10
Landscape and Visual Impacts
Background
10.1.1
The following
section is a Landscape and Visual Impact Assessment (LVIA) for the TKO-LT Tunnel
project in accordance with Annex 10 and 18 of the Technical Memorandum on
Environmental Impact Assessment Process, EIAO Guidance Note No. 8/2010 and the
project EIA Study Brief No. ESB-195/2008.
EIA Study
Brief
10.1.2
The TKO-LT Tunnel
project is a designated project under Schedule 2 of the Environmental Impact
Assessment Ordinance (EIAO). An EIA Study Brief No. ESB-195/2008 was issued by
the Director of Environmental Protection on 26th August 2008 to CEDD for an EIA
Study of the TKO-LT Tunnel. A separate but related EIA Study Brief No.
ESB-196/2008 was issued at the same time for the CBL and the LVIA aspects of
both EIAs are to be closely coordinated at the TKO interface.
Content of
this Section
10.1.3
The contents of
the following sub-sections of this section are described below:
·
Section 10.1
provides an introduction, describes the EIA Study Brief and provides a
description of the content of the LVIA forming Section 10 of the EIA.
·
Section 10.2 describes
the environmental legislation, standards and criteria upon which the LVIA is
based;
·
Section 10.3
provides the assessment methodology for the LVIA;
·
Section 10.4 provides
the scope and content of the study, outlines the limit of study area and provides
the project description, review of planning and development control framework, tentative
programme and identifies the concurrent projects;
·
Section 10.5
provides the baseline study which outlines the physical Landscape Resources and
Landscape Character Areas and their sensitivity,
tree survey data, the visual envelope, the Visually Sensitive Receivers and their
sensitivity and magnitude of impact;
·
Section 10.6
provides the landscape impact assessment with a description of the sources of potential
landscape impacts, the predicted magnitude of impact and the resulting
significance of impact on each Landscape Resource and Landscape Character Area;
·
Section 10.7
provides the visual impact assessment with a description of the sources of
potential visual impacts, the predicted magnitude of impact and the resulting
significance of impact on each Visually Sensitive Receiver;
·
Section 10.8 describes
the mitigation measures, the environmental monitoring and audit requirements,
the photomontages and the rationale for selecting the photomontage viewpoints;
·
Section 10.9
provides the evaluation of residual and the cumulative landscape and visual
impacts;
·
Section 10.10
provides a summary and conclusions, outlines the compatibility of TKO-LT Tunnel
with planning intent and summarises the residual landscape and visual impacts;
and
·
Section 10.11
provides the overall conclusion in accordance with the criteria and guidelines
for evaluating and assessing impacts as stated in Annex 10 and 18 of the TM of
the EIAO.
10.2
Environmental
Legislation, Standards and Criteria
10.2.1
The methodology
for undertaking the landscape and visual impact assessment is in accordance
with Annex 10 and 18 of the Technical Memorandum on Environment Impact
Assessment Process, EIAO Guidance Note No. 8/2010 and the EIA Study Brief No.
ESB-195/2008. The following legislation, standards and guidelines are
applicable to the evaluation of landscape and visual impacts associated with
the construction and operation of the proposed TKO-LT Tunnel:
·
Animals and
Plants (Protection of Endangered Species) Ordinance (Cap. 187);
·
Country Parks
Ordinance (Cap. 208);
·
Environmental
Impact Assessment Ordinance (Cap. 499, section 16) and the Technical Memorandum
on EIA Process (EIAO-TM), particularly Annexes 10, 11, 18, 20 and 21;
·
Environmental
Impact Assessment Ordinance Guidance Note (EIAO GN) 8/2010;
·
ETWB TC No.
34/2003 – Community Involvement in Greening Works;
·
ETWB TC No.
29/2004 – Registration of Old & Valuable Trees and Guidelines for their
Preservation;
·
ETWB TC No.
2/2004 – Maintenance of Vegetation and Hard Landscape Features;
·
ETWB TC No.
11/2004 – Cyber Manual for Greening;
·
ETWB TC No.
5/2005 – Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction
Works;
·
ETWB TC No.
10/2005 – Planting on Footbridges and Flyovers;
·
ETWB TC No.
3/2006 – Tree Preservation;
·
Forests and
Countryside Ordinance (Cap. 96) and its subsidiary legislation the Forestry
Regulations;
·
GEO 1/2011 –
Technical Guidelines on Landscape Treatment for Slopes;
·
GEO Publication
(1999) – Use of Vegetation as Surface Protection on Slopes;
·
Hong Kong
Planning Standards and Guidelines (HK PSG);
·
Land
Administration Office Guidance Note (LAO GN) No. 7/2007 – Tree Preservation and
Tree Removal Application for Building Development in Private Projects;
·
Landscape Value
Mapping Study of Hong Kong;
·
Approved Tseung
Kwan O Outline Zoning Plan No. S/TKO/20, Approved Cha Kwo Ling, Yau Tong, Lei
Yue Mun Outline Zoning Plan No. S/K15/19 and current Outline Zoning Plan for
Kai Tak No. S/K22/4; and current Kwun Tong South OZP No. S/K14S/17;
·
Protection of
Endangered Species of Animals and Plants Ordinance (Cap. 586);
·
SILTech
Publication (1991) – Tree Planting and Maintenance in Hong Kong (Standing
Interdepartmental Landscape Technical Group);
·
Town Planning
Ordinance (Cap. 131);
·
DEVB TC(W) no.
3/2012 – Site coverage of Greenery for Government; Building Projects;
·
DEVB publication
(April 2012) – Guidelines on Greening of Noise Enclosure;
·
WBTC No. 7/2002 –
Tree Planting in Public Works;
·
WBTC No. 36/2004
– Advisory Committee on the Appearance of Bridges and Associated Structures
(ACABAS).
Assessment of Landscape Impacts
10.3.1
Landscape
and visual impacts have been assessed separately for the Construction and Operational Phases, following the methodology set out
in EIAO GN 8/2010.
10.3.2
The
assessment of landscape impacts has adopted the following procedures:
·
Identification
of the baseline physical and cultural Landscape Resources (LRs) and Landscape Character
Areas (LCAs) found within the assessment area:. This is achieved by site visits and desk-top study of
topographical maps, information databases and photographs.
·
Assessment of
the degree of sensitivity of the LRs and LCAs: This is influenced by a number of factors including
whether the resource/character is common or rare, whether it is considered to
be of local, regional, national or global importance, whether there are any
statutory or regulatory limitations/ requirements relating to the resource, the
quality of the resource/character, the maturity of the resource, and the
ability of the resource/character to accommodate change. The sensitivity of
each landscape feature and character area is classified as follows:
High |
LR
or LCA of particularly distinctive character or high importance, sensitive to
relatively small changes |
Medium |
LR
or LCA of moderately valued landscape characteristics reasonably tolerant to
change |
Low |
LR
or LCA, the nature of which is largely tolerant to change |
·
Identification
of potential sources of landscape impacts: These are the various elements of the construction
works and operational procedures that will generate landscape impacts.
Landscape impacts may be beneficial/adverse, direct/indirect, short/long-tem,
reversible/irreversible and cumulative. Impacts in this report are adverse
unless specifically stated as positive.
·
Identification
of the magnitude of landscape impacts: The magnitude of the impact depends on a number of
factors including the physical extent of the impact, the landscape and visual
context of the impact, the compatibility of the Project with the surrounding
landscape; and the time-scale of the impact – i.e. whether it is temporary
(short, medium or long term), permanent but potentially reversible, or
permanent and irreversible. Landscape impacts have been quantified wherever
possible. The magnitude of landscape impacts is classified as follows:
Large |
The
LR or LCA would suffer major change |
Intermediate |
The
LR or LCA would suffer moderate change |
Small |
The LR or LCA would suffer slight or
barely perceptible change |
Negligible |
The LR or LCA would suffer no discernible
change |
10.3.3
Identification
of potential landscape mitigation measures: These may take the form of adopting alternative
designs or revisions to the basic engineering and architectural design to
prevent and/or minimise adverse impacts; remedial measures such as colour and
textural treatment of building features; and compensatory measures such as the
implementation of landscape design measures (eg. tree planting, creation of new
open space, etc.) to compensate for unavoidable adverse impacts and to attempt
to generate potentially positive long term impacts. The proposed mitigation
measures for the project and the agencies responsible for the funding, implementation, management and maintenance
of the mitigation measures are identified in Table 10.8.1. and Table 10.8.2.
10.3.4
Prediction of
the significance of landscape impacts before and after the implementation of
the mitigation measures: By synthesising the magnitude of the various impacts and the
sensitivity of the various landscape resources it is possible to categorise
impacts in a logical, well-reasoned and consistent fashion. Table 10.3.1 shows the rationale for
dividing the degree of significance into four thresholds, namely Insubstantial, Slight, Moderate, and Substantial, depending on the
combination of a negligible-small-intermediate-large magnitude of change and a
low-medium-high degree of sensitivity of landscape resource/character. The
significant thresholds are defined as follows:
Substantial |
Adverse/beneficial impact where the
proposal would cause significant deterioration or improvement in existing
landscape quality |
Moderate |
Adverse/beneficial impact where the
proposal would cause a noticeable deterioration or improvement in existing
landscape quality |
Slight |
Adverse/beneficial impact where the
proposal would cause a barely perceptible deterioration or improvement in
existing landscape quality |
Insubstantial |
No discernible change in the existing
landscape quality |
10.3.5
Prediction of
Acceptability of Impacts: An overall assessment of the significance of the
impacts according to the five criteria set out in Annex 10 of the EIAO-TM is
summarized in Table 10.3.1 below:
Table
10.3.1 Evaluation of Significance of Landscape and Visual Impacts
Magnitude
of Impact (Change) |
Large |
Moderate |
Moderate/ Substantial |
Substantial |
Intermediate |
Slight/ Moderate |
Moderate |
Moderate/ Substantial |
|
Small |
Slight |
Slight/ Moderate |
Moderate |
|
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
|
Sensitivity
to change (of Landscape Resource, Landscape Character Area or VSR) |
10.3.6
Conclusion: from an analysis of the significance thresholds
derived for landscape (and visual) impacts, an overall conclusion in terms of
impact significance for the project is determined in accordance with the five
evaluation criteria set out in Annex 10 of the EIAO-TM:
Beneficial |
The project impact is beneficial if it
will complement the landscape and visual character of its setting, will
follow the relevant planning objectives and will improve overall visual amenity. |
Acceptable |
The project impact is acceptable if the
assessment indicates that there will be no significant effects on the
landscape, no significant visual effects caused by the appearance of the
project, or no interference with key views. |
Acceptable with Mitigation Measures |
The project impact is acceptable with
mitigation measures if there will be some adverse effects, but these can be
eliminated, reduced or offset to a large extent by specific measures. |
Unacceptable |
The project impact is unacceptable if the
adverse effects are considered too excessive and are unable to be practically
mitigated. |
Undetermined |
The project impact is undetermined if
significant adverse effects are likely, but the extent to which they may
occur or may be mitigated cannot be determined from the study. Further
detailed study will be required of the specific effects in question. |
Assessment of
Visual Impacts
10.3.7
The assessment of
visual impacts has adopted the following procedures:
·
Identification
of the Zone of Visual Influence (ZVI) during the Construction and Operational Phases
of the Project: This is
achieved by site visit and desk-top study of topographic maps and photographs,
and preparation of cross-sections to determine visibility of the Project from
various locations. The ZVI is the
view shed from which the project can be seen and is defined by natural landform
and man-made building structures.
·
Identification of
the Visually Sensitive Receivers (VSRs)
within the ZVI during the Construction and Operational Phases: These are the
people who would reside within, work within, play within, or travel through,
the ZVI.
·
Assessment of
the degree of sensitivity to change of the VSRs: This is influenced by the type of VSRs, which is
classified according to whether the person is at home, at work, at play, or
travelling. Those who view the impact from their homes are considered to be
highly sensitive as the attractiveness or otherwise of the outlook from their
home will have a substantial effect on their perception of the quality and
acceptability of their home environment and their general quality of life.
Those who view the impact from their workplace are considered to be of low
sensitivity as the attractiveness or otherwise of the outlook will have a less
important, although still material, effect on their perception of their quality
of life. The degree to which this applies may vary depending on whether the
workplace is industrial, retail or commercial. Those who view the impact whilst
taking part in an outdoor leisure activity may display varying sensitivity
depending on the type of leisure activity. Those who view the impact whilst
travelling on a public thoroughfare will also display varying sensitivity
depending on the speed of travel. The degree to which this applies is also
influenced by the value and quality of existing views; the availability and
amenity of alternative views; the duration or frequency of view, the degree of
visibility and the numbers of receivers. The sensitivity of each VSR is
classified as follows:
High |
The VSR is highly sensitive to any change
in their viewing experience |
Medium |
The VSR is moderately sensitive to any
change in their viewing experience |
Low |
The VSR is only slightly sensitive to any
change in their viewing experience |
·
Assessment of
the potential magnitude of visual impacts: This includes consideration of the compatibility with
the visual character of the surrounding landscape under the Construction and Operation
Phase; the duration of the impact; scale of the development in the view; the
reversibility of the impact; the distance of the source of impact from the
viewer; and the change / blockage to the character of existing views. (Note:
for the purposes of this assessment, those VSRs within a VSR group with the
greater or worst case magnitude of change are selected for assessment. For
example, the VSRs on the upper floors of a tower block may experience a greater
magnitude of change than those on the lower floors which may have their views
obstructed by existing ground level features. In this case therefore, the
magnitude of impact for the VSRs on the upper floors is assessed as it is the
greater, rather than the VSRs on the lower floors).
·
The magnitude of
visual impacts are classified as follows:
Large |
The VSRs would suffer a major change in
their viewing experience |
Intermediate |
The VSRs would suffer a moderate change
in their viewing experience |
Small |
The VSRs would suffer a small change in
their viewing experience |
Negligible |
The VSRs would suffer no discernible
change in the character of their viewing experience |
10.3.8
Identification
of potential sources of visual impacts: These are the various elements of the construction
works and operational procedures that would generate visual impacts.
10.3.9
Identification
of potential visual mitigation measures: These may take the form of adopting alternative
designs or revisions to the basic engineering and architectural design to
prevent and/or minimise adverse impacts; remedial measures such as colour and
textural treatment of building features; and compensatory measures such as the
implementation of landscape design measures (e.g. tree planting, creation of
new open space etc) to compensate for unavoidable adverse impacts and to
attempt to generate potentially positive long term impacts. The agencies
responsible for the funding, implementation, management and maintenance of the
mitigation measures are identified and their approval-in-principle is being
sought. Tables 10.8.1 and 10.8.2
identify these mitigation measures during the Construction and Operation Phases respectively.
10.3.10 Prediction of the significance of visual impacts
before and after the implementation of the mitigation measures: By synthesising the magnitude of the various visual
impacts, the sensitivity of the VSRs and the numbers of VSRs that are affected,
it is possible to categorise the degree of significance of the impacts in a
logical, well-reasoned and consistent fashion. Table 10.3.1 shows the rationale for dividing the degree of
significance into four thresholds, namely, Insubstantial, Slight, Moderate and Substantial,
depending on the combination of a negligible-small-intermediate-large magnitude
of change and a low-medium-high degree of sensitivity of VSRs. Photomontages
showing views of the Project from key VSRs at day 1 without mitigation, and at
day 1 and year 10 with mitigation are provided. The significance of the visual
impacts is categorised as follows:
Substantial |
Adverse/beneficial impact where the
proposal would cause significant deterioration or improvement in existing
landscape visual character |
Moderate |
Adverse/beneficial impact where the
proposal would cause a noticeable deterioration or improvement in existing
landscape visual character |
Slight |
Adverse/positive impact where the proposal
would cause a barely perceptible deterioration or improvement in existing
landscape visual character |
Insubstantial |
No discernible change in the existing
landscape visual character |
10.4
Scope
and Content of the Study
10.4.1
The study area
for the landscape impact assessment is an area 500 meters from the work limit
of the project and is indicated on Figure
No. 10.4.1.
10.4.2
The area for the
visual impact assessment is defined by the limits of the visual envelope (or
ZVI) which forms the view shed for the visibility of the project. The ZVI is
indicated on Figure No. 10.4.1.
10.4.3
At present, the
existing TKO Tunnel is the main connection between TKO and the urban areas of
Kowloon and Hong Kong. According to traffic impact assessments, the existing
tunnel will experience serious congestion if an alternative external road link
is not provided to meet the population growth and the continuing commercial and
industrial development in the TKO area. To cope with the anticipated transport
need, the TKO-LT Tunnel and Cross Bay Link (CBL) are proposed to meet the
long-term traffic demand between TKO and the external areas.
10.4.4
TKO-LT Tunnel,
together with the proposed Trunk Road T2 (T2) in the Kai Tak Development (KTD)
and Central Kowloon Route (CKR), will form Route 6 in the strategic trunk road
network. Route 6 will provide an east-west highway link between Kowloon and
TKO. Upon completion, this trunk road will also provide the necessary relief to
the existing heavily trafficked road network in the central and eastern Kowloon
areas, and reduce the related environmental impacts on these areas.
10.4.5
TKO-LT Tunnel
comprises a dual two-lane highway approximately 4.2 km long, about 2.6 km of
which is in the form of tunnel. At either end of the tunnel are portal
facilities and road interchanges linking into existing and future road systems.
10.4.6
The project
elements of relevance to the landscape and visual impact assessment on the TKO
side include the following:
·
TKO interface
with the CBL and the TKO Interchange comprising dual two-lane highway linking
to tunnel and slip roads to Road P2;
·
The TKO tunnel
portal with weight bridge and roadside kiosk with lay-by (the tunnel portal has
major slope works);
·
Temporary haul
road and barging point for removal of excavated slope and tunnel debris at the
base of the tunnel portal;
·
Reclamation for
the slip roads landing point;
·
Slip roads
landing and transition into a depressed roadway beneath a landscape deck in
front of Ocean Shores;
·
Road works along
Road P2 including a landscape deck in front of Ocean Shores;
·
Feature
footbridge connections at the junction of Road P2 and D4 (Po Yap Road).
10.4.7
The preferred
engineering alignment has been selected and endorsed by the Project Steering
Group following a process of option development and review. A review of the
Conforming Scheme of TKO-LT Tunnel and development of alternative alignments has been
conducted. The conforming scheme and the 3 major alternative tunnel alignments
of the TKO Section are shown in Figure 10.1.
After evaluation of the pros and cons including the respective landscape and
visual aspects, of the conforming scheme and the alternative alignments and
taking into account the comments received from the public engagement of the
project, Alternative Alignment 3 (straight tunnel without toll plaza) has been
endorsed by the Project Steering Group (PSG) as the Recommended Scheme for
TKO-LT Tunnel.
10.4.8
The project
elements of relevance to the landscape and visual impact assessment on the Lam
Tin side include the following:
·
The Lam Tin Tunnel
Portal and associated ventilation building in the north east and western walls
of the Ex-Cha Kwo Ling Kaolin Mine Site;
·
The Lam Tin
Interchange comprising the main highway and slip roads in the Ex-Cha Kwo Ling
Kaolin Mine Site; full noise enclosure for the main highway and partial noise
enclosures for the slip roads;
·
Associated
buildings for the TKO-LT Tunnel including an Administration Building, a vehicle
garage, a pumping station and maintenance facilities including a workshop,
training ground, vehicle recovery base and petrol station;
·
Associated
facilities for Trunk Road T2;
·
Road improvements
at the junction of Cha Kwo Ling Road and Yau Tong Road;
·
Road improvements
along Cha Kwo Ling Road including the proposed Cha Kwo Ling Roundabout;
·
Reprovisioning of
the slip road from Lei Yue Mun Road onto the west bound carriageway of the EHC
and the addition of Link Road EHC2;
·
Temporary
waterfront barging point and elevated conveyor for removal of excavated tunnel
and site formation debris.
Review of Planning and
Development Control Framework
10.4.9
A review has been
undertaken of the current planning goals and objectives, statutory land-use and
landscape planning designations for the assessment area.
10.4.10 The relevant OZP for the project works within TKO is
the Tseung Kwan O Outline Zoning Plan No. S/TKO/20, an extract of which is
shown in Figure No. 10.4.2. The land
uses under this Plan directly affected by the Project Site footprint are zoned
as Open Space (O), Open Space 1 (O(1)), Other Specified Uses (OU), Government/
Institution/ Community 1 G/IC(1), G/IC(4), Commercial/ Residential (C/R) and
Green Belt (GB) and areas designated as
“Road” and are summarised in Table 10.4.1.
Table 10.4.1
Tseung
Kwan O Outline Zoning Plan No. S/TKO/20 Zones
Land Uses affected by the Project |
|||
Land Use Zoning |
Area Affected |
Sources of Impact/ Design
Intent |
Future Outlook |
C/R |
East
of junction of Po Yap Road and Po Shun
Road |
Road,
footbridge and footpath works |
Road,
footbridge and footpath adjacent to mixed commercial residential development |
O |
Open
Space zoned for future Tiu Keng Leng Park |
Depressed
Road P2 |
Landscaped
Deck |
O(1) |
Open
Space to west of junction of Po Yap
Road and Po Shun Road |
Road,
footpath, footbridge and cycleway |
Road,
footpath, footbridge and cycleway adjacent to Sports Centre & Library |
OU |
Tseung
Kwan O/Junk Bay sea area |
TKO
interchange plus connection to Road P2 |
TKO
interchange plus connection to Road P2 |
G/IC(1) |
Reclamation
area zoned as Civic Node |
Road,
footpath, footbridge and cycleway |
Road,
footpath and cycleway adjacent to planned cultural complex, Government
Offices and parking |
G/IC(4) |
Reclamation
area zoned as Civic Node |
Road,
footpath, footbridge and cycleway |
Road,
footpath and cycleway adjacent to planned clinic, police station, fire
station cum ambulance depot & RCP |
GB |
Slopes
and coastal strip of Tiu Keng Leng |
Tunnel
Portal |
Tunnel
Portal |
Road
P2 |
Po
Yap Road to TKO Interchange |
Construction
of Road P2 and footbridge crossings |
Road
P2 integrated into adjacent Open Space, GIC and Residential developments with
signature Civic Node at junction of Po Yap Road |
10.4.11 TKO is a third generation New Town with a unique
waterfront and valley setting. A 2005 Study formulated an urban design
framework to concentrate new development in the Town Centre South and Tiu Keng
Leng areas on newly reclaimed land in the south and west and Pak Shing Kok in
the north east. The planning vision is to create “a new and distinctive
waterfront district that capitalizes on the dramatic visual and physical
relationship of the surrounding country parks and Junk Bay” with the primary
objective of providing “a high quality vibrant leisure and recreational area
for the enjoyment of the TKO residents and visitors”.
10.4.12 The OZP recognises the future CBL and TKO-LT Tunnel
development and has indicated the corridor indicatively on plan (a ‘cross-bay
bridge road’ was indicated on the first Outline Zoning Plan for Tseung Kwan O
in 1992. For details of the planning history refer to Section 2.7.7 – 2.7.27 of the EIA Report). The
TKO Interchange and Road P2 will affect an area zoned as OU and O in the south
east corner of the TKO extension. Tiu Keng Leng Park is a planned open space
over the depressed Road P2 in front of Ocean Shores and the park will extend
onto the reclamation formed for the Road P2 landing. The TKO interchange will
occupy an area of coast and Junk Bay zoned as OU and indicated on the OZP as
allocated for “Toll Plaza, Ventilation Building and Associated Facilities”.
Road P2 extends north to the junction of Po Yap Road where a new Civic Node will
be developed with surrounding Open Space, G/IC and Residential development.
10.4.13 Following a series of public consultation/engagement
activities from April 2009 to April 2012 (see Table 2.5 of the EIA Report), the comments and recommendations from
the public on the Project including alignment selection, form of
construction, land intake, environmental impact, traffic impact and
engineering issues, as well as preservation of local culture and heritage,
land-use planning and social impact were collected and considered for formulation of the
recommended scheme. It is considered that the TKO-LT Tunnel is compatible
with the current planning context in TKO and the transitional nature of the
area requires that the visual impact analysis should take account of significant
planned visually sensitive land-uses and receivers.
10.4.14 The relevant OZPs for the project works within the Kowloon
side of the project are the Cha Kwo Ling, Yau Tong and Lei Yue Mun Outline
Zoning Plan No S/K15/19, Kwun Tong South OZP No. S/K14S/17 and the Kai Tak OZP
S/K22/4, extracts of which are shown in Figure
No. 10.4.3. The land uses under these Plans affected by the Project Site
footprint are zoned as G/IC, O, OU and GB and are summarised in Table 10.4.2.
Table 10.4.2
Cha
Kwo Ling, Yau Tong and Lei Yue Mun Outline Zoning Plan No S/K15/19 Zoned
Land Uses affected by the Project |
|||
Land Use Zoning |
Area Affected |
Sources of Impact/ Design Intent |
Future Outlook |
G/IC |
Cha Kwo Ling Road and FEHD Vehicle
Depot within old quarry |
Road improvements and Lam Tin
Interchange |
Public road and Lam Tin Interchange
comprising elevated slip roads within quarry footprint |
R(A)4 |
West of former Cha Kwo Ling Kaolin
Mine Site |
Cha Kwo Ling Road improvements |
High density residential with GIC
facilities and Open Space provision |
R(A)5 |
East of former Cha Kwo Ling Kaolin
Mine Site & EHC |
Road improvements |
|
O |
Abandoned Kaolin Mine Site east of Cha
Kwo Ling (reserved for District Open Space) |
Lam Tin Interchange |
Public road and Lam Tin Interchange
comprising elevated slip roads within quarry footprint |
OU |
Cross Harbour Tunnel Toll Plaza |
Integration of Lam Tin Interchange
with EHC and Cha Kwo Ling Road |
Additional slip road connections |
GB |
Green belt surrounding ex Cha Kwo Ling
Kaolin Mine Site and Sai Tso Wan Recreation Ground |
Slope works and slip roads of Lam Tin
Interchange |
Slope works and slip roads of Lam Tin
Interchange |
10.4.15 The planning intent of the Lam Tin area is to
redevelop Yau Tong to the east with new residential and commercial development,
particularly within the Yau Tong Bay CDA. The Cha Kwo Ling village area facing
the waterfront and the area behind is zoned as R(A)4 residential development
and G/IC and the waterfront will be upgraded to provide public access and link
into the Kai Tak Development to the
north. The TKO-LT Tunnel therefore is compatible with the future development vision
for the area in that it will enhance transport connections for the growing
urban population in the adjacent development areas.
10.4.16 The project works footprint will fall primarily within
the G/IC zoned land, and the existing FEHD Vehicle Depot and Seized Goods Compound,
LCSD Nursery Site and the
proposed LCSD Sports Complex/Indoor Recreation Centre cum District Open Space
would be affected. Areas zoned as Open Space to the south and north east may be
affected. Works related to public utilities are permitted within areas zoned as
Open Space. The area of Open Space and Green Belt to the north of the quarry
area would also be only temporarily impacted and the long term intent of
providing a District Open Space would not be affected.
Hong Kong
Island Side (north-eastern part)
10.4.17 A desk-top study has been undertaken of the current
planning context of the waterfront portion along the northeast part of Hong
Kong Island. With reference to the draft Chai Wan Outline Zoning
Plan No. S/H20/20, it is noted that the current waterfront of Chai Wan and Siu
Sai Wan are currently occupied by private residential developments, namely Heng
Fa Chuen, Island Resort, Tai Koo Shing,
Tung To Court, Tung Yuk Court and Aldrich Bay at Shau Kei Wan, Lei King
Wan Grand Promenade and Les Saisons, all of which represent potential VSR
groups for the TKO-LT Tunnel. There is no known planned new development or redevelopment along the
waterfront portion within the study area that would result in any new VSR groups.
10.4.18 The TKO-LT Tunnel is to be implemented in parallel
with the CBL. The works is tentatively scheduled to commence in February 2016 and
be completed by November 2020. The project is anticipated to be commissioned in
2021.
10.4.19 Concurrent projects have been identified below and are indicated on Figure No. 10.4.4.
TKO Side
·
Cross Bay Link
(CBL);
·
TKO Town Centre
South Development in Areas 65 and 66;
·
Cycle tracks and
promenade developments around TKO Bay in Area 68;
·
TKO Area 86
Development;
·
Hong Kong
Offshore Wind Farm in South Eastern Waters;
·
Residential
Developments in Area 85;
·
G/IC developments
in Area 78;
·
Planned
recreational facilities at TKO Stage I Landfill, Area 77
Kowloon Side
·
Trunk Road T2
·
Kai Tak Development
·
Yau Tong Bay CDA
development
·
Residential
Development at ex-Cha Kwo Ling Kaolin
Mine Site R(A) 4 zone
Description of Concurrent Projects - TKO Side
10.4.20 Cross Bay Link (CBL): the CBL is a designated project under the EIAO
Ordinance and the EIA Study Brief No.ESB-195/2008 was issued by the Director of
Environmental Protection on 26th August 2008 to CEDD for an EIA study. The CBL
is a dual two-lane elevated carriageway of approximately 1.8km long, primarily
on viaduct, running east-west across Junk Bay and connecting TKO–LT Tunnel to the Area 86 developments and Wan Po Road in south
eastern TKO. There is a direct interface with the TKO-LT Tunnel in the west and the two projects will be implemented
in parallel. The landscape and visual impacts of the CBL are assessed under a
separate but related report under Agreement No. CE 43/2008 (HY).
10.4.21 TKO Town Centre South Development in Areas 65 and 66: this area is currently under construction. The area
will be primarily residential and will generate VSRs in large numbers. It is
anticipated phases of the development will be in operation between 2017 and
2018.
10.4.22 TKO Area 86 Comprehensive Development: the first phases of residential development have
already been constructed at Area 86 and additional residential and educational
developments are planned above the MTRCL depot. All these developments will
generate potential VSRs and the TKO-LT Tunnel landing point, slip roads and tunnel portal will all
be potentially visible. The comprehensive development is due for completion on
or before 2019.
10.4.23 Cycle Tracks and Promenade Developments around TKO Bay
in Area 68: a promenade
and cycle tracks are proposed as part of the TKO Comprehensive Development.
These will provide prime viewpoints for walkers and cyclists across Junk Bay
from the edge of the reclamation (Area 68) across a proposed southern
footbridge over Eastern Channel and around the edge of Area 77 which is a
planned recreational facility proposed to be completed by Year 10 of the TKO-LT
Tunnel. A footpath connecting Area 68 with the Junk Bay Chinese Permanent
Cemetery will interface directly with the TKO-LT Tunnel at the tunnel portal
area and at the landscaped deck in front of Ocean Shores. Walkers on this
footpath will have direct views of the TKO tunnel portal and the TKO
interchange and associated reclamation area. The Cycle Tracks and Promenade
Developments are anticipated to be in operation on or before 2018.
10.4.24 Hong Kong Offshore Windfarm in Southeastern Waters: with reference to the Project Profile and EIA Study
Brief (ESB – 146/2006) the project is to construct and operate a wind farm in
the south eastern waters of Hong Kong. There is a proposed transmission cable
landing point south of Ocean Shores which will connect cables from the offshore
turbines to the CLP electricity grid. As the proposed works are minor and will
consist of only a small underground cable connection pit these works are not
considered further in this LVIA assessment.
10.4.25 Residential Areas in Area 85: two sites
comprising 4ha are zoned for Group (E) Residential development. The planning
intent is to phase out existing industrial uses in the area and develop it into
a residential extension of the Area 86 CDA. Building heights up to 130m will be
permitted. The construction of this residential development will likely be
completed in 2013.
10.4.26 G/IC developments in Area 78: Sites at Pak Shing Kok have been reserved for a Fire
Services Training School cum Driving Training School, a private hospital and
other as yet undetermined G/IC uses. The site is largely screened by a large
ridge to the west and building heights have been controlled so as not to exceed
this. The G/IC developments are proposed to begin operation in 2017.
10.4.27 Planned Recreational Facilities at TKO Stage 1 Landfill Area 77: the total area of this site is 65.85ha and has been
reserved for active and/or passive recreation and tourism/eco-tourism developments for the use of the general public and is anticipated to be completed by Year 10 of the TKO-LT Tunnel.
Description of
Concurrent Projects - Kowloon Side
10.4.28 Trunk Road T2 (T2): T2 is a dual two-lane trunk road of about 3.6km
long, 2.6km of which will be in tunnel.
T2 will connect the CKR with the TKO-LT Tunnel and together they will form
Route 6 in the strategic trunk road network. T2 and TKO-LT Tunnel will
interface at the Lam Tin Interchange near Cha Kwo Ling Village and Laguna City.
10.4.29 Kai Tak Development: the development of the former airport site at Kai Tak
affects an area of approximately 460ha and includes proposals for a variety of
housing types, a tourism node, a Cruise Terminal, a multi-purpose stadium and a
Metropolitan Park. The area is intended to house a population of some 260,000.
Whilst the development is related to the Route 6 works there will be no direct
interface with the TKO-LT Tunnel. VSRs in the new Kai Tak developments will not
be aware of the Lam Tin Interchange due to the screening landform north of Cha
Kwo Ling Village.
10.4.30 Yau Tong Bay CDA Development: the CDA zone in Yau Tong Bay is proposed to be
comprehensively redeveloped for residential, commercial and community uses. A
planning application has been submitted by a developer for waterfront housing
with public promenade and open space. Should this be approved, the construction
would be concurrent with the TKO-LT Tunnel. The development will create new
residential VSRs along Cha Kwo Ling Road but screen out existing VSRs to the
south east.
10.4.31 The Ex- Cha Kwo Ling Kaolin Mine Site: the site is proposed to be developed for residential use, G/IC facilities and public open space. A planning study is being
conducted but no planning application has been submitted for the proposed
development to date. If a planning application is submitted and approved, it is likely that the development
would be completed during the construction of the TKO-LT Tunnel between 2016
and 2019. The new development would create additional VSRs overlooking the Lam
Tin Interchange.
Physical Landscape Resources and Landscape Character
Areas
10.5.1
The study area on
the TKO side lies within the existing urban area of Po Yap Road and on the flat
reclaimed land of the TKO extension in the north, on the western hill slopes of
the Tiu Keng Leng hills to the south west and the seawater body of Junk Bay to
the south east. Landscape resources
include amenity tree planting in the urban areas, amenity tree planting on
roadsides and modified slopes, self -seeded vegetation on the reclamation, grassland/shrubland
vegetation on the coastal hill slopes, ponds and streams, the natural rocky and
sandy shoreline and the open water expanse of west Junk Bay.
