17                          Conclusion

17.1                   Alternative Options

 

CBL Alignment Options

17.1.1                     The routing of the CBL is proposed as an east-west connection between Wan Po Road and TKO-LT Tunnel across the south of the TKO Town Centre. Four route alignments for the CBL have been identified.

17.1.2                     According to “Further Development of Tseung Kwan O Feasibility Study – Final Topical Study Report: Cross Bay Link” (2005), the four route alignment options are appraised broadly in terms of traffic performance, compatibility with land use planning intentions, and potential environmental impacts. Based on the outcome of the assessment, Route Alignment Option 2 is considered suitable. Consequently, the two structural forms of the option – Scheme A (Bridge Arrangement) and Scheme B (Tunnel Arrangement) is further assessed in terms of four aspects including engineering, highway traffic, environmental and cost. In overall terms, Scheme A (Bridge Arrangement) of Route Alignment Option 2 is selected as the preferred CBL scheme.

17.1.3                     Following a preliminary evaluation of the long list of bridge options, six design options were identified as technically feasible for the project and were shortlisted in the Final Design Options Review Report (2010). According to the public consultation, Design Option 5, the Eternity Arch, is carried forward as the preferred option for CBL.

 

Preferred Construction Method

17.1.4                     Off-site precast segmental construction and off-site erection will be adopted for the construction of the CBL. The environmental impact was one of the key reasons for adopting these construction methods since moving construction away from the site reduces the nuisance to local residents and the impact on the local environment. However, the purpose of the off-site fabrication is not to transfer the problems elsewhere.  The concrete pre-casting and steel fabrication yards in China are purpose-built facilities, with production line practices implemented. Hence, the impacts would be better managed and controlled.

17.2                   Construction Descriptions

17.2.1                     The CBL is targeted to be commissioned by 2020. Hence, the construction of the CBL will start in late 2016, for completion in 2020, with a construction period of 4 years.

17.2.2                     The major construction works would include the following activities:

CBL

·         Foundations – Installation of piles by marine piling rigs, erection of cofferdam, building of pile caps, and building of piers;

·         Substructure and superstructure – erection of concrete deck segments of the approach, and installation of main bridge and side spans; and

·         Construction of the cycle track ramp.

Road D9

·         Sea wall modification and strengthening;

·         Ground improvement works;

·         Piling and erection of noise barrier.

17.3                   Air Quality Impact

17.3.1                     During construction phase, potential dust impact would be generated from the soil excavation activities, backfilling, site erosion, storage of spoil on site, and transportation of soil during the construction phase. Quantitative fugitive dust assessments have therefore been conducted for the construction of CBL. The assessment result has concluded that watering once per hour on exposed worksites and haul road is recommended to achieve dust removal efficiency of 91.7%.  In addition to the watering and required intensity, the Contractor will also be obliged to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation.  With the implementation of recommended mitigation measures, no adverse air quality impact is anticipated during the construction phase.

17.3.2                     Cumulative air quality impact arising from the vehicular emissions from the open roads, tunnel portals and the chimney emissions from various industries in the TKOIE during the operational phase has been assessed. The assessment results have concluded that all the 1-hour, 24-hour and annual NO2 and RSP concentrations would comply with the relevant AQOs. Hence, no adverse cumulative air quality is therefore anticipated during the operational phase.

17.3.2.1                 Overall, it was concluded that during the both the construction and operational phases of CBL, Annex 12 of the TM-EIAO would be fully complied with.

17.4                   Noise Impact

17.4.1                     During construction phase, construction noise impacts would arise from major construction works for CBL (i.e. installation of piles by marine piling rigs, erection of cofferdam, building pile caps, erection of noise barrier, etc.  Unmitigated construction noise assessment results indicate exceedance of the daytime noise criteria, and therefore, mitigation measures are required.  However, with the implementation of proposed mitigation measures (i.e. good site practice, use of quite plant and working methods, use of site hoarding/shrouds/temporary noise barriers, etc.), predicted mitigated noise levels at all Noise Sensitive Receivers will be within the respective noise criteria due to the construction of CBL. The predicted cumulative noise impacts exceed the noise criterion for Planned Primary School & Secondary School near Wan Po Road (R33 & R34) during examination period.  The contractor should therefore further confirm the construction program of this NSR at the commencement of the CBL construction work.  The CBL construction work at Road D9 will be scheduled to avoid the examination period at the Planned Primary and Secondary School (R33 & R34) if the educational institution at R33 and R34 are constructed before the commencement of CBL construction work.

