptance criteria), further excavation shall be carried out in 0.5m increment vertically and/or horizontally depending on the location(s) of the sample(s) which has exceeded the acceptance criteria. Further sampling shall also be conducted for compliance testing.  The process of excavation, sampling and compliance testing should continue until all contaminated materials are removed and should be supervised by a Land Contamination Specialist.

9.4                         Protective and Safety Measures

In order to minimise the potential adverse effects on health and safety of the workers during the course of site remediation works, and to ensure there are no significant residual health and safety risk imposed on the workers, the following good practices are recommended:

·        Personal Protective Equipment (PPE) such as safety hat, chemical protective gloves, masks, eye goggles, protective clothing (upgraded if contact with contaminated material cannot be avoided) and protective footwear etc. must be provided to staff, which would be involved in the remediation work. No works should be allowed without the suitable PPE.

·        Workers should inspect and check their PPE before, during and after use. In cases where any of the PPE is broken, the worker shall stop work immediately and inform the on-site registered safety officer. The worker is not allowed to re-start his work until the broken PPE is replaced.

·        Hand washing basins or other washing facilities shall be provided in areas easily accessible to all workers.

·        Workers should always maintain basic hygiene standard (e.g. hand wash before leaving the contaminated work zone). Workers shall also be responsible for cleaning and storing their own PPE in a secure place before leaving the site.

·        Eating, drinking and smoking must be strictly prohibited within the site areas.

It should be noted that these precautions are additional to any other health and safety requirements that will be applied on the site such as those requiring protective footwear and headgear.

9.5                         Remediation Report

A Remediation Report (RR) to demonstrate adequate clean-up shall be prepared by the Contractor and submitted to EPD for endorsement prior to the commencement of any construction/ development works within the site. No construction/ development works shall be carried out prior to the endorsement of the RR.


 

10                          Hazard to Life

10.1                   Introduction

Blasting activities regarding transport and use of explosives should be supervised and audited by the competent site staff to ensure that the assumptions and recommendations from the quantitative risk assessment (QRA) are implemented in accordance with the intent of the Hazard to Life assessment.

10.2                   Mitigation Measures

The recommended mitigation measures as outlined in the EMIS included in Appendix C of this EM&A Manual should be implemented to meet the TM- EIAO requirements.

 

 

11                          Landscape and Visual Impact

11.1                   Introduction

The EIA has recommended EM&A for landscape and visual resources is undertaken during the design, construction and operational stages of the project.  The design, implementation and maintenance of landscape mitigation measures is a key aspect of this and should be checked to ensure that they are fully realised and that potential conflicts between the proposed landscape measures and any other project works and operational requirements are resolved at the earliest possible date and without compromise to the intention of the mitigation measures.  In addition, implementation of the mitigation measures recommended by the EIA will be monitored through the site audit programme.

11.2                   Mitigation Measures

The Landscape and Visual Assessment of the EIA proposes a number of mitigation measures to ameliorate the landscape and visual impacts of the Project.  These measures include , but are not limited to the following and implementation is summarised in the EMIS in Appendix C. 

·      Reduction of construction stage to the shortest possible time;

·      Incorporation of landscape and visual considerations into the detailed design;

·      General good site management;

·      Screen hoarding;

·      Erosion control;

·      Measures concerning trees, including tree protection and preservation, tree transplantation and compensatory planting;

·      Screen planting;

·      Reinstatement and re-provising of public open space; 

·      General landscape enhancement; and specific landscape enhancement through such means as vertical greening, landscape deck, planters on viaducts, roadside planting and green roofs;

·      Lighting control during both construction and operation.

The landscape and visual mitigation measures proposed should be incorporated in the landscape and engineering design.  Mitigation measures to be implemented during construction should be adopted from the start of construction and be in place throughout the entire construction period.  Mitigation measures to be implemented during operation should be integrated into the detailed design and built as part of the construction works so that they are in place on commissioning of the Project.  Tree transplantation and compensatory planting should be carried out as early as possible in the Project with transplantation carried out prior to construction starting in any particular area.

