3            AIR QUALITY ASSESSMENT

3.1          Overview

This section describes the potential air quality impacts associated with the construction and operation of the NENT NDAs. Construction dust impact has been assessed. With the implementation of practical mitigation measures, adverse construction dust impact is not anticipated.

During operational phase, vehicular emission from the associated road traffic and the odour emission of sewerage treatment works have been investigated. The predicted air quality impacts due to vehicular emission and chimney emissions are well within acceptable levels when comparing to the prevailing Air Quality Objectives (AQO).

Odour levels of the proposed SWHSTW expansion in FLN, which will be equipped with an odour removal system, are predicted at the identified air sensitive receivers (ASRs) to be in compliance with the odour criterion. Adverse odour impacts due to the project are not anticipated.

The air quality impact assessment has been conducted in accordance with the requirements of Annexes 4 and 12 of the TM-EIAO as well as the requirements set out under Clause of the EIA Study Brief.

3.2          Environmental Legislation, Standards and Guidelines

The relevant legislations, standards and guidelines applicable to the present study for the assessment of air quality impacts are:

·         Air Pollution Control Ordinance (APCO) (Cap 311);

·         Air Pollution Control (Construction Dust) Regulation:

·         Environmental Impact Assessment Ordinance (EIAO) (Cap. 499), Technical Memorandum on Environmental Impact Assessment Process (TM-EIAO), Annex 4 and Annex 12; and

·         Practice Note on Control of Air Pollution in Vehicle Tunnels.

3.2.1     Air Quality Objectives

The principal legislation for controlling air pollutants is the APCO and its subsidiary regulations, which define statutory Air Quality Objective (AQOs) for 7 common air pollutants. The AQOs for these air pollutants are tabulated in Table 3.1 below.

 

Table 3.1 – Hong Kong Air Quality Objectives

Pollutant

Concentration in micrograms per cubic metre [1]

(Parts per million, ppm in brackets)

1 Hour

[2]

8 Hours [3]

24 Hours [3]

3 Months [4]

1 Year

[4]

Sulphur Dioxide

800

(0.3)

 

350

(0.13)

 

80

(0.03)

Total Suspended Particulates

500 [7]

 

260

 

80

Respirable Suspended Particulates [5]

 

 

180

 

55

Carbon Monoxide

30,000

(26.2)

10,000

(8.7)

 

 

 

Nitrogen Dioxide

300

(0.16)

 

150

(0.08)

 

80

(0.04)

Photochemical

Oxidants (as ozone) [6]

240

 

 

 

 

Lead

 

 

 

1.5

 

Notes: 

[1]  Measured at 298K and 101.325 kPa.

[2]  Not to be exceeded more than three times per year.

[3]  Not to be exceeded more than once per year.

[4]  Arithmetic mean.

[5]  Respirable suspended particulates means suspended particulates in air with a nominal aerodynamic diameter of 10 micrometres or smaller.

[6]  Photochemical oxidants are determined by measurement of ozone only.

[7]  Not an AQO but is a criterion for evaluating air quality impacts as stated in Technical Memorandum on Environmental Impact Assessment Process.

3.2.2     Air Pollution Control (Construction Dust) Regulation

The Air Pollution Control (Construction Dust) Regulation identifies works that require special dust control. Works relevant to this Project are the site formation and infrastructure elements, for which Total Suspended Particulates (TSP) concentration shall not exceed the respective criterion in Table 3.1.

3.2.3     Odour Criteria

In accordance with Annex 4 of TM-EIAO, the limit of 5 odour units based on an averaging time of 5 seconds for odour prediction assessment should not be exceeded at any sensitive receivers.


 

3.3          Description of Environment

3.3.1     Assessment Area

With reference to the EIA Study Brief, the assessment area for air quality impact assessment should generally be defined by a distance of 500 metres expanded from the boundary of the NDAs and associated infrastructure works. Figures 2.1 and Figures 2.2 show the proposed landuse for each NDA, associated works, and 500m assessment boundary. The assessment includes existing and planned sensitive receivers in the assessment area. Potential sources of impact within the assessment area are identified, where appropriate.

3.3.2     Baseline Condition

There is no EPD baseline air quality monitoring station (AQMS) within the Study Area. According to Appendix B-2 Section 3.2 of the EIA Study Brief for this project, the district of Shatin, Tai Po, Junk Bay, Hong Kong South and Yuen Long are Rural/New Development areas. The mean of the annual average concentrations monitored at these 5 districts could therefore be adopted to represent the baseline concentrations for the current study area. However, there is no monitoring station in Hong Kong South and Tseung Kwan O. Air quality monitoring data is not available for the two AQMS. The latest 5 published years of available air quality monitoring data, i.e. 2007 to 2011 are tabulated in Table 3.2 below:

Table 3.2 – Air quality monitoring data in Year 2007-2011

Pollutant

Station

Annual Concentration (μg/m3)

2007

2008

2009

2010

2011

5-year Mean

NO2

Shatin

45

44

40

42

45

48.5

Tai Po

53

52

45

46

45

Yuen Long

55

56

52

54

54

RSP

Shatin

52

50

45

45

47

50.5

Tai Po

53

50

46

45

46

Yuen Long

64

60

51

49

54

TSP

Shatin

73

66

60

67

66

73.1

Tai Po

73

73

60

64

69

Yuen Long

97

87

77

78

86

SO2

Shatin

19

17

11

12

14

14.3

Tai Po

16

17

9

8

8

Yuen Long

24

21

14

11

13

Notes: 

[1]  Air quality data not available.

In view of the air quality data between 2007 and 2011, the annual averaged concentrations of air pollutants (e.g. NO2, RSP) showed a gradual decreasing trend. The 5-year mean of annual average concentrations at Shatin, Tai Po, Tseung Kwan O, Hong Kong South and Yuen Long Monitoring Stations in 2007 – 2011 have been taken as the baseline air quality data.

3.4          Air Sensitive Receivers

The representative air sensitive receivers (ASRs) within 500m from the boundary of NDAs and associated road network have been identified. These include any domestic premises, hotel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre. Existing ASRs outside the site boundary mainly comprise village houses and residential developments.

The existing and planned ASRs outside the NDA boundary were identified from topographic maps, aerial photos, land status plans and site surveys.  Planned ASRs within the NDA boundary were identified by making reference to the Recommended Outline Development Plans (RODP) mentioned in  Section 2.3, Population Intake Programme and Implementation Programme.

Since the population intake would proceed in phases, certain land-lots of existing ASRs inside the NDAs would be resumed for development and some of the planned ASRs would exist before the Project development is fully completed. Therefore, consideration of the phased development over time has been taken to identify ASRs, representative of the different implementation stages of the Project. 

The locations of representative existing ASRs within the 500m assessment area of KTN and FLN NDAs and are shown in Figure 3.1 and Figure 3.2, and tabulated in Table 3.3 and Table 3.4 respectively.

Locations of representative planned ASRs within the 500m assessment area of KTN and FLN NDAs have been identified and are shown in Figure 3.3 and Figure 3.4 and tabulated in Table 3.5 and Table 3.6 respectively. Details of the future land lots of the Revised RODP (including land uses, building heights) are shown in Appendix 2.1.

 


Table 3.3 – Representative existing ASRs within the 500m assessment area and in the vicinity of KTN NDA

Description

ASRID

Landuse

Building Height Above Ground (approx.) (m)

Separation Distance between ASR and Site Boundary (approx.) (m)

Assessment

Year [1]

Dills Corner Garden

KTN-E1

R

6

within the KTN NDA

2018

KTN-E3

R

6

within the KTN NDA

2018

KTN-E4

R

6

within the KTN NDA

2018

KTN-E5

R

6

within the KTN NDA

2018

KTN-E6

R

6

within the KTN NDA

2018

KTN-E7

R

6

within the KTN NDA

2018

KTN-E8

R

6

within the KTN NDA

2018

KTN-E9

R

6

within the KTN NDA

2018

KTN-E10

R

6

within the KTN NDA

2018

KTN-E11

R

6

within the KTN NDA

2018

Kwu Tung Playground

KTN-E15

RC

1.5

within the KTN NDA

2024

Oil Wah School

KTN-E18

E

12

within the KTN NDA

2024

Home of Loving Faithfulness

KTN-E19

H

9

within the KTN NDA

2024

Temporary Structure near Han Clan Grave

KTN-E20

OU

3

within the KTN NDA

2024

KTN-E21

OU

3

within the KTN NDA

2024

KTN-E22

OU

3

within the KTN NDA

2024

Temporary Structure near Sheung Yue River

KTN-E24

OU

3

within the KTN NDA

2025

KTN-E25

OU

3

within the KTN NDA

2024

KTN-E26

OU

3

within the KTN NDA

2024

KTN-E27

OU

3

within the KTN NDA

2024

Temporary Structure near Shek Tsai Leng

KTN-E28

OU

3

within the KTN NDA

2024

KTN-E30

OU

3

within the KTN NDA

2024

Shek Tsai Leng Factory

KTN-E31

I

3

within the KTN NDA

2024

KTN-E32

I

3

within the KTN NDA

2024

KTN-E33

I

3

within the KTN NDA

2024

KTN-E34

I

3

within the KTN NDA

2024

KTN-E35

I

3

within the KTN NDA

2024

KTN-E36

I

3

within the KTN NDA

2024

KTN-E37

I

3

within the KTN NDA

2024

KTN-E38

I

3

within the KTN NDA

2024

KTN-E39

I

3

within the KTN NDA

2024

Temporary Structure at Fung Kong

KTN-E40

R

3

within the KTN NDA

2024

KTN-E41

R

3

within the KTN NDA

2024

KTN-E42

R

3

within the KTN NDA

2024

KTN-E43

R

3

within the KTN NDA

2024

KTN-E44

R

3

within the KTN NDA

2024

KTN-E45

R

3

within the KTN NDA

2024

Shek Tsai Leng Factory

KTN-E46

I

3

within the KTN NDA

2024

Factory near Ho Sheung Heung Road

KTN-E47

I

3

within the KTN NDA

2024

KTN-E48

I

3

within the KTN NDA

2024

KTN-E49

I

3

within the KTN NDA

2024

Village Houses between Tung Kok and Tung Fong

KTN-E50

R

6

within the KTN NDA

2024

KTN-E52

R

6

within the KTN NDA

2024

KTN-E53

R

6

within the KTN NDA

2024

KTN-E54

R

6

within the KTN NDA

2024

Temporary Structure at Tung Fong

KTN-E55

OU

6

within the KTN NDA

2018

KTN-E56

OU

6

within the KTN NDA

2018

KTN-E57

OU

6

within the KTN NDA

2018

KTN-E58

OU

6

within the KTN NDA

2018

KTN-E59

OU

6

within the KTN NDA

2018

Temporary Structure at Pak Shek Au

KTN-E60

OU

6

within the KTN NDA

2018

KTN-E61

OU

6

within the KTN NDA

2018

KTN-E62

OU

6

within the KTN NDA

2018

KTN-E63

OU

6

within the KTN NDA

2018

KTN-E64

OU

6

within the KTN NDA

2018

KTN-E65

OU

6

within the KTN NDA

2018

KTN-E67

OU

6

within the KTN NDA

2018

KTN-E68

OU

6

within the KTN NDA

2018

KTN-E69

OU

6

within the KTN NDA

2018

KTN-E70

OU

6

within the KTN NDA

2018

KTN-E71

OU

6

within the KTN NDA

2018

KTN-E72

OU

6

within the KTN NDA

2018

KTN-E73

OU

6

within the KTN NDA

2018

KTN-E78

OU

6

within the KTN NDA

2018

KTN-E79

OU

6

within the KTN NDA

2018

Temporary Structure Western to Yin Kong Tsuen

KTN-E80

OU

3

within the KTN NDA

2024

KTN-E81

OU

3

within the KTN NDA

2024

KTN-E82

OU

3

within the KTN NDA

2024

KTN-E83

OU

3

within the KTN NDA

2024

KTN-E84

OU

3

within the KTN NDA

2024

Yin Kong Tsuen

KTN-E85

R

9

within the KTN NDA

2044

KTN-E86

R

9

within the KTN NDA

2044

KTN-E87

R

9

within the KTN NDA

2044

Sports Ground near Enchi Lodge

KTN-E88

RC

1.5

within the KTN NDA

2044

Temporary Structure near Castle Peak Road

KTN-E89

OU

3

within the KTN NDA

2044

KTN-E90

OU

3

within the KTN NDA

2044

KTN-E91

OU

3

within the KTN NDA

2044

Temporary Structure Southern to Ho Sheung Heung Village

KTN-E92

OU

3

within the KTN NDA

2022

KTN-E93

OU

3

within the KTN NDA

2022

Ho Sheung Heung Temple

KTN-E94

W

3

within the KTN NDA

2044

Ho Sheung Heung Village

KTN-E97

R

9

within the KTN NDA

2044

KTN-E99

R

9

within the KTN NDA

2044

KTN-E100

R

9

within the KTN NDA

2044

KTN-E101

R

9

within the KTN NDA

2044

Temporary Structure Northern to Ho Sheung Heung Village

KTN-E102

OU

3

within the KTN NDA

2044

Village Houses near Tsung Yuen

KTN-E104

R

9

within the KTN NDA

2044

KTN-E106

R

9

within the KTN NDA

2044

KTN-E108

R

9

within the KTN NDA

2044

Temporary Structure at Tsung Yuen

KTN-E109

R

3

within the KTN NDA

2044

Temporary Structure near Lo Wu Correctional Institution

KTN-E110

OU

3

within the KTN NDA

2044

Lo Wu Correctional Institution Basketball Court

KTN-E111

RC

1.5

within the KTN NDA

2044

Lo Wu Correctional Institution

KTN-E112

IC

3

within the KTN NDA

2044

Temporary Structure near Phoenix Garden

KTN-E113

OU

3

within the KTN NDA

2024

Temporary Structure along Fung Kong Shan

KTN-E114

OU

3

within the KTN NDA

2024

KTN-E115

OU

3

within the KTN NDA

2024

KTN-E116

OU

3

within the KTN NDA

2024

KTN-E117

OU

3

within the KTN NDA

2024

KTN-E118

OU

3

within the KTN NDA

2024

KTN-E119

OU

3

within the KTN NDA

2019

KTN-E120

OU

3

within the KTN NDA

2019

Lo Wu Firing Range (Eastern)

KTN-E123

IC

1.5

within the KTN NDA

2044

Temporary Structure at Ma Tso Lung (Eastern)

KTN-E124

R

3

within the KTN NDA

2024

KTN-E125

R

3

within the KTN NDA

2024

KTN-E126

R

3

within the KTN NDA

2024

KTN-E127

R

3

within the KTN NDA

2024

Lo Wu Firing Range (Western)

KTN-E128

IC

1.5

within the KTN NDA

2044

Temporary Structure at Ma Tso Lung (Western)

KTN-E129

OU

3

within the KTN NDA

2024

KTN-E130

OU

3

within the KTN NDA

2024

KTN-E131

OU

3

within the KTN NDA

2024

Temporary Structure near Lo Wu Firing Range

KTN-E133

OU

3

within the KTN NDA

2024

KTN-E134

OU

3

within the KTN NDA

2024

KTN-E135

OU

3

within the KTN NDA

2024

Giant Soccer Academy

KTN-E136

IC

1.5

within the KTN NDA

2017

Temporary Structure near Fung Kong Shan

KTN-E137

OU

3

within the KTN NDA

2024

KTN-E138

OU

3

within the KTN NDA

2024

KTN-E139

OU

3

within the KTN NDA

2024

KTN-E140

OU

3

within the KTN NDA

2024

Temporary Structure near Giant Soccer Academy

KTN-E141

OU

3

within the KTN NDA

2024

Temporary Structure near Community Sports

KTN-E142

OU

3

within the KTN NDA

2024

Temporary Structure near Fung Kong

KTN-E143

OU

3

within the KTN NDA

2024

KTN-E145

OU

3

within the KTN NDA

2024

Open Storage near Fung Kong

KTN-E146

OS

1.5

within the KTN NDA

2018

Temporary Structure near Fung Kong

KTN-E148

OS

3

within the KTN NDA

2018

Temporary Structure near Ma Tso Lung Road

KTN-E149

R

3

within the KTN NDA

2018

KTN-E150

R

3

within the KTN NDA

2018

KTN-E151

R

3

within the KTN NDA

2018

Temporary Structure near Fung Kong

KTN-E152

R

3

within the KTN NDA

2024

Ho Sheung Heung Village

KTN-E154

R

9

within the KTN NDA

2044

KTN-E155

R

9

within the KTN NDA

2044

KTN-E156

R

9

within the KTN NDA

2044

Temporary Structure near Dills Corner Garden

KTN-E157

OU

3

within the KTN NDA

2018

KTN-E158

OU

3

within the KTN NDA

2018

KTN-E159

OU

3

within the KTN NDA

2018

Kwu Tung Grass Soccer Pitch

KTN-E160

RC

1.5

within the KTN NDA

2024

KTN-E161

RC

1.5

within the KTN NDA

2024

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

OU

3

within the KTN NDA

2044

KTN-E163

OU

3

within the KTN NDA

2044

KTN-E164

OU

3

within the KTN NDA

2044

Temporary Structure at Pak Shek Au

KTN-E165

OU

3

within the KTN NDA

2018

KTN-E166

OU

3

within the KTN NDA

2018

KTN-E167

OU

3

within the KTN NDA

2018

KTN-E168

OU

3

within the KTN NDA

2018

KTN-E169

OU

3

within the KTN NDA

2018

KTN-E170

OU

3

within the KTN NDA

2025

KTN-E171

OU

3

within the KTN NDA

2025

KTN-E172

OU

3

within the KTN NDA

2025

KTN-E173

OU

3

within the KTN NDA

2025

KTN-E174

OU

3

within the KTN NDA

2025

KTN-E175

OU

3

within the KTN NDA

2025

KTN-E176

OU

3

within the KTN NDA

2018

Temporary Structure near Shek Tsai Leng

KTN-E177

OU

3

within the KTN NDA

2024

KTN-E178

OU

3

within the KTN NDA

2024

KTN-E179

OU

3

within the KTN NDA

2024

KTN-E180

OU

3

within the KTN NDA

2024

KTN-E181

OU

3

within the KTN NDA

2024

Pui Yau Kindergarten

KTN-E182

E

9

within the KTN NDA

2024

Temporary Structure near Tung Fong

KTN-E183

R

3

within the KTN NDA

2024

KTN-E184

R

3

within the KTN NDA

2024

Village Houses between Tung Kok and Tung Fong

KTN-E185

R

9

within the KTN NDA

2024

KTN-E186

R

9

within the KTN NDA

2024

KTN-E187

R

9

within the KTN NDA

2024

KTN-E188

R

9

within the KTN NDA

2024

Temporary Structure near Tung Fong

KTN-E189

R

6

within the KTN NDA

2024

KTN-E190

R

6

within the KTN NDA

2024

Village Houses between Tung Kok and Tung Fong

KTN-E191

R

6

within the KTN NDA

2024

Temporary Structure near Fung Kong

KTN-E192

R

6

within the KTN NDA

2024

KTN-E193

R

6

within the KTN NDA

2024

KTN-E194

R

6

within the KTN NDA

2024

KTN-E195

R

6

within the KTN NDA

2024

KTN-E196

R

6

within the KTN NDA

2024

KTN-E197

R

6

within the KTN NDA

2024

KTN-E198

R

6

within the KTN NDA

2024

KTN-E199

R

6

within the KTN NDA

2024

KTN-E200

R

6

within the KTN NDA

2024

KTN-E201

R

6

within the KTN NDA

2024

KTN-E202

R

6

within the KTN NDA

2024

Open Storage nenar Fung Kong

KTN-E203

OS

1.5

within the KTN NDA

2024

Temporary Structure near Lo Wu Fire Range

KTN-E204

R

3

within the KTN NDA

2024

Temporary Structure near Fung Kong Shan

KTN-E205

OU

3

within the KTN NDA

2019

KTN-E206

OU

3

within the KTN NDA

2019

KTN-E207

OU

3

within the KTN NDA

2019

KTN-E208

OU

3

within the KTN NDA

2019

Ma Tso Lung San Tsuen

KTN-E209

R

9

within the KTN NDA

2044

Temporary Structure Western to Ho Sheung Heung Village

KTN-E210

OU

3

within the KTN NDA

2024

KTN-E211

OU

3

within the KTN NDA

2024

KTN-E212

OU

3

within the KTN NDA

2024

KTN-E213

OU

3

within the KTN NDA

2024

Open Storage along Castle Peak Road - San Tin

KTN-E1001

OS

1.5

991

2044

Container Trailer Park along Kwu Tung Road

KTN-E1002

OS

1.5

195

2044

Europa Garden Phase I

KTN-E1003

R

9

23

2044

Lady Ho Tung Welfare Centre

KTN-E1004

IC

6

73

2044

Valais Phase 1

KTN-E1005

R

9

25

2044

KTN-E1006

R

9

13

2044

KTN-E1007

R

9

73

2044

Village House north to Casas Domingo

KTN-E1008

R

3-9

292

2044

St Paul's House of Prayer

KTN-E1009

W

12

22

2044

Kam Tsin Village Ho Tung School

KTN-E1010

E

3

9

2044

Golf Parkview

KTN-E1011

R

12

34

2044

Tsung Pak Long

KTN-E1012

R

3-9

51

2044

Tsung Pak Long (Hakka Wai)

KTN-E1013

R

3-9

209

2044

Tai Tau Leng

KTN-E1014

R

10

568

2044

KTN-E1015

R

10

638

2044

Choi Ngan House

KTN-E1016

R

110

777

2044

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

R

3-9

14

2044

KTN-E1018

R

3-9

11

2044

Village Houses at Ma Tso Lung

KTN-E1019

R

3-9

27

2044

Village Houses at Tit Hang

KTN-E1020

R

3-9

27

2044

Workshop northwest to Pak Shek Au

KTN-E1021

I

9

17

2044

Chau Tau Tsuen

KTN-E1022

R

9

509

2044

Village House southeast to Chau Tau Tsuen

KTN-E1023

R

3-9

150

2044

Open Storage north to Pai Tau Lo

KTN-E1024

OS

1.5

360

2044

Notes:

[1]      Existing ASRs inside NDAs would be resumed for development, and thus the time effect has been considered for the identification of existing ASRs: i.e. KTN-E1 would not be identified as an ASR after Year 2018.

