This section reports on the Study to assess the potential landscape and visual impacts arising from construction and operation of any above ground structures and works areas associated with the Schedule 2 DPs 8, 9, 10 and 12 in FLN NDA only.
The components of DP Package D are summarised in Table 12D.1.1 below.
Table
12D.1.1 - Schedule 2 DP Package D
DP Package D |
|||
8 |
Po Shek Wu Interchange Improvement
(Major Improvement) |
A1 |
A road which is an
expressway, trunk road, primary distributor road or district distributor road
including new roads, and major extensions or improvements to existing road. |
9 |
Fanling Bypass Western
Section (New Road) |
A1 |
A
road which is an expressway, trunk road, primary distributor road or district
distributor road including new roads, and major extensions or improvements to
existing road. |
10 |
Fanling Bypass Eastern
Section (New Road) |
A1 |
A road which is an
expressway, trunk road, primary distributor road or district distributor road
including new roads, and major extensions or improvements to existing road. |
12 |
Reprovision of temporary
wholesale market in FLN NDA |
N3 |
A
wholesale market. |
This section provides an overview of the HKSAR Government’s development intentions, statutory land-use and planning within the Study Areas, specifically from landscape and visual standpoints. It considers relevant, published studies, such as HK2030 Study, OZPs, and DPA Plans. This information has been considered in relation to the relevant revised RODP of the NDAs and their Layout Plans with the aim of assessing whether the Project can fit into the surrounding setting.
During public consultations, people were noted to be concerned about the landscape and visual impacts of the noise barriers specifically. Some people also suggest maximising the greening opportunities. The planning proposal for the NDAs which includes the Schedule 2 DPs therefore aims to minimise the area needing noise barriers and maximize the greening opportunities to reduce the landscape and visual impacts.
12D.2.1
Design measures adopted within the Schedule 2
Designated Projects
The Schedule 2 DPs form the key infrastructure developments to support the future development and population growth within KTN and FLN NDAs. KTN and FLN NDAs will provide a mix of housing types as well as basic infrastructure and community facilities. The development opportunities and constraints of the Schedule 2 DPs are presented in Section 2.4.1, these have informed the development and consideration of alternative infrastructure options. A summary of the key design rationale for each project is provided below:
DP8 - Po Shek Wu Interchange Improvement (Major Improvement)
The Po Shek Wu Interchange is currently exceeding its junction capacity. In order to cater for the traffic flow from the FLN NDA, improvement work, including realignment of the Po Shek Wu Road and the construction of an elevated southbound right-turning slip road to bypass the interchange, is proposed.
The selected scheme has been designed to minimise the land total requirement, avoid encroachment upon the proposed neighbouring public rental housing site, Tai Tau Leng village at the west and Choi Po Court at the east. In addition, existing mature tree planting on either side of the road has been taken into account within the alignment. In this case the proposed slip road will be elevated above the existing Po Shek Wu Road, at a level of +20mPD (i.e. road infrastructure has been stacked to reduce the overall footprint and accommodated the improvement works within the existing constraints).
DP 9 - Fanling Bypass Western Section (New Road)
The proposed Fanling Bypass Western Section provides a linkage between the Man Kam To Road and the proposed Fanling Bypass Eastern Section. The planning intention is to arrange the bypass at the northern periphery of FLN NDA alongside Ng Tung River, such that through traffic will be diverted away from the town centre to minimise the environmental impact of the traffic to FLN NDA.
The alignment of the road sits within the level ground to the north of Ng Tung River and generally runs parallel to the channel adjacent to the existing access track. The alignment avoids disruption of more natural topography found to the north.
DP 10 – Fanling Bypass Eastern Section (New Road)
The proposed Fanling Bypass Eastern Section provides a direct bypass linkage between FLN NDA and Sha Tau Kok Road (STKR) with the Fanling Highway Tai Po direction. Generally the Fanling Bypass Eastern Section is wholly elevated, except an underpass portion near Lung Yeuk Tau. There are footbridges across Fanling Highway and at the Lung Yeuk Tau Interchange. A key design measure of this route responds to feedback during the public engagement on improving traffic conditions around STKR Luen Wo Hui Section and Wo Hop Shek Interchange.
In this case the road is elevated predominantly on a viaduct to minimise the proposed land take, disturbance to natural terrain and reduce the operational footprint. The alignment also follows the outer edge of the existing urban development area to avoid further encroachment to the east within the less development and more natural areas.
DP 12 – Reprovision of Temporary Wholesale Market
The North District Temporary Wholesale Market for Agricultural Products will be affected by the NDA development. Reorientation of the existing site in the current location so that it fits with the alignment of the new road (DP 10) is proposed. This approach means this established land use is not displaced to another location, potentially exerting land pressure elsewhere.
The precise details of the development at this stage are not confirmed however the facilities would include temporary style stalls (i.e. moveable) of approximate 2-3m height. The number of stalls would vary depending on seller requirements; this cannot be ascertained at this time. The majority of the facility is the creation of flexible open space/hardstanding to accommodate these facilities. Perimeter security fencing pprox.. 2.5m high to replace the existing would be provided together with an access booth for security personnel.
12D.2.2
Existing Outline Zoning Plans (OZPs)
The review of the OZPs has included a review of the Plans as well as the accompanying Notes and Explanatory Statements. The DP sites and study areas have been superimposed onto existing OZPs and DPA Plans to determine the potential influence on the existing zoning. The study areas and site boundaries for DPs 8, 9, 10, and 12 have been combined on Figure 12.50.4.
The FLN DPs 8, 9, 10 and 12 study areas are covered by the following OZP/DPA documents:
·
Draft
Fanling/Sheung Shui OZP No. S/FSS/17.
·
Approved
Fu Tei Au and Sha Ling OZP No. S/NE-FTA/12.
·
Approved
Kau Lung Hang OZP No. S/NE-KLH/11.
·
Draft
Lung Yeuk Tau and Kwan Tei South OZP No. S/NE-LYT/15.
·
Approved
Hok Tau OZP No. S/NE-HT/5.
·
Approved
Hung Lung Hang OZP No. S/NE-HLH/7.
Table 12D.2.1, summarizes the areas of existing zoning types which will be directly affected by the site boundary of each DP. In some cases, as the DPs are located within or traverse different OZP/DPA areas, this has been highlighted in the tables accordingly.
Table
12D.2.1- Schedule 2 Designated
Project 8, 9, 10 and 12.
Zoning Type |
OZP/DPA
number and extent of zoning within the site boundary that will undergo change
(ha) |
Comments on
Major land use changes |
DP8 – Po Shek Wu Interchange
Improvement |
||
Green Belt (GB) |
S/FSS/17 0.42 |
Approximately 0.42ha of the zoning type would be modified at the
junction point with the Fanling Highway south Tai Tau Leng. |
Industrial (I) |
S/FSS/17 1.87 |
Approximately 1.87ha of this zoning type located to the west of Po
Shek Wu Road would be modified, between Choi Yuen Road and the MTR East Rail
line. |
Government /Institution / Community (GIC) |
S/FSS/17 0.21 |
Approximately 0.21ha of this zoning type would be modified, adjacent
to the MTR East Rail Corridor and to the south of the Fanling Highway
corridor. |
Other Specified uses |
S/FSS/17 0.67 |
Approximately 0.67ha of this zoning type would be modified. This zoning relates to the MTR East Rail
Corridor. The Po Shek Wu Road at this
point is elevated on a bridge and would not directly interfere with this
zone. |
Open Space (0) |
S/FSS/17 0.22 |
Approximately 0.22ha of this zoning would be affected to the south
east of Po Shek Wu Road, close to San Wan Road. |
Residential (Group A) (R(A)) |
S/FSS/17 0.61 |
Approximately 0.61ha of this zoning would be affected to the east of
Po Shek Wu Road. |
Village Type Development (V) |
S/FSS/17 0.85 |
Approximately 0.85ha of this zoning would be affected to the west of
Po Shek Wu Road. |
DP9 –
Fanling By-pass Western Section (New Road). |
||
Agriculture (AGR) |
S/NE-FTA/12 11.2 |
Approximately 11.2ha of this zoning type would be modified
starting from the south of Hung Kiu San Tsuen, through Sheung Shui Wa San and
to the junction point with the proposed eastern section of the Fanling
Highway north of Shek Wu San Tsuen. |
Other Specified Uses (OU) |
S/NE-FTA/12 2.33 |
Approximately 2.33ha of this zoning type would be
modified as the alignment of the road passes through Hung Kiu San Tsuen. |
Green Belt (GB) |
S/FSS/17 1.81 |
Approximately 1.81ha of this zoning
type would be modified as the alignment of the road passes to the south of Wa
Shan Tsuen. |
DP10 – Fanling Bypass Eastern Section (New Road) |
||
Agriculture (AGR) |
S/NE-FTA/12 2.45 S/NE-LYT/15 3.02 S/NE-KLH/11 4.44 |
A total of 9.91ha of this type of zoning will be modified
as a result of the road alignment as it travels from north of Wu Nga Lok
Yeung, passes Ma Wat Tsuen and the south of Tong Hang Tung. |
Green Belt (GB) |
S/NE-FTA/12 0.20 S/FSS/17 5.48 S/NE-LYT/15 1.18 |
A total of 6.86ha of this type of zoning will be
modified as a result of the road alignment |
Government /Institution / Community (GIC) |
S/FSS/17 0.92 S/NE-KLH/11 1.07 |
Approximately 0.92 ha of this zoning type would be
modified by the alignment of the road as it passes through the existing North District Temporary
Wholesale Market for Agricultural Products and Water Supplies Department facilities off Sha Tau Kok Road. An additional 1.07ha of this zoning type would be modified
at the southern end of the proposed by-pass where the junction is formed with
the existing Fanling Highway to the west of Yuen Leng. |
Industrial (I) |
S/FSS/17 2.64 |
Approximately 2.64ha of this zoning type will be
modified as the alignment of the road passes by the Fanling Industrial area. |
Recreation (REC) |
S/NE-LYT/15 1.46 |
Approximately 1.46ha of this zoning type will be
modified as the alignment of the road passes through land located to the west
of the Cyber Domaine residential development. |
Other Specified Uses (OU) |
S/NE-LYT/15 2.32 |
Approximately 2.32ha of this zoning type would be
modified as a result of the alignment of the road. 0.36ha of this total would be associated with
the proposed bridge crossing of the MTR East Rail track to the west of the
existing Cyber Domaine residential development. The remaining 1.96ha is associated with the
petrol filling station and amenity area located adjacent to the Fanling
Highway east of Wo Hop Shek. |
Open Space (O) |
S/FSS/17 0.31 |
Approximately 0.31ha of this zoning would be
affected at Wo Hop Shek as a result of viaduct and noise barrier
construction. |
DP12 – Reprovision of wholesale market in FLN NDA |
||
Government /Institution / Community (GIC) |
S/FSS/17 0.61 |
Approximately 0.61ha of this zoning type would be
modified associated with the existing North District Temporary Wholesale Market
for Agricultural Products and Water
Supplies Department facilities off Sha Tau Kok Road. |
Industrial (I) |
S/FSS/17 0.7 |
Approximately 0.7ha of this zoning type would be
modified associated with the existing wholesale market area. |
12D.2.3 Summary of land use changes
In summary, Schedule 2 DP 8 and 12 would be largely compatible with the existing planning zones. The main conflicts arise in relation to DP 9 and 10 – Fanling Bypass Eastern and Western Sections which cross numerous OZP zones. In this case, approximately 8.67ha of green belt and 21.11ha of agricultural land would be affected.
According to the Study Brief (ESB-176/2008) baseline review comprises the identification of all existing LR and LCA within 500m of the DP boundaries.
The overall Study Area for all the DPs is very generally natural and rural. Complex LRs can be classified into different major categories, as follows:
· LR1 – Channelized Water Course
· LR2 – Water Course
· LR3 – Water Pond
· LR4 – Marsh/ Wetland
· LR5 – Plantation
· LR6 – Hillside Woodland
· LR7 – Lowland Woodland
· LR8 – Shrubland/Grassland Mosaic
· LR9 – Agricultural Land
· LR10 – Open Space / Recreational Area
· LR11 – Urban Development Area
· LR12 – Rural Development Area
· LR13 – Industrial / Open Storage
· LR14 – Major Transportation Corridor
· LR15 - Columbarium
The LCAs are classified as follows:
· LCA1 Natural Hillside Landscape
· LCA2 Rural and Urban Peripheral Village Landscape
· LCA3 Urban Development Landscape
· LCA4 Industrial Landscape
· LCA5 Lowland Agricultural Landscape
· LCA6 Major Transportation Corridor Landscape
· LCA7 Major Water Course Corridor Landscape
The landscape resources and landscape character areas of each NDA are described in further detail below, together with their sensitivity.
12D.3.1 Broad Brush Tree Survey
A Broad brush tree survey has been carried out within the study areas identifying more than 1000 trees affected by the proposed works. Major tree species included Acacia confusa, Acacia auriculiformis, Araucaria heterophylla, Bauhinia blakeana, Bombax ceiba, Cassia siamea, Celtis sinensis, Cinnamomum camphora, Clausena lansium, Citrus maxima, Dimocarpus longan, Eucalyptus camaldulensis, Ficus virens, Ficus microcarpa, Litchi chinensis, Leucaena leucocephala, Macaranga tanarius, Mangifera indica, and Melaleuca quinquenervia. Many trees are found in the foothills of the natural upland, as well as the rural fringe in between different villages and they are generally mature.
12D.3.2 Schedule 2 DPs 8, 9, 10 and 12 Baseline Landscape Resources and Landscape Character Areas
The baseline LRs and LCAs of FLN DPs 8, 9, 10 and 12 are detailed along with their sensitivity; figures presenting this information are set out below:
Figure 12.51.4 presents LRs
Figure 12.51.19 to 27 presents LRs enlarged plan versions
Figure 12.51.57 to 67 for representative images of LRs.
Figure 12.52.4 presents LCAs.
Figure 12.52.11 to 12 for representative images of LCAs.
Table 12D.3.1- Landscape Resources
and their Sensitivity- FLN DPs 8, 9, 10 and 12
Id. No. |
Landscape Resource |
Quality & Maturity |
Rarity |
Ability to Accommodate Change |
Sensitivity |
||
FLR 1 - Channelized Water Course |
|||||||
Refers to modified water courses channelized with
concrete or grasscrete, or with gabion-fortified banks, water courses
undergoing such channelization. This
LR includes both large channelized river water courses as well as some much
smaller concrete lined water courses associated with agricultural land. This LR also includes some walkways along
the larger water course and the vegetation associated with the water course,
both within the channel and along the banks as well as the ridge of the
banks. The vegetation mainly consists
of grasses and shrubs, but also includes trees in some areas as detailed
further in the individual LR descriptions.
|
|||||||
Within the Study Area this LR includes sections of
Ng Tung River, Shek Sheung River and Ma Wat River and is one of the prominent
landscape features running across a large part of the Study Area. |
|||||||
1.1 |
Ng Tung River (Fanling District) |
Medium |
Medium |
Medium |
Medium |
||
Ng Tung River (Fanling District) runs in an
east-west direction in FLN NDA Study Area.
It collects water from Ma Wat River in the east, then Shek Sheung River and Sheung Yue River
further west and finally empties into the Shenzhen River outside the study
area. Ng Tung River is modified with grasscrete banks and tree planting is
found in its immediate vicinity.
Dominant plantation tree species are Acacia auriculiformis and Acacia
confusa. Other trees also recorded
include Ficus virens and Leucaena leucocephala. The river also
includes a nullah in the south of the Study Area and some small channels
linking through culverts under the banks of the main channel to smaller
channelized watercourses which connect to drainage systems and sometimes to
more natural watercourses. |
|||||||
This resource is reasonably tolerant to change and
its sensitivity is medium. |
|||||||
1.2 |
Shek Sheung River |
Medium |
Medium |
Medium |
Medium |
||
Shek Sheung River collects water from the south and
flows north, joining the Sheung Yue River west of the Sheung Shui Slaughter
House. There is another branch of Shek
Sheung River that splits from Ng Tung River and flows round the south of the
Shek Wu Hui Sewage Treatment Works.
Water drained from Tin Ping San Tsuen low land area flows into this
branch after passing through a floodwater storage area. This LR is mainly a grasscrete banked,
trapezoidal channel, formed for the purpose of flood protection of the
Fanling and Kwu Tung areas. Water
partially dries out during the dry season and there is only a small amount of
water at the base of the channel, with grass on either side. There are grasses and shrubs along the
river’s embankment also, as well as trees planted along both sides in many
sections of the river. The dominant
tree species are exotic, including Acacia
auriculiformis, Acacia confusa, Eucalyptus
spp. and Leucaena leucocephala. Native trees of lower abundance can also be
found, e.g. Celtis sinensis, Cinnamomum
camphora, Cleistocalyx operculatus, Ficus microcarpa, Ficus virens and Sapium sebiferum. |
|||||||
Overall this river is relatively tolerant to change
and its sensitivity is considered to be medium. |
|||||||
1.4 |
Ma Wat River |
Medium |
Medium |
Medium |
Medium |
||
Ma Wat River runs across the southeast part of the
FLN NDA Study Area, passing through industrial, rural and agricultural
areas. It joins Ng Tung River near Kan
Lung Tsuen. Water in the channel decreases
significantly during the dry season when its concrete bottom is often partly
exposed and dry. There is grasscrete
along both its banks, where Imperata
koenigii is one of the dominant grasses.
Tree planting consisting of large and mature trees is found in the
immediate vicinity of this river.
Dominant tree species are Acacia
confusa, Ficus microcarpa, Melia azedarach and Leucaena leucocephala. Trees with
lower abundance include native (Bauhinia
blakeana, Celtis sinensis, Macaranga tanarius and Sapium sebiferum) and exotic (Casuarina equisetifolia and Pterocarpus indicus) species. Overall this river is relatively tolerant to change
and its sensitivity is considered to be medium. |
|||||||
1.5 |
Water Course through Ma Shi Po Agricultural Land |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This LR describes a
channelized concrete watercourse flowing through agricultural land from the
Ma Shi Po area towards Ng Tung River where it connects through a concrete channelized
link. It is likely to have been used
for irrigation purposes, but there is limited water flow and the watercourse
is polluted by domestic waste.
Vegetation associated with this LR includes the herb species Bidens alba, Eleusine
indica and Mikania micrantha. This LR is reasonably tolerant to change and its
sensitivity is considered to be low. |
|||||||
FLR 2 – Water Course |
|||||||
Refers to natural or semi-natural water courses,
including short sections with concreted banks. This LR also includes vegetation associated
with the water course, both within the streams and along the banks as well as
in the immediate vicinity. The
vegetation mainly consists of grasses and shrubs, but also includes some
trees in certain areas such as the upland streams, as detailed further in the
individual LR descriptions. The
vegetation often provides a subtle transition between this LR and its
surrounding LR(s). |
|||||||
Within the Study Area, this LR includes watercourses
running down from different hills into lowland areas. |
|||||||
2.1 |
Natural Streams in Tin Ping Shan Agricultural Land |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. Refers to a natural stream passing though Tin Ping
Shan (Sacred Hill) agricultural land and finally flowing into the channelized
Shek Sheung River. This is a narrow
stream with grasses and climbers overgrowing along its banks. The grasses mainly include Bidens alba, Polygonum chinense and Oxalis corymbosa. Although parts of this stream are more
natural, much of it passes through development areas and is adjacent to open
storage areas. It is degraded by
pollution while some sections of the stream are fortified by concrete
banks. |
|||||||
This LR has medium tolerance to
change and its sensitivity is considered to be medium. |
|||||||
2.2 |
Natural Streams at Cham Shan and Wa Shan |
Medium |
Medium |
Low |
Medium |
||
This LR sits outside the works area and will not be
affected. This natural stream comes from Cham Shan and flows
down to the lowland rural area in the northwest of the FLN NDA Study
Area. It is not perennial and water
flow may cease during the dry season.
The banks of this stream is overgrown with common grasses such as Alocasia odora, Bidens alba and Panicum maximum, particularly in the
upstream sections where it flows through extensive grasslands. Within the downstream sections in lowland
rural areas, its banks are partially paved in places and the water quality is
low as rubbish is commonly found near and in the stream. |
|||||||
This LR is not of high quality but it is relatively
intolerant to change. The sensitivity
is considered to be medium. |
|||||||
2.3 |
Natural Streams at Lung Shan |
Medium |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. This LR refers to natural streams located at the foothill
of Lung Shan and running through all heavily vegetated areas. The streams are intermittent and
cease flowing during the dry season. Grasses and climbers grow along their banks. These
include Alocasia odora and Cuscuta chinensis as well as some invasive
species such as Mikania micrantha. |
|||||||
This LR is relatively intolerant to change and its
sensitivity is considered to be high.
|
|||||||
2.4 |
Natural Streams at Siu Hang San Tsuen |
Medium |
Medium |
Low |
High |
||
This LR describes streams
at around Siu Hang San Tsuen. Stream banks are colonized by common species
such as Commelina diffusa, Polygonum
lapathifolium, Alocasia odora and Macaranga
tanarius. Part of one stream at Siu Hang San Tsuen is regarded as
ecologically important due to its naturalness and moderately diverse aquatic
community. This LR is relatively intolerant to change and its
sensitivity is considered to be high. |
|||||||
2.5 |
Natural Streams at Kau
Lung Hang, Yuen Leng and Nam Wa Po |
Medium |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. Refers to a natural stream passing though Kau Lung Hang San Wai, Kau Lung Hang Lo Wai and Yuen Leng from Kau
Lung Hang Shan and finally flowing
into the main channel, also
includes streams in Nam Wa Po. The streams are intermittent and
cease flowing during the dry season. Grasses and climbers grow along their banks such as Alocasia odora, Bidens alba and Panicum maximum. This LR is relatively intolerant to change and its sensitivity
is considered to be high. |
|||||||
FLR 3 – Water Pond |
|||||||
Refers to freshwater ponds. The ponds are often associated with
agricultural land and used for irrigation, and punctuate the traditional
field pattern. Some ponds are also found
near residential or developed areas, and have aesthetic, landscape value and
some are fish ponds. This LR also
includes vegetation associated with the ponds, both within and around the
banks as well as in the immediate vicinity.
The vegetation mainly consists of grasses and shrubs, with scarce
trees. |
|||||||
These water ponds are mainly in Fu Tei Au in FLN NDA and Lung Yeuk Tau. |
|||||||
3.3 |
Fu Tei Au Water Ponds |
Low |
Medium |
Low |
Medium |
||
This LR sits outside the works area and will not be
affected. This is a group of water ponds located between Fu
Tei Au Road and Ng Tung River. The
ponds were most likely used for commercial fish farming and for irrigation
purposes in the past and have now mainly been abandoned. Common grasses (e.g. Bidens alba and Pennisetum spp.)
and small trees (e.g. Bombax ceiba
and Leucaena leucocephala) grow
densely along the banks. Trees are
planted or naturally have established themselves on the pond bunds; these include
Macaranga tanarius, Litchi chinensis, Dimocarpus longan and Ficus
hispida. |
|||||||
The quality and significance of this LR is
relatively low, but it is intolerant to change. Its sensitivity is therefore
considered as medium. |
|||||||
3.4 |
Water Ponds in Eastern Rural Area |
Low |
Medium |
Low |
Medium |
||
This LR sits outside the works area and will not be
affected. There are two isolated ponds located in Lung Yeuk
Tau in the east of Study Area, one in San
Uk Tsuen and the other one in Ma Wat Tsuen.
Both are no longer used and not actively managed. Grasses and climbers grow along their banks
and are also present in their immediate vicinity. The water surface of these ponds is largely
colonized by plants. |
|||||||
This LR has low landscape quality and is small in
area but it is relatively intolerant to change. Its sensitivity is medium. |
|||||||
3.5 |
Wai Loi Tsuen Pond |
Low |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR is on the periphery of Wai Loi Tsuen serving as the moat of
this traditional village. It has
concrete banks and is connected with the Shek Sheung River to its west. |
|||||||
Overall these ponds have medium amenity value and
are relatively intolerant to change. This LR’s sensitivity is considered to
be high. |
|||||||
3.6 |
Water Pond in Nam Wa Po |
Low |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR is located in Nam Wa Po in the south of Study Area. The ponds were most
likely used for commercial fish farming and for irrigation purposes in the
past and have now mainly been abandoned. Common grasses (e.g. Bidens alba and Pennisetum spp.)
and small trees (e.g. Bombax ceiba
and Leucaena leucocephala) grow
along the banks. The quality and significance of this LR is
relatively low, but it is intolerant to change. Its sensitivity is therefore
considered as medium. |
|||||||
Since this is a LR with significant artificial
characteristics, it is relatively tolerant to change, however the moat has
cultural landscape significance and therefore its sensitivity is considered
to be medium. |
|||||||
FLR 4 – Marsh/ Wetland |
|||||||
Refers to freshwater wetland landscape resources.
Some of them are found at old river meanders which have been truncated during
river channelization and retraining, overgrown with herbaceous vegetation and
often with some areas of seasonal or permanent open water. |
|||||||
Within the Study Area, this LR is found along
certain sections of Ng Tung River. |
|||||||
4.2 |
Mitigation Wetland |
Medium |
High |
Low |
High |
||
Several plots of marsh are located along Ng Tung
River. They were formerly meanders of
the river and were isolated during the river channelization. To mitigate the ecological impact resulting
from channelization, these areas are now managed by a government department
to provide marsh habitat, mainly for wetland dependent wildlife and are hence
a wetland landscape resource. Wetland
plants and riparian vegetation have been planted and include Commelina diffusa, Hedychium coronarium, Ludwigia perennis and Nelumbo nucifera. Bamboos and trees are also planted along
the bunds, e.g. Acacia auriculiformis,
Cinnamomum camphora, Hibiscus tiliaceus and Ilex rotunda. |
|||||||
This LR had medium quality and maturity and in
general marsh habitats are reasonably rare in Hong Kong. Additionally this LR is relatively
intolerant to change so its sensitivity is considered to be high. |
|||||||
FLR 5 – Plantation |
|||||||
Refers to medium sized and larger clusters of trees that
have been planted and are distinct from natural woodland in terms of species
composition since they have been planted by man. Common tree species in this LR include Ficus virens, Ficus microcarpa, Acacia
confusa, Bombax ceiba, Macaranga tanarius and Melaleuca quinquenervia. Further details are given in the
individual LR descriptions. |
|||||||
Within the Study Area this LR is found in the
vicinity of Wai Loi Tsuen, Hak Ka Wai, Ha Pak Tsuen, On
Kwok Villa and Noble Hill. |
|||||||
5.1 |
Plantation in the Vicinity of Wai Loi Tsuen |
Medium |
Medium |
High |
Medium |
||
This LR sits outside the works area and will not be
affected. A mixture of native and exotic trees is planted around
the moat of Wai Loi Tsuen and its vicinity, serving as a good screen for the
road and industrial area to the west of the village. Compared to those trees planted immediately
along the Shek Sheung River in its vicinity, trees in this plantation have a
relatively higher diversity, including native species (Bauhinia blakeana, Celtis
sinensis and Ficus microcarpa)
and exotic species (Acacia confusa,
Aleurites moluccana, Bombax ceiba, Cassia siamea, Casuarina equisetifolia, Eucalyptus
citriodora, Grevillea robusta, Lagerstroemia speciosa and Melaleuca quinquenervia). |
|||||||
This LR has medium amenity value and relatively high
capacity to accommodate change and its sensitivity is considered to be medium. |
|||||||
5.2 |
Ha Pak Tsuen Plantation |
High |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. A patch of plantation is located to the east of Ha
Pak Tsuen. Trees are densely planted
within the village as well as along the nearby roads leading to the village to
enhance the landscape value of this area.
Among these planted trees, Chinese Banyan Ficus microcarpa is one of the most prominent trees as most of
them are mature and large. Other tree
species include native (Macaranga
tanarius) and exotic (Acacia confusa
and Bombax ceiba) species. |
|||||||
Although this resource was originally man made, it
now has many large, mature trees in a traditional village setting and this is
harder to recreate, so it has a relatively low capacity to accommodate
change. Its sensitivity is considered
to be high. |
|||||||
5.3 |
Plantation in the Vicinity of On Kwok Villa and
Noble Hill |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. There is significant plantation on the periphery of
On Kwok Villa and Noble Hill mainly along Tin Ping Road, Lung Sum Road, Ma
Sik Road and a branch of Ng Tung River.
Trees planted in this area are reasonably mature and dense. They include native (Ficus virens, Ficus
microcarpa, Bauhinia blakeana
and Macaranga tanarius) and exotic
(Bombax ceiba, Cassia siamea, Delonix
regia, Eucalyptus spp., Ficus religiosa and Melaleuca quinquenervia) species. |
|||||||
Although trees in this LR provide a certain high
landscape value, the trees are set amongst modern residential areas. The LR was originally a man-made resource
and is able to be recreated fairly easily meaning it has a reasonable
capacity to accommodate change. Its
sensitivity is therefore considered to be medium. |
|||||||
5.4 |
Plantation South of Fanling Highway |
High |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR mainly includes a plantation patches found just north of Hong Kong Golf Club and trees
commonly recorded in this area include native (Cinnamomum camphora, Ficus
virens and Macaranga tanarius)
and exotic species (Acacia confusa,
Bombax ceiba, Melaleuca
quinquenervia and Leucaena leucocephala). Trees in this LR are dense and mature, providing a
relatively high landscape value.