10.5.2
The baseline
Landscape Resources for TKO that will be affected during the Construction and
Operation Phases and their sensitivity are described below in Table 10.5.1. An overall view of
Baseline Landscape Resources - TKO and Lam Tin
is illustrated on Figure 10.5.1.1. The locations of the TKO Baseline Landscape
Resources are illustrated at a larger scale on Figures 10.5.1.1a - 1b. Photographic Views illustrating the Landscape
Resources are provided on Figure 10.5.1.2.
Table
10.5.1 – Tseung Kwan O Landscape Resources and their Sensitivity
ID
No. |
TKO
Landscape Resource |
Sensitivity |
TKO-LR1 |
Junk
Bay (Tseung Kwan O) Sea Waterbody The sea waterbody comprises part of Junk
Bay and is a valuable landscape resource contributing to the unique
waterfront setting of TKO. The approximate area within the study boundary is
114 ha. The sensitivity is assessed as High given
the channel’s physical characteristics and the statutory presumption against
reclamation. |
High |
TKO-LR2 |
Natural
Rocky Shore along Chiu Keng Wan Coastline This rocky shore forms part of the last
stretch of natural coastline in Junk Bay (apart from Fat Tong Chau on the
eastern side) and measures approximately 1102m. The sensitivity of the natural coastline
is High due to its relative rarity within the locality (due to the high
proportion of reclamation coast within Junk Bay), its distinctive character
and low tolerance of change (it cannot be replaced). |
High |
TKO-LR3A |
Amenity/
Roadside Planting/ Vegetation on modified
slopes at Chiu Keng Wan Shan The vegetation on the natural hillsides
of Chiu Keng Wan Shan consists of planting on engineered slopes. In general,
the vegetation is dominated by exotic tree species typically planted throughout
Hong Kong including Acacia confusa, Acacia auriculiformis,
Eucalyptus spp., Casuarina equisetifolia and with occasional native
tree species such as Celtis sinensis, Macaranga
tanarius and Schefflera heptaphylla. Representative shrubs recorded
include Rhodomyrtus tomentosa, Lantana
camara and Rhaphiolepis indica and
grasses recorded include Hedyotis
acutangula and Neyraudia reynaudiana. No plant species of conservation
interest were recorded within these areas. The sensitivity of the vegetation is
assessed as Medium as it is generally semi-mature secondary woodland or
roadside planting and a relatively common local resource that can easily be
reinstated and is therefore reasonably tolerant of change. |
Medium |
TKO- LR3B |
Vegetation on modified slopes at Tiu Keng Leng The vegetation on the natural hillsides
of Tiu Keng Leng and Mau Wu Shan consists of planting on engineered slopes.
In general, the vegetation is dominated by exotic tree species typically
planted throughout Hong Kong including
Acacia confusa, Acacia auriculiformis,
Eucalyptus spp., Casuarina equisetifolia and with occasional native
tree species such as Celtis sinensis,
Macaranga tanarius and Schefflera
heptaphylla. Representative shrubs recorded include Rhodomyrtus tomentosa, Lantana camara and Rhaphiolepis indica and grasses recorded include Hedyotis acutangula and Neyraudia
reynaudiana. No plant species of conservation interest were recorded
within these areas. The sensitivity of the vegetation is
assessed as Medium as it is generally semi-mature secondary woodland or
roadside planting and a relatively common local resource that can easily be
reinstated and is therefore reasonably tolerant of change. |
Medium |
TKO- LR3C |
Amenity/
Roadside Planting on modified slopes
at Junk Bay Chinese Permanent Cemetery The amenity planting/ vegetation on the
natural hillsides southeast of Chiu Keng Wan Shan and at Junk Bay Chinese
Permanent Cemetery consists of planting on engineered slopes. In general, the
composition is dominated by exotic tree species typically planted throughout
Hong Kong including Acacia confusa, Acacia auricuioformis,
Eucalyptus spp., Casuarina equisetifolia and with occasional native
tree species such as Celtis sinensis,
Macaranga tanarius and Schefflera
heptaphylla. No plant species of conservation interest were recorded
within these areas. The sensitivity of the vegetation is
assessed as Medium as it is generally semi-mature secondary woodland or
roadside planting and a relatively common local resource that can easily be
reinstated and is therefore reasonably tolerant of change. |
Medium |
TKO- LR3D
|
Amenity
/Roadside Planting on modified slopes along Road D4 (Po Yap Road and Chui
Ling Road) and P2 (Po Shun Road) The Amenity / Roadside planting on
modified slopes and at grade along Po Yap Road and the northern edge of the
TKO reclamation consists of common roadside tree species including Bauhinia blakeana and Hibiscus tiliaceus. Representative shrubs recorded
include Rhodomyrtus tomentosa, Lantana
camara and Rhaphiolepis indica and
grasses recorded include Hedyotis
acutangla and Neyraudia reynaudiana. The sensitivity of the vegetation is
assessed as Medium as it is generally semi-mature roadside planting and a
relatively common local resource that can easily be reinstated and is
therefore reasonably tolerant of change. |
Medium |
TKO-LR4 |
Mixed
Woodland Vegetation on hillside areas at Chiu Keng Wan Shan The mixed woodland habitat covers an area
of 2.8ha south of the residential blocks of Ocean Shores. This resource is
dominated by common and widespread native pioneer tree species (Macaranga tanarius, Mallotus paniculatus,
Sapium discolour, Ficus hispida and Schefflera
heptaphylla). Other common species include trees (Celtis sinensis and
Araucaria heterophylla), various fruit tree species, climbers (Dalbergia benthamii) and shrubs (Manihot esculenta and Phyllanthus cochinchinensis). No rare
flora or species of conservation interest were recorded during recent
surveys. The sensitivity of the Cemetery tree
planting is Medium as it comprises common species that can easily be
reinstated and is therefore reasonably able to accommodate change. |
Medium |
TKO-LR5A |
Grassland/Shrubland
Mosaic at Chiu Keng Wan Shan Grassland/Shrubland Mosaic
covers an approximate area of 63ha. This resource covers most of Chiu Keng
Wan Shan and the back-shore slope along the coast of Chiu Keng Wan.
Representative vegetation recorded includes young pioneer trees (Macaranga
tanarius, Litsea glutinosa and Bridelia
tomentosa), shrubs (Rhodomyrtus
tomentosa, Lantana camara and Rhaphiolepis
indica) and grasses (Hedyotis
acutangula and Neyraudia reynaudiana). This resource is assessed as having
Medium sensitivity given its common species composition and secondary nature,
and the large expanses of similar vegetation stretching to the north and
east. It could be reinstated if impacted and is therefore reasonable able to
accommodate change. |
Medium |
TKO-LR5B |
Grassland/
shrubland mosaic at Tiu Keng Leng Grassland/ shrubland mosaic
covers an approximate area of 29ha. This resource covers the upper slopes of
Tiu Keng Leng. Representative
vegetation recorded within grassland/ shrubland mosaic habitat includes young
pioneer trees (Macaranga tanarius, Litsea glutinosa and Bridelia
tomentose), shrubs (Rhodomyrtus
tomentosa, Lantana camara and Rhaphiolepis
indica) and grasses (Hedyotis
acutangula and Neyraudia reynaudiana). This resource is assessed as having
Medium sensitivity given its common species composition and secondary nature.
It could be reinstated if impacted and is therefore reasonable able to
accommodate change. |
Medium |
TKO-LR6A |
Ponds
at Junk Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan Several concrete water
retention ponds were recorded within the TKO Chinese Permanent Cemetery.
These ponds serve as a flood prevention measure to store the surface runoff
from the Cemetery. They are surrounded by plantation habitat. They have a
total area of approximately 0.24ha. Given their artificial character this
resource is assessed as having a Medium sensitivity. |
Medium |
TKO-LR6B |
Streams
at Junk Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan Three natural streams (identified
on plan as Streams 2, 3 and 4) with a total length of approximately 750m run
down the western coast of Chiu Keng Wan. These rocky streams are intermittent
in nature depending on season and discharge into Junk Bay. Given their natural character, that they
are few in number within the study area and the fact that they cannot be
easily recreated, these resources are assessed as having a High sensitivity. |
High |
TKO-LR7 |
Village
Trees within Chiu Keng Wan Shan This resource is located at the slope
below the TKO Chinese Permanent Cemetery and covers an area of 2ha. It
comprises scattered orchard planting within village housing areas. The
species include Dimocarpus longan, Antirhea chinensis and Schefflera
heptaphylla. This resource is assessed as having a High
sensitivity as the trees contribute to local amenity (although none are rare, endangered species
or registered OVTs and they could be reinstated should they be impacted). |
High |
TKO-LR8 |
Sandy
Shore along Chiu Keng Wan Shan Coastline On the western coast of Junk Bay, natural
sandy shore occurs in 3 small bays within the study area and these have a
combined length of approximately 437 m. The sensitivity of the natural sandy
shore is High due to its relative rarity within the locality (due to the high
proportion of reclamation coast within Junk Bay), its distinctive character
and low tolerance of change (it cannot be easily replaced). |
High |
TKO-LR9 |
Self-seeded
Vegetation on TKO Reclamation This includes self-seeded trees, shrubs
and grasses on the new reclamation area forming the southern extension of
TKO. Most are common native species and are in poor condition having received
no formal maintenance. Dominant tree species include Acacia spp., Albizia spp., Bauhinia blakeana, Cassia siamea,
Eucalyptus spp., Hibiscus tiliaceus, Leucaena leucocephala. The
reclamation occupies an area of approximately 9.7ha of which the vegetation
only covers limited areas which are subject to change due to on-going
building works. The sensitivity of this vegetation is
considered as Low as it is predominantly incidental, of common species and of
low quality. |
Low |
10.5.3
The baseline
Landscape Character Areas for TKO that will be affected during the Construction
and Operation Phases and their sensitivity are described below in Table 10.5.2. The locations of the
Baseline Landscape Character Areas for TKO are illustrated on Figure No. 10.5.2.1. Photographic Views
illustrating the Landscape Character Areas are provided on Figure No 10.5.2.2.
Table 10.5.2 – Tseung Kwan O Landscape
Character Areas and their Sensitivity
ID
No. |
TKO
Landscape Character Area |
Sensitivity |
TKO-LCA1 |
Junk
Bay Inshore Water Landscape This includes the open water of Junk Bay
and its interface with the natural and reclaimed coastline. Junk Bay provides
a dramatic contrast to the surrounding ridges and hills and creates the
unique waterside setting for TKO. The western portion is delimited by natural
coastline and the northern edge by reclamation which offers the potential for
an enhanced waterfront environment and access. Junk Bay is not only of value
to TKO but also to viewers from the south on Hong Kong Island, seaborne
viewers and viewers on elevated ground to the west, north and east. Given the role this LCA plays in setting
the bay side context of TKO, and the fact that its characteristic is flat and
open, the sensitivity is assessed as High. |
High |
TKO-LCA2 |
Junk
Bay Chinese Permanent Cemetery Landscape This is a highly distinctive landscape
character area comprising a concrete terraced hillside housing graves and
shrines and a central columbarium. There are some groups of mature trees
around the columbarium and small trees and shrubs along the terraces but
overall the cemetery has a stark, hard aspect contrasting dramatically with
the natural vegetation of the adjacent hills. Cemetery landscape is common on
the urban fringe throughout Hong Kong. As the cemetery landscape is a common
resource, of no particular visual or landscape quality and has a high
tolerance to change, the sensitivity is assessed as Medium. |
Medium |
TKO-LCA3 |
Chiu
Keng Wan Coastal Upland and Hillside Landscape This landscape area covers the steep
natural terrain on the western side of Junk Bay. It is designated Green Belt
and forms a buffer to the urban area of TKO to the north. The area is largely
undeveloped with a road and footpaths forming the only manmade elements. It
is mostly covered in secondary woodland comprising trees, shrubs and grasses.
This semi-natural landscape acts as a foil to the hard man-made forms of the
residential high-rise to the north and the cemetery terraces to the south. Given that this character area is a
remnant of the original Junk Bay landscape, that there is a statutory
presumption against development and it provides a green backdrop to the dense
built up area of TKO, it is assessed as having a High sensitivity. |
High |
TKO-LCA4 |
Mixed
Modern Comprehensive Urban Development Landscape This character area consists of the
existing urban area of TKO which comprises a mix of relatively recent
Government, commercial, community and residential developments and transport
corridors. The scale of the developments is large with multi-storey
developments and the population density is high. This landscape character area is assessed
as having a Medium sensitivity as it is a common urban character type
throughout Hong Kong and has no particular distinctive qualities. Given its
context next to the TKO reclamation to the south which is in a continuing
state of transition it has a reasonable tolerance to change. |
Medium |
TKO-LCA5 |
Reclamation/Ongoing
Major Development Landscape at proposed Tseung Kwan O Town Centre south The reclamation is a transitional
landscape which is currently largely an area of earthworks, hoardings and
fences, groups of self-seeded vegetation and mechanical plant. There is a
temporary golf driving range in the eastern portion. The infrastructure for
the new TKO Town Centre South Development is currently being installed. Given the transitional nature of this
character area and the planning intention to develop it into a new town extension,
this area is assessed as having a Low sensitivity. |
Low |
TKO-LCA6 |
Urban
Residential Landscape This area is characterised by high rise
residential developments with podiums served by commercial and institutional
facilities and road connections. The margins of the area are well defined by
transport corridors and podium edges. The built form is typical of Hong Kong
housing estates and has no particular landscape character value. The sensitivity of this character area is
assessed as Medium given its proximity to the ongoing TKO Town Centre South
Development to the east. |
Medium |
TKO-LCA7 |
Mau
Wu Shan Upland and Hillside Landscape This landscape area covers the southern
slopes of the hills behind TKO. It is designated Green Belt and forms a
buffer to the urban area of TKO to the south. The area consists of a
combination of artificial slopes at the lower level and natural landform
above. The artificial slopes are sparsely vegetated but the natural slopes
have dense woodland coverage. Given that this character has already
been impacted by slope works and is of semi-natural quality, it has a Medium
sensitivity. |
Medium |
10.5.4
The study area
within the Lam Tin side of the project area is flanked by Victoria Harbour and the Lei Yue
Mun Channel to the west and the Black Hill (Ng Kwai Shan) ridgeline to the
east. The Cha Kwo Ling ridge is the site of old granite and kaolin quarry workings
and supports areas of mature woodland and sparse scrub. The northern part of
the workings now incorporates Sai Tso Wan Recreational Ground. The main quarry
site is currently utilised for vehicular storage. Cha Kwo Ling Village lies to
the west of the ridge facing the waterfront and comprises old, low-rise
development including the historic Tin Hau Temple. The Eastern Harbour Crossing Tunnel approaches
and toll plaza cut through the centre of the study area and has associated
peripheral tree planting. The urban area to the east contains new residential,
educational and park facilities incorporating amenity planting. The Yau Tong
Bay waterfront is currently derelict and is scheduled for comprehensive
redevelopment. The Lei Yue Mun Channel is the narrowest point of Victoria
Harbour and is a busy sea lane used by shipping, ferries, fishing boats and
pleasure craft. The open channel also affords panoramic views of the Hong Kong
Island skyline. Landscape Resources
include amenity trees along roadsides and modified slopes, mixed woodland,
ponds and natural watercourses, amenity grassland, natural grass and shrub
areas and the Lei Yue Mun Channel sea waterbody.
10.5.5
The baseline
Landscape Resources at Lam Tin that will be affected during the Construction
and Operation Phases and their sensitivity are described below in Table 10.5.3. An overall view of
Baseline Landscape Resources - TKO and Lam Tin is
illustrated on Figure 10.5.1.1. The locations of the Baseline Landscape Resources at Lam Tin are illustrated on Figure No.s 10.5.3.1a- 1b. Photographic Views illustrating the Landscape
Resources at Lam Tin are provided on Figure
10.5.3.2.
Table 10.5.3 – Lam Tin Landscape Resources
and their Sensitivity
ID
No. |
Lam
Tin Landscape Resources |
Sensitivity
(Low, Medium, High) |
LT-LR1 |
Lei
Yue Mun Channel Sea Waterbody The Lei Yue Mun Channel is the narrowest
point of Hong Kong Harbour and is a busy sea lane for ocean going ships,
fishing boats, pleasure craft and sampans. There is a presumption against
reclamation of the harbour under the Protection of the Harbour Ordinance.
This is particularly pertinent at Lei Yue Mun given the narrowness of the
channel. The channel marks the gateway to Hong Kong Harbour and has played a significant
role in the cultural history of the city. The area within the study boundary
is approximately 68 ha. The sensitivity is assessed as High given
the water body’s physical characteristics, cultural history value and the
statutory presumption against reclamation. |
High |
LT-LR2 |
Trees
within Yau Tong Bay Industrial Waterfront Area There are approximately 125 no. existing
trees in the derelict industrial waterfront strip of Yau Tong Bay (Kwun Tong
Tsai Wan). These are mostly common self-seeded species that have established
on vacant and derelict sites and are generally of low value. Dominant tree
species include Albizia lebbek, Acacia
spp., Macaranga tanarius, Hibiscus tiliaceus, Leucaena leucocephala. The sensitivity is assessed as Medium
given the poor quality of the trees and their general low amenity value and
that they could be replaced. |
Medium |
LT- LR3 |
Mixed
Woodland Vegetation on Hillside Areas There is approximately 10 ha of hillside vegetation
comprising trees, shrubs, grass and climbers on the natural slopes to the
north east fringe of the Lam Tin urban area. It comprises secondary woodland
and dominant tree species include Acacia
spp., Casuarina equisetifolia, Celtis sinensis, Ficus spp., Leucaena
leucocephala and Macaranga tanarius.
Part of this area is designated Greenbelt, G/IC uses and Residential (Group
A). The vegetation provides a valuable green buffer and backdrop to this
dense urban area and begins the transition to the natural uplands of the
Black Hill (Ng Kwai Shan) ridge. This resource is assessed as having
Medium sensitivity given its common species composition, secondary nature, urban
fringe context and the large expanses of similar vegetation stretching to the
north and east. |
Medium |
LT- LR4 |
Pond
at Cha Kwo Ling A seasonal pond is located in the abandoned
quarry site north east of Cha Kwo Ling Tsuen. The pond covers approximately
0.16ha and accommodates a variety of low, water loving vegetation. Due to its transitory nature and low
ecological value, this resource is assessed as having a Medium sensitivity. |
Medium |
LT- LR5 |
Natural
Watercourse A branching natural stream flows down the
vegetated slopes between Ping Tin and Kwong Tin Estates. It is an uncommon
resource in an urban area and provides a wildlife habitat. The stream lies
within an area zoned for G/IC and Residential land uses. The length of the watercourse
is approximately 600m. Given its natural character and relative
rarity within this urban area, the stream is assessed as having High
sensitivity. |
High |
LT- LR6 |
Grass
Sports Pitch within Sai Tso Wan Recreation Ground The sports pitch provides a valuable
recreational resource within a dense urban area and occupies an area of
approximately 1.53 ha. As this resource comprises turf of common
commercially available grass species which is easily reinstated, the sensitivity
for this recreational resource is assessed as Low. |
Low |
LT- LR7 |
Village
Trees within Cha Kwo Ling Residential Area A number of mature trees lie within the
low rise Cha Kwo Ling Village. Dominant tree species include Acacia spp., Eucalyptus spp., Ficus spp.,
Litsea glutinosa, Mallotus paniculatus, Sterculia lanceolata. The
existing trees and shrubs occupy an approximate area of 1ha. This resource is assessed as having a High
sensitivity as the trees are mature and contribute to local amenity. |
High |
LT-LR8A |
Amenity/Roadside
Planting/Vegetation on Modified Slopes at Sai Tso Wan Within the assessment area there is a
network of amenity planting along roads and on modified slopes which support
a wide variety of flora. There are significant quantities of semi mature and
mature tree species situated in these areas including on quarry and other
modified slopes, in recreational facilities, temporary and permanent depots.
This vegetation comprises common ornamental tree, shrub and climber species
and native pioneer tree species including: Acacia spp., Bauhinia spp. Bischofia jananica, Bombax ceiba,
Casuarina equisetifolia, Celtis sinensis, Cinnamomum camphora, Eucalyptus
spp., Ficus spp., Hibiscus tiliaceus, Leucaena leucocephala, Litsea
glutinosa, Macaranga tanarius, Melia azadarach, Schefflera heptaphylla, Sterculia
lanceolata, Syzygium jambos. The sensitivity of this resource is
assessed as High due the maturity of the vegetation and the greening and
amenity value it provides throughout the assessment area. |
High |
LT-LR8B |
Amenity/Roadside
Planting/Vegetation on Modified Slopes at Former Quarry This resource is similar in composition
to LT/LR8A but occupies a distinct
and significant location (in terms of the project footprint) on the rock
walls and surrounding slopes of the former quarry site. The area of
vegetation is approximately 5.08ha. The sensitivity of this resource is
assessed as High due the mature nature of the vegetation and the greening
value it provides for the quarry. |
High |
LT-LR9A |
Grassland/Shrubland
Mosaic on Ng Kwai Shan Grassland/shrubland mosaic areas are
located at Ng Kwai Shan on undulating or sloping terrain. Vegetation recorded includes pioneer tree
species such as Macaranga tanarius,
Litsea glutinosa and Bridelia
tomentosa, shrubs such as Rhodomyrtus
tomentosa, Lantana camara and
Rhaphiolepis indica, ferns Dicranopteris
pedata, grasses Hedyotis acutangula
and Neyraudia reynaudiana and
herbs Bidens alba and Ageratum conyzoides. This resource is assessed as having
Medium sensitivity given its common species composition. |
Medium |
LT-LR9B |
Grassland/Shrubland
Mosaic at Cha Kwo Ling Grassland/shrubland mosaic areas are
located at Cha Kwo Ling on
undulating or sloping terrain.
Vegetation recorded within grassland/shrubland mosaic includes pioneer
tree species such as Macaranga
tanarius, Litsea glutinosa and
Bridelia tomentosa, shrubs Rhodomyrtus
tomentosa, Lantana camara and
Rhaphiolepis indica, ferns Dicranopteris
pedata, grasses Hedyotis acutangula
and Neyraudia reynaudiana and
herbs Bidens alba and Ageratum conyzoides. This resource is assessed as having
Medium sensitivity given its common species composition. |
Medium |
10.5.6
The baseline
Landscape Character Areas at Lam Tin that will be affected during the
Construction and Operation Phases and their sensitivity are described below in Table 10.5.4. The locations of the
Baseline Landscape Character Areas at Lam Tin are illustrated on Figure No. 10.5.4.1.
Photographic Views illustrating the Landscape Character Areas at Lam Tin are provided on Figure
10.5.4.2.
Table
10.5.4 – Lam Tin Landscape Character Areas and their Sensitivity
ID
No. |
Lam
Tin Landscape Character Areas |
Sensitivity (Low, Medium, High) |
LT-LCA1 |
Lei
Yue Mun Channel Inshore Water Landscape The Lei Yue Mun Channel is the narrowest
point of Hong Kong Harbour and is a busy sea lane for ocean going ships,
fishing boats, pleasure craft and sampans. The proximity of the shorelines
either side of the channel at this point provide a unique sense of enclosure
and intimacy in the harbour. The channel marks the gateway to Hong Kong
Harbour and has played a significant role in the rich history of the
development of the harbour city. The sensitivity is assessed as High given
the channel’s physical characteristics, unique local sense of scale, the
cultural history and the statutory presumption against reclamation. |
High |
LT-LCA2 |
Yau
Tong Bay Coastal Industrial Urban Landscape This is a waterfront strip of derelict
and downgraded industrial uses. It is now predominantly zoned as a CDA with
the intention of redevelopment into residential and commercial waterfront to
revitalise the area. The waterfront extension in front of Cha Kwo Ling
Village is zoned as Open Space, G/IC and Other Uses and the planning vision
is to connect the upgraded waterfront with that of the Kai Tak redevelopment
to the north. The existing visual character is poor and there are no
landscape features of intrinsic value apart from some existing trees. It is
the waterfront context that imparts the character to this zone. The sensitivity of this landscape
character area is assessed as Low given the current derelict condition and
the planning intent to redevelop it. |
Low |
LT-LCA3 |
Lam
Tin Upland and Hillside Landscape The green vegetated slopes within and behind
Yau Tong provide an organic backdrop which acts as a visual foil to the dense
urban development. It also marks the urban fringe transition to the
undeveloped natural upland landscapes above and is generally zoned for
Residential and G/IC uses although part of its area is zoned as Greenbelt. The sensitivity of this character area is
assessed as Medium as it lies within the urban fringe zone and is juxtaposed
with dense urban development and is reasonably tolerant to change. |
Medium |
LT- LCA4 |
Miscellaneous
Urban Fringe Landscape This distinctive character area comprises
Cha Kwo Ling Village and lies between Cha Kwo Ling Road and the waterfront
strip to the south west and the elevated ridge of land of the former quarry site
to the north east. The village comprises an organic patchwork of low rise
dwellings with sporadic tree planting. This area is assessed as being of Medium
sensitivity due to its organic nature and it location adjacent to the
transitional waterfront area (LCA2) to the southwest, and it is reasonably
tolerant to change. |
Medium |
LT-LCA5 |
Urban
Recreational Landscape This character area is focused around the
Sai Tso Wan Recreation Ground and Sin Fat Road Tennis Courts immediately
north of the quarry site. The recreational facilities lie within a broad
swathe of mature woodland which screens adjacent LCAs and provides a strong
sense of enclosure for the facilities. This area is reasonably tolerant to
change due to the dense woodland screen which could be reinstated and is
therefore assessed as having a Medium sensitivity. |
Medium |
LT-LCA6 |
Urban
Transport Corridor A broad, linear zone stretching from
the Cha Kwo Ling Road and The Eastern
Harbour Crossing in the south west to Lei Yue Mun Road in the north west is
characterised by carriageways, slip roads, toll plazas, traffic islands, foot
bridges and overpasses, roadside slopes and retaining structures. Due to the low visual quality of this
area and as it is largely tolerant to change the sensitivity is assessed as
Low. |
Low |
LT-LCA7 |
Lam
Tin Residential Urban Landscape This character area forms the main urban
landscape of the study area and comprises modern high rise residential
developments and associated pockets of associated facilities such as
commercial and educational establishments, punctuated in places with amenity
planting. The urban character is unremarkable and similar to most of Hong
Kong’s urban residential character. As the landscape quality of this area is
unremarkable and as it is reasonably tolerant to change the sensitivity is assessed
as Medium. |
Medium |
LT-LCA8 |
Former
Quarry Landscape – Abandoned This landscape character area comprises
the north west portion of the abandoned Ex-Cha Kwo Ling Quarry Site. It
consists of uneven ground with modified slopes and rock-cut platforms. Some
slopes and areas of ground are bare and devoid of vegetation cover. Most of the
area supports a patchy mosaic of trees, shrubs and grass which are
self-seeded and in various stages of maturity. The area is abandoned except
for a level platform on the northern side with associated access road which
is currently utilised as a storage facility. This landscape character area is assessed
as having Low sensitivity due to its abandoned state and incidental
vegetation coverage and is considered to be tolerant to change. |
Low |
LT-LCA9 |
Former
Quarry Landscape – Occupied This southern portion of the Ex-Cha Kwo
Ling Quarry Site is defined by steep rock cut walls with benches which
enclose a flat central portion which has been actively used as an FEHD
storage facility (Cha Kwo Ling Vehicle Depot) and formerly a nursery area. The
surrounding slopes and rock-cut benches are covered with a combination of
self-seeded and planted tree, shrub and climber vegetation which reinforces
the sense of enclosure of the area and provides a degree of visual amenity. Whilst this landscape character area has
a large number of existing mature trees, a significant proportion
(approximately 40%) of the area is access road or hardstanding and the land
uses that it supports are transient in nature. Overall, the sensitivity is
therefore assessed as Medium as it is reasonably able to tolerate change. |
Medium |
10.5.7
A detailed tree
survey has been undertaken within the anticipated footprint of the engineering
alignment and works areas. The survey was undertaken in accordance with ETWB-TC
No.3/2006 and includes Tree Survey Plans recording all trees with a stem
diameter over 95mm DBH (diameter at breast height or 1.3m above ground level). The
Tree Preservation Report has been circulated to relevant government departments.
10.5.8
On the TKO side
of the tunnel the tree survey was undertaken for 2 distinct areas. For “Area A”
of the tree survey, including roads P2 and D4 on the edge of the existing TKO
urban area and some of the recent reclamation to the south a total of 327 no.
existing trees comprising 19 no. species were surveyed. No rare or endangered
species and no “Old and Valuable Trees” (OVTs) as defined under ETWB TC(W)
29/2004 or listed in the LCSD OVT Register were identified within the survey
area. There were also no potential OVTs or “Important Trees” (ITs) as defined
by ETWB TC(W) 3/2006. The dominant species surveyed were Acacia confusa, Bauhinia blakeana, Hibiscus tiliaceus, Cassia siamea
and Eucalyptus camaldulensis and
together these comprise over 72% of the trees. Acacia confusa, Cassia siamea and Eucalyptus camuldensis are exotic species whereas Bauhinia blakeana and Hibiscus tiliaceus are native to Hong
Kong. All the trees are in roadside environments and have been planted relatively
recently (within approximately the last 5 to 10 years). As the trees are
predominantly common species and are not yet mature, their Amenity Value is
rated Medium to Low. Existing trees impacted along Po Yap Road will be
compensated at a ratio of 1:1 by number and girth (provisionally 26 no. heavy
standard compensatory trees will be planted along roadsides). All 30 of the
trees proposed to be transplanted will be transplanted to permanent sites
within the project site.
10.5.9
Tree survey “Area
B” is on the TKO side of the tunnel and includes the tunnel portal area. A
total of 191 no. existing live trees comprising 13 no. species were surveyed.
No rare or endangered species and no “Old and Valuable Trees” (OVTs) and no
potential OVTs or “Important Trees” (ITs) were identified. The dominant species
surveyed were Acacia auriculiformis,
Acacia confusa, Acacia mangium, Acronychia pedunculata, Sapium discolor and
Schefflera heptaphylla and together these 6 species comprise 93% of the
trees. All the species are exotic
except for Acronychia pedunculata and
Sapium discolor which are native to Hong Kong suggesting that this area is
secondary woodland that was planted rather than natural indigenous vegetation
cover. Approximately 50 trees on slopes surrounding the TKO tunnel portal will
be impacted. Tree planting or woodland mix planting is not feasible on the new tunnel portal slopes but
they will be ‘greened’ with shrub and climber planting to reduce the visual
impact. The trees removed within Area B will be compensated at a ratio of 1:1
by number and girth along the reclaimed Road P2 within the project site.
10.5.10 Tree survey “Area C” on the Lam Tin side of the
tunnel, includes the Link Road EHC2 and the realignment of the slip road from
Lei Yue Mun Road onto the westbound carriageway of the EHC. A total of 132 no. trees
comprising 22 no. species were individually surveyed. No rare or endangered
species and no “Old and Valuable Trees” (OVTs) and no potential OVTs or
“Important Trees” (ITs) were identified. The dominant species surveyed were Acacia auriculiformis, Acacia confusa,
Bauhinia blakeana, Caryota mitis, Ficus benjamina, and Melaleuca
quinquenervia and together these comprise over 67% of the trees. All the species are exotic except for Bauhinia blakeana which is
native to Hong Kong. The trees include roadside/street tree planting and trees
planted within and around the former Cha Kwo Ling Kaolin Mine Site. Existing
trees impacted along Link Road EH2 and along the slip road from Lei Yue Mun
Road to the westbound carriageway of the EHC will be compensated at a
ratio of 1:1 by number and girth (provisionally 23 no. heavy standard
compensatory trees will be planted along roadsides).
10.5.11 On the Lam Tin side of the tunnel, tree survey “Area
D” includes the area of the Lam Tin tunnel portal and associated ventilation
building on the north east and western walls of the Ex-Cha Kwo Ling Kaolin Mine
Site; the proposed Lam Tin Interchange comprising the main highway and slip
roads in the Ex-Cha Kwo Ling Kaolin Mine Site, associated buildings of the
TKO-LTT including administration block, a vehicle garage, a Pumping Station and
maintenance facilities including a workshop, training ground, vehicle garage, a
vehicle recovery base and petrol station; road improvements along Cha Kwo Ling
Road and at the junction of Yau Tong Road and at the Roundabout. A total of 3,152 trees were surveyed individually or under the
group survey method comprising 61 different species. No rare or endangered
species and no “Old and Valuable Trees” (OVTs) and no potential OVTs or
“Important Trees” (ITs) were identified. The dominant species surveyed were Acacia confusa, Casuarina equisetifolia, Eucalyptus
exserta, Ficus hispida, Leucaena leucocephala, Macaranga tanarius and Mallotus
paniculatus and together these comprise over 80% of the trees. Acacia
confusa, Casuarina
equisetifolia, Eucalyptus exserta, Ficus hispida and Leucaena
leucocephala are exotic species whereas Macaranga
tanarius and Mallotus paniculatus
are native to Hong Kong. The trees surveyed under the group survey lie on
slopes and uneven ground on the former Cha Kwo Ling Kaolin mine site and were
either planted following cessation of mine workings or have self-seeded since
that date. Existing trees impacted
within the ex-Cha Kwo Ling Quarry Site will be compensated a ratio of 1:1 by
number and girth. Provisionally approximately 700 no. heavy standard compensatory trees will be
planted in and around the Lam Tin Interchange. In addition, some slopes will be
planted with woodland whip mix planting that will ultimately develop into
woodland.
10.5.12 Drawings extracted from Tree Preservation Report include
the Tree Survey Plans (Drawing No.s
URB/MCA75/TA000-003, 101-103, 201, 203-212 and 301) and the Preliminary
Compensatory Planting Plans (Drawing
No.s URB/MCA75/CP-101, 201, 203, 301, 403-408) of the tree survey Areas A
to D are attached in Appendix 10.1.
10.5.13 The visual envelope of the project is illustrated on Figure No. 10.4.1. The two
geographically separate areas of the project at TKO and Lam Tin generate two
distinct visual envelopes or ZVIs. The ZVIs overlap in their southern portions.
VSRs for the two areas are identified and tabulated separately for clarity.
10.5.14 The ZVI for the TKO side of the project is bounded by
Shau Kei Wan, Lei Yue Mun and the ridgeline of the hills enclosing Junk Bay to
the west, the urban area of TKO to the north, the ridgeline of Clearwater Bay
Country Park to the east, the Tathong Channel to the south west and the
ridgeline of the hills of Hong Kong Island in the Tai Tam Country Park in the
south west. The ZVI adopts a cut-off at the Tathong Channel as the only
potential VSRs beyond this would be on Sung Kong and Waglan Island from which
visual impacts would be negligible due to their distant location.
10.5.15 The ZVI for the Lam Tin side of the project is bounded
by the ridgelines of Hong Kong Island to the south and south west, the wooded
ridge behind Cha Kwo Ling Village, the quarry walls and the proposed
residential developments at the Ex-Cha Kwo Ling Kaolin Mine Site to the west and
north and the urban area of Yau Tong to the east and south east.