[2]      R– Residential; E – Educational; H – Hospital/Clinic/ home for the aged; G – Government; IC – Institution and Community; O – Open space; OS – Open storage; RC – Recreational;  OU – Other specific uses

Table 3.4 – Representative existing ASRs within 500m assessment area and in the vicinity of FLN NDA

 

Description

ASRID

Landuse

Building Height Above Ground (approx.) (m)

Separation Distance between ASR and Site Boundary (approx.) (m)

Assessment

Year [1]

Village Houses at Fu Tei Au Tsuen (Western)

FLN-E1

R

3-9

within the FLN NDA

2024

Agriculture Lands at  Fu Tei Au Tsuen

FLN-E2

AGR

3-9

within the FLN NDA

2044

FLN-E3

AGR

3-9

within the FLN NDA

2044

FLN-E4

AGR

3-9

within the FLN NDA

2044

FLN-E5

AGR

3-9

within the FLN NDA

2044

FLN-E6

AGR

3-9

within the FLN NDA

2044

FLN-E7

AGR

3-9

within the FLN NDA

2044

FLN-E8

AGR

3-9

within the FLN NDA

2044

FLN-E9

AGR

3-9

within the FLN NDA

2044

FLN-E10

AGR

3-9

within the FLN NDA

2044

FLN-E11

AGR

3-9

within the FLN NDA

2044

FLN-E12

AGR

3-9

within the FLN NDA

2044

Man Ming Temple at Fu Tei Au Tsuen

FLN-E13

W

3-9

within the FLN NDA

2044

Village Houses at Fu Tei Au Tsuen (Eastern)

FLN-E14

R

3-9

within the FLN NDA

2024

FLN-E15

R

3-9

within the FLN NDA

2018

FLN-E16

R

3-9

within the FLN NDA

2018

FLN-E17

R

3-9

within the FLN NDA

2018

FLN-E18

R

3-9

within the FLN NDA

2018

FLN-E19

R

3-9

within the FLN NDA

2018

FLN-E20

R

3-9

within the FLN NDA

2018

FLN-E21

R

3-9

within the FLN NDA

2018

FLN-E22

R

3-9

within the FLN NDA

2018

FLN-E23

R

3-9

within the FLN NDA

2018

FLN-E24

R

3-9

within the FLN NDA

2044

FLN-E25

R

3-9

within the FLN NDA

2044

FLN-E26

R

3-9

within the FLN NDA

2044

FLN-E27

R

3-9

within the FLN NDA

2044

FLN-E28

R

3-9

within the FLN NDA

2044

Hung Kiu Sun Tsuen

FLN-E29

R

3-9

within the FLN NDA

2018

FLN-E30

R

3-9

within the FLN NDA

2018

FLN-E31

R

3-9

within the FLN NDA

2018

FLN-E32

R

3-9

within the FLN NDA

2018

FLN-E33

R

3-9

within the FLN NDA

2018

FLN-E34

R

3-9

within the FLN NDA

2018

FLN-E35

R

3-9

within the FLN NDA

2018

Temporary Structure Southern to Ng Tung River

FLN-E36

OU

3

within the FLN NDA

2019

FLN-E37

OU

3

within the FLN NDA

2019

FLN-E38

OU

3

within the FLN NDA

2019

FLN-E39

OU

3

within the FLN NDA

2019

FLN-E40

OU

3

within the FLN NDA

2019

FLN-E41

OU

3

within the FLN NDA

2019

FLN-E42

OU

3

within the FLN NDA

2019

FLN-E43

OU

3

within the FLN NDA

2024

FLN-E44

OU

3

within the FLN NDA

2024

FLN-E45

OU

3

within the FLN NDA

2019

FLN-E46

OU

3

within the FLN NDA

2024

FLN-E47

OU

3

within the FLN NDA

2024

FLN-E48

OU

3

within the FLN NDA

2024

FLN-E49

OU

3

within the FLN NDA

2024

FLN-E50

OU

3

within the FLN NDA

2024

FLN-E51

OU

3

within the FLN NDA

2024

FLN-E52

OU

3

within the FLN NDA

2024

FLN-E53

OU

3

within the FLN NDA

2024

FLN-E54

OU

3

within the FLN NDA

2024

FLN-E55

OU

3

within the FLN NDA

2024

Tin Ping Shan Tsuen

FLN-E56

R

3-9

within the FLN NDA

2024

FLN-E57

R

3-9

within the FLN NDA

2024

FLN-E58

R

3-9

within the FLN NDA

2024

FLN-E59

R

3-9

within the FLN NDA

2024

FLN-E60

R

3-9

within the FLN NDA

2024

FLN-E61

R

3-9

within the FLN NDA

2024

Scattered Village Houses North of Proposed Potential Town-park

FLN-E62

R

3-9

within the FLN NDA

2025

Temporary Structure Eastern to Woodland Crest

FLN-E63

OU

3

within the FLN NDA

2024

Temporary Structure at Wu Nga Lok Yeung (Western)

FLN-E64

R

3-9

within the FLN NDA

2024

FLN-E65

R

3-9

within the FLN NDA

2024

FLN-E66

R

3-9

within the FLN NDA

2024

FLN-E67

R

3-9

within the FLN NDA

2024

FLN-E68

R

3-9

within the FLN NDA

2024

FLN-E69

R

3-9

within the FLN NDA

2024

Temporary Structure at Ma Shi Po (Eastern)

FLN-E70

R

3-6

within the FLN NDA

2019

Temporary Structure at Wu Nga Lok Yeung (Northern)

FLN-E71

R

3-9

within the FLN NDA

2024

FLN-E72

R

3-9

within the FLN NDA

2024

Village Houses at Ma Shi Po (Northern)

FLN-E73

R

3-9

within the FLN NDA

2024

FLN-E74

R

3-9

within the FLN NDA

2024

FLN-E75

R

3-9

within the FLN NDA

2024

FLN-E76

R

3-9

within the FLN NDA

2019

Village Houses at Ma Shi Po (Eastern)

FLN-E77

R

3-9

within the FLN NDA

2019

FLN-E78

R

3-9

within the FLN NDA

2019

FLN-E79

R

3-9

within the FLN NDA

2019

FLN-E80

R

3-9

within the FLN NDA

2019

FLN-E81

R

3-9

within the FLN NDA

2019

FLN-E82

R

3-9

within the FLN NDA

2019

FLN-E83

R

3-9

within the FLN NDA

2019

FLN-E84

R

3-9

within the FLN NDA

2019

North District Temporary Wholesale Market for Agricultural Products

FLN-E85

G, C

6

within the FLN NDA

2019

Temporary Structure at Wu Nga Lok Yeung (Southern)

FLN-E86

R

3-9

within the FLN NDA

2024

FLN-E87

R

3-9

within the FLN NDA

2024

FLN-E88

R

3-9

within the FLN NDA

2024

FLN-E89

R

3-9

within the FLN NDA

2024

FLN-E90

R

3-9

within the FLN NDA

2024

FLN-E91

R

3-9

within the FLN NDA

2024

Temporary Structure at Wu Nga Lok Yeung (Eastern)

FLN-E92

R

3-9

within the FLN NDA

2024

FLN-E93

R

3-9

within the FLN NDA

2024

FLN-E94

R

3-9

within the FLN NDA

2024

FLN-E95

R

3-9

within the FLN NDA

2024

FLN-E97

R

3-9

within the FLN NDA

2024

FLN-E98

R

3-9

within the FLN NDA

2024

Village Houses at Ma Shi Po (Southern)

FLN-E99

R

3-9

within the FLN NDA

2024

FLN-E100

R

3-9

within the FLN NDA

2019

FLN-E101

R

3-9

within the FLN NDA

2019

FLN-E102

R

3-9

within the FLN NDA

2019

Buddhist Li Chong Yuet Ming Nursing Home for The Elderly

FLN-E103

H

20

1150

2044

Choi Po Court

FLN-E104

R

110

1130

2044

Tai Tau Leng

FLN-E105

R

10

1260

2044

No. 56 San Fung Avenue

FLN-E106

R

15

650

2044

Po Sheung Tsuen

FLN-E107

R

10

600

2044

Tsui Lai Garden

FLN-E108

R

100

330

2044

Hing Yan Tsuen

FLN-E109

R

10

430

2044

Sheung Pak Tsuen

FLN-E110

R

3-9

370

2044

Fung Kai Liu Man Shek Tong Secondary School

FLN-E111

E

27

410

2044

Woodland Crest

FLN-E112

R

40

40

2044

Tin Ping Shan Tsuen

FLN-E113

R

3-9

80

2044

Fung Kai Primary School

FLN-E114

E

6-9

280

2044

Fung Kai No. 1 Secondary School

FLN-E115

E

6-9

240

2044

Fung Kai No. 2 Secondary School

FLN-E116

E

6-9

140

2044

Man Kok Village

FLN-E117

R

3-9

100

2044

Ancestor of Lui Temple (Tak Yeung Tong)

FLN-E118

W

3

5

2044

Hung Kiu San Tsuen

FLN-E119

R

3-9

30

2044

Tin Hau Ancient Temple

FLN-E120

W

3

60

2044

Scattered Village Houses in Sheung Shui Wa Shan

FLN-E121

R

3-9

140

2044

Scattered Village Houses North of Proposed Potential Town-park

FLN-E122

R

3-9

40

2044

On Kwok Villa

FLN-E123

R

9

20

2044

Noble Hill

FLN-E124

R

54

10

2044

Good View New Village

FLN-E125

R

6-9

40

2044

Scattered Village Houses East of Good View New Village

FLN-E126

R

3-9

40

2044

Wing Fok Centre

FLN-E127

C

84

30

2044

Wing Fai Centre

FLN-E128

C

102

30

2044

Belair Monte

FLN-E129

R

90

20

2044

Siu Hang San Tsuen

FLN-E130

R

3-9

220

2044

Siu Hang Tsuen

FLN-E131

R

3-9

270

2044

Kan Lung Tsuen

FLN-E132

R

3-9

120

2044

The Sisters of the Precious Blood Children Village

FLN-E133

R

3-9

230

2044

San Uk Tsuen

FLN-E134

R

3-9

60

2044

Wing Ning Wai

FLN-E135

R

3-9

50

2044

Wing Ning Tsuen

FLN-E136

R

10

50

2044

FLN-E137

R

10

110

2044

Ma Wat Tsuen

FLN-E138

R

10

210

2044

Ma Wat Wai

FLN-E139

R

10

200

2044

Village House near Ma Wat Wai

FLN-E140

R

3-9

60

2044

Village House near Fanling Tsung Kyam Church

FLN-E141

R

3-9

370

2044

Village House near On Lok Garden

FLN-E142

R

3-9

500

2044

Village House near Tong Hang

FLN-E143

R

3-9

830

2044

Village House at Tong Hang

FLN-E144

R

3-9

1260

2044

Wong Kong Shan

FLN-E145

R

10

1180

2044

FLN-E146

R

10

1400

2044

Wo Hop Shek Village

FLN-E147

R

10

1590

2044

Kau Lung Hang

FLN-E148

R

3-9

1760

2044

Shek Wu Hui Sewage Treatment Works

FLN-E149

G

6

230

2044

On Wu Centre

FLN-E150

C

19

690

2044

Smile Centre

FLN-E151

C

19

480

2044

Kader Industrial Centre

FLN-E152

I

19

620

2044

Heraeus Technology Centre

FLN-E153

C

19

190

2044

Wo Fung Building

FLN-E154

I

19

840

2044

Village House near Wu Nga Lok Yeung

FLN-E155

R

3-9

15

2044

FLN-E156

R

3-9

10

2044

North District Sports Ground

FLN-E157

RC

1.5

350

2044

Grand Tower Block A

FLN-E158

R

50

550

2044

Tin Ping Estate Tin Mei House

FLN-E159

R

93

280

2044

Golf Parkville Block 7

FLN-E160

R

17

130

2044

Yuk Po Court Tsun Wu House

FLN-E161

R

65

860

2044

Temporary Structure at Wu Nga Lok Yeung (Eastern)

FLN-E162

R

3-9

within the FLN NDA

2024

FLN-E163

R

3-9

within the FLN NDA

2024

FLN-E164

R

3-9

within the FLN NDA

2024

FLN-E165

R

3-9

within the FLN NDA

2024

FLN-E166

R

3-9

within the FLN NDA

2024

FLN-E167

R

3-9

within the FLN NDA

2024

Village Houses at Ma Shi Po (Southern)

FLN-E168

R

3-9

within the FLN NDA

2019

FLN-E169

R

3-9

within the FLN NDA

2019

FLN-E170

R

3-9

within the FLN NDA

2019

Tin Ping Estate Tin Cheung House

FLN-E171

R

100

310

2044

Sunningdale Garden Block 1

FLN-E172

R

65

340

2044

102 Jockeyclub Road

FLN-E173

R

11

500

2044

Grand Regentville Block 6

FLN-E174

R

101

200

2044

Notes:

[1]   Existing ASRs inside NDAs would be resumed for development, and thus the time effect has been considered for the identification of existing ASRs: i.e. KTN-E1 would not be identified as an ASR after   Year 2018.

[2]   R– Residential; E – Educational; H – Hospital/ Clinic/ Home for the aged; G – Government; RC – Recreational;  W – Worship; I – Industrial; C – Commercial; AGR – Agricultural; OU – Other specific uses

Table 3.5 – Representative planned ASRs within 500m assessment area and in the vicinity of KTN NDA [1]

Land Lot

Description

ASRID

Landuse

Proposed Building Height Above Ground (m)

Population Intake  Year

A1-2

Residential home for the elderly (RCHEs); Nursery Classes and Kindergartens; Local Rehousing [3]

KTN-1 to KTN-11

P

78.75 - 110.25

2023

A1-4

Nursery Classes and Kindergartens[4]

KTN-12 to KTN-18

R

68.85 - 97.2

2023

A1-5

Nursery Classes and Kindergartens; Post Offices

KTN-19 to KTN-28

C

68.85 - 97.2

2023

A1-6

Nursery Classes and Kindergartens[4]; Early Education and Training Centre

KTN-29 to KTN-37

R

68.85 - 97.2

2029

A1-8

Nursery Classes and Kindergartens[4]

KTN-38 to KTN-46

H

68.85 - 97.2

2030

A1-9

Residential Uses

KTN-47 to KTN65

R

47.25 - 63

2031

A2-11

Primary School

KTN-66 to KTN-75

E

36

2028

A2-13

Secondary School

KTN-76 to KTN-81

E

36

2028

A2-2

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre[3]

KTN-82 to KTN-99

P

78.75 - 110.25

2023

A2-4

Nursery Classes and Kindergartens[4]

KTN-100 to KTN-107

H

68.85 - 97.2

2030

A2-5

Special Child Care Centre [4]

KTN-108 to KTN-115

R

68.85 - 97.2

2029

A2-7

Nursery Classes and Kindergartens; Neighbourhood Elderly Community Centre[3]

KTN-116 to KTN-128

P

78.75 - 110.25

2030

A2-9

Residential Uses

KTN-129 to KTN-144

R

47.25 - 63

2031

A3-1

Primary School

KTN-145 to KTN-149

E

36

2028

A3-2

Secondary School

KTN-150 to KTN-154

E

36

2028

A3-3

Nursery Classes and Kindergartens (3 nos);  Integrated Children and Youth Services Centre; Day Care Centre for the Elderly ; Supported Hostel for Ex-mentally Ill Persons , Half-way House and  Long Stay Care Home; Post Office[3][5]

KTN-155 to KTN-174

P

78.75 - 110.25

2030

A3-4

Primary School

KTN-175 to KTN-180

E

36

2028

A3-6

Residential Uses

KTN-181 to KTN-195

R

47.25 - 63

2031

B2-10

Commercial, Research & Development; Residential and Preservation of Home of Loving Faithfulness’s Building; Day Activity Centre, Hostel for Severely Mentally Handicapped, Integrated Vocational and Rehabilitation Service Centre, Hostel for Moderately Mentally Handicapped Persons:, Hostel for Severely Physically Handicapped Persons, Care and Attention Home for Severely Disable Persons

KTN-196 to KTN-203

CDA

45 - 90

2029

B2-12

Commercial, Research & Development

KTN-204 to KTN-210

OU(C,R&D)

18 - 45

2029

B2-2

Hospital, Polyclinic - Site Reservation: 4700 (sqm) and Clinic - Site Reservation: 2200 (sqm)

KTN-211 to KTN219

GIC

45

2029

B2-5

Primary School

KTN-220 to KTN-224

E

36

2022

B2-6

Secondary School

KTN-225 to KTN-230

E

36

2022

B2-7

Primary School

KTN-231 to KTN-232

E

36

2022

B2-8

Sports Centre , District Library, Integrated Children and Youth Services
Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre  and Social Security Field Unit

KTN-233 to KTN-237

GIC

45

2022

B3-12

Commercial, Research & Development

KTN-238 to KTN-247

OU(C,R&D)

18 - 45

2029

B3-16

Visitor Centre

KTN-248 to KTN-249

GIC

10

2020

B3-2

Post Office

KTN-250 to KTN-258

OU(C,R&D)

18 - 45

2029

B3-5

Commercial, Research & Development

KTN-259 to KTN-264

OU(C,R&D)

18 - 45

2029

B3-8

Hotel and Conference Facilities; Post Office

KTN-265 to KTN-270

OU(C,R&D)

18 - 45

2029

C1-11

Reprovision Site of Kwu Tung Vegetable Marketing and Credit Co-operative Society

KTN-271

GIC

-

2027

C1-9

Long Valley Core Area, Area for Wetland Enhancement Works and
Area for Facilities Supporting the Nature Park

KTN-272 to KTN287

GIC

-

2020

D1-11

Residential Uses

KTN-288 to KTN-301

R2

25.2 - 31.5

2031

D1-12

Potential Activity Centre

KTN-302 to KTN308

GIC

0

2023

D1-13

Potential Activity Centre

KTN-309 to KTN314

GIC

0

2023

D1-14

Government Reserve

KTN-315 to KTN-320

GIC

36

2028

D1-5

Village Resite

KTN-321 to KTN-326

VR

8.23

2024

D1-7

Residential Uses

KTN-327 to KTN-347

R2

66.15 - 78.75

2031

E1-2

Primary School

KTN-348 to KTN-352

E

36

2028

E1-3

District Headquarters and Divisional Police Station

KTN-353, KTN-359 to 361

GIC

56.7

2029

E1-3

Reprovisioning of Fan Garden Junior Police Officers' Police Married Quarters

KTN-354 to KTN-358

GIC

56.7

2022

E1-4

Secondary School

KTN-362 to KTN367

E

36

2028

E1-5

Standard Swimming Pool and Sports Centre

KTN-368 to KTN-376

GIC

22.5

2028

E1-6

Fire Station and Ambulance Depot

KTN-377 to KTN-382

GIC

40.5

2022

E1-7

Open Space, Fung Kong Shan and Cycle Park

KTN-383 to KTN-390

O

-

2027

F1-1

Sports Ground/Sports Complex[6]

KTN-391 to KTN-394

GIC

13.5

2028

F1-3

Reserve for Supporting Lok Ma Chau Loop Development[6]

KTN-395 to KTN407

OU(R&D)

45

2028

F1-4

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)[6]

KTN-408 to KTN-411

GIC

13.5

2020

PFS

Proposed houses at Zone A/NE -Temporary Structure/267

KTN-C1

R

9

2017

Notes:

[1]    Based on Revised RODP shown in Appendix 2.1.

