|
Civil Engineering and Development Department and Planning Department |
|
|
|
|
Contamination Assessment Plan for Government Sites |
|
Rpt
ref. |
|
|
||||||||||
Agreement No. CE61/2007(CE) North East New Territories New Development Areas Planning and Engineering Study - Investigation |
|||||||||||
Contamination Assessment Plan for Government Site |
|||||||||||
8.34 |
|||||||||||
042-03 |
|||||||||||
G:\env\project\25278\reports\land
contamination\Submission to CEDD (revised on 2009-09-02 Gov Site
only)\037-00_Draft CAP fro Gov Site_Rev1.doc |
|||||||||||
03/09/09 |
|||||||||||
|
|||||||||||
Ken Chan |
|||||||||||
|
|
|
|||||||||
Draft 2 |
28/02/13 |
G:\env\project\25278\reports\land contamination\Submission to CEDD (revised on 2009-09-24 Gov Site only)\042-00_Final CAP fro Gov Site_Rev1.doc |
|||||||||
Update in accordance with EPD’s comment on 22 September 2009 and latest RODP |
|||||||||||
|
|||||||||||
Thomas Chan |
|
||||||||||
|
|
|
|||||||||
Draft 3 |
15/04/13 |
Filename |
G:\env\project\25278\reports\Stage 4 EIA - Option 2\Working File\Chap 8 Land Contamination\Appendices\Appendix 8.2_CAP for Gov Sites\042-00_Final CAP for Gov Site_Rev1.doc |
||||||||
Description |
Update in accordance with comments of various departments from 13 March to 10 April 2013 and revised RODP |
||||||||||
|
|||||||||||
|
|
|
|||||||||
|
|
|
|||||||||
Draft 4 |
26/06/13 |
Filename |
G:\env\project\25278\reports\Stage 4 EIA - Option 2\Working File\Chap 8 Land Contamination\Part F (Ch 8)\App\App 8.2_CAP for Gov Sites\042-00_Final CAP for Gov Site.doc |
||||||||
Description |
Update in accordance with comments of various departments from 10 May 2013 to 5 June 2013 |
||||||||||
|
|||||||||||
|
|
|
|||||||||
|
|
|
|||||||||
|
|||||||||||
|
|
|
|||||||||
|
|||||||||||
1.5 Statutory
Legislation and Evaluation Criteria
2.3 Future
Landuse and Activities
3 Potentially Contaminated
Sites
3.1 Summary
of Potentially Contaminated Sites
4 Potential Human Health and
Environmental Impacts
4.1 Potential
Impact on Receptors
4.2 Health
Risk to Site Workers
4.3 Disposal
of Contaminated Soil
4.4 Contaminated
Groundwater Disposal
4.5 Potential
Health Risks to Future Users of the Site
5.1 Proposed
Site Investigation in Government Sites
Figures
Figure
1.1 NENT NDA Project Boundaries
Figure 2.1.1 Locations of Potentially Contaminated Sites
at Government Lot in Kwu Tung North
Figure 2.1.2 Locations of Potentially Contaminated Site
at Government Lot in Fanling North
Figure 2.2.1 KTN – Recommended Outline Development Plan
Figure 2.2.2 FLN – Recommended Outline Development Plan
Figure 5.1.1a Location of Potentially Contaminated Site at
Government Lot in Kwu Tung North (KTN-23b)
Figure 5.1.1b Locations of Proposed Boreholes at Government
Lot in Kwu Tung North (KTN-23b)
Figure 5.1.2b Locations of Proposed Boreholes at Government
Lot in Kwu Tung North (KTN-35a)
Figure 5.1.3b Locations of Proposed Boreholes at Government
Lot in Kwu Tung North (KTN-77,78)
Figure 5.1.4a Location of Potentially Contaminated Site at
Government Lot in Fanling North (FLN-9a)
Figure 5.1.4b Locations of Proposed Boreholes at Government
Lot in Fanling North (FLN-9a)
Appendices
Typical Details of Proposed Groundwater Monitoring Well
The Planning and Development Study on North East New Territories (NENT Study, CE64/96) commenced in 1998 had identified areas in Kwu Tung North (KTN), Fanling North (FLN) and Ping Che/Ta Kwu Ling (PC/TKL) to be suitable for New Development Areas (NDAs). The NENT Study also confirmed the feasibility of NDAs based on the findings and recommendations from the technical assessments on various aspects including planning, environmental and engineering. In 2003, having regard to the housing demand at the time, the Government decided to shelve the NDAs proposal in the interim pending a comprehensive review of Hong Kong’s overall planning under the Study on Hong Kong 2030: Planning Vision and Strategy (HK2030 Study).
The HK2030 Study carried out by the Planning Department (PlanD) completed in 2007 was a comprehensive review of Hong Kong’s territorial development strategy for formulating a broad planning framework to guide the future development of Hong Kong up to 2030. It recommended proceeding with KTN, FLN and PC/TKL NDAs (i.e. NENT NDAs) as well as Hung Shui Kui NDA to address long-term housing demand and to provide job opportunities. NENT NDAs and Hung Shui Kui NDA were included as one of ten major infrastructure projects in the 2007-08 Policy Address. .
Further to the recommendations for NDAs in HK2030 Study, the Civil Engineering and Development Department (CEDD) and PlanD jointly commissioned the North East New Territories New Development Areas Planning and Engineering Study - Investigation (the Project) to formulate updated development proposals for NENT NDAs. The Project aims to review and update the findings and recommendations of the NENT Study, and to formulate revised proposals for NENT NDAs.