However, it is a man-made resource and is able to be recreated
reasonably easily meaning it has a high capacity to accommodate change. Its sensitivity is therefore considered to
be medium. |
|||||||
5.5 |
Plantation in the Vicinity of Hak Ka Wai |
Medium |
Medium |
High |
Medium |
||
This LR sits outside the works area and will not be
affected. This area of plantation is largely associated with
the narrow Sheung Yue River channel and the villages of Hak Ka Wai and Tsung
Pak Long, including in their playground areas and public facilities. This plantation generally comprises exotic
tree species dominated by Acacia
confusa. Other species of lower abundance include exotic species (Acacia auriculiformis, Acacia mangium, Araucaria heterophylla, Casuarina
equisetifolia, Livistona chinensis
and Leucaena leucocephala) and
native species (Cinnamomum camphora,
Ficus microcarpa, Macaranga tanarius). This LR has a relatively high capacity to
accommodate change and its sensitivity is considered to be medium. |
|||||||
FLR 6 - Hillside Woodland |
|||||||
Refers to woodland areas largely scattered over
hillsides, including at the base of hills and associated patches of
woodland. This LR is predominantly
composed of native tree species and is generally
located some distance from intense human activities (except at the base of
hills where it often borders rural development areas), growing naturally with
some understory vegetation. Common
tree species in this LR include Acacia
confusa, Macaranga tanarius, Ficus microcarpa, Dimocarpus longan, Celtis
sinensis, Cinnamomum camphora and
Ficus hispida. Further details are
given in the individual LR descriptions. |
|||||||
Within the Study Area, this LR is largely scattered
at the foothill of Cham Shan, Wa Shan, Lung Shan and Wa
Mei Shan. |
|||||||
6.1 |
Sheung Shui Water Treatment Works
Hillside Woodland |
High |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. Several small patches of woodland lie at the eastern
base of the hillside surrounding Sheung Shui Water Treatment
Works. Trees grow naturally and
densely in this area and dominant species include Macaranga tanarius, Celtis
sinensis, Cinnamomum camphora, Melia azedarach and Leucaena leucocephala. |
|||||||
This LR is relatively mature and intolerant to
change. The sensitivity of this LR is
considered to be high. |
|||||||
6.2 |
Cham Shan and Wa Shan Hillside Woodland |
High |
Medium |
Low |
High |
||
This LR refers to the relatively large and
continuous woodlands along the foothills of Cham Shan and Wa Shan to their
northern, western and southern sides, bordering shrubland/grassland on the
higher ground above and rural villages and agricultural lands in the lowland
area below. Due to limited human
disturbance, these trees are mature in medium to large sizes. Dominant tree species include both native
and exotic ones. Dominant native trees
are Celtis sinensis, Cinnamomum camphora, Ficus hispida, Ficus variegata var. chlorocarpa,
Rhus succedanea, Sapium discolor, Ficus
microcarpa and Macaranga tanarius. Dominant exotic species include Melia azedarach, Dimocarpus longan, Syzygium
jambos, Leucaena leucocephala, Acacia confusa and Casuarina equisetifolia. |
|||||||
This LR is considered to be relatively mature and of
high quality and it has little capacity to tolerate change. The sensitivity of this LR is considered to
be high. |
|||||||
6.3 |
Ma Wat Wai Hillside Woodland |
High |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. This LR refers to a small and isolated woodland patch
embracing Ma Wat Wai on all sides expect the northeast. A mixture of exotic and native trees as
well as many bamboos are present in this area. Dominant trees include native species (Celtis sinensis, Ficus microcarpa, Ficus
hispida, Sterculia lanceolata, Rhus succedanea and Sapium discolor) and exotic species (Dimocarpus longan and Melia azedarach). |
|||||||
This is a mature resource and of relatively high
quality. It has little capacity to tolerate change. Its sensitivity is considered to be high. |
|||||||
6.4 |
Hillside Woodland at Lung Shan and Wa Mei Shan |
High |
Medium |
Low |
High |
||
This LR covers part of the woodlands on the foothill
of Lung Shan to the northeast of Fanling Highway and the foothill of Wa Mei Shan
to the southwest in the vicinity of Wo Hop Shek. This resource includes mature woodland
trees growing on hillside slopes, including native species (Celtis sinensis, Macaranga tanarius, Ficus
hispida, Ficus microcarpa and Litsea glutinosa) and exotic species (Acacia confusa, Eucalyptus spp., Dimocarpus
longan, Melia azedarach and Syzygium jambos). |
|||||||
The quality and landscape value of this LR is
relatively high, with little tolerance to change and its sensitivity is
considered to be high. |
|||||||
FLR 7 – Lowland Woodland |
|||||||
Refers to woodland growing on low ground (generally
<40 mPD), often found near rural village areas of human activities in
small, fragmented patches, with differing tree species according to
location. Common tree species found in
this LR include Dimocarpus longan, Cinnamomum camphora, Macaranga tanarius, and Leucaena leucocephala. Further details
are given in the individual LR descriptions. |
|||||||
Within the Study Area, this LR is found in Fu Tei Au,
Hung Kiu San Tsuen, Sacred Hill, Ling Hill, Ling Shan Tsuen, Wong Kong Shan, Tai Tau
Leng and North District Hospital. |
|||||||
7.2 |
Lowland Woodland at Fu Tei Au and Sheung Shui Water Treatment Works |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR refers to several patches of woodland in Fu
Tei Au area and in the close vicinity of Sheng Shui Water Treatment
Works. They are generally surrounded
by or bordering rural areas and abandoned agricultural lands and so receive
moderate human disturbance leading to the vegetation within the LR being of
lower quality. Trees in this resource
are not diverse and dominated by Dimocarpus
longan, Hibiscus tiliaceus, Celtis sinensis, Macaranga tanarius and Cinnamomum camphora. |
|||||||
This is a landscape resource of medium quality and
has a medium tolerance to change, making its sensitivity medium. |
|||||||
7.3 |
Hung Kiu San Tsuen Lowland Woodland |
Medium |
Medium |
Medium |
Medium |
||
This LR refers to the lowland woodlands in the
vicinity of Hung Kiu San Tsuen, east of Man Kam To
Road. These woodlands are largely
surrounded by adjacent industrial/open storage areas and therefore
potentially suffer from disturbance by human activities making this resource
of lower quality than it would otherwise be.
|
|||||||
These trees are of medium to large sizes, and are
dominated by both native and exotic species.
The most abundant native species include Celtis sinensis, Ficus microcarpa, Ficus hispida, Bischofia javanica,
Cinnamomum camphora, and Macaranga
tanarius, while exotic species include Averrhoa carambola, Casuarina
equisetifolia, Leucaena leucocephala, Dimocarpus
longan and Melia azedarach. |
|||||||
This LR has a medium amenity value, relatively low
quality, a medium tolerance to change and its sensitivity is considered to be medium. |
|||||||
7.4 |
Sacred Hill Lowland Woodland |
Medium |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. This LR is located to the east of Tin Ping Shan
Tsuen, adjacent to the large Tin Ping Shan Tsuen agricultural lands. Common
tree species include Celtis sinensis,
Ficus microcarpa and Macaranga tanarius. |
|||||||
This LR is relatively intolerant to change and its
sensitivity is considered to be high.
|
|||||||
7.5 |
Ling Hill and Ling Shan Tsuen Lowland Woodland |
High |
Medium |
Low |
High |
||
This LR sits outside the works area and will not be
affected. This LR refers to the woody areas near the
intersection of Ma Sik Road and Jockey Club Road. These woodland patches are on the periphery
of and associated with Ling Shan Tsuen.
There is an old temple (Sam Sheung Temple) located in this village and
it is also surrounded by this woodland.
Trees in this resource are fairly large and mature including both
native and exotic species. They are
native (Celtis sinensis, Ficus microcarpa and Macaranga tanarius) and exotic (Acacia confusa, Delonix regia and Dimocarpus
longan). |
|||||||
This is a natural resource of high quality and is
not able to accommodate change. Its
sensitivity is considered to be high. |
|||||||
7.6 |
Wong Kong Shan Lowland Woodland |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR refers to a small patch of woodland located at Wong Kong Shan to the southeast of Cheung Wah Estate. This woodland patch is largely surrounded by adjacent residential and industrial areas and
therefore potentially suffered from disturbance by human activities making this
resource of lower quality than it would otherwise be. Common tree species include Acacia confuse, Bauhinia blakeana, Macaranga tanarius This is a landscape resource of medium quality and
has a medium tolerance to change, making its sensitivity medium. |
|||||||
7.7 |
Lowland Woodland near Tai
Tau Leng |
Medium |
Medium |
Medium |
Medium |
||
This LR refers to a small patch of woodland located near Tai Tau Ling. This woodland patch is largely surrounded by adjacent industrial/open
storage areas and therefore potentially suffered from disturbance by human activities making this
resource of lower quality than it would otherwise be. Common tree species include Leucaena leucocephala, Acacia confuse and Cinnamomum camphora. This LR has a medium amenity value and medium tolerance to change. Its sensitivity is considered to be medium. |
|||||||
7.8 |
Lowland Woodland at North District Hospital |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR refers to the small patch of
woodland located at North District
Hospital. This woodland patch is largely surrounded by residential area and
GIC area. Human disturbance is medium. Main species include Leucaena leucocephala, Macaranga tanarius, Acacia confuse, Aleurites moluccana, Ficus microcarpa. This LR has a medium amenity value and medium tolerance to change. Its sensitivity is considered to be medium. |
|||||||
FLR 8 - Shrubland / Grassland Mosaic |
|||||||
Refers to a mosaic of shrubland and grassland which is
usually large in size and uniform in appearance. This LR is typical of the fire-maintained
hill-slopes in Hong Kong and common grass species include Miscanthus
sinensis, Neyraudia spp. and Panicum spp.
Further details are given in the individual LR descriptions. |
|||||||
Within the Study Area, this LR is found largely on
hillsides, particularly on Wa Shan, Cham Shan and Lung Shan, as well as some
relatively lowland areas to the west of the Study Area. |
|||||||
8.2 |
Fu Tei Au Shrubland/Grassland Mosaic |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This resource is located north of Fu Tei Au Road
surrounding the Sheung Shui Water Treatment
Works. It is dominated by grasses such
as Miscanthus sinensis and Miscanthus floridulus and some small
trees including Rhus succedanea and
Macaranga tanarius are also present
in this area. |
|||||||
This LR is of low landscape value and amenity and is
relatively tolerant to change. Its
sensitivity is low. |
|||||||
8.3 |
Shrubland/Grassland Mosaic at Cham Shan and Wa Shan |
Medium |
Low |
Medium |
Medium |
||
This LR can re-establish itself fairly easily and is
therefore considered to be relatively tolerant to change but is of medium
quality and maturity. Its sensitivity
is considered to be medium. |
|||||||
8.4 |
Shrubland/Grassland Mosaic at Lung Shan |
Medium |
Low |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR is part of the extensive shrubby grassland
on the uplands of Lung Shan. It merges
into hillside woodland at the foothills and is sometimes adjacent to the
urban development area. Similar to the
other hilly shrubland/grassland in Hong Kong, this LR is maintained by
periodical hill fires. |
|||||||
This LR can re-establish itself fairly easily and is
therefore considered to be relatively tolerant to change. It is of medium quality and maturity and
its sensitivity is considered to be medium.
|
|||||||
FLR 9 - Agricultural Land |
|||||||
Refers to land used for agriculture including crops
and orchards as well as ornamental plant nurseries. This LR contains a small number of
structures such as small irrigation ponds, green houses, equipment sheds and
small/ narrow hard paved areas. It not
only contains agricultural vegetation but also some scattered non-agricultural
vegetation including some shrubs and trees.
It is often an intermediary between areas of development and natural
areas. |
|||||||
Within the Study Area, this LR is mainly found in
Tin Ping Shan, Ma Shi Po and Sheung Shui Wa Shan. |
|||||||
9.2 |
Fu Tei Au Agricultural Land |
Medium |
Medium |
Medium |
Medium |
||
Agricultural land in Fu Tei Au area is partially
abandoned. Common vegetables such as Brassica parachinensis and Lactuca sativa are grown in the active
fields. In those inactive fields,
grasses dominated by Miscanthus
spp. have colonized the land, with some isolated shrubs and trees growing
along the previous field bunds without management. Those trees include Dimocarpus longan, Litchi
chinensis and Magnifera indica. The active portion of this LR is of high
quality. |
|||||||
This LR provides some green space between the hard
surfaces of industrial/open storage areas or rural development areas making
it locally reasonably important.
Agricultural land is fairly easy to re-establish in the right environment
and especially given some of this land is abandoned, it has medium tolerance
to change. The LR is considered to
have medium sensitivity. |
|||||||
9.3 |
Agricultural Land between Ng Tung River and Shek
Sheung River |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. A patch of active agricultural land is located in
the flood area between Ng Tung River and Shek Sheung River, north of Po Wan
Road. This agricultural land probably
connected with the agricultural land in Tin Ping Shan Tsuen (FLR-9.4) in the
past but has now been separated by an open storage area between them
(FLR-13.1). The area of this LR is
relatively small, but of reasonable quality. |
|||||||
This LR has medium value and being agricultural land
has medium ability to tolerate change in the right environment. It is considered to have medium sensitivity. |
|||||||
9.4 |
Tin Ping Shan Tsuen Agricultural Land |
Medium |
Medium |
High |
Medium |
||
This LR sits outside the works area and will not be
affected. Tin Ping Shan Tsuen agricultural land is located on
the north of Tin Ping Shan Tsuen. This
is a reasonably sized,un-fragmented area of agricultural land and more than
half the fields remain active. In
addition to open farmlands, there are also some orchards in which small fruit
trees including Musa x paradisiaca, Litchi chinensis and Dimocarpus
longan are cultivated. |
|||||||
The LR is mature and established and of high
quality, yet since it is agricultural land, in the right environment it could
be recreated, meaning it has reasonable capacity to accommodate change. It is considered to have medium sensitivity. |
|||||||
9.5 |
Agricultural Land at Sheung Shui Wa Shan |
Medium |
Medium |
High |
Medium |
||
This LR is located in the lowland area at the foot
of Wa Shan, along the eastern bank of Ng Tung River. Much of the agricultural land within this
area is abandoned with weeds, climbers, isolated shrubs and banana trees and
some other invasive trees (e.g. Leucaena
leucocephala) colonizing the land.
However some areas are still active and this land is a green resource
neighboring village developments. |
|||||||
This LR has medium landscape quality and
maturity. Being agricultural land it
is relatively tolerant to change in the right environment. It is considered to have medium sensitivity. |
|||||||
9.6 |
Agricultural Land in Wu Nga Lok Yueng, Siu Hang San
Tsuen, Siu Hang Tsuen and Shek Wu San Tsuen |
Medium |
Medium |
Low |
Medium |
||
This resource is mainly situated in the east of the
Study Area of FLN NDA and includes both active and inactive agricultural
lands. A variety of crops are grown in
the active fields, including Benincasa
hispida, Pisum sativum, Solanum melongena and Lactuca sativa. As a
result of human activity of cultivation, vegetation on the bunds of these
fields is poorly developed and is dominated by common herbs such as Ageratum conyzoides, Hedyotis diffusa and Kyllinga brevifolia and Lobelia chinensis and few
shrubs and trees are present. Some of the inactive fields, due to the
lack of management and disturbance for a long time, are beginning to develop
naturally into grassland or shrubby grassland with colonisation by herbs,
isolated shrubs and small trees. |
|||||||
This LR is mature and established yet the land is
highly fragmented and overall the LR is not of high quality. Since it is agricultural land, in the right
environment it could be re-established, meaning it has reasonable capacity to
accommodate change. I It is considered to have medium sensitivity. |
|||||||
9.7 |
Agricultural Land South of Sha Tau Kok Road |
Medium |
Medium |
Medium |
Medium |
||
This resource is situated in the south east of the
Study Area of FLN NDA, south of Sha Tau Kok road and near the base of Lung
Shan. It includes both active and
inactive agricultural lands near Lung Yeuk Tau, Mat Wat Wai and east of Wing
Ning Wai, Wing Ning Tsuen and Tung Kok Wai.
A variety of crops are grown in the active fields, including Benincasa hispida, Brassica chinensis and Lactuca sativa. For those inactive fields, due to the lack
of management, they are beginning to develop naturally into grassland or
shrubby grassland with colonisation by herbs (e.g. Alocasia odora, Miscanthus
sinensis, and Bidens alba) and
small trees (e.g. Ficus hispida and Macaranga tanarius). |
|||||||
This LR has medium value and, being agricultural
land, is reasonably easy to recreate in the right environment, which means it
has medium capacity to accommodate change and it is considered to have medium sensitivity. |
|||||||
9.8 |
Other Agricultural Lands in KLN |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR refers to
several small and fragmented agricultural lands in different locations within
the Study Area of DPs, including Hak Ka Wai and Tai Tau
Leng. Most of these agricultural lands
have been wholly or partly abandoned and grass and shrubs now grow in the
fields. For those fields remaining
active, common crops cultivated by farmers include Brassica parachinensis and Lactuca
sativa. This LR has low to medium value in terms of crop
production and is relatively tolerant to change. It is considered to have medium sensitivity. |
|||||||
FLR 10 - Open Space / Recreation Area |
|||||||
Refers to areas that provide recreational use either
in the form of playground areas or sports pitches. There is vegetation
associated with this LR, as well as landscaped planting. |
|||||||
Within the Study Area, this LR is found at North
District Sports Ground and Hong Kong Golf Club. |
|||||||
10.1 |
North District Sports Ground |
Medium |
Medium |
High |
Low |
||
This LR sits outside the works area and will not be
affected. North District Sports Ground is a multi-purpose
sports ground located between Jockey Club Road and Tin Ping Road. Facilities provided in this sports ground
include natural grass football field, running track, covered grandstand,
public leisure pool, basketball/volleyball courts and outdoor and indoor
tennis courts. Dominant amenity trees
planted in this LR include Ficus
microcarpa, Bauhinia blakeana and
Bauhinia variegata. |
|||||||
This LR has medium landscape value and due to its
man-made nature and high percentage of hard landscape, has a high capacity to
accommodate change. Apart from the
open grass pitch, it has little planting and therefore soft landscape is
relatively low value. Overall its
sensitivity is considered to be low. |
|||||||
10.2 |
Hong Kong Golf Club |
High |
Medium |
High |
Medium |
||
This LR sits outside the works area and will not be
affected. Hong Kong Golf Club is located either side of Fan
Kam Road. It is a large private golf
club with an extensive greens maintained for golfing activities. Besides the golf course, the club has
some built structures including the Club House and facilities to
accommodate swimming and tennis, as well as restaurants and
accommodation. The Halfway House at Hong Kong Golf Club is graded as
a Grade II historic building. Trees, dominated by Melaleuca quinquenervia, are planted around the golf course for
landscaping purposes. Water lilies (Nymphaea spp.) are cultivated in the
golf course ponds. The entire
plantation is well maintained and in good condition. This LR is of high quality and amenity value and
covers an extensive area of land; however it is an artificial resource and
has a high capacity to accommodate change.
Its sensitivity is considered to be medium. |
|||||||
FLR 11 – Urban Development Area |
|||||||
Refers to urbanized areas which are heavily
developed with considerable hard paved surfaces and limited landscaped
areas. These LRs consist mainly of
large clusters of medium to high density buildings with a high degree of
related infrastructure and often with some high rise developments, with some
associated facilities such as post office, police station, hospital,
restaurants, supermarkets etc. The LR
also includes work sites where construction is ongoing, or sites being
cleared/ formed prior to development of a structure that would form part of
an urban area. Vegetation in this LR
is mainly landscape planting with scattered amenity shrubs and trees, some
small public green spaces and private gardens. |
|||||||
Within the Study Area, this LR broadly covers the
large urban development areas in Wo Hop Shek , Sheung Shui and
Fanling. |
|||||||
11.2 |
Sheung Shui Urban Development Area |
Low |
Low |
High |
Low |
||
This LR refers to the northeastern part of the
Sheung Shui town centre. There are
high-rise public (e.g. Tin Ping Estate) and private (e.g. Tsui Lai Garden, On
Kwok Villa and Noble Hill) estates, training centres, multi-storey car park
and home for the aged located in this area.
Gardens and small scale playgrounds can also be found associated with
those residential blocks. Amenity
trees and shrubs are planted and well maintained to enhance the environment,
and the dominant tree species are Melaleuca
quinquenervia, Acacia confusa, Bauhinia blakeana, Ficus microcarpa, Bombax ceiba, Cassia siamea, Eucalyptus
citriodora and Phoenix roebelenii.
|
|||||||
This LR has low landscape value and due to its
man-made nature, has a high capacity to accommodate change. Its sensitivity is considered to be low.
|
|||||||
11.3 |
Fanling Urban Development Area |
Low |
Low |
High |
Low |
||
This LR mainly covers Luen Wo Hui urban development
area in Fanling. Medium and high rise
residential buildings (e.g. Fanling Garden, Wing Fok Centre, Wing Fai Centre,
Union Plaza, Belair Monte, Grand Regentville), schools (e.g. Fanling Public
School, Buddhist Ma Kam Chan Memorial English Secondary School and Fanling
Rhenish Church Secondary School), a church (St. Joseph’s Church), cinema,
commercial complexes and street markets can be found in this area. Gardens and playgrounds of small scale can
also be found associated with the residential blocks. Amenity trees and shrubs are planted along roads
but are relatively limited. The dominant tree
species are Melaleuca quinquenervia,
Acacia confusa, Ficus microcarpa, Cassia siamea and Bauhinia variegata. |
|||||||
This LR has low landscape value and due to its
man-made nature, has a high capacity to accommodate change. Its sensitivity is considered to be low.
|
|||||||
11.4 |
Wo Hop Shek Urban
Development Area |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This LR refers to the
eastern part of Wo Hop Shek urban development area. There are high-rise
public estate (Wah Sum Estate) and private estates (Avon Park and Dawning
views) as well as a school (Fanling Government Secondary School) in this LR. Amenity trees and
shrubs are planted along roads such as Ficus microcarpa, Cassia siamea and Bauhinia variegata. Both native and exotic species
can be found in the open area along Pak Wo Road. These include Acacia Confusa, Macaranga tanarius, Leucaena leucocephala, Ficus microcarpa and some bamboo species This LR has low landscape value and due to its
man-made nature, has a high capacity to accommodate change. Its sensitivity is considered to be low.
|
|||||||
FLR 12 - Rural Development Area |
|||||||
Refers to traditional villages, modern villages and
small scale residential areas dominated by domestic structures (mainly of 2-3
stories) interwoven with roads and paths,
There are some Ancestral Halls, shrines and temples, and this LR may
also contain some facilities such as small police stations, post offices, and
covered water reservoirs and pumping stations and some small, managed,
recreational areas (such as football and basketball pitches) and small
wasteland areas either wholly or partly covered by weedy or sparse
vegetation. This LR has a few small
orchard areas associated with it and private gardens, as well as amenity
planting among the built structures.
This LR usually occurs in fragmented patches with agricultural or
natural landscape resources adjacent to it. |
|||||||
Within the Study Area this LR includes Hak Ka Wai, Fu Tei Au, Sheung
Shui lowland area, Lung Yeuk Tau, Wo Hap Shek, Kiu Tau and Nam Wa Po, as well as some
areas at the base of Wa Shan and Lung Shan. |
|||||||
12.2 |
Rural Development Area in the Vicinity of Fu Tei Au |
Low |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR mainly covers the rural area between Fu Tei
Au Road and Ng Tung River. Settlements
in this area consist predominantly of simple and traditional houses of a
single storey, some of which are fenced off.
Trees are present both along the roads winding between houses and in
private gardens, including Dimocarpus
longan, Macaranga tanarius and Aleurites moluccana. |
|||||||
Man Ming Temple, constructed before 1924, is located
within to the south of this LR. It is a Grade 3 Historic
Building which is a three-hall
building, with two open corridors on the two sides of the central hall, used
to access the end hall. |
|||||||
This resource has limited landscape value, but some
of its structures have heritage significance and therefore have little
ability to accommodate change. Its
sensitivity is overall considered to be medium.
|
|||||||
12.3 |
Rural Development Area in the North of FLN NDA |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This LR covers the rural development areas in the north
of the Study Area and it is partially located within the Closed Area. Main structures included in this LR are
the Border District Police Headquarters, Sha Ling Livestock Waste Control
Centre, a firing range at the uphill of Cheung Po Tau, as well as some
scattered village settlements in Sha Ling.
A number of individual Chinese Banyan (Ficus microcarpa) are well maintained along the boundary fence of
Border District Police Headquarters, while in other areas there are patches
of trees along the roads, most of them without management. These trees mainly include Macaranga tanarius, Acacia confusa, Bombax ceiba and Casuarina
equisetifolia. |
|||||||
Overall this LR has limited landscape value and high
ability to accommodate change. It is considered
to have low sensitivity. |
|||||||
12.4 |
Rural Development Area in Sheung Shui Lowland Area |
Medium |
Medium |
Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This is a lowland resource where a number of
villages are concentrated, particularly in the western part which encompasses
Wai Loi Tsuen, Man Kok Village, Mun Hau Tsuen, Po Sheung Tsuen, Ha Pak Tsuen,
Chung Sum Tsuen, Sheung Pak Tsuen, Tai Yuen Tsuen and Hing Yan Tsuen (collective named as Sheung Shui
Heung/Sheung Shui Wai). The eastern part of this LR includes Tin
Ping Shan Tsuen. Fung Kai School with
its associated football pitch and several basketball pitches and some mature
trees are also located at the centre of this LR. |
|||||||
Those villages in the west are well established,
consisting of some modern housing of 2-3 storeys and some traditional housing
and include one declared monument and
two graded historical buildings. Liu Man Shek Tong Ancestral Hall, a declared monument, was built
by Liu Man Shek Tong in 1751 at Mun Hau Tsuen. This typical
three-hall two-courtyard building is decorated by plaster mouldings,
wood carvings and murals of auspicious motifs and pictures. One of the graded historic
buildings is Liu Ying Lung Study Hall, situated at Po Sheung
Tsuen which is a confirmed Grade 1 Historic Building. It was renovated in 1923 and was once the
place where Spring Equinox, births and weddings were celebrated. The other is Old Sheung Shui Police
Station, which is a confirmed Grade 2 Historic Building. It was one of thirteen police stations
built soon after the British took over the New Territories and later became a
police reporting centre and then a Junior Police Call (JPC) Club House after
the new Sheung Shui Police Station was opened in 1979. Tin Ping Shan Tsuen in the east is
relatively small, mainly consisting of more traditional and simple structured
houses of a single storey. Most areas
are hard-surfaced and have limited vegetation except those private amenity
plantings. |
|||||||
Given the traditional nature of much of this LR and
its historical buildings, this LR is relatively intolerant to change and is
considered to have medium
sensitivity. |
|||||||
12.5 |
Wa Shan Rural Development Area |
Medium |
Medium |
Medium |
Medium |
||
This LR refers to several rural development areas
along the hillsides or at the foothill of Wa Shan. They are largely rural settlements including
Sheung Shui Wa Shan village, Siu Hang Tsuen and Siu Hang San Tsuen. Most of these villages are undergoing
transformation due to the fact that many houses have been replaced by modern
housing blocks of 2-3 storeys and some new housing blocks are being
constructed. This LR has limited
softscape treatment but does include some trees (e.g. Mangifera indica, Dimocarpus
longan and Livistona chinensis)
and private amenity plantings (e.g. Duranta
erecta). |
|||||||
One temple is located in Siu Hang Tsuen, (Fuk Tak
Temple), established some 100 years ago.
The temple is for the worship of the Earth God and other gods/deities
that give protection to the villagers and so is locally important. Although the temple has a ‘Nil Grade’
historic building value, it is at one end of the Lung Yeung Tau Heritage
Trail. Part of San Wai/Tai Ling
Firing Range is also included in this LR.
It is a large piece of grassland for military purpose. Many mature trees grow in the surroundings,
including Macaranga tanarius, Celtis
sinensis, Leucaena leucocephala
and Eucalyptus spp. |
|||||||
This LR is largely a man-made area but some of the
historical buildings and the vegetation associated with the firing range are
relatively intolerant to change. The overall
sensitivity of this LR is medium. |
|||||||
12.6 |
Lung Yeuk Tau Rural Development Area |
Medium |
Medium |
Medium |
Medium |
||
A group of villages aggregate in Lung Yeuk Tau, including
Kan Lung Tsuen, San Wai, San Uk Tsuen, Wing Ning Wai, Wing Ning Tsuen, Tung
Kok Wai, Ma Wat Wai, Ma Wat Tsuen and Lo Wai. These villages
are largely divided into two parts (i.e. northern and southern parts) by Sha
Tau Kok Road. |
|||||||
Houses in Kan Lung Tsuen, San Wai and San Uk Tsuen
in the north are relatively traditional and simple. The Sisters of the Precious Blood
Children’s Village is also located in this area. There are facilities such as a playground
and basketball pitch provided in this village. |
|||||||
Wing Ning Wai, Wing Ning Tsuen, Tung Kok Wai, Ma Wat
Wai, Ma Wat Tsuen and Lo Wai in the southern
part of this LR are either modern villages with housing blocks of 2-3 storeys
or villages undergoing transformation.
However, some historical elements remain in these villages. These include the Entrance Gate of Wing
Ning Wai and Tsung Kyam Church at Shung Him Tong Tsuen, both of which are
classified as Grade 3 Historic Buildings, as well as the Entrance Tower of Ma
Wat Wai and Entrance Tower and Enclosing Walls of Lo Wai, which are declared monuments. The whole village area is mostly
hard-surfaced and has limited softscape treatment but does include some trees
(e.g. Dimocarpus longan, Sterculia lanceolata and Ficus microcarpa) and some bamboos. |
|||||||
The Lung Yeuk Tau Heritage Trail passes through this
LR taking in the high number of heritage buildings in the LR. Although many village areas in this LR are
relatively modern, the historic buildings and declared monument are vulnerable
to change since they cannot be easily recreated and overall this LR has medium sensitivity. |
|||||||
12.7 |
Rural Development Area at Wo Hop Shek and Wong Kong Shan |
Low |
Low |
High |
Low |
||
This LR
includes Cyber Domaine, Tong Hang, Tong Hang Tung Chuen (at the foothill
of Lung Shan), part of the Wo Hop Shek San Tsuen in Wo Hop Shek, Kau Lung
Hang San Wai and Yuen Leng. It also
includes the Tong Hang Fresh Water Service Reservoir that is located on the
hillside of Lung Shan. Trees commonly
found in this LR are Melaleuca
quinquenervia, Celtis sinensis , Ficus hispida, Leucaena leucocephala, Dimocarpus longan, and Eucalyptus citriodora This LR is
dominated by domestic residencies. Its
landscape amenity, significance and quality are moderate and it has a high
ability to tolerate change, making its overall sensitivity low. |
|||||||
|
|||||||
12.8 |
Rural Development Area at Ma Shi Po |
Medium |
Low |
Medium |
Medium |
||
This LR refers to the rural settlements scattered among
the agricultural lands in Ma Shi Po.