Visually Sensitive Receivers (VSRs)
10.5.16 Key Visually Sensitive Receivers (VSRs) have been
identified for the Construction and Operation phases. For ease of reference,
each VSR is given an identity number, which is used in the text tables and
Drawings in this assessment. The VSRs for TKO and Lam Tin are tabulated
separately. They are listed and assessed below, for their sensitivity to change in view as a result of the
Project in Tables 10.6.5 and 10.5.7. They are listed and assessed
below for the magnitude of change in view in Tables 10.5.6 and 10.5.8.
10.5.17 VSRs for TKO during the Construction Phase are mapped
on Figure No.s 10.5.5.1 to 10.5.5.3, namely Baseline VSRs
during Construction - TKO (Sheets 1 to 3) and VSRs for TKO during the Operation
Phase are mapped on Figure No.s 10.5.5.4
to 10.5.5.6 namely Baseline VSRs during Operation - TKO (Sheets 1 to 3)
Baseline VSR Photographs with views to or from the VSRs at TKO are shown on Figure
No.s 10.5.5.7 to 10.5.5.19
(Sheets 1 to 13).
10.5.18 VSRs for Lam Tin during the Construction Phase are
mapped on Figure No.s 10.5.6.1
and 10.5.6.2, namely Baseline VSRs during Construction – Lam Tin (Sheets 1
to 2) and VSRs for Lam Tin during the Operation Phase are mapped on Figure No.s
10.5.6.3 and 10.5.6.4, namely Baseline VSRs during Operation – Lam Tin (Sheets 1 to
2). Baseline VSR Photographs with views to or from the VSRs at Lam Tin are shown on Figure
No.s 10.5.6.5 to 10.5.6.15. (Sheets 1 to 12).
10.5.19 Certain VSRs which lie outside the ZVI have also been included in the assessment, particularly for the Lam Tin side of the
project. These VSRs due to their location and proximity have the potential for
views to the project, but it is confirmed by site inspection that the project
would not be visible from them. To demonstrate that these VSRs have been
considered and not mistakenly omitted, they are also included in the
assessment.
10.5.20 For the avoidance of doubt, VSRs in the planned developments
which, based on latest programme information, will be completed before the
completion of the TKO-LT Tunnel have been considered as existing VSRs in this assessment. They are
identified in the tables and text with an asterisk (*) to distinguish them from
VSRs which are currently in existence.
Table 10.5.5 Tseung Kwan O Visually
Sensitive Receivers and their Sensitivity
VSR ID No. |
Key VSR |
No. of Viewers (Many, Medium, Few) |
Quality of Existing View (Good, Fair,
Poor) |
Availability of Alternative Views (Yes,
No) If Yes, Amenity Value of Alternative
View (Good, Fair, Poor) |
Degree of Visibility (Full, Partial,
Glimpse) |
Duration of View (Long, Medium, Short) |
Frequency of View (Frequent, Occasional,
Rare) |
Sensitivity
to Change (Low,
Medium, High) |
|
Construction |
Operation |
||||||||
Existing
VSRs in TKO |
|||||||||
TKO-CDA1A |
Existing
Residents and |
Many |
Good |
Yes
(Fair) |
Glimpse |
Long |
Frequent |
Medium |
Medium |
TKO-CDA1B* |
Residents
in planned new Residential Development at CDA in Area 86/LOHAS Park * |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
TKO-GIC1 |
Workers
in TKO Sewage Treatment Works, Area 85 |
Few |
Poor |
Yes
(Fair) |
Nil |
N/A |
N/A |
Low |
Low |
TKO-GIC2 |
Staff
and students at |
Medium |
Fair |
Yes
(Fair) |
Partial |
Short |
Frequent |
Low |
Low |
TKO-GIC4 |
Staff
and students at Hong Kong Design Institute Campus |
Medium |
Good |
Yes
(Fair) |
Partial |
Short |
Frequent |
Low |
Low |
TKO-GIC5 |
Workers
at |
Medium |
Fair |
Yes
(Fair) |
Partial |
Short |
Frequent |
Low |
Low |
TKO-GIC6 |
Staff
and students at Heung To Secondary School and GT College |
Medium |
Poor |
No
|
Nil |
N/A |
N/A |
Low |
Low |
TKO-GIC7 |
Staff
and students at Caritas Bianchi College of Careers |
Medium |
Poor |
No |
Nil |
N/A |
N/A |
Low |
Low |
TKO-GIC8 |
Workers
at Logistics Centre and Preliminary Treatment Works and |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Occasional |
Low |
Low |
TKO-GIC9* |
Workers
in planned GIC Development at TKO Area 67 |
Medium |
Fair |
Yes
(Fair) |
Partial |
Medium |
Occasional |
Low |
Low |
TKO-GIC10* |
Patients
and staff at planned private hospital and students and staff at planned Fire |
Medium |
Fair |
Yes
(Fair) |
Partial |
Medium |
Occasional |
Low |
Low |
TKO-OU1A |
Workers
at TKO Industrial Estate |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Occasional |
Low |
Low |
TKO-OU2 |
Visitors
of |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Low |
Low |
TKO-O1 |
Users
of Heng Fa Chuen Playground |
Medium |
Good |
Yes
(Good) |
Full |
Medium |
Occasional |
High |
High |
TKO-O2 |
Users
of Siu Sai Wan Promenade |
Medium |
Good |
Yes
(Good) |
Full |
Medium |
Occasional |
High |
High |
TKO-O3* |
Users
of planned Open Space at TKO Area 68 |
Many |
Good |
Yes
(Good) |
Full |
Medium |
Occasional |
High |
High |
TKO-R1 |
Residents
of Heng Fa Chuen |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
TKO-R2 |
Residents
of |
Many |
Fair
|
Yes
(Fair) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R3 |
Residents
of |
Many |
Good |
Yes
(Fair) |
Full |
Long |
Frequent |
High |
High |
TKO-R4 |
Residents
of |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R5 |
Residents
of Park Central |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R6 |
Residents
of the Grandiose and |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R7 |
Residents
of Oscar by the Sea |
Many |
Fair |
Yes
(Fair) |
Partial |
Medium |
Frequent |
Medium |
Medium |
TKO-R8 |
Residents
& users of Island Resort residential area and promenade |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
TKO-R9 |
Residents
in Choi Ming Court |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R10 |
Residents
in Chai Wan high rise estates |
Many |
Good |
Yes
(Fair) |
Full |
Long |
Frequent |
High |
High |
TKO-R11 |
Residents
in Kin Ming Estate |
Many |
Poor |
Yes
(Poor) |
Nil |
N/A |
N/A |
Medium |
Medium |
TKO-R12 |
Residents
in Shin Ming Estate |
Many |
Poor |
Yes
(Poor) |
Nil |
N/A |
N/A |
Medium |
Medium |
TKO-R13 |
Residents
at MTRC TKO Station Residential Development |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R14a* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)2 |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R14b* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)3 |
Many |
Fair |
Yes
(Poor) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R14c* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)4 Areas (a) & (b) |
Many |
Fair |
Yes
(Fair) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-R14d* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)5 |
Many |
Good |
Yes
(Fair) |
Partial |
Long |
Frequent |
High |
High |
TKO-R14e* |
Residents
in planned Residential Development on TKO Town Centre South reclamation R(A)6
Area (a), (b) & (c) East |
Many |
Good |
Yes
(Good) |
Partial |
Long |
Frequent |
High |
High |
TKO-R14f* |
Residents
in planned Residential Development on TKO Town Centre South reclamation R
(A)6 Area (a), (b) & (c) West |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
TKO-R15* |
Residents
in upper floors of planned Residential Group (E) Development in Area 85 |
Many |
Poor |
Yes
(Fair) |
Partial |
Long |
Frequent |
Medium |
Medium |
TKO-REC1 |
Hikers
along |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-REC2 |
Hikers
along the |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
TKO-REC3A |
Visitors
of |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-REC3B |
Visitors
of |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-REC4 |
Hikers
along Pottinger Trail and Pottinger |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-REC5 |
Hikers
at |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-REC6 |
Hikers
at |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Rare |
Medium |
Medium |
TKO-T1 |
Seaborne
Leisure Travellers in |
Medium |
Fair |
Yes
(Good) |
Full |
Short |
Occasional |
Medium |
Medium |
TKO-T2 |
Seaborne
Leisure Travellers along Lei Yue Mun
and Tathong Channel |
Many |
Fair |
Yes
(Good) |
Full |
Short |
Occasional |
Medium |
Medium |
TKO-T3 |
Travellers
along Wan Po Road |
Many |
Fair |
Yes (Fair) |
Partial/
Glimpse |
Short |
Occasional |
Low |
Low |
TKO-T4 |
Travellers
at TKO MTR Station and along |
Many |
Poor |
Yes
(Poor) |
Partial/
Glimpse |
Short |
Occasional |
Low |
Low |
TKO-T5 |
Pedestrians
on footpath link from |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Occasional |
Medium |
Medium |
TKO-T7 |
Travellers
on new Southern Footbridge crossing Eastern Channel |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Occasional |
Medium |
Medium |
Planned future VSRs in TKO |
|||||||||
TKO-OU1B |
Workers
in planned TKO Industrial Estate Extension |
Medium |
Good |
Yes
(Good) |
Full |
Short |
Occasional |
N/A |
Low |
TKO-REC7 |
Users
of planned recreational facilities at TKO Stage I Landfill, Area 77 |
Many |
Good |
Yes
(Good) |
Full |
Medium |
Occasional |
N/A |
Medium |
*VSRs in developments planned to be
completed before completion of TKO-LT
Tunnel
Table 10.5.6 Tseung Kwan O Visually
Sensitive Receivers and their Magnitude of Change
VSR ID No. |
Key VSR |
Potential Blockage of View (Full/ Partial/Glimpse) |
Minimum Viewing Distance (m) |
Scale of Develop-ment (Large/ Medium/ Small) |
Compati-bility
(Good/ Fair/ Poor) |
Duration of Impacts (Long/ Medium/ Short) |
Revers-ibility
of Change (Yes/No) |
Magnitude of
Impacts (Large/Intermediate/Small/ /Negligible) |
||
Construction |
Operation |
Construction |
Operation |
|||||||
Existing VSRs in
TKO |
||||||||||
TKO-CDA1A |
Residents
and |
Partial |
1500m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-CDA1B* |
Residents in planned new Residential Development at
CDA in Area 86/LOHAS Park |
Partial |
1000m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-GIC1 |
Workers
in TKO Sewage Treatment Works, Area 85 |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-GIC2 |
Staff
and students at |
Partial |
750m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-GIC4 |
Staff
and students at Hong Kong Design Institute Campus |
Partial
|
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
TKO-GIC5 |
Workers
at |
Partial |
1750m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Small |
TKO-GIC6 |
Staff
and students at Heung To Secondary School and GT College |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-GIC7 |
Staff
and students at Caritas Bianchi College of Careers |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-GIC8 |
Workers
at Logistics Centre and Preliminary Treatment Works and |
Partial
|
3000m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-GIC9* |
Future
workers in planned GIC Development at TKO Area 67 |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Large |
Intermediate |
TKO-GIC10* |
Patients
and staff at planned private hospital and students and staff at planned |
Partial |
2000m |
Medium |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-OU1A |
Workers
at TKO Industrial Estate |
Partial |
1500m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-OU2 |
Visitors
of |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
TKO-O1 |
Users
of Heng Fa Chuen Playground |
Partial |
2700m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-O2 |
Users
of Siu Sai Wan Promenade |
Partial |
3200m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-O3* |
Users
of planned Open Space at TKO Area 68 |
Partial |
500m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-R1 |
Residents
of Heng Fa Chuen |
Partial |
2500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-R2 |
Residents
of |
Partial |
350m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R3 |
Residents
of |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-R4 |
Residents
of |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate
|
Intermediate |
TKO-R5 |
Residents
of Park Central |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
TKO-R6 |
Residents
of the Grandiose and |
Partial |
350m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R7 |
Residents
of Oscar by the Sea |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-R8 |
Residents
& users of Island Resort residential area and promenade |
Partial |
3300m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-R9 |
Residents
in |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R10 |
Residents
in Chai Wan high rise estates |
Partial |
3500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-R11 |
Residents
in Kin Ming Estate |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-R12 |
Residents
in Shin Ming Estate |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
TKO-R13 |
Residents
at MTRC TKO Station Residential Development |
Partial |
100m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R14a* |
Residents
in planned Residential Development on TKO Town Centre South reclam-ation OZP
Zone R(A)2 |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R14b* |
Residents
in planned Residential Development on TKO Town Centre South reclam-ation OZP
Zone R(A)3 |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R14c* |
Residents
in planned Residential Development on TKO Town Centre South reclam-ation OZP
Zone R(A)4 Areas (a) & (b) |
Partial |
500m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-R14d* |
Residents
in planned Residential Development on TKO Town Centre South reclam-ation OZP
Zone R(A)5 |
Partial |
200m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-R14e* |
Residents
in planned Residential Development on TKO Town Centre South reclam-ation
R(A)6 Area (a), (b) & (c) East |
Partial |
550m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-R14f* |
Residents
in planned Residential Development on TKO Town Centre South reclamation R(A)6
Area (a), (b) & (c) West |
Partial |
100m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
TKO-R15 |
Residents
in upper floors of planned Residential Group (E) development in Area 85 * |
Partial |
1750m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-REC1 |
Hikers
along |
Partial |
3500m |
Small |
Fair |
Medium |
Long |
No |
Small |
Small |
TKO-REC2 |
Hikers
along the |
Partial |
1000m |
Medium |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
TKO-REC3A |
Visitors
of |
Partial |
2750m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-REC3B |
Visitors
of |
Partial |
2750m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
TKO-REC4 |
Hikers
along Pottinger Trail and Pottinger |
Partial |
4500m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
TKO-REC5 |
Hikers
at |
Partial |
5500m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
TKO-REC6 |
Hikers
at |
Partial |
5000m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
TKO-T1 |
Seaborne
Leisure Travellers in |
Partial |
10m |
Large |
Good |
Medium |
Long |
No |
Large |
Large |
TKO-T2 |
Seaborne
Leisure Travellers along Lei Yue Mun
and Tathong Channel |
Partial |
1500m |
Medium |
Good |
Medium |
Long |
No |
Intermediate |
Intermediate |
TKO-T3 |
Travellers
along Wan |
Partial |
1500m |
Large |
Fair |
Medium |
Long |
No |
Small |
Small
|
TKO-T4 |
Travellers
at TKO MTR Station and along |
Partial |
10m |
Large |
Fair |
Medium |
Long |
No |
Large |
Intermediate |
TKO-T5 |
Pedestrians on footpath link from |
Partial |
0m |
Large |
Poor |
Medium |
Long |
No |
Large |
Large |
TKO-T7 |
Travellers
on new Southern Footbridge crossing Eastern Channel |
Partial |
750
m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
Planned future VSRs in TKO |
||||||||||
TKO-OU1B |
Workers
in planned TKO Industrial Estate Extension |
Partial |
1500m |
Large |
Fair |
N/A |
Long |
No |
N/A |
Large |
TKO-REC7 |
Users
of planned recreational facilities at TKO Stage I Landfill, Area 77 |
Partial |
750m |
Large |
Fair |
N/A |
Long |
No |
N/A |
Large |
*VSRs in developments planned to be
completed before completion of TKO-LT Tunnel
Sensitivity
and Magnitude of Change for VSRs in TKO
Existing VSRs in
TKO
10.5.21 Existing Residents and workers in TKO Area 86
Comprehensive Development Area/ LOHAS Park (TKO-CDA1A): Residents are generally considered to be sensitive to
changes in their views as the quality of the view affects their perception of
their home environment and quality of life. These particular residents are many
in number and will experience good quality glimpse views between the new tower
blocks of TKO-CDA1B. Alternative
views are available. Their views will also be frequent and of long duration.
Overall the assessment of sensitivity for this VSR is therefore Medium during
the Construction and Operation Phases due largely to the visual obstruction by TKO-CDA1B.
10.5.22 The potential blockage of the view by the development
will be partial and the distance of view 1500m. The scale of development is large
and irreversible. The compatibility with the visual context is fair given the existing
TKO reclamation and planned intent for new town extension and Area 77 Landfill.
The duration of impacts is long and the development is irreversible. The
magnitude of visual impact for this VSR is assessed as Small during the Construction and Operation Phases due
largely to the visual obstruction by TKO-CDA1B.
10.5.23 Residents in planned new Residential Development at CDA
in Area 86/LOHAS Park (TKO-CDA1B*): These
residents will be many in number, enjoy good quality existing views with full
visibility across Junk Bay. Alternative views are available. Their views are
also frequent and of long duration. Overall the assessment of sensitivity for
this VSR is therefore High during the Construction and Operation Phases.
10.5.24 The potential blockage of the
view by the development will be partial and the distance of view is 1000m. The scale of development is large and irreversible. The compatibility
with the visual context is fair given the existing TKO reclamation and planned
intent for new town extension and Area 77 Landfill. Due to
the unobstructed views to the development site, long duration of impacts and the permanence of the
development, overall the magnitude of visual impact for this VSR is assessed as
Large during the Construction and Operation Phases.
10.5.25 Workers in TKO Sewage Treatment Works, Area 85 (TKO-GIC1): Workers are generally
considered to be only moderately sensitive to impacts on their view as the
attractiveness or otherwise of their outlook has a relatively low effect on
their perceived quality of life. These workers are few in number and the
quality of their existing view west is poor and alternative views are available
to the east. Views of the development site are obstructed by LOHAS Park (TKO-CDA1A
and TKO-CDA1B). Overall the sensitivity of this VSR is therefore Low
during the Construction and Operation Phases.
10.5.26 As this VSR will be obstructed by LOHAS Park (TKO-CDA1A and TKO-CDA1B), the visibility will be nil and the magnitude of visual
impact for this VSR is therefore Negligible during the Construction and
Operation Phases.
10.5.27 Staff and students at TKO Methodist Primary School
& Evangelical College (TKO-GIC2): College/school Staff and students are generally
considered to be only moderately sensitive to impacts on their view as the
attractiveness or otherwise of their outlook has a relatively low effect on
their perceived quality of life. These particular staff and students are medium
in number and the quality of their existing view is fair and alternative views
are available. They will experience partial, frequent views of short duration. The
degree of visibility will be partial during the construction and operation as
planned residential developments (TKO-R14a,
14d, 14e & 14f) will be built in front, screening the project site. Overall,
the sensitivity of this VSR is therefore assessed as Low during the
Construction and Operation Phases.
10.5.28 The potential blockage of the view by the development
will be partial and VSRs will view the project from a distance of 750m. The
compatibility of the large scale permanent development with the visual context
is fair given the transitional nature of the TKO reclamation and planned intent
for new town extension. Due to the long duration of impacts and partial obstruction,
the overall magnitude of impact for this VSR is assessed as Small during the Construction Phase and the Operation Phase.
10.5.29 Staff and students at Hong Kong Design Institute
Campus (TKO-GIC4): Staff and
students are generally considered to be only moderately sensitive to impacts on
their view as the attractiveness or otherwise of their outlook has a relatively
low effect on their perceived quality of life. The number of staff and students
is medium in number and the quality of their existing view is good with
visibility of parts of the project site and alternative views available. They
will experience frequent views of short duration. Overall, the sensitivity of
this VSR is therefore Low during the Construction and Operation Phases.
10.5.30 The potential blockage of the view by the development
will be partial and VSRs will have views of parts of the project site from a
close distance (50m). The compatibility of the development with the existing
visual context will be fair given the transitional nature of the TKO
Reclamation and planned intent for new town extension. The Visual impacts will be long term and
irreversible. Overall the magnitude of impacts for this VSR will be
Intermediate during the Construction and Operation Phases.
10.5.31 Workers at Hong Kong Movie City (TKO-GIC5): Workers are generally considered to be only moderately
sensitive to impacts on their view as the attractiveness or otherwise of their
outlook has a relatively low effect on their perceived quality of life. These workers
are medium in number and the quality of their existing view is fair with
partial visibility due to obstruction by the Area 77 Landfill. Alternative
views are available. They will experience frequent views of short duration. Overall,
the sensitivity of this VSR is therefore assessed as Low during the
Construction and Operation Phases.
10.5.32 The potential blockage of the view by the development
will be partial and VSRs will have distant views of the project development.
The compatibility of the development with the existing visual context is fair
given the nature of Area 77 and TKO-CDA1A and TKO-CDA1B. Overall the magnitude of impact for this VSR
will be Intermediate during the Construction Phase and will be reduced to Small
during the Operation Phase when the planned recreational facilities at TKO
Stage I Landfill, Area 77 (TKO-REC7) have been developed and the VSR’s views
are further obstructed.
10.5.33 Staff and students at Heung To Secondary School and GT
College (TKO-GIC6) and Caritas
Bianchi College of Careers (TKO-GIC7): These
VSRs are medium in number and the quality of their existing view is poor with
no alternative views available. The degree of visibility is nil due to the
surrounding existing development and topography and the overall sensitivity of
these VSRs is therefore assessed as Low during the Construction and Operation
Phases.
10.5.34 As the degree of visibility will be nil, the magnitude
of impacts for this VSR is Negligible during the Construction and Operation
Phases.
10.5.35 Workers at Logistics Centre and Preliminary Treatment
Works and Cargo Handling Basin (TKO-GIC8):
These workers are medium in number and the quality of their existing view
is good with full visibility and alternative views available. Their frequency
of view is occasional and of short duration. Overall the sensitivity of this
VSR is assessed as Low during the Construction and Operation Phases.
10.5.36 The potential blockage of the view by the development
will be partial and the viewing distance will be great (3km). The compatibility
of the development with the existing visual context will be good given the
existing backdrop of the TKO urban area and planned intent for new town
extension. Although the duration of impact will be long, the VSR distance will
result in a Small magnitude of impact during the Construction and Operation
Phases.
10.5.37 Workers in planned GIC Development at TKO Area 67 (TKO-GIC9*): The numbers of VSRs will be
medium and the quality of their view will be fair. Alternative views will be
available. The degree of visibility will be partial due to the surrounding
planned residential development (TKO-R14f).
The frequency of view will be occasional and the
duration of view will be medium. Overall the sensitivity to change for this VSR
will be Low.
10.5.38 The potential blockage of the view by the development
will be partial and these VSRs will have close views of parts of the project
site. The scale of development will be perceived as large due to its proximity.
The compatibility of the development will be perceived as fair given the
context of the TKO reclamation and planned intent for new town extension. The
magnitude of impact for this VSR will be Large during the Construction Phase
given its proximity, and will be reduced to Intermediate during the Operational Phase when the
completed road infrastructure is viewed in the context of the surrounding reclamation
development.
10.5.39 Patients and staff at planned private hospital and
students and staff at planned Fire Services Training School cum Driving
Training School in Area 78 (TKO-GIC10*):
The numbers of VSRs will be medium and the quality of their view will be fair.
Alternative views will be available. The degree of visibility will be partial
due to the screening provided by the landform to the west of the GIC site. The
frequency of view will be occasional and of medium duration. Overall the
sensitivity to change for this VSR will be Low during the Construction and Operation Phases.
10.5.40 The potential blockage of the view by the development
will be partial from a distance of 2km and the scale of development will be
perceived as medium due to the distance of view. The compatibility of the
development will be fair given the context of the TKO reclamation town extension
and Area 77 landfill, and the Junk Bay Chinese Permanent Cemetery backdrop. The
magnitude of impact for this VSR will be Small during the Construction and Operational
Phases.
10.5.41 Workers at TKO Industrial Estate (TKO-OU1A): These workers are medium in number, enjoy good quality
existing and alternative views with full visibility of the proposed development
site. Their views however are only occasional and of short duration. Overall
the assessment of sensitivity for this VSR is Low during the Construction and
Operation Phases.
10.5.42 The potential blockage of the view by the development
will be partial and the viewing distance will be 1.5km. The compatibility of
the development with the visual context will be fair given the backdrop of TKO
and the Junk Bay Permanent Chinese Cemetery.
Due to the long duration of impacts and the large scale of development,
the overall magnitude of impact for this VSR is Large during the Construction
and Operation Phases.
10.5.43 Visitors of Junk Bay Chinese Permanent Cemetery (TKO-OU2): Visitors in a cemetery are
generally considered to be moderately sensitive to changes in their views as
the quality of the view affects the perception of their visit. This VSR is
medium in number and enjoys good quality existing views with partial visibility
of the proposed project site. Alternative views are available. However, as the
frequency of their views is rare and of short duration and as views is only
partial, the overall assessment of sensitivity for this VSR is Low during the
Construction and Operation Phases.
10.5.44 The potential blockage of the view by the development
will be partial and the viewing distance will be potentially as little as worst
50m but generally much greater than this. The compatibility of the proposed
development with the existing visual context is fair given the backdrop of TKO,
landfill, CDA and industrial uses on the north and east sides of Junk Bay. As
the visibility of the development will only be partial, the overall magnitude
of impacts for this VSR is assessed as Intermediate during the Construction and
Operation Phases.
10.5.45 Users of Heng Fa Chuen Playground (TKO-O1) and Users of Siu Sai Wan
Promenade (TKO-O2): Users of
recreational facilities are generally considered to be sensitive to changes in
their views as the quality of the view affects their perception of the leisure
environment and quality of experience. These VSRs are medium in number, enjoy
good quality existing views with full visibility. Alternative views are available. Their views
are occasional and of medium duration. Overall the assessment of sensitivity
for these VSRs is therefore High during the Construction and Operation Phases.
10.5.46 The potential blockage of the view by the development
will be partial and the viewing distance will be 2.7 and 3.2km respectively.
The compatibility of the proposed development with the visual context is good
given the built-up urban backdrop of TKO and planned intent for new town
extension. Although the project will be fully visible, it is considered that it
will be perceived as small in scale when viewed from this distance. Overall the
magnitude of impacts will therefore be Small during the Construction and
Operation Phases.
10.5.47 Users of planned Open Space at TKO Area 68 (TKO-O3*): This planned VSR will be
many in number, enjoy good quality existing views with full visibility of the
proposed reclamation and interchange. Alternative views will be available.
Their views will be occasional and of medium duration. Overall the assessment
of sensitivity for this VSR is High during the Construction and Operation
Phases.
10.5.48 The potential blockage of the view by the development
will be partial and the viewing distance will be 500m. The compatibility of the
proposed development with the visual context will be fair as VSRs will view the
development against the backdrop of the Junk Bay Chinese Permanent Cemetery and
the associated slopeworks of the new connecting footpath and the green hillside
landscape above. The scale of the project will perceived as large. Impacts will
be irreversible and of long duration. Overall the magnitude of impacts will
therefore be Large during the Construction and Operation Phases.
10.5.49 Residents of Heng Fa Chuen (TKO-R1), Residents of Chai Wan high rise estates
(TKO-R10) and Residents and users of Island Resort residential area and promenade (TKO-R8): Residents are generally
considered to be sensitive to changes in their views as the quality of the view
affects their perception of their home environment and quality of life. These
particular VSRs are many in number, enjoy good quality existing views across
the Thatong Channel and Junk Bay with partial visibility of the projects site.
Alternative views are available. Their views are also frequent and of long
duration. Overall the assessment of sensitivity for this VSR is therefore High
during the Construction and Operation Phases.
10.5.50 The potential blockage of the view by the development
will be partial and from considerable distance (2.5 - 3.5km) making the
perception of the scale of the development small. The compatibility of the
development with the existing visual context is good given the backdrop of JBCPC, TKO and planned intent for new town extension, Area
77 Landfill site and TKO Industrial Estate. The duration of impact will be long
and irreversible. Overall the magnitude of impact for TKO-R1, TKO-R8 and TKO-R10 is therefore Small during the Construction and
Operation Phases.
10.5.51 Residents of Bauhinia Garden (TKO-R2) and Residents of The Grandiose and TKO Plaza (TKO-R6): Residents are generally considered to be sensitive to
changes in their views as the quality of the view affects their perception of
their home environment and quality of life. These particular residents are many
in number, will experience fair quality existing views with partial visibility
of the project site due to the construction of planned residential development
to the south and west (TKO-14a to 14f).
Alternative views are available. Their views are frequent and of long duration.
Overall the assessment of sensitivity for these VSRs is therefore Medium during the Construction and Operation Phases.
10.5.52 The potential blockage of the view by the development
will be partial and from a distance of 350m to the roadworks element of the
project making the perception of the scale of the development large. The
compatibility of the development with the existing visual context is fair given
the transitional nature of the TKO reclamation and planned intent for new town
extension. The duration of impacts will be long. Overall the magnitude of
impact for both VSRs is assessed as Small during the Construction Phase and the
Operation Phase.
10.5.53 Residents of Ocean Shores (Phases I to III) (TKO-R3): These residents are many in
number and experience good quality existing views. Alternative views are
available. The views are frequent and of long duration. Overall the assessment
of sensitivity of the residents
on the upper floors is therefore High during the Construction and Operation
Phases (however, some residents on lower floors may
experience lower visual impacts due to blockage of views by existing podium
planting and associated recreational features).
10.5.54 The potential blockage of the view towards Junk Bay by
the development will be partial and from a distance of 50m making the
perception of the scale of the development large. The compatibility of the
development with the existing visual context is fair given the transitional nature
of the TKO reclamation and planned intent for new town extension, Area 77
Landfill, CDA1 and the TKO Industrial Estate. Overall, the magnitude of impacts
is assessed as Large during the Construction and Operation Phases.
10.5.55 Residents of Metro Town (TKO-R4) and Residents of Park
Central (TKO-R5): These particular residents are many in number, will
experience fair quality existing views with partial visibility of the project
site due to the construction of planned residential development to the east and
south. Alternative views are available. Their views are frequent and of long
duration. Overall the assessment of sensitivity for these VSRs is therefore
Medium during the Construction and Operation Phases.
10.5.56 The potential blockage of the view by the development
will be partial and from a distance of 50m to the roadworks element of the
project making the perception of the scale of the development large. The
compatibility of the development with the existing visual context is fair given
the current transitional nature and planned intent of the TKO reclamation. The
duration of impacts will be long. Overall the magnitude of impact for both VSRs
is assessed as Intermediate during the Construction Phase and the Operation
Phase.
10.5.57 Residents of Oscar by the Sea (TKO-R7): These residents are many in number, will experience partial
visibility of the project site due to the construction of planned residential
development to the south and west however views will be frequent and of medium duration.
Overall the assessment of sensitivity for these VSRs is therefore Medium during the Construction and Operation Phases.
10.5.58 As the view towards to the development will be largely
blocked by the planned Residential Development on TKO Town Centre South
Reclamation, the magnitude of impacts for this VSR will be Negligible during the
Construction and Operation Phases.
10.5.59 Residents of Choi Ming Court (TKO-R9): Residents at this VSR are many in number, experience fair,
partial views of the project site due to planned development to the south and
west. Alternative views are available. Views will be frequent and of long duration. Overall the
sensitivity of this VSR is assessed as Medium during the Construction and
Operation Phases.
10.5.60 The potential blockage of the view by the development
will be partial and from a distance of 50m making the perception of the scale
of the development large. The compatibility of the development with the
existing visual context will be fair given the transitional nature of the TKO
reclamation and planned intent for new town extension between the VSR and the
proposed development. The duration of impacts will be long and the visual
impacts will be irreversible. The magnitude of change for this VSR is assessed as Small during the Construction Phase
and Operation Phase due to the completed planned developments on the TKO
reclamation which will obstruct the views.
10.5.61 Residents in Kin Ming Estate (TKO-R11) and Shin Ming Estate (TKO-R12):
These residents are many in number and experience poor quality existing views
due to the density of surrounding development. The degree of visibility of the
project site will be nil. The assessment of sensitivity is Medium during the
Construction and Operation Phases.
10.5.62 The potential blockage of the view by the development
will be nil and the overall magnitude of impact will be Negligible during the Construction
and Operation Phases.
10.5.63 Residents at MTRC TKO Station Residential Development (TKO-R13): Residents are generally
considered to be sensitive to changes in their views as the quality of the view
affects their perception of their home environment and quality of life. These
particular residents are many in number, will experience fair quality existing views with partial visibility of the
project site due to the completion of planned construction to the south and
west. Alternative views are available. Their views are frequent and of long
duration. Overall the assessment of sensitivity for these VSRs is assessed as Medium
during the Construction and Operation Phases.
10.5.64 The potential blockage of the view by the development
will be partial and from a distance of 100m to the roadworks element of the
project making the perception of the scale of the development large. The
compatibility of the development with the existing visual context is fair given
the transitional nature of the TKO reclamation and planned intent for new town
extension. The duration of impacts will be long. Overall the magnitude of
impact for VSR TKO-R13 is assessed
as Small during the Construction Phase and Operation Phases.
10.5.65 Residents in planned Residential Development on TKO
Town Centre South reclamation OZP Zones R(A)2, R(A)3 and R(A)4 Areas
(a) & (b) (TKO-R14a* to TKO-R14c* respectively): The future residents of
these developments on the TKO reclamation will be many in number and the
quality of their view of the project will be fair due to screening by other
adjacent projects. Alternative views will be available. Views will be frequent
and of long duration. Overall the sensitivity of these VSRs will be Medium.
10.5.66 The potential blockage of the view by the development
will be partial and from a distance of 50 to 500m making the perception of the
scale of the development large. The compatibility of the development with the
existing visual context will be fair given its integrated nature with the TKO
new town extension on the reclamation. The duration of impacts will be long and
the visual impacts will be irreversible. The magnitude of impact is assessed as
Small during the Construction Phase and Operation Phases due to the surrounding completed planned developments
on the TKO reclamation which will obstruct the views of the project site.
10.5.67 Residents in planned Residential Development on TKO
Town Centre South reclamation OZP Zones R(A)5 , R(A)6 Area (a), (b) & (c)
East and R(A)6 Area (a), (b) & (c) West (TKO-R14d* to TKO-R14f* respectively): The future residents of these
planned developments on the TKO reclamation will be many in number and the
quality of their view will be good with open views to the south across Junk
Bay. Alternative views will be available. Views will be frequent and of long
duration. Overall the sensitivity of these VSRs during the Construction Phase
and Operation Phases will be High.
10.5.68 The potential blockage of the view by the development
will be partial and from a distance of 100 to 550m making the perception of the
scale of the development large. The compatibility of the development with the
existing visual context will be fair given its integrated nature with the TKO
new town extension on the reclamation. The duration of impacts will be long and
the visual impacts will be irreversible. The magnitude of impact is assessed as
Large during the Construction Phase and Operation Phases.