Section 3.4.9.4 of the EIA Study Brief No.: ESB-176/2008 for the NENT NDAs project dated January 2008 issued by the EPD specified that a land contamination assessment shall be undertaken and that a Contamination Assessment Plan (CAP) shall be submitted to the EPD for endorsement prior to conducting the assessment.
This CAP is prepared only for 4 identified government sites with potential land contamination issue where access for site investigation is available. A full CAP covering entire NENT NDAs project area will be prepared and submitted to EPD for approval separately.
The NENT NDAs under this Study including Kwu Tung North (KTN) NDA, and Fanling North (FLN) NDA covering a total area of about 612ha as shown in Figure 1.1.
It should be noted that the development boundaries of the NDAs have been readjusted and fine-tuned during the planning stage. The Study Area outlined in Figure 1.1 is reference to the revised Recommended Outline Development Plan (RODP) of NENT NDAs study.
1.2.1 Kwu Tung North (KTN) NDA
The KTN NDA covers an area of about 450 ha. It is located to the west and northwest respectively of the proposed FLN NDA and the existing Fanling/Sheung Shui New Town. It is generally bounded by the Shek Sheung River in the east, Castle Peak Road and the Fanling Highway in the south, Tit Hang in the west and Tai Shek Mo (Crest Hill) in the north.
Long
The majority of KTN NDA lies on a relatively flat area
within the central and southern parts where the main developed areas are
located. They involve mixed land uses
which comprise small residential developments, scattered villages, agricultural
lands, rural areas and rural industries including vehicle repair, construction
material storage, container storage etc.
In particular, Yin Kong Tsuen and Ho Sheung Heung are the recognised villages within KTN
NDA. They are located at the southern
end of
Within the northern portion of KTN NDA, the elevation of the topography rises gradually as a series of east-west striking hills to Fung Kong Shan. A number of smaller valleys branch off through this high ground in a northeast to southwest orientation. The Lo Wu Classification Range is located near to the northern end of KTN NDA, and the Ma Tso Lung Restored Landfill is located at the north-western end of KTN NDA.
1.2.2 Fanling North (FLN) NDA
The FLN NDA covers an area of about 164 ha. It is located immediately to the north of the established Fanling/Sheung Shui New Town and to the southeast of the proposed KTN NDA. It is generally bounded by Wa Shan in the north, the Ma Wat River in the east, Ma Sik Road and Tin Ping Road in the south, Ng Tung River in the southwest and Sheung Yue River in the west.
The majority of FLN NDA lies on a relatively flat area with mixed land uses which comprise agricultural and rural areas with scattered villages, some small isolated buildings and residential developments. Rural industries including vehicle repair and material storage are concentrated on the two sides of Jockey Club Road with FLN NDA. There is no recognized village in FLN NDA.
Sheung Shui Slaughter House and Shek Wu Hui Sewage Treatment Works are located at the western end, and Sheung Shui Water Treatment Works is located immediately to the north of FLN NDA. San Wai Barracks and San Wai/Tai Ling Firing Range are located to the north-east of FLN NDA.
1.2.3 Ping Che / Ta Kwu Ling (PC/TKL) NDA
PC/TKL NDA, which is previously included as a part of the NDAs, would be subject to replanning and would be proceeded at a later stage. Thus, there will not be a revised RODP for PC/TKL NDA at this juncture and no EIA and contamination assessment would be required in this context.
The planning study for the NENT NDAs is a Designated Project (DP) under Item 1 of Schedule 3 of EIAO - Engineering feasibility study of urban development projects with a study area covering more than 20 ha or involving a total population of more than 100,000.
In addition, the following work components also fall under various Schedule 2 DP categories as summarized in Table 1.1a and Table 1.1b. The locations of the Schedule 2 Designated Projects are shown in Figures 1.2.1 – 1.2.3.
Table 1.1a - Schedule 2 Designated Projects
in KTN NDA
Item |
Work Component |
Schedule 2 DP Category |
|
1 |
San Tin Highway and Fanling Highway Kwu Tung Section Widening (between San Tin Interchange
and Po Shek Wu Interchange) (Major Improvement) |
A1 |
A road which is an expressway, trunk road, primary distributor road or
district distributor road including new roads, and major extensions or
improvements to existing road |
2 |
Castle Peak Road Diversion (Major Improvement) |
A1 |
A road which is an expressway, trunk road, primary distributor road or
district distributor road including new roads, and major extensions or
improvements to existing road. |
3 |
KTN NDA Road P1 and P2 (New Road) and associated new Kwu Tung Interchange (New Road) and Pak Shek Au Interchange Improvement (Major Improvement) |
A1 |
A road which is an expressway, trunk road, primary distributor road or
district distributor road including new roads, and major extensions or
improvements to existing road. |
4 |
KTN NDA Road D1 to D5 (New Road) |
A1 |
A road which is an expressway, trunk road, primary distributor road or
district distributor road including new roads, and major extensions or
improvements to existing road. |
5 |
New Sewage Pumping Stations (SPS) in KTN NDA |
F3 |
A sewage pumping station---(b) with an installed capacity of more than
2000 m3 per day and a boundary of
which is less than 150 m from an existing or planned residential area or
educational institution. |
6 |
Proposed railway station and associated facilities in KTN NDA (To be
conducted under other separated studies). |
A2 |
A railway and its associated stations. |
7 |
Utilization of Treated Sewage Effluent |
F4 |
An
activity for the reuse of treated sewage effluent from a treatment plant |
Table 1.1b - Schedule 2 Designated Projects
in FLN NDA
Item |
Work Component |
Schedule 2 DP Category |
|
7 |
Utilization of Treated Sewage Effluent |
F4 |
An activity for the reuse of treated sewage
effluent from a treatment plant |
8 |
Po Shek Wu Interchange Improvement (Major
Improvement) |
A1 |
A road which is an expressway, trunk road,
primary distributor road or district distributor road including new roads,
and major extensions or improvements to existing road |
9 |
Fanling Bypass Western Section (New Road) |
A1 |
A road which is an expressway, trunk road,
primary distributor road or district distributor road including new roads,
and major extensions or improvements to existing road |
10 |
Fanling Bypass Eastern Section (New Road) |
A1 |
A road which is an expressway, trunk road,
primary distributor road or district distributor road including new roads,
and major extensions or improvements to existing road. |
11 |
Shek Wu Hui Sewage Treatment Works - Further Expansion at FLN NDA |
F1 |
Sewage treatment works with an installed
capacity of more than 15,000 m3 per day. |
12 |
Reprovision of temporary wholesale market in FLN NDA. |
N3 |
A wholesale market. |
13 |
New Sewage
Pumping Stations (SPSs) in FLN NDA |
F3 |
A sewage pumping station---(b) with an
installed capacity of more than 2000 m3
per day and a boundary of which is less than 150 m from an
existing or planned residential area or educational institution. |
The purpose of this Contamination Assessment Plan (CAP) for Government Sites is to provide information, guidance and instruction to characterise land contamination and identify where any contamination is or may be present during the construction and operation of 4 identified government sites in NDAs. The objectives of this CAP are:
· To provide an account of the land use within project site boundary and relevant past land use history in relation to possible land contamination;
· To identify areas of potential contamination and the associated impacts, risks or hazards; and
· To identify the contaminant of concern and scoping of requirements for sampling and laboratory testing of soil and groundwater sampling.