Most of the settlements are old in style and of small and simple
structure. Trees associated with these
village houses include Celtis sinensis
, Ficus hispida, Leucaena leucocephala
and Dimocarpus longan etc. |
|||||||
This LR is dominated by domestic residencies. Its landscape amenity, significance and
quality are medium and it has limited ability to tolerate change given the
age of those old village houses and its relationship with the surrounding agricultural
land, making its overall sensitivity
medium. |
|||||||
12.9 |
Wu Nga Lok Yeung and Ling Shan Tsuen Rural
Development Area |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This LR mainly refers to two patches of continuous
rural development located at Wu Nga Lok Yeung as well as Ling Shan Tsuen and
Good View New Village. Some of the construction works at Wu Nga Lok Yeung
are suspended, leaving two rows of 3-storey unfinished village houses on
exposed ground. Plants are generally
absent from this area. The village
houses in Ling Shan Tsuen and Good View New Village are relatively
concentrated with large trees frequently found along the winding roads and in
private gardens. These trees include Celtis sinensis, Dimocarpus longan, Livistona
chinensis and Macaranga tanarius, etc. This LR is dominated by domestic residencies. Its landscape amenity, significance and
quality are medium and it has high ability to tolerate change, making its
overall sensitivity low. |
|||||||
12.11 |
Rural Development Area at
Kiu Tau and Nam Wa Po |
Medium |
Medium |
High / Medium |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR mainly includes
Kiu Tau and Nam Wa Po. 2 to 3 storeys modern village houses are commonly
found. There is the oldest school building and a church more than a half
century in the village. Most area has hard surface paving. Ornamental trees
like Ficus Benjamina, Schefflera heptaphylla and
Plumeria acutifolia and some private amenity plants can be
easily seen. There is also fruit tree like Carica papaya. This LR is dominated by
domestic residencies. Its landscape
amenity, significance and quality are moderate and therefore the overall sensitivity of this LR is medium. |
|||||||
12.12 |
Rural Development Area in Long Valley, Yin Kong and
Hak Ka Wai |
Medium |
High |
Low |
High |
||
This LR lies between Shek Sheung River and Fanling
Highway to the southeast of Long Valley.
It covers 4 villages: Yin Kong Village, Hak Ka Wai and
Tsung Pak Long and Tai Tau Leng. Hak Ka Wai is a
traditional village with around 100 years of history. It consists of two rows of residences, an
ancestral hall (the Wong Shek Chung Ancestral Hall), a study hall, an
entrance gate, enclosing walls and a watch tower. This village is proposed as a Grade 1
Historic Building but the status is not confirmed as of September 2010. Tsung Pak Long is a
traditional village undergoing transformation. It contains ancestral halls, earth shrines,
a school and a church in traditional style to its northwest. Most areas within this LR are hard-surfaced
and have limited vegetation except those private amenity plantings, in which
fruit trees Dimocarpus longan, Carica papaya and Citrus reticulata and
landscaping shrub Duranta erecta and Murraya paniculata are commonly found. Tai Tau Leng is a
traditional village undergoing transformation. It contains a village hall, a
school, a factory, a basketball court and a football field to its
northwest. Most areas within this LR
are hard-surfaced and have limited vegetation. Green buffer trees are planted
to its east and south along Po Shek Wu Road and Fanling Highway. The main
species include Bauhinia variegate, Acacia auriculiformis, Leucaena
leucocephala. The historic buildings
located in this LR, particularly the Hak Ka Wai village, cannot be easily
recreated and this LR is relatively intolerant to change. This LR has high sensitivity. |
|||||||
12.13 |
Rural Development Area to the North of Hong Kong
Golf Club |
Medium |
Low |
High |
Low |
||
This LR mainly covers one modern village, Golf Park
View, consisting of residential 4-5 storey blocks enclosed by walls. Overall this LR is
considered to have low sensitivity. |
|||||||
FLR 13 - Industrial / Open Storage |
|||||||
Refers to areas which are heavily adapted for human
industrial use, such as factory facilities, waste processing plants and other
industrial buildings, often with some open areas for storage, parking or
other associated activities. These
areas have small roads within them and some concrete drainage channels. There is very little existing vegetation
within this LR. |
|||||||
Within the Study Area, this LR is geographically
divided into Sheung Shui and Fanling industrial/open storage areas and will
be further described individually. |
|||||||
13.1 |
Sheung Shui Industrial/Open Storage Area |
Low |
Low |
High |
Low |
||
The western part of this LR contains Shek Wu Hui Sewage Treatment Works and several warehouses and industrial buildings. Planted trees are found along the roads and
dominant species include Acacia
auriculiformis, Acacia confusa and
Leucaena leucocephala. |
|||||||
The rest of this LR is largely used for open storage
and car parks as well as several waste processing plants but there is one
recognized Tin Hau Temple (No. 41 Hung Kiu San Tsuen), but this has a ‘Nil
Grade’ historic building value. Trees within
this area are not actively managed and grasses occupy many places between the
car parks. Tree species commonly found
include Leucaena leucocephala, Bauhinia blakeana, Bauhinia variegata,
Macaranga tanarius, Delonix regia, Cassia siamea, Bombax ceiba, Syzygium
jambos, Ficus virens, Mangifera indica and Acacia auriculiformis. |
|||||||
This LR has relatively low landscape amenity value
and consists mostly of modern man-made structures that can be easily
recreated. Its sensitivity is considered
to be low. |
|||||||
13.2 |
Fanling Industrial Area |
Low |
Low |
High |
Low |
||
This LR refers to the warehouses and industrial
buildings, factories and workshops southwest of Luen Wo Hui in Fanling
District. There are individual fenced
factories containing some open areas for car parks with small patches of wild
grasses or small shrubs growing on exposed ground. Trees grow sparsely along the roads between
building blocks and include Celtis
sinensis, Hibiscus tiliaceus,
Aleurites moluccana and Leucaena
leucocephala. |
|||||||
This LR has low amenity value and is capable of
accommodating change. It is considered
to have low sensitivity. |
|||||||
13.3 |
Industrial / Open Storage Area in Nam Wa Po |
Low |
Low |
High |
Low |
||
This LR sits outside the works area and will not be
affected. This is an isolated plot beside Nam Wa Po Tsuen and is now used for
open storage. Trees in this LR include Acacia confusa, Leucaena leucocephala.
Delonix regia. This LR predominantly consists of man-made
structures which have a high capacity to tolerate change and have low
landscape value. This LR is considered
to have low sensitivity. |
|||||||
FLR 14 - Major Transportation Corridor |
|||||||
Refers to MTRC railway, Fanling Highway, as well as
Sha Tau Kok Road (Lung Yeuk Tau) and all the associated intersections. There
is tree planting along the sides of the roads consisting of a variety of
indigenous and exotic species such Cassia
siamea and Acacia confusa. In addition, there is some planting along
the central divider (median) in some sections, including of amenity shrubs
such as Allamanda schottii and
sometimes palm trees Livistona
chinensis. Drainage channels associated with the roads/highway
are considered part of this LR as they are an integral function of the
roadscape. |
|||||||
14.1 |
MTRC East Rail |
Low |
Low |
High |
Low |
||
The LR includes a short section of MTRC East Railway
running between Sheung Shui and Lo Wu Stations. No significant planting is found along the railway
lines and trees growing randomly in its vicinity are dominated by Leucaena leucocephala. |
|||||||
This resource is highly utilized by the general
public and well linked but it is man-made with low landscape value and a high
ability to accommodate change. Its
sensitivity is low. |
|||||||
14.2 |
Sha Tau Kok Road (Lung Yeuk Tau) |
Medium |
Low |
Medium |
Medium |
||
Sha Tau Kok Road (Lung Yeuk Tau) starts from Sheung Shui
Police Station and runs northwest through the south of Luen Wo Hui in the FLN
NDA Study Area.
There is significant roadside planting, with planted trees dominated
by Melaleuca quinquenervia found
along the road sides and the central divider.
In addition to trees, amenity shrubs such as Ixora chinensis and Schefflera
arboricola are also planted to enhance to landscape value of this area. |
|||||||
Despite this being a man-made resource, the
landscape value of this LR is increased by the significant roadside planting
with many mature roadside trees and overall its sensitivity is considered to
be medium. |
|||||||
14.3 |
Fanling Highway |
Medium |
Low |
Medium |
Medium |
||
This LR is a major transportation corridor
connecting Fanling, Sheung Shui, Kwu Tung and other adjacent areas. It includes a short section of Fanling
Highway with a reasonable amount of roadside planting with some mature
tree. Species include Melaleuca quinquenervia, Bombax ceiba, Ficus microcarpa, Casuarina
equisetifolia, Acacia confusa
and Bauhinia blakeana. |
|||||||
This is a man-made resource, and due to the roadside
planting is less able to accommodate change and its overall sensitivity is
considered to be medium. |
|||||||
14.4 |
MTRC near Fanling Highway |
Low |
Low |
High |
Low |
||
This LR is small section of the MTRC East Rail line running
parallel to Fanling Highway. It has no
planting associated with it, only noise barriers at its edges. This is a man-made resource which has a high ability
to accommodate change. Its overall
sensitivity is considered to be low. |
|||||||
FLR 15 - Columbarium Refers to Columbarium in Wo Hop Shek. Built form is scattered throughout the
woodland area consisting of a variety of indigenous (Celtis sinensis, Macaranga tanarius, Ficus hispida, Ficus microcarpa
and Litsea glutinosa) and exotic species (Acacia confusa, Eucalyptus spp., Dimocarpus longan, Melia azedarach
and Syzygium jambos). |
|||||||
15.1 |
Wo Hop Shek Columbarium |
Medium |
Medium |
Low |
Medium |
||
This LR sits outside the works area and will not be
affected. This LR refers to the
columbarium in Wo Hop Shek. It sits inside the natural woodland area. Trees
include indigenous (Celtis
sinensis, Macaranga tanarius, Ficus hispida, Ficus microcarpa and Litsea
glutinosa) and exotic species (Acacia
confusa, Eucalyptus spp., Dimocarpus longan, Melia azedarach and Syzygium jambos). |
|||||||
The quality and landscape value of this LR is
relatively high, with little tolerance to change and its sensitivity is
considered to be medium. |
|||||||
Table 12D.3.2 Landscape Character
Areas and their Sensitivity – DP 8, 9, 10 and 12
Id. No. |
Landscape Character Area (LCA) |
Quality & Maturity |
Rarity |
Ability to Accommodate Change |
Sensitivity |
FLCA-1 |
Natural Hillside Landscape |
High |
High |
Low |
High |
Refers to large hillside areas which are dominated
by shrubland, grassland and some woodland in places such as the ravines. |
|||||
Within the Study Area for DPs this LCA
encompasses Cham Shan and Wa Shan to the north reaching 164 mPD and the
foothills of Lung Shan to the south.
Other areas of this LCA found within the study area are at Wong Kong
Shan, Stable Hill (Wu Tip Shan), and Ling Hill. They are relatively at lower height and close
to human activities. |
|||||
This LCA is predominantly natural and of high
quality. It is a significant LCA within the Study Area and has a low
tolerance to change. Therefore its
sensitivity is considered to be high.
|
|||||
FLCA-2 |
Rural and Urban Peripheral Village Landscape |
Medium |
Medium |
Medium |
Medium |
Refers to rural village areas and village areas on
the fringes of urban developments, including relic landscapes of former
villages. This LCA is dominated by
small or medium sized villages with modern and traditional houses and some
temples, interspersed with small agricultural plots and comprises a broad
mixture of other land uses including water ponds, schools, sports grounds,
and playgrounds, some open storage areas and car parks. This LCA also has some patches of woodland
as well as vegetation associated with the villages and park areas. |
|||||
Within the Study Area for DPs this LCA is
generally found at the foothills of the Cham Shan and Wa Shan to the east and
some lowland areas to the southwest, such as Sheung
Shui Wai, Tai Tau Leng, Tsung Pak Long, North District Hospital and Hong Kong Golf Club. |
|||||
This LCA is
considered to have medium tolerance to change and be of moderate amenity
value. Its sensitivity is therefore medium. |
|||||
FLCA-3 |
Urban Development Landscape |
Low |
Low |
HIgh |
Low |
Refers to urban areas with significant numbers of
high-rise developments and extensive transport infrastructure. It also contains car parks and open areas
associated with urban development such as playgrounds and small parks and
sitting out areas. This LCA has
limited natural vegetation but does include some man-made landscaping. |
|||||
Within the Study Area for FLN NDA this LCA is found
only towards the south-western boundary including Sheung Shui and Fanling
town centres, with buildings becoming more modern. It includes the high-rise developments such
as Woodland Crest, Grand Regentvillie, Regentville, and Avon Park and some
high rise estates such as Tin Ping Estate. |
|||||
This is an important residential landscape and has
high tolerance to change. The sensitivity of this LCA is considered to be low. |
|||||
FLCA-4 |
Industrial Landscape |
Low |
Low |
High |
Low |
Refers to areas comprising a broad mix of land uses
including factories, utility facilities, workshops, open storage and some
channelized water courses. It is
normally located on low lying ground or at the base of hills and may include
small and fragmented areas of residential houses and their associated
agricultural land. There is little
significant vegetation among this built environment, but small patches of
vegetation do exist, particularly along the channelized river. |
|||||
Within the Study Area for DPs this LCA is mainly
comprised of vacant land and open storage such as that found along Sha Tau
Kok Road near Ng Tung River, Sheung Shui Industrial and
Fanling Industrial Area. Some open storage uses are also found near
some villages, such as Lung Yeuk Tau and Kiu Tau. |
|||||
This LCA contains man-made facilities that are able
to accommodate change, particularly if they have been abandoned. Except for the significant planting along
the Ng Tung River, most areas in this LCA are exposed with the vegetation
largely removed, resulting in a low landscape amenity. Therefore, the sensitivity of this LCA is
considered to be low. |
|||||
FLCA-5 |
Lowland Agricultural Landscape |
Medium |
Medium |
Medium |
Medium |
Refers to large areas dominated by agricultural land
(active and abandoned) with scattered small villages and low-rise buildings
and may also include some fishponds and irrigation ponds. This LCA is mostly found among lowlands and
floodplain areas. |
|||||
Within the Study Area for DPs the key area of
this LCA is found at Tin Ping Shan Valley and Ma Shi Po. Tin Ping Shan Valley is located in the
valley between Ng Tung River and Wa Shan.
Around the promontory of Wa Shan past Sacred Hill are abandoned
agricultural fields and drained concrete fishponds. The remaining area is active agriculture
and contains Wu Nga Lok Yeung village. Ma Shi Po agricultural land is in the
lowland area located to the east of Wu Nga Lok Yeung. It is primarily
agricultural land with a mixed use of villages and light industry amongst
manmade woodland and nursery. The fragmented greenery pattern extends from the
north to the south side of the Ng Tung River. |
|||||
The value and significance of the LCA is high with
the much of the agricultural land having been established for a number of
years in this the FLN NDA Study Area.
This LCA can accommodate limited change and its overall sensitivity is
considered to be high. |
|||||
FLCA-6 |
Major Transportation Corridor Landscape |
Low |
Low |
High |
Low |
Refers to major highway and railway areas, with
their scattered associated buildings. |
|||||
Within the Study Area for DPs, Fanling Highway,
Sha Tau Kok Road and MTRC East Railway are major transport routes stretching
in a variety of directions and located at the west and south boundaries of
the Study Area, connecting the FLN NDA with other adjacent areas. |
|||||
The LCA is considered to be highly tolerant to
change and its sensitivity is low.
|
|||||
FLCA-7 |
Major Water Course Corridor Landscape |
Medium |
Medium |
Medium |
Medium |
Refers to modified water courses channelized with
concrete or grasscrete and also includes some walkways along the water course
and the vegetation associated with the water course, both within the channel
and along the banks as well as in the ridge of the banks. |
|||||
Within the Study Area of DPs this LCA includes
sections of Ng Tung River, Shek Sheung River and Ma Wat River. |
|||||
The landscape
amenity and significance of this LCA are medium. Due to its largely man-made state, it is
reasonably tolerant to change and its sensitivity is considered to be medium. |
12D.3.1 Summary of Baseline Conditions
The LRs within the Study Area which have been identified for their higher sensitivity are generally natural streams, woodland, marsh/ wetland, some water ponds, although other resources may also have high sensitivity due to certain characteristics.
LRs associated with natural water bodies are often considered higher value resources. With the exception of a natural stream at Tin Ping Shan Agricultural Land (FLR-2.1) which much of it passes through development areas and is degraded by pollution while some sections of the stream are fortified by concrete banks and a natural steam at Cham Shan (FLR-2.2), which has banks partially paved in places and low water quality (commonly polluted with rubbish). The natural streams in FLN (in Lung Shan (FLR-2.3), Siu Hang San Tsuen (FLR-2.4) and Kau Lung Hang, Yuen Leng and Nam Wa Po (FLR-2.5)) all have high sensitivity, largely due to their intactness and low ability to accommodate change. Pond areas which are no longer used or actively managed in the area consist of ponds at Fu Tei Au (FLR-3.3), within the eastern rural area (FLR-3.4), at Wai Loi Tsuen (FLR-3.5) and Nam Wa Po (FLR-3.6); all of these ponds are noted as having medium sensitivity. In addition, the mitigation wetland along Ng Tung River (FLR-4.2), is rated as highly sensitive largely due to their rarity within a developed landscape setting, natural characteristics and sensitivity to change.
Trees are considered as a precious LR therefore, all areas of hillside woodland within the Study Area are rated as having high sensitivity. These include Sheung Shui Water Treatment Works Hillside Woodland (FLR-6.1), Cham Shan and Wa Shan Hillside Woodland (FLR-6.2), Ma Wat Wai Hillside Woodland (FLR-6.3) and Hillside Woodland at Lung Shan and Wa Mei Shan (FLR-6.4). Unlike woodland within KTN, the lowland woodland around FLN is generally of low to medium quality as a result of human disturbance. The lowland woodland at Sacred Hill (FLR-7.4) and at Ling Hill/Ling Shan Tsuen (FLR-7.5) are considered to have high sensitivity as they are of better quality, more pristine and therefore less able to accommodate change. There are no OVTs in this area but one area of plantation (at Ha Pak Tsuen (FLR-5.2) is considered to have high sensitivity as a result of its maturity, number of mature tree specimens within a traditional village setting, giving it a low ability to accommodate change.
FLR8 Shrubland/Grassland Mosaic surrounds the study area such around Fu Tei Au (FLR-8.2), Cham Shan and Wa Shan (FLR-8.3). It is also commonly associated with hillsides and local prominences such as Lung Shan (FLR 8.4). These LR are generally located on undeveloped areas of natural topography however they are managed using periodic fires, therefore their overall sensitivity is considered to be medium. Areas of shrubland/grassland mosaic located close to Sheung Shui STW at Fu Tei Au (FLR8.2)is established on a man-made landscape feature (artificial watercourse channel) therefore the sensitivity is considered to be low.
All agricultural LRs within the study boundary for the schedule 2 DPs have been attributed with medium sensitivity as a result of generally medium quality and that it is relatively easy to re-create in the right environment and not overly rare in the New Territories.
With regards to LCAs, Natural Hillside Landscape in FLN NDA (FLCA-1) is considered highly sensitive, largely due to its high landscape quality and inability to accommodate change. Rural and Urban Peripheral Village Landscape (FLCA-2) and Major Water Course Corridor Landscape (FLCA-7) have medium sensitivity, largely due to their moderate amenity value and medium tolerance to change. The Lowland Agricultural Landscape in this area (FLCA-5) is predominantly of medium value and considered reasonably easy to recreate given the right environment, and therefore also has medium sensitivity. The Major Transport Corridor Landscape in this area (FLCA-6) includes the southern Fanling Highway and part of the MTRC East Rail Line. Unlike in the KTN area, there is limited planting within this LCA within the Study Area so it has a high ability to accommodate change and therefore this LCA has low sensitivity. Urban Development Landscape (FLCA-3) and Industrial Landscape (FLCA-4) also have low sensitivity due to their low landscape quality through human development and high ability to accommodate change.
The proposed DPs relate to the provision of new road infrastructure together with improvements to existing road and reprovision of a temporary wholesale market. A summary of the likely site formation impact for each DP is provided below:
12D.4.1
DP
8 - Po Shek Wu Interchange Improvement
A flyover along the southbound direction of Po Shek Wu Road will be constructed from south of Po Wan Road to westbound Fanling Highway. This flyover is responsible for diverting the traffic from southbound Po Shek Wu Road to westbound Fanling Highway from Po Shek Wu Interchange. This will involve the construction of a new northbound lane at the west side of Po Shek Wu Road (section between Po Wan Road and San Wan Road). In this case the proposed slip road will be elevated above the existing Po Shek Wu Road, at a level of +20mPD (i.e. road infrastructure has been stacked to reduce the overall footprint and accommodated the improvement works within the existing constraints). The existing northbound and southbound lanes would then be realigned to the west side. This provides the space for the construction of the foundation and pile cap of the piers of the bridge at the east side of Po Shek Wu Road. The existing slope on the eastern side of Po Shek Wu Road would be maintained.
The majority of the road falling within the improvement works will be contained within a new fully enclosed system of 6m high noise barriers.
12D.4.2 DP 9 and 10 - Fanling Bypass, East and West Sections
The
proposed Fanling Bypass Western Section serves as a district distributer road
with 2 lanes with an average carriageway width of 7.3m. The alignment will require site clearance,
tree felling, demolition and cut and fill works throughout the works area to
form the road. This
section of the Fanling Bypass will be constructed at-grade along its entire
route. A short section of 3m high noise
barriers will be constructed at the western end of the scheme close to Man Kam
To Road. On the north side of the road
in the same location a 150m section of 5m high vertical barrier will be
constructed. In addition 2no pedestrian footbridges are proposed.
The
proposed Fanling Bypass Eastern Section acts as a primary distributor road with
dual lanes with a carriageway width of 14.6m.
The dual carriageway includes a central reservation. Initially the road is constructed at-grade
before it crosses Ng Tung River, after this crossing the road returns to
at-grade level and progressively drops to form an underpass beneath Sha Tau Kok
Road. Beyond the underpass, as the road
travels further south it becomes elevated and remains on viaduct along the
remaining alignment until it joins with the existing Fanling Highway. The construction works for this section are
far more extensive and will include site clearance, tree felling, demolition
and cut and fill works throughout the works area to form the road. Major excavation works will be required to
form the underpass at Sha Tau Kok Road.
In addition, the realigned Ma Wat River channel will be required to the
west of Wing Ning Tsuen. Numerous pedestrian
footbridges are proposed along the route at key crossing points. Noise barriers are proposed along the
majority of the route.
12D.4.3
DP12
Reprovision of wholesale market in FLN NDA.
As a result of the alignment of the Fanling Bypass Eastern Section where passes through the existing wholesale market site off On Kui Street, Reprovision of the site is proposed in the same location although it will be re-orientated to run parallel to the road alignment and partially occupy the adjacent land plot occupied by the water supplies department. Breaking out of existing surfaces, vegetation clearance, demolition of temporary structures and formation of new surfaces would be required.
During the construction of the various components of DPs 8, 9, 10 and 12, potential landscape and visual impacts will generally result from the following:
· Site clearance including demolition of structures and tree removal/transplantation would have a negative landscape and visual impact due the appearance of construction activities and loss of vegetation cover. Demolition of unsightly or temporary structures may generate positive impacts.
· Site formation works including cutting and filling e.g. of farmland, streams would generate negative impacts as a result of the loss of these features of high landscape value.
· Stockpiling of construction and demolition materials, including existing topsoil, storage of construction equipment and mechanical plant would generate negative visual impact as a result of these operations intruding into existing views.
· Construction of at-grade and above ground facilities including, bridges, viaducts, interchanges, roads and noise barriers are likely to generate negative visual impacts as a result of these operations intruding into existing views and the scale of the construction footprint.
· Temporary structures within the Project Site including site offices, boundary fencing/hoarding and parking areas would generate negative visual impact due to generally low aesthetical value of these types of structures.
· Re-alignment of roads would generate negative visual impacts due to the visibility of construction operations and the likely large scale construction footprint.
· Re-alignment of streams and watercourses would generate negative visual impacts due to the loss of visual amenity provided by these resources
· Alteration to natural terrain would generate negative landscape and visual impact as a result of the appearance of major earth works, construction movements, loss of visual amenity and likely large scale construction footprint.
During the operation phase, potential impacts will result from the following:
· Operation of new roads including intersections and viaducts would generate negative visual impacts due to the potential obstruction of existing views visibility of new structures, and traffic movements.
· Provisions of noise mitigation structures are likely to generate some negative visual impacts due to the appearance of new built form and potential to obstruct existing views. This may be balanced where the barriers may provide screening from visual detractors.
· Residual impacts from loss of trees and vegetation during the construction phase would generate negative landscape and visual impacts in the short term until compensation planting has established and replaced these resources.
The landscape impact assessment has been carried out taking into consideration the baseline LRs and LCAs described in Section 12D.3 and potential impacts described in Sections 12D.4 and 12D.5.
Further details of the potential landscape impacts are provided for each DP below. The magnitude of change for LRs and LCAs is presented in Tables 12D.6.1 and 12D.6.2 below.
Landscape
impacts are presented on Figures 12.52.23 and 12.52.41
to 50.
Table 12D.6.1 - Magnitude of Change on LRs (DP8, 9, 10, 12)
Note - For LRs where no impact is recorded, these are not
shown.
Name |
DPs and Site No. (Land Use Type*) Impacting LR |
Area of LR
within study area and within DP boundary
(ha) or length (m or Km) |
Physical extent of the impact (Small/ Medium/ Large) |
Compatibility with Surrounding Landscape |
Duration of Impact |
Reversibility of Change |
Magnitude of Change |
||||||||||||||||||||||||||||||||||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||||||||||||||||||||||||||||||||||||||||
KLR 1 |
Channelized Water
Course |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
1.1 |
Ng Tung River (Fanling District) |
DP 9: Fanling Bypass
Western Section DP 10: Fanling
Bypass Eastern Section |
Study Area: 40.68ha/ 3.60km DP Boundary: 9.82ha/ 2.6km |
Medium |
Poor |
Fair |
Temporary Medium |
Permanent |
Reversible |
Irreversible |
Small |
Small |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation. The majority of DP9 sits within this LR as it runs parallel to the
river channel. The upper embankment of
the river comprises a road access track which will generally not be
affected. The road is lined with
mature and semi-mature trees, a small proportion of which will require
felling in localized areas where junction points are formed with bridges
crossing the river (outside the scope of the schedule 2 DPs). Where the road formation becomes closer to
the channel as it approach the proposed junction with DP10, earthworks to
bring levels up may impact on intervening vegetation between the road
alignment and the channel. The river
banks and bed of the river would not be affected, only the surface beyond the
banks. DP10 will have a larger impact on this resource as the road alignment
is wider and runs closer to the channel edge therefore a larger proportion of
the tree planting lining the access road will require felling. The alignment then crosses the river
channel. Bridge construction works are
likely to require large scale excavations to form abutments beyond the river
banks. As a result of the partial loss of tree cover along the river
alignment, the compatibility of the work during construction is considered to
be poor. Taking into account the heavily engineered nature of the channelized
river course and the realigned channel profile the compatibility during
operation would be fair. The majority of this resource will remain intact throughout the
construction and operation stage therefore the overall magnitude of change is
considered to be small. |
|||||||||||||||||||||||||||||||||||||||||||||||||
1.2 |
Shek Sheung River |
DP8: Po Shek Wu Interchange Improvement |
Study Area: 4.30ha/633m DP Boundary: 0.18ha/63m |
Small |
Good |
Good |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Negligible |
Negligible |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction and Operation. A very small part
of DP 8 will affect an area of existing hardstanding, due to the very small
scale and previous developed nature, the compatibility is considered to be
good in construction and operation. The DP will have a
very limited impact on this LR, therefore the magnitude of change is
considered to be negligible in construction and operation. |
|||||||||||||||||||||||||||||||||||||||||||||||
1.4 |
Ma Wat River |
DP 10: Fanling
Bypass Eastern Section DP 12:
Reprovision of Wholesale Market |
Study Area: 25.84ha / 5.5km DP Boundary 12.30ha/ 4.4km |
Large |
Poor |
Fair |
Temporary Medium |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction and Operation As a result of the
localised loss of vegetation and channel realignment works, the compatibility
in construction is considered to be poor.
Taking into account the heavily engineered nature of the channelized
river course and the realigned channel profile the compatibility during
operation would be fair. DP12 will be
realigned to fit the new road and channel alignment, the principal influence
on the LR comes from DP10. The majority of this resource will remain intact throughout the
construction and operation stage however the associated earthworks and bypass
construction are large scheme, therefore the magnitude of change during
construction is considered to be large.
As the subsequent development will replace the river channel with an
identical channel albeit on a different alignment and with the reduce scale
of the construction area, the magnitude of change is operation would be
intermediate. The main difference
being the alignment of the new bypass. |
|||||||||||||||||||||||||||||||||||||||||||||||
KLR 2 |
Water Course |
|
|
|
|
|
|
|
|
|
|
|
|
||||||||||||||||||||||||||||||||||||
2.4 |
Natural Streams at
Siu Hang San Tsuen |
DP 10: Fanling Bypass
Eastern Section |
Study Area: 1.13km DP Boundary: 160m |
Medium |
Poor |
Fair |
Temporary Short Term |
Permanent |
Reversible |
Reversible |
Small |
Small |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction
and Operation The downstream area
of the stream at Siu Hang San Tsuen falls within the footprint of the DP and will be
affected by the site designated for the Fanling Bypass Eastern Section. Fanling Bypass will be an elevated viaduct over the
section close to the stream and should avoid directly impacting it and
causing any loss of the stream. It is expected that the intensity of sunlight
that can reach the stream area will be reduce by the viaduct and as a result
the growing conditions of riparian plants and the landscape quality provided
by such riparian plants, will be reduced.