11.3                   Audit Requirement

The measures proposed within the EIA to mitigate the landscape and visual impacts of the Project should be embodied into the detailed landscape design drawings and contract documents including the protection of existing trees where possible, the transplanting of existing trees, the planting of new trees and shrubs, re-provisioning of public open space. 

The design stage EM&A requirements for landscape and visual resources comprise the audit of the detailed landscaping and visual specifications to be prepared during the detailed design together with ensuring that the design is sensitive to landscape and visual impacts.  The landscape and visual auditor shall review the designs as and when they are prepared and liaise with the landscape architect and design engineer to ensure all measures have been incorporated in the design in a format that can be specified to the Contractor for implementation.  In the event of non-compliance, the responsibilities of the relevant parties are detailed in the Event/Action plan provided in Table 11.1.

Table 11.1 Event / Action Plan for Design Stage

Action Level

Landscape and Visual Auditor

Project Engineer (PE)

Project Landscape Architect (PLA)

Non Conformity (with Design Standards and Specification)

1.   Identify Source

2.   Inform PE and PLA

3.   Discuss remedial actions and preventive measures with PE, PLA

4.   Verify remedial actions when complete

1.   Notify PLA

2.   Discuss remedial actions and preventive measures with PLA

3.   Ensure remedial designs and preventive measures are fully incorporated

1.  Amend designs

2.   Discuss remedial actions and preventive measures with PE

Note: PE – Project Engineer; PLA – Project Landscape Architect

 

Site audits should be undertaken during the construction stage of the Project to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives. Site inspections should be undertaken by the ET at least once every two weeks during the construction period.

Soft landscaping works have an establishment period of 24 months.  This period will start once plants have been planted, and this may be prior to, during or post-construction and/or during operation stages.  Should the establishment period start or continue outside the construction stage (when regular inspections are taken every two weeks), regular inspections (e.g. quarterly) should be undertaken until the end of the establishment period.

In the event of non-compliance, the responsibilities of the relevant parties are detailed in the Event/Action plan provided in Table 11.2.

Table 11.2 Event / Action Plan for Landscape and Visual during construction phase

Action Level

ET

IEC

ER

Contractor

Non-conformity on one occasion

1. Identify source(s)

2. Inform the Contractor, IEC and ER

3. Discuss remedial actions and preventive measures with IEC, ER and Contractor

4. Monitor remedial action(s) and preventive measures until rectification has been completed

1. Check inspection report

2. Check Contractor’s working method

3. Discuss with ET, ER and Contractor on possible remedial measure(s) and preventive measure(s)

4. Advise ER on effectiveness of proposed remedial measure(s) and preventive measure(s)

5. Check implementation of proposed remedial measure(s) and preventive measure(s)

1. Confirm receipt of notification of non-conformity in writing

2. Notify the Contractor

3. Review and agree on the remedial measure(s) and preventive measures proposed by the Contractor

4. Check implementation of remedial measure(s) and preventive measures

1. Identify source and investigate the non-conformity

2. Implement remedial measure(s) and preventive measure(s)

3. Amend working methods agreed with ER as appropriate

4. Rectify damage and undertake any necessary replacement

Repeated Non-conformity

1. Identify source(s)

2. Inform Contractor, IEC and ER

3. Discuss inspection frequency

4. Discuss remedial action(s) and preventive measures with IEC, ER and Contractor

5. Monitor remedial action(s) and preventive measure(s) until rectification has been completed

6. If non-conformity stops, cease any additional monitoring

1. Check inspection report

2. Check Contractor’s working method

3. Discuss with ET, ER and Contractor on possible remedial measure(s) and preventive measure(s)

4. Advise ER on effectiveness of proposed remedial measure(s) and preventive measures

5. Supervise implementation of proposed remedial measure(s) and preventive measure(s)

1. Notify the Contractor

2. In consultation with the ET and IEC, agree with the Contractor on the remedial measure(s) and preventive measure(s) to be implemented

3. Supervise implementation of remedial measure(s) and preventive measure(s)

1. Identify source and investigate the non-conformity

2. Implement remedial measure(s) and preventive measure(s)

3. Amend working methods agreed with ER as appropriate

4. Rectify damage and undertake any necessary replacement. Stop relevant portion of works as determined by ER until the non-conformity is abated.