10.5.69 Residents in upper floors of planned Residential Group
(E) Development in Area 85 (TKO-R15*):
the VSRs will be many in number and will experience poor views of the project
site of a partial nature due to the visual obstruction of LOHAS Park tower
blocks (TKO-CDA1A & CDA1B).
Alternative views will be available, particularly to the east. Views will be
frequent and of long duration. Overall the sensitivity to change of views to
the development will be Medium.
10.5.70 The potential blockage of the view by the development
will be partial and from a distance of 1750m making the perception of the scale
of the development large. The compatibility of the development with the
existing visual context will be fair given the proximity of other large scale
developments such as LOHAS Park to the west, the Area 77 landfill to the north
and TKO Industrial Estate to the south. Overall the magnitude of impact will be
Small during the Construction and Operational Phases due to the high level of
visual obstruction towards the site as a result of the LOHAS Park residential
developments.
10.5.71 Hikers on High Junk Peak
(Tiu Yue Yung) Country Trail in Clear Water Bay Country Park (TKO-REC1): Visitors of recreational
facilities and hikers are generally considered to be moderately sensitive to
changes in their views as the quality of the view affects the perception of
their leisure environment and quality of experience. These particular VSRs are
medium in number and enjoy good quality existing views with full visibility of
the project site. Alternative views are available. Views are of short duration
and infrequent. Overall the assessment of sensitivity for these VSRs is
therefore Medium during the Construction and Operation Phases.
10.5.72 The potential blockage of the view by the development
will be partial and from a distance of 3.5km making the perception of the scale
of the development small. The compatibility of the development with the
existing visual context will be fair given the proximity of other large scale
developments such as the Junk Bay Chinese Permanent Cemetery and new connecting
footpath and the TKO reclamation/town centre extension. The duration of the
impacts will be long and irreversible. Overall the magnitude of impact will be
Small during the Construction and Operational Phases.
10.5.73 Hikers along the Wilson Trail to Devil’s Peak and Chiu
Keng Wan Shan (TKO-REC2): These particular VSRs
medium in number, enjoy good quality existing views with partial visibility of
the project site due to intervening landform and development. Alternative views
are available. Views are of short duration and rare. Overall the assessment of
sensitivity for these VSRs is therefore Medium during the Construction and
Operation Phases.
10.5.74 The potential blockage of the view by the development
will be partial and from a distance of 1km making the perception of the scale
of the development medium. The compatibility of the development with the
existing visual context will be fair given the proximity of other large scale
developments such as the Junk Bay Chinese Permanent Cemetery and new connecting
footpath and the TKO reclamation/town centre extension, Area 77 Landfill, CDA1
and 2, and the TKO Industrial Estate. The duration of the impacts will be long
and irreversible. Overall the magnitude of impact will be Intermediate during
the Construction and Operational Phases.
10.5.75 Visitors of Lei Yue Mun Holiday Village, Lei Yue Mun
Park (TKO-REC3A) and Visitors of H.K.
Museum of Coastal Defence (TKO-REC3B): These
particular VSRs are medium in number, enjoy good quality existing views with
full visibility of the project site. Alternative views are available. However,
their views are of short duration and rare. Overall the assessment of
sensitivity for these VSRs is therefore Medium during the Construction and
Operation Phases.
10.5.76 The potential blockage of the view by the development
will be partial and from a distance of 2750m. making the perception of the
scale of the development small. The compatibility of the development with the
existing visual context will be good given the backdrop of the TKO urban area
and planned intent for new town extension. The duration of the impacts will be
long and irreversible. Overall the magnitude of impact will be Small during the Construction and Operational Phases.
10.5.77 Hikers along Pottinger Trail and Pottinger Peak (TKO-REC4), Hikers at Mount Collinson (TKO-REC5)
and Hikers at Mount
Parker (TKO-REC6): These particular
VSRs are medium in number, enjoy good quality existing views with full
visibility of the project site. Alternative views are available. However, their
views are of short duration and rare. Overall the assessment of sensitivity for
these VSRs is therefore Medium during the Construction and Operation Phases.
10.5.78 The potential blockage of view by the development will
be partial and from a distance of 4.5km to 5.5km making the perception of the
scale of the development small. The compatibility of the development with the
existing visual context will be good given the backdrop of the TKO urban area
and planned intent for new town extension. The duration of the impacts will be
long and irreversible. Overall the magnitude of impact will be Negligible during
the Construction and Operational Phases, primarily due to the distance of view.
10.5.79 Seaborne Leisure Travellers in Junk Bay (TKO-T1): Seaborne leisure travellers
are generally considered to be moderately sensitive to impacts on their view as
the attractiveness or otherwise of their outlook has some bearing on their
perceived quality of experience. These seaborne leisure travelers are medium in
number and the quality of their existing view is fair as it includes both a
waterfront of unremarkable urban development, and reclamation with limited
areas of natural coastline and a more attractive natural hill skyline behind. Alternative
views are available. Their frequency of view is of short duration and
occasional. Overall the sensitivity of these VSRs is therefore assessed as Medium
during the Construction and Operation Phases.
10.5.80 The potential blockage of the view by the development
will be partial and from a distance as little as 10m making the perception of
the scale of the development large. The compatibility of the development with
the existing visual context will be good given the backdrop of the TKO urban
area and planned intent for new town extension. The duration of the impacts
will be long and irreversible. Overall the magnitude of impact will be Large during the Construction and Operational Phases.
10.5.81 Seaborne Leisure Travellers along Lei Yue Mun and
Tathong Channel (TKO-T2): These
seaborne leisure travellers are many in number and the quality of their
existing view is fair as it includes both a waterfront of unremarkable urban
development, and reclamation with limited areas of natural coastline and a more
attractive natural hill skyline behind. Alternative views are available. Their
frequency of view is of short duration and occasional. Overall the sensitivity
of these VSRs is therefore assessed as Medium during the Construction and
Operation Phases.
10.5.82 The potential blockage of the view by the development
will be partial and from a distance of approximately 1.5km making the
perception of the scale of the development medium. The compatibility of the
development with the existing visual context will be good given the backdrop of
the TKO urban area and planned intent for new town extension. The duration of
the impacts will be long and irreversible. Overall the magnitude of impact will
be Intermediate during the Construction and Operational Phases.
10.5.83 Travellers along Wan Po Road (TKO-T3): these travellers are many in number and experience fair quality partial/glimpse views towards the project
site. Alternative views are available. The frequency of view is occasional and
of short duration. The overall sensitivity of these VSRs is assessed as Low.
10.5.84 The potential blockage of the view by the development
will be partial and from a distance of approximately 1.5km making the
perception of the scale of the development large. The compatibility of the
development with the existing visual context will be fair given the backdrop of the TKO urban area and planned
intent for new town extension. The duration of the impacts will be long and
irreversible. Overall the magnitude of impact will be Small during the
Construction and Operational Phases.
10.5.85 Travellers at TKO MTR Station and along Po Yap Road
and Chui Ling Road (TKO-T4): these travellers
are many in number and experience poor quality partial/glimpse views towards the project
site due to the planned developments on the TKO reclamation. Alternative views
are available. The frequency of view is occasional and of short duration. The
overall sensitivity of these VSRs is assessed as Low.
10.5.86 The potential blockage of the view by the development
will be partial and from a close distance (approximately 10m) making the
perception of the scale of the development large. The compatibility of the
development with the existing visual context will be fair given the existing
road layout and surrounding urban context of TKO and planned intent for new
town extension. The duration of the impacts will be long and irreversible.
Overall the magnitude of impact will be Large during the Construction Phase and Intermediate
during the Operational Phase.
10.5.87 Pedestrians on
footpath link from Ocean Shores to Junk Bay Chinese Permanent Cemetery (TKO-T5): the number of viewers is medium and they will experience
occasional, short, full views of the project site. Alternative views are
available. The quality of the existing
view is good across Junk Bay. Overall the sensitivity of this VSR will be
Medium.
10.5.88 The potential blockage of the view by the development
will be partial and from a close distance (the path crosses above the elevated
road in front of the tunnel portal) making the perception of the scale of the
development large. The compatibility of the development with the existing
visual context when viewed from the path will be poor given the existing clear
views across Junk Bay to the east and the natural hillside of the tunnel
portal. The duration of the impacts will be long and irreversible. Overall the
magnitude of impact will be Large during the Construction and Operational
Phases.
10.5.89 Travellers on new Southern Footbridge crossing Eastern
Channel (TKO-T7): these VSRs will be
medium in number and will experience good quality views across Junk Bay towards
the project site. Alternative views will be available. Views will be
occasional, full and of short duration. Overall sensitivity to change will be Medium given that
these VSRs are likely to be using bridge and footpath recreationally.
10.5.90 The potential blockage of the view by the development
will be partial and the distance of view will be 750m. The scale of development is large and the
change is irreversible. The compatibility with the visual context is fair given
the nature of the TKO reclamation and planned TKO town centre south extension
and the Junk Bay Chinese Permanent Cemetery. Due to the unobstructed views to
the development site, long duration of impacts and the permanence of the
development, overall the magnitude of visual impact for this VSR is assessed as
Large during the Construction and Operation Phases.
Planned future
VSRs in Tseung Kwan O
10.5.91 For the purposes of this assessment, it is assumed
that the future planned developments will be constructed after the completion
of the TKO-LT Tunnel. Assessment of sensitivity and magnitude of impact during
the Construction Phase is therefore not applicable.
10.5.92 Workers in planned TKO Industrial Estate Extension (TKO-OU1B): These workers will be
medium in number, enjoy good quality existing and alternative views with full
visibility of the proposed development site. Their views however will only be
occasional and of short duration. Overall the assessment of sensitivity for
this VSR is Low during the Operation Phase.
10.5.93 The potential blockage of the view by the development
will be partial and the viewing distance will be 1.5km. The compatibility of
the development with the visual context will be fair given the backdrop of TKO and
planned intent for new town extension and the Junk Bay Permanent Chinese
Cemetery. Due to the long duration of
impacts and the large scale of development, the overall magnitude of impact on
this planned VSR will be Large during the Operation Phase.
10.5.94 Users of planned recreational facilities at TKO Stage
I Landfill, Area 77 (TKO-REC7): These
users will be many in number, enjoy good quality views with full visibility
across Junk Bay. Alternative views will be available. Their views will also be occasional
and of medium duration. Overall the assessment of sensitivity for this VSR is
therefore Medium during the Operation Phase.
10.5.95 The potential blockage of the view by the development
will be partial and the distance of view will be 750m. The scale of development is large and the
change irreversible. The compatibility with the visual context is fair given
the nature of the TKO reclamation and TKO town centre south extension and the
Junk Bay Permanent Chinese Cemetery. Due to the unobstructed views to the
development site, long duration of impacts and the permanence of the
development, overall the magnitude of visual impact for this VSR is assessed as
Large during the Operation Phase.
Table
10.5.7 Lam Tin Visually Sensitive Receivers and their Sensitivity
VSR ID No. |
Key VSR |
No. of Viewers (Many, Medium, Few) |
Quality of Existing View (Good, Fair,
Poor) |
Availability of Alternative Views (Yes,
No) If Yes, Amenity Value of Alternative
View (Good, Fair, Poor) |
Degree of Visibility (Full, Partial,
Glimpse) |
Duration of View (Long, Medium, Short) |
Frequency of View ((Very
Frequent, Frequent, Occasional, Rare) |
Sensitivity to Change (Low, Medium,
High) |
|
|
Construction |
Operation |
|||||||
Existing VSRs in Lam Tin |
|||||||||
LT-C1 |
Workers
at Yau Tong Industrial Area |
Many |
Fair
|
Yes
(Poor) |
Partial
|
Short
|
Occasional
|
Low |
Low |
LT-C2 |
Office
workers in |
Many |
Good |
Yes
(Fair) |
Partial |
Medium |
Frequent |
Low |
Low |
LT-GIC1 |
Staff
and pupils of schools east of EHC |
Many |
Poor |
Yes
(Poor) |
Partial |
Medium |
Frequent |
Low |
Low |
LT-GIC2 |
Staff
and pupils of Schools and Government facilities at Rehab Path |
Many |
Poor |
Yes
(Poor) |
Nil |
N/A |
N/A |
Low |
Low |
LT-R3 |
Residents
of Ping Tin Estate and |
Many |
Good |
Yes
(Poor) |
Full |
Long |
Frequent |
High |
High |
LT-R4A |
Residents
of Yau Lai Estate |
Many |
Good |
Yes
(Fair) |
Full |
Long |
Frequent |
High |
High |
LT-R4B |
Residents
of Yau Tong Estate and |
Many |
Poor |
Yes
(Fair) |
Partial
|
Long |
Frequent |
Medium |
Medium |
LT- R5 |
Residents
in Yau Tong - The Canaryside and The Spectacle |
Many |
Good |
Yes (Fair) |
Partial |
Long |
Frequent |
High |
High |
LT- R6A |
Residents
at Sai Wan Ho (Lei King Wan, Grande
Promenade, Les Saisons) |
Many |
Good |
Yes (Good) |
Partial |
Long |
Frequent |
Medium |
Medium |
LT-R6B |
Residents
of Shau Kei Wan (Tung To Court, Tung Yuk Court, |
Many |
Good |
Yes (Good) |
Partial |
Long |
Frequent |
Medium |
Medium |
LT- R7 |
Residents
at Sai Wan Ho (Hing Tung Estate, |
Many |
Fair |
Yes (Fair) |
Partial |
Long |
Frequent |
Medium |
Medium |
LT-R8 |
Residents
at Tai Koo Shing |
Many |
Good |
Yes (Good) |
Partial |
Long |
Frequent |
Medium |
Medium |
LT-R9A |
Residents
at |
Many |
Fair |
Yes (Good) |
NIL |
N/A |
N/A |
Medium |
Medium |
LT-R9B* |
Residents
at Cha Kwo Ling housing developments west of interchange |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
LT-R10 |
Residents
at |
Many |
Fair |
Yes
(Good) |
NIL |
N/A |
N/A |
Medium |
Medium |
LT-R11 |
Residents
at Kwong Tin Estate and |
Many |
Good |
Yes
(Fair) |
Full |
Long |
Frequent |
High |
High |
LT-R12 |
Residents
at |
Many |
Good |
Yes
(Fair) |
NIL |
N/A |
N/A |
Medium |
Medium |
LT-R13 |
Residents
at |
Many |
Good |
Yes
(Fair) |
NIL |
N/A |
N/A |
Medium |
Medium |
LT-CDA1* |
Residents
of Yau Tong Bay CDA development |
Many |
Good |
Yes
(Good) |
Full |
Long |
Frequent |
High |
High |
LT-REC1A |
Hikers
along |
Medium
|
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC1B |
Hikers
along |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC2 |
Hikers
along Pottinger Trail and Pottinger |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT- REC3 |
Hikers
at |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC4 |
Hikers
at |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC5 |
Hikers
at |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC6 |
Hikers
at Braemar Hill Lookout |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT- REC7A |
Visitors
of Lei Yue Mun Fort ( |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT- REC7B |
Visitors
of Lei Yue Mun Observation Post ( |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT- REC8 |
Visitors
of |
Medium |
Good |
Yes
(Good) |
Partial |
Short |
Rare |
Medium |
Medium |
LT-REC9 |
Users
of Sai Tso Wan Recreation Ground and Tennis Courts |
Medium |
Poor |
No |
NIL |
N/A |
N/A |
Low |
Low |
LT-O1 |
Users
of |
Many |
Fair |
Yes
(Fair) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-O2 |
Users
of |
Many |
Good |
Yes
(Good) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-O3 |
Visitors
to |
Many |
Good |
Yes
(Good) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-O4 |
Visitors
of Sai Wan Ho |
Many |
Good |
Yes
(Good) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-O5* |
Users
of public open space on promenade |
Many |
Good |
Yes
(Good) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-O6* |
Users
of planned open space |
Many |
Good |
Yes
(Fair) |
Partial |
Medium |
Occasional |
Medium |
Medium |
LT-T1 |
Seaborne
Leisure Travellers along Lei Yue Mun
Channel |
Many |
Good |
Yes
(Good) |
Partial/ Glimpse |
Short |
Occasional |
Low |
Low |
LT-T2 |
Travellers
along |
Many |
Good |
Yes
(Good) |
Partial/ Glimpse |
Short |
Occasional |
Low |
Low |
LT-T3 |
Travellers
on Eastern Harbour Crossing approaches |
Many |
Poor |
No |
Partial/ Glimpse |
Short |
Occasional |
Low |
Low |
*VSRs in developments planned to be
completed before completion of TKO-LT Tunnel
Table 10.5.8 Lam
Tin Visually Sensitive Receivers and their Magnitude of Impact
VSR ID No. |
Key VSR |
Potential
Blockage of View (Full/ Partial
Glimpse) |
Minimum Viewing Distance (m) |
Scale of Development (Large/ Medium /Small) |
Compatibility
(Good/Fair/ /Poor) |
Duration of Impacts (Long/ Medium/ Short) |
Reversibility of
Change (Yes/No) |
Magnitude of
Impacts (Large/Intermediate/Small/ /Negligible) |
|||
|
|
|
|
|
|
Construction |
Operation |
|
Construction |
Operation |
|
Existing VSRs in
Lam Tin |
|||||||||||
LT-C1 |
Workers
at Yau Tong Industrial Area |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-C2 |
Office
workers in |
Partial |
2000m |
Small |
Fair |
Medium |
Long |
No |
Small |
Small |
|
LT-GIC1 |
Staff
and pupils of schools east of EHC |
Partial |
100m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
|
LT-GIC2 |
Staff
and pupils of Schools and Government facilities at Rehab Path |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-R3 |
Residents
of Ping Tin Estate and |
Partial |
300m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
|
LT-R4A |
Residents
of Yau Lai Estate |
Partial |
80m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
|
LT-R4B |
Residents
of Yau Tong Estate and |
Partial |
700m |
Medium |
Fair |
Medium |
Long |
No |
Small |
Small |
|
LT- R5 |
Residents
in Yau Tong - The Canaryside and The Spectacle |
Partial |
800m |
Medium |
Fair |
Medium |
Long |
No |
Small |
Small |
|
LT- R6A |
Residents
at Sai Wan Ho (Lei King Wan, Grand
Promenade, Les Saisons) |
Partial |
1500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-R6B |
Residents
of Shau Kei Wan (Tung To Court, Tung Yuk Court, |
Partial |
1600m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT- R7 |
Residents
at Sai Wan Ho (Hing Tung Estate, |
Partial |
2000m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT -R8 |
Residents
at Tai Koo Shing |
Partial |
1500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT -R9A |
Residents
at |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-R9B* |
Residents
at Cha Kwo Ling housing develop-ments west of inter-change |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
|
LT - R10 |
Residents
at |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-R11 |
Residents
at Kwong Tin Estate and |
Partial |
400m |
Large |
Fair |
Medium |
Long |
No |
Large |
Large |
|
LT-R12 |
Residents
at |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-R13 |
Residents
at |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-CDA1 * |
Residents
of Yau Tong Bay CDA development |
Partial |
200m |
Large |
Fair |
Long |
Long |
No |
Large |
Large |
|
LT-REC1A |
Hikers
along |
Partial |
750m |
Medium |
Fair |
Medium |
Long |
No |
Small |
Small |
|
LT-REC1B |
Hikers
along |
Partial |
1250m |
Medium |
Fair |
Medium |
Long |
No |
Small |
Small |
|
LT-REC2 |
Hikers
along Pottinger Trail and Pottinger |
Partial |
5000m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
|
LT- REC3 |
Hikers
at |
Partial |
5200m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
|
LT-REC4 |
Hikers
at |
Partial |
3500m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
|
LT-REC5 |
Hikers
at |
Partial |
4000m |
Small |
Good |
Medium |
Long |
No |
Negligible |
Negligible |
|
LT-REC6 |
Hikers
at Braemar Hill Lookout |
Partial |
2700m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-REC7A |
Visitors
of Lei Yue Mun Fort ( |
Partial |
2000m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT- REC7B |
Visitors
of Lei Yue Mun Observation Post ( |
Partial |
2000m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT- REC8 |
Visitors
of |
Partial |
2400m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-REC9 |
Users
of Sai Tso Wan Recreation Ground and Tennis Courts |
Nil |
N/A |
N/A |
N/A |
N/A |
N/A |
N/A |
Negligible |
Negligible |
|
LT-O1 |
Users
of |
Partial |
100m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
|
LT-O2 |
Users
of |
Partial |
1500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-O3 |
Visitors
to |
Partial |
1700m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-O4 |
Visitors
of Sai Wan Ho |
Partial |
1500m |
Small |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-O5* |
Users
of public open space on promenade |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
|
LT-O6* |
Users
of planned open space |
Partial |
50m |
Large |
Fair |
Medium |
Long |
No |
Intermediate |
Intermediate |
|
LT-T1 |
Seaborne
Leisure Travellers along Lei Yue Mun
Channel |
Partial |
100m |
Large |
Good |
Medium |
Long |
No |
Intermediate |
Intermediate |
|
LT-T2 |
Travellers
along |
Partial |
1400m |
Medium |
Good |
Medium |
Long |
No |
Small |
Small |
|
LT-T3 |
Travellers
on Eastern Harbour Crossing approaches |
Partial |
10m |
Large |
Good |
Medium |
Long |
No |
Intermediate |
Intermediate |
|
*VSRs in developments planned to be
completed before completion of TKO-LT Tunnel
Sensitivity and Magnitude
of Change for VSRs in Lam Tin
Existing VSRs
in Lam Tin
10.5.96 Workers in Yau Tong Industrial Area (LT-C1): Workers are generally
considered to be only moderately sensitive to impacts on their view as the
attractiveness or otherwise of their outlook has a relatively low effect on
their perceived quality of life. This VSR is many in
number and the quality of their existing view is fair with
visibility largely blocked by the proposed CDA development to the northwest (it is
anticipated that the CDA will have been constructed by the time the TKO-LT is
constructed). Alternative views are available. The overall assessment of sensitivity
for this VSR is Low during the Construction and Operation Phases.
10.5.97 The degree of visibility of the large permanent
development will be nil due to the CDA constructed to the north-west. Consequently,
the magnitude of impact for this VSR is assessed as Negligible during the
Construction and Operation Phases.
10.5.98 Office workers in Taikoo Place and One Island East (LT-C2): VSRS are many in number and
the quality of their existing view is good with partial visibility due to
intervening buildings and the ridge of land behind Cha Kwo Ling Village.
Alternative views are available. Their view is frequent and of medium duration.
The overall assessment of sensitivity for this VSR is Low during the
Construction and Operation Phases.
10.5.99 The potential blockage of the view by the development
will be partial and from a distance of 2km making the perception of the scale
of the development small. The compatibility of the development with the
existing visual context will be fair given the backdrop of the Lam Tin urban
area. The visual impacts will be irreversible and of long duration. Overall,
the magnitude of impact for this VSR is assessed as Small during the
Construction and Operation Phases.
10.5.100 Staff and pupils of schools east of EHC (LT-GIC1): Staff and
students of schools are generally considered to be only moderately sensitive to
impacts on their view as the attractiveness or otherwise of their outlook has a
relatively low effect on their perceived quality of life. These particular VSRs
are many in number and the quality of their existing view is poor although alternative
views to the west are available. Their views are frequent and partially
obstructed by the EHC advertising hoardings. Due to the partial nature of the
views and the nature of the building design which does not afford good views
out for staff or pupils, the overall sensitivity of this VSR is assessed as Low
during the Construction and Operation Phases.
10.5.101 The potential blockage of the view by the development
will be partial and from a distance of 100m. Due to this proximity the scale of
the development will be perceived as large. The compatibility of the
development with the existing visual context will be fair given the existing
EHC corridor and associated slip roads and buildings. The visual impacts will
be irreversible and of long duration. Overall, the magnitude of impact for this
VSR is assessed as Large during the Construction and Operation Phases.
10.5.102 Staff and pupils of School and Government facilities
at Rehab Path (LT-GIC2): Staff and pupils
are generally considered to be only moderately sensitive to impacts on their
view as the attractiveness or otherwise of their outlook has a relatively low
effect on their perceived quality of life. This VSR is many in number and has
poor existing views. However, due to the screening nature of the topography
between the facilities and the development, the degree of visibility will be
nil as will the duration and frequency of view. The overall sensitivity of this
VSR is assessed as Low during the Construction and Operation Phases.
10.5.103 As the degree of visibility will be nil, the magnitude
of impact for this VSR is therefore assessed as Negligible during the
Construction and Operation Phases.
10.5.104 Residents of Ping Tin Estate and Hong Ngar Court (LT-R3) and Yau Lai Estate (LT-R4A): Residents are generally considered to be
sensitive to changes in their views as the quality of the view affects their
perception of their home environment and quality of life. These VSRs are many
in number, enjoy good quality existing views with full visibility. Alternative
views are available. Their views are frequent and of long duration. The overall
sensitivity for this VSR is therefore assessed as High during the Construction
and Operation Phases.
10.5.105 The potential blockage of the view by the development
will be partial and from a close distance. These VSRs will have close (300m to
80m respectively) full views overlooking the permanent project development. The
compatibility of the development with the existing visual context will be fair
given the existing EHC corridor and associated infrastructure and the
industrial landscape of the Ex - Cha Kwo Ling Kaolin Mine Site. The visual
impacts will be irreversible and of long duration. The scale of the development
will be perceived as large due to the close elevated viewpoints. Overall, the
magnitude of impact for these VSRs is assessed as Large during the Construction
and Operation Phases.
10.5.106 Residents of Yau Tong Estate and Yau Mei Court (LT-R4B): These VSRs are many in
number and experience poor quality existing views. Views of the project site
are partially screened by the towers of the Yau Lai Estate (LT-R4A) and hence
the degree of visibility is partial. The overall sensitivity for these VSRs is
assessed as Medium during the Construction and Operation Phases.
10.5.107 As the degree of visibility will be partial, the
magnitude of impact for this VSR is therefore assessed as Small during the
Construction and Operation Phases. Residents
in Yau Tong – The Canaryside and The Spectacle (LT-R5): These VSRs are many in number, enjoy good quality elevated existing
views with partial visibility due to intervening buildings including those of LT-CDA1,
LT-GIC1 and LT-R4A. Alternative views are available. Their views are frequent
and of long duration. The overall sensitivity for these VSRs is assessed as High
during the Construction and Operation Phases.
10.5.108 The potential blockage of the view by the development
will be partial and these VSRs will have a relatively long viewing distance
(750 to 800m) with views partially screened by intervening buildings. The
compatibility of the development with the existing visual context will be fair
given the existing EHC corridor and associated infrastructure and the
industrial landscape of the Ex - Cha Kwo Ling Kaolin Mine Site. The visual
impacts will be irreversible and of long duration. The scale of the development
will be perceived as medium in scale due to the distance of viewpoint. Overall,
the magnitude of impact for this VSR is assessed as Small during the
Construction and Operation Phases.
10.5.109 Residents at Cha Kwo Ling Village (LT-R9A) and Residents at Fan
Wah Street (LT-R10): These VSRs are many
in number and experience fair existing views. These residential developments
are low rise and the degree of visibility of the proposed development is nil
due to the ridge of forested high ground forming the edge of the former ex-Cha
Kwo Ling Kaolin Mine Site which will completely screen the development from
view. Alternative views are available. The overall sensitivity for these VSRs is
therefore assessed as Medium during the Construction and Operation Phases.
10.5.110 In spite of their close distance to the proposed
development (100 to 500m), the development will not be visible to these VSRs
due to the screening ridge of land to the north of them. The magnitude of
impact for this VSR is therefore assessed as Negligible during the Construction
and Operation Phases.
10.5.111 Residents at Kwong Tin Estate and Hong Pak Court (LT-R11): Residents at Kwong Tin
Estate and Hong Pak Court are many in number and experience good quality views
towards the site. Alternative views are available to these VSRs. The degree of
visibility is full and as residents, their duration of the view towards the
site is long and frequent. The overall sensitivity to change for these
residents is assessed as High during the Construction and Operation Phases.
10.5.112 In spite of their close distance to the proposed
development (400m), the development will be only partially visible to these
VSRs. The scale of the development will be perceived as large due to the proximity
of view. The magnitude of impact for this VSR is therefore assessed as Large
during the Construction and Operation Phases.
10.5.113 Residents at Laguna City (LT-R12) and Residents at Sceneway
Garden (LT-R13): Residents at Laguna
City and residents at Sceneway Garden are many in number and currently
experience views of good quality. Alternative views are available to these
VSRs. The degree of visibility is nil due to the intervening elevated ground of
the ex-Cha Kwo Ling Quarry Site. The overall sensitivity to change for these
residents is considered to be Medium during the Construction and Operation
Phases.
10.5.114 The development will not be visible to these VSRs and
the magnitude of impact for this VSR is therefore assessed as Negligible during
the Construction and Operation Phases.
10.5.115 Residents at Sai Wan Ho (Lei King Wan, Grand
Promenade, Les Saisons) (LT-R6A), Residents
of Shau Kei Wan (Tung To Court, Tung
Yuk Court and Aldrich Bay) (LT-R6B), Residents
of Sai Wan Ho (Hing Tung Estate, Tung Hei Court, Tung Lam Court) (LT-R7) and Residents at Tai Koo Shing (LT-R8): These VSRs are many
in number and enjoy good quality existing views across Victoria Harbour (LT-R7
experiences fair views due to its greater distance and degree of obstruction
from surrounding buildings). All these VSRs experience only partial visibility
of the proposed development site because of surrounding developments on the
Hong Kong side and the screening effect of the high ground to the north west
of Cha Kwo Ling Village. Alternative
views are available. Their views are frequent and of long duration. The overall
sensitivity for these VSRs is assessed as Medium during the Construction and Operation
Phases.
10.5.116 The potential blockage of the view by the development
will be partial. These VSRs will have a long viewing distance (1.5 to 2.0km)
with views partially screened by intervening buildings and wooded ridge. From
this distance the scale of the development will be perceived as small. The
compatibility of the proposed development with the existing visual context is good
given the backdrop of the Lam Tin urban area to the north. The visual impacts
are irreversible and of long duration. The magnitude of impact for this VSR, is
assessed as Small during the Construction and Operation Phases.
10.5.117 Residents at Cha Kwo Ling housing developments west of
interchange (LT-R9B*): Future residents
of the planned housing developments on the Ex-Cha Kwo Ling Kaolin Mine Site
west of the Lam Tin Interchange will be many and will have full views over the site
due to their elevated location to the north west of the quarry. Views will be
frequent and the duration of views will be long. Alternative views will be
available. The sensitivity to change for
this planned VSR during the Construction and Operation Phases will be High.
10.5.118 The potential blockage of the view by the development
will be partial. VSRs will have a close viewing distance (50m worst case) from
where the scale of the development will appear large. The compatibility of the
Lam Tin Interchange with the existing visual context will be fair given the
existing EHC transport corridor character and the transitional character of the
Ex - Cha Kwo Ling Kaolin Mine Site. The visual impacts will be irreversible and
of long duration. The magnitude of impact during the Construction Phase and
Operation Phase will be Large.
10.5.119 Residents of Yau Tong Bay CDA development (LT-CDA1*): Residents of the completed
Yau Tong Bay CDA will be many and the upper floors will have good, full views of
the Lam Tin Interchange. Views will be frequent and the duration of views will
be long. Alternative views will be available.
The sensitivity to change for the VSR during the Construction and Operation
Phases will be High.
10.5.120 The potential blockage of the view by the development
will be partial. VSRs will have a close viewing distance (200m) from where the
scale of the development will appear large. The compatibility of the Lam Tin
Interchange with the existing visual context will be fair given the existing
EHC transport corridor character. The visual impacts will be irreversible and
of long duration. The magnitude of impact during both the Construction and
Operation Phases will be Large.
10.5.121 Hikers along Wilson Trail near Black Hill (LT-REC1A) and Hikers along Wilson
Trail at Devil’s Peak (LT-REC1B): Hikers
are generally considered to be moderately sensitive to changes in their views
as the quality of the view affects their perception of their leisure environment.
These particular VSRs are medium in number, enjoy good quality existing views
with partial visibility due to intervening tower blocks and development. Alternative
views are available. However, the frequency of their views is usually rare and
of short duration. The overall sensitivity for these VSRs is therefore assessed
as Medium during the Construction and Operation Phases.
10.5.122 The potential
blockage of the view by the development will be partial. These VSRs will have
an intermediate viewing distance (0.75km to 1.25km). From this distance the
scale of the development will be perceived as medium. The compatibility of the
proposed development with the existing visual context is fair given the
existing level of dense urban development in Lam Tin and the existing EHC
infrastructure corridor. The visual impacts will be irreversible and of long duration.
The magnitude of impact for this VSR is assessed as Small during the
Construction and Operation Phases.
10.5.123 Hikers along Pottinger Trail and Pottinger Peak (LT-REC2), Hikers at Mount Collinson (LT-REC3), Hikers at Mount
Parker (LT-REC4), Hikers at Mount Butler (LT-REC5): These particular VSRs are medium in number, enjoy good
quality existing views with partial visibility due to intervening development
on Hong Kong Island and the wooded ridge north of Cha Kwo Ling Village.
Alternative views are available. However, the frequency of their views is
usually rare and of short duration. The overall sensitivity for these VSRs is
assessed as Medium during the Construction and Operation Phases.
10.5.124 The potential blockage of the view by the development
will be partial. These VSRs will have a long viewing distance (3.5km to 5.0km).
From this distance the scale of the development will be perceived as small. The
compatibility of the proposed development with the existing visual context is
good given the backdrop of the Lam Tin urban area. The visual impacts will be
irreversible and of long duration. The magnitude of impact for this VSR given
the distance and partially obstructed view, is assessed as Negligible during
the Construction and Operation Phases.
10.5.125 Hikers at Braemar Hill Lookout (LT-REC6): These particular VSRs are medium in number, enjoy good
quality existing views with partial visibility due to intervening tower blocks
and the wooded ridge north of Cha Kwo Ling Village. Alternative views are
available. However, the frequency of their views is usually rare and of short
duration. The overall sensitivity for these VSRs is therefore assessed as
Medium during the Construction and Operation Phases.
10.5.126 The potential blockage of the view by the development
will be partial. These VSRs will have a closer viewing distance (2.7km) from which
the scale of the development will be perceived as small. The compatibility of
the proposed development with the existing visual context is good given the
backdrop of the Lam Tin urban area. The visual impacts will be irreversible and
of long duration. The magnitude of impact for this VSR given the distance and
partially obstructed view, is assessed as Small during the Construction and
Operation Phases.
10.5.127 Visitors of Lei Yue Mun Fort (H.K. Museum of Coastal
Defence) (LT-REC7A), Visitors of Lei Yue Mun Observation Post (H.K.