[2]    R1c – Residential Zone 1 (with Commercial); R2 – Residential Zone 2; R3 – Residential Zone 3; E – Educational; CDA – Comprehensive Development Areas; PRH – Public Rental Housing; GIC – Government, Institution & Community, VR – Village Resite; OU (C, R &D) – Other Specified Uses (Commercial, Research & Development); OU (NP) – Other Specified Uses (Nature Park); OU (R &D) – Other Specified Uses (Research & Development); O – Open Space

[3]    Free standing non-domestic purpose-built buildings in PRH sites are for retail and carparking facilities (all carparks assumed to be underground) are assumed

[4]    Commercial podium development of R1c and CDA sites are assumed to be not more than 2 storeys.

[5]    The no. of flats includes that for reprovisioniing of Fan Garden Junior Police Officers’ Police Married Quarters as well as that for the District Headquarters Associated Married Staff Quarters.

[6]    As per the GFS Helicopter Landing Site Specification Guidelines, development of sites falling within the flight paths of the helipad at Lo Wu Fire Range will be subject to the GFS's (height restriction) requirement for safety (i.e. Section 5(d) of GFS Helicopter Landing Site Specification


 

Table 3.6 Representative planned ASRs within 500m assessment area and in the vicinity of FLN NDA[1]

 

Land Lot

Description

ASRID

Landuse

Proposed Building Height Above Ground (m)

Population Intake  Year

A1-8

Police Driving and Traffic Training Division

FLN-1 to FLN-14

GIC

31.5

2022

A1-11

Weapons Training Division

FLN-15 to FLN-22

GIC

22.5

2022

B1-7

Residential Buildings

FLN-23 to FLN-33

R2

31.5 – 47.25

2031

B1-8

Village Resite

FLN-34 to FLN-36

VR

8.23

2018

B1-9

Residential Buildings

FLN-37 to FLN-46

R3

25.2 - 37.8

2031

B2-4

Government Reserve

FLN-47 to FLN-50

GIC

22.5

2028

B2-6

Residential Buildings

FLN-51 to FLN-58

PRH

63 - 78.75

2030

B2-7

Residential Buildings, Nursery Classes and Kindergartens, Care and Attention Home for Severely Disable Persons [3]

FLN-59 to FLN-69

PRH, E, H, GIC

78.75 - 110.25

2030

B2-11

Residential Buildings

FLN-70 to FLN-77

PRH

63 - 78.75

2031

B2-12

Residential Buildings, Hostel for Severely Physically Handicapped Persons,  Day Care Centre for the Elderly, Post Office [3]

FLN-78 to FLN-88

PRH, H, GIC

78.75 - 110.25

2030

B3-2

Residential Buildings

FLN-89 to FLN-94

PRH

63 - 78.75

2031

B3-3

Residential Buildings, Hostel for Moderately Mentally Handicapped Persons [3]

FLN-95 to FLN-106

PRH, H, GIC

78.75 - 110.25

2030

B3-4

Primary School

FLN-107 to FLN-112

E

36

2028

B3-5

Primary School

FLN-113 to FLN-118

E

36

2028

B3-6

Residential and Commercial Buildings, Nursery Classes and Kindergarten [5]

FLN-119 to FLN-127

R2c, E

49.95 - 65.7

2031

B3-7

Residential Buildings

FLN-128 to FLN-135

R2

47.25 - 63

2031

B3-9

Residential Buildings

FLN-136 to FLN-143

R2

47.25 - 63

2031

B3-10

Secondary School

FLN-144 to FLN-150

E

36

2028

B3-12

Primary School

FLN-151 to FLN-155

E

36

2028

C2-5

Clinic

FLN-156 to FLN-159

H

22.5

2028

C2-6

Sports Centre (Leisure Centre), Integrated Children and Youth Service Centre, Special Child Care Centre, Early Education and Training Centre

FLN-160 to FLN-164

RC, GIC, E

22.5

2029

C2-7

Primary School

FLN-165 to FLN-170

E

36

2028

C2-8

Town Park

FLN-171 to FLN-181

RC

1.5

2027

C2-9

Secondary School

FLN-182 to FLN-187

E

36

2028

D1-6

Existing North District Temporary Wholesale Market for Agricultural Products

FLN-188 to FLN-191

GIC

22.5

2019

D2-2

Residential Buildings

FLN-192 to FLN-206

HOS

47.25 - 63

2031

D2-4

Residential Buildings

FLN-207 to FLN-218

R2

47.25 - 63

2031

D2-6

Residential Buildings

FLN-219 to FLN-225

PRH

63-78.75

2030

D2-9

Residential Buildings, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre,  Residential Home for the Elderly, Post Office [5]

FLN-226 to FLN-243

PRH, E, GIC, H

94.5 - 110.25

2023

D2-12

Residential Buildings

FLN-244 to FLN-254

R2

47.25 - 63

2024

D3-1a

Residential Buildings

FLN-255 to FLN-264

R1

78.75 - 94.5

2029

D3-1b

Residential Buildings

FLN-265 to FLN-274

HOS

66.15 - 94.5

2030

D3-1c

Residential and Commercial Buildings, Nursery Classes and Kindergartens

FLN-275 to FLN-285

R1c, E

68.85 - 97.2

2029

D3-3

Residential and Commercial Buildings [4]

FLN-286 to FLN-295

R1c

68.85 - 97.2

2031

D3-4

Residential and Commercial Buildings, Nursery Classes and Kindergartens [4]

FLN-296 to FLN-310

R1c, E

68.85 - 97.2

2031

D3-6

Residential and Commercial Buildings, Nursery Classes and Kindergartens [4]

FLN-311 to FLN-324

R1c, E

68.85 - 97.2

2029

D3-7

Residential and Commercial Buildings [4]

FLN-325 to FLN-338

R1c

68.85 - 97.2

2029

D3-8

Residential Buildings, Nursery Classes and Kindergartens, Integrated Vocational and Rehabilitation Service Centre

FLN-339 to FLN-349

PRH, E, GIC

78.75 - 94.5

2030

D3-11

Secondary School

FLN-350 to FLN-355

E

36

2023

D3-12

Primary School

FLN-356 to FLN-362

E

36

2023

Notes:             

[1]    Based on Revised RODP shown in Appendix 2.1.

[2]   R1c – Residential Zone 1 (with Commercial); R2c – Residential Zone 2 (with Commercial); R2 – Residential Zone 2; R3 – Residential Zone 3; E – Educational; PRH – Public Rental Housing; GIC – Government, Institution & Community; VR – Village Resite; RC – Recreational; HOS – Home Ownership Scheme Residential Buildings; H – Hospital/ Clinic/ Home for the aged;

[3]    Free standing non-domestic purpose-built buildings in PRH sites are for retail and carparking facilities (all carparks assumed to be underground) and assumed to be not more than 3 stories.

[4]    Commercial podium developments of R1c and R2c sites are assumed to be not more than 2 stories.

[5]    Due to site constraints, free standing non-domestic purpose-built buildings in this PRH site are assumed to be not more than 5 stories.

 


 


3.5          Assessment Methodology

3.5.1     Construction Phase

The prediction of dust emissions is based on the typical values and emission factors obtained from United States Environmental Protection Agency (USEPA) Compilation of Air Pollution Emission Factors, AP-42, 5th Edition.

According to the implementation programme, the construction of KTN and FLN NDAs will be divided into six development packages. Each of these packages would be implemented according to the development programme and the associated dusty construction activities for each package will be assessed.

Since the air quality impact due to different construction packages will vary, the assessment identifies the worst case scenario over the entire construction phase to address the specific impacts arising from each of different work areas.

Construction dust assessment for short-term impact (i.e. 1-hour and 24-hour average) will be undertaken by a 3-Tier approach. Tier 1 screening assessment is a theoretical worst case scenario evaluation to identify hot spot areas of construction air quality impact by assuming 100% active construction area for all worksites. The identified hot spot areas will be further assessed by a more focused Tier 2 assessment to predict a more realistic worst case impact by altering the active construction areas to 15% and locating them nearest to the ASRs. Specific hot spot areas will be assessed by a Tier 3 assessment to predict a detailed impact by altering the active construction areas to the actual active area and locating them nearest to the ASRs. Long-term impact (i.e. annual average) will be assessed with 6% active construction area for all work sites. Details discussions are given in the following subsections.

Odour impact due to the emission of existing sewage treating facilities at the Shek Wu Hui Sewage Treatment Works during the expansion works will be also assessed.

3.5.1.1    Assessment Year

The construction programme given in Appendix 3.1 and implementation programme given in Appendix 2.1 have been reviewed to identify the assessment years for inclusion in the assessment.

According to the implementation programme, the Project will be implemented under six development packages.

Each development package comprises a number of works contracts (WC) and are works area of each WC will be divided into sub-areas (up to 6 sub-areas). Construction works at each of these sub-areas will be carried out in sequence based on the estimation as shown in Appendix 3.1.

Within the boundary of each WC, construction works will be carried out and dust emissions will arise from dusty construction activities such as site clearance, ground excavation etc. According to Table 3.7 and the extent of different works contracts given in Appendix 3.3, major site formation for different works contracts will be carried out after the first population intake, i.e. Year 2025 for both KTN NDA and FLN NDA. Hence, Year 2025 is considered as the worst-case scenario for both KTN NDA and FLN NDA.

Table 3.7 – Dust emission sources for dust impact assessment [1]

Year when Major Site Formation Works is On-going

Development Package

Works Contract/ Dust Emission Sources

Designated Project

Year 2018

Advance Works Package – Infrastructure and Development at KTN and FLN

WC03, WC04, WC07, WC09, WC19, WC33

DP3, DP4, DP5, DP12

Package 1 – First Stage of Infrastructure and Development at KTN and FLN

WC21

 

Package 2 – Infrastructure and development at KTN (South)

WC31

Year 2021

Advance Works Package – Infrastructure and Development at KTN and FLN

WC03, WC04, WC06, WC07, WC28, WC32, WC33

DP5, DP10, DP13

Package 2 – Infrastructure and development at KTN (South)

WC29

Package 3 - Infrastructure and Development at KTN (North)

WC31

Package 4 – Remaining Infrastructure and Development at FLN (East)

WC13

Year 2025

Package 2 – Infrastructure and development at KTN (South)

WC10, WC11, WC26

DP1, DP3, DP4, DP8, DP9

Package 3 - Infrastructure and Development at KTN (North)

WC12, WC21,

Package 4 – Remaining Infrastructure and Development at FLN (East)

WC14, WC15

Package 5 – Remaining Infrastructure and Development at FLN (West)

WC22

Year 2028

Package 2 – Infrastructure and development at KTN (South)

WC10, WC11, WC26

DP1, DP4, DP5, DP8, DP9, DP13

Package 3 - Infrastructure and Development at KTN (North)

WC12

Package 4 – Remaining Infrastructure and Development at FLN (East)

WC14

 

Package 5 – Remaining Infrastructure and Development at FLN (West)

WC22

 

Note

[1] Based on Implementation Programme shown in Appendix 2.1.

As certain WCs are scheduled to commence and finish before or after the worst case assessment year, two additional assessment years for both KTN and FLN (as shown in Table 3.8) have been adopted. Moreover, to ensure all the designated projects in FLN have been covered by the assessment, 4 additional WC/ WC sub-areas i.e. WC08 and sub-areas b/d/e of WC14 (as shown in Table 3.9) have also been included.

Table 3.8 – Summary of additional assessment year

Name of NDA

Additional Assessment Year

KTN

2018, 2028

FLN

2018, 2021

 

Table 3.9 – Additional WC included in the assessment for FLN NDA

WC

Designated Projects

Proposed Schedule for the Site Formation Works

Assessment Year to be included

WC08

DP7 & DP11

2022 – 2024

2021

WC14b

DP8

2027 – 2029

2025

WC14d

DP9, DP13

2026 – 2028

2025

WC14e

DP9

2028 – 2029

2025

3.5.1.2    Construction Vehicle Access

Dust emissions from construction vehicle movement within the work contract sites and the temporary construction access routes have been taken into account. An estimated average of 66 trucks/hour would travel into and out of the work contract sites through the construction access routes during working hours.

Effective from September 2009, all grab-mounted dump trucks travelling into and out construction sites should be equipped with suitable covers before the trucks leaving the site. It is expected that dust emission from dump trucks travelling on the temporary construction access road outside the site would be minimal. Construction dust emissions from vehicle movement inside the site are included in the assessment.

3.5.1.3    Operating Hours

Subject to the construction work being required and permitted at night-time and during Sundays or holiday, normal construction working periods of 26 days a month and 12 hours a day are assumed.

3.5.1.4    Tier 1 Screening Assessment

In terms of the construction programme, it should be noted that the sequencing of works activities within individual work sites or areas will be determined by the Contractor and is not known at this stage.  However, due to the size of the work sites and the need for orderly sequencing of construction activities, active construction activities will occur in different locations of the work site at different time periods. Therefore, it is not possible to pinpoint the exact locations of individual dust emission sources over the entire work site in any short-term period (i.e. 1-hour and 24-hour).

Base on previous experience, there would be no more than 15% of active work area in each work site during any short period of time. Hence, the chance of having all 15% active works areas is unlikely within an individual work site.

Tier 1 screening assessment is to establish a theoretical worst case scenario for identifying hot spot areas with potential short term 1-hour and 24-hour impacts on ASRs. The basis of the Tier 1 screening assessment for short term impact evaluation has assumed a 100% active work area for all worksites. Areas within the criteria contour (i.e. exceeding the criteria) are considered hot spot locations for which a focused Tier 2 assessment will be conducted.

3.5.1.5    Tier 2 Assessment

In Tier 2 assessment, each hot spot area is assumed with 15% active works areas occurring nearest to the potentially worst affected ASRs. Although results of Tier 2 assessment are still conservative based on previous experience, areas within the criteria contour (i.e. exceeding the criteria) are considered hot spot locations for which a focused Tier 3 assessment will be conducted.

3.5.1.6    Tier 3 Assessment

In Tier 3 assessment, the specific hot spot area is assumed with the actual active works areas occurring nearest to the potentially worst affected ASRs. Results of the Tier 3 assessment serve as a representation of the detailed construction dust impact prediction for the study.

3.5.1.7    Long-term Annual Predictions

Dust modelling assessment for long term annual predictions assumes that the work activities would evenly distribute across the whole area of each site over the year with an effective 6% active work area. In the modelling analysis, the dust emission rates are proportionally reduced to produce this effect in the assessment. Appendix 3.2 present the justifications for the percentage of active areas and tentative construction programme respectively.

3.5.1.8    Dust Dispersion Modelling

Dust impact assessment was undertaken using the Fugitive Dust Model (FDM) developed by USEPA and approved by EPD. It is a Gaussian plume model for computing air dispersion due to fugitive dust emission. Modelling parameters including dust emission factors, particle size distributions, surface roughness, etc can be referred to in EPD guideline entitled “Guideline on Choice of Models and Model parameters in Air Quality Assessment” and the USEPA AP-42.

The density of dust was assumed to be 2.5g/m3. The 5-year mean of the annual averaged TSP concentration will be taken as the background concentration. As mentioned in Section 3.3.2, the TSP background concentration of 73.1 µg/m3 is adopted for the fugitive dust modelling. A surface roughness of 100 cm is assumed in the model to represent the terrain.

During daytime working hours (7am to 7pm), it is assumed that dust emissions would be generated from all dust generating activities and site erosion. During night-time non-working hours (7pm to 7am the next day), Sunday and public holidays, dust emission would be from site erosion only as there would not be normally construction activities during these hours.

The worst-case 1-hour, 24-hour and annual average TSP concentrations were predicted with Year 2011 meteorological data from Ta Kwu Ling Weather Station and mixing height from King’s Park Station.

Fugitive dust impacts have been modeled for ASR heights at 1.5m, 5m and 10m above ground. Since all the dust generating sources associated with the Project are at ground level only, these assessment levels would therefore represent the worst-case scenario. Both the unmitigated and mitigated scenarios for the project are presented. Key modelling parameters are summarized in Table 3.10.

 

Table 3.10 - Modelling parameters for FDM

Parameters

Input

Remark

Particle size distribution

1.25um = 7%

3.75um = 20%

7.5um = 20%

12.5um = 18%

22.5um = 35%

Reference from S13.2.4.3 of USEPA AP-42

Background Concentration

Recent 5-year average value of monitoring stations of rural and new development category (2007 -2011)

Shatin, Tai Po and Yuen Long included as no data available from Tseung Kwan O and Hong Kong South and Monitoring Stations (73.1 μg/m3)

Modeling mode

Flatted terrain

-

Meteorological data

Data recorded in 2011 at Ta Kwu Ling (TKL) Meteorological Station

-

Anemometer Height

13m for TKL

-

Surface Roughness

100cm

-

Emission period

General construction activities during daytime working hours (7 am to 7 pm);

Wind erosion during both day-time (7am to 7pm) and night-time (7pm to 7am of the next day)

-

ASR calculating levels

1.5m, 5m and 10m

-

3.5.1.9    Dust Emission Factor and Assumptions

Fugitive dust impact assessment was carried out based on typical values and emission factors from United States Environmental Protection Agency (USEPA) Compilation of Air Pollution Emission Factors (AP-42), 5th Edition. Calculation of dust emission factors is given in Appendix 3.3.  References of the calculations of dust emission factors for different dust generating activities are listed in Table 3.11. Detailed descriptions are also discussed in the following sections.

Table 3.11 - References of dust emission factors for different activities

Activities

Operating Sites

Equations and Assumptions

Reference

Heavy construction activities including land clearance, ground excavation, cut and fill operations, construction of the facilities, haul road, etc

All construction and excavation sites

E    = 1.2 tons/acre/month of activity or;

      = 2.69Mg/hectare/month of activity

 

USEPA AP42, S.13.2.3.3

Wind Erosion

 

All construction sites, any stockpile areas, barging area (all open sites)

E = 0.85 Mg/hectare/yr (24 hour emission)

USEPA AP42, S.11.9, Table 11.9.4

3.5.2     Operational Phase

The prediction of operational air quality impact covers chimney emission from existing industrial area, road traffic emission from associated road network and odour emission due to the operation of sewage treating facilities at the Shek Wu Hui Sewage Treatment Works and Sheung Sui Slaughter House.

3.5.2.1    Determination of Assessment Year

According to Clause 3.4.4.3 (v) (b) of the EIA Study Brief for this project, the air pollution impacts of future road traffic should be calculated based on the highest emission strength from vehicles within the next 15 years after commencement of operation of the proposed road.

Based on the current implementation schedule, for KTN NDA, the planned roads will be implemented in 3 stages, with completion of the 1st stage for operation in 2021, the 2nd stage for operation in 2028, and the 3rd stage for operation in 2029. For FLN NDA, the planned roads will be implemented in 4 stages, with completion of the 1st stage for operation in 2022, the 2nd stage for operation in 2023, the 3rd stage for operation in 2028, and the 4th stage for operation in 2029. Sensitivity test has been conducted based on these operational years by using the Emfac-HK model (v2.5, dated 3 January 2013) to determine the worst assessment years given the combination of vehicular emission factors and the projected traffic flow. Appendix 3.4  presents the detailed methodology.

3.5.2.2    Vehicular Emission from Open Roads

NO2 and RSP generated from the additional open-road networks associated with the proposed NDAs in the study area are the major air pollutants due to vehicular emissions and have been adopted for assessment of their potential air quality impacts. Additional traffic flow would also be induced on the existing roads and therefore a corresponding increase in vehicular emissions is anticipated. EmFAC-HK was used to calculate the vehicular tailpipe emission in lieu of the traditional fleet average emission factors. The road grouping for this assessment is shown in Annex A of Appendix 3.4.

Preliminary traffic flows in each assessment year presented in Annex E of Appendix 3.4 have been reviewed and highest traffic flow (either PM Peak or AM peak) for each assessment year has been selected to represent the worst case. Appendix 3.4 presents the key assumptions for the EmFAC-HK modelling. A 24-hour daily profile in terms of total traffic flow has been assumed for all vehicle classes.  Appendix 3.5 presents the detailed estimation of the vehicular emission factors from open roads for NO2 and RSP within the assessment area. Assessment points are shown in Table 3.3 and Table 3.4. 