In construction, the works will occur over the stream and therefore
the compatibility would be poor. In
operation the works would not directly impact the stream although would cross
the LR on viaduct, in this case the compatibility would be fair. Overall, the
magnitude of change during construction and operation would be small due to
the lack of direct impact on the stream. |
|||||||||||||||||||||||||||||||||||||||||||||||
FLR 4 |
Marsh / Wetland |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
4.2 |
Mitigation Wetland |
DP 9: Fanling
Bypass Western Section |
Study Area: 5.53ha DP Boundary: 1.59ha |
Medium |
Poor |
Poor |
Permanent |
Permanent |
Irreversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and OperationThere are five main
mitigation wetland areas located along Ng Tung River
within the DP boundary. The proposed DP will cut
across two of the wetlands on the northern side of Ng Tung River; road formation
will require partial filling and permanent loss off the resource where
affected. As these works will
involve the partial loss of this resource, the compatibility is considered to
be poor in construction and operation. The majority of the
impact would be as a result of the Schedule 3 development, in the case the
magnitude of change is considered to be intermediate in
construction and operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 6 |
Hillside Woodland |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
6.2 |
Cham Shan and Wa
Shan Hillside Woodlands |
DP 9: Fanling
Bypass Western Section DP 10: Fanling Bypass
Eastern Section |
Study Area: 62.25ha DP Boundary 1.52ha |
Small |
Poor |
Poor |
Permanent |
Permanent |
Irreversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Part of this LR
along the northern bank of Ng Tung River will be adversely
affected by the Fanling Bypass construction work. Trees are likely to be removed
during site clearance and formation and the land use will be permanently
changed. Considering a small area will be affected, the magnitude of impact
is considered to be small. |
|||||||||||||||||||||||||||||||||||||||||||||||||
6.4 |
Hillside Woodlands at Lung Shan and Wa Mei Shan |
DP 10: Fanling
Bypass Eastern Section |
Study Area: 23.28ha DP Boundary: 1.50ha |
Small |
Poor |
Poor |
Permanent |
Permanent |
Irreversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Due to permanent
loss but small scale of works, the magnitude of change is considered to be
Intermediate during construction and operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 7 |
Lowland Woodland |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
7.3 |
Hung Kiu San Tsuen
Lowland Woodland |
DP 9: Fanling Bypass
Western Section |
Study Area: 5.2ha DP Boundary: 0.46 |
Small |
Poor |
Poor |
Permanent |
Permanent |
Irreversible |
Irreversible |
Small |
Small |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Due to permanent
loss of resource the compatibility during construction and operation is
considered to be poor. Only a very small
area of this LR falls within the DP.
Woodland here will be cleared prior to site formation. Since the area affected is so small, less
that 9% of the LR area and taking into account the poor compatibility, the
overall magnitude of change is considered to be small during construction and
operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
7.7 |
Lowland Woodland near Tai Tau Leng |
DP8: Po Shek Wu Interchange
Improvement |
Study Area: 1.25ha DP Boundary: 0.57 |
Small |
Poor |
Poor |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Due to permanent loss of resource the compatibility during
construction and operation is considered to be poor. As around 45% of the LR will be permanently changed, the magnitude of
change is considered to be intermediate in construction and operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 8 |
Shrubland /
Grassland Mosaic |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
8.3 |
Shrubland/Grassland
Mosaic at Cham Shan and Wa Shan |
DP 9: Fanling
Bypass Western Section DP 10: Fanling
Bypass Eastern Section |
Study Area: 85.81ha DP Boundary 0.65ha |
Small |
Poor |
Poor |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Small |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation The works will
require permanent change to the LR therefore compatibility in construction
and operation is considered to be poor. As a result of the
small scale of the area which forms part of a more extensive area of the LR,
the magnitude of change is considered to be small in construction and
operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 9 |
Agricultural Land |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
9.2 |
Fu Tei Au Agricultural
Land |
DP 9: Fanling Bypass
Western Section |
Study Area: 3.61ha DP Boundary: 0.06 |
Small |
Poor |
Poor |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation A small area of farmland falls within the boundary of the proposed DP,
vegetation clearance and filling works will be required. As the work would involve loss of the LR
the compatibility is considered to be poor during construction and operation. Due to the very small scale of the intrusion of these works into the
LR, the magnitude of change is considered to be small during construction and
negligible in operation. The majority
of the impact would be as a result of the Schedule 3 works. |
|||||||||||||||||||||||||||||||||||||||||||||||||
|
|||||||||||||||||||||||||||||||||||||||||||||||||
9.5 |
Agricultural Land
at Sheung Shui Wa Shan |
DP 9: Fanling
Bypass Western Section |
Study Area: 8.47ha DP Boundary: 2.28 |
Medium |
Poor |
Poor |
Temporary Medium |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Under half of this LR
falls within the wider RODP boundary but this small area is affected by roads
The agricultural land will be lost during site clearance and site formation
here, and by operation this area of LR will be converted to incompatible land
uses, therefore compatibility during construction and operation is considered
to be poor. Given the relatively small
area however and absence of many trees on agricultural land, overall the
magnitude of change is considered intermediate during construction and
operation.. |
|||||||||||||||||||||||||||||||||||||||||||||||||
9.6 |
Agricultural Land
in Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu Hang Tsuen and Lung Yeuk Tau |
DP 9: Fanling
Bypass Western Section DP 10: Fanling
Bypass Eastern Section |
Study Area: 36.76ha DP Boundary: 5.45 |
Medium |
Poor |
Poor |
Temporary Medium |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation A large area of this LR will be affected by road construction works
which will involve vegetation clearance, cut and fill works. As the work would involve
loss of the LR the compatibility is considered to be poor during construction
and operation. Due to the scale of
the works and permanent loss of the LR, the magnitude of change is considered
to be intermediate in construction and
operation as the works only affect a relatively small area of the LR. The wider Schedule 3 works would have a
more significant impact on this LR. |
|||||||||||||||||||||||||||||||||||||||||||||||||
9.7 |
Agricultural Land
South of Sha Tau Kok Road |
DP 10: Fanling
Bypass Eastern Section |
Study Area: 8.95ha DP Boundary: 1.52 |
Large |
Poor |
Poor |
Temporary Medium |
Permanent |
Irreversible |
Irreversible |
Intermediate |
Intermediate |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Due to the scale of
the works and permanent loss of the LR, the magnitude of change is considered
to be intermediate in construction and operation. |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 11 |
Urban Development Area |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
11.2 |
Sheung Shui Urban Development Area |
DP8: Po Shek Wu Interchange Improvement |
Study Area: 110ha DP Boundary: 1.2ha |
Small |
Good |
Good |
Temporary Short Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction and Operation A small area of this LR
falls within the works area for DP however the majority of the LR relates to
the existing roadscape. Whilst the construction
works would cause some disruption to the LR, in operation this area would
remain as a road. In this case the
compatibility is considered to be good in both construction and operation. As a result of the very
small area affected and overall good compatibly of the DP with the LR, the
magnitude of change is considered to be Small during construction and
negligible in operation. |
|||||||||||||||||||||||||||||||||||||||||||||||
11.3 |
Fanling Urban Development Area |
DP 10: Fanling Bypass Eastern
Section |
Study Area: 57.21ha DP Boundary: 0.27ha |
Small |
Good |
Good |
Temporary Short Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction and Operation A small area of this LR
falls within the works area for DP 10 close to Ma Sik Road. Whilst the construction works would cause
some disruption to the LR, in operation this area would remain as a road. In this case the compatibility is
considered to be good in both construction and operation. As a result of the very
small area affected and overall good compatibly of the DP with the LR, the
magnitude of change is considered to be Small during construction and
negligible in operation. |
|||||||||||||||||||||||||||||||||||||||||||||||
FLR 12 |
Rural Development
Area |
|
|
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||
12.5 |
Wa Shan Rural
Development Area |
DP 9: Fanling
Bypass Western Section DP 10: Fanling
Bypass Eastern Section |
Study Area: 22.65ha DP Boundary: 1.59ha |
Medium |
Poor |
Fair |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
12.6 |
Lung Yeuk Tau Rural
Development Area |
DP 10: Fanling
Bypass Eastern Section |
Study Area: 54.07ha DP Boundary: 1.26 |
Small |
Fair |
Fair |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
12.7 |
Rural Development
Area at Wo Hop Shek and Wong Kong Shan |
DP 10: Fanling Bypass Eastern Section |
1.40 |
Small |
Fair |
Fair |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
12.8 |
Rural Development Area at Ma Shi Po |
DP 10: Fanling
Bypass Eastern Section |
Study Area: 12.72 DP Boundary: 0.13 |
Small |
Fair |
Fair |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
|
|
Construction impacts will result in the demolition of structures and
buildings together with clearance of vegetation and trees. Cut and fill works will be required to
achieve the correct road levels and reconfiguration of existing road
junction. The DP will require a
partial loss of this resource within a previously developed area therefore the
compatibility is considered to be fair in construction and operation. As a result of the overall scale of the
impacted area, it is considered that the magnitude of change will be small
during construction. As these are
previously developed areas, it is considered the magnitude of change would
drop to negligible during the operation stage. |
|||||||||||||||||||||||||||||||||||||||||||||||
12.12 |
Rural Development Area in Long Valley, Yin
Kong and Hak Ka Wai |
DP 8: Po Shek Wu
Interchange Improvement |
Study Area 10.6ha DP Boundary: 0.78 |
Small |
Fair |
Fair |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation The works area for the proposed DP will require some vegetation
clearance to allow road construction within this LR. The DP will require only a very small loss of this resource
within a previously developed area therefore the compatibility is considered to
be fair during construction and operation.
As a result of the overall scale of the impacted area, it is
considered that the magnitude of change will be small during
construction. As these are previously
developed areas, it is considered the magnitude of change would drop to
negligible during the operation stage. |
|||||||||||||||||||||||||||||||||||||||||||||||||
12.13 (KLR-12.5) |
Rural Development
Area to the North of Hong Kong Golf Club |
DP 8: Po Shek Wu
Interchange Improvement |
Study area: 5.3ha DP boundary: 0.06ha |
Small |
Fair |
Fair |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
|
|
Description of Key Impacts during Construction and Operation The works area for the proposed DP will require some vegetation
clearance to allow road construction within this LR. The DP will require a partial loss of this
resource within a previously developed area therefore the compatibility is
considered to be fair during construction and operation. As a result of the overall scale of the
impacted area, it is considered that the magnitude of change will be small
during construction. As these are
previously developed areas, it is considered the magnitude of change would
drop to negligible during the operation stage. |
|||||||||||||||||||||||||||||||||||||||||||||||
FLR 13 |
Industrial / Open Storage |
||||||||||||||||||||||||||||||||||||||||||||||||
13.1 |
Sheung Shui
Industrial/ Open Storage Area |
DP8: Po Shek Wu Interchange Improvements DP 9: Fanling Bypass Western Section |
Study Area: 70.03ha DP Boundary 4.02 |
Medium |
Fair |
Fair |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Intermediate |
Small |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during
Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
13.2 |
Fanling Industrial
Area |
DP 9: Fanling
Bypass Western Section DP 12:
Reprovision of Wholesale Market |
Study Area: 16.02 3.17 |
Small |
Good |
Good |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Small |
Small |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
FLR 14 |
MTRC East Rail |
|
|
|
|
|
|
|
|
|
|||||||||||||||||||||||||||||||||||||||
14.1 |
MTRC East Rail |
DP 8: Po Shek Wu Interchange Improvement |
Study Area: 7.00ha / 1.3km DP Boundary: 0.46ha 150m |
Small |
Good |
Good |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Negligible |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation As there will be no direct impacts, the magnitude of change is
considered to be negligible in construction and operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
14.2 |
Sha Tau Kok Road (Lung Yeuk Tau) |
DP 10: Fanling Bypass Eastern Section DP 12: Reprovision of Wholesale Market |
Study Area: 5.4ha/1.6km DP Boundary: 1.41ha/ 20m |
Small |
Fair |
Good |
Temporary Short |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
14.3 |
Fanling Highway |
DP8: Po Shek Wu
Interchange Improvement DP 10: Fanling
Bypass Eastern Section |
Site Area: 20.24ha/ 3.84km DP Boundary: 14.14ha/ 2km |
Large |
Fair |
Good |
Temporary Medium |
Permanent |
Reversible |
Irreversible |
Intermediate |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation Taking into account the likely large scale of the construction
footprint, it is considered that the magnitude of change during construction
would be intermediate. As the works
will form part of the existing highway corridor in the future, the magnitude
of change during operation is considered to be negligible. |
|||||||||||||||||||||||||||||||||||||||||||||||||
14.4 |
MTRC near Fanling Highway |
DP 10: Fanling
Bypass Eastern Section |
Study Area: 9.80ha / 3.8km DP Boundary: 0.27ha 170m |
Small |
Good |
Good |
Temporary Short
Term |
Permanent |
Reversible |
Irreversible |
Negligible |
Negligible |
|||||||||||||||||||||||||||||||||||||
Description of Key Impacts during Construction and Operation As there will be no direct impacts, the magnitude of change is
considered to be negligible in construction and operation |
|||||||||||||||||||||||||||||||||||||||||||||||||
Table 12D.6.2 Magnitude of Change
on LCAs (DP 8, 9, 10 and 12)
Note - For LCAs where no
impact is recorded, these are not shown.
LCA Code |
Name |
Site No. (Land Use Type*) Impacting LCA |
Area of LCA
within study area and within DP
boundary (ha) or length (m or Km) |
Physical extent of the impact (Small/ Medium/ Large) |
Compatibility with Surrounding Landscape |
Duration of Impact |
Reversibility of Change |
Magnitude of Change |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|||||
FLCA-1 |
Natural Hillside Landscape |
The LCA is affected by sites: DP10:Fanling Bypass Eastern Section (New Road) |
Study Area: 285.67ha DP Boundary 1.39ha |
Small |
Fair |
Fair |
Temporary Medium Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|
|
Description of Key Impacts
during Construction and Operation As a result of the scale and extent of the
works throughout the study area, the magnitude of change is considered to be
small in construction and negligible in operation. |
||||||||||
FLCA-2 |
Rural and Urban Peripheral Village Landscape |
The LCA is affected by sites: DP 8:Po Shek Wu Interchange Improvement (Major Improvement) DP9:Fanling Bypass Western Section (New Road) DP10:Fanling Bypass Eastern Section (New Road) |
Study Area: 454.08ha DP Boundary: 25.56ha |
Medium |
Fair |
Fair |
Temporary Medium Term |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|
|
Description of Key
Impacts during Construction and Operation As a result of the medium scale and extent
of the works throughout the study area, the magnitude of change is considered
to be intermediate in operation. |
||||||||||
|
|
|||||||||||
FLCA-3 |
Urban Development Landscape |
This LCA is affected by site: DP 8: Po Shek Wu Interchange Improvement
(Major Improvement) DP10: Fanling Bypass Eastern Section (New
Road) |
Study Area: 106.85ha DP Boundary: 1.77 |
Small |
Fair |
Fair |
Temporary Medium Team |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
|
|
Road construction works within this LCA
will require the minor road reconfiguration works. These works will remove a relatively
small proportion of this character area therefore the compatibility during
construction and operation is considered to be fair. As a result of the scale and extent of the
works throughout the study area, the magnitude of change is considered to be
small in construction and negligible in operation. |
||||||||||
FLCA-4 |
Industrial Landscape |
The LCA is affected by sites: DP 8: Po Shek Wu Interchange Improvement
(Major Improvement) DP9: Fanling Bypass Western Section (New
Road) DP10: Fanling Bypass Eastern Section (New
Road) DP12: Reprovision of wholesale market in
FLN NDA. |
Study Area: 89.05ha DP Boundary: 12.85ha |
Small |
Fair |
Fair |
Temporary Medium Term |
Permanent |
Reversible |
Irreversible |
Small |
Small |
|
|
Description of Key
Impacts during Construction and Operation As a result of the small scale and extent
of the works throughout the study area together with fair compatibility, the
magnitude of change is considered to be small in construction and operation. |
||||||||||
FLCA-5 |
Lowland Agricultural Landscape |
The LCA is affected by sites: DP 10:Fanling Bypass Eastern Section (New Road) |
Study Area: 167.98ha DP Boundary: 5.29 |
Small |
Poor |
Poor |
Temporary Medium Term |
Permanent |
Reversible |
Irreversible |
Small |
Small |
|
|
Description of Key Impacts
during Construction and Operation As a result of the relatively small area
affected, the magnitude of change during construction and operation is
considered to be small |
||||||||||
FLCA-6 |
Major Transportation Corridor Landscape |
The LCA is affected by sites: DP 8: Po Shek Wu Interchange Improvement (Major Improvement) DP10:Fanling Bypass Eastern Section (New Road) |
Study Area: 41.04 / 10.54km DP Boundary: 18.37/2.21km |
Medium |
Good |
Good |
Temporary Short Term |
Permanent |
Reversible |
Irreversible |
Small |
Negligible |
Description of Key
Impacts during Construction and Operation The majority of the works will involve the reconfiguration isolated
parts of the road to allow connection to the proposed DP, drainage provision
and highway structures (road barriers, noise barriers etc.) therefore the
overall compatibility of the work is considered to be fair during
construction. In operation the works
will fall within the existing highway infrastructure corridor therefore are
considered to have a good compatibility. Taking into account the likely large scale of the construction
footprint, it is considered that the magnitude of change during construction
would be small. As the works will form
part of the existing highway corridor in the future, the magnitude of change
during operation is considered to be negligible. |
||||||||||||
FLCA-7 |
Major Water Course Corridor Landscape |
The LCA is affected by sites: DP9: Fanling Bypass Western Section (New Road) DP10:Fanling Bypass Eastern Section (New Road) DP12: Reprovision of wholesale market in FLN NDA. |
Study Area: 66.52 / 9.1km DP Boundary: 22.12/7.00km |
Medium |
Fair |
Fair |
Temporary Short Term |
Permanent |
Reversible |
Irreversible |
Intermediate |
Small |
Description of Key
Impacts during Construction and Operation The river banks has already been heavily altered through
channelization and alignment modifications, therefore no valuable natural
features will be lost or affected. In
this case the compatibility of the scheme is considered to be fair both in
construction and operation. Due to the relatively large scale of the area affected the magnitude
of change is considered to be Intermediate during construction and small in
operation. |
A summary of the key landscape impacts identified in Tables 12D.6.1 and 12D.6.2 for each DP is provided below.
DP8 Po Shek Wu Interchange Improvements
The principal impacts as a result of the improvement works will occur
during the construction stage. The
following LRs/LCAs are affected:
FLR-1.2 Shek Sheung River
FLR-7.7 Lowland Woodland near Tai Tau Leng
FLR-11.2 Sheung Shui Urban Development
Area
FLR-12.12 Rural Development Area in Long Valley, Yin Kong and Hak Ka Wai
FLR- 12.13 Rural Development Area to the North of Hong Kong Golf Club
FLR-13.1 Sheung Shui Industrial/Open Storage Area
FLR-14.1 MTRC East Rail
FLR-14.3 Fanling HighwayFLCA-2 Rural and Urban Peripheral
Village Landscape
FLCA-3 Urban Development Landscape
FLCA-4 Industrial Landscape
FLCA-6 Major Transportation Corridor Landscape
It is predicted that most impacts will be generated in relation to FLR 12.12 where construction works will encroach onto this resource requiring clearance of vegetation to form the road alignment. Generally the compatibility of these works is considered to be fair in construction and fair in operation.
DP9 Fanling Bypass Western Section
The principal impacts as a result of the bypass construction works will
occur during the construction stage and operational stage. The following LRs/LCAs are affected:
FLR-1.1 Ng Tung River (Fanling District)
FLR-4.2 Mitigation Wetland
FLR-6.2 Cham Shan and Wa Shan Hillside Woodlands
FLR-7.3 Hung Kiu San Tsuen Lowland Woodland
FLR-8.3 Shrubland/Grassland Mosaic at Cham Shan and Wa Shan
FLR-9.2 Fu Tei Au Agricultural Land
FLR-9.5 Agricultural Land at Sheung Shui Wa Shan
FLR-9.6 Agricultural Land in Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu
Hang Tsuen and Lung Yeuk Tau
FLR-12.5 Wa Shan Rural Development Area
FLR-13.1 Sheung Shui Industrial/Open Storage Area
FLR-13.2 Fanling Industrial Area
FLCA-2 Rural and Urban Peripheral Village Landscape
FLCA-4 Industrial Landscape
FLCA-7 Major Watercourse Corridor Landscape
It is predicted that most impacts will be generated in relation to FLR 4.2, 6.2, 7.3, 9.5 where construction works will encroach onto these resources requiring clearance of vegetation, mature trees, loss of agricultural land, cut and fill works to form the road alignment. Generally the compatibility of these works is considered to be poor in construction and operation.
DP10 Fanling Bypass Eastern Section
The principal impacts as a result of the bypass construction works will
occur during the construction and operational stage. The following LRs/LCAs are affected:
FLR-1.1 Ng Tung River (Fanling District)
FLR-1.4 Ma Wat River
FLR-2.4 Natural Streams at Siu Hang San Tsuen
FLR-6.2 Cham Shan and Wa Shan Hillside Woodlands
FLR-6.4 Hillside Woodlands at Lung
Shan and Wa Mei Shan
FLR-8.3 Shrubland/Grassland Mosaic at Cham Shan and Wa Shan
FLR-9.6 Agricultural Land in Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu
Hang Tsuen and Lung Yeuk Tau
FLR-9.7 Agricultural Land South of Sha Tau Kok Road
FLR-11.3 Fanling Urban Development Area
FLR-12.5 Wa Shan Rural Development Area
FLR-12.6 Lung Yeuk Tau Rural Development Area
FLR-12.7 Rural Development Area at Wo Hop Shek and Wong Kong Shan
FLR-12.8 Rural Development Area at Ma Shi Po
FLR-14.2 Sha Tau Kok Road (Lung Yeuk Tau)
FLR-14.3 Fanling Highway
FLR-14.4 MTRC near Fanling Highway
FLCA 1 Natural Hillside Landscape
FLCA-2 Rural and Urban Peripheral Village Landscape
FLCA-3 Urban Development Landscape
FLCA-4 Industrial Landscape
FLCA-5 Lowland Agricultural Landscape
FLCA-6 Major Transportation Corridor Landscape
FLCA-7 Major Water Course Corridor Landscape
It is predicted that most impacts will be generated in relation to FLR 6.2, 6.4, 8.3, 9.6, 9.7 where construction works will encroach onto these resources requiring clearance of vegetation, mature trees, cut & fills works, loss of agricultural land to form the road alignment. Generally the compatibility of these works is considered to be poor in construction and operation.
DP 12: Reprovision of Wholesale Market
The principal impacts as a result of the wholesale market reprovision
works will occur during the construction stage.
The following LRs/LCAs are affected:
FLR-1.4 Ma Wat River
FLR-13.2 Fanling Industrial Area
FLR-14.2 Sha Tau Kok Road (Lung Yeuk Tau)
FLCA-4 Industrial Landscape
FLCA-7 Major Water Course Corridor Landscape
It is predicted that most impacts related to the DP construction will be limited due to the good compatibility with the receiving landscape.
The potential significance of landscape impacts during the construction and operational phases, before mitigation, is provided in Tables 12D.8.1 and 12D.8.2 below. The assessment follows the methodology proposed in Section 12.18 and the matrix provided in Table 12.18.1.
Landscape
impacts are presented on Figures 12.52.23 and 12.52.41 to 50.
Table 12D.8.1 Significance of landscape impacts on LRs (DP
8, 9, 10 and 12)
Name |
LR Sensitivity (High/ Medium/ Low) |
Magnitude of Impact (Large/ Intermediate/ Small/
Negligible |
Impact Significance BEFORE Mitigation (Substantial/
Moderate/ Slight/ Insignificant) |
||||
Construction |
Operation |
Construction |
Operation |
||||
FLR 1 |
Channelized Water Course |
|
|
|
|||
1.1 |
Ng Tung River
(Fanling District) |
Medium |
Small |
Small |
Slight |
Slight |
|
1.2 |
Shek Sheung River |
Medium |
Negligible |
Negligible |
Insignificant |
Insignificant |
|
1.4 |
Ma Wat River |
Medium |
Large |
Intermediate |
Substantial |
Moderate |
|
FLR 2 |
Water Course |
|
|
|
|
||
2.4 |
Natural Streams at Siu
Hang San Tsuen |
High |
Small |
Small |
Moderate |
Moderate |
|
FLR 4 |
Marsh / Wetland |
|
|
|
|
||
4.2 |
Mitigation Wetland |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
FLR 6 |
Hillside Woodland |
|
|
|
|
||
6.2 |
Cham Shan and Wa
Shan Hillside Woodland |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
6.4 |
Hillside Woodland
at Lung Shan and Wa Mei Shan |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
FLR 7 |
Lowland Woodland |
|
|
|
|||
7.3 |
Hung Kiu San Tsuen
Lowland Woodland |
Medium |
Small |
Small |
Moderate |
Moderate |
|
7.7 |
Lowland Woodland
near Tai Tau Leng |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
FLR 8 |
Shrubland/Grassland Mosaic |
|
|
|
|||
8.3 |
Shrubland/Grassland
Mosaic at Cham Shan and Wa Shan |
Medium |
Small |
Small |
Slight |
Slight |
|
FLR 9 |
Agricultural Land |
|
|
|
|||
9.2 |
Fu Tei Au Agricultural
Land |
Medium |
Small |
Negligible |
Slight |
Insignificant |
|
9.5 |
Agricultural Land
at Sheung Shui Wa Shan |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
9.6 |
Agricultural Land
in Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu Hang Tsuen and Lung Yeuk Tau |
Medium |
Intermediate |
Intermediate |
Moderate |
Slight |
|
9.7 |
Agricultural Land
in South of Sha Tau Kok Road |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
|
FLR 11 |
Urban Development Area |
|
|
||||
11.2 |
Sheung Shui Urban
Area |
Low |
Small |
Negligible |
Slight |
Insignificant |
|
11.3 |
Fanling Urban Area |
Low |
Small |
Negligible |
Slight |
Insignificant |
|
FLR 12 |
Rural Development Area |
|
|
||||
12.5 |
Wa Shan Rural
Development Area |
Medium |
Small |
Negligible |
Slight |
Insignificant |
|
12.6 |
Lung Yeuk Tau Rural
Development Area |
Medium |
Small |
Negligible |
Slight |
Insignificant |
|
12.7 |
Rural Development
Area at Wo Hop Shek and Lung Shan |
Low |
Small |
Negligible |
Slight |
Insignificant |
|
12.8 |
Rural Development
Area at Ma Shi Po |
Medium |
Small |
Negligible |
Slight |
Insignificant |
|
12.12 |
Rural Development
Area in Long Valley, Yin Kong and Hak Ka Wai |
High |
Small |
Negligible |
Moderate |
Insignificant |
|
12.13 |
Rural Development
Area to the North of Hong Kong Golf Club |
Low |
Small |
Negligible |
Slight |
Insignificant |
|
FLR 13 |
Industrial / Open Storage |
|
|
|
|||
13.1 |
Sheung Shui
Industrial/ Open Storage Area |
Low |
Intermediate |
Small |
Slight |
Slight |
|
13.2 |
Fanling Industrial
Area |
Low |
Small |
Small |
Slight |
Slight |
|
FLR 14 |
Major Transportation Corridor |
|
|
|
|||
14.1 |
MTRC East Rail |
Low |
Negligible |
Negligible |
Insignificant |
Insignificant |
|
14.2 |
Sha Tau Kok Road
(Lung Yeuk Tau) |
Medium |
Small |
Negligible |
Slight |
Insignificant |
|
14.3 |
Fanling Highway |
Medium |
Intermediate |
Negligible |
Moderate |
Insignificant |
|
14.4 |
MTRC near Fanling
Highway |
Low |
Negligible |
Negligible |
Insignificant |
Insignificant |
|
In summary for LRs, substantial adverse impacts have been predicted in the construction stage prior to mitigation in relation to FLR-1.4 Ma Wat Channel due the large scale works involved with the realignment of the river channel to accommodate the alignment of the new Fanling Bypass. These impacts would reduce to moderate in operation as the works generally return the channel back to the original condition albeit on a different alignment.
Moderate adverse impacts are predicted at FLR4.2 Mitigation Wetland due to the required filling works to form the Fanling Bypass. Additionally, FLR6.2 Cham Shan and Wa Shan Hillside Woodland, FLR 6.4 Hillside Woodland at Lung Shan and Wa Mei Shan, FLR7.3 Hung Kiu San Tsuen Lowland Woodland, FLR7.7 Lowland Woodland near Tai Tau Leng, FLR 9.5 Agricultural Land at Sheung Shui Wa Shan and FLR9.6 Agricultural Land in Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu Hang Tsuen and Lung Yeuk Tau and FLR9.7 Agricultural Land South of Sha Tau Kok Road will also experience moderate adverse impacts during construction and operation, prior to mitigation, as a result of tree felling and filling of agricultural land which will lead to a direct loss of these landscape resources within the road construction works.
FLR2.4 Natural Stream at Siu Hang San Tsuen will be affected by Fanling Bypass Eastern Section; moderate adverse impacts are predicted due to the high sensitivity of this natural feature.
In construction moderate adverse impacts will occur in relation to FLR 12.12 Rural Development Area in Long Valley, Yin Kong and Hak Ka Wai and FLR 14.3 Fanling Highway, this moderate adverse impact will drop to insignificant mainly due to the compatibility of the LRs with the previously developed landscape and limited extent of the impact area.