This CAP is prepared in accordance with the following Technical Memorandum and Guidance Notes:
· Annex 19 of the TM-EIAO, Guidelines for Assessment of Impact On Sites of Cultural Heritage and Other Impacts (Section 3 : Potential Contaminated Land Issues), EPD, 1997;
· Guidance Notes for Investigation Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repairing/Dismantling Workshops, EPD, 1999 (i.e. superseded in August 2011);
· Guidance Manual for Use of Risk-Based Remediation Goals (RBRGs) for Contaminated Land Management, EPD, 2007; and
· Guidance Notes for Contaminated Land Assessment and Remediation EPD, 2007.
In accordance with EPD’s Guidance Note for Contamination Land Assessment and Remediation, a contamination assessment evaluation should:
· provide a clear and detailed account of the present use of the land and the relevant past land history, in relation to possible land contamination;
· identify areas of potential contamination and associated impacts, risks or hazards; and
· submit a plan to evaluate the actual contamination conditions for soil and/or groundwater, if required.
The EPD’s Guidance Notes include a summary of the general steps of a detail contamination assessment study.
Under the Annex 19 of the TM-EIAO, consideration shall be given to a number of potentially contaminating historical land uses, including oil installations, gas works, metal workshops, car repair and dismantling workshops, as having the potential to cause or have caused land contamination. All of these land uses have been identified either adjacent to, or within the NDAs area and work area boundary. This CAP has been prepared to set out the requirements for a baseline contamination evaluation of the NDAs area and work areas. A Contamination Assessment Report (CAR) will be prepared following site investigation activities. If significant contamination is identified in the CAR, a Remediation Action Plan (RAP) will be developed to deal with these areas during excavation works for the Project. The RAP should follow the contents requirements as specified in the EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites. A remediation Report (RR) will be prepared to demonstrate adequate clean-up and submitted to EPD for endorsement prior to the commencement of any construction/ development works within the NDAs.
A desktop study has been conducted to review past and present landuses and activities in the vicinity of these 4 government sites that may pose potential for land contamination. These 4 government sites include:
· KTN-23b,
· KTN-35a,
· KTN-77,78; and
· FLN-9a.
Locations of these 4 government sites are given in Figures 2.1.1 – 2.1.2.
Existing information from historical study report for areas located within the vicinity of these 4 government sites have been reviewed, including the following:
· Hong Kong Ordinance Survey Maps from various years;
· Relevant Outline Zoning Plans (OZPs) for Kwu Tung and Fanling;
·
· Relevant aerial photos from 1963;
· Landuse information from the District Land Offices in Yuen Long (DLO Yuen Long) and Fanling (DLO North);
·
“Mapping
· “Environmental Impact Assessment Report for Planning and Development Study on North East New Territories”, CEDD and PlanD”, 2003.
The desktop review summary, including the historical aerial photos, has been provided in the full CAP to include desktop findings of all surveyed sites (i.e. approximately 300 sites have been surveyed). Nevertheless, the desktop review findings have no impact for deciding the detailed site investigation program of these 4 government sites.
The aerial photos of the 4 government sites were extracted and given in Appendix A.
Site surveys have been conducted in May and June 2009 to confirm findings of desktop study as well
as to identify the hotspots for subsequent detail site investigation of these 4
government sites.
The existing land use and activities of these 4 government sites are summarized in Table 3.1.
2.3 Future Landuse and Activities
The RBRGs have developed four
different post-restoration land uses, namely “Urban Residential”, “Rural
Residential”, “Industrial” and “
The revised RODP of NDAs is given in Figures 2.2.1 - 2.2.2, which
consisted of different facilities, such as residential buildings, education
institutions, outdoor sport facilities, commercial, mixed development, police
facilities, primary and district distributors, sewage treatment works, sewage
pumping stations, wholesale market, railway and monorail, pedestrian walkway,
open space, car park and various of public utilities etc. The relevant RBRGs for the identified contaminated sites should be
decided with reference to the revised RODP of NDAs. The most relevant RBRG corresponding to its future land use should be adopted
in assessing its land contamination level.