The air dispersion model, CALINE4 developed by the California Department of Transport and approved by USEPA was used to assess vehicular emission impacts from the existing and planned road network. In view of the limitation of the model, elevated roads higher than 10m were set to the maximum height of 10m to represent the condition, albeit in a more conservative manner.

In determining the surface roughness, due consideration was given to the number of existing mid-rise and high-rise buildings sited within 1km study area. A surface roughness of 100cm was therefore considered appropriate.  Hourly meteorological data, including wind direction, wind speed, temperature and stability, collected from the nearest weather station, the Ta Kwu Ling meteorological station in Year 2011 were adopted in this assessment.  The mixing height data from the King’s Park Station in Year 2011 were adopted.

For background concentrations, they were made to the 5 years mean of annual-averaged NO2 and RSP concentration at Shatin, Tai Po, Tseung Kwan O, Hong Kong South and Yuen Long Monitoring Stations from 2007 to 2011. It was assumed that 20% of NOx would be converted to NO2, in accordance with the EPD’s “Guidelines on Choice of Models and Model Parameters”.

In addition, the effect of existing and proposed noise barrier on the dispersion of vehicular emission has been taken into account in this study.

3.5.2.3    Portal Emission

During the operation of KTN NDA and FLN NDA, a short portion of Castle Peak Road will go beneath the slip roads and another short portion of Fanling Bypass will go beneath the Lung Yeuk Tau Interchange in the form of underpass. Some full-enlcosures are also proposed in both KTN NDA and FLN NDA. In respect of these, the ISCST3 Model was adopted to estimate the portal emission from the underpasses and proposed full-enclosures in accordance with the Permanent International Association of Road Congress Report (PIARC, 1991), where it is assumed that  pollutants will be ejected from the portal as a portal jet such that 2/3s of the total emission will be dispersed within first 50m, and the remaining 1/3 of the total emission within the next 50m. Portal emission factors are summarized in Appendix 3.5.

3.5.2.4    In-tunnel Air Quality

In accordance with the “Practice Note on Control of Air Pollution in Vehicle Tunnels”, the air quality inside the tunnel should achieve the EPD recommended standard of 1ppm NO2 concentration. Given that the length of underpass is less than 200m, mechanical ventilation system will not be required. The in-tunnel air quality assessment for each underpass section and each proposed full-enclosure is given in Appendix 3.6. Results indicated that the EPD recommended standard will be achieved.

3.5.2.5    Chimney Emission from Industrial Areas

Gaseous emissions from the identified existing industrial chimneys identified have been assessed by ISCST3 model. The modelling parameters are listed in Table 3.12. The assumptions, chimney configuration and emission rates presented in the TP13 have been adopted in this assessment. In addition, the chimneys presented in the approved EIA Study “Provision of Cremators at Wo Hop Shek Crematorium” (EIA-146/2008) have been adopted. For the chimneys newly identified during the site survey in 2012, an average fuel usage of 200 L/hr is assumed for the calculation of emissions, while the heights and internal diameters of the chimneys are based on observation.

Table 3.12 – Modelling parameters for ISCST3

Parameters

Input

Background Concentration

Annual Averaged value recorded from Tai Po, Yuen Long, and Sha Tin Monitoring Stations (Year 2007 – Year 2011)

Modeling mode

Urban without terrain effect

Meteorological data

Ta Kwu Ling weather station in Year 2011; in accordance with EPD Guidelines on Choice of Models and Model Parameters, the validity is over 90%

Loading Factor

(for existing industrial source only)

Daytime (0800-2000) : 41%

Night-time (2000-0800) : 23%

Moreover, for the chimney emission from the North District Hospital (NDH), it is noted from the fuel consumption data provided by the hospital (NDH) that about 1,250,000 unit of town gas and 3190 litres of ultra low sulphur diesel oil were used in Year 2009-10. Chimney emissions from these sources were therefore estimated based on the method adopted in approved EIA for Provision of a Poultry Slaughtering Centre in Sheung Shui (AEIAR-142/2009) or emission factor from AP42, USEPA. Table 3.13 summarizes the emission factors. Appendix 3.7 presents the detailed calculations of chimney emission.

Table 3.13 – References of chimney emission factors

Fuel Type

Pollutant

Emission Factor

Assumptions

Reference

Fuel Oil

NOx

E = 20 lb/103 gal

-

USEPA AP42, S.1.3, Table 1.3-1

SO2

E = 142S lb/103 gal

 

S = 0.5% (for general fuel)

S = 0.005% (for ultra low sulphur diesel)

RSP

E = 2 lb/103 gal

-

Towngas

 

NOx

E = 220 mg/kWh

-

EIA for Provision of a Poultry Slaughtering Centre in Sheung Shui

A hospital and polyclinics are also proposed in the KTN NDA, which are considered as a potential emission source. However, during this Final Stage EIA, there is no available information on the chimney design and the pollutant emission rate. The chimney emission is therefore estimated based on pro-rata of the existing information of the NDH.

According to information provided by from Town Gas and Hospital Authority, the fuels are used by Bunsen burners, cooking range, steam boilers and emergency generator.  With such application, it is understood that the total chimney emission from a hospital should be proportional to the total number of patient accommodated in the hospital (i.e. number of bed). According to the latest Department of Health Annual Report 2009/10, it is noted that there are a total of 607 beds available in the NDH, while the number of beds in the proposed hospital and polyclinics is estimated to be about 860. Therefore, in order to estimate the emission from the proposed hospital and polyclinics, a correction factor of 1.42 has been multiplied to the chimney emission from NDH.

Expansion of Shek Wu Hui Sewage Treatment Works is proposed in the FLN NDA. According to the outline design report of “Tender for the Provision of Services for Shek Wu Hui Sewage Treatment  Works – Further Expansion – Feasibility Study” from EPD, two layout options have been developed. As option 2 is more preferable from an operations and maintenance perspective (see section 3.6.2.3), it is considered as a preferred option and has therefore been adopted by this study for further assessment.

The biogas produced from the sludge digestion process will be collected and stored in the gas holders. After pre-treatment, desulphurization and moisture removal, the biogas will be utilized by a combined heat and power (CHP) generator to produce hot water and electricity, and the residual will be flared in a biogas burner. The CHP and biogas burner are considered as potential emission sources within the assessment area of this study. Appendix 3.7 presents the detailed calculations of biogas production based on the latest design of sewage treatment capacity (190000 m3/day) after the expansion, and the emission rates of CHP and biogas burner.

3.5.2.6    Odour Emission

Dispersion Model and Modelling Parameters

Odour propagation was modelled by AUSPLUME model, which is based on the Gaussian dispersion equation. The use of AUSPLUME has been approved by EPD. Other modelling parameters were determined according to EPD’s “Guidelines on Choice of Models and Model Parameters”. 

Hourly meteorological data, including wind speed, wind direction, air temperature, and Pasquill stability class as recorded at the Ta Kwu Ling weather station in 2011, and the daily mixing height data measured at King’s Park Station were obtained from the Hong Kong Observatory for modelling the 1-hour average odour concentrations.

As required in the TM-EIAO, the odour criterion is defined as 5 OU units based on an averaging time of 5 seconds. Hence, it is required to convert the predicted odour concentration in 1-hour averaging time from the AUSPLUME model to 5-second average. Reference has been made to the peak-to-mean ratio stated in the “Approved Methods for Modelling and Assessment of Air Pollutants in New South Wales” published by the Department of Environment and Conservation, New South Wales, Australia (NSW Approved Method). In accordance with the NSW Approved Method, the conversion factors for converting 1-hour average to 1-second average concentration are adopted directly to convert the 1-hour concentration predicted by the AUSPLUME model to 5-second concentration as a conservative approach. The conversion factors for different types of source and stability classes are listed in Table 3.14 below.

Table 3.14 – Conversion factors for 1-hour to 5-second averaging time

Pasquill Stability Class

Point Sources

Area Sources

Volume Sources

A

2.3

2.5

2.3

B

2.3

2.5

2.3

C

2.3

2.5

2.3

D

2.3

2.5

2.3

E

2.3

2.3

2.3

F

2.3

2.3

2.3

The overall modelling parameters are summarised in Table 3.15 for ease of reference.

Table 3.15 – Modelling parameters for AUSPLUME

Parameters

Input

Background Concentration

No

Modelling Mode

Flat terrain

Surface Roughness

100cm

Meteorological data

Ta Kwu Ling and King’s Park weather station in Year 2011

Anemometer Height

13m

Emission period

24-hour

Odour Emission Rates

Proposed Sewage Treatment Work Expansion in FLN NDA

On-site odour measurement was conducted in September 2011 of different components inside the existing SWHSTW. Since the treatment process of the proposed STW Expansion is in general similar to that of the existing SWHSTW, the odour emission will be similar. As such, the recent odour emission measurement results for existing SWHSTW have been adopted as the basis to estimate the odour emission rates of sources associated with the proposed STW Expansion. The odour measurement was conducted by the Hong Kong Polytechnic University during the hot season to represent the worst-case scenario. Table 3.16 summarises the measured odour emission rates of each source in existing SWHSTW. Table 3.17 summarises the odour emission rate adopted at each source in the proposed STW Expansion. Detailed calculation is presented in Appendix 3.8.

Table 3.16 – Summary of measured odour emission rate in existing SWHSTW

Location

Maximum Emission Rate (OU/m2/s)

Inlet pumping station

3.26

Fine Screening (at screen debris chamber)

3.51

Grit Channels

1.84

Degritting

1.10

Primary Sedimentation Tank (Weir Zone)

1.54

Primary Sedimentation Tank (Quiescent Zone)

4.03

Bioreactor

1.65

Feed Channel to FST

0.02

Final Sedimentation Tank

0.02

Sludge Holding Tank

0.43

Sludge Dewatering House

0.06

Thickener

3.98

Sludge Conditioning Tank

0.20

Table 3.17 – Odour emission rates for the proposed STW expansion

Odour Source

Corresponding Odour Source in SWHSTW

Odour Emission Rate (OU/m2/s)

Inlet Works

Inlet pumping station

3.26

Primary Sedi

Primary Sedimentation Tank (Quiescent Zone)

4.03

MBR Pretreatment Screen

Primary Sedimentation Tank (Quiescent Zone)

4.03

Bioreactor

Bioreactor

1.65

Membrane Tank

Final Sedimentation Tank

0.02

Primary Sludge Thickener

Thickener

3.98

SAS Consolidation House

Thickener

3.98

Sludge Holding Tank

Sludge Holding Tank

0.43

Dewatering House

Sludge Dewatering House

0.06

All measured odour emission rates adopted for the proposed STW expansion were adjusted to the local ambient temperature. According to the equation from the approved EIA for Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008) below:

G = M[BOD5]1.07T-20

where    G = sulphide flux from wall slimes, g/m2h

               [BOD5] = 5-day biochemical oxygen demand

               T = temperature, oC

               M = coefficient, m/h

For example, maximum hourly temperature at Ta Kwu Ling during Year 2011 was 36 oC and the odour emission was measured at temperature ~32-34 oC. Based on the equation above, the odour emission rate would be increased by 14%-31%.

Existing Sheung Shui Slaughter House

Reference has been made to the odour emission inventory adopted in the approved EIA study “Supplementary EIA Study for Sheung Shui Slaughter House” (EIA-069/BC). Table 3.18 summarises the odour emission rate of each source under mitigated condition. Appendix 3.8 presents the details of odour emissions.

Table 3.18 – Odour emission rates for existing Sheung Shui Slaughter House

Source Type

Odour Source

Mitigated Odour Emission Rate (OU/s)

Remarks

Lairages

Pig lairage

597.25

Odour emission from these sources are centralized and released via 1 exhaust.

Manure collection rooms

Slaughter Block Room 1

Blood handling room

223.70

Odour emission from these sources are centralized and released via 1 exhaust.

Isolation lairage

Slaughter Block Room 2

Manure pump rooms

30.63

Odour emissions from these sources are centralized and released via 1 exhaust.

Pig bristle chute room

By-product collection room & unloading bay

By-product Plant

Wastewater treatment plant

1980.70

Odour emission from these sources are centralized and released via 1 exhaust.

By-product room

Wastewater Treatment Plant

-

290.00

-

Livestock Transit Pens

-

13

10 sources in total

Livestock Train Unloading Area

-

7.8

20 sources in total

Livestock Truck Unloading Area

-

14.69

-


 

3.6          Identification of Environmental Impact

3.6.1     Construction Phase

3.6.1.1   Construction Dust

The construction programme for the project is listed in Appendix 3.1. It is anticipated that the major construction works associated with the development of the NDAs will be site formation and construction of the following infrastructure:

KTN NDA

·               San Tin Highway / Fanling Highway Kwu Tung Section Widening (between San Tin Interchange and Po Shek Wu Interchange) (Major Improvement); (DP1)

·               Castle Peak Road Diversion (Major Improvement) (DP2)

·               KTN NDA Road P1 and P2 (New Road), and associated new Kwu Tung Interchange (New Road) and Pak Shek Au Interchange Improvement (Major Improvement) (DP 3)

·               KTN NDA Road D1 to D5 (New Road) (DP 4)

·               New Sewage Pumping Stations (SPS) in KTN (DP5)

·               Utilization of Treated Sewage Effluent from SWHSTW (DP 7)

 

FLN NDA

·               Utilization of Treated Sewage Effluent from SWHSTW (DP 7)

·               Po Shek Wu Interchange Improvement (Major Improvement) (DP 8)

·               Fanling Bypass Western Section (New Road) (DP 9)

·               Fanling Bypass Eastern Section (New Road) (DP10)

·               Shek Wu Hui Sewage Treatmen Works - Further Expansion at FLN NDA (DP 11)

·               Reprovision of temporary wholesale market in FLN NDA (DP 12)

·               New Sewage Pumping Stations (SPS) in FLN NDA (DP13)

Potential dust impact from other construction activities such as the utilities works, building and landscape works within the two NDAs is considered to be minor. Locations of the dust emission sources mentioned above for different works contracts are shown in Appendix 3.3.

According to the best available information at the time of this study, the only concurrent projects activities for cumulative air quality assessment are the site formation from the construction work on the Lok Ma Chau Loop during Year 2025. Hence, these concurrent construction activities are included in the construction impact assessment.

3.6.2     Operational Phase

Operational air quality impact assessments have been carried out based on conservative assumptions of the following projects and their cumulative impacts:

KTN NDA

·         San Tin Highway / Fanling Highway Kwu Tung Section Widening (between San Tin Interchange and Po Shek Wu Interchange) (Major Improvement) (DP1)

·         Castle Peak Road Diversion (Major Improvement) (DP2)

·         KTN NDA Road P1 and P2 (New Road), and associated new Kwu Tung Interchange (New Road) and Pak Shek Au Interchange Improvement  (Major Improvement) (DP 3)

·         KTN NDA Road D1 to D5 (New Road) (DP 4)

·         New Sewage Pumping Stations (SPS) in KTN (DP5)

FLN NDA

·         Utilization of Treated Sewage Effluent from Shek Wu Hui Sewage Treatment Works (SWHSTW) (DP 7)

·         Po Shek Wu Interchange Improvement (Major Improvement) (DP 8)

·         Fanling Bypass Western Section (New Road) (DP 9)

·         Fanling Bypass Eastern Section (New Road) (DP10)

·         Shek Wu Hui Sewage Treatment Works - Further Expansion at FLN NDA (DP 11)

·         Reprovision of temporary wholesale market in FLN NDA (DP 12)

·         New Sewage Pumping Stations (SPS) in FLN NDA (DP13)

3.6.2.1    Industrial Emission

Existing Industrial Emission

The key environmental pollutants due to industrial chimneys (employing diesel) include nitrogen dioxide (NO2), sulphur dioxide (SO2) and respirable suspended particulates (RSP).

As previously investigated in the “Technical Paper 13 – Planning and Development Study on North East New Territories” (TP13), a number of chimneys were identified in On Lok Tsuen industrial area, located at the junction of Lok Yip Street and Sha Tau Kok Road at Fanling. Other than On Lok Tsuen, there are other industrial chimneys scattered in the area adjacent to KTN NDA and FLN NDA.

Subsequent site surveys and another reconnaissance survey were conducted in 2008 and 2012 respectively to verify the chimneys identified in TP13. The more recent survey revealed that some of these chimneys have been demolished or relocated. Industrial emissions from these chimneys are therefore updated in the assessment accordingly. Site surveys have also identified some chimneys, which were not mentioned in TP13, for the assessment. A total of 14 existing chimneys have been identified within the Study Area.

In addition, with reference to the approved EIA Study “Provision of Cremators at Wo Hop Shek Crematorium” (EIA-146/2008), a total number of 9 chimneys would be installed at the Wo Hop Shek Crematorium, which is located at about 1800m to the South of FLN NDA. These chimneys have been included in this assessment to account for the cumulative impact. The emission of the chimneys has been updated according to the corresponding specified process license.

1.    Emission inventory of industrial chimneys are presented in Appendix 3.7 and their locations are illustrated in Figure 3.7.

Chimney Emission from the North District Hospital (NDH)

Two chimneys located at the NDH are identified within 500m study area from the boundary of NDAs. The latest chimney details as well as fuel consumption data have been obtained from the NDH in 2010, as given in Appendix 3.7, and the information has been included in the assessment to account for the cumulative impact. Figure 3.7 shows the locations of industrial chimneys adopted in the assessment.

Industrial Emission associated with the NDAs

Based on the latest development plan, KTN NDA and FLN NDA will comprise mainly residential developments with associated employment and community facilities. Chimney emissions have not been identified for the existing rural industrial and open storage sites in NDAs during site survey. It is expected that the operational modes of these relocated industrial premises will be similar to previous industries. Hence, chimney emissions from these industrials are therefore not expected.

A hospital & polyclinics is also proposed in the KTN NDA (Site B2-2), which is considered as a potential emission source. The associated chimney emission has been included in the assessment.

Expansion of Shek Wu Hui Sewage Treatment Works is proposed in the FLN NDA (Site A2-3). Emissions from the CHP and biogas burner are considered as potential emission sources. On comparing with the existing emission, the future emission is anticipated to be increased. The associated chimney emissions have been included in the assessment.

Table 3.19 summarises the air pollution sources within each NDA. Figure 3.8 and Figure 3.9 illustrate the locations of these potential air pollution sources. Emission inventory of air pollutants sources is shown in Appendix 3.7.

Table 3.19 – Industrial emission sources in each NDA [1]

Land lot

Landuse [2]

Emission Type

Description

KTN NDA

B2-2

G

Industrial

Hospital, polyclinics and clinic

FLN NDA

A2-3

OU(STW)

Industrial

Sewage treatment works

Notes:       

[1]  Based on Revised RODP shown in Appendix 2.1

[2]  G - Government; OU(STW) – Other specific uses (sewage treatment works)

3.6.2.2    Vehicular Emission

During the operational phase of the Project, major sources of vehicular emission for each NDA include:

KTN NDA

·               Vehicular emission from proposed road networks within 500m from KTN NDA boundary.

·               Vehicular emission from existing road networks within 500m from KTN NDA boundary.

·               Vehicular emission from San Tin Highway / Fanling Highway Kwu Tung Section Widening (between San Tin Interchange and Po Shek Wu Interchange) (Major Improvement) (DP1)

·               Vehicular emission from Castle Peak Road Diversion (Major Improvement) (DP2)

·               Vehicular emission from KTN NDA Road P1 and P2 (New Road), and associated new Kwu Tung Interchange (New Road) and Pak Shek Au Interchange Improvement  (Major Improvement) (DP 3)

·               Vehicular emission from KTN NDA Road D1 to D5 (New Road) (DP 4)

FLN NDA

·               Vehicular emission from proposed road networks within 500m from FLN NDA boundary.

·               Vehicular emission from existing road networks within 500m from FLN NDA boundary.

·               Vehicular emission from Po Shek Wu Interchange Improvement (Major Improvement) (DP 8)

·               Vehicular emission from Fanling Bypass Western Section (New Road) (DP 9)

·               Vehicular emission from Fanling Bypass Eastern Section (New Road) (DP10)

Vehicular tailpipe emissions from open roads are calculated based on the EmFAC-HK model. The latest model version EmFAC-HK v2.5 has been employed in this assessment. Traffic data were prepared by traffic engineer and have been separately submitted to the Transport Department (TD) for endorsement. No adverse comment is raised by TD (see Appendix 3.4).   Appendix 3.4 presents the methodology and assumptions adopted in estimating the vehicular emission factors. The results have concluded that Year 2021 is the worst assessment year for KTN NDA and Year 2022 for FLN NDA. Table 3.20 and Table 3.21 below summarize the total daily emissions within each NDA for each of selected assessment years.