Museum of Coastal Defence) (LT-REC7B), Visitors
of Lei Yue Mun Holiday Village, Lei
Yue Mun Park (LT-REC8): Visitors of recreational facilities are
generally considered to be moderately sensitive to changes in their views as
the quality of the view affects the perception of their leisure environment and
quality of experience. These particular VSRs are medium in number, enjoy good quality
existing views with partial visibility primarily due to the obstruction of
existing buildings on the Lam Tin shoreline and the EHC complex. Alternative
views are available. The frequency of their views is rare and of short duration.
The overall sensitivity for these VSRs is therefore assessed as Medium during
the Construction and Operation Phases.
10.5.128 The potential blockage of the view by the development
will be partial. These VSRs will have a long viewing distance (2.0km to 2.4km).
From this distance the scale of the development will be perceived as small. The
compatibility of the proposed development with the existing visual context is
good given the backdrop of the Lam Tin urban area. The visual impacts will be
irreversible and of long duration. The magnitude of impact for this VSR given
the distance and partially obstructed view, is assessed as Small during the
Construction and Operation Phases.
10.5.129 Users of Sai Tso Wan Recreation Ground and Tennis
Courts (LT-REC9): This particular VSR group is medium in
number, and only experience existing views of the sports facilities within the
bounds of the surrounding tree screens. Alternative views are not available. The
degree of visibility of the proposed development site is nil due to the dense
peripheral tree screens. The overall sensitivity for these VSRs is therefore
assessed as Low during the Construction and Operation Phases.
10.5.130 In spite of their close proximity, the development
will not be visible to these VSRs due to the dense tree screen surrounding
them. The magnitude of impact for this VSR is therefore assessed as Negligible
during the Construction and Operation Phases.
10.5.131 Users of Yau Tong Road Playground (LT-O1): Visitors of open spaces are generally considered to be
moderately sensitive to changes in their views as the quality of the view
affects the perception of their leisure environment and quality of experience. LT-O1 VSRs are many in number, enjoy
fair quality existing views across to the wooded slopes of the development site
although visibility is only partial due to the screening effect of the open
space fencing and planting and the EHC advertising hoardings. Alternative views
are available. The frequency of their views is occasional and of medium duration.
The overall sensitivity for these VSRs is therefore assessed as Medium during
the Construction and Operation Phases.
10.5.132 The potential blockage of the view by the development
will be partial. These VSRs will have a short viewing distance (100m). From
this distance the scale of the development will be perceived as large. The
compatibility of the proposed development with the existing visual context is fair
given the existing EHC corridor in the foreground. The visual impacts will be
irreversible and of long duration. The magnitude of impact for this VSR given
the partially obstructed views and the separation by existing transport
infrastructure, is assessed as Intermediate during the
Construction and Operation Phases.
10.5.133 Users of Quarry Bay Park (LT-O2), Visitors to Aldrich
Bay Promenade (LT-O3), Visitors to Sai Wan Ho Harbour Park (LT-O4): These VSR groups are many in
number, enjoy fair to good quality existing views across the harbour although
visibility of the development site is only partial due to the screening effect
of buildings on the Lam Tin waterfront, the EHC, the ridge behind Cha Kwo Ling
Village and waterborne craft on the harbour. Alternative views are available.
The frequency of their views is occasional and of medium duration. The overall
sensitivity for these VSRs is assessed as Medium during the Construction and
Operation Phases.
10.5.134 The potential blockage of the view by the development
will be partial. These VSRs will have a long viewing distance (1.5 to 1.75 km).
From this distance the scale of the development will be perceived as small. The
compatibility of the proposed development with the existing visual context is
good given the backdrop of the urban area of Lam Tin. The visual impacts will
be irreversible and of long duration. The magnitude of impact for this VSR
given the partially obstructed views and the distance of view is assessed as
Small during the Construction and Operation Phases.
10.5.135 Users of public open space on promenade (LT-O5*): Users of the public open space
on the promenade will be many and will experience good but partial views of the
Lam Tin Interchange due to the screening provided by the ridge along the
southern edge of the quarry. Views will be occasional and the duration of views
will be medium. Alternative views will be available. The sensitivity to change for this planned
VSR during the Construction and Operation Phase will be Medium.
10.5.136 The potential blockage of the view by the development
will be partial. VSRs will have a close viewing distance (50m) from where the
scale of the development will appear large. The compatibility of the Lam Tin
Interchange with the existing visual context will be fair given the existing
EHC transport corridor character and the transitional character of the Ex - Cha
Kwo Ling Kaolin Mine Site. The visual impacts will be irreversible and of long
duration. The magnitude of impact implicated on the VSR will be Intermediate during
both the Construction and Operation Phases.
10.5.137 Users of planned open space north west of Lam Tin
Interchange (LT-O6*): Users of the
public open space north west of the Lam Tin Interchange on the ex-Cha Kwo Ling
Quarry Site will be many and will experience fair, partial views of the project
site because much of the interchange will be screened by the quarry walls and
lie below the line of site of the open space area. Views will be occasional and
the duration of views will be short. Alternative views will be available. The sensitivity to change for the VSR during the Construction Operation
Phase will be Medium.
10.5.138 The potential blockage of the view by the development
will be partial. VSRs will have a close viewing distance (50m) from where the scale of the
development will appear large. The compatibility of the Lam Tin Interchange with the
existing visual context will be fair given the existing EHC transport
corridor character and the
transitional character of the Ex - Cha Kwo
Ling Kaolin Mine Site. The visual impacts will be irreversible and of long
duration. The magnitude of impact during the Construction and Operation
Phases will be Intermediate.
10.5.139 Seaborne Leisure Travellers along Lei Yue Mun Channel (LT-T1), Travellers along Island
Eastern Corridor (LT-T2): Seaborne
and road travellers are generally considered to be only slightly sensitive to
impacts on their view as the attractiveness or otherwise of their outlook has a
relatively low effect on their perceived quality of experience and the view is
only fleeting. LT-T1 and LT-T2 are many in number, enjoy good quality existing
views across the harbour although visibility of the development site is only
partial/glimpse due to the screening effect of buildings on the Lam Tin
waterfront, the EHC and the ridge behind Cha Kwo Ling Village and in the case
of seaborne travellers, other craft in the foreground. Alternative views are
available. The frequency of their views is occasional and of short duration.
The overall sensitivity for these VSRs is assessed as Low during the
Construction and Operation Phases.
10.5.140 The potential blockage of the view by the development
will be partial due to the screening elements mentioned above. LT-T1 Seaborne
travelers will have a potentially close viewing distance (minimum 100m) from
where the scale of the development will appear large whereas the viewing
distance for LT-T2 will be greater (1.4km) from where the development will
appear medium. The compatibility of the proposed development with the existing
visual context is good given the backdrop of the urban area of Lam Tin. The
visual impacts will be irreversible and of long duration. The magnitude of
impact for LT-T1 will be Intermediate
during the Construction and Operation Phases given the transient, partially
obstructed views and the potentially close viewing distance. The magnitude of
impact for LT-T2 will be Small
during the Construction and Operation Phases given the transient, partially
obstructed views and its long viewing distance.
10.5.141 Travellers on Eastern Harbour Crossing approaches (LT-T3): This VSR group are many in
number and experience poor quality existing views to the site due to the low
elevation of the EHC road corridor. Visibility of the development site is only
partial/glimpse due to the screening effect of existing trees and advertising
hoardings. Alternative views are not available. The frequency of their views is
occasional and of short duration. The overall sensitivity for these VSRs is
assessed as Low during the Construction and Operation Phases.
10.5.142 The potential blockage of the view by the development
will be partial due to the screening elements mentioned above. This VSR will have a close viewing distance
(10m) from where the scale of the development will appear large. The
compatibility of the proposed development with the existing visual context is
good given the existing transport corridor character. The visual impacts will
be irreversible and of long duration. The magnitude of impact will be Intermediate
during the Construction and Operation Phases given the transient, partial
nature of the views.
10.6
Landscape Impact Assessment
Potential Sources of Landscape Impacts
10.6.1
The nature and
scope of the works have been described in Section 10.4 above. Sources of
landscape impacts during the Construction Phase are as follows:
·
TKO Interchange
with viaduct piers in sea waterbody and land reclamation for slip road landing;
·
TKO tunnel portal
construction with coastline impacts and major slope works;
·
Road P2 works
including landscape deck in front of Ocean Shores, footbridges and cycle tracks;
·
Lam Tin tunnel
portals and associated ventilation building in Ex - Cha Kwo Ling Kaolin Mine
Site;
·
Lam Tin
Interchange with major slope works, slip roads and noise enclosures;
·
Associated tunnel
buildings at Lam Tin;
·
Road improvements
along Cha Kwo Ling Road and junction with Yau Tong Road;
·
Modification of
link road from Lei Yue Mun Road to EHC;
·
The installation
of associated utilities;
·
Temporary site
areas, site offices, materials and plant;
·
Temporary barging
point at Lei Yue Mun Channel waterfront;
·
Temporary barging
point at Tseung Kwan O;
·
Temporary haul
roads at both TKO and Lam Tin sites;
·
Construction
traffic.
10.6.2
The nature and
scope of the works that will generate landscape impacts during the Operational
Phase are as follows:
·
TKO Interchange
with viaduct piers in sea waterbody and land reclamation for slip road landing;
·
TKO tunnel portal
construction with major slope works;
·
Road P2 works
including landscape deck in front of Ocean Shores, footbridges and cycletracks;
·
Lam Tin tunnel
portals and associated ventilation building in Ex - Cha Kwo Ling Kaolin Mine
Site;
·
Lam Tin
Interchange with major slope works, slip roads and noise enclosures;
·
Associated tunnel
buildings at Lam Tin;
·
Road improvements
along Cha Kwo Ling Road and junction with Yau Tong Road and Junction of Lei Yue
Mun Road and Yau Tong Road;
·
Modified link
road from Lei Yue Mun Road to EHC;
·
North Footbridge
and South footbridge at Road P2/D4.
Prediction of Significance of Landscape Impacts
10.6.3
The magnitude of
the impacts, before implementation of the mitigation measures on the landscape
resources and the landscape character areas that would occur in the Construction
Phase are tabulated below in Tables 10.6.1
and 10.6.2.
Table 10.6.1: Magnitude of Landscape
Impacts during the Construction & Operation Phase – Tseung Kwan O
ID No. |
Landscape Resources/ Landscape Character
Areas |
Source of Impact |
Description of Impacts |
Magnitude
of Impact |
TKO-LR1 |
Junk
Bay (Tseung Kwan O) Sea Waterbody |
TKO Interchange with viaduct piers in sea waterbody
and land reclamation for slip road landing plus temporary barging point |
49
no. piers; approx. 3.0ha of the 114ha area affected by reclamation plus 0.19ha
affected by temporary barging point |
Small |
TKO-LR2 |
Natural
Rocky Shore along Chiu Keng Wan Coastline |
TKO tunnel portal construction with coastline
impacts and major slope works plus temporary barging point access and
associated haul road along coastal edge |
Approx.
180m of the total 1102m of coastline affected |
Small |
TKO-LR3A |
Amenity
/ Roadside planting/ Vegetation on modified slopes at Chiu Keng Wan Shan |
None |
N/A |
Negligible |
TKO-LR3B |
Vegetation
on modified slopes at Tiu Keng Leng |
None |
N/A |
Negligible |
TKO-LR3C |
Amenity
/ roadside planting on modified slopes at Junk Bay Chinese Permanent Cemetery |
None |
N/A |
Negligible |
TKO-LR3D |
Amenity
/ roadside planting on modified slopes
along Road D4 (Po Yap Road and Chui Ling Road) and Road P2 (Po Shun Road) |
Road
P2 works including, footbridges and cycle tracks |
Approximately
75 no. trees will be felled or transplanted out of a total of 327 surveyed
trees |
Intermediate |
TKO-LR4 |
Mixed
Woodland Vegetation on hillside
areas at Chiu Keng Wan Shan |
None |
N/A |
Negligible |
TKO-LR5A |
Grassland/
shrubland mosaic at Chiu Keng Wan Shan |
TKO
tunnel portal construction and associated major slope works |
Approx.
3 ha of the total 63 ha affected (48 trees are proposed to be felled within
this affected area out of 191 surveyed) |
Small |
TKO-LR5B |
Grassland/
shrubland mosaic at Tiu Keng Leng |
None |
N/A |
Negligible |
TKO-LR6A |
Ponds
at Junk Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan |
None |
N/A |
Negligible |
TKO-LR6B |
Streams
at Junk Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan |
Temporary
haul route from temporary barging point |
Minor
impacts on lower reaches of 1 no. stream where it meets the coast |
Small |
TKO-LR7 |
Village
Trees within Chiu Keng Wan Shan |
None |
N/A |
Negligible |
TKO-LR8 |
Sandy
Shore along Chiu Keng Wan Shan Coastline |
None |
N/A |
Negligible |
TKO-LR9 |
Self-seeded
vegetation on TKO Reclamation |
None |
N/A |
Negligible |
TKO-LCA1 |
Junk
Bay Inshore Water Landscape |
TKO
Interchange with viaduct piers in sea waterbody and land reclamation for slip
road landing plus temporary barging point |
49
no. piers Out
of a total of 114 ha. approx. 3.0ha will be lost to permanent reclamation and
0.19 ha affected by temporary barging point. Approximately
5.9 ha will be affected by the permanent ‘footprint’ of the elevated
interchange |
Intermediate |
TKO-LCA2 |
Junk
Bay Chinese Permanent Cemetery Landscape |
None |
N/A |
Negligible |
TKO-LCA3 |
Chiu
Keng Wan Coastal Upland and Hillside
Landscape |
TKO tunnel
portal construction with coastline impacts and major slope works; the
installation of associated utilities; temporary site areas, site offices,
materials and plant; construction traffic. |
Approx.
2.8 ha affected out of a total area of 63 ha. A total of 48 trees will be
felled within this area out of 191 surveyed. |
Small |
TKO-LCA4 |
Mixed
Modern Comprehensive Urban Development Landscape |
Road
P2 works including footbridges and cycletracks; the installation of
associated utilities; temporary
site areas, site offices, materials and plant; construction traffic. |
Approx.
600m of road affected out of a total area of 48.9ha. Approximately 49 no.
trees will be felled or transplanted out of a total of 211 surveyed trees |
Small |
TKO-LCA5 |
Reclamation/On-
going Major Development Landscape at proposed Tseung Kwan O Town Centre
south |
Road
P2 works including landscape deck in front of Ocean Shores, footbridges and
cycletracks; the installation of associated utilities; temporary
site areas, site offices, materials and plant; construction traffic. |
Out
of a total LCA area of 49 ha, 9.7 ha will be impacted by the works.
Approximately 26 no. trees will be felled or transplanted out of a total of
116 surveyed trees |
Intermediate |
TKO-LCA6 |
Urban
Residential Landscape |
None |
N/A |
Negligible |
TKO-LCA7 |
Mau
Wu Shan Upland and Hillside Landscape |
None |
N/A |
Negligible |
Table
10.6.2: Magnitude of Landscape Impacts during the Construction and Operation Phase
– Lam Tin
ID
No. |
Landscape
Resources/ Landscape Character Areas |
Source
of Impact |
Description
of Impacts |
Magnitude
of Impact |
LT-
LR1 |
Lei
Yue Mun Channel Sea Waterbody |
Temporary
Barging Point at waterfront |
Approximately
1,500 sq.m out of a total of 68ha within the assessment boundary. |
Negligible |
LT-
LR2 |
Trees
within Yau Tong Bay Industrial Waterfront Area |
Road
improvements along Cha Kwo Ling Road and junction with Yau Tong Road |
Out
of an estimated total of 61 trees, approximately 14 no. trees will be felled. |
Small |
LT-LR3 |
Mixed
Woodland Vegetation on Hillside Areas |
None |
N/A |
Negligible |
LT-LR4 |
Pond
at Cha Kwo Ling |
None |
N/A |
Negligible |
LT-LR5 |
Natural
Watercourse |
None |
N/A |
Negligible |
LT-LR6 |
Grass
sports pitch within Sai Tso Wan Recreation Ground |
None |
N/A |
Negligible |
LT-LR7 |
Village
trees within Cha Kwo Ling residential area |
None |
N/A |
Negligible |
LT-LR8A |
Amenity
Roadside Planting/Vegetation on Modified Slopes at Sai Tso Wan |
None |
N/A |
Negligible |
LT-LR8B |
Amenity
Roadside Planting/Vegetation on Modified Slopes at Former Quarry |
Lam
Tin tunnel portals and associated ventilation building and tunnel buildings
in Ex - Cha Kwo Ling Kaolin Mine Site; Lam Tin Interchange with major slope
works, slip roads and noise enclosures. |
Out
of a total of approximately 2,835 surveyed trees, approximately 960 trees
will be impacted. |
Large |
LT-LR9A |
Grassland/Shrubland
mosaic on Ng Kwai Shan |
None |
N/A |
Negligible |
LT-LR9B |
Grassland/Shrubland
mosaic at Cha Kwo Ling |
Lam
Tin Interchange with major slope works, slip roads and noise enclosures. |
Only
12 no. trees will be impacted along the edge of the LR which has a total area
of in an area of approximately 6ha |
Small |
LT-
LCA1 |
Lei
Yue Mun Channel Inshore Water Landscape |
Temporary
barging point at Lei Yue Mun Channel waterfront; Temporary
site areas, site offices, materials and plant; Construction
traffic. |
Temporary
pier or pontoon, approx. 0.15ha out of a total area of 68ha. |
Negligible |
LT-LCA2 |
Yau
Tong Bay Coastal Industrial Urban Landscape |
Road
improvements along Cha Kwo Ling Road and junction with Yau Tong Road; temporary
barging point at Lei Yue Mun Channel waterfront; construction traffic. |
Approx.
0.1ha (1,000 sq.m) out of a total area of 19.9ha. |
Small |
LT-LCA3 |
Lam
Tin Upland and Hillside Landscape |
None |
N/A |
Negligible |
LT-LCA4 |
Miscellaneous Urban Fringe Landscape |
None |
N/A |
Negligible |
LT-LCA5 |
Urban
Recreational Landscape |
None |
N/A |
Negligible |
LT-LCA6 |
Urban
Transport Corridor |
Road
improvements along Cha Kwo Ling Road and junction with Yau Tong Road and
Junction of Lei Yue Mun Road and Yau Tong Road; Modified
link road from Lei Yue Mun Road to EHC. |
Minor
reconfiguration of road layout. Approximately 112 trees out of 266 surveyed
will be felled. |
Small |
LT-
LCA7 |
Lam
Tin Residential Urban Landscape |
Road
improvements along Cha Kwo Ling Road and junction with Yau Tong Road and
Junction of Lei Yue Mun Road and Yau Tong Road. |
Approximately 30ha out of a
total area of 90ha will be impacted and approximately 48 streets trees out of a total
of 191 surveyed trees will be affected |
Small |
LT-LCA8 |
Former
Quarry Landscape – Abandoned |
Lam
Tin Interchange with major slope works, slip roads and noise enclosures. |
Approximately 0.6ha will be impacted due to slope works out of a total area of
approximately 13.5ha and approx. 50 trees out of 51 trees surveyed will be affected. |
Small |
LT-LCA9 |
Former
Quarry Landscape – Occupied |
Lam
Tin tunnel portals and associated ventilation buildings; major
slope works, slip roads and noise enclosures; the installation of associated
utilities; temporary
site areas, site offices, materials and plant; temporary construction
traffic; permanent interchange traffic. |
Total
alteration of existing conditions to form Lam Tin Interchange. Approximately
960 trees will be felled out of 2835 surveyed. |
Large |
Nature and
Magnitude of Landscape Impacts before Mitigation during the Construction and
Operation Phases
10.6.4
The potential
significance of the landscape impacts during the Construction and Operation
Phases before the implementation of mitigation measures are tabulated in Tables 10.6.3 and 10.6.4 below.
Landscape Impacts at TKO
10.6.5
Junk Bay (Tseung Kwan O) Sea
Water body (TKO-LR1) has a
High sensitivity as it is a valuable landscape resource contributing to the
unique waterfront setting of TKO. The magnitude of impact caused by the
construction of the interchange and reclamation is Small given the overall size
of Junk Bay (3ha is affected out of an an approximate total area of 114ha). The
resulting significance of impact before mitigation is therefore Moderate.
10.6.6
Natural
Rocky Shore along Chiu Keng Wan Coastline (TKO-LR2)
has a High
sensitivity as it is a relatively rare resource within the
locality (due to the high proportion of reclamation coast within Junk Bay). The
magnitude of
impact caused by the construction of the temporary barging
point and haul road for access during the Construction Phase is small (approximately
180m of the total 1102m of coastline affected). The resulting significance of impact before
mitigation is therefore Moderate.
10.6.7
Amenity / roadside planting on modified slopes along Road D4 (Po Yap
Road and Chui Ling Road) (TKO-LR3D) has a Medium sensitivity as it is a common local
resource that can easily be reinstated. The magnitude of impact caused by the loss of
roadside tree planting along Road D4 and P2 works including construction of footbridges and
cycle tracks is Intermediate (approximately 75 no. trees will
be felled or transplanted out of a total of 327 surveyed trees). The resulting significance
of impact before mitigation is therefore Moderate.
10.6.8
Grassland/shrubland
mosaic at Chiu Keng Wan Shan stretching to the north and east (TKO-LR5A) has a Medium sensitivity due
to its common species composition and secondary nature. The magnitude of impact caused
by the construction of the TKO tunnel portal and associated major slope works is
Small (approx. 3 ha of the total 63ha are affected and 48 trees are proposed to
be felled within the affected area out of 191 surveyed). The resulting
significance of impact before mitigation is therefore Moderate.
10.6.9
Streams at Junk
Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan (TKO-LR6B) have a High sensitivity as they are rare and few in
number within the study area and cannot be easily recreated. The magnitude of impact caused
by the temporary haul route from the temporary barging point is Small (there
will be minor impacts on the lower reaches of 1 no. stream where it meets the
coast). The resulting significance of impact before mitigation is therefore Moderate.
10.6.10
Amenity/
roadside planting/ vegetation on
modified slopes at Chiu Keng Wan Shan
(TKO-LR3A), Vegetation on modified slopes at Tiu Keng Leng (TKO-LR3B),
Amenity/roadside planting on modified slopes at Junk Bay Chinese
Permanent Cemetery (TKO-LR3C), Mixed
woodland vegetation on hillside areas at Chiu Keng Wan Shan (TKO-LR4), Grassland/shrubland mosaic
at Tiu Keng Leng (TKO-LR5B), Ponds at Junk
Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan (TKO-LR6A) and Village Trees
within Chiu Keng Wan Shan (TKO-LR7) have Medium sensitivity as they are common local resources that
can easily be reinstated and are
reasonably tolerant of change. Natural Sandy Shore along Chiu Keng Wan Shan
Coastline (TKO-LR8) has a High
sensitivity as it is a rare resource in this locality and cannot be replicated.
Self-seeded planting on TKO Reclamation (TKO-LR9)
has a Low sensitivity due to its
common species composition and incidental nature. The magnitude of impact is Negligible as the
construction works cause no impact to these resources. The resulting significance
of impact of these resources before mitigation is therefore Insubstantial.
10.6.11 Junk Bay Inshore Water Landscape (TKO-LCA1) has a High sensitivity as it provides the bayside context of the TKO and has
a unique flat and open characteristic which cannot be easily recreated. The
magnitude of impact caused by the TKO Interchange with viaduct piers and land reclamation for
slip road landing and temporary barging point is Intermediate (out of a total
of 114ha, only approximately 3.0ha will be permanent reclamation and approximately
0.19ha will be affected by the permanent footprint of the elevated interchange).
However, the overall impact to the LCA is perceived as greater than the
physically impacted area due to the volume of the viaduct structure supported
by the piers, hence the evaluation of Intermediate impact). The resulting
significance of impact before mitigation is therefore Substantial.
10.6.12 Chiu Keng Wan Coastal Upland and Hillside Landscape (TKO-LCA3) has a High sensitivity as it
is a remnant of the original Junk Bay Landscape and provides a green backdrop
to the dense built up area of TKO. The magnitude of impact caused by the TKO tunnel portal construction with slope
works and minor coastline impacts is Small
(approx. 2.8ha will be affected out of a total area of 63 ha and a total of 48
trees impacted within this area of 191 surveyed.) The resulting significance of impact before
mitigation is therefore Moderate.
10.6.13 Mixed Modern Comprehensive Urban Development Landscape
(TKO-LCA4) has a Medium sensitivity
as it is a common local landscape character type with no unique attributes. The
magnitude of
impact caused by the construction of Road P2 works and associated footbridges
and facilities is Small (approximately 600m of road are affected within the total character area of 48.9ha and approximately 49 trees are impacted
out of a total of 211 surveyed). The resulting significance
of impact of these landscape characters before mitigation is
therefore Moderate.
10.6.14 Reclamation/On- going Major Development Landscape at
proposed Tseung Kwan O Town Centre South (TKO-LCA5)
has a Low sensitivity due to its undeveloped transitional nature and planned
designation for development. The magnitude of impact
caused by the construction of road works and associated
footbridges and cycle tracks on the reclamation is Intermediate (9.7ha will be
impacted by the works out of a total area of 49ha and approximately 26 trees will be affected
out of a total of 116 surveyed trees). The resulting significance of impact before
mitigation is therefore Moderate.
10.6.15
Junk Bay
Chinese Permanent Cemetery Landscape (TKO-LCA2),
Residential Urban Landscape (TKO-LCA6)
and Mau Wu Shan Upland and
Hillside Landscape (TKO-LCA7) have a
Medium sensitivity as they are common local landscape character types with no
intrinsic or unique value. The magnitude of impact is negligible as the construction works cause no impact
to these Landscape Character Areas. The resulting significance of impact of these landscape
characters
before mitigation is therefore Insubstantial.
Landscape
Impacts at Lam Tin
10.6.16 Amenity Roadside Planting/Vegetation on Modified
Slopes at Former Quarry (LT-LR8B) has
a High sensitivity
due to its mature nature and the greening value it provides for the quarry. The
magnitude of impact caused by the construction of the Lam Tin
Interchange within the Ex - Cha Kwo Ling Kaolin Mine Site is Large (approximately 960
trees will be impacted out of a total of approximately 2835 surveyed trees).
The resulting significance of impact before mitigation is therefore
Substantial.
10.6.17 Grassland/Shrubland Mosaic at Cha Kwo Ling (LT-LR9B) has Medium sensitivity due to its
common species composition. The magnitude of impact caused by slope
works within the Ex
- Cha Kwo Ling Kaolin Mine Site is Small (only 12 no. trees will be impacted
along the edge of the LR which has a total area of in an area of approximately
6ha). The
resulting significance of impact before mitigation is therefore
Slight.
10.6.18 Trees within Yau Tong Bay Industrial Waterfront Area (LT-LR2) have a Medium sensitivity
given their poor quality and their general low amenity value. The magnitude of impact
caused by road
improvements along Cha Kwo Ling Road and junction with Yau Tong Road is Small
(approximately 14 no. trees affected out of a an estimated total of 61 trees
from the Yau Tong Bay waterfront area). The resulting significance
of impact before mitigation is therefore Slight.
10.6.19 Lei Yue Mun Channel Sea Waterbody (LT-LR1), Natural Watercourse (LT-LR5), Village Trees within Cha Kwo Ling Residential Area (LT-LR7) and Amenity Roadside planting/Vegetation
on modified slopes at Sai Tso Wan (LT-LR8A) all have High sensitivity and
a Negligible magnitude of impact. The resulting significance of impact before
mitigation is Insubstantial.
10.6.20
Mixed
Woodland Vegetation on Hillside Areas (LT-LR3),
Pond at Cha Kwo Ling (LT-LR4) and Grassland/Shrubland Mosaic
on Ng Kwai Shan (LT-LR9A) have a Medium sensitivity due to its common
local species and low ecological value. Grass sports pitch within Sai Tso Wan
Recreational Ground (LT-LR6) has a Low
sensitivity as it is common, commercially available grass species that can be
easily reinstated. However, the magnitude of impact of all of these Landscape
Resources is Negligible as the construction works cause no impact to these resources. The resulting significance
of impact of these Landscape Resources before mitigation is therefore Insubstantial.
10.6.21 Former Quarry Landscape – Occupied (LT-LCA9) has Medium sensitivity as a large portion
(approximately 40%) of it is access road or hard standing and it is
occupied by temporary land uses which are reasonably able to tolerate change. The magnitude of impact caused
by Lam Tin Interchange and Tunnel Portal will be Large due to the total
alteration of existing conditions by the construction of the Lam Tin Interchange
(approximately 960 trees will be affected out of 2835 surveyed). The resulting
significance of impact before mitigation is therefore Substantial.
10.6.22
Lam Tin
Residential Urban Landscape (LT-LCA7) has
a Medium sensitivity as it is a common, unremarkable landscape type and largely
tolerant to change. The magnitude of impact
caused by the road modification works to the EHC transport
corridor is Small (approximately 30ha out of a total area of 90ha will be impacted and approximately 48 streets trees out of a total of 191
surveyed trees will be affected). The
resulting significance of impact of this Landscape Character Area before mitigation is
therefore Moderate.
10.6.23 Former Quarry Landscape – Abandoned (LT-LCA8) has a Low sensitivity due to
its abandoned state and incidental vegetation coverage comprising common
species. The magnitude of impact
caused by the
construction of the Lam Tin Interchange will be Small (approximately 0.6ha will
be impacted due to slope works out of a total area of approximately 13.5ha and
approx. 50 trees out of 51 trees surveyed will be affected). The resulting significance of impact of this Landscape
Character Area before mitigation is
therefore Slight.
10.6.24 Urban Transport Corridor (LT-LCA6) has a Low sensitivity due to its generally low visual
quality. The magnitude
of impact caused by the
road modification works to the EHC transport corridor is Small (minor
reconfiguration of road layout and impacts to approximately 112 street trees
out of a total of 266 surveyed trees). The resulting significance
of impact before mitigation is therefore Slight.
10.6.25 Yau Tong Bay Coastal Industrial Urban Landscape (LT-LCA2) has a Low sensitivity given
the current derelict condition and the planning intent to redevelop it. The magnitude of impact caused by the
construction of access for a temporary barging point and minor road
realignments is Small (approximately 0.1ha will be affected out of a total area
of 19.9ha). The resulting significance
of impact before mitigation is therefore Slight.
10.6.26
Lei Yue
Mun Channel Inshore Water Landscape (LT-LCA1) has a high
sensitivity due to its unique physical characteristics, historical and cultural
context. Lam Tin Upland and Hillside Landscape (LT-LCA3), Miscellaneous Urban Fringe
Landscape (LT-LCA4) and Urban Recreational Landscape (LT-LCA5) have a Medium sensitivity as they are largely tolerant to
change. The magnitude
of impact is Negligible as the construction works cause no impact to these Landscape Character
Areas. The
resulting significance of impact before mitigation is therefore Insubstantial.
Table 10.6.3: Significance of Landscape Impacts in
the Construction and Operation Phases - Tseung Kwan O
ID
No. |
Landscape
Resources / Landscape Character |
Sensitivity (Low, Medium, High) |
Magnitude
of Impact (Negligible, Small, Intermediate, Large) |
Impact
Significance Threshold BEFORE Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended
Mitigation Measures |
Residual
Impact Significance Threshold AFTER Mitigation (Insubstantial, Slight,
Moderate, Substantial) |
||
Construction |
Operation |
|||||||
DAY
1 |
YEAR
10 |
|||||||
TKO-LR1 |
|
High |
Small |
Moderate |
CM1,
2, 11,12 OM4 |
Moderate |
Slight |
Slight |
TKO- LR2 |
Natural Rocky Shore along Chiu
Keng Wan Coastline |
High |
Small |
Moderate |
CM1
|
Moderate |
Slight |
Slight |
TKO-LR3A |
Amenity
/Roadside planting /Vegetation on modified slopes at Chiu Keng Wan Shan |
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LR3B |
Vegetation
on modified slopes at Tiu Keng Leng |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
|
TKO-LR3C |
Amenity
/Roadside planting on modified slopes at |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LR3D |
Amenity
/Roadside planting on modified slopes along
Road D4 ( |
Medium |
Intermediate |
Moderate |
CM1,
2, 3,4,5 OM1,8 |
Moderate |
Moderate |
Slight |
TKO-LR4 |
Mixed
Woodland Vegetation on hillside areas at Chiu Keng Wan Shan |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO- LR5A |
Grassland/
shrubland mosaic at Chiu Keng Wan Shan |
Medium |
Small |
Moderate |
CM1,
2, 3,7 OM1,3 |
Moderate
|
Slight |
Slight
|
TKO-LR5B |
Grassland/
shrubland mosaic at Tiu Keng Leng |
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LR6A |
Ponds
at |
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LR6B |
Streams
at |
High |
Small |
Moderate |
CM1,2,11 OM1,
OM3 |
Moderate |
Slight |
Insubstantial |
TKO-LR7 |
Village
Trees within Chiu Keng Wan Shan |
High |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO- LR8 |
|
High |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LR9 |
Self-seeded
vegetation on TKO Reclamation |
Low |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LCA1 |
Junk
Bay Inshore Water Landscape |
High |
Intermediate |
Substantial |
CM1,
2, 8, 11,12 OM4,
5, 6, 7,8 |
Substantial |
Moderate |
Moderate |
TKO-LCA2 |
|
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LCA3 |
Chiu
Keng Wan Coastal |
High |
Small |
Moderate |
CM1,3,4,
7,11 OM1,2,3,4,5,6,7,8 |
Moderate |
Moderate |
Slight |
TKO- LCA4 |
Mixed
Modern Comprehensive Urban Development Landscape |
Medium |
Small |
Moderate |
CM1,3,4,
7,11 OM1,2,3,4,5,6,7,8 |
Moderate |
Slight |
Insubstantial |
TKO- LCA5 |
Reclamation/Ongoing
Major Development Landscape at proposed Tseung Kwan O Town Centre south |
Low |
Intermediate |
Moderate |
CM1,2,3,4,5,6,7,9,10,11,
12 OM1,2,3,4,5,6,7,8 |
Moderate |
Slight |
Insubstantial |
TKO-LCA6 |
Urban
Residential Landscape |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
TKO-LCA7 |
Mau
Wu Shan |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
Table 10.6.4: Significance of Landscape Impacts in the Construction
and Operation Phases - Lam Tin
ID No. |
Landscape Resources / Landscape
Characters |
Sensitivity (Low, Medium, High) |
Magnitude of Impact (Negligible, Small,
Intermediate, Large) |
Impact Significance Threshold BEFORE
Mitigation (Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual Impact Significance Threshold
AFTER Mitigation (Insubstantial, Slight, Moderate, Substantial) |
||
Construction |
Operation |
|||||||
DAY 1 |
YEAR 10 |
|||||||
LT-LR1 |
|
High |
Negligible |
Insubstantial |
CM1,11 |
Insubstantial |
Insubstantial |
Insubstantial |
LT- LR2 |
Trees
within |
Medium |
Small |
Slight |
CM1,
4, 5 OM1 |
Slight |
Slight |
Insubstantial |
LT-LR3 |
Mixed
Woodland Vegetation on |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR4 |
Pond
at Cha Kwo Ling |
Medium |
Negligible |
Insubstantial |
CM1,11 |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR5 |
Natural
Watercourse |
High |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
LT- LR6 |
Grass
Sports Pitch within Sai Tso Wan Recreation Ground |
Low |
Negligible |
Insubstantial |
CM1,4 |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR7 |
Village
Trees Within Cha Kwo Ling Residential Area |
High |
Negligible |
Insubstantial |
CM1,4 |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR8A |
Amenity/Roadside
planting/Vegetation on Modified Slopes
at Sai Tso Wan |
High |
Negligible |
Insubstantial |
CM1,4 |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR8B |
Amenity/Roadside
planting/Vegetation on Modified Slopes at Former Quarry |
High |
Large |
Substantial |
CM1,3,4,
7, OM1,2,3,7,8 |
Substantial |
Substantial |
Moderate |
LT-LR9A |
Grassland/ Shrubland
Mosaic on Ng Kwai Shan |
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LR9B |
Grassland/
Shrubland Mosaic at Cha Kwo Ling |
Medium |
Small |
Slight |
CM1,3,4,
7 OM1,3 |
Slight |
Slight |
Insubstantial |
LT- LCA1 |
Lei
Yue Mun Channel Inshore Water Landscape |
High |
Negligible |
Insubstantial |
CM1, 2, 11 |
Insubstantial |
Insubstantial |
Insubstantial |
LT- LCA2 |
|
Low |
Small |
Slight |
CM1,
2, 4, 5 OM1 |
Slight |
Insubstantial |
Insubstantial |
LT- LCA3 |
Lam
Tin Upland and |
Medium |
Negligible |
Insubstantial |
Not Required |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LCA4 |
Miscellaneous Urban Fringe Landscape |
Medium |
Negligible |
Insubstantial |
CM1,
4 OM1,
2 |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LCA5 |
Urban
Recreational Landscape |
Medium |
Negligible |
Insubstantial |
Not
Required |
Insubstantial |
Insubstantial |
Insubstantial |
LT-LCA6 |
Urban
Transport Corridor |
Low |
Small |
Slight |
CM1,
2, 4, 5, 6, 9 OM1,
2, 3,4,5,6,8 |
Slight |
Insubstantial |
Insubstantial |
LT-LCA7 |
Lam
Tin Residential Urban Landscape |
Medium |
Small |
Moderate |
CM1,
2, 4, 5, 6, 9 OM1, 2, 3,4,5,6,8 |
Slight |
Slight |
Insubstantial |
LT-LCA8 |
Former
Quarry Landscape – Abandoned |
Low |
Small |
Slight |
CM1,3,4,
7,11 OM1,3 |
Slight |
Slight |
Insubstantial |
LT-LCA9 |
Former
Quarry Landscape – Occupied |
Medium |
Large |
Substantial |
CM1,3,4,
7,8,11 OM1,3,4,5,6,7,8 |
Substantial |
Moderate |
Slight |
Potential Sources of Visual Impacts
10.7.1
The nature and
scope of the works have been described in Section 10.4.3 above. Sources of
visual impacts during the Construction Phase and are listed below:
·
TKO Interchange
with viaduct piers in sea waterbody and land reclamation for slip road landing;
·
TKO tunnel portal
construction with major slope works;
·
Temporary haul
road and barging point for removal of excavated slope and tunnel debris at the
base of the tunnel portal.