Note:

ET – Environmental Team

IEC – Independent Environmental Checker

ER – Engineer’s Representative

 

 

12                          Impact on Cultural Heritage (Terrestrial and Marine Archaeology)

12.1                   Introduction

The assessment has considered both the construction and operational phases of the project.

12.2                   Mitigation Measures

Terrestrial Archaeology

Any development encroaching on sites of archaeological interest should be avoided as far as possible. The contractor should be alerted during the construction on the possibility of locating archaeological remains as a precautionary measure.  AMO shall be informed immediately in case of discovery of antiquities or supposed antiquities in the subject areas.

According to the EIA, no mitigation will be required during the construction and operational phase. Therefore, no monitoring and audit programme will be required.

Marine Archaeology

According to the EIA, there are buried unidentified objects beneath the disused fuel dolphin located by geophysical survey. The dredging contractor should be alerted during the construction on the possibility of locating archaeological remains such as cannon and AMO shall be informed immediately in case of discovery of antiquities or supposed antiquities in the subject areas.

As no additional mitigation is required, monitoring and audit programme will be not required.

 

13                          Impact on Cultural Heritage (Built Heritage)

13.1                   Introduction

A cultural and heritage impact assessment on built heritage for the Project has been conducted according to the EIA Study Brief. The assessment has considered both the construction and operational phases of the project.

The assessment has recommended some mitigation measures for both the archaeological sites and some of the historical buildings where impacts would be envisaged.

13.2                   Mitigation Measures

13.2.1             Construction Phase

All the proposed mitigation measures are presented below and summarised in the EMIS in Appendix C.

Yau Ma Tei Police Station

Table 13.1 Mitigation Recommendations for Yau Ma Tei Police Station (Construction Phase) of CKR

Wing

Mitigation Recommendation

New Wing (CKR-01)

(Figure 13.1)

·      Protective covering should be provided for the buildings in the form of plastic sheeting;

·      Buffer zones should be provided between the construction works and the external walls of the buildings and should be as large as site restrictions allow and be marked out by temporary fencing or hoarding;

·      An underpinning scheme is required to transfer the existing column loadings to a deeper rock stratum. The supporting system includes cutting the existing ground floor slab to expose the existing pile caps and then construct transfer beams at both sides of the pile caps. The transfer beams will tie up with the existing caps. Loadings of the transfer beams will be transferred to the rock socket piles installed at the two ends of the beams;

·      the AAA settlement and tilting limit should be 6/8/10 mm and 1/2000, 1/1500 and 1/1000;

·      Monitoring of vibration levels will be undertaken during the construction phase and the Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s;

·      A monitoring proposal will be submitted to AMO before commencement of work;

·      Regular site inspections and monitoring works will be carried out by the contractor and the monitoring results will be submitted to the resident site staff of HyD to ensure compliance.

Old Wing (CKR-01)

(Figure 13.1)

·      Adopting diaphragm wall construction method;

·      Grout curtain should be provided in front of the building;

·      Recharging system should be installed as a contingency measure to mitigate the fluctuation of water table;

·      the AAA settlement and tilting limit should be 6/8/10 mm and 1/2000, 1/1500 and 1/1000;

·      Monitoring of vibration levels will be undertaken during the construction phase and the Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s;

·      A monitoring proposal will be submitted to AMO before commencement of work;

·      Regular site inspections and monitoring works will be carried out by the contractor and the monitoring results will be submitted to the resident site staff of HyD to ensure compliance.

 

Other Built Heritage

Table 13.2 Mitigation Recommendations for Other Impacted Heritage Features (Construction Phase) of CKR

Resource

Mitigation Recommendation

Tin Hau Temple (CKR-02)

(Figure 13.1)

The Alert, Alarm and Action (AAA) vibration limit will be set at 3/4/5 mm/s and a condition survey shall be carried out by the project proponent prior to the construction phase to confirm this assessment

Vibration monitoring of the structure shall be employed during the construction phase to ensure that the level is not exceeded. A monitoring proposal will be submitted to AMO before commencement of work.