 

Table 3.20 – Summary of total daily air pollutant emissions for KTN NDA

Year of Assessment

Total Daily NOx Emission(kg/day)

Total Daily RSP Emission

(kg/day)

Remark

2021

492

28

Commissioning year for 1st Stage  road network

2025

350

24

Interim year between Year 2021 and Year 2028

2028

271

21

Commissioning year for 2nd Stage road network

2029

250

20

Commissioning year for 3rd Stage road network

2044

187

16

15 years after commencement of operation of all proposed roads


Table 3.21 – Summary of total daily air pollutant emissions for FLN NDA

Year of Assessment

Total Daily NOx Emission

(kg/day)

Total Daily RSP Emission

(kg/day)

Remark

2022

618

33

Commissioning year for 1st Stage  road network

2023

571

32

Commissioning year for 2nd Stage road network

2026

434

28

Interim year between Year 2023 and Year 2028

2028

355

25

Commissioning year for 3rd Stage road network

2029

328

24

Commissioning year for 4th  Stage  road network

2044

233

19

15 years after commencement of  operation of all proposed roads

According to the latest development plan, for KTN NDA, the planned roads will be implemented in 3 stages, with completion of the 1st stage for operation in 2021, the 2nd stage for operation in 2028, and the 3rd stage for operation in 2029. Emissions for Year 2021, Year 2025, Year 2028, Year 2039 and Year 2044 were determined. Year 2021 is taken as the assessment year as vehicular emission within the KTN NDA will be the highest when compared with the other four years. As Year 2029 is the year with all roads opened, this gives the 2nd highest emission, and has also been assessed to predict the air quality impact from the entire open-road network.

For FLN NDA, the planned roads will be implemented in 4 stages, with completion of the 1st stage for operation in 2022, the 2nd stage for operation in 2023, the 3rd stage for operation in 2028, and the 4th stage for operation in 2029. Emissions for Year 2022, Year 2023, Year 2026, Year 2028, Year 2039 and Year 2044 were determined. Year 2022 is taken as the assessment year as it generates the highest vehicular emission within the FLN NDA when compared with the other five years. As Year 2029 is the year with all roads opened, this gives the 2nd highest emission, and has also been assessed to predict the air quality impact from the entire open-road network. 

3.6.2.3    Odour Emission

Existing Odour Sources

The existing odour sources adjacent to the KTN and FLN NDAs may include the Sheung Shui Slaughter House (SSSH), Ma Tso Lung Restored Landfill, NENT Landfill and its extension, and livestock farm.

Existing Sheung Shui Slaughter House (SSSH)

The site covers an area of about 57,800m2 and comprises several functional blocks. It can accommodate 12,000 pigs, 2,200 cattle and 300 goats, and the designed daily production throughput is 5,000 pigs, 400 cattle and 300 goats. Figure 3.9 illustrates the location of SSSH.  The SSSH receives approximately 100 livestock carrying trucks per day from China via Man Kam To Boundary Control Point.

Environmental impacts of SSSH has been assessed and presented in the approved EIA study “Supplementary EIA Study for Sheung Shui Slaughter House” (EIA-069/BC). A number of mitigation measures have been implemented in order to reduce the potential odour impact, including wet scrubbers, ozone systems and neutralising agent systems, etc.  Table 3.22 summarizes the potential odour sources:

Table 3.22 – Potential odour sources in the existing SSSH and mitigation measures adopted

Area

Control Technology

Removal Efficiency (%)

Neutralising Spray

Ozone

Wet Scrubber

Pig lairage

ü

 

ü

97.5

Manure collection rooms

 

ü

ü

95

Blood handling room

 

ü

 

90

Isolation lairage

ü

 

 

90

Manure pump rooms

 

ü

 

90

Pig bristle chute room

 

ü

 

90

Wastewater treatment plant

 

 

ü

95

By-product collection room & unloading bay

 

ü

 

90

By-product room

 

ü

 

90

Livestock transit pens

ü

 

 

90

Train unloading area

ü

 

 

90

Livestock truck unloading area

ü

 

 

90

Ref: Sheung Shui Slaughter House Supplementary Environmental Impact Assessment

 

The current assessment has been conducted based on information from the approved EIA study “Supplementary EIA Study for Sheung Shui Slaughter House” (EIA-069/BC).

Ma Tso Lung Restored Landfill

According to information provided by EPD (Special Waste and Landfill Restoration Group, Landfill Restoration and Aftercare Section), the restoration works on the Ma Tso Lung Landfill (MTLL) were completed by the end of May 2000 and it was returned to Tung Wah Group of Hospitals in August 2000 for recreational use. EPD is currently undertaking “Aftercare” of landfill which includes operating and maintaining the landfill gas management system and quarterly monitoring work. The contract period of the Aftercare would last for about 30 years, commencing in June 2000 and completing in May 2030.

In addition, according to the record of odour monitoring conducted by EPD in 2007-2012, there was no odour nuisance during this period. The detailed odour monitoring record is presented in Appendix 3.8. It is therefore anticipated that MTLL would not cause any odour concern at the neighbouring receivers and hence would not cause any constraints on the development plan. As such, odour assessment of MTLL is not necessary. Figure 3.8 illustrates the location of the Ma Tso Lung Restored Landfill.

NENT Landfill and its Extension

An extension of the existing NENT Landfill is planned to be ready for solid waste disposal after the existing NENT Landfills reaches its capacity. The proposed NENT Extension is about 63 ha in size with an estimated waste capacity of 21.4 Mm3. The NENT Landfill Extension is forecasted to operate for about 10 to 12 years.

NENT Landfill is located approximately 4500m from FLN NDA. With reference to the findings in the approved EIA Study “North East New Territories (NENT) Landfill Extension – Feasibility Study” (EIA-133/2007), odour impact is insignificant at such separation distance. Hence, odour impact on the development is not anticipated.

Livestock Farm

There are scattered livestock farms / poultry farms in the Study Area. Farms within the NDAs will be cleared for development and therefore odour impact from these farms is not anticipated.


 

Potential Odour Sources

Sewage Treatment Work (STW) Expansion in FLN NDA

To cater for the increase in sewage due to the KTN NDA and FLN NDA, expansion of Shek Wu Hui Sewage Treatment Works is necessary. Based on the capacity and effluent quality requirement, two layout options have been developed in the outline design report of “Tender for the Provision of Services for Shek Wu Hui Sewage Treatment Works - Further Expansion – Feasibility Study” from EPD. These two layout options include:

Option 1: To conduct separate treatment work of 40,000m3 / day plus 20,000 m3/day at the proposed site, which is south of Ng Tung River and to retrofit / upgrade the existing SHSTW to provide 110,000m3/ day at tertiary level.

Option 2: To retrofit / update the existing facilities so as to confine the whole sewage stream of 170,000m3/day at tertiary level within the existing SWHSTW and to construct associated sludge handling facilities at the proposed site.

Option 2 will impose less odour, visual and/or ecological impacts to the adjacent sensitive receivers and it is more preferable in terms of operations and maintenance perspective. Hence, Option 2 is considered as a preferred option. Based on the latest design, the sewage treatment capacity will be upgraded to 190,000 m3/day after the expansion.

The expansion of the Shek Wu Hui Sewage Treatment Works would be carried out in three phases:

·         Phase 1A – from year 2015 to year 2020 (the total treatment capacity will be increase to 133,000 m3/day)

·         Phase 1B – from year 2021 to year 2023 (the total treatment capacity will be increase to 153,000 m3/day)

·         Phase 2 – from year 2022 to year 2028 (the total treatment capacity will be increase to 190,000 m3/day)

During the expansion works, newly constructed and retrofitted odour sources will be covered and provided with deodourizing unit. Therefore, the odour impact from the existing SHWSTW will improve as a result of the expansion works. Potential odour impact of the SWHSTW and other odour emission sources after the completion of the expansion works (i.e the ultimate scenario) will be assessed.

 

The layout plan of the proposed STW expansion is shown in Figure 3.10. A summary of the key treatment process elements in the proposed STW Expansion for the preferred Option 2 is given below:

·         Sewage Treatment

·         Sludge Treatment

·         Inlet works

·         Preliminary Treatment

·         Equalization

·         Primary Sedimentation

·         MBR Pre-treatment Screen

·         Bioreactor and Membrane Filtration System

·         Primary Sludge Thickening

·         Waste Activated Sludge Thickening

·         Sludge Digestion and Biogas Utilization

·         Sludge Dewatering

·          

Chlorination and dechlorination facilities for the treated sewage effluent

Superchlorination will be adopted for colour removal from reclaimed water.

Sodium hypochlorite solution will then be delivered to the contact tank. After mixing of the sodium hypochlorite solution with the treated sewage effluent, the chemical will react with the ammonia in the effluent to form chloramines, which will give a “swimming pool” odour. As superchlorination process resembles breakpoint chlorination, higher dosage of sodium hypochlorite will be added and chloramines will  themselves be broken down under this situation resulting their  chloramines removed. In addition, the contact tank will be covered. Hence, no odour impact is expected.

Proposed Sewage Pumping Stations

According to the latest development plan, a total of 6 sewerage pumping stations (SPS) have been proposed within the NDAs including KTN D1-3, KTN F1-2, FLN A1-6, FLN B1-4, FLN B2-3 and FLN C2-3. Potential odour emission sources include wet well and discharge chamber.

The wet well and other sewage facilities would be covered and foul air ventilated to a deodorizer for treatment before discharge to the environment. The ventilation system would also maintain a slight negative pressure within the facilities. Similar odour mitigation measures have also been implemented at other SPSs in the urban areas which successfully controlled odour nuisance. With proper implementation of these mitigation measures, adverse odour impact from SPS is not anticipated.

Table 3.23 below summarises the location of potential odour emission sources associated with the Project. Figure 3.8 and Figure 3.9 illustrates the location of the proposed sewage pumping stations in KTN NDA and FLN NDA respectively.

Table 3.23 – Summary of potential odour emission sources associated with the Project [1]

Land lot

Landuse [2]

Emission Type

Description

KTN NDA

D1-3

OU (SPS)

Odour

Sewage pumping station

F1-2

OU (SPS)

Odour

Sewage pumping station

FLN NDA

A2-3

OU(STW)

Odour

Sewage treatment works expansion

A1-6

OU(SPS)

Odour

Sewage pumping station

B1-4

OU(SPS)

Odour

Sewage pumping station

B2-3

OU(SPS)

Odour

Sewage pumping station

C2-3

OU(SPS)

Odour

Sewage pumping station

Notes: 

[1]  Based on Revised RODP shown in Figure 2.5 – 2.7.

[2]  OU (SPS) – Other specific uses (sewage pumping station); OU(STW) – Other specific uses (sewage treatment works).

 

3.6.2.4    Other Emission Sources

Shooting Range and Weapons Training Facilities

Two shooting ranges have been  identified within and in the vicinity of the NDA sites including Lo Wu Classification Range and San Wai/ Tai Ling Firing Range.  Due to security reason, information on the number and types of bullets fired is not available from Hong Kong Police Force (HKPF), and People Liberation Army (PLA).

Weapons training facilities within the weapon training division site (FLN A1-11) of the HKPF are also proposed within the FLN NDA site. Gunfire will be involved in the training activities at this location.

There is limited emission from normal gun shots. With reference to the approved EIA Study “Proposed Shooting Range at Pillar Point Valley Landfill” (DIR-164/2008), the lead content of lead shots is about 97%. Lead dust, including lead metal, lead ion, and oxidized lead compound, are generated during the breakdown of a lead bullet. It is understood that most of airborne lead, in form of lead dust or lead fume, emitted from gunshot comes from the bullet being ejected. Drag force during gun shot is impulsive but not considered to be an important mechanism that would carry lead dust further away and hence the lead emission will be localized. Given that the firing range and weapons training facilities are located in open spaces and accumulation of air pollutants leading to exceedance of criteria is not anticipated, potential impacts due to lead dust emission from the firing practice are not anticipated.

Helipad

Four helipads, at Lo Wu Camp, Crest Hill Operation Base, Lo Wu Classification Range, and San Wai/ Tai Ling Firing Range, have been identified within 500m of the proposed development area. The helipad at Lo Wu Camp has been closed, and is therefore not included in this assessment. The other three helipads at Crest Hill Operation Base, Lo Wu Classification Range,  and San Wai/ Tai Ling Firing Range are of low usage frequency and are located at open spaces, and therefore accumulation of emissions from helicopters associated with these three helipads are not expected. 

3.6.2.5    Emission from Concurrent Projects

Concurrent projects in the vicinity, which would have potential cumulative air quality impact to existing and planned ASRs, have been identified. These projects include the vehicular emissions from the committed Liantang / Heung Yuen Wai Boundary Control Point (BCP) and its associated road networks, planned Development of Lok Ma Chau Loop, and the industrial emissions from existing industries, proposed hospital in KTN NDA previously described, and Wo Hop Shek Crematorium.

Committed Liantang / Heung Yuen Wai BCP and its associated road networks

The Liantang/ Heung Yuen Wai BCP will connect with the Eastern Corridor and provide efficient access to Guangdong, Fujian, and Jiangxi for enhancing ties between Hong Kong and the Mainland. It will also help extend the economic hinterland of Hong Kong and Shenzhen and promote regional development. In addition, the BCP will satisfy the long-term transport needs and help re-distribute the cross-boundary traffic from Man Kam To BCP and Sha Tau Kok BCP to alleviate the frequent traffic congestions.

For the purpose of cumulative air quality assessment, the induced traffic caused by Liantang/ Heung Yuen Wai BCP and the road sections located within 500m from the project boundary have been included in this assessment.

In addition, according to the approved EIA Study of “Liantang / Heung Yuen Wai Boundary Control Point and Associated Works” (AEIAR-161/2011), vehicular emissions inside the long tunnel with a length of about 4.8km would be released via a ventilation shaft located near the Tong Hang Tung Chuen, which is within 500m of the study area. The tunnel emission from the ventilation shaft at its southern portal has also been included in the assessment to account for the cumulative impact.

Planned Development of Lok Ma Chau Loop

In the “Hong Kong 2030: Planning Vision and Strategy Study”, the Lok Ma Chau Loop was identified as an area having potential for special uses pertinent to its boundary location. A comprehensive plan has been formulated for the development of the Loop meet the long-term social, economic and environmental needs.

The induced traffic flow due to the operation of the eastern connection road of the Lok Ma Chau Loop has been included to take into account the cumulative air quality impacts in this assessment.


 

3.7          Prediction and Evaluation of Impacts

3.7.1     Construction Phase

For fugitive dust impacts, the environmental performance of the unmitigated scenario would likely exceed the TSP criterion at majority of ASR locations. Therefore, mitigation measures are needed to reduce the predicted dust impacts. Appendix 3.9 shows the results of unmitigated scenarios for the two NDA areas and Tables 3.24 to 3.26 present a summary of these results. Figures 3.11 to 3.28 show the contours of unmitigated cumulative 1-hour, 24-hour, and annual TSP concentrations in the study area. Results of dust impact assessment with mitigations are discussed in Section 3.8.

Table 3.24 – Summary of 1-hour TSP concentrations results under unmitigated scenario

NDA

Assessment Year

1-hour TSP Concentrations at Various Heights (µg/m3)

1.5m

5m

10m

KTN

2018

603 - 9280

662 – 5609

626 – 3287

2025

1624 – 12631

1799 – 7805

1698 – 5236

2028

430 – 10095

460 – 5464

426 – 3143

FLN

2018

138 - 7227

150 - 3129

147 - 1688

2021

587 – 7494

653 – 5070

622 - 3473

2025

568 – 7124

646 - 5038

619 – 3374

Notes: 

[1]  Values which exceed the criterion of 500 µg/m3 are shown in bold

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

Table 3.25 – Summary of 24-hour TSP concentrations results under unmitigated scenario

NDA

Assessment Year

24-hour TSP Concentrations at Various Heights (µg/m3)

1.5m

5m

10m

KTN

2018

102 – 2593

105 – 1335

103 – 858

2025

159 – 3667

168 – 2339

163 – 1537

2028

114 – 2504

117 – 1458

113 – 836

FLN

2018

78 - 1854

78 – 872

78 - 460

2021

135 – 2321

141 – 1358

137 – 807

2025

132 - 1775

138 – 1167

133 – 749

Notes: 

[1]  Values which exceed the criterion of 260 µg/m3 are shown in bold

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

Table 3.26Summary of annual TSP concentrations results under unmitigated scenario

NDA

Assessment Year

Annual TSP Concentrations at Various Heights (µg/m3)

1.5m

5m

10m

KTN

2018

73.1 – 120.0

73.2 – 99.3

73.2 – 88.2

2025

73.3 – 122.0

73.3 – 108.5

73.3 – 98.4

2028

73.2 – 87.5

73.2 – 81.0

73.2 – 78.2

FLN

2018

73.1 – 95.1

73.1 – 83.2

73.1 – 77.9

2021

73.7 – 94.9

73.8 – 90.3

73.7 – 84.5

2025

73.5 – 89.4

73.2 – 84.2

73.2 – 80.5

Notes: 

[1]  Values which exceed the criterion of 80 µg/m3 are shown in bold

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

3.7.2     Cumulative Emission during Operational Phase

3.7.2.1    NO2 and RSP

The cumulative 1-hour, 24-hour and annual NO2 concentrations and 24-hour and annual RSP concentrations generated by chimney plume impingement and vehicular emission have been assessed at all existing and planned ASRs in KTN NDA for the worst case assessment year of Year 2021 and in FLN NDA for the worst case assessment year of Year 2022. The assessment results are presented in Appendix 3.10. A summary of the results for the worst case assessment year at worst hit level is presented in Table 3.27:


 

Table 3.27 – Cumulative NO2 and RSP concentrations at worst hit level at worst assessment year

NDA

Worst Assessment Year

NO2 Concentration

(µg/m3)

RSP Concentration (µg/m3)

1-Hour

24-Hour

Annual

24-Hour

Annual

Background

48.5

50.5

Vehicular Emission and Chimney Emission

KTN

2021

10.7 – 84.0

1.5 – 22.8

0.3 – 10.2

0.6 –

5.8

0.2 –

2.6

FLN

2022

15.8 – 57.8

2.9 – 18.8

0.7 – 10.7

0.7 –

5.6

0.2 

3.1

Cumulative Concentration

KTN

2021

59.2 – 131.4

50.0 – 71.3

48.8 – 58.7

51.1 – 56.3

50.7 – 53.1

FLN

2022

64.3 – 106.3

51.4 – 67.3

49.2 –59.2

51.2 – 56.1

50.7 – 53.6

 

Notes:

[1]  Worst hit

No

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: [1]       Worst hit level is 1.5m above ground. 

 

The following figures illustrate the contour plots of NO2 and RSP:

·         Figures 3.29 3.31:   1-hour, 24-hour and annual NO2 concentrations at 1.5m above ground in KTN NDA at Year 2021

·         Figures 3.32 3.34:   1-hour, 24-hour and annual NO2 concentrations at 1.5m above ground in FLN NDA at Year 2022

·         Figures 3.35 3.36:   24-hour and annual RSP concentrations at 1.5m above ground in KTN NDA at Year 2021

·         Figure 3.37Figure 3.38:    24-hour and annual RSP concentrations at 1.5m above ground in FLN NDA at Year 2022

For KTN NDA in Year 2021, no exceedances of NO2 and RSP concentrations are identified at all ASRs within 500m from the boundary of KTN NDA and associated road networks, except annual-averaged RSP concentrations at certain areas within and along Fanling Highway. These non-compliance regions do not encroach into any air sensitive use. Adverse cumulative air quality impact within and in the vicinity of KTN NDA is not anticipated during operational phase in Year 2021.

For FLN NDA in Year 2022, no exceedances of NO2 and RSP concentrations are identified at all ASRs within 500m from the boundary of FLN NDA and associated road networks, except that exceedance in annual-averaged RSP concentration at certain areas within and along Fanling Highway is observed. These non-compliance regions do not encroach into any air sensitive use. Adverse cumulative air quality impact within and in the vicinity of FLN NDA is not anticipated during operational phase in Year 2022.

Since the entire proposed road network for KTN NDA and FLN NDA would be completed and operating by Year 2029, the assessment results in Table 3.27 do not include the emissions from the entire planned open-road development in both NDAs. According to the emission information between the year of “all roads completed year” and 15 years after, Year 2029 represents a worst emission scenario for KTN NDA and FLN NDA. Hence, air quality impact during Year 2029 has also been assessed to provide supplementary information on air quality impact. Cumulative NO2 and RSP concentrations for “all roads completion year” at various heights are listed in Appendix 3.10. A summary of results cumulative NO2 and RSP concentrations for all roads completion year at worst hit level is presented in Table 3.28.