Corresponding RBRGs
landuse of the associated facilities are defined and
given in Table 2.1.
Table
2.1 Post-restoration land use and
RBRGs land use
Landuse |
Corresponding RBRGs Landuse |
Commercial /
Residential · Urban High Rise ·
Low Rise in
Rural Area |
Urban Residential Rural Residential |
Commercial /
Business & Office |
Urban Residential |
School |
Rural Residential |
|
Lower of |
Warehouse
& Storage |
Industrial |
Government,
Institution & Community Facilities |
Urban Residential |
Road
including Pedestrian Walkway |
Lower of Industrial or |
Railway |
Industrial |
Open Space |
|
Public
Utilities |
Industrial |
Nevertheless, if the future land uses is changed after the approval of
this CAP or in doubt during the assessment (i.e. interpretation of the soil and
groundwater testing results), the most stringent set of RBRGs
should be adopted.
3 Potentially Contaminated Sites
Locations of these 4 potentially contaminated government sites are given in Figures 2.1.1 – 2.1.2 and summarised in Table 3.1.
Table 3.1 Potentially
Contaminated Government Sites
Site No. |
Location |
|
Lot No. |
Potentially Sources of Contamination |
Approximate Area (m²) |
Recommended No. of Boreholes(i) |
Future Landuse
(Corresponding RBRGs) |
KTN-23b |
Chung Hing Hong, petrol station (partially
paved) Shell Gas (North of Castle Peak Road) |
Fuelling Area/ Fuel Storage |
DD95–T19636 |
Possible spillage/ leakage of fuel |
203 |
2 |
Amenity (Public Park) |
KTN-35a |
Vehicle repair and maintenance (partially unpaved) (North of Ma Tso
Lung Road) |
Vehicle Repair |
STT344 |
Potential spillage/ leakage of fuels and
oils during maintenance activities |
632 |
2 |
Public Rental Housing, Open Space (Urban Residential) |
KTN-77 |
Container trailer park with vehicle repairing workshop (unpaved).
Metal workshop (unpaved). (area behind
saw mills) (Behind Saw Mills KTN-76) |
Heavy Vehicle Parking and Repairing. Metal Painting on Unpaved
Ground |
No record |
Possible spillage/ leakage of fuels, oils
and other chemicals during previous storage and dumping activities (i.e. oil
stain observed in some area) |
5,421 |
8 |
Public Rental Housing, Open Space (Urban Residential) |
KTN-78 |
Combine with 77 |
No record |
|||||
FLN-9a |
Luen Fat, vehicle repairing workshop (paved) (To the east of Woodland
Crest) |
Vehicle Repair |
DD51–STT435 |
Possible spillage/ leakage of fuels and oils
during maintenance activities |
343 |
3 |
Road network (Lower of Industrial or Public Park) |
Note (i): All
4 government sites have been accessed and hotspots have been identified.
The selection of chemicals of concern (COCs) for the potentially contaminated government sites should be based on the historical land use and the information collected during the site survey with reference to RBRGs and EPD’s Guidance Notes for Investigation and Remediation of Contaminated Sites of Petrol Filling Stations, Boatyards, and Car Repairing/Dismantling Workshops. However, as only 4 government lot sites are accessible and allowed for intrusive site investigation throughout the NDAs at this stage, it is proposed to use a board testing approach, including VOCs, SVOCs, Metals and TPH for these 4 accessible government lot sites in order to gather as much data as possible. PCBs and Cyanide are also proposed for site KTN-77,78 due to the worse site observation. The gathered data could provide the Project Proponent (PP) a preliminary picture and understanding of land contamination level/extent of other potentially contaminated sites with similar industrial activity.
4 Potential Human Health and Environmental Impacts
The potential impacts to the Project from contaminated soil and groundwater are judged to be as follows:
· Health risks to site workers;
· Disposal of contaminated soils, where encountered;
· Disposal of contaminated groundwater, where encountered; and
· Potential health risks to future users of the sites.
Site construction workers may become exposed to contaminated soils and groundwater during earth moving operations and the laying of pipelines or underground services. The main exposure routes for site construction workers are accidental direct ingestion of contaminated materials through poor hygiene and eating or smoking on site, or through direct contact with potentially toxic or harmful contaminants in excavated soil.
In the event that any contaminated soils are identified during site investigation (SI) works or further environmental investigations, they may require remediation or disposal prior to or as part of the construction programme. Prior agreement will need to be reached with EPD to ensure that these materials are dealt with appropriately in accordance with EPD’s Guidance Note for Contaminated land Assessment and Remediation. Any contaminated soils which are excavated will require treatment and/or off site disposal at an appropriate site which is licensed to accept “contaminated” soils. Nevertheless, the off-site disposal of the treated contaminated soil should always be considered as the last resort.
The actual type(s) and concentration(s) of contaminants will determine the final remediation method and disposal requirements. The proposed remediation method of the contaminated soil and disposal arrangement of the treated soil will be presented and addressed in the RAP, which will be submitted to EPD for approval during the course of this EIA Study. Agreement of the proposed disposal arrangement should also be sought with the Waste Facilities Management Group, and Waste Policy and Service Group of the EPD.
Where excavations for these 4 government sites take place below the groundwater table, there may be a need to dewater the pits for safety and construction purposes. Where dewatering takes place through layers of contaminated material or where any contaminated soil is being excavated, the groundwater may become contaminated, thereby requiring appropriate handling and disposal. The proposed remediation method and disposal arrangement of the contaminated groundwater will be presented and addressed in the RAP, which will be submitted to EPD for approval during the course of this EIA Study.