·
Road P2 works
including landscape deck in front of Ocean Shores, footbridges and cycle
tracks;
·
Lam Tin tunnel
portals and associated ventilation building in Ex-Cha Kwo Ling Kaolin Mine Site;
·
Lam Tin
Interchange with major slope works, slip roads and noise enclosures;
·
Associated tunnel
buildings at Lam Tin;
·
Road improvements
along Cha Kwo Ling Road and junction with Yau Tong Road;
·
The installation
of associated utilities;
·
Temporary site
areas, site offices, materials, plant and hoardings;
·
Temporary
waterfront barging point and elevated conveyor for removal of excavated tunnel
and site formation debris.
·
Sea and land
construction traffic including lorries and barges;
·
Night time
construction lighting;
·
Temporary road
works;
·
Dust and
construction debris.
10.7.2
Sources of visual
impacts during the Operation Phase are as follows:
·
TKO Interchange
with viaduct piers in sea waterbody and land reclamation for slip road landing;
·
TKO tunnel portal
construction with major slope works;
·
Road P2 works
including landscape deck in front of Ocean Shores, footbridges and cycletracks;
·
Lam Tin tunnel
portals and associated ventilation building in Ex-Cha Kwo Ling Kaolin Mine Site;
·
Lam Tin
Interchange with major slope works, slip roads and noise enclosures;
·
Associated tunnel
buildings at Lam Tin;
·
Road improvements
along Cha Kwo Ling Road and junction with Yau Tong Road and Junction of Lei Yue
Mun Road and Yau Tong Road;
·
Increased road
traffic;
·
Road and
architectural lighting
Nature and Magnitude of Visual Impacts before
Mitigation during the Construction and Operation Phases
10.7.3
The significance
of the visual impacts on VSRs before the implementation of mitigation measures
during the Construction and Operation Phases are assessed in Tables 10.7.1 for TKO and Table 10.7.2 for Lam Tin below.
Photomontages illustrating the permanent works before the implementation of
mitigation measures are provided in Figure
No.s 10.8.5.1 to 10.8.5.13 and 10.8.7.1 to 10.8.7.9 (Note: Photomontage viewpoints and mitigation measures
are described in more detail in Section 8).
10.7.4
For the purposes
of this assessment, based on the latest available programme information it is
assumed that planned developments will largely be constructed before the
completion of the TKO-LT Tunnel (the exceptions being TKO-OU1B and TKO-REC7).
Significance
of Visual Impacts before Mitigation during the Construction and Operation
Phases - Existing VSRs in Tseung Kwan O
10.7.5
Existing Residents
and workers in TKO Area 86 Comprehensive Development Area/LOHAS Park (TKO-CDA1A) have a Medium sensitivity
and will experience a Small magnitude of impact during the Construction and
Operation Stage due largely to the visual obstruction of the tower blocks of CDA1B
to the west. This will result in Slight/Moderate visual impacts during the Construction Phase and
Operation Phases before the
implementation of mitigation measures.
10.7.6
Residents in
planned new Residential Development at CDA in Area 86/LOHAS Park (TKO-CDA1B) have a High sensitivity and will experience a Large
magnitude of impact during the Construction and Operation Stage due to their unobstructed
views to the west. This will result in Substantial
visual impacts during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.7
The receptor
sensitivity of workers in TKO Sewage Treatment Works, Area 85 (TKO-GIC1) is Low and the magnitude of
impact is Negligible due to visual obstruction by CDA1A and CDA1B. This VSR
group will therefore experience Insubstantial
visual impacts during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.8
TKO-GIC2: The receptor sensitivity of staff and students at
the TKO Methodist Primary School and Evangelical College will be Low and the
magnitude of impact will be Small during the Construction and Operation Phases due largely to the planned residential areas which
will obstruct views of the project site. This VSR group will therefore
experience Slight visual impacts
during the Construction Phase and Operation Phases before the implementation of mitigation measures.
10.7.9
TKO-GIC4: The receptor sensitivity for Staff and Students at
the Hong Kong Design Institute Campus is Low and the magnitude of impact will
be Intermediate during the Construction and Operation Phases as views of much
of the proposed development will be obstructed by planned G/IC, Open Space and
Residential development to the south. This VSR group will therefore experience Slight/Moderate visual impacts during the Construction and Operation
Phases before the
implementation of mitigation measures.
10.7.10 TKO-GIC5: The receptor sensitivity for Workers at Hong Kong
Movie City is Low and the magnitude of impact is Intermediate during the
Construction Phase when views across the undeveloped TKO reclamation are available and
will be Small during the Operation Phase once planned recreational facilities on the Area
77 Landfill are built including tree planting providing a degree of screening
to the TKO-LT Tunnel. This VSR group will therefore experience Slight/Moderate visual impacts during
the Construction Phase and Slight
visual impacts during the Operation Phase before the implementation of
mitigation measures.
10.7.11 Heung To Secondary School and GT College (TKO-GIC6) and Staff and Students at
Caritas Bianchi College of Careers (TKO-GIC7):
The receptor sensitivity for staff and students is Low and the magnitude of
impact is Negligible due to visual obstruction of existing development in TKO
to the east and natural topography to the south. These VSR groups will
therefore experience Insubstantial
visual impacts during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.12 Workers at Logistic Centre and Preliminary Treatment
Works and Cargo Handling Basin (TKO-GIC8):
The receptor sensitivity for these workers is Low and the magnitude of impact
is Small. This VSR group will therefore experience Slight visual impacts during the Construction and Operation Phases
before the implementation of mitigation measures.
10.7.13 Workers in the planned GIC development in TKO Area 67 (TKO-GIC9*): Receptor sensitivity for
the workers will be Low and the magnitude of impact will be Large during
construction due to the proximity of the roadworks, and they will be Intermediate
during the Operation Phase with the absence of temporary construction impacts.
Visual impacts will therefore be Moderate
during the Construction Phase and Slight/Moderate
during the Operation Phase before the implementation of mitigation measures.
10.7.14 Patients and Staff at Planned Private Hospital and
Students and Staff at Planned Fire
Services Training School cum Driving Training School in Area 78 (TKO-GIC10): Receptor sensitivity for
patients, staff and students will be Low and the magnitude of impact will be Small
for both Construction and Operation Phases, given the distance of view and the
screening effect of the topography and the planting on Area 77 Landfill between
the VSRs and the TKO-LT Tunnel. Visual impacts will therefore be Slight during both the Construction and
Operation Phases before the implementation
measures.
10.7.15 Workers at the TKO Industrial Estate (TKO-OU1A): The receptor sensitivity
for these VSRs is Low and the magnitude of visual impact will be Large due to
the open panoramic views of the TKO interchange and tunnel portal resulting in Moderate visual impacts at the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.16 Visitors of Junk Bay Chinese Permanent Cemetery (TKO-OU2): The receptor
sensitivity for the visitors is Low and the magnitude of visual impact will be
Intermediate as the TKO interchange will be partially visible. This will result
in Slight/Moderate visual impacts
during the Construction and Operation Phases before the implementation of
mitigation measures.
10.7.17 Users of Heng Fa Chuen Playground (TKO-O1) and Users of Siu Sai Wan Promenade (TKO-O2): The receptor sensitivity for these VSRs is High but
the magnitude of visual impact will be Small due to the long viewing distance.
This will result in Moderate visual
impacts during the Construction and Operation Phases before the implementation
of mitigation measures.
10.7.18 Users of planned Open Space at TKO Area 68 (TKO-O3*): The receptor
sensitivity for these VSRs is High and the magnitude of visual impact will be
Large due to the proximity of viewing distance and openness of view. This will
result in Substantial visual impacts
during the Construction and Operation Phases before the implementation of
mitigation measures.
10.7.19 Residents of Heng Fa Chuen (TKO-R1) and Residents
and Users of Island Resort Residential Area and Promenade (TKO-R8): The receptor sensitivity for these VSRs is High and the
magnitude of impact is Small due to the distance of view. This will result in Moderate visual impacts during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.20 Residents of Bauhinia Garden (TKO-R2): The receptor sensitivity for these VSRs is Medium due to
the existing partial visibility. The magnitude of visual impact will be Small during the construction and operation due to the
obstruction from planned development between the VSRs and the project site. This will result in Slight/Moderate visual impacts during the Construction and
Operation Phases before the implementation of mitigation measures.
10.7.21 TKO-R3: The receptor sensitivity for Residents at Ocean Shores (Phases I to III) is High and the magnitude of visual impact will be Large
due to the elevated viewpoints and proximity to the TKO-LT Tunnel works. Full, panoramic
views down onto the TKO interchange and associated roadworks will result in Substantial visual impacts during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.22 Residents of Metro Park (TKO-R4) and Residents of Park Central (TKO-R5): The receptor sensitivity for these VSRs is Medium due to
the lack of good existing views and the magnitude of impact will be Intermediate
during the Construction Phase and Operational Phases due largely to the obstruction from planned new
development on the TKO reclamation which will screen much of the visual impacts
of the TKO-LT Tunnel. This will result in Moderate visual impacts during the Construction and Operation
Phases before the
implementation of mitigation measures.
10.7.23 Residents of the Grandiose and TKO Plaza (TKO-R6): The receptor sensitivity for
these VSRs is Medium due to the poor quality of existing views towards the
project site due to intervening planned development. The magnitude of impact
will be Small during the Construction and Operational Phases due to the obstruction by the new intervening development
on the TKO reclamation screening the visual impacts of the TKO-LT Tunnel. This will
result in Slight/Moderate visual
impacts during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.24 Residents of Oscar by the Sea (TKO-R7): The receptor sensitivity for these VSRs is Medium due to
the poor quality of existing views towards the projects site due to intervening
planned development. The magnitude of impact will be Negligible during the
Construction Phase and Operational Phases due to the obstruction by the new intervening
development on the TKO reclamation screening the visual impacts of the TKO-LT
Tunnel. This will result in Insubstantial visual impacts during the Construction and Operation
Phases before the
implementation of mitigation measures.
10.7.25 Residents in Choi Ming Court (TKO-R9): the receptor sensitivity for these VSRs is Medium due to
poor views of the project site and the magnitude of visual impact will be Small
due to the partial screening of the TKO-LT Tunnel works by existing and planned
new development to the south. The significance of visual impacts will be Slight/Moderate during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.26 Residents Chai Wan high-rise estates (TKO-R10): The receptor sensitivity
for these VSRs is High due to their good existing views but the magnitude of
impact is Small due largely to the distance of view. This will result in Moderate visual impacts during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.27 Residents in Kin Ming Estate (TKO-R11), and Residents in Shin Ming Estate (TKO-R12): The receptor
sensitivity for these VSRs is Medium due to the poor quality of existing views
and the magnitude of visual impact will be Negligible during the Construction
and Operation Phases due to the screening effects of surrounding existing
development and topography. The significance of visual impacts will be Insubstantial during the Construction
and Operation Phases both before and after the implementation of mitigation
measures.
10.7.28 Residents in MTRC TKO Station Residential Development (TKO-R13): The receptor sensitivity
for these VSRs is Medium due to the poor quality of existing views which will
be screened by planned new development on the reclamation to the south. The magnitude
of impact will be Small. This will result in Slight/Moderate visual impacts during the Construction and
Operation Phases before the
implementation of mitigation measures.
10.7.29 Residents in Planned Residential Developments in TKO
Town Centre South reclamation OZP Zone R(A)2 (TKO-R14a*), OZP Zone R(A)3
(TKO-R14b*) and OZP Zone R(A)4 Areas a & b (TKO-R14c*): Receptor sensitivity for these VSRs is Medium due
to the poor quality of existing views and the magnitude of impact will be Small
due to the screening effect of planned development to the west and south
between the VSRs and the TKO-LT Tunnel development. Visual impacts will
therefore be Slight/Moderate during
the Construction and Operation Phases before the implementation of mitigation measures.
10.7.30 Residents in Planned Residential Developments on TKO
Town Centre South reclamation OZP Zone R(A)5 (TKO-R14d*), OZP Zone R(A)6 Area (a),
(b) & (c) East (TKO-R14e*), OZP
Zone R(A)6 Area (a), (b) & (c) West
(R14f*): Receptor sensitivity
for these VSRs is High and the magnitude of impact will be Large given the open,
unobstructed views west and south to the TKO interchange and reclamation and
the relative proximity. Visual impacts will therefore be Substantial during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.31 Residents in upper floors of planned Residential Group
E Development in Area 85 (TKO-R15*):
Receptor sensitivity for these VSRs will be Medium due to poor existing views
towards project site and the magnitude of impact will be Small given the visual
obstruction of LOHAS Park and CDA1B and future recreational facilities on Area
77 Landfill. Visual impacts will therefore be Slight/Moderate during both the Construction and Operation Phases before the implementation of mitigation measures.
10.7.32 Hikers along the High Junk Peak (Tiu Yue Yung) Country
Trail in Clearwater Bay Country Park (TKO-REC1)
and Hikers along the Wilson Trail to Devil’s Peak and Chiu Keng Wan Shan (TKO-REC2): The receptor sensitivity
for these VSRs is Medium and the magnitude of impact will be Small and Intermediate
respectively due largely to
the distance of view and the fact that the impacts will form only part of a
much broader panoramic view observed from the ridgelines. This will result in Slight/Moderate visual impacts during
the Construction and Operation Phases before the implementation of mitigation
measures.
10.7.33 Visitors to Lei Yue Mun Holiday Village, Lei Yue Mun
Park (TKO-REC3A) and Visitors to the
Hong Kong Museum of Coastal Defence (TKO-REC3B):
The receptor sensitivity for these VSRs is Medium and the magnitude of
impact is Small due largely to the distance of view. This will result in Slight/Moderate visual impacts during
the Construction and Operation Phases before the implementation of mitigation
measures.
10.7.34 Hikers along Pottinger Trail and Pottinger Peak (TKO-REC4), Hikers at Mount Collinson (TKO-REC5), and Hikers at Mount Parker
(TKO-REC6): The receptor sensitivity
for these VSRs is Medium but the
magnitude of impact is Negligible due to the distance of view. This will result
in Insubstantial visual impacts
during the Construction and Operation Phases before the implementation of
mitigation measures.
10.7.35 Seaborne Leisure Travellers in Junk Bay (TKO-T1): The receptor
sensitivity for these VSRs is Medium and the magnitude of impact is Large due to the
potential proximity of the view. This will result in Moderate/Substantial visual impacts during the Construction and
Operation Phases before the implementation of mitigation measures.
10.7.36 Seaborne Leisure Travellers along Lei Yue Mun and
Tathong Channel (TKO-T2): The
receptor sensitivity for these VSRs is Medium and the magnitude of impact isIintermediate due
to the greater distance of view. This will result in Moderate visual impacts during the Construction and Operation
Phases before the implementation of mitigation measures.
10.7.37 Travellers along Wan Po Road (TKO-T3): The receptor sensitivity for these VSRs is Low and
the magnitude of impact will be Small as views are largely obscured by the Area
77 landfill, the LOHAS Park CDA development and the TKO Industrial Estate. These
VSRs will therefore experience Slight
visual impacts during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.38 Travellers at TKO MTR Station and along Po Yap Road
and Chui Ling Road (TKO-T4): The
receptor sensitivity for these VSRs is Low and the magnitude of impact will be Large
during the Construction Stage due to the proximity of the temporary works and will be reduced to Intermediate during the Operation Phase. This VSR
group will therefore experience Moderate
visual impacts during the Construction Phase and Slight/Moderate visual impacts during the Operation Phase before
the implementation of mitigation measures.
10.7.39 Pedestrians on Footpath Link from Ocean Shores to Junk
Bay Chinese Permanent Cemetery (TKO-T5):
The receptor sensitivity for these VSRs is Medium and the magnitude of impact
will be Large with close views of the TKO interchange and the TKO portal. This
VSR group will experience Moderate/Substantial
visual impacts during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.40 Travellers on new Southern Footbridge Crossing Eastern
Channel (TKO-T7*): Receptor
sensitivity for these VSRs is Medium and the magnitude of impact will be Large
given the open unobstructed views south and west to the TKO-LT Tunnel. Visual
impacts will therefore be Moderate/Substantial
during the Operation Phase before the implementation of mitigation measures.
Significance of Visual Impacts before Mitigation
during the Construction and Operation Phases - Planned Future VSRs in Tseung
Kwan O
10.7.41 For the purposes of this assessment, it is assumed
that the following future planned developments will be constructed after
the completion of the TKO-LT Tunnel. Assessment of significance of impact
during the Construction Phase is therefore not applicable and neither is
assessment of significance at Day 1 of the Operation Phase.
10.7.42 Workers in planned TKO Industrial Estate Extension (TKO-OUIB): Receptor sensitivity for these VSRs will be Low and the magnitude of impact will be Large
given the open panoramic views towards the TKO-LT Tunnel. Visual impacts will
therefore be Moderate during the
Operation Phase before the implementation of mitigation measures.
10.7.43 Users of Planned Recreational Facilities at TKO Stage
I Landfill in Area 77 (TKO-REC7):
Receptor sensitivity for these VSRs will be Medium and the magnitude of impact will be Large
given the open unobstructed views south and west to the TKO-LT Tunnel. Visual
impacts will therefore be Moderate/Substantial
during the Operation Phase before the implementation of mitigation measures.
Significance
of Visual Impacts before Mitigation during the Construction and Operation
Phases - Existing VSRs in Lam Tin
10.7.44 Workers in Yau Tong Industrial Area (LT-C1): The receptor sensitivity of
these VSRs is Low and the magnitude of impact is Negligible due to the
screening effect of the planned Yau Tong Bay CDA development to the north west.
This VSR group will therefore experience Insubstantial
visual impacts during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.45 Workers in Tai Koo Place and One Island East (LT-C2): The receptor sensitivity of these
VSRs is Low and the magnitude of impact is Small due to the distance of view
and the screening of most the Lam Tin Interchange by the ridge of land behind
Cha Kwo Ling Village. This VSR group will therefore experience visual impacts
of Slight significance during the
Construction and Operational Phases before the implementation of mitigation measures.
10.7.46 Staff and Pupils of Schools East of EHC (LT-GIC1): The receptor sensitivity of
these VSRs is Low and the magnitude of impact is Large due to the proximity of
view and elevated viewpoint. This VSR group will therefore experience visual
impacts of Moderate significance
during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.47 Staff and pupils of School and Government facilities
at Rehab Path (LT-GIC2): The
receptor sensitivity for these VSRs is Low and the magnitude of impact is Negligible
due to screening by existing topography and woodland. This VSR group will
therefore experience Insubstantial
visual impacts during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.48 Residents of Ping Tin Estate and Hong Ngar Court (LT-R3), Residents of Yau Lai Estate (LT-R4A), Residents of Kwong Tin
Estate and Hong Pak Court (LT-R11):
The receptor sensitivity for these VSRs is High and the magnitude of impact is Large
due to the clear elevated, fixed views of the project and proximity. This will
result in Substantial visual impacts
during the Construction and Operation Phases before the implementation of
mitigation measures.
10.7.49 Residents of Yau Tong Estate and Yau Mei Court (LT-R4B): The receptor sensitivity for
these VSRs is Medium due to poor existing views of the project site and the
magnitude of impact is Small due to the obstruction of intervening development.
This will result in visual impacts of Slight/Moderate
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.50 Residents in Yau Tong - The Canaryside and the
Spectacle (R5): The receptor
sensitivity for these VSRs is High and the magnitude of impact is Small due to
the distance of view of the project and obstruction of intervening planned and
existing development. This will result in visual impacts of Moderate significance during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.51 Residents at Sai Wan Ho (Lei King Wan, Grand
Promenade, Les Saisons) (LT-R6A), Residents
at Shau Kei Wan (Tung To Court, Tung Yuk Court and Aldrich Bay) (LT-R6B), Residents at Sai Wan Ho
(Hing Tung Estate, Tung Hei Court, Tung Lam Court) (LT-R7), and Residents at Tai Koo Shing (LT-R8): The receptor sensitivity for these VSRs is Medium and the
magnitude of impact is Small due to the distance of view and partial screening
of the project site by landform and buildings. This will result in visual
impacts of Slight/Moderate
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.52 Residents at Cha Kwo Ling Village (LT-R9A), and Residents at Fan Wah Street (LT-R10): Whilst these VSRs are close to the project site, the
receptor sensitivity for them is Medium and the magnitude of impact is Negligible
primarily due to their lack of views of the project site as it is screened by
the high ground behind Cha Kwo Ling Village. This will result in visual impacts
of Insubstantial significance during
the Construction and Operation Phases before the implementation of mitigation
measures.
10.7.53 Residents at Cha Kwo Ling housing developments west of
interchange (LT-R9B): Receptor
sensitivity for these VSRs will be High and the magnitude of impact will be Large
given the proximity, and the panoramic elevated views over the Lam Tin
Interchange. Visual impacts will therefore be Substantial during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.54 Residents at Laguna City (LT-R12) and Residents at Sceneway Garden (LT-R13): Whilst these VSRs are close to the project site, the
receptor sensitivity for them is Medium and the magnitude of impact is Negligible
due to their lack of views of the project site as it is screened by the high
ground between. This will result in visual impacts of Insubstantial significance during the Construction and Operation
Phases before the implementation of mitigation measures.
10.7.55 Residents in Yau Tong Bay CDA development (LT-CDA1): Receptor sensitivity for these
VSRs will be High and the magnitude of impact will be Large given the proximity
and the panoramic elevated views over the Lam Tin Interchange. Visual impacts
will therefore be Substantial during
the Construction and Operation Phases before the implementation of mitigation measures.
10.7.56 Hikers along Wilson Trails near Black Hill (LT-REC1A), and Hikers along Wilson
Trail at Devil’s Peak (LT-REC1B): The
receptor sensitivity of these VSRs is Medium and the magnitude of impact is Small
due to partial obstruction of views of the site by high rise building blocks
and distance of view. This will result in visual impacts of Slight/Moderate significance during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.57 Hikers along Pottinger Trail and Pottinger Peak (LT-REC2), Hikers at Mount Collinson (LT-REC3), Hikers at Mount Parker (LT-REC4), and Hikers at Mount Butler (LT-REC5): The receptor sensitivity of
these VSRs is Medium and the magnitude of impact is Negligible due to the distance
of view and partial obstruction of views of the site by high rise building
blocks and high ground behind Cha Kwo Ling Village. This will result in visual
impacts of Insubstantial significance
during the Construction and Operation Phases before the implementation of
mitigation measures.
10.7.58 Hikers at Braemar Hill Lookout (LT-REC6), Visitors of Lei Yue Mun Fort (Hong Kong Museum of
Coastal Defence) (LT-REC7A),
Visitors of Lei Yue Mun Observation Post (Hong Kong Museum of Coastal Defence) (LT-REC7B), and Visitors of Lei Yue
Mun Holiday Village, Lei Yue Mun Park (LT-REC8):
The receptor sensitivity of, these VSRs
is Medium and the magnitude of impact is Small due to the distance of
view and partial obstruction of views of the site by high-rise building blocks and
high ground behind Cha Kwo Ling Village. This will result in visual impacts of Slight/Moderate significance during the
Construction and Operation Phases before the implementation of mitigation
measures.
10.7.59 Users of Sai Tso Wan Recreation Ground and Tennis
Courts (LT-REC9): Whilst these VSRs
are close to the project site, the receptor sensitivity for is Low and the
magnitude of impact is Negligible due to the screening effect of existing
woodland. This will result in visual impacts of Insubstantial significance during the Construction and Operation
Phases before the implementation of mitigation measures.
10.7.60 Users of Yau Tong
Road Playground (LT-O1): The receptor sensitivity for these VSRs is Medium
and the magnitude of impact is Intermediate due to the partial screening effect
of existing tree planting and advertising banners along the edges of the
EHC. This will result in visual impacts
of Moderate significance during the Construction and Operation Phases before
the implementation of mitigation measures.
10.7.61 Users of Quarry Bay Park (LT-O2), Visitors to Aldrich Bay Promenade (LT-O3) and Visitors of Sai Wan Ho Harbour Park (LT-O4): The receptor sensitivity for,these
VSRs is Medium and the magnitude of impact will be Small due to the distance of
view and partial screening effect of existing buildings along the Lam Tin
waterfront and the high ground behind Cha Kwo Ling Village. This will result in
visual impacts of Slight/Moderate
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.62 Users of public open space on promenade (LT-O5*) and Users of planned open
space north west of Lam Tin Interchange
(LT-O6*): Receptor sensitivity for these VSRs will be Medium and the
magnitude of impact will be Intermediate given the screening effect of the
quarry landform in reducing potential views across the Lam Tin Interchange.
Visual impacts will therefore be Moderate
during the Construction and Operation Phases before the implementation of mitigation measures.
10.7.63 Seaborne leisure travellers along Lei Yue Mun Channel (LT-T1): The sensitivity for these
VSRs is Low and the magnitude of impact will be Intermediate due to the
distance of view and partial screening effect of existing buildings along the
Lam Tin waterfront and the high ground behind Cha Kwo Ling Village. This will
result in visual impacts of Slight/Moderate
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.64 Travellers along the Island Eastern Corridor (LT-T2): The receptor sensitivity is Low and the magnitude of impact will be Small
due to the distance of view and partial screening effect of existing buildings
along the Lam Tin waterfront and the high ground behind Cha Kwo Ling Village.
This will result in visual impacts of Slight
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
10.7.65 Travellers on EHC approaches (LT-T3): The receptor sensitivity is Low and the magnitude of
impact will be Intermediate due to the proximity of view and partial screening
effect of existing trees, buildings and advertising hoardings along the south
western side of the Ex- Cha Kwo Ling Kaolin Mine Site. This will result in
visual impacts of Slight/Moderate
significance during the Construction and Operation Phases before the
implementation of mitigation measures.
Significance
of Visual Impacts before Mitigation during the Construction and Operation
Phases - Planned Future VSRs in Lam Tin
10.7.66 There are no known planned future developments in the
Lam
Tin area that will be constructed after the completion of the TKO-LT Tunnel.