Table 3.28 – NO2 and RSP concentrations at worst hit level at all roads completion year

NDA

Worst Assessment Year

NO2 Concentration

(µg/m3)

RSP Concentration (µg/m3)

1-Hour

24-Hour

Annual

24-Hour

Annual

Background

48.5

50.5

Vehicular Emission and Chimney Emission

KTN

2029

5.7 – 42.8

0.9 – 10.5

0.2 –

4.5

0.5 –

4.4

0.2 –

1.7

FLN

2029

10.0 – 33.6

1.8 – 10.2

0.2 –

4.5

0.6 –

5.8

0.2 –

2.6

Cumulative Concentration

KTN

2029

54.2 – 91.4

49.4 – 59.0

48.7 – 53.0

51.0 – 54.9

50.7 – 52.2

FLN

2029

58.5 – 82.1

50.3 – 58.7

49.0 – 54.2

51.1 – 56.3

50.7 – 53.1


Note:
[1] Worst hit level is 1.5m above ground. 

The following figures illustrate the contour plots of NO2 and RSP:

Figures 3.393.41:   1-hour, 24-hour and annual NO2 concentrations at 1.5m above ground in KTN NDA at Year 2029

Figures 3.423.44:   1-hour, 24-hour and annual NO2 concentrations at 1.5m above ground in FLN NDA at Year 2029

Figures 3.453.46:   24-hour and annual RSP concentrations at 1.5m above ground in KTN NDA at Year 2029

Figures 3.47 3.48:   24-hour and annual RSP concentrations at 1.5m above ground in FLN NDA at Year 2029

For KTN NDA in Year 2029, no exceedances of NO2 and RSP concentrations are identified at all ASRs within 500m from the boundary of KTN NDA and associated road networks. Hence, there is no adverse cumulative air quality impact on the ASRs within and in the vicinity of KTN NDA during operational phase in Year 2029.

For FLN NDA in Year 2029, no exceedances of NO2 and RSP concentrations are identified at all ASRs within 500m from the boundary of FLN NDA and associated road networks, except that exccedance in annual-averaged RSP concentration at the area of Po Shek Wu Road Interchange along Fanling Highway is observed. It is also observed that the non-compliance regions do not encroach into any air sensitive use. Hence, there is no adverse cumulative air quality impact in the FLN NDA and the vicinity of FLN NDA during operational phase in Year 2029.

3.7.2.2    SO2

The worst case assessment year for SO2 is considered to be Year 2029 and onwards after the commissioning of the proposed hospital in KTN NDA and the Shek Wu Hui Sewage Treatment Works Expansion. Contours of 1-hour, 24-hour and annual-averaged SO2 concentration from chimney emissions at worst hit level are shown in Figures 3.49 – 3.51 for KTN NDA and Figures 3.52 –  3.54 for FLN NDA. The results show that the predicted SO2 concentrations are well below the relevant criteria in both NDAs. Mitigation measures are not required. Cumulative SO2 concentrations at worst hit level are presented in Appendix 3.11. A summary of cumulative concentrations at all ASRs at worst hit level is presented in the Table 3.29.


 

Table 3.29 – Cumulative SO2 concentration at worst hit level at worst assessment year

NDA

SO2 Concentration (µg/m3)

1-Hour

24-Hour

Annual

Background

14.3

Chimney Emission 

KTN

2.4 – 15.6 [1]

0.5 – 2.7 [1]

0.1  – 0.5 [1]

FLN

5.4  – 45.9 [3]

0.9 – 7.8 [3]

0.3 – 1.4 [2]

Cumulative Concentration

KTN

16.7 – 29.9 [1]

14.8 – 17.0 [1]

14.4 – 14.8 [1]

FLN

19.7 – 60.2 [3]

15.2 – 22.1 [3]

14.6 – 15.7 [2]

Notes:

[1]  Worst hit level is 10m above ground. 

[2]  Worst hit level is 35m above ground. 

[3]  Worst hit level is 40m above ground.   

3.7.2.3    Odour

Proposed Sewage Treatment Work Expansion in FLN NDA

The maximum 5-second averaged odour concentrations at all ASRs in FLN and KTN NDA at Year 2028 and onwards were assessed and presented in Appendix 3.12. No exceedance in odour criterion at all ASRs in FLN and KTN NDA are identified. According to the contours of odour concentrations at ground level (1.5m above ground) and worst hit level (55m above ground) shown in Figure 3.55a and Figure 3.55b, the 5OU non-compliance zone (i.e. at 55m above the ground) have been identified. According to the revised RODP, there is no sir sensitive use within the non-compliance zone. Nevertheless, for the future development, it is necessary to ensure that no sensitive receivers will fall into this non-compliance zone.  

A summary of results of 5-second averaged odour concentrations at existing and planned sensitive receivers is presented in Table 3.30.

Table 3.30 – 5-second averaged odour concentration at sensitive receivers

NDA

ASR Status

Odour Concentration (OU)

FLN

(Year 2028 and onwards)

Existing

0.2 – 0.7 [1]

Planned

0.2 – 0.7 [1]

KTN

(Year 2028 and onwards)

Existing

0.6 [1]

Planned

0.2 – 0.5 [1]

Note:

[1]  Worst hit level is at 55m above ground.  5OU unit is identified near the boundary of the SHWSTW

3.8          Mitigation Measures

3.8.1     Construction Phase

In order to reduce the dust impact and achieve compliance with TSP criteria at ASRs, mitigation measures in the form of regular watering under good site practice should be adopted. In accordance with the “Control of Open Fugitive Dust Sources” (USEPA AP-42) as given in Appendix 3.2, watering once per hour on exposed worksites and haul roads is proposed to achieve a dust removal efficiency of 92.1%. This dust suppression efficiency is derived from average haul road traffic, average evaporation rate and an assumed application intensity of 1.7 L/m2 for the respective watering frequencies (see Appendix 3.2).  Any potential dust impact and watering mitigation would be subject to actual site conditions.  For example, a construction activity that produces inherently wet conditions or in cases under rainy weather, the above water application intensity may not be necessary.  While the above watering frequencies are to be followed, the extent of watering may vary depending on actual site conditions but should be sufficient to maintain an equivalent intensity of no less than 1.7 L/m2 to achieve the respective dust removal efficiencies. The dust levels would be monitored and managed under an EM&A programme as specified in the EM&A Manual.

In addition, the Contractor is also obliged to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation. The regulation stipulates the construction dust control requirements for both Notifiable (e.g. site formation) and Regulatory (e.g. road opening) Works to be carried out by the Contractor. The following dust suppression measures should also be incorporated by the Contractor to control the dust nuisance throughout the construction phase:

·      Any excavated or stockpile of dusty material should be covered entirely by impervious sheeting or sprayed with water to maintain the entire surface wet and then removed or backfilled or reinstated where practicable within 24 hours of the excavation or unloading;

·      Any dusty material remaining after a stockpile is removed should be wetted with water and cleared from the surface of roads;

·      A stockpile of dusty material should not be extended beyond the pedestrian barriers, fencing or traffic cones;

·      The load of dusty materials on a vehicle leaving a construction site should be covered entirely by impervious sheeting to ensure that the dusty materials do not leak from the vehicle;

·      Where practicable, vehicle washing facilities with high pressure water jet should be provided at every discernible or designated vehicle exit point.  The area where vehicle washing takes place and the road section between the washing facilities and the exit point should be paved with concrete, bituminous materials or hardcores;

·      When there are open excavation and reinstatement works, hoarding of not less than 2.4m high should be provided as far as practicable along the site boundary with provision for public crossing. Good site practice shall also be adopted by the Contractor to ensure the conditions of the hoardings are properly maintained throughout the construction period.

·      The portion of any road leading only to construction site that is within 30m of a vehicle entrance or exit should be kept clear of dusty materials;

·      Surfaces where any pneumatic or power-driven drilling, cutting, polishing or other mechanical breaking operation takes place should be sprayed with water or a dust suppression chemical continuously;

·      Any area that involves demolition activities should be sprayed with water or a dust suppression chemical immediately prior to, during and immediately after the activities so as to maintain the entire surface wet;

·      Where a scaffolding is erected around the perimeter of a building under construction, effective dust screens, sheeting or netting should be provided to enclose the scaffolding from the ground floor level of the building, or a canopy should be provided from the first floor level up to the highest level of the scaffolding;

·      Any skip hoist for material transport should be totally enclosed by impervious sheeting;

·      Every stock of more than 20 bags of cement or dry pulverised fuel ash (PFA) should be covered entirely by impervious sheeting or placed in an area sheltered on the top and the 3 sides;

·      Cement or dry PFA delivered in bulk should be stored in a closed silo fitted with an audible high level alarm which is interlocked with the material filling line and no overfilling is allowed;

·      Loading, unloading, transfer, handling or storage of bulk cement or dry PFA should be carried out in a totally enclosed system or facility, and any vent or exhaust should be fitted with an effective fabric filter or equivalent air pollution control system; and

·      Exposed earth should be properly treated by compaction, turfing, hydroseeding, vegetation planting or sealing with latex, vinyl, bitumen, shortcrete or other suitable surface stabiliser within six months after the last construction activity on the construction site or part of the construction site where the exposed earth lies.

These requirements should be incorporated into the contract specification for the civil work.  In addition, an audit and monitoring programme during the construction phase should be implemented by the project proponent to ensure that the construction dust impacts are controlled to within the required criteria. Detailed requirements for the audit and monitoring programme are given separately in the EM&A manual.

3.8.1.1     Assessment Results – Mitigated Scenarios for KTN NDA

Short-term Assessment (Tier 1) for Worst Case Scenario – Year 2025

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.31 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that, for some of the ASRs, exceedance of 1-hour and 24-hour TSP criteria would not be anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (e.g. Lo Wu Firing Range, District Headquarters Associated Married Staff Quarters, Divisional Police Station and Reprovisioning of Fan Garden Junior Police Officers’ Police Married Quarters), exceedance of 1-hour and 24-hour TSP criteria is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken.

Figure 3.61 and Figure 3.62 show the contours of Tier 1 1-hour and 24-hour TSP concentrations respectively.

Short-term Assessment (Tier 2) for Worst Case Scenario – Year 2025

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.6.1.6, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.32 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria except KTN-97. As such, adverse short-term construction dust impact is not anticipated.

Contours are presented in Figure 3.63 and Figure 3.64 for 1-hour (Tier 2), and 24-hour (Tier 2) TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.


 

Short-term Assessment (Tier 3) for Worst Case Scenario – Year 2025

Based on the Tier 2 assessment which is a reasonably conservative, 1-hour TSP exceedance at one ASR is predicted. However, it is estimated that the actual active area for KTN NDA in 2025 is 7.9%. A more focused Tier 3 assessment has been conducted with the assumed 7.9% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs.

The maximum 1-hour and 24-hour TSP concentrations from Tier 3 screening assessment have been predicted. Appendix 3.15 shows the assessment results and Table 3.33 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 3) at the ASR concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figure 3.65 and Figure 3.66 for 1-hour (Tier 3) and 24-hour (Tier 3) TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Worst Case Scenario – Year 2025

The annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.34 below summarises the cumulative annual TSP impact at the ASRs concerned concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore, no adverse long-term impact is anticipated. Contour of annual TSP concentrations at 1.5m above ground are shown in Figure 3.67.

 


Table 3.31 – Tier 1 assessment – Predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2025

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hour TSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Temporary Structure near Sheung Yue River

KTN-E24

941

660

446

294

237

189

Yin Kong Tsuen

KTN-E85

558

527

409

110

107

100

KTN-E86

501

488

400

102

101

97

KTN-E87

586

549

418

110

109

103

Sports Ground near Enchi Lodge

KTN-E88

667

623

478

147

137

117

Temporary Structure near Castle Peak Road

KTN-E89

531

535

453

104

105

101

Ho Sheung Heung Temple

KTN-E94

640

587

423

187

173

142

KTN-E97

542

513

409

149

147

132

Lo Wu Firing Range (Eastern)

KTN-E123

514

439

381

175

158

137

Lo Wu Firing Range (Western)

KTN-E128

515

461

392

169

154

135

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

624

403

290

252

172

135

KTN-E163

504

336

291

190

153

131

KTN-E164

512

407

299

169

158

136

KTN-E170

503

316

291

176

135

128

KTN-E173

583

368

293

256

157

129

KTN-E174

590

325

287

201

139

128

KTN-E175

701

425

304

245

166

136

Ma Tso Lung San Tsuen

KTN-E209

731

536

369

171

139

114

Lady Ho Tung Welfare Centre

KTN-E1004

517

507

403

140

141

129

Valais Phase 1

KTN-E1005

670

612

442

179

171

149

KTN-E1006

723

657

470

201

196

171

KTN-E1007

619

600

471

174

174

158

St Paul's House of Prayer

KTN-E1009

585

587

481

185

175

143

Kam Tsin Village Ho Tung School

KTN-E1010

547

552

462

131

129

117

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

770

528

384

177

138

112

KTN-E1018

843

550

372

223

166

125

Village Houses at Ma Tso Lung

KTN-E1019

517

513

423

153

155

144

Village Houses at Tit Hang

KTN-E1020

511

520

442

165

167

152

Workshop northwest to Pak Shek Au

KTN-E1021

650

432

306

223

164

136

Planned/ Committed ASRs

Nursery Classes and Kindergartens

KTN-12

539

501

371

171

172

156

KTN-13

597

531

372

182

181

161

KTN-17

521

469

376

185

183

163

KTN-18

592

523

377

186

184

163

KTN-19

761

550

394

233

200

170

KTN-20

600

510

383

199

190

166

KTN-21

517

505

400

187

186

164

KTN-22

565

539

408

200

196

169

KTN-23

743

616

400

255

229

179

KTN-24

799

622

395

267

232

179

KTN-25

784

577

382

273

236

180

KTN-26

806

597

375

289

237

177

KTN-27

770

595

385

268

227

176

KTN-28

643

554

393

242

214

174

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre

KTN-85

542

480

395

170

168

152

KTN-86

577

489

410

190

174

158

KTN-87

576

515

421

194

179

161

KTN-88

599

576

439

216

203

169

KTN-89

698

632

444

242

223

176

KTN-90

921

661

420

323

239

181

KTN-91

856

628

411

294

238

181

KTN-92

663

586

426

217

207

174

KTN-93

541

529

422

181

180

160

KTN-94

558

537

421

187

186

165

KTN-97

937

640

410

306

241

180

KTN-98

910

673

431

295

242

180

KTN-99

535

523

419

176

176

159

Secondary School

KTN-227

521

512

405

174

172

153

KTN-228

571

545

410

189

183

157

KTN-229

549

527

409

179

175

153

KTN-230

507

501

403

168

167

149

Primary School

KTN-231

550

522

401

191

187

163

KTN-232

577

548

409

196

190

163

Sports Centre, District Library, Integrated Children and Youth Services Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-233

678

595

404

227

212

172

KTN-234

773

600

396

251

217

173

KTN-235

842

636

407

243

206

164

KTN-236

713

616

414

203

190

157

KTN-237

624

566

414

197

188

157

Visitor Centre

KTN-248

970

631

432

242

171

136

KTN-249

886

655

444

191

163

134

Long Valley Core Area, Area for Wetland Enhancement Works and Area for Facilities Supporting the Nature Park

KTN-272

711

580

446

179

142

127

KTN-273

640

608

462

178

166

141

KTN-274

649

572

445

127

125

113

KTN-275

595

573

451

135

133

119

KTN-286

625

548

424

131

116

108

KTN-287

528

529

443

140

124

114

Potential Activity Centre

KTN-302

710

597

417

155

131

118

KTN-306

523

514

420

136

135

122

KTN-307

635

586

432

156

148

125

KTN-308

664

581

404

159

136

117

KTN-309

537

517

403

140

131

117

KTN-310

797

551

383

139

128

120

KTN-311

530

408

317

140

126

117

KTN-312

518

471

362

122

123

116

Village Resite

KTN-321

803

654

444

190

166

132

KTN-322

617

583

441

162

154

130

KTN-323

506

507

420

148

145

128

KTN-325

635

602

453

154

148

127

KTN-326

771

652

455

197

161

128

District Headquarters, District Headquarters Associated Married Staff Quarters, Divisional Police Station and Reprovisioning of Fan Garden Junior Police Officers’ Police Married Quarters

KTN-354

850

657

466

285

252

195

KTN-355

1065

684

469

378

264

192

KTN-356

783

602

445

270

231

181

KTN-357

935

661

432

269

210

169

KTN-358

709

618

451

260

231

181

Fire Station and Ambulance Depot

KTN-377

687

631

453

174

165

139

KTN-378

747

651

448

188

172

140

KTN-379

799

668

448

202

177

141

KTN-380

944

671

448

263

193

145

KTN-381

819

659

450

238

194

146

KTN-382

774

663

456

198

176

141

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)

KTN-408

651

505

369

173

146

116

KTN-409

741

487

353

196

143

112

KTN-410

756

477

352

212

148

114

KTN-411

837

512

372

217

151

119

Proposed houses at Zone A/NE -Temporary Structure/267

KTN-C1

576

552

438

197

189

158

Notes: 

[1]        Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]        Values include background concentration: 73.1 µg/m3 of TSP.


 

Table 3.32 – Tier 2 assessment – Predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2025.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Temporary Structure near Sheung Yue River

KTN-E24

488

256

160

194

131

103

Yin Kong Tsuen

KTN-E85

276

249

183

86

85

82

KTN-E86

220

211

172

84

83

81

KTN-E87

241

212

154

84

84

82

Sports Ground near Enchi Lodge

KTN-E88

205

198

165

97

94

86

Temporary Structure near Castle Peak Road

KTN-E89

158

157

139

83

83

81

Ho Sheung Heung Temple

KTN-E94

383

248

167

121

107

94

KTN-E97

233

210

152

98

94

87

Lo Wu Firing Range (Eastern)

KTN-E123

383

268

156

111

101

93

Lo Wu Firing Range (Western)

KTN-E128

309

247

163

113

101

93

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

408

250

159

167

120

93

KTN-E163

282

202

146

133

109

92

KTN-E164

216

175

140

108

101

92

KTN-E170

223

155

124

105

96

88

KTN-E173

192

153

124

97

93

86

KTN-E174

338

164

129

133

99

89

KTN-E175

348

177

126

123

99

89

Ma Tso Lung San Tsuen

KTN-E209

281

190

142

104

89

82

Lady Ho Tung Welfare Centre

KTN-E1004

184

182

157

92

92

88

Valais Phase 1

KTN-E1005

226

222

186

92

92

88

KTN-E1006

291

244

161

120

110

94

KTN-E1007

215

200

150

106

102

92

St Paul's House of Prayer

KTN-E1009

183

180

154

90

89

86

Kam Tsin Village Ho Tung School

KTN-E1010

169

171

154

88

88

85

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

447

237

142

129

97

86

KTN-E1018

255

161

123

118

96

87

Village Houses at Ma Tso Lung

KTN-E1019

170

172

156

90

91

89

Village Houses at Tit Hang

KTN-E1020

172

175

160

91

92

89

Workshop northwest to Pak Shek Au

KTN-E1021

223

173

123

96

92

87

Planned/ Committed ASRs

Nursery Classes and Kindergartens

KTN-12

291

253

168

99

97

91

KTN-13

338

274

164

106

102

94

KTN-17

321

250

161

110

105

93

KTN-18

364

269

167

110

104

92

KTN-19

490

258

169

151

113

95

KTN-20

384

258

167

121

109

93

KTN-21

229

209

153

103

100

92

KTN-22

226

208

155

107

104

94

KTN-23

243

226

173

117

107

94

KTN-24

268

238

174

123

109

96

KTN-25

356

277

172

137

114

99

KTN-26

456

274

170

154

124

103

KTN-27

419

250

163

148

120

101

KTN-28

379

236

160

141

118

99

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre

KTN-85

311

246

156

107

101

94

KTN-86

363

228

171

129

107

94

KTN-87

348

221

177

140

113

95

KTN-88

337

250

184

167

126

96

KTN-89

323

267

181

152

119

94

KTN-90

402

285

182

125

110

93

KTN-91

472

268

175

182

136

102

KTN-92

341

270

173

129

120

102

KTN-93

239

222

165

110

107

97

KTN-94

265

244

179

108

105

96

KTN-97

544

275

177

198

136

102

KTN-98

336

270

172

135

110

94

KTN-99

260

243

183

105

103

96

Secondary School

KTN-227

193

184

149

95

94

89

KTN-228

203

186

153

97

95

89

KTN-229

206

200

167

96

94

89

KTN-230

229

219

175

93

93

88

Primary School

KTN-231

193

187

155

99

98

91

KTN-232

187

184

155

101

98

91

Sports Centre, District Library, Integrated Children and Youth Services Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-233

209

202

167

107

102

92

KTN-234

238

208

174

117

104

92

KTN-235

282

197

168

118

102

91

KTN-236

205

189

162

104

99

90

KTN-237

218

192

160

100

97

89

Visitor Centre

KTN-248

See Note [2]

285

169

186

125

101

KTN-249

426

289

170

145

117

100

Long Valley Core Area, Area for Wetland Enhancement Works and Area for Facilities Supporting the Nature Park

KTN-272

409

292

182

142

101

89

KTN-273

286

226

157

121

101

91

KTN-274

413

325

192

107

95

87

KTN-275

279

241

176

96

95

89

KTN-286

346

271

186

101

92

84

KTN-287

255

232

172

108

94

86

Potential Activity Centre

KTN-302

339

237

166

93

86

81

KTN-306

164

161

146

86

85

80

KTN-307

237

181

141

92

87

83

KTN-308

314

218

144

108

89

83

KTN-309

225

203

154

85

85

83

KTN-310

334

214

169

94

88

86

KTN-311

241

196

169

90

89

86

KTN-312

206

192

168

88

87

85

Village Resite

KTN-321

394

257

167

138

115

95

KTN-322

290

236

157

119

111

96

KTN-323

251

225

159

109

105

95

KTN-325

289

234

156

118

110

95

KTN-326

464

274

174

160

121

96

District Headquarters, District Headquarters Associated Married Staff Quarters, Divisional Police Station and Reprovisioning of Fan Garden Junior Police Officers’ Police Married Quarters

KTN-354

374

240

174

118

104

92

KTN-355

See Note [2]

279

170

158

112

94

KTN-356

See Note [2]

273

174

216

136

100

KTN-357

484

315

176

175

129

101

KTN-358

444

288

183

174

134

101

Fire Station and Ambulance Depot

KTN-377

292

229

153

109

101

90

KTN-378

336

233

157

123

106

90

KTN-379

365

231

153

132

110

92

KTN-380

473

232

146

179

118

95

KTN-381

436

233

150

174

122

95

KTN-382

338

226

153

133

112

92

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)

KTN-408

437

225

151

116

101

87

KTN-409

348

208

159

124

98

87

KTN-410

435

228

158

135

99

88

KTN-411

400

228

137

161

105

89

Proposed houses at Zone A/NE -Temporary Structure/267

KTN-C1

188

187

164

91

90

86

Notes: 

[1]  Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]  No ASR at the height of 1.5mAG.