Slight adverse impacts would be experience by FLR 1.1 Ng Tung River (Fanling District), FLR8.3 Shrubland/Grassland Mosaic at Cham Shan and Wa Shan, FLR9.2 Fu Tei Au Agricultural Land, FLR12.5 Wa Shan Rural Development Area, FLR12.6 Lung Yeuk Tau Rural Development Area, FLR 12.7 Rural Development Area at Wo Hop Shek and Wong Kong Shan, FLR12.8 Rural Development Area at Ma Shi Po, FLR12.13 Rural Development Area to the North of Hong Kong Golf Club, FLR13.1 Sheung Shui Industrial/Open Storage Area, FLR13.2 Fanling Industrial Area, and FLR 14.2 Sha Tau Kok Road (Lung Yeuk Tau). In the case of FLR 9.2, 12.5, 12.6, 12.7, 12.8, 12.13 and 14.2, the impact significance would drop to insignificant during operation as a result of the limited extent of the area impacts and compatibility of the proposed road works with these LRs.
The remaining LRs with respect to industrial/ open storage and major infrastructure corridors such as the MTRC East Rail will all experience a slight or insignificant impact at the construction and operational stage due to their sensitivity rating and overall good compatibility with the road developments.
Table 12D.8.2 Significance of Impacts on LCAs (DP8, 9, 10 and 12)
LCA Code |
Name |
LCA Sensitivity (High/ Medium/ Low) |
Magnitude of Impact (Large/ Intermediate/
Small/ Negligible |
Impact Significance BEFORE Mitigation
(Substantial/ Moderate/ Slight/ Insignificant) |
||
Construction |
Operation |
Construction |
Operation |
|||
FLCA1 |
Natural Hillside Landscape |
High |
Small |
Negligible |
Moderate |
Insignificant |
FLCA2 |
Rural and Urban Peripheral Village Landscape |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
FLCA3 |
Urban Development Landscape |
Low |
Small |
Negligible |
Slight |
Insignificant |
FLCA4 |
Industrial Landscape |
Low |
Small |
Small |
Slight |
Slight |
FLCA5 |
Lowland Agricultural Landscape |
Medium |
Small |
Small |
Slight |
Slight |
FLCA6 |
Major Transportation Corridor Landscape |
Low |
Small |
Negligible |
Slight |
Insignificant |
FLCA7 |
Major Water Course Corridor Landscape |
Medium |
Intermediate |
Small |
Moderate |
Slight |
In summary for LCAs, moderate adverse impacts are predicted in relation to FLCA 2 Rural and Urban Peripheral Village Landscape and FLCA 7 Major Water Course Corridor Landscape in the construction stage prior to mitigation, as these LCAs will be exposed to the majority of the road improvements, bypass and associated development works.
It is predicted that FLCA 1 will experience moderate adverse impacts in the construction stage as a small area will fall within the bypass construction works area. In operation this will drop to insignificant as a result of the limited extent of the intrusion into this zone.
Slight adverse impacts were identified in the construction stage, prior to mitigation, in the assessment in relation to FLCA 5 Lowland Agricultural Landscape; this is as a result of the small scape loss of the medium sensitivity agricultural land as a result of the DPs.
Slight adverse impacts are predicted in relation to FLCA 3 Urban Development Landscape and FLCA 6 Major Transportation Corridor as a result of the construction works associated with Po Shek Wu Interchange Improvements and a small section of the Fanling Bypass works at Sha Tau Kok Road. In both cases the impact would drop to insignificant during the operational stage as the road works would be compatible with the urban / infrastructure characters.
Slight impacts are predicted in relation to FLCA 4 Industrial Landscape as is considered to have a low sensitivity rating and good compatibility with the proposed works. In this case the works are unlikely to have a beneficial impact as identified within the Schedule 3 study as the road have a neutral influence within the industrial areas.
The proposed mitigation measures for the Project are summarised in Table 12D.9.1 below. The same table also lists the agents responsible for the capital funding, the implementation and the maintenance of the suggested measures. These agents will be agreed before the start of construction.
Table 12D.9.1 Summary of proposed mitigation measures
Mitigation
Measure Code |
Summary
Description |
Capital
Funding Agency ([1]) |
Implementation
Agency |
Post-Construction
Maintenance Agency ([2]) |
MM1 |
Minimum Topographical Change |
Government |
Contractors of the Government |
n/a |
MM2 |
Detailed Design - Visual |
Government |
Contractors of the Government |
HyD |
MM4 |
Tree Protection & Preservation |
Government |
Contractors of the Government |
n/a |
MM5 |
Tree Transplantation |
Government |
Contractors of the Government |
HyD/ LCSD |
MM6 |
Slope Landscaping |
Government |
Contractors of the Government |
HyD/ LCSD |
MM7 |
Compensatory Planting |
Government |
Contractors of the Government |
HyD/ LCSD |
MM8 |
Woodland Compensatory Planting |
Government |
Contractors of the Government |
AFCD ([3]) |
MM9 |
Vertical Greening |
Government |
Contractors of the Government |
HyD/ LCSD |
MM11 |
Screen Planting |
Government |
Contractors of the Government |
HyD/ LCSD |
MM12 |
Road Greening |
Government |
Contractors of the Government |
HyD/ LCSD |
MM13 |
Marsh/Wetland Compensation |
Government |
Contractors of the Government |
CEDD/ LCSD/ AFCD |
MM14.3 |
Watercourse Impact Mitigation – Enhancement Planting on Embankment |
Government/Private Section |
Contractors of the Government/ Private
Sector |
DSD/LCSD/ AFCD |
MM14.4 |
Watercourse Impact Mitigation – Avoid affecting Watercourses |
Government |
Contractors of the Government |
DSD |
MM16 |
Screen Hoarding |
Government |
Contractors of the Government |
n/a |
MM17 |
Light Control |
Government/ Private Sector |
Contractors of the Government |
n/a |
Minimising Topographical Change (MM1)
To minimise landscape and visual impacts, the vertical and horizontal alignment of the at-grade road construction works should be optimised to reduce topographical/ landform changes, as well as reduce land take and interference with natural terrain. Where there is a need to significantly cut into the existing landform, retaining walls should be considered as well as cut slopes, to minimize landform changes and land resumption, whilst also considering visual amenity. Earthworks and engineered slopes should be designed to visually interesting landform, compatible with the surrounding landscape and to mimic the natural contouring and terrain e.g. introduction and continuation of natural features such as spurs and ridges where appropriate to support landscape and visual assimilation with the surrounding terrain.
This measure is recommended throughout the road construction in relation to the channelised water courses (Ng Tung River and Ma Wat River) where the Fanling Bypass will have numerous interfaces and crossing point; care needs to be taken in terms of future alterations to avoid damaging this resource further.
Minimising topographical change has also been recommended in relation to marshland, hillside woodland, shrubland/ grassland mosaic, agricultural land and within the rural development areas. In this case the road works will interfere with natural terrain and minimising the extent of this interference will assist in reducing the overall impact.
Detailed Design (Visual) (MM2)
The construction and operational footprint of the road infrastructure components should be kept to a practical minimum. The form, textures, finishes and colours of the proposed road structures such as viaducts, footbridges and noise barriers should aim to be compatible with the existing surroundings. The engineering design should be refined to reduce visual bulkiness and incorporate aesthetically pleasing surface treatments to promote visual amenity. For example, textured finishes for concrete surfaces to assist in breaking up uniform surface treatments on parapet structures should be considered. In addition light earthy tone colours such as shades of green, shades of grey, shades of brown and off-white should also be considered to reduce the visibility of the development components.
Noise barriers should be kept to a practical minimum and be of such a design as to integrate as well as possible into the landscape setting, where appropriate transparent materials should be incorporated to help reduce visual obstruction.
Tree Protection & Preservation (MM4)
Exiting trees to be retained within the Project Site should be carefully protected during construction. Detailed Tree Protection Specification shall be provided in the Contract Specification. Under this specification, the Contractor shall be required to submit, for approval, a detailed working method statement for the protection of trees prior to undertaking any works adjacent to all retained trees, including trees in contractor’s works areas. (Tree protection measures will be detailed at Tree Removal Application stage).
Tree Transplantation (MM5)
Trees unavoidably affected by the Project works should be transplanted where practical. Trees should be transplanted straight to their final receptor site and not held in a temporary nursery as far as possible. A detailed Tree Transplanting Specification shall be provided in the Contract Specification, where applicable. Sufficient time for necessary tree root and crown preparation periods shall be allowed in the project programme. A detailed transplanting proposal will be submitted to relevant government departments for approval in accordance with ETWBTC 2/2004 and 3/2006 HyD HQ/GN/13 Interim Guidelines for Tree Transplanting Works under Highways Department's Vegetation Maintenance Ambit. The final locations of transplanted trees should be agreed prior to commencement of the work.
Slope Landscaping (MM6)
Site formation has been reduced as far as possible to avoid substantial slope cutting (also see MM1).
Hydroseeding of modified slopes should be done as soon as grading works are completed to prevent erosion and subsequent loss of landscape resources and characters. Woodland tree seedlings and/ or shrubs should be planted where the slope gradient and site conditions allow. In addition, landscape planting should be provided for the retaining structures associated with modified slopes, where conditions allow. All slope landscaping works should comply with GEO Publication No. 1/2011-Technical Guidelines on Landscape Treatment for Slopes.
Slope landscaping has been recommended in relation to hillside and lowland woodland areas together with shrubland/grassland mosaic resources as slope cutting works may be required.
Compensatory Planting (MM7)
Compensatory tree planting for felled trees shall be provided to the satisfaction of relevant Government departments. Required numbers and locations of compensatory trees shall be determined and agreed separately with Government during the Tree Felling Application process under ETWBTC 3/2006. Compensatory planting is proposed at the potential open areas such as open spaces, amenity areas, open areas of the streetscapes, as well as the open areas within development lots. The provision of space for compensatory planting takes into account both schedule 2 and 3 designated projects.
The location of compensatory planting for DP Package D also
includes the roadside areas, street tree planting, central medians (within the
centre of the Fanling Highway) and any soft landscape areas affected by the
works area.
For specific woodland compensatory planting, see MM8.
Woodland Compensatory Planting (MM8)
Specific Woodland compensatory planting is proposed for any
areas of woodland that are unavoidably affected. The location and design of the woodland
compensatory planting will principally be within habitats of lower value such
as upland grassland. These have been considered both within the NDAs.
The
proposed locations are mostly on the foothills of Tai Shek Mo and on Fung Kong
Shan in KTN NDA with a small area in the northern FLN NDA.
The total
area allocated for compensatory woodland planting is more than 16 ha. This
provision allows in part for the fact that it will take some time for the
compensatory planting to achieve the landscape and ecological function and
value of the area to be lost. In addition, it allows for the fact that not all
of the areas identified for planting will prove to be plantable, by virtue of
topography and ground conditions and, especially, because though the areas
identified are largely grassland it is inevitable that these areas will already
support some patches of trees and shrubs which would be inappropriate for
further planting.
The
intention of the compensatory woodland will be to recreate areas of quality
woodland, not necessarily to compensate for loss of trees on a like for like
basis. Native tree species are suggested
for planting, including Ailanthus fordii, Bischofia javanica, Castanopsis
fissa, Celtis sinensis, Cinnamomum burmannii, Cinnamomum camphora, Xanthoxlyum
avicennae, Liquidambar formosana, Sapium discolor, Schefflera heptaphylla and
Ilex rotunda. In addition some
understory vegetation may be planted including shrubs such as Atalantia
buxifolia, Diospyros vaccinioides, Gardenia jasminoides, Ixora chinensis,
Ligustrum sinense, Litsea rotundifolia, Melastoma malabathricum, Melastoma
dodecandrum, Rhodomyrtus tomentosa, Rhaphiolepis indica, and Rhododendron
simsii.
Vertical Greening (MM9)
Where space and appropriate planting conditions allow (i.e. where suitable depth of planting medium is possible, maintenance access available and enough light penetration to ground level), climbing plants should be considered to grow up vertical surfaces such as viaduct piers or noise barriers. The planting once established will assist in breaking up the appearance of uniform engineered structures and surfaces.
The proposed Fanling Bypass comprises numerous vertical structures including pedestrian footbridges, viaduct piers and noise barriers which can receive vertical greening treatment as described above.
The noise barriers structures proposed in relation to the Po Shek Wu Interchange Improvement can also receive vertical where space permits.
Screen Planting (MM11)
Tall screen/buffer trees and shrubs should be planted to screen proposed structures such as roads and buildings. This measure may additionally form part of the compensatory planting and will improve compatibility with the surrounding environment and create a pleasant pedestrian environment.
Road Greening (MM12)
For viaducts, soft landscaping should be provided to soften
the hard, straight edges (for climbers used to cover the vertical, hard
surfaces of the piers – see MM9 Vertical Greening) and shade tolerant plants
should be planted, where light is insufficient, to improve aesthetic value of
areas under viaducts. Both at grade
planting and use of elevated planters should be considered for the soft
landscaping of viaducts, taking into account the preference to minimise the
overall viaduct bulk and integrate architectural forms and textural finishes
which improve aesthetics.
At grade roads planting should be considered along central dividers and on road islands e.g. in the middle of roundabouts. (Roadside planting i.e. at the road edge and not in the central divider or road island, is considered part of MM11 Screen Planting). HQ/GN/15 - Guidelines for Greening Works along Highways should be referred to for greening of highways specifically and Development Bureau TCW No. 2/2013 – Greening on Footbridges and Flyovers for footbridges and flyovers.
MM12 is used throughout the Fanling Bypass works where space to include planted central reservations and verges has been maximised.
Marsh/Wetland Compensation (MM13)
Works in relation to the Ng Tung River and Ma Wat River should match the existing and include enhancement planting to upgrade the channels as appropriate, including consideration of wetland planting along embankments where appropriate. The provision of space for marsh/wetland compensation takes into account both schedule 2 and 3 designated projects.
This measure has been recommended in relation to FLR 4.2 Mitigation Wetland where this LR will be filled in relation to the Fanling Bypass works.
Direct loss of marsh and wetland areas caused by the DPs will be mitigated by compensatory habitat and management in
the proposed Long Valley Nature Park (LVNP) where there will be some addition of wetland areas.
Watercourse Impact Mitigation (MM14)
For channelized watercourses if these are modified, they should match the existing and include enhancement planting to upgrade the channels as appropriate, including consideration of wetland planting along embankments where appropriate.
Enhancement Planting on Embankment MM14.3
For channelised watercourses, if these are modified, the Drainage Services Department Practice Note No.1/2005 – Guidelines on Environmental Considerations for River Channel Design, should be considered and appropriate mitigation measures included ensuring the new watercourses match the existing as far as possible. Measures can include enhancement planting to upgrade the channels as appropriate, including consideration of wetland planting along embankments where appropriate; as well as consideration of the best materials for the channel lining (e.g. gabion). All measures must also ensure any necessary maintenance work can be carried out and that the channel meets all its requirements for water flow.
The proposed alignment of the Fanling Bypass works will interface and cross the channels of Ng Tung River and Ma Wat River. In addition the alignment of Ma Wat River will changed to the west of Wing Ning Tsuen requiring a new channel to be excavated and the previous channels filled in, to allow for the new bypass alignment. As stated above, the replacement channel works should match the existing and where possible include enhancement planting. Both rivers presently have a grasscrete/ soft bank treatments to the riverbank which should be continued and replaced where required.
Avoid affecting Watercourses (MM14.4)
For the stream at Siu Hang San Tsuen, part of the lower stream
would be located underneath the viaduct for the proposed Fanling Bypass Eastern
Section. In order to avoid impacts to the stream, the detailed final design of
the viaduct should follow the recommendations of ETWB TCW No. 5/2005 as well as Building Department (BD) Practice
Note for Authorized Persons and Registered Structural Engineers 295: Protection
of natural streams/rivers from adverse impacts arising from construction works.
To the south of the viaduct where the stream flows through the area will be
protected by a 10m buffer in which natural vegetation will be retained and
enhanced and human activities will be limited in order to avoid direct impacts
to the stream bed and to minimise potential indirect impacts to the stream and
riparian corridor.
Screen Hoarding (MM16)
Screen hoarding shall be erected along areas of the
construction works site boundary where the works site borders with public
accessible routes and/or is close to visually sensitive receivers (VSRs), to
screen undesirable views of the works site. It is proposed that the screening
be compatible with the surrounding environment and where possible,
non-reflective, recessive colours be used.
Light Control (MM17)
Construction day and night time lighting should be
controlled to minimize glare impact to adjacent VSRs during the construction
stage. Street and night time lighting shall also be controlled to minimize
glare impact to adjacent VSRs during the operation phase. This is considered a
general measure for good practice.
Other good practise measures.
For areas unavoidably disturbed by the Project on a short
term basis e.g. works areas, the general principle to try and restore these to
their former state to suit future land use, should be adhered to.
With regard to topsoil, where identified, it should be stripped, treated appropriately, and where suitable and practical stored for re-use in the construction of the soft landscape works such as roadside amenity strips, and open space sites. It is assumed that the topmost 100mm of soil surface will be topsoil material. This good site practice and will also minimize off-site disposal.
For all planting, this should be installed as soon as the areas become available, to achieve early establishment.
The proposed landscape and visual mitigation measures, as described in Section 12D.9, have been applied to the various impacts and used to identify potential residual impacts.
The potential significance of residual landscape impacts during the construction and operational phases, before and after mitigation at day 1 and year 10, are provided in Tables 12D.10.1 and 12D.10.2. The tables assume that the appropriate mitigation measures have been applied and that the full effect of the soft landscape mitigation measures would be fully realised and established after 10 years.
Landscape mitigation measures are presented on Figures 12.52.70 to 75.
Typical
sections are presented on Figure 12.52.81 to 86.
Table
12D.10.1 Significance of landscape impacts on LRs (DP
8, 9, 10 and 12)
LR Code |
Name |
Impact
Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/
Insignificant) |
Recommended
Mitigation Measures |
Residual Impact
Significance UPON Mitigation (Substantial/ Moderate/ Slight/ Insignificant) |
|||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation (Day 1) |
Operation (Year 10) |
|||
FLR 1 |
Channelized Water
Course |
||||||||
1.1 |
Ng Tung River
(Fanling District) |
Slight |
Slight |
1, 4, 5, 14.3 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
1.2 |
Shek Sheung River |
Insignificant |
Insignificant |
1, 4, 5, 14.3 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
|
1.4 |
Ma Wat River |
Substantial |
Moderate |
1, 4, 14.3, |
1, 4, 7 |
Moderate |
Slight |
Insignificant |
|
FLR 2 |
Water Course |
||||||||
2.4 |
Natural Streams at Siu
Hang San Tsuen |
Moderate |
Moderate |
1, 4, 5 14.4 |
1, 4,7 |
Slight |
Insignificant |
Insignificant |
|
FLR 4 |
Marsh / Wetland |
||||||||
4.2 |
Mitigation Wetland |
Moderate |
Moderate |
1, 13 |
1, 13 |
Slight |
Slight |
Insignificant |
|
FLR 6 |
Hillside Woodland |
||||||||
6.2 |
Cham Shan and Wa
Shan Hillside Woodland |
Moderate |
Moderate |
1, 4, 5, 6, 8 |
1, 4, 6, 8 |
Moderate |
Slight |
Insignificant |
|
6.4 |
Hillside Woodland
at Lung Shan and Wa Mei Shan |
Moderate |
Moderate |
1, 4, 5, 6, 8 |
1, 4,6, 8 |
Moderate |
Slight |
Insignificant |
|
FLR 7 |
Lowland Woodland |
||||||||
7.3 |
Hung Kiu San Tsuen
Lowland Woodland |
Moderate |
Moderate |
1, 4, 5, 6,8 |
1, 4, 6, 8 |
Moderate |
Slight |
Insignificant |
|
7.7 |
Lowland Woodland
near Tai Tau Leng |
Moderate |
Moderate |
1, 4, 5, 6, 8 |
1, 4, 6, 8 |
Moderate |
Slight |
Insignificant |
|
FLR 8 |
Shrubland/Grassland Mosaic |
||||||||
8.3 |
Shrubland/Grassland
Mosaic at Cham Shan and Wa Shan |
Slight |
Slight |
1, 5, 6, 7 |
1, 6, 7 |
Slight |
Insignificant |
Insignificant |
|
FLR 9 |
Agricultural Land |
||||||||
9.2 |
Fu Tei Au
Agricultural Land |
Slight |
Insignificant |
1, 5,4, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
9.5 |
Agricultural Land
at Sheung Shui Wa Shan |
Moderate |
Moderate |
1, 4,5, 7 |
1, 4, 7 |
Moderate |
Moderate |
Slight |
|
9.6 |
Agricultural Land in
Wu Nga Lok Yueng, Siu Hang San Tsuen, Siu Hang Tsuen and Lung Yeuk Tau |
Moderate |
Slight |
1, 4, 5, 7 |
1, 4, 7 |
Moderate |
Moderate |
Slight |
|
9.7 |
Agricultural Land
in South of Sha Tau Kok Road |
Moderate |
Moderate |
1, 4, 5, 7 |
1, 4, 7 |
Moderate |
Moderate |
Slight |
|
FLR 11 |
Urban Development Area |
||||||||
11.2 |
Sheung Shui Urban
Area |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
|
11.3 |
Fanling Urban Area |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
|
FLR 12 |
Rural Development Area |
||||||||
12.5 |
Wa Shan Rural
Development Area |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
12.6 |
Lung Yeuk Tau Rural
Development Area |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
12.7 |
Rural Development
Area at Wo Hop Shek and Lung Shan |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
12.8 |
Rural Development
Area at Ma Shi Po |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
12.12 |
Rural Development
Area in Long Valley, Yin Kong and Hak Ka Wai |
Moderate |
Insignificant |
1, 4 , 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
12.13 |
Rural Development
Area North of Hong Kong Golf Club |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
FLR 13 |
Industrial / Open Storage |
||||||||
13.1 |
Sheung Shui
Industrial/Open Storage Area |
Slight |
Slight |
4, 5, 7 |
4, 7 |
Slight |
Insignificant |
Insignificant |
|
13.2 |
Fanling Industrial
Area |
Slight |
Slight |
4, 5, 7 |
4, 7 |
Insignificant |
Insignificant |
Insignificant |
|
FLR 14 |
Major Transportation Corridor |
||||||||
14.1 |
MTRC East Rail |
Insignificant |
Insignificant |
n/a |
n/a |
Insignificant |
Insignificant |
Insignificant |
|
14.2 |
Sha Tau Kok Road
(Lung Yeuk Tau) |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
14.3 |
Fanling Highway |
Moderate |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
|
14.4 |
MTRC near Fanling
Highway |
Insignificant |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
|
Table 12D.10.2 Significance of Impacts on LCAs (DP8, 9, 10 and 12)
LCA Code |
Name |
Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/
Insignificant) |
Recommended Mitigation Measures |
Residual Impact Significance UPON Mitigation (Substantial/ Moderate/
Slight/ Insignificant) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation (Day 1) |
Operation (Day 10) |
||
FLCA-1 |
Natural Hillside Landscape |
Moderate |
Insignificant |
1, 4, 6, 5, 7 |
1, 4, 7 |
Slight |
Insignificant |
Insignificant |
FLCA-2 |
Rural and Urban Peripheral Village Landscape |
Moderate |
Moderate |
1, 4, 5, 7 |
1, 4, 7 |
Moderate |
Slight |
Insignificant |
FLCA-3 |
Urban Development Landscape |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Slight |
Insignificant |
FLCA-4 |
Industrial Landscape |
Slight |
Slight |
1, 4, 5, 7 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
FLCA-5 |
Lowland Agricultural Landscape |
Slight |
Slight |
1, 4, 5, 7 |
1, 4, 7 |
Slight |
Slight |
Slight |
FLCA-6 |
Major Transportation Corridor Landscape |
Slight |
Insignificant |
1, 4, 5, 7 |
1, 4, 7 |
Insignificant |
Insignificant |
Insignificant |
FLCA-7 |
Major Water Course Corridor Landscape |
Moderate |
Slight |
1, 4, 5, 7, 14 |
1, 4, 7 |
Moderate |
Slight |
Insignificant |
In summary, prior to mitigation, substantial adverse impacts have been predicted in the construction stage for FLR 1.4 Ma Wat River. This is as a result of the major excavations required for the channel realignment (approximately 600m in length) to accommodate the route of the Fanling Bypass. As the LR would be replaced albeit in a different alignment, the impact would reduce to moderate adverse in operation without any mitigation. It is considered through the application of mitigation measures in the construction stage including minimising the requirement for topographical changes, enhancement planting along embankment, protecting and preserving exising trees, transplanting trees where feasible together with replacement of the channel to match the existing that this impact can be reduced to slight by operation day 1. Following the establishment of transplanted and compensatory planting by year 10 of operation, these impacts would have reduced to insignificant.
The Natural Stream at Siu Hang San Tsuen (FLR-2.4) will suffer a small change due to the Project (where it flows under the Fanling Bypass Eastern Section) due to the high sensitivity, a moderate adverse impact is predicted prior to mitigation in construction and operation. The affected stream at Siu Hang San Tsuen, has largely been protected by changes to the proposed Schedule 3 boundary during the planning of the revised RODP with much of this stream avoided. However the stretch of this stream within the DP10 boundary would be located underneath the road viaduct. To the south of the viaduct the stream flows through the area D1-3, zoned as Open Space, prior to joining Ng Tung River. In this Open Space Zone a 10m buffer is proposed in which natural vegetation will be retained and enhanced. Human activities will be limited in order to avoid direct impacts to the stream bed and to minimise potential indirect impacts to the stream and riparian corridor. At detailed design, in order to avoid impacts to the stream, the design of the viaduct should follow guidelines such as ETWB Technical Circular (Works) No. 5/2005 Protection of natural streams/rivers from adverse impacts arising from construction works as well as Building Department (BD) Practice Note for Authorized Persons and Registered Structural Engineers 295: Protection of natural streams/rivers from adverse impacts arising from construction works. This will ensure that no viaduct footings or other structures are placed in the stream; in this case the impact is considered to reduce to slight at construction, becoming insignificant by day 1 and year 10 of operation.
Planning of the revised RODP has taken care to
place much of the Mitigation Wetland in FLN NDA (FLR-4.2) that falls within the
revised RODP on land for ‘Open Space’.
The main impacts on this resource are as a result of the Schedule 3
works however moderate adverse impacts in construction and operation, prior to
mitigation, are predicted as a result of the construction of the Fanling Bypass
Western Section. Whilst the overall area
affected is relatively small (1.59ha), this is a highly sensitive and uncommon
resource. To address this impact
mitigation is provided in the form of the LVNP which will be managed and the
land there, including marsh and wetland areas, enhanced, with a slightly
increase in wetland areas. Taking into
account the LVNP enhancement and smaller level of impact as a result of the
Schedule 2 work, the residual impact significance at construction and operation
day 1 is considered to reduce to slight, and by year 10 when wetland and marshes in the LVNP mature, the residual impact will
insignificant.
Although a relatively small area of Cham Shan and Wa Shan Hillside
Woodland (FLR-6.2) and Hillside Woodland at Lung Shan and Wa Mei Shan (FLR-6.4)
is affected by the construction of the Fanling Bypass, this LR has a high
sensitivity and tree felling together with disturbance of natural topography is
considered to generate moderate adverse impacts in construction and operation
prior to mitigation. In this case,
minimising the topographical change within the LR will assist in reducing the
overall impact combined with tree preservation, tree transplantation and
woodland compensation planting. Moderate
adverse impacts would still remain in the construction stages post mitigation,
however given the small areas affected planting measures would quickly address
the impact reducing it to insignificant by year 10 of operation.
A number of agricultural landscape resources are predicted to
experience moderate adverse impacts prior to mitigation in the construction and
operational stage. These are FLR9.5
Agricultural Land at Sheung Shui Wa Shan, 9.6 Agricultural Land in Wu Nga Lok
Yueng, Siu Hang San Tsuen, Siu Hang Tsuen and Lung Yeuk Tau and 9.7
Agricultural Land in South of Sha Tau Kok Road.
Whilst there is no direct
compensation for the agricultural land lost, direct mitigation includes the possible
preservation and protection of any trees in such LRs and where unavoidably affected, transplantation and
compensatory planting will assist in reducing the level of impact very
slightly. The LVNP is a key component of
the Project with preservation
and even enhancement of agricultural land which is intended to help alleviate
impacts on agricultural land losses across the whole NDA. In addition, this
broad agricultural land category (LR9) encompasses both active and abandoned
agricultural land including orchard areas.
According to a further review and site inspection in December
2012/January 2013 by PlanD with assistance from AFCD, the amount of active
agricultural land affected by the Project in FLN NDA is approximately 24
ha. According to the AFCD Annual Report 2011-2012, currently, there are 4,071 ha of abandoned agricultural land in Hong Kong and 734 ha of active agricultural
farmland and as such, the affected agricultural land represents a small
percentage of active agriculture land in Hong Kong. In the surrounding areas of the Project, 160
ha of land have been found potentially suitable for agricultural
rehabilitation/re-site in the above
mentioned site inspection. The major cluster (34 ha) is
found at Kwu Tung South. Given all these
considerations, the significance of impact on agricultural land in these areas
will remain the same at construction and operation day 1, but by year 10 will
have dropped to slight.
Moderate adverse impacts in construction and operation prior to mitigation are predicted in relation to FLR 7.3 Hung Kiu San Tsuen Lowland Woodland, FLR 7.7 Lowland Woodland near Tai Tau Leng. These impacts are relate to the loss of lowland woodland resources along the alignments of the proposed Fanling Bypass and Po Shek Wu Interchange. The level of impact is considered to reduce to slight by day 1 and insignificant by year 10 as landscape planting works would provide some compensation and through woodland compensation.
Moderate adverse impacts during construction prior to mitigation are predicted in relation to FLR12.12 Rural Development Area in Long Valley, Yin Kong and Hak Ka Wai and FLR 14.3 Fanling Highway. Given the previously developed nature of 12.12 and existing highway function of 14.3, the proposed works are considered to have fair/good compatibility. The initial impacts would be generated due to the large scale of the construction works. In operation it is considered that the impacts would drop to insignificant levels due to the good compatibility of the DPs with the recieving landscape. In terms of mitigation works, minimisation of topographical change, tree transplanting and compensatory planting is predicted to reduce the moderate adverse impact at the construction stage to slight in relation to the both LRs and insignificant by operation day 1.