17.4.2                     For operational phase, noise impacts are contributed by traffic at Road D9 and CBL and therefore a 6m height partial enclosure along road D9 and low noise surfacing on CBL and Road D9 have been proposed to mitigate impacts.  However, exceedance of the noise criterion is still predicted at planned development residential block R22 of Lohas Park Stage 3.  As R22 was previously assessed, mitigation measures have been proposed by the Area 86 development proponent.  Further analysis revealed that the noise exceedance is predominantly due to the Road R5 and model predictions indicate that the new roads contribute less than 1dB(A) to the overall noise level and the predicted noise level arising from new roads is less than 70dB(A). No further actions are therefore required by the CBL Project proponent. 

17.4.2.1                Overall, in respect of both the construction and operational phases of CBL, Annex 5 of the TM-EIAO would be complied with.

17.5                   Sediment Quality

17.5.1                     A marine GI with sediment sampling and laboratory testing has been undertaken and analysed in accordance with the requirements in ETWB 34/2002.  It is estimated that a total of approximately 4,300m3 marine deposit is required to be dredged. Amongst the dredged volume, approximately 97% is Category L sediment. Category Mp, Mf, and H sediments contribute approximately 3% of the total volume.

17.5.2                     Overall, it was concluded that in respect of the marine sediment to be excavated and disposed at sea during the construction of the CBL, Annex 7 of the TM-EIAO would be complied with.

17.6                   Waste Management

17.6.1                     Potential waste management implications from the generation of waste during the construction and operational phase of the Project have been evaluated. A range of best practice mitigation measures have been proposed for implementation by the Contractor during the construction period to minimise waste generation and off-site disposal. In addition, monitoring and audit measures are proposed to ensure that robust measures are promoted to minimise impacts and that waste is controlled effectively.

17.6.2                     With the implementation of all the proposed mitigation measures, no adverse residual waste management implications were anticipated during both the construction and operational phases.   Overall, it was concluded that the waste management implications of CBL would comply with Annex 7 of the TM-EIAO.

 

17.7                   Water Quality Impact

17.7.1                     During construction phase, water quality impacts may arise from pile excavation works, construction site runoff and sewage from workforce.  For pile excavation works, assessment results indicate  that non-compliance with the assessment criteria for WSD’s salt water intakes for flushing water (10mg/L), or any Fish Culture Zone in the vicinity, is not anticipated.  Although the interface of the marine works for CBL project with T2 is anticipated, the plume from CBL was well confined in Junk Bay area and superpositions of plume with T2 is not anticipated.  With the implementation of proposed mitigation measures, adverse water quality impacts during construction phase are not anticipated.

17.7.2                     During operational phase, no significant change in the hydrodynamic and water quality regime is anticipated.  No mitigation measures such as maintenance dredging are therefore required.  Due to potential runoff from road surfaces, proper drainage systems with silt traps and oil interceptors should be installed, maintained and cleaned at regular intervals as a precautionary measure.

17.7.2.1                Overall, it was concluded that water quality impacts would comply with Annex 6 of the TM-EIAO during both the construction and operational phases of CBL.

17.8                   Marine Ecological Impact

17.8.1                     There are no recognised sites of conservation importance (e.g. SSSIs, Country Parks and Marine Parks) inside Junk Bay, and there are no ecological sensitive areas (e.g. high value coral communities) inside or close to the CBL alignment.

17.8.2                     The CBL would cause only limited (< 0.3ha) soft substrate seabed and marine waters loss and potentially affect a section of 450m vertical seawall with low coverage of common soft and hard corals. These habitat loss impacts ranked as insignificant to minor due to the small size and low ecological value of the habitats. And it is anticipated that there will be new seawalls along the waterfront of the future landing point/reclamation, and artificial intertidal and subtidal hard substrate habitat is available for intertidal fauna and coral colonisation after construction.

17.8.3                     Only limited marine water quality impacts are anticipated as only 12 pier sites are needed for the project and no reclamation will be performed. Other impacts are also minor or insignificant. The residual impacts, mainly habitat loss, are considered acceptable. No species ecological monitoring programme is needed. Overall, it was concluded that ecological impact due to CBL would comply with Annex 8 of the TM-EIAO.

17.9                   Fisheries Impact

17.9.1                     There is no fish culture zone or spawning and nursery grounds for fisheries species inside Junk Bay, or inside or close to the CBL alignment.

17.9.2                     The CBL would cause only limited (< 1ha) loss of fishing ground of low to moderate production. These habitat loss impacts ranked as insignificant to minor due to the small size and low ecological value of the habitats.