Kowloon Methodist Church

(CKR-10)

(Figure 13.1)

The Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s. 

Vibration monitoring of the structure shall be employed during the construction phase to ensure that the level is not exceeded and as such appropriate vibration monitoring on the building should be complied with as appropriate. A monitoring proposal will be submitted to AMO before commencement of work.

Ma Tau Kok Animal Quarantine Depot (CKR-12)

(Figure 13.2)

The Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s. 

Vibration monitoring of the structure shall be employed during the construction phase to ensure that the level is not exceeded, and as such appropriate vibration monitoring on the building should be complied with as appropriate. A monitoring proposal will be submitted to AMO before commencement of work.

Kowloon City Ferry Pier (CKR-13)

(Figure 13.2)

A monitoring system for settlement, vibration and tilting will be determined and implemented pending determination of the future grading. A monitoring proposal will be submitted to AMO before commencement of work if a historic building grade is accorded.

Air raid precaution tunnels of the K1  Network (CKR-14)

(Figure 13.1)

An evaluation of the structural integrity and condition of the tunnel network is outside the scope of this BHIA study.

A condition survey for the tunnel network should be undertaken by the project proponent to determine the present condition of the air raid tunnels and to recommend protective measures to ensure that the tunnels are not damaged by the construction works. and as such appropriate vibration monitoring on the building should be complied with as appropriate. . A monitoring proposal will be submitted to AMO before commencement of work.

Ma Tau Kok Public Pier (CKR-16)

(Figure 13.2)

No mitigation is required at present. If the public pier is granted Grade 1, Grade 2 or Grade 3 status, the mitigation will be revised to adhere to the requirements for protective measures for Graded Historic Buildings.

The Kowloon City Vehicular Ferry Pier (CKR-17)

(Figure 13.2)

A monitoring system for settlement, vibration and tilting will be determined and implemented pending determination of the future grading. A monitoring proposal will be submitted to AMO before commencement of work if a historic building grade is accorded.

Kowloon Permanent Pier No. 70 (CKR-18)

(Figure 12.4)

The pier contains active gas pipelines and will be strictly monitored for safety precautions during the works based on guidelines from the HK China Gas Company. It is concluded that these guidelines will provide sufficient protection for the pier structure and no additional precautions from a heritage perspective would be required. However, if the pier is granted Grade 1, Grade 2 or Grade 3 status, the mitigation will be revised if necessary,  to adhere to the requirements for protective measures for Graded Historic Buildings.

13.2.2             Operational Phase

The operation of the CKR will not impose any adverse impacts on any built heritage. No mitigation will be required regarding this issue.

13.3                   Audit Requirements

The ET shall audit the relevant condition survey and ground-borne vibration to ensure that the peak vibration levels are not exceeded.

Table 13.3:                Audit Requirements and Frequency

ID

Structure / buildings

Audit Requirements

Audit frequency

CKR-02

Tin Hau Temple

The Alert, Alarm and Action (AAA) vibration limit will be set at 3/4/5 mm/s.

On a weekly basis throughout the construction period for bored tunnel formation and daily within 100m (vector distance) of the historic building

CKR-10

Kowloon Methodist Church

The Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s. 

On a weekly basis throughout the construction period for bored tunnel formation and daily within 100m (vector distance) of the historic building

CKR-12

Ma Tau Kok Animal Quarantine Depot

The Alert, Alarm and Action (AAA) vibration limit will be set at 5/6/7.5 mm/s. 

On a weekly basis throughout the construction period for bored tunnel formation and daily within 100m (vector distance) of the historic building

In addition, the appropriate vibration monitoring on the attached built heritage resources will be agreed with BD/GEO under the requirement of Buildings Ordinance and/or Blasting Permit as appropriate. The project proponent should ensure that vibration levels are controlled to appropriate level. Vibration monitoring should be carried out by the contractor.

 

14                          Site Environmental Audit

14.1                   Site Inspection

Site inspection provides a direct means to initiate and enforce specified environmental protection and pollution control measures.  These shall be undertaken routinely to inspect construction activities in order to ensure that appropriate environmental protection and pollution control mitigation measures are properly implemented.  Site inspection is one of the most effective tools to enforce the environmental protection requirements at the works area.