Slight adverse impacts prior to mitigation are predicted in relation to FLR 1.1 Ng Tung River (Fanling District), 8.3 Shrubland/Grassland Mosaic at Cham Shan and Wa Shan, 9.2 Fu Tei Au Agricultural Land, 11.2 Sheung Shui Urban Area, 11.3 Fanling Urban Area, 12.5 Wa Shan Rural Development Area, 12.6 Lung Yeuk Tau Rural Development Area, 12.7 Rural Development Area at Wo Hop Shek and Lung Shan, 12.8 Rural Development at Ma Shi Po, 12.13 Rural Development Area North of Hong Kong Golf Club, 13.1 Sheung Shui Industrial/Open Storage Area 13.2 Fanling Industrial Area and 14.2 Sha Tau Kok Road (Lung Yeuk Tau). These impacts principally relate to loss of associated tree cover, large scale construction footprint and in the case of FLR 1.1 and 14.2 excavation works associated with the construction of the Fanling Bypass. It is considered that these impacts can be reduced to slight or insignificant levels at the construction stage through tree protection, transplantation, compensatory planting mitigation measures combined with minimising topographical changes. By year 10 all impacts would be insignficant.
It is considered that all the remaining adverse impacts on LRs could be mitigated to insignificant levels at the construction and operational stage through mitigation works, as these remaining resources fall either within industrial or open storage areas where the works would have a good compatibility with the receiving landscape.
The Lowland Agricultural Landscape (FLCA5) affected by the Schedule 2 DPs is predicted to experience slight adverse impacts, prior to mitigation, in the construction and operational stage. Careful planning of the revised RODP means about 58 ha are designated to remain as agricultural land in KTN and FLN NDAs but in these areas referenced agricultural land will be lost. There is no direct compensation measure for the agricultural land lost but some mitigation can be achieved preservation and protection of any trees and where unavoidably affected, transplantation and compensatory planting will assist in reducing the level of impact very slightly. The LVNP is a key component of the Project with preservation and even enhancement of agricultural land which is intended to help alleviate impacts on agricultural land losses across the whole NDA. In the surrounding areas of the Project, 160 ha of land has been found potentially suitable for agricultural rehabilitation/re-site by PlanD with assistance from AFCD. The major cluster (34 ha) is found at Kwu Tung South. By year 10 of operation it is considered the residual impact would remain at a slight adverse level.
Moderate adverse impacts are predicted prior to mitigation works in relation to FLCA1 Natural Hillside Landscape, FLCA2 Rural and Urban Peripheral Village Landscape and FLCA7 Major Water Course Corridor Landscape as a result of the road construction projects. In terms of LCA1, this relates to the high sensitivity of the LCA. The overall area affected in this case is limited and it is considered compensatory woodland planting would quickly reduce this impact to an insignificant level. In terms of FLCA2 and FLCA7, the impacts are mainly generated due to the overall scale of the construction footprint and associated medium sensitivity. In both cases these character areas have undergone development in the past and have capacity to accept a certain level of development. Through mitigation works, in particularly compensatory woodland planting, watercourse mitigation and minimising the need to alter topography, it is considered these impacts can be reduced to insignificant by year 10 of operation.
Slight adverse impacts are predicted in relation to FLCA 3 Urban Development Landscape, FLCA 4 Industrial Landscape and FLCA 6 Major Transportation Corridor Landscape at the construction stage prior to mitigation. The proposed works are considered to have a good compatiblity with these LCAs, therefore would assimilate very quickly during operation. In all cases any adverse impacts can be mitigated to slight or insignificant levels by operation day 1. All impacts would be insignificant by operation year 10 through implementation of tree protection measures, tree transplantation and compensation planting.
12D.10.1 Conclusion
As a result of mitigation measures it is considered that all adverse impacts can be reduced to slight or insignificant levels at the operation stage for the majority of LRs and LCAs in relation to all DP Package D projects.
Mitigation works in relation to these DPs during the construction stage rely heavily on the minimisation of the footprint of the works area, avoidance of significant topographical changes together with retention and protection of existing trees / vegetation. These measures if deployed have the capacity to reduce, in most cases, the level of residual impact experienced by the LRs and LCAs at the construction stage.
It is not possible to fully mitigate all impacts in relation to loss of mature woodland, agriculture and wetland/marsh for all LRs and LCAs in the construction period and early operational stages, mainly as long periods of time are required to sufficiently compensate for this type of impact or sufficient/ suitable space allocated to provide compensation. Woodland compensation measures in combination with transplantation of existing trees (which can help to accelerate the establishment period) applied to the woodland LRs affected will reduce impact levels to slight or insignificant by year 10 of operation when planting has reached maturity.
In
terms of agricultural land and wetland/marsh, the LVNP is a key component of
the Project with preservation and even enhancement of these LRs which is
intended to help alleviate the overall losses across the whole NDA.
Taking into account the above points it is considered that DP 8, 9, 10 and 12 would be broadly acceptable in terms of landscape impacts subject to the full implementation of recommended landscape mitigation measures.
Visual impacts have been assessed for the construction and operational phases of the Schedule 2 DPs with the methodology and processes as set out in Section 12.19.
12D.11.1
Visual
Baseline Conditions
The FLN NDA site boundary occupies around 164 ha and is bound by Fu Tei Au Road to the north, the hill range of Cheung Po Tau, Cham Shan, Wa Shan and Ma Tau Leng to the north-east, Ma Wat River to the east, Sha Tau Kok Road and Ma Sik Road to the south, and Tin Ping Road, Jockey Club Road and Po Wan Road to the south-west with a very small section of the MTRC East Rail line binding it to the west.
Ng Tung River is a major visual component of the area, which flows along the base of the hill ranges to the north of Fanling and Sheung Shui. The area is generally of medium landscape value with high value upland areas of Cham Shan and Wa Shan defining one side of the river valley as a green backdrop into which San Wai/Tai Ling Firing Range integrates well. The urban areas of Fanling/ Sheung Shui, with a number of high rise structures and new developments as well as industries such as vehicle repair and material storage, define the other side of the river. The low-lying river flood plains in between are predominantly of a rural nature, with small scale agricultural plots (both active and abandoned) and some scattered residential settlements and isolated buildings and some open storage, which contrasts with the more natural character of the area. Sheung Shui Slaughter House and Shek Wu Hui Sewage Treatment Works are also located in the western area of this NDA, and Sheung Shui Water Treatment Works is located immediately to the north. At the north of Fanling/ Sheung Shui New Town, a number of traditional villages are concentrated, including Sheung Shui Heung, Sheung Shui Wa Shan, Siu Hang Tsuen, Siu Hang San Tsuen and Kan Lung Tsuen, San Wai also lie to the north of the river and are set against the hillside backdrop.
DP 8 – Po Shek Wu Interchange Improvement
This DP, which forms part of the Po Shek Wu Road, is outside the FLN NDA site boundary. It is located to the south of the Sheung Shui urban area linking the Fanling Highway to the Shek Wu Hui district. Po Shek Wu Road passes between the village area of Tai Tau Leng and highrise residential towers of the Choi Yuen Estate, bridging over the MTRC East Rail Line adjacent to the industrial area on San Wan Road, finally linking to the main Sheung Shui urban area. As this in an existing road, development has already established along its alignment; mature street tree planting and plantations in addition to the surrounding buildings generally provides strong visual enclosure to the site. Whilst existing mature tree planting on either side of the road provides important visual amentity, this is an extremely busy 4-lane road (southern section increases to 5 lanes) with large junctions which generates a relatively low quality visual environment. Visibility to the wider landscape is generally restricted to glimpse views of the surrounding mountains however, as the road passes over the MTRC Rail line this open landscape corridor allows unrestricted views to the south east through the Sheung Shui urban area.
To cater for the traffic flow from the FLN NDA, improvement work, including realignment of the Po Shek Wu Road and the construction of an elevated southbound right-turning slip road to bypass the interchange, is proposed. In this case the proposed slip road will be elevated above the existing Po Shek Wu Road, at a level of +20mPD (i.e. road infrastructure has been stacked to reduce the overall footprint and accommodate the improvement works within the existing constraints). A fully enclosed noise barrier, approximately 6m high, will be constructed from the Fanling Highway over a 120m length. At this point the barrier changes to a semi-enclosed type which runs for 320m, splitting in two over the junction with Choi Yuen Road. The full and semi-enclosed barriers generally appears the same, the latter incorporates openings on the side panels. To accommodate the new slip road, the existing bridge crossing the MTR East Rail line will be widened.
The proposed general layout and extent of noise barriers
works is presented on Figure 12.52.74. Sections demonstrating the elevated slip road
and elevations are provided on Figure 12.52.81 and 82.
DP 9– Fanling Bypass Western Section
This DP interfaces with the northern extent of the FLN NDA boundary along its entire route; this also aligns with the curved route of Ng Tung River. Locally the landscape is low lying, comprising of a series of village areas, some open storage areas and small agricultural plots. Development is set back from the river edge. Tree planting along the river banks helps to conceal the low scale developed areas beyond whereas the open river corridor provides long distance views to the mountain landscape to the north. Open storage land uses in the vicinity are a strong visual detractor in the landscape, in particularly associated with storage of containers along Man Kam To Road.
A roundabout formed on Man Kam To Road on the northside of Ng Tung River is the western most extent of the DP; a pedestrian footbridge crosses the roundabout connecting footpaths to the north, east and west of the roundabout. From this point the bypass heads east and will comprise of two lanes (total 7.5m width) running broadly parallel (not adjacent) to Ng Tung River. The first 200m (approx.) will include a 5m high vertical noise barrier on the north side of the road forming a boundary with Hung Kiu San Tsuen. A 40m section of 3m high barrier is positioned to the east of the roundabout on the boundary of A1-11, a second 45m long section is located on the south side (riverside) of the bypass commencing 50m along the carriageway after the junction with the roundabout. Running parallel with the 3m high noise barrier on the south side of the road, a shorter 3m high section will run for approximately 50m, just after the roundabout.
A further 5m section of noise barrier will run for 130m to the west of Wa Shan together with an 80m section of cantilevered barrier (5m high plus 3m inclined) prior to the proposed roundabout junction with the eastern section of the bypass.
The majority of the proposed road alignment is set away from the main Sheung Shui urban areas to the south however; prior to the junction with DP 10 the alignment comes close the residential areas of Tin Ping Shan Tsuen and Shek Wu San Tsuen.
The proposed general layout and extent of noise barriers works is presented on Figure 12.52.72.
DP 10 – Fanling Bypass Eastern Section
This DP also interfaces with the northern extent of the FLN
NDA boundary. At the junction beween the
western and eastern section of the bypass a roundabout will be formed approximately 80m in
diameter. From this roundabout the
by-pass then forms a dual carriageway with central reservation approximately
20m wide constructed on a viaduct. The northern side of the road
will have a 3m high noise barrier running for approximately 330m.
Prior to Ng Tung River joining with Ma Wat River, a bridge crossing carries the road alignment south. Half-way across the bridge a 5m high noise barrier will be erected on the northbound parapet and will run for around 120m before changing to a 5m high with 3m inclined canopy noise barrier which will run for around 200m. The road is at grade within this section.
The proposed road follows the alignment of Ng Tung River for a short section, locally this landscape appears much less developed and rural in nature with scattered dwellings and more extensive agricultural plots. Beyond the river corridor where more open views of the wider mountain landscape are experienced; the agricultural areas are low lying and well wooded which encloses potential views. The proposed road crosses Ng Tung River to the west of Kan Lung Tsuen and heads south towards the Sheung Shui industrial area, broadly following the alignment of Ma Wat River. The river is lined with well established woodland areas containing mature tree planting which helps to break up the appearance and extent of village areas to the east of the river.
As the bypass reaches the intersection with Sha Tau Kok road it will be in cutting and pass beneath the existing road. An at-grade roundabout will be formed above the intersection of the two roads connecting them with slip roads. Above the roadabout a pedestrian footbridge links footpaths on either side of the road.
Proceeding south the bypass comes out of cutting and crosses the present alignment of the Ma Wat River. A section of the existing channelised river channel approximately 600m long will be realigned by 100m to the east towards Wing Ning Tsuen and Ma Wat Wai. A 50m section of 5m high noise barrier runs parallel to a 70m section of 5m high with 3m cantilever barrier on this part of the bypass.
The alignment of the bypass remains on viaduct as it heads south following the outer edges of the Fanling industrial area and crossing the river channel at three more points. A 45m section of 4m high noise barrier will be located on the eastern side of the carriageway as it passes Shung Him Tong. To the east of the bypass local villages areas appear within a lush green landscape with undulating topography and mature landscape planting, the industrial area is dominated by generally 6-storey factory buildings, access roads and car parks.
At the southern extent of the Fanling industrial area, the alignment of the bypass will require the demolition of a single factory unit located off Yip Wo Street. From this point the highway continues south and splits into two viaducts to the west of Cyber Domain and then crosses the MTR East Rail Line corridor and Ma Wat River Channel. These viaducts connect the bypass to the northbound and southbound Fanling Highway. A series of 5m high and 5m plus 3m cantilever noise barriers are postioned within the Fanling Highway corridor and along Tai Wo Service Road West. In addition a 66m section of 5m high noise barrier is located on Wo Hing Road to the north of Wo Hop Shek San Tsuen. The landscape in this area opens up considerably into the valley formed by Kei Lak Tsai Mountain and Lung Shan Mountain.
As the southbound section of the bypass joins the Fanling Highway to the west of Yuen Leng a series of 5m high, 5m high with 3m cantilever and 4m high noise barriers run along the eastern side of the Higway. A 7m high noise barrier runs for 200m alongside the slip road of the bypass.
The level ground at the bottom of the valley has been widely developed, most extensively by the Fanling Highway, MTRC East Rail corridor and engineering works to channelise Ma Wat River. Whilst dramatic and highly scenic views are available to the surrounding landscape, many short distance views are of disturbed and developed landscape. Tree planting along the alignment of the Fanling Highway is well established and almost screens the entirety of this major infrastructure corridor.
The proposed general layout and extent of noise barriers works is presented on Figure 12.52.73 & 75. Sections demonstrating the construction of the viaducts and vertical alignment are provided on Figure 12.52.84, 85 & 86.
DP12 – Reprovision of temporary wholesale market in FLN NDA.
The DP involves the reorientation of the existing temporary wholesale market as a result the works to construct DP10 which passes through the existing site. The alignment of Ma Wat River channel forms the boundary to the eastern side with the remaining boundary formed by the Sheung Shui industrial area. The existing market comprises a large expanse of hard standing accessed of On Kui Street. There are no permanent structures or buildings within the site which is entirely level. The majority of the boundary contain planting although the quality and extent is lower along the interface with the industrial area.
The villages of Ma Wat Tsuen and Wing Ning Wai sit just beyond the site boundary across the river channel at a slightly lower ground elevation. Visual connection between these areas is generally restricted to the frontages of the village and where gaps have formed in the existing tree planting on the site boundary. To the west of the site, beyond the industrial area, the high rise residential towers of the Belair Monte and Grand Regentville developments peer into the site. There is a strong visual connection to the mountain backdrop of Kat Tsai Shan Au from within the site.
The precise details of the development at this stage are not confirmed however the facilities would include temporary style stalls (i.e. moveable) of approximate 2-3m height. The number of stalls would vary depending on seller requirements; this cannot be ascertained at this time. The majority of the facility is the creation of flexible open space/hardstanding to accommodate these facilities. Perimeter security fencing approx. 2.5m high to replace the existing would be provided together with an access booth for security personnel.
The proposed
general layout and extent of noise barriers works is presented on Figure
12.52.73.
12D.11.2
Visual
envelope
The visual envelope (VE) for these DPs is generally shared with that of the FLN NDA project although this area has been extended to incoporate the Po Shek Wu Interchange improvments and the southern section of the Fanling Bypass eastern section. Generally the viewshed is confined to the north and east by the ridgeline formed by the summits of Cheung Po Tau, Cham Shan, Wa Shan and reaching across to the more distant and easterly Tsung Shan and Mau Tau Leng summits. To the south east the foothills of Lung Shan contain the view while to the southern and western side the VE is contained by the high-rise development of Fanling / Sheung Shui.
Table 12D.12.1 below details the VSRs/VPs in relation to the DPs and describes their overall sensitivity. This information is also presented on the following figures:
Figures 12.53.2 VP locations
Figures 12.54.1 to 26 provide representative photographic records from location within each VSR, looking towards the relevant NDA and the DPs. Since special access could not be gained for all VSRs, especially for private residential developments, the representative viewing locations may have been adjusted if necessary. The selected viewing point is considered the best alternative that represents the typical view of the VSRs.
Figures 12.55.8a to 12.55.19b provide respresentative photomontages showing the predicted view from selected
viewpoints depicting existing conditions, Day 1 of Operation Phase without
Mitigation Measures, Day 1 of Operation Phase with Mitigation Measures and Year
10 of Operation Phase with Mitigation Measures.
Table
12D.12.1 – VSRs and their sensitivity (DP 8, 9, 10 and 12)
VSR Code |
Name |
Category of
VSR (Strategic/ District/ Local) |
Type of VSR |
Approximate
Closest Viewing Distance (m) to Proposed Schedule 2 DP |
Number of
Individuals (Very Many / Many / Few / Very Few) |
Quality of
Existing View (Good / Fair / Poor) |
Availability
of Alternative Views (Yes / No) |
Degree of
Visibility (Full / Partial / Glimpse) |
Duration of
view (Long, Medium, Short) |
Frequency
of View (Very Frequent / Frequent / Occasional / Rare) |
Sensitivity
(Low, Medium, High) |
|||||
Description of Existing View |
||||||||||||||||
FVP1 |
Po Shek Wu Road adjacent Tai Tau Leng |
Local |
Pedestrian, Residential Travelling. |
0 |
Very Many |
Poor |
Yes |
Full |
Short |
Very Frequent |
Medium |
|||||
Ground level roadside view experienced by
pedestrians and motorists using Po Shek Wu Road. Residential views from adjacent village area are
restricted due to intervening planting; some glimpsed views are possible through
screen vegetation. The road infrastructure dominates the foreground
with longer distance views comprising high rise residential towers. Mature tree planting provides valuable visual
amenity and screens low level views to/from adjacent high rise residential
estates. High-rise residential tower blocks together with the
large expanse of road reinforce the urban identity of this view. |
||||||||||||||||
FVP2 |
Residential tower, Choi Po Court, Choi Ying House |
District |
Residential |
100 |
Very Many |
Good |
Yes |
Full |
Long |
Very Frequent |
High |
|||||
Elevated view from residential tower block provides
a panorama view across the western Sheung Shui area. The combination of the large scale buildings in the Sheung
Shui industrial zone, MTR East Rail corridor, villages and comprehensive
development areas form a strong urban character. The canopies of mature trees throughout the zone
help to break up the appearance of built form and provide a green link to the
dramatic mountain scenery in the background. |
||||||||||||||||
FVP3 |
Pedestrian footbridge, San Wan Road |
Local |
Pedestrian, travelling |
180 |
Many |
Poor |
Yes |
Partial |
Short |
Frequent |
Low |
|||||
View from pedestrian bridge crossing and looking
back along the MTR East Rail Line corridor towards the Sheung Shui urban
area. High rise residential and commercial development
within Sheung Shui limits long distance views. Open air car parking, the MTR rail corridor and industrial
functions are detractors in the view. The canopy of mature trees forming boundary planting
around the car park and the embankments of the elevated Po Shek Wu Road
assist in breaking up the appearance of built form. |
||||||||||||||||
FVP6b |
Highpoint above Fu Tei Au Tsuen, facing east. |
District |
Recreational |
400 |
Few |
Good |
Yes |
Full |
Short |
Occasional |
Medium |
|||||
View from high point above Fu Tei Au Tsuen facing east
towards Sheung Shui and Fanling provides a panorama view across the local landscape incorporating numerous villages and
agricultural land. The channelized Ng Tung River is a dominant feature in the view as
it winds through the level terrain in the middle ground. The development pattern and scale of the village
areas creates a strong contrast with the high-rise urban areas. The open storage area located between Fung Kai
Secondary School and Man Kam To Road is a significant visual detractor within
the view. Stacked container boxes throughout this area are highly visible. |
||||||||||||||||
FVP8 |
Access road adjacent Ng Tung River, west of Wa Shan |
Local |
Recreational |
50 |
Many |
Fair |
Yes |
Partial |
Short |
Frequent |
Medium |
|||||
Typical view from access path running parallel to Ng Tung River to the
west of Wa Shan Tsuen. The river corridor allows open uninterrupted views through the local
area towards high rise residential tower such as Belair Monte and the
mountains in the background. Mature tree cover along the boundary of the path (on both sides of the
river) screens the appearance of the smaller scale village type developments
and surrounding agricultural land, only the high rise built form within the
Sheung Shui / Fanling urban areas is visible. |
||||||||||||||||
FVP9 |
Access track, Sheung Shui Wa Shan |
Local |
Residential Occupational |
125 |
Few |
Fair |
Yes |
Glimpse |
Long |
Frequent |
Medium |
|||||
Typical view experienced from within the Sheung Shui
Wa Shan area. The gently sloping terrain and intervening mature
vegetation cover forms a comprehensive screen between the village area and Ng
Tung River and subsequent urban area of Sheung Shui making outward views
difficult. Glimpsed views of mountains and ridgelines within
Lam Tsuen Country Park can be seen above the tree line. Land uses within this area are varied; parking, hard
standing and smaller commercial units detract from the overall visual
quality. |
||||||||||||||||
FVP10 |
Access road, south of Sheung Shui Wa Shan. |
Local |
Travelling |
65 |
Few |
Fair |
Yes |
Full |
Short |
Frequent |
Low |
|||||
Typical view from access road to the south of Sheung
Shui Wa Shan, the land use changes to several small agricultural plots which
form a border with Ng Tung River access road.
The openness of the river corridor allows clear
views across to Sheung Shui urban area and the mountain backdrop. The mature tree planting along Ng Tung river helps to screen views towards the river channel;
glimpsed views of the engineered river banks and access paths/ramps can be
seen below the tree canopies. |
||||||||||||||||
FVP13 (F20) |
High Rise Residential buildings around Tin Ping Estate |
District |
Residential - High Rise |
390 |
Very Many |
Good |
No |
Full |
Long |
Very Frequent |
High |
|||||
Typical view experienced by residents on the upper
floors of the Ting Pin Estate; similar views would be experienced by
residents of neighboring developments such as Woodland Crest. For those flats in this area facing north east, at
high levels the view is generally open and panoramic. Some blocks will have their views north
east partially blocked by the towers of Noble Hill and high rise developments
are evident in the foreground to middle distance. Ng Tung River is a dominant visual component which
runs through the center of the view along the level valley floor surrounded
by a rural landscape of agricultural fields, small villages and extensive
woodland. There is a strong visual contrast between the high
rise residential towers in the view and the low scale village type
development scattered through the valley floor. The back drop to the view is formed by numerous
mountains including Tsung Shan and Lung Shan. |
||||||||||||||||
FVP14 |
Footbridge north of Wu Nga Lok Yeung |
Local |
Pedestrian, Recreational |
90 |
Few |
Fair |
Yes |
Partial |
Short |
Occasional |
Medium |
|||||
Typical view experienced by pedestrians using local
footpaths along Ng Tung River leading to the Chan Shan and Ting Ping Shan
areas from the southern side of Ng Tung River, close to Wu Nga Lok
Yeung. A small wooded hill in the middle ground creates a
strong focal point which is strengthened by the surrounding mature and
semi-natural vegetation cover. Village type development and agricultural plots on
the opposing bank of the river is well concealed. Glimpse views to mountain peaks and ridgelines can
be seen above the tree canopy. |
||||||||||||||||
FVP15 (F4) |
Siu Hang San Tsuen |
Local |
Residential - Low Rise |
200 |
Few |
Good |
No |
Partial |
Long |
Very Frequent |
High |
|||||
Typical view from southern extent of the village of
Siu Hang San Tsuen. As a result of local topography and vegetation
cover, views from this point are very open.
Ground level views are across agricultural fields on
the opposing side of the Ng Tung River. The high-rise buildings of the Sheung Shui / Fanling
urban area are clearly visible in the middle distance serving as a backdrop
to this rural area. |
||||||||||||||||
FVP16 (F11) |
Belair Monte & Regentville |
District |
Residential - High Rise |
70 |
Very Many |
Good |
No |
Full |
Long |
Very Frequent |
High |
|||||
Typical view from high rise residential tower; there
are a number of high rise residential buildings in this vicinity including Belair Monte and Regentville with similar
views. Views at ground level are blocked by buildings and
existing vegetation whereas apartments at elevated levels and facing north
will have direct views towards the DP and wider landscape setting. The current
view north is very rural and green in nature, with agricultural land
interspersed with houses and small village areas and parts of Ng Tung River
channel also visible In the background the green Tsung Shan and Wa Shan
hills are evident with wooded lower slopes leading to shrub land near the
summits. High rise buildings in Shenzhen are also visible in
the far distance. |
||||||||||||||||
FVP17 |
Bridge over Ma Wat River, Sha Tau Road. |
Local |
Travelling, |
100 |
Many |
Fair |
Yes |
Partial |
Short |
Frequent |
Medium |
|||||
Typical view on approaching the Fanling urban area
from Sha Tau Kok Road. Mature tree and amenity shrub planting helps to
reduce the appearance of built form and create a formal / municipal style
landscape character. High rise developments such as Grand Regentville
appear above the tree line. Long distance views area limited by tree cover and
intervening built form. |
||||||||||||||||
FVP18 |
Road Junction west of Ning Wai & Wing Ning Tsuen |
Local |
Residential, Pedestrian |
30 |
Many |
Fair |
Yes |
Partial |
Long |
Frequent |
High |
|||||
Typical view from properties fronting the villages of Ning Wai and
Wing Ning Tsuen which look directly over Ng Tung River towards the existing
wholesale market site. As a result of breaks in vegetation cover and neighboring land uses
the view is relatively open. A clear view towards Grand Regentville and Belair Monte residential
developments is possible. Temporary cabins, market stalls and canopies can be seen within the
market site. Long distance views are generally limited by the local woodland cover. |
||||||||||||||||
FVP19 (F9) |
Agricultural plots, Ma Wat Wai. |
Local |
Recreational |
600 |
Few |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
|||||
Views along the Heritage trail change along the route but generally to
the west, in the direction of the DPs, they extend over a rural landscape of
agricultural fields to Ma Wat River Channel in the foreground with Lung Shan
mountain range visible to the south east.
Looking north, the natural uplands of Wa Shan and Tsung Shan are in
the background. The trail is predominantly along low lying ground and at certain
points the large medium-rise commercial/ industrial area near On Lok Tsuen is
visible, as is Sha Tau Kok Road, but these are often blocked by vegetation
and other village structures. The high-rise buildings of Sheung Shui / Fanling urban area are also
visible in the background at certain points along the route. In general views along this trail are mixed being largely rustic at
close range and taking in ancient buildings, but with elements of urban
development clearly evident in the middle to far distance. |
||||||||||||||||
FVP20 (F8) |
Access road, Shung Him Tong |
Local |
Residential - Low Rise |
475 |
Very Few |
Fair |
No |
Glimpse |
Long |
Frequent |
Medium |
|||||
Views from Shung Him Tong north west extend over Ma
Wat River Channel to the medium rise commercial / industrial area at On Lok
Tsuen. The view is partially screened
by existing vegetation in the foreground.
High rise residential buildings such as Grand
Regentville are clearly visible above the vegetation. To the north, the uplands of Wa Shan and Tsung Shan
can be seen. |
||||||||||||||||
FVP21 |
Highpoint within On Lok Tsuen |
Local |
Residential |
50 |
Few |
Fair |
No |
Partial |
Long |
Frequent |
High |
|||||
In general, views out of this area are limited to
highpoints or upper floors of buildings as low level views are screened by
dense and mature woodland which covers a large proportion of this lowland
hillside area. The views out generally comprise a wall of urban
development formed by the Fanling Industrial zone and high rise residential
development which appears above the industrial roof line. The dense and mature vegetation in the foreground of
the view creates a robust buffer between this land and adjacent urban uses,
also creating a strong visual contrast between natural landscape and large
scale urban form. |
||||||||||||||||
FVP22 |
Bus stop, Cyber Domaine residential estate |
Local |
Residential, pedestrian, travelling. |
70 |
Many |
Good |
Yes |
Full |
Long |
Frequent |
High |
|||||
Typical view from street level at the front of the
Cyber Domaine residential area. The views from this area are generally open as the
landscape between the estate and the Fanling Highway, in the middle ground,
has relatively little vegetation cover and is predominantly level. Mature tree planting on the embankments along the Fanling Highway almost completely screen the
highway. Residential high-rise development within the Dawning
Views Estate and Avon Park Estate are dominant elements of the view. The ridgeline of Lam Tsuen Country Park from the
backdrop can also be seen. |
||||||||||||||||
FVP23 |
Pedestrian footbridge, Kau Lung Hang San Wai |
District |
Residential, Pedestrian, travelling. |
100 |
Many |
Good |
Yes |
Full |
Long |
Frequent |
High |
|||||
|
Typical view experienced from the south east of
Fanling, looking back up through the Fanling Highway and MTR East rail corridor
from residential village area of Kau Lung Hang San Wai. Dense and mature tree planting on the embankments of
the Fanling Highway almost completely screen this major piece of
infrastructure. The undulating hillside terrain on either side of
this low valley promotes a strong rural feeling. This floor of the valley has undergone significant
visual and physical change as a result of the Fanling Highway development,
MTR East rail line and major channelisation of Ma Wat River. Service roads, drainage channels and randomly
development plots within the middle ground detract from the quality of the
view. |
|||||||||||||||
FVP24 |
Wo Hing Road, Wo Hop Shek Village |
Local |
Residential, Occupational, pedestrian, travelling. |
50 |
Many |
Fair |
Yes |
Partial |
Long |
Frequent |
High |
|||||
This VP demonstrates the view in front of the Wo Hop Shek Village from Wo Hing Road. Dense and mature vegetation in the foreground
creates a robust screen between this area and the Fanling Highway interchange
slip roads and viaducts. Glimpse views over this planting to the mountains
and ridgelines of Lung Shan provide valuable visual amenity. |
||||||||||||||||
FVP25 |
Residential Block, Wah Sum Estate |
District |
Residential |
515 |
Very Many |
Good |
Yes |
Full |
Long |
Very Frequent |
High |
|||||
This VP demonstrates the typical view from
residential towers located at the Wah Sum Estate and its immediate
vicinity. The elevation allows for an unobstructed view through
the valley to the south east of Fanling and along the infrastructure corridor
formed by the MTR East Rail Line and Fanling Highway. The mountainsides of Lung Shan and Kau Lung Hang
Shan dominate the view. Villages and isolated developments occupy a large
percentage of the valley floor. |
||||||||||||||||
Remarks: The approximate
closest viewing distance to the proposed DP is measured from the edge of
the VSR group to the closest building proposed within the DP.