17.9.3                     Only limited marine water quality impacts are anticipated as only 12 pier sites are needed for the project and no reclamation will be performed. Other impacts are also minor or insignificant.

17.9.4                     The residual impacts, fishing ground loss, are considered acceptable. No specific fisheries monitoring programme is needed.  Overall, it was concluded that CBL would comply fully with Annex 9 of the TM-EIAO.

17.10              Cultural Heritage Impact

17.10.1                  A comprehensive Marine Archaeological Investigation was completed which followed exactly the methodology set out by the HKSAR Antiquities and Monuments Office.  The study did not locate any cultural heritage resources. The diver survey indicated that in many areas the seabed had been disturbed by previous construction work.  Consequently, no further action or mitigation is therefore required.  Overall, the  CBL would comply fully with Annex 10 of the TM-EIAO.

 

 

17.11              Landfill Gas Hazard

17.11.1                  A preliminary qualitative risk assessment for LFG hazards associated with the proposed CBL development has been conducted. The TKOL-II/III is considered as a “Medium” source of gas migration due to occasional high carbon dioxide levels of more than 5% v/v above natural background level detected in the gas monitoring wells though LFG control measures such as in the active gas extraction system installed. The source-pathway-target analysis indicates that the overall risks to the receivers within the 250m Consultation Zone during both construction and operational phases would be categorised as “Low to Medium”.  Appropriate precautionary measures and monitoring were reccomended to minimise the potential risk of LFG migration to the respective targets and requirements of Annex 7 of the TM-EIAO. 

17.12              Landscape and Visual Impact

17.12.1.1              The proposed development and associated works follow in principle the planning intentions from the draft Tseung Kwan O – Outline Zoning Plan (S/TKO/20).  However, the scale of CBL together with concurrent projects, namely, TKO-LTT will inevitably result in some landscape and visual impacts.

17.12.1.2              Based on the tree survey report on CBL, approximately 308 no. of trees will be affected (LR3), of which approximately 58 no. are proposed to be transplanted, and  approximately 250 no. trees are proposed to be felled (including 190 no. Leucaena leucocephala and 60 no. common trees). Due to construction of the CBL, it is unavoidably considered to remove the affected trees. Affected trees with high to medium amenity value and medium survival rate are proposed to be transplanted. Trees surveyed within the proposed works boundary are primarily common species. There are no LCSD Champion Trees, Registered Old and Valuable Trees and Protected Species under Cap 586 Protection of Endangered Species of Animals and Plants Ordinance. It is expected approx. 67 heavy standard sized trees shall be planted as compensatory tree planting. The overall residual impact on vegetation along Wan O Road (LR3) is considered as acceptable with mitigation measures.

17.12.1.3              With the proposed mitigation measures including the compensatory planting and aesthetic treatments, the Junk Bay Coastal Landscape (LCA 1) will still suffer from slight landscape impact during construction and operation due to the artificial engineering structure which is incompatible with the natural Junk Bay character.

17.12.1.4              LCA2 - There will be slight impact on Reclamation / ongoing major development landscape due to the operation of CBL. However, with the proposed mitigation measures including the aesthetic design of the built structures and soft landscape treatment works, it is considered that the residual impact on this LCA is insubstantial.

17.12.1.5              LCA3 – Tseung Kwan O Industrial Urban Landscape will be subject to insubstantial impact as this LCA is relatively far away from the CBL.

17.12.1.6              LCA4 – Chiu Keng Wan Coastal Upland and Hillside Landscape will be subject to insubstantial impact as this LCA is relatively far away from the CBL. However, this LCA will definitely be affected by the interface project: TKO-LT Tunnel.

17.12.1.7              LCA5 – Tseung Kwan O Landfill Landscape (Stage II and III) will be subject to insubstantial impact as this LCA is relatively far away from CBL and will not be affected.

17.12.1.8              LCA6 – Tseung Kwan O Miscellaneous Urban Fringe Landscapewill be subject to insubstantial impact as this LCA is relatively far away from CBL and will not be affected.

17.12.1.9              LCA7 – High Junk Peak Coastal Upland and Hillside Landscape will be subject to insubstantial impact as this LCA is relatively far away from CBL and will not be affected.

17.12.1.10          LCA8 – Residential Urban Fringe Landscape will be subject to insubstantial impact as this LCA is relatively far away from CBL and will not be affected.

17.12.1.11          There is expected to be some minor impact upon the sea waterbody in Junk Bay (LR1).  The sea water body will be permanent lost due to the construction of the piers for CBL bridge. Residual impacts after 10 years of operation are expected to be slight.