Depending on the level of contamination encountered, and subject to the agreement of the EPD, groundwater will need to be disposed of in an appropriate manner, comply with the WPCO.
During the operational phase, there is little potential for impacts associated with contaminated soils. However, maintenance workers may come into contact with such materials, at which time all of the above mentioned impacts may be applicable. However, if contaminated material is identified during the construction stage, it is expected that appropriate remedial measures will have been undertaken either to ensure this material is mitigated or removed, or to ensure that future, direct contact with in-situ materials is avoided.
Due to the limitation of access in private land lot areas, sampling will be carried out at first in those potentially contaminated sites within government lot. There are three sites at KTN NDA (Sites KTN-23b, KTN-35a, and KTN-77,78), and one at FLN NDA (Site FLN-9a). Observed activities at the sites included car repair/ maintenance, petrol refilling, open storage and workshop. They are shown in Figures 2.1.1 - 2.1.2.
With permission from the site operators of government lot areas, photos were taken to identify the land contamination hot spot of government sites, of which are shown in Figures 5.1.1a - 5.1.4b. The landuse description of these 4 potentially contaminated government sites is summarized in Table 3.1.
Totally, there are 15 sampling locations for the CAP (see Table 5.1 and Figures 5.1.1a - 5.1.4b for details). Assignment of the sampling points and locations are mainly based on the observed hot spots (e.g. stain areas) during the site visits. The historical drilling records in the nearby locations of the proposed boreholes are taken into reference to decide the termination levels of each borehole. The historical drillhole records are given in Appendix B. Nevertheless, the on-site Land Contamination Specialist will decide the appropriate depths for sampling on a point by point basis.
Since all of these 4 potentially contaminated sites are still in operation and any propose remediation works after intrusive site investigation at this stage will only be carried out in a number of years later. Hence, the proposed site investigation for these 4 government sites during this EIA study will only serve as a preliminary assessment of the current site situation. After the individual sites is handed over to the PP, the PP’s appointed consultants should revisit the site to access the latest site situation, review the available information, carry out further site investigation, and submit an updated SI report to EPD for approval. Also, the PP are required to submit the supplementary CAP to EPD prior to the commencement of SI works. Following on from the submission of CAP and completion of SI, the PP’s appointed consultants would prepare CAR, RAP and RR for contaminations other than As (which will follow the recommendations of the Health Risk Assessment (HRA)) for all of these 4 concerned government sites after these sites are handed over to the PP.
In order to avoid errors and misplacement of documents, the PP’s appointed consultants should submit the supplementary CAP, CAR, RAP and RR for contaminations other than As (which will follow the recommendations of the HRA) in separate packages (e.g. one package for one project/development area) instead of one set of report which includes all of the concerned sites as mentioned in aforementioned sections.
Locations |
Coordinates |
Sampling Strategy |
Estimated No. of
Samples (1) |
||||
NDA |
Site ID |
Borehole No. |
Easting |
Northing |
Termination Level
for Environmental Sampling (bgl) (mbgl) (1) |
Frequency of
Sampling Analysis (2) |
|
Kwu
Tung North |
KTN-23b (Figures 2.1.1, 5.1.1a & 5.1.1b) |
KTN 23b-1 |
828497 |
840470 |
14.20 - (Drillhole Record at (E828509.67, N840339.42) in Jan 95
was referred. (i.e. ALLUVIUM ended at Saprolite
layer of 14.10mbgl) |
Drilling
of a borehole and collection of soil samples at depths of 0.5, 1.5 & 3.0,
and then at 3.0m intervals to the termination level for environmental
sampling. One groundwater sample if encountered. |
6
soil + 1 water samples |
KTN 23b-2 |
828504 |
840458 |
6 soil + 1 water samples |
||||
KTN-35a (Figure 2.1.1, 5.1.2a & 5.1.2b) |
KTN
35a-1 |
828455 |
841025 |
6.45 - (Drillhole Record at
(E828480.29, N841189.88) in April 97 was referred. (i.e. COLLUVIUM
ended at Saprolite layer of 6.45mbgl) |
4
soil + 1 water samples |
||
KTN
35a-2 |
828468 |
841029 |
4
soil + 1 water samples |
||||
KTN-77,78 (Figures 2.1.1. 5.1.3a & 5.1.3b) |
KTN 77,78-1 |
827968 |
840911 |
1.50 + 4.50 = 6.00 (Drillhole Record at
(E827999.14, N840957.17) in Nov/Dec 97 was referred. Owing to the relative thin COLLUVIUM layer ended at Saprolite
layer of 1.5m, it is recommended to extend the Termination Level into the
first layer of Saprolite (Grade V slightly gravelly
sandy SILT/CLAY) from 1.5 to 6.0m |
4 soil + 1 water samples |
||
KTN 77,78-2 |
827983 |
840935 |
4 soil + 1 water samples |
||||
KTN 77,78-3 |
827989 |
840916 |
4 soil + 1 water samples |
||||
KTN 77,78-4 |
828003 |
840921 |
4 soil + 1 water samples |
||||
KTN 77,78-5 |
828021 |
840941 |
4 soil + 1 water samples |
||||
KTN 77,78-6 |
828023 |
840925 |
4 soil + 1 water samples |
||||
KTN 77,78-7 |
828014 |
840917 |
4 soil + 1 water samples |
||||
KTN 77,78-8 |
828025 |
840907 |
4 soil + 1 water samples |
||||
Fanling
North |
FLN-9a (Figure 2.1.2, , 5.1.4a & 5.1.4b) |
FLN
9a-1 |
832062 |
840917 |
10.3 - (Drillhole Record at
(E832033, N840928) in Aug 88 was referred. (i.e. ALLUVIUM stopped at Saprolite layer of 10.3mbgl) |
5 soil + 1 water samples |
|
FLN
9a-2 |
832073 |
840915 |
5 soil + 1 water samples |
||||
FLN
9a-3 |
832075 |
840906 |
5 soil + 1 water samples |
(1)
The proposed Termination
Levels for Environmental Sampling and Estimated No. of Samples are just for
reference purpose. The exact termination levels and no. of soil/ groundwater
samples of each borehole should be decided by the on-site Land Contamination
Specialist.