The potential sources of visual impact due to the Project are described in Section 12D.4 and 5. They will create varying levels of visual impact during the construction and operation phases in relation to each DP, due to factors such as obstruction of views, degradation of the quality of existing views and visual incompatibility with the surrounding landscape context. The visual impact assessment will consider each DP individually.
12D.13.1 Magnitude of Visual Change
The magnitude of visual change is largely dependent on a number of factors as outlined in the methodology. In general, the magnitude of change will reduce the further a VSR is from the Project.
Detailed engineering design of built elements the DPs is ongoing at this stage therefore, the structures shown in the photomontages may change as detailed design is refined.
Table 12D.13.1 details the
magnitude of change in relation to DPs 8, 9, 10 and 12.
Table
12D.13.1- Magnitude of visual change for VSRs - DPs 8, 9,
10 and 12
Remarks: The approximate closest viewing distance to the
proposed DP is measured from the edge of the VSR group to the closest built
structure.
VP (Yes
[Y]/ blank) |
VSR Code |
Name |
VSR
Category (Strategic/ District/ Local) |
Key
Designated Projects (DPs)/ Sites with Structures causing Visual Impact (Land
Use Type)* |
Blockage of
View (Full/ Partial/ Nil) |
Approximate
Closest Viewing Distance to Proposed NDA (m) |
Scale of
Development (Large/ Medium/ Small) |
Compatibility
with Surrounding Landscape |
Duration of
Impact |
Reversibility
of Change |
Magnitude
of Change (Large/ Intermediate/ Small/ Negligible) |
||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||||||
Description of Impacts during
Construction and Operation |
|||||||||||||||
|
FVP1 |
Po Shek Wu Road adjacent Tai Tau Leng. |
Local |
DP8 |
Full |
0 |
Large |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
The construction of a fully enclosed acoustic
barrier, approximately 6m high, combined with an elevated viaduct structure
approximately 14m high (to top of enclosure) above will obstruct the entirety
of this view and prevent any medium to long distance views from pedestrian
level. At ground level only small sections of the new
structure will be visible at any one time however for elevated views from
upper storeys of local buildings a more entire view of the whole structure
will be possible. Whilst this development will be within an existing
road corridor, it is considered the height and extent of new above ground
structures will create a considerable change in the view, in particularly
during construction where extensive temporary works will be required
therefore, it is considered that the compatibility during construction would
be poor. The present 4 (in part 5)
lane road is very busy and an existing visual detractor, given this function
and the neighbouring industrial and rail infrastructure landscapes the
compatibility of the DP in operation is considered to be fair. In general, views form this
VSR will experience full blockage by the proposed DP. The scale of
development is considered to be large taking into account the size and height
of the proposed structure. Overall the magnitude of change is predicted to be large during construction as the temporary works are
likely to be extensive. In operation
the magnitude of change is also considered to be large as this significant
new structure will be largely unscreened. |
|||||||||||||
Y |
FVP2 |
Residential tower, Choi Po Court, Choi Ying House. |
Strategic |
DP8 |
Partial |
100 |
Large |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
The construction of a fully enclosed acoustic
barrier, approximately 6m high, combined with an elevated viaduct structure
approximately 14m high (to top of enclosure) above will appear over the
entire section of Po Shek Wu Road leading up to the crossing point of the
MTRC East Rail Corridor where the enclosure terminates and the viaduct drops
down to the deck level of the existing bridge and then crosses over the MTRC
East Rail corridor. The viaduct joins
to the eastern side of the bridge forming an additional two lanes. Elevated views from neighbouring high-rise
developments will experience a more comprehensive view of the height and
extent of these structures together with their roofscape. The widening of the existing bridge of the
rail corridor will also increase the visibility of engineered structures. Beyond the existing bridge the additional road lanes
converge with the existing road alignment however, some tree losses on the
eastern side will be required to form the slip roads. Whilst the DP sits within an existing road corridor,
the proposed above ground structures are very different to the existing type
of road development in form and height and will greatly increase the visual
presence of the road, constituting a large change in the view especially
during construction therefore the compatibility is considered to be poor at
this stage. The existing 4-5 lane road is very busy and an
existing visual detractor, given this function and the context of
neighbouring industrial and major infrastructure landscapes the compatibility
of the DP in operation is considered to be fair,
in addition the enclosures will help block views of traffic. Overall the magnitude of change is predicted to be large during construction and large during operation. |
|||||||||||||
|
FVP3 |
Pedestrian footbridge, San Wan Road |
Local |
DP8 |
Partial |
180 |
Small |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
The construction of a fully enclosed acoustic barrier,
approximately 6m high, combined with an elevated viaduct structure
approximately 14m high (to top of enclosure) above will appear to the right
hand side of the bridge in the centre of the view. The full enclosure of the road terminates
prior to the bridge crossing however; the elevated viaduct above the lower
enclosure will taper down to meet the bridge level at the threshold to the
crossing point. The viaduct joins to
the eastern side of the bridge forming an additional two lanes, this is the
other side of the bridge when viewed from this position. Existing tree planting on either side of the bridge
is likely to screen low level views of new structures as it already provides
a robust screen in relation to the road therefore the full scale of the proposed
DP would not visible from this point. Whilst the DP sits within an existing road corridor
and would be seen in the context of the rail corridor and industrial setting,
the proposed above ground structures are very different to the existing type
of road development in form and height.
It is considered this will greatly increase the visual presence of the
road and bridge crossing, creating a relatively large change in the view
especially during construction therefore the construction stage compatibility
is considered to the poor, reducing to fair in operation. Overall the magnitude of change is predicted to be
large during construction as temporary works are likely to extensive and
intermediate during operation as the majority of the works will be screened
by intervening vegetation. |
|||||||||||||
Y |
FVP6b |
Highpoint above Fu Tei Au Tsuen, facing east. |
District |
DP9 |
Partial |
400 |
Medium |
Poor |
Fair |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
The construction of the Fanling Bypass Western
Section would commence in the middle-ground of this view to the northof the
road bridge crossing Ng Tung River. At
this point a roundabout will be formed to create a junction with the Man Kam
To Road which will require an extensive area of lowland woodland to be felled
which will open up views along the new road corridor. A pedestrian footbridge bridge would be
constructed over the roundabout. Beyond the woodland the road corridor would pass through
an area of open storage with some small woodland areas. The road at this point will comprise two lanes
(total 7.5m width) running broadly parallel (not adjacent) to Ng Tung
River. The first 200m (approx.) will
include a 5m high vertical noise barrier on the north side of the road
forming a boundary with Hung Kiu San Tsuen.
Running parallel with the 3m high noise barrier on the south side (riverside)
of the road, a 3m high section will run for approximately 50m, just after the
roundabout. There are no further noise
barriers visible along this section. As the road continues east, away from this view, it
veers towards Ng Tung River and starts to follow the curve of the channel,
the road would then gradually disappear from view after approximately 600m as
existing woodland cover along the river channel would start to screen the
view. Whilst landscape within the alignment has been
previously disturbed through open storage functions, the road will introduce
a completely new type of development into this zone requiring the removal of
numerous tree groups which during construction would constitute a large
change in the view. In terms of compatibility, the highly engineered
channel of Ng Tung River provides a precedent for large scale engineered
linear forms within the landscape, albeit that the river is not a transport
corridor. It is considered that as the
new road is situated close to this existing feature that this would make the
new road appear less alien within the landscape setting. However, the road in combination with the
river channel would create a wide corridor of engineered linear forms which
would make these features even more conspicuous, especially within the more
natural appearance of the landscape to the north of the river. In this case the compatibility during
construction is considered to be poor given the likely footprint of
construction works; during operation the compatibility would become fair as
the footprint reduces and only short sections of the road can be seen at any
one time, due to the curved alignment. Given the panoramic nature of this view comprising
numerous elements and a large scale backdrop, the scale of the development in
the view is considered to be medium. The magnitude of change is considered to be large during construction
and intermediate in operation. |
|||||||||||||
|
FVP8 |
Access road adjacent Ng Tung River, west of Wa Shan |
Local |
DP9 |
Partial |
50 |
large |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|
|
The Fanling Bypass Western Section runs parallel to the riverside
access road at the east. The road
corridor including the pedestrian footpaths on either side would be around
25m wide at this point. In order to construct the bypass, tree felling will
occur throughout the proposed alignment which will open up direct views to
the road corridor along this route. In
addition a pedestrian footbridge will be constructed over the road which would
appear above the tree line. The road alignment continues parallel to the river channel throughout
this view until it follows the river around the bend and out of view. The existing line of trees which run
directly parallel to the access road provide intermittent screening, in
addition the route is slightly elevated compared to the adjacent ground level
which may increase the visibility into the centre of the road scheme. 200m along the road from this point, on the north side (far side) of
the bypass, there will be a 200m long section of 5m high noise barrier. This barrier would be visible in front of
the small hill in the middle ground of this view. It is likely that partial views of the
upper sections of these barriers would just be visible above the tree
canopies on the access road. Vegetation that would be removed within the proposed road alignment
currently screens the developments beyond.
This function would be compromised resulting in increased visibility
through this area in addition to views of a new road. It is considered that this development
would have a poor compatibility with the existing view during construction
and operation due to the scale of the construction footprint. The visibility of the proposed road would be restricted as a result of
existing tree cover; in addition the curved alignment limits the extent of
the view. In this case the magnitude
of change is considered to be intermediate in both construction and
operational stages. |
|||||||||||||
|
FVP9 |
Access track, Sheung Shui Wa Shan |
Local |
DP9 |
Partial |
125 |
Medium |
Fair |
Fair |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|
|
The Fanling Bypass Western Section would pass this VSR approximately 125m
at the southwest; the road corridor inclusive of pedestrian footpath would be
around 27m wide. The additional width
relates to a new bridge and road junction (not part of the DP) which connects
to the bypass at this point. The typical view at ground level is contained by tree and shrub
planting in the foreground therefore, direct views of the DP are not
considered to be possible; this is the case throughout the immediate
area. Views from upper floors of village
houses are likely to have partial views of the development as this area is
elevated above the proposed road corridor providing the opportunity for more
direct views. The higher the viewing
elevation, the more of the road corridor would be visible. Whilst the road corridor would be generally obscured by intervening
vegetation, a 200m section of 5m high noise barrier located approximately
180m to the south of this point (left hand side of the view) would become
visible from upper floor of local buildings.
It is likely only the upper section of the barriers would be visible. As the majority of the development in this area is low rise and
extensive views over the road corridor are limited by vegetation and
topography, it is considered that the compatibility of this development with
the existing view would be fair in construction and operation. The magnitude of change therefore, is considered to be intermediate
during construction and in operation. |
|||||||||||||
|
FVP10 |
Access road, south of Sheung Shui Wa Shan. |
Local |
DP9 |
Partial |
65 |
Large |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
The Fanling Bypass Western Section would pass directly through the
centre of this view on the near side of the line of trees visible in the
middle ground. The route would run
parallel to the alignment of the riverside path which can be seen beneath the
tree canopy. The bypass would mainly replace agricultural land through this section
with less tree felling required. As the view demonstrates, this area is wide
open with minimal tree cover therefore direct and uninterrupted views of the
development are possible. The road would comprise of two lanes in this location; the road from
which this view is taken would also form a junction with the bypass and
riverside road. The bypass including pedestrian footpaths is approximately
25m wide; the road would also be elevated on embankment at the same height as
the riverside access road. There is no noise barrier proposed within the section so views would
continue over and beyond Ng Tung River. Whilst this area has already been cleared of vegetation for
agricultural uses it still retains a rural character and separation from the
high rise urban in the back ground of the view, in this case it is considered
the compatibility of the development would be poor during construction due to
the scale of the works area. In
operation the compatibility would become fair as the visibility of
construction operation/footprint reduces, the roadscape would also be seen
next to the highly engineered form of Ng Tung River. As views towards the works area are completely unscreened and would
occupy the entirety of the immediate foreground the magnitude of change is
considered to be large both during construction and operation. |
|||||||||||||
Y |
FVP13 (F20) |
High Rise Residential buildings around Tin Ping Estate |
District |
DP9 and DP10 |
Partial |
390 |
Large |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
DP 9 The Fanling Bypass Western Section would appear at the west (from the
left hand side of the view) running parallel to the Ng Tung river from this
elevated location. The road corridor
would be approximately 10m wide at this point. Tree felling would be required along the
alignment in an area containing pockets of mature vegetation and agricultural
land; this would open up views of the developed areas beyond the tree cover. There is no noise barrier or pedestrian bridge proposed on this
section, all construction will be at-grade. Given the varying quality and density of existing planting along the
riverside, intermittent views of the road through the planting is
likely. Whilst there are relatively
large areas of low scale development in this location, the overall picture is
that of a rural and wooded lower hillside therefore, the compatibility of DP
9 at this point is considered to be poor both in construction and operation. DP10 Western section of the bypass joins with DP 10 Fanling Bypass Eastern
Section at a roundabout near the second bridge at the northern bank of the
river. The roundabout is approximately
80m across and will require an extensive area of tree felling, demolition of
existing structures and alterations to existing levels and topography. From this roundabout the by-pass then forms
a dual carriageway with central reservation approximately 20m wide. The northern side of the road will have a
3m high noise barrier running for approximately 330m. Views from this point will be able to look up through the alignment of
the road corridor therefore increasing the overall visibility of the
development. The road alignment will also pass through a well wooded area requiring
extensive tree clearance works. Beyond the second river crossing visible in the centre of the view, Ng
Tung River turns to the south at which point the by-pass crosses the channel
on a new bridge (location marked on existing image for reference), just
before the river joins with Ma Wat River, and then passes through an area of
relatively open ground in front of Kan Lung San Tsuen. The bridge would be a highly visible and
large structure in the view. Half-way across the bridge a 5m high noise barrier will be erected on
the near-side parapet and will run for around 120m before changing to a 5m
high with 3m inclined canopy noise barrier which will run for around
200m. The barrier will be seen
crossing the open ground to the right hand side of the river in this view. Beyond the river crossing the acoustic
barriers will screen views of the bypass however; the barriers would be a
highly visible linear element in the landscape. In the case of both DP9 and DP 10, a large proportion of the works
area would be visible including significant structures such as the bridge
crossing and extensive noise barrier works.
The combined works area will span the entire view and introduce a
series of large scale engineered structures into a relatively low scale and
open landscape setting; as a result it is considered that the compatibility
of the development would be poor in construction and operation. The magnitude of change, therefore, is considered to be large during
construction and large during operation. |
|||||||||||||
|
FVP14 |
Footbridge north of Wu Nga Lok Yeung |
Local |
DP9 and DP10 |
Partial |
90 |
Large |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
DP9 The Fanling Bypass Western section would be visible from the west to east
(to the left hand side of the footbridge) on the opposing riverbank; it would
appear as a 10m wide road corridor running parallel to the river channel set
back by around 20m from the line of existing trees. There are no noise barriers or pedestrian bridges on this section of
DP9. The proposed bypass would be at a
similar ground elevation at this point therefore views of the road surface
are likely to be restricted. The most noticeable change would be that the tree felling required for
the route alignment would open up views deeper into the developed areas
beyond. DP10 Directly across the footbridge on the opposing side of the river, the
western by-pass joins with DP 10 Fanling Bypass Eastern Section at a
roundabout. The roundabout is
approximately 80m across and will require an extensive area of tree felling,
demolition of existing structures and alterations to existing levels and
topography. From this roundabout the
by-pass forms a dual carriageway with central reservation, the approximate
width is 20m. The northern side of the
road will have a 3m high noise barrier running for approximately 330m. Views along this road corridor will be
possible. To the east, further along Ng Tung River, the channel turns to the
south. At this point the eastern by-pass
crosses the channel on a new bridge (location marked on existing image for
reference), just before the river joins with Ma Wat River. The bridge would be a highly visible and large structure appearing
above the existing crossing point which can be seen in the view. Half-way across the bridge a 5m high noise barrier will be erected on
the near-side parapet and will be visible above the channel. The extent of the barrier visible will be
restricted by tree cover as the bridge and bypass continue out of the view to
the right hand side. In the case of both DP9 and DP 10, a large proportion of the works
area would be visible, including significant above ground structures, such as
the bridge crossing and extensive noise barrier works. As a result the overall compatibility
during construction and operation is considered to be poor. The combined works area will span the entire view and introduce a
series of large scale engineered structures into an area which appears
undeveloped and relatively natural therefore, the magnitude of change is
considered to be large during construction and operation. |
|||||||||||||
|
FVP15 (F4) |
Siu Hang San Tsuen |
Local |
DP10 |
Partial |
200 |
Medium |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Intermediate |
Small |
|
|
The alignment of the Fanling Bypass Eastern section would cross
directly through the middle ground of this view. The ground elevation can be seen dropping away
in the foreground; in this case lower level sections of the bypass will not
be visible, in additional a belt of tree planting to the south of the village
provides some screening. Directly in the centre of the view, beyond the first line of existing
trees, the bypass crosses the Ng Tung river at which point the structure of
the bridge would appear above the tree line. Half-way across the bridge a 5m
high noise barrier will be erected on the far-side parapet and will be highly
visible. The barrier will run for around 120m before changing to a 5m high
with 3m inclined canopy noise barrier which runs for a further 200m. Over this distance the barrier and bridge
will slowly taper out of view. Views from the upper storeys of local village houses in Siu Hang San
Tsuen will have a more extensive and entire view of the bypass construction
and the bridge formation. The views from this point are currently very open, over a level
landscape. The new bypass will appear
directly in the centre of the view, partially obstructing the current long
distance vistas. It is therefore
considered that the compatibility of the development in construction and
operational stages would be poor. Given the long viewing distance and screening provided by vegetation
to the south of the village the magnitude of change is considered to be
intermediate during construction. In
operation the bypass will sit low down within the landscape with an urban
backdrop, slowly tapering out of view; as a result the magnitude of change in
operation would be small. |
|||||||||||||
Y |
FVP16 (F11) |
Belair Monte & Regentville |
District |
DP10 |
Partial |
70 |
Medium |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
The Fanling Bypass Eastern section would start at the base of the
small hill on the left hand side of this view, commencing with a roundabout
approximately 80m across. The
alignment of the road would then run horizontally across the centre of the
view following the alignment of the Ng Tung River Channel. The bypass
construction along this entire section is dual carriageway with a central
reservation. The roundabout will require an extensive area of tree felling,
demolition of existing structures and alteration to existing levels and
topography. Tree felling will continue
along the alignment of the road creating an open corridor of about 20m which
would be visible across the landscape.
The construction width of this corridor may require additional felling. The first 330m of the bypass leading from
the roundabout will have a 3m high noise barrier on the far side, the upper
section of the this structure may be visible from this point. Approximately 2/3 of the way across this view, the bypass crosses the
Ng Tung River on a new bridge and the alignment follows the Ma Wat River
Channel which approaches the viewpoint. From this angle the road alignment would be relatively well embedded
into the existing tree/vegetation cover within this rural landscape however,
where the highway bridge the river, the construction will become increasingly
more visible. In addition, a 5m high
noise barrier which runs from the midpoint of the bridge for around 120m
before changing to a 5m high with 3m inclined canopy noise barrier which runs
for a further 200m will be highly visible and add significant bulk to the
structure from this angle. The bypass
will run through the agricultural land on the right hand side of the image,
on a viaduct initially, then returning to at-grade level. The viaduct deck level will be around 6m
above adjacent ground level, the road will then move out of view from this
point. Given the scale and visibility of the bypass in the view and taking
into account the existing strong rural character and openness, the
compatibility of the development in this location is considered to be poor
both in construction and operation. Given the scale and likely high visibility of the highway, bridge and
associated noise barriers the magnitude of change is considered to be large
during construction and operational stages. |
|||||||||||||
Y |
FVP17 |
Bridge over Ma Wat River, Sha Tau Road. |
Local |
DP10 |
Partial |
100 |
Large |
Poor |
Good |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
DP10 The existing wide junction in the foreground will be reconfigured into
a roundabout approximately 75m across and the alignment of the Fanling
Highway Eastern section will pass beneath in cutting. A series of pedestrian walkways crosses the
roundabout connecting to the footpaths on either side of the roundabout. The construction of the above ground
structure would require minor tree clearance to the west of the roundabout
(right hand side of the picture) however this would not open up any
additional views. As a result of existing tree cover and surrounding urban development
the extent of the view is limited, in addition the proposed above ground
structures are generally in keeping with the existing urban setting. The scale of the roundabout is broadly
similar to the existing junction and the bypass will be in cutting therefore
it will not be visible. In this case
it is considered the development would have a good compatibility with the
existing visual setting during operation.
In the construction stage it is considered the compatibility would be
poor due to the likely scale of works required, in particularly the
excavation required to sink the alignment. Given the likely large scale of the temporary works, the magnitude of
change during the construction stage is considered to be large. As a result of the good compatibility of
the development, mainly due to the concealment of the highway, the magnitude
of change in operation is considered to be intermediate. |
|||||||||||||
Y |
FVP18 |
Road Junction west of Ning Wai & Wing Ning Tsuen |
Local |
DP10 and DP 12 |
Partial |
30 |
Large |
Poor |
Good |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
DP 10 The Fanling Bypass Eastern section will be in cutting throughout this
view therefore will not be visible. In
the centre of the view, to the right hand side of the existing residential
towers, a series of pedestrian walkways will be visible associated with the
new roundabout formed at the junction of Sha Tau Kok Road and Ma Sik
Road. The construction of the above
ground structure would require minor tree clearance to the west of the
roundabout (right hand side of the junction) however this would not open up
any additional views towards this area.
It is likely that partial views into the road cutting from the upper
storeys of village houses on the frontage of Wing Ning Tsuen would be
possible due to close proximity. The
overall width of the cutting and slip roads is approximately 40m at this
point. It is considered that the above ground structures in this view are
generally in keeping with the urban setting; in this case it is considered
the development would have a good compatibility with the existing visual
setting during operation. In the
construction stage it is considered the compatibility would be poor due to
the likely scale of construction works required, mainly due to the excavation
required to sink the alignment of the by-pass. DP 12 The alignment of DP 10 requires that the existing Fanling Wholesale
market, which is visible as the area of level ground in the centre of the
view across the river channel, will require re-orientation. The existing site is presently completely
open and surfaced with asphalt; there are also no permanent above ground
structures. Half of the site will be
taken by the bypass construction to the left hand side of the view and be
re-provided to the north in between the current site and Sha Tau Kok
Road. Some minor tree clearance will
be required within the centre of the site however this will not open up any
new views towards this area. Views
from the upper floors of the house on the frontage of Wing Ning Tsuen will be
able to look across the new area of hard standing where the intervening trees
screen is broken. As the reprovision works will affect a relatively large area and will
increase the visibility of hard standing from elevated views, it is
considered the compatibility during construction would be relatively poor. As the market contains no permanent above
ground structures and comprises of just temporary stalls and canopies, in
addition to a large area of hard standing, the compatibility during operation
is considered to be fair. Given the likely large scale of the temporary works for both of these
projects, large scale excavation and the overall extent of the construction
footprint, the magnitude of change during the construction stage is
considered to be large. As a result of
the good compatibility of the development, mainly due to the concealment of
the highway and relocation of the market facilities broadly in the same
location, the magnitude of change in operation is considered to be
intermediate. |
|||||||||||||
|
FVP19 (F9) |
Agricultural plots, Ma Wat Wai. |
Local |
DP10 |
Partial |
90 |
Large |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
The Fanling Bypass Eastern Section will pass through the mid-ground of
this view (approx. 90m) in the place of the various sheds, buildings, trees
and agricultural plots which can be seen across the open agricultural land in
the foreground. The openness of the
agricultural fields will allow a direct view of the bypass which will be on
viaduct at this point. The viaduct
will gradually increase in height from the right to the left of the view as
the road comes out of cutting; the road deck level will be 7.6m above
existing ground level. In addition to
the viaduct structure, two sections of 5m high plus 3m inclined canopy noise
barrier will be constructed on either side of the viaduct which will be
clearly visible from this point. The
longest section of the noise barrier runs for approximately 150m on the far
side of the viaduct, the second section on the nearside runs for 50m and will
be seen in front of the longer section. Given the openness and undeveloped nature of the view in the foreground, the
compatibility of the works in construction would be poor, in operation the road
would be seen with a large scape urban backdrop, as a result the
compatibility would be fair. It is considered, due to the scale of the works, that the
compatibility of the project during construction and operation will be poor. There will be a significant level of visual change in this location,
therefore the magnitude of change is considered to be large during
construction. Post construction the
road will be seen with a large scale urban backdrop, as a result the
magnitude of change would drop to Intermediate. |
|||||||||||||
|
FVP20 (F8) |
Access road, Shung Him Tong |
Local |
DP10 |
Partial |
120 |
Large |
Poor |
Fair |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
DP10 The Fanling Bypass Eastern Section will pass through the mid-ground,
to the left hand side of this view (approx. 120m). The alignment will require the felling of
trees and clearance of land within a 25m corridor. Intervening mature vegetation, in the foreground
of the view, will break up the visibility of new structure from this point,
including views from the upper storeys of village houses in the
vicinity. The bypass will comprise a
viaduct at around 7.6m above existing ground level. In addition to the viaduct structure, two
sections of 5m high plus 3m inclined canopy noise barrier will be constructed
on either side; glimpse views of these structures are likely between retained
vegetation. The viaduct and associated noise barriers are likely to be partially
screened by intervening vegetation and in this case the views from this point
will not be fully obstructed with the bypass appearing more embedded with the
local landscape. The construction works for the bypass are likely to be large in scale
within an undeveloped rural area therefore the compatibility during
construction is considered to be poor.
As the majority of the structure is likely to be screened by
intervening vegetation the compatibility is considered to be fair during
operation, taking into account the further encroachment of urban development
towards this VSR. Due to the anticipated scale of the works the magnitude of change is
considered to be large in the construction stage; as the structure is likely
to be partially screened by existing vegetation the magnitude of change will
reduce to intermediate during operation. |
|||||||||||||
Y |
FVP21 |
Highpoint within On Lok Tsuen |
Local |
DP10 |
Partial |
60 |
Large |
Poor |
Poor |
Temporary [Short] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
The Fanling Bypass will cross the middle ground of this view,
approximately 60m away. The ground
elevates away from the bypass at this point, the viewpoint elevation is
approximately 34mPD whereas the road deck level will be around 11.2mPD
therefore the view will overlook the road structure with potential direct
views into the corridor and of the road surface. The bypass construction will be on viaduct
throughout this section including a 45m length of 5m high noise barrier. Views will partially screened by the tree
canopy immediately in front of this viewpoint. Extensive tree felling and site clearance
works will be required within the construction corridor to form the road
which will be approximate 20m wide at this location. In this case the extent of tree canopy
within the view will be significantly reduced which will further expose the
road corridor. The construction works for the bypass are likely to be large in scale
within an undeveloped rural area therefore the compatibility during
construction is considered to be poor.
The road will encroach further into this well wooded location
obstructing a significant proportion of the view therefore the compatibility
in operation is considered to be poor. Due to the anticipated scale of the works the magnitude of change is
considered to be large in the construction stage; although the bypass will
have some screening it will dominate the immediate view therefore the
magnitude of change during operation is considered to be large. |
|||||||||||||
Y |
FVP22 |
Bus stop, Cyber Domaine residential estate |
Local |
DP10 |
Partial |
70 |
Large |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
DP10 The Fanling Bypass Eastern section will run directly through the
centre of this view, right to left, on a viaduct approximately 70m away. The viaduct is approximately 20m wide; it
then splits into two slip roads which then continue south connecting to the
north and south carriageways of the Fanling Highway. The bypass would run through open ground
therefore would be highly visible; the elevation of the viaduct at road level
would be around 7.6m above the adjacent ground level. There are no noise
structures planned at this location. The viaduct structure will obstruct the entire middle ground of the
view, removing the existing long distance vistas to the woodland cover around
the Fanling Highway. The residential
towers of Dawning Views and hillside beyond would remain above the structure. The construction works for the bypass are likely to be large in scale
within an open and undeveloped rural area therefore the compatibility during
construction and operation is considered to be poor. The structure will be highly visible and occupy a large proportion of
the existing view therefore the magnitude of change is considered to be large
during construction and large in operation. |
|||||||||||||
Y |
FVP23 |
Pedestrian footbridge, Kau Lung Hang San Wai |
District |
DP10 |
Partial |
100 |
Large |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Large |
|
|
DP10 At this point the Fanling Bypass Eastern Section forms a slip road connecting
to the south bound carriageway of the Fanling Highway. The road would be on a viaduct at this
point gradually tapering down to the level of the existing highway. The bypass slip lane is approximately 6.5m
wide in this location. The bypass runs
down the centre of the valley on the far side of the Ma Wat River and joins
the highway to the left hand side of the view. Clearance of well-established woodland plantation associated with the
Fanling Highway would be required, whilst this would not open up new views,
it would reduce the overall appearance of woodland within this zone. The open view down through the valley would allow unobstructed views
of a large proportion of the construction works for the bypass therefore the
compatibility with the existing view is considered to be poor. Whilst the
landscape within the valley floor has been highly disturbed as a result of
the MTRC East Rail Line corridor, channelisation of the Ma Wat River and
alignment of the Fanling Highway, the new bypass would be elevated and highly
visible and introduce a large scale structure into a relatively open
landscape, in this respect the compatibility of the project during operation
is considered to be poor. The scale and extent of the bypass will be
significant and highly visible, introducing a large new structure within a
relatively open landscape therefore, the magnitude of change during
construction and operation is considered to be large. |
|||||||||||||
Y |
FVP24 |
Wo Hing Road, Wo Hop Shek Village |
Local |
DP10 |
Partial |
50 |
Medium |
Poor |
Poor |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Intermediate |
Intermediate |
|
|
The construction of the Fanling Bypass Eastern Section slip road connecting
to the Fanling Bypass would be partially visible through the line of mature
trees on the opposing side of the road.