Table 10.7.1: Significance of Visual Impacts in the
Construction and Operation Phases – TKO
VSR
Type & ID. |
Key
Visually Sensitive Receiver (VSR) |
Magnitude
of Impact (Negligible, Small, Intermediate, Large) |
Receptor
Sensitivity (Low, Medium, High) |
Impact
Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended
Mitigation Measures |
Residual
Impact Significance Threshold After Mitigation (Insubstantial, Slight,
Moderate, Substantial) |
|||||||||||
Construc- tion |
Operation |
||||||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
DAY
1 |
YEAR
10 |
||||||||||
Existing VSRs in TKO |
|||||||||||||||||
TKO-CDA1A |
Existing
Residents and |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
||||||
TKO-CDA1B* |
Residents
in planned new Residential Development at CDA in Area 86/LOHAS Park |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/ Substantial |
Moderate |
||||||
TKO-GIC1 |
Workers
in TKO Sewage Treatment Works, Area 85 |
Negligible |
Negligible |
Low |
Low |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
|||||||
TKO-GIC2 |
Staff
and students at |
Small |
Small |
Low |
Low |
Slight
|
Slight |
CM1,2,4,6,8,9,10 OM1
to 8 |
Slight
|
Slight |
Insub-stantial |
||||||
TKO-GIC4 |
Staff
and students at Hong Kong Design Institute Campus |
Intermediate |
Intermediate |
Low |
Low |
Slight/
Moderate |
Slight/
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial
|
||||||
TKO-GIC5 |
Workers
at |
Intermediate |
Small |
Low |
Low |
Slight/ Moderate |
Slight |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/
Moderate |
Slight |
Insub-stantial |
||||||
TKO-GIC6 |
Staff
and students at Heung To Secondary School and GT College |
Negligible |
Negligible |
Low |
Low |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
||||||
TKO-GIC7 |
Staff
and students at Caritas Bianchi College of Careers |
Negligible |
Negligible |
Low |
Low |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
||||||
TKO-GIC8 |
Workers
at Logistics Centre and Preliminary Treatment Works and |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM1,
2, 4, 6, 7, 8, 9, 10 OM1,
2, 3, 4, 5, 7 |
Slight |
Insub-stantial |
Insub-stantial |
||||||
TKO-GIC9* |
Workers
in planned GIC Development at TKO Area 67 |
Large |
Intermediate |
Low |
Low |
Moderate |
Slight/ Moderate |
OM1,2,4
to 8 |
Moderate |
Slight/ Moderate |
Slight |
||||||
TKO-GIC10* |
Patients
and staff at planned private hospital and students and staff at planned |
Small |
Small |
Low |
Low |
Slight |
Slight
|
CM1,
2, 4, 6, 7, 8, 9, 10 OM1,
2, 3, 4, 5, 7 |
Slight |
Insub-stantial |
Insub-stantial |
||||||
TKO-OU1A |
Workers
at TKO Industrial Estate |
Large |
Large |
Low |
Low |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight |
||||||
TKO-OU2 |
Visitors
of |
Intermediate |
Intermediate |
Low |
Low |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Slight |
||||||
TKO-O1 |
Users
of Heng Fa Chuen Playground |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,
2, 4, 6, 7, 8, 9, 10 OM1,
2, 3, 4, 5, 7 |
Slight/ Moderate
|
Slight |
Slight |
||||||
TKO-O2 |
Users
of Siu Sai Wan Promenade |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,
2, 4, 6, 7, 8, 9, 10 OM1,
2, 3, 4, 5, 7 |
Slight/ Moderate
|
Slight |
Slight |
||||||
TKO-O3* |
Users
of planned Open Space at TKO Area 68 |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,
2, 4, 6, 7, 8, 9, 10 OM1,
2, 3, 4, 5, 7 |
Substantial |
Moderate/Substantial |
Moderate |
||||||
TKO-R1 |
Residents
of Heng Fa Chuen |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight |
Slight |
||||||
TKO-R2 |
Residents
of |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
||||||
TKO-R3 |
Residents
of |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/ Substantial |
Moderate |
||||||
TKO-R4 |
Residents
of |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight/ Moderate |
Slight |
||||||
TKO-R5 |
Residents
of Park Central |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight/ Moderate |
Slight |
||||||
TKO-R6 |
Residents
of the Grandiose and |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Insub- stantial |
||||||
TKO-R7 |
Residents
of Oscar by the Sea |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Insub-stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-R8 |
Residents
& users of Island Resort residential area and promenade |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight |
Slight |
||||||
TKO-R9 |
Residents
in |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Insub- stantial |
||||||
TKO-R10 |
Residents
in Chai Wan high rise estates |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight |
Slight |
||||||
TKO-R11 |
Residents
in Kin Ming Estate |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub- stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-R12 |
Residents
in Shin Ming Estate |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub- stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-R13 |
Residents
in MTRC TKO Station Residential Development |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Slight/ Moderate |
Slight |
Insub- substantial |
||||||
TKO-R14a* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)2 |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Slight/ Moderate |
Slight |
Insub- substantial |
||||||
TKO-R14b* |
Residents
in planned Future residential Development on TKO Town Centre South
reclamation OZP
Zone R(A)3 |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Slight/ Moderate |
Slight |
Insub- substantial |
||||||
TKO-R14c* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)4 Areas (a) & (b) |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Slight/ Moderate |
Slight |
Insub- substantial |
||||||
TKO-R14d* |
Residents
in planned Residential Development on TKO Town Centre South reclamation OZP
Zone R(A)5 |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Substantial |
Moderate/ Substantial |
Moderate |
||||||
TKO-R14e* |
Residents
in planned Residential Development on TKO Town Centre South reclamation R(A)6
Area (a), (b) & (c) East |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Substantial |
Moderate/ Substantial |
Moderate |
||||||
TKO-R14f* |
Residents
in planned Residential Development on TKO Town Centre South reclamation R(A)6
Area (a), (b) & (c) West |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,5,6,7,8,9,10,12 OM1,2,3,4,5,6,7 |
Substantial |
Moderate/ Substantial |
Moderate |
||||||
TKO-R15* |
Residents
in upper floors of planned Residential Group (E) Development in Area 85 |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
N/A |
Slight/ Moderate |
Slight |
Insub-stantial |
||||||
TKO-REC1 |
Hikers
along |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
||||||
TKO-REC2 |
Hikers
along the |
Intermediate |
Intermediate |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight
|
Slight |
||||||
TKO-REC3A |
Visitors
of Lei Yue Mun Holiday Village, Lei Yue Mun Park |
Small |
Small |
Medium |
Medium |
Slight/
Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Slight |
||||||
TKO-REC3B |
Visitors
of H.K. Museum of Coastal Defence |
Small |
Small |
Medium |
Medium |
Slight/
Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Slight/ Moderate |
Slight |
Slight |
||||||
TKO-REC4 |
Hikers
along Pottinger Trail and |
Negligible |
Negligible |
Medium |
Medium |
Insub- stantial |
Insub- stantial |
N/A |
Insub- stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-REC5 |
Hikers
at |
Negligible |
Negligible |
Medium |
Medium |
Insub- stantial |
Insub- stantial |
N/A |
Insub- stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-REC6 |
Hikers
at |
Negligible |
Negligible |
Medium |
Medium |
Insub- stantial |
Insub- stantial |
N/A |
Insub- stantial |
Insub- stantial |
Insub- stantial |
||||||
TKO-T1 |
Seaborne
Leisure Travellers in |
Large |
Large |
Medium |
Medium |
Moderate/ Substantial |
Moderate/ Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate/ Substantial |
Moderate |
Slight/ Moderate |
||||||
TKO-T2 |
Seaborne
Leisure Travellers along Lei Yue Mun
and Tathong Channel |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight/ Moderate |
||||||
TKO-T3 |
Travellers
along Wan |
Small |
Small
|
Low
|
Low |
Slight |
Slight |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight |
Insub- stantial |
Insub- stantial |
||||||
TKO-T4 |
Travellers
at TKO MTR Station and along |
Large |
Intermediate |
Low |
Low |
Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate |
Slight/ Moderate |
Slight |
||||||
TKO-T5 |
Pedestrians on footpath link from Ocean
Shores to Junk Bay Chinese Permanent Cemetery |
Large |
Large |
Medium |
Medium |
Moderate/
Substantial |
Moderate/
Substantial |
CM1,2,4,6,7,8,9,10 OM1,2,4
to 8 |
Moderate/
Substantial |
Moderate |
Slight/ Moderate |
||||||
TKO-T7* |
Travellers on new Southern Footbridge
crossing Eastern Channel |
Large |
Large |
Medium |
Medium |
Moderate/ Substantial |
Moderate/ Substantial |
OM1
to 8 |
Moderate/ Substantial |
Moderate |
Slight/ Moderate |
||||||
Planned Future VSRs in TKO |
|||||||||||||||||
TKO-OU1B |
Workers
in planned TKO Industrial Estate Extension |
N/A |
Large |
N/A |
Low |
N/A |
Moderate |
OM1
to 8 |
N/A |
Moderate |
Slight/
Moderate |
||||||
TKO-REC7 |
Users
of planned recreational facilities at TKO Stage I Landfill, Area 77 |
N/A |
Large |
N/A |
Medium |
N/A |
Moderate/
Substantial |
OM1
to 8 |
N/A |
Moderate |
Slight/ Moderate |
||||||
*VSRs in developments planned to be completed before
completion of TKO-LT Tunnel
Table 10.7.2: Significance of Visual Impacts in the Construction and
Operation Phases - Lam Tin
VSR
Type & ID. |
Key
Visually Sensitive Receiver (VSR) |
Magnitude
of Impact (Negligible, Small, Intermediate, Large) |
Receptor
Sensitivity (Low, Medium, High) |
Impact
Significance Threshold Before Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
Recommended
Mitigation Measures |
Residual
Impact Significance Threshold After Mitigation (Insubstantial, Slight,
Moderate, Substantial) |
|||||
Construction |
Operation |
||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
DAY
1 |
YEAR
10 |
||||
Existing VSRs in Lam Tin |
|||||||||||
LT-C1 |
Workers
in Yau Tong Industrial Area |
Negligible |
Negligible |
Low |
Low |
Insub- stantial |
Insub- stantial |
N/A |
Moderate |
Slight/
Moderate |
Insub-stantial |
LT-C2 |
Office
workers in |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight |
In-substantial |
Insub-stantial |
LT – GIC1 |
Staff
and pupils of schools east of EHC |
Large |
Large |
Low |
Low |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/
Moderate |
Slight |
LT – GIC2 |
Staff
and pupils of School and Government facilities at Rehab Path |
Negligible |
Negligible |
Low |
Low |
Insub-stantial |
Insub-stantial |
Not
Required |
Insub-stantial |
In-substantial |
Insub-stantial |
LT- R3 |
Residents
of Ping Tin Estate and |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/ Substantial |
Moderate |
LT- R4A |
Residents
of Yau Lai Estate |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/ Substantial |
Moderate |
LT- R4B |
Residents
of Yau Tong Estate and |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT- R5 |
Residents
in Yau Tong – The Canaryside and The Spectacle |
Small |
Small |
High |
High |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight |
LT- R6A |
Residents
at Sai Wan Ho (Lei King Wan, Grand Promenade, Les Saisons) |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT- R6B |
Residents
at Shau Kei Wan (Tung To Court, |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT- R7 |
Residents
at Sai Wan Ho (Hing Tung Estate, |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT- R8 |
Residents
at Tai Koo Shing |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT- R9A |
Residents
at |
Negligible |
Negligible |
Medium |
Medium |
Insub-stantial |
Insub-stantial |
N/A |
In-substantial |
In-substantial |
Insub-stantial |
LT – R9B* |
Residents
at Cha Kwo Ling housing developments west of interchange |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/Substantial |
Moderate |
LT- R10 |
Residents
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
In-substantial |
Insub-stantial |
LT- R11 |
Residents
at Kwong Tin Estate and |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/
Substantial |
Moderate |
LT- R12 |
Residents
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
LT-R13 |
Residents
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insubstantial |
Insub-stantial |
Insub-stantial |
LT-CDA1* |
Residents
of Yau Tong Bay CDA development |
Large |
Large |
High |
High |
Substantial |
Substantial |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Substantial |
Moderate/ Substantial |
Moderate |
LT
- REC1 A |
Hikers
along |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
In-substantial |
LT - REC1 B |
Hikers along |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
In-substantial |
LT – REC2 |
Hikers
along Pottinger Trail and Pottinger |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
LT – REC3 |
Hikers
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
LT – REC4 |
Hikers
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
LT – REC5 |
Hikers
at |
Negligible |
Negligible |
Medium |
Medium |
Insubstantial |
Insub-stantial |
N/A |
Insub-stantial |
Insub-stantial |
Insub-stantial |
LT – REC6 |
Hikers
at Braemar Hill Lookout |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT – REC7A |
Visitors
of Lei Yue Mun Fort ( |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT – REC7B |
Visitors
of Lei Yue Mun Observation Post ( |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT – REC8 |
Visitors
of |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT – REC9 |
Users
of Sai Tso Wan Recreation Ground and Tennis Courts |
Negligible |
Negligible |
Low |
Low |
In-substantial |
In-substantial |
N/A |
In-substantial |
In-substantial |
In-substantial |
LT-O1 |
Users
of Yau Tong Road Playground |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight |
LT-O2 |
Users
of |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
In-substantial |
LT-O3 |
Visitors
to |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
In-substantial |
LT-O4 |
Visitors
of Sai Wan Ho |
Small |
Small |
Medium |
Medium |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
In-substantial |
LT – O5* |
Users
of public open space on promenade |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight |
LT – O6* |
Users
of planned open space |
Intermediate |
Intermediate |
Medium |
Medium |
Moderate |
Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Moderate |
Slight/ Moderate |
Slight |
LT-T1 |
Seaborne
Leisure Travellers along Lei Yue Mun
Channel |
Intermediate |
Intermediate |
Low |
Low |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 |
Slight/ Moderate |
Slight |
Insub-stantial |
LT - T2 |
Travellers
along |
Small |
Small |
Low |
Low |
Slight |
Slight |
CM1,2,4,6,7,8,9,10 |
Slight |
Insu-stantial |
Insub-stantial |
LT - T3 |
Travellers
on Eastern Harbour Crossing approaches |
Intermediate |
Intermediate |
Low |
Low |
Slight/ Moderate |
Slight/ Moderate |
CM1,2,4,6,7,8,9,10 OM1
to 8 |
Slight/ Moderate |
Slight |
Insub-stantial |
*VSRs in developments planned to be completed before
completion of TKO-LT Tunnel
Mitigation of Landscape and Visual Impacts
10.8.1
The mitigation
measures listed in Tables 10.8.1 and
10.8.2 describe mitigation measures
during the Construction
and Operation Phases which if implemented may reduce the degree of
impact of the landscape and visual impacts identified in earlier sections of this report and potentially
enhance the landscape and visual amenity.
Construction
Phase Mitigation Measures
10.8.2
Landscape and
visual mitigation measures during the Construction Phase are listed and
described in Table 10.8.1 below.
Table
10.8.1: Construction Phase Mitigation Measures
ID
No. |
Construction
Phase Mitigation Measures |
Funding
& Implementation Agency |
Management
& Maintenance Agency |
CM1 |
Construction
area and contractor’s temporary works areas to be minimised to avoid impacts
on adjacent landscape. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM2 |
Reduction
of construction period to practical minimum. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM3 |
Topsoil,
where the soil material meets acceptable criteria and where practical, to be
stripped and stored for re-use in the construction of the soft landscape
works. The Contract Specification shall include storage and reuse of topsoil
as appropriate. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM4 |
Existing
trees at boundary of site and retained trees within site boundary to be
carefully protected during construction. Detailed Tree Protection
Specification shall be provided in the Contract Specification, under which
the Contractor shall be required to submit, for approval, a detailed working
method statement for the protection of trees prior to undertaking any works
adjacent to all retained trees, including trees in contractor’s works areas.
(Tree protection measures will be detailed at Tree Removal Application
stage). |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM5 |
Trees
unavoidably affected by the works shall be transplanted where practicable.
Where possible, trees should be transplanted direct to permanent locations
rather than temporary holding nurseries. A detailed tree transplanting
specification shall be provided in the Contract Specification and sufficient
time for preparation shall be allowed in the construction programme. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM6 |
Advance
screen planting of fast growing tree and shrub species to noise barriers and
hoardings. Trees shall be capable of reaching a height >10m within 10
years. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM7 |
Hydroseeding
or sheeting of soil stockpiles with visually unobtrusive material. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM8 |
Control
of night-time lighting by hooding all lights and through minimisation of
night working periods. |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM9 |
Screening
of works areas with hoardings with appropriate colours compatible with the
surrounding area |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM10 |
Avoidance
of excessive height and bulk of site buildings and structures |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM11 |
Limitation
of run-off into freshwater streams,
ponds and sea areas |
CEDD (via Contractor) |
CEDD (via Contractor) |
CM12 |
Minimise
area of reclamation and design the edges sensitively to tie in with adjacent
coastline character |
CEDD (via Contractor) |
CEDD (via Contractor) |
Operation
Phase Mitigation Measures
10.8.3
Landscape and
visual mitigation measures during the Operation Phase are listed and described
below in Table 10.8.2 below.
Table
10.8.2: Operation Phase Mitigation Measures
ID
No. |
Operation
Phase Mitigation Measures |
Implementation
Agency |
Maintenance/
Management Agency |
OM1 |
Compensatory
Tree Planting for all felled trees to the satisfaction of relevant Government
Departments. Required numbers and locations of compensatory trees shall be
determined and agreed separately with Government during the Tree Felling
Application process. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 Along
non-expressway public roads – LCSD Within
expressway boundary (ie route 6) – HyD |
OM2 |
Screen
tree planting along the site boundary featuring trees capable of reaching a
height >10m within 10 years. Offsite screen planting by agreement may also
be considered should space within the site be insufficient. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 Along
non-expressway public roads – LCSD Within
expressway boundary (ie route 6) – HyD |
OM3 |
Slope
greening works on all disturbed, new or reinstated slopes including trees,
shrubs, groundcover and climbers. For slopes which are not feasible for
planting, sensitive design of hard landscape treatment with appropriate
material and color should be provided. The use of unobtrusive colours and
tones for all hard elements on slopes (concrete channels, access stairs,
railings, catch pits etc) including pigmented concrete and paints. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 and DEVB TC (W) 06/2011; Maintenance of Man- made Slopes and Emergency
works to Deal with Landslides |
OM4 |
Sensitive
design of buildings and structures in terms of scale, form, height and bulk
(visual weight) |
CEDD (via Contractor) |
Building Operator |
OM5 |
Use
appropriate (visually unobtrusive and non-reflective) building materials and
colours in buildings and structures. |
CEDD (via Contractor) |
Building Operator |
OM6 |
Streetscape
and highway elements including paving, signage, street furniture, lighting
etc. sensitively designed in a manner that responds to the local context, and
minimises potential negative landscape and visual impacts. Lighting units to
be directional and minimise unnecessary light spill. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 Features
associated with public road safety, paving, in-situ planters and street
lighting – HyD; Street
furniture & amenity lighting - CEDD |
OM7 |
Greening
measures on elevated road sections. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 – HyD on expressways; LCSD on non-expressways |
OM8 |
Sensitive
design of footbridges, noise barriers and enclosures with greening (screen
planting/climbers/planters) and chromatic measures. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 – hardworks elements CEDD; softworks elements by LCSD |
OM9 |
Additional
greening measures for streetscape and building associated with infrastructure
for further enhancement and optimization of the overall greening effect
within the Project Area. |
CEDD (via Contractor) |
As
per ETWB(W)
2/2004 – hardworks elements CEDD; softworks elements by LCSD |
Environmental Monitoring and Audit Requirements
Construction Phase
10.8.5
It is recommended
that a professionally qualified Resident Site Landscape Architect supervises
and monitors the construction phase landscape and visual mitigation measures.
This is necessary to ensure the minimisation of the works footprint, to ensure
that topsoil is saved, to ensure that those existing trees earmarked for
retention on site or transplanting are protected and to monitor advance screen
planting works and the effectiveness of temporary screen hoardings. Regular
site inspections should be undertaken to closely monitor all these aspects of
the work.
Operational Phase
10.8.6
During the
operational phase, landscape and visual mitigation measures should be monitored
by the Environmental Team and Independent Environmental Checker during the first 10 years to check that the
intended mitigation effects are realised. Regular monitoring should be
undertaken to ensure that the landscape and visual mitigation measures have
been implemented, are effective and are being managed and maintained. The
compensatory tree planting required to offset the loss of existing trees should
be checked, and the additional planting works for screening, slope
stabilisation and amenity purposes. Planting must be established and
sustainable and provide long term landscape and visual mitigation. Hardworks
elements that have been provided as part of the new works or as the
reinstatement of impacted works should also be monitored and checked that they
are being maintained and are achieving their mitigation function.
Photomontages
10.8.7
Photomontages
have been developed to highlight the key mitigation measures introduced to
reduce residual visual impacts of above-ground and sea structures.
The locations of the viewpoints at TKO and LT for the
photomontages can be seen on Figures 10.8.5.1 and 10.8.7.1 respectively. Viewpoints were selected to
provide representative examples of the “worst case scenario” in terms of visual
impacts of the project. The photomontages illustrate the project works for the four
scenarios listed below:
·
Existing Condition;
·
Day
1 without Mitigation Measures;
·
Day 1 with
Mitigation Measures;
·
Year
10 with Mitigation Measures.
Photomontage from VSR TKO-R1 to TKO
Interchange (Figure no.s 10.8.5.2 to 10.8.5.3)
10.8.8
This viewpoint
from Heng Fa Chuen was selected as representative of views from the
highly sensitive residential VSR groups on Hong Kong Island. This is the worst
case scenario as it is the closest of the Hong Kong Island VSRs and also has
direct views of the TKO Interchange in Junk Bay. The photograph was taken on
the waterfront promenade at an elevation of approximately 5m m.p.d. (access to
the residential towers to take photographs from a higher viewpoint was not
permitted). This viewpoint is also representative of VSR group TKO-O1 and
TKO-REC3B.
Photomontage from VSR TKO-R3 to TKO
Interchange (Figure no.s 10.8.5.12 to 10.8.5.13)
10.8.9
This viewpoint
from Ocean Shores was selected as representative of views from highly sensitive
residential VSR groups along the western side of Junk Bay overlooking TKO
Interchange and the interface of the TKO tunnel portal with the existing
hillsides. The photograph was taken from the roof of Ocean Shores at an
elevation of approximately 180m m.p.d. which gives the maximum view and a worst
case scenario for residents in the upper floors.
Photomontage from VSR TKO-R5 to TKO
Interchange (Figure no.s 10.8.5.4
to 10.8.5.5)
10.8.10 This viewpoint from Park Central was selected as
representative of views from highly sensitive residential VSR groups along the
southern edge of TKO overlooking the new reclamation extension area with the future
road works on the and the TKO interchange in Junk Bay beyond. The photograph
was taken from the roof of Park Central at an elevation of approximately 180m
m.p.d. which gives the maximum view and a worst case scenario for residents in
the upper floors.
Photomontage from VSR
TKO-CDA1 to TKO Interchange (Figure no.s 10.8.5.6 to 10.8.5.7)
10.8.11
This
viewpoint represents the outlook from the planned waterfront residential blocks
in CDA1A (LOHAS Park). It was taken from one of the existing residential blocks
on the east side of LOHAS Park at an elevation of approximately 180m m.p.d. The
viewpoint has been zoomed in to give a representative view from the planned new
waterfront blocks on the west of the site which will represent the worst case
scenario. This VSR group is the most
sensitive on the eastern side of Junk Bay and has direct panoramic views across
the entire TKO side of the project including the TKO interchange, the TKO
tunnel portal and the Road P2 reclamation.
Photomontage from VSR TKO-REC1 to TKO
Interchange (Figure no.s 10.8.5.8 to 10.8.5.9)
10.8.12 This is a representative viewpoint for another
important VSR group (recreational hikers in surrounding Country Parks) and the
location on High Junk Peak (Tiu Yue Yung) at 344m m.p.d. is the focal viewpoint
from the High Junk Peak Country Trail
and as such represents the worst case scenario. Recreational hikers will have
direct panoramic views across the entire TKO side of the project including the
TKO interchange, the TKO tunnel portal and the Road P2 reclamation.
Photomontage from VSR TKO-REC2 to TKO
Interchange (Figure no.s 10.8.5.10 to 10.8.5.11)
10.8.13 This is a representative viewpoint for hikers
along the western view shed of TKO and the location on Devil’s Peak at 222m
m.p.d is the principal viewpoint from the Wilson Trail. It has direct panoramic
views to the north and east across Junk Bay which will include part of the TKO
interchange.
Photomontage from VSR LT-T1 to Lam Tin Interchange (Figure no.s 10.8.7.2
to 10.8.7.3)
10.8.14 This is a representative viewpoint for seaborne travellers
in Lei Yue Mun Channel and also VSRs along the Hong Kong Island Waterfront. The
photograph was taken from a ferry (at approximately 3m m.p.d.) and as seaborne
travellers approach the project site more closely than VSRs on the Hong Kong
waterfront, this is considered the worst case scenario. Viewers have an
extensive view of the Lam Tin Interchange and the greening
mitigation measures employed on the surrounding quarry slopes.
Photomontage from VSR LT-GIC1 to Lam Tin Interchange (Figure no.s 10.8.7.4
to 10.8.7.5)
10.8.15 This is a representative viewpoint for VSRs in the school
east of the EHC and is taken from an elevation of approximately 40m m.p.d.
Staff and pupils will have a panoramic view west across the EHC
towards the Lam Tin Interchange. Due to its proximity and elevation it
represents a worst case scenario for viewers to the east of the interchange.
Photomontage from VSR LT-R5 to Lam Tin Interchange (Figure no.s 10.8.7.6
to 10.8.7.7)
10.8.16
This is
a representative viewpoint for highly sensitive VSR groups in high-rise
residential developments to the east. The elevation of the viewpoint is
approximately 125m m.p.d. Due to the elevated viewpoint, residents will
have panoramic views to the west over the Lam Tin Interchange and this
therefore represents a worst case scenario. It is likely that this VSR group
will increase in future as more residential redevelopment takes place.
Photomontage from VSR LT-R4 to Lam
Tin
portal area (Figure no.s 10.8.7.8
to 10.8.7.9)
10.8.17 This is a representative
viewpoint for highly sensitive VSR groups in high-rise residential developments
to the north. The photograph was taken from Yau Lai Estate and the elevation of the viewpoint
is approximately 150m m.p.d. Residents will have elevated panoramic views to
the south over the Lam Tin Interchange and this therefore represents a worst
case scenario.
10.9
Evaluation
of Residual Impacts
Prediction of Significance of Landscape and Visual
Impacts
10.9.1
The potential
significance of the landscape and visual impacts during the construction and
operation phases, before and after mitigation, are provided in Tables 10.6.3, 10.6.4, 10.7.1 and 10.7.2. The
assessment has adopted the methodology described in Section 10.3 and assumes
that the assessed design is implemented and that the mitigation measures identified
in Tables 10.8.1 and 10.8.2 are implemented and that the
full effects of the
soft landscape mitigation measures would be realized after 10 years. The
residual landscape and visual impacts of the works after the Construction Phase
and during the Operational Phase are summarised below. Residual Landscape
Impacts at Year 10 at TKO and LT are mapped on Figure No.s 10.9.1, 10.9.3 and 10.9.2,
10.9.4 respectively. Residual Visual
Impacts at Year 10 at TKO and LT are mapped on Figure No.s 10.9.5 to 10.9.7 and 10.9.8, 10.9.9
respectively.
Residual
Landscape Impacts at TKO
10.9.2
For the Junk Bay
sea water body (TKO-LR1) the
Moderate impacts experienced during the Construction Phase after the
implementation of mitigation measures due to the loss of sea waterbody area of
Junk Bay would reduce to Slight at Day 1. This
will be due primarily to the effects of reducing the area of reclamation and
sensitive design of the elevated road structure and piers. As planting on these
elements will not mitigate the loss of sea waterbody area, the residual impact will
remain the same at Year 10.
10.9.3
For the natural
rocky shore along Chiu Keng Wan Coastline (TKO-LR2)
the Moderate impacts experienced during the Construction Phase after the
implementation of mitigation measures due to the loss of approximately 180m of
natural coastline would be reduced to Slight
at Day 1 and
Year 10 of the Operational Phase following mitigation. This will be due
primarily to the effects of reducing the area of impact. As natural coastline
cannot be reinstated, the residual impact remains the same at Year 10.
10.9.4
For the amenity / roadside planting on modified slopes along Road D4 and Road P2 (TKO-LR3D) the Moderate impacts experienced during the Construction
Phase after the implementation of mitigation measures would stay as Moderate at Day 1 and reduce to Slight at Year 10 of the Operational Phase due to
compensatory roadside tree planting which will progressively mature.
10.9.5
For the
grassland/ shrubland mosaic at Chiu Keng Wan Shan (TKO-LR5A) the Moderate impacts experienced during the Construction
Phase after the implementation of mitigation measures due to the loss of
approximately 3ha of area due to the construction of the tunnel portal slopes would
be reduced to Slight at Day 1 and remain
as Slight at Year 10 of the
Operational Phase following mitigation. The reason there is no change with time
is that the nature of the compensatory planting is different from that of the
original resource (climbers and shrubs rather than natural grassland/shrubland
mosaic). Whilst the proposed planting will provide greening to the new slopes
it will not be a continuous cover as per the existing condition.
10.9.6
For streams at
Junk Bay Chinese Permanent Cemetery and Chiu Keng Wan Shan (TKO-LR6B), Moderate impacts during construction will be reduced to
Slight at Day 1 due to reinstatement
of adjacent planting. Impacts will reduce to Insubstantial at Year 10 as the natural
system within the stream course re-establishes.
10.9.7
All the other
landscape resources identified at TKO (TKO-LR3A,
TKO-LR3B, TKO-LR3C, TKO-LR4, TKO-LR5B, TKO-LR6A, TKO-LR7, TKO-LR8, TKO-LR9)
will experience Insubstantial
Residual Impacts at Day 1 and Year 10 respectively regardless of mitigation
measures.
10.9.8
For the Junk Bay
Inshore Water Landscape (TKO-LCA1) the
Substantial impacts experienced after the implementation of mitigation measures
during the Construction Phase will be reduced to Moderate at Day 1 due to the absence of temporary construction
works and plant and due to the positive effects of mitigation measures,
particularly the sensitive design of structures and finishes. These impacts
stay as Moderate at Year 10 because
the planting elements on the interchange and viaducts over the water areas will
not have a significant effect in further mitigating the impacts.
10.9.9
For Chiu Keng Wan
Coastal Upland and Hillside Landscape (TKO-LCA3), mixed Modern Comprehensive Urban Development Landscape (TKO-LCA4) and the reclamation/ ongoing Major
Development Landscape at proposed Tseung Kwan O Town Centre south (TKO-LCA5), Moderate impacts will be experienced after the implementation of mitigation
measures during the Construction Phase. Chiu Keng Wan
Coastal Upland and Hillside Landscape (TKO-LCA3) will stay as Moderate at Day 1 as the positive
effects of mitigation measures, particularly the mitigation planting on the
tunnel portal slopes and the green roof of the tunnel portal building will not
have established sufficiently to reduce the significance. As the slope greening measures on the tunnel portal slopes
integrate the portal into the surrounding landscape character area, the
residual impact will be reduced to Slight
by Year 10 of the Operational Phase. During the
Operation Stage, the mixed Modern
Comprehensive Urban Development Landscape (TKO-LCA4) and the reclamation/ ongoing Major
Development Landscape at proposed Tseung Kwan O Town Centre south (TKO-LCA5) will experience
Slight residual impacts at Day 1 due
to the positive effects of mitigation measures and be reduced
to Insubstantial at Year 10 by the effects of the
maturing planting works.
10.9.10 For the remaining Landscape Character Areas (TKO-LCA2, TKO-LCA6, TKO-LCA7), Insubstantial impacts will be experienced before the implementation
of mitigation measures due to the construction of the TKO Interchange in Junk
Bay and it will remain as Insubstantial
at Day 1 and Year 10 of the Operational Phase regardless of mitigation.
Residual Landscape Impacts at Lam Tin
10.9.11 The following residual impacts are based on the
cumulative impact of the TKO-LT Tunnel and the concurrent CBL.
10.9.12 Amenity/roadside
planting/vegetation on modified slopes at Former Quarry (LT-LR8B) will experience
the same Substantial impacts after the implementation of mitigation
measures during the Construction Phase due to the necessity of felling a
minimum number of existing trees. The impact of the loss of large numbers of
existing trees within the ex Cha Kwo Ling Kaolin Mine Site will stay as Substantial at Day 1 even with the reinstatement of the planting as it will be immature and not yet provide
significant mitigation effect. This will have reduced to Moderate by year 10 of the Operational Phase due to the maturing of
the planting. It is to be expected that the residual impact will continue to
decline as the planting further matures with age.
10.9.13 All other Landscape Resources LT-LR1, LT-LR2, LT-LR3, LT-LR4,
LT-LR5, LT-LR6, LT-LR7, LT-LR8A, LT-LR9A and LT-LR9B will
experience Insubstantial residual impacts at Year 10 of the Operation
Phase.
10.9.14 The Former Quarry Landscape (occupied) (LT-LCA9), will experience
the same Substantial impacts after the implementation of mitigation
measures during the Construction Phase due to the necessity of felling a
minimum number of existing trees. However, peripheral tree screens will be
maintained to mitigate initial impacts. In addition, the central area of the
LCA is open and the works will not have a detrimental effect on this portion.
The impact on landscape character within the ex Cha Kwo Ling Kaolin Mine Site
will be reduced to Moderate at Day 1
due to extensive compensatory planting and sensitive design of road and
associated building elements including noise enclosures. This will have reduced
to Slight by year 10 of the
Operational Phase due to the maturing of the planting. It is to be expected
that the residual impact will continue to decline as the planting further
matures with age.
10.9.15 All remaining Landscape Character Areas including LT-LCA1,
LT-LCA2, LT-LCA3, LT-LCA4, LT-LCA5, LT-LCA6, LT-LCA7 and LT-LCA8
will experience Insubstantial
residual impacts at Year 10 of the Operation Phase.
Residual
Visual Impacts at Tseung Kwan O
10.9.16 The following residual impacts are based on the
cumulative impact of the TKO-LT Tunnel and the concurrent CBL.
10.9.17 The existing VSRs with the highest residual visual
impacts at Year 10 include the Eesidents and workers in TKO Area 86/LOHAS Park (TKO-CDA1B). They will experience residual impacts of Moderate significance at Year 10 after
mitigation measures due to the wide unobstructed views towards the site. Residents in Ocean Shores (TKO-R3) will experience residual visual impacts of Moderate significance in Year 10 due to
their close proximity and unobstructed outlook over the site. Also, Residents in planned high rise estates along the
southern edge of the TKO reclamation (TKO-R14d,
TKO-R14e and TKO-R14f) and Rrecreational users of the planned open space at Area
68 (TKO-O3) will experience residual
visual impacts of Moderate
significance in Year 10 due to their close proximity and unobstructed outlook
towards the site.
10.9.18 Seaborne leisure travellers in Junk Bay (TKO-T1) will experience residual
visual impacts of Slight/Moderate
significance at Year 10 after mitigation measures due to the potentially close
low level views of the elevated interchange and reclamation. Pedestrians on the
footpath link from Ocean Shores to Junk Bay Chinese Permanent Cemetery (TKO-T5) will also experience residual
visual impacts of Slight/Moderate
significance at Year 10 after mitigation measures due to the proximity to the
TKO Portal and unobstructed views of the TKO Interchange and Road P2
reclamation.
10.9.19 Users of planned recreational facilities at TKO Stage
1 Landfill, Area 77 (TKO-REC7) and Users
of the footbridge crossing the Eastern Channel (TKO-T7*) will experience residual impacts of Slight/Moderate significance at Year 10 after mitigation measures
due to their wide unobstructed views towards the site.
10.9.20 In the TKO area, Travellers at the TKO MTR Station and
along Po Yap Road and Chui Ling Road
(TKO-T4), Residents of Metrotown (TKO-R4),
Park Central (TKO-R5), Workers in
the planned GIC Development at TKO Area 67
(TKO-GIC9), Existing and planned workers
at TKO Industrial Estate (TKO-OU1A and OU1B respectively), Visitors to JBPCC (TKO-OU2),
hikers on the Wilson Trail (TKO-REC2) will experience residual
visual impacts of Slight
significance at Year 10 after mitigation measures.
10.9.21 On Hong Kong Island, Residents of Heng Fa Chuen (TKO-R1) and Users of Heng Fa Chuen
Playground (TKO-O1), Users of Siu
Sai Wan promenade (TKO-O2), Residents
& users of Island Resort residential area and promenade (TKO-R8), Residents in Chai Wan high
rise estates (TKO-R10), Visitors of
Lei Yue Mun Holiday Village/Lei Yue Mun Park and the H.K. Museum of Coastal
Defence (TKO-REC3A and REC3B respectively), and Seaborne leisure travellers in Lei Yue Mun and Tathong
Channel (TKO-T2) will experience
residual visual impacts of Slight
significance at Year 10 after mitigation measures.
10.9.22 All remaining
VSRs will experience
residual visual impacts of Insubstantial significance at Year 10 after mitigation measures.
10.9.23 More detailed descriptions for each of the VSRs
identified in the report as providing residual visual impacts is provided below. The residual
impacts are based on the cumulative impact of the TKO-LT Tunnel and the
concurrent CBL.
10.9.24 TKO-CDA1B: Following the implementation of mitigation measures residents and
workers in the planned development at TKO Area 86 CDA/LOHAS Park will still experience
Substantial visual impacts during the Construction Phase as they will have
unobstructed views of the project site and the highly visible temporary impacts.
During the Operation Phase, the VSR group will experience Moderate/Substantial visual impacts at Day 1 due to the absence of
the temporary construction impacts and the positive effects of the mitigation
measures including design forms, finishes and planting works. At Year 10, the
maturing of the mitigation planting will reduce residual visual impacts to Moderate.
10.9.25 TKO-O3*: Following the implementation of mitigation measures
users of planned recreational facilities at Open Space at TKO Area 68 will
still experience Substantial visual impacts during the Construction Phase due
to the proximity and scale of the development and unobstructed views towards
it. The visual impacts will be reduced to Moderate/Substantial
at Day 1 of the Operational Phase due to the absence of temporary construction
plant and the positive effects of the mitigation measures including design
forms, finishes and planting works. At Year 10 visual impacts will be reduced
further to Moderate significance due
to the maturing mitigation planting, in particular on the TKO tunnel portal and
the Road P2 reclamation.
10.9.26 TKO-R3: after the implementation of mitigation measures
residents at Ocean Shores will still experience Substantial visual impacts
during the Construction Phase as mitigation measures will not be able to
significantly reduce the degree of visual impact caused by temporary
construction activity and plant. These visual impacts will be reduced to Moderate/Substantial at Day 1 due to
the absence of temporary construction impacts and the positive effects of
planting and paving of previously exposed surfaces and the use of sensitive
design and finishes for structures. By Year 10 the residual visual impact will
be reduced to Moderate due to the
extensive mature planting works on the reclamation area, landscape deck,
roadsides and elevated viaducts. The degree of impact will also be lessened by
the integration of the project into the new planned context of the TKO Town
Centre South extension which includes ground level public open space (TKO-O3).
10.9.27 TKO-R14d*,
TKO-R14e* and TKO-R14f*: Following the implementation
of mitigation measures residents in planned new developments on the TKO Town
Centre South Reclamation will experience Substantial visual impacts during the
Construction Phase following mitigation due to their unobstructed views of
temporary construction plant and activity within Junk Bay, on the new Road P2 reclamation
area and at TKO tunnel portal. These visual impacts will be reduced to Moderate/Substantial at Day 1 following
completion of the works and removal of temporary construction impacts and the
positive effects of mitigation planting and hardworks design and finishes. The
residual visual impacts will be further reduced to Moderate at Year 10 due to the effect of maturing planting on the
elevated interchange viaducts, on the reclamation and tunnel portal.