The ET shall be responsible for formulating the environmental site inspection programme as well as the deficiency and action reporting system, and for carrying out the site inspections.  The proposal for rectification, if any, should be prepared and submitted to the ET Leader and IEC by the Contractor.

Regular site inspections shall be carried out and led by the ER and attended by the Contractor and ET at least once per week during the construction phase.  The areas of inspection shall not be limited to the environmental situation, pollution control and mitigation measures within the site.  It should also review the environmental situations outside the works area which is likely to be affected, directly or indirectly, by the construction site activities of the Project.  The ET shall make reference to the following information in conducting the inspection.  During the inspection, the following information should be referred to:

(i)                  EIA Report recommendations on environmental protection and pollution control mitigation measures;

(ii)                works progress and programme;

(iii)               individual works methodology proposals (which shall include the proposal on associated pollution control measures);

(iv)              contract specifications on environmental protection;

(v)                relevant environmental protection and pollution control legislations; and

(vi)              previous site inspection results.

The Contractor shall keep the ER and ET Leader updated with all relevant environmental related information on the construction contract necessary for him to carry out the site inspections.  Site inspection results and associated recommendations for improvements to the environmental protection and pollution control efforts should be recorded and followed up by the Contractor in an agreed time-frame.  The Contractor shall follow the procedures and time-frame as stipulated in the environmental site inspection, and the deficiency and action reporting system formulated by the ET, to report on any remedial measures subsequent to the site inspections.

The ER, ET and the Contractor should also carry out ad-hoc site inspections if significant environmental problems are identified. Inspections may also be required subsequent to receipt of a valid environmental complaint, or as part of the investigation work, as specified in the Action Plan for the EM&A programme.

14.2                   Environmental Compliance

There are statutory requirements on environmental protection and pollution control requirements with which construction activities must comply.

In order that the works comply with all method statements of works should be submitted by the Contractor to the ER for approval and to the ET Leader to ensure sufficient environmental protection and pollution control measures have been included.  The Environmental Mitigation Implementation schedule (EMIS) is summarised in Appendix C.  Any proposed changes to the mitigation measures shall be certified by the ET Leader and verified by the IEC as conforming to the relevant information and recommendations contained in the EIA Report.

The ER and ET shall also review the progress and programme of the works to check that relevant environmental legislations have not been violated, and that any foreseeable potential for violating laws can be prevented.

The Contractor should provide the update of the relevant documents to the ET Leader so that checking can be carried out.  The document shall at least include the updated Works Progress Reports, updated Works Programme, method statements, any application letters for different licences / permits under the environmental protection laws, and copies of all valid licences / permits.  The site diary and environmental records shall also be available for inspection by the relevant parties.

After reviewing the document, the ET shall advise the IEC and Contractor of any non-compliance with legislative requirements on environmental protection and pollution control so that they can timely take follow-up actions as appropriate.  If the follow-up actions may still result in potential violation of environmental protection and pollution control requirements, the ER and ET should provide further advice to the Contractor to take remedial action to resolve the problem.

Upon receipt of the advice, the Contractor shall undertake immediate actions to correct the situation.  The ER and ET shall follow up to ensure that appropriate action has been taken in order to satisfy legal requirements.

14.3                   Choice of Construction Method

At times during the construction phase the Contractor may submit method statements for various aspects of construction.  This state of affairs would only apply to those construction methods that the EIA has not imposed conditions while for construction methods that have been assessed in the EIA, the Contractor is bound to follow the requirements and recommendations in the EIA study.  The Contractors options for alternative construction methods may introduce adverse environmental impacts into the Project.  It is the responsibility of the Contractor and ET, in accordance with established standards, guidelines and EIA study recommendations and requirements, to review and determine the adequacy of the environmental protection and pollution control measures in the Contractors proposal in order to ensure no unacceptable impacts would result.  To achieve this end, the ET shall provide a copy of the Proactive Environmental Protection Proforma as shown in Appendix G to the IEC for approval.  The IEC should audit the review of the construction method and endorse the proposal on the basis of no adverse environmental impacts.