The slip road would be constructed on a viaduct elevated above the
existing highway; the road would be approximately 10m wide. Tree clearance would be required on this
section however this would occur on the other side of the Fanling Highway and
would not affect views at this point.
The existing mature trees and landform in the foreground would screen
the majority of views of new structures. A section of 5m high noise barrier will run for 30m in front of Wo Hop
Shek Village at ground level, this commences at the back of the pavement on
the right hand side of the view and runs back along Wo Hing Road. Some tree
clearance may be required to construct this section of barrier. An 80m long section of 5m high plus 3m
inclined barrier will sit within the highway corridor and would not be
visible from this point. Existing mature trees within the vicinity provide robust screening of
the road corridor and will conceal the majority of view of the bypass during
construction and operation. The
proposed 30m noise barrier would be the most significant in views from this
area. Taking into account that there
are no similar structures to the barrier in the immediate vicinity, potential
loss of existing trees and the overall height of 5m metres, it is considered
that the compatibility would be poor during construction and operation. The noise barrier would be a highly visible new element within this
environment as there would be no immediate screening available in addition to
the potential loss of trees required to construct the barrier, in this case
the magnitude of change in construction and operation is considered to be
intermediate. |
|||||||||||||
Y |
FVP25 |
Residential Block, Wah Sum Estate |
District |
DP10 |
Partial |
515 |
Large |
Poor |
Fair |
Temporary [Medium] |
Permanent |
Reversible |
Irreversible |
Large |
Intermediate |
|
|
The construction of the two slip road tails of the Fanling Bypass
Eastern section would appear to the rear of the residential tower on the left
hand side of the view, approximately 515m from this point. The slip road forms a fork which joins to
the north and south carriageways of the existing highway. The south bound connecting slip road
(furthest from view) would be predominantly screened by existing mature
vegetation along the Fanling Highway corridor, a short section would be
visible where the bypass viaduct would cross the MTRC East Rail Line and Ma
Wat River channel before being concealed. The northbound connecting slip road (nearside of the view) would be
visible for a greater distance as it crosses the highway corridor obliquely
before turning and running parallel to the highway prior to joining it. Both
slip roads are approximately 10m wide and elevated on viaducts within open
areas therefore would be highly visible. To the right hand side of the northbound connecting slip road, as soon
as it crosses the highway corridor, an 80m long section of 5m high with 3m
inclined noise barrier will run along the Fanling Highway. The upper section of this barrier would be
visible above existing tree canopies. 6no. individual sections of noise barrier (consisting of 5m high and
5m high plus 3m inclined barriers) are proposed to the east of Wo Hop Shek
Village, parts of which would be visible before being screened by existing
vegetation cover along the highway. In order to construct the above elements there would be tree losses
within the woodland plantation associated with the Fanling Highway corridor
therefore the overall tree cover in this view would be reduced and views of
new and existing engineered structures would be increased. For this reason it is considered that the
compatibility during construction would be poor. As the structures would be integrated with
an existing major road corridor and given the sheer scale of this view the
compatibility during operation is considered to be fair. The scale and visibility of the development during construction is
likely to be very large and occupy a significant proportion of the view
therefore the magnitude of change during construction is considered to be
large. It is considered that the
magnitude of change in operation would be intermediate as the project would
be integrated into an existing major infrastructure corridor. |
Based on the sensitivity assessment of VSRs as described in Section 12D.12 and the magnitude of change they might experience described in Section 12D.13 the potential significance of the unmitigated visual impacts from DPs during the construction and operation are provided in Table 12D.13.1 using the matrix given in the methodology, and taking into account site visits to the area.
Residual impact significance is also determined in this Section, considering the mitigation measures described in full in Section 12D.9.
Photomontages demonstrating the potential visual impact of the proposed project before and after mitigation from certain VPs are illustrated on Figure 12.55.8a to 19b.
Table 12D.14.1 - Significance of visual impacts for DP 8, 9, 10 and 12
VSR Code |
Name |
VSR Category (Strategic/ District/ Local) |
VSR Type |
VSR Sensitivity (High/ Medium/ Low) |
Magnitude of Change (Large/ Intermediate/ Small/ Negligible) |
Impact Significance BEFORE Mitigation (Substantial/ Moderate/ Slight/
Insignificant) |
Recommended Mitigation Measures |
Residual Impact Significance UPON Mitigation (Substantial/ Moderate/
Slight/ Insignificant) |
|||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation Day 1 |
Operation Year 10 |
|||||
FVP1 |
Po Shek Wu Road adjacent
Tai Tau Lan. |
Local |
Pedestrian, Residential,
Travelling. |
Medium |
Large |
Large |
Moderate/Substantial |
Moderate/Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 16, 17 |
Moderate |
Moderate |
Slight |
FVP2 |
Residential tower, Choi Po Court, Choi Ying House. |
District |
Residential |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 7, 11, 16, 17 |
2, 7, 9, 11, 12, 17 |
Moderate |
Moderate |
Moderate |
FVP3 |
Pedestrian footbridge, San Wan Road |
Local |
Pedestrian, travelling |
Low |
Large |
Intermediate |
Slight/Moderate |
Slight/Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Slight |
Slight |
Insignificant |
FVP6b |
Highpoint above Fu Tei Au Tsuen, facing east. |
District |
Recreational. |
Medium |
Large |
Intermediate |
Moderate/substantial |
Moderate |
2, 4, 11, 16, 17 |
2, 6, 9, 11, 17 |
Moderate |
Sight |
Insignificant |
FVP8 |
Access road adjacent Ng Tung River, west of Wa Shan |
Local |
Recreational |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 17 |
Moderate |
Slight |
Insignificant |
FVP9 |
Access track, Sheung Shui Wa Shan |
Local |
Residential, Occupational |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Slight |
Insignificant |
FVP10 |
Access road, south of Sheung Shui Wa Shan. |
Local |
Travelling |
Low |
Large |
Large |
Slight/Moderate |
Slight/Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Slight |
Slight |
Insignificant |
FVP13 (F20) |
High Rise Residential buildings around Tin Ping
Estate |
District |
Residential - High Rise |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 11, 16, 17 |
2, 6, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP14 |
Footbridge north of Wu Nga Lok Yeung |
Local |
Pedestrian, Recreational |
Medium |
Large |
Large |
Moderate/Substantial |
Moderate/Substantial |
2, 4, 11, 16, 17 |
2, 6, 9, 11, 12, 14, 17 |
Moderate |
Moderate |
Insignificant |
FVP15 (F4) |
Siu Hang San Tsuen |
Local |
Residential - Low Rise |
High |
Intermediate |
Small |
Moderate |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP16 (F11) |
Belair Monte & Regentville |
District |
Residential - High Rise |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 11, 16, 17 |
2, 6, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP17 |
Bridge over Ma Wat River, Sha Tau Road. |
Local |
Pedestrian, Recreational, Travelling |
Medium |
Large |
Intermediate |
Moderate/ Substantial |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Slight |
Insignificant |
FVP18 |
Road Junction west of Ning Wai & Wing Ning Tsuen |
Local |
Residential, Pedestrian |
High |
Large |
Intermediate |
Substantial |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP19 (F9) |
Agricultural plots, Ma Wat Wai. |
Local |
Recreational |
Medium |
Large |
Intermediate |
Moderate |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP20 (F8) |
Access road, Shung Him Tong |
Local |
Residential - Low Rise |
Medium |
Large |
Intermediate |
Moderate/ Substantial |
Moderate |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Slight |
Insignificant |
FVP21 |
Highpoint within On Lok Tsuen |
Local |
Residential |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight/ moderate |
FVP22 |
Bus stop, Cyber Domaine residential estate |
Local |
Residential, pedestrian, travelling. |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate/ substantial |
Moderate |
Slight/ moderate |
FVP23 |
Pedestrian footbridge, Kau Lung Hang San Wai |
District |
Residential, Pedestrian, travelling. |
High |
Large |
Large |
Substantial |
Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Slight |
Insignificant |
FVP24 |
Wo Hing Road, Wo Hop Shek Village |
Local |
Residential, Occupational, pedestrian, travelling. |
High |
Intermediate |
Intermediate |
Moderate/ Substantial |
Moderate/ Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
FVP25 |
Residential Block, Wah Sum Estate |
District |
Residential |
High |
Large |
Intermediate |
Substantial |
Moderate/ Substantial |
2, 4, 11, 16, 17 |
2, 9, 11, 12, 17 |
Moderate |
Moderate |
Slight |
12D.15.1
Landscape
Character Areas
The Lowland Agricultural Landscape (FLCA5) affected by the Schedule 2 DPs is predicted to experience slight adverse impacts, prior to mitigation, in the construction and operational stage. Careful planning of the revised RODP means about 58 ha of land are designated to remain as agricultural land in KTN and FLN NDAs but in these areas referenced agricultural land will be lost. There is no direct compensation measure for the agricultural land lost but some mitigation can be achieved preservation and protection of any trees and where unavoidably affected, transplantation and compensatory planting will assist in reducing the level of impact very slightly. The LVNP is a key component of the Project with preservation and even enhancement of agricultural land which is intended to help alleviate impacts on agricultural land losses across the whole NDA. In the surrounding areas of the Project, 160 ha of land has been found potentially suitable for agricultural rehabilitation/re-site by PlanD with assistance from AFCD . The major cluster (34 ha) is found at Kwu Tung South. By year 10 of operation it is considered the residual impact would remain at a slight adverse level.
Moderate adverse impacts are predicted prior to mitigation works in relation to FLCA1 Natural Hillside Landscape, FLCA2 Rural and Urban Peripheral Village Landscape and FLCA7 Major Water Course Corridor Landscape as a result of the road construction projects. In terms of LCA1, this relates to the high sensitivity of the LCA. The overall area affected in this case is limited and it is considered compensatory woodland planting would quickly reduce this impact to an insignificant level. In terms of FLCA2 and FLCA7, the impacts are mainly generated due to the overall scale of the construction footprint and associated medium sensitivity. In both cases these character areas have undergone development in the past and have capacity to accept a certain level of development. Through mitigation works, in particularly compensatory woodland planting, watercourse mitigation and minimising the need to alter topography, it is considered these impacts can be reduced to insignificant by year 10 of operation.
Slight adverse impacts are predicted in relation to FLCA 3 Urban Development Landscape, FLCA 4 Industrial Landscape and FLCA 6 Major Transportation Corridor Landscape at the construction stage prior to mitigation. The proposed works are considered to have a good compatiblity with these LCAs, therefore would assimilate very quickly during operation. In all cases any adverse impacts can be mitigated to slight or insignificant levels by operation day 1. All impacts would be insignificant by operation year 10 through implementation of tree protection measures, tree transplantation and compensation planting.
12D.15.2
Landscape
Resources
In summary, prior to mitigation, substantial adverse impacts have been predicted in the construction stage for FLR 1.4 Ma Wat River. This is as a result of the major excavations required for the channel realignment (approximately 600m in length) to accommodate the route of the Fanling Bypass. As the LR would be replaced albeit in a different alignment, the impact would reduce to moderate adverse in operation without any mitigation. It is considered through the application of mitigation measures in the construction stage including minimising the requirement for topographical changes, enhancement planting along embankment, protecting and preserving exising trees, transplanting trees where feasible together with replacement of the channel to match the existing that this impact can be reduced to slight by operation day 1. Following the establishment of transplanted and compensatory planting by year 10 of operation, these impacts would have reduced to insignificant.
The Natural Stream at Siu Hang San Tsuen (FLR-2.4) will suffer a small change due to the Project (where it flows under the Fanling Bypass Eastern Section) due to the high sensitivity, a moderate adverse impact is predicted prior to mitigation in construction and operation. The affected stream at Siu Hang San Tsuen, has largely been protected by changes to the proposed Schedule 3 boundary during the planning of the revised RODP with much of this stream avoided. However the stretch of this stream within the DP10 boundary would be located underneath the road viaduct. To the south of the viaduct the stream flows through the area D1-3, zoned as Open Space, prior to joining Ng Tung River. In this Open Space Zone a 10m buffer is proposed in which natural vegetation will be retained and enhanced. Human activities will be limited in order to avoid direct impacts to the stream bed and to minimise potential indirect impacts to the stream and riparian corridor. At detailed design, in order to avoid impacts to the stream, the design of the viaduct should follow guidelines such as ETWB Technical Circular (Works) No. 5/2005 Protection of natural streams/rivers from adverse impacts arising from construction works as well as Building Department (BD) Practice Note for Authorized Persons and Registered Structural Engineers 295: Protection of natural streams/rivers from adverse impacts arising from construction works. This will ensure that no viaduct footings or other structures are placed in the stream; in this case the impact is considered to reduce to slight at construction, becoming insignificant by day 1 and year 10 of operation.
Planning of
the revised RODP has taken care to place much of the Mitigation Wetland in FLN
NDA (FLR-4.2) that falls within the revised RODP on land for ‘Open Space’. The main impacts on this resource are as a
result of the Schedule 3 works however moderate adverse impacts in construction
and operation, prior to mitigation, are predicted as a result of the
construction of the Fanling Bypass Western Section. Whilst the overall area affected is
relatively small (1.59ha), this is a highly sensitive and uncommon
resource. To address this impact
mitigation is provided in the form of the LVNP which will be managed and the
land there, including marsh and wetland areas, enhanced, with a slightly
increase in wetland areas. Taking into account the LVNP enhancement and smaller
level of impact as a result of the Schedule 2 work, the residual impact
significance at construction and operation day 1 is considered to reduce to slight, and by year 10 when wetland and marshes in the
LVNP mature, the residual impact will insignificant.
Although a relatively small area of Cham
Shan and Wa Shan Hillside Woodland (FLR-6.2) and Hillside Woodland at Lung Shan
and Wa Mei Shan (FLR-6.4) is affected by the construction of the Fanling
Bypass, this LR has a high sensitivity and tree felling together with
disturbance of natural topography is considered to generate moderate adverse
impacts in construction and operation prior to mitigation. In this case, minimising the topographical
change within the LR will assist in reducing the overall impact combined with
tree preservation, tree transplantation and woodland compensation
planting. Moderate adverse impacts would
still remain in the construction stages post mitigation, however given the
small areas affected planting measures would quickly address the impact
reducing it to insignificant by year 10 of operation.
A number of agricultural landscape
resources are predicted to experience moderate adverse impacts prior to
mitigation in the construction and operational stage. These are FLR9.5 Agricultural Land at Sheung
Shui Wa Shan, 9.6 Agricultural Land in Wu Nga Lok Yueng, Siu Hang San Tsuen,
Siu Hang Tsuen and Lung Yeuk Tau and 9.7 Agricultural Land in South of Sha Tau
Kok Road. Whilst there is no direct compensation for the
agricultural land lost, direct mitigation includes the possible preservation and protection of any trees
in such LRs and where unavoidably affected,
transplantation and compensatory planting will assist in reducing the level of
impact very slightly. The LVNP is a key
component of the Project with preservation and even
enhancement of agricultural land which is intended to help alleviate impacts on
agricultural land losses across the whole NDA. In addition, this broad
agricultural land category (LR9) encompasses both active and abandoned
agricultural land including orchard areas.
According to a further review and site inspection in December
2012/January 2013 by PlanD with assistance from
AFCD, the amount of active agricultural land affected by the Project in FLN NDA
is approximately 24 ha. According to the AFCD Annual Report 2011-2012, currently, there are 4,071 ha of
abandoned
agricultural land in Hong Kong and 734 ha of active agricultural farmland and
as such, the affected agricultural land represents a small percentage of active
agriculture land in Hong Kong. In the
surrounding areas of the Project, 160 ha of land have been found potentially
suitable for agricultural
rehabilitation/re-site in the above mentioned site inspection. The major cluster (34 ha) is found at Kwu Tung South. Given all these considerations, the
significance of impact on agricultural land in these areas will remain the same
at construction and operation day 1, but by year 10 will have dropped to
slight.
Moderate adverse impacts in construction and operation prior to mitigation are predicted in relation to FLR 7.3 Hung Kiu San Tsuen Lowland Woodland, FLR 7.7 Lowland Woodland near Tai Tau Leng. These impacts are relate to the loss of lowland woodland resources along the alignments of the proposed Fanling Bypass and Po Shek Wu Interchange. The level of impact is considered to reduce to slight by day 1 and insignificant by year 10 as landscape planting works would provide some compensation and through woodland compensation.
Moderate adverse impacts during construction prior to mitigation are predicted in relation to FLR12.12 Rural Development Area in Long Valley, Yin Kong and Hak Ka Wai and FLR 14.3 Fanling Highway. Given the previously developed nature of 12.12 and existing highway function of 14.3, the proposed works are considered to have fair/good compatibility. The initial impacts would be generated due to the large scale of the construction works. In operation it is considered that the impacts would drop to insignificant levels due to the good compatibility of the DPs with the recieving landscape. In terms of mitigation works, minimisation of topographical change, tree transplanting and compensatory planting is predicted to reduce the moderate adverse impact at the construction stage to slight in relation to the both LRs and insignificant by operation day 1.
Slight adverse impacts prior to mitigation are predicted in relation to FLR 1.1 Ng Tung River (Fanling District), 8.3 Shrubland/Grassland Mosaic at Cham Shan and Wa Shan, 9.2 Fu Tei Au Agricultural Land, 11.2 Sheung Shui Urban Area, 11.3 Fanling Urban Area, 12.5 Wa Shan Rural Development Area, 12.6 Lung Yeuk Tau Rural Development Area, 12.7 Rural Development Area at Wo Hop Shek and Lung Shan, 12.8 Rural Development at Ma Shi Po, 12.13 Rural Development Area North of Hong Kong Golf Club, 13.1 Sheung Shui Industrial/Open Storage Area, 13.2 Fanling Industrial Area and 14.2 Sha Tau Kok Road (Lung Yeuk Tau). These impacts principally relate to loss of associated tree cover, large scale construction footprint and in the case of FLR 1.1 and 14.2 excavation works associated with the construction of the Fanling Bypass. It is considered that these impacts can be reduced to slight or insignificant levels at the construction stage through tree protection, transplantation, compensatory planting mitigation measures combined with minimising topographical changes. By year 10 all impacts would be reduce to insignficant levels.
It is
considered that all the remaining adverse impacts on LRs could be mitigated to
insignificant levels at the construction and operational stage through
mitigation works, as these remaining resources fall either within industrial or
open storage areas where the works would have a good compatibility with the
receiving landscape.
12D.15.1
Visual Impact
In comparison to the level of visual impact experienced by VSRs in KTN associated with the DP Package A, the visual impacts in KTN are generally less severe. This is as a result of several factors. In terms of high sensitivity residential VSRs, in KTN these are generally at lower levels (2-3 storey village type housing) with less extensive views of the proposed development or in high rise residential towers with a more strategic overview of the development. In the latter case, these broad panoramic views encompass a huge area whereby the proposed development works would only form a small component. The same is true in relation to high sensitivity recreational views from local prominences such as Ki Lun Shan (KVP2) in that the development forms a very small part of a very large landscape view. The proposed road works are also mainly constructed at-grade which results in them being less conspicuous in the landscape and provides for easy integration of visual mitigation measures such as screen planting, vertical green or road greening.
In FLN, the proposed road works are located in or adjacent to areas of dense population within high rise residential towers whereby the visibility of the works is less practical to mitigate. The works for DP 8, 9, 10 also involve construction of large scale viaducts, noise barriers, noise enclosures, bridges and river channel realignments. Subsequently a higher level of residual impacts is generated.
In summary, the visual impact assessment determined that VSRs in the vicinity of FVP2 Residential tower, Choi Po Court, Choi Ying House, FVP13 High rise residential buildings around Tin Ping Estate, FVP16 Belair Monte & Regentville, FVP18 Road Junction west of Ning Wai & Wing Ning Tsuen, FVP21 Highpoint within On Lok Tsuen, FVP22 Bus stop, Cyber Domaine residential estate, FVP23 Pedestrian footbridge, Kau Lung Hang San Wai and FVP25 Residential Block, Wah Sum Estate have substantial visual impact prior mitigation. In all cases these are residential VSRs with elevated panoramic views over the works areas of for the road schemes (DP8, 9 and 10). Given these elevated vantage points will experience unobstructed view of the construction works, it is not possible to fully mitigate the visibility of the construction works therefore these impacts drop to and remain at a moderate adverse level during the construction after implementing mitigation measures. It is considered through road greening and screen planting that the impact can be further reduced to slight levels by year 10 of operation where these planting works will have fully established and helped to assimilate the works into the landscape. In the case of FVP21 and FVP22 slight/moderate impacts are predicted at year 10 of operation due to the visibility of the Fanling Bypass including new noise barriers remaining highly visible even with mitigation.
Moderate/ substantial
impacts have been predicted to VSRs in the vicinity of FVP1 Po Shek Wu Road adjacent Tai Tau
Lan, FVP6b Highpoint above Fu Tei Au Tsuen, facing east, FVP14 Footbridge north
of Wu Nga Lok Yeung, FVP17 Bridge over Ma Wat River, Sha Tau Road, FVP20 Access
road, Shung Him Tong and FVP24 Wo Hing Road, Wo Hop Shek Village. Generally these VSRs relate to non residential
views where the development will be a large component of the future view. Due to scale of the works and proximity of
these views, a moderate adverse residual impact during the construction works
after mitigation is predicted. It is
considered in all cases this can be reduced to slight or insignificant levels
by year 10 of opereration.
Moderate impacts have been predicted to VSRs in the
vicinity of FVP8 Access road adjacent Ng Tung River, west
of Wa Shan and FVP 9 Access track,
Sheung Shui Wa Shan, FVP15 Siu Hang San Tsuen and FVP19 Agricultural plots, Ma Wat Wai at the
construction stage before mitigation. The development
will be a large component of the future view.
Due to scale of the works and proximity of these views, a moderate
adverse residual impact during the construction works after mitigation is
predicted. It is considered in all
cases this can be reduced to insignificant levels by year 10 of opereration
through road greening and screen planting measures.
Slight/ moderate
impacts are predicted in relation to VSRs in the vicinity of FVP3 Pedestrian
footbridge, San Wan Road and FVP10 Access road, south of Sheung Shui Wa
Shan. In both cases these are pedestrian
level views where the development will be major component of the view. It is considered in all cases this can be
reduced to insignificant levels by year 10 of opereration through road greening
and screen planting measures.
It is considered that all remaining VSRs could be mitigated to slight and insignificant at the construction stage through mitigation works.
12D.15.2
Cumulative
impacts
Cumulative impacts are assessed for concurrent developments together with the wider NDA projects as follows.
12D.15.3
FLN
& KTN NDA
The assessment of impacts in relation to LRs and LCAs in this section has considered the construction of the schedule 2 DPs in isolation so that it is possible to identify and quantify their specific influences and contributions to potential landscape and visual impacts within the wider NDA projects. In general the construction footprint of the schedule 2 DPs are significantly smaller than the schedule 3 components and the associated impacts on LRs and LCAs are also far smaller. When considered together the impact of the schedule 2 projects would not alter the outcome of the schedule 3 assessment as this has taken into the account the same LRs/LCAs within broadly the same study area. It is only on the periphery of the urban area where the schedule 2 DPs potentially exert additional impact on LRs and LCAs beyond the construction footprint of the schedule 3 works, in this case the Fanling Bypass and Po Shek Wu Interchange works. In this case the additional impact, providing mitigation measures are implemented, would prove to be insignificant.
In terms of visual impact, the proposed DPs principally exert negative impacts from VSRs experiencing a panoramic view over the development; in the future this will include the extensive and large scale NDA development. It is considered that, as the road will be seen in the context of the new urban development, it would become more visually acceptable and potential reduce the level of residual impact.
12D.15.4
Agreement
No. CE42/2006(TP) Planning Study on Liantang/Heung Yuen Wai Cross-boundary
Control Point and its Associated Connecting Roads in Hong Kong – Feasibility
Study.
A new Boundary Control Point (BCP) is proposed to be constructed at Liantang/Heung Yuen Wai together with its connecting roads and other associated works. These works involve a tunnel portal which will appear on the Lung Shan hillside east of the Fanling Highway. The Fanling Bypass Eastern works will integrate with these works as these join the Bypass in the same vicinity. It is considered that the DP10 works are considerably smaller than the BCP works and will be far less visually dominant There will be a significant intrusion of new road into the open valley landscape which will have a far greater operational footprint. In this case, this case there may be a marginal increase in the cumulative impact from high sensitivity VSRs with a view of this area.
12D.15.5
Agreement
No. CE53/2008(CE) Planning and Engineering Study on Development of Lok Ma Chau
Loop - Investigation
The LMC Loop eastern connection road lies within the study
area of KTN NDA; this will link to DP 4 (KTN NDA Road D1 to D5) distributor
road south of Ma Tso Lung. This project
is remote from the DPs within this assessment; there would be no cumulative
impacts.
12D.15.6
Widening
of Tolo Highway/ Fanling Highway between Island House Interchange and Fanling
(Stage 2)
This project is the vicinity of the Po Shek Wu Interchange improvement works (DP8). The majority of the DP8 works are offline from the main highway, it is considered that only if the projects are run concurrently that VSRs experiencing views of both of the project would experience potentially worse visual impacts during the construction.
12D.15.7
Construction
of cycle tracks and the associated supporting facilities from Sha Po Tsuen to
Shek Sheung River.
This project is remote from the DPs within this assessment; there would be no cumulative impacts.
12D.15.8
Site
Formation and Associated Infrastructural Works for Development of Columbarium,
Crematorium and Related Facilities at Sandy Ridge Cemetery.
The Sandy Ridge site is located to the north of the two NDA sites, to the east of the NG Tung River and adjacent to Lo Wu MTR station at the border with Shenzhen. This project is remote from these DPs and there would be no cumulative impact.
12D.15.9
Overall
conclusion
Landscape and visual mitigation works in relation to these DPs during the construction stage rely heavily on the minimisation of the footprint of the works area, avoidance of significant topographical changes together with the retention, protection and compensatory planting of trees / vegetation. These measures if deployed have the capacity to reduce, in most cases, the level of residual impact experienced by the VSRs, LRs and LCAs at the construction stage.
It is not possible to fully mitigate all impacts in relation to loss of mature woodland or tree planting, including the visual amenity/ screening they provide in the construction period and early operational stages, mainly as long periods of time are required to sufficiently compensate for the associated impacts. Providing compensatory measures are applied, in combination with transplantation of existing trees (which can help to accelerate the compensation period), the impacts to VSRs and LRs affected by these DPs can be reduced to slight or insignificant levels. Road greening measures such as use of climbing plants and verge planting help to break up the uniformity of new road formation and associated structures (such as footbridges), when used in combination with wider screening measures they will help to reduce the visual impacts in the early operational stages until tree screens have established and matured.
On review of the likely residual impacts and possibility to reduce all to slight or insignificant level by operational year 10, it is considered that DPs 8, 9, 10 and 12 would be acceptable in terms of landscape and visual impacts.
12D.15.10
Schedule
2 Designated Projects Overall conclusion
The following section provides the overall conclusion of the LVIA for Schedule 2 DPs at and associated with KTN and FLN NDAs.
In summary, the principal landscape character areas and resources that will be affected by the construction and operational phases of the scheme are rural and urban peripheral villages, hillside landscapes (including woodland) and agricultural land. Generally they experience substantial to moderate substantial adverse impacts as a result of road construction or the site of the FLN and KTN Flushing Water Service Reservoirs. In these cases, the level of residual impact significance remain at a moderate level until operational year 10 as direct compensation for the related LCAs/LRs cannot be achieved.
In addition, agricultural landscape resources cannot be direct compensated of which will be inevitably lost in the development. Agricultural land is easy to re-create given the right environment and not rare in the New Territories. According to the AFCD Annual Report 2011-2012, currently, there are 4,071 ha of abandoned agricultural land in Hong Kong and 734 ha of active agricultural farmland, the agricultural land affected by the Schedule 2 DPs only represents a small percentage of active agriculture land in Hong Kong. In view of medium sensitivity of this LR, the impact significant is considered moderate or lower. The residual impact to this LR remains unchanged as there is no direct mitigation measures to compensate the lost. Other measures, including retaining about 48 ha of land zoned agriculture in KTN and FLN NDAs, setting up of LVNP and preserving and transplanting trees in the concerned LR would alleviate the impacts slightly.
Most of the landscape impacts can be reduced to slight and insignificant after the implementation and full establishment of mitigation measures. After all, the residual impacts are considered to be acceptable. Given the proposed developments are located within in an existing rural area, it is inevitable that landscape and visual impacts caused by such major development cannot be fully reduced and remain at a certain level at some locations even after implementation of all possible mitigation measures, including minimising topographical change, detailed design of the engineered structures to ensure compatibility of the proposed development with the existing surroundings, tree protection, preservation and transplantation as well as compensatory planting, woodland compensatory planting, screen planting to buffer structures from views, decorative hoarding to screen undesirable views of work sites, light control within construction sites and at operation to reduce light glare that could potentially cause visual disturbance to VSRs at night time, provision for green roofs and vertical greening to soften hard surfaces on built structures in sight.
It is therefore anticipated that the overall residual landscape and visual impacts from the development of the schedule 2 DPs forming the key infrastructure component of the NDAs are considered acceptable with mitigation measures.