(2)
Historical drillhole records indicated that the water levels in the
nearby areas of proposed boreholes are approximately ranged from 2 to 5 mbgl, hence, it is very likely to encounter the groundwater
table of each proposed borehole.
5.3.1 General
The sampling work will be undertaken following appropriate protocols, to minimise the potential for cross-contamination between samples and between different sampling locations. The soil sampling methods are based on techniques developed by USEPA. These methods include decontamination procedures, sample collection, preparation and preservation, and chain-of-custody documentation.
For general land contamination assessments, samples are collected by drillholes as the sampling depth will often exceed 3.0m. This will minimise the chance of cross-contamination between samples that are often observed when using the trial pit method. When conducting the intrusive investigations, care will be taken to avoid underground utilities.
Samples for laboratory testing will be taken with clean stainless steel hand tools and clean latex gloves and placed in rigid containers made of a material that is non-reactive with the likely contaminants.
In addition to the samples collected for laboratory analysis, a strata log will be kept for record of additional data to aid in the interpretation of results. Information on the general structure of the subsurface strata including grain size, colour, and wetness, and the depth and thickness of each soil/rock layer will be noted. The presence of any foreign material such as metals, wood, or plastics is also to be recorded.
All field personnel should wear adequate personal protective equipment when working in potential contaminated areas.
5.3.2 Decontamination Procedures
Equipment in contact with the ground shall be thoroughly decontaminated between each sampling event to minimize the potential for cross contamination. The equipment shall be decontaminated by steam cleaning, then washed with phosphate-free detergent and finally rinsed with water. Only clean water shall be used for drilling.
A clean area immediately adjacent to the sample location should be established, using a clean plastic sheet, on which all cleaned, and foil wrapped equipment may be placed.
During sampling and decontamination activities, disposable latex gloves shall be worn to prevent the transfer of contaminants from other sources. Disposable accessories, such as latex gloves, will be discarded after use.
5.3.3 Soil Sampling
Drillhole sampling
Drilling of borehole and collection of soil samples should be conducted at depths of 0.5m, 1.5m & 3.0m, and then at 3.0m intervals to the base. The on-site Land Contamination Specialist will decide the appropriate depths for sampling on a point by point basis.
Sufficient sample (see Table 5.2) should be placed in a pre-cleaned glass sample jar. The jar lid should be covered with laboratory solvent washed aluminium foil and lids. The jar must be filled with no void space (or otherwise if specified by the lab) for samples to be tested for VOCs. Each sample jar should be labelled. Records should be made of the details of the sampling location and other pertinent data. A chain-of-custody form should be completed for the samples. All samples should be stored on ice in portable ice chests between 2oC – 4oC whilst in the field or in transit.
Trial pit sampling
Trial pits should be constructed on site for soil and groundwater sampling if drilling sampling is not feasible. Trial pits can be constructed either manually or by an excavator, as judged as suitable by the site investigation contractor. Exact location of soil sampling should be determined on site by the on-site Land Contamination Specialist based on observation. The trial pits should be constructed to allow soil samples to be collected at:
· 0.5m below ground
· Level immediate above the groundwater level; and
· Level in between (i) and (ii) above for each sampling point.
Inspection of soil should be made at 0.5m intervals. The depth of the trial pit should be determined by the groundwater level and should be at least 0.5 m below ground level.
5.3.4 Groundwater Sampling
Groundwater samples shall be collected at each drillhole when groundwater is encountered. Historical drillhole records indicated that the water levels in the nearby areas of proposed boreholes are approximately ranged from 2 to 5 mbgl, hence, it is very likely to encounter the groundwater table of each proposed borehole. Anyhow, the on-site Land Contamination Specialist will decide whether the groundwater sample should be collected in accordance with the actual geological situation of the borehole.
Each sample shall be truly representative of the groundwater at the point from which it is taken, without dilution or contamination by water from other sources or by other material. A groundwater monitoring well shall be installed at each drillhole, and upon completion of installation of monitoring wells, approximately five times volumes of well shall be flushed to remove silt and drilling fluid residue from the wells. The wells shall then be allowed to stand for a day to permit groundwater conditions to equilibrate. Groundwater level and thickness of free product layer, if present, shall be measured by dip meter and interface probe respectively, before groundwater samples are taken. Moreover, prior to groundwater sampling, the sampling wells shall be purged (at least three times volumes of well) to remove fine-grained materials and to collect freshly refilled groundwater samples. After purging, one groundwater sample shall then be collected at each sampling well with a Teflon bailer. Field measurement of temperature and pH shall also be taken for each of the samples. The free products, if present, shall also be sampled to allow identification by the laboratory. Typical details of proposed groundwater monitoring well is shown in Appendix C.
If the permeability of the surrounding strata and storage is low, dewatering by pumping may dry up the hole, in which case the on-site Land Contamination Specialist will decide whether the requirement to pump out three times the liquid volume is to be waived.
After the dewatering process (and allowing groundwater to percolate back into the hole if it has been pumped dry), enough quantity of groundwater sample shall be collected from each drillhole, and then stored in different sample containers for analysis. Immediately after collection, samples shall be transferred to labelled sample containers containing the necessary preservatives (supplied by the laboratory). Samples shall be stored between 2oC – 4oC, and delivered to the laboratory within 24 hours. All samples shall be collected under chain-of-custody protocols.