17.12.1.12          There is expected to be negligible impact upon the Landscaped Area and Plantation within High-rise residential development in CDA 86 (LOHAS Park) (LR2). It is considered that the residual impact is expected to be insubstantial.

17.12.1.13          There is expected to be negligible impact upon the Plantation within Vacant land (LR4), It is considered that the residual impact is expected to be insubstantial after year 10.

17.12.1.14          There is expected to be negligible impact upon Plantation within Industrial Building (LR5).  Residual impact after Year 10 is expected to be insubstantial.

17.12.1.15          There is expected to be negligible impact upon Woodland at Foothill and Hillside (LR6). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.16          There is expected to be negligible impact upon Grassland and Scrubland at Hillside in Chiu Keng Wan (LR7). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.17          There is expected to be negligible impact upon Vegetation of clustered newly planted trees and shrubs scattered on Tseung Kwan O Stage II and III Landfill Area (LR8). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.18          There is expected to be negligible impact upon Nature Rocky and Sand Shoreline in Chiu Keng Wan (LR9) and Plantation at Wasteland / Construction Area in Chiu Keng Wan (LR10). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.19          There is expected to be negligible impact upon Vegetation along the Coastline Adjacent to Lohas Park Road (LR11). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.20          There is expected to be negligible impact upon Roadside Planting in Lohas Park Road (LR12). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.21          There is expected to be negligible impact upon Seawall  in Tseung Kwan O Industrial Estate (LR13). Residual impact after Year 10 is expected to be insubstantial.

17.12.1.22          Lei Yue Mun and Tathong Channel are a unique public asset and natural visual resources as viewed from Shau Kei Wan, providing an open seascape along the Junk Bay. The proposed CBL, particularly the pier structure will induce partial blockage of views and permanent loss of open seascape view. The cumulative visual impacts can only be slightly mitigated by minimizing area, avoidance of excessive height and bulk of buildings and structures and construction period. Therefore, the VSRs (CDA1) located in close proximity to CBL will still suffer from moderate residual visual impact of the CBL

17.12.1.23          While for the proposed Open Space in Area 74 (O3), and Planned recreational users in TKO Stage I Landfill (REC1), the residual impact would be slight due to screening/amenity planting along the waterfront promenade will be fully established and can soften engineering structure built in Junk Bay.

17.12.1.24         The Planned proposed “Central Avenue” user in Town Centre South near the promenade in open space of TKO Area 68 and the promenade user in the former TKO Stage I Landfill site (O1), the Planned waterfront near the Eastern Channel in open space of TKO Area 68 (O2), and Planned Residential area of TKO Area 65, 66 and 68 (R7) will have direct and close range views to the CBL and TKO-LTT.  The cumulative visual impacts can only be mitigated by using visually unobtrusive building material and refinement of engineering design.  Screening planting/amenity planting in the open space itself is expected to have minor screening effect to these views because CBL are elevated.  Therefore, the VSRs (O1, O2 and R7) will still suffer from moderate residual visual impact of CBL and TKO-LT Tunnel.

17.12.1.25         The proposed Open Space in Area 74 (O3), and Planned recreational users in TKO Stage I Landfill (REC1), the residual impact would be slight due to screening/amenity planting along the waterfront promenade will be fully established and is expected to have screening effect on CBL and TKO-LT Tunnel.  Residents of Ocean Shores (R2) will have direct, close views to the new CBL and TKO-LT Tunnel which is immediately adjacent or very close to the VSRs.  Mitigation in the form of screening planting, refinement of structure and architectural design of road structures will help in reducing these visual impacts.  However, the VSRs will still be subject to the partial blockage of views and permanent loss of open seaview.  Therefore, the VSRs (R2) will still suffer from moderate residual visual impact of CBL and TKO-LT Tunnel.

17.12.1.26          The landscape and visual impact assessment has been conducted according to the criteria and guidelines for evaluating and assessing impacts as stated in Annex 10 and 18 of the TM-EIAO, it is considered that the identified residual impacts, taking account of both importance and degree of compliance, will be acceptable with mitigation measures.

17.13              Environmental Monitoring and Audit Requirement

17.13.1                  It is recommended to implement an Environmental Monitoring and Audit (EM&A) programme throughout the entire construction period to monitor the environmental impacts on the neighbouring sensitive receivers regularly. 

17.13.2                  An EM&A Manual has been prepared as a standalone document to specify the monitoring requirements, timeframe and responsibilities for the implementation of the environmental mitigation measures identified in the EIA process.

17.13.3                  An Environmental Mitigation Implementation Schedule is included in the EM&A Manual to summarises all the measures, the implementation location, timeframe, agency etc.