14.4                   Environment Complaints

The following procedures should be undertaken upon receipt of any environmental complaint:

(i)                  The Contractor to log complaint and date of receipt onto the complaint database and inform the ER, ET and IEC immediately;

(ii)                The Contractor to investigate, with the ER and ET, the complaint to determine its validity, and assess whether the source of the problem is due to construction works of the Project with the support of additional monitoring frequency and stations, if necessary;

(iii)               The Contractor to identify remedial measures in consultation with the IEC, ET and ER if a complaint is valid and due to the construction works of the Project;

(iv)              The Contractor to implement the remedial measures as required by the ER and to agree with the ET and IEC any additional monitoring frequency and stations, where necessary, for checking the effectiveness of the remedial measures;

(v)                The ER, ET and IEC to review the effectiveness of the Contractor's remedial measures and the updated situation;

(vi)              The ET to undertake additional monitoring and audit to verify the situation if necessary, and oversee that circumstances leading to the complaint do not recur;

(vii)             If the complaint is referred by the EPD, the Contractor to prepare interim report on the status of the complaint investigation and follow-up actions stipulated above, including the details of the remedial measures and additional monitoring identified or already taken, for submission to EPD within the time frame assigned by the EPD; and

(viii)           The ET to record the details of the complaint, results of the investigation, subsequent actions taken to address the complaint and updated situation including the effectiveness of the remedial measures, supported by regular and additional monitoring results in the monthly EM&A reports.


 

15                          Reporting

15.1                   General

Reports can be provided in an electronic medium upon agreeing the format with the ER and EPD.  This would enable a transition from a paper / historic and reactive approach to an electronic / real time proactive approach.  All the monitoring data (baseline and impact) shall also be submitted on diskettes or other approved media.  The formats for air quality, noise and water quality monitoring data to be submitted shall be separately agreed.

The ET is responsible for establishing and maintaining a dedicated website throughout the entire construction period for publishing all the relevant environmental monitoring data (including but not limited to the baseline and impact monitoring).  The ET shall propose the format and functionality of the website for agreement with the ER and IEC prior to publishing of data.  Once the monitoring data are available (e.g. noise, dust, water quality etc) and vetted by the IEC, the ET is responsible to upload the relevant data to the dedicated website.

Types of reports that the ET shall prepare and submit include baseline monitoring report, monthly EM&A report and final EM&A review report.  In accordance with Annex 21 of the EIAO-TM, a copy of the monthly and final review EM&A reports shall be made available to the Director of Environmental Protection.

15.2                   Baseline Monitoring Report

The ET should prepare and submit a Baseline Environmental Monitoring Report at least one month before commencement of construction of the Project.  Copies of the Baseline Environmental Monitoring Report should be submitted to the IEC, ER and EPD.  The ET should liaise with the relevant parties on the exact number of copies require.

The baseline monitoring report shall include at least the following:

(i)                  up to half a page executive summary;

(ii)                brief project background information;

(iii)               drawings showing locations of the baseline monitoring stations;

(iv)              monitoring results (in both hard and diskette copies) together with the following information:

·        monitoring methodology;

·        name of laboratory and types of equipment used and calibration details;

·        parameters monitored;

·        monitoring locations;

·        monitoring date, time, frequency and duration; and

·        quality assurance (QA) / quality control (QC) results and detection limits;

(v)                details of influencing factors, including:

·        major activities, if any, being carried out on the site during the period;

·        weather conditions during the period; and

·        other factors which might affect monitoring results;

(vi)              determination of the Action and Limit Levels for each monitoring parameter and statistical analysis of the baseline data;

(vii)             revisions for inclusion in the EM&A Manual; and

(viii)           comments, recommendations and conclusions.

15.3                   Monthly Monitoring Reports

The results and findings of all EM&A work required in the Manual shall be recorded in the monthly EM&A reports prepared by the ET and endorsed by the IEC.  The EM&A report shall be prepared and submitted to EPD within 10 working days of the end of each reporting month, with the first report due the month after construction commences.  Copies of each monthly EM&A report shall be submitted to the following parties: the IEC, the ER and EPD.  Before submission of the first EM&A report, the ET shall liaise with the parties on the required number of copies and format of the monthly reports in both hard copy and electronic medium.