10.9.28 TKO-T1: After the implementation of mitigation measures
seaborne travellers in Junk Bay will experience Moderate/Substantial visual
impacts during the Construction Phase due to on-going construction activity and
plant including cranes, scaffolding and barges. These visual impacts will be
reduced to Moderate at Day 1 due
largely to the disappearance of temporary construction works, their replacement
by the completed works which will incorporate visual mitigation measures
including planting and sensitive design of form, and finishes. The effect of
maturing planting on the elevated interchange viaducts, on the reclamation and
tunnel portal will progressively integrate the development throughout the
Operational Phase resulting in Slight/Moderate
residual visual impacts at Year 10.
10.9.29 TKO-T5: Following the implementation of mitigation measures
pedestrians on the JBCPC footpath
will experience Moderate/Substantial visual impacts during the Construction
Phase as the viewing distance will be very close and mitigation measures will
have little overall effect in reducing the effects of the temporary
construction impacts. During the Operation Phase, the VSR group will experience
Moderate visual impacts at Day 1
once the completed project is viewed with the positive effects of mitigation
measures including greening of the tunnel portal slopes, reclamation area and
sensitive design and finishes of highway structures and buildings. The planting
works will progressively soften the tunnel portal and reclamation area
resulting in Slight/Moderate residual visual impacts at Year 10.
10.9.30 TKO-T7: Following the implementation of mitigation measures
pedestrians on the new Southern Footbridge crossing the Eastern Channel will
experience visual impacts of Moderate/Substantial significance during
construction due to the clear views of the works to the south. This will be
reduced to Moderate at Day 1 with
views of the completed works with the positive effects of mitigation measures
including aesthetic design of structures, finishes and planting. Residual
visual impacts at Year 10 will be reduced to Slight/Moderate due to the effects of maturing mitigation planting.
10.9.31 TKO-GIC9*: Following the implementation of mitigation measures
future workers in the planned G/IC development in TKO Area 67 will experience
Moderate visual impacts during the Construction Phase due to the temporary
construction impacts. These VSRs will only experience the adjacent road works
as views to the south will largely be screened from view by planned residential
development to the south. Visual impacts will be reduced to Slight-Moderate at Year 1 due to
mitigation measures, primarily roadside planting and hard landscape treatments
and aesthetic design of footbridges. At Year 10 the effects of mature planting
on the roadsides will reduce residual visual impacts to Slight.
10.9.32 TKO-OU1A: After the implementation of mitigation measures
workers in TKO Industrial Estate will experience Moderate visual impacts during
the Construction Phase due to the temporary construction impacts required to
construct the interchange, reclamation and tunnel portal. These will be reduced
to Slight/Moderate at Day 1 once the
temporary impacts have ceased and views of the sensitively designed permanent
TKO-LT structures and finishes and associated planting are available. The
residual visual impacts will be further reduced to Slight at Year 10 due to the maturing planting on tunnel portal and
reclamation.
10.9.33 TKO-OU2: After the implementation of mitigation measures
visitors and workers at Junk Bay Chinese Permanent Cemetery will experience
Slight/Moderate visual impacts during the Construction Phase. These visual
impacts will be reduced to Slight at
Day 1 once the temporary impacts of construction works including cranes and
barges have disappeared. This will be due to the positive effects of mitigation
measures including sensitive design of form and finishes of the viaduct
structures. Due to the viewpoint, VSRs will not experience the planted portions
of the project and thus the visual impacts remain the same (Slight) at Year 10.
10.9.34 TKO-O1 and TKO-O2:
After the implementation of mitigation measures Lo Shue Pai Park and Siu Sai
Wan Promenade will experience Slight/Moderate visual impacts during the
Construction Phase due the effects of temporary construction plant. These
visual impacts will be reduced to Slight
at Day 1 during the Operation Phase due largely to the disappearance of
temporary construction plant and the positive effects of sensitive design of
form and finishes of the viaduct structures. Due to the viewpoint, the effect of maturing planting on the elevated
interchange viaducts will not have a significant effect in reducing the visual
impact further and therefore the degree of visual impact will remain the same (Slight) throughout the Operational
Phase.
10.9.35 TKO-R1 and TKO-R8:
After the implementation of mitigation measures residents in Heng Fa Chuen and
Island Resort will experience Moderate visual impacts during the Construction.
These visual impacts will be reduced to Slight
at Day 1 due to the absence of the temporary construction impacts and the
positive effects of sensitive design of form and finishes of the viaduct
structures and planting on reclamation and portal slopes. Due to the viewpoint,
the effect of maturing planting on the elevated interchange viaducts will not
have a significant effect in reducing the visual impact further and therefore
the degree of visual impact will remain the same (Slight) throughout the Operational Phase.
10.9.36 TKO-R4 and TKO-R5: Residents in Metro Town and Park Central will
experience Moderate visual impacts during the Construction Phase as much of the
project site will be screened from view by planned
development to the south. Moderate impacts will be generated by temporary construction works along Po Yap
Road. These visual
impacts will be reduced to Slight/
Moderate at Day 1 following the removal of the temporary construction plant
and due to the positive effects of mitigation measures including roadside
planting, well designed streetscape and sensitive
finishes on structures. Residual impacts will be reduced to Slight at Year 10 due to the effect of maturing
mitigation planting.
10.9.37 TKO-R10: After the implementation of mitigation measures
residents Chai Wan high-rise estates will experience Moderate visual impacts
during the Construction Phase. These visual impacts will be reduced to Slight at Day 1 with the removal of
temporary construction impacts, views of the completed works and the
implementation mitigation measures including sensitive design of form and
finishes of the viaduct structures and planting on reclamation and portal
slopes. Due to the viewpoint, the effect of maturing planting on the elevated
interchange viaducts will not have a significant effect in reducing the visual
impact further and therefore the degree of visual impact will remain the same (Slight) throughout the Operational
Phase.
10.9.38 TKO-REC2: After the implementation of mitigation measures,
hikers along the Wilson Trail will experience Slight/Moderate visual impacts
during the Construction Phase due to temporary construction plant and activity.
Hiker’s views will be ‘over’ the project works towards the broader expanse of
Junk Bay and the hills of Clearwater Bay Peninsula in the east which will
reduce the perceived impact. The visual
impacts will be reduced to Slight at
Day 1 with the absence of temporary construction plant and machinery, views of the
completed works and the implementation of mitigation measures including
planting and sensitive design and finishes to built structures. Due to the
angle of view, only the viaduct portion of the project will be visible and the
effect of maturing planting will not be seen, resulting in Slight visual impacts remaining at Year 10.
10.9.39 After the implementation of mitigation measures,
visitors to Lei Yue Mun Holiday Village, Lei Yue Mun Park and the Hong Kong
Museum of Coastal Defence (TKO-REC3A, TKO-REC3B respectively) will
experience Slight/Moderate visual impacts during the Construction Phase. These
impacts will be largely generated by temporary construction plant and activity
and the effects are reduced by distance of view. These visual impacts will be
reduced to Slight at Day 1 following
the disappearance of temporary construction works and replacement with views of
the completed interchange and reclamation and due to the positive effects of sensitive
design of the bridge structure and reclamation and portal. Visual impacts will
remain Slight ay Year 10 as the
effect of maturing mitigation planting will not be visible from their view
points.
10.9.40 Following the implementation of mitigation measures
travellers at the TKO MTR Station and along Po Yap Road and Chui Ling Road (TKO-T4) will experience Moderate visual impacts during the Construction Phase
due to temporary construction plant and activity. During the Operation Phase,
the VSR group will experience Slight/Moderate
visual impacts at Day 1 with the absence of the construction works, views
of the completed roads and footbridges and the positive effects of the
mitigation measures including sensitive design of form and finish, streetscape
design and planting. At Year 10 the residual visual impact will be reduced to Slight due to the maturing roadside planting.
The roadworks will also be seen in the context of the completed G/IC, Open
Space and Residential developments on the TKO reclamation to the south.
Residual
Visual Impacts on Future
Planned VSRs in Tseung Kwan O
10.9.41 For the purposes of this assessment, it is assumed
that the future planned developments will be constructed after the
completion of the TKO-LT Tunnel. Assessment of significance of impact during
the Construction Phase is therefore not applicable and neither is assessment of
significance at Day 1 of the Operation Phase.
10.9.42 Workers in planned extension to the TKO Industrial
Estate Extension (TKO-OU1B) will
experience Slight/Moderate
visual impacts
at Year 10 due to the visual mitigation measures including aesthetic design of
structures, finishes and maturing planting on tunnel portal and reclamation.
10.9.43 Users of planned recreational facilities at TKO Stage
I Landfill, Area 77 (TKO-REC7) will experience Slight/Moderate visual impacts at Year 10 due to the visual
mitigation measures and the maturing planting on tunnel portal and reclamation.
Residual Visual Impacts in Lam Tin
10.9.44 The existing VSRs with the highest residual visual
impacts at Year 10 are residents in surrounding high rise residential estates
which have relatively unobstructed elevated views and they will experience
residual visual impacts of Moderate
significance at Year 10. These VSRs
include residents at Ping Tin Estate and Hong Ngar Court (LT-R3), Yau Lai Estate (LT-R4A) , Cha Kwo Ling
housing developments west
of interchange (LT-R9B*), Kwong Tin
Estate and Hong Pak
Court (LT-R11) and Yau Tong Bay
CDA Development (LT-CDA1).
10.9.45 Receivers who will experience visual impacts of Slight significance include staff and
pupils of schools east of EHC (LT-GIC1),
residents of The Canaryside and The Spectacle in Yau Tong (LT-R5), users of Yau Tong Road Playground (LT-O1), users of the public open space
on the Cha Kwo Ling promenade (LT-O5*)
and users of the planned open space north west of the Lam Tin Interchange (LT-O6*).
10.9.46 All remaining VSRs will experience residual visual
impacts of Insubstantial
significance at Year 10 after mitigation measures.
10.9.47 The residual visual impacts for all the individual
VSRs in Lam Tin are described in more detail below.
10.9.48 Following the implementation of mitigation measures
residents of the existing Ping Tin Estate and Hong Ngar Court (LT-R3), Yau Lai Estate (LT-R4A) and Kwong Tin Estate and Hong Pak Court (LT-R11) will continue
to experience Substantial visual impacts during the Construction Phase due to
their unobstructed elevated views across the site. During the Operation Phase,
visual impact significance will be reduced to Moderate/Substantial at Day 1 due to the absence of the temporary
construction plant and activity and the effects of positive mitigation measures
on the completed Lam Tin Interchange including sensitive design of buildings
and structures and extensive planting at grade, on slopes and on buildings and
structures. At Year 10 the residual visual impacts will be reduced to Moderate due to the maturing of the
planting.
10.9.49 Following the implementation of mitigation measures
residents in the planned Yau Tong Bay CDA development (LT-CDA1) and The planned
housing development at Cha Kwo Ling north west of the Lam Tin Interchange (LT-R9B) will
experience Substantial visual impacts during the construction stage due to
their close, elevated views into the site of the Lam Tin Interchange. At Day 1,
the impact significance will be reduced to Moderate/Substantial
as views of construction will be replaced by views of the completed interchange
with the positive effects of sensitive visual impacts including sensitive
design of buildings and structures and extensive planting at grade, on slopes
and on buildings and structures. At Year 10 the residual residual visual
impacts will be reduced to Moderate
due to the maturing of the planting.
10.9.50 Following the implementation of mitigation measures
staff and pupils at schools east of EHC (LT-GIC1) will experience
Moderate visual impacts due to their relatively low sensitivity and because of
the screening effect of existing trees and advertising hoardings along the
eastern boundary of the former quarry site. During the Operation Phase, these
VSR group will experience Slight/Moderate
visual impacts at Day 1 due to the effects of the mitigation measures including
sensitive design of buildings and structures and extensive planting at grade,
on slopes and on buildings and structures. At Year 10 the residual visual impacts
will be reduced to Slight due to the
maturing of the planting, particularly along the eastern edge of the Lam Tin
Interchange.
10.9.51 Following the implementation of mitigation measures
residents in The Canaryside and The Spectacle in Yau Tong (LT-R5) will continue
to experience Moderate visual impacts during the Construction Phase due to
their elevated views across the site. During the Operation Phase, visual impact
significance will be reduced to Slight/Moderate
at Day 1 due to the effects of the mitigation measures including sensitive
design of buildings and structures and extensive planting at grade, on slopes
and on buildings and structures. At Year 10 the residual visual impacts will be
reduced to Slight due to the
maturing of the planting, particularly along the eastern edge of the Lam Tin
Interchange.
10.9.52 Following the implementation of mitigation measures users
of Yau Tong Road Playground (LT-O1) will
experience only Moderate visual impacts during the Construction Phase due to screening
provided by the playground fencing and amenity tree planting and the
effectiveness of screen hoardings and retention of existing tree screens along
the eastern edge of the Lam Tin Interchange site. During the Operation Phase,
visual impact significance will be reduced to Slight/Moderate at Day 1 due to the effects of the mitigation
measures including sensitive design of buildings and structures and extensive
planting at grade, on slopes and on buildings and structures. At Year 10 the
residual visual impacts will be reduced to Slight
due to the maturing of the planting, particularly along the eastern edge of the
Lam Tin Interchange.
10.9.53 Following the implementation of mitigation measures
users of the planned public open space on the promenade south of Cha Kwo Ling
Road (LT-O5*): will
experience Moderate visual impacts at Day 1 due to the screening effect of the
wooded ridge screening the Lam Tin Interchange to the north. During the
Operation Phase, visual impact significance will be reduced to Slight/Moderate at Day 1 due to the effects
of the mitigation measures including sensitive design of buildings and
structures and extensive planting at grade, on slopes and on buildings and
structures. At Year 10 the residual visual impacts will be reduced to Slight due to the maturing of the
planting, particularly along the southern edge of the Lam Tin Interchange.
10.9.54 Following the implementation of mitigation measures
users of the public open space north west of the ex Cha Kwo Ling Kaolin Mine
Site (LT-O6*) will
experience Moderate visual impacts at Day 1 as most of the Lam Tin Interchange
will be screened by the former quarry walls and associated tree planting.
During the Operation Phase, visual impact significance will be reduced to Slight/Moderate at Day 1 due to the
effects of the mitigation measures including sensitive design of buildings and
structures and extensive planting at grade, on slopes and on buildings and
structures. At Year 10 the residual visual impacts will be reduced to Slight due to the maturing of the
planting, particularly along the southern edge of the Lam Tin Interchange.
Cumulative Landscape
and Visual Impacts
10.9.55 The landscape and visual impacts generated by the
TKO-LT Tunnel must be assessed in the context of the associated impacts of the
concurrent projects (as described in Section
10.4.19 above).
10.9.56 The major projects which are planned to be constructed
concurrently with the TKO-LT Tunnel around TKO include the CBL, TKO Town Centre
South Development, Cycle tracks and promenade developments around TKO Bay, TKO
Area 86 Development, Residential Developments in Area 85, G/IC developments in
Area 78 and the SENT Landfill Extension in Area 137. These developments are
largely on reclaimed land or currently vacant sites and landscape impacts will
therefore be minimal. Visual impacts will be created by the new building works,
however building heights are controlled through planning regulations with the
intention of creating a positive overall composition to the new town
extensions. The combined effect of these projects will be to transform the
existing TKO Town Centre South reclamation and waterfront into a modern
new-town. The conversion of large areas of existing reclamation and vacant
waterfront will generally enhance the landscape quality of the area. The
portion of the TKO-LT Tunnel works affecting the Town Centre South reclamation
will be fully integrated into the new townscape. TKO interchange and its
associated reclamation will affect the Junk Bay and natural hillside landscape
resources and will be highly visible as a new landscape element. If the TKO-LT Tunnel was the only proposed
development in TKO, the relative scale of the landscape and visual impacts
would be perceived as greater. However, when viewed in the context of the other
major concurrent developments, the landscape and visual impacts generated by
the TKO-LT Tunnel are perceived as compatible and acceptable when the effect of
mitigation are taken into account. The
tunnel and interchange will form part of the overall new town extension and the
landscape and visual impacts will take place against a backdrop of other major
construction works.
10.9.57 The cumulative landscape impacts that the TKO-LT
Tunnel itself brings to the development context at TKO include the following:
·
Loss of water
body area of Junk Bay due to reclamation and enclosure of part of it by the
elevated viaducts (TKO-LR1). This
cannot be replaced but can be mitigated through sensitive design of the
reclamation and viaduct piers and structures.
·
Loss of a section
of natural rocky shore coastline (approximately 180m – TKO-LR2); this cannot be replaced but can be mitigated through
appropriate planting reinstatement.
·
Loss of
approximately 75 no. amenity roadside trees (TKO-LR3D). These can be replaced by compensatory planting.
·
Loss of
approximately 3ha of grassland/shrubland mosaic Chiu Keng Wan Shan (TKO-LR5A). This cannot be replaced but
the slopes that cause the impact will be vegetated with alternative appropriate
species which will mitigate the impacts.
·
Minor impacts on
a stream at Chiu Keng Wan Shan (TKO-LR6B).
The impacts to this stream will be temporary and it will recover its natural
state in time following reinstatement works.
10.9.58 The cumulative visual impacts that the TKO-LT Tunnel
itself brings to the development context at TKO include the following:
·
The TKO
Interchange in Junk Bay including piers and viaducts. This will form a highly
visible new element and cannot be screened or hidden. Mitigation can only be
addressed through sensitive design of form and finishes.
·
The TKO Tunnel
Portal building and associated slope works. The portal building is designed to
integrate with the existing slopes and be an attractive building appropriate to
a contemporary engineering structure. The visual impact of the slopes will be
mitigated through time due to extensive planting works.
·
The Road P2
reclamation area which acts as a landing for the interchange slip roads. The
visual impact of this element is greatly reduced by its relationship to the
existing reclamation coastline. The visual impacts of Road P2 are minimized by
decking in front of Ocean Shores. Extensive landscape treatment is proposed for
the reclamation area which will enhance the existing outlook (as well as offer practical
benefits of increased public open space and improvements to pedestrian and cycling
circulation).
·
Junction and road
improvements and footbridge construction at Po Yap Road. Whilst these will
generate visual impacts, they are modifications to an existing road system and
the net increase in visual impact will be minor and can be offset through
sensitive design and compensatory planting.
10.9.59 Overall, it is considered that the
cumulative landscape and visual impacts generated by the TKO-LT Tunnel
at TKO are acceptable within the context of the transitional landscape of which
it forms a part.
Lam Tin
10.9.60 The major concurrent projects in the Lam Tin area are
the comprehensive development at Yau
Tong Bay CDA zone and the planned residential development on the Ex-Cha
Kwo Ling Kaolin Mine Site ("R(A)4" zone). A planning
application has been submitted for a mixed residential, commercial and
community use development along the waterfront of Yau Tong Bay. The landscape
impacts would be relatively small as it would be constructed on vacant
industrial land. The visual impacts would be significant however with the
likely addition of a large number of residential towers. The planning intent is
to enhance the existing townscape
setting which is currently run-down and derelict. Residential developments have
been planned on the Ex-Cha Kwo Ling Kaolin Mine Site to the north west of the
Lam Tin Interchange and the waterfront is zoned for public open space and G/IC
uses. The area is undergoing rapid change from its existing condition. If the Lam Tin Interchange was the only
proposed development in the area, the landscape and visual impacts would appear
relatively more significant. However, as it will be constructed within the
context of the planned residential development to the west and the CDA
development to the east, viewed in the context of the cumulative impacts the
relative impacts of the project appear to be less.
10.9.61 The cumulative landscape impacts that the TKO-LT
Tunnel itself brings to this development context at Lam Tin include the
following:
·
Loss of existing
vegetation (including approximately 960 existing trees) at amenity/ roadside planting/vegetation
on modified slope at Former Quarry (LT-LR8B). Extensive compensatory planting
is proposed to offset this loss.
·
Loss of a portion
(only 12 no. trees will be impacted along the edge of the LR which has a total
area of in an area of approximately 6ha) of grassland/shrubland mosaic at the
ex- Cha Kwo Ling Kaolin Mine Site (LT-LR98). This area will be reinstated with
appropriate planting species.
·
Loss of roadside
trees at Yau Tong Bay Industrial Waterfront Area (LT-LR2) and due to minor road
amendments along the EHC corridor. All affected trees will be replaced with
compensatory roadside planting.
10.9.62 The cumulative visual impacts that the TKO-LT Tunnel
itself brings to this development context at Lam Tin include the following:
·
The Lam Tin
Interchange with depressed carriageway, elevated slip road connections and
associated service buildings. This will
transform the character of the former quarry site to elevated VSRs in
surrounding high-rise residential towers.
·
The existing site
consists of a tree fringed enclosure with an open paved central area used as a
temporary storage area. The rock-cut walls of the quarry form a distinctive
edge to the northern and western edge of the site. The proposed interchange
will result in a more intensive use of the space and visually it will result in
a more dynamic scene with a greener outlook overall due to extensive mitigation
planting.
·
Visual impacts
will also be caused by the road reconfigurations along the EHC corridor and the
proposed roundabout to the south on Cha Kwo Ling Road. The existing visual
character of this area is already heavily dominated by roads and these
modifications will not represent a significant increase in visual impact.
·
In addition,
there is the opportunity to rationalize and enhance the visual quality of the
area, which is currently has a rather neglected atmosphere, through the
introduction of consistent roadside treatments.
10.9.63 Overall, it is considered that the cumulative
landscape and visual impacts generated by the TKO-LT Tunnel at TKO are
acceptable within the context of the transitional landscape of which it forms a
part. The planning intent for the area sets the development within a zone of G/IC,
Residential and CDA lands uses. The principle landscape visual impacts can be
mitigated through mitigation measures including extensive compensatory planting
and appropriate, sensitive design and finishing of built structures.
Compatibility of TKO-LT Tunnel with Planning Intent
10.10.1
From
a review of the current planning legislation and OZP’s the proposed development
is compatible with the broad planning goals. Provision has been made on the
Approved Tseung Kwan OZP No. S/TKO/20 for the TKO-LT Tunnel (a ‘cross bay
bridge road’ has been indicated on the Tseung Kwan O OZP since 1992) and the
area affected on the Lam Tin side is primarily zoned as GIC uses which is
compatible with the intended development. Both TKO and Lam Tin are areas in
transition with major developments planned concurrently with the proposed
tunnel.
Residual
Landscape Impacts – TKO
10.10.2 For the Junk Bay sea water body (TKO-LR1) residual impacts would be Slight at Day 1 and Slight at Year 10 of the Operational
Phase following mitigation. This will be due primarily to the effects of
reducing the area of reclamation and sensitive design of the elevated road
structure and piers. As planting on these elements will not mitigate the loss
of sea waterbody area, the residual impact remains unchanged.
10.10.3 For the natural rocky shore along Chiu
Keng Wan coastline (TKO-LR2) the residual impact will be Slight at Day 1 and Year 10 of the
Operational Phase following mitigation. This will be due primarily to the
effects of reducing the area of impact. As natural coastline cannot be
recreated, the residual impact remains the same at Year 10.
10.10.4 For the amenity /roadside planting on modified slopes along Road D4 and Road P2 (TKO-LR3D) the residual impacts would be Slight at Year 10 of the Operational Phase due to compensatory
roadside tree planting which will progressively mature and replace what has
been impacted. The degree of impact would be expected to progressively decline
thereafter with the further growth of the planting.
10.10.5 For the grassland/shrubland mosaic at Chiu Keng Wan
Shan (TKO-LR5A) the residual impact
would be Slight at Year 10 of the
Operational Phase following mitigation. The reason there is no change with time
is that the nature of the compensatory planting is different from that of the
original resource (climbers and shrubs rather than natural grassland/shrubland mosaic).
Whilst the proposed planting will provide greening to the new slopes it will
not be a continuous cover as per the existing condition and it will be of a
different character so it is not a direct replacement of the existing resource.
10.10.6 For streams at Junk Bay Chinese Permanent Cemetery and
Chiu Keng Wan Shan (TKO-LR6B), the
residual impact will be Slight at
Year 10 due to the maturing of the vegetation and the re-establishment of the
natural system within the stream course with time.
10.10.7 Residual impacts on all the other landscape resources
identified (TKO-LR3A, TKO-LR3B,
TKO-LR3C, TKO-LR4, TKO-LR5B, TKO-LR6A, TKO-LR7, TKO-LR8, TKO-LR9) will
experience Insubstantial impacts at
Day 1 and Year 10 respectively regardless of mitigation measures due to the low
level or lack of anticipated impacts.
10.10.8 For the Junk Bay Inshore Water Landscape (TKO-LCA1) the residual impacts will be Moderate at Year 10. The new structures
will be highly visible but they can be mitigated by sensitive design of form
and finish. Because the planting elements on the interchange and viaducts over
the water areas will not have a significant effect, or change significantly
with time (there is no tree planting on the viaduct sections) the effects of
mitigation are experienced at Day 1 and will not change significantly
thereafter.
10.10.9 For Chiu Keng Wan Coastal Upland and Hillside
Landscape (TKO-LCA3) the residual
impact at Year 10 of the Operational Phase will be Slight due to the slope greening measures on the tunnel portal
slopes and the sensitive design of the tunnel portal building with green roof
treatment which will help to integrate the portal into the surrounding
landscape character area.
10.10.10 For the Mixed Modern Comprehensive Urban Development Landscape (TKO-LCA4) ) and the reclamation/ ongoing major development landscape at proposed Tseung Kwan O Town Centre south (TKO-LCA5) , the residual impact will be Slight at Day 1 and
Insubstantial at Year 10 due to the maturing of the vegetation and
the natural re-establishment of natural system within the stream course with
time.
10.10.11 For all the other Landscape Character Areas (TKO-LCA2, TKO-LCA6, TKO-LCA7) the Insubstantial impacts experienced
before the implementation of mitigation measures due to the construction of the
TKO Interchange in Junk Bay will remain as Insubstantial at Year 10 of the
Operational Phase regardless of mitigation due to the low level of anticipated
impacts.
Residual Landscape Impacts – Lam Tin
10.10.12 For the amenity/roadside planting within the former
quarry site (LT-LR8B) the residual
impacts by year 10 of the Operational Phase will be Moderate due to the maturing of extensive compensatory planting at
grade, on slopes and rock-cut benches. It is to be expected that the residual
impact will continue to decline as the planting further matures with age.
10.10.13 All other Landscape Resources LT-LR1, LT-LR2, LT-LR3, LT-LR4, LT-LR5, LT-LR6, LT-LR7, LT-LR8A,
LT-LR9A and LT-LR9B will experience Insubstantial residual impacts at Year
10 due to the low level or absence of anticipated impacts.
10.10.14 For Former quarry site (occupied) Landscape
Character Area (LT-LCA9), the
residual impacts by year 10 of the Operational Phase will be Slight. This will
be due to the combined mitigation effects including sensitive design of
depressed road, associated service and tunnel portal buildings, noise
enclosures and barriers, green slope treatments and extensive compensatory tree
planting. It is to be expected that the residual impact will continue to
decline as the planting further matures with age.
10.10.15 All other Landscape Character Areas LT-LCA1, LT-LCA2, LT-LCA3, LT-LCA4,
LT-LCA5, LT-LCA6, LT-LCA7 and
LT-LCA8 will experience Insubstantial
residual impacts at Year 10 due to the low level or absence of anticipated
impacts.
Residual Visual Impacts – TKO
10.10.16 The change in character of the visual resource of Junk
Bay caused by the TKO-LT Tunnel development must be assessed within the context
of the wider development parameters for the TKO extension. The primary visual
impacts of the project at TKO will be the addition of the TKO Interchange in
Junk Bay, the tunnel portal in the western hill slopes and the road improvement
works with footbridges on the TKO reclamation. Mitigation of the interchange
can primarily be achieved by minimisation of the size and scale of development
and sensitive design of the visible elements. The primary VSRs will be the
surrounding existing and planned residential blocks which will experience
elevated views and the users of the planned waterfront and open space
facilities. Negative views can be mitigated from the level of Substantial to
Moderate by the combined effects of the proposed mitigation measures which
include primarily the minimization of the footprint of the works (particularly
the area of reclamation and the extent of the tunnel portal slopes), sensitive
design of all structures and buildings in terms of scale, form and finishes,
decking of Road P2 with the provision of landscape treatments above, extensive
planting on slopes, reclamation, landscape deck and roadsides.
10.10.17 The existing VSRs with the highest residual visual
impacts at Year 10 are:
·
Residents in
planned new residential development at CDA Area 86/LOHAS Park (TKO-CDA1B) will experience residual
impacts of Moderate significance at
Year 10 after mitigation measures due to the wide unobstructed views towards
the site.
·
Residents in
Ocean Shores (Phases I to III) (TKO-R3) will
experience residual visual impacts of Moderate
significance in Year 10 due to their close proximity and unobstructed outlook
over the site.
·
Residents in planned
high rise estates along the southern edge of the TKO Town Centre reclamation (TKO-R14d, TKO-R14e and TKO-R14f) and
users of the planned open space at Area 68 (TKO-O3)
will experience residual visual impacts of Moderate
significance in Year 10 due to their close proximity and unobstructed outlook
towards the site.
·
Seaborne leisure
travellers in Junk Bay (TKO-T1) and
Seaborne leisure travellers along Lei Yue Mun and Tathong Channel (TKO-T2) will experience residual
visual impacts of Slight/Moderate significance
at Year 10 after mitigation measures due to the potentially close low level
views of the elevated interchange and reclamation. Pedestrians on the JBCPC
footpath (TKO-T5) will also
experience residual visual impacts of Slight/Moderate
significance at Year 10 after mitigation measures due to the proximity to the
TKO Portal and unobstructed views of the TKO Interchange and Road P2
reclamation. Users of planned recreational facilities at TKO Stage 1 Landfill,
Area 77 (TKO-REC7) and Users of footbridge
crossing the Eastern Channel (TKO-T7) and
Workers at planned TKO Industrial Estate (TKO-OU1B)
will experience residual impacts of Slight/Moderate
significance at Year 10 after mitigation measures due to the wide unobstructed
views towards the site.
·
In the TKO area, Travellers
at the TKO MTR Station and Travellers along Po Yap Road and Chui Ling Road (TKO-T4), Residents of Metro Town (TKO-R4) and Park Central (TKO-R5), Workers in planned G/IC
Development at TKO Area 67 (TKO-GIC9), Workers at existing TKO Industrial Estate (TKO-OU1A), Visitors to JBCPC (TKO-OU2), Hikers on the Wilson Trail (TKO-REC2) will experience residual
visual impacts of Slight
significance at Year 10 after mitigation measures.
·
On Hong Kong
Island, Residents of Heng Fa Chuen (TKO-R1)
and Users of Heng Fa Chuen Playground (TKO-O1) and Users of Siu Sai Wan
promenade (TKO-O2), Residents &
users of Island Resort residential area and promenade (TKO-R8), Residents in Chai Wan high rise estates (TKO-R10) and Visitors of Lei Yue Mun Holiday Village/Lei Yue Mun Park and the H.K.
Museum of Coastal Defence (TKO-REC3A and REC3B respectively) will experience residual visual
impacts of Slight significance at
Year 10 after mitigation measures.
10.10.18 All remaining VSRs will experience residual visual
impacts of Insubstantial significance
at Year 10 after mitigation measures.
Residual Visual Impacts – Lam Tin
10.10.19 The primary visual impacts at Lam Tin come from the
construction of the Lam Tin Interchange within the Ex-Cha Kwo Ling Kaolin Mine
Site. The existing quarry walls provide a high degree of visual containment and
the principal VSRs affected are the surrounding existing and planned high rise
residential blocks which define the ZVI to the north west, north east and south.
10.10.20 The visual quality of the former quarry site is
limited due to the fact that it has large expanses of paving used for parking
and storage and stark shear walls and steep slopes formed from previous
quarrying activity along the western, northern and eastern edges. The proposed
mitigation measures for the Lam Tin Interchange include the sensitive design of
form and finishes of all structures including at grade and elevated slip roads,
service and tunnel portal buildings, noise enclosures and barriers, retaining
walls and slopes and extensive tree, shrub and climber planting on all
available non-operational at-grade areas, on slopes and rock-cut benches and
building roofs. The combined effect of these treatments will be to transform a
plain, visually uninteresting area into one with dynamic visual characteristics
and increase the overall level and quality of greening of the site compared to
the existing condition.
10.10.21 The existing VSRs with the highest residual visual
impacts at Year 10 are:
·
Residents in
surrounding high rise residential estates which have relatively unobstructed
elevated views will experience visual impacts of Moderate significance at Year 10. These VSRs include Residents at Ping Tin Estate and
Hong Ngar Court (LT-R3), Residents at Yau Lai Estate (LT-R4A), Residents at Cha Kwo Ling housing
developments west of interchange (LT-R9B*), Residents at Kwong Tin Estate and Hong
Pak Court (LT-R11) and
Residents at Yau Tong Bay CDA (LT-CDA1) .
10.10.22 Receivers who will experience visual impacts of Slight significance include Staff and
pupils of schools east of EHC (LT-GIC1),
Residents of The Canaryside and The Spectacle in Yau Tong (LT-R5), Users of Yau Tong Road Playground (LT-O1), Users of public open space on promenade (LT-O5*) and Users
of planned open space north west of Lam Tin Interchange (LT-O6*).
10.10.23 All remaining VSRs will experience residual visual
impacts of Insubstantial significance at Year 10 after mitigation measures.
10.11.1 In accordance to the criteria and guidelines for
evaluating and assessing impacts as stated in Annex 10 and 18 of the TM- EIAO,
overall, it is considered that the residual landscape and visual impacts of the
proposed TKO-LT Tunnel are acceptable
with mitigation during the construction and operation phases.
10.11.2 For TKO, the Moderate adverse landscape and visual impacts
are considered acceptable given the context of an area which is planned for
large-scale development and the fact that the TKO-LT Tunnel will be integrated
with the TKO Town Centre South Extensions. Impacts on the Junk Bay Landscape Resource
and Character Area are unavoidable but the scale is considered acceptable in
relation to the scale of the Bay.
10.11.3 For Lam Tin, the Moderate adverse landscape and visual
impacts are also considered acceptable given the planning intent for the area
which includes major redevelopment of the waterfront and the abandoned ex-Cha
Kwo Ling Kaolin Mine Site. The
number of VSRs affected is relatively low due to the visual containment of the
site. In addition, the existing visual quality of the proposed site for the
interchange is relatively low and the proposed development can be integrated
into the overall development of the area with impacts reduced to acceptable
levels provided the recommended mitigation measures are implemented.