[3]  Values include background concentration: 73.1 µg/m3 of TSP.

Table 3.33 – Tier 3 assessment – Predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2025.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Planned/ Committed ASRs

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre

KTN-97

487

251

159

184

128

98

Notes: 

 [1] Values include background concentration: 73.1 µg/m3 of TSP.


Table 3.34 – Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2025.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

Temporary Structure near Sheung Yue River

KTN-E24

75.7

75.2

74.6

Yin Kong Tsuen

KTN-E85

73.4

73.4

73.3

KTN-E86

73.3

73.3

73.3

KTN-E87

73.4

73.4

73.3

Sports Ground near Enchi Lodge

KTN-E88

73.4

73.4

73.4

Temporary Structure near Castle Peak Road

KTN-E89

73.3

73.3

73.3

Ho Sheung Heung Temple

KTN-E94

74.3

74.1

73.8

Ho Sheung Heung Village

KTN-E97

73.7

73.7

73.6

Lo Wu Firing Range (Eastern)

KTN-E123

73.7

73.7

73.6

Lo Wu Firing Range (Western)

KTN-E128

73.7

73.7

73.6

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

75.3

74.5

74.0

KTN-E163

74.8

74.3

73.9

KTN-E164

74.3

74.1

73.9

Temporary Structure at Pak Shek Au

KTN-E170

74.6

74.1

73.9

KTN-E173

75.1

74.2

73.8

KTN-E174

75.0

74.3

73.9

KTN-E175

75.5

74.4

73.9

Ma Tso Lung San Tsuen

KTN-E209

73.4

73.4

73.3

Lady Ho Tung Welfare Centre

KTN-E1004

73.8

73.8

73.8

Valais Phase 1

KTN-E1005

74.2

74.2

74.0

KTN-E1006

74.6

74.5

74.2

KTN-E1007

74.2

74.2

74.0

St Paul's House of Prayer

KTN-E1009

73.6

73.6

73.5

Kam Tsin Village Ho Tung School

KTN-E1010

73.3

73.3

73.3

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

73.4

73.4

73.3

KTN-E1018

73.6

73.5

73.4

Village Houses at Ma Tso Lung

KTN-E1019

74.2

74.3

74.1

Village Houses at Tit Hang

KTN-E1020

74.1

74.1

74.0

Workshop northwest to Pak Shek Au

KTN-E1021

74.6

74.2

73.8

Planned/ Committed ASRs

Nursery Classes and Kindergartens

KTN-12

74.5

74.5

74.4

KTN-13

74.6

74.7

74.5

KTN-17

74.8

74.8

74.6

KTN-18

74.8

74.8

74.6

Nursery Classes and Kindergartens; Post Offices

KTN-19

75.4

75.2

74.8

KTN-20

75.0

75.0

74.7

KTN-21

74.7

74.7

74.5

KTN-22

74.8

74.8

74.6

KTN-23

75.4

75.3

74.8

KTN-24

75.6

75.4

74.9

KTN-25

76.1

75.7

75.1

KTN-26

76.3

75.9

75.2

KTN-27

76.1

75.8

75.2

KTN-28

75.7

75.5

75.0

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre

KTN-85

74.9

74.9

74.6

KTN-86

75.5

75.3

74.8

KTN-87

75.8

75.5

75.0

KTN-88

76.4

76.0

75.3

KTN-89

76.8

76.3

75.4

KTN-90

77.8

76.8

75.6

KTN-91

76.7

76.1

75.3

KTN-92

75.3

75.2

74.8

KTN-93

75.1

75.1

74.8

KTN-94

74.9

74.9

74.6

KTN-97

77.3

76.4

75.4

KTN-98

77.5

76.7

75.6

KTN-99

74.6

74.7

74.5

Secondary School

KTN-227

74.3

74.3

74.1

KTN-228

74.4

74.4

74.2

KTN-229

74.3

74.3

74.1

KTN-230

74.2

74.2

74.0

Primary School

KTN-231

74.6

74.6

74.4

KTN-232

74.6

74.6

74.4

Sports Centre, District Library, Integrated Children and Youth Services
Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-233

75.1

75.0

74.6

KTN-234

75.2

75.0

74.6

KTN-235

74.8

74.7

74.4

KTN-236

74.4

74.4

74.2

KTN-237

74.4

74.4

74.2

Visitor Centre

KTN-248

75.4

74.4

73.9

KTN-249

74.6

74.2

73.8

Long Valley Core Area, Area for Wetland Enhancement Works and
Area for Facilities Supporting the Nature Park

KTN-272

75.1

74.3

73.8

KTN-273

74.5

74.3

73.9

KTN-274

73.6

73.5

73.4

KTN-275

73.4

73.4

73.4

KTN-286

73.6

73.5

73.4

KTN-287

73.8

73.7

73.5

Potential Activity Centre

KTN-302

73.6

73.6

73.5

KTN-306

73.4

73.4

73.4

KTN-307

73.5

73.5

73.5

KTN-308

73.6

73.6

73.5

KTN-309

73.5

73.5

73.5

KTN-310

73.6

73.5

73.5

KTN-311

73.6

73.5

73.5

KTN-312

73.5

73.5

73.5

Village Resite

KTN-321

74.0

73.8

73.6

KTN-322

73.7

73.7

73.5

KTN-323

73.6

73.6

73.5

KTN-325

73.6

73.6

73.5

KTN-326

74.0

73.7

73.5

District Headquarters, District Headquarters Associated Married Staff Quarters, Divisional Police Station and Reprovisioning of Fan Garden Junior Police Officers’ Police Married Quarters

KTN-354

77.2

76.4

75.4

KTN-355

78.5

76.7

75.4

KTN-356

77.2

76.3

75.3

KTN-357

76.6

75.9

75.0

KTN-358

76.8

76.1

75.2

Fire Station and Ambulance Depot

KTN-377

74.6

74.5

74.1

KTN-378

75.0

74.7

74.2

KTN-379

75.4

75.0

74.3

KTN-380

76.5

75.4

74.5

KTN-381

76.0

75.4

74.6

KTN-382

75.3

75.0

74.4

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)

KTN-408

73.5

73.5

73.4

KTN-409

73.6

73.5

73.4

KTN-410

73.6

73.5

73.4

KTN-411

73.6

73.5

73.4

Proposed houses at Zone A/NE -Temporary Structure/267

KTN-C1

74.1

74.1

73.8

Notes: 

 [1] Values include background concentration: 73.1 µg/m3 of TSP.


Short-term Assessment (Tier 1) for Year 2018

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.35 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that, for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria is not anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (e.g. Pak Shek Au and Fung Kong), exceedance of 1-hour TSP criterion is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken. Figure 3.56 and Figure 3.57 show the contours of Tier 1 1-hour and 24-hour TSP concentrations.

Short-term Assessment (Tier 2) for Year 2018

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.6.1.6, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.36 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figure 3.58 and Figure 3.59 for 1-hour (Tier 2) and 24-hour (Tier 2) TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Year 2018

The annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.37 below summarises the cumulative annual TSP impact at the ASRs concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore, no adverse long-term impact is anticipated. Contour of annual TSP concentrations at 1.5m above ground is shown in Figure 3.60.


Table 3.35 – Tier 1 assessment - predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2018.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Village Houses between Tung Kok and Tung Fong

KTN-E53

523

370

244

176

151

120

KTN-E54

543

407

250

172

149

120

Temporary Structure at Tung Fong

KTN-E55

692

358

223

269

167

123

KTN-E56

789

363

225

296

178

126

KTN-E57

729

452

273

204

160

126

KTN-E58

737

380

231

223

170

130

Temporary Structure at Pak Shek Au

KTN-E61

621

386

291

194

140

112

KTN-E62

600

340

271

264

157

115

KTN-E63

566

331

258

252

144

112

KTN-E64

635

366

256

256

149

110

KTN-E65

594

355

261

269

158

115

KTN-E67

738

412

267

232

141

111

KTN-E68

676

402

259

239

145

112

KTN-E69

734

424

275

227

138

108

KTN-E70

564

466

325

155

136

115

KTN-E71

762

477

322

235

166

121

KTN-E73

755

430

257

214

172

131

KTN-E78

671

355

242

225

145

114

KTN-E79

611

324

265

214

140

111

Temporary Structure near Community Sports

KTN-E142

598

400

253

199

162

125

Temporary Structure near Fung Kong

KTN-E143

629

467

276

121

112

102

KTN-E145

686

493

301

214

183

140

KTN-E146

800

489

295

251

162

125

KTN-E148

788

439

271

229

136

111

Temporary Structure near Ma Tso Lung Road

KTN-E149

696

381

244

228

146

109

KTN-E150

668

418

253

274

162

121

KTN-E151

669

392

245

244

168

124

Temporary Structure near Dills Corner Garden

KTN-E157

608

300

231

229

135

111

KTN-E158

631

327

228

240

149

113

KTN-E159

519

343

214

132

120

107

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

509

411

315

135

117

104

KTN-E163

559

421

312

148

122

106

Temporary Structure at Pak Shek Au

KTN-E165

618

358

256

267

151

114

KTN-E168

534

332

270

202

145

112

KTN-E170

512

401

296

203

151

113

KTN-E171

602

446

315

234

164

118

KTN-E172

679

451

317

197

129

107

KTN-E176

652

333

245

225

138

116

Temporary Structure near Tung Fong

KTN-E189

800

367

229

224

160

122

KTN-E190

613

401

247

164

147

122

KTN-E193

516

461

315

129

123

105

KTN-E194

691

510

312

177

150

119

KTN-E195

732

510

306

160

134

113

Europa Garden Phase I

KTN-E1003

519

433

282

160

146

121

Notes: 

[1]  Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

 

Table 3.36 – Tier 2 assessment - predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2018.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Village Houses between Tung Kok and Tung Fong

KTN-E53

204

170

126

102

97

87

KTN-E54

233

178

127

96

93

86

Temporary Structure at Tung Fong

KTN-E55

414

187

120

165

107

89

KTN-E56

177

154

133

103

96

87

KTN-E57

175

166

136

87

86

83

KTN-E58

See Note [1]

228

138

169

113

89

Temporary Structure at Pak Shek Au

KTN-E61

425

245

160

154

112

91

KTN-E62

396

214

158

180

112

91

KTN-E63

467

218

136

140

101

88

KTN-E64

430

223

143

143

105

90

KTN-E65

426

213

147

185

110

93

KTN-E67

295

222

148

111

100

89

KTN-E68

272

208

143

110

100

88

KTN-E69

296

246

164

107

99

88

KTN-E70

382

278

164

114

99

87

KTN-E71

See Note [1]

261

159

171

118

93

KTN-E73

208

190

140

92

90

85

KTN-E78

258

198

133

113

97

83

KTN-E79

291

215

143

90

88

84

Temporary Structure near Community Sports

KTN-E142

301

192

140

116

92

84

Temporary Structure near Fung Kong

KTN-E143

349

256

161

102

95

87

KTN-E145

433

298

174

143

114

93

KTN-E146

See Note [1]

257

153

201

120

96

KTN-E148

See Note [1]

268

169

201

117

94

Temporary Structure near Ma Tso Lung Road

KTN-E149

See Note [1]

323

184

212

130

99

KTN-E150

291

196

132

118

105

89

KTN-E151

304

191

128

108

96

87

Temporary Structure near Dills Corner Garden

KTN-E157

163

160

138

88

87

84

KTN-E158

148

148

131

93

88

83

KTN-E159

156

140

125

86

83

81

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

350

244

170

106

94

85

KTN-E163

395

250

164

115

95

85

Temporary Structure at Pak Shek Au

KTN-E165

498

241

150

158

110

93

KTN-E168

238

197

131

89

86

83

KTN-E170

391

248

156

141

106

91

KTN-E171

461

253

152

182

120

93

KTN-E172

457

216

135

178

108

91

KTN-E176

262

206

140

87

85

83

Temporary Structure near Tung Fong

KTN-E189

425

176

117

150

105

87

KTN-E190

268

173

126

109

98

87

KTN-E193

240

206

142

102

98

89

KTN-E194

373

211

141

136

111

94

KTN-E195

368

211

147

125

105

92

Europa Garden Phase I

KTN-E1003

197

157

125

98

91

83

Notes: 

[1]  ASR does not exist during the construction period.

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 


Table 3.37 – Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2018.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

Village Houses between Tung Kok and Tung Fong

KTN-E53

74.3

74.1

73.7

KTN-E54

74.5

74.2

73.8

Temporary Structure at Tung Fong

KTN-E55

77.2

75.2

74.2

KTN-E56

78.1

75.7

74.5

KTN-E57

74.9

74.5

74.0

KTN-E58

75.8

74.3

73.8

Temporary Structure at Pak Shek Au

KTN-E61

75.3

74.5

73.9

KTN-E62

76.2

74.8

74.0

KTN-E63

76.2

74.7

74.0

KTN-E64

76.1

74.7

74.0

KTN-E65

76.7

74.8

74.0

KTN-E67

75.7

74.4

73.8

KTN-E68

75.3

74.3

73.8

KTN-E69

76.1

74.5

73.8

KTN-E70

74.5

74.2

73.8

KTN-E71

75.7

74.6

73.9

KTN-E73

74.9

74.5

74.0

KTN-E78

75.7

74.4

73.8

KTN-E79

75.7

74.5

73.9

Temporary Structure near Community Sports

KTN-E142

75.2

74.6

74.1

Temporary Structure near Fung Kong

KTN-E143

73.4

73.4

73.3

KTN-E145

74.8

74.3

73.8

Open Storage near Fung Kong

KTN-E146

75.9

74.2

73.6

Temporary Structure near Fung Kong

KTN-E148

76.6

74.2

73.6

Temporary Structure near Ma Tso Lung Road

KTN-E149

75.0

73.8

73.4

KTN-E150

77.6

75.3

74.2

KTN-E151

76.7

75.4

74.4

Temporary Structure near Dills Corner Garden

KTN-E157

74.5

73.8

73.5

KTN-E158

74.5

73.8

73.5

KTN-E159

73.5

73.5

73.4

Temporary Structure near Fanling Highway (near Pak Shek Au)

KTN-E162

73.9

73.8

73.6

KTN-E163

74.4

73.9

73.6

Temporary Structure at Pak Shek Au

KTN-E165

76.6

74.7

74.0

KTN-E168

74.7

74.2

73.8

KTN-E170

75.0

74.3

73.8

KTN-E171

75.5

74.5

73.9

KTN-E172

75.6

74.3

73.8

KTN-E176

76.1

74.6

73.9

Temporary Structure near Tung Fong

KTN-E189

74.7

74.2

73.8

KTN-E190

73.9

73.8

73.6

KTN-E193

73.4

73.4

73.3

KTN-E194

73.8

73.7

73.5

KTN-E195

73.7

73.6

73.4

Europa Garden Phase I

KTN-E1003

73.8

73.7

73.5

Notes: 

 [1] Values include background concentration: 73.1 µg/m3 of TSP.

 


Short-term Assessment (Tier 1) for Year 2028

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.38 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that, for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria is not anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (e.g. Castle Peak Road and Lo Wu Firing Range), exceedance of 1-hour and 24-hour TSP criterion is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken. Figure 3.68 and Figure 3.69 show the contours of Tier 1 1-hour and 24-hour TSP concentrations.

Short-term Assessment (Tier 2) for Year 2028

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.6.1.6, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.39 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figure 3.70 and Figure 3.71 for 1-hour (Tier 2) and 24-hour (Tier 2) TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Year 2028

The annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.40 below summarises the cumulative annual TSP impact at the ASRs concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore no adverse long-term impact is anticipated. Contour of annual TSP concentrations at 1.5m above ground is shown in Figure 3.72.


Table 3.38 – Tier 1 assessment – predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2028.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Temporary Structure near Castle Peak Road

KTN-E90

519

309

200

196

118

90

Lo Wu Firing Range (Eastern)

KTN-E123

580

413

244

194

161

119

Ma Tso Lung San Tsuen

KTN-E209

575

375

227

112

96

85

Europa Garden Phase I

KTN-E1003

671

355

260

154

107

97

Valais Phase 1

KTN-E1005

865

497

296

274

198

142

KTN-E1006

690

499

296

224

174

135

KTN-E1007

568

482

311

164

153

129

St Paul's House of Prayer

KTN-E1009

546

295

188

158

116

96

Kam Tsin Village Ho Tung School

KTN-E1010

521

294

190

160

115

96

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

641

395

236

127

109

93

KTN-E1018

709

443

272

165

130

105

Planned ASRs

Nursery Classes and Kindergartens; Post Offices

KTN-23

547

424

253

156

140

115

KTN-24

586

415

259

164

143

116

KTN-25

593

412

250

166

143

116

KTN-26

612

429

261

172

143

114

KTN-27

526

407

256

156

136

112

Sports Centre, District Library, Integrated Children and Youth Services Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-234

591

413

224

159

137

112

KTN-235

623

403

242

160

135

109

Reprovision Site of Kwu Tung Vegetable Marketing and Credit Co-operative Society

KTN-271

549

323

184

157

119

96

Government Reserve

KTN-315

617

359

241

221

140

110

KTN-316

587

352

245

223

145

115

KTN-318

586

373

248

173

138

114

KTN-319

561

339

243

162

127

107

Sports Ground/Sports Complex

KTN-391

678

399

242

216

141

112

KTN-392

762

432

263

220

140

108

KTN-393

706

378

230

239

153

114

KTN-394

651

315

205

252

150

112

Reserve for Supporting Lok Ma Chau Loop Development

KTN-395

787

449

247

185

127

99

KTN-396

672

388

227

221

140

106

KTN-397

725

345

214

233

145

108

KTN-398

697

318

190

271

162

115

KTN-399

740

328

210

291

158

113

KTN-400

713

379

237

276

172

120

KTN-401

591

266

183

213

134

101

KTN-402

688

320

211

184

117

93

KTN-403

665

334

207

169

108

88

KTN-404

630

314

205

176

107

90

KTN-405

691

369

229

184

118

95

KTN-406

667

371

236

186

123

96

KTN-407

629

329

201

190

136

103

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)

KTN-408

506

344

216

149

116

93

KTN-409

613

320

198

167

118

93

KTN-410

633

313

200

162

123

98

KTN-411

686

343

213

177

126

98

Notes: 

[1]  Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]  Values include background concentration: 73.1 µg/m3 of TSP.