5.3.5 Sample Size and Handling Criteria
Recommended sample size, sample containers and preservative procedures for each chemical analysis of the soil and groundwater have been summarized in Table 5.2. The containers shall be marked with sampling point codes and the depths at which the samples were taken. Samples shall be stored between 2oC – 4oC, and delivered to the laboratory within 24 hours.
Table
5.2 Summary of Sample Handling
Criteria
Analytical
Parameters |
Sample
Size |
Sample
Container |
Preservation |
Notes |
Soil Sampling |
||||
All major analyses in soil sample |
2 X 500g |
Glass Jar with Teflon Lined Lid |
Refrigeration at 2oC – 4oC |
The soil jar must be filled to minimise headspace when volatiles are to be determined. |
Groundwater
Sample |
||||
Metals |
250ml |
Clear Plastic Bottle |
Nitric
Acid (HNO3) Refrigeration at 2oC – 4oC |
For Dissolved Metals the sample must
be filtered prior to acidification. |
TPH (C6
– C8) & VOCs |
2 X 40ml |
Glass Vial with Teflon Lined Lid |
Hydrochloric
Acid (HCl) Refrigeration at 2oC – 4oC |
The vials must be filled for zero
headspace. |
|
||||
TPH (C9 – C16) |
1L |
Amber Glass Bottle with Teflon Lined
Cap |
Refrigeration at 2oC – 4oC |
- |
TPH (C17 – C35) |
||||
SVOCs |
||||
PCBs |
5.3.6 Analytical Programme and Parameters
Soil and groundwater samples collected at each sampling point should be analyzed for parameters in accordance with sampling and testing schedule shown in Table 5.3 and analysed by a HOKLAS accredited laboratory accordance with analytical method given in Table 5.4.
Table 5.3 Sampling and Testing Schedule
Locations |
Existing Landuse |
Testing
Parameters |
||||||
VOCs |
SVOCs |
Metals |
TPH |
Cyanide |
PCBs |
|||
Kwu
Tung North |
KTN-23b |
Chung Hing Hong,
petrol station |
√ |
√ |
√ |
√ |
|
|
KTN-35a |
Vehicle repairing workshops |
√ |
√ |
√ |
√ |
|
|
|
KTN-77,78 |
Container trailer park |
√ |
√ |
√ |
√ |
√ |
√ |
|
Fanling
North |
FLN-9a |
Luen
Fat, vehicle repairing workshop |
√ |
√ |
√ |
√ |
|
|
· Volatile Organic Compounds (VOCs): acetone, benzene, bromodichloromethane, 2-butanoe, chloroform, ethylbenzene, methyl tert-butyl ether, methylene chloride, styrene, tetrachloroethene, toluene, trichloroethene, xylenes (total)
· Semi Volatile Organic Compounds (SVOCs): acenaphthene, acenaphthylene, anthracene, benzo(a)anthracene, benzo(a)pyrene, benzo(b)fluoranthene, benzo(g.h.i)perylene, benzo(k)fluoranthene, bis-(2-ethylhexyl)phthalate, chrysene, dibenzo(a,h)anthracene, fluoranthene, fluorene, hexachlorobenzene, indeno(1,2,3-cd)pyrene, naphthalene, phenanthrene, phenol, pyrene
· Metals: antimony, arsenic, barium, cadmium, chromium III, chromium VI, cobalt, copper, lead, manganese, mercury, molybdenum, nickel, tin, zinc
·
Total
Petroleum Hydrocarbon (TPH):
·
Polychlorinated
Biphenyls (PCBs)
· Cyanide: Cyanide, free (i.e. only for soil samples)
Table
5.4 Method of Analysis for Soil
and Groundwater Samples
Parameter |
Referenced
Analytical Method |
Reporting Limit
for Soil (mg/kg) |
Reporting Limit
for Groundwater (mg/L) |
VOCs |
|||
Acetone |
USEPA Method 8260 |
5 |
0.05 |
Benzene |
0.2 |
0.005 |
|
Bromodichloromethane |
0.1 |
0.005 |
|
2-Butanone |
5 |
0.05 |
|
Chloroform |
0.05 |
0.005 |
|
Ethylbenzene |
0.5 |
0.005 |
|
Methyl tert-Butyl
Ether |
0.5 |
0.005 |
|
Methylene Chloride |
0.5 |
0.05 |
|
Styrene |
0.5 |
0.005 |
|
Tetrachloroethene |
0.04 |
0.005 |
|
Toluene |
0.5 |
0.005 |
|
Trichloroethene |
0.1 |
0.005 |
|
Xylenes (Total) |
1.5 |
0.015 |
|
SVOCs |
|||
Acenaphthlene |
USEPA Method 8270 |
0.5 |
0.002 |
Acenaphthene |
0.5 |
0.002 |
|
Anthracene |
0.5 |
0.002 |
|
Benzo(a)anthracene |
0.5 |
- |
|
Benzo(a)pyrene |
0.5 |
- |
|
Benze(b)floranthene |
1.0 |
0.004 |
|
Benzo(g,h,i)perylene |
0.5 |
- |
|
Benzo(k)fluoranthene |
1.0 |
0.004 |
|
Bis-(2-Ethylhexyl)phthalate |
5.0 |
- |
|
Chrysene |
0.5 |
0.002 |
|
Dibenzo(a,h)anthracene |
0.5 |
- |
|
Fluoranthene |
0.5 |
0.002 |
|
Fluorene |
0.5 |
0.002 |
|
Hexachlorobenzene |
0.2 |
0.004 |
|
Indeno(1,2,3-cd)pyrene |
0.5 |
- |
|
Naphthalene |
0.5 |
0.002 |
|
Phenanthrene |
0.5 |
0.002 |
|
Phenol |
0.5 |
- |
|
Pyrene |
0.5 |
0.002 |
|
Metals |
|||
Antimony |
USEPA Method 6020A |
1 |
- |
Arsenic |
1 |
- |
|
Barium |
0.5 |
- |
|
Cadmium |
0.2 |
- |
|
Chromium III |
0.5 |
- |
|
Chromium VI |
0.5 |
- |
|
Cobalt |
0.5 |
- |
|
Copper |
1 |
- |
|
Lead |
1 |
- |
|
Manganese |
0.5 |
- |
|
Mercury |
0.05 |
0.0001 |
|
Molybdenum |
1 |
- |
|
Nickel |
1 |
- |
|
Tin |
0.5 |
- |
|
Zinc |
1 |
- |
|
TPH |
|||
C6-C8 |
USEPA Method 8015 |
5 |
0.02 |
C9-C16 |
200 |
0.5 |
|
C17-C35 |
500 |
0.5 |
|
PCBs |
USEPA Method 8080 |