The ET shall review the number and location of monitoring stations and parameters every six months, or on as needed basis, in order to cater for any changes in the surrounding environment and the nature of works in progress.

First Monthly EM&A Report

The first monthly EM&A report shall include at least the following:

(i)                  Executive summary (1-2 pages):

·        breaches of Action and Limit levels;

·        compliant log

·        notifications of any summons and successful prosecutions;

·        reporting changes; and

·        future key issues.

(ii)                Basic project information:

·        project organization including key personnel contact names and telephone numbers;

·        programme;

·        management structure; and

·        works undertaken during the month.

(iii)               Environmental status:

·        advice on the status of statutory environmental compliance such as the status of compliance with the environmental permit (EP) conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;

·        works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc.); and

·        drawings showing the project are, any environmental sensitive receivers and the locations of the monitoring and control stations (with co-ordinates of the monitoring locations).

(iv)              A brief summary of EM&A requirements including:

·        all monitoring parameters;

·        environmental quality performance limits (Action and Limit levels);

·        Event-Action Plans;

·        environmental mitigation measures, as recommended in the project EIA study final report; and

·        environmental requirements in contract documents.

(v)                Implementation status

·        advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report.

(vi)              Monitoring results (in both hard and diskette copies) together with the following information:

·        monitoring methodology;

·        name of laboratory and types of equipment used and calibration details;

·        monitoring parameters;

·        monitoring locations;

·        monitoring date, time, frequency, and duration;

·        weather conditions during the period;

·        any other factors which might affect the monitoring results; and

·        QA / QC results and detection limits.

(vii)             Report on non-compliance, complaints, and notifications of summons and successful prosecutions:

·        record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

·        record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

·        record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

·        review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and

·        description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

(viii)           Others

·        an account of the future key issues as reviewed from the works programme and work method statements;

·        advice on the solid and liquid waste management status;

·        record of any project changes from the originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc.); and

·        comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.

Subsequent monthly EM&A Reports

Subsequent monthly EM&A reports shall include at least the following:

(i)                  Executive summary (1-2 pages):

·        breaches of Action and Limit levels;

·        compliant log

·        notifications of any summons and successful prosecutions;

·        reporting changes; and

·        future key issues.

(ii)                Basic project information:

·        project organization including key personnel contact names and telephone numbers;

·        programme;

·        management structure; and

·        works undertaken during the month; and

·        any updates as needed to the scope of works and construction methodologies.

(iii)               Environmental status:

·        advice on the status of statutory environmental compliance such as the status of compliance with the environmental permit (EP) conditions under the EIAO, submission status under the EP and implementation status of mitigation measures;

·        works undertaken during the month with illustrations (such as location of works, daily excavation rate, etc.); and

·        drawings showing the project are, any environmental sensitive receivers and the locations of the monitoring and control stations.

(iv)              Implementation status

·        advice on the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report.

(v)                Monitoring results (in both hard and diskette copies) together with the following information:

·        monitoring methodology;

·        name of laboratory and types of equipment used and calibration details;

·        monitoring parameters;

·        monitoring locations;

·        monitoring date, time, frequency, and duration;

·        weather conditions during the period;

·        any other factors which might affect the monitoring results; and

·        QA / QC results and detection limits.

(vi)              Report on non-compliance, complaints, and notifications of summons and successful prosecutions:

·        record of all non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

·        record of all complaints received (written or verbal) for each media, including locations and nature of complaints investigation, liaison and consultation undertaken, actions and follow-up procedures taken, results and summary;

·        record of all notification of summons and successful prosecutions for breaches of current environmental protection / pollution control legislation, including locations and nature of the breaches, investigation, follow-up actions taken, results and summary;

·        review of the reasons for and the implications of non-compliances, complaints, summons and prosecutions including review of pollution sources and working procedures; and

·        description of the actions taken in the event of non-compliance and deficiency reporting and any follow-up procedures related to earlier non-compliance.