 

Table 3.39 - Tier 2 assessment - predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2028.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Temporary Structure near Castle Peak Road

KTN-E90

422

231

142

154

89

79

Lo Wu Firing Range (Eastern)

KTN-E123

276

183

145

112

100

87

Ma Tso Lung San Tsuen

KTN-E209

246

165

109

89

82

77

Europa Garden Phase I

KTN-E1003

330

149

106

94

84

79

Valais Phase 1

KTN-E1005

429

170

141

152

99

90

KTN-E1006

266

171

119

113

98

85

KTN-E1007

168

140

108

88

86

81

St Paul's House of Prayer

KTN-E1009

369

177

114

148

102

85

Kam Tsin Village Ho Tung School

KTN-E1010

343

190

134

105

91

82

Scattered Village Houses at Northern Boundary of KTN

KTN-E1017

412

209

137

96

84

78

KTN-E1018

256

161

123

106

89

81

Planned ASRs

Nursery Classes and Kindergartens; Post Offices

KTN-23

191

166

116

95

88

82

KTN-24

211

172

112

97

89

83

KTN-25

252

175

117

105

96

84

KTN-26

334

167

116

122

98

84

KTN-27

282

146

112

110

92

82

Sports Centre, District Library, Integrated Children and Youth Services Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-234

227

173

123

102

89

83

KTN-235

219

178

127

99

89

83

Reprovision Site of Kwu Tung Vegetable Marketing and Credit Co-operative Society

KTN-271

292

177

121

132

103

86

Government Reserve

KTN-315

209

169

124

94

89

83

KTN-316

293

180

130

122

95

84

KTN-318

257

188

136

109

90

83

KTN-319

236

152

124

109

87

83

Sports Ground/Sports Complex

KTN-391

145

139

115

83

82

80

KTN-392

215

156

119

93

86

82

KTN-393

174

155

121

88

86

81

KTN-394

121

113

103

81

80

79

Reserve for Supporting Lok Ma Chau Loop Development

KTN-395

279

192

141

106

95

84

KTN-396

234

175

124

101

93

84

KTN-397

280

165

123

107

94

85

KTN-398

218

169

123

97

91

83

KTN-399

314

203

128

123

103

86

KTN-400

407

234

140

163

114

91

KTN-401

278

189

119

119

96

84

KTN-402

221

127

101

132

88

80

KTN-403

256

164

107

113

88

79

KTN-404

230

142

104

115

87

78

KTN-405

387

183

113

156

94

81

KTN-406

See Note [1]

See Note [1]

See Note [1]

See Note [1]

See Note [1]

See Note [1]

KTN-407

463

211

123

148

102

86

Disused School (Potential for Eco-tourism Education Centre, Holiday Camping or Other Recreational Uses)

KTN-408

434

178

123

119

93

81

KTN-409

266

187

112

109

91

81

KTN-410

368

183

119

122

94

82

KTN-411

417

180

115

166

100

83

Notes: 

[1]  ASR does not exist during the construction period.

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

Table 3.40 – Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in KTN NDA in Year 2028.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

Temporary Structure near Castle Peak Road

KTN-E90

74.7

73.8

73.4

Lo Wu Firing Range (Eastern)

KTN-E123

73.3

73.3

73.2

Ma Tso Lung San Tsuen

KTN-E209

73.1

73.1

73.1

Europa Garden Phase I

KTN-E1003

73.6

73.4

73.3

Valais Phase 1

KTN-E1005

73.9

73.6

73.5

KTN-E1006

74.1

73.8

73.6

KTN-E1007

73.7

73.6

73.5

St Paul's House of Prayer

KTN-E1009

74.3

73.8

73.5

Kam Tsin Village Ho Tung School

KTN-E1010

74.4

73.8

73.5

Golf Parkview

KTN-E1017

73.2

73.1

73.1

Scattered Village Houses at Northern Boundary of KTN

KTN-E1018

73.2

73.2

73.2

Planned ASRs

Nursery Classes and Kindergartens; Post Offices;

KTN-23

73.4

73.4

73.3

KTN-24

73.4

73.4

73.3

KTN-25

73.4

73.4

73.3

KTN-26

73.4

73.4

73.3

KTN-27

73.4

73.3

73.3

KTN-234

73.4

73.4

73.3

KTN-235

73.5

73.5

73.4

KTN-271

74.3

73.9

73.5

Nursery Classes and Kindergartens (2 nos); District Elderly Community Centre

KTN-315

73.4

73.2

73.2

KTN-316

73.5

73.3

73.2

Sports Centre, District Library, Integrated Children and Youth Services Centre and Family Service Centre; Integrated Community Centre for Mental Wellness, Child Care Centre and Social Security Field Unit

KTN-318

73.3

73.3

73.2

KTN-319

73.3

73.2

73.2

Reprovision Site of Kwu Tung Vegetable Marketing and Credit Co-operative Society

KTN-391

73.4

73.3

73.2

Government Reserve

KTN-392

73.4

73.2

73.2

KTN-393

73.6

73.3

73.2

KTN-394

73.5

73.3

73.2

KTN-395

73.4

73.2

73.2

Sports Ground/Sports Complex

KTN-396

73.5

73.3

73.2

KTN-397

73.6

73.3

73.2

KTN-398

73.6

73.4

73.2

KTN-399

73.6

73.3

73.2

Reserve for Supporting Lok Ma Chau Loop Development

KTN-400

73.5

73.3

73.2

KTN-401

73.5

73.3

73.2

KTN-402

73.4

73.2

73.1

KTN-403

73.3

73.2

73.1

KTN-404

73.3

73.2

73.1

KTN-405

73.4

73.2

73.1

KTN-406

73.3

73.2

73.1

KTN-407

73.3

73.2

73.2

KTN-408

73.2

73.2

73.1

KTN-409

73.3

73.2

73.1

KTN-410

73.3

73.2

73.2

KTN-411

73.4

73.2

73.2

Note: 

[1]  Values include background concentration: 73.1 µg/m3 of TSP.

 


3.8.1.2 Assessment Results – Mitigated Scenarios for FLN NDA

Short-term Assessment (Tier 1) for Worst Case Scenario – Year 2025

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.41 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria is not anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (e.g. scattered village houses north of proposed town-park, On Kwok Villa, etc.), exceedance of 1-hour TSP criterion is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken.

Figures 3.83 and Figure 3.84 show the contours of Tier 1 1-hour and 24-hour TSP concentrations at 1.5m above ground.

Short-term Assessment (Tier 2) for Worst Case Scenario – Year 2025

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.5.1.5, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.42 below summarizes the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figures 3.85 and Figure 3.86 for Tier 2 1-hour and 24-hour TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Worst Case Scenario – Year 2025

The annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.43 below summarises the cumulative annual TSP impact at the ASRs concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore no adverse long-term impact is anticipated. Contours of annual TSP concentrations at 1.5m above ground are shown in Figure 3.87.

 


Table 3.41 Tier 1 assessment – predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2025.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Scattered Village Houses North of Proposed Potential Town-park

FLN-E62

630

383

274

158

108

97

On Kwok Villa

FLN-E123

576

414

250

189

149

119

Noble Hill

FLN-E124

628

434

281

203

163

129

Scattered Village Houses East of Good View New Village

FLN-E126

546

465

318

167

151

125

Planned ASRs

Police Driving and Traffic Training Division

FLN-5

511

445

328

176

150

120

Weapons Training Division

FLN-20

511

375

263

163

134

113

FLN-21

560

417

287

160

132

113

FLN-22

604

446

322

192

150

120

Village Resite

FLN-35

612

377

262

194

142

109

FLN-36

502

377

273

152

133

109

Residential Buildings, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre,  Residential Home for the Elderly, Post Office

FLN-243

512

411

250

113

104

90

Notes: 

[1]  Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]  Values include background concentration: 73.1 µg/m3 of TSP.

 

Table 3.42 - Tier 2 assessment - predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario for existing ASRs in FLN NDA in Year 2025.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Scattered Village Houses North of Proposed Potential Town-park

FLN-E62

487

286

214

124

94

87

On Kwok Villa

FLN-E123

352

277

237

113

103

95

Noble Hill

FLN-E124

408

281

215

151

122

101

Scattered Village Houses East of Good View New Village

FLN-E126

325

292

202

109

99

90

Planned ASRs

Police Driving and Traffic Training Division

FLN-5

240

219

181

108

101

92

Weapons Training Division

Weapons Training Division

FLN-20

294

236

201

117

107

93

FLN-21

309

228

196

124

109

95

FLN-22

335

245

203

130

111

96

Village Resite

FLN-35

404

331

216

147

111

95

FLN-36

324

287

200

120

109

96

Residential Buildings, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre,  Residential Home for the Elderly, Post Office

FLN-243

337

315

234

87

86

82

Note: 

[1] Values include background concentration: 73.1 µg/m3 of TSP

 

Table 3.43 Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2025.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

 

Scattered Village Houses North of Proposed Potential Town-park

FLN-E62

74.3

73.7

73.5

On Kwok Villa

FLN-E123

73.6

73.6

73.5

Noble Hill

FLN-E124

73.7

73.6

73.4

Scattered Village Houses East of Good View New Village

FLN-E126

73.5

73.5

73.4

Planned ASRs

 

Police Driving and Traffic Training Division

FLN-5

74.4

74.1

73.7

Weapons Training Division

FLN-20

74.4

74.1

73.8

FLN-21

74.6

74.2

73.8

FLN-22

74.9

74.3

73.9

Village Resite

FLN-35

73.7

73.4

73.3

FLN-36

73.5

73.4

73.3

Residential Buildings, Nursery Classes and Kindergartens, Neighbourhood Elderly Community Centre,  Residential Home for the Elderly, Post Office

FLN-243

73.3

73.3

73.2

Note: 

 [1]       Values include background concentration: 73.1 µg/m3 of TSP

 


Short-term Assessment (Tier 1) for Year 2018

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.44 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that, for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria is not anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (i.e. village houses at Fu Tei Au Tsuen (Eastern)), exceedance of 1-hour TSP criterion is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken. Figures 3.73 and Figure 3.74 show the contours of Tier 1 1-hour and 24-hour TSP concentrations at 1.5m above ground.

Short-term Assessment (Tier 2) for Year 2018

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.5.1.5, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.45 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figures 3.75 and Figure 3.76 for Tier 2 1-hour and 24-hour TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Year 2018

The annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.46 below summarises the cumulative annual TSP impact at the ASRs concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore no adverse long-term impact is anticipated. Contours of annual TSP concentrations at 1.5m above ground are shown in Figure 3.77.

 


Table 3.44 Tier 1 assessment – predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2018.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hour TSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Village Houses at Fu Tei Au Tsuen (Eastern)

FLN-E15

625

299

180

155

120

99

FLN-E16

617

252

162

228

130

101

FLN-E17

540

249

159

229

130

102

FLN-E18

612

283

183

234

144

102

FLN-E19

641

317

196

223

141

103

FLN-E20

613

261

167

228

138

100

FLN-E22

539

231

142

220

126

97

FLN-E23

610

286

178

233

141

104

FLN-E28

531

264

170

193

132

98

Notes: 

[1]  Values which exceed the required criterion of 500 µg/m3 for 1-hour TSP and 260 µg/m3 for 24-hour TSP are shown in bolded

[2]  Values include background concentration: 73.1 µg/m3 of TSP.


 

Table 3.45 – Tier 2 assessment – Predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2018.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hour TSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

Village Houses at Fu Tei Au Tsuen (Eastern)

FLN-E15

116

111

95

75

75

74

FLN-E16

126

117

94

77

76

75

FLN-E17

159

131

98

81

79

77

FLN-E18

317

142

105

131

94

82

FLN-E19

371

152

105

152

96

81

FLN-E20

404

162

103

152

97

81

FLN-E22

147

124

99

78

77

75

FLN-E23

339

134

95

146

91

78

FLN-E28

255

173

111

90

85

79

Note: 

[1] Values include background concentration: 73.1 µg/m3 of TSP


 

Table 3.46 Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2018.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

 

Village Houses at Fu Tei Au Tsuen (Eastern)

FLN-E15

73.5

73.4

73.2

FLN-E16

74.6

73.6

73.3

FLN-E17

75.1

73.8

73.4

FLN-E18

75.3

73.9

73.4

FLN-E19

74.7

73.8

73.5

FLN-E20

75.3

74.0

73.5

FLN-E22

75.4

74.0

73.5

FLN-E23

75.3

74.0

73.5

FLN-E28

74.4

73.9

73.5

Note: 

 [1]       Values include background concentration: 73.1 µg/m3 of TSP.

 


Short-term Assessment (Tier 1) for Year 2021

The maximum 1-hour and 24-hour TSP concentrations from Tier 1 screening assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.47 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 1) at the ASRs concerned. The results indicate that for the majority of ASRs, exceedance of 1-hour and 24-hour TSP criteria is not anticipated even with this theoretical worst case situation where the entire worksites were assumed active (i.e. 100%). However, for the ASRs near the work sites (e.g. open storage, Wu Nga Lok Yeung, Wing Fai Centre, Belair Monte, etc.), exceedance of 1-hour and 24-hour TSP criterion is still predicted. As the Tier 1 assessment is for screening purposes only and does not reflect the actual on-site activities, a more focused Tier 2 assessment has been undertaken. Figures 3.78 and Figure 3.79 show the contours of Tier 1 1-hour and 24-hour TSP concentrations at 1.5m above ground.

Short-term Assessment (Tier 2) for Year 2021

A more focused Tier 2 assessment has been conducted with the assumed 15% active works areas for the adjacent construction site positioned nearest to the potentially worst affected ASRs. As mentioned in Section 3.5.1.5, the Tier 2 assessment is also very conservative and will lead to over prediction of the dust impacts.

The maximum 1-hour and 24-hour TSP concentrations from Tier 2 screening assessment have been predicted. Appendix 3.14 shows the assessment results and Table 3.48 below summarises the cumulative 1-hour and 24-hour TSP impact (Tier 2) at the ASRs concerned. Results show that the cumulative 1-hour and 24-hour TSP concentrations would comply with the respective criteria and as such, adverse short-term construction dust impact is not anticipated.

Contours have been presented in Figures 3.80 and Figure 3.81 for Tier 2 1-hour and 24-hour TSP concentrations at 1.5m above ground to illustrate the short-term dust impact on the ASR.

Long-term Assessment for Year 2021

The maximum annual TSP concentrations from long-term assessment have been predicted. Appendix 3.13 shows the assessment results and Table 3.49 below summarises the cumulative annual TSP impact at the ASRs concerned. In summary, the predicted annual TSP concentrations at all ASRs would comply with the criterion of 80µg/m3, and therefore no adverse long-term impact is anticipated. Contours of annual TSP concentrations at 1.5m above ground are shown in Figure 3.82.

 


Table 3.47 Tier 1 assessment – predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2021.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

 

Open Storage

FLN-E44

570

348

209

135

110

97

FLN-E47

575

317

187

264

153

107

Wu Nga Lok Yeung

FLN-E94

555

443

269

200

167

121

FLN-E98

525

377

235

217

162

122

Wing Fai Centre

FLN-E128

501

353

215

187

149

108

Belair Monte

FLN-E129

654

447

252

255

189

133

House near Ma Wat Wai

FLN-E140

576

409

279

209

168

133

Village House near Wu Nga Lok Yeung

FLN-E155

505

270

227

182

126

115

Wu Nga Lok Yeung

FLN-E166

504

374

236

209

169

127

Planned ASRs

 

Existing North District Temporary Wholesale Market for Agricultural Products

FLN-188

629

450

271

185

144

114

FLN-190

566

468

303

161

150

123

FLN-191

659

445

283

191

164

124

Note: 

 [1]       Values include background concentration: 73.1 µg/m3 of TSP


 

Table 3.48 – Tier 2 assessment – predicted cumulative 1-hour and 24-hour TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2021.

Locations

ASR

1-hour TSP concentrations at various height (µg/m3)

24-hourTSP concentrations at various height (µg/m3)

1.5m

5m

10m

1.5m

5m

10m

Existing ASRs

 

Open Storage

FLN-E44

277

180

134

105

90

84

FLN-E47

266

231

160

110

98

87

Wu Nga Lok Yeung

FLN-E94

311

218

153

137

115

94

FLN-E98

372

263

175

145

119

99

Wing Fai Centre

FLN-E128

260

221

143

99

97

90

Belair Monte

FLN-E129

380

253

160

187

131

99

House near Ma Wat Wai

FLN-E140

277

208

164

135

117

103

Village House near Wu Nga Lok Yeung

FLN-E155

434

202

165

144

102

96

Wu Nga Lok Yeung

FLN-E166

389

272

168

152

128

102

Planned ASRs

 

Existing North District Temporary Wholesale Market for Agricultural Products

FLN-188

369

268

174

107

102

93

FLN-190

428

311

202

124

113

98

FLN-191

468

309

194

136

120

98

Note: 

 [1]   Values include background concentration: 73.1 µg/m3 of TSP.

 

Table 3.49 - Long term assessment - predicted cumulative annual TSP concentrations at 1.5m above ground (including background concentration of 73.1μg/m3) under mitigated scenario in FLN NDA in Year 2021.

Locations

ASR

Annual TSP concentrations at various height (µg/m3)

1.5m

5m

10m

Existing ASRs

 

Open Storage

FLN-E44

73.7

73.6

73.4

FLN-E47

75.3

74.3

73.7

Wu Nga Lok Yeung

FLN-E94

75.3

74.9

74.2

FLN-E98

75.5

74.8

74.1

Wing Fai Centre

FLN-E128

74.5

74.3

73.9

Belair Monte

FLN-E129

75.4

74.9

74.2

House near Ma Wat Wai

FLN-E140

74.9

74.3

73.8

Village House near Wu Nga Lok Yeung

FLN-E155

74.2

74.0

73.7

Wu Nga Lok Yeung

FLN-E166

75.4

74.8

74.2

Planned ASRs

Existing North District Temporary Wholesale Market for Agricultural Products

FLN-188

73.9

73.7

73.5

FLN-190

73.8

73.7

73.5

FLN-191

74.1

73.8

73.5

Note: 

 [1]   Values include background concentration: 73.1 µg/m3 of TSP


3.8.2     Operation Phase

3.8.2.1    Chimney Emission

Based on the assessment, adverse cumulative air quality impact due to the chimney emissions is not anticipated and no mitigation measures would be required.

3.8.2.2    Vehicular Emission

Based on the assessment, adverse cumulative air quality impact due to the vehicular emissions is not anticipated and no mitigation measures would be required.

3.8.2.3    Odour Emission

With the implementation of the odour control design in the proposed STW expansion in FLN, it is predicted that, even with very conservative assumptions, the odour concentration at all ASRs would comply with the odour criterion. For other future development, any air sensitive use is required to avoid the non-compliance zone as shown in Figure 3.55b.


3.9          Conclusion

3.9.1     Construction Phase

The fugitive dust assessment for the construction phase has concluded that watering in all works areas once per hour during working hours (7:00am – 7:00pm) would be required to control the fugitive dust impact. In addition, the Contractor is also recommended to adopt good site practices and is required to follow the procedures and requirements given in the Air Pollution Control (Construction Dust) Regulation.

The results indicate that, with mitigation measures, the predicted 1-hour and 24-hour and annual TSP concentrations at the identified ASRs would comply with the respective criteria. Therefore, it is concluded that there will be no adverse residual air quality impacts during construction phase.

3.9.2     Operational Phase

Vehicular emissions from open roads are expected to be the major air pollutants during the operational phase of the NENT NDA development. Fixed polluting sources such as industrial emissions, odour emissions from sewage treatment works, sewage pumping stations and slaughtering house will also have potential air quality impact to ASRs. 

Chimney emissions impact is predicted to be acceptable and no mitigation measures would be required.

The results of the cumulative impact due to vehicular and chimney emissions revealed that 1-hour, 24-hour and annual average NO2 concentrations and 24-hour and annual average RSP concentrations would comply with the relevant AQO criteria.

Odour impact due to the existing SWHSTW will be improved gradually with the expansion of the STW, since odour control designs will be installed for the newly constructed or retrofitted odour sources during the expansion works. Odour impact due to the proposed STW Extension located in the FLN NDA is not anticipated with the incorporation of all the proposed odour control design. Odour non-compliance zone (the zone where the odour concentration exceeds the statutory odour limit) has been identified. It is necessary to ensure that no planned air sensitive receivers are located inside the non-compliance zone in the future detailed design stage.