0.1 |
0.0001 |
Cyanide,
free |
USEPA Method 9010A |
1 |
- |
A HOKLAS accredited (or equivalent) testing laboratory shall be appointed to conduct chemical analysis for the soil and groundwater samples. All laboratory tests shall be made in accordance with Guidance Manual for Use of Risk-Based Remediation Goals for Contaminated Land Management. The RBRGs for soil and soil saturation limits, and RBRGs for groundwater and groundwater solubility limits are given in Appendix D.
5.3.7 Storage of Surplus Soil Samples
It is
envisaged that the likely scale of contamination should be very much localized,
if found. The volume of soil expected to require cleanup should be of small
quantities. Landfill disposal may be a practical option and should be
considered as the last resort. Additional tests in terms of Toxicity
Characteristic Leaching Procedure (TCLP) would be
required to meet the criteria for disposal to landfills. Hence, surplus soil
samples obtained during the site investigation would be stored for subsequent TCLP tests if identified necessary.
Landfill
disposal Criteria for Contaminated Soil is show in Table
5.5.
Table 5.5 Landfill Disposal Criteria for Contaminated Soil
Parameter |
TCLP Limit (ppm) |
Referenced Analytical
Method |
Detection Limit (mg/L) |
Cadmium |
10 |
USEPA Method 1311 and 6020A |
0.2 |
Chromium |
50 |
1 |
|
Copper |
250 |
1 |
|
Nickel |
250 |
1 |
|
Lead |
50 |
1 |
|
Zinc |
250 |
1 |
|
Mercury |
1 |
0.2 |
|
Tin |
250 |
1 |
|
Silver |
50 |
1 |
|
Antimony |
150 |
1 |
|
Arsenic |
50 |
1 |
|
Beryllium |
10 |
1 |
|
Thallium |
50 |
1 |
|
Vanadium |
250 |
1 |
|
Selenium |
1 |
0.2 |
|
Barium |
1000 |
1 |
Ref: EPD’s Guidance notes for investigation and remediation of
contaminated sites of: petrol filling stations, boatyards, car repair/
dismantling workshops
5.3.8 Quality Control and Quality Assurance (QA/QC)
A proper
QA/QC program shall be established to ensure that the data collected are
accurate and representative of actual soil and groundwater conditions. The QA/QC programme shall include the
following:
·
1
duplicate per 20 samples;
·
1
equipment blank per 20 samples;
·
1
field blank per 20 samples; and
·
1
trip blank per trip for the analysis of volatile parameters.
5.3.9 Sample Handling, Packaging and Transport
The soil
and groundwater sampling shall be conducted by an experienced sampling
technician (provided by the G.I. Contractor), and the
appropriate procedures shall be adhered to. Sampling methodologies are based on
the techniques developed by the USEPA. Collection
tools shall be cleaned thoroughly before, in-between and after sampling. Special care shall be taken to prevent any
cross contamination of the samples during collection, handling, and storage.
Sample
containers shall be laboratory cleansed, airtight, and made of glass or other
suitable materials with Teflon-lined lids to ensure that the container does not
react with the sample or absorb contaminants.
Care shall be taken when recording and labeling the sample information
on the containers. Information such as
the date/time, sample point codes, depths, and any other relevant data shall be
included. Samples shall be stored in an
icebox (at about 2oC – 4oC) immediately after collection
and labeled, until they can be transported to the laboratory for analysis.
After
endorsement of the CAP by EPD, site investigation will be conducted and then
the Contamination Assessment Report (CAR) will be prepared. The CAR will
present the findings of the site investigation where site access can be
obtained and evaluate the level and extent of potential contamination. The CAR
will evaluate the potential environmental and human health impacts based on the
extent of potential contamination identified. If remediation is required, a
Remediation Action Plan (RAP) will be prepared. The objectives of the RAP will
be:
·
To
undertake further site investigation where required;
·
To
evaluate and recommended appropriate remedial measures for the contaminated
material identified in the assessment;
·
To
recommend good handling practices for the contaminated materials during all
stages of the remediation works;
·
To
recommend approximate handling and disposal measures; and
·
To
formulate optimal and cost-effective mitigation and remedial measures for the EPD’s agreement.
A
Remediation Report (RR) to demonstrate adequate clear-up shall be prepared and
submitted to EPD for endorsement prior to the commencement of any construction/
development works within the NDAs. No construction/ development works shall be
carried out before the endorsement of the RR.