(vii)             Others

·        an account of the future key issues as reviewed from the works programme and work method statements;

·        advice on the solid and liquid waste management status;

·        record of any project changes from the originally proposed as described in the EIA (e.g. construction methods, mitigation proposals, design changes, etc.); and

·        comments (for examples, effectiveness and efficiency of the mitigation measures), recommendations (for examples, any improvement in the EM&A programme) and conclusions.

(viii)           Appendices

·        Action and Limit levels;

·        graphical plots of trends of the monitoring parameters at key stations over the past four reporting periods for representative monitoring stations annotated against the following:

a)      major activities being carried out on site during the period;

b)      weather conditions during the period; and

c)      any other factors that might affect the monitoring results.

·        monitoring schedule for the present and next reporting period;

·        cumulative statistics on complaints, notifications of summons and successful prosecutions; and

·        outstanding issues and deficiencies.

15.4                   Final EM&A Review Reports

The EM&A programme should be terminated upon the completion of the construction activities that have the potential to result in significant environmental impacts.

Prior to the proposed termination, it may be advisable to consult relevant local communities.  The proposed termination should only be implemented after the proposal has been endorsed by the IEC, the Engineer and the Project Proponent followed by approval from the Director of Environmental Protection.

The final EM&A report should contain at least the following information:

(i)                  Executive summary (1-2 pages):

(ii)                Drawings showing the project are, any environmental sensitive receivers and the locations of the monitoring and control stations;

(iii)               Basic project information including a synopsis of the project organization, contacts of key management, and a synopsis of work undertaken during the course of the project or past twelve months;

(iv)              A brief summary of EM&A requirements including:

·        environmental mitigation measure, as recommended in the project EIA Report;

·        environmental impact hypotheses tested;

·        environmental quality performance limits (Action and Limit levels);

·        all monitoring parameters;

·        Event and Action Plans;

(v)                A summary of the implementation status of environmental protection and pollution control / mitigation measures, as recommended in the project EIA Report, summarized in the updated implementation schedule;

(vi)              Graphical plots and the statistical analysis of the trends of monitoring parameter over the course of the project, including the post-project monitoring for all monitoring stations annotated against:

·        the major activities being carried out on site during the period;

·        weather conditions during the period; and

·        any other factors which might affect the monitoring results;

(vii)             A summary of non-compliance (exceedances) of the environmental quality performance limits (Action and Limit levels);

(viii)           A review of the reasons for and the implications of non-compliance including review of pollution sources and working procedures as appropriate;

(ix)              A description of the actions taken in the event of non-compliance;

(x)                A summary record of all complaints received (written or verbal) for each media, liaison and consultation undertaken, actions and follow-up actions taken and results;

(xi)              A review of the validity of EIA predictions and identification of shortcomings in EIA recommendations;

(xii)             Comments (for examples, a review of the effectiveness and efficiency of the mitigation measures and of the performance of the environmental management system, that is, of the overall EM&A programme); and

(xiii)           Recommendations and conclusions (for example, a review of success of the overall EM&A programme to cost-effectively identify deterioration and to initiate prompt effective mitigatory action when necessary).

15.5                   Data Keeping

No site-based documents (such as monitoring field records, laboratory analysis records, site inspection forms, etc.) are required to be included in the monthly EM&A reports.  However, any such document shall be well kept by the ET and be ready for inspection upon request.  All relevant information shall be clearly and systematically recorded in the document.  Monitoring data shall also be recorded in magnetic media form, and the software copy must be available upon request.  Data format shall be agreed with EPD. All documents and data shall be kept for at least one year following completion of the construction contract.

15.6                   Interim Notifications of Environmental Quality Limit Exceedances

With reference to the Event and Action Plans, when the environmental quality performance limits are exceeded and if they are proven to be valid, the ET should immediately notify the IEC and EPD, as appropriate.  The notification should be followed up with advice to the IEC and EPD on the results of the investigation, proposed actions and success of the actions taken, with any necessary follow-up proposals.  A sample template for the interim notification is presented in Appendix F.